Anda di halaman 1dari 5

RINCIAN ANGGARAN BIAYA

TANGGAL : 20 MARET 2023


NOMOR : 026/R-RAB/01-02/WB-E/III/23
PROYEK : SY HOUSE
LOKASI : DIAN ISTANA PAR 2 / C10-01, SURABAYA
PEKERJAAN : ELEKTRIKAL

NO URAIAN PEKERJAAN SAT VOL

PEKERJAAN ELEKTRIKAL
A PEKERJAAN LISTRIK
A.1 PEKERJAAN PANEL
1 Main Distribusi Panel (MDP Lt. Dasar) unit 1.00
~ 1.0 pcs ATyS Sd 4P/100A ex. Socomec
~ 1.0 pcs AtyS Controller C-25 ex. Socomec
~ 1.0 pcs Baterai Charger 5A/24V DSE 9701ex. DeepSee
~ 1.0 pcs MCCB GoPact 125T 3P/100A Fixed type ex. Schneider
~ 2.0 pcs MCCB GoPact 125T 3P/63A Fixed type ex. Schneider
~ 3.0 pcs ELCB Domae-30mA 2P/63A ex. Schneider
~ 4.0 pcs MCB Domae-6kA 3P/16A ex. Schneider
~ 3.0 pcs MCB Domae-6kA 1P/25A ex. Schneider
~ 21.0 pcs MCB Domae-6kA 1P/16A ex. Schneider
~ 18.0 pcs MCB Domae-6kA 1P/10A ex. Schneider
~ 2.0 pcs Kontaktor 3P/AC Koil LC1-D18 ex. Schneider
~ 1.0 pcs Digital Time Switch Simplexa 601 ex. Theben
~ 1.0 pcs Digital Meter dengan Komunikasi DM6200H ex. Schneider
~ 3.0 pcs Current Transformer CT-70 Window 100/5A ex. GAE
~ 9.0 pcs Pilot Lamp XB7EV0…MP ex. Schneider
~ 1.0 lot Material Wiring
~ 1.0 unit Box Panel Indoor ((650+650)x1500x300)mm ex. Lokal
2 Sekunder Distribusi Panel (LT. 2+ATAP) unit 1.00
~ 1.0 pcs MCCB GoPact 125T 3P/63A Fixed type ex. Schneider
~ 3.0 pcs ELCB Domae-30mA 2P/63A ex. Schneider
~ 1.0 pcs MCB Domae-6kA 3P/16A ex. Schneider
~ 12.0 pcs MCB Domae-6kA 1P/16A ex. Schneider
~ 6.0 pcs MCB Domae-6kA 1P/10A ex. Schneider
~ 3.0 pcs Pilot Lamp XB7EV0…MP ex. Schneider
~ 1.0 lot Material Wiring
~ 1.0 unit Box Panel Indoor (600x1000x200)mm ex. Lokal

SUB TOTAL PEKERJAAN PANEL

A.2 PEKERJAAN KABEL POWER


1 Kabel Power dari KWH Meter menuju MDP mtr 76.00
Kabel NYY 4x(1x25) mm² ex. Supreme
2 Kabel Power dari Genset menuju MDP mtr 112.00
Kabel NYY 4x(1x25) mm² ex. Supreme
3 Kabel Power Charger Genset - Genset mtr 28.00
Kabel NYY 4x2,5 mm² ex. Supreme
4 Kabel Power dari MDP menuju Panel Pompa Air Bersih mtr 25.00
Kabel NYY 4x4 mm² ex. Supreme
5 Kabel Power dari MDP menuju SDP (LT. 2) mtr 19.00
Kabel NYY 4x10 mm² ex. Supreme

SUB TOTAL PEKERJAAN KABEL POWER

Halaman 1 dari 5 halaman


NO URAIAN PEKERJAAN SAT VOL

A.3 PEKERJAAN GROUNDING / ARDE


1 Grounding / Arde Genset unit 1.00
~ 1.0 btg Round Copper Ø ⅝"
~ 1.0 lot Kabel BC 16 mm²
~ 1.0 lot Material Bantu
2 Kabel Arde dari JB Genset menuju Genset mtr 10.00
Kabel BC 16 mm²
3 Grounding / Arde MDP unit 1.00
~ 1.0 btg Round Copper Ø ⅝"
~ 1.0 lot Kabel BC 16 mm²
~ 1.0 lot Material Bantu
4 Kabel Arde dari JB MDP menuju MDP mtr 10.00
Kabel BC 16 mm²
5 Kabel Arde dari MDP menuju Panel Pompa Air Bersih mtr 25.00
Kabel BC 6 mm²
6 Kabel Arde dari MDP menuju SDP (LT. 2) mtr 19.00
Kabel BC 6 mm²

SUB TOTAL PEKERJAAN GROUNDING / ARDE

A.4 PEKERJAAN INSTALASI LISTRIK


A.4.01 PEKERJAAN INSTALASI LISTRIK LT. 1
1 Line Ceiling/ Wall Lamp titik 34.00
Kabel NYM 2x2,5 & NYM 2x1,5 mm² ex. Supreme + Conduit PVC Ø 20 mm ex. Boss
2 Line Ceiling/ Wall Hotel Lamp titik 29.00
Kabel NYM 2x2,5 & NYM 2x1,5 mm² ex. Supreme + Conduit PVC Ø 20 mm ex. Boss
3 Line Floor Hotel Lamp titik 1.00
Kabel NYM 2x2,5 & NYYHY 2x1,5 mm² ex. Supreme + Conduit PVC Ø 20 mm ex. Boss
4 Line Ceiling Exhaust Fan titik 4.00
Kabel NYM 2x2,5 & NYM 2x1,5 mm² ex. Supreme + Conduit PVC Ø 20 mm ex. Boss
5 Line Garden Timer Lamp titik 37.00
Kabel NYM 2x2,5 & NYYHY 2x1,5 mm² ex. Supreme + Conduit PVC Ø 20 mm ex. Boss
6 Line Ceiling Timer Lamp titik 17.00
Kabel NYM 2x2,5 & NYM 2x1,5 mm² ex. Supreme + Conduit PVC Ø 20 mm ex. Boss
7 Line Power Socket titik 38.00
Kabel NYM 3x2,5 mm² ex. Supreme + Conduit PVC Ø 20 mm ex. Boss
8 Line Floor Power Socket titik 1.00
Kabel NYM 3x2,5 & NYY 3x2,5 mm² ex. Supreme + Conduit PVC Ø 20 mm ex. Boss
9 Line Power Socket (Refrigerator) titik 2.00
Kabel NYM 3x2,5 mm² ex. Supreme + Conduit PVC Ø 20 mm ex. Boss
10 Line Power Socket (Dispenser) titik 1.00
Kabel NYM 3x2,5 mm² ex. Supreme + Conduit PVC Ø 20 mm ex. Boss
11 Line Power Socket (Cooker Hood) titik 2.00
Kabel NYM 3x2,5 mm² ex. Supreme + Conduit PVC Ø 20 mm ex. Boss
12 Line Power Socket (Microwave/Oven) titik 1.00
Kabel NYY 3x4 mm² ex. Supreme + Conduit PVC Ø 20 mm ex. Boss
13 Line Power Socket (Electric Stove) titik 1.00
Kabel NYY 3x2,5 mm² ex. Supreme + Conduit PVC Ø 20 mm ex. Boss
14 Line Power Socket (JBE) titik 1.00
Kabel NYM 3x2,5 mm² ex. Supreme + Conduit PVC Ø 20 mm ex. Boss
15 Line Power Air Conditioning 1PK / 1Phase titik 2.00
Kabel NYY 3x2.5 mm² ex. Supreme + Conduit PVC Ø 20 mm ex. Boss
16 Line Power Air Conditioning 3PK / 3Phase titik 2.00
Kabel NYY 4x2,5 mm² ex. Supreme + Conduit PVC Ø 20 mm ex. Boss
17 Line Power Supply (Automatic Gate) titik 1.00
Kabel NYY 3x2.5 mm² ex. Supreme + Conduit PVC Ø 20 mm ex. Boss
18 Line Manual Switch (Automatic Gate) titik 1.00
Kabel NYY 3x1,5 mm² ex. Supreme + Conduit PVC Ø 20 mm ex. Boss
19 Line Sensor Switch (Automatic Gate) titik 2.00
Kabel NYYHY 4x0,75 mm² ex. Supreme + Conduit PVC Ø 20 mm ex. Boss
20 Line Door Bell titik 1.00
Kabel NYYHY 2x1,5 mm² ex. Supreme + Conduit PVC Ø 20 mm ex. Boss
21 Line Sound Bell titik 1.00
Kabel NYYHY 2x1,5 mm² ex. Supreme + Conduit PVC Ø 20 mm ex. Boss

Halaman 2 dari 5 halaman


NO URAIAN PEKERJAAN SAT VOL

A.4.02 PEKERJAAN INSTALASI LISTRIK LT. 2 + LT. ATAP


1 Line Ceiling/ Wall Lamp titik 34.00
Kabel NYM 2x2,5 & NYM 2x1,5 mm² ex. Supreme + Conduit PVC Ø 20 mm ex. Boss
2 Line Ceiling/ Wall Hotel Lamp titik 13.00
Kabel NYM 2x2,5 & NYM 2x1,5 mm² ex. Supreme + Conduit PVC Ø 20 mm ex. Boss
3 Line Ceiling Exhaust Fan titik 2.00
Kabel NYM 2x2,5 & NYM 2x1,5 mm² ex. Supreme + Conduit PVC Ø 20 mm ex. Boss
4 Line Power Socket titik 24.00
Kabel NYM 3x2,5 mm² ex. Supreme + Conduit PVC Ø 20 mm ex. Boss
5 Line Power Socket (Mesin Cuci) titik 1.00
Kabel NYM 3x2,5 mm² ex. Supreme + Conduit PVC Ø 20 mm ex. Boss
6 Line Power Socket (Solar Water Heater) titik 1.00
Kabel NYY 3x4 mm² ex. Supreme + Conduit PVC Ø 20 mm ex. Boss
7 Line Power Air Conditioning 1½ PK / 1Phase titik 1.00
Kabel NYY 3x2.5 mm² ex. Supreme + Conduit PVC Ø 20 mm ex. Boss
8 Line Power Air Conditioning 3PK / 3Phase titik 1.00
Kabel NYY 4x2,5 mm² ex. Supreme + Conduit PVC Ø 20 mm ex. Boss

SUB TOTAL PEKERJAAN INSTALASI LISTRIK

B PEKERJAAN PENANGKAL PETIR ELEKTROSTATIK


B.1 PEKERJAAN INSTALASI PENANGKAL PETIR
1 Penangkal Petir unit 1.00
~ 1.0 unit Kurn IDN R.80 - Made in Indonesia
~ 1.0 pcs Fiberglass
~ 1.0 btg Tiang Penangkal Petir - SS Ø 2"
~ 1.0 lot Material bantu
2 Kabel Penangkal Petir mtr 39.00
Kabel Coaxial 2x35 mm² ex. DCE
3 Grounding Penangkal Petir unit 2.00
~ 1.0 btg Round Copper Ø ⅝"
~ 1.0 lot Kabel BC 70 mm²
~ 1.0 lot Material Bantu

SUB TOTAL PEKERJAAN INSTALASI PENANGKAL PETIR

C PEKERJAAN TELEPHONE, TELEVISI DAN KABEL DATA


C.1 PEKERJAAN INSTALASI TELEPHONE
C.1.1 PEKERJAAN INSTALASI TELEPHONE LT. 1
1 Junction Box Electronic (JB-E) unit 1.00
~ 1.0 unit Wallmount Rack Double Door 15U WIR5515D ex. Indorack
2 Sparring Kabel Power dari Telkom menuju JB-E mtr 19.00
Konduit PE Ø 20 mm ex. Maspion
3 Kabel Arde dari MDP menuju JB-E mtr 14.00
Kabel NYA 10 mm²
4 Line Telephone titik 1.00
Kabel UTP CAT 6 ex. AMP + Konduit PVC Ø 20 mm ex. Boss

SUB TOTAL PEKERJAAN INSTALASI TELEPHONE

Halaman 3 dari 5 halaman


NO URAIAN PEKERJAAN SAT VOL

C.2 PEKERJAAN INSTALASI TELEVISI


C.2.1 PEKERJAAN INSTALASI TELEVISI LT. 1
1 Line Antena Televisi (Roof Floor) titik 1.00
Kabel Coaxial RG - 11 ex. Belden + Konduit PVC Ø 20 mm ex. Boss
2 Line Televisi titik 3.00
Kabel Coaxial RG - 6 ex. Belden + Konduit PVC Ø 20 mm ex. Boss

SUB TOTAL PEKERJAAN INSTALASI TELEVISI

C.3 PEKERJAAN INSTALASI KABEL DATA


C.3.1 PEKERJAAN INSTALASI KABEL DATA LT. 1
1 Line Internet titik 3.00
Kabel UTP CAT 6 ex. AMP + Konduit PVC Ø 20 mm ex. Boss
2 Line TV Internet titik 3.00
Kabel UTP CAT 6 ex. AMP + Konduit PVC Ø 20 mm ex. Boss

C.3.2 PEKERJAAN INSTALASI KABEL DATA LT. 2


1 Line Internet titik 1.00
Kabel UTP CAT 6 ex. AMP + Konduit PVC Ø 20 mm ex. Boss

SUB TOTAL PEKERJAAN INSTALASI KABEL DATA

C.4 PEKERJAAN INSTALASI CCTV


C.4.1 PEKERJAAN INSTALASI CCTV LT. 1
1 Line Camera CCTV titik 6.00
Kabel UTP CAT 6 ex. AMP + Konduit PVC Ø 20 mm ex. Boss

C.4.2 PEKERJAAN INSTALASI CCTV LT. 2


1 Line Camera CCTV titik 3.00
Kabel UTP CAT 6 ex. AMP + Konduit PVC Ø 20 mm ex. Boss

C.4.3 PEKERJAAN INSTALASI CCTV LT. 2


1 Line Camera CCTV titik 2.00
Kabel UTP CAT 6 ex. AMP + Konduit PVC Ø 20 mm ex. Boss

SUB TOTAL PEKERJAAN INSTALASI CCTV

D PEKERJAAN PEMASANGAN ACCESSORIES LIGHTING


D.1 PEKERJAAN PEMASANGAN LIGHT SWITCH
D.1.1 PEKERJAAN PEMASANGAN LIGHT SWITCH LT. 1
1 Outlet Saklar Tunggal pcs 15.00
2 Outlet Saklar Ganda pcs 4.00
3 Outlet Saklar Triple pcs 2.00
4 Outlet Saklar Ganda Hotel pcs 14.00
5 Outlet Stop Kontak pcs 49.00
6 Outlet Telephone pcs 1.00
7 Outlet Televisi pcs 3.00
8 Outlet Data pcs 3.00
9 Outlet Door Bell pcs 1.00
10 Outlet Speaker Bell pcs 1.00

D.1.2 PEKERJAAN PEMASANGAN LIGHT SWITCH LT. 2 + LT. ATAP


1 Outlet Saklar Tunggal pcs 7.00
2 Outlet Saklar Ganda pcs 5.00
3 Outlet Saklar Ganda Hotel pcs 8.00
4 Outlet Stop Kontak pcs 26.00
5 Outlet Data pcs 1.00

SUB TOTAL PEKERJAAN PEMASANGAN LIGHT SWITCH

Halaman 4 dari 5 halaman


NO URAIAN PEKERJAAN SAT VOL

D.2 PEKERJAAN PEMASANGAN LIGHT FIXTURE


D.2.1 PEKERJAAN PEMASANGAN LIGHT FIXTURE LT. 1
1 Recessed Downlight pcs 49.00
2 Surface Mounted Wall Lamp pcs 7.00
3 LED Strip Lamp pcs 79.00
4 Step Light / Inground Uplight pcs 3.00
5 Garden Lamp pcs 18.00
6 Ceiling Exhaust Fan pcs 4.00
7 Junction Box Trafo (Pengadaan + Pemasangan) pcs 3.00

D.2.2 PEKERJAAN PEMASANGAN LIGHT FIXTURE LT. 2 + LT. ATAP


1 Recessed Downlight pcs 48.00
2 LED Strip Lamp mtr 26.00
3 Step Light / Inground Uplight pcs 6.00
4 Wallwasher Lamp pcs 2.00
5 Ceiling Exhaust Fan pcs 2.00
6 Junction Box Trafo (Pengadaan + Pemasangan) pcs 2.00

SUB TOTAL PEKERJAAN PEMASANGAN LIGHT FIXTURE

E PEKERJAAN TESTING & COMMISIONING


E.1 PEKERJAAN TESTING & COMMISIONING
1 Testing & commisioning lot 1.00

SUB TOTAL PEKERJAAN TESTING & COMMISIONING

JUMLAH TOTAL

Halaman 5 dari 5 halaman