Anda di halaman 1dari 9

RANCANGAN ANGGARAN BIAYA PENGECORAN AREA CARABACO PT DENSO

NO DESKRIPSI SATUAN TOTAL HARGA SATUAN TOTAL HARGA


1 TENAGA 2 ORANG hr 3 Rp 350,000.00 Rp 1,050,000.00
2 COR K 300 1 X 11 X 0,10 m3 2 Rp 1,550,000.00 Rp 3,100,000.00
3 sewa jack hammer hr 2 Rp 350,000.00 Rp 700,000.00
4 Sewa mesin cutting cor hr 2 Rp 550,000.00 Rp 1,100,000.00
5 karung pcs 100 Rp 1,500.00 Rp 150,000.00
6 hollow 4x4 btg 1 Rp 55,000.00 Rp 55,000.00
7 Weirmesh m8 lbr 1 Rp 400,000.00 Rp 400,000.00
8 Rokok supir TM ls 1 Rp 20,000.00 Rp 20,000.00
9 Sepaty Safety neon pcs 2 Rp 170,000.00 Rp 340,000.00
10 kacamata safety pcs 3 Rp 6,500.00 Rp 19,500.00
11 sarung tangan safety ls 1 Rp 25,000.00 Rp 25,000.00
12 operational 1 Rp 1,000,000.00 Rp 1,000,000.00
13 Mobil Puing pcs 2 Rp 200,000.00 Rp 400,000.00
TOTAL MODAL Rp 8,359,500.00
PPN 10% Rp 835,950.00
PROFIT 45% Rp 3,761,775.00
TOTAL HARGA Rp 12,957,225.00
DAFTA

RENCANA
PT. GEMILANG PRIORITAS UTAMA
PROYEK
PEKERJAAN
ACUAN

LOKASI
PEMILIK
SCHEDULE

NO

a
I
1
2
3
4
5
6

II
1

III
1
3

I
II
III
DAFTAR ITEM
DAN
RENCANA ANGG
PT. GEMILANG PRIORITAS UTAMA
: PENGECORAN AREA CARABACO
: PENGECORAN AREA CARABACO
: GAMBAR FOR TENDER TGL :
: SPESIFIKASI TANGGAL :
:
: PT DENSO MANUFACTURING INDONESIA
: 3 HARI KERJA

URAIAN PEKERJAAN SAT

b c
PEKERJAAN PERSIAPAN
Pembersihan Lapangan ls
APD (Alat Perlindungan Diri) m1
Listrik Kerja & Air Kerja ls
Keamanan Proyek Direksi keet ls
Alat Bantu kerja ls
Mob Demob ls
JUMLAH
PEKERJAAN PEMBONGKARAN LANTAI
Pek Demolish Lantai cor m2
JUMLAH
PEKERJAAN PENGECORAN LANTAI
Pek Cor k 400 1 x 11 x 0,10 m m3
Finishing /perapihan ls
JUMLAH

REKAPITULASI ANGGARAN

PEKERJAAN PERSIAPAN
PEKERJAAN PEMBONGKARAN LANTAI
PEKERJAAN PENGECORAN LANTAI

JUMLAH
PPN 11%
PROFIT 10%
TOTAL
DAFTAR ITEM PEKERJAAN
DAN
RENCANA ANGGARAN BIAYA

Vol
HARGA JUMLAH
BOBOT (%)
SATUAN (Rp) HARGA (Rp)
AWAL VE
d e f h

1.00 Rp 300,000.00 Rp 300,000.00 2.80%


2.00 Rp 250,000.00 Rp 500,000.00 4.67%
1.00 Rp 300,000.00 Rp 300,000.00 2.80%
1.00 Rp 350,000.00 Rp 350,000.00 3.27%
1.00 Rp 300,000.00 Rp 300,000.00 2.80%
1.00 Rp 500,000.00 Rp 500,000.00 4.67%
Rp 2,250,000.00 21.02%

11.00 Rp 410,000 Rp 4,510,000.00 42.13%


Rp 4,510,000.00 42.13%

1.30 Rp 2,650,000.00 Rp 3,445,000.00 32.181%


1.00 Rp 500,000.00 Rp 500,000.00 4.671%
Rp 3,945,000.00 36.852%
QCC / GPU / RAB / PT DMIA / JUNI 2023 /

Rp 2,250,000.00 21.018%
Rp 4,510,000.00 42.130%
Rp 3,945,000.00 36.852%

Rp 10,705,000.00 100.0000%
Rp 1,177,550.00 11.0000%
Rp 1,070,500.00
Rp 12,953,050.00

QCC / GPU / RAB / PT DMIA/ JUNI 2023 / 0


KETERANGAN VE

i
350,000 399,500,000
75,000 365,000,000
171,000 34,500,000
841,000 8.64%

171,000
171,000
171,000
841,000
75,000

Anda mungkin juga menyukai