Anda di halaman 1dari 21

REKAPITULASI ANGGARAN BIAYA

PROYEK : PEMBANGUNAN RUMAH DAGO VALLEY


SUB PROYEK : BANGUNAN TYPE - 1
LOKASI : BANDUNG JAWA BARAT

NO PENJELASAN JUMLAH HARGA


PEKERJAAN STRUKTUR
1 A PEKERJAAN PERSIAPAN Rp 14,146,880.00
B PEKERJAAN LANATAI DASAR ( Elv -3,20) Rp 85,088,228.70
C PEKERJAAN LANTAI ATAS ( ElV ± 0,00 ) Rp 51,249,659.20
D PEKERJAAN BETON ATAP ( Elv + 3,20 ) Rp 30,865,815.80
SUB TOTAL PEKERJAAN STRUKTUR Rp 181,350,583.70

PEKERJAAN ARSITEKTUR
2 A PEKERJAAN LANTAI ( Elv - 3,20 ) Rp 98,672,224.10
B PEKRJAAN LANTAI DASAR ( ElV ± 0,00 ) Rp 84,496,448.60
C PEKERJAAN LANATAI ATAP ( Elv + 3,20 ) Rp 43,425,907.22
SUB TOTAL PEKERJAAN ARSITEKTUR Rp 226,594,579.92

PEKERJAAN ME
3 A PEKERJAAN ELEKTRIKAL Rp 19,945,000.00
B PEKRJAAN TATA UDARA Rp 6,335,000.00
C PEKERJAAN PLUMBING Rp 25,344,000.00
D PEKERJAAN IJIN SAMBUNGAN BARU Rp 6,850,000.00
SUB TOTAL PEKERJAAN ME Rp 58,474,000.00

SUB TOTAL Rp 466,419,163.62


FEE PEMBORONG 8 % Rp 37,313,533.09
TOTAL (SUB TOTAL + FEE) Rp 503,732,696.71
PPN 10% Rp 50,373,269.67
GRAND TOTAL Rp 554,105,966.38
DIBULATKAN Rp 554,105,000.00

Terbilang : # Enam Ratus Lima Juta Enam Ratus Sembilan Puluh Ribu Rupiah #

91%
Rp 554,105,000.00
RENCANA ANGGARAN BIAYA ( RAB ) STRUKTUR
PROYEK : PEMBANGUNAN RUMAH DAGO VALLEY
SUB PROYEK : BANGUNAN TYPE - 1
LOKASI : BANDUNG - JAWA BARAT

JUMLAH HARGA
NO URAIAN PEKERJAA SAT VOL
UPAH BAHAN
A PEKERJAAN PERSIAPAN
1 Pembersi m² 160.00 Rp 2,400,000.00 Rp -
2 Penguku m¹ 56.00 Rp 1,232,000.00 Rp 2,177,280.00
3 Direksi m² 43.20 Rp 1,857,600.00 Rp 6,480,000.00
4 Pagar pengaman proyek m¹ Rp - Rp -
5 Air kerja bln Rp - Rp -
6 Listrik Kerja bln Rp - Rp -

JUMLAH PEKERJAAN PERSIAPAN

B PEKERJAAN BETON LANTAI DASAR ( Elv - 3.20)


0 1 PEKERJAAN BATU KALI
1 Pekerjaan Pasangan Batu Kali m³ 37.36 Rp 3,362,400.00 Rp 13,109,997.60
2 Pekerjaan Pasir Urug berikut pemadatan m³ 3.16 Rp 79,000.00 Rp 268,600.00
3 Pekerjaan Galian Tanah berikut buang ke luar lokasi Proyek m³ 73.17 Rp 7,317,000.00 Rp -
4 Pekerjaan Urugan Tanah kembali berikut pemadatan m³ 28.81 Rp 1,008,350.00 Rp -
5 Pekerjaan Angkur Ø - 10 mm jarak 100 cm bh 123.00 Rp 61,500.00 Rp 184,500.00

0 2 PEKERJAAN TIE BEAM


1 Pekerjaan Beton K - 225 m³ 2.61 Rp 130,500.00 Rp 1,913,782.50
2 Pekerjaan Bekesting m² 34.82 Rp 870,500.00 Rp 2,321,449.40
3 Pekerjaan Pembesian
Ø - 8 mm kg 188.76 Rp 2,265,120.00 Rp 1,825,309.20
Ø - 10 mm kg 133.44 Rp 1,601,280.00 Rp 1,290,364.80
Ø - 12 mm kg 367.63 Rp 4,411,560.00 Rp 3,554,982.10

0 3 PEKERJAAN PLAT LANTAI


1 Pekerjaan Beton K - 225 m³ 5.03 Rp 251,500.00 Rp 3,688,247.50
2 Pekerjaan Bekesting m² 3.14 Rp 78,500.00 Rp 209,343.80
3 Pekerjaan Pembesian
Ø - 6 mm kg 166.17 Rp 1,994,040.00 Rp 1,606,863.90
4 Pekerjaan Lantai Kerja t = 5 cm m³ 2.51 Rp 251,000.00 Rp 1,201,235.80
5 Pekerjaan Pasir Urug t = 10 cm m³ 5.03 Rp 125,750.00 Rp 633,780.00

0 4 PEKERJAAN KOLOM
1 Pekerjaan Beton K - 225 m³ 1.81 Rp 90,500.00 Rp 1,327,182.50
2 Pekerjaan Bekesting m² 53.04 Rp 1,326,000.00 Rp 3,536,176.80
3 Pekerjaan Pembesian
Ø - 6 mm kg 44.16 Rp 529,920.00 Rp 427,027.20
Ø - 8 mm kg 180.05 Rp 2,160,600.00 Rp 1,741,083.50
D - 13 mm kg 216.61 Rp 2,599,320.00 Rp 2,094,618.70

0 5 PEKERJAAN TANGGA - 1
1 Pekerjaan Beton K - 225 m³ 1.46 Rp 73,000.00 Rp 1,070,545.00
2 Pekerjaan Bekesting m² 13.27 Rp 331,750.00 Rp 884,710.90
3 Pekerjaan Pembesian
Ø - 8 mm kg 32.27 Rp 387,240.00 Rp 312,050.90
Ø - 10 mm kg 44.14 Rp 529,680.00 Rp 426,833.80
D - 13 mm kg 140.59 Rp 1,687,080.00 Rp 1,359,505.30

0 6 PEKERJAAN TANGGA - 2
1 Pekerjaan Beton K - 225 m³ 1.29 Rp 64,500.00 Rp 945,892.50
2 Pekerjaan Bekesting m² 12.50 Rp 312,500.00 Rp 833,375.00
3 Pekerjaan Pembesian
Ø - 8 mm kg 37.81 Rp 453,720.00 Rp 365,622.70
Ø - 10 mm kg 47.15 Rp 565,800.00 Rp 455,940.50
D - 13 mm kg 119.04 Rp 1,428,480.00 Rp 1,151,116.80

JUMLAH PEKERJAAN BETON LANTAI DASAR ( Elv - 3.20 )


RENCANA ANGGARAN BIAYA ( RAB ) STRUKTUR
PROYEK : PEMBANGUNAN RUMAH DAGO VALLEY
SUB PROYEK : BANGUNAN TYPE - 1
LOKASI : BANDUNG - JAWA BARAT

JUMLAH HARGA
NO URAIAN PEKERJAA SAT VOL
UPAH BAHAN
C PEKERJAAN BETON LANATAI ATAS ( Elv ± 0.00 )
0 1 PEKERJAA KOLOM
1 Pekerjaan Beton K - 225 m³ 1.35 Rp 67,500.00 Rp 989,887.50
2 Pekerjaan Bekesting m² 36.75 Rp 918,750.00 Rp 2,450,122.50
3 Pekerjaan Pembesian
Ø - 6 mm kg 4.01 Rp 48,120.00 Rp 38,776.70
Ø - 8 mm kg 110.57 Rp 1,326,840.00 Rp 1,069,211.90
Ø - 10 mm kg 9.25 Rp 111,000.00 Rp 89,447.50
D - 13 mm kg 260.05 Rp 3,120,600.00 Rp 2,514,683.50

0 2 PEKERJAAN BALOK
1 Pekerjaan Beton K - 225 m³ 1.74 Rp 87,000.00 Rp 1,275,855.00
2 Pekerjaan Bekesting m² 21.47 Rp 536,750.00 Rp 1,431,404.90
3 Pekerjaan Pembesian
Ø - 8 mm kg 154.68 Rp 1,856,160.00 Rp 1,495,755.60
Ø - 10 mm kg 28.51 Rp 342,120.00 Rp 275,691.70
Ø - 12 mm kg 384.22 Rp 4,610,640.00 Rp 3,715,407.40
D - 13 mm kg 19.29 Rp 231,480.00 Rp 186,534.30

0 3 PEKERJAAN PLAT LANTAI


1 Pekerjaan Beton K - 225 m³ 6.00 Rp 300,000.00 Rp 4,399,500.00
2 Pekerjaan Bekesting m² 55.22 Rp 1,380,500.00 Rp 3,681,517.40
3 Pekerjaan Pembesian
Ø - 8 mm kg 585.99 Rp 7,031,880.00 Rp 5,666,523.30

JUMLAH PEKERJAAN BETON LANTAI ATAS ( Elv ± 0.00 )

D PEKERJAAN BETON ATAP (Elv + 3.20 )


0 1 PEKERJAAN RING BALOK
1 Pekerjaan Beton K - 225 m³ 1.75 Rp 87,500.00 Rp 1,283,187.50
2 Pekerjaan Bekesting m² 29.19 Rp 729,750.00 Rp 1,946,097.30
3 Pekerjaan Pembesian
Ø - 8 mm kg 121.3 Rp 1,455,600.00 Rp 1,172,971.00
Ø - 10 mm kg 259.55 Rp 3,114,600.00 Rp 2,509,848.50
Ø - 13 mm kg 55.76 Rp 669,120.00 Rp 539,199.20

0 2 PEKERJAAN PLAT LANTAI


1 Pekerjaan Beton K - 225 m³ 2.62 Rp 131,000.00 Rp 1,921,115.00
2 Pekerjaan Bekesting m² 30.34 Rp 758,500.00 Rp 2,022,767.80
3 Pekerjaan Pembesian
Ø - 8 mm kg 291.75 Rp 3,501,000.00 Rp 2,821,222.50

0 3 PEKERJAAN BALOK KUDA-KUDA


1 Pekerjaan Beton K - 225 m³ 1.05 Rp 52,500.00 Rp 715,890.00
2 Pekerjaan Bekesting m² 17.54 Rp 438,500.00 Rp 1,169,391.80
3 Pekerjaan Pembesian
Ø - 8 mm kg 48.86 Rp 586,320.00 Rp 472,476.20
Ø - 10 mm kg 127.70 Rp 1,532,400.00 Rp 1,234,859.00

JUMLAH PEKERJAAN BETON ATAP ( Elv + 3.20 )


JUMLAH TOTAL PEKERJAAN STRUKTUR
JUMLAH HARGA

Rp 2,400,000.00
Rp 3,409,280.00
Rp 8,337,600.00
Rp -
Rp -
Rp -

Rp 14,146,880.00

Rp 16,472,397.60
Rp 347,600.00
Rp 7,317,000.00
Rp 1,008,350.00
Rp 246,000.00

Rp 2,044,282.50
Rp 3,191,949.40

Rp 4,090,429.20
Rp 2,891,644.80
Rp 7,966,542.10

Rp 3,939,747.50
Rp 287,843.80

Rp 3,600,903.90
Rp 1,452,235.80
Rp 759,530.00

Rp 1,417,682.50
Rp 4,862,176.80

Rp 956,947.20
Rp 3,901,683.50
Rp 4,693,938.70

Rp 1,143,545.00
Rp 1,216,460.90

Rp 699,290.90
Rp 956,513.80
Rp 3,046,585.30

Rp 1,010,392.50
Rp 1,145,875.00

Rp 819,342.70
Rp 1,021,740.50
Rp 2,579,596.80

Rp 85,088,228.70
JUMLAH HARGA

Rp 1,057,387.50
Rp 3,368,872.50

Rp 86,896.70
Rp 2,396,051.90
Rp 200,447.50
Rp 5,635,283.50

Rp 1,362,855.00
Rp 1,968,154.90

Rp 3,351,915.60
Rp 617,811.70
Rp 8,326,047.40
Rp 418,014.30

Rp 4,699,500.00
Rp 5,062,017.40

Rp 12,698,403.30

Rp 51,249,659.20

Rp 1,370,687.50
Rp 2,675,847.30

Rp 2,628,571.00
Rp 5,624,448.50
Rp 1,208,319.20

Rp 2,052,115.00
Rp 2,781,267.80

Rp 6,322,222.50

Rp 768,390.00
Rp 1,607,891.80

Rp 1,058,796.20
Rp 2,767,259.00

Rp 30,865,816
Rp 181,350,583.70
RENCANA ANGGARAN BIAYA ( RAB ) ARSITEKTUR
PROYEK : PEMBANGUNAN RUMAH DAGO VALLEY
SUB PROYEK : BANGUNAN TIPE - 1 -15000 -10000
LOKASI : BANDUNG - JAWA BARAT 7500
-2500
JUMLAH HARGA
NO URAIAN PEKERJAAN SAT VOL JUMLAH HARGA
UPAH BAHAN
A PEKERJAAN LANTAI DASAR
0 1 PEKERJAAN PASANGAN & FINISHING DINDING
1 Pasangan Dinding ½ Bata merah m² 90.24 Rp 2,030,400.00 Rp 8,154,988.80 Rp 10,185,388.80
2 Pasangan Kolom Peraktis 4Ø8, Ø6-20 cm beton sitemix m¹ 22.40 Rp 268,800.00 Rp 378,470.40 Rp 647,270.40
3 Plesteran pada Dinding Bata merah m² 180.48 Rp 2,707,200.00 Rp 4,095,091.20 Rp 6,802,291.20
4 Acian pada Dinding Bata merah m² 180.48 Rp 2,256,000.00 Rp 758,016.00 Rp 3,014,016.00
5 Pek Pengecatan Dinding luar dan dalam m² 180.48 Rp 1,443,840.00 Rp 3,338,880.00 Rp 4,782,720.00

0 2 PEKERJAAN PELAFOND + RANGKA METAL FURING FULL SYISTEM


1 Pek pelafond Gypsum board t= 12 mm R. Keluarga,Makan,Pantry m² 25.57 Rp 575,325.00 Rp 2,429,150.00 Rp 3,004,475.00
2 Pek pelafond Calsium Silicate t= 8 mm
a Pelafond Teras AS - 2 - 2' m² 4.19 Rp 94,275.00 Rp 272,350.00 Rp 366,625.00
b Pelafond KM/WC AS - 2 - 2' m² 3.78 Rp 85,050.00 Rp 245,700.00 Rp 330,750.00
c Pelafond KM/WC AS - 4 - 4' m² 1.62 Rp 36,450.00 Rp 105,300.00 Rp 141,750.00
d Pelafond Kamar Pembantu m² 3.60 Rp 81,000.00 Rp 234,000.00 Rp 315,000.00
e Pelafond Teras AS - 4 - 5' m² 3.80 Rp 85,500.00 Rp 247,000.00 Rp 332,500.00
3 Pekerjaan Cuve Plafond R.Keluarga, Makan ,Pantry m¹ 6.65 Rp 149,625.00 Rp 432,250.00 Rp 581,875.00
4 Pekerjaan Pelafond Exposes bawah Tangga m² 7.50 Rp 168,750.00 Rp 487,500.00 Rp 656,250.00
a Pengecatan R. Keluarga,Makan,Pantry m² 25.57 Rp 204,560.00 Rp 460,260.00 Rp 664,820.00
b Pengecatan Teras AS - 2 - 2' m² 4.19 Rp 33,520.00 Rp 75,420.00 Rp 108,940.00
c Pengecatan KM/WC AS - 2 - 2' m² 3.78 Rp 30,240.00 Rp 68,040.00 Rp 98,280.00
d Pengecatan Kamar Pembantu m² 3.60 Rp 28,800.00 Rp 64,800.00 Rp 93,600.00
e Pengecatan Teras AS - 4 - 5' m² 3.80 Rp 30,400.00 Rp 68,400.00 Rp 98,800.00
f Pengecatan Plafond R.Keluarga, Makan ,Pantry m² 6.65 Rp 53,200.00 Rp 119,700.00 Rp 172,900.00
h Pengecatan Pelafond Exposes bawah Tangga m² 7.50 Rp 60,000.00 Rp 135,000.00 Rp 195,000.00

0 3 PEKERJAAN KUSEN PINTU DAN JENDELA + DAUN & FINISHING


1 Win # 1 unit 1.00 Rp - Rp 7,438,500.00 Rp 7,438,500.00
2 Win # 7 unit 1.00 Rp - Rp 3,160,310.00 Rp 3,160,310.00
3 Door # 1 unit 1.00 Rp - Rp 3,079,000.00 Rp 3,079,000.00
4 Door # 2 unit 1.00 Rp - Rp 6,575,000.00 Rp 6,575,000.00
5 Door # 3 unit 1.00 Rp - Rp 2,935,000.00 Rp 2,935,000.00
6 Door # 4 unit 1.00 Rp - Rp 2,908,000.00 Rp 2,908,000.00
7 Door # 5 unit 1.00 Rp - Rp 2,935,000.00 Rp 2,935,000.00
8 Door # 6 unit 3.00 Rp - Rp 8,805,000.00 Rp 8,805,000.00

0 4 PEKERJAAN KERAMIK LANTAI & DINDING KM/WC


1 Pekerjaan Keramik dinding Toilet 60x30 ( LK-4) m² 17.99 Rp 449,750.00 Rp 4,348,542.80 Rp 4,798,292.80
2 Pekerjaan Keramik dinding toilet 2 20x20 ( LK-1) m² 9.20 Rp 230,000.00 Rp 1,074,284.00 Rp 1,304,284.00
3 Pekerjaan Keramik lantai KM/WC .Pembantu 20x20 ( LK-1) m² 3.60 Rp 90,000.00 Rp 460,692.00 Rp 550,692.00
4 Pekerjaan Keramik lantai KM/WC 20x20 Unpolished ( LK-1U) m² 1.62 Rp 40,500.00 Rp 189,167.40 Rp 229,667.40
5 Pekerjaan Keramik lantai KM/WC 30x30 Unpolished ( LK-2) m² 4.19 Rp 104,750.00 Rp 536,194.30 Rp 640,944.30
6 Pekerjaan Keramik lantai R .Keluarga, Makan ,Pantry 60x60 ( LK-3) m² 25.57 Rp 639,250.00 Rp 6,180,780.40 Rp 6,820,030.40
7 Pekerjaan Grass Block Carport m² 16.42 Rp 410,500.00 Rp 2,377,451.80 Rp 2,787,951.80
8 Pekerjaan Beton Plester ,Tangga Entrance m² 7.06 Rp 176,500.00 Rp 776,600.00 Rp 953,100.00
9 Pekerjaan Lantai Papan Kayu Kamper t=30 cm ,Tangga m² 7.37 Rp 257,950.00 Rp 3,132,250.00 Rp 3,390,200.00

0 5 PEKERJAAN SANITARY
1 KM/WC - 1
a Closet duduk Ex-Tc CW4211/sw420JP bh 1.00 Rp 100,000.00 Rp 2,600,000.00 Rp 2,700,000.00
b Wastafel Ex-Tc LW665CJT1 bh 1.00 Rp 75,000.00 Rp 500,000.00 Rp 575,000.00
c Tissu Holder Ex-Tc TS116R bh 2.00 Rp 22,000.00 Rp 440,000.00 Rp 462,000.00
d Floor Drain Ex-TC TX1 BV 1N bh 1.00 Rp 21,000.00 Rp 200,000.00 Rp 221,000.00
e Jet Washer Ex-Tc THX20NBW bh 1.00 Rp 11,000.00 Rp 200,000.00 Rp 211,000.00
f Towel Bar ( gatungan handuk ) Ex-Tc TX 10 AEZ bh 1.00 Rp 25,000.00 Rp 200,000.00 Rp 225,000.00
g Meja Wastafel bh 1.00 Rp 50,000.00 Rp 450,000.00 Rp 500,000.00
h Cermin bh 1.00 Rp 15,000.00 Rp 250,000.00 Rp 265,000.00
l Screen Tray bh 1.00 Rp 11,000.00 Rp 250,000.00 Rp 261,000.00
j Kran Shower bh 1.00 Rp 45,000.00 Rp 385,000.00 Rp 430,000.00
2 KM/WC - 2
a Closet Jongkok bh 1.00 Rp 50,000.00 Rp 225,000.00 Rp 275,000.00
b Kran bh 1.00 Rp 11,000.00 Rp 200,000.00 Rp 211,000.00
c Jet Washer Ex-Tc THX20NBW bh 1.00 Rp 11,000.00 Rp 200,000.00 Rp 211,000.00
d Floor Drain Ex-Tc Tx1 BV 1 N bh 1.00 Rp 21,000.00 Rp 200,000.00 Rp 221,000.00

JUMLAH PEKERJAAN LANTAI DASAR Rp 98,672,224


RENCANA ANGGARAN BIAYA ( RAB ) ARSITEKTUR
PROYEK : PEMBANGUNAN RUMAH DAGO VALLEY
SUB PROYEK : BANGUNAN TIPE - 1 -15000 -10000
LOKASI : BANDUNG - JAWA BARAT 7500
-2500
JUMLAH HARGA
NO URAIAN PEKERJAAN SAT VOL JUMLAH HARGA
UPAH BAHAN
B PEKRJAAN LANTAI ATAS
0 1 PEKERJAAN PASANGAN & FINISHING DINDING
1 Pasangan Dinding ½ Bata merah m² 80.29 Rp 1,806,525.00 Rp 7,255,807.30 Rp 9,062,332.30
2 Pasangan Kolom Peraktis 4Ø8, Ø6-20 cm beton sitemix m¹ 6.40 Rp 76,800.00 Rp 108,134.40 Rp 184,934.40
3 Plesteran pada Dinding Bata merah m² 160.57 Rp 2,408,550.00 Rp 3,643,333.30 Rp 6,051,883.30
4 Acian pada Dinding Bata merah m² 160.57 Rp 2,007,125.00 Rp 674,394.00 Rp 2,681,519.00
5 Pek Pengecatan Dinding luar dan dalam m² 160.57 Rp 1,284,560.00 Rp 2,970,545.00 Rp 4,255,105.00

0 2 PEKERJAAN PELAFOND + RANGKA METAL FURING FULL SYISTEM


1 Pek pelafond Gypsum board t= 12 mm R. Tidur Utama AS -2-3/C-D m² 13.80 Rp 310,500.00 Rp 1,311,000.00 Rp 1,621,500.00
2 Pek Pelafond Gypsum board t= 12 mm R. Tidur Anak AS - 3-4' m² 9.48 Rp 213,300.00 Rp 900,600.00 Rp 1,113,900.00
3 Pek Pelafond Gypsum board t=12 mm R. Coridor AS - 3 -4 /A-B m² 4.84 Rp 108,900.00 Rp 459,800.00 Rp 568,700.00
4 Pek Pelafond Gypsum board t=12 mm R.Tidur anak m² 8.99 Rp 202,275.00 Rp 854,050.00 Rp 1,056,325.00
5 Pek pelafond Calsium Silicate t= 10 mm
a Pelafond KM/WC AS - 2 - 2' m² 3.73 Rp 83,925.00 Rp 261,100.00 Rp 345,025.00
6 Pekerjaan Pengecatan Pelafond
a Pengecatan R. Tidur Utama AS -2-3/C-D m² 13.80 Rp 110,400.00 Rp 248,400.00 Rp 358,800.00
b Pengecatan R. Tidur Anak AS - 3-4' m² 9.48 Rp 75,840.00 Rp 170,640.00 Rp 246,480.00
c Pengecatan R. Coridor AS - 3 -4 /A-B m² 4.84 Rp 38,720.00 Rp 87,120.00 Rp 125,840.00
d Pengecatan R.Tidur anak m² 8.99 Rp 71,920.00 Rp 161,820.00 Rp 233,740.00
f Pengecatan KM/WC AS - 2 - 2' m² 3.73 Rp 29,840.00 Rp 67,140.00 Rp 96,980.00

0 3 PEKERJAAN KUSEN PINTU DAN JENDELA + DAUN & FINISHING


1 Win # 1 unit 1.00 Rp - Rp 7,438,500.00 Rp 7,438,500.00
2 Win # 2 unit 1.00 Rp - Rp 3,550,800.00 Rp 3,550,800.00
3 Win # 3 unit 1.00 Rp - Rp 3,319,820.00 Rp 3,319,820.00
4 Win # 4 unit 1.00 Rp - Rp 3,160,310.00 Rp 3,160,310.00
5 Win # 5 unit 1.00 Rp - Rp 3,079,000.00 Rp 3,079,000.00
6 Win # 6 unit 1.00 Rp - Rp 2,962,000.00 Rp 2,962,000.00
7 Door # 3 unit 1.00 Rp - Rp 2,935,000.00 Rp 2,935,000.00
8 Door # 7 unit 3.00 Rp - Rp 8,805,000.00 Rp 8,805,000.00

0 4 PEKERJAAN KERAMIK LANTAI & DINDING KM/WC


1 Pekerjaan Keramik lantai R.Tidur Utama 30x30 ( LK-2) m² 9.93 Rp 248,250.00 Rp 1,270,742.10 Rp 1,518,992.10
2 Pekerjaan Keramik lantai KM/WC - 1 30x30 Unpolished ( LK-2U) m² 2.88 Rp 72,000.00 Rp 368,553.60 Rp 440,553.60
3 Pekerjaan Keramik lantai Teras 60x60 ( LK-3) m² 4.69 Rp 117,250.00 Rp 1,133,666.80 Rp 1,250,916.80
4 Pekerjaan Keramik lantai R.Makan,Pantry,R.Keluarga 60x60 ( LK-3) m² 22.25 Rp 556,250.00 Rp 5,378,270.00 Rp 5,934,520.00
5 Pekerjaan Keramik dinding KM/WC -1 60x60 ( LK-4) m² 10.8 Rp 270,000.00 Rp 2,610,576.00 Rp 2,880,576.00
6 Pekerjaan lanatai Paving Block area Carport m² 18.59 Rp 464,750.00 Rp 2,691,646.10 Rp 3,156,396.10

0 5 PEKERJAAN SANITARY
1 KM/WC - 1
a Closet duduk Ex-Tc CW4211/sw420JP bh 1.00 Rp 100,000.00 Rp 2,600,000.00 Rp 2,700,000.00
b Wastafel Ex-Tc LW665CJT1 bh 1.00 Rp 75,000.00 Rp 500,000.00 Rp 575,000.00
c Tissu Holder Ex-Tc TS116R bh 2.00 Rp 22,000.00 Rp 440,000.00 Rp 462,000.00
d Floor Drain Ex-TC TX1 BV 1N bh 1.00 Rp 21,000.00 Rp 200,000.00 Rp 221,000.00
e Jet Washer Ex-Tc THX20NBW bh 2.00 Rp 22,000.00 Rp 400,000.00 Rp 422,000.00
f Towel Bar ( gatungan handuk ) Ex-Tc TX 10 AEZ bh 1.00 Rp 25,000.00 Rp 200,000.00 Rp 225,000.00
g Meja Wastafel bh 1.00 Rp 50,000.00 Rp 450,000.00 Rp 500,000.00
h Cermin bh 1.00 Rp 15,000.00 Rp 250,000.00 Rp 265,000.00
l Screen Tray bh 1.00 Rp 11,000.00 Rp 250,000.00 Rp 261,000.00
j Kran Shower bh 1.00 Rp 45,000.00 Rp 385,000.00 Rp 430,000.00

JUMLAH PEKERJAAN LANTAI ATAS Rp 84,496,448.60

C PEKERJAAN LANTAI ATAP


0 1 PEKERJAAN PASANGAN & FINISHING DINDING
1 Pasangan Dinding ½ Bata merah m² 32.56 Rp 732,600.00 Rp 2,942,447.20 Rp 3,675,047.20
2 Plesteran pada Dinding Bata merah m² 63.13 Rp 946,950.00 Rp 1,432,419.70 Rp 2,379,369.70
3 Acian pada Dinding Bata merah m² 63.13 Rp 789,125.00 Rp 265,146.00 Rp 1,054,271.00
4 Pek Pengecatan Dinding luar m² 39.35 Rp 314,800.00 Rp 727,975.00 Rp 1,042,775.00

0 2 PEKERJAAN PELAFOND + RANGKA METAL FURING FULL SYISTEM


1 Pek pelafond Calsium Silicate t= 10 mm
a Pelafond area Atap m² 12.14 Rp 303,500.00 Rp 849,800.00 Rp 1,153,300.00
2 Pekerjaan Pengecatan Pelafond
a Pengecatan area Atap m² 12.14 Rp 97,120.00 Rp 218,520.00 Rp 315,640.00
RENCANA ANGGARAN BIAYA ( RAB ) ARSITEKTUR
PROYEK : PEMBANGUNAN RUMAH DAGO VALLEY
SUB PROYEK : BANGUNAN TIPE - 1 -15000 -10000
LOKASI : BANDUNG - JAWA BARAT 7500
-2500
JUMLAH HARGA
NO URAIAN PEKERJAAN SAT VOL JUMLAH HARGA
UPAH BAHAN

0 3 PEKERJAAN WATER PROFING MEMBRANE LANTAI


1 Dak Atap Beton AS - A-B/2-6 m² 20.37 Rp 509,250.00 Rp 3,666,600.00 Rp 4,175,850.00
3 Pekerjaan Sky Light Kaca t= 8 mm m² 5.1 Rp 229,500.00 Rp 720,349.50 Rp 949,849.50

0 4 PEKERJAAN ATAP
1 Pekerjaan Rangka Atap Baja ringan + Aluminium Foil double m² 43.09 Rp - Rp 7,971,650.00 Rp 7,971,650.00
2 Pekerjaan Penutup Atap Genteng Keramik Ex-Roman type Milenio m² 43.09 Rp 646,350.00 Rp 7,109,850.00 Rp 7,756,200.00
3 Pekerjaan Nok Atap m¹ 6.45 Rp 496,650.00 Rp 741,750.00 Rp 1,238,400.00
4 Pekerjaan Listplank + Finishing Cat m¹ 26.26 Rp 787,800.00 Rp 919,100.00 Rp 1,706,900.00

0 5 PEKERJAAN LAIN-LAIN
1 Pekerjaan Grill Kayu
- Tampak - B / AS - 2'/C-D m² 8.27 Rp 206,750.00 Rp 2,619,654.82 Rp 2,826,404.82
2 Pekerjaan Pemasangan Kaca
- Tampak - B Uk 10x270 cm unit 1.00 Rp 17,500.00 Rp 65,000.00 Rp 82,500.00
3 Pekerjaan Pemasangan Batu Alam tampak Depan m² 11.31 Rp 282,750.00 Rp 2,827,500.00 Rp 3,110,250.00
4 Pekerjaan Pemasangan Batu Alam + Coating area Tampak ( A ) m² 14.50 Rp 362,500.00 Rp 3,625,000.00 Rp 3,987,500.00

JUMLAH PEKERJAAN LANTAI ATAP Rp 43,425,907.22


JUMLAH TOTAL PEKERJAAN ARSITEKTUR Rp 226,594,579.92
RENCANA ANGGARAN BIAYA ( RAB ) MEKANIKAL ELEKTRIKAL
PROYEK : PEMBANGUNAN RUMAH DAGO VALLEY
SUB PROYEK : BANGUNAN TIPE - 1
LOKASI : BANDUNG - JAWA BARAT

NO URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN

I ELEKTRIKAL

Harga satuan pekerjaan sudah termasuk pengadaan,


pemasangan dan pengetesan material serta material bantu
yang diperlukan sehingga pekerjaan tersebut dinyatakan
tercapai dengan baik. Pekerjaan harus dilaksanakan sesuai
dengan gambar dan spesifikasi teknis.

A LANTAI DASAR

1 MCB BOX LT. DASAR (1) Unit 1 510,000

2 Kabel dari kWH Meter ke MCB Lt. Dasar


- NYM 3 x 6 mm2 m 5 65,000

3 Lampu Penerangan dan Accessories


- Downlight Bh 11 55,000
- Wall Mounted - Neon/ TL ( Lampu Wastafel ) Bh 1 175,000
- Lampu Taman l/d tiang setinggi 1 meter Bh 4 250,000

- TV Outlet Bh 1 45,000
- Telepon Bh 1 35,000
- Saklar Tunggal Bh 5 30,000
- Saklar Ganda Bh 5 35,000

- Stop Kontak Bh 3 30,000

3 Instalasi Lampu Penerangan dan Accessories


- Instalasi Lampu
- NYM 3 x 2,5 mm2 in PVC HI Conduit dia. 20 mm Titik 12 250,000
- Instalasi Lampu Taman
- NYY 3 x 2,5 mm2 in PVC HI Conduit dia. 20 mm Titik 4 300,000

- Instalasi TV Outlet
- Coaxial RG-6 Titik 1 255,000
- Instalasi Telepon
- ITC 2 x 2 x 0,6 mm2 in PVC HI Conduit dia. 20 mm Titik 1 210,000

- Instalasi Stop Kontak


- NYM 3 x 2,5 mm2 in PVC HI Conduit dia. 20 mm Titik 3 250,000

JUMLAH PEKERJAAN LANTAI DASAR

B LANTAI ATAS

1 MCB BOX LT. ATAS (2) Unit 1 510,000


2 Kabel dari MCB Box Lt. Dasar ke MCB Box Lt. Atas
- NYM 3 x 6 mm2 m 10 65,000

3 Lampu Penerangan dan Accessories


- Downlight Bh 12 55,000
- Wall Mounted - Neon/ TL ( Lampu Wastafel ) Bh 1 175,000
- Lampu Taman l/d tiang setinggi 1 meter Bh 1 250,000

- Saklar Tunggal Bh 6 30,000


- Saklar Ganda Bh 3 35,000

- Stop Kontak Bh 3 30,000

4 Instalasi Lampu Penerangan dan Accessories


- Instalasi Lampu
- NYM 3 x 2,5 mm2 in PVC HI Conduit dia. 20 mm Titik 13 250,000
- Instalasi Lampu Taman
- NYY 3 x 2,5 mm2 in PVC HI Conduit dia. 20 mm Titik 1 300,000

- Instalasi Stop Kontak


- NYM 3 x 2,5 mm2 in PVC HI Conduit dia. 20 mm Titik 3 250,000

C PENANGKAL PETIR
- Menggunakan Tipe Konvensional (Splitzen) lengkap Titik 3 1,500,000
dengan Bak Kontrol, Kabel BC atau kabel penghantar
lainnya lengkap dengan accessories dan material bantu
lainnya.

JUMLAH PEKERJAAN LANTAI ATAS

Sub Total - LANTAI DASAR

Sub Total - LANTAI ATAS

A PENJUMLAHAN TOTAL - ELEKTRIKAL

II TATA UDARA

Harga satuan pekerjaan sudah termasuk pengadaan,


pemasangan dan pengetesan material serta material bantu
yang diperlukan sehingga pekerjaan tersebut dinyatakan
tercapai dengan baik. Pekerjaan harus dilaksanakan sesuai
dengan gambar dan spesifikasi teknis.

A LANTAI DASAR

A.1 PERALATAN UTAMA

1 PERALATAN UTAMA UNIT AC


1.1 Unit AC - IU-DS.01 Unit 1
- Kap: 7.000 BTU/H
- Tip : Split Wall Mounted
- Ar : Ruang Keluarga

2 PERALATAN UTAMA UNIT FAN


2.1 EF-DS.01 Unit 1 350,000
- Kap: 50 cfm
- Tip : Ceiling Mounted
- Are: Toilet R. Makan
2.2 EF-DS.02 Unit 1 350,000
- Kap: 50 cfm
- Tip : Ceiling Mounted
- Are: Toilet R. Pembantu

A.2 INSTALASI PEMIPAAN

1 Pipa Refrigerant
Pengadaan, Pemasangan dan Pengetesan Pipa Refrigerant
dari bahan Cooper lengkap dengan peralatan bantu,
accessories dan semua material sehingga dapat berfungsi
dengan baik dan benar sesuai dengan gambar dan spesifikasi
teknis.

- OU-ke IU-DS.01 m 6 175,000


1/2 (G) + 1/4 (L)

2 Pipa Drain
Pengadaan, Pemasangan dan Pengetesan Pipa Drain dari
bahan PVC Klas AW lengkap dengan isolasi, peralatan
bantu, accessories dan semua material sehingga dapat
berfungsi dengan baik dan benar sesuai dengan Gambar
dan Spesifikasi Teknis.

- diameter 20 mm m 6 30,000

3 Pipa Exhaust Toilet


Pengadaan, Pemasangan dan Pengetesan Pipa Exhaust dari
bahan PVC Klas AW lengkap dengan isolasi, peralatan
bantu, accessories dan semua material sehingga dapat
berfungsi dengan baik dan benar sesuai dengan Gambar
dan Spesifikasi Teknis.

- diameter 100 mm m 2 55,000

- Exhaustdiameter 100 mm Bh 2 35,000

JUMLAH PEKERJAAN LANTAI DASAR

II TATA UDARA

B LANTAI ATAS

B.1 PERALATAN UTAMA

1 PERALATAN UTAMA UNIT AC


1.1 Unit AC - IU-A.01 Unit 1
- Kap: 7.000 BTU/H
- Tip : Split Wall Mounted
- Are: Ruang Tidur Utama

1.2 Unit AC - IU-A.02 Unit 1


- Kap: 7.000 BTU/H
- Tip : Split Wall Mounted
- Are: Ruang Tidur Anak

1.3 Unit AC - IU-A.03 Unit 1


- Kap: 5.000 BTU/H
- Tip : Split Wall Mounted
- Are: Ruang Tidur Anak

2 PERALATAN UTAMA UNIT FAN


2.1 EF-DS.01 Unit 1 350,000
- Kap: 150 cfm
- Tip : Ceiling Mounted
- Are: Toilet R. Tidur Utama

B.2 INSTALASI PEMIPAAN

1 Pipa Refrigerant
Pengadaan, Pemasangan dan Pengetesan Pipa Refrigerant
dari bahan Cooper lengkap dengan peralatan bantu,
accessories dan semua material sehingga dapat berfungsi
dengan baik dan benar sesuai dengan gambar dan spesifikasi
teknis.

- OU-ke IU-A.01 m 6 175,000


1/2 (G) + 1/4 (L)

- OU-ke IU-A.02 m 6 175,000


1/2 (G) + 1/4 (L)

- OU-ke IU-A.03 m 6 175,000


1/2 (G) + 1/4 (L)

2 Pipa Drain
Pengadaan, Pemasangan dan Pengetesan Pipa Drain dari
bahan PVC Klas AW lengkap dengan isolasi, peralatan
bantu, accessories dan semua material sehingga dapat
berfungsi dengan baik dan benar sesuai dengan Gambar
dan Spesifikasi Teknis.

- diameter 20 mm m 18 30,000

B.2 INSTALASI PEMIPAAN

3 Pipa Exhaust Toilet


Pengadaan, Pemasangan dan Pengetesan Pipa Exhaust dari
bahan PVC Klas AW lengkap dengan isolasi, peralatan
bantu, accessories dan semua material sehingga dapat
berfungsi dengan baik dan benar sesuai dengan Gambar
dan Spesifikasi Teknis.

- diameter 150 mm m 2 75,000

- Exhaustdiameter 150 mm Bh 1 35,000

JUMLAH PEKERJAAN LANTAI ATAS

Sub Total - LANTAI DASAR

Sub Total - LANTAI ATAS


B PENJUMLAHAN TOTAL TATA UDARA

III PLUMBING
Harga satuan pekerjaan sudah termasuk pengadaan,
pemasangan dan pengetesan material serta material bantu
yang diperlukan sehingga pekerjaan tersebut dinyatakan
tercapai dengan baik. Pekerjaan harus dilaksanakan sesuai
dengan gambar dan spesifikasi teknis.

A PERALATAN UTAMA

1 Jet Pump Unit 1 5,500,000


- Kap: 100 LPM
- Hea: 25 meter
- Pow: 900 W
2 Bak Tangki Atas Unit 1 2,000,000
- Kap: 1500 liter
- Ope: menggunakan WLC

B INSTALASI PEMIPAAN

1 Pipa Air Bersih


Pengadaan, Pemasangan dan Pengetesan Pipa Air bersih
dari bahan PPR PN 10 lengkap dengan support,
accessories dan material bantu lainnya yang diperlukan
sehingga dapat berfungsi dengan baik.

- diameter 32 mm m 8 107,000
- diameter 25 mm m 32 67,500
- diameter 20 mm m 16 52,000
- diameter 15 mm m 28 52,000

- Fitting dan Accessories Lot 1 750,000


B INSTALASI PEMIPAAN

2 Pipa Air Bekas


Pengadaan, Pemasangan dan Pengetesan Pipa Air bersih
dari bahan PVC Klas AW lengkap dengan support,
accessories dan material bantu lainnya yang diperlukan
sehingga dapat berfungsi dengan baik.

- diameter 80 mm m 12 47,500
- diameter 65 mm m 16 35,000
- diameter 50 mm m 8 25,000
- diameter 40 mm m 3 22,500

- Fitting dan Accesories Lot 1 750,000

3 Pipa Air Kotor


Pengadaan, Pemasangan dan Pengetesan Pipa Air bersih
dari bahan PVC Klas AW lengkap dengan support,
accessories dan material bantu lainnya yang diperlukan
sehingga dapat berfungsi dengan baik.

- diameter 100 mm m 30 85,000

- Fitting dan Accessories Lot 1 750,000


4 Pipa Vent
Pengadaan, Pemasangan dan Pengetesan Pipa Air bersih
dari bahan PVC Klas D lengkap dengan support,
accessories dan material bantu lainnya yang diperlukan
sehingga dapat berfungsi dengan baik.

- diameter 32 mm m 9 17,500
- Vent Cup, diameter 25 mm Bh 3 15,000

- Fitting dan Accessories Lot 1 75,000

5 Pipa Air Hujan


Pengadaan, Pemasangan dan Pengetesan Pipa Air bersih
dari bahan PVC Klas AW lengkap dengan support,
accessories dan material bantu lainnya yang diperlukan
sehingga dapat berfungsi dengan baik.

- diameter 80 mm m 38 47,500
- Roof Drain, diameter 80 mm Bh 5 75,000

- Fitting dan Accesories Lot 1 500,000

7 Accessories
- Gate Valve, diameter 25 mm Bh 1 135,000
- Gate Valve, diameter 15 mm Bh 4 125,000

8 Septictank, kap. 1 m3 Unit 1 2,750,000

C PENJUMLAHAN TOTAL PEKERJAAN PLUMBING

IV PERIJINAN SAMBUNGAN BARU


- PLN VA 3,500
- PDAM m3 5
- TELEPON Line 1

D JUMLAH PERIJINAN SAMBUNGAN BARU

JUMLAH TOTAL PEKERJAAN ME


ELEKTRIKAL

TOTAL

510,000

325,000

605,000
175,000
1,000,000

45,000
35,000
150,000
175,000

90,000

3,000,000

1,200,000

255,000

210,000

750,000

Rp 8,525,000

510,000
650,000

660,000
175,000
250,000

180,000
105,000

90,000

3,250,000

300,000

750,000

4,500,000

Rp 11,420,000

8,525,000

11,420,000

Rp 19,945,000

By Tenant

350,000
350,000

1,050,000

180,000

110,000

70,000

Rp 2,110,000

By Tenant

By Tenant

By Tenant
350,000

1,050,000

1,050,000

1,050,000

540,000

150,000

35,000

Rp 4,225,000

2,110,000

4,225,000
Rp 6,335,000

5,500,000

2,000,000

856,000
2,160,000
832,000
1,456,000

750,000

570,000
560,000
200,000
67,500

750,000

2,550,000

750,000
157,500
45,000

75,000

1,805,000
375,000

500,000

135,000
500,000

2,750,000

Rp 25,344,000

3,900,000
2,500,000
450,000

Rp 6,850,000

Rp 58,474,000
TIME SCHEDULE
PROYEK : PEMBANGUNAN RUMAH DAGO VALLEY
SUB PROYEK : BANGUNAN TYPE - 1

LOKASI : BANDUNG JAWA BARAT

Bulan 1 Bulan 2 Bulan 3 Bulan 4 Bulan 5


NO. Uraian Pekerjaan Bobot % Prosentase Keterangan
I II III IV I II III IV I II III IV I II III IV I II III IV
100%
A PEKERJAAN PERSIAPAN 3.03 1.52 1.52 - - - - - - - - - - - - - - - - - -
B PEKERJAAN STRUKTUR
I. Pekerjaan Beton Lt. Dasar ( Elv. -3.20 )
1 Pekerjaan Batu Kali 5.44 - 2.72 2.72 - - - - - - - - - - - - - - - - -
2 Pekerjaan Tie Biam 4.33 - - - 2.16 2.16 - - - - - - - - - - - - - - -
3 Pekerjaan Plat Lantai 2.15 - - - - - 1.08 1.08 - - - - - - - - - - - - -
4 Pekerjaan Kolom 3.39 - - - - - 1.13 1.13 1.13 - - - - - - - - - - - -
5 Pekerjaan Tangga 1 1.51 - - - - - - 0.50 0.50 0.50 - - - - - - - - - - -
6 Pekerjaan Tangga 2 1.41 - - - - - - - - 0.47 0.47 0.47 - - - - - - - - -
II. Pekerjaan Beton Lt. Atas ( Elv. ± 0.00 )
1 Pekerjaan Kolom 2.73 - - - - - - - - 0.91 0.91 0.91 - - - - - - - - -

JANGKA WAKTU PEMELIHARAAN PEKERJAAN : 160 HARI KALENDER


2 Pekerjaan Balok 3.44 - - - - - - 1.15 1.15 1.15 - - - - - - - - - - - 75%

JANGKA WAKTU PELAKSANAAN PEKERJAAN : 150 HARI KALENDER


3 Pekerjaan Plat Lantai 4.82 - - - - - - 1.61 1.61 1.61 - - - - - - - - - - -
III. Pekerjaan Beton Atap ( Elv. + 3.20 )
1 Pekerjaan Ring Balok 2.90 - - - - - - - - - - 1.45 1.45 - - - - - - - -
2 Pekerjaan Plat Lantai 2.39 - - - - - - - - - - - 1.20 1.20 - - - - - - -
3 Pekerjaan Balok Kuda-kuda 1.33 - - - - - - - - - - - 0.66 0.66 - - - - - - -
C PEKERJAAN ARSITEKTUR
I. Pekerjaan Lt. Dasar - - - - - - - - - - - - - - - - - - - -
1 Pekerjaan Pasangan & Finishing Dinding 5.45 - - - - - - - - - 1.82 1.82 1.82 - - - - - - - -
2 Pekerjaan Plafond + Rangka Metal 1.54 - - - - - - - - - - - - 0.77 0.77 - - - - - - 50%
3 Pekerjan Kusen Pintu & Jendela 8.11 - - - - - - - - - - - 2.70 2.70 2.70 - - - - - -
4 Pekerjaan Keramik Lantai & Dinding KM/WC 4.60 - - - - - - - - - - - - 2.30 2.30 - - - - - -
5 Pekerjaan Sanitary 1.45 - - - - - - - - - - - - - - 0.73 0.73 - - - -
II. Pekerjaan Lt. Atas
1 Pekerjaan Pasangan & Finishing Dinding 4.77 - - - - - - - - - - - - - 1.59 1.59 1.59 - - - -
2 Pekerjaan Plafond + Rangka Metal 1.24 - - - - - - - - - - - - - - - - 0.62 0.62 - -
3 Pekerjan Kusen Pintu & Jendela 7.56 - - - - - - - - - - - - - - - 2.52 2.52 2.52 - -
4 Pekerjaan Keramik Lantai & Dinding KM/WC 3.26 - - - - - - - - - - - - - - - - 1.63 1.63 - -
5 Pekerjaan Sanitary 1.30 - - - - - - - - - - - - - - - - - 0.65 0.65 -
III. Pekerjaan Lt. Atap
1 Pekerjaan Pasangan & Finishing Dinding 1.75 - - - - - - - - - - - - - 0.87 0.87 - - - - - 25%
2 Pekerjaan Plafond + Rangka Metal 0.31 - - - - - - - - - - - - - - 0.31 - - - - -
3 Pekerjaan Water Proofing Membrane Lantai 1.10 - - - - - - - - - - - - - - 0.55 0.55 - - - -
4 Pekerjaan Atap 4.00 - - - - - - - - - - - - - 2.00 2.00 - - - - -
5 Pekerjaan Lain-Lain 2.15 - - - - - - - - - - - - - - - - - - - 2.15
D PEKERJAAN ME
I. Pekerjaan Elektrikal 4.28 - - - - - - - - - - - - - - - - 1.43 1.43 1.43 -
II. Pekerjaan Tata Udara 1.36 - - - - - - - - - - - - - - - 0.68 0.68 -
III. Pekerjaan Plumbing 5.43 - - - - - - - - - - - - - - - 1.811 1.811 1.811 - -
IV. Pekerjaan Perijinan Sambungan Baru 1.47 - - - - - - - - - - - - - - - - 1.47 - - - 0%
Jumlah Nilai Bobot Pekerjaan 100.00
Nilai Bobot Rencana Dalam Minggu 1.52 4.24 2.72 2.16 2.16 2.21 5.46 4.39 4.64 3.20 4.65 7.83 7.63 10.24 6.05 7.19 9.47 9.33 2.75 2.15
Akumulasi Rencana Pelaks Pekerjaan 1.52 5.76 8.48 10.64 12.80 15.01 20.48 24.86 29.50 32.70 37.35 45.18 52.81 63.05 69.11 76.30 85.77 95.10 97.85 100.00