Anda di halaman 1dari 34

PT. REMBANG MIGAS ENERGI PT.

BUMIREJO MANDIRI PERKASA

PROPOSAL
KAWASAN INDUSTRI TERINTEGRASI
KABUPATEN REMBANG
JAWA TENGAH - INDONESSIA

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
INFORMASI TATA RUANG (ITR) – 3 BLOK

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
INFORMASI TATA RUANG (ITR)-BLOK TRAHAN

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
INFORMASI TATA RUANG (ITR)-BLOK JATISARI

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
INFORMASI TATA RUANG (ITR)-BLOK BLIMBING

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
LATAR BELAKANG

Koridor Ekonomi Jawa Tengah memiliki banyak daerah yang sangat berpotensi untuk
dikembangkan sebagai klaster industri Terintegrasi karena tersedianya potensi bahan
baku, sumber daya manusia, layanan jasa, pangsa pasar, minyak bumi dan gas alam.
Daerah tersebut salah satunya adalah Kabupaten Rembang yang memiliki potensi
infrastruktur serta produk-produk pertanian.

Kawasan Trahan, Jatisari, Blimbing dan Sluke Kawasan tersebut telah dimasukan
dalan Rencana Tata Ruang Wilayah (RTRW) sebagai kawasan industri oleh
pemerintah daerah Rembang

Kelebihan Kab. Remabang selain memiliki sumber hasil tambang juga memiliki
Pelabuhan yang dapat dikembangkan menjadi Pelabuhan bertaraf International
sebagai Toll Laut juga Kab. Rembang akan dilalui Toll Pantura Semarang – Gresik.

JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
TEMA KAWASAN INDUSTRI TERINTREGASI

Konsep Green Industry:


1. Aspek konsumsi air dan sumber daya alam lainnya oleh industri.
A 2. Aspek pengelolaan limbah industri.
3. Aspek manajemen daur air yang ada di kawasan.

Konsep Kawasan dengan Cluster Tertutup :


Kawasan perencanaan sebagai sebuah kawasan yang akan memiliki
B beberapa insentif khusus di bidang perpajakan, insfrastruktur dan
lainlain yang memerlukan batas fisik yang jelas agar penerapan
insentif tersebut tepat sasaran.

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
BLOK - KAWASAN INDUSTRI TERINTREGASI REMBANG

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
LUAS AREA BLOK - KAWASAN INDUSTRI TERINTREGASI REMBANG

No. BLOK SATUAN LUAS STATUS


1 TRAHAN HA 560
2 JATISARI HA 300
3 BLIMBING HA 200
4 PELABUHAN + PERLUASAN HA 85
5 PENGOLAHAN LIMBAH B3 HA 40
6 TOTAL HA 1,185

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
RENCANA ANGGARAN BIAYA BLOK TRAHAN ( 420.2 Ha )

No. URAIAN SATTUAN HARGA @ TOTAL


A. PENGADAAN LAHAN.
1 Pembebasan Lahan 5.600.000 m² 400,000 2.240.000.000.000
2 Legalitas Pembebasan Lahan 5.600.000 m² 50,000 280.000.000.000
3 Perencanaan, Drawing, Bathimetry, DED 5.600.000 m² 15,000 84.000.000.000
4 Koordinasi dan Perijinan 5.600.000 m² 2,000 11.200.000.000
5 Konsultan Perencana 5.600.000 m² 3,500 19.600.000.000
6 AMDAL 5.600.000 m² 4,000 22.400.000.000
7 Pematangan Lahan – Clearing, Cut & Fill 5.600.000 m² 150,000 840.000.000.000
Sub-Total 3.497.200.000.000

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
RENCANA ANGGARAN BIAYA BLOK TRAHAN ( 420.2 Ha )
No. URAIAN SATUAN HARGA @ TOTAL
B. INFRASTRUKTUR
1 Pembuatab Jalan Primer 32m ROW 5 km 55,280,000,00 371,481,600,000
0
2 Pembuatan Jalan Sekunder 24m ROW 7 km 41,460,000,00 371,481,600,000
0
3 Saluran Air Terbuka Heavy Duty Uditch 24 km 525,000,000 16,464,000,000
(80x100x120)
4 Listrik PLN Kap. 100 MVa 4,202,000 m² 18,250 102,200,000,000
5 Air Bersih Kap. 1.000 Lt/Detik 4,202,000 m² 15,000 84,000,000,000
6 Komunikasi Telepon/Internet 5G 1,000 sst 1,500,000 1,500,000,000
7 Fire Hydrant 24 km 350,000,000 10,976,000,000
8 Pemasasngan Pagar Precast 2.4 m 17,095 m¹ 525,000 8,974,875,000
Sub-Total 967,078,075,000

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
RENCANA ANGGARAN BIAYA BLOK TRAHAN ( 420.2 Ha )

No. URAIAN SATTUAN HARGA @ TOTAL


C. KANTOR – FASUM & FASOS
1 Kantor Staff 500 m² 4,200,000 2,100,000,000
2 Tempat Ibadah 250 m² 5,000,000 1,250,000,000
3 Fasilitas Olah Raga 1,000 m² 2,500,000 2,500,000,000
4 Pos Satpam 75 m² 315,000,000
5 Gapura/Gerbang 1 Unit 750,000,000 75,000,000
Sub-Total 6,915,000,000

GRAND TOTAL (A+B+C) 4,471,193,075,000

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
RENCANA ANGGARAN BIAYA BLOK JATISARI ( 216,6 Ha)

No. URAIAN SATTUAN HARGA @ TOTAL


A. PENGADAAN LAHAN.
1 Pembebasan Lahan 3,000,000 m² 400,000 1,200,000,000,000
2 Legalitas Pembebasan Lahan 3,000,000 m² 50,000 150,000,000,000
3 Perencanaan, Drawing, Bathimetry, DED 3,000,000 m² 15,000 45,000,000,000
4 Koordinasi dan Perijinan 3,000,000 m² 2,000 6,000,000,000
5 Konsultan Perencana 3,000,000 m² 3,500 10,500,000,000
6 AMDAL 3,000,000 m² 4,000 12,000,000,000
7 Pematangan Lahan – Clearing, Cut & Fill 3,000,000 m² 150,000 450,000,000,000
Sub-Total 1,873,500,000,000

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
RENCANA ANGGARAN BIAYA BLOK JATISARI ( 216,6 Ha)

No. URAIAN SATTUAN HARGA @ TOTAL


B. INFRASTRUKTUR
1 Pembuatab Jalan Primer 32m ROW 3.6 km 55,280,000,000 199,008,000,000
2 Pembuatan Jalan Sekunder 24m ROW 4,8 km 41,460,000,000 199,008,000,000
3 Saluran Air Terbuka Heavy Duty Uditch 12 km 525,000,000 5,520,000,000
(80x100x120)
4 Listrik PLN Kap. 100 MVa 2,166,150 m² 18,250 54,750,000,000
5 Air Bersih Kap. 1.000 Lt/Detik 2,166,150 m² 15,000 45,000,000,000
6 Komunikasi Telepon/Internet 5G 500 sst 1,500,000 750,000,000
7 Fire Hydrant 16 km 350,000,000 5,880,000,000
8 Pemasasngan Pagar Precast 2.4 m 8,548 m¹ 525,000 4,487,427,500
Sub-Total 517,703,437,500

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
RENCANA ANGGARAN BIAYA BLOK JATISARI ( 216,6 Ha)

No. URAIAN SATTUAN HARGA @ TOTAL


C. KANTOR – FASUM & FASOS
1 Kantor Staff 150 m² 4,200,000 630,000,000
2 Tempat Ibadah 100 m² 5,000,000 500,000,000
3 Fasilitas Olah Raga 500 m² 2,500,000 1,250,000,000
4 Pos Satpam 75 m² 4,200,000 315,000,000
5 Gapura/Gerbang 1 Unit 750,000,000 75,000,000
Sub-Total 3,445,000,000

GRAND TOTAL (A+B+C) 2,394,648,437,500

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
RENCANA ANGGARAN BIAYA BLOK BLIMBING (206.9 Ha)

No. URAIAN SATTUAN HARGA @ TOTAL


A. PENGADAAN LAHAN.
1 Pembebasan Lahan 2,000,000 m² 400,000 800,000,000,000
2 Legalitas Pembebasan Lahan 2,000,000 m² 50,000 100,000,000,000
3 Perencanaan, Drawing, Bathimetry, DED 2,000,000 m² 15,000 30,000,000,000
4 Koordinasi dan Perijinan 2,000,000 m² 2,000 4,000,000,000
5 Konsultan Perencana 2,000,000 m² 3,500 7,000,000,000
6 AMDAL 2,000,000 m² 4,000 8,000,000,000
7 Pematangan Lahan – Clearing, Cut & Fill 2,000,000 m² 150,000 300,000,000,000
Sub-Total 1,249,000,000,000

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
RENCANA ANGGARAN BIAYA BLOK JATISARI ( 216,6 Ha)

No. URAIAN SATTUAN HARGA @ TOTAL


B. INFRASTRUKTUR
1 Pembuatab Jalan Primer 32m ROW 2,4 km 55,280,000,000 132,672,000,000
2 Pembuatan Jalan Sekunder 24m ROW 3,2 km 41,460,000,000 132,672,000,000
3 Saluran Air Terbuka Heavy Duty Uditch 12 km 525,000,000 5,880,000,000
(80x100x120)
4 Listrik PLN Kap. 100 MVa 2,069,760 m² 18,250 36,500,000,000
5 Air Bersih Kap. 1.000 Lt/Detik 2,069,760 m² 15,000 30,000,000,000
6 Komunikasi Telepon/Internet 5G 250 sst 1,500,000 375,000,000
7 Fire Hydrant 12 km 350,000,000 3,920,000,000
8 Pemasasngan Pagar Precast 2.4 m 8,548 m¹ 525,000 4,487,427,500
Sub-Total 1,598,951,437,500

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
RENCANA ANGGARAN BIAYA BLOK JATISARI ( 216,6 Ha)

No. URAIAN SATTUAN HARGA @ TOTAL


C. KANTOR – FASUM & FASOS
1 Kantor Staff 150 m² 4,200,000 630,000,000
2 Tempat Ibadah 100 m² 5,000,000 500,000,000
3 Fasilitas Olah Raga 500 m² 2,500,000 1,250,000,000
4 Pos Satpam 75 m² 4,200,000 315,000,000
5 Gapura/Gerbang 1 Unit 750,000,000 75,000,000
Sub-Total 3,445,000,000

GRAND TOTAL (A+B+C) 1,598,951,437,500

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
RENCANA ANGGARAN BIAYA BLOK PELABUHAN (854.0 Ha)

No. URAIAN SATTUAN HARGA @ TOTAL


A. PENGADAAN LAHAN.
1 Akuisisi 264,000 m² 1,500,000 396,000,000,000
2 Reklamasi Tahap Pengembangan yg sudah ada
AMDAL
3 - Batu Boulder dan Pemasangan 854,000 m² 120,000 66,096,000,000
4 - Geotextile dan Pemasangan 136,000 m² 18,000 2,448,000,000
5 -Timbunan dan Pemadatan 856,800 m³ 75,000 64,260,000,000
6 -Administrasi Proyek 1,407,600 1,500 2,111,400,000

Sub-Total 350,915,400,000

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
RENCANA ANGGARAN BIAYA BLOK PELABUHAN (85,4 Ha)

No. URAIAN SATTUAN HARGA @ TOTAL


B. PERLUASAN
1 Perencanaan, Drawing, Bathimetry, DED 590,000 m² 15,000 8,850,000,000
2 AMDAL 590,000 m² 5,000 2,950,000,000
3 Rencana Induk Pelabuhan (RIP) 590,000 m² 5,000 2,950,000,000
4 Perijinan dan Koordinasi Daerah 590,000 m² 5,000 2,950,000,000
5 Kantor Proyek 50 m² 1,500,000 75,000,000
6 Batu Boulder dan Pemasangan 2,389,500 m³ 120,000 286,740,000,000
7 Geotextile dan Pemasangan 590,000 m² 18,000 10,620,000,000
8 Pemasasngan Pagar Precast 2.4 m 3,717,000 m³ 75,000 278,775,000,000
9 Administrasi Proyek 3,717,000 m³ 1,500 5,575,500,000
Sub-Total 599,485,500,000

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
RENCANA ANGGARAN BIAYA BLOK PELABUHAN (85.4 Ha)

No. URAIAN SATTUAN HARGA @ TOTAL


C. INFRASTRUKTUR
1 Pembuatab Jalan Primer 32m ROW 07 km 55,280,000,000 38,696,000,000
2 Pembuatan Jalan Sekunder 24m ROW 1.2 km 41,460,000,000 49,752,000,000
3 Saluran Air Terbuka Heavy Duty Uditch 3.8 km 525,000,000 6,360,288,000
(80x100x120)
4 Listrik PLN Kap. 100 MVa 590,000 m² 18,250 10,767,500,000
5 Air Bersih Kap. 1.000 Lt/Detik 590,000 m² 15,000 8,850,000,000
6 Komunikasi Telepon/Internet 5G 10 sst 1,500,000 15,000,000
7 Kantor 432 m² 3,500,000 1,512,000,000
7 Fire Hydrant 3,800 m¹ 350,000 1,330,000,000
8 Pemasasngan Pagar Precast 2.4 m 1,5 km 868,750,000 1,303,125,000
Sub-Total 118,585,913,000

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
RENCANA ANGGARAN BIAYA BLOK PELABUHAN (85.4 Ha)
No. URAIAN SATTUAN HARGA @ TOTAL
D. JETTY
1 Pekerjaan Persiapan 1 ls 712.500.000 712,500,000
2 Pengadaan Tiang Pancang 51,528 m² 3.500.000 180,348,000,000
3 Pemancangan Tiang Tegak 35,400 m¹ 472.000 16,708,800,000
4 Pemancangan Tiang Miring 16,128 m¹ 625.000 10,080,000,000
5 Pengangkutan Tiang Pancang 4,394 bh 75.750 325,270,500
6 Plat Lantai Beton Fc 35 20,000 m³ 5.162.000 103,240,000,000
7 Balok Melintang (80x120) 3,870 Ton 5.675.000 21,962,250,000
8 Balok Memanjang ( 80x120) 2,400 m³ 4.779.000 11,469,600,000
9 Poer Beton Tiang Ganda (300x75x120) 1,058 m³ 4.070.000 6,004,150,000
10 Balok Crane (100x150) 1,500 m³ 4..779.000 7,168,500,000
11 Poer Beton Tiang Ganda (300x75x120) 1,456 m³ 4.070.000 5,925,920,000
12 Beton Isi Tiang 1,708 m³ 2.900.000 4,953,780,000
13 Pengadaan Fender SA-800H 85 bh 2.900.000 246,500,000
14 Pengadaan Boulder BR 150 Kap. 150 Ton 30 bh 65.000.000 1,950,000,000
15 Rel Crane 1,984 m¹ 1.050.000 2,083,200,000
Sub-Total 373,178,470,500

GRAMD TOTAL 1,622,165,283,500

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
RENCANA ANGGARAN BIAYA BLOK PENGOLAHAN LIMBAH (40 Ha)

No. URAIAN SATTUAN HARGA @ TOTAL


A. PENGADAAN LAHAN.
1 Pembebasan Lahan 400,000 m² 400,000 160,000,000,000
2 Legalitas Pembebasan Lahan 400,000 m² 50,000 20,000,000,000
3 Perencanaan, Drawing, Bathimetry, DED 400,000 m² 15,000 600,000,000
4 Koordinasi dan Perijinan 400,000 m² 2,000 1,400,000,000
5 Konsultan Perencana 400,000 m² 3,500 1,600,000,000
6 AMDAL 400,000 m² 4,000 1,600,000,000
7 Pematangan Lahan – Clearing, Cut & Fill 400,000 m² 150,000 53,791,200,000
Sub-Total 243,591,200,000

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
RENCANA ANGGARAN BIAYA BLOK PENGOLAHAN LIMBAH (40 Ha)

No. URAIAN SATTUAN HARGA @ TOTAL


B. INFRASTRUKTUR
1 Pembuatab Jalan Primer 32m ROW 2 km 55,280,000,000 106,137,600,000
2 Pembuatan Jalan Sekunder 24m ROW 3 km 41,460,000,000 82,920,000,000
3 Saluran Air Terbuka Heavy Duty Uditch 8 km 525,000,000 4,200,000,000
(80x100x120)
4 Listrik PLN Kap. 100 MVa 400,000 m² 18,250 7,300,000,000
5 Air Bersih Kap. 1.000 Lt/Detik 400,000 m² 15,000 6,000,000,000
6 Komunikasi Telepon/Internet 5G 10 sst 1,500,000 15,000,000
7 Fire Hydrant 8 km 350,000,000 2,800,000,000
8 Pemasasngan Pagar Precast 2.4 m 5,300 m¹ 525,000 2,782,500,000
Sub-Total 358,422,980,220

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
RENCANA ANGGARAN BIAYA BLOK PENGOLAHAN LIMBAH (40 Ha)

No. URAIAN SATTUAN HARGA @ TOTAL


C. WARE HOUSE DAN OFFICE
1 Warehouse 10,000 m² 4,300,000 43,000,000,000
2 Office 200 m² 4,500,000 900,000,000
3 Laboratorium 150 m² 4,500,000 675,000,000
4 Tempat Ibadah 150 m² 4,500,000 675,000,000
5 Mes Karyawan dan Tamu 500 m² 4,500,000 2,250,000,000
6 Pos Satpam 50 m² 4,000,000 200,000,000
7 Mobil Truck 3 Unit 750,000,000 2,250,000,000
8 Mobil Oprasional 3 unit 550,000,000 1,650,000,000
Sub-Total 51,600,000,000

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
RENCANA ANGGARAN BIAYA BLOK PENGOLAHAN LIMBAH (40 Ha)

No. URAIAN SATTUAN HARGA @ TOTAL


D. MESIN PENGOLAHAN LIMBAH
1 Feedstock Preparation Sytem 1 unit 72,800,000,000 72,800,000,000
2 Oxygen Production System 1 unit 98,250,000,000 98,250,000,000
3 FastOx Gasification System 1 unit 295,400,000,00 295,400,000,000
0
4 Gas Cleaning System 1 unit 69,650,000,000 69,650,000,000
5 Utilities Sub System 1 unit 183,484,000,00 183,484,000,000
0
6 End Product (Elextricity) System 1 unit 126,700,000,00 126,700,000,000
0
Sub-Total 844,284,000,000

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
RENCANA ANGGARAN BIAYA BLOK PENGOLAHAN LIMBAH (40 Ha)

No. URAIAN SATTUAN HARGA @ TOTAL


E. GENERAL ADMINISTRATION & EXPENSES
1 Konsumsi Listrik 1 th 13,510,000,000 13,510,000,000
2 Supply dan Material 1 th 98,250,000,000 7,882,000,000
3 System Maintenance 1 th 295,400,000,00 21,112,000,000
0
4 Labor dan Admistrasi 1 th 69,650,000,000 26,628,000,000
Sub-Total 169,132,000,000

GRAND TOTAL ( A+B+C+E ) 1,420,762,000,000

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
REKAPIPULASI
RAB KAWASAN INDUSTRI TERINTEGRASI REMABANG

No. URAIAN LUAS AREA TOTAL

1 KAWASAN INDUSTRIAL ESTATE 5,600,000 m² 4,471,193,075,000


REMBANG – BLOK TRAHAN
2 KAWASAN INDUSTRIAL ESTATE 2,000,000 m² 1,598,951,437,500
REMBANG – BLOK BLIMBING
3 KAWASAN INDUSTRIAL ESTATE 3,000,000 m² 2,394,648,437,500
REMBANG – BLOK JATISARI
4 KAWASAN INDUSTRIAL ESTATE 854,000 m² 1,622,165,283,500
REMBANG – BLOK PELABUHAN
5 KAWASAN INDUSTRIAL ESTATE 400,000 m² 1,420,762,300,000
REMBANG – BLOK PENGOLAHAN LIMBAH
B3

GRAND TOTAL 11,507,720,533,500


HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
TAHAPAN PEMBANGUAN INFRASTRUKTUR

URAIAN SATUAN TRAHAN BLIMBINGSARI JATISARI PELABUHA PENGOLAHA


N N LIMBAH
(B3)
Lokasi Desa Trahan Ds.Blimbingsari Ds. Jatisari Ds. Sluke Ds. Trahan
Fokus Industri Industri Refenary Oil Pengolahan Export – Padat dan Cair
Baterai, Baja, Ikan, Kaca, Import,
Pupuk, industry Penumpang
Smelter. Textile pendukung

Luas Ha 560 200 277.24 100 40


Pengelola PT. BRMP PT.BRMP PT.BRMP PT.BRMP PT.BRMP

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
TINGKAT KESIAPAN
URAIAN SATUAN TRAHAN BLIMBING JATISARI PELABUHAN PENGOLAHA
N LIMBAH
(B3)
RTRW ceklist
RDTR ceklist
Master Plan ceklist
Studi Kelayakan ceklist
Renstra ceklist
DED ceklist
AMDAL ceklist

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
PEKERJAAN FISIK
URAIAN SATUAN TRAHAN BLIMBINGSARI JATISARI PELABUHAN PENGOLAHAN
LIMBAH (B3)
Pembebasan Lahan Ha
Pematangan Lahan Ha 560 200 277.24 100 40
Jalan Poros dan Ha 56 20 27 10 4
Lingkungan
WWTP Ha 10
WTP- 1000 Ltr/detik Unit 1
SALURAN UDITCH Km 31 11 15 5 2
LISTRIK MW 2.600
INTERNET/TELEPON 50 Mbps
PEMAGARAN Km 14 6.3 7.5 3
Timbunan Pelabuhan M³ 3.000.000 1.200.000
Penghijauan/Taman Ha 56 20 27 10 4

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
PEKERJAAN FISIK

URAIAN SATUA TRAHAN BLIMBINGSA JATISARI PELABUHAN PENGOLAH


N RI AN LIMBAH
(B3)
GEDUNG unit 1
PENGELOLA
GUDANG LOGISTIK unit 1 1 1 1 1
BALAI LATIHAN unit 1
KERJA
KLINIK/RS unit 1
RUSUNAWA unit 4 3 2
POLITEHNIK unit 1
TEMPAT IBADAH unit 1 1 1
PEMADAM unit 1 1 1
KEBAKARAN

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
TAHAPAN WAKTU PENGEMBANGAN
TAHUN 1 TAHUN 2 TAHUN 3 TAHUN 4
AKTIVITAS Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Survey Lokasi
Pengajuan Ijin Prinsip
Pembebasan Lahan
FS, Master Plan, RESTRA
Penyusunan AMDAL
Pengajuan Injin Lokasi dan
Lingkungan
Penyusunan DED
Pembangunan Infrastruktur
Pemasaran
Kawasan Beroperasi

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA
THANK YOU

HEAD OFFICE: JL. PEMUDA NO.80. REMBANG , JAWA -TENGAH BANCH OFFICE: JL. PURWOSARI II NO. 33, KEL. BUGEL, KEC. SIDOREJO, KOTA SALATIGA

Anda mungkin juga menyukai