Anda di halaman 1dari 203

DINAS PEKERJAAN UMUM DAN TATA RUANG PROV.

SULAWESI SELATAN
Jl. A. P. PETTARANI NO.90, MASALE, PANAKKUKANG, KOTA MAKASSAR, SUL-SEL 90222

PEKERJAAN : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba


NOMOR KONTRAK : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
TANGGAL KONTRAK : 16 Oktober 2020
KONTRAKTOR PELAKSANA : CV. KARYA WAFIQ GLOBAL
KONSULTAN PENGAWAS : CV.MULTILINE TATARANCANA

BACK UP DATA

A. PEMBANGUNAN RUANG KULINER, SUVENIR, MUSHOLLAH DAN MENARA RESERVOIR

JENIS PEKERJAAN : 2. PEKERJAAN STRUKTUR


ITEM PEKERJAAN : Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4, Entrance)

Panjang Lebar Tinggi Volume


No. Uraian Pekerjaan Section Unit Volume Sat
(m) (m) (m) MC 0%
a b c d e f h j k l
Pekerjaan Rangka Atap Bitumen Gelombang (Kuda -
2.3
Kuda Baja Ringan) 14.50 5.27 2.00 152.83

JUMLAH TOTAL 152.83 152.03 m3

Disetujui Oleh, Diajukan Oleh,


Pejabat Pelaksana Teknis Kegiatan Kontraktor Pelaksana
Dinas PUPR Prov SulSel CV. KARYA WAFIQ GLOBAL

L I L I, ST. VIKA APRILIA DWI PUTRI


Nip. 19821229 201503 2 001 Direktris
LAPORAN KEMAJUAN MINGGUAN

Kegiatan : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba Minggu Ke : 01 (Satu)
Satuan Kerja : Dinas Pekerjaan Umum Dan Tata Ruang Prov. Sulawesi Selatan Bidang Cipta Karya Periode : 16 Oktober S/d 22 Oktober 2020
Lokasi : Desa Ara, Kecamatan Bonto Bahari, Kabupaten Bulukumba, Provinsi Sulawesi Selatan No. Kontrak : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
Sumber Dana : Dana Bantuan Provinsi Nilai Kontrak : Rp. 1,088,939,358.00
Tahun Anggaran : 2020 Schedule Pelaksanaan : 16 Oktober S/d 14 Desember 2020

MINGGU LALU MINGGU INI S/D MINGGU INI


VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
NO URAIAN PEKERJAAN
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q

A. PEMBANGUNAN RUANG KULINER, SUVENIR, MUSHOLLAH DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Papan Proyek Ls 1.00 500,000.00 500,000.00 0.05 - - - - - - -
1.2 Bedeng/Direksi Keet M2 5.50 1,512,555.00 8,319,052.50 0.84 - - - - - - -

TOTAL PEKERJAAN PERSIAPAN 8,819,052.50 0.89 0.00 0.00 0.00

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Poerplat PP1 (Selasar Samping)
2.1.1.1 Galian Pondasi Poerplat < 1 m M3 0.32 73,837.50 23,628.00 0.00 - - - - - - -
2.1.1.2 Urugan Pasir dibawah Pondasi Poerplat T.5 cm M3 0.04 148,335.00 5,933.40 0.00 - - - - - - -
2.1.1.3 Urugan Tanah Kembali Pondasi Poerplat M3 0.31 54,175.00 16,794.25 0.00 - - - - - - -
2.1.1.4 Pasangan Lantai Kerja bawah Pondasi Poerplat T.5 cm (Beton K300) M3 0.04 1,118,216.00 44,728.64 0.00 - - - - - - -
2.1.1.5 Pondasi Poerplat 35x50 cm, T.20 cm - -
Beton Mutu F'c = 26,4 mpa (K300), Slump (12-2) cm, w/c = 0,52 M3 0.14 1,118,216.00 156,550.24 0.02 - - - - - - -
Bekisting 2x Pakai M2 0.56 107,013.50 59,927.56 0.01 - - - - - - -
Besi Beton Ø14 SNI Kg 29.40 21,464.85 631,066.59 0.06 - - - - - - -
2.1.2 Pekerjaan Pondasi Batu Kali (Badan Bangunan, Mushollah) - -
2.1.2.1 Galian Tanah Pondasi Batu Kali < 1 m M3 22.73 73,837.50 1,678,326.38 0.17 - - - - - - -
2.1.2.2 Urugan Pasir dibawah Pondasi Batu Kali T.5 cm M3 1.08 148,335.00 160,201.80 0.02 - - - - - - -
2.1.2.3 Pasangan Aanstamping bawah Pondasi Batu Kali T.10 M3 2.17 382,674.00 830,402.58 0.08 - - - - - - -
2.1.2.4 Urugan Tanah Kembali Pondasi Batu Kali M3 10.39 54,175.00 562,878.25 0.06 - - - - - - -
2.1.2.5 Pondasi Batu Kali 1 Sp : 3 Pp M3 9.09 827,447.50 7,521,497.78 0.76 - - - - - - -
2.1.3 Pekerjaan Pondasi Rollage L.15 cm (Entrance, Selasar Samping)
2.1.3.1 Galian Tanah Pondasi Rollage < 1 m M3 2.23 73,837.50 164,657.63 0.02 - - - - - - -
2.1.3.2 Urugan Pasir dibawah Pondasi Rollage T.5 cm M3 0.45 148,335.00 66,750.75 0.01 - - - - - - -
2.1.3.3 Pasangan Lantai Kerja bawah Pondasi Rollage T.5 cm (Beton K300) M3 0.45 1,118,216.00 499,003.89 0.05 - - - - - - -
2.1.3.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp M2 20.83 128,436.00 2,675,321.88 0.27 - - - - - - -
2.2 Pekerjaan Sloef, Kolom dan Ringbalk - -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Mushollah) - -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 1.62 1,118,216.00 1,815,703.23 0.18 - - - - - - -
2.2.1.2 Bekisting 2x Pakai M2 10.83 114,438.50 1,239,368.96 0.13 - - - - - - -
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI Kg 280.09 21,464.85 6,012,089.84 0.61 - - - - - - -
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan, Mushollah) - -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.88 1,118,216.00 981,234.54 0.10 - - - - - - -
2.2.2.2 Bekisting 2x Pakai M2 5.85 193,468.00 1,131,787.80 0.11 - - - - - - -
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 181.66 21,464.85 3,899,347.58 0.39 - - - - - - -
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Selasar, Westafel, Tempat Wudhu)
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 - - - - - - -
2.2.3.2 Bekisting 2x Pakai M2 2.26 193,468.00 437,237.68 0.04 - - - - - - -
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 70.10 21,464.85 1,504,686.30 0.15 - - - - - - -
2.2.4 Pekerjaan Kolom K1 15 x 30 (Selasar Samping)
2.2.4.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.62 1,118,216.00 694,412.14 0.07 - - - - - - -
2.2.4.2 Bekisting 2x Pakai M2 6.21 193,468.00 1,201,436.28 0.12 - - - - - - -
2.2.4.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 99.69 21,464.85 2,139,830.90 0.22 - - - - - - -
2.2.5 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan, Mushollah)
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 2.08 1,008,161.00 2,097,478.96 0.21 - - - - - - -
2.2.5.2 Bekisting 2x Pakai M2 13.87 197,923.00 2,745,192.01 0.28 - - - - - - -
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 299.22 21,464.85 6,422,712.42 0.65 - - - - - - -
2.2.6 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan)
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 - - - - - - -
2.2.6.2 Bekisting 2x Pakai M2 2.24 197,923.00 443,347.52 0.04 - - - - - - -
2.2.6.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 48.32 21,464.85 1,037,181.55 0.10 - - - - - - -
2.2.7 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Mushollah, Pintu Jendela)
2.2.7.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.84 1,008,161.00 846,855.24 0.09 - - - - - - -
2.2.7.2 Bekisting 2x Pakai M2 5.59 197,923.00 1,106,389.57 0.11 - - - - - - -
2.2.7.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 115.53 21,464.85 2,479,834.12 0.25 - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.2.8 Pekerjaan Plat Beton (Selasar Samping, Westafel)
2.2.8.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.22 1,008,161.00 221,795.42 0.02 - - - - - - -
2.2.8.2 Bekisting 2x Pakai M2 2.21 237,468.00 524,804.28 0.05 - - - - - - -
2.2.8.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 54.54 21,464.85 1,170,692.92 0.12 - - - - - - -
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) M2 152.03 163,636.00 24,877,581.08 2.51 - - - - - - -
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4, Entrance) M2 42.24 242,170.50 10,229,281.92 1.03 - - - - - - -
2.5 Pekerjaan Tiang Atap Bitumen Gelombang (Besi Hollow Galvanis 5/10, Entrance) M' 20.40 178,365.00 3,638,646.00 0.37 - - - - - - -
2.6 Pekerjaan Rangka Plafond Kalsiboard (Besi Hollow Metal Galvalume 4/4) M2 147.40 102,837.17 15,158,198.37 1.53 - - - - - - -

TOTAL PEKERJAAN STRUKTUR 109,840,345.70 11.10 0.00 0.00 0.00

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) M3 8.54 148,335.00 1,266,780.90 0.13 - - - - - - -
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) M3 25.63 167,227.00 4,285,636.74 0.43 - - - - - - -
3.1.1.3 Rabat Beton bawah Lantai T.5 cm (Keseluruhan, Beton K300) M3 8.54 1,118,216.00 9,549,564.64 0.96 - - - - - - -
3.1.1.4 Penutup Lantai Keramik Motif 60x60 (Badan Bangunan, Mushollah) M2 62.94 403,309.50 25,384,299.93 2.56 - - - - - - -
3.1.1.5 Penutup Lantai Conwood Deck 6" (Entrance) M2 59.01 866,833.08 51,151,820.09 5.17 - - - - - - -
3.1.1.6 Penutup Lantai Andesit Polos 30x30 (Selasar, Tempat Wudhu, Ram) M2 51.05 232,589.50 11,873,693.98 1.20 - - - - - - -
3.1.1.7 Plint Lantai Keramik 10x60 (Badan Bangunan, Mushollah) M' 38.85 51,605.03 2,004,855.55 0.20 - - - - - - -
3.1.2 Pekerjaan Dinding
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Mushollah, 1 Sp : 4 Pp) M2 74.55 242,979.00 18,114,084.45 1.83 - - - - - - -
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Selasar Samping, Tempat Wudhu) M2 5.14 65,550.32 336,928.64 0.03 - - - - - - -
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm (Badan Bangunan, Mushollah) M2 91.30 60,403.20 5,514,812.16 0.56 - - - - - - -
3.1.2.4 Plesteran Ciprat 1 Sp : 2 Pp Tebal 15 mm (Selasar Samping, Antar Kolom) M2 24.84 49,215.10 1,222,503.08 0.12 - - - - - - -
3.1.2.5 Dinding Keramik Mozaik 30x60 (Selasar Samping, Westafel, Tempat Wudhu) M2 18.44 410,432.00 7,568,366.08 0.76 - - - - - - -
3.1.2.6 Coating Bening (Badan Bangunan, Mushollah, Kolom Luar) M2 127.49 45,973.13 5,861,113.71 0.59 - - - - - - -
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) M2 8.64 995,043.50 8,597,175.84 0.87 - - - - - - -
3.1.2.8 Dinding Wallpaper Bata L.50 cm (Sisi Dalam) M2 28.13 80,005.50 2,250,554.72 0.23 - - - - - - -
3.1.3 Pekerjaan Plafond
3.1.3.1 Plafond Kalsiboard (Badan Bangunan, Kemiringan Atap, Mushollah) M2 147.40 44,924.00 6,621,797.60 0.67 - - - - - - -
3.1.3.2 Plafond Kalsiboard (Lapis Bawah Atap, Entrance) M2 42.24 44,924.00 1,897,589.76 0.19 - - - - - - -
3.2 Pekerjaan Pintu dan Jendela (Badan Bangunan)
3.2.1 Pintu P1 (Entrance dan Back Entrance, Badan Bangunan)
3.2.1.1 Pasangan Kusen Alumunium Coating P1 (4" x 1 3/4") cm M' 22.40 157,194.40 3,521,154.56 0.36 - - - - - - -
3.2.1.2 Pasangan Daun Pintu P1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - -
3.2.1.3 Pasangan Kaca Mati 5 mm P1 M2 11.20 145,703.80 1,631,882.56 0.16 - - - - - - -
3.2.1.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - -
3.2.1.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - -
3.2.1.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - -
3.2.1.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - -
3.2.2 Jendela J1 (Badan Bangunan)
3.2.2.1 Pasangan Kusen Alumunium Coating J1 (4" x 1 3/4") cm M' 40.60 157,194.40 6,382,092.64 0.64 - - - - - - -
3.2.2.2 Pasangan Kaca Mati 5 mm J1 M2 8.00 145,703.80 1,165,630.40 0.12 - - - - - - -
3.2.3 Pintu PJ1 (Mushollah)
3.2.3.1 Pasangan Kusen Alumunium Coating PJ1 (4" x 1 3/4") cm M' 22.20 157,194.40 3,489,715.68 0.35 - - - - - - -
3.2.3.2 Pasangan Daun Pintu PJ1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - -
3.2.3.3 Pasangan Kaca Mati 5 mm P1 M2 8.70 145,703.80 1,267,623.06 0.13 - - - - - - -
3.2.3.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - -
3.2.3.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - -
3.2.3.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - -
3.2.3.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - -
3.3 Pekerjaan Pengecatan
3.3.1 Pengecatan Plafond (1 Plamir ; 1 Cat Dasar : 2 Cat Penutup), (Interior) M2 189.64 35,536.05 6,739,056.52 0.68 - - - - - - -
3.3.2 Pengecatan Rangka Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 23.76 168,454.00 4,002,467.04 0.40 - - - - - - -
3.3.3 Pengecatan Tiang Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 6.12 168,454.00 1,030,938.48 0.10 - - - - - - -
3.4 Pekerjaan Atap
3.4.1 Atap Bitumen Gelombang (Badan Bangunan, Mushollah) M2 152.03 207,297.09 31,515,376.59 3.18 - - - - - - -
3.4.2 Atap Bitumen Gelombang (Entrance) M2 42.24 207,297.09 8,756,229.08 0.88 - - - - - - -
3.4.3 Nok Bitumen (Badan Bangunan, Mushollah) M' 14.55 134,101.00 1,951,169.55 0.20 - - - - - - -
3.4.4 Listplank (Kalsiplank, Badan Bangunan, Mushollah, Entrance) M' 50.00 70,950.00 3,547,500.00 0.36 - - - - - - -

TOTAL PEKERJAAN FINISHING ARSITEKTUR 257,222,142.77 25.98 0.00 0.00 0.00

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel Bh 1.00 1,572,826.75 1,572,826.75 0.16 - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt Bh 16.00 353,938.75 5,663,020.00 0.57 - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4.1.3 Pasangan Lampu Down Light 2,5" Outbow LED 5,5 Watt Bh 11.00 305,538.75 3,360,926.25 0.34 - - - - - - -
4.1.4 Pasangan Saklar Tunggal Bh 4.00 211,378.75 845,515.00 0.09 - - - - - - -
4.1.5 Pasangan Saklar Ganda Bh 2.00 223,478.75 446,957.50 0.05 - - - - - - -
4.2 Pasangan Instalasi Stop Kontak - -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA Bh 10.00 216,218.75 2,162,187.50 0.22 - - - - - - -
4.2.2 Pasangan Stop Kontak AC 220 VA/3520 W (AC Split 1 PK) Bh 4.00 253,728.75 1,014,915.00 0.10 - - - - - - -
4.3 Pasangan Instalasi Jaringan AC M' 30.00 108,772.68 3,263,180.25 0.33 - - - - - - -
4.3.1 Pasangan AC Split 1 PK Bh 3.00 3,365,799.34 10,097,398.03 1.02 - - - - - - -
4.4 Pasangan Penangkal Petir Ls 1.00 2,500,000.00 2,500,000.00 0.25 - - - - - - -
4.5 Pasangan Instalasi Jaringan Kabel Fiber Optic (CCTV) Ttk 6.00 786,326.75 4,717,960.50 0.48 - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2MP Bh 6.00 656,975.00 3,941,850.00 0.40 - - - - - - -
4.5.2 Pasangan NVR Channel Set 1.00 5,023,975.00 5,023,975.00 0.51 - - - - - - -
4.5.3 Pasangan Monitor LCD 32" Bh 1.00 2,944,975.00 2,944,975.00 0.30 - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm M' 12.00 20,442.68 245,312.10 0.02 - - - - - - -
4.6.1 Pasangan Horn Speaker Bh 6.00 494,826.75 2,968,960.50 0.30 - - - - - - -
4.6.2 Pasangan Volume Kontrol Set 1.00 252,826.75 252,826.75 0.03 - - - - - - -
4.6.3 Pasangan Perangkat Sound System Set 1.00 4,565,000.00 4,565,000.00 0.46 - - - - - - -
4.6.4 Pasangan TB-Sound System Set 1.00 5,846,326.75 5,846,326.75 0.59 - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25Kg) Ttk 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - -
4.8 Pasangan Instalasi Jaringan Kabel Fiber Optic (Akses Point) Ttk 3.00 786,326.75 2,358,980.25 0.24 - - - - - - -
4.8.1 Pasangan Server Set 1.00 7,578,826.75 7,578,826.75 0.77 - - - - - - -
4.8.2 Pasangan Akses Point Bh 1.00 2,034,826.75 2,034,826.75 0.21 - - - - - - -
4.8.3 Pasangan Switch HUB Bh 1.00 2,843,326.75 2,843,326.75 0.29 - - - - - - -
4.9 Pasangan Instalasi PLN Power (Inc. Jalur ke Mushollah dan Toilet) Ls 1.00 9,000,000.00 9,000,000.00 0.91 - - - - - - -

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 94,450,073.38 9.54 0.00 0.00 0.00

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVC Type AW Diameter 3/4" (Air Bersih Sambungan dari Tandon) M' 33.00 28,300.25 933,908.25 0.09 - - - - - - -
5.2 Pipa PVC Type AW Diameter 3" (Air Kotor ke Drainase Lingkungan) M' 25.80 135,531.00 3,496,699.80 0.35 - - - - - - -
5.3 Pasangan 1 Bh Wastafel Bh 2.00 3,934,865.00 7,869,730.00 0.79 - - - - - - -
5.4 Pasangan 1 Bh Wastafel Cuci Piring (WCP) Bh 1.00 890,945.00 890,945.00 0.09 - - - - - - -
5.5 Pasangan 1 Bh Floor Drain Bh 2.00 41,112.50 82,225.00 0.01 - - - - - - -
5.6 Pasangan 1 Bh Kran Dia. 1/2" atau 3/4" Bh 10.00 102,217.50 1,022,175.00 0.10 - - - - - - -
5.7 Pasangan 1 Bh Kran Wastafel Dia. 1/2" atau 3/4" Bh 3.00 335,417.50 1,006,252.50 0.10 - - - - - - -
5.8 Pasangan 1 Bh Stop Kran (Gate Valve) Dia. 3/4" Bh 1.00 141,417.50 141,417.50 0.01 - - - - - - -
5.9 Pasangan Mesin Air Bh 1.00 741,000.00 741,000.00 0.07 - - - - - - -
5.10 Menara Reservoir 200x150x350 cm - -
5.10.1 Pekerjaan Pondasi Pedestal Pd1 - -
5.10.1.1 Galian Tanah Pondasi Poerplat < 1 m M3 1.62 73,837.50 119,616.75 0.01 - - - - - - -
5.10.1.2 Urugan Tanah Kembali Pondasi Poerplat M3 0.43 54,175.00 23,295.25 0.00 - - - - - - -
5.10.1.3 Tiang Pondasi Pedestal 50x50 cm - -
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.80 1,118,216.00 894,572.80 0.09 - - - - - - -
Bekisting 2x Pakai M2 3.20 193,468.00 619,097.60 0.06 - - - - - - -
Besi Beton Ø12 SNI, Ø8 SNI Kg 49.44 21,464.85 1,061,130.60 0.11 - - - - - - -
5.10.1.4 Pondasi Poerplat 90x90 cm, T.20 cm
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.65 1,118,216.00 726,840.40 0.07 - - - - - - -
Bekisting 2x Pakai M2 1.44 107,013.50 154,099.44 0.02 - - - - - - -
Besi Beton Ø14 SNI Kg 214.35 21,464.85 4,600,940.54 0.46 - - - - - - -
5.10.2 Rangka Tengah dan Lantai Menara (Besi Hollow Galvanis 4/4) M2 34.82 244,970.00 8,529,855.40 0.86 - - - - - - -
5.10.3 Rangka Utama Menara (Besi Hollow Galvanis 5/10) M' 32.28 179,454.00 5,792,775.12 0.59 - - - - - - -
5.10.4 Plat Baja Lantai Menara T.3 mm M2 3.00 740,164.86 2,220,494.57 0.22 - - - - - - -
5.10.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) M2 5.00 244,970.00 1,224,850.00 0.12 - - - - - - -

TOTAL PEKERJAAN PLAMBING DAN SANITASI 42,151,921.52 4.26 0.00 0.00 0.00

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Pek. Pembersian Awal m2 81.86 17,600.00 1,440,780.00 0.15 - - - - - - -
1.2 Pek. Pengukuran & Pemasangan Bouwplank m1 48.60 106,461.25 5,174,016.75 0.52 - - - - - - -

TOTAL PEKERJAAN PERSIAPAN 6,614,796.75 0.67 0.00 0.00 0.00

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Batu Kali (Badan Bangunan,Ruang Bilas)
2.1.1.1 Galian Pondasi Batu Kali < 1 m m3 22.05 73,892.50 1,629,329.63 0.16 - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.1.1.2 Urugan Pasir Dibawah Pondasi Batu Kali T.5 cm m3 1.05 174,757.00 183,494.85 0.02 - - - - - - -
2.1.1.3 Pasangan Aanstamping Bawah Pondasi Batu Kali T.10 cm m3 2.10 392,699.70 824,669.37 0.08 - - - - - - -
2.1.1.4 Urugan Tanah Kembali Pondasi Batu Kali m3 10.08 54,285.00 547,192.80 0.06 - - - - - - -
2.1.1.5 Pondasi Batu Kali 1 Sp : 3 Pp m3 8.82 824,945.00 7,276,014.90 0.73 - - - - - - -
2.1.2 Pekerjaan Pondasi Rollage L.15 cm (Selasar) - -
2.1.2.1 Galian Tanah Pondasi Rollage < 1 m m3 1.52 73,892.50 112,501.33 0.01 - - - - - - -
2.1.2.2 Urugan Pasir Dibawah Pondasi Rollage T.5 cm m3 0.30 174,757.00 53,213.51 0.01 - - - - - - -
2.1.2.3 Pasangan Lantai Kerja Bawah Pondasi Rollage T.5 cm (Beton K300) m3 0.30 1,118,398.60 340,552.37 0.03 - - - - - - -
2.1.2.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp m2 14.21 128,260.00 1,822,574.60 0.18 - - - - - - -
2.2 Pekerjaan Sloef, Kolom, Plat dan Ringbalk - - - - - - -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Ruang Bilas) - - - - - - -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 m3 1.41 1,118,398.60 1,580,297.22 0.16 - - - - - - -
2.2.1.2 Bekisting 2x Pakai m2 9.42 114,467.10 1,078,280.08 0.11 - - - - - - -
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI kg 243.74 21,465.73 5,232,043.29 0.53 - - - - - - -
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan) - - - - - - -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slum (12 - 2) cm, w/c = 0,52 m3 0.48 1,118,398.60 533,476.13 0.05 - - - - - - -
2.2.2.2 Bekisting 2x Pakai m2 3.18 193,504.30 615,343.67 0.06 - - - - - - -
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI kg 98.75 21,465.73 2,119,732.25 0.21 - - - - - - -
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Ruang Bilas) - -
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.25 1,008,343.60 249,111.29 0.03 - - - - - - -
2.2.3.2 Bekisting 2x Pakai m2 1.65 193,504.30 318,701.58 0.03 - - - - - - -
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI kg 51.14 21,465.73 1,097,861.33 0.11 - - - - - - -
2.2.4 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan) - -
2.2.4.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.04 1,008,343.60 1,043,635.63 0.11 - - - - - - -
2.2.4.2 Bekisting 2x Pakai m2 6.90 197,959.30 1,365,919.17 0.14 - - - - - - -
2.2.4.3 Besi Beton Ø12 SNI, Ø6 SNI kg 148.86 21,465.73 3,195,302.68 0.32 - - - - - - -
2.2.5 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan) - - - - - - -
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.09 1,008,343.60 1,103,531.24 0.11 - - - - - - -
2.2.5.2 Bekisting 2x Pakai m2 14.59 197,959.30 2,888,622.11 0.29 - - - - - - -
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI kg 157.40 21,465.73 3,378,705.12 0.34 - - - - - - -
2.2.6 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Pintu Jendela)
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.15 1,008,343.60 148,831.52 0.02 - - - - - - -
2.2.6.2 Bekisting 2x Pakai m2 0.98 197,959.30 194,791.95 0.02 - - - - - - -
2.2.6.3 Besi Beton Ø10 SNI, Ø6 SNI kg 20.35 21,465.73 436,752.39 0.04 - - - - - - -
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) m2 59.01 163,856.00 9,669,142.56 0.98 - - - - - - -
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4) m2 48.59 102,876.77 4,998,782.09 0.50 - - - - - - -
2.5 Pekerjaan Rangka Plafond dan Dinding Dalam PVC Shunda (Besi Hollow Metal Galvalume 4/4) m2 56.16 102,876.77 5,777,559.22 0.58 - - - - - - -

TOTAL PEKERJAAN STRUKTUR 59,815,965.86 6.04 0.00 0.00 0.00

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) m3 4.09 174,757.00 715,280.40 0.07 - - - - - - -
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) m3 12.28 167,345.00 2,054,804.70 0.21 - - - - - - -
3.1.1.3 Rabat Beton T.5 cm (Keseluruhan, Beton K300) m3 4.09 1,118,398.60 4,577,605.47 0.46 - - - - - - -
3.1.1.4 Penutup Lantai Keramik Tekstur 60x60 (Badan Bangunan) m2 36.93 413,098.40 15,255,723.91 1.54 - - - - - - -
3.1.1.5 Penutup Lantai Andesit Polos 30x30 (Selasar, Ruang Bilas) m2 45.89 284,369.80 13,049,730.12 1.32 - - - - - - -
3.1.1.6 Penutup Plat Wastafel (Granit 60x60, Toilet Pria dan Wanita) m2 2.20 841,621.73 1,851,567.81 0.19 - - - - - - -
3.1.2 Pekerjaan Dinding - -
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Selasar, 1 Sp : 4 Pp) 90.64 242,533.50 21,983,236.44 2.22 - - - - - - -
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Wc ) 30.00 65,473.32 1,964,199.60 0.20 - - - - - - -
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm 121.28 60,304.20 7,313,693.38 0.74 - - - - - - -
3.1.2.4 Coating Bening 121.28 46,853.13 5,682,347.00 0.57 - - - - - - -
3.1.2.5 Dinding Andesit Polos 30x30 cm ( Wc, Ruang Bilas ) 56.52 284,369.80 16,072,581.10 1.62 - - - - - - -
3.1.2.6 Dinding Keramik 30x60 cm ( Sisi Dalam ) 69.88 370,557.00 25,894,523.16 2.62 - - - - - - -
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) 9.00 995,076.50 8,955,688.50 0.90 - - - - - - -
3.1.2.8 Cubicle Panel + Accessories (Pintu Wc dan Partisi Urinoir) 10.86 1,360,000.00 14,769,600.00 1.49 - - - - - - -
3.1.2.9 Dinding Bitumen Gelombang 48.59 201,749.24 9,802,995.57 0.99 - - - - - - -
3.1.2.10 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Pria) 1.00 1,200,000.00 1,200,000.00 0.12 - - - - - - -
3.1.2.11 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Wanita) 1.00 750,000.00 750,000.00 0.08 - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.1.3 Plafond dan Dinding Dalam Shunda ( Badan Bangunan ) 56.16 125,878.50 7,069,336.56 0.71 - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.2 Pekerjaan Pintu dan Jendela ( Badan Bangunan ) - -
3.2.1 Pintu P1 - -
3.2.1.1 Pasangan Kusen Almunium Coating P1 (4" x 13/4") cm 10.96 157,199.02 1,722,901.26 0.17 - - - - - - -
3.2.1.2 Pasangan Daun Pintu P1 (Panel Almunium Coating - Coating) 4.30 870,323.19 3,742,389.72 0.38 - - - - - - -
3.2.1.3 Pasangan Kunci Tanam 2x Slag P1 2.00 416,663.50 833,327.00 0.08 - - - - - - -
3.2.1.4 Pasangan ensel P1 6.00 61,225.56 367,353.36 0.04 - - - - - - -
3.2.1.5 Pasangan Doorcloser P1 2.00 241,902.10 483,804.20 0.05 - - - - - - -
3.2.1.6 Pasangan Handle P1 2.00 229,802.10 459,604.20 0.05 - - - - - - -
3.2.2 Jendela J1 - - - - - - -
3.2.2.1 Pasangan Kusen Almunium Coating J1 (4" x 13/4") cm 28.80 157,199.02 4,527,331.78 0.46 - - - - - - -
3.2.2.2 Pasangan Kaca Mati 5 mm J1 0.60 145,705.56 87,423.34 0.01 - - - - - - -
3.2.3 Jendela J2 - - - - - - -
3.2.3.1 Pasangan Kusen Almunium Coating J2 (4" x 13/4") cm 55.20 157,199.02 8,677,385.90 0.88 - - - - - - -
3.2.3.2 Pasangan Kaca Mati 5 mm J2 0.90 145,705.56 131,135.00 0.01 - - - - - - -
3.3. Pengecetan Plafond (1 Plamir : 1 Cat Dasar : 2 Cat Penutup), (Interior) 56.16 43,550.65 2,445,804.50 0.25 - - - - - - -
3.4 Pekerjaan Atap - -
3.4.1 Atap Bitumen Gelombang (Badan Bangunan) 59.01 201,749.24 11,905,222.65 1.20 - - - - - - -
3.4.2 Nok Bitumen (Badan Bangunan) 35.25 143,629.20 5,062,929.30 0.51 - - - - - - -
3.4.3 Listplank (Kasiplank, Badan Bangunan, Enterance) 39.08 70,972.00 2,773,585.76 0.28 - - - - - - -

TOTAL PEKERJAAN FINISHING ARSITEKTUR 202,183,111.69 20.42 0.00 0.00 0.00

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel 1.00 1,803,826.75 1,803,826.75 0.18 - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt 10.00 353,938.75 3,539,387.50 0.36 - - - - - - -
4.1.3 Pasangan Lampu Down Light 2.5" Outbow LED 5.5 Watt 12.00 305,538.75 3,666,465.00 0.37 - - - - - - -
4.1.4 Pasangan Saklar Ganda 5.00 223,478.75 1,117,393.75 0.11 - - - - - - -
4.2 Pasangan Instalasi Stop Kontak - -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA 3.00 216,218.75 648,656.25 0.07 - - - - - - -
4.2.2 Pasangan Stop Kontak Wall Exhauser 6.00 216,218.75 1,297,312.50 0.13 - - - - - - -
4.3 Pasangan Instalasi Jaringan Wall Exhauser 12.00 108,772.68 1,305,272.10 0.13 - - - - - - -
4.3.1 Pasangan Wall Exhauser 12 Inch - FV30RUN 6.00 513,500.00 3,081,000.00 0.31 - - - - - - -
4.4 Pasangan Penangkal Petir 1.00 3,500,000.00 3,500,000.00 0.35 - - - - - - -
4.5 Pasangan Instlasi Jaringan Kabel Fiber Optic (CCTV) 3.00 786,326.75 2,358,980.25 0.24 - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2 MP (Luar Bangunan, Sambungan Dari Mini Resto) 3.00 656,975.00 1,970,925.00 0.20 - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm 4.00 20,442.68 81,770.70 0.01 - - - - - - -
4.6.1 Pasangan Horn Speaker (Sambungan Dari Mini Resto) 2.00 494,826.75 989,653.50 0.10 - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25 kg) 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - -
4.8 Pasangan Instalasi PLN Power 1.00 10,000,000.00 10,000,000.00 1.01 - - - - - - -

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 44,560,643.30 4.50 0.00 0.00 0.00

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVc Tipe AW Diameter 3/4" (Air Bersih Dari Sumur Bor / PDAM Reservoir) m1 18.50 28,304.65 523,636.03 0.05 - - - - - - -
5.2 Pipa PVC Tipe AW Diameter 3/4" (Distribusi Air Bersih Dari Reservoir) m1 26.50 28,304.65 750,073.23 0.08 - - - - - - -
5.3 Pipa PVC Tipe AW Diameter 3" (Air Kotor Ke Drainase Lingkungan) m1 23.00 135,539.80 3,117,415.40 0.31 - - - - - - -
5.4 Pipa PVC Tipe AW Diameter 4" (Disposal) m1 18.00 186,689.80 3,360,416.40 0.34 - - - - - - -
5.5 Pasangan 1 bh Closet Duduk / Monoblock (TOTO) bh 6.00 3,655,597.00 21,933,582.00 2.22 - - - - - - -
5.6 Pasangan 1 bh Wastafel (TOTO) 3.00 3,571,942.00 10,715,826.00 1.08 - - - - - - -
5.7 Pasangan 1 bh Uninoir (TOTO) 2.00 6,665,285.00 13,330,570.00 1.35 - - - - - - -
5.8 Pasangan 1 bh Floor Drain 9.00 41,123.50 370,111.50 0.04 - - - - - - -
5.9 Pasangan 1 bh Kran dia. 1/2' atau 3/4" 8.00 102,228.50 817,828.00 0.08 - - - - - - -
5.10 Pasangan 1 bh Kran wastafel dia. 1/2' atau 3/4" 2.00 335,428.50 670,857.00 0.07 - - - - - - -
5.11 Pasangan 1 bh shower closet dia. 1/2' atau 3/4" 6.00 142,928.50 857,571.00 0.09 - - - - - - -
5.12 Pasangan 1 bh shower Wall dia. 1/2' atau 3/4" (Ruang Bilas) 4.00 1,435,428.50 5,741,714.00 0.58 - - - - - - -
5.13 Pasangan 1 bh Stop Kran (Gate Valve) dia. 3/4" 2.00 141,428.50 282,857.00 0.03 - - - - - - -
5.14 Pasangan Mesin Air 1.00 741,000.00 741,000.00 0.07 - - - - - - -
5.14b Pasangan Mesin Pemanas Air 1.00 5,000,000.00 5,000,000.00 0.51 - - - - - - -
5.15 Septictank Biotank Kap. 4m3 1.00 20,380,000.00 20,380,000.00 2.06 - - - - - - -
5.16 Pasangan Sumur Bor Jet Pump 30.00 350,000.00 10,500,000.00 1.06 - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.17 Reservoir 1200 Liter 1.00 1,850,000.00 1,850,000.00 0.19 - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.18 Reservoir 200x150x350 cm - -
5.18.1 Pekerjaan Pondasi Pedestal Pd1 - -
5.18.1.1 Galian Tanah Pondasi Poerplat < 1m 1.62 74,250.00 120,285.00 0.01 - - - - - - -
5.18.1.2 Urugan Tanah Kembali Pondasi Poerplat 0.43 55,000.00 23,760.00 0.00 - - - - - - -
5.18.1.3 Tiang Pondasi Pedestal 50x50 cm - - - - - - -
Beton Mutu fc = 26,6 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.80 1,485,144.21 1,188,115.37 0.12 - - - - - - -
Bekisting 2x Pakai 3.20 193,504.30 619,213.76 0.06 - - - - - - -
Besi Beton Ø12, Ø8 49.44 21,465.73 1,061,174.10 0.11 - - - - - - -
5.18.1.4 Pondasi Poerplat 90x90 cm,T.20 cm - -
Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.65 1,485,144.21 962,373.45 0.10 - - - - - - -
Bekisting 2x Pakai 1.44 124,547.50 179,348.40 0.02 - - - - - - -
Besi Beton Ø14 SNI 214.35 21,465.73 4,601,114.73 0.46 - - - - - - -
5.18.2 Rangkai Tengah Dan Lantai Menara (Besi Hollow Galvanis 4/4) 34.82 244,970.00 8,529,855.40 0.86 - - - - - - -
5.18.3 Rangka Utama menara ( Besi Hollow Galvanis 5/10 32.28 179,454.00 5,792,775.12 0.59 - - - - - - -
5.18.4 Tplat Baja Lantai Menara T.3mm 3.00 740,164.86 2,220,494.57 0.22 - - - - - - -
5.18.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) 5.00 244,970.00 1,224,850.00 0.12 - - - - - - -

TOTAL PEKERJAAN PLAMBING DAN SANITASI 127,466,817.45 12.88 - - -

6. PEKERJAAN AKHIR - - -
6.1 Pembersihan Sisa Pekerjaan Ls 1.00 2,400,000.00 2,400,000.00 0.24 - - - - - - -

TOTAL PEKERJAAN AKHIR 2,400,000.00 0.24 0.00 0.00 0.00

C. PENERAPAN SMKK

1. PENYIAPAN RKK
1.1 Pembuatan Dokumen Rencana Keselamatan Konstruksi
1.2 Pembuatan Prosedur dan instruksi kerja Set 1.00 2,000,000.00 2,000,000.00 0.20 - - - - - - -
1.3 Penyiapan formulir
TOTAL PENYIAPAN RKK 2,000,000.00 0.20 - - -
2. SOSIALISASI, PROMOSI DAN PELATIHAN
2.1 Induksi K3 (Safety Induction) Org 5.00 7,500.00 37,500.00 0.00 - - - - - - -
2.2 Pengarahan K3 (Safety Briefing) Org 5.00 15,000.00 75,000.00 0.01 - - - - - - -
2.3 Pelatihan K3 - -
2.3.1 Bekerja di ketinggian Org 4.00 7,500.00 30,000.00 0.00 - - - - - - -
2.3.2 Penggunaan Bahan Kimia (MSDS) Org 2.00 7,500.00 15,000.00 0.00 - - - - - - -
2.4 Simulasi K3 Org 5.00 7,500.00 37,500.00 0.00 - - - - - - -
2.5 Spanduk (Banner) Lb 1.00 150,000.00 150,000.00 0.02 - - - - - - -
2.6 Poster 2 2.00 50,000.00 100,000.00 0.01 - - - - - - -
2.7 Papan Informasi K3 1 1.00 500,000.00 500,000.00 0.05 - - - - - - -
TOTAL SOSIALISASI, PROMOSI DAN PELATIHAN 945,000.00 0.10 - - -
3. ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI
3.1 APK
3.1.1 Tali Keselamatan (Life Line) Ls 1.00 1,700,000.00 1,700,000.00 0.17 - - - - - - -
3.1.2 Pembatas Area (Restricted Area) Ls 1.00 2,000,000.00 2,000,000.00 0.20 - - - - - - -
3.2 APD
3.2.1 Topi Pelindung (Safety Helmet) Bh 10.00 75,000.00 750,000.00 0.08 - - - - - - -
3.2.2 Pelindung Mata (Googles, Spectacles) Bh 5.00 25,000.00 125,000.00 0.01 - - - - - - -
3.2.3 Pelindung Pernapasan dan Mulut (Masker) Bh 100.00 5,000.00 500,000.00 0.05 - - - - - - -
3.2.4 Sarung Tangan (Safety Gloves) Psg 10.00 15,000.00 150,000.00 0.02 - - - - - - -
3.2.5 Sepatu Keselamatan (Safety Shoes) Psg 10.00 350,000.00 3,500,000.00 0.35 - - - - - - -
3.2.6 Penunjang Seluruh Tubuh (Full Body Harness) Bh 2.00 500,000.00 1,000,000.00 0.10 - - - - - - -
3.2.7 Rompi Keselamatan (Safety Vest) Bh 10.00 25,000.00 250,000.00 0.03 - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 9,975,000.00 1.01 - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4. ASURANSI DAN PERIZINAN
4.1 Asuransi Ls 1.00 3,000,000.00 3,000,000.00 0.30 - - - - - - -
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 3,000,000.00 0.30 - - -
5. PERSONEL K3 KONSTRUKSI
5.1 Ahli K3 Konstruksi -
5.2 Petugas K3 Konstruksi Ob 4.00 3,675,000.00 14,700,000.00 1.48 - - - - - - -
TOTAL PERSONEL K3 KONSTRUKSI 14,700,000.00 1.48 - - -
6. FASILITAS, SARANA DAN PRASARANA KESEHATAN
6.1 Peralatan P3K (Kotak P3K, Tandu, Obat Luka, Perban, dll) Ls 1.00 500,000.00 500,000.00 0.05 - - - - - - -
TOTAL FASILITAS, SARANA DAN PRASARANA KESEHATAN 500,000.00 0.05 - - -
7. RAMBU - RAMBU YANG DIPERLUKAN
7.1 Rambu Petunjuk bh 2.00 75,000.00 150,000.00 0.02 - - - - - - -
7.2 Rambu Larangan bh 2.00 75,000.00 150,000.00 0.02 - - - - - - -
7.3 Rambu Peringatan bh 2.00 100,000.00 200,000.00 0.02 - - - - - - -
7.4 Jalur Evakuasi (Escape Route) Ls 1.00 250,000.00 250,000.00 0.03 - - - - - - -
TOTAL RAMBU - RAMBU YANG DIPERLUKAN 750,000.00 0.08 - - -
8. KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI
8.1 Ahli K3 Konstruksi Oj -
TOTAL KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI
9. LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN
KONSTRUKSI
9.1 Alat Pemadam Api Ringan (APAR) bh 1.00 500,000.00 500,000.00 0.05 - - - - - - -
9.2 Program Inspeksi Ls 1.00 1,500,000.00 1,500,000.00 0.15 - - - - - - -
9.3 Pelaporan dan Penyeledikan Insiden Ls 1.00 500,000.00 500,000.00 0.05 - - - - - - -
9.4 Pembuatan Kartu Identitas Pekerja (KIP) Org 10.00 5,000.00 50,000.00 0.01 - - - - - - -
TOTAL LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN KONSTRUKSI 2,550,000.00 0.26 - - -

A Jumlah Harga Penawaran 989,944,870.91 100.00 - - -


B PPN (10%) 98,994,487.09
C Jumlah (A+B) 1,088,939,358.00
PERSENTASE SAMPAI MINGGU INI -
D Jumlah Dibulatkan 1,088,939,358.00

Bulukumba, 22 Oktober 2020


Disetujui, Diketahui, Diperiksa Oleh, Dibuat Oleh,
Pejabat Pembuat Komitmen Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUTR Prov SulSel Dinas PUTR Prov SulSel CV.MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

A.KHADAFI HARUN, ST.,MT. L I L I, ST. IRHAM HARAHAP, ST. VIKA APRILIA DWI PUTRI
NIP. 19811126 200901 1 008 NIP. 19821229 201503 2 001 Site Engineer Direktris
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN
Jl. A. P. PETTARANI NO.90, MASALE, PANAKKUKANG, KOTA MAKASSAR, SUL-SEL 90222

PEKERJAAN : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba


NOMOR KONTRAK : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
TANGGAL KONTRAK : 16 Oktober 2020
KONTRAKTOR PELAKSANA : CV. KARYA WAFIQ GLOBAL
KONSULTAN PENGAWAS : CV.MULTILINE TATARANCANA

BACK UP DATA

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

JENIS PEKERJAAN : 2. PEKERJAAN STRUKTUR


ITEM PEKERJAAN : Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan)

Panjang Lebar Tinggi Volume


No. Uraian Pekerjaan Section Unit Volume Sat
(m) (m) (m) MC 0%
a b c d e f h j k l
Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Male
2.30
Kuda Baja Ringan) 6.40 2.68 2.00 34.30
Female
4.65 2.68 2.00 24.92

JUMLAH TOTAL 59.23 59.01 m3

GAMBAR KERJA

Tampak Depan
Tampak Belakang SKALA 1 : 100
SKALA 1 : 100

Tampak Samping Kanan


SKALA 1 : 100

Disetujui Oleh, Diperiksa Oleh, Diajukan Oleh,


Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUPR Prov SulSel CV. MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

L I L I, ST. MUHAMMAD AGIL AZHARI VIKA APRILIA DWI PUTRI


Nip. 19821229 201503 2 001 Inspector Direktris
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN
Jl. A. P. PETTARANI NO.90, MASALE, PANAKKUKANG, KOTA MAKASSAR, SUL-SEL 90222

PEKERJAAN : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba


NOMOR KONTRAK : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
TANGGAL KONTRAK : 16 Oktober 2020
KONTRAKTOR PELAKSANA : CV. KARYA WAFIQ GLOBAL
KONSULTAN PENGAWAS : CV.MULTILINE TATARANCANA

BACK UP DATA

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

JENIS PEKERJAAN : 2. PEKERJAAN STRUKTUR


ITEM PEKERJAAN : Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Pintu Jendela)

Lebar Jarak Jumlah 1 Rounded Panjang Besi Jumlah 2 Berat Sat Volume Jumlah VOLUME VOLUME
Uraian Sat
M M Bh Bh M Unit (kg/m) Kg Bh Ø10 Ø6 MC 0%

Besi Beton Ø10 SNI, Ø6 SNI


Male

Tul Pokok (besi Ø 10) 4.00 4.00 4.56 2.00 0.89 32.39 1.00 32.39
Tul Pembagi (besi Ø 6) 4.56 0.15 30.40 31.00 0.60 2.00 0.22 8.26 1.00 8.26

Female

Tul Pokok (besi Ø 10) 4.00 4.00 4.56 2.00 0.89 32.39 1.00 32.39
Tul Pembagi (besi Ø 6) 4.56 0.15 30.40 31.00 0.60 2.00 0.22 8.26 1.00 8.26

JUMLAH 64.77 16.51


Jumlah Besi Beton Ø10 SNI & Ø8 SNI 81.28 20.35 KG

GAMBAR KERJA
5160

1905 1905 1075


675600
1 2 75
1 7 50

-0. 05

TER AS BALOK LT
3 650

± 0.00
950 950

-0. 05

15
-0. 05

TERAS
2 150
2 1 50

15
1 3750

1 3750
1 680

-0. 05
1 000 9 80

-0. 05
5 400

± 0.00

TER AS
-0. 05 ± 0.00

JENIS KOLOM BALOK LT 15x15cm


1 740

TUL. POKOK 4 Ø 10
TUL. SENGKANG Ø 6 - 150
1 275

1 275

TERAS
± 0.00

200 3960 1000

5160
Denah Toilet

Disetujui Oleh, Diperiksa Oleh, Diajukan Oleh,


Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUPR Prov SulSel CV. MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

L I L I, ST. MUHAMMAD AGIL AZHARI VIKA APRILIA DWI PUTRI


Nip. 19821229 201503 2 001 Inspector Direktris
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN
Jl. A. P. PETTARANI NO.90, MASALE, PANAKKUKANG, KOTA MAKASSAR, SUL-SEL 90222

PEKERJAAN : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba


NOMOR KONTRAK : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
TANGGAL KONTRAK : 16 Oktober 2020
KONTRAKTOR PELAKSANA : CV. KARYA WAFIQ GLOBAL
KONSULTAN PENGAWAS : CV.MULTILINE TATARANCANA

BACK UP DATA

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

JENIS PEKERJAAN : 2. PEKERJAAN STRUKTUR


ITEM PEKERJAAN : Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Pintu Jendela)

Panjang Lebar Tinggi Volume


No. Uraian Pekerjaan Section Unit Volume Sat
(m) (m) (m) MC 0%
a b c d e f h j k l
Male
2.2.6.2 Bekisting 2x Pakai
4.56 0.15 0.15 2.00 0.21
Female
4.56 0.15 0.15 2.00 0.21

JUMLAH TOTAL 0.41 0.98 m3

GAMBAR KERJA

5160

1905 1905 1075


6 75 6 00
1 275
1 750

-0. 05

TERAS
BALOK LT
3 650

± 0.00
9 50

-0. 05
9 50

-0. 05

15
TERAS
2 150

2 150

15
1 3750

1 3750
1 680

-0. 05
1 000 9 80

-0. 05
5 400

± 0.00

TERAS
-0. 05 ± 0.00

JENIS KOLOM BALOK LT 15x15cm


TUL. POKOK 4 Ø 10
1 740

TUL. SENGKANG Ø 6 - 150


1 275
1 275

TERAS
± 0.00

200 3960 1000

5160
Denah Toilet

Disetujui Oleh, Diperiksa Oleh, Diajukan Oleh,


Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUPR Prov SulSel CV. MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL
L I L I, ST. MUHAMMAD AGIL AZHARI VIKA APRILIA DWI PUTRI
Nip. 19821229 201503 2 001 Inspector Direktris
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN
Jl. A. P. PETTARANI NO.90, MASALE, PANAKKUKANG, KOTA MAKASSAR, SUL-SEL 90222

PEKERJAAN : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba


NOMOR KONTRAK : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
TANGGAL KONTRAK : 16 Oktober 2020
KONTRAKTOR PELAKSANA : CV. KARYA WAFIQ GLOBAL
KONSULTAN PENGAWAS : CV.MULTILINE TATARANCANA

BACK UP DATA

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

JENIS PEKERJAAN : 2. PEKERJAAN STRUKTUR


ITEM PEKERJAAN : Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Pintu Jendela)

Panjang Lebar Tinggi Volume


No. Uraian Pekerjaan Section Unit Volume Sat
(m) (m) (m) MC 0%
a b c d e f h j k l
Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, Male
2.2.6.1
w/c = 0,66 4.56 0.15 0.15 2.00 0.21
Female
4.56 0.15 0.15 2.00 0.21

JUMLAH TOTAL 0.41 0.15 m3

GAMBAR KERJA

5160

1905 1905 1075


675 6 00
1 275
1 750

- 0.05

TERAS
3 650

± 0.00

BALOK LT
950 9 50

- 0.05

- 0.05

15
TERAS
2 150

2 150
1 3750

1 3750

15
1 680

- 0.05
1 000 9 80

- 0.05
5 400

± 0.00

TERAS
- 0.05 ± 0.00

JENIS KOLOM BALOK LT 15x15cm


1 740

TUL. POKOK 4 Ø 10
TUL. SENGKANG Ø 6 - 150
1 275

1 275

TERAS
± 0.00

200 3960 1000

5160
Denah Toilet

Disetujui Oleh, Diperiksa Oleh, Diajukan Oleh,


Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUPR Prov SulSel CV. MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

L I L I, ST. MUHAMMAD AGIL AZHARI VIKA APRILIA DWI PUTRI


Nip. 19821229 201503 2 001 Inspector Direktris
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN
Jl. A. P. PETTARANI NO.90, MASALE, PANAKKUKANG, KOTA MAKASSAR, SUL-SEL 90222

PEKERJAAN : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba


NOMOR KONTRAK : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
TANGGAL KONTRAK : 16 Oktober 2020
KONTRAKTOR PELAKSANA : CV. KARYA WAFIQ GLOBAL
KONSULTAN PENGAWAS : CV.MULTILINE TATARANCANA

BACK UP DATA

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

JENIS PEKERJAAN : 2. PEKERJAAN STRUKTUR


ITEM PEKERJAAN : Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan)

Lebar Jarak Jumlah 1 Rounded Panjang Besi Jumlah 2 Berat Sat Volume Jumlah VOLUME VOLUME
Uraian Sat
M M Bh Bh M Unit (kg/m) Kg Bh Ø12 Ø6 MC 0%

Besi Beton Ø12 SNI, Ø6 SNI


Male

Tul Pokok (besi Ø 12) 4.00 4.00 4.56 2.00 0.89 32.39 1.00 32.39
Tul Pembagi (besi Ø 6) 4.56 0.15 30.40 31.00 0.60 2.00 0.22 8.26 1.00 8.26

Female

Tul Pokok (besi Ø 12) 4.00 4.00 4.56 2.00 0.89 32.39 1.00 32.39
Tul Pembagi (besi Ø 6) 4.56 0.15 30.40 31.00 0.60 2.00 0.22 8.26 1.00 8.26

JUMLAH 64.77 16.51


Jumlah Besi Beton Ø12 SNI & Ø8 SNI 81.28 157.40 KG

GAMBAR KERJA

5160

1905 1905 1075


6 75 6 00
1 275
1 750

-0. 05

TER AS
RING BALK (RB)
3 650

± 0.00
9 50 9 50

-0. 05

15
-0. 05

TERAS
20
2 150

2 150
13750

1 3750
1 680

-0. 05
1 000 9 80

-0. 05
RING BALK 12/15cm
5 400

± 0.00

TERAS
-0. 05 ± 0.00
TUL. ATAS 2 - Ø 10
TUL. TENGAH -
1 740

TUL. BAWAH 2 - Ø 10
TUL. SENGKANG Ø 8 - 150
1 275

1 275

TERAS
± 0.00

200 3960 1000

5160
Denah Toilet

Disetujui Oleh, Diperiksa Oleh, Diajukan Oleh,


Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUPR Prov SulSel CV. MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

L I L I, ST. MUHAMMAD AGIL AZHARI VIKA APRILIA DWI PUTRI


Nip. 19821229 201503 2 001 Inspector Direktris
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN
Jl. A. P. PETTARANI NO.90, MASALE, PANAKKUKANG, KOTA MAKASSAR, SUL-SEL 90222

PEKERJAAN : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba


NOMOR KONTRAK : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
TANGGAL KONTRAK : 16 Oktober 2020
KONTRAKTOR PELAKSANA : CV. KARYA WAFIQ GLOBAL
KONSULTAN PENGAWAS : CV.MULTILINE TATARANCANA

BACK UP DATA

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

JENIS PEKERJAAN : 2. PEKERJAAN STRUKTUR


ITEM PEKERJAAN : Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan)

Panjang Lebar Sisi Volume


No. Uraian Pekerjaan Section Unit Volume Sat
(m) (m) (m) MC 0%
a b c d e f h j k l
Male
2.2.5.2 Bekisting 2x Pakai
4.56 0.15 2.00 2.00 2.74
Female
4.56 0.15 2.00 2.00 2.74

JUMLAH TOTAL 5.47 14.59 m3

GAMBAR KERJA
5160

1905 1905 1075


675 600
1 275
1 750

-0. 05

RING BALK (RB)


TERAS
3 650

± 0.00
950 950

-0. 05

15
-0. 05

TERAS 20
2 150

2 150
1 3750

1 3750
1 680

-0. 05

RING BALK 12/15cm


1 000 9 80

-0. 05
5 400

± 0.00

TERAS TUL. ATAS 2 - Ø 10


-0. 05 ± 0.00

TUL. TENGAH -
1 740

TUL. BAWAH 2 - Ø 10
TUL. SENGKANG Ø 8 - 150
1 275

1 275

TERAS
± 0.00

200 3960 1000

5160
Denah Toilet

Disetujui Oleh, Diperiksa Oleh, Diajukan Oleh,


Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUPR Prov SulSel CV. MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

L I L I, ST. MUHAMMAD AGIL AZHARI VIKA APRILIA DWI PUTRI


Nip. 19821229 201503 2 001 Inspector Direktris
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN
Jl. A. P. PETTARANI NO.90, MASALE, PANAKKUKANG, KOTA MAKASSAR, SUL-SEL 90222

PEKERJAAN : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba


NOMOR KONTRAK : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
TANGGAL KONTRAK : 16 Oktober 2020
KONTRAKTOR PELAKSANA : CV. KARYA WAFIQ GLOBAL
KONSULTAN PENGAWAS : CV.MULTILINE TATARANCANA

BACK UP DATA

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

JENIS PEKERJAAN : 2. PEKERJAAN STRUKTUR


ITEM PEKERJAAN : Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan)

Panjang Lebar Tinggi Volume


No. Uraian Pekerjaan Section Unit Volume Sat
(m) (m) (m) MC 0%
a b c d e f h j k l
Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, Male
2.2.5.1
w/c = 0,66 4.56 0.15 0.20 2.00 0.27
Female
4.56 0.15 0.20 2.00 0.27

JUMLAH TOTAL 0.55 1.09 m3

GAMBAR KERJA

5160

1905 1905 1075


6 75 6 00
1 275
1 750

-0. 05

RING BALK (RB)


TERAS
3 650

± 0.00
950

-0. 05

15
950

-0. 05

TERAS 20
2 150

2 150
1 3 75 0

1 3750
1 680

-0. 05

RING BALK 12/15cm


1 0 00 9 8 0

-0. 05
5 400

± 0.00

TERAS TUL. ATAS 2 - Ø 10


-0. 05 ± 0.00

TUL. TENGAH -
1 740

TUL. BAWAH 2 - Ø 10
TUL. SENGKANG Ø 8 - 150
1 2 75

1 275

TERAS
±0.00

200 3960 1000

5160
Denah Toilet

Disetujui Oleh, Diperiksa Oleh, Diajukan Oleh,


Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUPR Prov SulSel CV. MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL
L I L I, ST. MUHAMMAD AGIL AZHARI VIKA APRILIA DWI PUTRI
Nip. 19821229 201503 2 001 Inspector Direktris
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN
Jl. A. P. PETTARANI NO.90, MASALE, PANAKKUKANG, KOTA MAKASSAR, SUL-SEL 90222

PEKERJAAN : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba


NOMOR KONTRAK : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
TANGGAL KONTRAK : 16 Oktober 2020
KONTRAKTOR PELAKSANA : CV. KARYA WAFIQ GLOBAL
KONSULTAN PENGAWAS : CV.MULTILINE TATARANCANA

BACK UP DATA

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

JENIS PEKERJAAN : 2. PEKERJAAN STRUKTUR


ITEM PEKERJAAN : Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan)

Lebar Jarak Jumlah 1 Rounded Panjang Besi Jumlah 2 Berat Sat Volume Jumlah VOLUME VOLUME
Uraian Sat
M M Bh Bh M Unit (kg/m) Kg Bh Ø12 Ø6 MC 0%

Besi Beton Ø12 SNI, Ø6 SNI


Male
Horizontal
Tul Pokok (besi Ø 12) 4.00 4.00 3.96 2.00 0.89 28.12 1.00 28.12
Tul Pembagi (besi Ø 6) 3.96 0.15 26.40 27.00 0.60 2.00 0.22 7.19 1.00 7.19

Vertikal
Tul Pokok (besi Ø 12) 4.00 4.00 5.55 2.00 0.89 39.42 1.00 39.42
Tul Pembagi (besi Ø 6) 5.55 0.15 37.00 37.00 0.60 2.00 0.22 9.85 1.00 9.85

Female
Horizontal
Tul Pokok (besi Ø 12) 4.00 4.00 3.96 2.00 0.89 28.12 1.00 28.12
Tul Pembagi (besi Ø 6) 3.96 0.15 26.40 27.00 0.60 2.00 0.22 7.19 1.00 7.19

Vertikal
Tul Pokok (besi Ø 12) 4.00 4.00 3.80 2.00 0.89 26.99 1.00 26.99
Tul Pembagi (besi Ø 6) 3.80 0.15 25.33 26.00 0.60 2.00 0.22 6.92 1.00 6.92
JUMLAH 122.65 31.16
Jumlah Besi Beton Ø12 SNI & Ø8 SNI 153.81 148.86 KG

GAMBAR KERJA
5160

1905 1905 1075


6 75 6 00
1 275
1 750

-0. 05

TER AS RING BALK (RB)


3 650

± 0.00
9 50 9 50

-0. 05

-0. 05
15

TER AS
20
2 150

2 150
1 3750

1 3 750
1 680

-0. 05
1 000 9 80

-0. 05
5 400

RING BALK 12/15cm


± 0.00

TER AS
-0. 05 ± 0.00

TUL. ATAS 2 - Ø 10
TUL. TENGAH -
1 740

TUL. BAWAH 2 - Ø 10
1 275
1 275

TERAS
± 0.00 TUL. SENGKANG Ø 8 - 150

200 3960 1000

5160
Denah Toilet

Disetujui Oleh, Diperiksa Oleh, Diajukan Oleh,


Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUPR Prov SulSel CV. MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

L I L I, ST. MUHAMMAD AGIL AZHARI VIKA APRILIA DWI PUTRI


Nip. 19821229 201503 2 001 Inspector Direktris
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN
Jl. A. P. PETTARANI NO.90, MASALE, PANAKKUKANG, KOTA MAKASSAR, SUL-SEL 90222

PEKERJAAN : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba


NOMOR KONTRAK : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
TANGGAL KONTRAK : 16 Oktober 2020
KONTRAKTOR PELAKSANA : CV. KARYA WAFIQ GLOBAL
KONSULTAN PENGAWAS : CV.MULTILINE TATARANCANA

BACK UP DATA

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

JENIS PEKERJAAN : 2. PEKERJAAN STRUKTUR


ITEM PEKERJAAN : Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan)

Panjang Lebar sisi Volume


No. Uraian Pekerjaan Section Unit Volume Sat
(m) (m) (m) MC 0%
a b c d e f h j k l
Male
2.2.4.2 Bekisting 2x Pakai
h 3.96 0.15 2.00 2.00 2.38
v 5.55 0.15 2.00 2.00 3.33

Female
h 3.96 0.15 2.00 2.00 2.38
v 3.80 0.15 2.00 2.00 2.28

JUMLAH TOTAL 10.36 6.90 m3

GAMBAR KERJA
5160

1905 1905 1075


6 75 6 00
1 275

RING BALK (RB)


1 750

-0. 05

TERAS
3 650

± 0.00

15
950 9 50

-0. 05

-0. 05

20
TERAS
2 150
2 150
1 3750

1 3750
1680

-0. 05

RING BALK 12/15cm


1000 980

-0. 05

TUL. ATAS 2 - Ø 10
5 400

± 0.00

TERAS
-0. 05 ± 0.00
TUL. TENGAH -

TUL. BAWAH 2 - Ø 10
1740

TUL. SENGKANG Ø 8 - 150


1 275

1 275

TERAS
± 0.00

200 3960 1000

5160
Denah Toilet

Disetujui Oleh, Diperiksa Oleh, Diajukan Oleh,


Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUPR Prov SulSel CV. MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL
L I L I, ST. MUHAMMAD AGIL AZHARI VIKA APRILIA DWI PUTRI
Nip. 19821229 201503 2 001 Inspector Direktris
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN
Jl. A. P. PETTARANI NO.90, MASALE, PANAKKUKANG, KOTA MAKASSAR, SUL-SEL 90222

PEKERJAAN : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba


NOMOR KONTRAK : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
TANGGAL KONTRAK : 16 Oktober 2020
KONTRAKTOR PELAKSANA : CV. KARYA WAFIQ GLOBAL
KONSULTAN PENGAWAS : CV.MULTILINE TATARANCANA

BACK UP DATA

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

JENIS PEKERJAAN : 2. PEKERJAAN STRUKTUR


ITEM PEKERJAAN : Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan)

Panjang Lebar Tinggi Volume


No. Uraian Pekerjaan Section Unit Volume Sat
(m) (m) (m) MC 0%
a b c d e f h j k l
Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, Male
2.2.4.1
w/c = 0,66 h 3.96 0.15 0.20 2.00 0.24
v 5.55 0.15 0.20 2.00 0.33

Female
h 3.96 0.15 0.20 2.00 0.24
v 3.80 0.15 0.20 2.00 0.23

JUMLAH TOTAL 1.04 1.04 m3

GAMBAR KERJA
5160

1905 1905 1075


675 6 00
1 275
1 750

-0. 05

RING BALK (RB)


TERAS
3650

± 0.00
9 50

-0. 05

15
9 50

-0. 05

TERAS 20
2 150

2150
13750

1 3750
1 680

-0. 05
1 000 9 80

-0. 05 RING BALK 12/15cm


5 400

± 0.00

-0. 05
TERAS
± 0.00 TUL. ATAS 2 - Ø 10
TUL. TENGAH -
1 740

TUL. BAWAH 2 - Ø 10
TUL. SENGKANG Ø 8 - 150
1275
1 275

TERAS
± 0.00

200 3960 1000

5160
Denah Toilet

Disetujui Oleh, Diperiksa Oleh, Diajukan Oleh,


Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUPR Prov SulSel CV. MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL
L I L I, ST. MUHAMMAD AGIL AZHARI VIKA APRILIA DWI PUTRI
Nip. 19821229 201503 2 001 Inspector Direktris
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN
Jl. A. P. PETTARANI NO.90, MASALE, PANAKKUKANG, KOTA MAKASSAR, SUL-SEL 90222

PEKERJAAN : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba


NOMOR KONTRAK : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
TANGGAL KONTRAK : 16 Oktober 2020
KONTRAKTOR PELAKSANA : CV. KARYA WAFIQ GLOBAL
KONSULTAN PENGAWAS : CV.MULTILINE TATARANCANA

BACK UP DATA

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

JENIS PEKERJAAN : 2. PEKERJAAN STRUKTUR


ITEM PEKERJAAN : Pekerjaan Kolom Praktis 15 x 15 (Ruang Bilas)

Lebar Jarak Jumlah 1 Rounded Panjang Besi Jumlah 2 Berat Sat Volume Jumlah VOLUME VOLUME
Uraian Sat
M M Bh Bh M Unit (kg/m) Kg Bh Ø12 Ø8 MC 0%

Besi Beton Ø12 SNI, Ø8 SNI


Male
Badan Bangunan
Tul Pokok (besi Ø 12) 4.00 4.00 2.42 3.00 0.89 25.78 1.00 25.78
Tul Pembagi (besi Ø 8) 2.42 0.15 16.13 17.00 0.40 3.00 0.39 8.05 1.00 8.05

Sekat
Tul Pokok (besi Ø 12) 4.00 4.00 1.82 3.00 0.89 19.39 1.00 19.39
Tul Pembagi (besi Ø 8) 1.82 0.15 12.13 13.00 0.40 3.00 0.39 6.16 1.00 6.16

JUMLAH 45.17 14.20


Jumlah Besi Beton Ø12 SNI & Ø8 SNI 59.37 51.14 KG

GAMBAR KERJA
5160

1905 1905 1075


675 600
1 275
1 750

-0.05

TERAS KOLOM (K.P)


3650

± 0.00
9 50

-0.05
950

-0.05

15
T ERAS
2 150

2150
1 3750

1 3750

15
1 680

-0.05
1 000 9 80

-0.05
5400

± 0.00

TERAS
-0.05 ± 0.00

JENIS KOLOM KOLOM KP 15x15cm


1 740

TUL. POKOK 4 Ø 10
TUL. SENGKANG Ø 6 - 150
1 275

1275

T ERAS
± 0.00

200 3960 1000

5160
Denah Toilet

Disetujui Oleh, Diperiksa Oleh, Diajukan Oleh,


Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUPR Prov SulSel CV. MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

L I L I, ST. MUHAMMAD AGIL AZHARI VIKA APRILIA DWI PUTRI


Nip. 19821229 201503 2 001 Inspector Direktris
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN
Jl. A. P. PETTARANI NO.90, MASALE, PANAKKUKANG, KOTA MAKASSAR, SUL-SEL 90222

PEKERJAAN : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba


NOMOR KONTRAK : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
TANGGAL KONTRAK : 16 Oktober 2020
KONTRAKTOR PELAKSANA : CV. KARYA WAFIQ GLOBAL
KONSULTAN PENGAWAS : CV.MULTILINE TATARANCANA

BACK UP DATA

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

JENIS PEKERJAAN : 2. PEKERJAAN STRUKTUR


ITEM PEKERJAAN : Pekerjaan Kolom Praktis 15 x 15 (Ruang Bilas)

Sisi Lebar Tinggi Volume


No. Uraian Pekerjaan Section Unit Volume Sat
(m) (m) (m) MC 0%
a b c d e f h j k l
Female
2.2.3.2 Bekisting 2x Pakai
Badan Bangunan 4.00 0.15 2.42 3.00 4.36
Sisi Luar 3.00 0.15 1.82 3.00 2.46

JUMLAH TOTAL 6.81 1.65 m3

GAMBAR KERJA
5160

1905 1905 1075


6 75 6 00
1 275
1 750

-0. 05

TERAS KOLOM (K.P)


3 650

± 0.00
950 9 50

-0. 05

-0. 05

15
TERAS
2 150
2 150

15
1 3750

1 3750
1680

-0. 05
1000 980

-0. 05
5 400

± 0.00

TERAS
-0. 05 ± 0.00

JENIS KOLOM KOLOM KP 15x15cm


1740

TUL. POKOK 4 Ø 10
TUL. SENGKANG Ø 6 - 150
1 275

1 275

TERAS
± 0.00

200 3960 1000

5160
Denah Toilet

Disetujui Oleh, Diperiksa Oleh, Diajukan Oleh,


Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUPR Prov SulSel CV. MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL
L I L I, ST. MUHAMMAD AGIL AZHARI VIKA APRILIA DWI PUTRI
Nip. 19821229 201503 2 001 Inspector Direktris
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN
Jl. A. P. PETTARANI NO.90, MASALE, PANAKKUKANG, KOTA MAKASSAR, SUL-SEL 90222

PEKERJAAN : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba


NOMOR KONTRAK : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
TANGGAL KONTRAK : 16 Oktober 2020
KONTRAKTOR PELAKSANA : CV. KARYA WAFIQ GLOBAL
KONSULTAN PENGAWAS : CV.MULTILINE TATARANCANA

BACK UP DATA

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

JENIS PEKERJAAN : 2. PEKERJAAN STRUKTUR


ITEM PEKERJAAN : Pekerjaan Kolom Praktis 15 x 15 (Ruang Bilas)

Panjang Lebar Tinggi Volume


No. Uraian Pekerjaan Section Unit Volume Sat
(m) (m) (m) MC 0%
a b c d e f h j k l
Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, Female
2.2.2.1
w/c = 0,66 Badan Bangunan 0.15 0.15 2.42 3.00 0.16
Sisi Luar 0.15 0.15 1.82 3.00 0.12

JUMLAH TOTAL 0.29 0.25 m3

GAMBAR KERJA

5160

1905 1905 1075


6 75 6 00
1 275
1 750

-0. 05

KOLOM (K.P)
TERAS
3 650

± 0.00
9 50

-0. 05

15
950

-0. 05

TERAS
2 150

2 150

15
1 3750

1 3750
1 680

-0. 05
1 000 9 80

-0. 05
5 400

±0.00

TERAS
±0.00

JENIS KOLOM KOLOM KP 15x15cm


-0. 05

TUL. POKOK 4 Ø 10
1 740

TUL. SENGKANG Ø 6 - 150


1 275

1 275

TERAS
± 0.00

200 3960 1000

5160
Denah Toilet

Disetujui Oleh, Diperiksa Oleh, Diajukan Oleh,


Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUPR Prov SulSel CV. MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

L I L I, ST. MUHAMMAD AGIL AZHARI VIKA APRILIA DWI PUTRI


Nip. 19821229 201503 2 001 Inspector Direktris
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN
Jl. A. P. PETTARANI NO.90, MASALE, PANAKKUKANG, KOTA MAKASSAR, SUL-SEL 90222

PEKERJAAN : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba


NOMOR KONTRAK : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
TANGGAL KONTRAK : 16 Oktober 2020
KONTRAKTOR PELAKSANA : CV. KARYA WAFIQ GLOBAL
KONSULTAN PENGAWAS : CV.MULTILINE TATARANCANA

BACK UP DATA

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

JENIS PEKERJAAN : 2. PEKERJAAN STRUKTUR


ITEM PEKERJAAN : Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan)

Panjang Lebar Tinggi Volume


No. Uraian Pekerjaan Section Unit Volume Sat
(m) (m) (m) MC 0%
a b c d e f h j k l
Beton Mutu fc = 26,4 Mpa (K300), Slum (12 - 2) cm, Male
2.2.2.1
w/c = 0,52 0.15 0.15 2.22 4.00 0.20
0.15 0.15 2.00 3.00 0.14
Female
0.15 0.15 2.22 2.00 0.10
0.15 0.15 2.00 2.00 0.09
JUMLAH TOTAL 0.52 0.48 m3

GAMBAR KERJA
5160

1905 1905 1075


6 75 6 00
1 275
1 750

-0. 05

KOLOM (K.P)
TERAS
3 650

± 0.00
950

-0. 05

15
950

-0. 05

TERAS
2 150
2 150

15
1 3750

1 3750
1 680

-0. 05
1000 9 80

-0. 05
5 400

± 0.00

TERAS

JENIS KOLOM KOLOM KP 15x15cm


-0. 05 ± 0.00

TUL. POKOK 4 Ø 10
1 740

TUL. SENGKANG Ø 6 - 150


1 275

1 275

TERAS
± 0.00

200 3960 1000

5160
Denah Toilet

Disetujui Oleh, Diperiksa Oleh, Diajukan Oleh,


Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUPR Prov SulSel CV. MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

L I L I, ST. MUHAMMAD AGIL AZHARI VIKA APRILIA DWI PUTRI


Nip. 19821229 201503 2 001 Inspector Direktris
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN
Jl. A. P. PETTARANI NO.90, MASALE, PANAKKUKANG, KOTA MAKASSAR, SUL-SEL 90222

PEKERJAAN : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba


NOMOR KONTRAK : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
TANGGAL KONTRAK : 16 Oktober 2020
KONTRAKTOR PELAKSANA : CV. KARYA WAFIQ GLOBAL
KONSULTAN PENGAWAS : CV.MULTILINE TATARANCANA

BACK UP DATA

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

JENIS PEKERJAAN : 2. PEKERJAAN STRUKTUR


ITEM PEKERJAAN : Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan)

Lebar Jarak Jumlah 1 Rounded Panjang Besi Jumlah 2 Berat Sat Volume Jumlah VOLUME VOLUME
Uraian Sat
M M Bh Bh M Unit (kg/m) Kg Bh Ø12 Ø8 MC 0%

Besi Beton Ø12 SNI, Ø8 SNI


Male
Badan Bangunan
Tul Pokok (besi Ø 12) 4.00 4.00 2.22 4.00 0.89 31.53 1.00 31.53
Tul Pembagi (besi Ø 8) 2.22 0.15 14.80 15.00 0.40 4.00 0.39 9.47 1.00 9.47
Sekat
Tul Pokok (besi Ø 12) 4.00 4.00 2.00 3.00 0.89 21.31 1.00 21.31
Tul Pembagi (besi Ø 8) 2.00 0.15 13.33 14.00 0.40 3.00 0.39 6.63 1.00 6.63
Female
Badan Bangunan
Tul Pokok (besi Ø 12) 4.00 4.00 2.22 2.00 0.89 15.77 1.00 15.77
Tul Pembagi (besi Ø 8) 2.22 0.15 14.80 15.00 0.40 2.00 0.39 4.73 1.00 4.73
Sekat
Tul Pokok (besi Ø 12) 4.00 4.00 2.00 2.00 0.89 14.20 1.00 14.20
Tul Pembagi (besi Ø 8) 2.00 0.15 13.33 14.00 0.40 2.00 0.39 4.42 1.00 4.42

JUMLAH 82.81 25.25


Jumlah Besi Beton Ø12 SNI & Ø8 SNI 108.06 98.75 KG

GAMBAR KERJA

5160

1905 1905 1075


675 600
1275

KOLOM (K.P)
1750

-0. 05

TERAS
3650

± 0.00
950 950

-0. 05

15
-0. 05

TERAS
2150

2150

15
1 3750

1 3750
1680

-0. 05
1000 980

-0. 05
5400

± 0.00

TER AS
-0. 05 ± 0.00

JENIS KOLOM KOLOM KP 15x15cm


1740

TUL. POKOK 4 Ø 10
1275

1275

TUL. SENGKANG Ø 6 - 150


TERAS
± 0.00

200 3960 1000

5160
Denah Toilet

Disetujui Oleh, Diperiksa Oleh, Diajukan Oleh,


Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUPR Prov SulSel CV. MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL
L I L I, ST. MUHAMMAD AGIL AZHARI VIKA APRILIA DWI PUTRI
Nip. 19821229 201503 2 001 Inspector Direktris
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN
Jl. A. P. PETTARANI NO.90, MASALE, PANAKKUKANG, KOTA MAKASSAR, SUL-SEL 90222

PEKERJAAN : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba


NOMOR KONTRAK : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
TANGGAL KONTRAK : 16 Oktober 2020
KONTRAKTOR PELAKSANA : CV. KARYA WAFIQ GLOBAL
KONSULTAN PENGAWAS : CV.MULTILINE TATARANCANA

BACK UP DATA

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

JENIS PEKERJAAN : 2. PEKERJAAN STRUKTUR


ITEM PEKERJAAN : Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan)

sisi Lebar Tinggi Volume


No. Uraian Pekerjaan Section Unit Volume Sat
(m) (m) (m) MC 0%
a b c d e f h j k l
Male
2.2.2.2 Bekisting 2x Pakai
4.00 0.15 2.22 4.00 5.33
4.00 0.15 2.00 3.00 3.60
Female
4.00 0.15 2.22 2.00 2.66
4.00 0.15 2.00 2.00 2.40

JUMLAH TOTAL 13.99 m2


2x Pakai 7.00 3.18 m2

GAMBAR KERJA
5160

1905 1905 1075


6 75 6 00
1 275

KOLOM (K.P)
1 750

-0.05

TERAS
3 650

± 0.00
9 50

15
-0.05
9 50

-0.05

TERAS
2 150

2 150

15
1 3750

1 3750
1 680

-0.05
1 000 9 80

-0.05
5 400

± 0.00

TERAS
-0.05 ± 0.00

JENIS KOLOM KOLOM KP 15x15cm


1 740

TUL. POKOK 4 Ø 10
1 275

1 275

TERAS
±0.00
TUL. SENGKANG Ø 6 - 150
200 3960 1000

5160
Denah Toilet

Disetujui Oleh, Diperiksa Oleh, Diajukan Oleh,


Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUPR Prov SulSel CV. MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL
L I L I, ST. MUHAMMAD AGIL AZHARI VIKA APRILIA DWI PUTRI
Nip. 19821229 201503 2 001 Inspector Direktris
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN
Jl. A. P. PETTARANI NO.90, MASALE, PANAKKUKANG, KOTA MAKASSAR, SUL-SEL 90222

PEKERJAAN : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba


NOMOR KONTRAK : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
TANGGAL KONTRAK : 16 Oktober 2020
KONTRAKTOR PELAKSANA : CV. KARYA WAFIQ GLOBAL
KONSULTAN PENGAWAS : CV.MULTILINE TATARANCANA

BACK UP DATA

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

JENIS PEKERJAAN : 2. PEKERJAAN STRUKTUR


ITEM PEKERJAAN : Pekerjaan Sloef S1 15/25 (Badan Bangunan, Ruang Bilas)

Panjang Lebar Tinggi Volume


No. Uraian Pekerjaan Section Unit Volume Sat
(m) (m) (m) MC 0%
a b c d e f h j k l
Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) Male
2.2.1.2
cm, w/c = 0,52 h 3.96 0.15 0.25 2.00 0.30
v 5.55 0.15 0.25 2.00 0.42
h1 1.50 0.15 0.25 3.00 0.17
Female
h 3.96 0.15 0.25 2.00 0.30
v 3.80 0.15 0.25 2.00 0.29
h1 1.50 0.15 0.25 2.00 0.11

JUMLAH TOTAL 1.58 1.41 m2

GAMBAR KERJA

5160

1905 1905 1075


675 600
1275

S lo e f Be to n 15/ 25
S lo e f B e t o n 15/ 25

SLOEF (S1)
1750

S lo e f B e t o n 15/ 25

3650
950
950

S lo e f Be to n 15/ 25
2150

2150

13750
13750

S lo e f Be to n 15/ 25
1680

JENIS SLOEF SLOEF S1 15/20cm


TUL. ATAS 2 - Ø 12
980

5400
S lo e f B e t o n 15/ 25

TUL. TENGAH 2 - Ø 12
1000

TUL. BAWAH 2 - Ø 12
S lo e f B e t o n 15/ 25
1740

TUL. SENGKANG Ø 8 - 150


S lo e f Be to n 15/ 25
1275
1275

200 3960 1000

5160
Rencana Sloef
SKALA 1 : 100

Disetujui Oleh, Diperiksa Oleh, Diajukan Oleh,


Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUPR Prov SulSel CV. MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

L I L I, ST. MUHAMMAD AGIL AZHARI VIKA APRILIA DWI PUTRI


Nip. 19821229 201503 2 001 Inspector Direktris
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN
Jl. A. P. PETTARANI NO.90, MASALE, PANAKKUKANG, KOTA MAKASSAR, SUL-SEL 90222

PEKERJAAN : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba


NOMOR KONTRAK : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
TANGGAL KONTRAK : 16 Oktober 2020
KONTRAKTOR PELAKSANA : CV. KARYA WAFIQ GLOBAL
KONSULTAN PENGAWAS : CV.MULTILINE TATARANCANA

BACK UP DATA

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

JENIS PEKERJAAN : 2. PEKERJAAN STRUKTUR


ITEM PEKERJAAN : Pekerjaan Sloef S1 15/25 (Badan Bangunan, Ruang Bilas)

Panjang Lebar Tinggi Volume


No. Uraian Pekerjaan Section Unit Volume Sat
(m) (m) (m) MC 0%
a b c d e f h j k l
Male
2.2.1.2 Bekisting 2x Pakai
h 3.96 0.25 4.00 3.96
v 5.55 0.25 4.00 5.55
h1 1.50 0.25 6.00 2.25
Female
h 3.96 0.25 4.00 3.96
v 3.80 0.25 4.00 3.80
h1 1.50 0.25 4.00 1.50
JUMLAH TOTAL 21.02 9.42 m2

GAMBAR KERJA
5160

1905 1905 1075


675 600
1275

Sloe f Be t on 15/ 25
S lo e f B e t o n 15/ 25
1750

S lo e f B e to n 15/ 25

3650

SLOEF (S1)
950
950

Sloe f Be t on 15/ 25
2150
2150
13750

13750

Sloe f Be t on 15/ 25
1680

JENIS SLOEF SLOEF S1 15/20cm


980

TUL. ATAS 2 - Ø 12
5400
S lo e f B e to n 15/ 25
1000

TUL. TENGAH 2 - Ø 12
TUL. BAWAH 2 - Ø 12
S lo e f B e t o n 15/ 25
1740

TUL. SENGKANG Ø 8 - 150


Sloe f Be t on 15/ 25
1275
1275

200 3960 1000

5160
Rencana Sloef
SKALA 1 : 100

Disetujui Oleh, Diperiksa Oleh, Diajukan Oleh,


Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUPR Prov SulSel CV. MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL
L I L I, ST. MUHAMMAD AGIL AZHARI VIKA APRILIA DWI PUTRI
Nip. 19821229 201503 2 001 Inspector Direktris
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN
Jl. A. P. PETTARANI NO.90, MASALE, PANAKKUKANG, KOTA MAKASSAR, SUL-SEL 90222

PEKERJAAN : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba


NOMOR KONTRAK : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
TANGGAL KONTRAK : 16 Oktober 2020
KONTRAKTOR PELAKSANA : CV. KARYA WAFIQ GLOBAL
KONSULTAN PENGAWAS : CV.MULTILINE TATARANCANA

BACK UP DATA

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

JENIS PEKERJAAN : 2. PEKERJAAN STRUKTUR


ITEM PEKERJAAN : Pekerjaan Sloef S1 15/25 (Badan Bangunan, Ruang Bilas)

Lebar Jarak Jumlah 1 Rounded Panjang Besi Jumlah 2 Berat Sat Volume Jumlah VOLUME VOLUME
Uraian Sat
M M Bh Bh M Unit (kg/m) Kg Bh Ø14 Ø8 MC 0%

Besi Beton Ø14 SNI, Ø8 SNI


Male
Horizontal
Tul Pokok (besi Ø 14) 6.00 6.00 3.96 2.00 1.21 57.42 1.00 57.42
Tul Pembagi (besi Ø 8) 3.96 0.15 26.40 27.00 0.60 2.00 0.39 12.78 1.00 12.78
Vertikal
Tul Pokok (besi Ø 14) 6.00 6.00 5.55 2.00 1.21 80.48 1.00 80.48
Tul Pembagi (besi Ø 8) 5.55 0.15 37.00 37.00 0.60 2.00 0.39 17.52 1.00 17.52
Horizontal Sekat
Tul Pokok (besi Ø 14) 6.00 6.00 - 3.00 1.21 - 1.00 -
Tul Pembagi (besi Ø 8) - 0.15 - - 0.60 3.00 0.39 - 1.00 -
Male
Horizontal
Tul Pokok (besi Ø 14) 6.00 6.00 3.96 2.00 0.89 42.19 1.00 42.19
Tul Pembagi (besi Ø 8) 3.96 0.15 26.40 27.00 0.60 2.00 0.39 12.78 1.00 12.78
Vertikal
Tul Pokok (besi Ø 14) 6.00 6.00 3.80 2.00 0.89 40.48 1.00 40.48
Tul Pembagi (besi Ø 8) 3.80 0.15 25.33 26.00 0.60 2.00 0.39 12.31 1.00 12.31
Horizontal Sekat
Tul Pokok (besi Ø 14) 6.00 6.00 - 2.00 1.21 - 1.00 -
Tul Pembagi (besi Ø 8) - 0.15 - - 0.60 2.00 0.39 - 1.00 -
JUMLAH 220.56 55.40
Jumlah Besi Beton Ø14 SNI & Ø8 SNI 275.96 243.74 KG

GAMBAR KERJA
5160

1905 1905 1075


675 600
1275

S loef Be ton 1 5/ 25
S loe f Be t on 1 5/ 25
1750

S loe f Be t on 1 5/ 25

SLOEF (S1)
3650
950
950

S loef Be ton 1 5/ 25
2150

2150

13750
13750

S loef Be ton 1 5/ 25
1680

JENIS SLOEF SLOEF S1 15/20cm


980

5400
S loe f Be t on 1 5/ 25

TUL. ATAS 2 - Ø 12
1000

TUL. TENGAH 2 - Ø 12
S loe f Be t on 1 5/ 25
1740

TUL. BAWAH 2 - Ø 12
S loef Be ton 1 5/ 25

TUL. SENGKANG Ø 8 - 150


1275

1275

200 3960 1000 Rencana Sloef


SKALA 1 : 100
5160

Disetujui Oleh, Diperiksa Oleh, Diajukan Oleh,


Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUPR Prov SulSel CV. MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

L I L I, ST. MUHAMMAD AGIL AZHARI VIKA APRILIA DWI PUTRI


Nip. 19821229 201503 2 001 Inspector Direktris
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN
Jl. A. P. PETTARANI NO.90, MASALE, PANAKKUKANG, KOTA MAKASSAR, SUL-SEL 90222

PEKERJAAN : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba


NOMOR KONTRAK : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
TANGGAL KONTRAK : 16 Oktober 2020
KONTRAKTOR PELAKSANA : CV. KARYA WAFIQ GLOBAL
KONSULTAN PENGAWAS : CV.MULTILINE TATARANCANA

BACK UP DATA

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

JENIS PEKERJAAN : 2. PEKERJAAN STRUKTUR


ITEM PEKERJAAN : Pekerjaan Pondasi Rollage L.15 cm (Selasar)

Panjang Lebar Tinggi Volume


No. Uraian Pekerjaan Section Unit Volume Sat
(m) (m) (m) MC 0%
a b c d e f h j k l

2.1.2.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp


h 5.16 0.50 2.00 5.16
v 13.75 0.50 2.00 13.75

JUMLAH TOTAL 18.91 14.21 m2

GAMBAR KERJA
5160

1905 1905 1075


6 75 6 00
1 275
1 750

-0. 05

TERAS
3 650

± 0.00
9 50 950

-0. 05

-0. 05

TERAS
2 150
2 150
1 3750

1 3750
1680

-0. 05
1000 9 80

-0. 05
5 400

± 0.00

TERAS
-0. 05 ± 0.00
1740

1075 3810 275

5160
1 275

1 275

TERAS
± 0.00

200 3960 1000

5160
Denah Toilet

Disetujui Oleh, Diperiksa Oleh, Diajukan Oleh,


Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUPR Prov SulSel CV. MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

L I L I, ST. MUHAMMAD AGIL AZHARI VIKA APRILIA DWI PUTRI


Nip. 19821229 201503 2 001 Inspector Direktris
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN
Jl. A. P. PETTARANI NO.90, MASALE, PANAKKUKANG, KOTA MAKASSAR, SUL-SEL 90222

PEKERJAAN : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba


NOMOR KONTRAK : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
TANGGAL KONTRAK : 16 Oktober 2020
KONTRAKTOR PELAKSANA : CV. KARYA WAFIQ GLOBAL
KONSULTAN PENGAWAS : CV.MULTILINE TATARANCANA

BACK UP DATA

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

JENIS PEKERJAAN : 2. PEKERJAAN STRUKTUR


ITEM PEKERJAAN : Pekerjaan Pondasi Rollage L.15 cm (Selasar)

Panjang Lebar Tinggi Volume


No. Uraian Pekerjaan Section Unit Volume Sat
(m) (m) (m) MC 0%
a b c d e f h j k l

2.1.2.2 Urugan Pasir Dibawah Pondasi Rollage T.5 cm


Horizontal 5.16 0.15 0.10 2.00 0.15
Vertikal 13.75 0.15 0.10 2.00 0.41

JUMLAH TOTAL 0.57 0.30 m3

GAMBAR KERJA
5160

1905 1905 1075


6 75 6 00
1 275
1 750

-0. 05

TERAS
3 650

± 0.00
950 950

-0. 05

-0. 05

TERAS
2 150
2 150
1 3750

1 3750
1680

-0. 05
1000 980

-0. 05
5 400

± 0.00

TERAS
-0. 05 ± 0.00
1740

1075 3810 275

5160
1275

1 275

TERAS
± 0.00

200 3960 1000

5160
Denah Toilet

Disetujui Oleh, Diperiksa Oleh, Diajukan Oleh,


Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUPR Prov SulSel CV. MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

L I L I, ST. MUHAMMAD AGIL AZHARI VIKA APRILIA DWI PUTRI


Nip. 19821229 201503 2 001 Inspector Direktris
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN
Jl. A. P. PETTARANI NO.90, MASALE, PANAKKUKANG, KOTA MAKASSAR, SUL-SEL 90222

PEKERJAAN : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba


NOMOR KONTRAK : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
TANGGAL KONTRAK : 16 Oktober 2020
KONTRAKTOR PELAKSANA : CV. KARYA WAFIQ GLOBAL
KONSULTAN PENGAWAS : CV.MULTILINE TATARANCANA

BACK UP DATA

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

JENIS PEKERJAAN : 2. PEKERJAAN STRUKTUR


ITEM PEKERJAAN : Pekerjaan Pondasi Rollage L.15 cm (Selasar)

Panjang Lebar Tinggi Volume


No. Uraian Pekerjaan Section Unit Volume Sat
(m) (m) (m) MC 0%
a b c d e f h j k l
Pasangan Lantai Kerja Bawah Pondasi Rollage T.5 cm
2.1.2.3
(Beton K300) 5.16 0.15 0.10 2.00 0.15
13.75 0.15 0.10 2.00 0.41

JUMLAH TOTAL 0.57 0.30 m3

GAMBAR KERJA
5160

1905 1905 1075


6 75 6 00
1 275
1 750

-0. 05

TERAS
3 650

± 0.00
9 50 9 50

-0. 05

-0. 05

TERAS
2 150
2 150
1 3750

1 3750
1 680

-0. 05
1000 980

-0. 05
5 400

± 0.00

TERAS
-0. 05 ± 0.00
1 740

1075 3810 275


1 275

1 275

TERAS
± 0.00
5160

200 3960 1000

5160
Denah Toilet

Disetujui Oleh, Diperiksa Oleh, Diajukan Oleh,


Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUPR Prov SulSel CV. MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

L I L I, ST. MUHAMMAD AGIL AZHARI VIKA APRILIA DWI PUTRI


Nip. 19821229 201503 2 001 Inspector Direktris
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN
Jl. A. P. PETTARANI NO.90, MASALE, PANAKKUKANG, KOTA MAKASSAR, SUL-SEL 90222

PEKERJAAN : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba


NOMOR KONTRAK : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
TANGGAL KONTRAK : 16 Oktober 2020
KONTRAKTOR PELAKSANA : CV. KARYA WAFIQ GLOBAL
KONSULTAN PENGAWAS : CV.MULTILINE TATARANCANA

BACK UP DATA

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

JENIS PEKERJAAN : 2. PEKERJAAN STRUKTUR


ITEM PEKERJAAN : Pekerjaan Pondasi Batu Kali (Badan Bangunan,Ruang Bilas)

Panjang Lebar Tinggi Volume


No. Uraian Pekerjaan Section Unit Volume Sat
(m) (m) (m) MC 0%
a b c d e f h j k l
Pasangan Aanstamping Bawah Pondasi Batu Kali T.10 Male
2.1.1.3
cm h 3.96 0.55 0.10 2.00 0.44
v 5.55 0.55 0.10 2.00 0.61
h1 1.50 0.55 0.10 3.00 0.25

Female
h 3.96 0.55 0.10 2.00 0.44
v 3.80 0.55 0.10 2.00 0.42
h1 1.50 0.55 0.10 2.00 0.17

JUMLAH TOTAL 2.31 2.10 m3

GAMBAR KERJA
5160

1905 1905 1075


675600
1 2 75
1 7 50

- 0. 05

TERAS SLOEF - 15/25


3 6 50

±0.00
950 950

KERAMIK
- 0. 05

- 0. 05

TERAS
2 1 50

2 1 50

15 5 5
1 3750

1 3750
1 680

- 0. 05
55

TANAH URUG
1 000 9 80

- 0. 05
5 4 00

± 0.00

TERAS
PAS. BATU KOSONG
5 10

- 0. 05 ± 0.00

PASIR URUG 20
55
1 740

DETAIL PONDASI KALI


1 275

1 2 75

TERAS
± 0.00

200 3960 1000

5160
Denah Toilet

Disetujui Oleh, Diperiksa Oleh, Diajukan Oleh,


Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUPR Prov SulSel CV. MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

L I L I, ST. MUHAMMAD AGIL AZHARI VIKA APRILIA DWI PUTRI


Nip. 19821229 201503 2 001 Inspector Direktris
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN
Jl. A. P. PETTARANI NO.90, MASALE, PANAKKUKANG, KOTA MAKASSAR, SUL-SEL 90222

PEKERJAAN : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba


NOMOR KONTRAK : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
TANGGAL KONTRAK : 16 Oktober 2020
KONTRAKTOR PELAKSANA : CV. KARYA WAFIQ GLOBAL
KONSULTAN PENGAWAS : CV.MULTILINE TATARANCANA

BACK UP DATA

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

JENIS PEKERJAAN : 2. PEKERJAAN STRUKTUR


ITEM PEKERJAAN : Pekerjaan Pondasi Batu Kali (Badan Bangunan,Ruang Bilas)

Panjang Lebar Tinggi Volume


No. Uraian Pekerjaan Section Unit Volume Sat
(m) (m) (m) MC 0%
a b c d e f h j k l
Male
2.1.1.2 Urugan Pasir Dibawah Pondasi Batu Kali T.5 cm
h 3.96 0.55 0.05 2.00 0.22
v 5.55 0.55 0.05 2.00 0.31
h1 1.50 0.55 0.05 3.00 0.12

Female
h 3.96 0.55 0.05 2.00 0.22
v 3.80 0.55 0.05 2.00 0.21
h1 1.50 0.55 0.05 2.00 0.08

JUMLAH TOTAL 1.16 1.05 m2

GAMBAR KERJA
5160

1905 1905 1075


675 600
1 275
1 750

-0.05

TERAS SLOEF - 15/25


3650

± 0.00
9 50 9 50

-0.05

KERAMIK
-0.05

TERAS
2150
2 150

15 5 5
1 3750

1 3750
1 680

-0.05
55
1 000 9 80

-0.05
TANAH URUG
5400

± 0.00

TERAS

PAS. BATU KOSONG


5 10

-0.05 ± 0.00

PASIR URUG 20
1 740

55

DETAIL PONDASI KALI


1 275
1 275

TERAS
± 0.00

200 3960 1000

5160
Denah Toilet

Disetujui Oleh, Diperiksa Oleh, Diajukan Oleh,


Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUPR Prov SulSel CV. MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

L I L I, ST. MUHAMMAD AGIL AZHARI VIKA APRILIA DWI PUTRI


Nip. 19821229 201503 2 001 Inspector Direktris
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN
Jl. A. P. PETTARANI NO.90, MASALE, PANAKKUKANG, KOTA MAKASSAR, SUL-SEL 90222

PEKERJAAN : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba


NOMOR KONTRAK : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
TANGGAL KONTRAK : 16 Oktober 2020
KONTRAKTOR PELAKSANA : CV. KARYA WAFIQ GLOBAL
KONSULTAN PENGAWAS : CV.MULTILINE TATARANCANA

BACK UP DATA

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

JENIS PEKERJAAN : 2. PEKERJAAN STRUKTUR


ITEM PEKERJAAN : Pekerjaan Pondasi Batu Kali (Badan Bangunan,Ruang Bilas)

Panjang Lebar Tinggi Volume


No. Uraian Pekerjaan Section Unit Volume Sat
(m) (m) (m) MC 0%
a b c d e f h j k l
Male
2.1.1.5 Pondasi Batu Kali 1 Sp : 3 Pp
h 3.96 0.40 0.55 2.00 1.74
v 5.55 0.40 0.55 2.00 2.44
h1 1.50 0.40 0.55 3.00 0.99

Female
h 3.96 0.40 0.55 2.00 1.74
v 3.80 0.40 0.55 2.00 1.67
h1 1.50 0.40 0.55 2.00 0.66

JUMLAH TOTAL 9.25 8.82 m2

GAMBAR KERJA
5160

1905 1905 1075


6 75 600
1275
1750

-0. 05

TERAS SLOEF - 15/25


3650

± 0.00
950 950

-0. 05

KERAMIK
-0. 05

TERAS
2 150

2 150

15 5 5
13750

1 3750
1680

-0. 05
55

TANAH URUG
1000 9 80

-0. 05
5400

± 0.00

TERAS
PAS. BATU KOSONG
5 10

-0. 05 ±0.00

PASIR URUG 20
1740

55

DETAIL PONDASI KALI


1275

1275

TERAS
± 0.00

200 3960 1000

5160
Denah Toilet

Disetujui Oleh, Diperiksa Oleh, Diajukan Oleh,


Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUPR Prov SulSel CV. MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

L I L I, ST. MUHAMMAD AGIL AZHARI VIKA APRILIA DWI PUTRI


Nip. 19821229 201503 2 001 Inspector Direktris
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN
Jl. A. P. PETTARANI NO.90, MASALE, PANAKKUKANG, KOTA MAKASSAR, SUL-SEL 90222

PEKERJAAN : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba


NOMOR KONTRAK : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
TANGGAL KONTRAK : 16 Oktober 2020
KONTRAKTOR PELAKSANA : CV. KARYA WAFIQ GLOBAL
KONSULTAN PENGAWAS : CV.MULTILINE TATARANCANA

BACK UP DATA

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

JENIS PEKERJAAN : 2. PEKERJAAN STRUKTUR


ITEM PEKERJAAN : Pekerjaan Pondasi Batu Kali (Badan Bangunan,Ruang Bilas)

Panjang Lebar Tinggi Volume


No. Uraian Pekerjaan Section Unit Volume Sat
(m) (m) (m) MC 0%
a b c d e f h j k l
Male
1.1 Galian Pondasi Batu Kali < 1 m
h 3.96 0.55 0.30 2.00 1.31
v 5.55 0.55 0.30 2.00 1.83
h1 1.50 0.55 0.30 3.00 0.74

Female
h 3.96 0.55 0.30 2.00 1.31
v 3.80 0.55 0.30 2.00 1.25
h1 1.50 0.55 0.30 2.00 0.50

JUMLAH TOTAL 6.94 22.05 m3

GAMBAR KERJA
5160

1905 1905 1075


6 756 00
1275
1750

-0.05

TERAS
SLOEF - 15/25
3 650

± 0.00
9 50 9 50

-0.05

KERAMIK
-0.05

TERAS
2150

2 150

15 5 5
13750

1 3750
1680

-0.05
55
1 000 9 80

-0.05
TANAH URUG
5 400

±0.00

TERAS
±0.00

PAS. BATU KOSONG


-0.05
5 10

PASIR URUG
1740

20
55

DETAIL PONDASI KALI


1275

1 275

TERAS
± 0.00

200 3960 1000

5160
Denah Toilet

Disetujui Oleh, Diperiksa Oleh, Diajukan Oleh,


Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUPR Prov SulSel CV. MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL
L I L I, ST. MUHAMMAD AGIL AZHARI VIKA APRILIA DWI PUTRI
Nip. 19821229 201503 2 001 Inspector Direktris
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN
Jl. A. P. PETTARANI NO.90, MASALE, PANAKKUKANG, KOTA MAKASSAR, SUL-SEL 90222

PEKERJAAN : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba


NOMOR KONTRAK : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
TANGGAL KONTRAK : 16 Oktober 2020
KONTRAKTOR PELAKSANA : CV. KARYA WAFIQ GLOBAL
KONSULTAN PENGAWAS : CV.MULTILINE TATARANCANA

BACK UP DATA

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

JENIS PEKERJAAN : 1. PEKERJAAN PERSIAPAN


ITEM PEKERJAAN : Pek. Pengukuran & Pemasangan Bouwplank

Panjang Lebar Tinggi Volume


No. Uraian Pekerjaan Section Unit Volume Sat
(m) (m) (m) MC 0%
a b c d e f h j k l

1.2 Pek. Pengukuran & Pemasangan Bouwplank


Luasan Toilet 10.32 27.50 2.00 65.32

JUMLAH TOTAL 65.32 48.60 M1

GAMBAR KERJA
5160

1905 1905 1075


6 756 00
1 275
1 750

-0.05

TERAS
3 650

± 0.00
9 50 9 50

-0.05

-0.05

TERAS
2 150

2 150
13750

1 3750
1 680

-0.05
1 000 9 80

-0.05
5 400

±0.00

TERAS
-0.05 ±0.00
1 740
1 275

1 275

TERAS
±0.00

200 3960 1000

5160
Denah Toilet

Disetujui Oleh, Diperiksa Oleh, Diajukan Oleh,


Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUPR Prov SulSel CV. MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL
L I L I, ST. MUHAMMAD AGIL AZHARI VIKA APRILIA DWI PUTRI
Nip. 19821229 201503 2 001 Inspector Direktris
DINAS PEKERJAAN UMUM DAN TATA RUANG PROV. SULAWESI SELATAN
Jl. A. P. PETTARANI NO.90, MASALE, PANAKKUKANG, KOTA MAKASSAR, SUL-SEL 90222

PEKERJAAN : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba


NOMOR KONTRAK : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
TANGGAL KONTRAK : 16 Oktober 2020
KONTRAKTOR PELAKSANA : CV. KARYA WAFIQ GLOBAL
KONSULTAN PENGAWAS : CV.MULTILINE TATARANCANA

BACK UP DATA

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

JENIS PEKERJAAN : 1. PEKERJAAN PERSIAPAN


ITEM PEKERJAAN : Pek. Pembersian Awal

Panjang Lebar Tinggi Volume


No. Uraian Pekerjaan Section Unit Volume Sat
(m) (m) (m) MC 0%
a b c d e f h j k l

1.1 Pek. Pembersian Awal


Luasan Toilet 5.16 13.75 1.00 70.95
Luasan Menara Reservoir 3.40 3.90 1.00 13.26

JUMLAH TOTAL 84.21 81.86 m2

GAMBAR KERJA

5160

1905 1905 1075


6 756 00
1 275
1 750

-0. 05
3 650

TERAS
± 0.00
950 950

-0. 05

-0. 05

TERAS
2 150
2 150

1 3750
1 3750

1 6 80

-0. 05
1 0 00 9 8 0

-0. 05
5 400

± 0.00

TERAS
-0. 05 ± 0.00
1 7 40

1 275
1 2 75

TERAS
± 0.00

200 3960 1000

5160
Denah Toilet

Disetujui Oleh, Diperiksa Oleh, Diajukan Oleh,


Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUPR Prov SulSel CV. MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

L I L I, ST. MUHAMMAD AGIL AZHARI VIKA APRILIA DWI PUTRI


Nip. 19821229 201503 2 001 Inspector Direktris
LAPORAN KEMAJUAN MINGGUAN

Kegiatan : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba Minggu Ke : 01 (Satu)
Satuan Kerja : Dinas Pekerjaan Umum Dan Tata Ruang Prov. Sulawesi Selatan Bidang Cipta Karya Periode : 16 Oktober S/d 22 Oktober 2020
Lokasi : Desa Ara, Kecamatan Bonto Bahari, Kabupaten Bulukumba, Provinsi Sulawesi Selatan No. Kontrak : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
Sumber Dana : APBD Nilai Kontrak : Rp. 1,088,939,358.00
Tahun Anggaran : 2020 Schedule Pelaksanaan : 16 Oktober S/d 14 Desember 2020

MINGGU LALU MINGGU INI S/D MINGGU INI


VOLUME HARGA SATUAN JUMLAH HARGA PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
NO URAIAN PEKERJAAN BOBOT %
SATUAN (Rp.) (Rp.) VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q

A. PEMBANGUNAN RUANG KULINER, SOUVENIR, MUSHOLLAH DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Papan Proyek Ls 1.00 500,000.00 500,000.00 0.05 - - 1.00 100.00 0.05 1.00 100.00 0.05
1.2 Bedeng/Direksi Keet M2 5.50 1,512,555.00 8,319,052.50 0.84 - - 5.50 100.00 0.84 5.50 100.00 0.84

TOTAL PEKERJAAN PERSIAPAN 8,819,052.50 0.89 0.00 0.89 0.89

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Poerplat PP1 (Selasar Samping)
2.1.1.1 Galian Pondasi Poerplat < 1 m M3 0.32 73,837.50 23,628.00 0.00 - - 0.32 100.00 0.00 0.32 100.00 0.00
2.1.1.2 Urugan Pasir dibawah Pondasi Poerplat T.5 cm M3 0.04 148,335.00 5,933.40 0.00 - - - - - - -
2.1.1.3 Urugan Tanah Kembali Pondasi Poerplat M3 0.31 54,175.00 16,794.25 0.00 - - - - - - -
2.1.1.4 Pasangan Lantai Kerja bawah Pondasi Poerplat T.5 cm (Beton K300) M3 0.04 1,118,216.00 44,728.64 0.00 - - - - - - -
2.1.1.5 Pondasi Poerplat 35x50 cm, T.20 cm - -
Beton Mutu F'c = 26,4 mpa (K300), Slump (12-2) cm, w/c = 0,52 M3 0.14 1,118,216.00 156,550.24 0.02 - - - - - - -
Bekisting 2x Pakai M2 0.56 107,013.50 59,927.56 0.01 - - - - - - -
Besi Beton Ø14 SNI Kg 29.40 21,464.85 631,066.59 0.06 - - - - - - -
2.1.2 Pekerjaan Pondasi Batu Kali (Badan Bangunan, Mushollah) - -
2.1.2.1 Galian Tanah Pondasi Batu Kali < 1 m M3 22.73 73,837.50 1,678,326.38 0.17 - - 22.73 100.00 0.17 22.73 100.00 0.17
2.1.2.2 Urugan Pasir dibawah Pondasi Batu Kali T.5 cm M3 1.08 148,335.00 160,201.80 0.02 - - 1.08 100.00 0.02 1.08 100.00 0.02
2.1.2.3 Pasangan Aanstamping bawah Pondasi Batu Kali T.10 M3 2.17 382,674.00 830,402.58 0.08 - - 1.93 88.71 0.07 1.93 88.71 0.07
2.1.2.4 Urugan Tanah Kembali Pondasi Batu Kali M3 10.39 54,175.00 562,878.25 0.06 - - 6.44 61.97 0.04 6.44 61.97 0.04
2.1.2.5 Pondasi Batu Kali 1 Sp : 3 Pp M3 9.09 827,447.50 7,521,497.78 0.76 - - 4.06 44.67 0.34 4.06 44.67 0.34
2.1.3 Pekerjaan Pondasi Rollage L.15 cm (Entrance, Selasar Samping)
2.1.3.1 Galian Tanah Pondasi Rollage < 1 m M3 2.23 73,837.50 164,657.63 0.02 - - - - - - -
2.1.3.2 Urugan Pasir dibawah Pondasi Rollage T.5 cm M3 0.45 148,335.00 66,750.75 0.01 - - - - - - -
2.1.3.3 Pasangan Lantai Kerja bawah Pondasi Rollage T.5 cm (Beton K300) M3 0.45 1,118,216.00 499,003.89 0.05 - - - - - - -
2.1.3.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp M2 20.83 128,436.00 2,675,321.88 0.27 - - - - - - -
2.2 Pekerjaan Sloef, Kolom dan Ringbalk - -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Mushollah) - -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 1.62 1,118,216.00 1,815,703.23 0.18 - - - - - - -
2.2.1.2 Bekisting 2x Pakai M2 10.83 114,438.50 1,239,368.96 0.13 - - - - - - -
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI Kg 280.09 21,464.85 6,012,089.84 0.61 - - - - - - -
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan, Mushollah) - -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.88 1,118,216.00 981,234.54 0.10 - - - - - - -
2.2.2.2 Bekisting 2x Pakai M2 5.85 193,468.00 1,131,787.80 0.11 - - - - - - -
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 181.66 21,464.85 3,899,347.58 0.39 - - - - - - -
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Selasar, Westafel, Tempat Wudhu)
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 - - - - - - -
2.2.3.2 Bekisting 2x Pakai M2 2.26 193,468.00 437,237.68 0.04 - - - - - - -
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 70.10 21,464.85 1,504,686.30 0.15 - - - - - - -
2.2.4 Pekerjaan Kolom K1 15 x 30 (Selasar Samping)
2.2.4.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.62 1,118,216.00 694,412.14 0.07 - - - - - - -
2.2.4.2 Bekisting 2x Pakai M2 6.21 193,468.00 1,201,436.28 0.12 - - - - - - -
2.2.4.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 99.69 21,464.85 2,139,830.90 0.22 - - - - - - -
2.2.5 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan, Mushollah)
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 2.08 1,008,161.00 2,097,478.96 0.21 - - - - - - -
2.2.5.2 Bekisting 2x Pakai M2 13.87 197,923.00 2,745,192.01 0.28 - - - - - - -
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 299.22 21,464.85 6,422,712.42 0.65 - - - - - - -
2.2.6 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan)
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 - - - - - - -
2.2.6.2 Bekisting 2x Pakai M2 2.24 197,923.00 443,347.52 0.04 - - - - - - -
2.2.6.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 48.32 21,464.85 1,037,181.55 0.10 - - - - - - -
2.2.7 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Mushollah, Pintu Jendela)
2.2.7.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.84 1,008,161.00 846,855.24 0.09 - - - - - - -
2.2.7.2 Bekisting 2x Pakai M2 5.59 197,923.00 1,106,389.57 0.11 - - - - - - -
2.2.7.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 115.53 21,464.85 2,479,834.12 0.25 - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT % PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.2.8 Pekerjaan Plat Beton (Selasar Samping, Westafel)
2.2.8.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.22 1,008,161.00 221,795.42 0.02 - - - - - - -
2.2.8.2 Bekisting 2x Pakai M2 2.21 237,468.00 524,804.28 0.05 - - - - - - -
2.2.8.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 54.54 21,464.85 1,170,692.92 0.12 - - - - - - -
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) M2 152.03 163,636.00 24,877,581.08 2.51 - - - - - - -
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4, Entrance) M2 42.24 242,170.50 10,229,281.92 1.03 - - - - - - -
2.5 Pekerjaan Tiang Atap Bitumen Gelombang (Besi Hollow Galvanis 5/10, Entrance) M' 20.40 178,365.00 3,638,646.00 0.37 - - - - - - -
2.6 Pekerjaan Rangka Plafond Kalsiboard (Besi Hollow Metal Galvalume 4/4) M2 147.40 102,837.17 15,158,198.37 1.53 - - - - - - -

TOTAL PEKERJAAN STRUKTUR 109,840,345.70 11.10 0.00 0.64 0.64

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) M3 8.54 148,335.00 1,266,780.90 0.13 - - - - - - -
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) M3 25.63 167,227.00 4,285,636.74 0.43 - - - - - - -
3.1.1.3 Rabat Beton bawah Lantai T.5 cm (Keseluruhan, Beton K300) M3 8.54 1,118,216.00 9,549,564.64 0.96 - - - - - - -
3.1.1.4 Penutup Lantai Keramik Motif 60x60 (Badan Bangunan, Mushollah) M2 62.94 403,309.50 25,384,299.93 2.56 - - - - - - -
3.1.1.5 Penutup Lantai Conwood Deck 6" (Entrance) M2 59.01 866,833.08 51,151,820.09 5.17 - - - - - - -
3.1.1.6 Penutup Lantai Andesit Polos 30x30 (Selasar, Tempat Wudhu, Ram) M2 51.05 232,589.50 11,873,693.98 1.20 - - - - - - -
3.1.1.7 Plint Lantai Keramik 10x60 (Badan Bangunan, Mushollah) M' 38.85 51,605.03 2,004,855.55 0.20 - - - - - - -
3.1.2 Pekerjaan Dinding
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Mushollah, 1 Sp : 4 Pp) M2 74.55 242,979.00 18,114,084.45 1.83 - - - - - - -
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Selasar Samping, Tempat Wudhu) M2 5.14 65,550.32 336,928.64 0.03 - - - - - - -
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm (Badan Bangunan, Mushollah) M2 91.30 60,403.20 5,514,812.16 0.56 - - - - - - -
3.1.2.4 Plesteran Ciprat 1 Sp : 2 Pp Tebal 15 mm (Selasar Samping, Antar Kolom) M2 24.84 49,215.10 1,222,503.08 0.12 - - - - - - -
3.1.2.5 Dinding Keramik Mozaik 30x60 (Selasar Samping, Westafel, Tempat Wudhu) M2 18.44 410,432.00 7,568,366.08 0.76 - - - - - - -
3.1.2.6 Coating Bening (Badan Bangunan, Mushollah, Kolom Luar) M2 127.49 45,973.13 5,861,113.71 0.59 - - - - - - -
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) M2 8.64 995,043.50 8,597,175.84 0.87 - - - - - - -
3.1.2.8 Dinding Wallpaper Bata L.50 cm (Sisi Dalam) M2 28.13 80,005.50 2,250,554.72 0.23 - - - - - - -
3.1.3 Pekerjaan Plafond
3.1.3.1 Plafond Kalsiboard (Badan Bangunan, Kemiringan Atap, Mushollah) M2 147.40 44,924.00 6,621,797.60 0.67 - - - - - - -
3.1.3.2 Plafond Kalsiboard (Lapis Bawah Atap, Entrance) M2 42.24 44,924.00 1,897,589.76 0.19 - - - - - - -
3.2 Pekerjaan Pintu dan Jendela (Badan Bangunan)
3.2.1 Pintu P1 (Entrance dan Back Entrance, Badan Bangunan)
3.2.1.1 Pasangan Kusen Alumunium Coating P1 (4" x 1 3/4") cm M' 22.40 157,194.40 3,521,154.56 0.36 - - - - - - -
3.2.1.2 Pasangan Daun Pintu P1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - -
3.2.1.3 Pasangan Kaca Mati 5 mm P1 M2 11.20 145,703.80 1,631,882.56 0.16 - - - - - - -
3.2.1.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - -
3.2.1.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - -
3.2.1.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - -
3.2.1.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - -
3.2.2 Jendela J1 (Badan Bangunan)
3.2.2.1 Pasangan Kusen Alumunium Coating J1 (4" x 1 3/4") cm M' 40.60 157,194.40 6,382,092.64 0.64 - - - - - - -
3.2.2.2 Pasangan Kaca Mati 5 mm J1 M2 8.00 145,703.80 1,165,630.40 0.12 - - - - - - -
3.2.3 Pintu PJ1 (Mushollah)
3.2.3.1 Pasangan Kusen Alumunium Coating PJ1 (4" x 1 3/4") cm M' 22.20 157,194.40 3,489,715.68 0.35 - - - - - - -
3.2.3.2 Pasangan Daun Pintu PJ1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - -
3.2.3.3 Pasangan Kaca Mati 5 mm P1 M2 8.70 145,703.80 1,267,623.06 0.13 - - - - - - -
3.2.3.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - -
3.2.3.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - -
3.2.3.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - -
3.2.3.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - -
3.3 Pekerjaan Pengecatan
3.3.1 Pengecatan Plafond (1 Plamir ; 1 Cat Dasar : 2 Cat Penutup), (Interior) M2 189.64 35,536.05 6,739,056.52 0.68 - - - - - - -
3.3.2 Pengecatan Rangka Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 23.76 168,454.00 4,002,467.04 0.40 - - - - - - -
3.3.3 Pengecatan Tiang Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 6.12 168,454.00 1,030,938.48 0.10 - - - - - - -
3.4 Pekerjaan Atap
3.4.1 Atap Bitumen Gelombang (Badan Bangunan, Mushollah) M2 152.03 207,297.09 31,515,376.59 3.18 - - - - - - -
3.4.2 Atap Bitumen Gelombang (Entrance) M2 42.24 207,297.09 8,756,229.08 0.88 - - - - - - -
3.4.3 Nok Bitumen (Badan Bangunan, Mushollah) M' 14.55 134,101.00 1,951,169.55 0.20 - - - - - - -
3.4.4 Listplank (Kalsiplank, Badan Bangunan, Mushollah, Entrance) M' 50.00 70,950.00 3,547,500.00 0.36 - - - - - - -

TOTAL PEKERJAAN FINISHING ARSITEKTUR 257,222,142.77 25.98 0.00 0.00 0.00

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel Bh 1.00 1,572,826.75 1,572,826.75 0.16 - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt Bh 16.00 353,938.75 5,663,020.00 0.57 - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT % PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4.1.3 Pasangan Lampu Down Light 2,5" Outbow LED 5,5 Watt Bh 11.00 305,538.75 3,360,926.25 0.34 - - - - - - -
4.1.4 Pasangan Saklar Tunggal Bh 4.00 211,378.75 845,515.00 0.09 - - - - - - -
4.1.5 Pasangan Saklar Ganda Bh 2.00 223,478.75 446,957.50 0.05 - - - - - - -
4.2 Pasangan Instalasi Stop Kontak - -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA Bh 10.00 216,218.75 2,162,187.50 0.22 - - - - - - -
4.2.2 Pasangan Stop Kontak AC 220 VA/3520 W (AC Split 1 PK) Bh 4.00 253,728.75 1,014,915.00 0.10 - - - - - - -
4.3 Pasangan Instalasi Jaringan AC M' 30.00 108,772.68 3,263,180.25 0.33 - - - - - - -
4.3.1 Pasangan AC Split 1 PK Bh 3.00 3,365,799.34 10,097,398.03 1.02 - - - - - - -
4.4 Pasangan Penangkal Petir Ls 1.00 2,500,000.00 2,500,000.00 0.25 - - - - - - -
4.5 Pasangan Instalasi Jaringan Kabel Fiber Optic (CCTV) Ttk 6.00 786,326.75 4,717,960.50 0.48 - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2MP Bh 6.00 656,975.00 3,941,850.00 0.40 - - - - - - -
4.5.2 Pasangan NVR Channel Set 1.00 5,023,975.00 5,023,975.00 0.51 - - - - - - -
4.5.3 Pasangan Monitor LCD 32" Bh 1.00 2,944,975.00 2,944,975.00 0.30 - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm M' 12.00 20,442.68 245,312.10 0.02 - - - - - - -
4.6.1 Pasangan Horn Speaker Bh 6.00 494,826.75 2,968,960.50 0.30 - - - - - - -
4.6.2 Pasangan Volume Kontrol Set 1.00 252,826.75 252,826.75 0.03 - - - - - - -
4.6.3 Pasangan Perangkat Sound System Set 1.00 4,565,000.00 4,565,000.00 0.46 - - - - - - -
4.6.4 Pasangan TB-Sound System Set 1.00 5,846,326.75 5,846,326.75 0.59 - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25Kg) Ttk 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - -
4.8 Pasangan Instalasi Jaringan Kabel Fiber Optic (Akses Point) Ttk 3.00 786,326.75 2,358,980.25 0.24 - - - - - - -
4.8.1 Pasangan Server Set 1.00 7,578,826.75 7,578,826.75 0.77 - - - - - - -
4.8.2 Pasangan Akses Point Bh 1.00 2,034,826.75 2,034,826.75 0.21 - - - - - - -
4.8.3 Pasangan Switch HUB Bh 1.00 2,843,326.75 2,843,326.75 0.29 - - - - - - -
4.9 Pasangan Instalasi PLN Power (Inc. Jalur ke Mushollah dan Toilet) Ls 1.00 9,000,000.00 9,000,000.00 0.91 - - - - - - -

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 94,450,073.38 9.54 0.00 0.00 0.00

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVC Type AW Diameter 3/4" (Air Bersih Sambungan dari Tandon) M' 33.00 28,300.25 933,908.25 0.09 - - - - - - -
5.2 Pipa PVC Type AW Diameter 3" (Air Kotor ke Drainase Lingkungan) M' 25.80 135,531.00 3,496,699.80 0.35 - - - - - - -
5.3 Pasangan 1 Bh Wastafel Bh 2.00 3,934,865.00 7,869,730.00 0.79 - - - - - - -
5.4 Pasangan 1 Bh Wastafel Cuci Piring (WCP) Bh 1.00 890,945.00 890,945.00 0.09 - - - - - - -
5.5 Pasangan 1 Bh Floor Drain Bh 2.00 41,112.50 82,225.00 0.01 - - - - - - -
5.6 Pasangan 1 Bh Kran Dia. 1/2" atau 3/4" Bh 10.00 102,217.50 1,022,175.00 0.10 - - - - - - -
5.7 Pasangan 1 Bh Kran Wastafel Dia. 1/2" atau 3/4" Bh 3.00 335,417.50 1,006,252.50 0.10 - - - - - - -
5.8 Pasangan 1 Bh Stop Kran (Gate Valve) Dia. 3/4" Bh 1.00 141,417.50 141,417.50 0.01 - - - - - - -
5.9 Pasangan Mesin Air Bh 1.00 741,000.00 741,000.00 0.07 - - - - - - -
5.10 Menara Reservoir 200x150x350 cm - -
5.10.1 Pekerjaan Pondasi Pedestal Pd1 - -
5.10.1.1 Galian Tanah Pondasi Poerplat < 1 m M3 1.62 73,837.50 119,616.75 0.01 - - - - - - -
5.10.1.2 Urugan Tanah Kembali Pondasi Poerplat M3 0.43 54,175.00 23,295.25 0.00 - - - - - - -
5.10.1.3 Tiang Pondasi Pedestal 50x50 cm - -
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.80 1,118,216.00 894,572.80 0.09 - - - - - - -
Bekisting 2x Pakai M2 3.20 193,468.00 619,097.60 0.06 - - - - - - -
Besi Beton Ø12 SNI, Ø8 SNI Kg 49.44 21,464.85 1,061,130.60 0.11 - - - - - - -
5.10.1.4 Pondasi Poerplat 90x90 cm, T.20 cm
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.65 1,118,216.00 726,840.40 0.07 - - - - - - -
Bekisting 2x Pakai M2 1.44 107,013.50 154,099.44 0.02 - - - - - - -
Besi Beton Ø14 SNI Kg 214.35 21,464.85 4,600,940.54 0.46 - - - - - - -
5.10.2 Rangka Tengah dan Lantai Menara (Besi Hollow Galvanis 4/4) M2 34.82 244,970.00 8,529,855.40 0.86 - - - - - - -
5.10.3 Rangka Utama Menara (Besi Hollow Galvanis 5/10) M' 32.28 179,454.00 5,792,775.12 0.59 - - - - - - -
5.10.4 Plat Baja Lantai Menara T.3 mm M2 3.00 740,164.86 2,220,494.57 0.22 - - - - - - -
5.10.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) M2 5.00 244,970.00 1,224,850.00 0.12 - - - - - - -

TOTAL PEKERJAAN PLAMBING DAN SANITASI 42,151,921.52 4.26 0.00 0.00 0.00

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Pek. Pembersian Awal m2 81.86 17,600.00 1,440,780.00 0.15 - - 81.86 100.00 0.15 81.86 100.00 0.15
1.2 Pek. Pengukuran & Pemasangan Bouwplank m1 48.60 106,461.25 5,174,016.75 0.52 - - 48.60 100.00 0.52 48.60 100.00 0.52

TOTAL PEKERJAAN PERSIAPAN 6,614,796.75 0.67 0.00 0.67 0.67

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Batu Kali (Badan Bangunan,Ruang Bilas)
2.1.1.1 Galian Pondasi Batu Kali < 1 m m3 22.05 73,892.50 1,629,329.63 0.16 - - 22.05 100.00 0.16 22.05 100.00 0.16
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT % PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.1.1.2 Urugan Pasir Dibawah Pondasi Batu Kali T.5 cm m3 1.05 174,757.00 183,494.85 0.02 - - 1.05 100.00 0.02 1.05 100.00 0.02
2.1.1.3 Pasangan Aanstamping Bawah Pondasi Batu Kali T.10 cm m3 2.10 392,699.70 824,669.37 0.08 - - 1.16 55.05 0.05 1.16 55.05 0.05
2.1.1.4 Urugan Tanah Kembali Pondasi Batu Kali m3 10.08 54,285.00 547,192.80 0.06 - - - - - - -
2.1.1.5 Pondasi Batu Kali 1 Sp : 3 Pp m3 8.82 824,945.00 7,276,014.90 0.73 - - 4.62 52.43 0.39 4.62 52.43 0.39
2.1.2 Pekerjaan Pondasi Rollage L.15 cm (Selasar) - -
2.1.2.1 Galian Tanah Pondasi Rollage < 1 m m3 1.52 73,892.50 112,501.33 0.01 - - - - - - -
2.1.2.2 Urugan Pasir Dibawah Pondasi Rollage T.5 cm m3 0.30 174,757.00 53,213.51 0.01 - - - - - - -
2.1.2.3 Pasangan Lantai Kerja Bawah Pondasi Rollage T.5 cm (Beton K300) m3 0.30 1,118,398.60 340,552.37 0.03 - - - - - - -
2.1.2.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp m2 14.21 128,260.00 1,822,574.60 0.18 - - - - - - -
2.2 Pekerjaan Sloef, Kolom, Plat dan Ringbalk - -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Ruang Bilas) - -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 m3 1.41 1,118,398.60 1,580,297.22 0.16 - - - - - - -
2.2.1.2 Bekisting 2x Pakai m2 9.42 114,467.10 1,078,280.08 0.11 - - - - - - -
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI kg 243.74 21,465.73 5,232,043.29 0.53 - - - - - - -
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan) - -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slum (12 - 2) cm, w/c = 0,52 m3 0.48 1,118,398.60 533,476.13 0.05 - - - - - - -
2.2.2.2 Bekisting 2x Pakai m2 3.18 193,504.30 615,343.67 0.06 - - - - - - -
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI kg 98.75 21,465.73 2,119,732.25 0.21 - - - - - - -
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Ruang Bilas) - -
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.25 1,008,343.60 249,111.29 0.03 - - - - - - -
2.2.3.2 Bekisting 2x Pakai m2 1.65 193,504.30 318,701.58 0.03 - - - - - - -
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI kg 51.14 21,465.73 1,097,861.33 0.11 - - - - - - -
2.2.4 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan) - -
2.2.4.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.04 1,008,343.60 1,043,635.63 0.11 - - - - - - -
2.2.4.2 Bekisting 2x Pakai m2 6.90 197,959.30 1,365,919.17 0.14 - - - - - - -
2.2.4.3 Besi Beton Ø12 SNI, Ø6 SNI kg 148.86 21,465.73 3,195,302.68 0.32 - - - - - - -
2.2.5 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan) - -
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.09 1,008,343.60 1,103,531.24 0.11 - - - - - - -
2.2.5.2 Bekisting 2x Pakai m2 14.59 197,959.30 2,888,622.11 0.29 - - - - - - -
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI kg 157.40 21,465.73 3,378,705.12 0.34 - - - - - - -
2.2.6 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Pintu Jendela)
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.15 1,008,343.60 148,831.52 0.02 - - - - - - -
2.2.6.2 Bekisting 2x Pakai m2 0.98 197,959.30 194,791.95 0.02 - - - - - - -
2.2.6.3 Besi Beton Ø10 SNI, Ø6 SNI kg 20.35 21,465.73 436,752.39 0.04 - - - - - - -
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) m2 59.01 163,856.00 9,669,142.56 0.98 - - - - - - -
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4) m2 48.59 102,876.77 4,998,782.09 0.50 - - - - - - -
2.5 Pekerjaan Rangka Plafond dan Dinding Dalam PVC Shunda (Besi Hollow Metal Galvalume 4/4) m2 56.16 102,876.77 5,777,559.22 0.58 - - - - - - -

TOTAL PEKERJAAN STRUKTUR 59,815,965.86 6.04 0.00 0.61 0.61

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) m3 4.09 174,757.00 715,280.40 0.07 - - - - - - -
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) m3 12.28 167,345.00 2,054,804.70 0.21 - - - - - - -
3.1.1.3 Rabat Beton T.5 cm (Keseluruhan, Beton K300) m3 4.09 1,118,398.60 4,577,605.47 0.46 - - - - - - -
3.1.1.4 Penutup Lantai Keramik Tekstur 60x60 (Badan Bangunan) m2 36.93 413,098.40 15,255,723.91 1.54 - - - - - - -
3.1.1.5 Penutup Lantai Andesit Polos 30x30 (Selasar, Ruang Bilas) m2 45.89 284,369.80 13,049,730.12 1.32 - - - - - - -
3.1.1.6 Penutup Plat Wastafel (Granit 60x60, Toilet Pria dan Wanita) m2 2.20 841,621.73 1,851,567.81 0.19 - - - - - - -
3.1.2 Pekerjaan Dinding - -
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Selasar, 1 Sp : 4 Pp) 90.64 242,533.50 21,983,236.44 2.22 - - - - - - -
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Wc ) 30.00 65,473.32 1,964,199.60 0.20 - - - - - - -
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm 121.28 60,304.20 7,313,693.38 0.74 - - - - - - -
3.1.2.4 Coating Bening 121.28 46,853.13 5,682,347.00 0.57 - - - - - - -
3.1.2.5 Dinding Andesit Polos 30x30 cm ( Wc, Ruang Bilas ) 56.52 284,369.80 16,072,581.10 1.62 - - - - - - -
3.1.2.6 Dinding Keramik 30x60 cm ( Sisi Dalam ) 69.88 370,557.00 25,894,523.16 2.62 - - - - - - -
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) 9.00 995,076.50 8,955,688.50 0.90 - - - - - - -
3.1.2.8 Cubicle Panel + Accessories (Pintu Wc dan Partisi Urinoir) 10.86 1,360,000.00 14,769,600.00 1.49 - - - - - - -
3.1.2.9 Dinding Bitumen Gelombang 48.59 201,749.24 9,802,995.57 0.99 - - - - - - -
3.1.2.10 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Pria) 1.00 1,200,000.00 1,200,000.00 0.12 - - - - - - -
3.1.2.11 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Wanita) 1.00 750,000.00 750,000.00 0.08 - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT % PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.1.3 Plafond dan Dinding Dalam Shunda ( Badan Bangunan ) 56.16 125,878.50 7,069,336.56 0.71 - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT % PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.2 Pekerjaan Pintu dan Jendela ( Badan Bangunan ) - -
3.2.1 Pintu P1 - -
3.2.1.1 Pasangan Kusen Almunium Coating P1 (4" x 13/4") cm 10.96 157,199.02 1,722,901.26 0.17 - - - - - - -
3.2.1.2 Pasangan Daun Pintu P1 (Panel Almunium Coating - Coating) 4.30 870,323.19 3,742,389.72 0.38 - - - - - - -
3.2.1.3 Pasangan Kunci Tanam 2x Slag P1 2.00 416,663.50 833,327.00 0.08 - - - - - - -
3.2.1.4 Pasangan ensel P1 6.00 61,225.56 367,353.36 0.04 - - - - - - -
3.2.1.5 Pasangan Doorcloser P1 2.00 241,902.10 483,804.20 0.05 - - - - - - -
3.2.1.6 Pasangan Handle P1 2.00 229,802.10 459,604.20 0.05 - - - - - - -
3.2.2 Jendela J1 - -
3.2.2.1 Pasangan Kusen Almunium Coating J1 (4" x 13/4") cm 28.80 157,199.02 4,527,331.78 0.46 - - - - - - -
3.2.2.2 Pasangan Kaca Mati 5 mm J1 0.60 145,705.56 87,423.34 0.01 - - - - - - -
3.2.3 Jendela J2 - -
3.2.3.1 Pasangan Kusen Almunium Coating J2 (4" x 13/4") cm 55.20 157,199.02 8,677,385.90 0.88 - - - - - - -
3.2.3.2 Pasangan Kaca Mati 5 mm J2 0.90 145,705.56 131,135.00 0.01 - - - - - - -
3.3. Pengecetan Plafond (1 Plamir : 1 Cat Dasar : 2 Cat Penutup), (Interior) 56.16 43,550.65 2,445,804.50 0.25 - - - - - - -
3.4 Pekerjaan Atap - -
3.4.1 Atap Bitumen Gelombang (Badan Bangunan) 59.01 201,749.24 11,905,222.65 1.20 - - - - - - -
3.4.2 Nok Bitumen (Badan Bangunan) 35.25 143,629.20 5,062,929.30 0.51 - - - - - - -
3.4.3 Listplank (Kasiplank, Badan Bangunan, Enterance) 39.08 70,972.00 2,773,585.76 0.28 - - - - - - -

TOTAL PEKERJAAN FINISHING ARSITEKTUR 202,183,111.69 20.42 0.00 0.00 0.00

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel 1.00 1,803,826.75 1,803,826.75 0.18 - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt 10.00 353,938.75 3,539,387.50 0.36 - - - - - - -
4.1.3 Pasangan Lampu Down Light 2.5" Outbow LED 5.5 Watt 12.00 305,538.75 3,666,465.00 0.37 - - - - - - -
4.1.4 Pasangan Saklar Ganda 5.00 223,478.75 1,117,393.75 0.11 - - - - - - -
4.2 Pasangan Instalasi Stop Kontak - -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA 3.00 216,218.75 648,656.25 0.07 - - - - - - -
4.2.2 Pasangan Stop Kontak Wall Exhauser 6.00 216,218.75 1,297,312.50 0.13 - - - - - - -
4.3 Pasangan Instalasi Jaringan Wall Exhauser 12.00 108,772.68 1,305,272.10 0.13 - - - - - - -
4.3.1 Pasangan Wall Exhauser 12 Inch - FV30RUN 6.00 513,500.00 3,081,000.00 0.31 - - - - - - -
4.4 Pasangan Penangkal Petir 1.00 3,500,000.00 3,500,000.00 0.35 - - - - - - -
4.5 Pasangan Instlasi Jaringan Kabel Fiber Optic (CCTV) 3.00 786,326.75 2,358,980.25 0.24 - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2 MP (Luar Bangunan, Sambungan Dari Mini Resto) 3.00 656,975.00 1,970,925.00 0.20 - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm 4.00 20,442.68 81,770.70 0.01 - - - - - - -
4.6.1 Pasangan Horn Speaker (Sambungan Dari Mini Resto) 2.00 494,826.75 989,653.50 0.10 - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25 kg) 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - -
4.8 Pasangan Instalasi PLN Power 1.00 10,000,000.00 10,000,000.00 1.01 - - - - - - -

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 44,560,643.30 4.50 0.00 0.00 0.00

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVc Tipe AW Diameter 3/4" (Air Bersih Dari Sumur Bor / PDAM Reservoir) m1 18.50 28,304.65 523,636.03 0.05 - - - - - - -
5.2 Pipa PVC Tipe AW Diameter 3/4" (Distribusi Air Bersih Dari Reservoir) m1 26.50 28,304.65 750,073.23 0.08 - - - - - - -
5.3 Pipa PVC Tipe AW Diameter 3" (Air Kotor Ke Drainase Lingkungan) m1 23.00 135,539.80 3,117,415.40 0.31 - - - - - - -
5.4 Pipa PVC Tipe AW Diameter 4" (Disposal) m1 18.00 186,689.80 3,360,416.40 0.34 - - - - - - -
5.5 Pasangan 1 bh Closet Duduk / Monoblock (TOTO) bh 6.00 3,655,597.00 21,933,582.00 2.22 - - - - - - -
5.6 Pasangan 1 bh Wastafel (TOTO) 3.00 3,571,942.00 10,715,826.00 1.08 - - - - - - -
5.7 Pasangan 1 bh Uninoir (TOTO) 2.00 6,665,285.00 13,330,570.00 1.35 - - - - - - -
5.8 Pasangan 1 bh Floor Drain 9.00 41,123.50 370,111.50 0.04 - - - - - - -
5.9 Pasangan 1 bh Kran dia. 1/2' atau 3/4" 8.00 102,228.50 817,828.00 0.08 - - - - - - -
5.10 Pasangan 1 bh Kran wastafel dia. 1/2' atau 3/4" 2.00 335,428.50 670,857.00 0.07 - - - - - - -
5.11 Pasangan 1 bh shower closet dia. 1/2' atau 3/4" 6.00 142,928.50 857,571.00 0.09 - - - - - - -
5.12 Pasangan 1 bh shower Wall dia. 1/2' atau 3/4" (Ruang Bilas) 4.00 1,435,428.50 5,741,714.00 0.58 - - - - - - -
5.13 Pasangan 1 bh Stop Kran (Gate Valve) dia. 3/4" 2.00 141,428.50 282,857.00 0.03 - - - - - - -
5.14 Pasangan Mesin Air 1.00 741,000.00 741,000.00 0.07 - - - - - - -
5.14b Pasangan Mesin Pemanas Air 1.00 5,000,000.00 5,000,000.00 0.51 - - - - - - -
5.15 Septictank Biotank Kap. 4m3 1.00 20,380,000.00 20,380,000.00 2.06 - - - - - - -
5.16 Pasangan Sumur Bor Jet Pump 30.00 350,000.00 10,500,000.00 1.06 - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT % PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.17 Reservoir 1200 Liter 1.00 1,850,000.00 1,850,000.00 0.19 - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT % PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.18 Reservoir 200x150x350 cm - -
5.18.1 Pekerjaan Pondasi Pedestal Pd1 - -
5.18.1.1 Galian Tanah Pondasi Poerplat < 1m 1.62 74,250.00 120,285.00 0.01 - - - - - - -
5.18.1.2 Urugan Tanah Kembali Pondasi Poerplat 0.43 55,000.00 23,760.00 0.00 - - - - - - -
5.18.1.3 Tiang Pondasi Pedestal 50x50 cm - -
Beton Mutu fc = 26,6 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.80 1,485,144.21 1,188,115.37 0.12 - - - - - - -
Bekisting 2x Pakai 3.20 193,504.30 619,213.76 0.06 - - - - - - -
Besi Beton Ø12, Ø8 49.44 21,465.73 1,061,174.10 0.11 - - - - - - -
5.18.1.4 Pondasi Poerplat 90x90 cm,T.20 cm - -
Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.65 1,485,144.21 962,373.45 0.10 - - - - - - -
Bekisting 2x Pakai 1.44 124,547.50 179,348.40 0.02 - - - - - - -
Besi Beton Ø14 SNI 214.35 21,465.73 4,601,114.73 0.46 - - - - - - -
5.18.2 Rangkai Tengah Dan Lantai Menara (Besi Hollow Galvanis 4/4) 34.82 244,970.00 8,529,855.40 0.86 - - - - - - -
5.18.3 Rangka Utama menara ( Besi Hollow Galvanis 5/10 32.28 179,454.00 5,792,775.12 0.59 - - - - - - -
5.18.4 Tplat Baja Lantai Menara T.3mm 3.00 740,164.86 2,220,494.57 0.22 - - - - - - -
5.18.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) 5.00 244,970.00 1,224,850.00 0.12 - - - - - - -

TOTAL PEKERJAAN PLAMBING DAN SANITASI 127,466,817.45 12.88 - - -

6. PEKERJAAN AKHIR - - -
6.1 Pembersihan Sisa Pekerjaan Ls 1.00 2,400,000.00 2,400,000.00 0.24 - - - - - - -

TOTAL PEKERJAAN AKHIR 2,400,000.00 0.24 0.00 0.00 0.00

C. PENERAPAN SMKK

1. PENYIAPAN RKK
1.1 Pembuatan Dokumen Rencana Keselamatan Konstruksi
1.2 Pembuatan Prosedur dan instruksi kerja Set 1.00 2,000,000.00 2,000,000.00 0.20 - - 1.00 100.00 0.20 1.00 100.00 0.20
1.3 Penyiapan formulir
TOTAL PENYIAPAN RKK 2,000,000.00 0.20 - 0.20 0.20
2. SOSIALISASI, PROMOSI DAN PELATIHAN
2.1 Induksi K3 (Safety Induction) Org 5.00 7,500.00 37,500.00 0.00 - - 5.00 100.00 0.00 5.00 100.00 0.00
2.2 Pengarahan K3 (Safety Briefing) Org 5.00 15,000.00 75,000.00 0.01 - - 5.00 100.00 0.01 5.00 100.00 0.01
2.3 Pelatihan K3 - -
2.3.1 Bekerja di ketinggian Org 4.00 7,500.00 30,000.00 0.00 - - 4.00 100.00 0.00 4.00 100.00 0.00
2.3.2 Penggunaan Bahan Kimia (MSDS) Org 2.00 7,500.00 15,000.00 0.00 - - 2.00 100.00 0.00 2.00 100.00 0.00
2.4 Simulasi K3 Org 5.00 7,500.00 37,500.00 0.00 - - 5.00 100.00 0.00 5.00 100.00 0.00
2.5 Spanduk (Banner) Lb 1.00 150,000.00 150,000.00 0.02 - - 1.00 100.00 0.02 1.00 100.00 0.02
2.6 Poster 2 2.00 50,000.00 100,000.00 0.01 - - 2.00 100.00 0.01 2.00 100.00 0.01
2.7 Papan Informasi K3 1 1.00 500,000.00 500,000.00 0.05 - - 1.00 100.00 0.05 1.00 100.00 0.05
TOTAL SOSIALISASI, PROMOSI DAN PELATIHAN 945,000.00 0.10 - 0.10 0.10
3. ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI
3.1 APK
3.1.1 Tali Keselamatan (Life Line) Ls 1.00 1,700,000.00 1,700,000.00 0.17 - - 1.00 100.00 0.17 1.00 100.00 0.17
3.1.2 Pembatas Area (Restricted Area) Ls 1.00 2,000,000.00 2,000,000.00 0.20 - - 1.00 100.00 0.20 1.00 100.00 0.20
3.2 APD
3.2.1 Topi Pelindung (Safety Helmet) Bh 10.00 75,000.00 750,000.00 0.08 - - 10.00 100.00 0.08 10.00 100.00 0.08
3.2.2 Pelindung Mata (Googles, Spectacles) Bh 5.00 25,000.00 125,000.00 0.01 - - 5.00 100.00 0.01 5.00 100.00 0.01
3.2.3 Pelindung Pernapasan dan Mulut (Masker) Bh 100.00 5,000.00 500,000.00 0.05 - - 100.00 100.00 0.05 100.00 100.00 0.05
3.2.4 Sarung Tangan (Safety Gloves) Psg 10.00 15,000.00 150,000.00 0.02 - - 10.00 100.00 0.02 10.00 100.00 0.02
3.2.5 Sepatu Keselamatan (Safety Shoes) Psg 10.00 350,000.00 3,500,000.00 0.35 - - 10.00 100.00 0.35 10.00 100.00 0.35
3.2.6 Penunjang Seluruh Tubuh (Full Body Harness) Bh 2.00 500,000.00 1,000,000.00 0.10 - - 2.00 100.00 0.10 2.00 100.00 0.10
3.2.7 Rompi Keselamatan (Safety Vest) Bh 10.00 25,000.00 250,000.00 0.03 - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT % PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 9,975,000.00 1.01 - 0.98 0.98
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT % PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4. ASURANSI DAN PERIZINAN
4.1 Asuransi Ls 1.00 3,000,000.00 3,000,000.00 0.30 - - 1.00 100.00 0.30 1.00 100.00 0.30
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 3,000,000.00 0.30 - 0.30 0.30
5. PERSONEL K3 KONSTRUKSI
5.1 Ahli K3 Konstruksi -
5.2 Petugas K3 Konstruksi Ob 4.00 3,675,000.00 14,700,000.00 1.48 - - 4.00 100.00 1.48 4.00 100.00 1.48
TOTAL PERSONEL K3 KONSTRUKSI 14,700,000.00 1.48 - 1.48 1.48
6. FASILITAS, SARANA DAN PRASARANA KESEHATAN
6.1 Peralatan P3K (Kotak P3K, Tandu, Obat Luka, Perban, dll) Ls 1.00 500,000.00 500,000.00 0.05 - - 1.00 100.00 0.05 1.00 100.00 0.05
TOTAL FASILITAS, SARANA DAN PRASARANA KESEHATAN 500,000.00 0.05 - 0.05 0.05
7. RAMBU - RAMBU YANG DIPERLUKAN
7.1 Rambu Petunjuk bh 2.00 75,000.00 150,000.00 0.02 - - 2.00 100.00 0.02 2.00 100.00 0.02
7.2 Rambu Larangan bh 2.00 75,000.00 150,000.00 0.02 - - 2.00 100.00 0.02 2.00 100.00 0.02
7.3 Rambu Peringatan bh 2.00 100,000.00 200,000.00 0.02 - - 2.00 100.00 0.02 2.00 100.00 0.02
7.4 Jalur Evakuasi (Escape Route) Ls 1.00 250,000.00 250,000.00 0.03 - - 1.00 100.00 0.03 1.00 100.00 0.03
TOTAL RAMBU - RAMBU YANG DIPERLUKAN 750,000.00 0.08 - 0.08 0.08
8. KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI
8.1 Ahli K3 Konstruksi Oj -
TOTAL KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI
9. LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN
KONSTRUKSI
9.1 Alat Pemadam Api Ringan (APAR) bh 1.00 500,000.00 500,000.00 0.05 - - 1.00 100.00 0.05 1.00 100.00 0.05
9.2 Program Inspeksi Ls 1.00 1,500,000.00 1,500,000.00 0.15 - - 1.00 100.00 0.15 1.00 100.00 0.15
9.3 Pelaporan dan Penyeledikan Insiden Ls 1.00 500,000.00 500,000.00 0.05 - - 1.00 100.00 0.05 1.00 100.00 0.05
9.4 Pembuatan Kartu Identitas Pekerja (KIP) Org 10.00 5,000.00 50,000.00 0.01 - - 10.00 100.00 0.01 10.00 100.00 0.01
TOTAL LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN KONSTRUKSI 2,550,000.00 0.26 - 0.26 0.26

A Jumlah Harga Penawaran 989,944,870.91 100.00 - 6.26 6.26


B PPN (10%) 98,994,487.09
C Jumlah (A+B) 1,088,939,358.00
PERSENTASE SAMPAI MINGGU INI 6.26
D Jumlah Dibulatkan 1,088,939,358.00

Bulukumba, 22 Oktober 2020


Disetujui, Diketahui, Diperiksa Oleh, Dibuat Oleh,
Pejabat Pembuat Komitmen Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUTR Prov SulSel Dinas PUTR Prov SulSel CV.MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

A.KHADAFI HARUN, ST.,MT. L I L I, ST. IRHAM HARAHAP, ST. VIKA APRILIA DWI PUTRI
NIP. 19811126 200901 1 008 NIP. 19821229 201503 2 001 Site Engineer Direktris
LAPORAN KEMAJUAN MINGGUAN

Kegiatan : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba Minggu Ke : 01 ( Satu )
Satuan Kerja : Dinas Pekerjaan Umum Dan Tata Ruang Prov. Sulawesi Selatan Bidang Cipta Karya Periode :16 Oktober S/d 22 Oktober 2020
Lokasi : Desa Ara, Kecamatan Bonto Bahari, Kabupaten Bulukumba, Provinsi Sulawesi Selatan No. Kontrak : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
Sumber Dana : Dana Bantuan Provinsi Nilai Kontrak : Rp. 1,088,939,358.00
Tahun Anggaran : 2020 Schedule Pelaksanaan : 16 Oktober S/d 14 Desember 2020

MINGGU LALU MINGGU INI S/D MINGGU INI


VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
NO URAIAN PEKERJAAN
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q

A. PEMBANGUNAN RUANG KULINER, SOUVENIR, MUSHOLLAH DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Papan Proyek Ls 1.00 500,000.00 500,000.00 0.05 - - 1.00 100.00 0.05 1.00 100.00 0.05
1.2 Bedeng/Direksi Keet M2 5.50 1,512,555.00 8,319,052.50 0.84 - - 5.50 100.00 0.84 5.50 100.00 0.84

TOTAL PEKERJAAN PERSIAPAN 8,819,052.50 0.89 0.00 0.89 0.89

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Poerplat PP1 (Selasar Samping)
2.1.1.1 Galian Pondasi Poerplat < 1 m M3 0.32 73,837.50 23,628.00 0.00 - - 0.32 100.00 0.00 0.32 100.00 0.00
2.1.1.2 Urugan Pasir dibawah Pondasi Poerplat T.5 cm M3 0.04 148,335.00 5,933.40 0.00 - - 0.04 100.00 0.00 0.04 100.00 0.00
2.1.1.3 Urugan Tanah Kembali Pondasi Poerplat M3 0.31 54,175.00 16,794.25 0.00 - - 0.31 100.00 0.00 0.31 100.00 0.00
2.1.1.4 Pasangan Lantai Kerja bawah Pondasi Poerplat T.5 cm (Beton K300) M3 0.04 1,118,216.00 44,728.64 0.00 - - 0.04 100.00 0.00 0.04 100.00 0.00
2.1.1.5 Pondasi Poerplat 35x50 cm, T.20 cm
Beton Mutu F'c = 26,4 mpa (K300), Slump (12-2) cm, w/c = 0,52 M3 0.14 1,118,216.00 156,550.24 0.02 - - 0.14 100.00 0.02 0.14 100.00 0.02
Bekisting 2x Pakai M2 0.56 107,013.50 59,927.56 0.01 - - 0.56 100.00 0.01 0.56 100.00 0.01
Besi Beton Ø14 SNI Kg 29.40 21,464.85 631,066.59 0.06 - - 29.40 100.00 0.06 29.40 100.00 0.06
2.1.2 Pekerjaan Pondasi Batu Kali (Badan Bangunan, Mushollah) -
2.1.2.1 Galian Tanah Pondasi Batu Kali < 1 m M3 22.73 73,837.50 1,678,326.38 0.17 - - 22.73 100.00 0.17 22.73 100.00 0.17
2.1.2.2 Urugan Pasir dibawah Pondasi Batu Kali T.5 cm M3 1.08 148,335.00 160,201.80 0.02 - - 1.08 100.00 0.02 1.08 100.00 0.02
2.1.2.3 Pasangan Aanstamping bawah Pondasi Batu Kali T.10 M3 2.17 382,674.00 830,402.58 0.08 - - 2.17 100.00 0.08 2.17 100.00 0.08
2.1.2.4 Urugan Tanah Kembali Pondasi Batu Kali M3 10.39 54,175.00 562,878.25 0.06 - - 10.39 100.00 0.06 10.39 100.00 0.06
2.1.2.5 Pondasi Batu Kali 1 Sp : 3 Pp M3 9.09 827,447.50 7,521,497.78 0.76 - - 9.09 100.00 0.76 9.09 100.00 0.76
2.1.3 Pekerjaan Pondasi Rollage L.15 cm (Entrance, Selasar Samping) - -
2.1.3.1 Galian Tanah Pondasi Rollage < 1 m M3 2.23 73,837.50 164,657.63 0.02 - - - - - - -
2.1.3.2 Urugan Pasir dibawah Pondasi Rollage T.5 cm M3 0.45 148,335.00 66,750.75 0.01 - - - - - - -
2.1.3.3 Pasangan Lantai Kerja bawah Pondasi Rollage T.5 cm (Beton K300) M3 0.45 1,118,216.00 499,003.89 0.05 - - - - - - -
2.1.3.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp M2 20.83 128,436.00 2,675,321.88 0.27 - - - - - - -
2.2 Pekerjaan Sloef, Kolom dan Ringbalk -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Mushollah) -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 1.62 1,118,216.00 1,815,703.23 0.18 - - 1.62 100.00 0.18 1.62 100.00 0.18
2.2.1.2 Bekisting 2x Pakai M2 10.83 114,438.50 1,239,368.96 0.13 - - 10.83 100.00 0.13 10.83 100.00 0.13
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI Kg 280.09 21,464.85 6,012,089.84 0.61 - - 280.09 100.00 0.61 280.09 100.00 0.61
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan, Mushollah) -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.88 1,118,216.00 981,234.54 0.10 - - 0.88 100.00 0.10 0.88 100.00 0.10
2.2.2.2 Bekisting 2x Pakai M2 5.85 193,468.00 1,131,787.80 0.11 - - 5.85 100.00 0.11 5.85 100.00 0.11
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 181.66 21,464.85 3,899,347.58 0.39 - - 181.66 100.00 0.39 181.66 100.00 0.39
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Selasar, Westafel, Tempat Wudhu)
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 - - 0.17 50.00 0.02 0.17 50.00 0.02
2.2.3.2 Bekisting 2x Pakai M2 2.26 193,468.00 437,237.68 0.04 - - 1.13 50.00 0.02 1.13 50.00 0.02
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 70.10 21,464.85 1,504,686.30 0.15 - - 35.05 50.00 0.08 35.05 50.00 0.08
2.2.4 Pekerjaan Kolom K1 15 x 30 (Selasar Samping)
2.2.4.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.62 1,118,216.00 694,412.14 0.07 - - - - - - -
2.2.4.2 Bekisting 2x Pakai M2 6.21 193,468.00 1,201,436.28 0.12 - - - - - - -
2.2.4.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 99.69 21,464.85 2,139,830.90 0.22 - - - - - - -
2.2.5 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan, Mushollah)
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 2.08 1,008,161.00 2,097,478.96 0.21 - - - - - - -
2.2.5.2 Bekisting 2x Pakai M2 13.87 197,923.00 2,745,192.01 0.28 - - - - - - -
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 299.22 21,464.85 6,422,712.42 0.65 - - - - - - -
2.2.6 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan)
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 - - - - - - -
2.2.6.2 Bekisting 2x Pakai M2 2.24 197,923.00 443,347.52 0.04 - - - - - - -
2.2.6.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 48.32 21,464.85 1,037,181.55 0.10 - - - - - - -
2.2.7 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Mushollah, Pintu Jendela)
2.2.7.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.84 1,008,161.00 846,855.24 0.09 - - - - - - -
2.2.7.2 Bekisting 2x Pakai M2 5.59 197,923.00 1,106,389.57 0.11 - - - - - - -
2.2.7.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 115.53 21,464.85 2,479,834.12 0.25 - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.2.8 Pekerjaan Plat Beton (Selasar Samping, Westafel)
2.2.8.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.22 1,008,161.00 221,795.42 0.02 - - - - - - -
2.2.8.2 Bekisting 2x Pakai M2 2.21 237,468.00 524,804.28 0.05 - - - - - - -
2.2.8.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 54.54 21,464.85 1,170,692.92 0.12 - - - - - - -
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) M2 152.03 163,636.00 24,877,581.08 2.51 - - - - - - -
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4, Entrance) M2 42.24 242,170.50 10,229,281.92 1.03 - - - - - - -
2.5 Pekerjaan Tiang Atap Bitumen Gelombang (Besi Hollow Galvanis 5/10, Entrance) M' 20.40 178,365.00 3,638,646.00 0.37 - - - - - - -
2.6 Pekerjaan Rangka Plafond Kalsiboard (Besi Hollow Metal Galvalume 4/4) M2 147.40 102,837.17 15,158,198.37 1.53 - - - - - - -

TOTAL PEKERJAAN STRUKTUR 109,840,345.70 11.10 0.00 2.82 2.82

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) M3 8.54 148,335.00 1,266,780.90 0.13 - - - - - - -
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) M3 25.63 167,227.00 4,285,636.74 0.43 - - - - - - -
3.1.1.3 Rabat Beton bawah Lantai T.5 cm (Keseluruhan, Beton K300) M3 8.54 1,118,216.00 9,549,564.64 0.96 - - - - - - -
3.1.1.4 Penutup Lantai Keramik Motif 60x60 (Badan Bangunan, Mushollah) M2 62.94 403,309.50 25,384,299.93 2.56 - - - - - - -
3.1.1.5 Penutup Lantai Conwood Deck 6" (Entrance) M2 59.01 866,833.08 51,151,820.09 5.17 - - - - - - -
3.1.1.6 Penutup Lantai Andesit Polos 30x30 (Selasar, Tempat Wudhu, Ram) M2 51.05 232,589.50 11,873,693.98 1.20 - - - - - - -
3.1.1.7 Plint Lantai Keramik 10x60 (Badan Bangunan, Mushollah) M' 38.85 51,605.03 2,004,855.55 0.20 - - - - - - -
3.1.2 Pekerjaan Dinding
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Mushollah, 1 Sp : 4 Pp) M2 74.55 242,979.00 18,114,084.45 1.83 - - 44.73 60.00 1.10 44.73 60.00 1.10
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Selasar Samping, Tempat Wudhu) M2 5.14 65,550.32 336,928.64 0.03 - - - - - - -
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm (Badan Bangunan, Mushollah) M2 91.30 60,403.20 5,514,812.16 0.56 - - - - - - -
3.1.2.4 Plesteran Ciprat 1 Sp : 2 Pp Tebal 15 mm (Selasar Samping, Antar Kolom) M2 24.84 49,215.10 1,222,503.08 0.12 - - - - - - -
3.1.2.5 Dinding Keramik Mozaik 30x60 (Selasar Samping, Westafel, Tempat Wudhu) M2 18.44 410,432.00 7,568,366.08 0.76 - - - - - - -
3.1.2.6 Coating Bening (Badan Bangunan, Mushollah, Kolom Luar) M2 127.49 45,973.13 5,861,113.71 0.59 - - - - - - -
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) M2 8.64 995,043.50 8,597,175.84 0.87 - - - - - - -
3.1.2.8 Dinding Wallpaper Bata L.50 cm (Sisi Dalam) M2 28.13 80,005.50 2,250,554.72 0.23 - - - - - - -
3.1.3 Pekerjaan Plafond
3.1.3.1 Plafond Kalsiboard (Badan Bangunan, Kemiringan Atap, Mushollah) M2 147.40 44,924.00 6,621,797.60 0.67 - - - - - - -
3.1.3.2 Plafond Kalsiboard (Lapis Bawah Atap, Entrance) M2 42.24 44,924.00 1,897,589.76 0.19 - - - - - - -
3.2 Pekerjaan Pintu dan Jendela (Badan Bangunan)
3.2.1 Pintu P1 (Entrance dan Back Entrance, Badan Bangunan)
3.2.1.1 Pasangan Kusen Alumunium Coating P1 (4" x 1 3/4") cm M' 22.40 157,194.40 3,521,154.56 0.36 - - - - - - -
3.2.1.2 Pasangan Daun Pintu P1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - -
3.2.1.3 Pasangan Kaca Mati 5 mm P1 M2 11.20 145,703.80 1,631,882.56 0.16 - - - - - - -
3.2.1.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - -
3.2.1.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - -
3.2.1.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - -
3.2.1.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - -
3.2.2 Jendela J1 (Badan Bangunan)
3.2.2.1 Pasangan Kusen Alumunium Coating J1 (4" x 1 3/4") cm M' 40.60 157,194.40 6,382,092.64 0.64 - - - - - - -
3.2.2.2 Pasangan Kaca Mati 5 mm J1 M2 8.00 145,703.80 1,165,630.40 0.12 - - - - - - -
3.2.3 Pintu PJ1 (Mushollah)
3.2.3.1 Pasangan Kusen Alumunium Coating PJ1 (4" x 1 3/4") cm M' 22.20 157,194.40 3,489,715.68 0.35 - - - - - - -
3.2.3.2 Pasangan Daun Pintu PJ1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - -
3.2.3.3 Pasangan Kaca Mati 5 mm P1 M2 8.70 145,703.80 1,267,623.06 0.13 - - - - - - -
3.2.3.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - -
3.2.3.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - -
3.2.3.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - -
3.2.3.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - -
3.3 Pekerjaan Pengecatan
3.3.1 Pengecatan Plafond (1 Plamir ; 1 Cat Dasar : 2 Cat Penutup), (Interior) M2 189.64 35,536.05 6,739,056.52 0.68 - - - - - - -
3.3.2 Pengecatan Rangka Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 23.76 168,454.00 4,002,467.04 0.40 - - - - - - -
3.3.3 Pengecatan Tiang Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 6.12 168,454.00 1,030,938.48 0.10 - - - - - - -
3.4 Pekerjaan Atap
3.4.1 Atap Bitumen Gelombang (Badan Bangunan, Mushollah) M2 152.03 207,297.09 31,515,376.59 3.18 - - - - - - -
3.4.2 Atap Bitumen Gelombang (Entrance) M2 42.24 207,297.09 8,756,229.08 0.88 - - - - - - -
3.4.3 Nok Bitumen (Badan Bangunan, Mushollah) M' 14.55 134,101.00 1,951,169.55 0.20 - - - - - - -
3.4.4 Listplank (Kalsiplank, Badan Bangunan, Mushollah, Entrance) M' 50.00 70,950.00 3,547,500.00 0.36 - - - - - - -

TOTAL PEKERJAAN FINISHING ARSITEKTUR 257,222,142.77 25.98 0.00 1.10 1.10

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel Bh 1.00 1,572,826.75 1,572,826.75 0.16 - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt Bh 16.00 353,938.75 5,663,020.00 0.57 - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4.1.3 Pasangan Lampu Down Light 2,5" Outbow LED 5,5 Watt Bh 11.00 305,538.75 3,360,926.25 0.34 - - - - - - -
4.1.4 Pasangan Saklar Tunggal Bh 4.00 211,378.75 845,515.00 0.09 - - - - - - -
4.1.5 Pasangan Saklar Ganda Bh 2.00 223,478.75 446,957.50 0.05 - - - - - - -
4.2 Pasangan Instalasi Stop Kontak -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA Bh 10.00 216,218.75 2,162,187.50 0.22 - - - - - - -
4.2.2 Pasangan Stop Kontak AC 220 VA/3520 W (AC Split 1 PK) Bh 4.00 253,728.75 1,014,915.00 0.10 - - - - - - -
4.3 Pasangan Instalasi Jaringan AC M' 30.00 108,772.68 3,263,180.25 0.33 - - - - - - -
4.3.1 Pasangan AC Split 1 PK Bh 3.00 3,365,799.34 10,097,398.03 1.02 - - - - - - -
4.4 Pasangan Penangkal Petir Ls 1.00 2,500,000.00 2,500,000.00 0.25 - - - - - - -
4.5 Pasangan Instalasi Jaringan Kabel Fiber Optic (CCTV) Ttk 6.00 786,326.75 4,717,960.50 0.48 - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2MP Bh 6.00 656,975.00 3,941,850.00 0.40 - - - - - - -
4.5.2 Pasangan NVR Channel Set 1.00 5,023,975.00 5,023,975.00 0.51 - - - - - - -
4.5.3 Pasangan Monitor LCD 32" Bh 1.00 2,944,975.00 2,944,975.00 0.30 - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm M' 12.00 20,442.68 245,312.10 0.02 - - - - - - -
4.6.1 Pasangan Horn Speaker Bh 6.00 494,826.75 2,968,960.50 0.30 - - - - - - -
4.6.2 Pasangan Volume Kontrol Set 1.00 252,826.75 252,826.75 0.03 - - - - - - -
4.6.3 Pasangan Perangkat Sound System Set 1.00 4,565,000.00 4,565,000.00 0.46 - - - - - - -
4.6.4 Pasangan TB-Sound System Set 1.00 5,846,326.75 5,846,326.75 0.59 - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25Kg) Ttk 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - -
4.8 Pasangan Instalasi Jaringan Kabel Fiber Optic (Akses Point) Ttk 3.00 786,326.75 2,358,980.25 0.24 - - - - - - -
4.8.1 Pasangan Server Set 1.00 7,578,826.75 7,578,826.75 0.77 - - - - - - -
4.8.2 Pasangan Akses Point Bh 1.00 2,034,826.75 2,034,826.75 0.21 - - - - - - -
4.8.3 Pasangan Switch HUB Bh 1.00 2,843,326.75 2,843,326.75 0.29 - - - - - - -
4.9 Pasangan Instalasi PLN Power (Inc. Jalur ke Mushollah dan Toilet) Ls 1.00 9,000,000.00 9,000,000.00 0.91 - - - - - - -

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 94,450,073.38 9.54 0.00 0.00 0.00

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVC Type AW Diameter 3/4" (Air Bersih Sambungan dari Tandon) M' 33.00 28,300.25 933,908.25 0.09 - - - - - - -
5.2 Pipa PVC Type AW Diameter 3" (Air Kotor ke Drainase Lingkungan) M' 25.80 135,531.00 3,496,699.80 0.35 - - - - - - -
5.3 Pasangan 1 Bh Wastafel Bh 2.00 3,934,865.00 7,869,730.00 0.79 - - - - - - -
5.4 Pasangan 1 Bh Wastafel Cuci Piring (WCP) Bh 1.00 890,945.00 890,945.00 0.09 - - - - - - -
5.5 Pasangan 1 Bh Floor Drain Bh 2.00 41,112.50 82,225.00 0.01 - - - - - - -
5.6 Pasangan 1 Bh Kran Dia. 1/2" atau 3/4" Bh 10.00 102,217.50 1,022,175.00 0.10 - - - - - - -
5.7 Pasangan 1 Bh Kran Wastafel Dia. 1/2" atau 3/4" Bh 3.00 335,417.50 1,006,252.50 0.10 - - - - - - -
5.8 Pasangan 1 Bh Stop Kran (Gate Valve) Dia. 3/4" Bh 1.00 141,417.50 141,417.50 0.01 - - - - - - -
5.9 Pasangan Mesin Air Bh 1.00 741,000.00 741,000.00 0.07 - - - - - - -
5.10 Menara Reservoir 200x150x350 cm -
5.10.1 Pekerjaan Pondasi Pedestal Pd1 -
5.10.1.1 Galian Tanah Pondasi Poerplat < 1 m M3 1.62 73,837.50 119,616.75 0.01 - - - - - - -
5.10.1.2 Urugan Tanah Kembali Pondasi Poerplat M3 0.43 54,175.00 23,295.25 0.00 - - - - - - -
5.10.1.3 Tiang Pondasi Pedestal 50x50 cm - -
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.80 1,118,216.00 894,572.80 0.09 - - - - - - -
Bekisting 2x Pakai M2 3.20 193,468.00 619,097.60 0.06 - - - - - - -
Besi Beton Ø12 SNI, Ø8 SNI Kg 49.44 21,464.85 1,061,130.60 0.11 - - - - - - -
5.10.1.4 Pondasi Poerplat 90x90 cm, T.20 cm
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.65 1,118,216.00 726,840.40 0.07 - - - - - - -
Bekisting 2x Pakai M2 1.44 107,013.50 154,099.44 0.02 - - - - - - -
Besi Beton Ø14 SNI Kg 214.35 21,464.85 4,600,940.54 0.46 - - - - - - -
5.10.2 Rangka Tengah dan Lantai Menara (Besi Hollow Galvanis 4/4) M2 34.82 244,970.00 8,529,855.40 0.86 - - - - - - -
5.10.3 Rangka Utama Menara (Besi Hollow Galvanis 5/10) M' 32.28 179,454.00 5,792,775.12 0.59 - - - - - - -
5.10.4 Plat Baja Lantai Menara T.3 mm M2 3.00 740,164.86 2,220,494.57 0.22 - - - - - - -
5.10.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) M2 5.00 244,970.00 1,224,850.00 0.12 - - - - - - -

TOTAL PEKERJAAN PLAMBING DAN SANITASI 42,151,921.52 4.26 0.00 0.00 0.00

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Pek. Pembersian Awal m2 81.86 17,600.00 1,440,780.00 0.15 - - - - - - -
1.2 Pek. Pengukuran & Pemasangan Bouwplank m1 48.60 106,461.25 5,174,016.75 0.52 - - - - - - -

TOTAL PEKERJAAN PERSIAPAN 6,614,796.75 0.67 0.00 0.00 0.00

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Batu Kali (Badan Bangunan,Ruang Bilas)
2.1.1.1 Galian Pondasi Batu Kali < 1 m m3 22.05 73,892.50 1,629,329.63 0.16 - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.1.1.2 Urugan Pasir Dibawah Pondasi Batu Kali T.5 cm m3 1.05 174,757.00 183,494.85 0.02 - - - - - - -
2.1.1.3 Pasangan Aanstamping Bawah Pondasi Batu Kali T.10 cm m3 2.10 392,699.70 824,669.37 0.08 - - - - - - -
2.1.1.4 Urugan Tanah Kembali Pondasi Batu Kali m3 10.08 54,285.00 547,192.80 0.06 - - - - - - -
2.1.1.5 Pondasi Batu Kali 1 Sp : 3 Pp m3 8.82 824,945.00 7,276,014.90 0.73 - - - - - - -
2.1.2 Perjaan Pondasi Rollage L.15 cm (Selasar) -
2.1.2.1 Galian Tanah Pondasi Rollage < 1 m m3 1.52 73,892.50 112,501.33 0.01 - - - - - - -
2.1.2.2 Urugan Pasir Dibawah Pondasi Rollage T.5 cm m3 0.30 174,757.00 53,213.51 0.01 - - - - - - -
2.1.2.3 Pasangan Lantai Kerja Bawah Pondasi Rollage T.5 cm (Beton K300) m3 0.30 1,118,398.60 340,552.37 0.03 - - - - - - -
2.1.2.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp m3 14.21 128,260.00 1,822,574.60 0.18 - - - - - - -
2.2 Pekerjaan Sloef, Kolom, Plat dan Ringbalk -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Ruang Bilas) -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 m3 1.41 1,118,398.60 1,580,297.22 0.16 - - - - - - -
2.2.1.2 Bekisting 2x Pakai m2 9.42 114,467.10 1,078,280.08 0.11 - - - - - - -
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI kg 243.74 21,465.73 5,232,043.29 0.53 - - - - - - -
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan) -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slum (12 - 2) cm, w/c = 0,52 m3 0.48 1,118,398.60 533,476.13 0.05 - - - - - - -
2.2.2.2 Bekisting 2x Pakai m2 3.18 193,504.30 615,343.67 0.06 - - - - - - -
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI kg 98.75 21,465.73 2,119,732.25 0.21 - - - - - - -
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Ruang Bilas) -
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.25 1,008,343.60 249,111.29 0.03 - - - - - - -
2.2.3.2 Bekisting 2x Pakai m2 1.65 193,504.30 318,701.58 0.03 - - - - - - -
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI kg 51.14 21,465.73 1,097,861.33 0.11 - - - - - - -
2.2.4 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan) -
2.2.4.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.04 1,008,343.60 1,043,635.63 0.11 - - - - - - -
2.2.4.2 Bekisting 2x Pakai m2 6.90 197,959.30 1,365,919.17 0.14 - - - - - - -
2.2.4.3 Besi Beton Ø12 SNI, Ø6 SNI kg 148.86 21,465.73 3,195,302.68 0.32 - - - - - - -
2.2.5 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan) -
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.09 1,008,343.60 1,103,531.24 0.11 - - - - - - -
2.2.5.2 Bekisting 2x Pakai m2 14.59 197,959.30 2,888,622.11 0.29 - - - - - - -
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI kg 157.40 21,465.73 3,378,705.12 0.34 - - - - - - -
2.2.6 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Pintu Jendela)
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.15 1,008,343.60 148,831.52 0.02 - - - - - - -
2.2.6.2 Bekisting 2x Pakai m2 0.98 197,959.30 194,791.95 0.02 - - - - - - -
2.2.6.3 Besi Beton Ø10 SNI, Ø6 SNI kg 20.35 21,465.73 436,752.39 0.04 - - - - - - -
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) m2 59.01 163,856.00 9,669,142.56 0.98 - - - - - - -
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4) m2 48.59 102,876.77 4,998,782.09 0.50 - - - - - - -
2.5 Pekerjaan Rangka Plafond dan Dinding Dalam PVC Shunda (Besi Hollow Metal Galvalume 4/4) m2 56.16 102,876.77 5,777,559.22 0.58 - - - - - - -

TOTAL PEKERJAAN STRUKTUR 59,815,965.86 6.04 0.00 0.00 0.00

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) m3 4.09 174,757.00 715,280.40 0.07 - - - - - - -
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) m3 12.28 167,345.00 2,054,804.70 0.21 - - - - - - -
3.1.1.3 Rabat Beton T.5 cm (Keseluruhan, Beton K300) m3 4.09 1,118,398.60 4,577,605.47 0.46 - - - - - - -
3.1.1.4 Penutup Lantai Keramik Tekstur 60x60 (Badan Bangunan) m2 36.93 413,098.40 15,255,723.91 1.54 - - - - - - -
3.1.1.5 Penutup Lantai Andesit Polos 30x30 (Selasar, Ruang Bilas) m2 45.89 284,369.80 13,049,730.12 1.32 - - - - - - -
3.1.1.6 Penutup Plat Wastafel (Granit 60x60, Toilet Pria dan Wanita) m2 2.20 841,621.73 1,851,567.81 0.19 - - - - - - -
3.1.2 Pekerjaan Dinding -
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Selasar, 1 Sp : 4 Pp) 90.64 242,533.50 21,983,236.44 2.22 - - - - - - -
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Wc ) 30.00 65,473.32 1,964,199.60 0.20 - - - - - - -
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm 121.28 60,304.20 7,313,693.38 0.74 - - - - - - -
3.1.2.4 Coating Bening 121.28 46,853.13 5,682,347.00 0.57 - - - - - - -
3.1.2.5 Dinding Andesit Polos 30x30 cm ( Wc, Ruang Bilas ) 56.52 284,369.80 16,072,581.10 1.62 - - - - - - -
3.1.2.6 Dinding Keramik 30x60 cm ( Sisi Dalam ) 69.88 370,557.00 25,894,523.16 2.62 - - - - - - -
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) 9.00 995,076.50 8,955,688.50 0.90 - - - - - - -
3.1.2.8 Cubicle Panel + Accessories (Pintu Wc dan Partisi Urinoir) 10.86 1,360,000.00 14,769,600.00 1.49 - - - - - - -
3.1.2.9 Dinding Bitumen Gelombang 48.59 201,749.24 9,802,995.57 0.99 - - - - - - -
3.1.2.10 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Pria) 1.00 1,200,000.00 1,200,000.00 0.12 - - - - - - -
3.1.2.11 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Wanita) 1.00 750,000.00 750,000.00 0.08 - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.1.3 Plafond dan Dinding Dalam Shunda ( Badan Bangunan ) 56.16 125,878.50 7,069,336.56 0.71 - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.2 Pekerjaan Pintu dan Jendela ( Badan Bangunan ) -
3.2.1 Pintu P1 -
3.2.1.1 Pasangan Kusen Almunium Coating P1 (4" x 13/4") cm 10.96 157,199.02 1,722,901.26 0.17 - - - - - - -
3.2.1.2 Pasangan Daun Pintu P1 (Panel Almunium Coating - Coating) 4.30 870,323.19 3,742,389.72 0.38 - - - - - - -
3.2.1.3 Pasangan Kunci Tanam 2x Slag P1 2.00 416,663.50 833,327.00 0.08 - - - - - - -
3.2.1.4 Pasangan ensel P1 6.00 61,225.56 367,353.36 0.04 - - - - - - -
3.2.1.5 Pasangan Doorcloser P1 2.00 241,902.10 483,804.20 0.05 - - - - - - -
3.2.1.6 Pasangan Handle P1 2.00 229,802.10 459,604.20 0.05 - - - - - - -
3.2.2 Jendela J1 -
3.2.2.1 Pasangan Kusen Almunium Coating J1 (4" x 13/4") cm 28.80 157,199.02 4,527,331.78 0.46 - - - - - - -
3.2.2.2 Pasangan Kaca Mati 5 mm J1 0.60 145,705.56 87,423.34 0.01 - - - - - - -
3.2.3 Jendela J2 - -
3.2.3.1 Pasangan Kusen Almunium Coating J2 (4" x 13/4") cm 55.20 157,199.02 8,677,385.90 0.88 - - - - - - -
3.2.3.2 Pasangan Kaca Mati 5 mm J2 0.90 145,705.56 131,135.00 0.01 - - - - - - -
3.3. Pengecetan Plafond (1 Plamir : 1 Cat Dasar : 2 Cat Penutup), (Interior) 56.16 43,550.65 2,445,804.50 0.25 - - - - - - -
3.4 Pekerjaan Atap -
3.4.1 Atap Bitumen Gelombang (Badan Bangunan) 59.01 201,749.24 11,905,222.65 1.20 - - - - - - -
3.4.2 Nok Bitumen (Badan Bangunan) 35.25 143,629.20 5,062,929.30 0.51 - - - - - - -
3.4.3 Listplank (Kasiplank, Badan Bangunan, Enterance) 39.08 70,972.00 2,773,585.76 0.28 - - - - - - -

TOTAL PEKERJAAN FINISHING ARSITEKTUR 202,183,111.69 20.42 0.00 0.00 0.00

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel 1.00 1,803,826.75 1,803,826.75 0.18 - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt 10.00 353,938.75 3,539,387.50 0.36 - - - - - - -
4.1.3 Pasangan Lampu Down Light 2.5" Outbow LED 5.5 Watt 12.00 305,538.75 3,666,465.00 0.37 - - - - - - -
4.1.4 Pasangan Saklar Ganda 5.00 223,478.75 1,117,393.75 0.11 - - - - - - -
4.2 Pasangan Instalasi Stop Kontak -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA 3.00 216,218.75 648,656.25 0.07 - - - - - - -
4.2.2 Pasangan Stop Kontak Wall Exhauser 6.00 216,218.75 1,297,312.50 0.13 - - - - - - -
4.3 Pasangan Instalasi Jaringan Wall Exhauser 12.00 108,772.68 1,305,272.10 0.13 - - - - - - -
4.3.1 Pasangan Wall Exhauser 12 Inch - FV30RUN 6.00 513,500.00 3,081,000.00 0.31 - - - - - - -
4.4 Pasangan Penangkal Petir 1.00 3,500,000.00 3,500,000.00 0.35 - - - - - - -
4.5 Pasangan Instlasi Jaringan Kabel Fiber Optic (CCTV) 3.00 786,326.75 2,358,980.25 0.24 - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2 MP (Luar Bangunan, Sambungan Dari Mini Resto) 3.00 656,975.00 1,970,925.00 0.20 - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm 4.00 20,442.68 81,770.70 0.01 - - - - - - -
4.6.1 Pasangan Horn Speaker (Sambungan Dari Mini Resto) 2.00 494,826.75 989,653.50 0.10 - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25 kg) 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - -
4.8 Pasangan Instalasi PLN Power 1.00 10,000,000.00 10,000,000.00 1.01 - - - - - - -

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 44,560,643.30 4.50 0.00 0.00 0.00

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVc Tipe AW Diameter 3/4" (Air Bersih Dari Sumur Bor / PDAM Reservoir) m1 18.50 28,304.65 523,636.03 0.05 - - - - - - -
5.2 Pipa PVC Tipe AW Diameter 3/4" (Distribusi Air Bersih Dari Reservoir) m1 26.50 28,304.65 750,073.23 0.08 - - - - - - -
5.3 Pipa PVC Tipe AW Diameter 3" (Air Kotor Ke Drainase Lingkungan) m1 23.00 135,539.80 3,117,415.40 0.31 - - - - - - -
5.4 Pipa PVC Tipe AW Diameter 4" (Disposal) m1 18.00 186,689.80 3,360,416.40 0.34 - - - - - - -
5.5 Pasangan 1 bh Closet Duduk / Monoblock (TOTO) bh 6.00 3,655,597.00 21,933,582.00 2.22 - - - - - - -
5.6 Pasangan 1 bh Wastafel (TOTO) 3.00 3,571,942.00 10,715,826.00 1.08 - - - - - - -
5.7 Pasangan 1 bh Uninoir (TOTO) 2.00 6,665,285.00 13,330,570.00 1.35 - - - - - - -
5.8 Pasangan 1 bh Floor Drain 9.00 41,123.50 370,111.50 0.04 - - - - - - -
5.9 Pasangan 1 bh Kran dia. 1/2' atau 3/4" 8.00 102,228.50 817,828.00 0.08 - - - - - - -
5.10 Pasangan 1 bh Kran wastafel dia. 1/2' atau 3/4" 2.00 335,428.50 670,857.00 0.07 - - - - - - -
5.11 Pasangan 1 bh shower closet dia. 1/2' atau 3/4" 6.00 142,928.50 857,571.00 0.09 - - - - - - -
5.12 Pasangan 1 bh shower Wall dia. 1/2' atau 3/4" (Ruang Bilas) 4.00 1,435,428.50 5,741,714.00 0.58 - - - - - - -
5.13 Pasangan 1 bh Stop Kran (Gate Valve) dia. 3/4" 2.00 141,428.50 282,857.00 0.03 - - - - - - -
5.14 Pasangan Mesin Air 1.00 741,000.00 741,000.00 0.07 - - - - - - -
5.14b Pasangan Mesin Pemanas Air 1.00 5,000,000.00 5,000,000.00 0.51 - - - - - - -
5.15 Septictank Biotank Kap. 4m3 1.00 20,380,000.00 20,380,000.00 2.06 - - - - - - -
5.16 Pasangan Sumur Bor Jet Pump 30.00 350,000.00 10,500,000.00 1.06 - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.17 Reservoir 1200 Liter 1.00 1,850,000.00 1,850,000.00 0.19 - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.18 Reservoir 200x150x350 cm
5.18.1 Pekerjaan Pondasi Pedestal Pd1
5.18.1.1 Galian Tanah Pondasi Poerplat < 1m 1.62 74,250.00 120,285.00 0.01 - - - - - - -
5.18.1.2 Urugan Tanah Kembali Pondasi Poerplat 0.43 55,000.00 23,760.00 0.00 - - - - - - -
5.18.1.3 Tiang Pondasi Pedestal 50x50 cm
Beton Mutu fc = 26,6 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.80 1,485,144.21 1,188,115.37 0.12 - - - - - - -
Bekisting 2x Pakai 3.20 193,504.30 619,213.76 0.06 - - - - - - -
Besi Beton Ø12, Ø8 49.44 21,465.73 1,061,174.10 0.11 - - - - - - -
5.18.1.4 Pondasi Poerplat 90x90 cm,T.20 cm
Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.65 1,485,144.21 962,373.45 0.10 - - - - - - -
Bekisting 2x Pakai 1.44 124,547.50 179,348.40 0.02 - - - - - - -
Besi Beton Ø14 SNI 214.35 21,465.73 4,601,114.73 0.46 - - - - - - -
5.18.2 Rangkai Tengah Dan Lantai Menara (Besi Hollow Galvanis 4/4) 34.82 244,970.00 8,529,855.40 0.86 - - - - - - -
5.18.3 Rangka Utama menara ( Besi Hollow Galvanis 5/10 32.28 179,454.00 5,792,775.12 0.59 - - - - - - -
5.18.4 Tplat Baja Lantai Menara T.3mm 3.00 740,164.86 2,220,494.57 0.22 - - - - - - -
5.18.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) 5.00 244,970.00 1,224,850.00 0.12 - - - - - - -

TOTAL PEKERJAAN PLAMBING DAN SANITASI 127,466,817.45 12.88 - - -

6. PEKERJAAN AKHIR - - -
6.1 Pembersihan Sisa Pekerjaan Ls 1.00 2,400,000.00 2,400,000.00 0.24 - - - - - - -

TOTAL PEKERJAAN AKHIR 2,400,000.00 0.24 0.00 0.00 0.00

C. PENERAPAN SMKK

1. PENYIAPAN RKK
1.1 Pembuatan Dokumen Rencana Keselamatan Konstruksi
1.2 Pembuatan Prosedur dan instruksi kerja Set 1.00 2,000,000.00 2,000,000.00 0.20 - - 1.00 100.00 0.20 1.00 100.00 0.20
1.3 Penyiapan formulir
TOTAL PENYIAPAN RKK 2,000,000.00 0.20 - 0.20 0.20
2. SOSIALISASI, PROMOSI DAN PELATIHAN
2.1 Induksi K3 (Safety Induction) Org 5.00 7,500.00 37,500.00 0.00 - - 0.50 10.00 0.00 0.50 10.00 0.00
2.2 Pengarahan K3 (Safety Briefing) Org 5.00 15,000.00 75,000.00 0.01 - - 5.00 100.00 0.01 5.00 100.00 0.01
2.3 Pelatihan K3 -
2.3.1 Bekerja di ketinggian Org 4.00 7,500.00 30,000.00 0.00 - - 4.00 100.00 0.00 4.00 100.00 0.00
2.3.2 Penggunaan Bahan Kimia (MSDS) Org 2.00 7,500.00 15,000.00 0.00 - - 2.00 100.00 0.00 2.00 100.00 0.00
2.4 Simulasi K3 Org 5.00 7,500.00 37,500.00 0.00 - - 5.00 100.00 0.00 5.00 100.00 0.00
2.5 Spanduk (Banner) Lb 1.00 150,000.00 150,000.00 0.02 - - 1.00 100.00 0.02 1.00 100.00 0.02
2.6 Poster 2 2.00 50,000.00 100,000.00 0.01 - - 2.00 100.00 0.01 2.00 100.00 0.01
2.7 Papan Informasi K3 1 1.00 500,000.00 500,000.00 0.05 - - 1.00 100.00 0.05 1.00 100.00 0.05
TOTAL SOSIALISASI, PROMOSI DAN PELATIHAN 945,000.00 0.10 - 0.09 0.09
3. ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI
3.1 APK
3.1.1 Tali Keselamatan (Life Line) Ls 1.00 1,700,000.00 1,700,000.00 0.17 - - 1.00 100.00 0.17 1.00 100.00 0.17
3.1.2 Pembatas Area (Restricted Area) Ls 1.00 2,000,000.00 2,000,000.00 0.20 - - 1.00 100.00 0.20 1.00 100.00 0.20
3.2 APD
3.2.1 Topi Pelindung (Safety Helmet) Bh 10.00 75,000.00 750,000.00 0.08 - - 10.00 100.00 0.08 10.00 100.00 0.08
3.2.2 Pelindung Mata (Googles, Spectacles) Bh 5.00 25,000.00 125,000.00 0.01 - - 5.00 100.00 0.01 5.00 100.00 0.01
3.2.3 Pelindung Pernapasan dan Mulut (Masker) Bh 100.00 5,000.00 500,000.00 0.05 - - 100.00 100.00 0.05 100.00 100.00 0.05
3.2.4 Sarung Tangan (Safety Gloves) Psg 10.00 15,000.00 150,000.00 0.02 - - 10.00 100.00 0.02 10.00 100.00 0.02
3.2.5 Sepatu Keselamatan (Safety Shoes) Psg 10.00 350,000.00 3,500,000.00 0.35 - - 10.00 100.00 0.35 10.00 100.00 0.35
3.2.6 Penunjang Seluruh Tubuh (Full Body Harness) Bh 2.00 500,000.00 1,000,000.00 0.10 - - 2.00 100.00 0.10 2.00 100.00 0.10
3.2.7 Rompi Keselamatan (Safety Vest) Bh 10.00 25,000.00 250,000.00 0.03 - - 10.00 100.00 0.03 10.00 100.00 0.03
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 9,975,000.00 1.01 - 1.01 1.01
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4. ASURANSI DAN PERIZINAN
4.1 Asuransi Ls 1.00 3,000,000.00 3,000,000.00 0.30 - - - - - - -
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 3,000,000.00 0.30 - - -
5. PERSONEL K3 KONSTRUKSI
5.1 Ahli K3 Konstruksi -
5.2 Petugas K3 Konstruksi Ob 4.00 3,675,000.00 14,700,000.00 1.48 - - - - - - -
TOTAL PERSONEL K3 KONSTRUKSI 14,700,000.00 1.48 - - -
6. FASILITAS, SARANA DAN PRASARANA KESEHATAN
6.1 Peralatan P3K (Kotak P3K, Tandu, Obat Luka, Perban, dll) Ls 1.00 500,000.00 500,000.00 0.05 - - - - - - -
TOTAL FASILITAS, SARANA DAN PRASARANA KESEHATAN 500,000.00 0.05 - - -
7. RAMBU - RAMBU YANG DIPERLUKAN
7.1 Rambu Petunjuk bh 2.00 75,000.00 150,000.00 0.02 - - - - - - -
7.2 Rambu Larangan bh 2.00 75,000.00 150,000.00 0.02 - - - - - - -
7.3 Rambu Peringatan bh 2.00 100,000.00 200,000.00 0.02 - - - - - - -
7.4 Jalur Evakuasi (Escape Route) Ls 1.00 250,000.00 250,000.00 0.03 - - - - - - -
TOTAL RAMBU - RAMBU YANG DIPERLUKAN 750,000.00 0.08 - - -
8. KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI
8.1 Ahli K3 Konstruksi Oj -
TOTAL KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI - 0.00
9. LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN
KONSTRUKSI
9.1 Alat Pemadam Api Ringan (APAR) bh 1.00 500,000.00 500,000.00 0.05 - - - - - - -
9.2 Program Inspeksi Ls 1.00 1,500,000.00 1,500,000.00 0.15 - - - - - - -
9.3 Pelaporan dan Penyeledikan Insiden Ls 1.00 500,000.00 500,000.00 0.05 - - - - - - -
9.4 Pembuatan Kartu Identitas Pekerja (KIP) Org 10.00 5,000.00 50,000.00 0.01 - - - - - - -
TOTAL LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN KONSTRUKSI 2,550,000.00 0.26 - - -

A Jumlah Harga Penawaran 989,944,870.91 100.00 - 6.11 6.11


B PPN (10%) 98,994,487.09
C Jumlah (A+B) 1,088,939,358.00
PERSENTASE SAMPAI MINGGU INI 6.11
D Jumlah Dibulatkan 1,088,939,358.00

Bulukumba, 29 Oktober 2020


Disetujui, Diketahui, Diperiksa Oleh, Dibuat Oleh,
Pejabat Pembuat Komitmen Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUTR Prov SulSel Dinas PUTR Prov SulSel CV.MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

A.KHADAFI HARUN, ST.,MT. L I L I, ST. IRHAM HARAHAP, ST. VIKA APRILIA DWI PUTRI
NIP. 19811126 200901 1 008 NIP. 19821229 201503 2 001 Site Engineer Direktris
LAPORAN KEMAJUAN MINGGUAN

Kegiatan : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba Minggu Ke : 02 ( Dua )
Satuan Kerja : Dinas Pekerjaan Umum Dan Tata Ruang Prov. Sulawesi Selatan Bidang Cipta Karya Periode : 23 Oktober S/d 29 Oktober 2020
Lokasi : Desa Ara, Kecamatan Bonto Bahari, Kabupaten Bulukumba, Provinsi Sulawesi Selatan No. Kontrak : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
Sumber Dana : Dana Bantuan Provinsi Nilai Kontrak : Rp. 1,088,939,358.00
Tahun Anggaran : 2020 Schedule Pelaksanaan : 16 Oktober S/d 14 Desember 2020

MINGGU LALU MINGGU INI S/D MINGGU INI


VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
NO URAIAN PEKERJAAN
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q

A. PEMBANGUNAN RUANG KULINER, SUVENIR, MUSHOLLAH DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Papan Proyek Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
1.2 Bedeng/Direksi Keet M2 5.50 1,512,555.00 8,319,052.50 0.84 5.50 100.00 0.84 - - 5.50 100.00 0.84

TOTAL PEKERJAAN PERSIAPAN 8,819,052.50 0.89 0.89 0.00 0.89

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Poerplat PP1 (Selasar Samping)
2.1.1.1 Galian Pondasi Poerplat < 1 m M3 0.32 73,837.50 23,628.00 0.00 0.32 100.00 0.00 - - 0.32 100.00 0.00
2.1.1.2 Urugan Pasir dibawah Pondasi Poerplat T.5 cm M3 0.04 148,335.00 5,933.40 0.00 0.04 100.00 0.00 - - 0.04 100.00 0.00
2.1.1.3 Urugan Tanah Kembali Pondasi Poerplat M3 0.31 54,175.00 16,794.25 0.00 0.31 100.00 0.00 - - 0.31 100.00 0.00
2.1.1.4 Pasangan Lantai Kerja bawah Pondasi Poerplat T.5 cm (Beton K300) M3 0.04 1,118,216.00 44,728.64 0.00 0.04 100.00 0.00 - - 0.04 100.00 0.00
2.1.1.5 Pondasi Poerplat 35x50 cm, T.20 cm -
Beton Mutu F'c = 26,4 mpa (K300), Slump (12-2) cm, w/c = 0,52 M3 0.14 1,118,216.00 156,550.24 0.02 0.14 100.00 0.02 - - 0.14 100.00 0.02
Bekisting 2x Pakai M2 0.56 107,013.50 59,927.56 0.01 0.56 100.00 0.01 - - 0.56 100.00 0.01
Besi Beton Ø14 SNI Kg 29.40 21,464.85 631,066.59 0.06 29.40 100.00 0.06 - - 29.40 100.00 0.06
2.1.2 Pekerjaan Pondasi Batu Kali (Badan Bangunan, Mushollah) - -
2.1.2.1 Galian Tanah Pondasi Batu Kali < 1 m M3 22.73 73,837.50 1,678,326.38 0.17 22.73 100.00 0.17 - - 22.73 100.00 0.17
2.1.2.2 Urugan Pasir dibawah Pondasi Batu Kali T.5 cm M3 1.08 148,335.00 160,201.80 0.02 1.08 100.00 0.02 - - 1.08 100.00 0.02
2.1.2.3 Pasangan Aanstamping bawah Pondasi Batu Kali T.10 M3 2.17 382,674.00 830,402.58 0.08 2.17 100.00 0.08 - - 2.17 100.00 0.08
2.1.2.4 Urugan Tanah Kembali Pondasi Batu Kali M3 10.39 54,175.00 562,878.25 0.06 10.39 100.00 0.06 - - 10.39 100.00 0.06
2.1.2.5 Pondasi Batu Kali 1 Sp : 3 Pp M3 9.09 827,447.50 7,521,497.78 0.76 9.09 100.00 0.76 - - 9.09 100.00 0.76
2.1.3 Pekerjaan Pondasi Rollage L.15 cm (Entrance, Selasar Samping) - - -
2.1.3.1 Galian Tanah Pondasi Rollage < 1 m M3 2.23 73,837.50 164,657.63 0.02 - - - 2.23 100.00 0.02 2.23 100.00 0.02
2.1.3.2 Urugan Pasir dibawah Pondasi Rollage T.5 cm M3 0.45 148,335.00 66,750.75 0.01 - - - 0.45 100.00 0.01 0.45 100.00 0.01
2.1.3.3 Pasangan Lantai Kerja bawah Pondasi Rollage T.5 cm (Beton K300) M3 0.45 1,118,216.00 499,003.89 0.05 - - - 0.45 100.00 0.05 0.45 100.00 0.05
2.1.3.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp M2 20.83 128,436.00 2,675,321.88 0.27 - - - 20.83 100.00 0.27 20.83 100.00 0.27
2.2 Pekerjaan Sloef, Kolom dan Ringbalk - -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Mushollah) - -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 1.62 1,118,216.00 1,815,703.23 0.18 1.62 100.00 0.18 - - 1.62 100.00 0.18
2.2.1.2 Bekisting 2x Pakai M2 10.83 114,438.50 1,239,368.96 0.13 10.83 100.00 0.13 - - 10.83 100.00 0.13
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI Kg 280.09 21,464.85 6,012,089.84 0.61 280.09 100.00 0.61 - - 280.09 100.00 0.61
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan, Mushollah) - -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.88 1,118,216.00 981,234.54 0.10 0.88 100.00 0.10 - - 0.88 100.00 0.10
2.2.2.2 Bekisting 2x Pakai M2 5.85 193,468.00 1,131,787.80 0.11 5.85 100.00 0.11 - - 5.85 100.00 0.11
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 181.66 21,464.85 3,899,347.58 0.39 181.66 100.00 0.39 - - 181.66 100.00 0.39
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Selasar, Westafel, Tempat Wudhu) -
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 0.17 50.00 0.02 0.17 50.00 0.02 0.34 100.00 0.03
2.2.3.2 Bekisting 2x Pakai M2 2.26 193,468.00 437,237.68 0.04 1.13 50.00 0.02 1.13 50.00 0.02 2.26 100.00 0.04
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 70.10 21,464.85 1,504,686.30 0.15 35.05 50.00 0.08 35.05 50.00 0.08 70.10 100.00 0.15
2.2.4 Pekerjaan Kolom K1 15 x 30 (Selasar Samping) -
2.2.4.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.62 1,118,216.00 694,412.14 0.07 - - - 0.62 100.00 0.07 0.62 100.00 0.07
2.2.4.2 Bekisting 2x Pakai M2 6.21 193,468.00 1,201,436.28 0.12 - - - 6.21 100.00 0.12 6.21 100.00 0.12
2.2.4.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 99.69 21,464.85 2,139,830.90 0.22 - - - 99.69 100.00 0.22 99.69 100.00 0.22
2.2.5 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan, Mushollah) -
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 2.08 1,008,161.00 2,097,478.96 0.21 - - - 2.08 100.00 0.21 2.08 100.00 0.21
2.2.5.2 Bekisting 2x Pakai M2 13.87 197,923.00 2,745,192.01 0.28 - - - 13.87 100.00 0.28 13.87 100.00 0.28
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 299.22 21,464.85 6,422,712.42 0.65 - - - 299.22 100.00 0.65 299.22 100.00 0.65
2.2.6 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan) -
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 - - - 0.34 100.00 0.03 0.34 100.00 0.03
2.2.6.2 Bekisting 2x Pakai M2 2.24 197,923.00 443,347.52 0.04 - - - 2.24 100.00 0.04 2.24 100.00 0.04
2.2.6.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 48.32 21,464.85 1,037,181.55 0.10 - - - 48.32 100.00 0.10 48.32 100.00 0.10
2.2.7 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Mushollah, Pintu Jendela) -
2.2.7.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.84 1,008,161.00 846,855.24 0.09 - - - 0.84 100.00 0.09 0.84 100.00 0.09
2.2.7.2 Bekisting 2x Pakai M2 5.59 197,923.00 1,106,389.57 0.11 - - - 5.59 100.00 0.11 5.59 100.00 0.11
2.2.7.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 115.53 21,464.85 2,479,834.12 0.25 - - - 115.53 100.00 0.25 115.53 100.00 0.25
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.2.8 Pekerjaan Plat Beton (Selasar Samping, Westafel) -
2.2.8.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.22 1,008,161.00 221,795.42 0.02 - - - - - - - -
2.2.8.2 Bekisting 2x Pakai M2 2.21 237,468.00 524,804.28 0.05 - - - - - - - -
2.2.8.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 54.54 21,464.85 1,170,692.92 0.12 - - - - - - - -
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) M2 152.03 163,636.00 24,877,581.08 2.51 - - - 152.03 100.00 2.51 152.03 100.00 2.51
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4, Entrance) M2 42.24 242,170.50 10,229,281.92 1.03 - - - - - - - -
2.5 Pekerjaan Tiang Atap Bitumen Gelombang (Besi Hollow Galvanis 5/10, Entrance) M' 20.40 178,365.00 3,638,646.00 0.37 - - - - - - - -
2.6 Pekerjaan Rangka Plafond Kalsiboard (Besi Hollow Metal Galvalume 4/4) M2 147.40 102,837.17 15,158,198.37 1.53 - - - - - - - -

TOTAL PEKERJAAN STRUKTUR 109,840,345.70 11.10 2.82 5.15 7.97

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) M3 8.54 148,335.00 1,266,780.90 0.13 - - - - - - - -
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) M3 25.63 167,227.00 4,285,636.74 0.43 - - - - - - - -
3.1.1.3 Rabat Beton bawah Lantai T.5 cm (Keseluruhan, Beton K300) M3 8.54 1,118,216.00 9,549,564.64 0.96 - - - - - - - -
3.1.1.4 Penutup Lantai Keramik Motif 60x60 (Badan Bangunan, Mushollah) M2 62.94 403,309.50 25,384,299.93 2.56 - - - - - - - -
3.1.1.5 Penutup Lantai Conwood Deck 6" (Entrance) M2 59.01 866,833.08 51,151,820.09 5.17 - - - - - - - -
3.1.1.6 Penutup Lantai Andesit Polos 30x30 (Selasar, Tempat Wudhu, Ram) M2 51.05 232,589.50 11,873,693.98 1.20 - - - - - - - -
3.1.1.7 Plint Lantai Keramik 10x60 (Badan Bangunan, Mushollah) M' 38.85 51,605.03 2,004,855.55 0.20 - - - - - - - -
3.1.2 Pekerjaan Dinding -
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Mushollah, 1 Sp : 4 Pp) M2 74.55 242,979.00 18,114,084.45 1.83 44.73 60.00 1.10 29.82 40.00 0.73 74.55 100.00 1.83
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Selasar Samping, Tempat Wudhu) M2 5.14 65,550.32 336,928.64 0.03 - - - - - - - -
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm (Badan Bangunan, Mushollah) M2 91.30 60,403.20 5,514,812.16 0.56 - - - 91.30 100.00 0.56 91.30 100.00 0.56
3.1.2.4 Plesteran Ciprat 1 Sp : 2 Pp Tebal 15 mm (Selasar Samping, Antar Kolom) M2 24.84 49,215.10 1,222,503.08 0.12 - - - - - - - -
3.1.2.5 Dinding Keramik Mozaik 30x60 (Selasar Samping, Westafel, Tempat Wudhu) M2 18.44 410,432.00 7,568,366.08 0.76 - - - - - - - -
3.1.2.6 Coating Bening (Badan Bangunan, Mushollah, Kolom Luar) M2 127.49 45,973.13 5,861,113.71 0.59 - - - - - - - -
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) M2 8.64 995,043.50 8,597,175.84 0.87 - - - - - - - -
3.1.2.8 Dinding Wallpaper Bata L.50 cm (Sisi Dalam) M2 28.13 80,005.50 2,250,554.72 0.23 - - - - - - - -
3.1.3 Pekerjaan Plafond -
3.1.3.1 Plafond Kalsiboard (Badan Bangunan, Kemiringan Atap, Mushollah) M2 147.40 44,924.00 6,621,797.60 0.67 - - - - - - - -
3.1.3.2 Plafond Kalsiboard (Lapis Bawah Atap, Entrance) M2 42.24 44,924.00 1,897,589.76 0.19 - - - - - - - -
3.2 Pekerjaan Pintu dan Jendela (Badan Bangunan) -
3.2.1 Pintu P1 (Entrance dan Back Entrance, Badan Bangunan) -
3.2.1.1 Pasangan Kusen Alumunium Coating P1 (4" x 1 3/4") cm M' 22.40 157,194.40 3,521,154.56 0.36 - - - - - - - -
3.2.1.2 Pasangan Daun Pintu P1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - - -
3.2.1.3 Pasangan Kaca Mati 5 mm P1 M2 11.20 145,703.80 1,631,882.56 0.16 - - - - - - - -
3.2.1.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - - -
3.2.1.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - - -
3.2.1.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - - -
3.2.1.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - - -
3.2.2 Jendela J1 (Badan Bangunan) -
3.2.2.1 Pasangan Kusen Alumunium Coating J1 (4" x 1 3/4") cm M' 40.60 157,194.40 6,382,092.64 0.64 - - - - - - - -
3.2.2.2 Pasangan Kaca Mati 5 mm J1 M2 8.00 145,703.80 1,165,630.40 0.12 - - - - - - - -
3.2.3 Pintu PJ1 (Mushollah) -
3.2.3.1 Pasangan Kusen Alumunium Coating PJ1 (4" x 1 3/4") cm M' 22.20 157,194.40 3,489,715.68 0.35 - - - - - - - -
3.2.3.2 Pasangan Daun Pintu PJ1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - - -
3.2.3.3 Pasangan Kaca Mati 5 mm P1 M2 8.70 145,703.80 1,267,623.06 0.13 - - - - - - - -
3.2.3.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - - -
3.2.3.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - - -
3.2.3.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - - -
3.2.3.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - - -
3.3 Pekerjaan Pengecatan -
3.3.1 Pengecatan Plafond (1 Plamir ; 1 Cat Dasar : 2 Cat Penutup), (Interior) M2 189.64 35,536.05 6,739,056.52 0.68 - - - - - - - -
3.3.2 Pengecatan Rangka Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 23.76 168,454.00 4,002,467.04 0.40 - - - - - - - -
3.3.3 Pengecatan Tiang Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 6.12 168,454.00 1,030,938.48 0.10 - - - - - - - -
3.4 Pekerjaan Atap -
3.4.1 Atap Bitumen Gelombang (Badan Bangunan, Mushollah) M2 152.03 207,297.09 31,515,376.59 3.18 - - - - - - - -
3.4.2 Atap Bitumen Gelombang (Entrance) M2 42.24 207,297.09 8,756,229.08 0.88 - - - - - - - -
3.4.3 Nok Bitumen (Badan Bangunan, Mushollah) M' 14.55 134,101.00 1,951,169.55 0.20 - - - - - - - -
3.4.4 Listplank (Kalsiplank, Badan Bangunan, Mushollah, Entrance) M' 50.00 70,950.00 3,547,500.00 0.36 - - - - - - - -

TOTAL PEKERJAAN FINISHING ARSITEKTUR 257,222,142.77 25.98 1.10 1.29 2.39

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel Bh 1.00 1,572,826.75 1,572,826.75 0.16 - - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt Bh 16.00 353,938.75 5,663,020.00 0.57 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4.1.3 Pasangan Lampu Down Light 2,5" Outbow LED 5,5 Watt Bh 11.00 305,538.75 3,360,926.25 0.34 - - - - - - - -
4.1.4 Pasangan Saklar Tunggal Bh 4.00 211,378.75 845,515.00 0.09 - - - - - - - -
4.1.5 Pasangan Saklar Ganda Bh 2.00 223,478.75 446,957.50 0.05 - - - - - - - -
4.2 Pasangan Instalasi Stop Kontak - -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA Bh 10.00 216,218.75 2,162,187.50 0.22 - - - - - - - -
4.2.2 Pasangan Stop Kontak AC 220 VA/3520 W (AC Split 1 PK) Bh 4.00 253,728.75 1,014,915.00 0.10 - - - - - - - -
4.3 Pasangan Instalasi Jaringan AC M' 30.00 108,772.68 3,263,180.25 0.33 - - - - - - - -
4.3.1 Pasangan AC Split 1 PK Bh 3.00 3,365,799.34 10,097,398.03 1.02 - - - - - - - -
4.4 Pasangan Penangkal Petir Ls 1.00 2,500,000.00 2,500,000.00 0.25 - - - - - - - -
4.5 Pasangan Instalasi Jaringan Kabel Fiber Optic (CCTV) Ttk 6.00 786,326.75 4,717,960.50 0.48 - - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2MP Bh 6.00 656,975.00 3,941,850.00 0.40 - - - - - - - -
4.5.2 Pasangan NVR Channel Set 1.00 5,023,975.00 5,023,975.00 0.51 - - - - - - - -
4.5.3 Pasangan Monitor LCD 32" Bh 1.00 2,944,975.00 2,944,975.00 0.30 - - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm M' 12.00 20,442.68 245,312.10 0.02 - - - - - - - -
4.6.1 Pasangan Horn Speaker Bh 6.00 494,826.75 2,968,960.50 0.30 - - - - - - - -
4.6.2 Pasangan Volume Kontrol Set 1.00 252,826.75 252,826.75 0.03 - - - - - - - -
4.6.3 Pasangan Perangkat Sound System Set 1.00 4,565,000.00 4,565,000.00 0.46 - - - - - - - -
4.6.4 Pasangan TB-Sound System Set 1.00 5,846,326.75 5,846,326.75 0.59 - - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25Kg) Ttk 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - - -
4.8 Pasangan Instalasi Jaringan Kabel Fiber Optic (Akses Point) Ttk 3.00 786,326.75 2,358,980.25 0.24 - - - - - - - -
4.8.1 Pasangan Server Set 1.00 7,578,826.75 7,578,826.75 0.77 - - - - - - - -
4.8.2 Pasangan Akses Point Bh 1.00 2,034,826.75 2,034,826.75 0.21 - - - - - - - -
4.8.3 Pasangan Switch HUB Bh 1.00 2,843,326.75 2,843,326.75 0.29 - - - - - - - -
4.9 Pasangan Instalasi PLN Power (Inc. Jalur ke Mushollah dan Toilet) Ls 1.00 9,000,000.00 9,000,000.00 0.91 - - - - - - - -

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 94,450,073.38 9.54 0.00 0.00 0.00

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVC Type AW Diameter 3/4" (Air Bersih Sambungan dari Tandon) M' 33.00 28,300.25 933,908.25 0.09 - - - - - - - -
5.2 Pipa PVC Type AW Diameter 3" (Air Kotor ke Drainase Lingkungan) M' 25.80 135,531.00 3,496,699.80 0.35 - - - - - - - -
5.3 Pasangan 1 Bh Wastafel Bh 2.00 3,934,865.00 7,869,730.00 0.79 - - - - - - - -
5.4 Pasangan 1 Bh Wastafel Cuci Piring (WCP) Bh 1.00 890,945.00 890,945.00 0.09 - - - - - - - -
5.5 Pasangan 1 Bh Floor Drain Bh 2.00 41,112.50 82,225.00 0.01 - - - - - - - -
5.6 Pasangan 1 Bh Kran Dia. 1/2" atau 3/4" Bh 10.00 102,217.50 1,022,175.00 0.10 - - - - - - - -
5.7 Pasangan 1 Bh Kran Wastafel Dia. 1/2" atau 3/4" Bh 3.00 335,417.50 1,006,252.50 0.10 - - - - - - - -
5.8 Pasangan 1 Bh Stop Kran (Gate Valve) Dia. 3/4" Bh 1.00 141,417.50 141,417.50 0.01 - - - - - - - -
5.9 Pasangan Mesin Air Bh 1.00 741,000.00 741,000.00 0.07 - - - - - - - -
5.10 Menara Reservoir 200x150x350 cm - -
5.10.1 Pekerjaan Pondasi Pedestal Pd1 - -
5.10.1.1 Galian Tanah Pondasi Poerplat < 1 m M3 1.62 73,837.50 119,616.75 0.01 - - - - - - - -
5.10.1.2 Urugan Tanah Kembali Pondasi Poerplat M3 0.43 54,175.00 23,295.25 0.00 - - - - - - - -
5.10.1.3 Tiang Pondasi Pedestal 50x50 cm - - -
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.80 1,118,216.00 894,572.80 0.09 - - - - - - - -
Bekisting 2x Pakai M2 3.20 193,468.00 619,097.60 0.06 - - - - - - - -
Besi Beton Ø12 SNI, Ø8 SNI Kg 49.44 21,464.85 1,061,130.60 0.11 - - - - - - - -
5.10.1.4 Pondasi Poerplat 90x90 cm, T.20 cm -
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.65 1,118,216.00 726,840.40 0.07 - - - - - - - -
Bekisting 2x Pakai M2 1.44 107,013.50 154,099.44 0.02 - - - - - - - -
Besi Beton Ø14 SNI Kg 214.35 21,464.85 4,600,940.54 0.46 - - - - - - - -
5.10.2 Rangka Tengah dan Lantai Menara (Besi Hollow Galvanis 4/4) M2 34.82 244,970.00 8,529,855.40 0.86 - - - - - - - -
5.10.3 Rangka Utama Menara (Besi Hollow Galvanis 5/10) M' 32.28 179,454.00 5,792,775.12 0.59 - - - - - - - -
5.10.4 Plat Baja Lantai Menara T.3 mm M2 3.00 740,164.86 2,220,494.57 0.22 - - - - - - - -
5.10.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) M2 5.00 244,970.00 1,224,850.00 0.12 - - - - - - - -

TOTAL PEKERJAAN PLAMBING DAN SANITASI 42,151,921.52 4.26 0.00 0.00 0.00

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Pek. Pembersian Awal m2 81.86 17,600.00 1,440,780.00 0.15 - - - - - - - -
1.2 Pek. Pengukuran & Pemasangan Bouwplank m1 48.60 106,461.25 5,174,016.75 0.52 - - - - - - - -

TOTAL PEKERJAAN PERSIAPAN 6,614,796.75 0.67 0.00 0.00 0.00

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Batu Kali (Badan Bangunan,Ruang Bilas)
2.1.1.1 Galian Pondasi Batu Kali < 1 m m3 22.05 73,892.50 1,629,329.63 0.16 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.1.1.2 Urugan Pasir Dibawah Pondasi Batu Kali T.5 cm m3 1.05 174,757.00 183,494.85 0.02 - - - - - - - -
2.1.1.3 Pasangan Aanstamping Bawah Pondasi Batu Kali T.10 cm m3 2.10 392,699.70 824,669.37 0.08 - - - - - - - -
2.1.1.4 Urugan Tanah Kembali Pondasi Batu Kali m3 10.08 54,285.00 547,192.80 0.06 - - - - - - - -
2.1.1.5 Pondasi Batu Kali 1 Sp : 3 Pp m3 8.82 824,945.00 7,276,014.90 0.73 - - - - - - - -
2.1.2 Perjaan Pondasi Rollage L.15 cm (Selasar) - -
2.1.2.1 Galian Tanah Pondasi Rollage < 1 m m3 1.52 73,892.50 112,501.33 0.01 - - - - - - - -
2.1.2.2 Urugan Pasir Dibawah Pondasi Rollage T.5 cm m3 0.30 174,757.00 53,213.51 0.01 - - - - - - - -
2.1.2.3 Pasangan Lantai Kerja Bawah Pondasi Rollage T.5 cm (Beton K300) m3 0.30 1,118,398.60 340,552.37 0.03 - - - - - - - -
2.1.2.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp m3 14.21 128,260.00 1,822,574.60 0.18 - - - - - - - -
2.2 Pekerjaan Sloef, Kolom, Plat dan Ringbalk - -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Ruang Bilas) - -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 m3 1.41 1,118,398.60 1,580,297.22 0.16 - - - - - - - -
2.2.1.2 Bekisting 2x Pakai m2 9.42 114,467.10 1,078,280.08 0.11 - - - - - - - -
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI kg 243.74 21,465.73 5,232,043.29 0.53 - - - - - - - -
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan) - -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slum (12 - 2) cm, w/c = 0,52 m3 0.48 1,118,398.60 533,476.13 0.05 - - - - - - - -
2.2.2.2 Bekisting 2x Pakai m2 3.18 193,504.30 615,343.67 0.06 - - - - - - - -
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI kg 98.75 21,465.73 2,119,732.25 0.21 - - - - - - - -
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Ruang Bilas) - -
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.25 1,008,343.60 249,111.29 0.03 - - - - - - - -
2.2.3.2 Bekisting 2x Pakai m2 1.65 193,504.30 318,701.58 0.03 - - - - - - - -
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI kg 51.14 21,465.73 1,097,861.33 0.11 - - - - - - - -
2.2.4 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan) - -
2.2.4.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.04 1,008,343.60 1,043,635.63 0.11 - - - - - - - -
2.2.4.2 Bekisting 2x Pakai m2 6.90 197,959.30 1,365,919.17 0.14 - - - - - - - -
2.2.4.3 Besi Beton Ø12 SNI, Ø6 SNI kg 148.86 21,465.73 3,195,302.68 0.32 - - - - - - - -
2.2.5 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan) - -
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.09 1,008,343.60 1,103,531.24 0.11 - - - - - - - -
2.2.5.2 Bekisting 2x Pakai m2 14.59 197,959.30 2,888,622.11 0.29 - - - - - - - -
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI kg 157.40 21,465.73 3,378,705.12 0.34 - - - - - - - -
2.2.6 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Pintu Jendela) -
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.15 1,008,343.60 148,831.52 0.02 - - - - - - - -
2.2.6.2 Bekisting 2x Pakai m2 0.98 197,959.30 194,791.95 0.02 - - - - - - - -
2.2.6.3 Besi Beton Ø10 SNI, Ø6 SNI kg 20.35 21,465.73 436,752.39 0.04 - - - - - - - -
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) m2 59.01 163,856.00 9,669,142.56 0.98 - - - - - - - -
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4) m2 48.59 102,876.77 4,998,782.09 0.50 - - - - - - - -
2.5 Pekerjaan Rangka Plafond dan Dinding Dalam PVC Shunda (Besi Hollow Metal Galvalume 4/4) m2 56.16 102,876.77 5,777,559.22 0.58 - - - - - - - -

TOTAL PEKERJAAN STRUKTUR 59,815,965.86 6.04 0.00 0.00 0.00

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) m3 4.09 174,757.00 715,280.40 0.07 - - - - - - - -
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) m3 12.28 167,345.00 2,054,804.70 0.21 - - - - - - - -
3.1.1.3 Rabat Beton T.5 cm (Keseluruhan, Beton K300) m3 4.09 1,118,398.60 4,577,605.47 0.46 - - - - - - - -
3.1.1.4 Penutup Lantai Keramik Tekstur 60x60 (Badan Bangunan) m2 36.93 413,098.40 15,255,723.91 1.54 - - - - - - - -
3.1.1.5 Penutup Lantai Andesit Polos 30x30 (Selasar, Ruang Bilas) m2 45.89 284,369.80 13,049,730.12 1.32 - - - - - - - -
3.1.1.6 Penutup Plat Wastafel (Granit 60x60, Toilet Pria dan Wanita) m2 2.20 841,621.73 1,851,567.81 0.19 - - - - - - - -
3.1.2 Pekerjaan Dinding - -
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Selasar, 1 Sp : 4 Pp) 90.64 242,533.50 21,983,236.44 2.22 - - - - - - - -
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Wc ) 30.00 65,473.32 1,964,199.60 0.20 - - - - - - - -
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm 121.28 60,304.20 7,313,693.38 0.74 - - - - - - - -
3.1.2.4 Coating Bening 121.28 46,853.13 5,682,347.00 0.57 - - - - - - - -
3.1.2.5 Dinding Andesit Polos 30x30 cm ( Wc, Ruang Bilas ) 56.52 284,369.80 16,072,581.10 1.62 - - - - - - - -
3.1.2.6 Dinding Keramik 30x60 cm ( Sisi Dalam ) 69.88 370,557.00 25,894,523.16 2.62 - - - - - - - -
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) 9.00 995,076.50 8,955,688.50 0.90 - - - - - - - -
3.1.2.8 Cubicle Panel + Accessories (Pintu Wc dan Partisi Urinoir) 10.86 1,360,000.00 14,769,600.00 1.49 - - - - - - - -
3.1.2.9 Dinding Bitumen Gelombang 48.59 201,749.24 9,802,995.57 0.99 - - - - - - - -
3.1.2.10 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Pria) 1.00 1,200,000.00 1,200,000.00 0.12 - - - - - - - -
3.1.2.11 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Wanita) 1.00 750,000.00 750,000.00 0.08 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.1.3 Plafond dan Dinding Dalam Shunda ( Badan Bangunan ) 56.16 125,878.50 7,069,336.56 0.71 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.2 Pekerjaan Pintu dan Jendela ( Badan Bangunan ) - -
3.2.1 Pintu P1 - -
3.2.1.1 Pasangan Kusen Almunium Coating P1 (4" x 13/4") cm 10.96 157,199.02 1,722,901.26 0.17 - - - - - - - -
3.2.1.2 Pasangan Daun Pintu P1 (Panel Almunium Coating - Coating) 4.30 870,323.19 3,742,389.72 0.38 - - - - - - - -
3.2.1.3 Pasangan Kunci Tanam 2x Slag P1 2.00 416,663.50 833,327.00 0.08 - - - - - - - -
3.2.1.4 Pasangan ensel P1 6.00 61,225.56 367,353.36 0.04 - - - - - - - -
3.2.1.5 Pasangan Doorcloser P1 2.00 241,902.10 483,804.20 0.05 - - - - - - - -
3.2.1.6 Pasangan Handle P1 2.00 229,802.10 459,604.20 0.05 - - - - - - - -
3.2.2 Jendela J1 - -
3.2.2.1 Pasangan Kusen Almunium Coating J1 (4" x 13/4") cm 28.80 157,199.02 4,527,331.78 0.46 - - - - - - - -
3.2.2.2 Pasangan Kaca Mati 5 mm J1 0.60 145,705.56 87,423.34 0.01 - - - - - - - -
3.2.3 Jendela J2 - - -
3.2.3.1 Pasangan Kusen Almunium Coating J2 (4" x 13/4") cm 55.20 157,199.02 8,677,385.90 0.88 - - - - - - - -
3.2.3.2 Pasangan Kaca Mati 5 mm J2 0.90 145,705.56 131,135.00 0.01 - - - - - - - -
3.3. Pengecetan Plafond (1 Plamir : 1 Cat Dasar : 2 Cat Penutup), (Interior) 56.16 43,550.65 2,445,804.50 0.25 - - - - - - - -
3.4 Pekerjaan Atap - -
3.4.1 Atap Bitumen Gelombang (Badan Bangunan) 59.01 201,749.24 11,905,222.65 1.20 - - - - - - - -
3.4.2 Nok Bitumen (Badan Bangunan) 35.25 143,629.20 5,062,929.30 0.51 - - - - - - - -
3.4.3 Listplank (Kasiplank, Badan Bangunan, Enterance) 39.08 70,972.00 2,773,585.76 0.28 - - - - - - - -

TOTAL PEKERJAAN FINISHING ARSITEKTUR 202,183,111.69 20.42 0.00 0.00 0.00

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel 1.00 1,803,826.75 1,803,826.75 0.18 - - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt 10.00 353,938.75 3,539,387.50 0.36 - - - - - - - -
4.1.3 Pasangan Lampu Down Light 2.5" Outbow LED 5.5 Watt 12.00 305,538.75 3,666,465.00 0.37 - - - - - - - -
4.1.4 Pasangan Saklar Ganda 5.00 223,478.75 1,117,393.75 0.11 - - - - - - - -
4.2 Pasangan Instalasi Stop Kontak - -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA 3.00 216,218.75 648,656.25 0.07 - - - - - - - -
4.2.2 Pasangan Stop Kontak Wall Exhauser 6.00 216,218.75 1,297,312.50 0.13 - - - - - - - -
4.3 Pasangan Instalasi Jaringan Wall Exhauser 12.00 108,772.68 1,305,272.10 0.13 - - - - - - - -
4.3.1 Pasangan Wall Exhauser 12 Inch - FV30RUN 6.00 513,500.00 3,081,000.00 0.31 - - - - - - - -
4.4 Pasangan Penangkal Petir 1.00 3,500,000.00 3,500,000.00 0.35 - - - - - - - -
4.5 Pasangan Instlasi Jaringan Kabel Fiber Optic (CCTV) 3.00 786,326.75 2,358,980.25 0.24 - - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2 MP (Luar Bangunan, Sambungan Dari Mini Resto) 3.00 656,975.00 1,970,925.00 0.20 - - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm 4.00 20,442.68 81,770.70 0.01 - - - - - - - -
4.6.1 Pasangan Horn Speaker (Sambungan Dari Mini Resto) 2.00 494,826.75 989,653.50 0.10 - - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25 kg) 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - - -
4.8 Pasangan Instalasi PLN Power 1.00 10,000,000.00 10,000,000.00 1.01 - - - - - - - -

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 44,560,643.30 4.50 0.00 0.00 0.00

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVc Tipe AW Diameter 3/4" (Air Bersih Dari Sumur Bor / PDAM Reservoir) m1 18.50 28,304.65 523,636.03 0.05 - - - - - - - -
5.2 Pipa PVC Tipe AW Diameter 3/4" (Distribusi Air Bersih Dari Reservoir) m1 26.50 28,304.65 750,073.23 0.08 - - - - - - - -
5.3 Pipa PVC Tipe AW Diameter 3" (Air Kotor Ke Drainase Lingkungan) m1 23.00 135,539.80 3,117,415.40 0.31 - - - - - - - -
5.4 Pipa PVC Tipe AW Diameter 4" (Disposal) m1 18.00 186,689.80 3,360,416.40 0.34 - - - - - - - -
5.5 Pasangan 1 bh Closet Duduk / Monoblock (TOTO) bh 6.00 3,655,597.00 21,933,582.00 2.22 - - - - - - - -
5.6 Pasangan 1 bh Wastafel (TOTO) 3.00 3,571,942.00 10,715,826.00 1.08 - - - - - - - -
5.7 Pasangan 1 bh Uninoir (TOTO) 2.00 6,665,285.00 13,330,570.00 1.35 - - - - - - - -
5.8 Pasangan 1 bh Floor Drain 9.00 41,123.50 370,111.50 0.04 - - - - - - - -
5.9 Pasangan 1 bh Kran dia. 1/2' atau 3/4" 8.00 102,228.50 817,828.00 0.08 - - - - - - - -
5.10 Pasangan 1 bh Kran wastafel dia. 1/2' atau 3/4" 2.00 335,428.50 670,857.00 0.07 - - - - - - - -
5.11 Pasangan 1 bh shower closet dia. 1/2' atau 3/4" 6.00 142,928.50 857,571.00 0.09 - - - - - - - -
5.12 Pasangan 1 bh shower Wall dia. 1/2' atau 3/4" (Ruang Bilas) 4.00 1,435,428.50 5,741,714.00 0.58 - - - - - - - -
5.13 Pasangan 1 bh Stop Kran (Gate Valve) dia. 3/4" 2.00 141,428.50 282,857.00 0.03 - - - - - - - -
5.14 Pasangan Mesin Air 1.00 741,000.00 741,000.00 0.07 - - - - - - - -
5.14b Pasangan Mesin Pemanas Air 1.00 5,000,000.00 5,000,000.00 0.51 - - - - - - - -
5.15 Septictank Biotank Kap. 4m3 1.00 20,380,000.00 20,380,000.00 2.06 - - - - - - - -
5.16 Pasangan Sumur Bor Jet Pump 30.00 350,000.00 10,500,000.00 1.06 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.17 Reservoir 1200 Liter 1.00 1,850,000.00 1,850,000.00 0.19 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.18 Reservoir 200x150x350 cm -
5.18.1 Pekerjaan Pondasi Pedestal Pd1 -
5.18.1.1 Galian Tanah Pondasi Poerplat < 1m 1.62 74,250.00 120,285.00 0.01 - - - - - - - -
5.18.1.2 Urugan Tanah Kembali Pondasi Poerplat 0.43 55,000.00 23,760.00 0.00 - - - - - - - -
5.18.1.3 Tiang Pondasi Pedestal 50x50 cm -
Beton Mutu fc = 26,6 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.80 1,485,144.21 1,188,115.37 0.12 - - - - - - - -
Bekisting 2x Pakai 3.20 193,504.30 619,213.76 0.06 - - - - - - - -
Besi Beton Ø12, Ø8 49.44 21,465.73 1,061,174.10 0.11 - - - - - - - -
5.18.1.4 Pondasi Poerplat 90x90 cm,T.20 cm -
Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.65 1,485,144.21 962,373.45 0.10 - - - - - - - -
Bekisting 2x Pakai 1.44 124,547.50 179,348.40 0.02 - - - - - - - -
Besi Beton Ø14 SNI 214.35 21,465.73 4,601,114.73 0.46 - - - - - - - -
5.18.2 Rangkai Tengah Dan Lantai Menara (Besi Hollow Galvanis 4/4) 34.82 244,970.00 8,529,855.40 0.86 - - - - - - - -
5.18.3 Rangka Utama menara ( Besi Hollow Galvanis 5/10 32.28 179,454.00 5,792,775.12 0.59 - - - - - - - -
5.18.4 Tplat Baja Lantai Menara T.3mm 3.00 740,164.86 2,220,494.57 0.22 - - - - - - - -
5.18.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) 5.00 244,970.00 1,224,850.00 0.12 - - - - - - - -

TOTAL PEKERJAAN PLAMBING DAN SANITASI 127,466,817.45 12.88 - - -

6. PEKERJAAN AKHIR - - -
6.1 Pembersihan Sisa Pekerjaan Ls 1.00 2,400,000.00 2,400,000.00 0.24 - - - - - - - -

TOTAL PEKERJAAN AKHIR 2,400,000.00 0.24 0.00 0.00 0.00

C. PENERAPAN SMKK

1. PENYIAPAN RKK
1.1 Pembuatan Dokumen Rencana Keselamatan Konstruksi
1.2 Pembuatan Prosedur dan instruksi kerja Set 1.00 2,000,000.00 2,000,000.00 0.20 1.00 100.00 0.20 - - 1.00 100.00 0.20
1.3 Penyiapan formulir
TOTAL PENYIAPAN RKK 2,000,000.00 0.20 0.20 - 0.20
2. SOSIALISASI, PROMOSI DAN PELATIHAN
2.1 Induksi K3 (Safety Induction) Org 5.00 7,500.00 37,500.00 0.00 0.50 10.00 0.00 - - 0.50 10.00 0.00
2.2 Pengarahan K3 (Safety Briefing) Org 5.00 15,000.00 75,000.00 0.01 5.00 100.00 0.01 - - 5.00 100.00 0.01
2.3 Pelatihan K3 - -
2.3.1 Bekerja di ketinggian Org 4.00 7,500.00 30,000.00 0.00 4.00 100.00 0.00 - - 4.00 100.00 0.00
2.3.2 Penggunaan Bahan Kimia (MSDS) Org 2.00 7,500.00 15,000.00 0.00 2.00 100.00 0.00 - - 2.00 100.00 0.00
2.4 Simulasi K3 Org 5.00 7,500.00 37,500.00 0.00 5.00 100.00 0.00 - - 5.00 100.00 0.00
2.5 Spanduk (Banner) Lb 1.00 150,000.00 150,000.00 0.02 1.00 100.00 0.02 - - 1.00 100.00 0.02
2.6 Poster 2 2.00 50,000.00 100,000.00 0.01 2.00 100.00 0.01 - - 2.00 100.00 0.01
2.7 Papan Informasi K3 1 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
TOTAL SOSIALISASI, PROMOSI DAN PELATIHAN 945,000.00 0.10 0.09 - 0.09
3. ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI
3.1 APK
3.1.1 Tali Keselamatan (Life Line) Ls 1.00 1,700,000.00 1,700,000.00 0.17 1.00 100.00 0.17 - - 1.00 100.00 0.17
3.1.2 Pembatas Area (Restricted Area) Ls 1.00 2,000,000.00 2,000,000.00 0.20 1.00 100.00 0.20 - - 1.00 100.00 0.20
3.2 APD -
3.2.1 Topi Pelindung (Safety Helmet) Bh 10.00 75,000.00 750,000.00 0.08 10.00 100.00 0.08 - - 10.00 100.00 0.08
3.2.2 Pelindung Mata (Googles, Spectacles) Bh 5.00 25,000.00 125,000.00 0.01 5.00 100.00 0.01 - - 5.00 100.00 0.01
3.2.3 Pelindung Pernapasan dan Mulut (Masker) Bh 100.00 5,000.00 500,000.00 0.05 100.00 100.00 0.05 - - 100.00 100.00 0.05
3.2.4 Sarung Tangan (Safety Gloves) Psg 10.00 15,000.00 150,000.00 0.02 10.00 100.00 0.02 - - 10.00 100.00 0.02
3.2.5 Sepatu Keselamatan (Safety Shoes) Psg 10.00 350,000.00 3,500,000.00 0.35 10.00 100.00 0.35 - - 10.00 100.00 0.35
3.2.6 Penunjang Seluruh Tubuh (Full Body Harness) Bh 2.00 500,000.00 1,000,000.00 0.10 2.00 100.00 0.10 - - 2.00 100.00 0.10
3.2.7 Rompi Keselamatan (Safety Vest) Bh 10.00 25,000.00 250,000.00 0.03 10.00 100.00 0.03 - - 10.00 100.00 0.03
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 9,975,000.00 1.01 1.01 - 1.01
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4. ASURANSI DAN PERIZINAN
4.1 Asuransi Ls 1.00 3,000,000.00 3,000,000.00 0.30 - - - 1.00 100.00 0.30 1.00 100.00 0.30
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 3,000,000.00 0.30 - 0.30 0.30
5. PERSONEL K3 KONSTRUKSI
5.1 Ahli K3 Konstruksi -
5.2 Petugas K3 Konstruksi Ob 4.00 3,675,000.00 14,700,000.00 1.48 - - - 4.00 100.00 1.48 4.00 100.00 1.48
TOTAL PERSONEL K3 KONSTRUKSI 14,700,000.00 1.48 - 1.48 1.48
6. FASILITAS, SARANA DAN PRASARANA KESEHATAN
6.1 Peralatan P3K (Kotak P3K, Tandu, Obat Luka, Perban, dll) Ls 1.00 500,000.00 500,000.00 0.05 - - - 1.00 100.00 0.05 1.00 100.00 0.05
TOTAL FASILITAS, SARANA DAN PRASARANA KESEHATAN 500,000.00 0.05 - 0.05 0.05
7. RAMBU - RAMBU YANG DIPERLUKAN
7.1 Rambu Petunjuk bh 2.00 75,000.00 150,000.00 0.02 - - - 2.00 100.00 0.02 2.00 100.00 0.02
7.2 Rambu Larangan bh 2.00 75,000.00 150,000.00 0.02 - - - 2.00 100.00 0.02 2.00 100.00 0.02
7.3 Rambu Peringatan bh 2.00 100,000.00 200,000.00 0.02 - - - 2.00 100.00 0.02 2.00 100.00 0.02
7.4 Jalur Evakuasi (Escape Route) Ls 1.00 250,000.00 250,000.00 0.03 - - - 1.00 100.00 0.03 1.00 100.00 0.03
TOTAL RAMBU - RAMBU YANG DIPERLUKAN 750,000.00 0.08 - 0.08 0.08
8. KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI
8.1 Ahli K3 Konstruksi Oj -
TOTAL KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI - 0.00
9. LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN
KONSTRUKSI
9.1 Alat Pemadam Api Ringan (APAR) bh 1.00 500,000.00 500,000.00 0.05 - - - 1.00 100.00 0.05 1.00 100.00 0.05
9.2 Program Inspeksi Ls 1.00 1,500,000.00 1,500,000.00 0.15 - - - 1.00 100.00 0.15 1.00 100.00 0.15
9.3 Pelaporan dan Penyeledikan Insiden Ls 1.00 500,000.00 500,000.00 0.05 - - - 1.00 100.00 0.05 1.00 100.00 0.05
9.4 Pembuatan Kartu Identitas Pekerja (KIP) Org 10.00 5,000.00 50,000.00 0.01 - - - 10.00 100.00 0.01 10.00 100.00 0.01
TOTAL LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN KONSTRUKSI 2,550,000.00 0.26 - 0.26 0.26

A Jumlah Harga Penawaran 989,944,870.91 100.00 6.11 8.61 14.72


B PPN (10%) 98,994,487.09
C Jumlah (A+B) 1,088,939,358.00
PERSENTASE SAMPAI MINGGU INI 14.72
D Jumlah Dibulatkan 1,088,939,358.00

Bulukumba, 29 Oktober 2020


Disetujui, Diketahui, Diperiksa Oleh, Dibuat Oleh,
Pejabat Pembuat Komitmen Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUTR Prov SulSel Dinas PUTR Prov SulSel CV.MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

A.KHADAFI HARUN, ST.,MT. L I L I, ST. IRHAM HARAHAP, ST. VIKA APRILIA DWI PUTRI
NIP. 19811126 200901 1 008 NIP. 19821229 201503 2 001 Site Engineer Direktris
LAPORAN KEMAJUAN MINGGUAN

Kegiatan : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba Minggu Ke : 03 ( Tiga )
Satuan Kerja : Dinas Pekerjaan Umum Dan Tata Ruang Prov. Sulawesi Selatan Bidang Cipta Karya Periode : 30 Oktober S/d 05 November 2020
Lokasi : Desa Ara, Kecamatan Bonto Bahari, Kabupaten Bulukumba, Provinsi Sulawesi Selatan No. Kontrak : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
Sumber Dana : Dana Bantuan Provinsi Nilai Kontrak : Rp. 1,088,939,358.00
Tahun Anggaran : 2020 Schedule Pelaksanaan : 16 Oktober S/d 14 Desember 2020

MINGGU LALU MINGGU INI S/D MINGGU INI


VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
NO URAIAN PEKERJAAN
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q

A. PEMBANGUNAN RUANG KULINER, SUVENIR, MUSHOLLAH DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Papan Proyek Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
1.2 Bedeng/Direksi Keet M2 5.50 1,512,555.00 8,319,052.50 0.84 5.50 100.00 0.84 - - 5.50 100.00 0.84

TOTAL PEKERJAAN PERSIAPAN 8,819,052.50 0.89 0.89 0.00 0.89

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Poerplat PP1 (Selasar Samping)
2.1.1.1 Galian Pondasi Poerplat < 1 m M3 0.32 73,837.50 23,628.00 0.00 0.32 100.00 0.00 - - 0.32 100.00 0.00
2.1.1.2 Urugan Pasir dibawah Pondasi Poerplat T.5 cm M3 0.04 148,335.00 5,933.40 0.00 0.04 100.00 0.00 - - 0.04 100.00 0.00
2.1.1.3 Urugan Tanah Kembali Pondasi Poerplat M3 0.31 54,175.00 16,794.25 0.00 0.31 100.00 0.00 - - 0.31 100.00 0.00
2.1.1.4 Pasangan Lantai Kerja bawah Pondasi Poerplat T.5 cm (Beton K300) M3 0.04 1,118,216.00 44,728.64 0.00 0.04 100.00 0.00 - - 0.04 100.00 0.00
2.1.1.5 Pondasi Poerplat 35x50 cm, T.20 cm -
Beton Mutu F'c = 26,4 mpa (K300), Slump (12-2) cm, w/c = 0,52 M3 0.14 1,118,216.00 156,550.24 0.02 0.14 100.00 0.02 - - 0.14 100.00 0.02
Bekisting 2x Pakai M2 0.56 107,013.50 59,927.56 0.01 0.56 100.00 0.01 - - 0.56 100.00 0.01
Besi Beton Ø14 SNI Kg 29.40 21,464.85 631,066.59 0.06 29.40 100.00 0.06 - - 29.40 100.00 0.06
2.1.2 Pekerjaan Pondasi Batu Kali (Badan Bangunan, Mushollah) -
2.1.2.1 Galian Tanah Pondasi Batu Kali < 1 m M3 22.73 73,837.50 1,678,326.38 0.17 22.73 100.00 0.17 - - 22.73 100.00 0.17
2.1.2.2 Urugan Pasir dibawah Pondasi Batu Kali T.5 cm M3 1.08 148,335.00 160,201.80 0.02 1.08 100.00 0.02 - - 1.08 100.00 0.02
2.1.2.3 Pasangan Aanstamping bawah Pondasi Batu Kali T.10 M3 2.17 382,674.00 830,402.58 0.08 2.17 100.00 0.08 - - 2.17 100.00 0.08
2.1.2.4 Urugan Tanah Kembali Pondasi Batu Kali M3 10.39 54,175.00 562,878.25 0.06 10.39 100.00 0.06 - - 10.39 100.00 0.06
2.1.2.5 Pondasi Batu Kali 1 Sp : 3 Pp M3 9.09 827,447.50 7,521,497.78 0.76 9.09 100.00 0.76 - - 9.09 100.00 0.76
2.1.3 Pekerjaan Pondasi Rollage L.15 cm (Entrance, Selasar Samping) - - -
2.1.3.1 Galian Tanah Pondasi Rollage < 1 m M3 2.23 73,837.50 164,657.63 0.02 2.23 100.00 0.02 - - 2.23 100.00 0.02
2.1.3.2 Urugan Pasir dibawah Pondasi Rollage T.5 cm M3 0.45 148,335.00 66,750.75 0.01 0.45 100.00 0.01 - - 0.45 100.00 0.01
2.1.3.3 Pasangan Lantai Kerja bawah Pondasi Rollage T.5 cm (Beton K300) M3 0.45 1,118,216.00 499,003.89 0.05 0.45 100.00 0.05 - - 0.45 100.00 0.05
2.1.3.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp M2 20.83 128,436.00 2,675,321.88 0.27 20.83 100.00 0.27 - - 20.83 100.00 0.27
2.2 Pekerjaan Sloef, Kolom dan Ringbalk -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Mushollah) -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 1.62 1,118,216.00 1,815,703.23 0.18 1.62 100.00 0.18 - - 1.62 100.00 0.18
2.2.1.2 Bekisting 2x Pakai M2 10.83 114,438.50 1,239,368.96 0.13 10.83 100.00 0.13 - - 10.83 100.00 0.13
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI Kg 280.09 21,464.85 6,012,089.84 0.61 280.09 100.00 0.61 - - 280.09 100.00 0.61
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan, Mushollah) -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.88 1,118,216.00 981,234.54 0.10 0.88 100.00 0.10 - - 0.88 100.00 0.10
2.2.2.2 Bekisting 2x Pakai M2 5.85 193,468.00 1,131,787.80 0.11 5.85 100.00 0.11 - - 5.85 100.00 0.11
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 181.66 21,464.85 3,899,347.58 0.39 181.66 100.00 0.39 - - 181.66 100.00 0.39
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Selasar, Westafel, Tempat Wudhu)
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 0.34 100.00 0.03 - - 0.34 100.00 0.03
2.2.3.2 Bekisting 2x Pakai M2 2.26 193,468.00 437,237.68 0.04 2.26 100.00 0.04 - - 2.26 100.00 0.04
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 70.10 21,464.85 1,504,686.30 0.15 70.10 100.00 0.15 - - 70.10 100.00 0.15
2.2.4 Pekerjaan Kolom K1 15 x 30 (Selasar Samping)
2.2.4.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.62 1,118,216.00 694,412.14 0.07 0.62 100.00 0.07 - - 0.62 100.00 0.07
2.2.4.2 Bekisting 2x Pakai M2 6.21 193,468.00 1,201,436.28 0.12 6.21 100.00 0.12 - - 6.21 100.00 0.12
2.2.4.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 99.69 21,464.85 2,139,830.90 0.22 99.69 100.00 0.22 - - 99.69 100.00 0.22
2.2.5 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan, Mushollah)
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 2.08 1,008,161.00 2,097,478.96 0.21 2.08 100.00 0.21 - - 2.08 100.00 0.21
2.2.5.2 Bekisting 2x Pakai M2 13.87 197,923.00 2,745,192.01 0.28 13.87 100.00 0.28 - - 13.87 100.00 0.28
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 299.22 21,464.85 6,422,712.42 0.65 299.22 100.00 0.65 - - 299.22 100.00 0.65
2.2.6 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan)
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 0.34 100.00 0.03 - - 0.34 100.00 0.03
2.2.6.2 Bekisting 2x Pakai M2 2.24 197,923.00 443,347.52 0.04 2.24 100.00 0.04 - - 2.24 100.00 0.04
2.2.6.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 48.32 21,464.85 1,037,181.55 0.10 48.32 100.00 0.10 - - 48.32 100.00 0.10
2.2.7 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Mushollah, Pintu Jendela)
2.2.7.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.84 1,008,161.00 846,855.24 0.09 0.84 100.00 0.09 - - 0.84 100.00 0.09
2.2.7.2 Bekisting 2x Pakai M2 5.59 197,923.00 1,106,389.57 0.11 5.59 100.00 0.11 - - 5.59 100.00 0.11
2.2.7.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 115.53 21,464.85 2,479,834.12 0.25 115.53 100.00 0.25 - - 115.53 100.00 0.25
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.2.8 Pekerjaan Plat Beton (Selasar Samping, Westafel)
2.2.8.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.22 1,008,161.00 221,795.42 0.02 - - - 0.22 100.00 0.02 0.22 100.00 0.02
2.2.8.2 Bekisting 2x Pakai M2 2.21 237,468.00 524,804.28 0.05 - - - 2.21 100.00 0.05 2.21 100.00 0.05
2.2.8.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 54.54 21,464.85 1,170,692.92 0.12 - - - 54.54 100.00 0.12 54.54 100.00 0.12
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) M2 152.03 163,636.00 24,877,581.08 2.51 152.03 100.00 2.51 - - 152.03 100.00 2.51
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4, Entrance) M2 42.24 242,170.50 10,229,281.92 1.03 - - - - - - - -
2.5 Pekerjaan Tiang Atap Bitumen Gelombang (Besi Hollow Galvanis 5/10, Entrance) M' 20.40 178,365.00 3,638,646.00 0.37 - - - - - - - -
2.6 Pekerjaan Rangka Plafond Kalsiboard (Besi Hollow Metal Galvalume 4/4) M2 147.40 102,837.17 15,158,198.37 1.53 - - - - - - - -

TOTAL PEKERJAAN STRUKTUR 109,840,345.70 11.10 7.97 0.19 8.16

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) M3 8.54 148,335.00 1,266,780.90 0.13 - - - - - - - -
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) M3 25.63 167,227.00 4,285,636.74 0.43 - - - - - - - -
3.1.1.3 Rabat Beton bawah Lantai T.5 cm (Keseluruhan, Beton K300) M3 8.54 1,118,216.00 9,549,564.64 0.96 - - - - - - - -
3.1.1.4 Penutup Lantai Keramik Motif 60x60 (Badan Bangunan, Mushollah) M2 62.94 403,309.50 25,384,299.93 2.56 - - - - - - - -
3.1.1.5 Penutup Lantai Conwood Deck 6" (Entrance) M2 59.01 866,833.08 51,151,820.09 5.17 - - - - - - - -
3.1.1.6 Penutup Lantai Andesit Polos 30x30 (Selasar, Tempat Wudhu, Ram) M2 51.05 232,589.50 11,873,693.98 1.20 - - - - - - - -
3.1.1.7 Plint Lantai Keramik 10x60 (Badan Bangunan, Mushollah) M' 38.85 51,605.03 2,004,855.55 0.20 - - - - - - - -
3.1.2 Pekerjaan Dinding
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Mushollah, 1 Sp : 4 Pp) M2 74.55 242,979.00 18,114,084.45 1.83 74.55 100.00 1.83 - - 74.55 100.00 1.83
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Selasar Samping, Tempat Wudhu) M2 5.14 65,550.32 336,928.64 0.03 - - - - - - - -
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm (Badan Bangunan, Mushollah) M2 91.30 60,403.20 5,514,812.16 0.56 91.30 100.00 0.56 - - 91.30 100.00 0.56
3.1.2.4 Plesteran Ciprat 1 Sp : 2 Pp Tebal 15 mm (Selasar Samping, Antar Kolom) M2 24.84 49,215.10 1,222,503.08 0.12 - - - - - - - -
3.1.2.5 Dinding Keramik Mozaik 30x60 (Selasar Samping, Westafel, Tempat Wudhu) M2 18.44 410,432.00 7,568,366.08 0.76 - - - - - - - -
3.1.2.6 Coating Bening (Badan Bangunan, Mushollah, Kolom Luar) M2 127.49 45,973.13 5,861,113.71 0.59 - - - - - - - -
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) M2 8.64 995,043.50 8,597,175.84 0.87 - - - - - - - -
3.1.2.8 Dinding Wallpaper Bata L.50 cm (Sisi Dalam) M2 28.13 80,005.50 2,250,554.72 0.23 - - - - - - - -
3.1.3 Pekerjaan Plafond
3.1.3.1 Plafond Kalsiboard (Badan Bangunan, Kemiringan Atap, Mushollah) M2 147.40 44,924.00 6,621,797.60 0.67 - - - - - - - -
3.1.3.2 Plafond Kalsiboard (Lapis Bawah Atap, Entrance) M2 42.24 44,924.00 1,897,589.76 0.19 - - - - - - - -
3.2 Pekerjaan Pintu dan Jendela (Badan Bangunan)
3.2.1 Pintu P1 (Entrance dan Back Entrance, Badan Bangunan)
3.2.1.1 Pasangan Kusen Alumunium Coating P1 (4" x 1 3/4") cm M' 22.40 157,194.40 3,521,154.56 0.36 - - - - - - - -
3.2.1.2 Pasangan Daun Pintu P1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - - -
3.2.1.3 Pasangan Kaca Mati 5 mm P1 M2 11.20 145,703.80 1,631,882.56 0.16 - - - - - - - -
3.2.1.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - - -
3.2.1.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - - -
3.2.1.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - - -
3.2.1.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - - -
3.2.2 Jendela J1 (Badan Bangunan)
3.2.2.1 Pasangan Kusen Alumunium Coating J1 (4" x 1 3/4") cm M' 40.60 157,194.40 6,382,092.64 0.64 - - - - - - - -
3.2.2.2 Pasangan Kaca Mati 5 mm J1 M2 8.00 145,703.80 1,165,630.40 0.12 - - - - - - - -
3.2.3 Pintu PJ1 (Mushollah)
3.2.3.1 Pasangan Kusen Alumunium Coating PJ1 (4" x 1 3/4") cm M' 22.20 157,194.40 3,489,715.68 0.35 - - - - - - - -
3.2.3.2 Pasangan Daun Pintu PJ1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - - -
3.2.3.3 Pasangan Kaca Mati 5 mm P1 M2 8.70 145,703.80 1,267,623.06 0.13 - - - - - - - -
3.2.3.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - - -
3.2.3.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - - -
3.2.3.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - - -
3.2.3.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - - -
3.3 Pekerjaan Pengecatan
3.3.1 Pengecatan Plafond (1 Plamir ; 1 Cat Dasar : 2 Cat Penutup), (Interior) M2 189.64 35,536.05 6,739,056.52 0.68 - - - - - - - -
3.3.2 Pengecatan Rangka Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 23.76 168,454.00 4,002,467.04 0.40 - - - - - - - -
3.3.3 Pengecatan Tiang Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 6.12 168,454.00 1,030,938.48 0.10 - - - - - - - -
3.4 Pekerjaan Atap
3.4.1 Atap Bitumen Gelombang (Badan Bangunan, Mushollah) M2 152.03 207,297.09 31,515,376.59 3.18 - - - 152.03 100.00 3.18 152.03 100.00 3.18
3.4.2 Atap Bitumen Gelombang (Entrance) M2 42.24 207,297.09 8,756,229.08 0.88 - - - 42.24 100.00 0.88 42.24 100.00 0.88
3.4.3 Nok Bitumen (Badan Bangunan, Mushollah) M' 14.55 134,101.00 1,951,169.55 0.20 - - - 14.55 100.00 0.20 14.55 100.00 0.20
3.4.4 Listplank (Kalsiplank, Badan Bangunan, Mushollah, Entrance) M' 50.00 70,950.00 3,547,500.00 0.36 - - - 25.00 50.00 0.18 25.00 50.00 0.18

TOTAL PEKERJAAN FINISHING ARSITEKTUR 257,222,142.77 25.98 2.39 4.44 6.83

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel Bh 1.00 1,572,826.75 1,572,826.75 0.16 - - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt Bh 16.00 353,938.75 5,663,020.00 0.57 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4.1.3 Pasangan Lampu Down Light 2,5" Outbow LED 5,5 Watt Bh 11.00 305,538.75 3,360,926.25 0.34 - - - - - - - -
4.1.4 Pasangan Saklar Tunggal Bh 4.00 211,378.75 845,515.00 0.09 - - - - - - - -
4.1.5 Pasangan Saklar Ganda Bh 2.00 223,478.75 446,957.50 0.05 - - - - - - - -
4.2 Pasangan Instalasi Stop Kontak -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA Bh 10.00 216,218.75 2,162,187.50 0.22 - - - - - - - -
4.2.2 Pasangan Stop Kontak AC 220 VA/3520 W (AC Split 1 PK) Bh 4.00 253,728.75 1,014,915.00 0.10 - - - - - - - -
4.3 Pasangan Instalasi Jaringan AC M' 30.00 108,772.68 3,263,180.25 0.33 - - - - - - - -
4.3.1 Pasangan AC Split 1 PK Bh 3.00 3,365,799.34 10,097,398.03 1.02 - - - - - - - -
4.4 Pasangan Penangkal Petir Ls 1.00 2,500,000.00 2,500,000.00 0.25 - - - - - - - -
4.5 Pasangan Instalasi Jaringan Kabel Fiber Optic (CCTV) Ttk 6.00 786,326.75 4,717,960.50 0.48 - - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2MP Bh 6.00 656,975.00 3,941,850.00 0.40 - - - - - - - -
4.5.2 Pasangan NVR Channel Set 1.00 5,023,975.00 5,023,975.00 0.51 - - - - - - - -
4.5.3 Pasangan Monitor LCD 32" Bh 1.00 2,944,975.00 2,944,975.00 0.30 - - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm M' 12.00 20,442.68 245,312.10 0.02 - - - - - - - -
4.6.1 Pasangan Horn Speaker Bh 6.00 494,826.75 2,968,960.50 0.30 - - - - - - - -
4.6.2 Pasangan Volume Kontrol Set 1.00 252,826.75 252,826.75 0.03 - - - - - - - -
4.6.3 Pasangan Perangkat Sound System Set 1.00 4,565,000.00 4,565,000.00 0.46 - - - - - - - -
4.6.4 Pasangan TB-Sound System Set 1.00 5,846,326.75 5,846,326.75 0.59 - - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25Kg) Ttk 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - - -
4.8 Pasangan Instalasi Jaringan Kabel Fiber Optic (Akses Point) Ttk 3.00 786,326.75 2,358,980.25 0.24 - - - - - - - -
4.8.1 Pasangan Server Set 1.00 7,578,826.75 7,578,826.75 0.77 - - - - - - - -
4.8.2 Pasangan Akses Point Bh 1.00 2,034,826.75 2,034,826.75 0.21 - - - - - - - -
4.8.3 Pasangan Switch HUB Bh 1.00 2,843,326.75 2,843,326.75 0.29 - - - - - - - -
4.9 Pasangan Instalasi PLN Power (Inc. Jalur ke Mushollah dan Toilet) Ls 1.00 9,000,000.00 9,000,000.00 0.91 - - - - - - - -

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 94,450,073.38 9.54 0.00 0.00 0.00

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVC Type AW Diameter 3/4" (Air Bersih Sambungan dari Tandon) M' 33.00 28,300.25 933,908.25 0.09 - - - - - - - -
5.2 Pipa PVC Type AW Diameter 3" (Air Kotor ke Drainase Lingkungan) M' 25.80 135,531.00 3,496,699.80 0.35 - - - - - - - -
5.3 Pasangan 1 Bh Wastafel Bh 2.00 3,934,865.00 7,869,730.00 0.79 - - - - - - - -
5.4 Pasangan 1 Bh Wastafel Cuci Piring (WCP) Bh 1.00 890,945.00 890,945.00 0.09 - - - - - - - -
5.5 Pasangan 1 Bh Floor Drain Bh 2.00 41,112.50 82,225.00 0.01 - - - - - - - -
5.6 Pasangan 1 Bh Kran Dia. 1/2" atau 3/4" Bh 10.00 102,217.50 1,022,175.00 0.10 - - - - - - - -
5.7 Pasangan 1 Bh Kran Wastafel Dia. 1/2" atau 3/4" Bh 3.00 335,417.50 1,006,252.50 0.10 - - - - - - - -
5.8 Pasangan 1 Bh Stop Kran (Gate Valve) Dia. 3/4" Bh 1.00 141,417.50 141,417.50 0.01 - - - - - - - -
5.9 Pasangan Mesin Air Bh 1.00 741,000.00 741,000.00 0.07 - - - - - - - -
5.10 Menara Reservoir 200x150x350 cm
5.10.1 Pekerjaan Pondasi Pedestal Pd1
5.10.1.1 Galian Tanah Pondasi Poerplat < 1 m M3 1.62 73,837.50 119,616.75 0.01 - - - - - - - -
5.10.1.2 Urugan Tanah Kembali Pondasi Poerplat M3 0.43 54,175.00 23,295.25 0.00 - - - - - - - -
5.10.1.3 Tiang Pondasi Pedestal 50x50 cm - - -
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.80 1,118,216.00 894,572.80 0.09 - - - - - - - -
Bekisting 2x Pakai M2 3.20 193,468.00 619,097.60 0.06 - - - - - - - -
Besi Beton Ø12 SNI, Ø8 SNI Kg 49.44 21,464.85 1,061,130.60 0.11 - - - - - - - -
5.10.1.4 Pondasi Poerplat 90x90 cm, T.20 cm
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.65 1,118,216.00 726,840.40 0.07 - - - - - - - -
Bekisting 2x Pakai M2 1.44 107,013.50 154,099.44 0.02 - - - - - - - -
Besi Beton Ø14 SNI Kg 214.35 21,464.85 4,600,940.54 0.46 - - - - - - - -
5.10.2 Rangka Tengah dan Lantai Menara (Besi Hollow Galvanis 4/4) M2 34.82 244,970.00 8,529,855.40 0.86 - - - - - - - -
5.10.3 Rangka Utama Menara (Besi Hollow Galvanis 5/10) M' 32.28 179,454.00 5,792,775.12 0.59 - - - - - - - -
5.10.4 Plat Baja Lantai Menara T.3 mm M2 3.00 740,164.86 2,220,494.57 0.22 - - - - - - - -
5.10.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) M2 5.00 244,970.00 1,224,850.00 0.12 - - - - - - - -

TOTAL PEKERJAAN PLAMBING DAN SANITASI 42,151,921.52 4.26 0.00 0.00 0.00

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Pek. Pembersian Awal m2 81.86 17,600.00 1,440,780.00 0.15 - - - 81.86 100.00 0.15 81.86 100.00 0.15
1.2 Pek. Pengukuran & Pemasangan Bouwplank m1 48.60 106,461.25 5,174,016.75 0.52 - - - 48.60 100.00 0.52 48.60 100.00 0.52

TOTAL PEKERJAAN PERSIAPAN 6,614,796.75 0.67 0.00 0.67 0.67

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Batu Kali (Badan Bangunan,Ruang Bilas)
2.1.1.1 Galian Pondasi Batu Kali < 1 m m3 22.05 73,892.50 1,629,329.63 0.16 - - - 6.62 30.00 0.05 6.62 30.00 0.05
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.1.1.2 Urugan Pasir Dibawah Pondasi Batu Kali T.5 cm m3 1.05 174,757.00 183,494.85 0.02 - - - 1.05 100.00 0.02 1.05 100.00 0.02
2.1.1.3 Pasangan Aanstamping Bawah Pondasi Batu Kali T.10 cm m3 2.10 392,699.70 824,669.37 0.08 - - - 2.10 100.00 0.08 2.10 100.00 0.08
2.1.1.4 Urugan Tanah Kembali Pondasi Batu Kali m3 10.08 54,285.00 547,192.80 0.06 - - - 3.02 30.00 0.02 3.02 30.00 0.02
2.1.1.5 Pondasi Batu Kali 1 Sp : 3 Pp m3 8.82 824,945.00 7,276,014.90 0.73 - - - 8.82 100.00 0.73 8.82 100.00 0.73
2.1.2 Perjaan Pondasi Rollage L.15 cm (Selasar)
2.1.2.1 Galian Tanah Pondasi Rollage < 1 m m3 1.52 73,892.50 112,501.33 0.01 - - - - - - - -
2.1.2.2 Urugan Pasir Dibawah Pondasi Rollage T.5 cm m3 0.30 174,757.00 53,213.51 0.01 - - - - - - - -
2.1.2.3 Pasangan Lantai Kerja Bawah Pondasi Rollage T.5 cm (Beton K300) m3 0.30 1,118,398.60 340,552.37 0.03 - - - - - - - -
2.1.2.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp m3 14.21 128,260.00 1,822,574.60 0.18 - - - - - - - -
2.2 Pekerjaan Sloef, Kolom, Plat dan Ringbalk -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Ruang Bilas) -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 m3 1.41 1,118,398.60 1,580,297.22 0.16 - - - 1.41 100.00 0.16 1.41 100.00 0.16
2.2.1.2 Bekisting 2x Pakai m2 9.42 114,467.10 1,078,280.08 0.11 - - - 9.42 100.00 0.11 9.42 100.00 0.11
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI kg 243.74 21,465.73 5,232,043.29 0.53 - - - 243.74 100.00 0.53 243.74 100.00 0.53
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan) -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slum (12 - 2) cm, w/c = 0,52 m3 0.48 1,118,398.60 533,476.13 0.05 - - - 0.48 100.00 0.05 0.48 100.00 0.05
2.2.2.2 Bekisting 2x Pakai m2 3.18 193,504.30 615,343.67 0.06 - - - 3.18 100.00 0.06 3.18 100.00 0.06
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI kg 98.75 21,465.73 2,119,732.25 0.21 - - - 98.75 100.00 0.21 98.75 100.00 0.21
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Ruang Bilas) -
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.25 1,008,343.60 249,111.29 0.03 - - - - - - - -
2.2.3.2 Bekisting 2x Pakai m2 1.65 193,504.30 318,701.58 0.03 - - - - - - - -
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI kg 51.14 21,465.73 1,097,861.33 0.11 - - - - - - - -
2.2.4 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan) -
2.2.4.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.04 1,008,343.60 1,043,635.63 0.11 - - - - - - - -
2.2.4.2 Bekisting 2x Pakai m2 6.90 197,959.30 1,365,919.17 0.14 - - - - - - - -
2.2.4.3 Besi Beton Ø12 SNI, Ø6 SNI kg 148.86 21,465.73 3,195,302.68 0.32 - - - - - - - -
2.2.5 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan) -
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.09 1,008,343.60 1,103,531.24 0.11 - - - - - - - -
2.2.5.2 Bekisting 2x Pakai m2 14.59 197,959.30 2,888,622.11 0.29 - - - - - - - -
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI kg 157.40 21,465.73 3,378,705.12 0.34 - - - - - - - -
2.2.6 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Pintu Jendela)
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.15 1,008,343.60 148,831.52 0.02 - - - - - - - -
2.2.6.2 Bekisting 2x Pakai m2 0.98 197,959.30 194,791.95 0.02 - - - - - - - -
2.2.6.3 Besi Beton Ø10 SNI, Ø6 SNI kg 20.35 21,465.73 436,752.39 0.04 - - - - - - - -
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) m2 59.01 163,856.00 9,669,142.56 0.98 - - - - - - - -
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4) m2 48.59 102,876.77 4,998,782.09 0.50 - - - - - - - -
2.5 Pekerjaan Rangka Plafond dan Dinding Dalam PVC Shunda (Besi Hollow Metal Galvalume 4/4) m2 56.16 102,876.77 5,777,559.22 0.58 - - - - - - - -

TOTAL PEKERJAAN STRUKTUR 59,815,965.86 6.04 0.00 2.03 2.03

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) m3 4.09 174,757.00 715,280.40 0.07 - - - - - - - -
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) m3 12.28 167,345.00 2,054,804.70 0.21 - - - - - - - -
3.1.1.3 Rabat Beton T.5 cm (Keseluruhan, Beton K300) m3 4.09 1,118,398.60 4,577,605.47 0.46 - - - - - - - -
3.1.1.4 Penutup Lantai Keramik Tekstur 60x60 (Badan Bangunan) m2 36.93 413,098.40 15,255,723.91 1.54 - - - - - - - -
3.1.1.5 Penutup Lantai Andesit Polos 30x30 (Selasar, Ruang Bilas) m2 45.89 284,369.80 13,049,730.12 1.32 - - - - - - - -
3.1.1.6 Penutup Plat Wastafel (Granit 60x60, Toilet Pria dan Wanita) m2 2.20 841,621.73 1,851,567.81 0.19 - - - - - - - -
3.1.2 Pekerjaan Dinding -
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Selasar, 1 Sp : 4 Pp) 90.64 242,533.50 21,983,236.44 2.22 - - - 72.51 80.00 1.78 72.51 80.00 1.78
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Wc ) 30.00 65,473.32 1,964,199.60 0.20 - - - 24.00 80.00 0.16 24.00 80.00 0.16
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm 121.28 60,304.20 7,313,693.38 0.74 - - - 97.02 80.00 0.59 97.02 80.00 0.59
3.1.2.4 Coating Bening 121.28 46,853.13 5,682,347.00 0.57 - - - - - - - -
3.1.2.5 Dinding Andesit Polos 30x30 cm ( Wc, Ruang Bilas ) 56.52 284,369.80 16,072,581.10 1.62 - - - - - - - -
3.1.2.6 Dinding Keramik 30x60 cm ( Sisi Dalam ) 69.88 370,557.00 25,894,523.16 2.62 - - - - - - - -
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) 9.00 995,076.50 8,955,688.50 0.90 - - - - - - - -
3.1.2.8 Cubicle Panel + Accessories (Pintu Wc dan Partisi Urinoir) 10.86 1,360,000.00 14,769,600.00 1.49 - - - - - - - -
3.1.2.9 Dinding Bitumen Gelombang 48.59 201,749.24 9,802,995.57 0.99 - - - - - - - -
3.1.2.10 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Pria) 1.00 1,200,000.00 1,200,000.00 0.12 - - - - - - - -
3.1.2.11 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Wanita) 1.00 750,000.00 750,000.00 0.08 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.1.3 Plafond dan Dinding Dalam Shunda ( Badan Bangunan ) 56.16 125,878.50 7,069,336.56 0.71 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.2 Pekerjaan Pintu dan Jendela ( Badan Bangunan ) -
3.2.1 Pintu P1 -
3.2.1.1 Pasangan Kusen Almunium Coating P1 (4" x 13/4") cm 10.96 157,199.02 1,722,901.26 0.17 - - - - - - - -
3.2.1.2 Pasangan Daun Pintu P1 (Panel Almunium Coating - Coating) 4.30 870,323.19 3,742,389.72 0.38 - - - - - - - -
3.2.1.3 Pasangan Kunci Tanam 2x Slag P1 2.00 416,663.50 833,327.00 0.08 - - - - - - - -
3.2.1.4 Pasangan ensel P1 6.00 61,225.56 367,353.36 0.04 - - - - - - - -
3.2.1.5 Pasangan Doorcloser P1 2.00 241,902.10 483,804.20 0.05 - - - - - - - -
3.2.1.6 Pasangan Handle P1 2.00 229,802.10 459,604.20 0.05 - - - - - - - -
3.2.2 Jendela J1 -
3.2.2.1 Pasangan Kusen Almunium Coating J1 (4" x 13/4") cm 28.80 157,199.02 4,527,331.78 0.46 - - - - - - - -
3.2.2.2 Pasangan Kaca Mati 5 mm J1 0.60 145,705.56 87,423.34 0.01 - - - - - - - -
3.2.3 Jendela J2
3.2.3.1 Pasangan Kusen Almunium Coating J2 (4" x 13/4") cm 55.20 157,199.02 8,677,385.90 0.88 - - - - - - - -
3.2.3.2 Pasangan Kaca Mati 5 mm J2 0.90 145,705.56 131,135.00 0.01 - - - - - - - -
3.3. Pengecetan Plafond (1 Plamir : 1 Cat Dasar : 2 Cat Penutup), (Interior) 56.16 43,550.65 2,445,804.50 0.25 - - - - - - - -
3.4 Pekerjaan Atap -
3.4.1 Atap Bitumen Gelombang (Badan Bangunan) 59.01 201,749.24 11,905,222.65 1.20 - - - - - - - -
3.4.2 Nok Bitumen (Badan Bangunan) 35.25 143,629.20 5,062,929.30 0.51 - - - - - - - -
3.4.3 Listplank (Kasiplank, Badan Bangunan, Enterance) 39.08 70,972.00 2,773,585.76 0.28 - - - - - - - -

TOTAL PEKERJAAN FINISHING ARSITEKTUR 202,183,111.69 20.42 0.00 2.53 2.53

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel 1.00 1,803,826.75 1,803,826.75 0.18 - - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt 10.00 353,938.75 3,539,387.50 0.36 - - - - - - - -
4.1.3 Pasangan Lampu Down Light 2.5" Outbow LED 5.5 Watt 12.00 305,538.75 3,666,465.00 0.37 - - - - - - - -
4.1.4 Pasangan Saklar Ganda 5.00 223,478.75 1,117,393.75 0.11 - - - - - - - -
4.2 Pasangan Instalasi Stop Kontak -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA 3.00 216,218.75 648,656.25 0.07 - - - - - - - -
4.2.2 Pasangan Stop Kontak Wall Exhauser 6.00 216,218.75 1,297,312.50 0.13 - - - - - - - -
4.3 Pasangan Instalasi Jaringan Wall Exhauser 12.00 108,772.68 1,305,272.10 0.13 - - - - - - - -
4.3.1 Pasangan Wall Exhauser 12 Inch - FV30RUN 6.00 513,500.00 3,081,000.00 0.31 - - - - - - - -
4.4 Pasangan Penangkal Petir 1.00 3,500,000.00 3,500,000.00 0.35 - - - - - - - -
4.5 Pasangan Instlasi Jaringan Kabel Fiber Optic (CCTV) 3.00 786,326.75 2,358,980.25 0.24 - - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2 MP (Luar Bangunan, Sambungan Dari Mini Resto) 3.00 656,975.00 1,970,925.00 0.20 - - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm 4.00 20,442.68 81,770.70 0.01 - - - - - - - -
4.6.1 Pasangan Horn Speaker (Sambungan Dari Mini Resto) 2.00 494,826.75 989,653.50 0.10 - - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25 kg) 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - - -
4.8 Pasangan Instalasi PLN Power 1.00 10,000,000.00 10,000,000.00 1.01 - - - - - - - -

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 44,560,643.30 4.50 0.00 0.00 0.00

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVc Tipe AW Diameter 3/4" (Air Bersih Dari Sumur Bor / PDAM Reservoir) m1 18.50 28,304.65 523,636.03 0.05 - - - - - - - -
5.2 Pipa PVC Tipe AW Diameter 3/4" (Distribusi Air Bersih Dari Reservoir) m1 26.50 28,304.65 750,073.23 0.08 - - - - - - - -
5.3 Pipa PVC Tipe AW Diameter 3" (Air Kotor Ke Drainase Lingkungan) m1 23.00 135,539.80 3,117,415.40 0.31 - - - - - - - -
5.4 Pipa PVC Tipe AW Diameter 4" (Disposal) m1 18.00 186,689.80 3,360,416.40 0.34 - - - - - - - -
5.5 Pasangan 1 bh Closet Duduk / Monoblock (TOTO) bh 6.00 3,655,597.00 21,933,582.00 2.22 - - - - - - - -
5.6 Pasangan 1 bh Wastafel (TOTO) 3.00 3,571,942.00 10,715,826.00 1.08 - - - - - - - -
5.7 Pasangan 1 bh Uninoir (TOTO) 2.00 6,665,285.00 13,330,570.00 1.35 - - - - - - - -
5.8 Pasangan 1 bh Floor Drain 9.00 41,123.50 370,111.50 0.04 - - - - - - - -
5.9 Pasangan 1 bh Kran dia. 1/2' atau 3/4" 8.00 102,228.50 817,828.00 0.08 - - - - - - - -
5.10 Pasangan 1 bh Kran wastafel dia. 1/2' atau 3/4" 2.00 335,428.50 670,857.00 0.07 - - - - - - - -
5.11 Pasangan 1 bh shower closet dia. 1/2' atau 3/4" 6.00 142,928.50 857,571.00 0.09 - - - - - - - -
5.12 Pasangan 1 bh shower Wall dia. 1/2' atau 3/4" (Ruang Bilas) 4.00 1,435,428.50 5,741,714.00 0.58 - - - - - - - -
5.13 Pasangan 1 bh Stop Kran (Gate Valve) dia. 3/4" 2.00 141,428.50 282,857.00 0.03 - - - - - - - -
5.14 Pasangan Mesin Air 1.00 741,000.00 741,000.00 0.07 - - - - - - - -
5.14b Pasangan Mesin Pemanas Air 1.00 5,000,000.00 5,000,000.00 0.51 - - - - - - - -
5.15 Septictank Biotank Kap. 4m3 1.00 20,380,000.00 20,380,000.00 2.06 - - - - - - - -
5.16 Pasangan Sumur Bor Jet Pump 30.00 350,000.00 10,500,000.00 1.06 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.17 Reservoir 1200 Liter 1.00 1,850,000.00 1,850,000.00 0.19 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.18 Reservoir 200x150x350 cm -
5.18.1 Pekerjaan Pondasi Pedestal Pd1 -
5.18.1.1 Galian Tanah Pondasi Poerplat < 1m 1.62 74,250.00 120,285.00 0.01 - - - - - - - -
5.18.1.2 Urugan Tanah Kembali Pondasi Poerplat 0.43 55,000.00 23,760.00 0.00 - - - - - - - -
5.18.1.3 Tiang Pondasi Pedestal 50x50 cm
Beton Mutu fc = 26,6 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.80 1,485,144.21 1,188,115.37 0.12 - - - - - - - -
Bekisting 2x Pakai 3.20 193,504.30 619,213.76 0.06 - - - - - - - -
Besi Beton Ø12, Ø8 49.44 21,465.73 1,061,174.10 0.11 - - - - - - - -
5.18.1.4 Pondasi Poerplat 90x90 cm,T.20 cm -
Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.65 1,485,144.21 962,373.45 0.10 - - - - - - - -
Bekisting 2x Pakai 1.44 124,547.50 179,348.40 0.02 - - - - - - - -
Besi Beton Ø14 SNI 214.35 21,465.73 4,601,114.73 0.46 - - - - - - - -
5.18.2 Rangkai Tengah Dan Lantai Menara (Besi Hollow Galvanis 4/4) 34.82 244,970.00 8,529,855.40 0.86 - - - - - - - -
5.18.3 Rangka Utama menara ( Besi Hollow Galvanis 5/10 32.28 179,454.00 5,792,775.12 0.59 - - - - - - - -
5.18.4 Tplat Baja Lantai Menara T.3mm 3.00 740,164.86 2,220,494.57 0.22 - - - - - - - -
5.18.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) 5.00 244,970.00 1,224,850.00 0.12 - - - - - - - -

TOTAL PEKERJAAN PLAMBING DAN SANITASI 127,466,817.45 12.88 - - -

6. PEKERJAAN AKHIR - - -
6.1 Pembersihan Sisa Pekerjaan Ls 1.00 2,400,000.00 2,400,000.00 0.24 - - - - - - - -

TOTAL PEKERJAAN AKHIR 2,400,000.00 0.24 0.00 0.00 0.00

C. PENERAPAN SMKK

1. PENYIAPAN RKK
1.1 Pembuatan Dokumen Rencana Keselamatan Konstruksi
1.2 Pembuatan Prosedur dan instruksi kerja Set 1.00 2,000,000.00 2,000,000.00 0.20 1.00 100.00 0.20 - - 1.00 100.00 0.20
1.3 Penyiapan formulir
TOTAL PENYIAPAN RKK 2,000,000.00 0.20 0.20 - 0.20
2. SOSIALISASI, PROMOSI DAN PELATIHAN
2.1 Induksi K3 (Safety Induction) Org 5.00 7,500.00 37,500.00 0.00 0.50 10.00 0.00 - - 0.50 10.00 0.00
2.2 Pengarahan K3 (Safety Briefing) Org 5.00 15,000.00 75,000.00 0.01 5.00 100.00 0.01 - - 5.00 100.00 0.01
2.3 Pelatihan K3 -
2.3.1 Bekerja di ketinggian Org 4.00 7,500.00 30,000.00 0.00 4.00 100.00 0.00 - - 4.00 100.00 0.00
2.3.2 Penggunaan Bahan Kimia (MSDS) Org 2.00 7,500.00 15,000.00 0.00 2.00 100.00 0.00 - - 2.00 100.00 0.00
2.4 Simulasi K3 Org 5.00 7,500.00 37,500.00 0.00 5.00 100.00 0.00 - - 5.00 100.00 0.00
2.5 Spanduk (Banner) Lb 1.00 150,000.00 150,000.00 0.02 1.00 100.00 0.02 - - 1.00 100.00 0.02
2.6 Poster 2 2.00 50,000.00 100,000.00 0.01 2.00 100.00 0.01 - - 2.00 100.00 0.01
2.7 Papan Informasi K3 1 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
TOTAL SOSIALISASI, PROMOSI DAN PELATIHAN 945,000.00 0.10 0.09 - 0.09
3. ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI
3.1 APK
3.1.1 Tali Keselamatan (Life Line) Ls 1.00 1,700,000.00 1,700,000.00 0.17 1.00 100.00 0.17 - - 1.00 100.00 0.17
3.1.2 Pembatas Area (Restricted Area) Ls 1.00 2,000,000.00 2,000,000.00 0.20 1.00 100.00 0.20 - - 1.00 100.00 0.20
3.2 APD
3.2.1 Topi Pelindung (Safety Helmet) Bh 10.00 75,000.00 750,000.00 0.08 10.00 100.00 0.08 - - 10.00 100.00 0.08
3.2.2 Pelindung Mata (Googles, Spectacles) Bh 5.00 25,000.00 125,000.00 0.01 5.00 100.00 0.01 - - 5.00 100.00 0.01
3.2.3 Pelindung Pernapasan dan Mulut (Masker) Bh 100.00 5,000.00 500,000.00 0.05 100.00 100.00 0.05 - - 100.00 100.00 0.05
3.2.4 Sarung Tangan (Safety Gloves) Psg 10.00 15,000.00 150,000.00 0.02 10.00 100.00 0.02 - - 10.00 100.00 0.02
3.2.5 Sepatu Keselamatan (Safety Shoes) Psg 10.00 350,000.00 3,500,000.00 0.35 10.00 100.00 0.35 - - 10.00 100.00 0.35
3.2.6 Penunjang Seluruh Tubuh (Full Body Harness) Bh 2.00 500,000.00 1,000,000.00 0.10 2.00 100.00 0.10 - - 2.00 100.00 0.10
3.2.7 Rompi Keselamatan (Safety Vest) Bh 10.00 25,000.00 250,000.00 0.03 10.00 100.00 0.03 - - 10.00 100.00 0.03
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 9,975,000.00 1.01 1.01 - 1.01
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4. ASURANSI DAN PERIZINAN
4.1 Asuransi Ls 1.00 3,000,000.00 3,000,000.00 0.30 1.00 100.00 0.30 - - 1.00 100.00 0.30
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 3,000,000.00 0.30 0.30 - 0.30
5. PERSONEL K3 KONSTRUKSI
5.1 Ahli K3 Konstruksi -
5.2 Petugas K3 Konstruksi Ob 4.00 3,675,000.00 14,700,000.00 1.48 4.00 100.00 1.48 - - 4.00 100.00 1.48
TOTAL PERSONEL K3 KONSTRUKSI 14,700,000.00 1.48 1.48 - 1.48
6. FASILITAS, SARANA DAN PRASARANA KESEHATAN
6.1 Peralatan P3K (Kotak P3K, Tandu, Obat Luka, Perban, dll) Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
TOTAL FASILITAS, SARANA DAN PRASARANA KESEHATAN 500,000.00 0.05 0.05 - 0.05
7. RAMBU - RAMBU YANG DIPERLUKAN
7.1 Rambu Petunjuk bh 2.00 75,000.00 150,000.00 0.02 2.00 100.00 0.02 - - 2.00 100.00 0.02
7.2 Rambu Larangan bh 2.00 75,000.00 150,000.00 0.02 2.00 100.00 0.02 - - 2.00 100.00 0.02
7.3 Rambu Peringatan bh 2.00 100,000.00 200,000.00 0.02 2.00 100.00 0.02 - - 2.00 100.00 0.02
7.4 Jalur Evakuasi (Escape Route) Ls 1.00 250,000.00 250,000.00 0.03 1.00 100.00 0.03 - - 1.00 100.00 0.03
TOTAL RAMBU - RAMBU YANG DIPERLUKAN 750,000.00 0.08 0.08 - 0.08
8. KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI
8.1 Ahli K3 Konstruksi Oj -
TOTAL KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI - 0.00
9. LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN
KONSTRUKSI
9.1 Alat Pemadam Api Ringan (APAR) bh 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
9.2 Program Inspeksi Ls 1.00 1,500,000.00 1,500,000.00 0.15 1.00 100.00 0.15 - - 1.00 100.00 0.15
9.3 Pelaporan dan Penyeledikan Insiden Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
9.4 Pembuatan Kartu Identitas Pekerja (KIP) Org 10.00 5,000.00 50,000.00 0.01 10.00 100.00 0.01 - - 10.00 100.00 0.01
TOTAL LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN KONSTRUKSI 2,550,000.00 0.26 0.26 - 0.26

A Jumlah Harga Penawaran 989,944,870.91 100.00 14.72 9.86 24.58


B PPN (10%) 98,994,487.09
C Jumlah (A+B) 1,088,939,358.00
PERSENTASE SAMPAI MINGGU INI 24.58
D Jumlah Dibulatkan 1,088,939,358.00

Bulukumba, 05 November 2020


Disetujui, Diketahui, Diperiksa Oleh, Dibuat Oleh,
Pejabat Pembuat Komitmen Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUTR Prov SulSel Dinas PUTR Prov SulSel CV.MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

A.KHADAFI HARUN, ST.,MT. L I L I, ST. IRHAM HARAHAP, ST. VIKA APRILIA DWI PUTRI
NIP. 19811126 200901 1 008 NIP. 19821229 201503 2 001 Site Engineer Direktris
LAPORAN KEMAJUAN MINGGUAN

Kegiatan : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba Minggu Ke : 04 ( Empat )
Satuan Kerja : Dinas Pekerjaan Umum Dan Tata Ruang Prov. Sulawesi Selatan Bidang Cipta Karya Periode : 06 November S/d 12 November 2020
Lokasi : Desa Ara, Kecamatan Bonto Bahari, Kabupaten Bulukumba, Provinsi Sulawesi Selatan No. Kontrak : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
Sumber Dana : Dana Bantuan Provinsi Nilai Kontrak : Rp. 1,088,939,358.00
Tahun Anggaran : 2020 Schedule Pelaksanaan : 16 Oktober S/d 14 Desember 2020

MINGGU LALU MINGGU INI S/D MINGGU INI


VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
NO URAIAN PEKERJAAN
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q

A. PEMBANGUNAN RUANG KULINER, SUVENIR, MUSHOLLAH DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Papan Proyek Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
1.2 Bedeng/Direksi Keet M2 5.50 1,512,555.00 8,319,052.50 0.84 5.50 100.00 0.84 - - 5.50 100.00 0.84

TOTAL PEKERJAAN PERSIAPAN 8,819,052.50 0.89 0.89 0.00 0.89

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Poerplat PP1 (Selasar Samping)
2.1.1.1 Galian Pondasi Poerplat < 1 m M3 0.32 73,837.50 23,628.00 0.00 0.32 100.00 0.00 - - 0.32 100.00 0.00
2.1.1.2 Urugan Pasir dibawah Pondasi Poerplat T.5 cm M3 0.04 148,335.00 5,933.40 0.00 0.04 100.00 0.00 - - 0.04 100.00 0.00
2.1.1.3 Urugan Tanah Kembali Pondasi Poerplat M3 0.31 54,175.00 16,794.25 0.00 0.31 100.00 0.00 - - 0.31 100.00 0.00
2.1.1.4 Pasangan Lantai Kerja bawah Pondasi Poerplat T.5 cm (Beton K300) M3 0.04 1,118,216.00 44,728.64 0.00 0.04 100.00 0.00 - - 0.04 100.00 0.00
2.1.1.5 Pondasi Poerplat 35x50 cm, T.20 cm -
Beton Mutu F'c = 26,4 mpa (K300), Slump (12-2) cm, w/c = 0,52 M3 0.14 1,118,216.00 156,550.24 0.02 0.14 100.00 0.02 - - 0.14 100.00 0.02
Bekisting 2x Pakai M2 0.56 107,013.50 59,927.56 0.01 0.56 100.00 0.01 - - 0.56 100.00 0.01
Besi Beton Ø14 SNI Kg 29.40 21,464.85 631,066.59 0.06 29.40 100.00 0.06 - - 29.40 100.00 0.06
2.1.2 Pekerjaan Pondasi Batu Kali (Badan Bangunan, Mushollah) - -
2.1.2.1 Galian Tanah Pondasi Batu Kali < 1 m M3 22.73 73,837.50 1,678,326.38 0.17 22.73 100.00 0.17 - - 22.73 100.00 0.17
2.1.2.2 Urugan Pasir dibawah Pondasi Batu Kali T.5 cm M3 1.08 148,335.00 160,201.80 0.02 1.08 100.00 0.02 - - 1.08 100.00 0.02
2.1.2.3 Pasangan Aanstamping bawah Pondasi Batu Kali T.10 M3 2.17 382,674.00 830,402.58 0.08 2.17 100.00 0.08 - - 2.17 100.00 0.08
2.1.2.4 Urugan Tanah Kembali Pondasi Batu Kali M3 10.39 54,175.00 562,878.25 0.06 10.39 100.00 0.06 - - 10.39 100.00 0.06
2.1.2.5 Pondasi Batu Kali 1 Sp : 3 Pp M3 9.09 827,447.50 7,521,497.78 0.76 9.09 100.00 0.76 - - 9.09 100.00 0.76
2.1.3 Pekerjaan Pondasi Rollage L.15 cm (Entrance, Selasar Samping) - - -
2.1.3.1 Galian Tanah Pondasi Rollage < 1 m M3 2.23 73,837.50 164,657.63 0.02 2.23 100.00 0.02 - - 2.23 100.00 0.02
2.1.3.2 Urugan Pasir dibawah Pondasi Rollage T.5 cm M3 0.45 148,335.00 66,750.75 0.01 0.45 100.00 0.01 - - 0.45 100.00 0.01
2.1.3.3 Pasangan Lantai Kerja bawah Pondasi Rollage T.5 cm (Beton K300) M3 0.45 1,118,216.00 499,003.89 0.05 0.45 100.00 0.05 - - 0.45 100.00 0.05
2.1.3.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp M2 20.83 128,436.00 2,675,321.88 0.27 20.83 100.00 0.27 - - 20.83 100.00 0.27
2.2 Pekerjaan Sloef, Kolom dan Ringbalk - -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Mushollah) - -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 1.62 1,118,216.00 1,815,703.23 0.18 1.62 100.00 0.18 - - 1.62 100.00 0.18
2.2.1.2 Bekisting 2x Pakai M2 10.83 114,438.50 1,239,368.96 0.13 10.83 100.00 0.13 - - 10.83 100.00 0.13
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI Kg 280.09 21,464.85 6,012,089.84 0.61 280.09 100.00 0.61 - - 280.09 100.00 0.61
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan, Mushollah) - -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.88 1,118,216.00 981,234.54 0.10 0.88 100.00 0.10 - - 0.88 100.00 0.10
2.2.2.2 Bekisting 2x Pakai M2 5.85 193,468.00 1,131,787.80 0.11 5.85 100.00 0.11 - - 5.85 100.00 0.11
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 181.66 21,464.85 3,899,347.58 0.39 181.66 100.00 0.39 - - 181.66 100.00 0.39
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Selasar, Westafel, Tempat Wudhu) -
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 0.34 100.00 0.03 - - 0.34 100.00 0.03
2.2.3.2 Bekisting 2x Pakai M2 2.26 193,468.00 437,237.68 0.04 2.26 100.00 0.04 - - 2.26 100.00 0.04
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 70.10 21,464.85 1,504,686.30 0.15 70.10 100.00 0.15 - - 70.10 100.00 0.15
2.2.4 Pekerjaan Kolom K1 15 x 30 (Selasar Samping) - -
2.2.4.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.62 1,118,216.00 694,412.14 0.07 0.62 100.00 0.07 - - 0.62 100.00 0.07
2.2.4.2 Bekisting 2x Pakai M2 6.21 193,468.00 1,201,436.28 0.12 6.21 100.00 0.12 - - 6.21 100.00 0.12
2.2.4.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 99.69 21,464.85 2,139,830.90 0.22 99.69 100.00 0.22 - - 99.69 100.00 0.22
2.2.5 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan, Mushollah) - -
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 2.08 1,008,161.00 2,097,478.96 0.21 2.08 100.00 0.21 - - 2.08 100.00 0.21
2.2.5.2 Bekisting 2x Pakai M2 13.87 197,923.00 2,745,192.01 0.28 13.87 100.00 0.28 - - 13.87 100.00 0.28
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 299.22 21,464.85 6,422,712.42 0.65 299.22 100.00 0.65 - - 299.22 100.00 0.65
2.2.6 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan) -
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 0.34 100.00 0.03 - - 0.34 100.00 0.03
2.2.6.2 Bekisting 2x Pakai M2 2.24 197,923.00 443,347.52 0.04 2.24 100.00 0.04 - - 2.24 100.00 0.04
2.2.6.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 48.32 21,464.85 1,037,181.55 0.10 48.32 100.00 0.10 - - 48.32 100.00 0.10
2.2.7 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Mushollah, Pintu Jendela) -
2.2.7.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.84 1,008,161.00 846,855.24 0.09 0.84 100.00 0.09 - - 0.84 100.00 0.09
2.2.7.2 Bekisting 2x Pakai M2 5.59 197,923.00 1,106,389.57 0.11 5.59 100.00 0.11 - - 5.59 100.00 0.11
2.2.7.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 115.53 21,464.85 2,479,834.12 0.25 115.53 100.00 0.25 - - 115.53 100.00 0.25
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.2.8 Pekerjaan Plat Beton (Selasar Samping, Westafel) -
2.2.8.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.22 1,008,161.00 221,795.42 0.02 0.22 100.00 0.02 - - 0.22 100.00 0.02
2.2.8.2 Bekisting 2x Pakai M2 2.21 237,468.00 524,804.28 0.05 2.21 100.00 0.05 - - 2.21 100.00 0.05
2.2.8.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 54.54 21,464.85 1,170,692.92 0.12 54.54 100.00 0.12 - - 54.54 100.00 0.12
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) M2 152.03 163,636.00 24,877,581.08 2.51 152.03 100.00 2.51 - - 152.03 100.00 2.51
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4, Entrance) M2 42.24 242,170.50 10,229,281.92 1.03 - - - 42.24 100.00 1.03 42.24 100.00 1.03
2.5 Pekerjaan Tiang Atap Bitumen Gelombang (Besi Hollow Galvanis 5/10, Entrance) M' 20.40 178,365.00 3,638,646.00 0.37 - - - 20.40 100.00 0.37 20.40 100.00 0.37
2.6 Pekerjaan Rangka Plafond Kalsiboard (Besi Hollow Metal Galvalume 4/4) M2 147.40 102,837.17 15,158,198.37 1.53 - - - 147.40 100.00 1.53 147.40 100.00 1.53

TOTAL PEKERJAAN STRUKTUR 109,840,345.70 11.10 8.16 2.93 11.10

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) M3 8.54 148,335.00 1,266,780.90 0.13 - - - 8.54 100.00 0.13 8.54 100.00 0.13
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) M3 25.63 167,227.00 4,285,636.74 0.43 - - - 25.63 100.00 0.43 25.63 100.00 0.43
3.1.1.3 Rabat Beton bawah Lantai T.5 cm (Keseluruhan, Beton K300) M3 8.54 1,118,216.00 9,549,564.64 0.96 - - - 8.54 100.00 0.96 8.54 100.00 0.96
3.1.1.4 Penutup Lantai Keramik Motif 60x60 (Badan Bangunan, Mushollah) M2 62.94 403,309.50 25,384,299.93 2.56 - - - - - - - -
3.1.1.5 Penutup Lantai Conwood Deck 6" (Entrance) M2 59.01 866,833.08 51,151,820.09 5.17 - - - - - - - -
3.1.1.6 Penutup Lantai Andesit Polos 30x30 (Selasar, Tempat Wudhu, Ram) M2 51.05 232,589.50 11,873,693.98 1.20 - - - - - - - -
3.1.1.7 Plint Lantai Keramik 10x60 (Badan Bangunan, Mushollah) M' 38.85 51,605.03 2,004,855.55 0.20 - - - - - - - -
3.1.2 Pekerjaan Dinding -
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Mushollah, 1 Sp : 4 Pp) M2 74.55 242,979.00 18,114,084.45 1.83 74.55 100.00 1.83 - - 74.55 100.00 1.83
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Selasar Samping, Tempat Wudhu) M2 5.14 65,550.32 336,928.64 0.03 - - - - - - - -
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm (Badan Bangunan, Mushollah) M2 91.30 60,403.20 5,514,812.16 0.56 91.30 100.00 0.56 - - 91.30 100.00 0.56
3.1.2.4 Plesteran Ciprat 1 Sp : 2 Pp Tebal 15 mm (Selasar Samping, Antar Kolom) M2 24.84 49,215.10 1,222,503.08 0.12 - - - - - - - -
3.1.2.5 Dinding Keramik Mozaik 30x60 (Selasar Samping, Westafel, Tempat Wudhu) M2 18.44 410,432.00 7,568,366.08 0.76 - - - - - - - -
3.1.2.6 Coating Bening (Badan Bangunan, Mushollah, Kolom Luar) M2 127.49 45,973.13 5,861,113.71 0.59 - - - - - - - -
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) M2 8.64 995,043.50 8,597,175.84 0.87 - - - - - - - -
3.1.2.8 Dinding Wallpaper Bata L.50 cm (Sisi Dalam) M2 28.13 80,005.50 2,250,554.72 0.23 - - - - - - - -
3.1.3 Pekerjaan Plafond -
3.1.3.1 Plafond Kalsiboard (Badan Bangunan, Kemiringan Atap, Mushollah) M2 147.40 44,924.00 6,621,797.60 0.67 - - - - - - - -
3.1.3.2 Plafond Kalsiboard (Lapis Bawah Atap, Entrance) M2 42.24 44,924.00 1,897,589.76 0.19 - - - - - - - -
3.2 Pekerjaan Pintu dan Jendela (Badan Bangunan) -
3.2.1 Pintu P1 (Entrance dan Back Entrance, Badan Bangunan) -
3.2.1.1 Pasangan Kusen Alumunium Coating P1 (4" x 1 3/4") cm M' 22.40 157,194.40 3,521,154.56 0.36 - - - - - - - -
3.2.1.2 Pasangan Daun Pintu P1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - - -
3.2.1.3 Pasangan Kaca Mati 5 mm P1 M2 11.20 145,703.80 1,631,882.56 0.16 - - - - - - - -
3.2.1.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - - -
3.2.1.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - - -
3.2.1.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - - -
3.2.1.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - - -
3.2.2 Jendela J1 (Badan Bangunan) -
3.2.2.1 Pasangan Kusen Alumunium Coating J1 (4" x 1 3/4") cm M' 40.60 157,194.40 6,382,092.64 0.64 - - - - - - - -
3.2.2.2 Pasangan Kaca Mati 5 mm J1 M2 8.00 145,703.80 1,165,630.40 0.12 - - - - - - - -
3.2.3 Pintu PJ1 (Mushollah) -
3.2.3.1 Pasangan Kusen Alumunium Coating PJ1 (4" x 1 3/4") cm M' 22.20 157,194.40 3,489,715.68 0.35 - - - - - - - -
3.2.3.2 Pasangan Daun Pintu PJ1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - - -
3.2.3.3 Pasangan Kaca Mati 5 mm P1 M2 8.70 145,703.80 1,267,623.06 0.13 - - - - - - - -
3.2.3.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - - -
3.2.3.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - - -
3.2.3.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - - -
3.2.3.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - - -
3.3 Pekerjaan Pengecatan -
3.3.1 Pengecatan Plafond (1 Plamir ; 1 Cat Dasar : 2 Cat Penutup), (Interior) M2 189.64 35,536.05 6,739,056.52 0.68 - - - - - - - -
3.3.2 Pengecatan Rangka Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 23.76 168,454.00 4,002,467.04 0.40 - - - - - - - -
3.3.3 Pengecatan Tiang Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 6.12 168,454.00 1,030,938.48 0.10 - - - - - - - -
3.4 Pekerjaan Atap -
3.4.1 Atap Bitumen Gelombang (Badan Bangunan, Mushollah) M2 152.03 207,297.09 31,515,376.59 3.18 152.03 100.00 3.18 - - 152.03 100.00 3.18
3.4.2 Atap Bitumen Gelombang (Entrance) M2 42.24 207,297.09 8,756,229.08 0.88 42.24 100.00 0.88 - - 42.24 100.00 0.88
3.4.3 Nok Bitumen (Badan Bangunan, Mushollah) M' 14.55 134,101.00 1,951,169.55 0.20 14.55 100.00 0.20 - - 14.55 100.00 0.20
3.4.4 Listplank (Kalsiplank, Badan Bangunan, Mushollah, Entrance) M' 50.00 70,950.00 3,547,500.00 0.36 25.00 50.00 0.18 25.00 50.00 0.18 50.00 100.00 0.36

TOTAL PEKERJAAN FINISHING ARSITEKTUR 257,222,142.77 25.98 6.83 1.70 8.54

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel Bh 1.00 1,572,826.75 1,572,826.75 0.16 - - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt Bh 16.00 353,938.75 5,663,020.00 0.57 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4.1.3 Pasangan Lampu Down Light 2,5" Outbow LED 5,5 Watt Bh 11.00 305,538.75 3,360,926.25 0.34 - - - - - - - -
4.1.4 Pasangan Saklar Tunggal Bh 4.00 211,378.75 845,515.00 0.09 - - - - - - - -
4.1.5 Pasangan Saklar Ganda Bh 2.00 223,478.75 446,957.50 0.05 - - - - - - - -
4.2 Pasangan Instalasi Stop Kontak - -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA Bh 10.00 216,218.75 2,162,187.50 0.22 - - - - - - - -
4.2.2 Pasangan Stop Kontak AC 220 VA/3520 W (AC Split 1 PK) Bh 4.00 253,728.75 1,014,915.00 0.10 - - - - - - - -
4.3 Pasangan Instalasi Jaringan AC M' 30.00 108,772.68 3,263,180.25 0.33 - - - - - - - -
4.3.1 Pasangan AC Split 1 PK Bh 3.00 3,365,799.34 10,097,398.03 1.02 - - - - - - - -
4.4 Pasangan Penangkal Petir Ls 1.00 2,500,000.00 2,500,000.00 0.25 - - - - - - - -
4.5 Pasangan Instalasi Jaringan Kabel Fiber Optic (CCTV) Ttk 6.00 786,326.75 4,717,960.50 0.48 - - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2MP Bh 6.00 656,975.00 3,941,850.00 0.40 - - - - - - - -
4.5.2 Pasangan NVR Channel Set 1.00 5,023,975.00 5,023,975.00 0.51 - - - - - - - -
4.5.3 Pasangan Monitor LCD 32" Bh 1.00 2,944,975.00 2,944,975.00 0.30 - - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm M' 12.00 20,442.68 245,312.10 0.02 - - - - - - - -
4.6.1 Pasangan Horn Speaker Bh 6.00 494,826.75 2,968,960.50 0.30 - - - - - - - -
4.6.2 Pasangan Volume Kontrol Set 1.00 252,826.75 252,826.75 0.03 - - - - - - - -
4.6.3 Pasangan Perangkat Sound System Set 1.00 4,565,000.00 4,565,000.00 0.46 - - - - - - - -
4.6.4 Pasangan TB-Sound System Set 1.00 5,846,326.75 5,846,326.75 0.59 - - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25Kg) Ttk 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - - -
4.8 Pasangan Instalasi Jaringan Kabel Fiber Optic (Akses Point) Ttk 3.00 786,326.75 2,358,980.25 0.24 - - - - - - - -
4.8.1 Pasangan Server Set 1.00 7,578,826.75 7,578,826.75 0.77 - - - - - - - -
4.8.2 Pasangan Akses Point Bh 1.00 2,034,826.75 2,034,826.75 0.21 - - - - - - - -
4.8.3 Pasangan Switch HUB Bh 1.00 2,843,326.75 2,843,326.75 0.29 - - - - - - - -
4.9 Pasangan Instalasi PLN Power (Inc. Jalur ke Mushollah dan Toilet) Ls 1.00 9,000,000.00 9,000,000.00 0.91 - - - - - - - -

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 94,450,073.38 9.54 0.00 0.00 0.00

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVC Type AW Diameter 3/4" (Air Bersih Sambungan dari Tandon) M' 33.00 28,300.25 933,908.25 0.09 - - - - - - - -
5.2 Pipa PVC Type AW Diameter 3" (Air Kotor ke Drainase Lingkungan) M' 25.80 135,531.00 3,496,699.80 0.35 - - - - - - - -
5.3 Pasangan 1 Bh Wastafel Bh 2.00 3,934,865.00 7,869,730.00 0.79 - - - - - - - -
5.4 Pasangan 1 Bh Wastafel Cuci Piring (WCP) Bh 1.00 890,945.00 890,945.00 0.09 - - - - - - - -
5.5 Pasangan 1 Bh Floor Drain Bh 2.00 41,112.50 82,225.00 0.01 - - - - - - - -
5.6 Pasangan 1 Bh Kran Dia. 1/2" atau 3/4" Bh 10.00 102,217.50 1,022,175.00 0.10 - - - - - - - -
5.7 Pasangan 1 Bh Kran Wastafel Dia. 1/2" atau 3/4" Bh 3.00 335,417.50 1,006,252.50 0.10 - - - - - - - -
5.8 Pasangan 1 Bh Stop Kran (Gate Valve) Dia. 3/4" Bh 1.00 141,417.50 141,417.50 0.01 - - - - - - - -
5.9 Pasangan Mesin Air Bh 1.00 741,000.00 741,000.00 0.07 - - - - - - - -
5.10 Menara Reservoir 200x150x350 cm -
5.10.1 Pekerjaan Pondasi Pedestal Pd1 -
5.10.1.1 Galian Tanah Pondasi Poerplat < 1 m M3 1.62 73,837.50 119,616.75 0.01 - - - - - - - -
5.10.1.2 Urugan Tanah Kembali Pondasi Poerplat M3 0.43 54,175.00 23,295.25 0.00 - - - - - - - -
5.10.1.3 Tiang Pondasi Pedestal 50x50 cm - - -
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.80 1,118,216.00 894,572.80 0.09 - - - - - - - -
Bekisting 2x Pakai M2 3.20 193,468.00 619,097.60 0.06 - - - - - - - -
Besi Beton Ø12 SNI, Ø8 SNI Kg 49.44 21,464.85 1,061,130.60 0.11 - - - - - - - -
5.10.1.4 Pondasi Poerplat 90x90 cm, T.20 cm -
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.65 1,118,216.00 726,840.40 0.07 - - - - - - - -
Bekisting 2x Pakai M2 1.44 107,013.50 154,099.44 0.02 - - - - - - - -
Besi Beton Ø14 SNI Kg 214.35 21,464.85 4,600,940.54 0.46 - - - - - - - -
5.10.2 Rangka Tengah dan Lantai Menara (Besi Hollow Galvanis 4/4) M2 34.82 244,970.00 8,529,855.40 0.86 - - - - - - - -
5.10.3 Rangka Utama Menara (Besi Hollow Galvanis 5/10) M' 32.28 179,454.00 5,792,775.12 0.59 - - - - - - - -
5.10.4 Plat Baja Lantai Menara T.3 mm M2 3.00 740,164.86 2,220,494.57 0.22 - - - - - - - -
5.10.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) M2 5.00 244,970.00 1,224,850.00 0.12 - - - - - - - -

TOTAL PEKERJAAN PLAMBING DAN SANITASI 42,151,921.52 4.26 0.00 0.00 0.00

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Pek. Pembersian Awal m2 81.86 17,600.00 1,440,780.00 0.15 81.86 100.00 0.15 - - 81.86 100.00 0.15
1.2 Pek. Pengukuran & Pemasangan Bouwplank m1 48.60 106,461.25 5,174,016.75 0.52 48.60 100.00 0.52 - - 48.60 100.00 0.52

TOTAL PEKERJAAN PERSIAPAN 6,614,796.75 0.67 0.67 0.00 0.67

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Batu Kali (Badan Bangunan,Ruang Bilas)
2.1.1.1 Galian Pondasi Batu Kali < 1 m m3 22.05 73,892.50 1,629,329.63 0.16 6.62 30.00 0.05 - - 6.62 30.00 0.05
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.1.1.2 Urugan Pasir Dibawah Pondasi Batu Kali T.5 cm m3 1.05 174,757.00 183,494.85 0.02 1.05 100.00 0.02 - - 1.05 100.00 0.02
2.1.1.3 Pasangan Aanstamping Bawah Pondasi Batu Kali T.10 cm m3 2.10 392,699.70 824,669.37 0.08 2.10 100.00 0.08 - - 2.10 100.00 0.08
2.1.1.4 Urugan Tanah Kembali Pondasi Batu Kali m3 10.08 54,285.00 547,192.80 0.06 3.02 30.00 0.02 - - 3.02 30.00 0.02
2.1.1.5 Pondasi Batu Kali 1 Sp : 3 Pp m3 8.82 824,945.00 7,276,014.90 0.73 8.82 100.00 0.73 - - 8.82 100.00 0.73
2.1.2 Perjaan Pondasi Rollage L.15 cm (Selasar) -
2.1.2.1 Galian Tanah Pondasi Rollage < 1 m m3 1.52 73,892.50 112,501.33 0.01 - - - 0.15 10.00 0.00 0.15 10.00 0.00
2.1.2.2 Urugan Pasir Dibawah Pondasi Rollage T.5 cm m3 0.30 174,757.00 53,213.51 0.01 - - - 0.03 10.00 0.00 0.03 10.00 0.00
2.1.2.3 Pasangan Lantai Kerja Bawah Pondasi Rollage T.5 cm (Beton K300) m3 0.30 1,118,398.60 340,552.37 0.03 - - - 0.30 100.00 0.03 0.30 100.00 0.03
2.1.2.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp m3 14.21 128,260.00 1,822,574.60 0.18 - - - 14.21 100.00 0.18 14.21 100.00 0.18
2.2 Pekerjaan Sloef, Kolom, Plat dan Ringbalk
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Ruang Bilas)
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 m3 1.41 1,118,398.60 1,580,297.22 0.16 1.41 100.00 0.16 - - 1.41 100.00 0.16
2.2.1.2 Bekisting 2x Pakai m2 9.42 114,467.10 1,078,280.08 0.11 9.42 100.00 0.11 - - 9.42 100.00 0.11
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI kg 243.74 21,465.73 5,232,043.29 0.53 243.74 100.00 0.53 - - 243.74 100.00 0.53
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan) - -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slum (12 - 2) cm, w/c = 0,52 m3 0.48 1,118,398.60 533,476.13 0.05 0.48 100.00 0.05 - - 0.48 100.00 0.05
2.2.2.2 Bekisting 2x Pakai m2 3.18 193,504.30 615,343.67 0.06 3.18 100.00 0.06 - - 3.18 100.00 0.06
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI kg 98.75 21,465.73 2,119,732.25 0.21 98.75 100.00 0.21 - - 98.75 100.00 0.21
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Ruang Bilas) - -
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.25 1,008,343.60 249,111.29 0.03 - - - 0.25 100.00 0.03 0.25 100.00 0.03
2.2.3.2 Bekisting 2x Pakai m2 1.65 193,504.30 318,701.58 0.03 - - - 1.65 100.00 0.03 1.65 100.00 0.03
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI kg 51.14 21,465.73 1,097,861.33 0.11 - - - 51.14 100.00 0.11 51.14 100.00 0.11
2.2.4 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan) - -
2.2.4.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.04 1,008,343.60 1,043,635.63 0.11 - - - 1.04 100.00 0.11 1.04 100.00 0.11
2.2.4.2 Bekisting 2x Pakai m2 6.90 197,959.30 1,365,919.17 0.14 - - - 6.90 100.00 0.14 6.90 100.00 0.14
2.2.4.3 Besi Beton Ø12 SNI, Ø6 SNI kg 148.86 21,465.73 3,195,302.68 0.32 - - - 148.86 100.00 0.32 148.86 100.00 0.32
2.2.5 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan) - -
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.09 1,008,343.60 1,103,531.24 0.11 - - - 1.09 100.00 0.11 1.09 100.00 0.11
2.2.5.2 Bekisting 2x Pakai m2 14.59 197,959.30 2,888,622.11 0.29 - - - 14.59 100.00 0.29 14.59 100.00 0.29
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI kg 157.40 21,465.73 3,378,705.12 0.34 - - - 157.40 100.00 0.34 157.40 100.00 0.34
2.2.6 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Pintu Jendela) -
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.15 1,008,343.60 148,831.52 0.02 - - - 0.15 100.00 0.02 0.15 100.00 0.02
2.2.6.2 Bekisting 2x Pakai m2 0.98 197,959.30 194,791.95 0.02 - - - 0.98 100.00 0.02 0.98 100.00 0.02
2.2.6.3 Besi Beton Ø10 SNI, Ø6 SNI kg 20.35 21,465.73 436,752.39 0.04 - - - 20.35 100.00 0.04 20.35 100.00 0.04
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) m2 59.01 163,856.00 9,669,142.56 0.98 - - - 59.01 100.00 0.98 59.01 100.00 0.98
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4) m2 48.59 102,876.77 4,998,782.09 0.50 - - - 48.59 100.00 0.50 48.59 100.00 0.50
2.5 Pekerjaan Rangka Plafond dan Dinding Dalam PVC Shunda (Besi Hollow Metal Galvalume 4/4) m2 56.16 102,876.77 5,777,559.22 0.58 - - - - - - - -

TOTAL PEKERJAAN STRUKTUR 59,815,965.86 6.04 2.03 3.26 5.29

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) m3 4.09 174,757.00 715,280.40 0.07 - - - 4.09 100.00 0.07 4.09 100.00 0.07
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) m3 12.28 167,345.00 2,054,804.70 0.21 - - - 12.28 100.00 0.21 12.28 100.00 0.21
3.1.1.3 Rabat Beton T.5 cm (Keseluruhan, Beton K300) m3 4.09 1,118,398.60 4,577,605.47 0.46 - - - 4.09 100.00 0.46 4.09 100.00 0.46
3.1.1.4 Penutup Lantai Keramik Tekstur 60x60 (Badan Bangunan) m2 36.93 413,098.40 15,255,723.91 1.54 - - - 29.54 80.00 1.23 29.54 80.00 1.23
3.1.1.5 Penutup Lantai Andesit Polos 30x30 (Selasar, Ruang Bilas) m2 45.89 284,369.80 13,049,730.12 1.32 - - - - - - - -
3.1.1.6 Penutup Plat Wastafel (Granit 60x60, Toilet Pria dan Wanita) m2 2.20 841,621.73 1,851,567.81 0.19 - - - - - - - -
3.1.2 Pekerjaan Dinding - -
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Selasar, 1 Sp : 4 Pp) 90.64 242,533.50 21,983,236.44 2.22 72.51 80.00 1.78 - - 72.51 80.00 1.78
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Wc ) 30.00 65,473.32 1,964,199.60 0.20 24.00 80.00 0.16 - - 24.00 80.00 0.16
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm 121.28 60,304.20 7,313,693.38 0.74 97.02 80.00 0.59 - - 97.02 80.00 0.59
3.1.2.4 Coating Bening 121.28 46,853.13 5,682,347.00 0.57 - - - - - - - -
3.1.2.5 Dinding Andesit Polos 30x30 cm ( Wc, Ruang Bilas ) 56.52 284,369.80 16,072,581.10 1.62 - - - - - - - -
3.1.2.6 Dinding Keramik 30x60 cm ( Sisi Dalam ) 69.88 370,557.00 25,894,523.16 2.62 - - - - - - - -
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) 9.00 995,076.50 8,955,688.50 0.90 - - - - - - - -
3.1.2.8 Cubicle Panel + Accessories (Pintu Wc dan Partisi Urinoir) 10.86 1,360,000.00 14,769,600.00 1.49 - - - - - - - -
3.1.2.9 Dinding Bitumen Gelombang 48.59 201,749.24 9,802,995.57 0.99 - - - - - - - -
3.1.2.10 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Pria) 1.00 1,200,000.00 1,200,000.00 0.12 - - - - - - - -
3.1.2.11 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Wanita) 1.00 750,000.00 750,000.00 0.08 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.1.3 Plafond dan Dinding Dalam Shunda ( Badan Bangunan ) 56.16 125,878.50 7,069,336.56 0.71 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.2 Pekerjaan Pintu dan Jendela ( Badan Bangunan ) - -
3.2.1 Pintu P1 - -
3.2.1.1 Pasangan Kusen Almunium Coating P1 (4" x 13/4") cm 10.96 157,199.02 1,722,901.26 0.17 - - - - - - - -
3.2.1.2 Pasangan Daun Pintu P1 (Panel Almunium Coating - Coating) 4.30 870,323.19 3,742,389.72 0.38 - - - - - - - -
3.2.1.3 Pasangan Kunci Tanam 2x Slag P1 2.00 416,663.50 833,327.00 0.08 - - - - - - - -
3.2.1.4 Pasangan ensel P1 6.00 61,225.56 367,353.36 0.04 - - - - - - - -
3.2.1.5 Pasangan Doorcloser P1 2.00 241,902.10 483,804.20 0.05 - - - - - - - -
3.2.1.6 Pasangan Handle P1 2.00 229,802.10 459,604.20 0.05 - - - - - - - -
3.2.2 Jendela J1 - -
3.2.2.1 Pasangan Kusen Almunium Coating J1 (4" x 13/4") cm 28.80 157,199.02 4,527,331.78 0.46 - - - - - - - -
3.2.2.2 Pasangan Kaca Mati 5 mm J1 0.60 145,705.56 87,423.34 0.01 - - - - - - - -
3.2.3 Jendela J2 -
3.2.3.1 Pasangan Kusen Almunium Coating J2 (4" x 13/4") cm 55.20 157,199.02 8,677,385.90 0.88 - - - - - - - -
3.2.3.2 Pasangan Kaca Mati 5 mm J2 0.90 145,705.56 131,135.00 0.01 - - - - - - - -
3.3. Pengecetan Plafond (1 Plamir : 1 Cat Dasar : 2 Cat Penutup), (Interior) 56.16 43,550.65 2,445,804.50 0.25 - - - - - - - -
3.4 Pekerjaan Atap - -
3.4.1 Atap Bitumen Gelombang (Badan Bangunan) 59.01 201,749.24 11,905,222.65 1.20 - - - - - - - -
3.4.2 Nok Bitumen (Badan Bangunan) 35.25 143,629.20 5,062,929.30 0.51 - - - - - - - -
3.4.3 Listplank (Kasiplank, Badan Bangunan, Enterance) 39.08 70,972.00 2,773,585.76 0.28 - - - - - - - -

TOTAL PEKERJAAN FINISHING ARSITEKTUR 202,183,111.69 20.42 2.53 1.98 4.50

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel 1.00 1,803,826.75 1,803,826.75 0.18 - - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt 10.00 353,938.75 3,539,387.50 0.36 - - - - - - - -
4.1.3 Pasangan Lampu Down Light 2.5" Outbow LED 5.5 Watt 12.00 305,538.75 3,666,465.00 0.37 - - - - - - - -
4.1.4 Pasangan Saklar Ganda 5.00 223,478.75 1,117,393.75 0.11 - - - - - - - -
4.2 Pasangan Instalasi Stop Kontak - -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA 3.00 216,218.75 648,656.25 0.07 - - - - - - - -
4.2.2 Pasangan Stop Kontak Wall Exhauser 6.00 216,218.75 1,297,312.50 0.13 - - - - - - - -
4.3 Pasangan Instalasi Jaringan Wall Exhauser 12.00 108,772.68 1,305,272.10 0.13 - - - - - - - -
4.3.1 Pasangan Wall Exhauser 12 Inch - FV30RUN 6.00 513,500.00 3,081,000.00 0.31 - - - - - - - -
4.4 Pasangan Penangkal Petir 1.00 3,500,000.00 3,500,000.00 0.35 - - - - - - - -
4.5 Pasangan Instlasi Jaringan Kabel Fiber Optic (CCTV) 3.00 786,326.75 2,358,980.25 0.24 - - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2 MP (Luar Bangunan, Sambungan Dari Mini Resto) 3.00 656,975.00 1,970,925.00 0.20 - - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm 4.00 20,442.68 81,770.70 0.01 - - - - - - - -
4.6.1 Pasangan Horn Speaker (Sambungan Dari Mini Resto) 2.00 494,826.75 989,653.50 0.10 - - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25 kg) 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - - -
4.8 Pasangan Instalasi PLN Power 1.00 10,000,000.00 10,000,000.00 1.01 - - - - - - - -

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 44,560,643.30 4.50 0.00 0.00 0.00

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVc Tipe AW Diameter 3/4" (Air Bersih Dari Sumur Bor / PDAM Reservoir) m1 18.50 28,304.65 523,636.03 0.05 - - - - - - - -
5.2 Pipa PVC Tipe AW Diameter 3/4" (Distribusi Air Bersih Dari Reservoir) m1 26.50 28,304.65 750,073.23 0.08 - - - - - - - -
5.3 Pipa PVC Tipe AW Diameter 3" (Air Kotor Ke Drainase Lingkungan) m1 23.00 135,539.80 3,117,415.40 0.31 - - - - - - - -
5.4 Pipa PVC Tipe AW Diameter 4" (Disposal) m1 18.00 186,689.80 3,360,416.40 0.34 - - - - - - - -
5.5 Pasangan 1 bh Closet Duduk / Monoblock (TOTO) bh 6.00 3,655,597.00 21,933,582.00 2.22 - - - - - - - -
5.6 Pasangan 1 bh Wastafel (TOTO) 3.00 3,571,942.00 10,715,826.00 1.08 - - - - - - - -
5.7 Pasangan 1 bh Uninoir (TOTO) 2.00 6,665,285.00 13,330,570.00 1.35 - - - - - - - -
5.8 Pasangan 1 bh Floor Drain 9.00 41,123.50 370,111.50 0.04 - - - - - - - -
5.9 Pasangan 1 bh Kran dia. 1/2' atau 3/4" 8.00 102,228.50 817,828.00 0.08 - - - - - - - -
5.10 Pasangan 1 bh Kran wastafel dia. 1/2' atau 3/4" 2.00 335,428.50 670,857.00 0.07 - - - - - - - -
5.11 Pasangan 1 bh shower closet dia. 1/2' atau 3/4" 6.00 142,928.50 857,571.00 0.09 - - - - - - - -
5.12 Pasangan 1 bh shower Wall dia. 1/2' atau 3/4" (Ruang Bilas) 4.00 1,435,428.50 5,741,714.00 0.58 - - - - - - - -
5.13 Pasangan 1 bh Stop Kran (Gate Valve) dia. 3/4" 2.00 141,428.50 282,857.00 0.03 - - - - - - - -
5.14 Pasangan Mesin Air 1.00 741,000.00 741,000.00 0.07 - - - - - - - -
5.14b Pasangan Mesin Pemanas Air 1.00 5,000,000.00 5,000,000.00 0.51 - - - - - - - -
5.15 Septictank Biotank Kap. 4m3 1.00 20,380,000.00 20,380,000.00 2.06 - - - - - - - -
5.16 Pasangan Sumur Bor Jet Pump 30.00 350,000.00 10,500,000.00 1.06 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.17 Reservoir 1200 Liter 1.00 1,850,000.00 1,850,000.00 0.19 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.18 Reservoir 200x150x350 cm - -
5.18.1 Pekerjaan Pondasi Pedestal Pd1 - -
5.18.1.1 Galian Tanah Pondasi Poerplat < 1m 1.62 74,250.00 120,285.00 0.01 - - - - - - - -
5.18.1.2 Urugan Tanah Kembali Pondasi Poerplat 0.43 55,000.00 23,760.00 0.00 - - - - - - - -
5.18.1.3 Tiang Pondasi Pedestal 50x50 cm -
Beton Mutu fc = 26,6 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.80 1,485,144.21 1,188,115.37 0.12 - - - - - - - -
Bekisting 2x Pakai 3.20 193,504.30 619,213.76 0.06 - - - - - - - -
Besi Beton Ø12, Ø8 49.44 21,465.73 1,061,174.10 0.11 - - - - - - - -
5.18.1.4 Pondasi Poerplat 90x90 cm,T.20 cm - -
Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.65 1,485,144.21 962,373.45 0.10 - - - - - - - -
Bekisting 2x Pakai 1.44 124,547.50 179,348.40 0.02 - - - - - - - -
Besi Beton Ø14 SNI 214.35 21,465.73 4,601,114.73 0.46 - - - - - - - -
5.18.2 Rangkai Tengah Dan Lantai Menara (Besi Hollow Galvanis 4/4) 34.82 244,970.00 8,529,855.40 0.86 - - - - - - - -
5.18.3 Rangka Utama menara ( Besi Hollow Galvanis 5/10 32.28 179,454.00 5,792,775.12 0.59 - - - - - - - -
5.18.4 Tplat Baja Lantai Menara T.3mm 3.00 740,164.86 2,220,494.57 0.22 - - - - - - - -
5.18.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) 5.00 244,970.00 1,224,850.00 0.12 - - - - - - - -

TOTAL PEKERJAAN PLAMBING DAN SANITASI 127,466,817.45 12.88 - - -

6. PEKERJAAN AKHIR - - -
6.1 Pembersihan Sisa Pekerjaan Ls 1.00 2,400,000.00 2,400,000.00 0.24 - - - - - - - -

TOTAL PEKERJAAN AKHIR 2,400,000.00 0.24 0.00 0.00 0.00

C. PENERAPAN SMKK

1. PENYIAPAN RKK
1.1 Pembuatan Dokumen Rencana Keselamatan Konstruksi
1.2 Pembuatan Prosedur dan instruksi kerja Set 1.00 2,000,000.00 2,000,000.00 0.20 1.00 100.00 0.20 - - 1.00 100.00 0.20
1.3 Penyiapan formulir
TOTAL PENYIAPAN RKK 2,000,000.00 0.20 0.20 - 0.20
2. SOSIALISASI, PROMOSI DAN PELATIHAN
2.1 Induksi K3 (Safety Induction) Org 5.00 7,500.00 37,500.00 0.00 0.50 10.00 0.00 - - 0.50 10.00 0.00
2.2 Pengarahan K3 (Safety Briefing) Org 5.00 15,000.00 75,000.00 0.01 5.00 100.00 0.01 - - 5.00 100.00 0.01
2.3 Pelatihan K3 -
2.3.1 Bekerja di ketinggian Org 4.00 7,500.00 30,000.00 0.00 4.00 100.00 0.00 - - 4.00 100.00 0.00
2.3.2 Penggunaan Bahan Kimia (MSDS) Org 2.00 7,500.00 15,000.00 0.00 2.00 100.00 0.00 - - 2.00 100.00 0.00
2.4 Simulasi K3 Org 5.00 7,500.00 37,500.00 0.00 5.00 100.00 0.00 - - 5.00 100.00 0.00
2.5 Spanduk (Banner) Lb 1.00 150,000.00 150,000.00 0.02 1.00 100.00 0.02 - - 1.00 100.00 0.02
2.6 Poster 2 2.00 50,000.00 100,000.00 0.01 2.00 100.00 0.01 - - 2.00 100.00 0.01
2.7 Papan Informasi K3 1 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
TOTAL SOSIALISASI, PROMOSI DAN PELATIHAN 945,000.00 0.10 0.09 - 0.09
3. ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI
3.1 APK
3.1.1 Tali Keselamatan (Life Line) Ls 1.00 1,700,000.00 1,700,000.00 0.17 1.00 100.00 0.17 - - 1.00 100.00 0.17
3.1.2 Pembatas Area (Restricted Area) Ls 1.00 2,000,000.00 2,000,000.00 0.20 1.00 100.00 0.20 - - 1.00 100.00 0.20
3.2 APD -
3.2.1 Topi Pelindung (Safety Helmet) Bh 10.00 75,000.00 750,000.00 0.08 10.00 100.00 0.08 - - 10.00 100.00 0.08
3.2.2 Pelindung Mata (Googles, Spectacles) Bh 5.00 25,000.00 125,000.00 0.01 5.00 100.00 0.01 - - 5.00 100.00 0.01
3.2.3 Pelindung Pernapasan dan Mulut (Masker) Bh 100.00 5,000.00 500,000.00 0.05 100.00 100.00 0.05 - - 100.00 100.00 0.05
3.2.4 Sarung Tangan (Safety Gloves) Psg 10.00 15,000.00 150,000.00 0.02 10.00 100.00 0.02 - - 10.00 100.00 0.02
3.2.5 Sepatu Keselamatan (Safety Shoes) Psg 10.00 350,000.00 3,500,000.00 0.35 10.00 100.00 0.35 - - 10.00 100.00 0.35
3.2.6 Penunjang Seluruh Tubuh (Full Body Harness) Bh 2.00 500,000.00 1,000,000.00 0.10 2.00 100.00 0.10 - - 2.00 100.00 0.10
3.2.7 Rompi Keselamatan (Safety Vest) Bh 10.00 25,000.00 250,000.00 0.03 10.00 100.00 0.03 - - 10.00 100.00 0.03
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 9,975,000.00 1.01 1.01 - 1.01
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4. ASURANSI DAN PERIZINAN
4.1 Asuransi Ls 1.00 3,000,000.00 3,000,000.00 0.30 1.00 100.00 0.30 - - 1.00 100.00 0.30
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 3,000,000.00 0.30 0.30 - 0.30
5. PERSONEL K3 KONSTRUKSI
5.1 Ahli K3 Konstruksi -
5.2 Petugas K3 Konstruksi Ob 4.00 3,675,000.00 14,700,000.00 1.48 4.00 100.00 1.48 - - 4.00 100.00 1.48
TOTAL PERSONEL K3 KONSTRUKSI 14,700,000.00 1.48 1.48 - 1.48
6. FASILITAS, SARANA DAN PRASARANA KESEHATAN
6.1 Peralatan P3K (Kotak P3K, Tandu, Obat Luka, Perban, dll) Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
TOTAL FASILITAS, SARANA DAN PRASARANA KESEHATAN 500,000.00 0.05 0.05 - 0.05
7. RAMBU - RAMBU YANG DIPERLUKAN
7.1 Rambu Petunjuk bh 2.00 75,000.00 150,000.00 0.02 2.00 100.00 0.02 - - 2.00 100.00 0.02
7.2 Rambu Larangan bh 2.00 75,000.00 150,000.00 0.02 2.00 100.00 0.02 - - 2.00 100.00 0.02
7.3 Rambu Peringatan bh 2.00 100,000.00 200,000.00 0.02 2.00 100.00 0.02 - - 2.00 100.00 0.02
7.4 Jalur Evakuasi (Escape Route) Ls 1.00 250,000.00 250,000.00 0.03 1.00 100.00 0.03 - - 1.00 100.00 0.03
TOTAL RAMBU - RAMBU YANG DIPERLUKAN 750,000.00 0.08 0.08 - 0.08
8. KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI
8.1 Ahli K3 Konstruksi Oj -
TOTAL KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI - 0.00
9. LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN
KONSTRUKSI
9.1 Alat Pemadam Api Ringan (APAR) bh 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
9.2 Program Inspeksi Ls 1.00 1,500,000.00 1,500,000.00 0.15 1.00 100.00 0.15 - - 1.00 100.00 0.15
9.3 Pelaporan dan Penyeledikan Insiden Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
9.4 Pembuatan Kartu Identitas Pekerja (KIP) Org 10.00 5,000.00 50,000.00 0.01 10.00 100.00 0.01 - - 10.00 100.00 0.01
TOTAL LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN KONSTRUKSI 2,550,000.00 0.26 0.26 - 0.26

A Jumlah Harga Penawaran 989,944,870.91 100.00 24.58 9.87 34.46


B PPN (10%) 98,994,487.09
C Jumlah (A+B) 1,088,939,358.00
PERSENTASE SAMPAI MINGGU INI 34.46
D Jumlah Dibulatkan 1,088,939,358.00

Bulukumba, 12 November 2020


Disetujui, Diketahui, Diperiksa Oleh, Dibuat Oleh,
Pejabat Pembuat Komitmen Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUTR Prov SulSel Dinas PUTR Prov SulSel CV.MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

A.KHADAFI HARUN, ST.,MT. L I L I, ST. IRHAM HARAHAP, ST. VIKA APRILIA DWI PUTRI
NIP. 19811126 200901 1 008 NIP. 19821229 201503 2 001 Site Engineer Direktris
LAPORAN KEMAJUAN MINGGUAN

Kegiatan : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba Minggu Ke : 05 ( Lima )
Satuan Kerja : Dinas Pekerjaan Umum Dan Tata Ruang Prov. Sulawesi Selatan Bidang Cipta Karya Periode : 13 November S/d 19 November 2020
Lokasi : Desa Ara, Kecamatan Bonto Bahari, Kabupaten Bulukumba, Provinsi Sulawesi Selatan No. Kontrak : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
Sumber Dana : Dana Bantuan Provinsi Nilai Kontrak : Rp. 1,088,939,358.00
Tahun Anggaran : 2020 Schedule Pelaksanaan : 16 Oktober S/d 14 Desember 2020

MINGGU LALU MINGGU INI S/D MINGGU INI


VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
NO URAIAN PEKERJAAN
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q

A. PEMBANGUNAN RUANG KULINER, SUVENIR, MUSHOLLAH DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Papan Proyek Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
1.2 Bedeng/Direksi Keet M2 5.50 1,512,555.00 8,319,052.50 0.84 5.50 100.00 0.84 - - 5.50 100.00 0.84

TOTAL PEKERJAAN PERSIAPAN 8,819,052.50 0.89 0.89 0.00 0.89

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Poerplat PP1 (Selasar Samping)
2.1.1.1 Galian Pondasi Poerplat < 1 m M3 0.32 73,837.50 23,628.00 0.00 0.32 100.00 0.00 - - 0.32 100.00 0.00
2.1.1.2 Urugan Pasir dibawah Pondasi Poerplat T.5 cm M3 0.04 148,335.00 5,933.40 0.00 0.04 100.00 0.00 - - 0.04 100.00 0.00
2.1.1.3 Urugan Tanah Kembali Pondasi Poerplat M3 0.31 54,175.00 16,794.25 0.00 0.31 100.00 0.00 - - 0.31 100.00 0.00
2.1.1.4 Pasangan Lantai Kerja bawah Pondasi Poerplat T.5 cm (Beton K300) M3 0.04 1,118,216.00 44,728.64 0.00 0.04 100.00 0.00 - - 0.04 100.00 0.00
2.1.1.5 Pondasi Poerplat 35x50 cm, T.20 cm
Beton Mutu F'c = 26,4 mpa (K300), Slump (12-2) cm, w/c = 0,52 M3 0.14 1,118,216.00 156,550.24 0.02 0.14 100.00 0.02 - - 0.14 100.00 0.02
Bekisting 2x Pakai M2 0.56 107,013.50 59,927.56 0.01 0.56 100.00 0.01 - - 0.56 100.00 0.01
Besi Beton Ø14 SNI Kg 29.40 21,464.85 631,066.59 0.06 29.40 100.00 0.06 - - 29.40 100.00 0.06
2.1.2 Pekerjaan Pondasi Batu Kali (Badan Bangunan, Mushollah)
2.1.2.1 Galian Tanah Pondasi Batu Kali < 1 m M3 22.73 73,837.50 1,678,326.38 0.17 22.73 100.00 0.17 - - 22.73 100.00 0.17
2.1.2.2 Urugan Pasir dibawah Pondasi Batu Kali T.5 cm M3 1.08 148,335.00 160,201.80 0.02 1.08 100.00 0.02 - - 1.08 100.00 0.02
2.1.2.3 Pasangan Aanstamping bawah Pondasi Batu Kali T.10 M3 2.17 382,674.00 830,402.58 0.08 2.17 100.00 0.08 - - 2.17 100.00 0.08
2.1.2.4 Urugan Tanah Kembali Pondasi Batu Kali M3 10.39 54,175.00 562,878.25 0.06 10.39 100.00 0.06 - - 10.39 100.00 0.06
2.1.2.5 Pondasi Batu Kali 1 Sp : 3 Pp M3 9.09 827,447.50 7,521,497.78 0.76 9.09 100.00 0.76 - - 9.09 100.00 0.76
2.1.3 Pekerjaan Pondasi Rollage L.15 cm (Entrance, Selasar Samping)
2.1.3.1 Galian Tanah Pondasi Rollage < 1 m M3 2.23 73,837.50 164,657.63 0.02 2.23 100.00 0.02 - - 2.23 100.00 0.02
2.1.3.2 Urugan Pasir dibawah Pondasi Rollage T.5 cm M3 0.45 148,335.00 66,750.75 0.01 0.45 100.00 0.01 - - 0.45 100.00 0.01
2.1.3.3 Pasangan Lantai Kerja bawah Pondasi Rollage T.5 cm (Beton K300) M3 0.45 1,118,216.00 499,003.89 0.05 0.45 100.00 0.05 - - 0.45 100.00 0.05
2.1.3.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp M2 20.83 128,436.00 2,675,321.88 0.27 20.83 100.00 0.27 - - 20.83 100.00 0.27
2.2 Pekerjaan Sloef, Kolom dan Ringbalk
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Mushollah)
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 1.62 1,118,216.00 1,815,703.23 0.18 1.62 100.00 0.18 - - 1.62 100.00 0.18
2.2.1.2 Bekisting 2x Pakai M2 10.83 114,438.50 1,239,368.96 0.13 10.83 100.00 0.13 - - 10.83 100.00 0.13
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI Kg 280.09 21,464.85 6,012,089.84 0.61 280.09 100.00 0.61 - - 280.09 100.00 0.61
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan, Mushollah)
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.88 1,118,216.00 981,234.54 0.10 0.88 100.00 0.10 - - 0.88 100.00 0.10
2.2.2.2 Bekisting 2x Pakai M2 5.85 193,468.00 1,131,787.80 0.11 5.85 100.00 0.11 - - 5.85 100.00 0.11
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 181.66 21,464.85 3,899,347.58 0.39 181.66 100.00 0.39 - - 181.66 100.00 0.39
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Selasar, Westafel, Tempat Wudhu)
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 0.34 100.00 0.03 - - 0.34 100.00 0.03
2.2.3.2 Bekisting 2x Pakai M2 2.26 193,468.00 437,237.68 0.04 2.26 100.00 0.04 - - 2.26 100.00 0.04
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 70.10 21,464.85 1,504,686.30 0.15 70.10 100.00 0.15 - - 70.10 100.00 0.15
2.2.4 Pekerjaan Kolom K1 15 x 30 (Selasar Samping)
2.2.4.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.62 1,118,216.00 694,412.14 0.07 0.62 100.00 0.07 - - 0.62 100.00 0.07
2.2.4.2 Bekisting 2x Pakai M2 6.21 193,468.00 1,201,436.28 0.12 6.21 100.00 0.12 - - 6.21 100.00 0.12
2.2.4.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 99.69 21,464.85 2,139,830.90 0.22 99.69 100.00 0.22 - - 99.69 100.00 0.22
2.2.5 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan, Mushollah)
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 2.08 1,008,161.00 2,097,478.96 0.21 2.08 100.00 0.21 - - 2.08 100.00 0.21
2.2.5.2 Bekisting 2x Pakai M2 13.87 197,923.00 2,745,192.01 0.28 13.87 100.00 0.28 - - 13.87 100.00 0.28
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 299.22 21,464.85 6,422,712.42 0.65 299.22 100.00 0.65 - - 299.22 100.00 0.65
2.2.6 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan)
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 0.34 100.00 0.03 - - 0.34 100.00 0.03
2.2.6.2 Bekisting 2x Pakai M2 2.24 197,923.00 443,347.52 0.04 2.24 100.00 0.04 - - 2.24 100.00 0.04
2.2.6.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 48.32 21,464.85 1,037,181.55 0.10 48.32 100.00 0.10 - - 48.32 100.00 0.10
2.2.7 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Mushollah, Pintu Jendela)
2.2.7.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.84 1,008,161.00 846,855.24 0.09 0.84 100.00 0.09 - - 0.84 100.00 0.09
2.2.7.2 Bekisting 2x Pakai M2 5.59 197,923.00 1,106,389.57 0.11 5.59 100.00 0.11 - - 5.59 100.00 0.11
2.2.7.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 115.53 21,464.85 2,479,834.12 0.25 115.53 100.00 0.25 - - 115.53 100.00 0.25
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.2.8 Pekerjaan Plat Beton (Selasar Samping, Westafel)
2.2.8.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.22 1,008,161.00 221,795.42 0.02 0.22 100.00 0.02 - - 0.22 100.00 0.02
2.2.8.2 Bekisting 2x Pakai M2 2.21 237,468.00 524,804.28 0.05 2.21 100.00 0.05 - - 2.21 100.00 0.05
2.2.8.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 54.54 21,464.85 1,170,692.92 0.12 54.54 100.00 0.12 - - 54.54 100.00 0.12
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) M2 152.03 163,636.00 24,877,581.08 2.51 152.03 100.00 2.51 - - 152.03 100.00 2.51
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4, Entrance) M2 42.24 242,170.50 10,229,281.92 1.03 42.24 100.00 1.03 - - 42.24 100.00 1.03
2.5 Pekerjaan Tiang Atap Bitumen Gelombang (Besi Hollow Galvanis 5/10, Entrance) M' 20.40 178,365.00 3,638,646.00 0.37 20.40 100.00 0.37 - - 20.40 100.00 0.37
2.6 Pekerjaan Rangka Plafond Kalsiboard (Besi Hollow Metal Galvalume 4/4) M2 147.40 102,837.17 15,158,198.37 1.53 147.40 100.00 1.53 - - 147.40 100.00 1.53

TOTAL PEKERJAAN STRUKTUR 109,840,345.70 11.10 11.10 0.00 11.10

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) M3 8.54 148,335.00 1,266,780.90 0.13 8.54 100.00 0.13 - - 8.54 100.00 0.13
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) M3 25.63 167,227.00 4,285,636.74 0.43 25.63 100.00 0.43 - - 25.63 100.00 0.43
3.1.1.3 Rabat Beton bawah Lantai T.5 cm (Keseluruhan, Beton K300) M3 8.54 1,118,216.00 9,549,564.64 0.96 8.54 100.00 0.96 - - 8.54 100.00 0.96
3.1.1.4 Penutup Lantai Keramik Motif 60x60 (Badan Bangunan, Mushollah) M2 62.94 403,309.50 25,384,299.93 2.56 - - - 59.79 95.00 2.44 59.79 95.00 2.44
3.1.1.5 Penutup Lantai Conwood Deck 6" (Entrance) M2 59.01 866,833.08 51,151,820.09 5.17 - - - - - - - -
3.1.1.6 Penutup Lantai Andesit Polos 30x30 (Selasar, Tempat Wudhu, Ram) M2 51.05 232,589.50 11,873,693.98 1.20 - - - - - - - -
3.1.1.7 Plint Lantai Keramik 10x60 (Badan Bangunan, Mushollah) M' 38.85 51,605.03 2,004,855.55 0.20 - - - - - - - -
3.1.2 Pekerjaan Dinding
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Mushollah, 1 Sp : 4 Pp) M2 74.55 242,979.00 18,114,084.45 1.83 74.55 100.00 1.83 - - 74.55 100.00 1.83
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Selasar Samping, Tempat Wudhu) M2 5.14 65,550.32 336,928.64 0.03 - - - 5.14 100.00 0.03 5.14 100.00 0.03
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm (Badan Bangunan, Mushollah) M2 91.30 60,403.20 5,514,812.16 0.56 91.30 100.00 0.56 - - 91.30 100.00 0.56
3.1.2.4 Plesteran Ciprat 1 Sp : 2 Pp Tebal 15 mm (Selasar Samping, Antar Kolom) M2 24.84 49,215.10 1,222,503.08 0.12 - - - 24.84 100.00 0.12 24.84 100.00 0.12
3.1.2.5 Dinding Keramik Mozaik 30x60 (Selasar Samping, Westafel, Tempat Wudhu) M2 18.44 410,432.00 7,568,366.08 0.76 - - - - - - - -
3.1.2.6 Coating Bening (Badan Bangunan, Mushollah, Kolom Luar) M2 127.49 45,973.13 5,861,113.71 0.59 - - - - - - - -
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) M2 8.64 995,043.50 8,597,175.84 0.87 - - - - - - - -
3.1.2.8 Dinding Wallpaper Bata L.50 cm (Sisi Dalam) M2 28.13 80,005.50 2,250,554.72 0.23 - - - - - - - -
3.1.3 Pekerjaan Plafond
3.1.3.1 Plafond Kalsiboard (Badan Bangunan, Kemiringan Atap, Mushollah) M2 147.40 44,924.00 6,621,797.60 0.67 - - - 147.40 100.00 0.67 147.40 100.00 0.67
3.1.3.2 Plafond Kalsiboard (Lapis Bawah Atap, Entrance) M2 42.24 44,924.00 1,897,589.76 0.19 - - - 42.24 100.00 0.19 42.24 100.00 0.19
3.2 Pekerjaan Pintu dan Jendela (Badan Bangunan)
3.2.1 Pintu P1 (Entrance dan Back Entrance, Badan Bangunan)
3.2.1.1 Pasangan Kusen Alumunium Coating P1 (4" x 1 3/4") cm M' 22.40 157,194.40 3,521,154.56 0.36 - - - - - - - -
3.2.1.2 Pasangan Daun Pintu P1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - - -
3.2.1.3 Pasangan Kaca Mati 5 mm P1 M2 11.20 145,703.80 1,631,882.56 0.16 - - - - - - - -
3.2.1.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - - -
3.2.1.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - - -
3.2.1.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - - -
3.2.1.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - - -
3.2.2 Jendela J1 (Badan Bangunan)
3.2.2.1 Pasangan Kusen Alumunium Coating J1 (4" x 1 3/4") cm M' 40.60 157,194.40 6,382,092.64 0.64 - - - - - - - -
3.2.2.2 Pasangan Kaca Mati 5 mm J1 M2 8.00 145,703.80 1,165,630.40 0.12 - - - - - - - -
3.2.3 Pintu PJ1 (Mushollah)
3.2.3.1 Pasangan Kusen Alumunium Coating PJ1 (4" x 1 3/4") cm M' 22.20 157,194.40 3,489,715.68 0.35 - - - - - - - -
3.2.3.2 Pasangan Daun Pintu PJ1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - - -
3.2.3.3 Pasangan Kaca Mati 5 mm P1 M2 8.70 145,703.80 1,267,623.06 0.13 - - - - - - - -
3.2.3.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - - -
3.2.3.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - - -
3.2.3.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - - -
3.2.3.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - - -
3.3 Pekerjaan Pengecatan
3.3.1 Pengecatan Plafond (1 Plamir ; 1 Cat Dasar : 2 Cat Penutup), (Interior) M2 189.64 35,536.05 6,739,056.52 0.68 - - - 189.64 100.00 0.68 189.64 100.00 0.68
3.3.2 Pengecatan Rangka Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 23.76 168,454.00 4,002,467.04 0.40 - - - 23.76 100.00 0.40 23.76 100.00 0.40
3.3.3 Pengecatan Tiang Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 6.12 168,454.00 1,030,938.48 0.10 - - - 6.12 100.00 0.10 6.12 100.00 0.10
3.4 Pekerjaan Atap
3.4.1 Atap Bitumen Gelombang (Badan Bangunan, Mushollah) M2 152.03 207,297.09 31,515,376.59 3.18 152.03 100.00 3.18 - - 152.03 100.00 3.18
3.4.2 Atap Bitumen Gelombang (Entrance) M2 42.24 207,297.09 8,756,229.08 0.88 42.24 100.00 0.88 - - 42.24 100.00 0.88
3.4.3 Nok Bitumen (Badan Bangunan, Mushollah) M' 14.55 134,101.00 1,951,169.55 0.20 14.55 100.00 0.20 - - 14.55 100.00 0.20
3.4.4 Listplank (Kalsiplank, Badan Bangunan, Mushollah, Entrance) M' 50.00 70,950.00 3,547,500.00 0.36 50.00 100.00 0.36 - - 50.00 100.00 0.36

TOTAL PEKERJAAN FINISHING ARSITEKTUR 257,222,142.77 25.98 8.54 4.64 13.18

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel Bh 1.00 1,572,826.75 1,572,826.75 0.16 - - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt Bh 16.00 353,938.75 5,663,020.00 0.57 - - - 16.00 100.00 0.57 16.00 100.00 0.57
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4.1.3 Pasangan Lampu Down Light 2,5" Outbow LED 5,5 Watt Bh 11.00 305,538.75 3,360,926.25 0.34 - - - 11.00 100.00 0.34 11.00 100.00 0.34
4.1.4 Pasangan Saklar Tunggal Bh 4.00 211,378.75 845,515.00 0.09 - - - 4.00 100.00 0.09 4.00 100.00 0.09
4.1.5 Pasangan Saklar Ganda Bh 2.00 223,478.75 446,957.50 0.05 - - - 2.00 100.00 0.05 2.00 100.00 0.05
4.2 Pasangan Instalasi Stop Kontak
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA Bh 10.00 216,218.75 2,162,187.50 0.22 - - - 10.00 100.00 0.22 10.00 100.00 0.22
4.2.2 Pasangan Stop Kontak AC 220 VA/3520 W (AC Split 1 PK) Bh 4.00 253,728.75 1,014,915.00 0.10 - - - 4.00 100.00 0.10 4.00 100.00 0.10
4.3 Pasangan Instalasi Jaringan AC M' 30.00 108,772.68 3,263,180.25 0.33 - - - 30.00 100.00 0.33 30.00 100.00 0.33
4.3.1 Pasangan AC Split 1 PK Bh 3.00 3,365,799.34 10,097,398.03 1.02 - - - 1.50 50.00 0.51 1.50 50.00 0.51
4.4 Pasangan Penangkal Petir Ls 1.00 2,500,000.00 2,500,000.00 0.25 - - - 1.00 100.00 0.25 1.00 100.00 0.25
4.5 Pasangan Instalasi Jaringan Kabel Fiber Optic (CCTV) Ttk 6.00 786,326.75 4,717,960.50 0.48 - - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2MP Bh 6.00 656,975.00 3,941,850.00 0.40 - - - - - - - -
4.5.2 Pasangan NVR Channel Set 1.00 5,023,975.00 5,023,975.00 0.51 - - - - - - - -
4.5.3 Pasangan Monitor LCD 32" Bh 1.00 2,944,975.00 2,944,975.00 0.30 - - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm M' 12.00 20,442.68 245,312.10 0.02 - - - - - - - -
4.6.1 Pasangan Horn Speaker Bh 6.00 494,826.75 2,968,960.50 0.30 - - - - - - - -
4.6.2 Pasangan Volume Kontrol Set 1.00 252,826.75 252,826.75 0.03 - - - - - - - -
4.6.3 Pasangan Perangkat Sound System Set 1.00 4,565,000.00 4,565,000.00 0.46 - - - - - - - -
4.6.4 Pasangan TB-Sound System Set 1.00 5,846,326.75 5,846,326.75 0.59 - - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25Kg) Ttk 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - - -
4.8 Pasangan Instalasi Jaringan Kabel Fiber Optic (Akses Point) Ttk 3.00 786,326.75 2,358,980.25 0.24 - - - - - - - -
4.8.1 Pasangan Server Set 1.00 7,578,826.75 7,578,826.75 0.77 - - - - - - - -
4.8.2 Pasangan Akses Point Bh 1.00 2,034,826.75 2,034,826.75 0.21 - - - - - - - -
4.8.3 Pasangan Switch HUB Bh 1.00 2,843,326.75 2,843,326.75 0.29 - - - - - - - -
4.9 Pasangan Instalasi PLN Power (Inc. Jalur ke Mushollah dan Toilet) Ls 1.00 9,000,000.00 9,000,000.00 0.91 - - - - - - - -

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 94,450,073.38 9.54 0.00 2.46 2.46

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVC Type AW Diameter 3/4" (Air Bersih Sambungan dari Tandon) M' 33.00 28,300.25 933,908.25 0.09 - - - 16.50 50.00 0.05 16.50 50.00 0.05
5.2 Pipa PVC Type AW Diameter 3" (Air Kotor ke Drainase Lingkungan) M' 25.80 135,531.00 3,496,699.80 0.35 - - - 2.58 10.00 0.04 2.58 10.00 0.04
5.3 Pasangan 1 Bh Wastafel Bh 2.00 3,934,865.00 7,869,730.00 0.79 - - - - - - - -
5.4 Pasangan 1 Bh Wastafel Cuci Piring (WCP) Bh 1.00 890,945.00 890,945.00 0.09 - - - - - - - -
5.5 Pasangan 1 Bh Floor Drain Bh 2.00 41,112.50 82,225.00 0.01 - - - - - - - -
5.6 Pasangan 1 Bh Kran Dia. 1/2" atau 3/4" Bh 10.00 102,217.50 1,022,175.00 0.10 - - - - - - - -
5.7 Pasangan 1 Bh Kran Wastafel Dia. 1/2" atau 3/4" Bh 3.00 335,417.50 1,006,252.50 0.10 - - - - - - - -
5.8 Pasangan 1 Bh Stop Kran (Gate Valve) Dia. 3/4" Bh 1.00 141,417.50 141,417.50 0.01 - - - - - - - -
5.9 Pasangan Mesin Air Bh 1.00 741,000.00 741,000.00 0.07 - - - - - - - -
5.10 Menara Reservoir 200x150x350 cm
5.10.1 Pekerjaan Pondasi Pedestal Pd1
5.10.1.1 Galian Tanah Pondasi Poerplat < 1 m M3 1.62 73,837.50 119,616.75 0.01 - - - - - - - -
5.10.1.2 Urugan Tanah Kembali Pondasi Poerplat M3 0.43 54,175.00 23,295.25 0.00 - - - - - - - -
5.10.1.3 Tiang Pondasi Pedestal 50x50 cm
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.80 1,118,216.00 894,572.80 0.09 - - - - - - - -
Bekisting 2x Pakai M2 3.20 193,468.00 619,097.60 0.06 - - - - - - - -
Besi Beton Ø12 SNI, Ø8 SNI Kg 49.44 21,464.85 1,061,130.60 0.11 - - - - - - - -
5.10.1.4 Pondasi Poerplat 90x90 cm, T.20 cm
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.65 1,118,216.00 726,840.40 0.07 - - - - - - - -
Bekisting 2x Pakai M2 1.44 107,013.50 154,099.44 0.02 - - - - - - - -
Besi Beton Ø14 SNI Kg 214.35 21,464.85 4,600,940.54 0.46 - - - - - - - -
5.10.2 Rangka Tengah dan Lantai Menara (Besi Hollow Galvanis 4/4) M2 34.82 244,970.00 8,529,855.40 0.86 - - - - - - - -
5.10.3 Rangka Utama Menara (Besi Hollow Galvanis 5/10) M' 32.28 179,454.00 5,792,775.12 0.59 - - - - - - - -
5.10.4 Plat Baja Lantai Menara T.3 mm M2 3.00 740,164.86 2,220,494.57 0.22 - - - - - - - -
5.10.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) M2 5.00 244,970.00 1,224,850.00 0.12 - - - - - - - -

TOTAL PEKERJAAN PLAMBING DAN SANITASI 42,151,921.52 4.26 0.00 0.08 0.08

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Pek. Pembersian Awal m2 81.86 17,600.00 1,440,780.00 0.15 81.86 100.00 0.15 - - 81.86 100.00 0.15
1.2 Pek. Pengukuran & Pemasangan Bouwplank m1 48.60 106,461.25 5,174,016.75 0.52 48.60 100.00 0.52 - - 48.60 100.00 0.52

TOTAL PEKERJAAN PERSIAPAN 6,614,796.75 0.67 0.67 0.00 0.67

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Batu Kali (Badan Bangunan,Ruang Bilas)
2.1.1.1 Galian Pondasi Batu Kali < 1 m m3 22.05 73,892.50 1,629,329.63 0.16 6.62 30.00 0.05 - - 6.62 30.00 0.05
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.1.1.2 Urugan Pasir Dibawah Pondasi Batu Kali T.5 cm m3 1.05 174,757.00 183,494.85 0.02 1.05 100.00 0.02 - - 1.05 100.00 0.02
2.1.1.3 Pasangan Aanstamping Bawah Pondasi Batu Kali T.10 cm m3 2.10 392,699.70 824,669.37 0.08 2.10 100.00 0.08 - - 2.10 100.00 0.08
2.1.1.4 Urugan Tanah Kembali Pondasi Batu Kali m3 10.08 54,285.00 547,192.80 0.06 3.02 30.00 0.02 - - 3.02 30.00 0.02
2.1.1.5 Pondasi Batu Kali 1 Sp : 3 Pp m3 8.82 824,945.00 7,276,014.90 0.73 8.82 100.00 0.73 - - 8.82 100.00 0.73
2.1.2 Perjaan Pondasi Rollage L.15 cm (Selasar)
2.1.2.1 Galian Tanah Pondasi Rollage < 1 m m3 1.52 73,892.50 112,501.33 0.01 0.15 10.00 0.00 - - 0.15 10.00 0.00
2.1.2.2 Urugan Pasir Dibawah Pondasi Rollage T.5 cm m3 0.30 174,757.00 53,213.51 0.01 0.03 10.00 0.00 - - 0.03 10.00 0.00
2.1.2.3 Pasangan Lantai Kerja Bawah Pondasi Rollage T.5 cm (Beton K300) m3 0.30 1,118,398.60 340,552.37 0.03 0.30 100.00 0.03 - - 0.30 100.00 0.03
2.1.2.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp m3 14.21 128,260.00 1,822,574.60 0.18 14.21 100.00 0.18 - - 14.21 100.00 0.18
2.2 Pekerjaan Sloef, Kolom, Plat dan Ringbalk - -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Ruang Bilas) - -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 m3 1.41 1,118,398.60 1,580,297.22 0.16 1.41 100.00 0.16 - - 1.41 100.00 0.16
2.2.1.2 Bekisting 2x Pakai m2 9.42 114,467.10 1,078,280.08 0.11 9.42 100.00 0.11 - - 9.42 100.00 0.11
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI kg 243.74 21,465.73 5,232,043.29 0.53 243.74 100.00 0.53 - - 243.74 100.00 0.53
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan) - -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slum (12 - 2) cm, w/c = 0,52 m3 0.48 1,118,398.60 533,476.13 0.05 0.48 100.00 0.05 - - 0.48 100.00 0.05
2.2.2.2 Bekisting 2x Pakai m2 3.18 193,504.30 615,343.67 0.06 3.18 100.00 0.06 - - 3.18 100.00 0.06
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI kg 98.75 21,465.73 2,119,732.25 0.21 98.75 100.00 0.21 - - 98.75 100.00 0.21
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Ruang Bilas) - -
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.25 1,008,343.60 249,111.29 0.03 0.25 100.00 0.03 - - 0.25 100.00 0.03
2.2.3.2 Bekisting 2x Pakai m2 1.65 193,504.30 318,701.58 0.03 1.65 100.00 0.03 - - 1.65 100.00 0.03
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI kg 51.14 21,465.73 1,097,861.33 0.11 51.14 100.00 0.11 - - 51.14 100.00 0.11
2.2.4 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan) - -
2.2.4.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.04 1,008,343.60 1,043,635.63 0.11 1.04 100.00 0.11 - - 1.04 100.00 0.11
2.2.4.2 Bekisting 2x Pakai m2 6.90 197,959.30 1,365,919.17 0.14 6.90 100.00 0.14 - - 6.90 100.00 0.14
2.2.4.3 Besi Beton Ø12 SNI, Ø6 SNI kg 148.86 21,465.73 3,195,302.68 0.32 148.86 100.00 0.32 - - 148.86 100.00 0.32
2.2.5 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan) - -
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.09 1,008,343.60 1,103,531.24 0.11 1.09 100.00 0.11 - - 1.09 100.00 0.11
2.2.5.2 Bekisting 2x Pakai m2 14.59 197,959.30 2,888,622.11 0.29 14.59 100.00 0.29 - - 14.59 100.00 0.29
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI kg 157.40 21,465.73 3,378,705.12 0.34 157.40 100.00 0.34 - - 157.40 100.00 0.34
2.2.6 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Pintu Jendela) -
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.15 1,008,343.60 148,831.52 0.02 0.15 100.00 0.02 - - 0.15 100.00 0.02
2.2.6.2 Bekisting 2x Pakai m2 0.98 197,959.30 194,791.95 0.02 0.98 100.00 0.02 - - 0.98 100.00 0.02
2.2.6.3 Besi Beton Ø10 SNI, Ø6 SNI kg 20.35 21,465.73 436,752.39 0.04 20.35 100.00 0.04 - - 20.35 100.00 0.04
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) m2 59.01 163,856.00 9,669,142.56 0.98 59.01 100.00 0.98 - - 59.01 100.00 0.98
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4) m2 48.59 102,876.77 4,998,782.09 0.50 48.59 100.00 0.50 - - 48.59 100.00 0.50
2.5 Pekerjaan Rangka Plafond dan Dinding Dalam PVC Shunda (Besi Hollow Metal Galvalume 4/4) m2 56.16 102,876.77 5,777,559.22 0.58 - - - - - - - -

TOTAL PEKERJAAN STRUKTUR 59,815,965.86 6.04 5.29 0.00 5.29

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) m3 4.09 174,757.00 715,280.40 0.07 4.09 100.00 0.07 - - 4.09 100.00 0.07
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) m3 12.28 167,345.00 2,054,804.70 0.21 12.28 100.00 0.21 - - 12.28 100.00 0.21
3.1.1.3 Rabat Beton T.5 cm (Keseluruhan, Beton K300) m3 4.09 1,118,398.60 4,577,605.47 0.46 4.09 100.00 0.46 - - 4.09 100.00 0.46
3.1.1.4 Penutup Lantai Keramik Tekstur 60x60 (Badan Bangunan) m2 36.93 413,098.40 15,255,723.91 1.54 29.54 80.00 1.23 7.39 20.00 0.31 36.93 100.00 1.54
3.1.1.5 Penutup Lantai Andesit Polos 30x30 (Selasar, Ruang Bilas) m2 45.89 284,369.80 13,049,730.12 1.32 - - - 45.89 100.00 1.32 45.89 100.00 1.32
3.1.1.6 Penutup Plat Wastafel (Granit 60x60, Toilet Pria dan Wanita) m2 2.20 841,621.73 1,851,567.81 0.19 - - - - - - - -
3.1.2 Pekerjaan Dinding
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Selasar, 1 Sp : 4 Pp) 90.64 242,533.50 21,983,236.44 2.22 72.51 80.00 1.78 18.13 20.00 0.44 90.64 100.00 2.22
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Wc ) 30.00 65,473.32 1,964,199.60 0.20 24.00 80.00 0.16 6.00 20.00 0.04 30.00 100.00 0.20
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm 121.28 60,304.20 7,313,693.38 0.74 97.02 80.00 0.59 24.26 20.00 0.15 121.28 100.00 0.74
3.1.2.4 Coating Bening 121.28 46,853.13 5,682,347.00 0.57 - - - - - - - -
3.1.2.5 Dinding Andesit Polos 30x30 cm ( Wc, Ruang Bilas ) 56.52 284,369.80 16,072,581.10 1.62 - - - - - - - -
3.1.2.6 Dinding Keramik 30x60 cm ( Sisi Dalam ) 69.88 370,557.00 25,894,523.16 2.62 - - - - - - - -
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) 9.00 995,076.50 8,955,688.50 0.90 - - - - - - - -
3.1.2.8 Cubicle Panel + Accessories (Pintu Wc dan Partisi Urinoir) 10.86 1,360,000.00 14,769,600.00 1.49 - - - - - - - -
3.1.2.9 Dinding Bitumen Gelombang 48.59 201,749.24 9,802,995.57 0.99 - - - - - - - -
3.1.2.10 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Pria) 1.00 1,200,000.00 1,200,000.00 0.12 - - - - - - - -
3.1.2.11 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Wanita) 1.00 750,000.00 750,000.00 0.08 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.1.3 Plafond dan Dinding Dalam Shunda ( Badan Bangunan ) 56.16 125,878.50 7,069,336.56 0.71 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.2 Pekerjaan Pintu dan Jendela ( Badan Bangunan )
3.2.1 Pintu P1
3.2.1.1 Pasangan Kusen Almunium Coating P1 (4" x 13/4") cm 10.96 157,199.02 1,722,901.26 0.17 - - - - - - - -
3.2.1.2 Pasangan Daun Pintu P1 (Panel Almunium Coating - Coating) 4.30 870,323.19 3,742,389.72 0.38 - - - - - - - -
3.2.1.3 Pasangan Kunci Tanam 2x Slag P1 2.00 416,663.50 833,327.00 0.08 - - - - - - - -
3.2.1.4 Pasangan ensel P1 6.00 61,225.56 367,353.36 0.04 - - - - - - - -
3.2.1.5 Pasangan Doorcloser P1 2.00 241,902.10 483,804.20 0.05 - - - - - - - -
3.2.1.6 Pasangan Handle P1 2.00 229,802.10 459,604.20 0.05 - - - - - - - -
3.2.2 Jendela J1
3.2.2.1 Pasangan Kusen Almunium Coating J1 (4" x 13/4") cm 28.80 157,199.02 4,527,331.78 0.46 - - - - - - - -
3.2.2.2 Pasangan Kaca Mati 5 mm J1 0.60 145,705.56 87,423.34 0.01 - - - - - - - -
3.2.3 Jendela J2
3.2.3.1 Pasangan Kusen Almunium Coating J2 (4" x 13/4") cm 55.20 157,199.02 8,677,385.90 0.88 - - - - - - - -
3.2.3.2 Pasangan Kaca Mati 5 mm J2 0.90 145,705.56 131,135.00 0.01 - - - - - - - -
3.3. Pengecetan Plafond (1 Plamir : 1 Cat Dasar : 2 Cat Penutup), (Interior) 56.16 43,550.65 2,445,804.50 0.25 - - - - - - - -
3.4 Pekerjaan Atap
3.4.1 Atap Bitumen Gelombang (Badan Bangunan) 59.01 201,749.24 11,905,222.65 1.20 - - - - - - - -
3.4.2 Nok Bitumen (Badan Bangunan) 35.25 143,629.20 5,062,929.30 0.51 - - - - - - - -
3.4.3 Listplank (Kasiplank, Badan Bangunan, Enterance) 39.08 70,972.00 2,773,585.76 0.28 - - - - - - - -

TOTAL PEKERJAAN FINISHING ARSITEKTUR 202,183,111.69 20.42 4.50 2.26 6.76

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel 1.00 1,803,826.75 1,803,826.75 0.18 - - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt 10.00 353,938.75 3,539,387.50 0.36 - - - - - - - -
4.1.3 Pasangan Lampu Down Light 2.5" Outbow LED 5.5 Watt 12.00 305,538.75 3,666,465.00 0.37 - - - - - - - -
4.1.4 Pasangan Saklar Ganda 5.00 223,478.75 1,117,393.75 0.11 - - - - - - - -
4.2 Pasangan Instalasi Stop Kontak
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA 3.00 216,218.75 648,656.25 0.07 - - - - - - - -
4.2.2 Pasangan Stop Kontak Wall Exhauser 6.00 216,218.75 1,297,312.50 0.13 - - - - - - - -
4.3 Pasangan Instalasi Jaringan Wall Exhauser 12.00 108,772.68 1,305,272.10 0.13 - - - - - - - -
4.3.1 Pasangan Wall Exhauser 12 Inch - FV30RUN 6.00 513,500.00 3,081,000.00 0.31 - - - - - - - -
4.4 Pasangan Penangkal Petir 1.00 3,500,000.00 3,500,000.00 0.35 - - - - - - - -
4.5 Pasangan Instlasi Jaringan Kabel Fiber Optic (CCTV) 3.00 786,326.75 2,358,980.25 0.24 - - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2 MP (Luar Bangunan, Sambungan Dari Mini Resto) 3.00 656,975.00 1,970,925.00 0.20 - - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm 4.00 20,442.68 81,770.70 0.01 - - - - - - - -
4.6.1 Pasangan Horn Speaker (Sambungan Dari Mini Resto) 2.00 494,826.75 989,653.50 0.10 - - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25 kg) 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - - -
4.8 Pasangan Instalasi PLN Power 1.00 10,000,000.00 10,000,000.00 1.01 - - - - - - - -

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 44,560,643.30 4.50 0.00 0.00 0.00

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVc Tipe AW Diameter 3/4" (Air Bersih Dari Sumur Bor / PDAM Reservoir) m1 18.50 28,304.65 523,636.03 0.05 - - - - - - - -
5.2 Pipa PVC Tipe AW Diameter 3/4" (Distribusi Air Bersih Dari Reservoir) m1 26.50 28,304.65 750,073.23 0.08 - - - - - - - -
5.3 Pipa PVC Tipe AW Diameter 3" (Air Kotor Ke Drainase Lingkungan) m1 23.00 135,539.80 3,117,415.40 0.31 - - - - - - - -
5.4 Pipa PVC Tipe AW Diameter 4" (Disposal) m1 18.00 186,689.80 3,360,416.40 0.34 - - - - - - - -
5.5 Pasangan 1 bh Closet Duduk / Monoblock (TOTO) bh 6.00 3,655,597.00 21,933,582.00 2.22 - - - - - - - -
5.6 Pasangan 1 bh Wastafel (TOTO) 3.00 3,571,942.00 10,715,826.00 1.08 - - - - - - - -
5.7 Pasangan 1 bh Uninoir (TOTO) 2.00 6,665,285.00 13,330,570.00 1.35 - - - - - - - -
5.8 Pasangan 1 bh Floor Drain 9.00 41,123.50 370,111.50 0.04 - - - - - - - -
5.9 Pasangan 1 bh Kran dia. 1/2' atau 3/4" 8.00 102,228.50 817,828.00 0.08 - - - - - - - -
5.10 Pasangan 1 bh Kran wastafel dia. 1/2' atau 3/4" 2.00 335,428.50 670,857.00 0.07 - - - - - - - -
5.11 Pasangan 1 bh shower closet dia. 1/2' atau 3/4" 6.00 142,928.50 857,571.00 0.09 - - - - - - - -
5.12 Pasangan 1 bh shower Wall dia. 1/2' atau 3/4" (Ruang Bilas) 4.00 1,435,428.50 5,741,714.00 0.58 - - - - - - - -
5.13 Pasangan 1 bh Stop Kran (Gate Valve) dia. 3/4" 2.00 141,428.50 282,857.00 0.03 - - - - - - - -
5.14 Pasangan Mesin Air 1.00 741,000.00 741,000.00 0.07 - - - - - - - -
5.14b Pasangan Mesin Pemanas Air 1.00 5,000,000.00 5,000,000.00 0.51 - - - - - - - -
5.15 Septictank Biotank Kap. 4m3 1.00 20,380,000.00 20,380,000.00 2.06 - - - - - - - -
5.16 Pasangan Sumur Bor Jet Pump 30.00 350,000.00 10,500,000.00 1.06 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.17 Reservoir 1200 Liter 1.00 1,850,000.00 1,850,000.00 0.19 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.18 Reservoir 200x150x350 cm
5.18.1 Pekerjaan Pondasi Pedestal Pd1
5.18.1.1 Galian Tanah Pondasi Poerplat < 1m 1.62 74,250.00 120,285.00 0.01 - - - - - - - -
5.18.1.2 Urugan Tanah Kembali Pondasi Poerplat 0.43 55,000.00 23,760.00 0.00 - - - - - - - -
5.18.1.3 Tiang Pondasi Pedestal 50x50 cm
Beton Mutu fc = 26,6 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.80 1,485,144.21 1,188,115.37 0.12 - - - - - - - -
Bekisting 2x Pakai 3.20 193,504.30 619,213.76 0.06 - - - - - - - -
Besi Beton Ø12, Ø8 49.44 21,465.73 1,061,174.10 0.11 - - - - - - - -
5.18.1.4 Pondasi Poerplat 90x90 cm,T.20 cm
Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.65 1,485,144.21 962,373.45 0.10 - - - - - - - -
Bekisting 2x Pakai 1.44 124,547.50 179,348.40 0.02 - - - - - - - -
Besi Beton Ø14 SNI 214.35 21,465.73 4,601,114.73 0.46 - - - - - - - -
5.18.2 Rangkai Tengah Dan Lantai Menara (Besi Hollow Galvanis 4/4) 34.82 244,970.00 8,529,855.40 0.86 - - - - - - - -
5.18.3 Rangka Utama menara ( Besi Hollow Galvanis 5/10 32.28 179,454.00 5,792,775.12 0.59 - - - - - - - -
5.18.4 Tplat Baja Lantai Menara T.3mm 3.00 740,164.86 2,220,494.57 0.22 - - - - - - - -
5.18.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) 5.00 244,970.00 1,224,850.00 0.12 - - - - - - - -

TOTAL PEKERJAAN PLAMBING DAN SANITASI 127,466,817.45 12.88 - - -

6. PEKERJAAN AKHIR - - -
6.1 Pembersihan Sisa Pekerjaan Ls 1.00 2,400,000.00 2,400,000.00 0.24 - - - - - - - -

TOTAL PEKERJAAN AKHIR 2,400,000.00 0.24 0.00 0.00 0.00

C. PENERAPAN SMKK

1. PENYIAPAN RKK
1.1 Pembuatan Dokumen Rencana Keselamatan Konstruksi
1.2 Pembuatan Prosedur dan instruksi kerja Set 1.00 2,000,000.00 2,000,000.00 0.20 1.00 100.00 0.20 - - 1.00 100.00 0.20
1.3 Penyiapan formulir
TOTAL PENYIAPAN RKK 2,000,000.00 0.20 0.20 - 0.20
2. SOSIALISASI, PROMOSI DAN PELATIHAN
2.1 Induksi K3 (Safety Induction) Org 5.00 7,500.00 37,500.00 0.00 0.50 10.00 0.00 - - 0.50 10.00 0.00
2.2 Pengarahan K3 (Safety Briefing) Org 5.00 15,000.00 75,000.00 0.01 5.00 100.00 0.01 - - 5.00 100.00 0.01
2.3 Pelatihan K3
2.3.1 Bekerja di ketinggian Org 4.00 7,500.00 30,000.00 0.00 4.00 100.00 0.00 - - 4.00 100.00 0.00
2.3.2 Penggunaan Bahan Kimia (MSDS) Org 2.00 7,500.00 15,000.00 0.00 2.00 100.00 0.00 - - 2.00 100.00 0.00
2.4 Simulasi K3 Org 5.00 7,500.00 37,500.00 0.00 5.00 100.00 0.00 - - 5.00 100.00 0.00
2.5 Spanduk (Banner) Lb 1.00 150,000.00 150,000.00 0.02 1.00 100.00 0.02 - - 1.00 100.00 0.02
2.6 Poster 2 2.00 50,000.00 100,000.00 0.01 2.00 100.00 0.01 - - 2.00 100.00 0.01
2.7 Papan Informasi K3 1 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
TOTAL SOSIALISASI, PROMOSI DAN PELATIHAN 945,000.00 0.10 0.09 - 0.09
3. ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI
3.1 APK
3.1.1 Tali Keselamatan (Life Line) Ls 1.00 1,700,000.00 1,700,000.00 0.17 1.00 100.00 0.17 - - 1.00 100.00 0.17
3.1.2 Pembatas Area (Restricted Area) Ls 1.00 2,000,000.00 2,000,000.00 0.20 1.00 100.00 0.20 - - 1.00 100.00 0.20
3.2 APD
3.2.1 Topi Pelindung (Safety Helmet) Bh 10.00 75,000.00 750,000.00 0.08 10.00 100.00 0.08 - - 10.00 100.00 0.08
3.2.2 Pelindung Mata (Googles, Spectacles) Bh 5.00 25,000.00 125,000.00 0.01 5.00 100.00 0.01 - - 5.00 100.00 0.01
3.2.3 Pelindung Pernapasan dan Mulut (Masker) Bh 100.00 5,000.00 500,000.00 0.05 100.00 100.00 0.05 - - 100.00 100.00 0.05
3.2.4 Sarung Tangan (Safety Gloves) Psg 10.00 15,000.00 150,000.00 0.02 10.00 100.00 0.02 - - 10.00 100.00 0.02
3.2.5 Sepatu Keselamatan (Safety Shoes) Psg 10.00 350,000.00 3,500,000.00 0.35 10.00 100.00 0.35 - - 10.00 100.00 0.35
3.2.6 Penunjang Seluruh Tubuh (Full Body Harness) Bh 2.00 500,000.00 1,000,000.00 0.10 2.00 100.00 0.10 - - 2.00 100.00 0.10
3.2.7 Rompi Keselamatan (Safety Vest) Bh 10.00 25,000.00 250,000.00 0.03 10.00 100.00 0.03 - - 10.00 100.00 0.03
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 9,975,000.00 1.01 1.01 - 1.01
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4. ASURANSI DAN PERIZINAN
4.1 Asuransi Ls 1.00 3,000,000.00 3,000,000.00 0.30 1.00 100.00 0.30 - - 1.00 100.00 0.30
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 3,000,000.00 0.30 0.30 - 0.30
5. PERSONEL K3 KONSTRUKSI
5.1 Ahli K3 Konstruksi -
5.2 Petugas K3 Konstruksi Ob 4.00 3,675,000.00 14,700,000.00 1.48 4.00 100.00 1.48 - - 4.00 100.00 1.48
TOTAL PERSONEL K3 KONSTRUKSI 14,700,000.00 1.48 1.48 - 1.48
6. FASILITAS, SARANA DAN PRASARANA KESEHATAN
6.1 Peralatan P3K (Kotak P3K, Tandu, Obat Luka, Perban, dll) Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
TOTAL FASILITAS, SARANA DAN PRASARANA KESEHATAN 500,000.00 0.05 0.05 - 0.05
7. RAMBU - RAMBU YANG DIPERLUKAN
7.1 Rambu Petunjuk bh 2.00 75,000.00 150,000.00 0.02 2.00 100.00 0.02 - - 2.00 100.00 0.02
7.2 Rambu Larangan bh 2.00 75,000.00 150,000.00 0.02 2.00 100.00 0.02 - - 2.00 100.00 0.02
7.3 Rambu Peringatan bh 2.00 100,000.00 200,000.00 0.02 2.00 100.00 0.02 - - 2.00 100.00 0.02
7.4 Jalur Evakuasi (Escape Route) Ls 1.00 250,000.00 250,000.00 0.03 1.00 100.00 0.03 - - 1.00 100.00 0.03
TOTAL RAMBU - RAMBU YANG DIPERLUKAN 750,000.00 0.08 0.08 - 0.08
8. KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI
8.1 Ahli K3 Konstruksi Oj -
TOTAL KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI - 0.00
9. LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN
KONSTRUKSI
9.1 Alat Pemadam Api Ringan (APAR) bh 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
9.2 Program Inspeksi Ls 1.00 1,500,000.00 1,500,000.00 0.15 1.00 100.00 0.15 - - 1.00 100.00 0.15
9.3 Pelaporan dan Penyeledikan Insiden Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
9.4 Pembuatan Kartu Identitas Pekerja (KIP) Org 10.00 5,000.00 50,000.00 0.01 10.00 100.00 0.01 - - 10.00 100.00 0.01
TOTAL LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN KONSTRUKSI 2,550,000.00 0.26 0.26 - 0.26

A Jumlah Harga Penawaran 989,944,870.91 100.00 34.46 9.44 43.89


B PPN (10%) 98,994,487.09
C Jumlah (A+B) 1,088,939,358.00
PERSENTASE SAMPAI MINGGU INI 43.89
D Jumlah Dibulatkan 1,088,939,358.00

Bulukumba, 19 November 2020


Disetujui, Diketahui, Diperiksa Oleh, Dibuat Oleh,
Pejabat Pembuat Komitmen Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUTR Prov SulSel Dinas PUTR Prov SulSel CV.MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

A.KHADAFI HARUN, ST.,MT. L I L I, ST. IRHAM HARAHAP, ST. VIKA APRILIA DWI PUTRI
NIP. 19811126 200901 1 008 NIP. 19821229 201503 2 001 Site Engineer Direktris
LAPORAN KEMAJUAN MINGGUAN

Kegiatan : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba Minggu Ke : 06 ( Enam )
Satuan Kerja : Dinas Pekerjaan Umum Dan Tata Ruang Prov. Sulawesi Selatan Bidang Cipta Karya Periode : 20 November S/d 26 November 2020
Lokasi : Desa Ara, Kecamatan Bonto Bahari, Kabupaten Bulukumba, Provinsi Sulawesi Selatan No. Kontrak : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
Sumber Dana : Dana Bantuan Provinsi Nilai Kontrak : Rp. 1,088,939,358.00
Tahun Anggaran : 2020 Schedule Pelaksanaan : 16 Oktober S/d 14 Desember 2020

MINGGU LALU MINGGU INI S/D MINGGU INI


VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
NO URAIAN PEKERJAAN
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q

A. PEMBANGUNAN RUANG KULINER, SUVENIR, MUSHOLLAH DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Papan Proyek Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
1.2 Bedeng/Direksi Keet M2 5.50 1,512,555.00 8,319,052.50 0.84 5.50 100.00 0.84 - - 5.50 100.00 0.84

TOTAL PEKERJAAN PERSIAPAN 8,819,052.50 0.89 0.89 0.00 0.89

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Poerplat PP1 (Selasar Samping)
2.1.1.1 Galian Pondasi Poerplat < 1 m M3 0.32 73,837.50 23,628.00 0.00 0.32 100.00 0.00 - - 0.32 100.00 0.00
2.1.1.2 Urugan Pasir dibawah Pondasi Poerplat T.5 cm M3 0.04 148,335.00 5,933.40 0.00 0.04 100.00 0.00 - - 0.04 100.00 0.00
2.1.1.3 Urugan Tanah Kembali Pondasi Poerplat M3 0.31 54,175.00 16,794.25 0.00 0.31 100.00 0.00 - - 0.31 100.00 0.00
2.1.1.4 Pasangan Lantai Kerja bawah Pondasi Poerplat T.5 cm (Beton K300) M3 0.04 1,118,216.00 44,728.64 0.00 0.04 100.00 0.00 - - 0.04 100.00 0.00
2.1.1.5 Pondasi Poerplat 35x50 cm, T.20 cm -
Beton Mutu F'c = 26,4 mpa (K300), Slump (12-2) cm, w/c = 0,52 M3 0.14 1,118,216.00 156,550.24 0.02 0.14 100.00 0.02 - - 0.14 100.00 0.02
Bekisting 2x Pakai M2 0.56 107,013.50 59,927.56 0.01 0.56 100.00 0.01 - - 0.56 100.00 0.01
Besi Beton Ø14 SNI Kg 29.40 21,464.85 631,066.59 0.06 29.40 100.00 0.06 - - 29.40 100.00 0.06
2.1.2 Pekerjaan Pondasi Batu Kali (Badan Bangunan, Mushollah) - -
2.1.2.1 Galian Tanah Pondasi Batu Kali < 1 m M3 22.73 73,837.50 1,678,326.38 0.17 22.73 100.00 0.17 - - 22.73 100.00 0.17
2.1.2.2 Urugan Pasir dibawah Pondasi Batu Kali T.5 cm M3 1.08 148,335.00 160,201.80 0.02 1.08 100.00 0.02 - - 1.08 100.00 0.02
2.1.2.3 Pasangan Aanstamping bawah Pondasi Batu Kali T.10 M3 2.17 382,674.00 830,402.58 0.08 2.17 100.00 0.08 - - 2.17 100.00 0.08
2.1.2.4 Urugan Tanah Kembali Pondasi Batu Kali M3 10.39 54,175.00 562,878.25 0.06 10.39 100.00 0.06 - - 10.39 100.00 0.06
2.1.2.5 Pondasi Batu Kali 1 Sp : 3 Pp M3 9.09 827,447.50 7,521,497.78 0.76 9.09 100.00 0.76 - - 9.09 100.00 0.76
2.1.3 Pekerjaan Pondasi Rollage L.15 cm (Entrance, Selasar Samping) - - -
2.1.3.1 Galian Tanah Pondasi Rollage < 1 m M3 2.23 73,837.50 164,657.63 0.02 2.23 100.00 0.02 - - 2.23 100.00 0.02
2.1.3.2 Urugan Pasir dibawah Pondasi Rollage T.5 cm M3 0.45 148,335.00 66,750.75 0.01 0.45 100.00 0.01 - - 0.45 100.00 0.01
2.1.3.3 Pasangan Lantai Kerja bawah Pondasi Rollage T.5 cm (Beton K300) M3 0.45 1,118,216.00 499,003.89 0.05 0.45 100.00 0.05 - - 0.45 100.00 0.05
2.1.3.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp M2 20.83 128,436.00 2,675,321.88 0.27 20.83 100.00 0.27 - - 20.83 100.00 0.27
2.2 Pekerjaan Sloef, Kolom dan Ringbalk - -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Mushollah) - -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 1.62 1,118,216.00 1,815,703.23 0.18 1.62 100.00 0.18 - - 1.62 100.00 0.18
2.2.1.2 Bekisting 2x Pakai M2 10.83 114,438.50 1,239,368.96 0.13 10.83 100.00 0.13 - - 10.83 100.00 0.13
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI Kg 280.09 21,464.85 6,012,089.84 0.61 280.09 100.00 0.61 - - 280.09 100.00 0.61
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan, Mushollah) - -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.88 1,118,216.00 981,234.54 0.10 0.88 100.00 0.10 - - 0.88 100.00 0.10
2.2.2.2 Bekisting 2x Pakai M2 5.85 193,468.00 1,131,787.80 0.11 5.85 100.00 0.11 - - 5.85 100.00 0.11
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 181.66 21,464.85 3,899,347.58 0.39 181.66 100.00 0.39 - - 181.66 100.00 0.39
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Selasar, Westafel, Tempat Wudhu) -
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 0.34 100.00 0.03 - - 0.34 100.00 0.03
2.2.3.2 Bekisting 2x Pakai M2 2.26 193,468.00 437,237.68 0.04 2.26 100.00 0.04 - - 2.26 100.00 0.04
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 70.10 21,464.85 1,504,686.30 0.15 70.10 100.00 0.15 - - 70.10 100.00 0.15
2.2.4 Pekerjaan Kolom K1 15 x 30 (Selasar Samping) -
2.2.4.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.62 1,118,216.00 694,412.14 0.07 0.62 100.00 0.07 - - 0.62 100.00 0.07
2.2.4.2 Bekisting 2x Pakai M2 6.21 193,468.00 1,201,436.28 0.12 6.21 100.00 0.12 - - 6.21 100.00 0.12
2.2.4.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 99.69 21,464.85 2,139,830.90 0.22 99.69 100.00 0.22 - - 99.69 100.00 0.22
2.2.5 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan, Mushollah) -
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 2.08 1,008,161.00 2,097,478.96 0.21 2.08 100.00 0.21 - - 2.08 100.00 0.21
2.2.5.2 Bekisting 2x Pakai M2 13.87 197,923.00 2,745,192.01 0.28 13.87 100.00 0.28 - - 13.87 100.00 0.28
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 299.22 21,464.85 6,422,712.42 0.65 299.22 100.00 0.65 - - 299.22 100.00 0.65
2.2.6 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan) -
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 0.34 100.00 0.03 - - 0.34 100.00 0.03
2.2.6.2 Bekisting 2x Pakai M2 2.24 197,923.00 443,347.52 0.04 2.24 100.00 0.04 - - 2.24 100.00 0.04
2.2.6.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 48.32 21,464.85 1,037,181.55 0.10 48.32 100.00 0.10 - - 48.32 100.00 0.10
2.2.7 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Mushollah, Pintu Jendela) -
2.2.7.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.84 1,008,161.00 846,855.24 0.09 0.84 100.00 0.09 - - 0.84 100.00 0.09
2.2.7.2 Bekisting 2x Pakai M2 5.59 197,923.00 1,106,389.57 0.11 5.59 100.00 0.11 - - 5.59 100.00 0.11
2.2.7.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 115.53 21,464.85 2,479,834.12 0.25 115.53 100.00 0.25 - - 115.53 100.00 0.25
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.2.8 Pekerjaan Plat Beton (Selasar Samping, Westafel) -
2.2.8.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.22 1,008,161.00 221,795.42 0.02 0.22 100.00 0.02 - - 0.22 100.00 0.02
2.2.8.2 Bekisting 2x Pakai M2 2.21 237,468.00 524,804.28 0.05 2.21 100.00 0.05 - - 2.21 100.00 0.05
2.2.8.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 54.54 21,464.85 1,170,692.92 0.12 54.54 100.00 0.12 - - 54.54 100.00 0.12
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) M2 152.03 163,636.00 24,877,581.08 2.51 152.03 100.00 2.51 - - 152.03 100.00 2.51
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4, Entrance) M2 42.24 242,170.50 10,229,281.92 1.03 42.24 100.00 1.03 - - 42.24 100.00 1.03
2.5 Pekerjaan Tiang Atap Bitumen Gelombang (Besi Hollow Galvanis 5/10, Entrance) M' 20.40 178,365.00 3,638,646.00 0.37 20.40 100.00 0.37 - - 20.40 100.00 0.37
2.6 Pekerjaan Rangka Plafond Kalsiboard (Besi Hollow Metal Galvalume 4/4) M2 147.40 102,837.17 15,158,198.37 1.53 147.40 100.00 1.53 - - 147.40 100.00 1.53

TOTAL PEKERJAAN STRUKTUR 109,840,345.70 11.10 11.10 0.00 11.10

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) M3 8.54 148,335.00 1,266,780.90 0.13 8.54 100.00 0.13 - - 8.54 100.00 0.13
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) M3 25.63 167,227.00 4,285,636.74 0.43 25.63 100.00 0.43 - - 25.63 100.00 0.43
3.1.1.3 Rabat Beton bawah Lantai T.5 cm (Keseluruhan, Beton K300) M3 8.54 1,118,216.00 9,549,564.64 0.96 8.54 100.00 0.96 - - 8.54 100.00 0.96
3.1.1.4 Penutup Lantai Keramik Motif 60x60 (Badan Bangunan, Mushollah) M2 62.94 403,309.50 25,384,299.93 2.56 59.79 95.00 2.44 - - 59.79 95.00 2.44
3.1.1.5 Penutup Lantai Conwood Deck 6" (Entrance) M2 59.01 866,833.08 51,151,820.09 5.17 - - - - - - - -
3.1.1.6 Penutup Lantai Andesit Polos 30x30 (Selasar, Tempat Wudhu, Ram) M2 51.05 232,589.50 11,873,693.98 1.20 - - - - - - - -
3.1.1.7 Plint Lantai Keramik 10x60 (Badan Bangunan, Mushollah) M' 38.85 51,605.03 2,004,855.55 0.20 - - - - - - - -
3.1.2 Pekerjaan Dinding -
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Mushollah, 1 Sp : 4 Pp) M2 74.55 242,979.00 18,114,084.45 1.83 74.55 100.00 1.83 - - 74.55 100.00 1.83
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Selasar Samping, Tempat Wudhu) M2 5.14 65,550.32 336,928.64 0.03 5.14 100.00 0.03 - - 5.14 100.00 0.03
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm (Badan Bangunan, Mushollah) M2 91.30 60,403.20 5,514,812.16 0.56 91.30 100.00 0.56 - - 91.30 100.00 0.56
3.1.2.4 Plesteran Ciprat 1 Sp : 2 Pp Tebal 15 mm (Selasar Samping, Antar Kolom) M2 24.84 49,215.10 1,222,503.08 0.12 24.84 100.00 0.12 - - 24.84 100.00 0.12
3.1.2.5 Dinding Keramik Mozaik 30x60 (Selasar Samping, Westafel, Tempat Wudhu) M2 18.44 410,432.00 7,568,366.08 0.76 - - - - - - - -
3.1.2.6 Coating Bening (Badan Bangunan, Mushollah, Kolom Luar) M2 127.49 45,973.13 5,861,113.71 0.59 - - - - - - - -
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) M2 8.64 995,043.50 8,597,175.84 0.87 - - - - - - - -
3.1.2.8 Dinding Wallpaper Bata L.50 cm (Sisi Dalam) M2 28.13 80,005.50 2,250,554.72 0.23 - - - - - - - -
3.1.3 Pekerjaan Plafond -
3.1.3.1 Plafond Kalsiboard (Badan Bangunan, Kemiringan Atap, Mushollah) M2 147.40 44,924.00 6,621,797.60 0.67 147.40 100.00 0.67 - - 147.40 100.00 0.67
3.1.3.2 Plafond Kalsiboard (Lapis Bawah Atap, Entrance) M2 42.24 44,924.00 1,897,589.76 0.19 42.24 100.00 0.19 - - 42.24 100.00 0.19
3.2 Pekerjaan Pintu dan Jendela (Badan Bangunan) -
3.2.1 Pintu P1 (Entrance dan Back Entrance, Badan Bangunan) -
3.2.1.1 Pasangan Kusen Alumunium Coating P1 (4" x 1 3/4") cm M' 22.40 157,194.40 3,521,154.56 0.36 - - - - - - - -
3.2.1.2 Pasangan Daun Pintu P1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - - -
3.2.1.3 Pasangan Kaca Mati 5 mm P1 M2 11.20 145,703.80 1,631,882.56 0.16 - - - - - - - -
3.2.1.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - - -
3.2.1.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - - -
3.2.1.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - - -
3.2.1.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - - -
3.2.2 Jendela J1 (Badan Bangunan) -
3.2.2.1 Pasangan Kusen Alumunium Coating J1 (4" x 1 3/4") cm M' 40.60 157,194.40 6,382,092.64 0.64 - - - - - - - -
3.2.2.2 Pasangan Kaca Mati 5 mm J1 M2 8.00 145,703.80 1,165,630.40 0.12 - - - - - - - -
3.2.3 Pintu PJ1 (Mushollah) -
3.2.3.1 Pasangan Kusen Alumunium Coating PJ1 (4" x 1 3/4") cm M' 22.20 157,194.40 3,489,715.68 0.35 - - - - - - - -
3.2.3.2 Pasangan Daun Pintu PJ1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - - -
3.2.3.3 Pasangan Kaca Mati 5 mm P1 M2 8.70 145,703.80 1,267,623.06 0.13 - - - - - - - -
3.2.3.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - - -
3.2.3.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - - -
3.2.3.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - - -
3.2.3.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - - -
3.3 Pekerjaan Pengecatan -
3.3.1 Pengecatan Plafond (1 Plamir ; 1 Cat Dasar : 2 Cat Penutup), (Interior) M2 189.64 35,536.05 6,739,056.52 0.68 189.64 100.00 0.68 - - 189.64 100.00 0.68
3.3.2 Pengecatan Rangka Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 23.76 168,454.00 4,002,467.04 0.40 23.76 100.00 0.40 - - 23.76 100.00 0.40
3.3.3 Pengecatan Tiang Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 6.12 168,454.00 1,030,938.48 0.10 6.12 100.00 0.10 - - 6.12 100.00 0.10
3.4 Pekerjaan Atap -
3.4.1 Atap Bitumen Gelombang (Badan Bangunan, Mushollah) M2 152.03 207,297.09 31,515,376.59 3.18 152.03 100.00 3.18 - - 152.03 100.00 3.18
3.4.2 Atap Bitumen Gelombang (Entrance) M2 42.24 207,297.09 8,756,229.08 0.88 42.24 100.00 0.88 - - 42.24 100.00 0.88
3.4.3 Nok Bitumen (Badan Bangunan, Mushollah) M' 14.55 134,101.00 1,951,169.55 0.20 14.55 100.00 0.20 - - 14.55 100.00 0.20
3.4.4 Listplank (Kalsiplank, Badan Bangunan, Mushollah, Entrance) M' 50.00 70,950.00 3,547,500.00 0.36 50.00 100.00 0.36 - - 50.00 100.00 0.36

TOTAL PEKERJAAN FINISHING ARSITEKTUR 257,222,142.77 25.98 13.18 0.00 13.18

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel Bh 1.00 1,572,826.75 1,572,826.75 0.16 - - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt Bh 16.00 353,938.75 5,663,020.00 0.57 16.00 100.00 0.57 - - 16.00 100.00 0.57
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4.1.3 Pasangan Lampu Down Light 2,5" Outbow LED 5,5 Watt Bh 11.00 305,538.75 3,360,926.25 0.34 11.00 100.00 0.34 - - 11.00 100.00 0.34
4.1.4 Pasangan Saklar Tunggal Bh 4.00 211,378.75 845,515.00 0.09 4.00 100.00 0.09 - - 4.00 100.00 0.09
4.1.5 Pasangan Saklar Ganda Bh 2.00 223,478.75 446,957.50 0.05 2.00 100.00 0.05 - - 2.00 100.00 0.05
4.2 Pasangan Instalasi Stop Kontak - -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA Bh 10.00 216,218.75 2,162,187.50 0.22 10.00 100.00 0.22 - - 10.00 100.00 0.22
4.2.2 Pasangan Stop Kontak AC 220 VA/3520 W (AC Split 1 PK) Bh 4.00 253,728.75 1,014,915.00 0.10 4.00 100.00 0.10 - - 4.00 100.00 0.10
4.3 Pasangan Instalasi Jaringan AC M' 30.00 108,772.68 3,263,180.25 0.33 30.00 100.00 0.33 - - 30.00 100.00 0.33
4.3.1 Pasangan AC Split 1 PK Bh 3.00 3,365,799.34 10,097,398.03 1.02 1.50 50.00 0.51 - - 1.50 50.00 0.51
4.4 Pasangan Penangkal Petir Ls 1.00 2,500,000.00 2,500,000.00 0.25 1.00 100.00 0.25 - - 1.00 100.00 0.25
4.5 Pasangan Instalasi Jaringan Kabel Fiber Optic (CCTV) Ttk 6.00 786,326.75 4,717,960.50 0.48 - - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2MP Bh 6.00 656,975.00 3,941,850.00 0.40 - - - - - - - -
4.5.2 Pasangan NVR Channel Set 1.00 5,023,975.00 5,023,975.00 0.51 - - - - - - - -
4.5.3 Pasangan Monitor LCD 32" Bh 1.00 2,944,975.00 2,944,975.00 0.30 - - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm M' 12.00 20,442.68 245,312.10 0.02 - - - - - - - -
4.6.1 Pasangan Horn Speaker Bh 6.00 494,826.75 2,968,960.50 0.30 - - - - - - - -
4.6.2 Pasangan Volume Kontrol Set 1.00 252,826.75 252,826.75 0.03 - - - - - - - -
4.6.3 Pasangan Perangkat Sound System Set 1.00 4,565,000.00 4,565,000.00 0.46 - - - - - - - -
4.6.4 Pasangan TB-Sound System Set 1.00 5,846,326.75 5,846,326.75 0.59 - - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25Kg) Ttk 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - - -
4.8 Pasangan Instalasi Jaringan Kabel Fiber Optic (Akses Point) Ttk 3.00 786,326.75 2,358,980.25 0.24 - - - - - - - -
4.8.1 Pasangan Server Set 1.00 7,578,826.75 7,578,826.75 0.77 - - - - - - - -
4.8.2 Pasangan Akses Point Bh 1.00 2,034,826.75 2,034,826.75 0.21 - - - - - - - -
4.8.3 Pasangan Switch HUB Bh 1.00 2,843,326.75 2,843,326.75 0.29 - - - - - - - -
4.9 Pasangan Instalasi PLN Power (Inc. Jalur ke Mushollah dan Toilet) Ls 1.00 9,000,000.00 9,000,000.00 0.91 - - - - - - - -

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 94,450,073.38 9.54 2.46 0.00 2.46

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVC Type AW Diameter 3/4" (Air Bersih Sambungan dari Tandon) M' 33.00 28,300.25 933,908.25 0.09 16.50 50.00 0.05 - - 16.50 50.00 0.05
5.2 Pipa PVC Type AW Diameter 3" (Air Kotor ke Drainase Lingkungan) M' 25.80 135,531.00 3,496,699.80 0.35 2.58 10.00 0.04 - - 2.58 10.00 0.04
5.3 Pasangan 1 Bh Wastafel Bh 2.00 3,934,865.00 7,869,730.00 0.79 - - - - - - - -
5.4 Pasangan 1 Bh Wastafel Cuci Piring (WCP) Bh 1.00 890,945.00 890,945.00 0.09 - - - - - - - -
5.5 Pasangan 1 Bh Floor Drain Bh 2.00 41,112.50 82,225.00 0.01 - - - - - - - -
5.6 Pasangan 1 Bh Kran Dia. 1/2" atau 3/4" Bh 10.00 102,217.50 1,022,175.00 0.10 - - - - - - - -
5.7 Pasangan 1 Bh Kran Wastafel Dia. 1/2" atau 3/4" Bh 3.00 335,417.50 1,006,252.50 0.10 - - - - - - - -
5.8 Pasangan 1 Bh Stop Kran (Gate Valve) Dia. 3/4" Bh 1.00 141,417.50 141,417.50 0.01 - - - - - - - -
5.9 Pasangan Mesin Air Bh 1.00 741,000.00 741,000.00 0.07 - - - - - - - -
5.10 Menara Reservoir 200x150x350 cm -
5.10.1 Pekerjaan Pondasi Pedestal Pd1 -
5.10.1.1 Galian Tanah Pondasi Poerplat < 1 m M3 1.62 73,837.50 119,616.75 0.01 - - - - - - - -
5.10.1.2 Urugan Tanah Kembali Pondasi Poerplat M3 0.43 54,175.00 23,295.25 0.00 - - - - - - - -
5.10.1.3 Tiang Pondasi Pedestal 50x50 cm - - -
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.80 1,118,216.00 894,572.80 0.09 - - - - - - - -
Bekisting 2x Pakai M2 3.20 193,468.00 619,097.60 0.06 - - - - - - - -
Besi Beton Ø12 SNI, Ø8 SNI Kg 49.44 21,464.85 1,061,130.60 0.11 - - - - - - - -
5.10.1.4 Pondasi Poerplat 90x90 cm, T.20 cm -
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.65 1,118,216.00 726,840.40 0.07 - - - - - - - -
Bekisting 2x Pakai M2 1.44 107,013.50 154,099.44 0.02 - - - - - - - -
Besi Beton Ø14 SNI Kg 214.35 21,464.85 4,600,940.54 0.46 - - - - - - - -
5.10.2 Rangka Tengah dan Lantai Menara (Besi Hollow Galvanis 4/4) M2 34.82 244,970.00 8,529,855.40 0.86 - - - - - - - -
5.10.3 Rangka Utama Menara (Besi Hollow Galvanis 5/10) M' 32.28 179,454.00 5,792,775.12 0.59 - - - - - - - -
5.10.4 Plat Baja Lantai Menara T.3 mm M2 3.00 740,164.86 2,220,494.57 0.22 - - - - - - - -
5.10.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) M2 5.00 244,970.00 1,224,850.00 0.12 - - - - - - - -

TOTAL PEKERJAAN PLAMBING DAN SANITASI 42,151,921.52 4.26 0.08 0.00 0.08

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Pek. Pembersian Awal m2 81.86 17,600.00 1,440,780.00 0.15 81.86 100.00 0.15 - - 81.86 100.00 0.15
1.2 Pek. Pengukuran & Pemasangan Bouwplank m1 48.60 106,461.25 5,174,016.75 0.52 48.60 100.00 0.52 - - 48.60 100.00 0.52

TOTAL PEKERJAAN PERSIAPAN 6,614,796.75 0.67 0.67 0.00 0.67

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Batu Kali (Badan Bangunan,Ruang Bilas)
2.1.1.1 Galian Pondasi Batu Kali < 1 m m3 22.05 73,892.50 1,629,329.63 0.16 6.62 30.00 0.05 - - 6.62 30.00 0.05
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.1.1.2 Urugan Pasir Dibawah Pondasi Batu Kali T.5 cm m3 1.05 174,757.00 183,494.85 0.02 1.05 100.00 0.02 - - 1.05 100.00 0.02
2.1.1.3 Pasangan Aanstamping Bawah Pondasi Batu Kali T.10 cm m3 2.10 392,699.70 824,669.37 0.08 2.10 100.00 0.08 - - 2.10 100.00 0.08
2.1.1.4 Urugan Tanah Kembali Pondasi Batu Kali m3 10.08 54,285.00 547,192.80 0.06 3.02 30.00 0.02 - - 3.02 30.00 0.02
2.1.1.5 Pondasi Batu Kali 1 Sp : 3 Pp m3 8.82 824,945.00 7,276,014.90 0.73 8.82 100.00 0.73 - - 8.82 100.00 0.73
2.1.2 Perjaan Pondasi Rollage L.15 cm (Selasar) -
2.1.2.1 Galian Tanah Pondasi Rollage < 1 m m3 1.52 73,892.50 112,501.33 0.01 0.15 10.00 0.00 - - 0.15 10.00 0.00
2.1.2.2 Urugan Pasir Dibawah Pondasi Rollage T.5 cm m3 0.30 174,757.00 53,213.51 0.01 0.03 10.00 0.00 - - 0.03 10.00 0.00
2.1.2.3 Pasangan Lantai Kerja Bawah Pondasi Rollage T.5 cm (Beton K300) m3 0.30 1,118,398.60 340,552.37 0.03 0.30 100.00 0.03 - - 0.30 100.00 0.03
2.1.2.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp m3 14.21 128,260.00 1,822,574.60 0.18 14.21 100.00 0.18 - - 14.21 100.00 0.18
2.2 Pekerjaan Sloef, Kolom, Plat dan Ringbalk - -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Ruang Bilas) - -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 m3 1.41 1,118,398.60 1,580,297.22 0.16 1.41 100.00 0.16 - - 1.41 100.00 0.16
2.2.1.2 Bekisting 2x Pakai m2 9.42 114,467.10 1,078,280.08 0.11 9.42 100.00 0.11 - - 9.42 100.00 0.11
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI kg 243.74 21,465.73 5,232,043.29 0.53 243.74 100.00 0.53 - - 243.74 100.00 0.53
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan) - -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slum (12 - 2) cm, w/c = 0,52 m3 0.48 1,118,398.60 533,476.13 0.05 0.48 100.00 0.05 - - 0.48 100.00 0.05
2.2.2.2 Bekisting 2x Pakai m2 3.18 193,504.30 615,343.67 0.06 3.18 100.00 0.06 - - 3.18 100.00 0.06
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI kg 98.75 21,465.73 2,119,732.25 0.21 98.75 100.00 0.21 - - 98.75 100.00 0.21
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Ruang Bilas) - -
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.25 1,008,343.60 249,111.29 0.03 0.25 100.00 0.03 - - 0.25 100.00 0.03
2.2.3.2 Bekisting 2x Pakai m2 1.65 193,504.30 318,701.58 0.03 1.65 100.00 0.03 - - 1.65 100.00 0.03
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI kg 51.14 21,465.73 1,097,861.33 0.11 51.14 100.00 0.11 - - 51.14 100.00 0.11
2.2.4 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan) - -
2.2.4.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.04 1,008,343.60 1,043,635.63 0.11 1.04 100.00 0.11 - - 1.04 100.00 0.11
2.2.4.2 Bekisting 2x Pakai m2 6.90 197,959.30 1,365,919.17 0.14 6.90 100.00 0.14 - - 6.90 100.00 0.14
2.2.4.3 Besi Beton Ø12 SNI, Ø6 SNI kg 148.86 21,465.73 3,195,302.68 0.32 148.86 100.00 0.32 - - 148.86 100.00 0.32
2.2.5 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan) - -
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.09 1,008,343.60 1,103,531.24 0.11 1.09 100.00 0.11 - - 1.09 100.00 0.11
2.2.5.2 Bekisting 2x Pakai m2 14.59 197,959.30 2,888,622.11 0.29 14.59 100.00 0.29 - - 14.59 100.00 0.29
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI kg 157.40 21,465.73 3,378,705.12 0.34 157.40 100.00 0.34 - - 157.40 100.00 0.34
2.2.6 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Pintu Jendela) -
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.15 1,008,343.60 148,831.52 0.02 0.15 100.00 0.02 - - 0.15 100.00 0.02
2.2.6.2 Bekisting 2x Pakai m2 0.98 197,959.30 194,791.95 0.02 0.98 100.00 0.02 - - 0.98 100.00 0.02
2.2.6.3 Besi Beton Ø10 SNI, Ø6 SNI kg 20.35 21,465.73 436,752.39 0.04 20.35 100.00 0.04 - - 20.35 100.00 0.04
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) m2 59.01 163,856.00 9,669,142.56 0.98 59.01 100.00 0.98 - - 59.01 100.00 0.98
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4) m2 48.59 102,876.77 4,998,782.09 0.50 48.59 100.00 0.50 - - 48.59 100.00 0.50
2.5 Pekerjaan Rangka Plafond dan Dinding Dalam PVC Shunda (Besi Hollow Metal Galvalume 4/4) m2 56.16 102,876.77 5,777,559.22 0.58 - - - - - - - -

TOTAL PEKERJAAN STRUKTUR 59,815,965.86 6.04 5.29 0.00 5.29

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) m3 4.09 174,757.00 715,280.40 0.07 4.09 100.00 0.07 - - 4.09 100.00 0.07
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) m3 12.28 167,345.00 2,054,804.70 0.21 12.28 100.00 0.21 - - 12.28 100.00 0.21
3.1.1.3 Rabat Beton T.5 cm (Keseluruhan, Beton K300) m3 4.09 1,118,398.60 4,577,605.47 0.46 4.09 100.00 0.46 - - 4.09 100.00 0.46
3.1.1.4 Penutup Lantai Keramik Tekstur 60x60 (Badan Bangunan) m2 36.93 413,098.40 15,255,723.91 1.54 36.93 100.00 1.54 - - 36.93 100.00 1.54
3.1.1.5 Penutup Lantai Andesit Polos 30x30 (Selasar, Ruang Bilas) m2 45.89 284,369.80 13,049,730.12 1.32 45.89 100.00 1.32 - - 45.89 100.00 1.32
3.1.1.6 Penutup Plat Wastafel (Granit 60x60, Toilet Pria dan Wanita) m2 2.20 841,621.73 1,851,567.81 0.19 - - - - - - - -
3.1.2 Pekerjaan Dinding - -
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Selasar, 1 Sp : 4 Pp) 90.64 242,533.50 21,983,236.44 2.22 90.64 100.00 2.22 - - 90.64 100.00 2.22
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Wc ) 30.00 65,473.32 1,964,199.60 0.20 30.00 100.00 0.20 - - 30.00 100.00 0.20
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm 121.28 60,304.20 7,313,693.38 0.74 121.28 100.00 0.74 - - 121.28 100.00 0.74
3.1.2.4 Coating Bening 121.28 46,853.13 5,682,347.00 0.57 - - - - - - - -
3.1.2.5 Dinding Andesit Polos 30x30 cm ( Wc, Ruang Bilas ) 56.52 284,369.80 16,072,581.10 1.62 - - - - - - - -
3.1.2.6 Dinding Keramik 30x60 cm ( Sisi Dalam ) 69.88 370,557.00 25,894,523.16 2.62 - - - - - - - -
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) 9.00 995,076.50 8,955,688.50 0.90 - - - - - - - -
3.1.2.8 Cubicle Panel + Accessories (Pintu Wc dan Partisi Urinoir) 10.86 1,360,000.00 14,769,600.00 1.49 - - - - - - - -
3.1.2.9 Dinding Bitumen Gelombang 48.59 201,749.24 9,802,995.57 0.99 - - - - - - - -
3.1.2.10 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Pria) 1.00 1,200,000.00 1,200,000.00 0.12 - - - - - - - -
3.1.2.11 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Wanita) 1.00 750,000.00 750,000.00 0.08 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.1.3 Plafond dan Dinding Dalam Shunda ( Badan Bangunan ) 56.16 125,878.50 7,069,336.56 0.71 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.2 Pekerjaan Pintu dan Jendela ( Badan Bangunan ) - -
3.2.1 Pintu P1 - -
3.2.1.1 Pasangan Kusen Almunium Coating P1 (4" x 13/4") cm 10.96 157,199.02 1,722,901.26 0.17 - - - - - - - -
3.2.1.2 Pasangan Daun Pintu P1 (Panel Almunium Coating - Coating) 4.30 870,323.19 3,742,389.72 0.38 - - - - - - - -
3.2.1.3 Pasangan Kunci Tanam 2x Slag P1 2.00 416,663.50 833,327.00 0.08 - - - - - - - -
3.2.1.4 Pasangan ensel P1 6.00 61,225.56 367,353.36 0.04 - - - - - - - -
3.2.1.5 Pasangan Doorcloser P1 2.00 241,902.10 483,804.20 0.05 - - - - - - - -
3.2.1.6 Pasangan Handle P1 2.00 229,802.10 459,604.20 0.05 - - - - - - - -
3.2.2 Jendela J1 - -
3.2.2.1 Pasangan Kusen Almunium Coating J1 (4" x 13/4") cm 28.80 157,199.02 4,527,331.78 0.46 - - - - - - - -
3.2.2.2 Pasangan Kaca Mati 5 mm J1 0.60 145,705.56 87,423.34 0.01 - - - - - - - -
3.2.3 Jendela J2 -
3.2.3.1 Pasangan Kusen Almunium Coating J2 (4" x 13/4") cm 55.20 157,199.02 8,677,385.90 0.88 - - - - - - - -
3.2.3.2 Pasangan Kaca Mati 5 mm J2 0.90 145,705.56 131,135.00 0.01 - - - - - - - -
3.3. Pengecetan Plafond (1 Plamir : 1 Cat Dasar : 2 Cat Penutup), (Interior) 56.16 43,550.65 2,445,804.50 0.25 - - - - - - - -
3.4 Pekerjaan Atap - -
3.4.1 Atap Bitumen Gelombang (Badan Bangunan) 59.01 201,749.24 11,905,222.65 1.20 - - - - - - - -
3.4.2 Nok Bitumen (Badan Bangunan) 35.25 143,629.20 5,062,929.30 0.51 - - - - - - - -
3.4.3 Listplank (Kasiplank, Badan Bangunan, Enterance) 39.08 70,972.00 2,773,585.76 0.28 - - - - - - - -

TOTAL PEKERJAAN FINISHING ARSITEKTUR 202,183,111.69 20.42 6.76 0.00 6.76

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel 1.00 1,803,826.75 1,803,826.75 0.18 - - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt 10.00 353,938.75 3,539,387.50 0.36 - - - 10.00 100.00 0.36 10.00 100.00 0.36
4.1.3 Pasangan Lampu Down Light 2.5" Outbow LED 5.5 Watt 12.00 305,538.75 3,666,465.00 0.37 - - - 12.00 100.00 0.37 12.00 100.00 0.37
4.1.4 Pasangan Saklar Ganda 5.00 223,478.75 1,117,393.75 0.11 - - - 5.00 100.00 0.11 5.00 100.00 0.11
4.2 Pasangan Instalasi Stop Kontak - -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA 3.00 216,218.75 648,656.25 0.07 - - - 3.00 100.00 0.07 3.00 100.00 0.07
4.2.2 Pasangan Stop Kontak Wall Exhauser 6.00 216,218.75 1,297,312.50 0.13 - - - 6.00 100.00 0.13 6.00 100.00 0.13
4.3 Pasangan Instalasi Jaringan Wall Exhauser 12.00 108,772.68 1,305,272.10 0.13 - - - 12.00 100.00 0.13 12.00 100.00 0.13
4.3.1 Pasangan Wall Exhauser 12 Inch - FV30RUN 6.00 513,500.00 3,081,000.00 0.31 - - - 6.00 100.00 0.31 6.00 100.00 0.31
4.4 Pasangan Penangkal Petir 1.00 3,500,000.00 3,500,000.00 0.35 - - - 0.50 50.00 0.18 0.50 50.00 0.18
4.5 Pasangan Instlasi Jaringan Kabel Fiber Optic (CCTV) 3.00 786,326.75 2,358,980.25 0.24 - - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2 MP (Luar Bangunan, Sambungan Dari Mini Resto) 3.00 656,975.00 1,970,925.00 0.20 - - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm 4.00 20,442.68 81,770.70 0.01 - - - - - - - -
4.6.1 Pasangan Horn Speaker (Sambungan Dari Mini Resto) 2.00 494,826.75 989,653.50 0.10 - - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25 kg) 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - - -
4.8 Pasangan Instalasi PLN Power 1.00 10,000,000.00 10,000,000.00 1.01 - - - - - - - -

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 44,560,643.30 4.50 0.00 1.66 1.66

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVc Tipe AW Diameter 3/4" (Air Bersih Dari Sumur Bor / PDAM Reservoir) m1 18.50 28,304.65 523,636.03 0.05 - - - - - - - -
5.2 Pipa PVC Tipe AW Diameter 3/4" (Distribusi Air Bersih Dari Reservoir) m1 26.50 28,304.65 750,073.23 0.08 - - - 13.25 50.00 0.04 13.25 50.00 0.04
5.3 Pipa PVC Tipe AW Diameter 3" (Air Kotor Ke Drainase Lingkungan) m1 23.00 135,539.80 3,117,415.40 0.31 - - - 23.00 100.00 0.31 23.00 100.00 0.31
5.4 Pipa PVC Tipe AW Diameter 4" (Disposal) m1 18.00 186,689.80 3,360,416.40 0.34 - - - 18.00 100.00 0.34 18.00 100.00 0.34
5.5 Pasangan 1 bh Closet Duduk / Monoblock (TOTO) bh 6.00 3,655,597.00 21,933,582.00 2.22 - - - 3.00 50.00 1.11 3.00 50.00 1.11
5.6 Pasangan 1 bh Wastafel (TOTO) 3.00 3,571,942.00 10,715,826.00 1.08 - - - 3.00 100.00 1.08 3.00 100.00 1.08
5.7 Pasangan 1 bh Uninoir (TOTO) 2.00 6,665,285.00 13,330,570.00 1.35 - - - 2.00 100.00 1.35 2.00 100.00 1.35
5.8 Pasangan 1 bh Floor Drain 9.00 41,123.50 370,111.50 0.04 - - - 9.00 100.00 0.04 9.00 100.00 0.04
5.9 Pasangan 1 bh Kran dia. 1/2' atau 3/4" 8.00 102,228.50 817,828.00 0.08 - - - 8.00 100.00 0.08 8.00 100.00 0.08
5.10 Pasangan 1 bh Kran wastafel dia. 1/2' atau 3/4" 2.00 335,428.50 670,857.00 0.07 - - - 2.00 100.00 0.07 2.00 100.00 0.07
5.11 Pasangan 1 bh shower closet dia. 1/2' atau 3/4" 6.00 142,928.50 857,571.00 0.09 - - - 6.00 100.00 0.09 6.00 100.00 0.09
5.12 Pasangan 1 bh shower Wall dia. 1/2' atau 3/4" (Ruang Bilas) 4.00 1,435,428.50 5,741,714.00 0.58 - - - 4.00 100.00 0.58 4.00 100.00 0.58
5.13 Pasangan 1 bh Stop Kran (Gate Valve) dia. 3/4" 2.00 141,428.50 282,857.00 0.03 - - - 2.00 100.00 0.03 2.00 100.00 0.03
5.14 Pasangan Mesin Air 1.00 741,000.00 741,000.00 0.07 - - - - - - - -
5.14b Pasangan Mesin Pemanas Air 1.00 5,000,000.00 5,000,000.00 0.51 - - - - - - - -
5.15 Septictank Biotank Kap. 4m3 1.00 20,380,000.00 20,380,000.00 2.06 - - - 0.50 50.00 1.03 0.50 50.00 1.03
5.16 Pasangan Sumur Bor Jet Pump 30.00 350,000.00 10,500,000.00 1.06 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.17 Reservoir 1200 Liter 1.00 1,850,000.00 1,850,000.00 0.19 - - - 1.00 100.00 0.19 1.00 100.00 0.19
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.18 Reservoir 200x150x350 cm - -
5.18.1 Pekerjaan Pondasi Pedestal Pd1 - -
5.18.1.1 Galian Tanah Pondasi Poerplat < 1m 1.62 74,250.00 120,285.00 0.01 - - - - - - - -
5.18.1.2 Urugan Tanah Kembali Pondasi Poerplat 0.43 55,000.00 23,760.00 0.00 - - - - - - - -
5.18.1.3 Tiang Pondasi Pedestal 50x50 cm -
Beton Mutu fc = 26,6 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.80 1,485,144.21 1,188,115.37 0.12 - - - - - - - -
Bekisting 2x Pakai 3.20 193,504.30 619,213.76 0.06 - - - - - - - -
Besi Beton Ø12, Ø8 49.44 21,465.73 1,061,174.10 0.11 - - - - - - - -
5.18.1.4 Pondasi Poerplat 90x90 cm,T.20 cm - -
Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.65 1,485,144.21 962,373.45 0.10 - - - - - - - -
Bekisting 2x Pakai 1.44 124,547.50 179,348.40 0.02 - - - - - - - -
Besi Beton Ø14 SNI 214.35 21,465.73 4,601,114.73 0.46 - - - - - - - -
5.18.2 Rangkai Tengah Dan Lantai Menara (Besi Hollow Galvanis 4/4) 34.82 244,970.00 8,529,855.40 0.86 - - - 34.82 100.00 0.86 34.82 100.00 0.86
5.18.3 Rangka Utama menara ( Besi Hollow Galvanis 5/10 32.28 179,454.00 5,792,775.12 0.59 - - - 32.28 100.00 0.59 32.28 100.00 0.59
5.18.4 Tplat Baja Lantai Menara T.3mm 3.00 740,164.86 2,220,494.57 0.22 - - - - - - - -
5.18.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) 5.00 244,970.00 1,224,850.00 0.12 - - - 4.00 80.00 0.10 4.00 80.00 0.10

TOTAL PEKERJAAN PLAMBING DAN SANITASI 127,466,817.45 12.88 - 7.87 7.87

6. PEKERJAAN AKHIR - - -
6.1 Pembersihan Sisa Pekerjaan Ls 1.00 2,400,000.00 2,400,000.00 0.24 - - - - - - - -

TOTAL PEKERJAAN AKHIR 2,400,000.00 0.24 0.00 0.00 0.00

C. PENERAPAN SMKK

1. PENYIAPAN RKK
1.1 Pembuatan Dokumen Rencana Keselamatan Konstruksi
1.2 Pembuatan Prosedur dan instruksi kerja Set 1.00 2,000,000.00 2,000,000.00 0.20 1.00 100.00 0.20 - - 1.00 100.00 0.20
1.3 Penyiapan formulir
TOTAL PENYIAPAN RKK 2,000,000.00 0.20 0.20 - 0.20
2. SOSIALISASI, PROMOSI DAN PELATIHAN
2.1 Induksi K3 (Safety Induction) Org 5.00 7,500.00 37,500.00 0.00 0.50 10.00 0.00 - - 0.50 10.00 0.00
2.2 Pengarahan K3 (Safety Briefing) Org 5.00 15,000.00 75,000.00 0.01 5.00 100.00 0.01 - - 5.00 100.00 0.01
2.3 Pelatihan K3 -
2.3.1 Bekerja di ketinggian Org 4.00 7,500.00 30,000.00 0.00 4.00 100.00 0.00 - - 4.00 100.00 0.00
2.3.2 Penggunaan Bahan Kimia (MSDS) Org 2.00 7,500.00 15,000.00 0.00 2.00 100.00 0.00 - - 2.00 100.00 0.00
2.4 Simulasi K3 Org 5.00 7,500.00 37,500.00 0.00 5.00 100.00 0.00 - - 5.00 100.00 0.00
2.5 Spanduk (Banner) Lb 1.00 150,000.00 150,000.00 0.02 1.00 100.00 0.02 - - 1.00 100.00 0.02
2.6 Poster 2 2.00 50,000.00 100,000.00 0.01 2.00 100.00 0.01 - - 2.00 100.00 0.01
2.7 Papan Informasi K3 1 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
TOTAL SOSIALISASI, PROMOSI DAN PELATIHAN 945,000.00 0.10 0.09 - 0.09
3. ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI
3.1 APK
3.1.1 Tali Keselamatan (Life Line) Ls 1.00 1,700,000.00 1,700,000.00 0.17 1.00 100.00 0.17 - - 1.00 100.00 0.17
3.1.2 Pembatas Area (Restricted Area) Ls 1.00 2,000,000.00 2,000,000.00 0.20 1.00 100.00 0.20 - - 1.00 100.00 0.20
3.2 APD -
3.2.1 Topi Pelindung (Safety Helmet) Bh 10.00 75,000.00 750,000.00 0.08 10.00 100.00 0.08 - - 10.00 100.00 0.08
3.2.2 Pelindung Mata (Googles, Spectacles) Bh 5.00 25,000.00 125,000.00 0.01 5.00 100.00 0.01 - - 5.00 100.00 0.01
3.2.3 Pelindung Pernapasan dan Mulut (Masker) Bh 100.00 5,000.00 500,000.00 0.05 100.00 100.00 0.05 - - 100.00 100.00 0.05
3.2.4 Sarung Tangan (Safety Gloves) Psg 10.00 15,000.00 150,000.00 0.02 10.00 100.00 0.02 - - 10.00 100.00 0.02
3.2.5 Sepatu Keselamatan (Safety Shoes) Psg 10.00 350,000.00 3,500,000.00 0.35 10.00 100.00 0.35 - - 10.00 100.00 0.35
3.2.6 Penunjang Seluruh Tubuh (Full Body Harness) Bh 2.00 500,000.00 1,000,000.00 0.10 2.00 100.00 0.10 - - 2.00 100.00 0.10
3.2.7 Rompi Keselamatan (Safety Vest) Bh 10.00 25,000.00 250,000.00 0.03 10.00 100.00 0.03 - - 10.00 100.00 0.03
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 9,975,000.00 1.01 1.01 - 1.01
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4. ASURANSI DAN PERIZINAN
4.1 Asuransi Ls 1.00 3,000,000.00 3,000,000.00 0.30 1.00 100.00 0.30 - - 1.00 100.00 0.30
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 3,000,000.00 0.30 0.30 - 0.30
5. PERSONEL K3 KONSTRUKSI
5.1 Ahli K3 Konstruksi -
5.2 Petugas K3 Konstruksi Ob 4.00 3,675,000.00 14,700,000.00 1.48 4.00 100.00 1.48 - - 4.00 100.00 1.48
TOTAL PERSONEL K3 KONSTRUKSI 14,700,000.00 1.48 1.48 - 1.48
6. FASILITAS, SARANA DAN PRASARANA KESEHATAN
6.1 Peralatan P3K (Kotak P3K, Tandu, Obat Luka, Perban, dll) Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
TOTAL FASILITAS, SARANA DAN PRASARANA KESEHATAN 500,000.00 0.05 0.05 - 0.05
7. RAMBU - RAMBU YANG DIPERLUKAN
7.1 Rambu Petunjuk bh 2.00 75,000.00 150,000.00 0.02 2.00 100.00 0.02 - - 2.00 100.00 0.02
7.2 Rambu Larangan bh 2.00 75,000.00 150,000.00 0.02 2.00 100.00 0.02 - - 2.00 100.00 0.02
7.3 Rambu Peringatan bh 2.00 100,000.00 200,000.00 0.02 2.00 100.00 0.02 - - 2.00 100.00 0.02
7.4 Jalur Evakuasi (Escape Route) Ls 1.00 250,000.00 250,000.00 0.03 1.00 100.00 0.03 - - 1.00 100.00 0.03
TOTAL RAMBU - RAMBU YANG DIPERLUKAN 750,000.00 0.08 0.08 - 0.08
8. KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI
8.1 Ahli K3 Konstruksi Oj -
TOTAL KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI - 0.00
9. LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN
KONSTRUKSI
9.1 Alat Pemadam Api Ringan (APAR) bh 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
9.2 Program Inspeksi Ls 1.00 1,500,000.00 1,500,000.00 0.15 1.00 100.00 0.15 - - 1.00 100.00 0.15
9.3 Pelaporan dan Penyeledikan Insiden Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
9.4 Pembuatan Kartu Identitas Pekerja (KIP) Org 10.00 5,000.00 50,000.00 0.01 10.00 100.00 0.01 - - 10.00 100.00 0.01
TOTAL LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN KONSTRUKSI 2,550,000.00 0.26 0.26 - 0.26

A Jumlah Harga Penawaran 989,944,870.91 100.00 43.89 9.53 53.43


B PPN (10%) 98,994,487.09
C Jumlah (A+B) 1,088,939,358.00
PERSENTASE SAMPAI MINGGU INI 53.43
D Jumlah Dibulatkan 1,088,939,358.00

Bulukumba, 26 November 2020


Disetujui, Diketahui, Diperiksa Oleh, Dibuat Oleh,
Pejabat Pembuat Komitmen Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUTR Prov SulSel Dinas PUTR Prov SulSel CV.MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

A.KHADAFI HARUN, ST.,MT. L I L I, ST. IRHAM HARAHAP, ST. VIKA APRILIA DWI PUTRI
NIP. 19811126 200901 1 008 NIP. 19821229 201503 2 001 Site Engineer Direktris
LAPORAN KEMAJUAN MINGGUAN

Kegiatan : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba Minggu Ke : 07 ( Tujuh )
Satuan Kerja : Dinas Pekerjaan Umum Dan Tata Ruang Prov. Sulawesi Selatan Bidang Cipta Karya Periode : 27 November S/d 03 November 2020
Lokasi : Desa Ara, Kecamatan Bonto Bahari, Kabupaten Bulukumba, Provinsi Sulawesi Selatan No. Kontrak : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
Sumber Dana : Dana Bantuan Provinsi Nilai Kontrak : Rp. 1,088,939,358.00
Tahun Anggaran : 2020 Schedule Pelaksanaan : 16 Oktober S/d 14 Desember 2020

MINGGU LALU MINGGU INI S/D MINGGU INI


VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
NO URAIAN PEKERJAAN
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q

A. PEMBANGUNAN RUANG KULINER, SUVENIR, MUSHOLLAH DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Papan Proyek Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
1.2 Bedeng/Direksi Keet M2 5.50 1,512,555.00 8,319,052.50 0.84 5.50 100.00 0.84 - - 5.50 100.00 0.84

TOTAL PEKERJAAN PERSIAPAN 8,819,052.50 0.89 0.89 0.00 0.89

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Poerplat PP1 (Selasar Samping)
2.1.1.1 Galian Pondasi Poerplat < 1 m M3 0.32 73,837.50 23,628.00 0.00 0.32 100.00 0.00 - - 0.32 100.00 0.00
2.1.1.2 Urugan Pasir dibawah Pondasi Poerplat T.5 cm M3 0.04 148,335.00 5,933.40 0.00 0.04 100.00 0.00 - - 0.04 100.00 0.00
2.1.1.3 Urugan Tanah Kembali Pondasi Poerplat M3 0.31 54,175.00 16,794.25 0.00 0.31 100.00 0.00 - - 0.31 100.00 0.00
2.1.1.4 Pasangan Lantai Kerja bawah Pondasi Poerplat T.5 cm (Beton K300) M3 0.04 1,118,216.00 44,728.64 0.00 0.04 100.00 0.00 - - 0.04 100.00 0.00
2.1.1.5 Pondasi Poerplat 35x50 cm, T.20 cm - -
Beton Mutu F'c = 26,4 mpa (K300), Slump (12-2) cm, w/c = 0,52 M3 0.14 1,118,216.00 156,550.24 0.02 0.14 100.00 0.02 - - 0.14 100.00 0.02
Bekisting 2x Pakai M2 0.56 107,013.50 59,927.56 0.01 0.56 100.00 0.01 - - 0.56 100.00 0.01
Besi Beton Ø14 SNI Kg 29.40 21,464.85 631,066.59 0.06 29.40 100.00 0.06 - - 29.40 100.00 0.06
2.1.2 Pekerjaan Pondasi Batu Kali (Badan Bangunan, Mushollah) - -
2.1.2.1 Galian Tanah Pondasi Batu Kali < 1 m M3 22.73 73,837.50 1,678,326.38 0.17 22.73 100.00 0.17 - - 22.73 100.00 0.17
2.1.2.2 Urugan Pasir dibawah Pondasi Batu Kali T.5 cm M3 1.08 148,335.00 160,201.80 0.02 1.08 100.00 0.02 - - 1.08 100.00 0.02
2.1.2.3 Pasangan Aanstamping bawah Pondasi Batu Kali T.10 M3 2.17 382,674.00 830,402.58 0.08 2.17 100.00 0.08 - - 2.17 100.00 0.08
2.1.2.4 Urugan Tanah Kembali Pondasi Batu Kali M3 10.39 54,175.00 562,878.25 0.06 10.39 100.00 0.06 - - 10.39 100.00 0.06
2.1.2.5 Pondasi Batu Kali 1 Sp : 3 Pp M3 9.09 827,447.50 7,521,497.78 0.76 9.09 100.00 0.76 - - 9.09 100.00 0.76
2.1.3 Pekerjaan Pondasi Rollage L.15 cm (Entrance, Selasar Samping) - - -
2.1.3.1 Galian Tanah Pondasi Rollage < 1 m M3 2.23 73,837.50 164,657.63 0.02 2.23 100.00 0.02 - - 2.23 100.00 0.02
2.1.3.2 Urugan Pasir dibawah Pondasi Rollage T.5 cm M3 0.45 148,335.00 66,750.75 0.01 0.45 100.00 0.01 - - 0.45 100.00 0.01
2.1.3.3 Pasangan Lantai Kerja bawah Pondasi Rollage T.5 cm (Beton K300) M3 0.45 1,118,216.00 499,003.89 0.05 0.45 100.00 0.05 - - 0.45 100.00 0.05
2.1.3.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp M2 20.83 128,436.00 2,675,321.88 0.27 20.83 100.00 0.27 - - 20.83 100.00 0.27
2.2 Pekerjaan Sloef, Kolom dan Ringbalk - -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Mushollah) - -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 1.62 1,118,216.00 1,815,703.23 0.18 1.62 100.00 0.18 - - 1.62 100.00 0.18
2.2.1.2 Bekisting 2x Pakai M2 10.83 114,438.50 1,239,368.96 0.13 10.83 100.00 0.13 - - 10.83 100.00 0.13
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI Kg 280.09 21,464.85 6,012,089.84 0.61 280.09 100.00 0.61 - - 280.09 100.00 0.61
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan, Mushollah) - -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.88 1,118,216.00 981,234.54 0.10 0.88 100.00 0.10 - - 0.88 100.00 0.10
2.2.2.2 Bekisting 2x Pakai M2 5.85 193,468.00 1,131,787.80 0.11 5.85 100.00 0.11 - - 5.85 100.00 0.11
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 181.66 21,464.85 3,899,347.58 0.39 181.66 100.00 0.39 - - 181.66 100.00 0.39
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Selasar, Westafel, Tempat Wudhu) -
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 0.34 100.00 0.03 - - 0.34 100.00 0.03
2.2.3.2 Bekisting 2x Pakai M2 2.26 193,468.00 437,237.68 0.04 2.26 100.00 0.04 - - 2.26 100.00 0.04
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 70.10 21,464.85 1,504,686.30 0.15 70.10 100.00 0.15 - - 70.10 100.00 0.15
2.2.4 Pekerjaan Kolom K1 15 x 30 (Selasar Samping) -
2.2.4.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.62 1,118,216.00 694,412.14 0.07 0.62 100.00 0.07 - - 0.62 100.00 0.07
2.2.4.2 Bekisting 2x Pakai M2 6.21 193,468.00 1,201,436.28 0.12 6.21 100.00 0.12 - - 6.21 100.00 0.12
2.2.4.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 99.69 21,464.85 2,139,830.90 0.22 99.69 100.00 0.22 - - 99.69 100.00 0.22
2.2.5 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan, Mushollah) -
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 2.08 1,008,161.00 2,097,478.96 0.21 2.08 100.00 0.21 - - 2.08 100.00 0.21
2.2.5.2 Bekisting 2x Pakai M2 13.87 197,923.00 2,745,192.01 0.28 13.87 100.00 0.28 - - 13.87 100.00 0.28
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 299.22 21,464.85 6,422,712.42 0.65 299.22 100.00 0.65 - - 299.22 100.00 0.65
2.2.6 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan) -
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 0.34 100.00 0.03 - - 0.34 100.00 0.03
2.2.6.2 Bekisting 2x Pakai M2 2.24 197,923.00 443,347.52 0.04 2.24 100.00 0.04 - - 2.24 100.00 0.04
2.2.6.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 48.32 21,464.85 1,037,181.55 0.10 48.32 100.00 0.10 - - 48.32 100.00 0.10
2.2.7 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Mushollah, Pintu Jendela) -
2.2.7.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.84 1,008,161.00 846,855.24 0.09 0.84 100.00 0.09 - - 0.84 100.00 0.09
2.2.7.2 Bekisting 2x Pakai M2 5.59 197,923.00 1,106,389.57 0.11 5.59 100.00 0.11 - - 5.59 100.00 0.11
2.2.7.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 115.53 21,464.85 2,479,834.12 0.25 115.53 100.00 0.25 - - 115.53 100.00 0.25
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.2.8 Pekerjaan Plat Beton (Selasar Samping, Westafel) -
2.2.8.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.22 1,008,161.00 221,795.42 0.02 0.22 100.00 0.02 - - 0.22 100.00 0.02
2.2.8.2 Bekisting 2x Pakai M2 2.21 237,468.00 524,804.28 0.05 2.21 100.00 0.05 - - 2.21 100.00 0.05
2.2.8.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 54.54 21,464.85 1,170,692.92 0.12 54.54 100.00 0.12 - - 54.54 100.00 0.12
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) M2 152.03 163,636.00 24,877,581.08 2.51 152.03 100.00 2.51 - - 152.03 100.00 2.51
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4, Entrance) M2 42.24 242,170.50 10,229,281.92 1.03 42.24 100.00 1.03 - - 42.24 100.00 1.03
2.5 Pekerjaan Tiang Atap Bitumen Gelombang (Besi Hollow Galvanis 5/10, Entrance) M' 20.40 178,365.00 3,638,646.00 0.37 20.40 100.00 0.37 - - 20.40 100.00 0.37
2.6 Pekerjaan Rangka Plafond Kalsiboard (Besi Hollow Metal Galvalume 4/4) M2 147.40 102,837.17 15,158,198.37 1.53 147.40 100.00 1.53 - - 147.40 100.00 1.53

TOTAL PEKERJAAN STRUKTUR 109,840,345.70 11.10 11.10 0.00 11.10

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) M3 8.54 148,335.00 1,266,780.90 0.13 8.54 100.00 0.13 - - 8.54 100.00 0.13
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) M3 25.63 167,227.00 4,285,636.74 0.43 25.63 100.00 0.43 - - 25.63 100.00 0.43
3.1.1.3 Rabat Beton bawah Lantai T.5 cm (Keseluruhan, Beton K300) M3 8.54 1,118,216.00 9,549,564.64 0.96 8.54 100.00 0.96 - - 8.54 100.00 0.96
3.1.1.4 Penutup Lantai Keramik Motif 60x60 (Badan Bangunan, Mushollah) M2 62.94 403,309.50 25,384,299.93 2.56 59.79 95.00 2.44 - - 59.79 95.00 2.44
3.1.1.5 Penutup Lantai Conwood Deck 6" (Entrance) M2 59.01 866,833.08 51,151,820.09 5.17 - - - 56.01 94.92 4.90 56.01 94.92 4.90
3.1.1.6 Penutup Lantai Andesit Polos 30x30 (Selasar, Tempat Wudhu, Ram) M2 51.05 232,589.50 11,873,693.98 1.20 - - - 51.05 100.00 1.20 51.05 100.00 1.20
3.1.1.7 Plint Lantai Keramik 10x60 (Badan Bangunan, Mushollah) M' 38.85 51,605.03 2,004,855.55 0.20 - - - - - - - -
3.1.2 Pekerjaan Dinding -
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Mushollah, 1 Sp : 4 Pp) M2 74.55 242,979.00 18,114,084.45 1.83 74.55 100.00 1.83 - - 74.55 100.00 1.83
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Selasar Samping, Tempat Wudhu) M2 5.14 65,550.32 336,928.64 0.03 5.14 100.00 0.03 - - 5.14 100.00 0.03
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm (Badan Bangunan, Mushollah) M2 91.30 60,403.20 5,514,812.16 0.56 91.30 100.00 0.56 - - 91.30 100.00 0.56
3.1.2.4 Plesteran Ciprat 1 Sp : 2 Pp Tebal 15 mm (Selasar Samping, Antar Kolom) M2 24.84 49,215.10 1,222,503.08 0.12 24.84 100.00 0.12 - - 24.84 100.00 0.12
3.1.2.5 Dinding Keramik Mozaik 30x60 (Selasar Samping, Westafel, Tempat Wudhu) M2 18.44 410,432.00 7,568,366.08 0.76 - - - 18.44 100.00 0.76 18.44 100.00 0.76
3.1.2.6 Coating Bening (Badan Bangunan, Mushollah, Kolom Luar) M2 127.49 45,973.13 5,861,113.71 0.59 - - - - - - - -
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) M2 8.64 995,043.50 8,597,175.84 0.87 - - - 8.64 100.00 0.87 8.64 100.00 0.87
3.1.2.8 Dinding Wallpaper Bata L.50 cm (Sisi Dalam) M2 28.13 80,005.50 2,250,554.72 0.23 - - - - - - - -
3.1.3 Pekerjaan Plafond -
3.1.3.1 Plafond Kalsiboard (Badan Bangunan, Kemiringan Atap, Mushollah) M2 147.40 44,924.00 6,621,797.60 0.67 147.40 100.00 0.67 - - 147.40 100.00 0.67
3.1.3.2 Plafond Kalsiboard (Lapis Bawah Atap, Entrance) M2 42.24 44,924.00 1,897,589.76 0.19 42.24 100.00 0.19 - - 42.24 100.00 0.19
3.2 Pekerjaan Pintu dan Jendela (Badan Bangunan) -
3.2.1 Pintu P1 (Entrance dan Back Entrance, Badan Bangunan) -
3.2.1.1 Pasangan Kusen Alumunium Coating P1 (4" x 1 3/4") cm M' 22.40 157,194.40 3,521,154.56 0.36 - - - 22.40 100.00 0.36 22.40 100.00 0.36
3.2.1.2 Pasangan Daun Pintu P1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - - -
3.2.1.3 Pasangan Kaca Mati 5 mm P1 M2 11.20 145,703.80 1,631,882.56 0.16 - - - - - - - -
3.2.1.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - - -
3.2.1.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - - -
3.2.1.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - - -
3.2.1.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - - -
3.2.2 Jendela J1 (Badan Bangunan) -
3.2.2.1 Pasangan Kusen Alumunium Coating J1 (4" x 1 3/4") cm M' 40.60 157,194.40 6,382,092.64 0.64 - - - 40.60 100.00 0.64 40.60 100.00 0.64
3.2.2.2 Pasangan Kaca Mati 5 mm J1 M2 8.00 145,703.80 1,165,630.40 0.12 - - - - - - - -
3.2.3 Pintu PJ1 (Mushollah) -
3.2.3.1 Pasangan Kusen Alumunium Coating PJ1 (4" x 1 3/4") cm M' 22.20 157,194.40 3,489,715.68 0.35 - - - 22.20 100.00 0.35 22.20 100.00 0.35
3.2.3.2 Pasangan Daun Pintu PJ1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - - -
3.2.3.3 Pasangan Kaca Mati 5 mm P1 M2 8.70 145,703.80 1,267,623.06 0.13 - - - - - - - -
3.2.3.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - - -
3.2.3.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - - -
3.2.3.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - - -
3.2.3.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - - -
3.3 Pekerjaan Pengecatan -
3.3.1 Pengecatan Plafond (1 Plamir ; 1 Cat Dasar : 2 Cat Penutup), (Interior) M2 189.64 35,536.05 6,739,056.52 0.68 189.64 100.00 0.68 - - 189.64 100.00 0.68
3.3.2 Pengecatan Rangka Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 23.76 168,454.00 4,002,467.04 0.40 23.76 100.00 0.40 - - 23.76 100.00 0.40
3.3.3 Pengecatan Tiang Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 6.12 168,454.00 1,030,938.48 0.10 6.12 100.00 0.10 - - 6.12 100.00 0.10
3.4 Pekerjaan Atap -
3.4.1 Atap Bitumen Gelombang (Badan Bangunan, Mushollah) M2 152.03 207,297.09 31,515,376.59 3.18 152.03 100.00 3.18 - - 152.03 100.00 3.18
3.4.2 Atap Bitumen Gelombang (Entrance) M2 42.24 207,297.09 8,756,229.08 0.88 42.24 100.00 0.88 - - 42.24 100.00 0.88
3.4.3 Nok Bitumen (Badan Bangunan, Mushollah) M' 14.55 134,101.00 1,951,169.55 0.20 14.55 100.00 0.20 - - 14.55 100.00 0.20
3.4.4 Listplank (Kalsiplank, Badan Bangunan, Mushollah, Entrance) M' 50.00 70,950.00 3,547,500.00 0.36 50.00 100.00 0.36 - - 50.00 100.00 0.36

TOTAL PEKERJAAN FINISHING ARSITEKTUR 257,222,142.77 25.98 13.18 9.09 22.27

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel Bh 1.00 1,572,826.75 1,572,826.75 0.16 - - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt Bh 16.00 353,938.75 5,663,020.00 0.57 16.00 100.00 0.57 - - 16.00 100.00 0.57
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4.1.3 Pasangan Lampu Down Light 2,5" Outbow LED 5,5 Watt Bh 11.00 305,538.75 3,360,926.25 0.34 11.00 100.00 0.34 - - 11.00 100.00 0.34
4.1.4 Pasangan Saklar Tunggal Bh 4.00 211,378.75 845,515.00 0.09 4.00 100.00 0.09 - - 4.00 100.00 0.09
4.1.5 Pasangan Saklar Ganda Bh 2.00 223,478.75 446,957.50 0.05 2.00 100.00 0.05 - - 2.00 100.00 0.05
4.2 Pasangan Instalasi Stop Kontak - -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA Bh 10.00 216,218.75 2,162,187.50 0.22 10.00 100.00 0.22 - - 10.00 100.00 0.22
4.2.2 Pasangan Stop Kontak AC 220 VA/3520 W (AC Split 1 PK) Bh 4.00 253,728.75 1,014,915.00 0.10 4.00 100.00 0.10 - - 4.00 100.00 0.10
4.3 Pasangan Instalasi Jaringan AC M' 30.00 108,772.68 3,263,180.25 0.33 30.00 100.00 0.33 - - 30.00 100.00 0.33
4.3.1 Pasangan AC Split 1 PK Bh 3.00 3,365,799.34 10,097,398.03 1.02 1.50 50.00 0.51 - - 1.50 50.00 0.51
4.4 Pasangan Penangkal Petir Ls 1.00 2,500,000.00 2,500,000.00 0.25 1.00 100.00 0.25 - - 1.00 100.00 0.25
4.5 Pasangan Instalasi Jaringan Kabel Fiber Optic (CCTV) Ttk 6.00 786,326.75 4,717,960.50 0.48 - - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2MP Bh 6.00 656,975.00 3,941,850.00 0.40 - - - - - - - -
4.5.2 Pasangan NVR Channel Set 1.00 5,023,975.00 5,023,975.00 0.51 - - - - - - - -
4.5.3 Pasangan Monitor LCD 32" Bh 1.00 2,944,975.00 2,944,975.00 0.30 - - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm M' 12.00 20,442.68 245,312.10 0.02 - - - - - - - -
4.6.1 Pasangan Horn Speaker Bh 6.00 494,826.75 2,968,960.50 0.30 - - - - - - - -
4.6.2 Pasangan Volume Kontrol Set 1.00 252,826.75 252,826.75 0.03 - - - - - - - -
4.6.3 Pasangan Perangkat Sound System Set 1.00 4,565,000.00 4,565,000.00 0.46 - - - - - - - -
4.6.4 Pasangan TB-Sound System Set 1.00 5,846,326.75 5,846,326.75 0.59 - - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25Kg) Ttk 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - - -
4.8 Pasangan Instalasi Jaringan Kabel Fiber Optic (Akses Point) Ttk 3.00 786,326.75 2,358,980.25 0.24 - - - - - - - -
4.8.1 Pasangan Server Set 1.00 7,578,826.75 7,578,826.75 0.77 - - - - - - - -
4.8.2 Pasangan Akses Point Bh 1.00 2,034,826.75 2,034,826.75 0.21 - - - - - - - -
4.8.3 Pasangan Switch HUB Bh 1.00 2,843,326.75 2,843,326.75 0.29 - - - - - - - -
4.9 Pasangan Instalasi PLN Power (Inc. Jalur ke Mushollah dan Toilet) Ls 1.00 9,000,000.00 9,000,000.00 0.91 - - - - - - - -

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 94,450,073.38 9.54 2.46 0.00 2.46

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVC Type AW Diameter 3/4" (Air Bersih Sambungan dari Tandon) M' 33.00 28,300.25 933,908.25 0.09 16.50 50.00 0.05 - - 16.50 50.00 0.05
5.2 Pipa PVC Type AW Diameter 3" (Air Kotor ke Drainase Lingkungan) M' 25.80 135,531.00 3,496,699.80 0.35 2.58 10.00 0.04 - - 2.58 10.00 0.04
5.3 Pasangan 1 Bh Wastafel Bh 2.00 3,934,865.00 7,869,730.00 0.79 - - - - - - - -
5.4 Pasangan 1 Bh Wastafel Cuci Piring (WCP) Bh 1.00 890,945.00 890,945.00 0.09 - - - - - - - -
5.5 Pasangan 1 Bh Floor Drain Bh 2.00 41,112.50 82,225.00 0.01 - - - - - - - -
5.6 Pasangan 1 Bh Kran Dia. 1/2" atau 3/4" Bh 10.00 102,217.50 1,022,175.00 0.10 - - - - - - - -
5.7 Pasangan 1 Bh Kran Wastafel Dia. 1/2" atau 3/4" Bh 3.00 335,417.50 1,006,252.50 0.10 - - - - - - - -
5.8 Pasangan 1 Bh Stop Kran (Gate Valve) Dia. 3/4" Bh 1.00 141,417.50 141,417.50 0.01 - - - - - - - -
5.9 Pasangan Mesin Air Bh 1.00 741,000.00 741,000.00 0.07 - - - - - - - -
5.10 Menara Reservoir 200x150x350 cm -
5.10.1 Pekerjaan Pondasi Pedestal Pd1 -
5.10.1.1 Galian Tanah Pondasi Poerplat < 1 m M3 1.62 73,837.50 119,616.75 0.01 - - - - - - - -
5.10.1.2 Urugan Tanah Kembali Pondasi Poerplat M3 0.43 54,175.00 23,295.25 0.00 - - - - - - - -
5.10.1.3 Tiang Pondasi Pedestal 50x50 cm - - -
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.80 1,118,216.00 894,572.80 0.09 - - - - - - - -
Bekisting 2x Pakai M2 3.20 193,468.00 619,097.60 0.06 - - - - - - - -
Besi Beton Ø12 SNI, Ø8 SNI Kg 49.44 21,464.85 1,061,130.60 0.11 - - - - - - - -
5.10.1.4 Pondasi Poerplat 90x90 cm, T.20 cm -
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.65 1,118,216.00 726,840.40 0.07 - - - - - - - -
Bekisting 2x Pakai M2 1.44 107,013.50 154,099.44 0.02 - - - - - - - -
Besi Beton Ø14 SNI Kg 214.35 21,464.85 4,600,940.54 0.46 - - - - - - - -
5.10.2 Rangka Tengah dan Lantai Menara (Besi Hollow Galvanis 4/4) M2 34.82 244,970.00 8,529,855.40 0.86 - - - - - - - -
5.10.3 Rangka Utama Menara (Besi Hollow Galvanis 5/10) M' 32.28 179,454.00 5,792,775.12 0.59 - - - - - - - -
5.10.4 Plat Baja Lantai Menara T.3 mm M2 3.00 740,164.86 2,220,494.57 0.22 - - - - - - - -
5.10.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) M2 5.00 244,970.00 1,224,850.00 0.12 - - - - - - - -

TOTAL PEKERJAAN PLAMBING DAN SANITASI 42,151,921.52 4.26 0.08 0.00 0.08

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Pek. Pembersian Awal m2 81.86 17,600.00 1,440,780.00 0.15 81.86 100.00 0.15 - - 81.86 100.00 0.15
1.2 Pek. Pengukuran & Pemasangan Bouwplank m1 48.60 106,461.25 5,174,016.75 0.52 48.60 100.00 0.52 - - 48.60 100.00 0.52

TOTAL PEKERJAAN PERSIAPAN 6,614,796.75 0.67 0.67 0.00 0.67

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Batu Kali (Badan Bangunan,Ruang Bilas)
2.1.1.1 Galian Pondasi Batu Kali < 1 m m3 22.05 73,892.50 1,629,329.63 0.16 6.62 30.00 0.05 - - 6.62 30.00 0.05
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.1.1.2 Urugan Pasir Dibawah Pondasi Batu Kali T.5 cm m3 1.05 174,757.00 183,494.85 0.02 1.05 100.00 0.02 - - 1.05 100.00 0.02
2.1.1.3 Pasangan Aanstamping Bawah Pondasi Batu Kali T.10 cm m3 2.10 392,699.70 824,669.37 0.08 2.10 100.00 0.08 - - 2.10 100.00 0.08
2.1.1.4 Urugan Tanah Kembali Pondasi Batu Kali m3 10.08 54,285.00 547,192.80 0.06 3.02 30.00 0.02 - - 3.02 30.00 0.02
2.1.1.5 Pondasi Batu Kali 1 Sp : 3 Pp m3 8.82 824,945.00 7,276,014.90 0.73 8.82 100.00 0.73 - - 8.82 100.00 0.73
2.1.2 Perjaan Pondasi Rollage L.15 cm (Selasar) -
2.1.2.1 Galian Tanah Pondasi Rollage < 1 m m3 1.52 73,892.50 112,501.33 0.01 0.15 10.00 0.00 - - 0.15 10.00 0.00
2.1.2.2 Urugan Pasir Dibawah Pondasi Rollage T.5 cm m3 0.30 174,757.00 53,213.51 0.01 0.03 10.00 0.00 - - 0.03 10.00 0.00
2.1.2.3 Pasangan Lantai Kerja Bawah Pondasi Rollage T.5 cm (Beton K300) m3 0.30 1,118,398.60 340,552.37 0.03 0.30 100.00 0.03 - - 0.30 100.00 0.03
2.1.2.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp m3 14.21 128,260.00 1,822,574.60 0.18 14.21 100.00 0.18 - - 14.21 100.00 0.18
2.2 Pekerjaan Sloef, Kolom, Plat dan Ringbalk - -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Ruang Bilas) - -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 m3 1.41 1,118,398.60 1,580,297.22 0.16 1.41 100.00 0.16 - - 1.41 100.00 0.16
2.2.1.2 Bekisting 2x Pakai m2 9.42 114,467.10 1,078,280.08 0.11 9.42 100.00 0.11 - - 9.42 100.00 0.11
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI kg 243.74 21,465.73 5,232,043.29 0.53 243.74 100.00 0.53 - - 243.74 100.00 0.53
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan) - -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slum (12 - 2) cm, w/c = 0,52 m3 0.48 1,118,398.60 533,476.13 0.05 0.48 100.00 0.05 - - 0.48 100.00 0.05
2.2.2.2 Bekisting 2x Pakai m2 3.18 193,504.30 615,343.67 0.06 3.18 100.00 0.06 - - 3.18 100.00 0.06
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI kg 98.75 21,465.73 2,119,732.25 0.21 98.75 100.00 0.21 - - 98.75 100.00 0.21
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Ruang Bilas) - -
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.25 1,008,343.60 249,111.29 0.03 0.25 100.00 0.03 - - 0.25 100.00 0.03
2.2.3.2 Bekisting 2x Pakai m2 1.65 193,504.30 318,701.58 0.03 1.65 100.00 0.03 - - 1.65 100.00 0.03
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI kg 51.14 21,465.73 1,097,861.33 0.11 51.14 100.00 0.11 - - 51.14 100.00 0.11
2.2.4 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan) - -
2.2.4.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.04 1,008,343.60 1,043,635.63 0.11 1.04 100.00 0.11 - - 1.04 100.00 0.11
2.2.4.2 Bekisting 2x Pakai m2 6.90 197,959.30 1,365,919.17 0.14 6.90 100.00 0.14 - - 6.90 100.00 0.14
2.2.4.3 Besi Beton Ø12 SNI, Ø6 SNI kg 148.86 21,465.73 3,195,302.68 0.32 148.86 100.00 0.32 - - 148.86 100.00 0.32
2.2.5 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan) - -
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.09 1,008,343.60 1,103,531.24 0.11 1.09 100.00 0.11 - - 1.09 100.00 0.11
2.2.5.2 Bekisting 2x Pakai m2 14.59 197,959.30 2,888,622.11 0.29 14.59 100.00 0.29 - - 14.59 100.00 0.29
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI kg 157.40 21,465.73 3,378,705.12 0.34 157.40 100.00 0.34 - - 157.40 100.00 0.34
2.2.6 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Pintu Jendela) -
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.15 1,008,343.60 148,831.52 0.02 0.15 100.00 0.02 - - 0.15 100.00 0.02
2.2.6.2 Bekisting 2x Pakai m2 0.98 197,959.30 194,791.95 0.02 0.98 100.00 0.02 - - 0.98 100.00 0.02
2.2.6.3 Besi Beton Ø10 SNI, Ø6 SNI kg 20.35 21,465.73 436,752.39 0.04 20.35 100.00 0.04 - - 20.35 100.00 0.04
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) m2 59.01 163,856.00 9,669,142.56 0.98 59.01 100.00 0.98 - - 59.01 100.00 0.98
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4) m2 48.59 102,876.77 4,998,782.09 0.50 48.59 100.00 0.50 - - 48.59 100.00 0.50
2.5 Pekerjaan Rangka Plafond dan Dinding Dalam PVC Shunda (Besi Hollow Metal Galvalume 4/4) m2 56.16 102,876.77 5,777,559.22 0.58 - - - - - - - -

TOTAL PEKERJAAN STRUKTUR 59,815,965.86 6.04 5.29 0.00 5.29

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) m3 4.09 174,757.00 715,280.40 0.07 4.09 100.00 0.07 - - 4.09 100.00 0.07
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) m3 12.28 167,345.00 2,054,804.70 0.21 12.28 100.00 0.21 - - 12.28 100.00 0.21
3.1.1.3 Rabat Beton T.5 cm (Keseluruhan, Beton K300) m3 4.09 1,118,398.60 4,577,605.47 0.46 4.09 100.00 0.46 - - 4.09 100.00 0.46
3.1.1.4 Penutup Lantai Keramik Tekstur 60x60 (Badan Bangunan) m2 36.93 413,098.40 15,255,723.91 1.54 36.93 100.00 1.54 - - 36.93 100.00 1.54
3.1.1.5 Penutup Lantai Andesit Polos 30x30 (Selasar, Ruang Bilas) m2 45.89 284,369.80 13,049,730.12 1.32 45.89 100.00 1.32 - - 45.89 100.00 1.32
3.1.1.6 Penutup Plat Wastafel (Granit 60x60, Toilet Pria dan Wanita) m2 2.20 841,621.73 1,851,567.81 0.19 - - - - - - - -
3.1.2 Pekerjaan Dinding - -
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Selasar, 1 Sp : 4 Pp) 90.64 242,533.50 21,983,236.44 2.22 90.64 100.00 2.22 - - 90.64 100.00 2.22
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Wc ) 30.00 65,473.32 1,964,199.60 0.20 30.00 100.00 0.20 - - 30.00 100.00 0.20
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm 121.28 60,304.20 7,313,693.38 0.74 121.28 100.00 0.74 - - 121.28 100.00 0.74
3.1.2.4 Coating Bening 121.28 46,853.13 5,682,347.00 0.57 - - - - - - - -
3.1.2.5 Dinding Andesit Polos 30x30 cm ( Wc, Ruang Bilas ) 56.52 284,369.80 16,072,581.10 1.62 - - - - - - - -
3.1.2.6 Dinding Keramik 30x60 cm ( Sisi Dalam ) 69.88 370,557.00 25,894,523.16 2.62 - - - - - - - -
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) 9.00 995,076.50 8,955,688.50 0.90 - - - - - - - -
3.1.2.8 Cubicle Panel + Accessories (Pintu Wc dan Partisi Urinoir) 10.86 1,360,000.00 14,769,600.00 1.49 - - - - - - - -
3.1.2.9 Dinding Bitumen Gelombang 48.59 201,749.24 9,802,995.57 0.99 - - - - - - - -
3.1.2.10 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Pria) 1.00 1,200,000.00 1,200,000.00 0.12 - - - - - - - -
3.1.2.11 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Wanita) 1.00 750,000.00 750,000.00 0.08 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.1.3 Plafond dan Dinding Dalam Shunda ( Badan Bangunan ) 56.16 125,878.50 7,069,336.56 0.71 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.2 Pekerjaan Pintu dan Jendela ( Badan Bangunan ) - -
3.2.1 Pintu P1 - -
3.2.1.1 Pasangan Kusen Almunium Coating P1 (4" x 13/4") cm 10.96 157,199.02 1,722,901.26 0.17 - - - - - - - -
3.2.1.2 Pasangan Daun Pintu P1 (Panel Almunium Coating - Coating) 4.30 870,323.19 3,742,389.72 0.38 - - - - - - - -
3.2.1.3 Pasangan Kunci Tanam 2x Slag P1 2.00 416,663.50 833,327.00 0.08 - - - - - - - -
3.2.1.4 Pasangan ensel P1 6.00 61,225.56 367,353.36 0.04 - - - - - - - -
3.2.1.5 Pasangan Doorcloser P1 2.00 241,902.10 483,804.20 0.05 - - - - - - - -
3.2.1.6 Pasangan Handle P1 2.00 229,802.10 459,604.20 0.05 - - - - - - - -
3.2.2 Jendela J1 - -
3.2.2.1 Pasangan Kusen Almunium Coating J1 (4" x 13/4") cm 28.80 157,199.02 4,527,331.78 0.46 - - - - - - - -
3.2.2.2 Pasangan Kaca Mati 5 mm J1 0.60 145,705.56 87,423.34 0.01 - - - - - - - -
3.2.3 Jendela J2 -
3.2.3.1 Pasangan Kusen Almunium Coating J2 (4" x 13/4") cm 55.20 157,199.02 8,677,385.90 0.88 - - - - - - - -
3.2.3.2 Pasangan Kaca Mati 5 mm J2 0.90 145,705.56 131,135.00 0.01 - - - - - - - -
3.3. Pengecetan Plafond (1 Plamir : 1 Cat Dasar : 2 Cat Penutup), (Interior) 56.16 43,550.65 2,445,804.50 0.25 - - - - - - - -
3.4 Pekerjaan Atap - -
3.4.1 Atap Bitumen Gelombang (Badan Bangunan) 59.01 201,749.24 11,905,222.65 1.20 - - - - - - - -
3.4.2 Nok Bitumen (Badan Bangunan) 35.25 143,629.20 5,062,929.30 0.51 - - - - - - - -
3.4.3 Listplank (Kasiplank, Badan Bangunan, Enterance) 39.08 70,972.00 2,773,585.76 0.28 - - - - - - - -

TOTAL PEKERJAAN FINISHING ARSITEKTUR 202,183,111.69 20.42 6.76 0.00 6.76

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel 1.00 1,803,826.75 1,803,826.75 0.18 - - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt 10.00 353,938.75 3,539,387.50 0.36 10.00 100.00 0.36 - - 10.00 100.00 0.36
4.1.3 Pasangan Lampu Down Light 2.5" Outbow LED 5.5 Watt 12.00 305,538.75 3,666,465.00 0.37 12.00 100.00 0.37 - - 12.00 100.00 0.37
4.1.4 Pasangan Saklar Ganda 5.00 223,478.75 1,117,393.75 0.11 5.00 100.00 0.11 - - 5.00 100.00 0.11
4.2 Pasangan Instalasi Stop Kontak - -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA 3.00 216,218.75 648,656.25 0.07 3.00 100.00 0.07 - - 3.00 100.00 0.07
4.2.2 Pasangan Stop Kontak Wall Exhauser 6.00 216,218.75 1,297,312.50 0.13 6.00 100.00 0.13 - - 6.00 100.00 0.13
4.3 Pasangan Instalasi Jaringan Wall Exhauser 12.00 108,772.68 1,305,272.10 0.13 12.00 100.00 0.13 - - 12.00 100.00 0.13
4.3.1 Pasangan Wall Exhauser 12 Inch - FV30RUN 6.00 513,500.00 3,081,000.00 0.31 6.00 100.00 0.31 - - 6.00 100.00 0.31
4.4 Pasangan Penangkal Petir 1.00 3,500,000.00 3,500,000.00 0.35 0.50 50.00 0.18 - - 0.50 50.00 0.18
4.5 Pasangan Instlasi Jaringan Kabel Fiber Optic (CCTV) 3.00 786,326.75 2,358,980.25 0.24 - - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2 MP (Luar Bangunan, Sambungan Dari Mini Resto) 3.00 656,975.00 1,970,925.00 0.20 - - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm 4.00 20,442.68 81,770.70 0.01 - - - - - - - -
4.6.1 Pasangan Horn Speaker (Sambungan Dari Mini Resto) 2.00 494,826.75 989,653.50 0.10 - - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25 kg) 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - - -
4.8 Pasangan Instalasi PLN Power 1.00 10,000,000.00 10,000,000.00 1.01 - - - - - - - -

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 44,560,643.30 4.50 1.66 0.00 1.66

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVc Tipe AW Diameter 3/4" (Air Bersih Dari Sumur Bor / PDAM Reservoir) m1 18.50 28,304.65 523,636.03 0.05 - - - - - - - -
5.2 Pipa PVC Tipe AW Diameter 3/4" (Distribusi Air Bersih Dari Reservoir) m1 26.50 28,304.65 750,073.23 0.08 13.25 50.00 0.04 - - 13.25 50.00 0.04
5.3 Pipa PVC Tipe AW Diameter 3" (Air Kotor Ke Drainase Lingkungan) m1 23.00 135,539.80 3,117,415.40 0.31 23.00 100.00 0.31 - - 23.00 100.00 0.31
5.4 Pipa PVC Tipe AW Diameter 4" (Disposal) m1 18.00 186,689.80 3,360,416.40 0.34 18.00 100.00 0.34 - - 18.00 100.00 0.34
5.5 Pasangan 1 bh Closet Duduk / Monoblock (TOTO) bh 6.00 3,655,597.00 21,933,582.00 2.22 3.00 50.00 1.11 - - 3.00 50.00 1.11
5.6 Pasangan 1 bh Wastafel (TOTO) 3.00 3,571,942.00 10,715,826.00 1.08 3.00 100.00 1.08 - - 3.00 100.00 1.08
5.7 Pasangan 1 bh Uninoir (TOTO) 2.00 6,665,285.00 13,330,570.00 1.35 2.00 100.00 1.35 - - 2.00 100.00 1.35
5.8 Pasangan 1 bh Floor Drain 9.00 41,123.50 370,111.50 0.04 9.00 100.00 0.04 - - 9.00 100.00 0.04
5.9 Pasangan 1 bh Kran dia. 1/2' atau 3/4" 8.00 102,228.50 817,828.00 0.08 8.00 100.00 0.08 - - 8.00 100.00 0.08
5.10 Pasangan 1 bh Kran wastafel dia. 1/2' atau 3/4" 2.00 335,428.50 670,857.00 0.07 2.00 100.00 0.07 - - 2.00 100.00 0.07
5.11 Pasangan 1 bh shower closet dia. 1/2' atau 3/4" 6.00 142,928.50 857,571.00 0.09 6.00 100.00 0.09 - - 6.00 100.00 0.09
5.12 Pasangan 1 bh shower Wall dia. 1/2' atau 3/4" (Ruang Bilas) 4.00 1,435,428.50 5,741,714.00 0.58 4.00 100.00 0.58 - - 4.00 100.00 0.58
5.13 Pasangan 1 bh Stop Kran (Gate Valve) dia. 3/4" 2.00 141,428.50 282,857.00 0.03 2.00 100.00 0.03 - - 2.00 100.00 0.03
5.14 Pasangan Mesin Air 1.00 741,000.00 741,000.00 0.07 - - - - - - - -
5.14b Pasangan Mesin Pemanas Air 1.00 5,000,000.00 5,000,000.00 0.51 - - - - - - - -
5.15 Septictank Biotank Kap. 4m3 1.00 20,380,000.00 20,380,000.00 2.06 0.50 50.00 1.03 - - 0.50 50.00 1.03
5.16 Pasangan Sumur Bor Jet Pump 30.00 350,000.00 10,500,000.00 1.06 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.17 Reservoir 1200 Liter 1.00 1,850,000.00 1,850,000.00 0.19 1.00 100.00 0.19 - - 1.00 100.00 0.19
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.18 Reservoir 200x150x350 cm - -
5.18.1 Pekerjaan Pondasi Pedestal Pd1 - -
5.18.1.1 Galian Tanah Pondasi Poerplat < 1m 1.62 74,250.00 120,285.00 0.01 - - - - - - - -
5.18.1.2 Urugan Tanah Kembali Pondasi Poerplat 0.43 55,000.00 23,760.00 0.00 - - - - - - - -
5.18.1.3 Tiang Pondasi Pedestal 50x50 cm -
Beton Mutu fc = 26,6 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.80 1,485,144.21 1,188,115.37 0.12 - - - - - - - -
Bekisting 2x Pakai 3.20 193,504.30 619,213.76 0.06 - - - - - - - -
Besi Beton Ø12, Ø8 49.44 21,465.73 1,061,174.10 0.11 - - - - - - - -
5.18.1.4 Pondasi Poerplat 90x90 cm,T.20 cm - -
Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.65 1,485,144.21 962,373.45 0.10 - - - - - - - -
Bekisting 2x Pakai 1.44 124,547.50 179,348.40 0.02 - - - - - - - -
Besi Beton Ø14 SNI 214.35 21,465.73 4,601,114.73 0.46 - - - - - - - -
5.18.2 Rangkai Tengah Dan Lantai Menara (Besi Hollow Galvanis 4/4) 34.82 244,970.00 8,529,855.40 0.86 34.82 100.00 0.86 - - 34.82 100.00 0.86
5.18.3 Rangka Utama menara ( Besi Hollow Galvanis 5/10 32.28 179,454.00 5,792,775.12 0.59 32.28 100.00 0.59 - - 32.28 100.00 0.59
5.18.4 Tplat Baja Lantai Menara T.3mm 3.00 740,164.86 2,220,494.57 0.22 - - - - - - - -
5.18.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) 5.00 244,970.00 1,224,850.00 0.12 4.00 80.00 0.10 - - 4.00 80.00 0.10

TOTAL PEKERJAAN PLAMBING DAN SANITASI 127,466,817.45 12.88 7.87 - 7.87

6. PEKERJAAN AKHIR - - -
6.1 Pembersihan Sisa Pekerjaan Ls 1.00 2,400,000.00 2,400,000.00 0.24 - - - - - - - -

TOTAL PEKERJAAN AKHIR 2,400,000.00 0.24 0.00 0.00 0.00

C. PENERAPAN SMKK

1. PENYIAPAN RKK
1.1 Pembuatan Dokumen Rencana Keselamatan Konstruksi
1.2 Pembuatan Prosedur dan instruksi kerja Set 1.00 2,000,000.00 2,000,000.00 0.20 1.00 100.00 0.20 - - 1.00 100.00 0.20
1.3 Penyiapan formulir
TOTAL PENYIAPAN RKK 2,000,000.00 0.20 0.20 - 0.20
2. SOSIALISASI, PROMOSI DAN PELATIHAN
2.1 Induksi K3 (Safety Induction) Org 5.00 7,500.00 37,500.00 0.00 0.50 10.00 0.00 - - 0.50 10.00 0.00
2.2 Pengarahan K3 (Safety Briefing) Org 5.00 15,000.00 75,000.00 0.01 5.00 100.00 0.01 - - 5.00 100.00 0.01
2.3 Pelatihan K3 -
2.3.1 Bekerja di ketinggian Org 4.00 7,500.00 30,000.00 0.00 4.00 100.00 0.00 - - 4.00 100.00 0.00
2.3.2 Penggunaan Bahan Kimia (MSDS) Org 2.00 7,500.00 15,000.00 0.00 2.00 100.00 0.00 - - 2.00 100.00 0.00
2.4 Simulasi K3 Org 5.00 7,500.00 37,500.00 0.00 5.00 100.00 0.00 - - 5.00 100.00 0.00
2.5 Spanduk (Banner) Lb 1.00 150,000.00 150,000.00 0.02 1.00 100.00 0.02 - - 1.00 100.00 0.02
2.6 Poster 2 2.00 50,000.00 100,000.00 0.01 2.00 100.00 0.01 - - 2.00 100.00 0.01
2.7 Papan Informasi K3 1 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
TOTAL SOSIALISASI, PROMOSI DAN PELATIHAN 945,000.00 0.10 0.09 - 0.09
3. ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI
3.1 APK
3.1.1 Tali Keselamatan (Life Line) Ls 1.00 1,700,000.00 1,700,000.00 0.17 1.00 100.00 0.17 - - 1.00 100.00 0.17
3.1.2 Pembatas Area (Restricted Area) Ls 1.00 2,000,000.00 2,000,000.00 0.20 1.00 100.00 0.20 - - 1.00 100.00 0.20
3.2 APD -
3.2.1 Topi Pelindung (Safety Helmet) Bh 10.00 75,000.00 750,000.00 0.08 10.00 100.00 0.08 - - 10.00 100.00 0.08
3.2.2 Pelindung Mata (Googles, Spectacles) Bh 5.00 25,000.00 125,000.00 0.01 5.00 100.00 0.01 - - 5.00 100.00 0.01
3.2.3 Pelindung Pernapasan dan Mulut (Masker) Bh 100.00 5,000.00 500,000.00 0.05 100.00 100.00 0.05 - - 100.00 100.00 0.05
3.2.4 Sarung Tangan (Safety Gloves) Psg 10.00 15,000.00 150,000.00 0.02 10.00 100.00 0.02 - - 10.00 100.00 0.02
3.2.5 Sepatu Keselamatan (Safety Shoes) Psg 10.00 350,000.00 3,500,000.00 0.35 10.00 100.00 0.35 - - 10.00 100.00 0.35
3.2.6 Penunjang Seluruh Tubuh (Full Body Harness) Bh 2.00 500,000.00 1,000,000.00 0.10 2.00 100.00 0.10 - - 2.00 100.00 0.10
3.2.7 Rompi Keselamatan (Safety Vest) Bh 10.00 25,000.00 250,000.00 0.03 10.00 100.00 0.03 - - 10.00 100.00 0.03
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 9,975,000.00 1.01 1.01 - 1.01
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4. ASURANSI DAN PERIZINAN
4.1 Asuransi Ls 1.00 3,000,000.00 3,000,000.00 0.30 1.00 100.00 0.30 - - 1.00 100.00 0.30
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 3,000,000.00 0.30 0.30 - 0.30
5. PERSONEL K3 KONSTRUKSI
5.1 Ahli K3 Konstruksi -
5.2 Petugas K3 Konstruksi Ob 4.00 3,675,000.00 14,700,000.00 1.48 4.00 100.00 1.48 - - 4.00 100.00 1.48
TOTAL PERSONEL K3 KONSTRUKSI 14,700,000.00 1.48 1.48 - 1.48
6. FASILITAS, SARANA DAN PRASARANA KESEHATAN
6.1 Peralatan P3K (Kotak P3K, Tandu, Obat Luka, Perban, dll) Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
TOTAL FASILITAS, SARANA DAN PRASARANA KESEHATAN 500,000.00 0.05 0.05 - 0.05
7. RAMBU - RAMBU YANG DIPERLUKAN
7.1 Rambu Petunjuk bh 2.00 75,000.00 150,000.00 0.02 2.00 100.00 0.02 - - 2.00 100.00 0.02
7.2 Rambu Larangan bh 2.00 75,000.00 150,000.00 0.02 2.00 100.00 0.02 - - 2.00 100.00 0.02
7.3 Rambu Peringatan bh 2.00 100,000.00 200,000.00 0.02 2.00 100.00 0.02 - - 2.00 100.00 0.02
7.4 Jalur Evakuasi (Escape Route) Ls 1.00 250,000.00 250,000.00 0.03 1.00 100.00 0.03 - - 1.00 100.00 0.03
TOTAL RAMBU - RAMBU YANG DIPERLUKAN 750,000.00 0.08 0.08 - 0.08
8. KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI
8.1 Ahli K3 Konstruksi Oj -
TOTAL KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI - 0.00
9. LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN
KONSTRUKSI
9.1 Alat Pemadam Api Ringan (APAR) bh 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
9.2 Program Inspeksi Ls 1.00 1,500,000.00 1,500,000.00 0.15 1.00 100.00 0.15 - - 1.00 100.00 0.15
9.3 Pelaporan dan Penyeledikan Insiden Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
9.4 Pembuatan Kartu Identitas Pekerja (KIP) Org 10.00 5,000.00 50,000.00 0.01 10.00 100.00 0.01 - - 10.00 100.00 0.01
TOTAL LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN KONSTRUKSI 2,550,000.00 0.26 0.26 - 0.26

A Jumlah Harga Penawaran 989,944,870.91 100.00 53.43 9.09 62.52


B PPN (10%) 98,994,487.09
C Jumlah (A+B) 1,088,939,358.00
PERSENTASE SAMPAI MINGGU INI 62.52
D Jumlah Dibulatkan 1,088,939,358.00

Bulukumba, 03 Desember 2020


Disetujui, Diketahui, Diperiksa Oleh, Dibuat Oleh,
Pejabat Pembuat Komitmen Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUTR Prov SulSel Dinas PUTR Prov SulSel CV.MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

A.KHADAFI HARUN, ST.,MT. L I L I, ST. IRHAM HARAHAP, ST. VIKA APRILIA DWI PUTRI
NIP. 19811126 200901 1 008 NIP. 19821229 201503 2 001 Site Engineer Direktris
LAPORAN KEMAJUAN MINGGUAN

Kegiatan : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba Minggu Ke : 08 ( Delapan )
Satuan Kerja : Dinas Pekerjaan Umum Dan Tata Ruang Prov. Sulawesi Selatan Bidang Cipta Karya Periode : 04 Desember S/d 10 Desember 2020
Lokasi : Desa Ara, Kecamatan Bonto Bahari, Kabupaten Bulukumba, Provinsi Sulawesi Selatan No. Kontrak : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
Sumber Dana : Dana Bantuan Provinsi Nilai Kontrak : Rp. 1,088,939,358.00
Tahun Anggaran : 2020 Schedule Pelaksanaan : 16 Oktober S/d 14 Desember 2020

MINGGU LALU MINGGU INI S/D MINGGU INI


VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
NO URAIAN PEKERJAAN
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q

A. PEMBANGUNAN RUANG KULINER, SUVENIR, MUSHOLLAH DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Papan Proyek Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
1.2 Bedeng/Direksi Keet M2 5.50 1,512,555.00 8,319,052.50 0.84 5.50 100.00 0.84 - - 5.50 100.00 0.84

TOTAL PEKERJAAN PERSIAPAN 8,819,052.50 0.89 0.89 0.00 0.89

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Poerplat PP1 (Selasar Samping)
2.1.1.1 Galian Pondasi Poerplat < 1 m M3 0.32 73,837.50 23,628.00 0.00 0.32 100.00 0.00 - - 0.32 100.00 0.00
2.1.1.2 Urugan Pasir dibawah Pondasi Poerplat T.5 cm M3 0.04 148,335.00 5,933.40 0.00 0.04 100.00 0.00 - - 0.04 100.00 0.00
2.1.1.3 Urugan Tanah Kembali Pondasi Poerplat M3 0.31 54,175.00 16,794.25 0.00 0.31 100.00 0.00 - - 0.31 100.00 0.00
2.1.1.4 Pasangan Lantai Kerja bawah Pondasi Poerplat T.5 cm (Beton K300) M3 0.04 1,118,216.00 44,728.64 0.00 0.04 100.00 0.00 - - 0.04 100.00 0.00
2.1.1.5 Pondasi Poerplat 35x50 cm, T.20 cm - -
Beton Mutu F'c = 26,4 mpa (K300), Slump (12-2) cm, w/c = 0,52 M3 0.14 1,118,216.00 156,550.24 0.02 0.14 100.00 0.02 - - 0.14 100.00 0.02
Bekisting 2x Pakai M2 0.56 107,013.50 59,927.56 0.01 0.56 100.00 0.01 - - 0.56 100.00 0.01
Besi Beton Ø14 SNI Kg 29.40 21,464.85 631,066.59 0.06 29.40 100.00 0.06 - - 29.40 100.00 0.06
2.1.2 Pekerjaan Pondasi Batu Kali (Badan Bangunan, Mushollah) - -
2.1.2.1 Galian Tanah Pondasi Batu Kali < 1 m M3 22.73 73,837.50 1,678,326.38 0.17 22.73 100.00 0.17 - - 22.73 100.00 0.17
2.1.2.2 Urugan Pasir dibawah Pondasi Batu Kali T.5 cm M3 1.08 148,335.00 160,201.80 0.02 1.08 100.00 0.02 - - 1.08 100.00 0.02
2.1.2.3 Pasangan Aanstamping bawah Pondasi Batu Kali T.10 M3 2.17 382,674.00 830,402.58 0.08 2.17 100.00 0.08 - - 2.17 100.00 0.08
2.1.2.4 Urugan Tanah Kembali Pondasi Batu Kali M3 10.39 54,175.00 562,878.25 0.06 10.39 100.00 0.06 - - 10.39 100.00 0.06
2.1.2.5 Pondasi Batu Kali 1 Sp : 3 Pp M3 9.09 827,447.50 7,521,497.78 0.76 9.09 100.00 0.76 - - 9.09 100.00 0.76
2.1.3 Pekerjaan Pondasi Rollage L.15 cm (Entrance, Selasar Samping) - - -
2.1.3.1 Galian Tanah Pondasi Rollage < 1 m M3 2.23 73,837.50 164,657.63 0.02 2.23 100.00 0.02 - - 2.23 100.00 0.02
2.1.3.2 Urugan Pasir dibawah Pondasi Rollage T.5 cm M3 0.45 148,335.00 66,750.75 0.01 0.45 100.00 0.01 - - 0.45 100.00 0.01
2.1.3.3 Pasangan Lantai Kerja bawah Pondasi Rollage T.5 cm (Beton K300) M3 0.45 1,118,216.00 499,003.89 0.05 0.45 100.00 0.05 - - 0.45 100.00 0.05
2.1.3.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp M2 20.83 128,436.00 2,675,321.88 0.27 20.83 100.00 0.27 - - 20.83 100.00 0.27
2.2 Pekerjaan Sloef, Kolom dan Ringbalk - -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Mushollah) - -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 1.62 1,118,216.00 1,815,703.23 0.18 1.62 100.00 0.18 - - 1.62 100.00 0.18
2.2.1.2 Bekisting 2x Pakai M2 10.83 114,438.50 1,239,368.96 0.13 10.83 100.00 0.13 - - 10.83 100.00 0.13
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI Kg 280.09 21,464.85 6,012,089.84 0.61 280.09 100.00 0.61 - - 280.09 100.00 0.61
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan, Mushollah) - -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.88 1,118,216.00 981,234.54 0.10 0.88 100.00 0.10 - - 0.88 100.00 0.10
2.2.2.2 Bekisting 2x Pakai M2 5.85 193,468.00 1,131,787.80 0.11 5.85 100.00 0.11 - - 5.85 100.00 0.11
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 181.66 21,464.85 3,899,347.58 0.39 181.66 100.00 0.39 - - 181.66 100.00 0.39
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Selasar, Westafel, Tempat Wudhu) -
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 0.34 100.00 0.03 - - 0.34 100.00 0.03
2.2.3.2 Bekisting 2x Pakai M2 2.26 193,468.00 437,237.68 0.04 2.26 100.00 0.04 - - 2.26 100.00 0.04
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 70.10 21,464.85 1,504,686.30 0.15 70.10 100.00 0.15 - - 70.10 100.00 0.15
2.2.4 Pekerjaan Kolom K1 15 x 30 (Selasar Samping) -
2.2.4.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.62 1,118,216.00 694,412.14 0.07 0.62 100.00 0.07 - - 0.62 100.00 0.07
2.2.4.2 Bekisting 2x Pakai M2 6.21 193,468.00 1,201,436.28 0.12 6.21 100.00 0.12 - - 6.21 100.00 0.12
2.2.4.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 99.69 21,464.85 2,139,830.90 0.22 99.69 100.00 0.22 - - 99.69 100.00 0.22
2.2.5 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan, Mushollah) -
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 2.08 1,008,161.00 2,097,478.96 0.21 2.08 100.00 0.21 - - 2.08 100.00 0.21
2.2.5.2 Bekisting 2x Pakai M2 13.87 197,923.00 2,745,192.01 0.28 13.87 100.00 0.28 - - 13.87 100.00 0.28
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 299.22 21,464.85 6,422,712.42 0.65 299.22 100.00 0.65 - - 299.22 100.00 0.65
2.2.6 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan) -
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 0.34 100.00 0.03 - - 0.34 100.00 0.03
2.2.6.2 Bekisting 2x Pakai M2 2.24 197,923.00 443,347.52 0.04 2.24 100.00 0.04 - - 2.24 100.00 0.04
2.2.6.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 48.32 21,464.85 1,037,181.55 0.10 48.32 100.00 0.10 - - 48.32 100.00 0.10
2.2.7 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Mushollah, Pintu Jendela) -
2.2.7.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.84 1,008,161.00 846,855.24 0.09 0.84 100.00 0.09 - - 0.84 100.00 0.09
2.2.7.2 Bekisting 2x Pakai M2 5.59 197,923.00 1,106,389.57 0.11 5.59 100.00 0.11 - - 5.59 100.00 0.11
2.2.7.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 115.53 21,464.85 2,479,834.12 0.25 115.53 100.00 0.25 - - 115.53 100.00 0.25
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.2.8 Pekerjaan Plat Beton (Selasar Samping, Westafel) -
2.2.8.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.22 1,008,161.00 221,795.42 0.02 0.22 100.00 0.02 - - 0.22 100.00 0.02
2.2.8.2 Bekisting 2x Pakai M2 2.21 237,468.00 524,804.28 0.05 2.21 100.00 0.05 - - 2.21 100.00 0.05
2.2.8.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 54.54 21,464.85 1,170,692.92 0.12 54.54 100.00 0.12 - - 54.54 100.00 0.12
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) M2 152.03 163,636.00 24,877,581.08 2.51 152.03 100.00 2.51 - - 152.03 100.00 2.51
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4, Entrance) M2 42.24 242,170.50 10,229,281.92 1.03 42.24 100.00 1.03 - - 42.24 100.00 1.03
2.5 Pekerjaan Tiang Atap Bitumen Gelombang (Besi Hollow Galvanis 5/10, Entrance) M' 20.40 178,365.00 3,638,646.00 0.37 20.40 100.00 0.37 - - 20.40 100.00 0.37
2.6 Pekerjaan Rangka Plafond Kalsiboard (Besi Hollow Metal Galvalume 4/4) M2 147.40 102,837.17 15,158,198.37 1.53 147.40 100.00 1.53 - - 147.40 100.00 1.53

TOTAL PEKERJAAN STRUKTUR 109,840,345.70 11.10 11.10 0.00 11.10

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) M3 8.54 148,335.00 1,266,780.90 0.13 8.54 100.00 0.13 - - 8.54 100.00 0.13
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) M3 25.63 167,227.00 4,285,636.74 0.43 25.63 100.00 0.43 - - 25.63 100.00 0.43
3.1.1.3 Rabat Beton bawah Lantai T.5 cm (Keseluruhan, Beton K300) M3 8.54 1,118,216.00 9,549,564.64 0.96 8.54 100.00 0.96 - - 8.54 100.00 0.96
3.1.1.4 Penutup Lantai Keramik Motif 60x60 (Badan Bangunan, Mushollah) M2 62.94 403,309.50 25,384,299.93 2.56 59.79 95.00 2.44 - - 59.79 95.00 2.44
3.1.1.5 Penutup Lantai Conwood Deck 6" (Entrance) M2 59.01 866,833.08 51,151,820.09 5.17 56.01 94.92 4.90 - - 56.01 94.92 4.90
3.1.1.6 Penutup Lantai Andesit Polos 30x30 (Selasar, Tempat Wudhu, Ram) M2 51.05 232,589.50 11,873,693.98 1.20 51.05 100.00 1.20 - - 51.05 100.00 1.20
3.1.1.7 Plint Lantai Keramik 10x60 (Badan Bangunan, Mushollah) M' 38.85 51,605.03 2,004,855.55 0.20 - - - - - - - -
3.1.2 Pekerjaan Dinding -
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Mushollah, 1 Sp : 4 Pp) M2 74.55 242,979.00 18,114,084.45 1.83 74.55 100.00 1.83 - - 74.55 100.00 1.83
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Selasar Samping, Tempat Wudhu) M2 5.14 65,550.32 336,928.64 0.03 5.14 100.00 0.03 - - 5.14 100.00 0.03
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm (Badan Bangunan, Mushollah) M2 91.30 60,403.20 5,514,812.16 0.56 91.30 100.00 0.56 - - 91.30 100.00 0.56
3.1.2.4 Plesteran Ciprat 1 Sp : 2 Pp Tebal 15 mm (Selasar Samping, Antar Kolom) M2 24.84 49,215.10 1,222,503.08 0.12 24.84 100.00 0.12 - - 24.84 100.00 0.12
3.1.2.5 Dinding Keramik Mozaik 30x60 (Selasar Samping, Westafel, Tempat Wudhu) M2 18.44 410,432.00 7,568,366.08 0.76 18.44 100.00 0.76 - - 18.44 100.00 0.76
3.1.2.6 Coating Bening (Badan Bangunan, Mushollah, Kolom Luar) M2 127.49 45,973.13 5,861,113.71 0.59 - - - - - - - -
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) M2 8.64 995,043.50 8,597,175.84 0.87 8.64 100.00 0.87 - - 8.64 100.00 0.87
3.1.2.8 Dinding Wallpaper Bata L.50 cm (Sisi Dalam) M2 28.13 80,005.50 2,250,554.72 0.23 - - - - - - - -
3.1.3 Pekerjaan Plafond -
3.1.3.1 Plafond Kalsiboard (Badan Bangunan, Kemiringan Atap, Mushollah) M2 147.40 44,924.00 6,621,797.60 0.67 147.40 100.00 0.67 - - 147.40 100.00 0.67
3.1.3.2 Plafond Kalsiboard (Lapis Bawah Atap, Entrance) M2 42.24 44,924.00 1,897,589.76 0.19 42.24 100.00 0.19 - - 42.24 100.00 0.19
3.2 Pekerjaan Pintu dan Jendela (Badan Bangunan) -
3.2.1 Pintu P1 (Entrance dan Back Entrance, Badan Bangunan) -
3.2.1.1 Pasangan Kusen Alumunium Coating P1 (4" x 1 3/4") cm M' 22.40 157,194.40 3,521,154.56 0.36 22.40 100.00 0.36 - - 22.40 100.00 0.36
3.2.1.2 Pasangan Daun Pintu P1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - - -
3.2.1.3 Pasangan Kaca Mati 5 mm P1 M2 11.20 145,703.80 1,631,882.56 0.16 - - - - - - - -
3.2.1.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - - -
3.2.1.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - - -
3.2.1.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - - -
3.2.1.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - - -
3.2.2 Jendela J1 (Badan Bangunan) -
3.2.2.1 Pasangan Kusen Alumunium Coating J1 (4" x 1 3/4") cm M' 40.60 157,194.40 6,382,092.64 0.64 40.60 100.00 0.64 - - 40.60 100.00 0.64
3.2.2.2 Pasangan Kaca Mati 5 mm J1 M2 8.00 145,703.80 1,165,630.40 0.12 - - - - - - - -
3.2.3 Pintu PJ1 (Mushollah) -
3.2.3.1 Pasangan Kusen Alumunium Coating PJ1 (4" x 1 3/4") cm M' 22.20 157,194.40 3,489,715.68 0.35 22.20 100.00 0.35 - - 22.20 100.00 0.35
3.2.3.2 Pasangan Daun Pintu PJ1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - - -
3.2.3.3 Pasangan Kaca Mati 5 mm P1 M2 8.70 145,703.80 1,267,623.06 0.13 - - - - - - - -
3.2.3.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - - -
3.2.3.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - - -
3.2.3.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - - -
3.2.3.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - - -
3.3 Pekerjaan Pengecatan -
3.3.1 Pengecatan Plafond (1 Plamir ; 1 Cat Dasar : 2 Cat Penutup), (Interior) M2 189.64 35,536.05 6,739,056.52 0.68 189.64 100.00 0.68 - - 189.64 100.00 0.68
3.3.2 Pengecatan Rangka Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 23.76 168,454.00 4,002,467.04 0.40 23.76 100.00 0.40 - - 23.76 100.00 0.40
3.3.3 Pengecatan Tiang Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 6.12 168,454.00 1,030,938.48 0.10 6.12 100.00 0.10 - - 6.12 100.00 0.10
3.4 Pekerjaan Atap -
3.4.1 Atap Bitumen Gelombang (Badan Bangunan, Mushollah) M2 152.03 207,297.09 31,515,376.59 3.18 152.03 100.00 3.18 - - 152.03 100.00 3.18
3.4.2 Atap Bitumen Gelombang (Entrance) M2 42.24 207,297.09 8,756,229.08 0.88 42.24 100.00 0.88 - - 42.24 100.00 0.88
3.4.3 Nok Bitumen (Badan Bangunan, Mushollah) M' 14.55 134,101.00 1,951,169.55 0.20 14.55 100.00 0.20 - - 14.55 100.00 0.20
3.4.4 Listplank (Kalsiplank, Badan Bangunan, Mushollah, Entrance) M' 50.00 70,950.00 3,547,500.00 0.36 50.00 100.00 0.36 - - 50.00 100.00 0.36

TOTAL PEKERJAAN FINISHING ARSITEKTUR 257,222,142.77 25.98 22.27 0.00 22.27

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel Bh 1.00 1,572,826.75 1,572,826.75 0.16 - - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt Bh 16.00 353,938.75 5,663,020.00 0.57 16.00 100.00 0.57 - - 16.00 100.00 0.57
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4.1.3 Pasangan Lampu Down Light 2,5" Outbow LED 5,5 Watt Bh 11.00 305,538.75 3,360,926.25 0.34 11.00 100.00 0.34 - - 11.00 100.00 0.34
4.1.4 Pasangan Saklar Tunggal Bh 4.00 211,378.75 845,515.00 0.09 4.00 100.00 0.09 - - 4.00 100.00 0.09
4.1.5 Pasangan Saklar Ganda Bh 2.00 223,478.75 446,957.50 0.05 2.00 100.00 0.05 - - 2.00 100.00 0.05
4.2 Pasangan Instalasi Stop Kontak - -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA Bh 10.00 216,218.75 2,162,187.50 0.22 10.00 100.00 0.22 - - 10.00 100.00 0.22
4.2.2 Pasangan Stop Kontak AC 220 VA/3520 W (AC Split 1 PK) Bh 4.00 253,728.75 1,014,915.00 0.10 4.00 100.00 0.10 - - 4.00 100.00 0.10
4.3 Pasangan Instalasi Jaringan AC M' 30.00 108,772.68 3,263,180.25 0.33 30.00 100.00 0.33 - - 30.00 100.00 0.33
4.3.1 Pasangan AC Split 1 PK Bh 3.00 3,365,799.34 10,097,398.03 1.02 1.50 50.00 0.51 - - 1.50 50.00 0.51
4.4 Pasangan Penangkal Petir Ls 1.00 2,500,000.00 2,500,000.00 0.25 1.00 100.00 0.25 - - 1.00 100.00 0.25
4.5 Pasangan Instalasi Jaringan Kabel Fiber Optic (CCTV) Ttk 6.00 786,326.75 4,717,960.50 0.48 - - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2MP Bh 6.00 656,975.00 3,941,850.00 0.40 - - - - - - - -
4.5.2 Pasangan NVR Channel Set 1.00 5,023,975.00 5,023,975.00 0.51 - - - - - - - -
4.5.3 Pasangan Monitor LCD 32" Bh 1.00 2,944,975.00 2,944,975.00 0.30 - - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm M' 12.00 20,442.68 245,312.10 0.02 - - - - - - - -
4.6.1 Pasangan Horn Speaker Bh 6.00 494,826.75 2,968,960.50 0.30 - - - - - - - -
4.6.2 Pasangan Volume Kontrol Set 1.00 252,826.75 252,826.75 0.03 - - - - - - - -
4.6.3 Pasangan Perangkat Sound System Set 1.00 4,565,000.00 4,565,000.00 0.46 - - - - - - - -
4.6.4 Pasangan TB-Sound System Set 1.00 5,846,326.75 5,846,326.75 0.59 - - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25Kg) Ttk 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - - -
4.8 Pasangan Instalasi Jaringan Kabel Fiber Optic (Akses Point) Ttk 3.00 786,326.75 2,358,980.25 0.24 - - - - - - - -
4.8.1 Pasangan Server Set 1.00 7,578,826.75 7,578,826.75 0.77 - - - - - - - -
4.8.2 Pasangan Akses Point Bh 1.00 2,034,826.75 2,034,826.75 0.21 - - - - - - - -
4.8.3 Pasangan Switch HUB Bh 1.00 2,843,326.75 2,843,326.75 0.29 - - - - - - - -
4.9 Pasangan Instalasi PLN Power (Inc. Jalur ke Mushollah dan Toilet) Ls 1.00 9,000,000.00 9,000,000.00 0.91 - - - - - - - -

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 94,450,073.38 9.54 2.46 0.00 2.46

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVC Type AW Diameter 3/4" (Air Bersih Sambungan dari Tandon) M' 33.00 28,300.25 933,908.25 0.09 16.50 50.00 0.05 - - 16.50 50.00 0.05
5.2 Pipa PVC Type AW Diameter 3" (Air Kotor ke Drainase Lingkungan) M' 25.80 135,531.00 3,496,699.80 0.35 2.58 10.00 0.04 - - 2.58 10.00 0.04
5.3 Pasangan 1 Bh Wastafel Bh 2.00 3,934,865.00 7,869,730.00 0.79 - - - - - - - -
5.4 Pasangan 1 Bh Wastafel Cuci Piring (WCP) Bh 1.00 890,945.00 890,945.00 0.09 - - - - - - - -
5.5 Pasangan 1 Bh Floor Drain Bh 2.00 41,112.50 82,225.00 0.01 - - - - - - - -
5.6 Pasangan 1 Bh Kran Dia. 1/2" atau 3/4" Bh 10.00 102,217.50 1,022,175.00 0.10 - - - - - - - -
5.7 Pasangan 1 Bh Kran Wastafel Dia. 1/2" atau 3/4" Bh 3.00 335,417.50 1,006,252.50 0.10 - - - - - - - -
5.8 Pasangan 1 Bh Stop Kran (Gate Valve) Dia. 3/4" Bh 1.00 141,417.50 141,417.50 0.01 - - - - - - - -
5.9 Pasangan Mesin Air Bh 1.00 741,000.00 741,000.00 0.07 - - - - - - - -
5.10 Menara Reservoir 200x150x350 cm -
5.10.1 Pekerjaan Pondasi Pedestal Pd1 -
5.10.1.1 Galian Tanah Pondasi Poerplat < 1 m M3 1.62 73,837.50 119,616.75 0.01 - - - - - - - -
5.10.1.2 Urugan Tanah Kembali Pondasi Poerplat M3 0.43 54,175.00 23,295.25 0.00 - - - - - - - -
5.10.1.3 Tiang Pondasi Pedestal 50x50 cm - - -
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.80 1,118,216.00 894,572.80 0.09 - - - - - - - -
Bekisting 2x Pakai M2 3.20 193,468.00 619,097.60 0.06 - - - - - - - -
Besi Beton Ø12 SNI, Ø8 SNI Kg 49.44 21,464.85 1,061,130.60 0.11 - - - - - - - -
5.10.1.4 Pondasi Poerplat 90x90 cm, T.20 cm -
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.65 1,118,216.00 726,840.40 0.07 - - - - - - - -
Bekisting 2x Pakai M2 1.44 107,013.50 154,099.44 0.02 - - - - - - - -
Besi Beton Ø14 SNI Kg 214.35 21,464.85 4,600,940.54 0.46 - - - - - - - -
5.10.2 Rangka Tengah dan Lantai Menara (Besi Hollow Galvanis 4/4) M2 34.82 244,970.00 8,529,855.40 0.86 - - - - - - - -
5.10.3 Rangka Utama Menara (Besi Hollow Galvanis 5/10) M' 32.28 179,454.00 5,792,775.12 0.59 - - - - - - - -
5.10.4 Plat Baja Lantai Menara T.3 mm M2 3.00 740,164.86 2,220,494.57 0.22 - - - - - - - -
5.10.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) M2 5.00 244,970.00 1,224,850.00 0.12 - - - - - - - -

TOTAL PEKERJAAN PLAMBING DAN SANITASI 42,151,921.52 4.26 0.08 0.00 0.08

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Pek. Pembersian Awal m2 81.86 17,600.00 1,440,780.00 0.15 81.86 100.00 0.15 - - 81.86 100.00 0.15
1.2 Pek. Pengukuran & Pemasangan Bouwplank m1 48.60 106,461.25 5,174,016.75 0.52 48.60 100.00 0.52 - - 48.60 100.00 0.52

TOTAL PEKERJAAN PERSIAPAN 6,614,796.75 0.67 0.67 0.00 0.67

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Batu Kali (Badan Bangunan,Ruang Bilas)
2.1.1.1 Galian Pondasi Batu Kali < 1 m m3 22.05 73,892.50 1,629,329.63 0.16 6.62 30.00 0.05 - - 6.62 30.00 0.05
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.1.1.2 Urugan Pasir Dibawah Pondasi Batu Kali T.5 cm m3 1.05 174,757.00 183,494.85 0.02 1.05 100.00 0.02 - - 1.05 100.00 0.02
2.1.1.3 Pasangan Aanstamping Bawah Pondasi Batu Kali T.10 cm m3 2.10 392,699.70 824,669.37 0.08 2.10 100.00 0.08 - - 2.10 100.00 0.08
2.1.1.4 Urugan Tanah Kembali Pondasi Batu Kali m3 10.08 54,285.00 547,192.80 0.06 3.02 30.00 0.02 - - 3.02 30.00 0.02
2.1.1.5 Pondasi Batu Kali 1 Sp : 3 Pp m3 8.82 824,945.00 7,276,014.90 0.73 8.82 100.00 0.73 - - 8.82 100.00 0.73
2.1.2 Perjaan Pondasi Rollage L.15 cm (Selasar) -
2.1.2.1 Galian Tanah Pondasi Rollage < 1 m m3 1.52 73,892.50 112,501.33 0.01 0.15 10.00 0.00 - - 0.15 10.00 0.00
2.1.2.2 Urugan Pasir Dibawah Pondasi Rollage T.5 cm m3 0.30 174,757.00 53,213.51 0.01 0.03 10.00 0.00 - - 0.03 10.00 0.00
2.1.2.3 Pasangan Lantai Kerja Bawah Pondasi Rollage T.5 cm (Beton K300) m3 0.30 1,118,398.60 340,552.37 0.03 0.30 100.00 0.03 - - 0.30 100.00 0.03
2.1.2.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp m3 14.21 128,260.00 1,822,574.60 0.18 14.21 100.00 0.18 - - 14.21 100.00 0.18
2.2 Pekerjaan Sloef, Kolom, Plat dan Ringbalk - -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Ruang Bilas) - -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 m3 1.41 1,118,398.60 1,580,297.22 0.16 1.41 100.00 0.16 - - 1.41 100.00 0.16
2.2.1.2 Bekisting 2x Pakai m2 9.42 114,467.10 1,078,280.08 0.11 9.42 100.00 0.11 - - 9.42 100.00 0.11
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI kg 243.74 21,465.73 5,232,043.29 0.53 243.74 100.00 0.53 - - 243.74 100.00 0.53
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan) - -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slum (12 - 2) cm, w/c = 0,52 m3 0.48 1,118,398.60 533,476.13 0.05 0.48 100.00 0.05 - - 0.48 100.00 0.05
2.2.2.2 Bekisting 2x Pakai m2 3.18 193,504.30 615,343.67 0.06 3.18 100.00 0.06 - - 3.18 100.00 0.06
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI kg 98.75 21,465.73 2,119,732.25 0.21 98.75 100.00 0.21 - - 98.75 100.00 0.21
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Ruang Bilas) - -
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.25 1,008,343.60 249,111.29 0.03 0.25 100.00 0.03 - - 0.25 100.00 0.03
2.2.3.2 Bekisting 2x Pakai m2 1.65 193,504.30 318,701.58 0.03 1.65 100.00 0.03 - - 1.65 100.00 0.03
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI kg 51.14 21,465.73 1,097,861.33 0.11 51.14 100.00 0.11 - - 51.14 100.00 0.11
2.2.4 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan) - -
2.2.4.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.04 1,008,343.60 1,043,635.63 0.11 1.04 100.00 0.11 - - 1.04 100.00 0.11
2.2.4.2 Bekisting 2x Pakai m2 6.90 197,959.30 1,365,919.17 0.14 6.90 100.00 0.14 - - 6.90 100.00 0.14
2.2.4.3 Besi Beton Ø12 SNI, Ø6 SNI kg 148.86 21,465.73 3,195,302.68 0.32 148.86 100.00 0.32 - - 148.86 100.00 0.32
2.2.5 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan) - -
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.09 1,008,343.60 1,103,531.24 0.11 1.09 100.00 0.11 - - 1.09 100.00 0.11
2.2.5.2 Bekisting 2x Pakai m2 14.59 197,959.30 2,888,622.11 0.29 14.59 100.00 0.29 - - 14.59 100.00 0.29
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI kg 157.40 21,465.73 3,378,705.12 0.34 157.40 100.00 0.34 - - 157.40 100.00 0.34
2.2.6 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Pintu Jendela) -
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.15 1,008,343.60 148,831.52 0.02 0.15 100.00 0.02 - - 0.15 100.00 0.02
2.2.6.2 Bekisting 2x Pakai m2 0.98 197,959.30 194,791.95 0.02 0.98 100.00 0.02 - - 0.98 100.00 0.02
2.2.6.3 Besi Beton Ø10 SNI, Ø6 SNI kg 20.35 21,465.73 436,752.39 0.04 20.35 100.00 0.04 - - 20.35 100.00 0.04
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) m2 59.01 163,856.00 9,669,142.56 0.98 59.01 100.00 0.98 - - 59.01 100.00 0.98
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4) m2 48.59 102,876.77 4,998,782.09 0.50 48.59 100.00 0.50 - - 48.59 100.00 0.50
2.5 Pekerjaan Rangka Plafond dan Dinding Dalam PVC Shunda (Besi Hollow Metal Galvalume 4/4) m2 56.16 102,876.77 5,777,559.22 0.58 - - - - - - - -

TOTAL PEKERJAAN STRUKTUR 59,815,965.86 6.04 5.29 0.00 5.29

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) m3 4.09 174,757.00 715,280.40 0.07 4.09 100.00 0.07 - - 4.09 100.00 0.07
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) m3 12.28 167,345.00 2,054,804.70 0.21 12.28 100.00 0.21 - - 12.28 100.00 0.21
3.1.1.3 Rabat Beton T.5 cm (Keseluruhan, Beton K300) m3 4.09 1,118,398.60 4,577,605.47 0.46 4.09 100.00 0.46 - - 4.09 100.00 0.46
3.1.1.4 Penutup Lantai Keramik Tekstur 60x60 (Badan Bangunan) m2 36.93 413,098.40 15,255,723.91 1.54 36.93 100.00 1.54 - - 36.93 100.00 1.54
3.1.1.5 Penutup Lantai Andesit Polos 30x30 (Selasar, Ruang Bilas) m2 45.89 284,369.80 13,049,730.12 1.32 45.89 100.00 1.32 - - 45.89 100.00 1.32
3.1.1.6 Penutup Plat Wastafel (Granit 60x60, Toilet Pria dan Wanita) m2 2.20 841,621.73 1,851,567.81 0.19 - - - - - - - -
3.1.2 Pekerjaan Dinding - -
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Selasar, 1 Sp : 4 Pp) 90.64 242,533.50 21,983,236.44 2.22 90.64 100.00 2.22 - - 90.64 100.00 2.22
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Wc ) 30.00 65,473.32 1,964,199.60 0.20 30.00 100.00 0.20 - - 30.00 100.00 0.20
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm 121.28 60,304.20 7,313,693.38 0.74 121.28 100.00 0.74 - - 121.28 100.00 0.74
3.1.2.4 Coating Bening 121.28 46,853.13 5,682,347.00 0.57 - - - - - - - -
3.1.2.5 Dinding Andesit Polos 30x30 cm ( Wc, Ruang Bilas ) 56.52 284,369.80 16,072,581.10 1.62 - - - 56.52 100.00 1.62 56.52 100.00 1.62
3.1.2.6 Dinding Keramik 30x60 cm ( Sisi Dalam ) 69.88 370,557.00 25,894,523.16 2.62 - - - 69.88 100.00 2.62 69.88 100.00 2.62
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) 9.00 995,076.50 8,955,688.50 0.90 - - - 9.00 100.00 0.90 9.00 100.00 0.90
3.1.2.8 Cubicle Panel + Accessories (Pintu Wc dan Partisi Urinoir) 10.86 1,360,000.00 14,769,600.00 1.49 - - - 10.86 100.00 1.49 10.86 100.00 1.49
3.1.2.9 Dinding Bitumen Gelombang 48.59 201,749.24 9,802,995.57 0.99 - - - 48.59 100.00 0.99 48.59 100.00 0.99
3.1.2.10 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Pria) 1.00 1,200,000.00 1,200,000.00 0.12 - - - - - - - -
3.1.2.11 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Wanita) 1.00 750,000.00 750,000.00 0.08 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.1.3 Plafond dan Dinding Dalam Shunda ( Badan Bangunan ) 56.16 125,878.50 7,069,336.56 0.71 - - - 56.16 100.00 0.71 56.16 100.00 0.71
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.2 Pekerjaan Pintu dan Jendela ( Badan Bangunan ) - -
3.2.1 Pintu P1 - -
3.2.1.1 Pasangan Kusen Almunium Coating P1 (4" x 13/4") cm 10.96 157,199.02 1,722,901.26 0.17 - - - 10.96 100.00 0.17 10.96 100.00 0.17
3.2.1.2 Pasangan Daun Pintu P1 (Panel Almunium Coating - Coating) 4.30 870,323.19 3,742,389.72 0.38 - - - - - - - -
3.2.1.3 Pasangan Kunci Tanam 2x Slag P1 2.00 416,663.50 833,327.00 0.08 - - - - - - - -
3.2.1.4 Pasangan ensel P1 6.00 61,225.56 367,353.36 0.04 - - - - - - - -
3.2.1.5 Pasangan Doorcloser P1 2.00 241,902.10 483,804.20 0.05 - - - - - - - -
3.2.1.6 Pasangan Handle P1 2.00 229,802.10 459,604.20 0.05 - - - - - - - -
3.2.2 Jendela J1 - -
3.2.2.1 Pasangan Kusen Almunium Coating J1 (4" x 13/4") cm 28.80 157,199.02 4,527,331.78 0.46 - - - 28.80 100.00 0.46 28.80 100.00 0.46
3.2.2.2 Pasangan Kaca Mati 5 mm J1 0.60 145,705.56 87,423.34 0.01 - - - - - - - -
3.2.3 Jendela J2 -
3.2.3.1 Pasangan Kusen Almunium Coating J2 (4" x 13/4") cm 55.20 157,199.02 8,677,385.90 0.88 - - - - - - - -
3.2.3.2 Pasangan Kaca Mati 5 mm J2 0.90 145,705.56 131,135.00 0.01 - - - - - - - -
3.3. Pengecetan Plafond (1 Plamir : 1 Cat Dasar : 2 Cat Penutup), (Interior) 56.16 43,550.65 2,445,804.50 0.25 - - - - - - - -
3.4 Pekerjaan Atap - -
3.4.1 Atap Bitumen Gelombang (Badan Bangunan) 59.01 201,749.24 11,905,222.65 1.20 - - - - - - - -
3.4.2 Nok Bitumen (Badan Bangunan) 35.25 143,629.20 5,062,929.30 0.51 - - - - - - - -
3.4.3 Listplank (Kasiplank, Badan Bangunan, Enterance) 39.08 70,972.00 2,773,585.76 0.28 - - - - - - - -

TOTAL PEKERJAAN FINISHING ARSITEKTUR 202,183,111.69 20.42 6.76 8.97 15.73

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel 1.00 1,803,826.75 1,803,826.75 0.18 - - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt 10.00 353,938.75 3,539,387.50 0.36 10.00 100.00 0.36 - - 10.00 100.00 0.36
4.1.3 Pasangan Lampu Down Light 2.5" Outbow LED 5.5 Watt 12.00 305,538.75 3,666,465.00 0.37 12.00 100.00 0.37 - - 12.00 100.00 0.37
4.1.4 Pasangan Saklar Ganda 5.00 223,478.75 1,117,393.75 0.11 5.00 100.00 0.11 - - 5.00 100.00 0.11
4.2 Pasangan Instalasi Stop Kontak - -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA 3.00 216,218.75 648,656.25 0.07 3.00 100.00 0.07 - - 3.00 100.00 0.07
4.2.2 Pasangan Stop Kontak Wall Exhauser 6.00 216,218.75 1,297,312.50 0.13 6.00 100.00 0.13 - - 6.00 100.00 0.13
4.3 Pasangan Instalasi Jaringan Wall Exhauser 12.00 108,772.68 1,305,272.10 0.13 12.00 100.00 0.13 - - 12.00 100.00 0.13
4.3.1 Pasangan Wall Exhauser 12 Inch - FV30RUN 6.00 513,500.00 3,081,000.00 0.31 6.00 100.00 0.31 - - 6.00 100.00 0.31
4.4 Pasangan Penangkal Petir 1.00 3,500,000.00 3,500,000.00 0.35 0.50 50.00 0.18 - - 0.50 50.00 0.18
4.5 Pasangan Instlasi Jaringan Kabel Fiber Optic (CCTV) 3.00 786,326.75 2,358,980.25 0.24 - - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2 MP (Luar Bangunan, Sambungan Dari Mini Resto) 3.00 656,975.00 1,970,925.00 0.20 - - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm 4.00 20,442.68 81,770.70 0.01 - - - - - - - -
4.6.1 Pasangan Horn Speaker (Sambungan Dari Mini Resto) 2.00 494,826.75 989,653.50 0.10 - - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25 kg) 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - - -
4.8 Pasangan Instalasi PLN Power 1.00 10,000,000.00 10,000,000.00 1.01 - - - - - - - -

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 44,560,643.30 4.50 1.66 0.00 1.66

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVc Tipe AW Diameter 3/4" (Air Bersih Dari Sumur Bor / PDAM Reservoir) m1 18.50 28,304.65 523,636.03 0.05 - - - - - - - -
5.2 Pipa PVC Tipe AW Diameter 3/4" (Distribusi Air Bersih Dari Reservoir) m1 26.50 28,304.65 750,073.23 0.08 13.25 50.00 0.04 - - 13.25 50.00 0.04
5.3 Pipa PVC Tipe AW Diameter 3" (Air Kotor Ke Drainase Lingkungan) m1 23.00 135,539.80 3,117,415.40 0.31 23.00 100.00 0.31 - - 23.00 100.00 0.31
5.4 Pipa PVC Tipe AW Diameter 4" (Disposal) m1 18.00 186,689.80 3,360,416.40 0.34 18.00 100.00 0.34 - - 18.00 100.00 0.34
5.5 Pasangan 1 bh Closet Duduk / Monoblock (TOTO) bh 6.00 3,655,597.00 21,933,582.00 2.22 3.00 50.00 1.11 - - 3.00 50.00 1.11
5.6 Pasangan 1 bh Wastafel (TOTO) 3.00 3,571,942.00 10,715,826.00 1.08 3.00 100.00 1.08 - - 3.00 100.00 1.08
5.7 Pasangan 1 bh Uninoir (TOTO) 2.00 6,665,285.00 13,330,570.00 1.35 2.00 100.00 1.35 - - 2.00 100.00 1.35
5.8 Pasangan 1 bh Floor Drain 9.00 41,123.50 370,111.50 0.04 9.00 100.00 0.04 - - 9.00 100.00 0.04
5.9 Pasangan 1 bh Kran dia. 1/2' atau 3/4" 8.00 102,228.50 817,828.00 0.08 8.00 100.00 0.08 - - 8.00 100.00 0.08
5.10 Pasangan 1 bh Kran wastafel dia. 1/2' atau 3/4" 2.00 335,428.50 670,857.00 0.07 2.00 100.00 0.07 - - 2.00 100.00 0.07
5.11 Pasangan 1 bh shower closet dia. 1/2' atau 3/4" 6.00 142,928.50 857,571.00 0.09 6.00 100.00 0.09 - - 6.00 100.00 0.09
5.12 Pasangan 1 bh shower Wall dia. 1/2' atau 3/4" (Ruang Bilas) 4.00 1,435,428.50 5,741,714.00 0.58 4.00 100.00 0.58 - - 4.00 100.00 0.58
5.13 Pasangan 1 bh Stop Kran (Gate Valve) dia. 3/4" 2.00 141,428.50 282,857.00 0.03 2.00 100.00 0.03 - - 2.00 100.00 0.03
5.14 Pasangan Mesin Air 1.00 741,000.00 741,000.00 0.07 - - - - - - - -
5.14b Pasangan Mesin Pemanas Air 1.00 5,000,000.00 5,000,000.00 0.51 - - - - - - - -
5.15 Septictank Biotank Kap. 4m3 1.00 20,380,000.00 20,380,000.00 2.06 0.50 50.00 1.03 - - 0.50 50.00 1.03
5.16 Pasangan Sumur Bor Jet Pump 30.00 350,000.00 10,500,000.00 1.06 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.17 Reservoir 1200 Liter 1.00 1,850,000.00 1,850,000.00 0.19 1.00 100.00 0.19 - - 1.00 100.00 0.19
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.18 Reservoir 200x150x350 cm - -
5.18.1 Pekerjaan Pondasi Pedestal Pd1 - -
5.18.1.1 Galian Tanah Pondasi Poerplat < 1m 1.62 74,250.00 120,285.00 0.01 - - - - - - - -
5.18.1.2 Urugan Tanah Kembali Pondasi Poerplat 0.43 55,000.00 23,760.00 0.00 - - - - - - - -
5.18.1.3 Tiang Pondasi Pedestal 50x50 cm -
Beton Mutu fc = 26,6 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.80 1,485,144.21 1,188,115.37 0.12 - - - - - - - -
Bekisting 2x Pakai 3.20 193,504.30 619,213.76 0.06 - - - - - - - -
Besi Beton Ø12, Ø8 49.44 21,465.73 1,061,174.10 0.11 - - - - - - - -
5.18.1.4 Pondasi Poerplat 90x90 cm,T.20 cm - -
Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.65 1,485,144.21 962,373.45 0.10 - - - - - - - -
Bekisting 2x Pakai 1.44 124,547.50 179,348.40 0.02 - - - - - - - -
Besi Beton Ø14 SNI 214.35 21,465.73 4,601,114.73 0.46 - - - - - - - -
5.18.2 Rangkai Tengah Dan Lantai Menara (Besi Hollow Galvanis 4/4) 34.82 244,970.00 8,529,855.40 0.86 34.82 100.00 0.86 - - 34.82 100.00 0.86
5.18.3 Rangka Utama menara ( Besi Hollow Galvanis 5/10 32.28 179,454.00 5,792,775.12 0.59 32.28 100.00 0.59 - - 32.28 100.00 0.59
5.18.4 Tplat Baja Lantai Menara T.3mm 3.00 740,164.86 2,220,494.57 0.22 - - - - - - - -
5.18.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) 5.00 244,970.00 1,224,850.00 0.12 4.00 80.00 0.10 - - 4.00 80.00 0.10

TOTAL PEKERJAAN PLAMBING DAN SANITASI 127,466,817.45 12.88 7.87 - 7.87

6. PEKERJAAN AKHIR - - -
6.1 Pembersihan Sisa Pekerjaan Ls 1.00 2,400,000.00 2,400,000.00 0.24 - - - - - - - -

TOTAL PEKERJAAN AKHIR 2,400,000.00 0.24 0.00 0.00 0.00

C. PENERAPAN SMKK

1. PENYIAPAN RKK
1.1 Pembuatan Dokumen Rencana Keselamatan Konstruksi
1.2 Pembuatan Prosedur dan instruksi kerja Set 1.00 2,000,000.00 2,000,000.00 0.20 1.00 100.00 0.20 - - 1.00 100.00 0.20
1.3 Penyiapan formulir
TOTAL PENYIAPAN RKK 2,000,000.00 0.20 0.20 - 0.20
2. SOSIALISASI, PROMOSI DAN PELATIHAN
2.1 Induksi K3 (Safety Induction) Org 5.00 7,500.00 37,500.00 0.00 0.50 10.00 0.00 - - 0.50 10.00 0.00
2.2 Pengarahan K3 (Safety Briefing) Org 5.00 15,000.00 75,000.00 0.01 5.00 100.00 0.01 - - 5.00 100.00 0.01
2.3 Pelatihan K3 - -
2.3.1 Bekerja di ketinggian Org 4.00 7,500.00 30,000.00 0.00 4.00 100.00 0.00 - - 4.00 100.00 0.00
2.3.2 Penggunaan Bahan Kimia (MSDS) Org 2.00 7,500.00 15,000.00 0.00 2.00 100.00 0.00 - - 2.00 100.00 0.00
2.4 Simulasi K3 Org 5.00 7,500.00 37,500.00 0.00 5.00 100.00 0.00 - - 5.00 100.00 0.00
2.5 Spanduk (Banner) Lb 1.00 150,000.00 150,000.00 0.02 1.00 100.00 0.02 - - 1.00 100.00 0.02
2.6 Poster 2 2.00 50,000.00 100,000.00 0.01 2.00 100.00 0.01 - - 2.00 100.00 0.01
2.7 Papan Informasi K3 1 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
TOTAL SOSIALISASI, PROMOSI DAN PELATIHAN 945,000.00 0.10 0.09 - 0.09
3. ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI
3.1 APK
3.1.1 Tali Keselamatan (Life Line) Ls 1.00 1,700,000.00 1,700,000.00 0.17 1.00 100.00 0.17 - - 1.00 100.00 0.17
3.1.2 Pembatas Area (Restricted Area) Ls 1.00 2,000,000.00 2,000,000.00 0.20 1.00 100.00 0.20 - - 1.00 100.00 0.20
3.2 APD -
3.2.1 Topi Pelindung (Safety Helmet) Bh 10.00 75,000.00 750,000.00 0.08 10.00 100.00 0.08 - - 10.00 100.00 0.08
3.2.2 Pelindung Mata (Googles, Spectacles) Bh 5.00 25,000.00 125,000.00 0.01 5.00 100.00 0.01 - - 5.00 100.00 0.01
3.2.3 Pelindung Pernapasan dan Mulut (Masker) Bh 100.00 5,000.00 500,000.00 0.05 100.00 100.00 0.05 - - 100.00 100.00 0.05
3.2.4 Sarung Tangan (Safety Gloves) Psg 10.00 15,000.00 150,000.00 0.02 10.00 100.00 0.02 - - 10.00 100.00 0.02
3.2.5 Sepatu Keselamatan (Safety Shoes) Psg 10.00 350,000.00 3,500,000.00 0.35 10.00 100.00 0.35 - - 10.00 100.00 0.35
3.2.6 Penunjang Seluruh Tubuh (Full Body Harness) Bh 2.00 500,000.00 1,000,000.00 0.10 2.00 100.00 0.10 - - 2.00 100.00 0.10
3.2.7 Rompi Keselamatan (Safety Vest) Bh 10.00 25,000.00 250,000.00 0.03 10.00 100.00 0.03 - - 10.00 100.00 0.03
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 9,975,000.00 1.01 1.01 - 1.01
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4. ASURANSI DAN PERIZINAN
4.1 Asuransi Ls 1.00 3,000,000.00 3,000,000.00 0.30 1.00 100.00 0.30 - - 1.00 100.00 0.30
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 3,000,000.00 0.30 0.30 - 0.30
5. PERSONEL K3 KONSTRUKSI
5.1 Ahli K3 Konstruksi -
5.2 Petugas K3 Konstruksi Ob 4.00 3,675,000.00 14,700,000.00 1.48 4.00 100.00 1.48 - - 4.00 100.00 1.48
TOTAL PERSONEL K3 KONSTRUKSI 14,700,000.00 1.48 1.48 - 1.48
6. FASILITAS, SARANA DAN PRASARANA KESEHATAN
6.1 Peralatan P3K (Kotak P3K, Tandu, Obat Luka, Perban, dll) Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
TOTAL FASILITAS, SARANA DAN PRASARANA KESEHATAN 500,000.00 0.05 0.05 - 0.05
7. RAMBU - RAMBU YANG DIPERLUKAN
7.1 Rambu Petunjuk bh 2.00 75,000.00 150,000.00 0.02 2.00 100.00 0.02 - - 2.00 100.00 0.02
7.2 Rambu Larangan bh 2.00 75,000.00 150,000.00 0.02 2.00 100.00 0.02 - - 2.00 100.00 0.02
7.3 Rambu Peringatan bh 2.00 100,000.00 200,000.00 0.02 2.00 100.00 0.02 - - 2.00 100.00 0.02
7.4 Jalur Evakuasi (Escape Route) Ls 1.00 250,000.00 250,000.00 0.03 1.00 100.00 0.03 - - 1.00 100.00 0.03
TOTAL RAMBU - RAMBU YANG DIPERLUKAN 750,000.00 0.08 0.08 - 0.08
8. KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI
8.1 Ahli K3 Konstruksi Oj -
TOTAL KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI - 0.00
9. LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN
KONSTRUKSI
9.1 Alat Pemadam Api Ringan (APAR) bh 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
9.2 Program Inspeksi Ls 1.00 1,500,000.00 1,500,000.00 0.15 1.00 100.00 0.15 - - 1.00 100.00 0.15
9.3 Pelaporan dan Penyeledikan Insiden Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
9.4 Pembuatan Kartu Identitas Pekerja (KIP) Org 10.00 5,000.00 50,000.00 0.01 10.00 100.00 0.01 - - 10.00 100.00 0.01
TOTAL LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN KONSTRUKSI 2,550,000.00 0.26 0.26 - 0.26

A Jumlah Harga Penawaran 989,944,870.91 100.00 62.52 8.97 71.49


B PPN (10%) 98,994,487.09
C Jumlah (A+B) 1,088,939,358.00
PERSENTASE SAMPAI MINGGU INI 71.49
D Jumlah Dibulatkan 1,088,939,358.00

Bulukumba, 10 Desember 2020


Disetujui, Diketahui, Diperiksa Oleh, Dibuat Oleh,
Pejabat Pembuat Komitmen Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUTR Prov SulSel Dinas PUTR Prov SulSel CV.MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

A.KHADAFI HARUN, ST.,MT. L I L I, ST. IRHAM HARAHAP, ST. VIKA APRILIA DWI PUTRI
NIP. 19811126 200901 1 008 NIP. 19821229 201503 2 001 Site Engineer Direktris
LAPORAN KEMAJUAN MINGGUAN

Kegiatan : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba Minggu Ke : 09 ( Sembilan )
Satuan Kerja : Dinas Pekerjaan Umum Dan Tata Ruang Prov. Sulawesi Selatan Bidang Cipta Karya Periode : 11 Desember S/d 14 Desember 2020
Lokasi : Desa Ara, Kecamatan Bonto Bahari, Kabupaten Bulukumba, Provinsi Sulawesi Selatan No. Kontrak : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
Sumber Dana : Dana Bantuan Provinsi Nilai Kontrak : Rp. 1,088,939,358.00
Tahun Anggaran : 2020 Schedule Pelaksanaan : 16 Oktober S/d 14 Desember 2020

MINGGU LALU MINGGU INI S/D MINGGU INI


VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
NO URAIAN PEKERJAAN
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q

A. PEMBANGUNAN RUANG KULINER, SUVENIR, MUSHOLLAH DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Papan Proyek Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
1.2 Bedeng/Direksi Keet M2 5.50 1,512,555.00 8,319,052.50 0.84 5.50 100.00 0.84 - - 5.50 100.00 0.84

TOTAL PEKERJAAN PERSIAPAN 8,819,052.50 0.89 0.89 0.00 0.89

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Poerplat PP1 (Selasar Samping)
2.1.1.1 Galian Pondasi Poerplat < 1 m M3 0.32 73,837.50 23,628.00 0.00 0.32 100.00 0.00 - - 0.32 100.00 0.00
2.1.1.2 Urugan Pasir dibawah Pondasi Poerplat T.5 cm M3 0.04 148,335.00 5,933.40 0.00 0.04 100.00 0.00 - - 0.04 100.00 0.00
2.1.1.3 Urugan Tanah Kembali Pondasi Poerplat M3 0.31 54,175.00 16,794.25 0.00 0.31 100.00 0.00 - - 0.31 100.00 0.00
2.1.1.4 Pasangan Lantai Kerja bawah Pondasi Poerplat T.5 cm (Beton K300) M3 0.04 1,118,216.00 44,728.64 0.00 0.04 100.00 0.00 - - 0.04 100.00 0.00
2.1.1.5 Pondasi Poerplat 35x50 cm, T.20 cm - -
Beton Mutu F'c = 26,4 mpa (K300), Slump (12-2) cm, w/c = 0,52 M3 0.14 1,118,216.00 156,550.24 0.02 0.14 100.00 0.02 - - 0.14 100.00 0.02
Bekisting 2x Pakai M2 0.56 107,013.50 59,927.56 0.01 0.56 100.00 0.01 - - 0.56 100.00 0.01
Besi Beton Ø14 SNI Kg 29.40 21,464.85 631,066.59 0.06 29.40 100.00 0.06 - - 29.40 100.00 0.06
2.1.2 Pekerjaan Pondasi Batu Kali (Badan Bangunan, Mushollah) - -
2.1.2.1 Galian Tanah Pondasi Batu Kali < 1 m M3 22.73 73,837.50 1,678,326.38 0.17 22.73 100.00 0.17 - - 22.73 100.00 0.17
2.1.2.2 Urugan Pasir dibawah Pondasi Batu Kali T.5 cm M3 1.08 148,335.00 160,201.80 0.02 1.08 100.00 0.02 - - 1.08 100.00 0.02
2.1.2.3 Pasangan Aanstamping bawah Pondasi Batu Kali T.10 M3 2.17 382,674.00 830,402.58 0.08 2.17 100.00 0.08 - - 2.17 100.00 0.08
2.1.2.4 Urugan Tanah Kembali Pondasi Batu Kali M3 10.39 54,175.00 562,878.25 0.06 10.39 100.00 0.06 - - 10.39 100.00 0.06
2.1.2.5 Pondasi Batu Kali 1 Sp : 3 Pp M3 9.09 827,447.50 7,521,497.78 0.76 9.09 100.00 0.76 - - 9.09 100.00 0.76
2.1.3 Pekerjaan Pondasi Rollage L.15 cm (Entrance, Selasar Samping) - - -
2.1.3.1 Galian Tanah Pondasi Rollage < 1 m M3 2.23 73,837.50 164,657.63 0.02 2.23 100.00 0.02 - - 2.23 100.00 0.02
2.1.3.2 Urugan Pasir dibawah Pondasi Rollage T.5 cm M3 0.45 148,335.00 66,750.75 0.01 0.45 100.00 0.01 - - 0.45 100.00 0.01
2.1.3.3 Pasangan Lantai Kerja bawah Pondasi Rollage T.5 cm (Beton K300) M3 0.45 1,118,216.00 499,003.89 0.05 0.45 100.00 0.05 - - 0.45 100.00 0.05
2.1.3.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp M2 20.83 128,436.00 2,675,321.88 0.27 20.83 100.00 0.27 - - 20.83 100.00 0.27
2.2 Pekerjaan Sloef, Kolom dan Ringbalk - -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Mushollah) - -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 1.62 1,118,216.00 1,815,703.23 0.18 1.62 100.00 0.18 - - 1.62 100.00 0.18
2.2.1.2 Bekisting 2x Pakai M2 10.83 114,438.50 1,239,368.96 0.13 10.83 100.00 0.13 - - 10.83 100.00 0.13
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI Kg 280.09 21,464.85 6,012,089.84 0.61 280.09 100.00 0.61 - - 280.09 100.00 0.61
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan, Mushollah) - -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.88 1,118,216.00 981,234.54 0.10 0.88 100.00 0.10 - - 0.88 100.00 0.10
2.2.2.2 Bekisting 2x Pakai M2 5.85 193,468.00 1,131,787.80 0.11 5.85 100.00 0.11 - - 5.85 100.00 0.11
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 181.66 21,464.85 3,899,347.58 0.39 181.66 100.00 0.39 - - 181.66 100.00 0.39
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Selasar, Westafel, Tempat Wudhu) -
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 0.34 100.00 0.03 - - 0.34 100.00 0.03
2.2.3.2 Bekisting 2x Pakai M2 2.26 193,468.00 437,237.68 0.04 2.26 100.00 0.04 - - 2.26 100.00 0.04
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 70.10 21,464.85 1,504,686.30 0.15 70.10 100.00 0.15 - - 70.10 100.00 0.15
2.2.4 Pekerjaan Kolom K1 15 x 30 (Selasar Samping) -
2.2.4.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.62 1,118,216.00 694,412.14 0.07 0.62 100.00 0.07 - - 0.62 100.00 0.07
2.2.4.2 Bekisting 2x Pakai M2 6.21 193,468.00 1,201,436.28 0.12 6.21 100.00 0.12 - - 6.21 100.00 0.12
2.2.4.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 99.69 21,464.85 2,139,830.90 0.22 99.69 100.00 0.22 - - 99.69 100.00 0.22
2.2.5 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan, Mushollah) -
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 2.08 1,008,161.00 2,097,478.96 0.21 2.08 100.00 0.21 - - 2.08 100.00 0.21
2.2.5.2 Bekisting 2x Pakai M2 13.87 197,923.00 2,745,192.01 0.28 13.87 100.00 0.28 - - 13.87 100.00 0.28
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 299.22 21,464.85 6,422,712.42 0.65 299.22 100.00 0.65 - - 299.22 100.00 0.65
2.2.6 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan) -
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 0.34 100.00 0.03 - - 0.34 100.00 0.03
2.2.6.2 Bekisting 2x Pakai M2 2.24 197,923.00 443,347.52 0.04 2.24 100.00 0.04 - - 2.24 100.00 0.04
2.2.6.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 48.32 21,464.85 1,037,181.55 0.10 48.32 100.00 0.10 - - 48.32 100.00 0.10
2.2.7 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Mushollah, Pintu Jendela) -
2.2.7.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.84 1,008,161.00 846,855.24 0.09 0.84 100.00 0.09 - - 0.84 100.00 0.09
2.2.7.2 Bekisting 2x Pakai M2 5.59 197,923.00 1,106,389.57 0.11 5.59 100.00 0.11 - - 5.59 100.00 0.11
2.2.7.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 115.53 21,464.85 2,479,834.12 0.25 115.53 100.00 0.25 - - 115.53 100.00 0.25
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.2.8 Pekerjaan Plat Beton (Selasar Samping, Westafel) -
2.2.8.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.22 1,008,161.00 221,795.42 0.02 0.22 100.00 0.02 - - 0.22 100.00 0.02
2.2.8.2 Bekisting 2x Pakai M2 2.21 237,468.00 524,804.28 0.05 2.21 100.00 0.05 - - 2.21 100.00 0.05
2.2.8.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 54.54 21,464.85 1,170,692.92 0.12 54.54 100.00 0.12 - - 54.54 100.00 0.12
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) M2 152.03 163,636.00 24,877,581.08 2.51 152.03 100.00 2.51 - - 152.03 100.00 2.51
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4, Entrance) M2 42.24 242,170.50 10,229,281.92 1.03 42.24 100.00 1.03 - - 42.24 100.00 1.03
2.5 Pekerjaan Tiang Atap Bitumen Gelombang (Besi Hollow Galvanis 5/10, Entrance) M' 20.40 178,365.00 3,638,646.00 0.37 20.40 100.00 0.37 - - 20.40 100.00 0.37
2.6 Pekerjaan Rangka Plafond Kalsiboard (Besi Hollow Metal Galvalume 4/4) M2 147.40 102,837.17 15,158,198.37 1.53 147.40 100.00 1.53 - - 147.40 100.00 1.53

TOTAL PEKERJAAN STRUKTUR 109,840,345.70 11.10 11.10 0.00 11.10

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) M3 8.54 148,335.00 1,266,780.90 0.13 8.54 100.00 0.13 - - 8.54 100.00 0.13
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) M3 25.63 167,227.00 4,285,636.74 0.43 25.63 100.00 0.43 - - 25.63 100.00 0.43
3.1.1.3 Rabat Beton bawah Lantai T.5 cm (Keseluruhan, Beton K300) M3 8.54 1,118,216.00 9,549,564.64 0.96 8.54 100.00 0.96 - - 8.54 100.00 0.96
3.1.1.4 Penutup Lantai Keramik Motif 60x60 (Badan Bangunan, Mushollah) M2 62.94 403,309.50 25,384,299.93 2.56 59.79 95.00 2.44 - - 59.79 95.00 2.44
3.1.1.5 Penutup Lantai Conwood Deck 6" (Entrance) M2 59.01 866,833.08 51,151,820.09 5.17 56.01 94.92 4.90 - - 56.01 94.92 4.90
3.1.1.6 Penutup Lantai Andesit Polos 30x30 (Selasar, Tempat Wudhu, Ram) M2 51.05 232,589.50 11,873,693.98 1.20 51.05 100.00 1.20 - - 51.05 100.00 1.20
3.1.1.7 Plint Lantai Keramik 10x60 (Badan Bangunan, Mushollah) M' 38.85 51,605.03 2,004,855.55 0.20 - - - - - - - -
3.1.2 Pekerjaan Dinding -
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Mushollah, 1 Sp : 4 Pp) M2 74.55 242,979.00 18,114,084.45 1.83 74.55 100.00 1.83 - - 74.55 100.00 1.83
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Selasar Samping, Tempat Wudhu) M2 5.14 65,550.32 336,928.64 0.03 5.14 100.00 0.03 - - 5.14 100.00 0.03
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm (Badan Bangunan, Mushollah) M2 91.30 60,403.20 5,514,812.16 0.56 91.30 100.00 0.56 - - 91.30 100.00 0.56
3.1.2.4 Plesteran Ciprat 1 Sp : 2 Pp Tebal 15 mm (Selasar Samping, Antar Kolom) M2 24.84 49,215.10 1,222,503.08 0.12 24.84 100.00 0.12 - - 24.84 100.00 0.12
3.1.2.5 Dinding Keramik Mozaik 30x60 (Selasar Samping, Westafel, Tempat Wudhu) M2 18.44 410,432.00 7,568,366.08 0.76 18.44 100.00 0.76 - - 18.44 100.00 0.76
3.1.2.6 Coating Bening (Badan Bangunan, Mushollah, Kolom Luar) M2 127.49 45,973.13 5,861,113.71 0.59 - - - - - - - -
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) M2 8.64 995,043.50 8,597,175.84 0.87 8.64 100.00 0.87 - - 8.64 100.00 0.87
3.1.2.8 Dinding Wallpaper Bata L.50 cm (Sisi Dalam) M2 28.13 80,005.50 2,250,554.72 0.23 - - - - - - - -
3.1.3 Pekerjaan Plafond -
3.1.3.1 Plafond Kalsiboard (Badan Bangunan, Kemiringan Atap, Mushollah) M2 147.40 44,924.00 6,621,797.60 0.67 147.40 100.00 0.67 - - 147.40 100.00 0.67
3.1.3.2 Plafond Kalsiboard (Lapis Bawah Atap, Entrance) M2 42.24 44,924.00 1,897,589.76 0.19 42.24 100.00 0.19 - - 42.24 100.00 0.19
3.2 Pekerjaan Pintu dan Jendela (Badan Bangunan) -
3.2.1 Pintu P1 (Entrance dan Back Entrance, Badan Bangunan) -
3.2.1.1 Pasangan Kusen Alumunium Coating P1 (4" x 1 3/4") cm M' 22.40 157,194.40 3,521,154.56 0.36 22.40 100.00 0.36 - - 22.40 100.00 0.36
3.2.1.2 Pasangan Daun Pintu P1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - - -
3.2.1.3 Pasangan Kaca Mati 5 mm P1 M2 11.20 145,703.80 1,631,882.56 0.16 - - - - - - - -
3.2.1.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - - -
3.2.1.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - - -
3.2.1.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - - -
3.2.1.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - - -
3.2.2 Jendela J1 (Badan Bangunan) -
3.2.2.1 Pasangan Kusen Alumunium Coating J1 (4" x 1 3/4") cm M' 40.60 157,194.40 6,382,092.64 0.64 40.60 100.00 0.64 - - 40.60 100.00 0.64
3.2.2.2 Pasangan Kaca Mati 5 mm J1 M2 8.00 145,703.80 1,165,630.40 0.12 - - - - - - - -
3.2.3 Pintu PJ1 (Mushollah) -
3.2.3.1 Pasangan Kusen Alumunium Coating PJ1 (4" x 1 3/4") cm M' 22.20 157,194.40 3,489,715.68 0.35 22.20 100.00 0.35 - - 22.20 100.00 0.35
3.2.3.2 Pasangan Daun Pintu PJ1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - - -
3.2.3.3 Pasangan Kaca Mati 5 mm P1 M2 8.70 145,703.80 1,267,623.06 0.13 - - - - - - - -
3.2.3.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - - -
3.2.3.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - - -
3.2.3.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - - -
3.2.3.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - - -
3.3 Pekerjaan Pengecatan -
3.3.1 Pengecatan Plafond (1 Plamir ; 1 Cat Dasar : 2 Cat Penutup), (Interior) M2 189.64 35,536.05 6,739,056.52 0.68 189.64 100.00 0.68 - - 189.64 100.00 0.68
3.3.2 Pengecatan Rangka Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 23.76 168,454.00 4,002,467.04 0.40 23.76 100.00 0.40 - - 23.76 100.00 0.40
3.3.3 Pengecatan Tiang Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 6.12 168,454.00 1,030,938.48 0.10 6.12 100.00 0.10 - - 6.12 100.00 0.10
3.4 Pekerjaan Atap -
3.4.1 Atap Bitumen Gelombang (Badan Bangunan, Mushollah) M2 152.03 207,297.09 31,515,376.59 3.18 152.03 100.00 3.18 - - 152.03 100.00 3.18
3.4.2 Atap Bitumen Gelombang (Entrance) M2 42.24 207,297.09 8,756,229.08 0.88 42.24 100.00 0.88 - - 42.24 100.00 0.88
3.4.3 Nok Bitumen (Badan Bangunan, Mushollah) M' 14.55 134,101.00 1,951,169.55 0.20 14.55 100.00 0.20 - - 14.55 100.00 0.20
3.4.4 Listplank (Kalsiplank, Badan Bangunan, Mushollah, Entrance) M' 50.00 70,950.00 3,547,500.00 0.36 50.00 100.00 0.36 - - 50.00 100.00 0.36

TOTAL PEKERJAAN FINISHING ARSITEKTUR 257,222,142.77 25.98 22.27 0.00 22.27

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel Bh 1.00 1,572,826.75 1,572,826.75 0.16 - - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt Bh 16.00 353,938.75 5,663,020.00 0.57 16.00 100.00 0.57 - - 16.00 100.00 0.57
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4.1.3 Pasangan Lampu Down Light 2,5" Outbow LED 5,5 Watt Bh 11.00 305,538.75 3,360,926.25 0.34 11.00 100.00 0.34 - - 11.00 100.00 0.34
4.1.4 Pasangan Saklar Tunggal Bh 4.00 211,378.75 845,515.00 0.09 4.00 100.00 0.09 - - 4.00 100.00 0.09
4.1.5 Pasangan Saklar Ganda Bh 2.00 223,478.75 446,957.50 0.05 2.00 100.00 0.05 - - 2.00 100.00 0.05
4.2 Pasangan Instalasi Stop Kontak - -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA Bh 10.00 216,218.75 2,162,187.50 0.22 10.00 100.00 0.22 - - 10.00 100.00 0.22
4.2.2 Pasangan Stop Kontak AC 220 VA/3520 W (AC Split 1 PK) Bh 4.00 253,728.75 1,014,915.00 0.10 4.00 100.00 0.10 - - 4.00 100.00 0.10
4.3 Pasangan Instalasi Jaringan AC M' 30.00 108,772.68 3,263,180.25 0.33 30.00 100.00 0.33 - - 30.00 100.00 0.33
4.3.1 Pasangan AC Split 1 PK Bh 3.00 3,365,799.34 10,097,398.03 1.02 1.50 50.00 0.51 - - 1.50 50.00 0.51
4.4 Pasangan Penangkal Petir Ls 1.00 2,500,000.00 2,500,000.00 0.25 1.00 100.00 0.25 - - 1.00 100.00 0.25
4.5 Pasangan Instalasi Jaringan Kabel Fiber Optic (CCTV) Ttk 6.00 786,326.75 4,717,960.50 0.48 - - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2MP Bh 6.00 656,975.00 3,941,850.00 0.40 - - - - - - - -
4.5.2 Pasangan NVR Channel Set 1.00 5,023,975.00 5,023,975.00 0.51 - - - - - - - -
4.5.3 Pasangan Monitor LCD 32" Bh 1.00 2,944,975.00 2,944,975.00 0.30 - - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm M' 12.00 20,442.68 245,312.10 0.02 - - - - - - - -
4.6.1 Pasangan Horn Speaker Bh 6.00 494,826.75 2,968,960.50 0.30 - - - - - - - -
4.6.2 Pasangan Volume Kontrol Set 1.00 252,826.75 252,826.75 0.03 - - - - - - - -
4.6.3 Pasangan Perangkat Sound System Set 1.00 4,565,000.00 4,565,000.00 0.46 - - - - - - - -
4.6.4 Pasangan TB-Sound System Set 1.00 5,846,326.75 5,846,326.75 0.59 - - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25Kg) Ttk 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - - -
4.8 Pasangan Instalasi Jaringan Kabel Fiber Optic (Akses Point) Ttk 3.00 786,326.75 2,358,980.25 0.24 - - - - - - - -
4.8.1 Pasangan Server Set 1.00 7,578,826.75 7,578,826.75 0.77 - - - - - - - -
4.8.2 Pasangan Akses Point Bh 1.00 2,034,826.75 2,034,826.75 0.21 - - - - - - - -
4.8.3 Pasangan Switch HUB Bh 1.00 2,843,326.75 2,843,326.75 0.29 - - - - - - - -
4.9 Pasangan Instalasi PLN Power (Inc. Jalur ke Mushollah dan Toilet) Ls 1.00 9,000,000.00 9,000,000.00 0.91 - - - - - - - -

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 94,450,073.38 9.54 2.46 0.00 2.46

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVC Type AW Diameter 3/4" (Air Bersih Sambungan dari Tandon) M' 33.00 28,300.25 933,908.25 0.09 16.50 50.00 0.05 - - 16.50 50.00 0.05
5.2 Pipa PVC Type AW Diameter 3" (Air Kotor ke Drainase Lingkungan) M' 25.80 135,531.00 3,496,699.80 0.35 2.58 10.00 0.04 - - 2.58 10.00 0.04
5.3 Pasangan 1 Bh Wastafel Bh 2.00 3,934,865.00 7,869,730.00 0.79 - - - 2.00 100.00 0.79 2.00 100.00 0.79
5.4 Pasangan 1 Bh Wastafel Cuci Piring (WCP) Bh 1.00 890,945.00 890,945.00 0.09 - - - 1.00 100.00 0.09 1.00 100.00 0.09
5.5 Pasangan 1 Bh Floor Drain Bh 2.00 41,112.50 82,225.00 0.01 - - - 2.00 100.00 0.01 2.00 100.00 0.01
5.6 Pasangan 1 Bh Kran Dia. 1/2" atau 3/4" Bh 10.00 102,217.50 1,022,175.00 0.10 - - - 10.00 100.00 0.10 10.00 100.00 0.10
5.7 Pasangan 1 Bh Kran Wastafel Dia. 1/2" atau 3/4" Bh 3.00 335,417.50 1,006,252.50 0.10 - - - 3.00 100.00 0.10 3.00 100.00 0.10
5.8 Pasangan 1 Bh Stop Kran (Gate Valve) Dia. 3/4" Bh 1.00 141,417.50 141,417.50 0.01 - - - 0.10 10.00 0.00 0.10 10.00 0.00
5.9 Pasangan Mesin Air Bh 1.00 741,000.00 741,000.00 0.07 - - - - - - - -
5.10 Menara Reservoir 200x150x350 cm -
5.10.1 Pekerjaan Pondasi Pedestal Pd1 -
5.10.1.1 Galian Tanah Pondasi Poerplat < 1 m M3 1.62 73,837.50 119,616.75 0.01 - - - - - - - -
5.10.1.2 Urugan Tanah Kembali Pondasi Poerplat M3 0.43 54,175.00 23,295.25 0.00 - - - - - - - -
5.10.1.3 Tiang Pondasi Pedestal 50x50 cm - - -
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.80 1,118,216.00 894,572.80 0.09 - - - - - - - -
Bekisting 2x Pakai M2 3.20 193,468.00 619,097.60 0.06 - - - - - - - -
Besi Beton Ø12 SNI, Ø8 SNI Kg 49.44 21,464.85 1,061,130.60 0.11 - - - - - - - -
5.10.1.4 Pondasi Poerplat 90x90 cm, T.20 cm -
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.65 1,118,216.00 726,840.40 0.07 - - - - - - - -
Bekisting 2x Pakai M2 1.44 107,013.50 154,099.44 0.02 - - - - - - - -
Besi Beton Ø14 SNI Kg 214.35 21,464.85 4,600,940.54 0.46 - - - - - - - -
5.10.2 Rangka Tengah dan Lantai Menara (Besi Hollow Galvanis 4/4) M2 34.82 244,970.00 8,529,855.40 0.86 - - - 27.86 80.00 0.69 27.86 80.00 0.69
5.10.3 Rangka Utama Menara (Besi Hollow Galvanis 5/10) M' 32.28 179,454.00 5,792,775.12 0.59 - - - 25.82 80.00 0.47 25.82 80.00 0.47
5.10.4 Plat Baja Lantai Menara T.3 mm M2 3.00 740,164.86 2,220,494.57 0.22 - - - - - - - -
5.10.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) M2 5.00 244,970.00 1,224,850.00 0.12 - - - 4.00 80.00 0.10 4.00 80.00 0.10

TOTAL PEKERJAAN PLAMBING DAN SANITASI 42,151,921.52 4.26 0.08 2.36 2.44

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Pek. Pembersian Awal m2 81.86 17,600.00 1,440,780.00 0.15 81.86 100.00 0.15 - - 81.86 100.00 0.15
1.2 Pek. Pengukuran & Pemasangan Bouwplank m1 48.60 106,461.25 5,174,016.75 0.52 48.60 100.00 0.52 - - 48.60 100.00 0.52

TOTAL PEKERJAAN PERSIAPAN 6,614,796.75 0.67 0.67 0.00 0.67

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Batu Kali (Badan Bangunan,Ruang Bilas)
2.1.1.1 Galian Pondasi Batu Kali < 1 m m3 22.05 73,892.50 1,629,329.63 0.16 6.62 30.00 0.05 - - 6.62 30.00 0.05
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.1.1.2 Urugan Pasir Dibawah Pondasi Batu Kali T.5 cm m3 1.05 174,757.00 183,494.85 0.02 1.05 100.00 0.02 - - 1.05 100.00 0.02
2.1.1.3 Pasangan Aanstamping Bawah Pondasi Batu Kali T.10 cm m3 2.10 392,699.70 824,669.37 0.08 2.10 100.00 0.08 - - 2.10 100.00 0.08
2.1.1.4 Urugan Tanah Kembali Pondasi Batu Kali m3 10.08 54,285.00 547,192.80 0.06 3.02 30.00 0.02 - - 3.02 30.00 0.02
2.1.1.5 Pondasi Batu Kali 1 Sp : 3 Pp m3 8.82 824,945.00 7,276,014.90 0.73 8.82 100.00 0.73 - - 8.82 100.00 0.73
2.1.2 Perjaan Pondasi Rollage L.15 cm (Selasar) -
2.1.2.1 Galian Tanah Pondasi Rollage < 1 m m3 1.52 73,892.50 112,501.33 0.01 0.15 10.00 0.00 - - 0.15 10.00 0.00
2.1.2.2 Urugan Pasir Dibawah Pondasi Rollage T.5 cm m3 0.30 174,757.00 53,213.51 0.01 0.03 10.00 0.00 - - 0.03 10.00 0.00
2.1.2.3 Pasangan Lantai Kerja Bawah Pondasi Rollage T.5 cm (Beton K300) m3 0.30 1,118,398.60 340,552.37 0.03 0.30 100.00 0.03 - - 0.30 100.00 0.03
2.1.2.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp m3 14.21 128,260.00 1,822,574.60 0.18 14.21 100.00 0.18 - - 14.21 100.00 0.18
2.2 Pekerjaan Sloef, Kolom, Plat dan Ringbalk - -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Ruang Bilas) - -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 m3 1.41 1,118,398.60 1,580,297.22 0.16 1.41 100.00 0.16 - - 1.41 100.00 0.16
2.2.1.2 Bekisting 2x Pakai m2 9.42 114,467.10 1,078,280.08 0.11 9.42 100.00 0.11 - - 9.42 100.00 0.11
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI kg 243.74 21,465.73 5,232,043.29 0.53 243.74 100.00 0.53 - - 243.74 100.00 0.53
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan) - -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slum (12 - 2) cm, w/c = 0,52 m3 0.48 1,118,398.60 533,476.13 0.05 0.48 100.00 0.05 - - 0.48 100.00 0.05
2.2.2.2 Bekisting 2x Pakai m2 3.18 193,504.30 615,343.67 0.06 3.18 100.00 0.06 - - 3.18 100.00 0.06
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI kg 98.75 21,465.73 2,119,732.25 0.21 98.75 100.00 0.21 - - 98.75 100.00 0.21
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Ruang Bilas) - -
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.25 1,008,343.60 249,111.29 0.03 0.25 100.00 0.03 - - 0.25 100.00 0.03
2.2.3.2 Bekisting 2x Pakai m2 1.65 193,504.30 318,701.58 0.03 1.65 100.00 0.03 - - 1.65 100.00 0.03
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI kg 51.14 21,465.73 1,097,861.33 0.11 51.14 100.00 0.11 - - 51.14 100.00 0.11
2.2.4 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan) - -
2.2.4.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.04 1,008,343.60 1,043,635.63 0.11 1.04 100.00 0.11 - - 1.04 100.00 0.11
2.2.4.2 Bekisting 2x Pakai m2 6.90 197,959.30 1,365,919.17 0.14 6.90 100.00 0.14 - - 6.90 100.00 0.14
2.2.4.3 Besi Beton Ø12 SNI, Ø6 SNI kg 148.86 21,465.73 3,195,302.68 0.32 148.86 100.00 0.32 - - 148.86 100.00 0.32
2.2.5 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan) - -
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.09 1,008,343.60 1,103,531.24 0.11 1.09 100.00 0.11 - - 1.09 100.00 0.11
2.2.5.2 Bekisting 2x Pakai m2 14.59 197,959.30 2,888,622.11 0.29 14.59 100.00 0.29 - - 14.59 100.00 0.29
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI kg 157.40 21,465.73 3,378,705.12 0.34 157.40 100.00 0.34 - - 157.40 100.00 0.34
2.2.6 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Pintu Jendela) -
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.15 1,008,343.60 148,831.52 0.02 0.15 100.00 0.02 - - 0.15 100.00 0.02
2.2.6.2 Bekisting 2x Pakai m2 0.98 197,959.30 194,791.95 0.02 0.98 100.00 0.02 - - 0.98 100.00 0.02
2.2.6.3 Besi Beton Ø10 SNI, Ø6 SNI kg 20.35 21,465.73 436,752.39 0.04 20.35 100.00 0.04 - - 20.35 100.00 0.04
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) m2 59.01 163,856.00 9,669,142.56 0.98 59.01 100.00 0.98 - - 59.01 100.00 0.98
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4) m2 48.59 102,876.77 4,998,782.09 0.50 48.59 100.00 0.50 - - 48.59 100.00 0.50
2.5 Pekerjaan Rangka Plafond dan Dinding Dalam PVC Shunda (Besi Hollow Metal Galvalume 4/4) m2 56.16 102,876.77 5,777,559.22 0.58 - - - 56.16 100.00 0.58 56.16 100.00 0.58

TOTAL PEKERJAAN STRUKTUR 59,815,965.86 6.04 5.29 0.58 5.87

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) m3 4.09 174,757.00 715,280.40 0.07 4.09 100.00 0.07 - - 4.09 100.00 0.07
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) m3 12.28 167,345.00 2,054,804.70 0.21 12.28 100.00 0.21 - - 12.28 100.00 0.21
3.1.1.3 Rabat Beton T.5 cm (Keseluruhan, Beton K300) m3 4.09 1,118,398.60 4,577,605.47 0.46 4.09 100.00 0.46 - - 4.09 100.00 0.46
3.1.1.4 Penutup Lantai Keramik Tekstur 60x60 (Badan Bangunan) m2 36.93 413,098.40 15,255,723.91 1.54 36.93 100.00 1.54 - - 36.93 100.00 1.54
3.1.1.5 Penutup Lantai Andesit Polos 30x30 (Selasar, Ruang Bilas) m2 45.89 284,369.80 13,049,730.12 1.32 45.89 100.00 1.32 - - 45.89 100.00 1.32
3.1.1.6 Penutup Plat Wastafel (Granit 60x60, Toilet Pria dan Wanita) m2 2.20 841,621.73 1,851,567.81 0.19 - - - 2.20 100.00 0.19 2.20 100.00 0.19
3.1.2 Pekerjaan Dinding - -
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Selasar, 1 Sp : 4 Pp) 90.64 242,533.50 21,983,236.44 2.22 90.64 100.00 2.22 - - 90.64 100.00 2.22
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Wc ) 30.00 65,473.32 1,964,199.60 0.20 30.00 100.00 0.20 - - 30.00 100.00 0.20
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm 121.28 60,304.20 7,313,693.38 0.74 121.28 100.00 0.74 - - 121.28 100.00 0.74
3.1.2.4 Coating Bening 121.28 46,853.13 5,682,347.00 0.57 - - - - - - - -
3.1.2.5 Dinding Andesit Polos 30x30 cm ( Wc, Ruang Bilas ) 56.52 284,369.80 16,072,581.10 1.62 56.52 100.00 1.62 - - 56.52 100.00 1.62
3.1.2.6 Dinding Keramik 30x60 cm ( Sisi Dalam ) 69.88 370,557.00 25,894,523.16 2.62 69.88 100.00 2.62 - - 69.88 100.00 2.62
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) 9.00 995,076.50 8,955,688.50 0.90 9.00 100.00 0.90 - - 9.00 100.00 0.90
3.1.2.8 Cubicle Panel + Accessories (Pintu Wc dan Partisi Urinoir) 10.86 1,360,000.00 14,769,600.00 1.49 10.86 100.00 1.49 - - 10.86 100.00 1.49
3.1.2.9 Dinding Bitumen Gelombang 48.59 201,749.24 9,802,995.57 0.99 48.59 100.00 0.99 - - 48.59 100.00 0.99
3.1.2.10 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Pria) 1.00 1,200,000.00 1,200,000.00 0.12 - - - - - - - -
3.1.2.11 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Wanita) 1.00 750,000.00 750,000.00 0.08 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.1.3 Plafond dan Dinding Dalam Shunda ( Badan Bangunan ) 56.16 125,878.50 7,069,336.56 0.71 56.16 100.00 0.71 - - 56.16 100.00 0.71
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.2 Pekerjaan Pintu dan Jendela ( Badan Bangunan ) - -
3.2.1 Pintu P1 - -
3.2.1.1 Pasangan Kusen Almunium Coating P1 (4" x 13/4") cm 10.96 157,199.02 1,722,901.26 0.17 10.96 100.00 0.17 - - 10.96 100.00 0.17
3.2.1.2 Pasangan Daun Pintu P1 (Panel Almunium Coating - Coating) 4.30 870,323.19 3,742,389.72 0.38 - - - - - - - -
3.2.1.3 Pasangan Kunci Tanam 2x Slag P1 2.00 416,663.50 833,327.00 0.08 - - - - - - - -
3.2.1.4 Pasangan ensel P1 6.00 61,225.56 367,353.36 0.04 - - - - - - - -
3.2.1.5 Pasangan Doorcloser P1 2.00 241,902.10 483,804.20 0.05 - - - - - - - -
3.2.1.6 Pasangan Handle P1 2.00 229,802.10 459,604.20 0.05 - - - - - - - -
3.2.2 Jendela J1 - -
3.2.2.1 Pasangan Kusen Almunium Coating J1 (4" x 13/4") cm 28.80 157,199.02 4,527,331.78 0.46 28.80 100.00 0.46 - - 28.80 100.00 0.46
3.2.2.2 Pasangan Kaca Mati 5 mm J1 0.60 145,705.56 87,423.34 0.01 - - - - - - - -
3.2.3 Jendela J2 -
3.2.3.1 Pasangan Kusen Almunium Coating J2 (4" x 13/4") cm 55.20 157,199.02 8,677,385.90 0.88 - - - - - - - -
3.2.3.2 Pasangan Kaca Mati 5 mm J2 0.90 145,705.56 131,135.00 0.01 - - - - - - - -
3.3. Pengecetan Plafond (1 Plamir : 1 Cat Dasar : 2 Cat Penutup), (Interior) 56.16 43,550.65 2,445,804.50 0.25 - - - 56.16 100.00 0.25 56.16 100.00 0.25
3.4 Pekerjaan Atap - - -
3.4.1 Atap Bitumen Gelombang (Badan Bangunan) 59.01 201,749.24 11,905,222.65 1.20 - - - 59.01 100.00 1.20 59.01 100.00 1.20
3.4.2 Nok Bitumen (Badan Bangunan) 35.25 143,629.20 5,062,929.30 0.51 - - - 35.25 100.00 0.51 35.25 100.00 0.51
3.4.3 Listplank (Kasiplank, Badan Bangunan, Enterance) 39.08 70,972.00 2,773,585.76 0.28 - - - 39.08 100.00 0.28 39.08 100.00 0.28

TOTAL PEKERJAAN FINISHING ARSITEKTUR 202,183,111.69 20.42 15.73 2.43 18.16

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel 1.00 1,803,826.75 1,803,826.75 0.18 - - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt 10.00 353,938.75 3,539,387.50 0.36 10.00 100.00 0.36 - - 10.00 100.00 0.36
4.1.3 Pasangan Lampu Down Light 2.5" Outbow LED 5.5 Watt 12.00 305,538.75 3,666,465.00 0.37 12.00 100.00 0.37 - - 12.00 100.00 0.37
4.1.4 Pasangan Saklar Ganda 5.00 223,478.75 1,117,393.75 0.11 5.00 100.00 0.11 - - 5.00 100.00 0.11
4.2 Pasangan Instalasi Stop Kontak - -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA 3.00 216,218.75 648,656.25 0.07 3.00 100.00 0.07 - - 3.00 100.00 0.07
4.2.2 Pasangan Stop Kontak Wall Exhauser 6.00 216,218.75 1,297,312.50 0.13 6.00 100.00 0.13 - - 6.00 100.00 0.13
4.3 Pasangan Instalasi Jaringan Wall Exhauser 12.00 108,772.68 1,305,272.10 0.13 12.00 100.00 0.13 - - 12.00 100.00 0.13
4.3.1 Pasangan Wall Exhauser 12 Inch - FV30RUN 6.00 513,500.00 3,081,000.00 0.31 6.00 100.00 0.31 - - 6.00 100.00 0.31
4.4 Pasangan Penangkal Petir 1.00 3,500,000.00 3,500,000.00 0.35 0.50 50.00 0.18 - - 0.50 50.00 0.18
4.5 Pasangan Instlasi Jaringan Kabel Fiber Optic (CCTV) 3.00 786,326.75 2,358,980.25 0.24 - - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2 MP (Luar Bangunan, Sambungan Dari Mini Resto) 3.00 656,975.00 1,970,925.00 0.20 - - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm 4.00 20,442.68 81,770.70 0.01 - - - - - - - -
4.6.1 Pasangan Horn Speaker (Sambungan Dari Mini Resto) 2.00 494,826.75 989,653.50 0.10 - - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25 kg) 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - - -
4.8 Pasangan Instalasi PLN Power 1.00 10,000,000.00 10,000,000.00 1.01 - - - - - - - -

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 44,560,643.30 4.50 1.66 0.00 1.66

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVc Tipe AW Diameter 3/4" (Air Bersih Dari Sumur Bor / PDAM Reservoir) m1 18.50 28,304.65 523,636.03 0.05 - - - - - - - -
5.2 Pipa PVC Tipe AW Diameter 3/4" (Distribusi Air Bersih Dari Reservoir) m1 26.50 28,304.65 750,073.23 0.08 13.25 50.00 0.04 - - 13.25 50.00 0.04
5.3 Pipa PVC Tipe AW Diameter 3" (Air Kotor Ke Drainase Lingkungan) m1 23.00 135,539.80 3,117,415.40 0.31 23.00 100.00 0.31 - - 23.00 100.00 0.31
5.4 Pipa PVC Tipe AW Diameter 4" (Disposal) m1 18.00 186,689.80 3,360,416.40 0.34 18.00 100.00 0.34 - - 18.00 100.00 0.34
5.5 Pasangan 1 bh Closet Duduk / Monoblock (TOTO) bh 6.00 3,655,597.00 21,933,582.00 2.22 3.00 50.00 1.11 - - 3.00 50.00 1.11
5.6 Pasangan 1 bh Wastafel (TOTO) 3.00 3,571,942.00 10,715,826.00 1.08 3.00 100.00 1.08 - - 3.00 100.00 1.08
5.7 Pasangan 1 bh Uninoir (TOTO) 2.00 6,665,285.00 13,330,570.00 1.35 2.00 100.00 1.35 - - 2.00 100.00 1.35
5.8 Pasangan 1 bh Floor Drain 9.00 41,123.50 370,111.50 0.04 9.00 100.00 0.04 - - 9.00 100.00 0.04
5.9 Pasangan 1 bh Kran dia. 1/2' atau 3/4" 8.00 102,228.50 817,828.00 0.08 8.00 100.00 0.08 - - 8.00 100.00 0.08
5.10 Pasangan 1 bh Kran wastafel dia. 1/2' atau 3/4" 2.00 335,428.50 670,857.00 0.07 2.00 100.00 0.07 - - 2.00 100.00 0.07
5.11 Pasangan 1 bh shower closet dia. 1/2' atau 3/4" 6.00 142,928.50 857,571.00 0.09 6.00 100.00 0.09 - - 6.00 100.00 0.09
5.12 Pasangan 1 bh shower Wall dia. 1/2' atau 3/4" (Ruang Bilas) 4.00 1,435,428.50 5,741,714.00 0.58 4.00 100.00 0.58 - - 4.00 100.00 0.58
5.13 Pasangan 1 bh Stop Kran (Gate Valve) dia. 3/4" 2.00 141,428.50 282,857.00 0.03 2.00 100.00 0.03 - - 2.00 100.00 0.03
5.14 Pasangan Mesin Air 1.00 741,000.00 741,000.00 0.07 - - - - - - - -
5.14b Pasangan Mesin Pemanas Air 1.00 5,000,000.00 5,000,000.00 0.51 - - - - - - - -
5.15 Septictank Biotank Kap. 4m3 1.00 20,380,000.00 20,380,000.00 2.06 0.50 50.00 1.03 - - 0.50 50.00 1.03
5.16 Pasangan Sumur Bor Jet Pump 30.00 350,000.00 10,500,000.00 1.06 - - - - - - - -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.17 Reservoir 1200 Liter 1.00 1,850,000.00 1,850,000.00 0.19 1.00 100.00 0.19 - - 1.00 100.00 0.19
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.18 Reservoir 200x150x350 cm - -
5.18.1 Pekerjaan Pondasi Pedestal Pd1 - -
5.18.1.1 Galian Tanah Pondasi Poerplat < 1m 1.62 74,250.00 120,285.00 0.01 - - - - - - - -
5.18.1.2 Urugan Tanah Kembali Pondasi Poerplat 0.43 55,000.00 23,760.00 0.00 - - - - - - - -
5.18.1.3 Tiang Pondasi Pedestal 50x50 cm -
Beton Mutu fc = 26,6 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.80 1,485,144.21 1,188,115.37 0.12 - - - - - - - -
Bekisting 2x Pakai 3.20 193,504.30 619,213.76 0.06 - - - - - - - -
Besi Beton Ø12, Ø8 49.44 21,465.73 1,061,174.10 0.11 - - - - - - - -
5.18.1.4 Pondasi Poerplat 90x90 cm,T.20 cm - -
Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.65 1,485,144.21 962,373.45 0.10 - - - - - - - -
Bekisting 2x Pakai 1.44 124,547.50 179,348.40 0.02 - - - - - - - -
Besi Beton Ø14 SNI 214.35 21,465.73 4,601,114.73 0.46 - - - - - - - -
5.18.2 Rangkai Tengah Dan Lantai Menara (Besi Hollow Galvanis 4/4) 34.82 244,970.00 8,529,855.40 0.86 34.82 100.00 0.86 - - 34.82 100.00 0.86
5.18.3 Rangka Utama menara ( Besi Hollow Galvanis 5/10 32.28 179,454.00 5,792,775.12 0.59 32.28 100.00 0.59 - - 32.28 100.00 0.59
5.18.4 Tplat Baja Lantai Menara T.3mm 3.00 740,164.86 2,220,494.57 0.22 - - - - - - - -
5.18.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) 5.00 244,970.00 1,224,850.00 0.12 4.00 80.00 0.10 - - 4.00 80.00 0.10

TOTAL PEKERJAAN PLAMBING DAN SANITASI 127,466,817.45 12.88 7.87 - 7.87

6. PEKERJAAN AKHIR - - -
6.1 Pembersihan Sisa Pekerjaan Ls 1.00 2,400,000.00 2,400,000.00 0.24 - - - - - - - -

TOTAL PEKERJAAN AKHIR 2,400,000.00 0.24 0.00 0.00 0.00

C. PENERAPAN SMKK

1. PENYIAPAN RKK
1.1 Pembuatan Dokumen Rencana Keselamatan Konstruksi
1.2 Pembuatan Prosedur dan instruksi kerja Set 1.00 2,000,000.00 2,000,000.00 0.20 1.00 100.00 0.20 - - 1.00 100.00 0.20
1.3 Penyiapan formulir
TOTAL PENYIAPAN RKK 2,000,000.00 0.20 0.20 - 0.20
2. SOSIALISASI, PROMOSI DAN PELATIHAN
2.1 Induksi K3 (Safety Induction) Org 5.00 7,500.00 37,500.00 0.00 0.50 10.00 0.00 - - 0.50 10.00 0.00
2.2 Pengarahan K3 (Safety Briefing) Org 5.00 15,000.00 75,000.00 0.01 5.00 100.00 0.01 - - 5.00 100.00 0.01
2.3 Pelatihan K3 - -
2.3.1 Bekerja di ketinggian Org 4.00 7,500.00 30,000.00 0.00 4.00 100.00 0.00 - - 4.00 100.00 0.00
2.3.2 Penggunaan Bahan Kimia (MSDS) Org 2.00 7,500.00 15,000.00 0.00 2.00 100.00 0.00 - - 2.00 100.00 0.00
2.4 Simulasi K3 Org 5.00 7,500.00 37,500.00 0.00 5.00 100.00 0.00 - - 5.00 100.00 0.00
2.5 Spanduk (Banner) Lb 1.00 150,000.00 150,000.00 0.02 1.00 100.00 0.02 - - 1.00 100.00 0.02
2.6 Poster 2 2.00 50,000.00 100,000.00 0.01 2.00 100.00 0.01 - - 2.00 100.00 0.01
2.7 Papan Informasi K3 1 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
TOTAL SOSIALISASI, PROMOSI DAN PELATIHAN 945,000.00 0.10 0.09 - 0.09
3. ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI
3.1 APK
3.1.1 Tali Keselamatan (Life Line) Ls 1.00 1,700,000.00 1,700,000.00 0.17 1.00 100.00 0.17 - - 1.00 100.00 0.17
3.1.2 Pembatas Area (Restricted Area) Ls 1.00 2,000,000.00 2,000,000.00 0.20 1.00 100.00 0.20 - - 1.00 100.00 0.20
3.2 APD -
3.2.1 Topi Pelindung (Safety Helmet) Bh 10.00 75,000.00 750,000.00 0.08 10.00 100.00 0.08 - - 10.00 100.00 0.08
3.2.2 Pelindung Mata (Googles, Spectacles) Bh 5.00 25,000.00 125,000.00 0.01 5.00 100.00 0.01 - - 5.00 100.00 0.01
3.2.3 Pelindung Pernapasan dan Mulut (Masker) Bh 100.00 5,000.00 500,000.00 0.05 100.00 100.00 0.05 - - 100.00 100.00 0.05
3.2.4 Sarung Tangan (Safety Gloves) Psg 10.00 15,000.00 150,000.00 0.02 10.00 100.00 0.02 - - 10.00 100.00 0.02
3.2.5 Sepatu Keselamatan (Safety Shoes) Psg 10.00 350,000.00 3,500,000.00 0.35 10.00 100.00 0.35 - - 10.00 100.00 0.35
3.2.6 Penunjang Seluruh Tubuh (Full Body Harness) Bh 2.00 500,000.00 1,000,000.00 0.10 2.00 100.00 0.10 - - 2.00 100.00 0.10
3.2.7 Rompi Keselamatan (Safety Vest) Bh 10.00 25,000.00 250,000.00 0.03 10.00 100.00 0.03 - - 10.00 100.00 0.03
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 9,975,000.00 1.01 1.01 - 1.01
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4. ASURANSI DAN PERIZINAN
4.1 Asuransi Ls 1.00 3,000,000.00 3,000,000.00 0.30 1.00 100.00 0.30 - - 1.00 100.00 0.30
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 3,000,000.00 0.30 0.30 - 0.30
5. PERSONEL K3 KONSTRUKSI
5.1 Ahli K3 Konstruksi -
5.2 Petugas K3 Konstruksi Ob 4.00 3,675,000.00 14,700,000.00 1.48 4.00 100.00 1.48 - - 4.00 100.00 1.48
TOTAL PERSONEL K3 KONSTRUKSI 14,700,000.00 1.48 1.48 - 1.48
6. FASILITAS, SARANA DAN PRASARANA KESEHATAN
6.1 Peralatan P3K (Kotak P3K, Tandu, Obat Luka, Perban, dll) Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
TOTAL FASILITAS, SARANA DAN PRASARANA KESEHATAN 500,000.00 0.05 0.05 - 0.05
7. RAMBU - RAMBU YANG DIPERLUKAN
7.1 Rambu Petunjuk bh 2.00 75,000.00 150,000.00 0.02 2.00 100.00 0.02 - - 2.00 100.00 0.02
7.2 Rambu Larangan bh 2.00 75,000.00 150,000.00 0.02 2.00 100.00 0.02 - - 2.00 100.00 0.02
7.3 Rambu Peringatan bh 2.00 100,000.00 200,000.00 0.02 2.00 100.00 0.02 - - 2.00 100.00 0.02
7.4 Jalur Evakuasi (Escape Route) Ls 1.00 250,000.00 250,000.00 0.03 1.00 100.00 0.03 - - 1.00 100.00 0.03
TOTAL RAMBU - RAMBU YANG DIPERLUKAN 750,000.00 0.08 0.08 - 0.08
8. KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI
8.1 Ahli K3 Konstruksi Oj -
TOTAL KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI - 0.00
9. LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN
KONSTRUKSI
9.1 Alat Pemadam Api Ringan (APAR) bh 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
9.2 Program Inspeksi Ls 1.00 1,500,000.00 1,500,000.00 0.15 1.00 100.00 0.15 - - 1.00 100.00 0.15
9.3 Pelaporan dan Penyeledikan Insiden Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
9.4 Pembuatan Kartu Identitas Pekerja (KIP) Org 10.00 5,000.00 50,000.00 0.01 10.00 100.00 0.01 - - 10.00 100.00 0.01
TOTAL LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN KONSTRUKSI 2,550,000.00 0.26 0.26 - 0.26

A Jumlah Harga Penawaran 989,944,870.91 100.00 71.49 5.37 76.86


B PPN (10%) 98,994,487.09
C Jumlah (A+B) 1,088,939,358.00
PERSENTASE SAMPAI MINGGU INI 76.86
D Jumlah Dibulatkan 1,088,939,358.00

Bulukumba, 14 Desember 2020


Disetujui, Diketahui, Diperiksa Oleh, Dibuat Oleh,
Pejabat Pembuat Komitmen Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUTR Prov SulSel Dinas PUTR Prov SulSel CV.MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

A.KHADAFI HARUN, ST.,MT. L I L I, ST. IRHAM HARAHAP, ST. VIKA APRILIA DWI PUTRI
NIP. 19811126 200901 1 008 NIP. 19821229 201503 2 001 Site Engineer Direktris
LAPORAN KEMAJUAN BULANAN

Kegiatan : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba Bulan Ke : 01 ( Satu )
Satuan Kerja : Dinas Pekerjaan Umum Dan Tata Ruang Prov. Sulawesi Selatan Bidang Cipta Karya Periode : 16 Oktober S/d 12 November 2020
Lokasi : Desa Ara, Kecamatan Bonto Bahari, Kabupaten Bulukumba, Provinsi Sulawesi Selatan No. Kontrak : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
Sumber Dana : Dana Bantuan Provinsi Nilai Kontrak : Rp. 1,088,939,358.00
Tahun Anggaran : 2020 Schedule Pelaksanaan : 16 Oktober S/d 14 Desember 2020

BULAN LALU BULAN INI S/D BULAN INI


VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
NO URAIAN PEKERJAAN
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q

A. PEMBANGUNAN RUANG KULINER, SUVENIR, MUSHOLLAH DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Papan Proyek Ls 1.00 500,000.00 500,000.00 0.05 - - 1.00 100.00 0.05 1.00 100.00 0.05
1.2 Bedeng/Direksi Keet M2 5.50 1,512,555.00 8,319,052.50 0.84 - - 5.50 100.00 0.84 5.50 100.00 0.84

TOTAL PEKERJAAN PERSIAPAN 8,819,052.50 0.89 0.00 0.89 0.89

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Poerplat PP1 (Selasar Samping)
2.1.1.1 Galian Pondasi Poerplat < 1 m M3 0.32 73,837.50 23,628.00 0.00 - - 0.32 100.00 0.00 0.32 100.00 0.00
2.1.1.2 Urugan Pasir dibawah Pondasi Poerplat T.5 cm M3 0.04 148,335.00 5,933.40 0.00 - - 0.04 100.00 0.00 0.04 100.00 0.00
2.1.1.3 Urugan Tanah Kembali Pondasi Poerplat M3 0.31 54,175.00 16,794.25 0.00 - - 0.31 100.00 0.00 0.31 100.00 0.00
2.1.1.4 Pasangan Lantai Kerja bawah Pondasi Poerplat T.5 cm (Beton K300) M3 0.04 1,118,216.00 44,728.64 0.00 - - 0.04 100.00 0.00 0.04 100.00 0.00
2.1.1.5 Pondasi Poerplat 35x50 cm, T.20 cm - -
Beton Mutu F'c = 26,4 mpa (K300), Slump (12-2) cm, w/c = 0,52 M3 0.14 1,118,216.00 156,550.24 0.02 - - 0.14 100.00 0.02 0.14 100.00 0.02
Bekisting 2x Pakai M2 0.56 107,013.50 59,927.56 0.01 - - 0.56 100.00 0.01 0.56 100.00 0.01
Besi Beton Ø14 SNI Kg 29.40 21,464.85 631,066.59 0.06 - - 29.40 100.00 0.06 29.40 100.00 0.06
2.1.2 Pekerjaan Pondasi Batu Kali (Badan Bangunan, Mushollah) - -
2.1.2.1 Galian Tanah Pondasi Batu Kali < 1 m M3 22.73 73,837.50 1,678,326.38 0.17 - - 22.73 100.00 0.17 22.73 100.00 0.17
2.1.2.2 Urugan Pasir dibawah Pondasi Batu Kali T.5 cm M3 1.08 148,335.00 160,201.80 0.02 - - 1.08 100.00 0.02 1.08 100.00 0.02
2.1.2.3 Pasangan Aanstamping bawah Pondasi Batu Kali T.10 M3 2.17 382,674.00 830,402.58 0.08 - - 2.17 100.00 0.08 2.17 100.00 0.08
2.1.2.4 Urugan Tanah Kembali Pondasi Batu Kali M3 10.39 54,175.00 562,878.25 0.06 - - 10.39 100.00 0.06 10.39 100.00 0.06
2.1.2.5 Pondasi Batu Kali 1 Sp : 3 Pp M3 9.09 827,447.50 7,521,497.78 0.76 - - 9.09 100.00 0.76 9.09 100.00 0.76
2.1.3 Pekerjaan Pondasi Rollage L.15 cm (Entrance, Selasar Samping) - - -
2.1.3.1 Galian Tanah Pondasi Rollage < 1 m M3 2.23 73,837.50 164,657.63 0.02 - - 2.23 100.00 0.02 2.23 100.00 0.02
2.1.3.2 Urugan Pasir dibawah Pondasi Rollage T.5 cm M3 0.45 148,335.00 66,750.75 0.01 - - 0.45 100.00 0.01 0.45 100.00 0.01
2.1.3.3 Pasangan Lantai Kerja bawah Pondasi Rollage T.5 cm (Beton K300) M3 0.45 1,118,216.00 499,003.89 0.05 - - 0.45 100.00 0.05 0.45 100.00 0.05
2.1.3.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp M2 20.83 128,436.00 2,675,321.88 0.27 - - 20.83 100.00 0.27 20.83 100.00 0.27
2.2 Pekerjaan Sloef, Kolom dan Ringbalk - -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Mushollah) - -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 1.62 1,118,216.00 1,815,703.23 0.18 - - 1.62 100.00 0.18 1.62 100.00 0.18
2.2.1.2 Bekisting 2x Pakai M2 10.83 114,438.50 1,239,368.96 0.13 - - 10.83 100.00 0.13 10.83 100.00 0.13
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI Kg 280.09 21,464.85 6,012,089.84 0.61 - - 280.09 100.00 0.61 280.09 100.00 0.61
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan, Mushollah) - -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.88 1,118,216.00 981,234.54 0.10 - - 0.88 100.00 0.10 0.88 100.00 0.10
2.2.2.2 Bekisting 2x Pakai M2 5.85 193,468.00 1,131,787.80 0.11 - - 5.85 100.00 0.11 5.85 100.00 0.11
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 181.66 21,464.85 3,899,347.58 0.39 - - 181.66 100.00 0.39 181.66 100.00 0.39
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Selasar, Westafel, Tempat Wudhu) -
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 - - 0.34 100.00 0.03 0.34 100.00 0.03
2.2.3.2 Bekisting 2x Pakai M2 2.26 193,468.00 437,237.68 0.04 - - 2.26 100.00 0.04 2.26 100.00 0.04
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 70.10 21,464.85 1,504,686.30 0.15 - - 70.10 100.00 0.15 70.10 100.00 0.15
2.2.4 Pekerjaan Kolom K1 15 x 30 (Selasar Samping) -
2.2.4.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.62 1,118,216.00 694,412.14 0.07 - - 0.62 100.00 0.07 0.62 100.00 0.07
2.2.4.2 Bekisting 2x Pakai M2 6.21 193,468.00 1,201,436.28 0.12 - - 6.21 100.00 0.12 6.21 100.00 0.12
2.2.4.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 99.69 21,464.85 2,139,830.90 0.22 - - 99.69 100.00 0.22 99.69 100.00 0.22
2.2.5 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan, Mushollah) -
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 2.08 1,008,161.00 2,097,478.96 0.21 - - 2.08 100.00 0.21 2.08 100.00 0.21
2.2.5.2 Bekisting 2x Pakai M2 13.87 197,923.00 2,745,192.01 0.28 - - 13.87 100.00 0.28 13.87 100.00 0.28
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 299.22 21,464.85 6,422,712.42 0.65 - - 299.22 100.00 0.65 299.22 100.00 0.65
2.2.6 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan) -
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 - - 0.34 100.00 0.03 0.34 100.00 0.03
2.2.6.2 Bekisting 2x Pakai M2 2.24 197,923.00 443,347.52 0.04 - - 2.24 100.00 0.04 2.24 100.00 0.04
2.2.6.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 48.32 21,464.85 1,037,181.55 0.10 - - 48.32 100.00 0.10 48.32 100.00 0.10
2.2.7 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Mushollah, Pintu Jendela) -
2.2.7.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.84 1,008,161.00 846,855.24 0.09 - - 0.84 100.00 0.09 0.84 100.00 0.09
2.2.7.2 Bekisting 2x Pakai M2 5.59 197,923.00 1,106,389.57 0.11 - - 5.59 100.00 0.11 5.59 100.00 0.11
2.2.7.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 115.53 21,464.85 2,479,834.12 0.25 - - 115.53 100.00 0.25 115.53 100.00 0.25
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.2.8 Pekerjaan Plat Beton (Selasar Samping, Westafel) -
2.2.8.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.22 1,008,161.00 221,795.42 0.02 - - 0.22 100.00 0.02 0.22 100.00 0.02
2.2.8.2 Bekisting 2x Pakai M2 2.21 237,468.00 524,804.28 0.05 - - 2.21 100.00 0.05 2.21 100.00 0.05
2.2.8.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 54.54 21,464.85 1,170,692.92 0.12 - - 54.54 100.00 0.12 54.54 100.00 0.12
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) M2 152.03 163,636.00 24,877,581.08 2.51 - - 152.03 100.00 2.51 152.03 100.00 2.51
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4, Entrance) M2 42.24 242,170.50 10,229,281.92 1.03 - - 42.24 100.00 1.03 42.24 100.00 1.03
2.5 Pekerjaan Tiang Atap Bitumen Gelombang (Besi Hollow Galvanis 5/10, Entrance) M' 20.40 178,365.00 3,638,646.00 0.37 - - 20.40 100.00 0.37 20.40 100.00 0.37
2.6 Pekerjaan Rangka Plafond Kalsiboard (Besi Hollow Metal Galvalume 4/4) M2 147.40 102,837.17 15,158,198.37 1.53 - - 147.40 100.00 1.53 147.40 100.00 1.53

TOTAL PEKERJAAN STRUKTUR 109,840,345.70 11.10 0.00 11.10 11.10

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) M3 8.54 148,335.00 1,266,780.90 0.13 - - 8.54 100.00 0.13 8.54 100.00 0.13
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) M3 25.63 167,227.00 4,285,636.74 0.43 - - 25.63 100.00 0.43 25.63 100.00 0.43
3.1.1.3 Rabat Beton bawah Lantai T.5 cm (Keseluruhan, Beton K300) M3 8.54 1,118,216.00 9,549,564.64 0.96 - - 8.54 100.00 0.96 8.54 100.00 0.96
3.1.1.4 Penutup Lantai Keramik Motif 60x60 (Badan Bangunan, Mushollah) M2 62.94 403,309.50 25,384,299.93 2.56 - - - - - - - -
3.1.1.5 Penutup Lantai Conwood Deck 6" (Entrance) M2 59.01 866,833.08 51,151,820.09 5.17 - - - - - - - -
3.1.1.6 Penutup Lantai Andesit Polos 30x30 (Selasar, Tempat Wudhu, Ram) M2 51.05 232,589.50 11,873,693.98 1.20 - - - - - - - -
3.1.1.7 Plint Lantai Keramik 10x60 (Badan Bangunan, Mushollah) M' 38.85 51,605.03 2,004,855.55 0.20 - - - - - - - -
3.1.2 Pekerjaan Dinding -
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Mushollah, 1 Sp : 4 Pp) M2 74.55 242,979.00 18,114,084.45 1.83 - - 74.55 100.00 1.83 74.55 100.00 1.83
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Selasar Samping, Tempat Wudhu) M2 5.14 65,550.32 336,928.64 0.03 - - - - - - - -
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm (Badan Bangunan, Mushollah) M2 91.30 60,403.20 5,514,812.16 0.56 - - 91.30 100.00 0.56 91.30 100.00 0.56
3.1.2.4 Plesteran Ciprat 1 Sp : 2 Pp Tebal 15 mm (Selasar Samping, Antar Kolom) M2 24.84 49,215.10 1,222,503.08 0.12 - - - - - - - -
3.1.2.5 Dinding Keramik Mozaik 30x60 (Selasar Samping, Westafel, Tempat Wudhu) M2 18.44 410,432.00 7,568,366.08 0.76 - - - - - - - -
3.1.2.6 Coating Bening (Badan Bangunan, Mushollah, Kolom Luar) M2 127.49 45,973.13 5,861,113.71 0.59 - - - - - - - -
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) M2 8.64 995,043.50 8,597,175.84 0.87 - - - - - - - -
3.1.2.8 Dinding Wallpaper Bata L.50 cm (Sisi Dalam) M2 28.13 80,005.50 2,250,554.72 0.23 - - - - - - - -
3.1.3 Pekerjaan Plafond -
3.1.3.1 Plafond Kalsiboard (Badan Bangunan, Kemiringan Atap, Mushollah) M2 147.40 44,924.00 6,621,797.60 0.67 - - - - - - - -
3.1.3.2 Plafond Kalsiboard (Lapis Bawah Atap, Entrance) M2 42.24 44,924.00 1,897,589.76 0.19 - - - - - - - -
3.2 Pekerjaan Pintu dan Jendela (Badan Bangunan) -
3.2.1 Pintu P1 (Entrance dan Back Entrance, Badan Bangunan) -
3.2.1.1 Pasangan Kusen Alumunium Coating P1 (4" x 1 3/4") cm M' 22.40 157,194.40 3,521,154.56 0.36 - - - - - - - -
3.2.1.2 Pasangan Daun Pintu P1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - - -
3.2.1.3 Pasangan Kaca Mati 5 mm P1 M2 11.20 145,703.80 1,631,882.56 0.16 - - - - - - - -
3.2.1.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - - -
3.2.1.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - - -
3.2.1.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - - -
3.2.1.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - - -
3.2.2 Jendela J1 (Badan Bangunan) -
3.2.2.1 Pasangan Kusen Alumunium Coating J1 (4" x 1 3/4") cm M' 40.60 157,194.40 6,382,092.64 0.64 - - - - - - - -
3.2.2.2 Pasangan Kaca Mati 5 mm J1 M2 8.00 145,703.80 1,165,630.40 0.12 - - - - - - - -
3.2.3 Pintu PJ1 (Mushollah) -
3.2.3.1 Pasangan Kusen Alumunium Coating PJ1 (4" x 1 3/4") cm M' 22.20 157,194.40 3,489,715.68 0.35 - - - - - - - -
3.2.3.2 Pasangan Daun Pintu PJ1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - - -
3.2.3.3 Pasangan Kaca Mati 5 mm P1 M2 8.70 145,703.80 1,267,623.06 0.13 - - - - - - - -
3.2.3.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - - -
3.2.3.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - - -
3.2.3.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - - -
3.2.3.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - - -
3.3 Pekerjaan Pengecatan -
3.3.1 Pengecatan Plafond (1 Plamir ; 1 Cat Dasar : 2 Cat Penutup), (Interior) M2 189.64 35,536.05 6,739,056.52 0.68 - - - - - - - -
3.3.2 Pengecatan Rangka Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 23.76 168,454.00 4,002,467.04 0.40 - - - - - - - -
3.3.3 Pengecatan Tiang Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 6.12 168,454.00 1,030,938.48 0.10 - - - - - - - -
3.4 Pekerjaan Atap -
3.4.1 Atap Bitumen Gelombang (Badan Bangunan, Mushollah) M2 152.03 207,297.09 31,515,376.59 3.18 - - 152.03 100.00 3.18 152.03 100.00 3.18
3.4.2 Atap Bitumen Gelombang (Entrance) M2 42.24 207,297.09 8,756,229.08 0.88 - - 42.24 100.00 0.88 42.24 100.00 0.88
3.4.3 Nok Bitumen (Badan Bangunan, Mushollah) M' 14.55 134,101.00 1,951,169.55 0.20 - - 14.55 100.00 0.20 14.55 100.00 0.20
3.4.4 Listplank (Kalsiplank, Badan Bangunan, Mushollah, Entrance) M' 50.00 70,950.00 3,547,500.00 0.36 - - 50.00 100.00 0.36 50.00 100.00 0.36

TOTAL PEKERJAAN FINISHING ARSITEKTUR 257,222,142.77 25.98 0.00 8.54 8.54

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel Bh 1.00 1,572,826.75 1,572,826.75 0.16 - - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt Bh 16.00 353,938.75 5,663,020.00 0.57 - - - - - - - -
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4.1.3 Pasangan Lampu Down Light 2,5" Outbow LED 5,5 Watt Bh 11.00 305,538.75 3,360,926.25 0.34 - - - - - - - -
4.1.4 Pasangan Saklar Tunggal Bh 4.00 211,378.75 845,515.00 0.09 - - - - - - - -
4.1.5 Pasangan Saklar Ganda Bh 2.00 223,478.75 446,957.50 0.05 - - - - - - - -
4.2 Pasangan Instalasi Stop Kontak - -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA Bh 10.00 216,218.75 2,162,187.50 0.22 - - - - - - - -
4.2.2 Pasangan Stop Kontak AC 220 VA/3520 W (AC Split 1 PK) Bh 4.00 253,728.75 1,014,915.00 0.10 - - - - - - - -
4.3 Pasangan Instalasi Jaringan AC M' 30.00 108,772.68 3,263,180.25 0.33 - - - - - - - -
4.3.1 Pasangan AC Split 1 PK Bh 3.00 3,365,799.34 10,097,398.03 1.02 - - - - - - - -
4.4 Pasangan Penangkal Petir Ls 1.00 2,500,000.00 2,500,000.00 0.25 - - - - - - - -
4.5 Pasangan Instalasi Jaringan Kabel Fiber Optic (CCTV) Ttk 6.00 786,326.75 4,717,960.50 0.48 - - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2MP Bh 6.00 656,975.00 3,941,850.00 0.40 - - - - - - - -
4.5.2 Pasangan NVR Channel Set 1.00 5,023,975.00 5,023,975.00 0.51 - - - - - - - -
4.5.3 Pasangan Monitor LCD 32" Bh 1.00 2,944,975.00 2,944,975.00 0.30 - - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm M' 12.00 20,442.68 245,312.10 0.02 - - - - - - - -
4.6.1 Pasangan Horn Speaker Bh 6.00 494,826.75 2,968,960.50 0.30 - - - - - - - -
4.6.2 Pasangan Volume Kontrol Set 1.00 252,826.75 252,826.75 0.03 - - - - - - - -
4.6.3 Pasangan Perangkat Sound System Set 1.00 4,565,000.00 4,565,000.00 0.46 - - - - - - - -
4.6.4 Pasangan TB-Sound System Set 1.00 5,846,326.75 5,846,326.75 0.59 - - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25Kg) Ttk 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - - -
4.8 Pasangan Instalasi Jaringan Kabel Fiber Optic (Akses Point) Ttk 3.00 786,326.75 2,358,980.25 0.24 - - - - - - - -
4.8.1 Pasangan Server Set 1.00 7,578,826.75 7,578,826.75 0.77 - - - - - - - -
4.8.2 Pasangan Akses Point Bh 1.00 2,034,826.75 2,034,826.75 0.21 - - - - - - - -
4.8.3 Pasangan Switch HUB Bh 1.00 2,843,326.75 2,843,326.75 0.29 - - - - - - - -
4.9 Pasangan Instalasi PLN Power (Inc. Jalur ke Mushollah dan Toilet) Ls 1.00 9,000,000.00 9,000,000.00 0.91 - - - - - - - -

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 94,450,073.38 9.54 0.00 0.00 0.00

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVC Type AW Diameter 3/4" (Air Bersih Sambungan dari Tandon) M' 33.00 28,300.25 933,908.25 0.09 - - - - - - - -
5.2 Pipa PVC Type AW Diameter 3" (Air Kotor ke Drainase Lingkungan) M' 25.80 135,531.00 3,496,699.80 0.35 - - - - - - - -
5.3 Pasangan 1 Bh Wastafel Bh 2.00 3,934,865.00 7,869,730.00 0.79 - - - - - - - -
5.4 Pasangan 1 Bh Wastafel Cuci Piring (WCP) Bh 1.00 890,945.00 890,945.00 0.09 - - - - - - - -
5.5 Pasangan 1 Bh Floor Drain Bh 2.00 41,112.50 82,225.00 0.01 - - - - - - - -
5.6 Pasangan 1 Bh Kran Dia. 1/2" atau 3/4" Bh 10.00 102,217.50 1,022,175.00 0.10 - - - - - - - -
5.7 Pasangan 1 Bh Kran Wastafel Dia. 1/2" atau 3/4" Bh 3.00 335,417.50 1,006,252.50 0.10 - - - - - - - -
5.8 Pasangan 1 Bh Stop Kran (Gate Valve) Dia. 3/4" Bh 1.00 141,417.50 141,417.50 0.01 - - - - - - - -
5.9 Pasangan Mesin Air Bh 1.00 741,000.00 741,000.00 0.07 - - - - - - - -
5.10 Menara Reservoir 200x150x350 cm -
5.10.1 Pekerjaan Pondasi Pedestal Pd1 -
5.10.1.1 Galian Tanah Pondasi Poerplat < 1 m M3 1.62 73,837.50 119,616.75 0.01 - - - - - - - -
5.10.1.2 Urugan Tanah Kembali Pondasi Poerplat M3 0.43 54,175.00 23,295.25 0.00 - - - - - - - -
5.10.1.3 Tiang Pondasi Pedestal 50x50 cm - - -
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.80 1,118,216.00 894,572.80 0.09 - - - - - - - -
Bekisting 2x Pakai M2 3.20 193,468.00 619,097.60 0.06 - - - - - - - -
Besi Beton Ø12 SNI, Ø8 SNI Kg 49.44 21,464.85 1,061,130.60 0.11 - - - - - - - -
5.10.1.4 Pondasi Poerplat 90x90 cm, T.20 cm -
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.65 1,118,216.00 726,840.40 0.07 - - - - - - - -
Bekisting 2x Pakai M2 1.44 107,013.50 154,099.44 0.02 - - - - - - - -
Besi Beton Ø14 SNI Kg 214.35 21,464.85 4,600,940.54 0.46 - - - - - - - -
5.10.2 Rangka Tengah dan Lantai Menara (Besi Hollow Galvanis 4/4) M2 34.82 244,970.00 8,529,855.40 0.86 - - - - - - - -
5.10.3 Rangka Utama Menara (Besi Hollow Galvanis 5/10) M' 32.28 179,454.00 5,792,775.12 0.59 - - - - - - - -
5.10.4 Plat Baja Lantai Menara T.3 mm M2 3.00 740,164.86 2,220,494.57 0.22 - - - - - - - -
5.10.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) M2 5.00 244,970.00 1,224,850.00 0.12 - - - - - - - -

TOTAL PEKERJAAN PLAMBING DAN SANITASI 42,151,921.52 4.26 0.00 0.00 0.00

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Pek. Pembersian Awal m2 81.86 17,600.00 1,440,780.00 0.15 - - 81.86 100.00 0.15 81.86 100.00 0.15
1.2 Pek. Pengukuran & Pemasangan Bouwplank m1 48.60 106,461.25 5,174,016.75 0.52 - - 48.60 100.00 0.52 48.60 100.00 0.52

TOTAL PEKERJAAN PERSIAPAN 6,614,796.75 0.67 0.00 0.67 0.67

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Batu Kali (Badan Bangunan,Ruang Bilas)
2.1.1.1 Galian Pondasi Batu Kali < 1 m m3 22.05 73,892.50 1,629,329.63 0.16 - - 6.62 30.00 0.05 6.62 30.00 0.05
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.1.1.2 Urugan Pasir Dibawah Pondasi Batu Kali T.5 cm m3 1.05 174,757.00 183,494.85 0.02 - - 1.05 100.00 0.02 1.05 100.00 0.02
2.1.1.3 Pasangan Aanstamping Bawah Pondasi Batu Kali T.10 cm m3 2.10 392,699.70 824,669.37 0.08 - - 2.10 100.00 0.08 2.10 100.00 0.08
2.1.1.4 Urugan Tanah Kembali Pondasi Batu Kali m3 10.08 54,285.00 547,192.80 0.06 - - 3.02 30.00 0.02 3.02 30.00 0.02
2.1.1.5 Pondasi Batu Kali 1 Sp : 3 Pp m3 8.82 824,945.00 7,276,014.90 0.73 - - 8.82 100.00 0.73 8.82 100.00 0.73
2.1.2 Perjaan Pondasi Rollage L.15 cm (Selasar) -
2.1.2.1 Galian Tanah Pondasi Rollage < 1 m m3 1.52 73,892.50 112,501.33 0.01 - - 0.15 10.00 0.00 0.15 10.00 0.00
2.1.2.2 Urugan Pasir Dibawah Pondasi Rollage T.5 cm m3 0.30 174,757.00 53,213.51 0.01 - - 0.03 10.00 0.00 0.03 10.00 0.00
2.1.2.3 Pasangan Lantai Kerja Bawah Pondasi Rollage T.5 cm (Beton K300) m3 0.30 1,118,398.60 340,552.37 0.03 - - 0.30 100.00 0.03 0.30 100.00 0.03
2.1.2.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp m3 14.21 128,260.00 1,822,574.60 0.18 - - 14.21 100.00 0.18 14.21 100.00 0.18
2.2 Pekerjaan Sloef, Kolom, Plat dan Ringbalk - -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Ruang Bilas) - -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 m3 1.41 1,118,398.60 1,580,297.22 0.16 - - 1.41 100.00 0.16 1.41 100.00 0.16
2.2.1.2 Bekisting 2x Pakai m2 9.42 114,467.10 1,078,280.08 0.11 - - 9.42 100.00 0.11 9.42 100.00 0.11
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI kg 243.74 21,465.73 5,232,043.29 0.53 - - 243.74 100.00 0.53 243.74 100.00 0.53
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan) - -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slum (12 - 2) cm, w/c = 0,52 m3 0.48 1,118,398.60 533,476.13 0.05 - - 0.48 100.00 0.05 0.48 100.00 0.05
2.2.2.2 Bekisting 2x Pakai m2 3.18 193,504.30 615,343.67 0.06 - - 3.18 100.00 0.06 3.18 100.00 0.06
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI kg 98.75 21,465.73 2,119,732.25 0.21 - - 98.75 100.00 0.21 98.75 100.00 0.21
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Ruang Bilas) - -
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.25 1,008,343.60 249,111.29 0.03 - - 0.25 100.00 0.03 0.25 100.00 0.03
2.2.3.2 Bekisting 2x Pakai m2 1.65 193,504.30 318,701.58 0.03 - - 1.65 100.00 0.03 1.65 100.00 0.03
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI kg 51.14 21,465.73 1,097,861.33 0.11 - - 51.14 100.00 0.11 51.14 100.00 0.11
2.2.4 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan) - -
2.2.4.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.04 1,008,343.60 1,043,635.63 0.11 - - 1.04 100.00 0.11 1.04 100.00 0.11
2.2.4.2 Bekisting 2x Pakai m2 6.90 197,959.30 1,365,919.17 0.14 - - 6.90 100.00 0.14 6.90 100.00 0.14
2.2.4.3 Besi Beton Ø12 SNI, Ø6 SNI kg 148.86 21,465.73 3,195,302.68 0.32 - - 148.86 100.00 0.32 148.86 100.00 0.32
2.2.5 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan) - -
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.09 1,008,343.60 1,103,531.24 0.11 - - 1.09 100.00 0.11 1.09 100.00 0.11
2.2.5.2 Bekisting 2x Pakai m2 14.59 197,959.30 2,888,622.11 0.29 - - 14.59 100.00 0.29 14.59 100.00 0.29
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI kg 157.40 21,465.73 3,378,705.12 0.34 - - 157.40 100.00 0.34 157.40 100.00 0.34
2.2.6 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Pintu Jendela) -
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.15 1,008,343.60 148,831.52 0.02 - - 0.15 100.00 0.02 0.15 100.00 0.02
2.2.6.2 Bekisting 2x Pakai m2 0.98 197,959.30 194,791.95 0.02 - - 0.98 100.00 0.02 0.98 100.00 0.02
2.2.6.3 Besi Beton Ø10 SNI, Ø6 SNI kg 20.35 21,465.73 436,752.39 0.04 - - 20.35 100.00 0.04 20.35 100.00 0.04
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) m2 59.01 163,856.00 9,669,142.56 0.98 - - 59.01 100.00 0.98 59.01 100.00 0.98
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4) m2 48.59 102,876.77 4,998,782.09 0.50 - - 48.59 100.00 0.50 48.59 100.00 0.50
2.5 Pekerjaan Rangka Plafond dan Dinding Dalam PVC Shunda (Besi Hollow Metal Galvalume 4/4) m2 56.16 102,876.77 5,777,559.22 0.58 - - - - - - - -

TOTAL PEKERJAAN STRUKTUR 59,815,965.86 6.04 0.00 5.29 5.29

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) m3 4.09 174,757.00 715,280.40 0.07 - - 4.09 100.00 0.07 4.09 100.00 0.07
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) m3 12.28 167,345.00 2,054,804.70 0.21 - - 12.28 100.00 0.21 12.28 100.00 0.21
3.1.1.3 Rabat Beton T.5 cm (Keseluruhan, Beton K300) m3 4.09 1,118,398.60 4,577,605.47 0.46 - - 4.09 100.00 0.46 4.09 100.00 0.46
3.1.1.4 Penutup Lantai Keramik Tekstur 60x60 (Badan Bangunan) m2 36.93 413,098.40 15,255,723.91 1.54 - - 29.54 80.00 1.23 29.54 80.00 1.23
3.1.1.5 Penutup Lantai Andesit Polos 30x30 (Selasar, Ruang Bilas) m2 45.89 284,369.80 13,049,730.12 1.32 - - - - - - - -
3.1.1.6 Penutup Plat Wastafel (Granit 60x60, Toilet Pria dan Wanita) m2 2.20 841,621.73 1,851,567.81 0.19 - - - - - - - -
3.1.2 Pekerjaan Dinding - -
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Selasar, 1 Sp : 4 Pp) 90.64 242,533.50 21,983,236.44 2.22 - - 72.51 80.00 1.78 72.51 80.00 1.78
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Wc ) 30.00 65,473.32 1,964,199.60 0.20 - - 24.00 80.00 0.16 24.00 80.00 0.16
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm 121.28 60,304.20 7,313,693.38 0.74 - - 97.02 80.00 0.59 97.02 80.00 0.59
3.1.2.4 Coating Bening 121.28 46,853.13 5,682,347.00 0.57 - - - - - - - -
3.1.2.5 Dinding Andesit Polos 30x30 cm ( Wc, Ruang Bilas ) 56.52 284,369.80 16,072,581.10 1.62 - - - - - - - -
3.1.2.6 Dinding Keramik 30x60 cm ( Sisi Dalam ) 69.88 370,557.00 25,894,523.16 2.62 - - - - - - - -
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) 9.00 995,076.50 8,955,688.50 0.90 - - - - - - - -
3.1.2.8 Cubicle Panel + Accessories (Pintu Wc dan Partisi Urinoir) 10.86 1,360,000.00 14,769,600.00 1.49 - - - - - - - -
3.1.2.9 Dinding Bitumen Gelombang 48.59 201,749.24 9,802,995.57 0.99 - - - - - - - -
3.1.2.10 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Pria) 1.00 1,200,000.00 1,200,000.00 0.12 - - - - - - - -
3.1.2.11 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Wanita) 1.00 750,000.00 750,000.00 0.08 - - - - - - - -
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.1.3 Plafond dan Dinding Dalam Shunda ( Badan Bangunan ) 56.16 125,878.50 7,069,336.56 0.71 - - - - - - - -
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.2 Pekerjaan Pintu dan Jendela ( Badan Bangunan ) - -
3.2.1 Pintu P1 - -
3.2.1.1 Pasangan Kusen Almunium Coating P1 (4" x 13/4") cm 10.96 157,199.02 1,722,901.26 0.17 - - - - - - - -
3.2.1.2 Pasangan Daun Pintu P1 (Panel Almunium Coating - Coating) 4.30 870,323.19 3,742,389.72 0.38 - - - - - - - -
3.2.1.3 Pasangan Kunci Tanam 2x Slag P1 2.00 416,663.50 833,327.00 0.08 - - - - - - - -
3.2.1.4 Pasangan ensel P1 6.00 61,225.56 367,353.36 0.04 - - - - - - - -
3.2.1.5 Pasangan Doorcloser P1 2.00 241,902.10 483,804.20 0.05 - - - - - - - -
3.2.1.6 Pasangan Handle P1 2.00 229,802.10 459,604.20 0.05 - - - - - - - -
3.2.2 Jendela J1 - -
3.2.2.1 Pasangan Kusen Almunium Coating J1 (4" x 13/4") cm 28.80 157,199.02 4,527,331.78 0.46 - - - - - - - -
3.2.2.2 Pasangan Kaca Mati 5 mm J1 0.60 145,705.56 87,423.34 0.01 - - - - - - - -
3.2.3 Jendela J2 -
3.2.3.1 Pasangan Kusen Almunium Coating J2 (4" x 13/4") cm 55.20 157,199.02 8,677,385.90 0.88 - - - - - - - -
3.2.3.2 Pasangan Kaca Mati 5 mm J2 0.90 145,705.56 131,135.00 0.01 - - - - - - - -
3.3. Pengecetan Plafond (1 Plamir : 1 Cat Dasar : 2 Cat Penutup), (Interior) 56.16 43,550.65 2,445,804.50 0.25 - - - - - - - -
3.4 Pekerjaan Atap - -
3.4.1 Atap Bitumen Gelombang (Badan Bangunan) 59.01 201,749.24 11,905,222.65 1.20 - - - - - - - -
3.4.2 Nok Bitumen (Badan Bangunan) 35.25 143,629.20 5,062,929.30 0.51 - - - - - - - -
3.4.3 Listplank (Kasiplank, Badan Bangunan, Enterance) 39.08 70,972.00 2,773,585.76 0.28 - - - - - - - -

TOTAL PEKERJAAN FINISHING ARSITEKTUR 202,183,111.69 20.42 0.00 4.50 4.50

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel 1.00 1,803,826.75 1,803,826.75 0.18 - - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt 10.00 353,938.75 3,539,387.50 0.36 - - - - - - - -
4.1.3 Pasangan Lampu Down Light 2.5" Outbow LED 5.5 Watt 12.00 305,538.75 3,666,465.00 0.37 - - - - - - - -
4.1.4 Pasangan Saklar Ganda 5.00 223,478.75 1,117,393.75 0.11 - - - - - - - -
4.2 Pasangan Instalasi Stop Kontak - -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA 3.00 216,218.75 648,656.25 0.07 - - - - - - - -
4.2.2 Pasangan Stop Kontak Wall Exhauser 6.00 216,218.75 1,297,312.50 0.13 - - - - - - - -
4.3 Pasangan Instalasi Jaringan Wall Exhauser 12.00 108,772.68 1,305,272.10 0.13 - - - - - - - -
4.3.1 Pasangan Wall Exhauser 12 Inch - FV30RUN 6.00 513,500.00 3,081,000.00 0.31 - - - - - - - -
4.4 Pasangan Penangkal Petir 1.00 3,500,000.00 3,500,000.00 0.35 - - - - - - - -
4.5 Pasangan Instlasi Jaringan Kabel Fiber Optic (CCTV) 3.00 786,326.75 2,358,980.25 0.24 - - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2 MP (Luar Bangunan, Sambungan Dari Mini Resto) 3.00 656,975.00 1,970,925.00 0.20 - - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm 4.00 20,442.68 81,770.70 0.01 - - - - - - - -
4.6.1 Pasangan Horn Speaker (Sambungan Dari Mini Resto) 2.00 494,826.75 989,653.50 0.10 - - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25 kg) 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - - -
4.8 Pasangan Instalasi PLN Power 1.00 10,000,000.00 10,000,000.00 1.01 - - - - - - - -

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 44,560,643.30 4.50 0.00 0.00 0.00

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVc Tipe AW Diameter 3/4" (Air Bersih Dari Sumur Bor / PDAM Reservoir) m1 18.50 28,304.65 523,636.03 0.05 - - - - - - - -
5.2 Pipa PVC Tipe AW Diameter 3/4" (Distribusi Air Bersih Dari Reservoir) m1 26.50 28,304.65 750,073.23 0.08 - - - - - - - -
5.3 Pipa PVC Tipe AW Diameter 3" (Air Kotor Ke Drainase Lingkungan) m1 23.00 135,539.80 3,117,415.40 0.31 - - - - - - - -
5.4 Pipa PVC Tipe AW Diameter 4" (Disposal) m1 18.00 186,689.80 3,360,416.40 0.34 - - - - - - - -
5.5 Pasangan 1 bh Closet Duduk / Monoblock (TOTO) bh 6.00 3,655,597.00 21,933,582.00 2.22 - - - - - - - -
5.6 Pasangan 1 bh Wastafel (TOTO) 3.00 3,571,942.00 10,715,826.00 1.08 - - - - - - - -
5.7 Pasangan 1 bh Uninoir (TOTO) 2.00 6,665,285.00 13,330,570.00 1.35 - - - - - - - -
5.8 Pasangan 1 bh Floor Drain 9.00 41,123.50 370,111.50 0.04 - - - - - - - -
5.9 Pasangan 1 bh Kran dia. 1/2' atau 3/4" 8.00 102,228.50 817,828.00 0.08 - - - - - - - -
5.10 Pasangan 1 bh Kran wastafel dia. 1/2' atau 3/4" 2.00 335,428.50 670,857.00 0.07 - - - - - - - -
5.11 Pasangan 1 bh shower closet dia. 1/2' atau 3/4" 6.00 142,928.50 857,571.00 0.09 - - - - - - - -
5.12 Pasangan 1 bh shower Wall dia. 1/2' atau 3/4" (Ruang Bilas) 4.00 1,435,428.50 5,741,714.00 0.58 - - - - - - - -
5.13 Pasangan 1 bh Stop Kran (Gate Valve) dia. 3/4" 2.00 141,428.50 282,857.00 0.03 - - - - - - - -
5.14 Pasangan Mesin Air 1.00 741,000.00 741,000.00 0.07 - - - - - - - -
5.14b Pasangan Mesin Pemanas Air 1.00 5,000,000.00 5,000,000.00 0.51 - - - - - - - -
5.15 Septictank Biotank Kap. 4m3 1.00 20,380,000.00 20,380,000.00 2.06 - - - - - - - -
5.16 Pasangan Sumur Bor Jet Pump 30.00 350,000.00 10,500,000.00 1.06 - - - - - - - -
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.17 Reservoir 1200 Liter 1.00 1,850,000.00 1,850,000.00 0.19 - - - - - - - -
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.18 Reservoir 200x150x350 cm - -
5.18.1 Pekerjaan Pondasi Pedestal Pd1 - -
5.18.1.1 Galian Tanah Pondasi Poerplat < 1m 1.62 74,250.00 120,285.00 0.01 - - - - - - - -
5.18.1.2 Urugan Tanah Kembali Pondasi Poerplat 0.43 55,000.00 23,760.00 0.00 - - - - - - - -
5.18.1.3 Tiang Pondasi Pedestal 50x50 cm -
Beton Mutu fc = 26,6 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.80 1,485,144.21 1,188,115.37 0.12 - - - - - - - -
Bekisting 2x Pakai 3.20 193,504.30 619,213.76 0.06 - - - - - - - -
Besi Beton Ø12, Ø8 49.44 21,465.73 1,061,174.10 0.11 - - - - - - - -
5.18.1.4 Pondasi Poerplat 90x90 cm,T.20 cm - -
Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.65 1,485,144.21 962,373.45 0.10 - - - - - - - -
Bekisting 2x Pakai 1.44 124,547.50 179,348.40 0.02 - - - - - - - -
Besi Beton Ø14 SNI 214.35 21,465.73 4,601,114.73 0.46 - - - - - - - -
5.18.2 Rangkai Tengah Dan Lantai Menara (Besi Hollow Galvanis 4/4) 34.82 244,970.00 8,529,855.40 0.86 - - - - - - - -
5.18.3 Rangka Utama menara ( Besi Hollow Galvanis 5/10 32.28 179,454.00 5,792,775.12 0.59 - - - - - - - -
5.18.4 Tplat Baja Lantai Menara T.3mm 3.00 740,164.86 2,220,494.57 0.22 - - - - - - - -
5.18.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) 5.00 244,970.00 1,224,850.00 0.12 - - - - - - - -

TOTAL PEKERJAAN PLAMBING DAN SANITASI 127,466,817.45 12.88 - - -

6. PEKERJAAN AKHIR - - -
6.1 Pembersihan Sisa Pekerjaan Ls 1.00 2,400,000.00 2,400,000.00 0.24 - - - - - - - -

TOTAL PEKERJAAN AKHIR 2,400,000.00 0.24 0.00 0.00 0.00

C. PENERAPAN SMKK

1. PENYIAPAN RKK
1.1 Pembuatan Dokumen Rencana Keselamatan Konstruksi
1.2 Pembuatan Prosedur dan instruksi kerja Set 1.00 2,000,000.00 2,000,000.00 0.20 - - 1.00 100.00 0.20 1.00 100.00 0.20
1.3 Penyiapan formulir
TOTAL PENYIAPAN RKK 2,000,000.00 0.20 - 0.20 0.20
2. SOSIALISASI, PROMOSI DAN PELATIHAN
2.1 Induksi K3 (Safety Induction) Org 5.00 7,500.00 37,500.00 0.00 - - 0.50 10.00 0.00 0.50 10.00 0.00
2.2 Pengarahan K3 (Safety Briefing) Org 5.00 15,000.00 75,000.00 0.01 - - 5.00 100.00 0.01 5.00 100.00 0.01
2.3 Pelatihan K3 - -
2.3.1 Bekerja di ketinggian Org 4.00 7,500.00 30,000.00 0.00 - - 4.00 100.00 0.00 4.00 100.00 0.00
2.3.2 Penggunaan Bahan Kimia (MSDS) Org 2.00 7,500.00 15,000.00 0.00 - - 2.00 100.00 0.00 2.00 100.00 0.00
2.4 Simulasi K3 Org 5.00 7,500.00 37,500.00 0.00 - - 5.00 100.00 0.00 5.00 100.00 0.00
2.5 Spanduk (Banner) Lb 1.00 150,000.00 150,000.00 0.02 - - 1.00 100.00 0.02 1.00 100.00 0.02
2.6 Poster 2 2.00 50,000.00 100,000.00 0.01 - - 2.00 100.00 0.01 2.00 100.00 0.01
2.7 Papan Informasi K3 1 1.00 500,000.00 500,000.00 0.05 - - 1.00 100.00 0.05 1.00 100.00 0.05
TOTAL SOSIALISASI, PROMOSI DAN PELATIHAN 945,000.00 0.10 - 0.09 0.09
3. ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI
3.1 APK
3.1.1 Tali Keselamatan (Life Line) Ls 1.00 1,700,000.00 1,700,000.00 0.17 - - 1.00 100.00 0.17 1.00 100.00 0.17
3.1.2 Pembatas Area (Restricted Area) Ls 1.00 2,000,000.00 2,000,000.00 0.20 - - 1.00 100.00 0.20 1.00 100.00 0.20
3.2 APD -
3.2.1 Topi Pelindung (Safety Helmet) Bh 10.00 75,000.00 750,000.00 0.08 - - 10.00 100.00 0.08 10.00 100.00 0.08
3.2.2 Pelindung Mata (Googles, Spectacles) Bh 5.00 25,000.00 125,000.00 0.01 - - 5.00 100.00 0.01 5.00 100.00 0.01
3.2.3 Pelindung Pernapasan dan Mulut (Masker) Bh 100.00 5,000.00 500,000.00 0.05 - - 100.00 100.00 0.05 100.00 100.00 0.05
3.2.4 Sarung Tangan (Safety Gloves) Psg 10.00 15,000.00 150,000.00 0.02 - - 10.00 100.00 0.02 10.00 100.00 0.02
3.2.5 Sepatu Keselamatan (Safety Shoes) Psg 10.00 350,000.00 3,500,000.00 0.35 - - 10.00 100.00 0.35 10.00 100.00 0.35
3.2.6 Penunjang Seluruh Tubuh (Full Body Harness) Bh 2.00 500,000.00 1,000,000.00 0.10 - - 2.00 100.00 0.10 2.00 100.00 0.10
3.2.7 Rompi Keselamatan (Safety Vest) Bh 10.00 25,000.00 250,000.00 0.03 - - 10.00 100.00 0.03 10.00 100.00 0.03
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 9,975,000.00 1.01 - 1.01 1.01
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4. ASURANSI DAN PERIZINAN
4.1 Asuransi Ls 1.00 3,000,000.00 3,000,000.00 0.30 - - 1.00 100.00 0.30 1.00 100.00 0.30
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 3,000,000.00 0.30 - 0.30 0.30
5. PERSONEL K3 KONSTRUKSI
5.1 Ahli K3 Konstruksi -
5.2 Petugas K3 Konstruksi Ob 4.00 3,675,000.00 14,700,000.00 1.48 - - 4.00 100.00 1.48 4.00 100.00 1.48
TOTAL PERSONEL K3 KONSTRUKSI 14,700,000.00 1.48 - 1.48 1.48
6. FASILITAS, SARANA DAN PRASARANA KESEHATAN
6.1 Peralatan P3K (Kotak P3K, Tandu, Obat Luka, Perban, dll) Ls 1.00 500,000.00 500,000.00 0.05 - - 1.00 100.00 0.05 1.00 100.00 0.05
TOTAL FASILITAS, SARANA DAN PRASARANA KESEHATAN 500,000.00 0.05 - 0.05 0.05
7. RAMBU - RAMBU YANG DIPERLUKAN
7.1 Rambu Petunjuk bh 2.00 75,000.00 150,000.00 0.02 - - 2.00 100.00 0.02 2.00 100.00 0.02
7.2 Rambu Larangan bh 2.00 75,000.00 150,000.00 0.02 - - 2.00 100.00 0.02 2.00 100.00 0.02
7.3 Rambu Peringatan bh 2.00 100,000.00 200,000.00 0.02 - - 2.00 100.00 0.02 2.00 100.00 0.02
7.4 Jalur Evakuasi (Escape Route) Ls 1.00 250,000.00 250,000.00 0.03 - - 1.00 100.00 0.03 1.00 100.00 0.03
TOTAL RAMBU - RAMBU YANG DIPERLUKAN 750,000.00 0.08 - 0.08 0.08
8. KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI
8.1 Ahli K3 Konstruksi Oj -
TOTAL KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI - 0.00
9. LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN
KONSTRUKSI
9.1 Alat Pemadam Api Ringan (APAR) bh 1.00 500,000.00 500,000.00 0.05 - - 1.00 100.00 0.05 1.00 100.00 0.05
9.2 Program Inspeksi Ls 1.00 1,500,000.00 1,500,000.00 0.15 - - 1.00 100.00 0.15 1.00 100.00 0.15
9.3 Pelaporan dan Penyeledikan Insiden Ls 1.00 500,000.00 500,000.00 0.05 - - 1.00 100.00 0.05 1.00 100.00 0.05
9.4 Pembuatan Kartu Identitas Pekerja (KIP) Org 10.00 5,000.00 50,000.00 0.01 - - 10.00 100.00 0.01 10.00 100.00 0.01
TOTAL LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN KONSTRUKSI 2,550,000.00 0.26 - 0.26 0.26

A Jumlah Harga Penawaran 989,944,870.91 100.00 - 34.46 34.46


B PPN (10%) 98,994,487.09
C Jumlah (A+B) 1,088,939,358.00
PERSENTASE SAMPAI BULAN INI 34.46
D Jumlah Dibulatkan 1,088,939,358.00

Bulukumba, 12 November 2020


Disetujui, Diketahui, Diperiksa Oleh, Dibuat Oleh,
Pejabat Pembuat Komitmen Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUTR Prov SulSel Dinas PUTR Prov SulSel CV.MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

A.KHADAFI HARUN, ST.,MT. L I L I, ST. IRHAM HARAHAP, ST. VIKA APRILIA DWI PUTRI
NIP. 19811126 200901 1 008 NIP. 19821229 201503 2 001 Site Engineer Direktris
LAPORAN KEMAJUAN BULANAN

Kegiatan : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba Bulan Ke : 02 ( Dua )
Satuan Kerja : Dinas Pekerjaan Umum Dan Tata Ruang Prov. Sulawesi Selatan Bidang Cipta Karya Periode : 13 November S/d 14 Desember 2020
Lokasi : Desa Ara, Kecamatan Bonto Bahari, Kabupaten Bulukumba, Provinsi Sulawesi Selatan No. Kontrak : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
Sumber Dana : Dana Bantuan Provinsi Nilai Kontrak : Rp. 1,088,939,358.00
Tahun Anggaran : 2020 Schedule Pelaksanaan : 16 Oktober S/d 14 Desember 2020

BULAN LALU BULAN INI S/D BULAN INI


VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
NO URAIAN PEKERJAAN
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q

A. PEMBANGUNAN RUANG KULINER, SUVENIR, MUSHOLLAH DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Papan Proyek Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - - 1.00 100.00 0.05
1.2 Bedeng/Direksi Keet M2 5.50 1,512,555.00 8,319,052.50 0.84 5.50 100.00 0.84 - - - 5.50 100.00 0.84

TOTAL PEKERJAAN PERSIAPAN 8,819,052.50 0.89 0.89 0.00 0.89

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Poerplat PP1 (Selasar Samping)
2.1.1.1 Galian Pondasi Poerplat < 1 m M3 0.32 73,837.50 23,628.00 0.00 0.32 100.00 0.00 - - - 0.32 100.00 0.00
2.1.1.2 Urugan Pasir dibawah Pondasi Poerplat T.5 cm M3 0.04 148,335.00 5,933.40 0.00 0.04 100.00 0.00 - - - 0.04 100.00 0.00
2.1.1.3 Urugan Tanah Kembali Pondasi Poerplat M3 0.31 54,175.00 16,794.25 0.00 0.31 100.00 0.00 - - - 0.31 100.00 0.00
2.1.1.4 Pasangan Lantai Kerja bawah Pondasi Poerplat T.5 cm (Beton K300) M3 0.04 1,118,216.00 44,728.64 0.00 0.04 100.00 0.00 - - - 0.04 100.00 0.00
2.1.1.5 Pondasi Poerplat 35x50 cm, T.20 cm - - -
Beton Mutu F'c = 26,4 mpa (K300), Slump (12-2) cm, w/c = 0,52 M3 0.14 1,118,216.00 156,550.24 0.02 0.14 100.00 0.02 - - - 0.14 100.00 0.02
Bekisting 2x Pakai M2 0.56 107,013.50 59,927.56 0.01 0.56 100.00 0.01 - - - 0.56 100.00 0.01
Besi Beton Ø14 SNI Kg 29.40 21,464.85 631,066.59 0.06 29.40 100.00 0.06 - - - 29.40 100.00 0.06
2.1.2 Pekerjaan Pondasi Batu Kali (Badan Bangunan, Mushollah) - - -
2.1.2.1 Galian Tanah Pondasi Batu Kali < 1 m M3 22.73 73,837.50 1,678,326.38 0.17 22.73 100.00 0.17 - - - 22.73 100.00 0.17
2.1.2.2 Urugan Pasir dibawah Pondasi Batu Kali T.5 cm M3 1.08 148,335.00 160,201.80 0.02 1.08 100.00 0.02 - - - 1.08 100.00 0.02
2.1.2.3 Pasangan Aanstamping bawah Pondasi Batu Kali T.10 M3 2.17 382,674.00 830,402.58 0.08 2.17 100.00 0.08 - - - 2.17 100.00 0.08
2.1.2.4 Urugan Tanah Kembali Pondasi Batu Kali M3 10.39 54,175.00 562,878.25 0.06 10.39 100.00 0.06 - - - 10.39 100.00 0.06
2.1.2.5 Pondasi Batu Kali 1 Sp : 3 Pp M3 9.09 827,447.50 7,521,497.78 0.76 9.09 100.00 0.76 - - - 9.09 100.00 0.76
2.1.3 Pekerjaan Pondasi Rollage L.15 cm (Entrance, Selasar Samping) - - - -
2.1.3.1 Galian Tanah Pondasi Rollage < 1 m M3 2.23 73,837.50 164,657.63 0.02 2.23 100.00 0.02 - - - 2.23 100.00 0.02
2.1.3.2 Urugan Pasir dibawah Pondasi Rollage T.5 cm M3 0.45 148,335.00 66,750.75 0.01 0.45 100.00 0.01 - - - 0.45 100.00 0.01
2.1.3.3 Pasangan Lantai Kerja bawah Pondasi Rollage T.5 cm (Beton K300) M3 0.45 1,118,216.00 499,003.89 0.05 0.45 100.00 0.05 - - - 0.45 100.00 0.05
2.1.3.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp M2 20.83 128,436.00 2,675,321.88 0.27 20.83 100.00 0.27 - - - 20.83 100.00 0.27
2.2 Pekerjaan Sloef, Kolom dan Ringbalk - - -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Mushollah) - - -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 1.62 1,118,216.00 1,815,703.23 0.18 1.62 100.00 0.18 - - - 1.62 100.00 0.18
2.2.1.2 Bekisting 2x Pakai M2 10.83 114,438.50 1,239,368.96 0.13 10.83 100.00 0.13 - - - 10.83 100.00 0.13
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI Kg 280.09 21,464.85 6,012,089.84 0.61 280.09 100.00 0.61 - - - 280.09 100.00 0.61
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan, Mushollah) - - -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.88 1,118,216.00 981,234.54 0.10 0.88 100.00 0.10 - - - 0.88 100.00 0.10
2.2.2.2 Bekisting 2x Pakai M2 5.85 193,468.00 1,131,787.80 0.11 5.85 100.00 0.11 - - - 5.85 100.00 0.11
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 181.66 21,464.85 3,899,347.58 0.39 181.66 100.00 0.39 - - - 181.66 100.00 0.39
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Selasar, Westafel, Tempat Wudhu) - -
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 0.34 100.00 0.03 - - - 0.34 100.00 0.03
2.2.3.2 Bekisting 2x Pakai M2 2.26 193,468.00 437,237.68 0.04 2.26 100.00 0.04 - - - 2.26 100.00 0.04
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 70.10 21,464.85 1,504,686.30 0.15 70.10 100.00 0.15 - - - 70.10 100.00 0.15
2.2.4 Pekerjaan Kolom K1 15 x 30 (Selasar Samping) - -
2.2.4.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.62 1,118,216.00 694,412.14 0.07 0.62 100.00 0.07 - - - 0.62 100.00 0.07
2.2.4.2 Bekisting 2x Pakai M2 6.21 193,468.00 1,201,436.28 0.12 6.21 100.00 0.12 - - - 6.21 100.00 0.12
2.2.4.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 99.69 21,464.85 2,139,830.90 0.22 99.69 100.00 0.22 - - - 99.69 100.00 0.22
2.2.5 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan, Mushollah) - -
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 2.08 1,008,161.00 2,097,478.96 0.21 2.08 100.00 0.21 - - - 2.08 100.00 0.21
2.2.5.2 Bekisting 2x Pakai M2 13.87 197,923.00 2,745,192.01 0.28 13.87 100.00 0.28 - - - 13.87 100.00 0.28
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 299.22 21,464.85 6,422,712.42 0.65 299.22 100.00 0.65 - - - 299.22 100.00 0.65
2.2.6 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan) - -
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 0.34 100.00 0.03 - - - 0.34 100.00 0.03
2.2.6.2 Bekisting 2x Pakai M2 2.24 197,923.00 443,347.52 0.04 2.24 100.00 0.04 - - - 2.24 100.00 0.04
2.2.6.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 48.32 21,464.85 1,037,181.55 0.10 48.32 100.00 0.10 - - - 48.32 100.00 0.10
2.2.7 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Mushollah, Pintu Jendela) - -
2.2.7.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.84 1,008,161.00 846,855.24 0.09 0.84 100.00 0.09 - - - 0.84 100.00 0.09
2.2.7.2 Bekisting 2x Pakai M2 5.59 197,923.00 1,106,389.57 0.11 5.59 100.00 0.11 - - - 5.59 100.00 0.11
2.2.7.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 115.53 21,464.85 2,479,834.12 0.25 115.53 100.00 0.25 - - - 115.53 100.00 0.25
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.2.8 Pekerjaan Plat Beton (Selasar Samping, Westafel) - -
2.2.8.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.22 1,008,161.00 221,795.42 0.02 0.22 100.00 0.02 - - - 0.22 100.00 0.02
2.2.8.2 Bekisting 2x Pakai M2 2.21 237,468.00 524,804.28 0.05 2.21 100.00 0.05 - - - 2.21 100.00 0.05
2.2.8.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 54.54 21,464.85 1,170,692.92 0.12 54.54 100.00 0.12 - - - 54.54 100.00 0.12
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) M2 152.03 163,636.00 24,877,581.08 2.51 152.03 100.00 2.51 - - - 152.03 100.00 2.51
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4, Entrance) M2 42.24 242,170.50 10,229,281.92 1.03 42.24 100.00 1.03 - - - 42.24 100.00 1.03
2.5 Pekerjaan Tiang Atap Bitumen Gelombang (Besi Hollow Galvanis 5/10, Entrance) M' 20.40 178,365.00 3,638,646.00 0.37 20.40 100.00 0.37 - - - 20.40 100.00 0.37
2.6 Pekerjaan Rangka Plafond Kalsiboard (Besi Hollow Metal Galvalume 4/4) M2 147.40 102,837.17 15,158,198.37 1.53 147.40 100.00 1.53 - - - 147.40 100.00 1.53

TOTAL PEKERJAAN STRUKTUR 109,840,345.70 11.10 11.10 0.00 11.10

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) M3 8.54 148,335.00 1,266,780.90 0.13 8.54 100.00 0.13 - - - 8.54 100.00 0.13
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) M3 25.63 167,227.00 4,285,636.74 0.43 25.63 100.00 0.43 - - - 25.63 100.00 0.43
3.1.1.3 Rabat Beton bawah Lantai T.5 cm (Keseluruhan, Beton K300) M3 8.54 1,118,216.00 9,549,564.64 0.96 8.54 100.00 0.96 - - - 8.54 100.00 0.96
3.1.1.4 Penutup Lantai Keramik Motif 60x60 (Badan Bangunan, Mushollah) M2 62.94 403,309.50 25,384,299.93 2.56 - - - 59.79 95.00 2.44 59.79 95.00 2.44
3.1.1.5 Penutup Lantai Conwood Deck 6" (Entrance) M2 59.01 866,833.08 51,151,820.09 5.17 - - - 44.30 75.07 3.88 44.30 75.07 3.88
3.1.1.6 Penutup Lantai Andesit Polos 30x30 (Selasar, Tempat Wudhu, Ram) M2 51.05 232,589.50 11,873,693.98 1.20 - - - 51.05 100.00 1.20 51.05 100.00 1.20
3.1.1.7 Plint Lantai Keramik 10x60 (Badan Bangunan, Mushollah) M' 38.85 51,605.03 2,004,855.55 0.20 - - - - - - - - -
3.1.2 Pekerjaan Dinding - -
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Mushollah, 1 Sp : 4 Pp) M2 74.55 242,979.00 18,114,084.45 1.83 74.55 100.00 1.83 - - - 74.55 100.00 1.83
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Selasar Samping, Tempat Wudhu) M2 5.14 65,550.32 336,928.64 0.03 - - - 5.14 100.00 0.03 5.14 100.00 0.03
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm (Badan Bangunan, Mushollah) M2 91.30 60,403.20 5,514,812.16 0.56 91.30 100.00 0.56 - - - 91.30 100.00 0.56
3.1.2.4 Plesteran Ciprat 1 Sp : 2 Pp Tebal 15 mm (Selasar Samping, Antar Kolom) M2 24.84 49,215.10 1,222,503.08 0.12 - - - 24.84 100.00 0.12 24.84 100.00 0.12
3.1.2.5 Dinding Keramik Mozaik 30x60 (Selasar Samping, Westafel, Tempat Wudhu) M2 18.44 410,432.00 7,568,366.08 0.76 - - - 18.44 100.00 0.76 18.44 100.00 0.76
3.1.2.6 Coating Bening (Badan Bangunan, Mushollah, Kolom Luar) M2 127.49 45,973.13 5,861,113.71 0.59 - - - - - - - - -
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) M2 8.64 995,043.50 8,597,175.84 0.87 - - - 8.64 100.00 0.87 8.64 100.00 0.87
3.1.2.8 Dinding Wallpaper Bata L.50 cm (Sisi Dalam) M2 28.13 80,005.50 2,250,554.72 0.23 - - - - - - - - -
3.1.3 Pekerjaan Plafond - -
3.1.3.1 Plafond Kalsiboard (Badan Bangunan, Kemiringan Atap, Mushollah) M2 147.40 44,924.00 6,621,797.60 0.67 - - - 147.40 100.00 0.67 147.40 100.00 0.67
3.1.3.2 Plafond Kalsiboard (Lapis Bawah Atap, Entrance) M2 42.24 44,924.00 1,897,589.76 0.19 - - - 42.24 100.00 0.19 42.24 100.00 0.19
3.2 Pekerjaan Pintu dan Jendela (Badan Bangunan) - -
3.2.1 Pintu P1 (Entrance dan Back Entrance, Badan Bangunan) - -
3.2.1.1 Pasangan Kusen Alumunium Coating P1 (4" x 1 3/4") cm M' 22.40 157,194.40 3,521,154.56 0.36 - - - - - - - -
3.2.1.2 Pasangan Daun Pintu P1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - - - -
3.2.1.3 Pasangan Kaca Mati 5 mm P1 M2 11.20 145,703.80 1,631,882.56 0.16 - - - - - - - - -
3.2.1.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - - - -
3.2.1.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - - - -
3.2.1.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - - - -
3.2.1.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - - - -
3.2.2 Jendela J1 (Badan Bangunan) - -
3.2.2.1 Pasangan Kusen Alumunium Coating J1 (4" x 1 3/4") cm M' 40.60 157,194.40 6,382,092.64 0.64 - - - - - - - -
3.2.2.2 Pasangan Kaca Mati 5 mm J1 M2 8.00 145,703.80 1,165,630.40 0.12 - - - - - - - - -
3.2.3 Pintu PJ1 (Mushollah) - -
3.2.3.1 Pasangan Kusen Alumunium Coating PJ1 (4" x 1 3/4") cm M' 22.20 157,194.40 3,489,715.68 0.35 - - - - - - - -
3.2.3.2 Pasangan Daun Pintu PJ1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - - - -
3.2.3.3 Pasangan Kaca Mati 5 mm P1 M2 8.70 145,703.80 1,267,623.06 0.13 - - - - - - - - -
3.2.3.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - - - -
3.2.3.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - - - -
3.2.3.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - - - -
3.2.3.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - - - -
3.3 Pekerjaan Pengecatan - -
3.3.1 Pengecatan Plafond (1 Plamir ; 1 Cat Dasar : 2 Cat Penutup), (Interior) M2 189.64 35,536.05 6,739,056.52 0.68 - - - - - - - -
3.3.2 Pengecatan Rangka Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 23.76 168,454.00 4,002,467.04 0.40 - - - 23.76 100.00 0.40 23.76 100.00 0.40
3.3.3 Pengecatan Tiang Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 6.12 168,454.00 1,030,938.48 0.10 - - - 6.12 100.00 0.10 6.12 100.00 0.10
3.4 Pekerjaan Atap - -
3.4.1 Atap Bitumen Gelombang (Badan Bangunan, Mushollah) M2 152.03 207,297.09 31,515,376.59 3.18 152.03 100.00 3.18 - - - 152.03 100.00 3.18
3.4.2 Atap Bitumen Gelombang (Entrance) M2 42.24 207,297.09 8,756,229.08 0.88 42.24 100.00 0.88 - - - 42.24 100.00 0.88
3.4.3 Nok Bitumen (Badan Bangunan, Mushollah) M' 14.55 134,101.00 1,951,169.55 0.20 14.55 100.00 0.20 - - - 14.55 100.00 0.20
3.4.4 Listplank (Kalsiplank, Badan Bangunan, Mushollah, Entrance) M' 50.00 70,950.00 3,547,500.00 0.36 50.00 100.00 0.36 - - - 50.00 100.00 0.36

TOTAL PEKERJAAN FINISHING ARSITEKTUR 257,222,142.77 25.98 8.54 10.67 19.21

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel Bh 1.00 1,572,826.75 1,572,826.75 0.16 - - - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt Bh 16.00 353,938.75 5,663,020.00 0.57 - - - 16.00 100.00 0.57 16.00 100.00 0.57
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4.1.3 Pasangan Lampu Down Light 2,5" Outbow LED 5,5 Watt Bh 11.00 305,538.75 3,360,926.25 0.34 - - - 11.00 100.00 0.34 11.00 100.00 0.34
4.1.4 Pasangan Saklar Tunggal Bh 4.00 211,378.75 845,515.00 0.09 - - - 4.00 100.00 0.09 4.00 100.00 0.09
4.1.5 Pasangan Saklar Ganda Bh 2.00 223,478.75 446,957.50 0.05 - - - 2.00 100.00 0.05 2.00 100.00 0.05
4.2 Pasangan Instalasi Stop Kontak - - -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA Bh 10.00 216,218.75 2,162,187.50 0.22 - - - 10.00 100.00 0.22 10.00 100.00 0.22
4.2.2 Pasangan Stop Kontak AC 220 VA/3520 W (AC Split 1 PK) Bh 4.00 253,728.75 1,014,915.00 0.10 - - - 4.00 100.00 0.10 4.00 100.00 0.10
4.3 Pasangan Instalasi Jaringan AC M' 30.00 108,772.68 3,263,180.25 0.33 - - - 30.00 100.00 0.33 30.00 100.00 0.33
4.3.1 Pasangan AC Split 1 PK Bh 3.00 3,365,799.34 10,097,398.03 1.02 - - - 1.50 50.00 0.51 1.50 50.00 0.51
4.4 Pasangan Penangkal Petir Ls 1.00 2,500,000.00 2,500,000.00 0.25 - - - 1.00 100.00 0.25 1.00 100.00 0.25
4.5 Pasangan Instalasi Jaringan Kabel Fiber Optic (CCTV) Ttk 6.00 786,326.75 4,717,960.50 0.48 - - - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2MP Bh 6.00 656,975.00 3,941,850.00 0.40 - - - - - - - - -
4.5.2 Pasangan NVR Channel Set 1.00 5,023,975.00 5,023,975.00 0.51 - - - - - - - - -
4.5.3 Pasangan Monitor LCD 32" Bh 1.00 2,944,975.00 2,944,975.00 0.30 - - - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm M' 12.00 20,442.68 245,312.10 0.02 - - - - - - - - -
4.6.1 Pasangan Horn Speaker Bh 6.00 494,826.75 2,968,960.50 0.30 - - - - - - - - -
4.6.2 Pasangan Volume Kontrol Set 1.00 252,826.75 252,826.75 0.03 - - - - - - - - -
4.6.3 Pasangan Perangkat Sound System Set 1.00 4,565,000.00 4,565,000.00 0.46 - - - - - - - - -
4.6.4 Pasangan TB-Sound System Set 1.00 5,846,326.75 5,846,326.75 0.59 - - - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25Kg) Ttk 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - - - -
4.8 Pasangan Instalasi Jaringan Kabel Fiber Optic (Akses Point) Ttk 3.00 786,326.75 2,358,980.25 0.24 - - - - - - - - -
4.8.1 Pasangan Server Set 1.00 7,578,826.75 7,578,826.75 0.77 - - - - - - - - -
4.8.2 Pasangan Akses Point Bh 1.00 2,034,826.75 2,034,826.75 0.21 - - - - - - - - -
4.8.3 Pasangan Switch HUB Bh 1.00 2,843,326.75 2,843,326.75 0.29 - - - - - - - - -
4.9 Pasangan Instalasi PLN Power (Inc. Jalur ke Mushollah dan Toilet) Ls 1.00 9,000,000.00 9,000,000.00 0.91 - - - - - - - - -

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 94,450,073.38 9.54 0.00 2.46 2.46

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVC Type AW Diameter 3/4" (Air Bersih Sambungan dari Tandon) M' 33.00 28,300.25 933,908.25 0.09 - - - 16.50 50.00 0.05 16.50 50.00 0.05
5.2 Pipa PVC Type AW Diameter 3" (Air Kotor ke Drainase Lingkungan) M' 25.80 135,531.00 3,496,699.80 0.35 - - - 2.58 10.00 0.04 2.58 10.00 0.04
5.3 Pasangan 1 Bh Wastafel Bh 2.00 3,934,865.00 7,869,730.00 0.79 - - - 2.00 100.00 0.79 2.00 100.00 0.79
5.4 Pasangan 1 Bh Wastafel Cuci Piring (WCP) Bh 1.00 890,945.00 890,945.00 0.09 - - - 1.00 100.00 0.09 1.00 100.00 0.09
5.5 Pasangan 1 Bh Floor Drain Bh 2.00 41,112.50 82,225.00 0.01 - - - 2.00 100.00 0.01 2.00 100.00 0.01
5.6 Pasangan 1 Bh Kran Dia. 1/2" atau 3/4" Bh 10.00 102,217.50 1,022,175.00 0.10 - - - 10.00 100.00 0.10 10.00 100.00 0.10
5.7 Pasangan 1 Bh Kran Wastafel Dia. 1/2" atau 3/4" Bh 3.00 335,417.50 1,006,252.50 0.10 - - - 3.00 100.00 0.10 3.00 100.00 0.10
5.8 Pasangan 1 Bh Stop Kran (Gate Valve) Dia. 3/4" Bh 1.00 141,417.50 141,417.50 0.01 - - - 0.10 10.00 0.00 0.10 10.00 0.00
5.9 Pasangan Mesin Air Bh 1.00 741,000.00 741,000.00 0.07 - - - - - - - - -
5.10 Menara Reservoir 200x150x350 cm - -
5.10.1 Pekerjaan Pondasi Pedestal Pd1 - -
5.10.1.1 Galian Tanah Pondasi Poerplat < 1 m M3 1.62 73,837.50 119,616.75 0.01 - - - - - - - - -
5.10.1.2 Urugan Tanah Kembali Pondasi Poerplat M3 0.43 54,175.00 23,295.25 0.00 - - - - - - - - -
5.10.1.3 Tiang Pondasi Pedestal 50x50 cm - - - -
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.80 1,118,216.00 894,572.80 0.09 - - - - - - - - -
Bekisting 2x Pakai M2 3.20 193,468.00 619,097.60 0.06 - - - - - - - - -
Besi Beton Ø12 SNI, Ø8 SNI Kg 49.44 21,464.85 1,061,130.60 0.11 - - - - - - - - -
5.10.1.4 Pondasi Poerplat 90x90 cm, T.20 cm - -
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.65 1,118,216.00 726,840.40 0.07 - - - - - - - - -
Bekisting 2x Pakai M2 1.44 107,013.50 154,099.44 0.02 - - - - - - - - -
Besi Beton Ø14 SNI Kg 214.35 21,464.85 4,600,940.54 0.46 - - - - - - - - -
5.10.2 Rangka Tengah dan Lantai Menara (Besi Hollow Galvanis 4/4) M2 34.82 244,970.00 8,529,855.40 0.86 - - - - - - - -
5.10.3 Rangka Utama Menara (Besi Hollow Galvanis 5/10) M' 32.28 179,454.00 5,792,775.12 0.59 - - - - - - - -
5.10.4 Plat Baja Lantai Menara T.3 mm M2 3.00 740,164.86 2,220,494.57 0.22 - - - - - - - - -
5.10.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) M2 5.00 244,970.00 1,224,850.00 0.12 - - - - - - - -

TOTAL PEKERJAAN PLAMBING DAN SANITASI 42,151,921.52 4.26 0.00 1.18 1.18

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Pek. Pembersian Awal m2 81.86 17,600.00 1,440,780.00 0.15 81.86 100.00 0.15 - - - 81.86 100.00 0.15
1.2 Pek. Pengukuran & Pemasangan Bouwplank m1 48.60 106,461.25 5,174,016.75 0.52 48.60 100.00 0.52 - - - 48.60 100.00 0.52

TOTAL PEKERJAAN PERSIAPAN 6,614,796.75 0.67 0.67 0.00 0.67

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Batu Kali (Badan Bangunan,Ruang Bilas)
2.1.1.1 Galian Pondasi Batu Kali < 1 m m3 22.05 73,892.50 1,629,329.63 0.16 6.62 30.00 0.05 - - - 6.62 30.00 0.05
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.1.1.2 Urugan Pasir Dibawah Pondasi Batu Kali T.5 cm m3 1.05 174,757.00 183,494.85 0.02 1.05 100.00 0.02 - - - 1.05 100.00 0.02
2.1.1.3 Pasangan Aanstamping Bawah Pondasi Batu Kali T.10 cm m3 2.10 392,699.70 824,669.37 0.08 2.10 100.00 0.08 - - - 2.10 100.00 0.08
2.1.1.4 Urugan Tanah Kembali Pondasi Batu Kali m3 10.08 54,285.00 547,192.80 0.06 3.02 30.00 0.02 - - - 3.02 30.00 0.02
2.1.1.5 Pondasi Batu Kali 1 Sp : 3 Pp m3 8.82 824,945.00 7,276,014.90 0.73 8.82 100.00 0.73 - - - 8.82 100.00 0.73
2.1.2 Perjaan Pondasi Rollage L.15 cm (Selasar) - -
2.1.2.1 Galian Tanah Pondasi Rollage < 1 m m3 1.52 73,892.50 112,501.33 0.01 0.15 10.00 0.00 - - - 0.15 10.00 0.00
2.1.2.2 Urugan Pasir Dibawah Pondasi Rollage T.5 cm m3 0.30 174,757.00 53,213.51 0.01 0.03 10.00 0.00 - - - 0.03 10.00 0.00
2.1.2.3 Pasangan Lantai Kerja Bawah Pondasi Rollage T.5 cm (Beton K300) m3 0.30 1,118,398.60 340,552.37 0.03 0.30 100.00 0.03 - - - 0.30 100.00 0.03
2.1.2.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp m3 14.21 128,260.00 1,822,574.60 0.18 14.21 100.00 0.18 - - - 14.21 100.00 0.18
2.2 Pekerjaan Sloef, Kolom, Plat dan Ringbalk - - -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Ruang Bilas) - - -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 m3 1.41 1,118,398.60 1,580,297.22 0.16 1.41 100.00 0.16 - - - 1.41 100.00 0.16
2.2.1.2 Bekisting 2x Pakai m2 9.42 114,467.10 1,078,280.08 0.11 9.42 100.00 0.11 - - - 9.42 100.00 0.11
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI kg 243.74 21,465.73 5,232,043.29 0.53 243.74 100.00 0.53 - - - 243.74 100.00 0.53
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan) - - -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slum (12 - 2) cm, w/c = 0,52 m3 0.48 1,118,398.60 533,476.13 0.05 0.48 100.00 0.05 - - - 0.48 100.00 0.05
2.2.2.2 Bekisting 2x Pakai m2 3.18 193,504.30 615,343.67 0.06 3.18 100.00 0.06 - - - 3.18 100.00 0.06
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI kg 98.75 21,465.73 2,119,732.25 0.21 98.75 100.00 0.21 - - - 98.75 100.00 0.21
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Ruang Bilas) - - -
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.25 1,008,343.60 249,111.29 0.03 0.25 100.00 0.03 - - - 0.25 100.00 0.03
2.2.3.2 Bekisting 2x Pakai m2 1.65 193,504.30 318,701.58 0.03 1.65 100.00 0.03 - - - 1.65 100.00 0.03
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI kg 51.14 21,465.73 1,097,861.33 0.11 51.14 100.00 0.11 - - - 51.14 100.00 0.11
2.2.4 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan) - - -
2.2.4.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.04 1,008,343.60 1,043,635.63 0.11 1.04 100.00 0.11 - - - 1.04 100.00 0.11
2.2.4.2 Bekisting 2x Pakai m2 6.90 197,959.30 1,365,919.17 0.14 6.90 100.00 0.14 - - - 6.90 100.00 0.14
2.2.4.3 Besi Beton Ø12 SNI, Ø6 SNI kg 148.86 21,465.73 3,195,302.68 0.32 148.86 100.00 0.32 - - - 148.86 100.00 0.32
2.2.5 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan) - - -
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.09 1,008,343.60 1,103,531.24 0.11 1.09 100.00 0.11 - - - 1.09 100.00 0.11
2.2.5.2 Bekisting 2x Pakai m2 14.59 197,959.30 2,888,622.11 0.29 14.59 100.00 0.29 - - - 14.59 100.00 0.29
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI kg 157.40 21,465.73 3,378,705.12 0.34 157.40 100.00 0.34 - - - 157.40 100.00 0.34
2.2.6 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Pintu Jendela) - -
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.15 1,008,343.60 148,831.52 0.02 0.15 100.00 0.02 - - - 0.15 100.00 0.02
2.2.6.2 Bekisting 2x Pakai m2 0.98 197,959.30 194,791.95 0.02 0.98 100.00 0.02 - - - 0.98 100.00 0.02
2.2.6.3 Besi Beton Ø10 SNI, Ø6 SNI kg 20.35 21,465.73 436,752.39 0.04 20.35 100.00 0.04 - - - 20.35 100.00 0.04
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) m2 59.01 163,856.00 9,669,142.56 0.98 59.01 100.00 0.98 - - - 59.01 100.00 0.98
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4) m2 48.59 102,876.77 4,998,782.09 0.50 48.59 100.00 0.50 - - - 48.59 100.00 0.50
2.5 Pekerjaan Rangka Plafond dan Dinding Dalam PVC Shunda (Besi Hollow Metal Galvalume 4/4) m2 56.16 102,876.77 5,777,559.22 0.58 - - - - - - - -

TOTAL PEKERJAAN STRUKTUR 59,815,965.86 6.04 5.29 0.00 5.29

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) m3 4.09 174,757.00 715,280.40 0.07 4.09 100.00 0.07 - - - 4.09 100.00 0.07
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) m3 12.28 167,345.00 2,054,804.70 0.21 12.28 100.00 0.21 - - - 12.28 100.00 0.21
3.1.1.3 Rabat Beton T.5 cm (Keseluruhan, Beton K300) m3 4.09 1,118,398.60 4,577,605.47 0.46 4.09 100.00 0.46 - - - 4.09 100.00 0.46
3.1.1.4 Penutup Lantai Keramik Tekstur 60x60 (Badan Bangunan) m2 36.93 413,098.40 15,255,723.91 1.54 29.54 80.00 1.23 - - 29.54 80.00 1.23
3.1.1.5 Penutup Lantai Andesit Polos 30x30 (Selasar, Ruang Bilas) m2 45.89 284,369.80 13,049,730.12 1.32 - - - - - - - -
3.1.1.6 Penutup Plat Wastafel (Granit 60x60, Toilet Pria dan Wanita) m2 2.20 841,621.73 1,851,567.81 0.19 - - - - - - - -
3.1.2 Pekerjaan Dinding - - -
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Selasar, 1 Sp : 4 Pp) 90.64 242,533.50 21,983,236.44 2.22 72.51 80.00 1.78 18.13 20.00 0.44 90.64 100.00 2.22
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Wc ) 30.00 65,473.32 1,964,199.60 0.20 24.00 80.00 0.16 6.00 20.00 0.04 30.00 100.00 0.20
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm 121.28 60,304.20 7,313,693.38 0.74 97.02 80.00 0.59 24.26 20.00 0.15 121.28 100.00 0.74
3.1.2.4 Coating Bening 121.28 46,853.13 5,682,347.00 0.57 - - - - - - - - -
3.1.2.5 Dinding Andesit Polos 30x30 cm ( Wc, Ruang Bilas ) 56.52 284,369.80 16,072,581.10 1.62 - - - - - - - -
3.1.2.6 Dinding Keramik 30x60 cm ( Sisi Dalam ) 69.88 370,557.00 25,894,523.16 2.62 - - - - - - - -
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) 9.00 995,076.50 8,955,688.50 0.90 - - - 9.00 100.00 0.90 9.00 100.00 0.90
3.1.2.8 Cubicle Panel + Accessories (Pintu Wc dan Partisi Urinoir) 10.86 1,360,000.00 14,769,600.00 1.49 - - - 10.86 100.00 1.49 10.86 100.00 1.49
3.1.2.9 Dinding Bitumen Gelombang 48.59 201,749.24 9,802,995.57 0.99 - - - 48.59 100.00 0.99 48.59 100.00 0.99
3.1.2.10 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Pria) 1.00 1,200,000.00 1,200,000.00 0.12 - - - - - - - - -
3.1.2.11 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Wanita) 1.00 750,000.00 750,000.00 0.08 - - - - - - - - -
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.1.3 Plafond dan Dinding Dalam Shunda ( Badan Bangunan ) 56.16 125,878.50 7,069,336.56 0.71 - - - 56.16 100.00 0.71 56.16 100.00 0.71
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.2 Pekerjaan Pintu dan Jendela ( Badan Bangunan ) - - -
3.2.1 Pintu P1 - - -
3.2.1.1 Pasangan Kusen Almunium Coating P1 (4" x 13/4") cm 10.96 157,199.02 1,722,901.26 0.17 - - - - - - - -
3.2.1.2 Pasangan Daun Pintu P1 (Panel Almunium Coating - Coating) 4.30 870,323.19 3,742,389.72 0.38 - - - - - - - - -
3.2.1.3 Pasangan Kunci Tanam 2x Slag P1 2.00 416,663.50 833,327.00 0.08 - - - - - - - - -
3.2.1.4 Pasangan ensel P1 6.00 61,225.56 367,353.36 0.04 - - - - - - - - -
3.2.1.5 Pasangan Doorcloser P1 2.00 241,902.10 483,804.20 0.05 - - - - - - - - -
3.2.1.6 Pasangan Handle P1 2.00 229,802.10 459,604.20 0.05 - - - - - - - - -
3.2.2 Jendela J1 - - -
3.2.2.1 Pasangan Kusen Almunium Coating J1 (4" x 13/4") cm 28.80 157,199.02 4,527,331.78 0.46 - - - - - - - -
3.2.2.2 Pasangan Kaca Mati 5 mm J1 0.60 145,705.56 87,423.34 0.01 - - - - - - - - -
3.2.3 Jendela J2 - -
3.2.3.1 Pasangan Kusen Almunium Coating J2 (4" x 13/4") cm 55.20 157,199.02 8,677,385.90 0.88 - - - - - - - - -
3.2.3.2 Pasangan Kaca Mati 5 mm J2 0.90 145,705.56 131,135.00 0.01 - - - - - - - - -
3.3. Pengecetan Plafond (1 Plamir : 1 Cat Dasar : 2 Cat Penutup), (Interior) 56.16 43,550.65 2,445,804.50 0.25 - - - - - - - -
3.4 Pekerjaan Atap - - -
3.4.1 Atap Bitumen Gelombang (Badan Bangunan) 59.01 201,749.24 11,905,222.65 1.20 - - - 29.51 50.00 0.60 29.51 50.00 0.60
3.4.2 Nok Bitumen (Badan Bangunan) 35.25 143,629.20 5,062,929.30 0.51 - - - 35.25 100.00 0.51 35.25 100.00 0.51
3.4.3 Listplank (Kasiplank, Badan Bangunan, Enterance) 39.08 70,972.00 2,773,585.76 0.28 - - - - - - - -

TOTAL PEKERJAAN FINISHING ARSITEKTUR 202,183,111.69 20.42 4.50 5.85 10.35

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel 1.00 1,803,826.75 1,803,826.75 0.18 - - - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt 10.00 353,938.75 3,539,387.50 0.36 - - - 10.00 100.00 0.36 10.00 100.00 0.36
4.1.3 Pasangan Lampu Down Light 2.5" Outbow LED 5.5 Watt 12.00 305,538.75 3,666,465.00 0.37 - - - 12.00 100.00 0.37 12.00 100.00 0.37
4.1.4 Pasangan Saklar Ganda 5.00 223,478.75 1,117,393.75 0.11 - - - 5.00 100.00 0.11 5.00 100.00 0.11
4.2 Pasangan Instalasi Stop Kontak - - -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA 3.00 216,218.75 648,656.25 0.07 - - - 3.00 100.00 0.07 3.00 100.00 0.07
4.2.2 Pasangan Stop Kontak Wall Exhauser 6.00 216,218.75 1,297,312.50 0.13 - - - 6.00 100.00 0.13 6.00 100.00 0.13
4.3 Pasangan Instalasi Jaringan Wall Exhauser 12.00 108,772.68 1,305,272.10 0.13 - - - 12.00 100.00 0.13 12.00 100.00 0.13
4.3.1 Pasangan Wall Exhauser 12 Inch - FV30RUN 6.00 513,500.00 3,081,000.00 0.31 - - - 6.00 100.00 0.31 6.00 100.00 0.31
4.4 Pasangan Penangkal Petir 1.00 3,500,000.00 3,500,000.00 0.35 - - - 0.50 50.00 0.18 0.50 50.00 0.18
4.5 Pasangan Instlasi Jaringan Kabel Fiber Optic (CCTV) 3.00 786,326.75 2,358,980.25 0.24 - - - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2 MP (Luar Bangunan, Sambungan Dari Mini Resto) 3.00 656,975.00 1,970,925.00 0.20 - - - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm 4.00 20,442.68 81,770.70 0.01 - - - - - - - - -
4.6.1 Pasangan Horn Speaker (Sambungan Dari Mini Resto) 2.00 494,826.75 989,653.50 0.10 - - - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25 kg) 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - - - -
4.8 Pasangan Instalasi PLN Power 1.00 10,000,000.00 10,000,000.00 1.01 - - - - - - - - -

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 44,560,643.30 4.50 0.00 1.66 1.66

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVc Tipe AW Diameter 3/4" (Air Bersih Dari Sumur Bor / PDAM Reservoir) m1 18.50 28,304.65 523,636.03 0.05 - - - - - - - - -
5.2 Pipa PVC Tipe AW Diameter 3/4" (Distribusi Air Bersih Dari Reservoir) m1 26.50 28,304.65 750,073.23 0.08 - - - 13.25 50.00 0.04 13.25 50.00 0.04
5.3 Pipa PVC Tipe AW Diameter 3" (Air Kotor Ke Drainase Lingkungan) m1 23.00 135,539.80 3,117,415.40 0.31 - - - 23.00 100.00 0.31 23.00 100.00 0.31
5.4 Pipa PVC Tipe AW Diameter 4" (Disposal) m1 18.00 186,689.80 3,360,416.40 0.34 - - - 18.00 100.00 0.34 18.00 100.00 0.34
5.5 Pasangan 1 bh Closet Duduk / Monoblock (TOTO) bh 6.00 3,655,597.00 21,933,582.00 2.22 - - - 2.00 33.33 0.74 2.00 33.33 0.74
5.6 Pasangan 1 bh Wastafel (TOTO) 3.00 3,571,942.00 10,715,826.00 1.08 - - - 3.00 100.00 1.08 3.00 100.00 1.08
5.7 Pasangan 1 bh Uninoir (TOTO) 2.00 6,665,285.00 13,330,570.00 1.35 - - - - - - - -
5.8 Pasangan 1 bh Floor Drain 9.00 41,123.50 370,111.50 0.04 - - - 9.00 100.00 0.04 9.00 100.00 0.04
5.9 Pasangan 1 bh Kran dia. 1/2' atau 3/4" 8.00 102,228.50 817,828.00 0.08 - - - 8.00 100.00 0.08 8.00 100.00 0.08
5.10 Pasangan 1 bh Kran wastafel dia. 1/2' atau 3/4" 2.00 335,428.50 670,857.00 0.07 - - - 2.00 100.00 0.07 2.00 100.00 0.07
5.11 Pasangan 1 bh shower closet dia. 1/2' atau 3/4" 6.00 142,928.50 857,571.00 0.09 - - - 4.00 66.67 0.06 4.00 66.67 0.06
5.12 Pasangan 1 bh shower Wall dia. 1/2' atau 3/4" (Ruang Bilas) 4.00 1,435,428.50 5,741,714.00 0.58 - - - 2.00 50.00 0.29 2.00 50.00 0.29
5.13 Pasangan 1 bh Stop Kran (Gate Valve) dia. 3/4" 2.00 141,428.50 282,857.00 0.03 - - - 2.00 100.00 0.03 2.00 100.00 0.03
5.14 Pasangan Mesin Air 1.00 741,000.00 741,000.00 0.07 - - - - - - - - -
5.14b Pasangan Mesin Pemanas Air 1.00 5,000,000.00 5,000,000.00 0.51 - - - - - - - - -
5.15 Septictank Biotank Kap. 4m3 1.00 20,380,000.00 20,380,000.00 2.06 - - - 0.50 50.00 1.03 0.50 50.00 1.03
5.16 Pasangan Sumur Bor Jet Pump 30.00 350,000.00 10,500,000.00 1.06 - - - - - - - - -
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.17 Reservoir 1200 Liter 1.00 1,850,000.00 1,850,000.00 0.19 - - - - - - - -
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.18 Reservoir 200x150x350 cm - - -
5.18.1 Pekerjaan Pondasi Pedestal Pd1 - - -
5.18.1.1 Galian Tanah Pondasi Poerplat < 1m 1.62 74,250.00 120,285.00 0.01 - - - - - - - - -
5.18.1.2 Urugan Tanah Kembali Pondasi Poerplat 0.43 55,000.00 23,760.00 0.00 - - - - - - - - -
5.18.1.3 Tiang Pondasi Pedestal 50x50 cm - -
Beton Mutu fc = 26,6 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.80 1,485,144.21 1,188,115.37 0.12 - - - - - - - - -
Bekisting 2x Pakai 3.20 193,504.30 619,213.76 0.06 - - - - - - - - -
Besi Beton Ø12, Ø8 49.44 21,465.73 1,061,174.10 0.11 - - - - - - - - -
5.18.1.4 Pondasi Poerplat 90x90 cm,T.20 cm - - -
Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.65 1,485,144.21 962,373.45 0.10 - - - - - - - - -
Bekisting 2x Pakai 1.44 124,547.50 179,348.40 0.02 - - - - - - - - -
Besi Beton Ø14 SNI 214.35 21,465.73 4,601,114.73 0.46 - - - - - - - - -
5.18.2 Rangkai Tengah Dan Lantai Menara (Besi Hollow Galvanis 4/4) 34.82 244,970.00 8,529,855.40 0.86 - - - - - - - -
5.18.3 Rangka Utama menara ( Besi Hollow Galvanis 5/10 32.28 179,454.00 5,792,775.12 0.59 - - - - - - - -
5.18.4 Tplat Baja Lantai Menara T.3mm 3.00 740,164.86 2,220,494.57 0.22 - - - - - - - - -
5.18.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) 5.00 244,970.00 1,224,850.00 0.12 - - - - - - - -

TOTAL PEKERJAAN PLAMBING DAN SANITASI 127,466,817.45 12.88 - 4.11 4.11

6. PEKERJAAN AKHIR - - -
6.1 Pembersihan Sisa Pekerjaan Ls 1.00 2,400,000.00 2,400,000.00 0.24 - - - - - - - - -

TOTAL PEKERJAAN AKHIR 2,400,000.00 0.24 0.00 0.00 0.00

C. PENERAPAN SMKK

1. PENYIAPAN RKK
1.1 Pembuatan Dokumen Rencana Keselamatan Konstruksi
1.2 Pembuatan Prosedur dan instruksi kerja Set 1.00 2,000,000.00 2,000,000.00 0.20 1.00 100.00 0.20 - - - 1.00 100.00 0.20
1.3 Penyiapan formulir
TOTAL PENYIAPAN RKK 2,000,000.00 0.20 0.20 - 0.20
2. SOSIALISASI, PROMOSI DAN PELATIHAN
2.1 Induksi K3 (Safety Induction) Org 5.00 7,500.00 37,500.00 0.00 0.50 10.00 0.00 - - - 0.50 10.00 0.00
2.2 Pengarahan K3 (Safety Briefing) Org 5.00 15,000.00 75,000.00 0.01 5.00 100.00 0.01 - - - 5.00 100.00 0.01
2.3 Pelatihan K3 - - -
2.3.1 Bekerja di ketinggian Org 4.00 7,500.00 30,000.00 0.00 4.00 100.00 0.00 - - - 4.00 100.00 0.00
2.3.2 Penggunaan Bahan Kimia (MSDS) Org 2.00 7,500.00 15,000.00 0.00 2.00 100.00 0.00 - - - 2.00 100.00 0.00
2.4 Simulasi K3 Org 5.00 7,500.00 37,500.00 0.00 5.00 100.00 0.00 - - - 5.00 100.00 0.00
2.5 Spanduk (Banner) Lb 1.00 150,000.00 150,000.00 0.02 1.00 100.00 0.02 - - - 1.00 100.00 0.02
2.6 Poster 2 2.00 50,000.00 100,000.00 0.01 2.00 100.00 0.01 - - - 2.00 100.00 0.01
2.7 Papan Informasi K3 1 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - - 1.00 100.00 0.05
TOTAL SOSIALISASI, PROMOSI DAN PELATIHAN 945,000.00 0.10 0.09 - 0.09
3. ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI
3.1 APK
3.1.1 Tali Keselamatan (Life Line) Ls 1.00 1,700,000.00 1,700,000.00 0.17 1.00 100.00 0.17 - - - 1.00 100.00 0.17
3.1.2 Pembatas Area (Restricted Area) Ls 1.00 2,000,000.00 2,000,000.00 0.20 1.00 100.00 0.20 - - - 1.00 100.00 0.20
3.2 APD - -
3.2.1 Topi Pelindung (Safety Helmet) Bh 10.00 75,000.00 750,000.00 0.08 10.00 100.00 0.08 - - - 10.00 100.00 0.08
3.2.2 Pelindung Mata (Googles, Spectacles) Bh 5.00 25,000.00 125,000.00 0.01 5.00 100.00 0.01 - - - 5.00 100.00 0.01
3.2.3 Pelindung Pernapasan dan Mulut (Masker) Bh 100.00 5,000.00 500,000.00 0.05 100.00 100.00 0.05 - - - 100.00 100.00 0.05
3.2.4 Sarung Tangan (Safety Gloves) Psg 10.00 15,000.00 150,000.00 0.02 10.00 100.00 0.02 - - - 10.00 100.00 0.02
3.2.5 Sepatu Keselamatan (Safety Shoes) Psg 10.00 350,000.00 3,500,000.00 0.35 10.00 100.00 0.35 - - - 10.00 100.00 0.35
3.2.6 Penunjang Seluruh Tubuh (Full Body Harness) Bh 2.00 500,000.00 1,000,000.00 0.10 2.00 100.00 0.10 - - - 2.00 100.00 0.10
3.2.7 Rompi Keselamatan (Safety Vest) Bh 10.00 25,000.00 250,000.00 0.03 10.00 100.00 0.03 - - - 10.00 100.00 0.03
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 9,975,000.00 1.01 1.01 - 1.01
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4. ASURANSI DAN PERIZINAN
4.1 Asuransi Ls 1.00 3,000,000.00 3,000,000.00 0.30 1.00 100.00 0.30 - - - 1.00 100.00 0.30
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 3,000,000.00 0.30 0.30 - 0.30
5. PERSONEL K3 KONSTRUKSI
5.1 Ahli K3 Konstruksi -
5.2 Petugas K3 Konstruksi Ob 4.00 3,675,000.00 14,700,000.00 1.48 4.00 100.00 1.48 - - - 4.00 100.00 1.48
TOTAL PERSONEL K3 KONSTRUKSI 14,700,000.00 1.48 1.48 - 1.48
6. FASILITAS, SARANA DAN PRASARANA KESEHATAN
6.1 Peralatan P3K (Kotak P3K, Tandu, Obat Luka, Perban, dll) Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - - 1.00 100.00 0.05
TOTAL FASILITAS, SARANA DAN PRASARANA KESEHATAN 500,000.00 0.05 0.05 - 0.05
7. RAMBU - RAMBU YANG DIPERLUKAN
7.1 Rambu Petunjuk bh 2.00 75,000.00 150,000.00 0.02 2.00 100.00 0.02 - - - 2.00 100.00 0.02
7.2 Rambu Larangan bh 2.00 75,000.00 150,000.00 0.02 2.00 100.00 0.02 - - - 2.00 100.00 0.02
7.3 Rambu Peringatan bh 2.00 100,000.00 200,000.00 0.02 2.00 100.00 0.02 - - - 2.00 100.00 0.02
7.4 Jalur Evakuasi (Escape Route) Ls 1.00 250,000.00 250,000.00 0.03 1.00 100.00 0.03 - - - 1.00 100.00 0.03
TOTAL RAMBU - RAMBU YANG DIPERLUKAN 750,000.00 0.08 0.08 - 0.08
8. KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI
8.1 Ahli K3 Konstruksi Oj -
TOTAL KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI - 0.00
9. LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN
KONSTRUKSI
9.1 Alat Pemadam Api Ringan (APAR) bh 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - - 1.00 100.00 0.05
9.2 Program Inspeksi Ls 1.00 1,500,000.00 1,500,000.00 0.15 1.00 100.00 0.15 - - - 1.00 100.00 0.15
9.3 Pelaporan dan Penyeledikan Insiden Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - - 1.00 100.00 0.05
9.4 Pembuatan Kartu Identitas Pekerja (KIP) Org 10.00 5,000.00 50,000.00 0.01 10.00 100.00 0.01 - - - 10.00 100.00 0.01
TOTAL LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN KONSTRUKSI 2,550,000.00 0.26 0.26 - 0.26

A Jumlah Harga Penawaran 989,944,870.91 100.00 34.46 25.92 60.38


B PPN (10%) 98,994,487.09
C Jumlah (A+B) 1,088,939,358.00
PERSENTASE SAMPAI BULAN INI 60.38
D Jumlah Dibulatkan 1,088,939,358.00

Bulukumba, 14 Desember 2020


Disetujui, Diketahui, Diperiksa Oleh, Dibuat Oleh,
Pejabat Pembuat Komitmen Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUTR Prov SulSel Dinas PUTR Prov SulSel CV.MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

A.KHADAFI HARUN, ST.,MT. L I L I, ST. IRHAM HARAHAP, ST. VIKA APRILIA DWI PUTRI
NIP. 19811126 200901 1 008 NIP. 19821229 201503 2 001 Site Engineer Direktris
LAPORAN KEMAJUAN BULANAN

Kegiatan : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba Bulan Ke : 02 ( Dua )
Satuan Kerja : Dinas Pekerjaan Umum Dan Tata Ruang Prov. Sulawesi Selatan Bidang Cipta Karya Periode : 13 November S/d 14 Desember 2020
Lokasi : Desa Ara, Kecamatan Bonto Bahari, Kabupaten Bulukumba, Provinsi Sulawesi Selatan No. Kontrak : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
Sumber Dana : Dana Bantuan Provinsi Nilai Kontrak : Rp. 1,088,939,358.00
Tahun Anggaran : 2020 Schedule Pelaksanaan : 16 Oktober S/d 14 Desember 2020

BULAN LALU BULAN INI S/D BULAN INI


VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
NO URAIAN PEKERJAAN
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q

A. PEMBANGUNAN RUANG KULINER, SUVENIR, MUSHOLLAH DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Papan Proyek Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - - 1.00 100.00 0.05
1.2 Bedeng/Direksi Keet M2 5.50 1,512,555.00 8,319,052.50 0.84 5.50 100.00 0.84 - - - 5.50 100.00 0.84

TOTAL PEKERJAAN PERSIAPAN 8,819,052.50 0.89 0.89 0.00 0.89

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Poerplat PP1 (Selasar Samping)
2.1.1.1 Galian Pondasi Poerplat < 1 m M3 0.32 73,837.50 23,628.00 0.00 0.32 100.00 0.00 - - - 0.32 100.00 0.00
2.1.1.2 Urugan Pasir dibawah Pondasi Poerplat T.5 cm M3 0.04 148,335.00 5,933.40 0.00 0.04 100.00 0.00 - - - 0.04 100.00 0.00
2.1.1.3 Urugan Tanah Kembali Pondasi Poerplat M3 0.31 54,175.00 16,794.25 0.00 0.31 100.00 0.00 - - - 0.31 100.00 0.00
2.1.1.4 Pasangan Lantai Kerja bawah Pondasi Poerplat T.5 cm (Beton K300) M3 0.04 1,118,216.00 44,728.64 0.00 0.04 100.00 0.00 - - - 0.04 100.00 0.00
2.1.1.5 Pondasi Poerplat 35x50 cm, T.20 cm - - -
Beton Mutu F'c = 26,4 mpa (K300), Slump (12-2) cm, w/c = 0,52 M3 0.14 1,118,216.00 156,550.24 0.02 0.14 100.00 0.02 - - - 0.14 100.00 0.02
Bekisting 2x Pakai M2 0.56 107,013.50 59,927.56 0.01 0.56 100.00 0.01 - - - 0.56 100.00 0.01
Besi Beton Ø14 SNI Kg 29.40 21,464.85 631,066.59 0.06 29.40 100.00 0.06 - - - 29.40 100.00 0.06
2.1.2 Pekerjaan Pondasi Batu Kali (Badan Bangunan, Mushollah) - - -
2.1.2.1 Galian Tanah Pondasi Batu Kali < 1 m M3 22.73 73,837.50 1,678,326.38 0.17 22.73 100.00 0.17 - - - 22.73 100.00 0.17
2.1.2.2 Urugan Pasir dibawah Pondasi Batu Kali T.5 cm M3 1.08 148,335.00 160,201.80 0.02 1.08 100.00 0.02 - - - 1.08 100.00 0.02
2.1.2.3 Pasangan Aanstamping bawah Pondasi Batu Kali T.10 M3 2.17 382,674.00 830,402.58 0.08 2.17 100.00 0.08 - - - 2.17 100.00 0.08
2.1.2.4 Urugan Tanah Kembali Pondasi Batu Kali M3 10.39 54,175.00 562,878.25 0.06 10.39 100.00 0.06 - - - 10.39 100.00 0.06
2.1.2.5 Pondasi Batu Kali 1 Sp : 3 Pp M3 9.09 827,447.50 7,521,497.78 0.76 9.09 100.00 0.76 - - - 9.09 100.00 0.76
2.1.3 Pekerjaan Pondasi Rollage L.15 cm (Entrance, Selasar Samping) - - - -
2.1.3.1 Galian Tanah Pondasi Rollage < 1 m M3 2.23 73,837.50 164,657.63 0.02 2.23 100.00 0.02 - - - 2.23 100.00 0.02
2.1.3.2 Urugan Pasir dibawah Pondasi Rollage T.5 cm M3 0.45 148,335.00 66,750.75 0.01 0.45 100.00 0.01 - - - 0.45 100.00 0.01
2.1.3.3 Pasangan Lantai Kerja bawah Pondasi Rollage T.5 cm (Beton K300) M3 0.45 1,118,216.00 499,003.89 0.05 0.45 100.00 0.05 - - - 0.45 100.00 0.05
2.1.3.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp M2 20.83 128,436.00 2,675,321.88 0.27 20.83 100.00 0.27 - - - 20.83 100.00 0.27
2.2 Pekerjaan Sloef, Kolom dan Ringbalk - - -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Mushollah) - - -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 1.62 1,118,216.00 1,815,703.23 0.18 1.62 100.00 0.18 - - - 1.62 100.00 0.18
2.2.1.2 Bekisting 2x Pakai M2 10.83 114,438.50 1,239,368.96 0.13 10.83 100.00 0.13 - - - 10.83 100.00 0.13
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI Kg 280.09 21,464.85 6,012,089.84 0.61 280.09 100.00 0.61 - - - 280.09 100.00 0.61
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan, Mushollah) - - -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.88 1,118,216.00 981,234.54 0.10 0.88 100.00 0.10 - - - 0.88 100.00 0.10
2.2.2.2 Bekisting 2x Pakai M2 5.85 193,468.00 1,131,787.80 0.11 5.85 100.00 0.11 - - - 5.85 100.00 0.11
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 181.66 21,464.85 3,899,347.58 0.39 181.66 100.00 0.39 - - - 181.66 100.00 0.39
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Selasar, Westafel, Tempat Wudhu) - -
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 0.34 100.00 0.03 - - - 0.34 100.00 0.03
2.2.3.2 Bekisting 2x Pakai M2 2.26 193,468.00 437,237.68 0.04 2.26 100.00 0.04 - - - 2.26 100.00 0.04
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 70.10 21,464.85 1,504,686.30 0.15 70.10 100.00 0.15 - - - 70.10 100.00 0.15
2.2.4 Pekerjaan Kolom K1 15 x 30 (Selasar Samping) - -
2.2.4.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.62 1,118,216.00 694,412.14 0.07 0.62 100.00 0.07 - - - 0.62 100.00 0.07
2.2.4.2 Bekisting 2x Pakai M2 6.21 193,468.00 1,201,436.28 0.12 6.21 100.00 0.12 - - - 6.21 100.00 0.12
2.2.4.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 99.69 21,464.85 2,139,830.90 0.22 99.69 100.00 0.22 - - - 99.69 100.00 0.22
2.2.5 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan, Mushollah) - -
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 2.08 1,008,161.00 2,097,478.96 0.21 2.08 100.00 0.21 - - - 2.08 100.00 0.21
2.2.5.2 Bekisting 2x Pakai M2 13.87 197,923.00 2,745,192.01 0.28 13.87 100.00 0.28 - - - 13.87 100.00 0.28
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 299.22 21,464.85 6,422,712.42 0.65 299.22 100.00 0.65 - - - 299.22 100.00 0.65
2.2.6 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan) - -
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 0.34 100.00 0.03 - - - 0.34 100.00 0.03
2.2.6.2 Bekisting 2x Pakai M2 2.24 197,923.00 443,347.52 0.04 2.24 100.00 0.04 - - - 2.24 100.00 0.04
2.2.6.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 48.32 21,464.85 1,037,181.55 0.10 48.32 100.00 0.10 - - - 48.32 100.00 0.10
2.2.7 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Mushollah, Pintu Jendela) - -
2.2.7.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.84 1,008,161.00 846,855.24 0.09 0.84 100.00 0.09 - - - 0.84 100.00 0.09
2.2.7.2 Bekisting 2x Pakai M2 5.59 197,923.00 1,106,389.57 0.11 5.59 100.00 0.11 - - - 5.59 100.00 0.11
2.2.7.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 115.53 21,464.85 2,479,834.12 0.25 115.53 100.00 0.25 - - - 115.53 100.00 0.25
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.2.8 Pekerjaan Plat Beton (Selasar Samping, Westafel) - -
2.2.8.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.22 1,008,161.00 221,795.42 0.02 0.22 100.00 0.02 - - - 0.22 100.00 0.02
2.2.8.2 Bekisting 2x Pakai M2 2.21 237,468.00 524,804.28 0.05 2.21 100.00 0.05 - - - 2.21 100.00 0.05
2.2.8.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 54.54 21,464.85 1,170,692.92 0.12 54.54 100.00 0.12 - - - 54.54 100.00 0.12
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) M2 152.03 163,636.00 24,877,581.08 2.51 152.03 100.00 2.51 - - - 152.03 100.00 2.51
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4, Entrance) M2 42.24 242,170.50 10,229,281.92 1.03 42.24 100.00 1.03 - - - 42.24 100.00 1.03
2.5 Pekerjaan Tiang Atap Bitumen Gelombang (Besi Hollow Galvanis 5/10, Entrance) M' 20.40 178,365.00 3,638,646.00 0.37 20.40 100.00 0.37 - - - 20.40 100.00 0.37
2.6 Pekerjaan Rangka Plafond Kalsiboard (Besi Hollow Metal Galvalume 4/4) M2 147.40 102,837.17 15,158,198.37 1.53 147.40 100.00 1.53 - - - 147.40 100.00 1.53

TOTAL PEKERJAAN STRUKTUR 109,840,345.70 11.10 11.10 0.00 11.10

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) M3 8.54 148,335.00 1,266,780.90 0.13 8.54 100.00 0.13 - - - 8.54 100.00 0.13
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) M3 25.63 167,227.00 4,285,636.74 0.43 25.63 100.00 0.43 - - - 25.63 100.00 0.43
3.1.1.3 Rabat Beton bawah Lantai T.5 cm (Keseluruhan, Beton K300) M3 8.54 1,118,216.00 9,549,564.64 0.96 8.54 100.00 0.96 - - - 8.54 100.00 0.96
3.1.1.4 Penutup Lantai Keramik Motif 60x60 (Badan Bangunan, Mushollah) M2 62.94 403,309.50 25,384,299.93 2.56 - - - 59.79 95.00 2.44 59.79 95.00 2.44
3.1.1.5 Penutup Lantai Conwood Deck 6" (Entrance) M2 59.01 866,833.08 51,151,820.09 5.17 - - - 56.01 94.92 4.90 56.01 94.92 4.90
3.1.1.6 Penutup Lantai Andesit Polos 30x30 (Selasar, Tempat Wudhu, Ram) M2 51.05 232,589.50 11,873,693.98 1.20 - - - 51.05 100.00 1.20 51.05 100.00 1.20
3.1.1.7 Plint Lantai Keramik 10x60 (Badan Bangunan, Mushollah) M' 38.85 51,605.03 2,004,855.55 0.20 - - - - - - - - -
3.1.2 Pekerjaan Dinding - -
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Mushollah, 1 Sp : 4 Pp) M2 74.55 242,979.00 18,114,084.45 1.83 74.55 100.00 1.83 - - - 74.55 100.00 1.83
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Selasar Samping, Tempat Wudhu) M2 5.14 65,550.32 336,928.64 0.03 - - - 5.14 100.00 0.03 5.14 100.00 0.03
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm (Badan Bangunan, Mushollah) M2 91.30 60,403.20 5,514,812.16 0.56 91.30 100.00 0.56 - - - 91.30 100.00 0.56
3.1.2.4 Plesteran Ciprat 1 Sp : 2 Pp Tebal 15 mm (Selasar Samping, Antar Kolom) M2 24.84 49,215.10 1,222,503.08 0.12 - - - 24.84 100.00 0.12 24.84 100.00 0.12
3.1.2.5 Dinding Keramik Mozaik 30x60 (Selasar Samping, Westafel, Tempat Wudhu) M2 18.44 410,432.00 7,568,366.08 0.76 - - - 18.44 100.00 0.76 18.44 100.00 0.76
3.1.2.6 Coating Bening (Badan Bangunan, Mushollah, Kolom Luar) M2 127.49 45,973.13 5,861,113.71 0.59 - - - - - - - - -
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) M2 8.64 995,043.50 8,597,175.84 0.87 - - - 8.64 100.00 0.87 8.64 100.00 0.87
3.1.2.8 Dinding Wallpaper Bata L.50 cm (Sisi Dalam) M2 28.13 80,005.50 2,250,554.72 0.23 - - - - - - - - -
3.1.3 Pekerjaan Plafond - -
3.1.3.1 Plafond Kalsiboard (Badan Bangunan, Kemiringan Atap, Mushollah) M2 147.40 44,924.00 6,621,797.60 0.67 - - - 147.40 100.00 0.67 147.40 100.00 0.67
3.1.3.2 Plafond Kalsiboard (Lapis Bawah Atap, Entrance) M2 42.24 44,924.00 1,897,589.76 0.19 - - - 42.24 100.00 0.19 42.24 100.00 0.19
3.2 Pekerjaan Pintu dan Jendela (Badan Bangunan) - -
3.2.1 Pintu P1 (Entrance dan Back Entrance, Badan Bangunan) - -
3.2.1.1 Pasangan Kusen Alumunium Coating P1 (4" x 1 3/4") cm M' 22.40 157,194.40 3,521,154.56 0.36 - - - 22.40 100.00 0.36 22.40 100.00 0.36
3.2.1.2 Pasangan Daun Pintu P1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - - - -
3.2.1.3 Pasangan Kaca Mati 5 mm P1 M2 11.20 145,703.80 1,631,882.56 0.16 - - - - - - - - -
3.2.1.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - - - -
3.2.1.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - - - -
3.2.1.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - - - -
3.2.1.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - - - -
3.2.2 Jendela J1 (Badan Bangunan) - -
3.2.2.1 Pasangan Kusen Alumunium Coating J1 (4" x 1 3/4") cm M' 40.60 157,194.40 6,382,092.64 0.64 - - - 40.60 100.00 0.64 40.60 100.00 0.64
3.2.2.2 Pasangan Kaca Mati 5 mm J1 M2 8.00 145,703.80 1,165,630.40 0.12 - - - - - - - - -
3.2.3 Pintu PJ1 (Mushollah) - -
3.2.3.1 Pasangan Kusen Alumunium Coating PJ1 (4" x 1 3/4") cm M' 22.20 157,194.40 3,489,715.68 0.35 - - - 22.20 100.00 0.35 22.20 100.00 0.35
3.2.3.2 Pasangan Daun Pintu PJ1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - - - -
3.2.3.3 Pasangan Kaca Mati 5 mm P1 M2 8.70 145,703.80 1,267,623.06 0.13 - - - - - - - - -
3.2.3.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - - - -
3.2.3.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - - - -
3.2.3.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - - - -
3.2.3.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - - - -
3.3 Pekerjaan Pengecatan - -
3.3.1 Pengecatan Plafond (1 Plamir ; 1 Cat Dasar : 2 Cat Penutup), (Interior) M2 189.64 35,536.05 6,739,056.52 0.68 - - - 189.64 100.00 0.68 189.64 100.00 0.68
3.3.2 Pengecatan Rangka Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 23.76 168,454.00 4,002,467.04 0.40 - - - 23.76 100.00 0.40 23.76 100.00 0.40
3.3.3 Pengecatan Tiang Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 6.12 168,454.00 1,030,938.48 0.10 - - - 6.12 100.00 0.10 6.12 100.00 0.10
3.4 Pekerjaan Atap - -
3.4.1 Atap Bitumen Gelombang (Badan Bangunan, Mushollah) M2 152.03 207,297.09 31,515,376.59 3.18 152.03 100.00 3.18 - - - 152.03 100.00 3.18
3.4.2 Atap Bitumen Gelombang (Entrance) M2 42.24 207,297.09 8,756,229.08 0.88 42.24 100.00 0.88 - - - 42.24 100.00 0.88
3.4.3 Nok Bitumen (Badan Bangunan, Mushollah) M' 14.55 134,101.00 1,951,169.55 0.20 14.55 100.00 0.20 - - - 14.55 100.00 0.20
3.4.4 Listplank (Kalsiplank, Badan Bangunan, Mushollah, Entrance) M' 50.00 70,950.00 3,547,500.00 0.36 50.00 100.00 0.36 - - - 50.00 100.00 0.36

TOTAL PEKERJAAN FINISHING ARSITEKTUR 257,222,142.77 25.98 8.54 13.73 22.27

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel Bh 1.00 1,572,826.75 1,572,826.75 0.16 - - - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt Bh 16.00 353,938.75 5,663,020.00 0.57 - - - 16.00 100.00 0.57 16.00 100.00 0.57
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4.1.3 Pasangan Lampu Down Light 2,5" Outbow LED 5,5 Watt Bh 11.00 305,538.75 3,360,926.25 0.34 - - - 11.00 100.00 0.34 11.00 100.00 0.34
4.1.4 Pasangan Saklar Tunggal Bh 4.00 211,378.75 845,515.00 0.09 - - - 4.00 100.00 0.09 4.00 100.00 0.09
4.1.5 Pasangan Saklar Ganda Bh 2.00 223,478.75 446,957.50 0.05 - - - 2.00 100.00 0.05 2.00 100.00 0.05
4.2 Pasangan Instalasi Stop Kontak - - -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA Bh 10.00 216,218.75 2,162,187.50 0.22 - - - 10.00 100.00 0.22 10.00 100.00 0.22
4.2.2 Pasangan Stop Kontak AC 220 VA/3520 W (AC Split 1 PK) Bh 4.00 253,728.75 1,014,915.00 0.10 - - - 4.00 100.00 0.10 4.00 100.00 0.10
4.3 Pasangan Instalasi Jaringan AC M' 30.00 108,772.68 3,263,180.25 0.33 - - - 30.00 100.00 0.33 30.00 100.00 0.33
4.3.1 Pasangan AC Split 1 PK Bh 3.00 3,365,799.34 10,097,398.03 1.02 - - - 1.50 50.00 0.51 1.50 50.00 0.51
4.4 Pasangan Penangkal Petir Ls 1.00 2,500,000.00 2,500,000.00 0.25 - - - 1.00 100.00 0.25 1.00 100.00 0.25
4.5 Pasangan Instalasi Jaringan Kabel Fiber Optic (CCTV) Ttk 6.00 786,326.75 4,717,960.50 0.48 - - - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2MP Bh 6.00 656,975.00 3,941,850.00 0.40 - - - - - - - - -
4.5.2 Pasangan NVR Channel Set 1.00 5,023,975.00 5,023,975.00 0.51 - - - - - - - - -
4.5.3 Pasangan Monitor LCD 32" Bh 1.00 2,944,975.00 2,944,975.00 0.30 - - - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm M' 12.00 20,442.68 245,312.10 0.02 - - - - - - - - -
4.6.1 Pasangan Horn Speaker Bh 6.00 494,826.75 2,968,960.50 0.30 - - - - - - - - -
4.6.2 Pasangan Volume Kontrol Set 1.00 252,826.75 252,826.75 0.03 - - - - - - - - -
4.6.3 Pasangan Perangkat Sound System Set 1.00 4,565,000.00 4,565,000.00 0.46 - - - - - - - - -
4.6.4 Pasangan TB-Sound System Set 1.00 5,846,326.75 5,846,326.75 0.59 - - - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25Kg) Ttk 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - - - -
4.8 Pasangan Instalasi Jaringan Kabel Fiber Optic (Akses Point) Ttk 3.00 786,326.75 2,358,980.25 0.24 - - - - - - - - -
4.8.1 Pasangan Server Set 1.00 7,578,826.75 7,578,826.75 0.77 - - - - - - - - -
4.8.2 Pasangan Akses Point Bh 1.00 2,034,826.75 2,034,826.75 0.21 - - - - - - - - -
4.8.3 Pasangan Switch HUB Bh 1.00 2,843,326.75 2,843,326.75 0.29 - - - - - - - - -
4.9 Pasangan Instalasi PLN Power (Inc. Jalur ke Mushollah dan Toilet) Ls 1.00 9,000,000.00 9,000,000.00 0.91 - - - - - - - - -

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 94,450,073.38 9.54 0.00 2.46 2.46

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVC Type AW Diameter 3/4" (Air Bersih Sambungan dari Tandon) M' 33.00 28,300.25 933,908.25 0.09 - - - 16.50 50.00 0.05 16.50 50.00 0.05
5.2 Pipa PVC Type AW Diameter 3" (Air Kotor ke Drainase Lingkungan) M' 25.80 135,531.00 3,496,699.80 0.35 - - - 2.58 10.00 0.04 2.58 10.00 0.04
5.3 Pasangan 1 Bh Wastafel Bh 2.00 3,934,865.00 7,869,730.00 0.79 - - - 2.00 100.00 0.79 2.00 100.00 0.79
5.4 Pasangan 1 Bh Wastafel Cuci Piring (WCP) Bh 1.00 890,945.00 890,945.00 0.09 - - - 1.00 100.00 0.09 1.00 100.00 0.09
5.5 Pasangan 1 Bh Floor Drain Bh 2.00 41,112.50 82,225.00 0.01 - - - 2.00 100.00 0.01 2.00 100.00 0.01
5.6 Pasangan 1 Bh Kran Dia. 1/2" atau 3/4" Bh 10.00 102,217.50 1,022,175.00 0.10 - - - 10.00 100.00 0.10 10.00 100.00 0.10
5.7 Pasangan 1 Bh Kran Wastafel Dia. 1/2" atau 3/4" Bh 3.00 335,417.50 1,006,252.50 0.10 - - - 3.00 100.00 0.10 3.00 100.00 0.10
5.8 Pasangan 1 Bh Stop Kran (Gate Valve) Dia. 3/4" Bh 1.00 141,417.50 141,417.50 0.01 - - - 0.10 10.00 0.00 0.10 10.00 0.00
5.9 Pasangan Mesin Air Bh 1.00 741,000.00 741,000.00 0.07 - - - - - - - - -
5.10 Menara Reservoir 200x150x350 cm - -
5.10.1 Pekerjaan Pondasi Pedestal Pd1 - -
5.10.1.1 Galian Tanah Pondasi Poerplat < 1 m M3 1.62 73,837.50 119,616.75 0.01 - - - - - - - - -
5.10.1.2 Urugan Tanah Kembali Pondasi Poerplat M3 0.43 54,175.00 23,295.25 0.00 - - - - - - - - -
5.10.1.3 Tiang Pondasi Pedestal 50x50 cm - - - -
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.80 1,118,216.00 894,572.80 0.09 - - - - - - - - -
Bekisting 2x Pakai M2 3.20 193,468.00 619,097.60 0.06 - - - - - - - - -
Besi Beton Ø12 SNI, Ø8 SNI Kg 49.44 21,464.85 1,061,130.60 0.11 - - - - - - - - -
5.10.1.4 Pondasi Poerplat 90x90 cm, T.20 cm - -
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.65 1,118,216.00 726,840.40 0.07 - - - - - - - - -
Bekisting 2x Pakai M2 1.44 107,013.50 154,099.44 0.02 - - - - - - - - -
Besi Beton Ø14 SNI Kg 214.35 21,464.85 4,600,940.54 0.46 - - - - - - - - -
5.10.2 Rangka Tengah dan Lantai Menara (Besi Hollow Galvanis 4/4) M2 34.82 244,970.00 8,529,855.40 0.86 - - - 27.86 80.00 0.69 27.86 80.00 0.69
5.10.3 Rangka Utama Menara (Besi Hollow Galvanis 5/10) M' 32.28 179,454.00 5,792,775.12 0.59 - - - 25.82 80.00 0.47 25.82 80.00 0.47
5.10.4 Plat Baja Lantai Menara T.3 mm M2 3.00 740,164.86 2,220,494.57 0.22 - - - - - - - - -
5.10.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) M2 5.00 244,970.00 1,224,850.00 0.12 - - - 4.00 80.00 0.10 4.00 80.00 0.10

TOTAL PEKERJAAN PLAMBING DAN SANITASI 42,151,921.52 4.26 0.00 2.44 2.44

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Pek. Pembersian Awal m2 81.86 17,600.00 1,440,780.00 0.15 81.86 100.00 0.15 - - - 81.86 100.00 0.15
1.2 Pek. Pengukuran & Pemasangan Bouwplank m1 48.60 106,461.25 5,174,016.75 0.52 48.60 100.00 0.52 - - - 48.60 100.00 0.52

TOTAL PEKERJAAN PERSIAPAN 6,614,796.75 0.67 0.67 0.00 0.67

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Batu Kali (Badan Bangunan,Ruang Bilas)
2.1.1.1 Galian Pondasi Batu Kali < 1 m m3 22.05 73,892.50 1,629,329.63 0.16 6.62 30.00 0.05 - - - 6.62 30.00 0.05
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.1.1.2 Urugan Pasir Dibawah Pondasi Batu Kali T.5 cm m3 1.05 174,757.00 183,494.85 0.02 1.05 100.00 0.02 - - - 1.05 100.00 0.02
2.1.1.3 Pasangan Aanstamping Bawah Pondasi Batu Kali T.10 cm m3 2.10 392,699.70 824,669.37 0.08 2.10 100.00 0.08 - - - 2.10 100.00 0.08
2.1.1.4 Urugan Tanah Kembali Pondasi Batu Kali m3 10.08 54,285.00 547,192.80 0.06 3.02 30.00 0.02 - - - 3.02 30.00 0.02
2.1.1.5 Pondasi Batu Kali 1 Sp : 3 Pp m3 8.82 824,945.00 7,276,014.90 0.73 8.82 100.00 0.73 - - - 8.82 100.00 0.73
2.1.2 Perjaan Pondasi Rollage L.15 cm (Selasar) - -
2.1.2.1 Galian Tanah Pondasi Rollage < 1 m m3 1.52 73,892.50 112,501.33 0.01 0.15 10.00 0.00 - - - 0.15 10.00 0.00
2.1.2.2 Urugan Pasir Dibawah Pondasi Rollage T.5 cm m3 0.30 174,757.00 53,213.51 0.01 0.03 10.00 0.00 - - - 0.03 10.00 0.00
2.1.2.3 Pasangan Lantai Kerja Bawah Pondasi Rollage T.5 cm (Beton K300) m3 0.30 1,118,398.60 340,552.37 0.03 0.30 100.00 0.03 - - - 0.30 100.00 0.03
2.1.2.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp m3 14.21 128,260.00 1,822,574.60 0.18 14.21 100.00 0.18 - - - 14.21 100.00 0.18
2.2 Pekerjaan Sloef, Kolom, Plat dan Ringbalk - - -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Ruang Bilas) - - -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 m3 1.41 1,118,398.60 1,580,297.22 0.16 1.41 100.00 0.16 - - - 1.41 100.00 0.16
2.2.1.2 Bekisting 2x Pakai m2 9.42 114,467.10 1,078,280.08 0.11 9.42 100.00 0.11 - - - 9.42 100.00 0.11
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI kg 243.74 21,465.73 5,232,043.29 0.53 243.74 100.00 0.53 - - - 243.74 100.00 0.53
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan) - - -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slum (12 - 2) cm, w/c = 0,52 m3 0.48 1,118,398.60 533,476.13 0.05 0.48 100.00 0.05 - - - 0.48 100.00 0.05
2.2.2.2 Bekisting 2x Pakai m2 3.18 193,504.30 615,343.67 0.06 3.18 100.00 0.06 - - - 3.18 100.00 0.06
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI kg 98.75 21,465.73 2,119,732.25 0.21 98.75 100.00 0.21 - - - 98.75 100.00 0.21
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Ruang Bilas) - - -
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.25 1,008,343.60 249,111.29 0.03 0.25 100.00 0.03 - - - 0.25 100.00 0.03
2.2.3.2 Bekisting 2x Pakai m2 1.65 193,504.30 318,701.58 0.03 1.65 100.00 0.03 - - - 1.65 100.00 0.03
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI kg 51.14 21,465.73 1,097,861.33 0.11 51.14 100.00 0.11 - - - 51.14 100.00 0.11
2.2.4 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan) - - -
2.2.4.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.04 1,008,343.60 1,043,635.63 0.11 1.04 100.00 0.11 - - - 1.04 100.00 0.11
2.2.4.2 Bekisting 2x Pakai m2 6.90 197,959.30 1,365,919.17 0.14 6.90 100.00 0.14 - - - 6.90 100.00 0.14
2.2.4.3 Besi Beton Ø12 SNI, Ø6 SNI kg 148.86 21,465.73 3,195,302.68 0.32 148.86 100.00 0.32 - - - 148.86 100.00 0.32
2.2.5 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan) - - -
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.09 1,008,343.60 1,103,531.24 0.11 1.09 100.00 0.11 - - - 1.09 100.00 0.11
2.2.5.2 Bekisting 2x Pakai m2 14.59 197,959.30 2,888,622.11 0.29 14.59 100.00 0.29 - - - 14.59 100.00 0.29
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI kg 157.40 21,465.73 3,378,705.12 0.34 157.40 100.00 0.34 - - - 157.40 100.00 0.34
2.2.6 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Pintu Jendela) - -
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.15 1,008,343.60 148,831.52 0.02 0.15 100.00 0.02 - - - 0.15 100.00 0.02
2.2.6.2 Bekisting 2x Pakai m2 0.98 197,959.30 194,791.95 0.02 0.98 100.00 0.02 - - - 0.98 100.00 0.02
2.2.6.3 Besi Beton Ø10 SNI, Ø6 SNI kg 20.35 21,465.73 436,752.39 0.04 20.35 100.00 0.04 - - - 20.35 100.00 0.04
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) m2 59.01 163,856.00 9,669,142.56 0.98 59.01 100.00 0.98 - - - 59.01 100.00 0.98
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4) m2 48.59 102,876.77 4,998,782.09 0.50 48.59 100.00 0.50 - - - 48.59 100.00 0.50
2.5 Pekerjaan Rangka Plafond dan Dinding Dalam PVC Shunda (Besi Hollow Metal Galvalume 4/4) m2 56.16 102,876.77 5,777,559.22 0.58 - - - 56.16 100.00 0.58 56.16 100.00 0.58

TOTAL PEKERJAAN STRUKTUR 59,815,965.86 6.04 5.29 0.58 5.87

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) m3 4.09 174,757.00 715,280.40 0.07 4.09 100.00 0.07 - - - 4.09 100.00 0.07
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) m3 12.28 167,345.00 2,054,804.70 0.21 12.28 100.00 0.21 - - - 12.28 100.00 0.21
3.1.1.3 Rabat Beton T.5 cm (Keseluruhan, Beton K300) m3 4.09 1,118,398.60 4,577,605.47 0.46 4.09 100.00 0.46 - - - 4.09 100.00 0.46
3.1.1.4 Penutup Lantai Keramik Tekstur 60x60 (Badan Bangunan) m2 36.93 413,098.40 15,255,723.91 1.54 29.54 80.00 1.23 7.39 20.00 0.31 36.93 100.00 1.54
3.1.1.5 Penutup Lantai Andesit Polos 30x30 (Selasar, Ruang Bilas) m2 45.89 284,369.80 13,049,730.12 1.32 - - - 45.89 100.00 1.32 45.89 100.00 1.32
3.1.1.6 Penutup Plat Wastafel (Granit 60x60, Toilet Pria dan Wanita) m2 2.20 841,621.73 1,851,567.81 0.19 - - - 2.20 100.00 0.19 2.20 100.00 0.19
3.1.2 Pekerjaan Dinding - - -
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Selasar, 1 Sp : 4 Pp) 90.64 242,533.50 21,983,236.44 2.22 72.51 80.00 1.78 18.13 20.00 0.44 90.64 100.00 2.22
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Wc ) 30.00 65,473.32 1,964,199.60 0.20 24.00 80.00 0.16 6.00 20.00 0.04 30.00 100.00 0.20
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm 121.28 60,304.20 7,313,693.38 0.74 97.02 80.00 0.59 24.26 20.00 0.15 121.28 100.00 0.74
3.1.2.4 Coating Bening 121.28 46,853.13 5,682,347.00 0.57 - - - - - - - - -
3.1.2.5 Dinding Andesit Polos 30x30 cm ( Wc, Ruang Bilas ) 56.52 284,369.80 16,072,581.10 1.62 - - - 56.52 100.00 1.62 56.52 100.00 1.62
3.1.2.6 Dinding Keramik 30x60 cm ( Sisi Dalam ) 69.88 370,557.00 25,894,523.16 2.62 - - - 69.88 100.00 2.62 69.88 100.00 2.62
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) 9.00 995,076.50 8,955,688.50 0.90 - - - 9.00 100.00 0.90 9.00 100.00 0.90
3.1.2.8 Cubicle Panel + Accessories (Pintu Wc dan Partisi Urinoir) 10.86 1,360,000.00 14,769,600.00 1.49 - - - 10.86 100.00 1.49 10.86 100.00 1.49
3.1.2.9 Dinding Bitumen Gelombang 48.59 201,749.24 9,802,995.57 0.99 - - - 48.59 100.00 0.99 48.59 100.00 0.99
3.1.2.10 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Pria) 1.00 1,200,000.00 1,200,000.00 0.12 - - - - - - - - -
3.1.2.11 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Wanita) 1.00 750,000.00 750,000.00 0.08 - - - - - - - - -
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.1.3 Plafond dan Dinding Dalam Shunda ( Badan Bangunan ) 56.16 125,878.50 7,069,336.56 0.71 - - - 56.16 100.00 0.71 56.16 100.00 0.71
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.2 Pekerjaan Pintu dan Jendela ( Badan Bangunan ) - - -
3.2.1 Pintu P1 - - -
3.2.1.1 Pasangan Kusen Almunium Coating P1 (4" x 13/4") cm 10.96 157,199.02 1,722,901.26 0.17 - - - 10.96 100.00 0.17 10.96 100.00 0.17
3.2.1.2 Pasangan Daun Pintu P1 (Panel Almunium Coating - Coating) 4.30 870,323.19 3,742,389.72 0.38 - - - - - - - - -
3.2.1.3 Pasangan Kunci Tanam 2x Slag P1 2.00 416,663.50 833,327.00 0.08 - - - - - - - - -
3.2.1.4 Pasangan ensel P1 6.00 61,225.56 367,353.36 0.04 - - - - - - - - -
3.2.1.5 Pasangan Doorcloser P1 2.00 241,902.10 483,804.20 0.05 - - - - - - - - -
3.2.1.6 Pasangan Handle P1 2.00 229,802.10 459,604.20 0.05 - - - - - - - - -
3.2.2 Jendela J1 - - -
3.2.2.1 Pasangan Kusen Almunium Coating J1 (4" x 13/4") cm 28.80 157,199.02 4,527,331.78 0.46 - - - 28.80 100.00 0.46 28.80 100.00 0.46
3.2.2.2 Pasangan Kaca Mati 5 mm J1 0.60 145,705.56 87,423.34 0.01 - - - - - - - - -
3.2.3 Jendela J2 - -
3.2.3.1 Pasangan Kusen Almunium Coating J2 (4" x 13/4") cm 55.20 157,199.02 8,677,385.90 0.88 - - - - - - - - -
3.2.3.2 Pasangan Kaca Mati 5 mm J2 0.90 145,705.56 131,135.00 0.01 - - - - - - - - -
3.3. Pengecetan Plafond (1 Plamir : 1 Cat Dasar : 2 Cat Penutup), (Interior) 56.16 43,550.65 2,445,804.50 0.25 - - - 56.16 100.00 0.25 56.16 100.00 0.25
3.4 Pekerjaan Atap - - -
3.4.1 Atap Bitumen Gelombang (Badan Bangunan) 59.01 201,749.24 11,905,222.65 1.20 - - - 59.01 100.00 1.20 59.01 100.00 1.20
3.4.2 Nok Bitumen (Badan Bangunan) 35.25 143,629.20 5,062,929.30 0.51 - - - 35.25 100.00 0.51 35.25 100.00 0.51
3.4.3 Listplank (Kasiplank, Badan Bangunan, Enterance) 39.08 70,972.00 2,773,585.76 0.28 - - - 39.08 100.00 0.28 39.08 100.00 0.28

TOTAL PEKERJAAN FINISHING ARSITEKTUR 202,183,111.69 20.42 4.50 13.66 18.16

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel 1.00 1,803,826.75 1,803,826.75 0.18 - - - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt 10.00 353,938.75 3,539,387.50 0.36 - - - 10.00 100.00 0.36 10.00 100.00 0.36
4.1.3 Pasangan Lampu Down Light 2.5" Outbow LED 5.5 Watt 12.00 305,538.75 3,666,465.00 0.37 - - - 12.00 100.00 0.37 12.00 100.00 0.37
4.1.4 Pasangan Saklar Ganda 5.00 223,478.75 1,117,393.75 0.11 - - - 5.00 100.00 0.11 5.00 100.00 0.11
4.2 Pasangan Instalasi Stop Kontak - - -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA 3.00 216,218.75 648,656.25 0.07 - - - 3.00 100.00 0.07 3.00 100.00 0.07
4.2.2 Pasangan Stop Kontak Wall Exhauser 6.00 216,218.75 1,297,312.50 0.13 - - - 6.00 100.00 0.13 6.00 100.00 0.13
4.3 Pasangan Instalasi Jaringan Wall Exhauser 12.00 108,772.68 1,305,272.10 0.13 - - - 12.00 100.00 0.13 12.00 100.00 0.13
4.3.1 Pasangan Wall Exhauser 12 Inch - FV30RUN 6.00 513,500.00 3,081,000.00 0.31 - - - 6.00 100.00 0.31 6.00 100.00 0.31
4.4 Pasangan Penangkal Petir 1.00 3,500,000.00 3,500,000.00 0.35 - - - 0.50 50.00 0.18 0.50 50.00 0.18
4.5 Pasangan Instlasi Jaringan Kabel Fiber Optic (CCTV) 3.00 786,326.75 2,358,980.25 0.24 - - - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2 MP (Luar Bangunan, Sambungan Dari Mini Resto) 3.00 656,975.00 1,970,925.00 0.20 - - - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm 4.00 20,442.68 81,770.70 0.01 - - - - - - - - -
4.6.1 Pasangan Horn Speaker (Sambungan Dari Mini Resto) 2.00 494,826.75 989,653.50 0.10 - - - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25 kg) 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - - - -
4.8 Pasangan Instalasi PLN Power 1.00 10,000,000.00 10,000,000.00 1.01 - - - - - - - - -

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 44,560,643.30 4.50 0.00 1.66 1.66

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVc Tipe AW Diameter 3/4" (Air Bersih Dari Sumur Bor / PDAM Reservoir) m1 18.50 28,304.65 523,636.03 0.05 - - - - - - - - -
5.2 Pipa PVC Tipe AW Diameter 3/4" (Distribusi Air Bersih Dari Reservoir) m1 26.50 28,304.65 750,073.23 0.08 - - - 13.25 50.00 0.04 13.25 50.00 0.04
5.3 Pipa PVC Tipe AW Diameter 3" (Air Kotor Ke Drainase Lingkungan) m1 23.00 135,539.80 3,117,415.40 0.31 - - - 23.00 100.00 0.31 23.00 100.00 0.31
5.4 Pipa PVC Tipe AW Diameter 4" (Disposal) m1 18.00 186,689.80 3,360,416.40 0.34 - - - 18.00 100.00 0.34 18.00 100.00 0.34
5.5 Pasangan 1 bh Closet Duduk / Monoblock (TOTO) bh 6.00 3,655,597.00 21,933,582.00 2.22 - - - 3.00 50.00 1.11 3.00 50.00 1.11
5.6 Pasangan 1 bh Wastafel (TOTO) 3.00 3,571,942.00 10,715,826.00 1.08 - - - 3.00 100.00 1.08 3.00 100.00 1.08
5.7 Pasangan 1 bh Uninoir (TOTO) 2.00 6,665,285.00 13,330,570.00 1.35 - - - 2.00 100.00 1.35 2.00 100.00 1.35
5.8 Pasangan 1 bh Floor Drain 9.00 41,123.50 370,111.50 0.04 - - - 9.00 100.00 0.04 9.00 100.00 0.04
5.9 Pasangan 1 bh Kran dia. 1/2' atau 3/4" 8.00 102,228.50 817,828.00 0.08 - - - 8.00 100.00 0.08 8.00 100.00 0.08
5.10 Pasangan 1 bh Kran wastafel dia. 1/2' atau 3/4" 2.00 335,428.50 670,857.00 0.07 - - - 2.00 100.00 0.07 2.00 100.00 0.07
5.11 Pasangan 1 bh shower closet dia. 1/2' atau 3/4" 6.00 142,928.50 857,571.00 0.09 - - - 6.00 100.00 0.09 6.00 100.00 0.09
5.12 Pasangan 1 bh shower Wall dia. 1/2' atau 3/4" (Ruang Bilas) 4.00 1,435,428.50 5,741,714.00 0.58 - - - 4.00 100.00 0.58 4.00 100.00 0.58
5.13 Pasangan 1 bh Stop Kran (Gate Valve) dia. 3/4" 2.00 141,428.50 282,857.00 0.03 - - - 2.00 100.00 0.03 2.00 100.00 0.03
5.14 Pasangan Mesin Air 1.00 741,000.00 741,000.00 0.07 - - - - - - - - -
5.14b Pasangan Mesin Pemanas Air 1.00 5,000,000.00 5,000,000.00 0.51 - - - - - - - - -
5.15 Septictank Biotank Kap. 4m3 1.00 20,380,000.00 20,380,000.00 2.06 - - - 0.50 50.00 1.03 0.50 50.00 1.03
5.16 Pasangan Sumur Bor Jet Pump 30.00 350,000.00 10,500,000.00 1.06 - - - - - - - - -
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.17 Reservoir 1200 Liter 1.00 1,850,000.00 1,850,000.00 0.19 - - - 1.00 100.00 0.19 1.00 100.00 0.19
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.18 Reservoir 200x150x350 cm - - -
5.18.1 Pekerjaan Pondasi Pedestal Pd1 - - -
5.18.1.1 Galian Tanah Pondasi Poerplat < 1m 1.62 74,250.00 120,285.00 0.01 - - - - - - - - -
5.18.1.2 Urugan Tanah Kembali Pondasi Poerplat 0.43 55,000.00 23,760.00 0.00 - - - - - - - - -
5.18.1.3 Tiang Pondasi Pedestal 50x50 cm - -
Beton Mutu fc = 26,6 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.80 1,485,144.21 1,188,115.37 0.12 - - - - - - - - -
Bekisting 2x Pakai 3.20 193,504.30 619,213.76 0.06 - - - - - - - - -
Besi Beton Ø12, Ø8 49.44 21,465.73 1,061,174.10 0.11 - - - - - - - - -
5.18.1.4 Pondasi Poerplat 90x90 cm,T.20 cm - - -
Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.65 1,485,144.21 962,373.45 0.10 - - - - - - - - -
Bekisting 2x Pakai 1.44 124,547.50 179,348.40 0.02 - - - - - - - - -
Besi Beton Ø14 SNI 214.35 21,465.73 4,601,114.73 0.46 - - - - - - - - -
5.18.2 Rangkai Tengah Dan Lantai Menara (Besi Hollow Galvanis 4/4) 34.82 244,970.00 8,529,855.40 0.86 - - - 34.82 100.00 0.86 34.82 100.00 0.86
5.18.3 Rangka Utama menara ( Besi Hollow Galvanis 5/10 32.28 179,454.00 5,792,775.12 0.59 - - - 32.28 100.00 0.59 32.28 100.00 0.59
5.18.4 Tplat Baja Lantai Menara T.3mm 3.00 740,164.86 2,220,494.57 0.22 - - - - - - - - -
5.18.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) 5.00 244,970.00 1,224,850.00 0.12 - - - 4.00 80.00 0.10 4.00 80.00 0.10

TOTAL PEKERJAAN PLAMBING DAN SANITASI 127,466,817.45 12.88 - 7.87 7.87

6. PEKERJAAN AKHIR - - -
6.1 Pembersihan Sisa Pekerjaan Ls 1.00 2,400,000.00 2,400,000.00 0.24 - - - - - - - - -

TOTAL PEKERJAAN AKHIR 2,400,000.00 0.24 0.00 0.00 0.00

C. PENERAPAN SMKK

1. PENYIAPAN RKK
1.1 Pembuatan Dokumen Rencana Keselamatan Konstruksi
1.2 Pembuatan Prosedur dan instruksi kerja Set 1.00 2,000,000.00 2,000,000.00 0.20 1.00 100.00 0.20 - - - 1.00 100.00 0.20
1.3 Penyiapan formulir
TOTAL PENYIAPAN RKK 2,000,000.00 0.20 0.20 - 0.20
2. SOSIALISASI, PROMOSI DAN PELATIHAN
2.1 Induksi K3 (Safety Induction) Org 5.00 7,500.00 37,500.00 0.00 0.50 10.00 0.00 - - - 0.50 10.00 0.00
2.2 Pengarahan K3 (Safety Briefing) Org 5.00 15,000.00 75,000.00 0.01 5.00 100.00 0.01 - - - 5.00 100.00 0.01
2.3 Pelatihan K3 - - -
2.3.1 Bekerja di ketinggian Org 4.00 7,500.00 30,000.00 0.00 4.00 100.00 0.00 - - - 4.00 100.00 0.00
2.3.2 Penggunaan Bahan Kimia (MSDS) Org 2.00 7,500.00 15,000.00 0.00 2.00 100.00 0.00 - - - 2.00 100.00 0.00
2.4 Simulasi K3 Org 5.00 7,500.00 37,500.00 0.00 5.00 100.00 0.00 - - - 5.00 100.00 0.00
2.5 Spanduk (Banner) Lb 1.00 150,000.00 150,000.00 0.02 1.00 100.00 0.02 - - - 1.00 100.00 0.02
2.6 Poster 2 2.00 50,000.00 100,000.00 0.01 2.00 100.00 0.01 - - - 2.00 100.00 0.01
2.7 Papan Informasi K3 1 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - - 1.00 100.00 0.05
TOTAL SOSIALISASI, PROMOSI DAN PELATIHAN 945,000.00 0.10 0.09 - 0.09
3. ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI
3.1 APK
3.1.1 Tali Keselamatan (Life Line) Ls 1.00 1,700,000.00 1,700,000.00 0.17 1.00 100.00 0.17 - - - 1.00 100.00 0.17
3.1.2 Pembatas Area (Restricted Area) Ls 1.00 2,000,000.00 2,000,000.00 0.20 1.00 100.00 0.20 - - - 1.00 100.00 0.20
3.2 APD - -
3.2.1 Topi Pelindung (Safety Helmet) Bh 10.00 75,000.00 750,000.00 0.08 10.00 100.00 0.08 - - - 10.00 100.00 0.08
3.2.2 Pelindung Mata (Googles, Spectacles) Bh 5.00 25,000.00 125,000.00 0.01 5.00 100.00 0.01 - - - 5.00 100.00 0.01
3.2.3 Pelindung Pernapasan dan Mulut (Masker) Bh 100.00 5,000.00 500,000.00 0.05 100.00 100.00 0.05 - - - 100.00 100.00 0.05
3.2.4 Sarung Tangan (Safety Gloves) Psg 10.00 15,000.00 150,000.00 0.02 10.00 100.00 0.02 - - - 10.00 100.00 0.02
3.2.5 Sepatu Keselamatan (Safety Shoes) Psg 10.00 350,000.00 3,500,000.00 0.35 10.00 100.00 0.35 - - - 10.00 100.00 0.35
3.2.6 Penunjang Seluruh Tubuh (Full Body Harness) Bh 2.00 500,000.00 1,000,000.00 0.10 2.00 100.00 0.10 - - - 2.00 100.00 0.10
3.2.7 Rompi Keselamatan (Safety Vest) Bh 10.00 25,000.00 250,000.00 0.03 10.00 100.00 0.03 - - - 10.00 100.00 0.03
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 9,975,000.00 1.01 1.01 - 1.01
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4. ASURANSI DAN PERIZINAN
4.1 Asuransi Ls 1.00 3,000,000.00 3,000,000.00 0.30 1.00 100.00 0.30 - - - 1.00 100.00 0.30
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 3,000,000.00 0.30 0.30 - 0.30
5. PERSONEL K3 KONSTRUKSI
5.1 Ahli K3 Konstruksi -
5.2 Petugas K3 Konstruksi Ob 4.00 3,675,000.00 14,700,000.00 1.48 4.00 100.00 1.48 - - - 4.00 100.00 1.48
TOTAL PERSONEL K3 KONSTRUKSI 14,700,000.00 1.48 1.48 - 1.48
6. FASILITAS, SARANA DAN PRASARANA KESEHATAN
6.1 Peralatan P3K (Kotak P3K, Tandu, Obat Luka, Perban, dll) Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - - 1.00 100.00 0.05
TOTAL FASILITAS, SARANA DAN PRASARANA KESEHATAN 500,000.00 0.05 0.05 - 0.05
7. RAMBU - RAMBU YANG DIPERLUKAN
7.1 Rambu Petunjuk bh 2.00 75,000.00 150,000.00 0.02 2.00 100.00 0.02 - - - 2.00 100.00 0.02
7.2 Rambu Larangan bh 2.00 75,000.00 150,000.00 0.02 2.00 100.00 0.02 - - - 2.00 100.00 0.02
7.3 Rambu Peringatan bh 2.00 100,000.00 200,000.00 0.02 2.00 100.00 0.02 - - - 2.00 100.00 0.02
7.4 Jalur Evakuasi (Escape Route) Ls 1.00 250,000.00 250,000.00 0.03 1.00 100.00 0.03 - - - 1.00 100.00 0.03
TOTAL RAMBU - RAMBU YANG DIPERLUKAN 750,000.00 0.08 0.08 - 0.08
8. KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI
8.1 Ahli K3 Konstruksi Oj -
TOTAL KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI - 0.00
9. LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN
KONSTRUKSI
9.1 Alat Pemadam Api Ringan (APAR) bh 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - - 1.00 100.00 0.05
9.2 Program Inspeksi Ls 1.00 1,500,000.00 1,500,000.00 0.15 1.00 100.00 0.15 - - - 1.00 100.00 0.15
9.3 Pelaporan dan Penyeledikan Insiden Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - - 1.00 100.00 0.05
9.4 Pembuatan Kartu Identitas Pekerja (KIP) Org 10.00 5,000.00 50,000.00 0.01 10.00 100.00 0.01 - - - 10.00 100.00 0.01
TOTAL LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN KONSTRUKSI 2,550,000.00 0.26 0.26 - 0.26

A Jumlah Harga Penawaran 989,944,870.91 100.00 34.46 42.40 76.86


B PPN (10%) 98,994,487.09
C Jumlah (A+B) 1,088,939,358.00
PERSENTASE SAMPAI BULAN INI 76.86
D Jumlah Dibulatkan 1,088,939,358.00

Bulukumba, 14 Desember 2020


Disetujui, Diketahui, Diperiksa Oleh, Dibuat Oleh,
Pejabat Pembuat Komitmen Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUTR Prov SulSel Dinas PUTR Prov SulSel CV.MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

A.KHADAFI HARUN, ST.,MT. L I L I, ST. IRHAM HARAHAP, ST. VIKA APRILIA DWI PUTRI
NIP. 19811126 200901 1 008 NIP. 19821229 201503 2 001 Site Engineer Direktris
LAPORAN KEMAJUAN BULANAN

Kegiatan : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba Bulan Ke : 02 ( Dua )
Satuan Kerja : Dinas Pekerjaan Umum Dan Tata Ruang Prov. Sulawesi Selatan Bidang Cipta Karya Periode : 13 November S/d 14 Desember 2020
Lokasi : Desa Ara, Kecamatan Bonto Bahari, Kabupaten Bulukumba, Provinsi Sulawesi Selatan No. Kontrak : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
Sumber Dana : Dana Bantuan Provinsi Nilai Kontrak : Rp. 1,088,939,358.00
Tahun Anggaran : 2020 Schedule Pelaksanaan : 16 Oktober S/d 14 Desember 2020

BULAN LALU BULAN INI S/D BULAN INI


VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
NO URAIAN PEKERJAAN
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q

A. PEMBANGUNAN RUANG KULINER, SUVENIR, MUSHOLLAH DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Papan Proyek Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - - 1.00 100.00 0.05
1.2 Bedeng/Direksi Keet M2 5.50 1,512,555.00 8,319,052.50 0.84 5.50 100.00 0.84 - - - 5.50 100.00 0.84

TOTAL PEKERJAAN PERSIAPAN 8,819,052.50 0.89 0.89 0.00 0.89

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Poerplat PP1 (Selasar Samping)
2.1.1.1 Galian Pondasi Poerplat < 1 m M3 0.32 73,837.50 23,628.00 0.00 0.32 100.00 0.00 - - - 0.32 100.00 0.00
2.1.1.2 Urugan Pasir dibawah Pondasi Poerplat T.5 cm M3 0.04 148,335.00 5,933.40 0.00 0.04 100.00 0.00 - - - 0.04 100.00 0.00
2.1.1.3 Urugan Tanah Kembali Pondasi Poerplat M3 0.31 54,175.00 16,794.25 0.00 0.31 100.00 0.00 - - - 0.31 100.00 0.00
2.1.1.4 Pasangan Lantai Kerja bawah Pondasi Poerplat T.5 cm (Beton K300) M3 0.04 1,118,216.00 44,728.64 0.00 0.04 100.00 0.00 - - - 0.04 100.00 0.00
2.1.1.5 Pondasi Poerplat 35x50 cm, T.20 cm - - -
Beton Mutu F'c = 26,4 mpa (K300), Slump (12-2) cm, w/c = 0,52 M3 0.14 1,118,216.00 156,550.24 0.02 0.14 100.00 0.02 - - - 0.14 100.00 0.02
Bekisting 2x Pakai M2 0.56 107,013.50 59,927.56 0.01 0.56 100.00 0.01 - - - 0.56 100.00 0.01
Besi Beton Ø14 SNI Kg 29.40 21,464.85 631,066.59 0.06 29.40 100.00 0.06 - - - 29.40 100.00 0.06
2.1.2 Pekerjaan Pondasi Batu Kali (Badan Bangunan, Mushollah) - - -
2.1.2.1 Galian Tanah Pondasi Batu Kali < 1 m M3 22.73 73,837.50 1,678,326.38 0.17 22.73 100.00 0.17 - - - 22.73 100.00 0.17
2.1.2.2 Urugan Pasir dibawah Pondasi Batu Kali T.5 cm M3 1.08 148,335.00 160,201.80 0.02 1.08 100.00 0.02 - - - 1.08 100.00 0.02
2.1.2.3 Pasangan Aanstamping bawah Pondasi Batu Kali T.10 M3 2.17 382,674.00 830,402.58 0.08 2.17 100.00 0.08 - - - 2.17 100.00 0.08
2.1.2.4 Urugan Tanah Kembali Pondasi Batu Kali M3 10.39 54,175.00 562,878.25 0.06 10.39 100.00 0.06 - - - 10.39 100.00 0.06
2.1.2.5 Pondasi Batu Kali 1 Sp : 3 Pp M3 9.09 827,447.50 7,521,497.78 0.76 9.09 100.00 0.76 - - - 9.09 100.00 0.76
2.1.3 Pekerjaan Pondasi Rollage L.15 cm (Entrance, Selasar Samping) - - - -
2.1.3.1 Galian Tanah Pondasi Rollage < 1 m M3 2.23 73,837.50 164,657.63 0.02 2.23 100.00 0.02 - - - 2.23 100.00 0.02
2.1.3.2 Urugan Pasir dibawah Pondasi Rollage T.5 cm M3 0.45 148,335.00 66,750.75 0.01 0.45 100.00 0.01 - - - 0.45 100.00 0.01
2.1.3.3 Pasangan Lantai Kerja bawah Pondasi Rollage T.5 cm (Beton K300) M3 0.45 1,118,216.00 499,003.89 0.05 0.45 100.00 0.05 - - - 0.45 100.00 0.05
2.1.3.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp M2 20.83 128,436.00 2,675,321.88 0.27 20.83 100.00 0.27 - - - 20.83 100.00 0.27
2.2 Pekerjaan Sloef, Kolom dan Ringbalk - - -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Mushollah) - - -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 1.62 1,118,216.00 1,815,703.23 0.18 1.62 100.00 0.18 - - - 1.62 100.00 0.18
2.2.1.2 Bekisting 2x Pakai M2 10.83 114,438.50 1,239,368.96 0.13 10.83 100.00 0.13 - - - 10.83 100.00 0.13
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI Kg 280.09 21,464.85 6,012,089.84 0.61 280.09 100.00 0.61 - - - 280.09 100.00 0.61
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan, Mushollah) - - -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.88 1,118,216.00 981,234.54 0.10 0.88 100.00 0.10 - - - 0.88 100.00 0.10
2.2.2.2 Bekisting 2x Pakai M2 5.85 193,468.00 1,131,787.80 0.11 5.85 100.00 0.11 - - - 5.85 100.00 0.11
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 181.66 21,464.85 3,899,347.58 0.39 181.66 100.00 0.39 - - - 181.66 100.00 0.39
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Selasar, Westafel, Tempat Wudhu) - -
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 0.34 100.00 0.03 - - - 0.34 100.00 0.03
2.2.3.2 Bekisting 2x Pakai M2 2.26 193,468.00 437,237.68 0.04 2.26 100.00 0.04 - - - 2.26 100.00 0.04
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 70.10 21,464.85 1,504,686.30 0.15 70.10 100.00 0.15 - - - 70.10 100.00 0.15
2.2.4 Pekerjaan Kolom K1 15 x 30 (Selasar Samping) - -
2.2.4.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.62 1,118,216.00 694,412.14 0.07 0.62 100.00 0.07 - - - 0.62 100.00 0.07
2.2.4.2 Bekisting 2x Pakai M2 6.21 193,468.00 1,201,436.28 0.12 6.21 100.00 0.12 - - - 6.21 100.00 0.12
2.2.4.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 99.69 21,464.85 2,139,830.90 0.22 99.69 100.00 0.22 - - - 99.69 100.00 0.22
2.2.5 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan, Mushollah) - -
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 2.08 1,008,161.00 2,097,478.96 0.21 2.08 100.00 0.21 - - - 2.08 100.00 0.21
2.2.5.2 Bekisting 2x Pakai M2 13.87 197,923.00 2,745,192.01 0.28 13.87 100.00 0.28 - - - 13.87 100.00 0.28
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 299.22 21,464.85 6,422,712.42 0.65 299.22 100.00 0.65 - - - 299.22 100.00 0.65
2.2.6 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan) - -
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 0.34 100.00 0.03 - - - 0.34 100.00 0.03
2.2.6.2 Bekisting 2x Pakai M2 2.24 197,923.00 443,347.52 0.04 2.24 100.00 0.04 - - - 2.24 100.00 0.04
2.2.6.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 48.32 21,464.85 1,037,181.55 0.10 48.32 100.00 0.10 - - - 48.32 100.00 0.10
2.2.7 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Mushollah, Pintu Jendela) - -
2.2.7.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.84 1,008,161.00 846,855.24 0.09 0.84 100.00 0.09 - - - 0.84 100.00 0.09
2.2.7.2 Bekisting 2x Pakai M2 5.59 197,923.00 1,106,389.57 0.11 5.59 100.00 0.11 - - - 5.59 100.00 0.11
2.2.7.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 115.53 21,464.85 2,479,834.12 0.25 115.53 100.00 0.25 - - - 115.53 100.00 0.25
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.2.8 Pekerjaan Plat Beton (Selasar Samping, Westafel) - -
2.2.8.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.22 1,008,161.00 221,795.42 0.02 0.22 100.00 0.02 - - - 0.22 100.00 0.02
2.2.8.2 Bekisting 2x Pakai M2 2.21 237,468.00 524,804.28 0.05 2.21 100.00 0.05 - - - 2.21 100.00 0.05
2.2.8.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 54.54 21,464.85 1,170,692.92 0.12 54.54 100.00 0.12 - - - 54.54 100.00 0.12
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) M2 152.03 163,636.00 24,877,581.08 2.51 152.03 100.00 2.51 - - - 152.03 100.00 2.51
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4, Entrance) M2 42.24 242,170.50 10,229,281.92 1.03 42.24 100.00 1.03 - - - 42.24 100.00 1.03
2.5 Pekerjaan Tiang Atap Bitumen Gelombang (Besi Hollow Galvanis 5/10, Entrance) M' 20.40 178,365.00 3,638,646.00 0.37 20.40 100.00 0.37 - - - 20.40 100.00 0.37
2.6 Pekerjaan Rangka Plafond Kalsiboard (Besi Hollow Metal Galvalume 4/4) M2 147.40 102,837.17 15,158,198.37 1.53 147.40 100.00 1.53 - - - 147.40 100.00 1.53

TOTAL PEKERJAAN STRUKTUR 109,840,345.70 11.10 11.10 0.00 11.10

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) M3 8.54 148,335.00 1,266,780.90 0.13 8.54 100.00 0.13 - - - 8.54 100.00 0.13
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) M3 25.63 167,227.00 4,285,636.74 0.43 25.63 100.00 0.43 - - - 25.63 100.00 0.43
3.1.1.3 Rabat Beton bawah Lantai T.5 cm (Keseluruhan, Beton K300) M3 8.54 1,118,216.00 9,549,564.64 0.96 8.54 100.00 0.96 - - - 8.54 100.00 0.96
3.1.1.4 Penutup Lantai Keramik Motif 60x60 (Badan Bangunan, Mushollah) M2 62.94 403,309.50 25,384,299.93 2.56 - - - 62.94 100.00 2.56 62.94 100.00 2.56
3.1.1.5 Penutup Lantai Conwood Deck 6" (Entrance) M2 59.01 866,833.08 51,151,820.09 5.17 - - - 59.01 100.00 5.17 59.01 100.00 5.17
3.1.1.6 Penutup Lantai Andesit Polos 30x30 (Selasar, Tempat Wudhu, Ram) M2 51.05 232,589.50 11,873,693.98 1.20 - - - 51.05 100.00 1.20 51.05 100.00 1.20
3.1.1.7 Plint Lantai Keramik 10x60 (Badan Bangunan, Mushollah) M' 38.85 51,605.03 2,004,855.55 0.20 - - - 38.85 100.00 0.20 38.85 100.00 0.20
3.1.2 Pekerjaan Dinding - -
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Mushollah, 1 Sp : 4 Pp) M2 74.55 242,979.00 18,114,084.45 1.83 74.55 100.00 1.83 - - 74.55 100.00 1.83
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Selasar Samping, Tempat Wudhu) M2 5.14 65,550.32 336,928.64 0.03 - - - 5.14 100.00 0.03 5.14 100.00 0.03
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm (Badan Bangunan, Mushollah) M2 91.30 60,403.20 5,514,812.16 0.56 91.30 100.00 0.56 - - 91.30 100.00 0.56
3.1.2.4 Plesteran Ciprat 1 Sp : 2 Pp Tebal 15 mm (Selasar Samping, Antar Kolom) M2 24.84 49,215.10 1,222,503.08 0.12 - - - 24.84 100.00 0.12 24.84 100.00 0.12
3.1.2.5 Dinding Keramik Mozaik 30x60 (Selasar Samping, Westafel, Tempat Wudhu) M2 18.44 410,432.00 7,568,366.08 0.76 - - - 18.44 100.00 0.76 18.44 100.00 0.76
3.1.2.6 Coating Bening (Badan Bangunan, Mushollah, Kolom Luar) M2 127.49 45,973.13 5,861,113.71 0.59 - - - 127.49 100.00 0.59 127.49 100.00 0.59
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) M2 8.64 995,043.50 8,597,175.84 0.87 - - - 8.64 100.00 0.87 8.64 100.00 0.87
3.1.2.8 Dinding Wallpaper Bata L.50 cm (Sisi Dalam) M2 28.13 80,005.50 2,250,554.72 0.23 - - - 28.13 100.00 0.23 28.13 100.00 0.23
3.1.3 Pekerjaan Plafond - -
3.1.3.1 Plafond Kalsiboard (Badan Bangunan, Kemiringan Atap, Mushollah) M2 147.40 44,924.00 6,621,797.60 0.67 - - - 147.40 100.00 0.67 147.40 100.00 0.67
3.1.3.2 Plafond Kalsiboard (Lapis Bawah Atap, Entrance) M2 42.24 44,924.00 1,897,589.76 0.19 - - - 42.24 100.00 0.19 42.24 100.00 0.19
3.2 Pekerjaan Pintu dan Jendela (Badan Bangunan) - -
3.2.1 Pintu P1 (Entrance dan Back Entrance, Badan Bangunan) - -
3.2.1.1 Pasangan Kusen Alumunium Coating P1 (4" x 1 3/4") cm M' 22.40 157,194.40 3,521,154.56 0.36 - - - 22.40 100.00 0.36 22.40 100.00 0.36
3.2.1.2 Pasangan Daun Pintu P1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - 7.04 100.00 0.60 7.04 100.00 0.60
3.2.1.3 Pasangan Kaca Mati 5 mm P1 M2 11.20 145,703.80 1,631,882.56 0.16 - - - 11.20 100.00 0.16 11.20 100.00 0.16
3.2.1.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - 2.00 100.00 0.08 2.00 100.00 0.08
3.2.1.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - 12.00 100.00 0.07 12.00 100.00 0.07
3.2.1.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - 4.00 100.00 0.10 4.00 100.00 0.10
3.2.1.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - 4.00 100.00 0.09 4.00 100.00 0.09
3.2.2 Jendela J1 (Badan Bangunan) - -
3.2.2.1 Pasangan Kusen Alumunium Coating J1 (4" x 1 3/4") cm M' 40.60 157,194.40 6,382,092.64 0.64 - - - 40.60 100.00 0.64 40.60 100.00 0.64
3.2.2.2 Pasangan Kaca Mati 5 mm J1 M2 8.00 145,703.80 1,165,630.40 0.12 - - - 8.00 100.00 0.12 8.00 100.00 0.12
3.2.3 Pintu PJ1 (Mushollah) - -
3.2.3.1 Pasangan Kusen Alumunium Coating PJ1 (4" x 1 3/4") cm M' 22.20 157,194.40 3,489,715.68 0.35 - - - 22.20 100.00 0.35 22.20 100.00 0.35
3.2.3.2 Pasangan Daun Pintu PJ1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - 7.04 100.00 0.60 7.04 100.00 0.60
3.2.3.3 Pasangan Kaca Mati 5 mm P1 M2 8.70 145,703.80 1,267,623.06 0.13 - - - 8.70 100.00 0.13 8.70 100.00 0.13
3.2.3.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - 2.00 100.00 0.08 2.00 100.00 0.08
3.2.3.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - 12.00 100.00 0.07 12.00 100.00 0.07
3.2.3.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - 4.00 100.00 0.10 4.00 100.00 0.10
3.2.3.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - 4.00 100.00 0.09 4.00 100.00 0.09
3.3 Pekerjaan Pengecatan - -
3.3.1 Pengecatan Plafond (1 Plamir ; 1 Cat Dasar : 2 Cat Penutup), (Interior) M2 189.64 35,536.05 6,739,056.52 0.68 - - - 189.64 100.00 0.68 189.64 100.00 0.68
3.3.2 Pengecatan Rangka Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 23.76 168,454.00 4,002,467.04 0.40 - - - 23.76 100.00 0.40 23.76 100.00 0.40
3.3.3 Pengecatan Tiang Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 6.12 168,454.00 1,030,938.48 0.10 - - - 6.12 100.00 0.10 6.12 100.00 0.10
3.4 Pekerjaan Atap - -
3.4.1 Atap Bitumen Gelombang (Badan Bangunan, Mushollah) M2 152.03 207,297.09 31,515,376.59 3.18 152.03 100.00 3.18 - - - 152.03 100.00 3.18
3.4.2 Atap Bitumen Gelombang (Entrance) M2 42.24 207,297.09 8,756,229.08 0.88 42.24 100.00 0.88 - - - 42.24 100.00 0.88
3.4.3 Nok Bitumen (Badan Bangunan, Mushollah) M' 14.55 134,101.00 1,951,169.55 0.20 14.55 100.00 0.20 - - - 14.55 100.00 0.20
3.4.4 Listplank (Kalsiplank, Badan Bangunan, Mushollah, Entrance) M' 50.00 70,950.00 3,547,500.00 0.36 50.00 100.00 0.36 - - - 50.00 100.00 0.36

TOTAL PEKERJAAN FINISHING ARSITEKTUR 257,222,142.77 25.98 8.54 17.45 25.98

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel Bh 1.00 1,572,826.75 1,572,826.75 0.16 - - - 1.00 100.00 0.16 1.00 100.00 0.16
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt Bh 16.00 353,938.75 5,663,020.00 0.57 - - - 16.00 100.00 0.57 16.00 100.00 0.57
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4.1.3 Pasangan Lampu Down Light 2,5" Outbow LED 5,5 Watt Bh 11.00 305,538.75 3,360,926.25 0.34 - - - 11.00 100.00 0.34 11.00 100.00 0.34
4.1.4 Pasangan Saklar Tunggal Bh 4.00 211,378.75 845,515.00 0.09 - - - 4.00 100.00 0.09 4.00 100.00 0.09
4.1.5 Pasangan Saklar Ganda Bh 2.00 223,478.75 446,957.50 0.05 - - - 2.00 100.00 0.05 2.00 100.00 0.05
4.2 Pasangan Instalasi Stop Kontak - - -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA Bh 10.00 216,218.75 2,162,187.50 0.22 - - - 10.00 100.00 0.22 10.00 100.00 0.22
4.2.2 Pasangan Stop Kontak AC 220 VA/3520 W (AC Split 1 PK) Bh 4.00 253,728.75 1,014,915.00 0.10 - - - 4.00 100.00 0.10 4.00 100.00 0.10
4.3 Pasangan Instalasi Jaringan AC M' 30.00 108,772.68 3,263,180.25 0.33 - - - 30.00 100.00 0.33 30.00 100.00 0.33
4.3.1 Pasangan AC Split 1 PK Bh 3.00 3,365,799.34 10,097,398.03 1.02 - - - 3.00 100.00 1.02 3.00 100.00 1.02
4.4 Pasangan Penangkal Petir Ls 1.00 2,500,000.00 2,500,000.00 0.25 - - - 1.00 100.00 0.25 1.00 100.00 0.25
4.5 Pasangan Instalasi Jaringan Kabel Fiber Optic (CCTV) Ttk 6.00 786,326.75 4,717,960.50 0.48 - - - 6.00 100.00 0.48 6.00 100.00 0.48
4.5.1 Pasangan CCTV Type Bullet 2MP Bh 6.00 656,975.00 3,941,850.00 0.40 - - - 6.00 100.00 0.40 6.00 100.00 0.40
4.5.2 Pasangan NVR Channel Set 1.00 5,023,975.00 5,023,975.00 0.51 - - - 1.00 100.00 0.51 1.00 100.00 0.51
4.5.3 Pasangan Monitor LCD 32" Bh 1.00 2,944,975.00 2,944,975.00 0.30 - - - 1.00 100.00 0.30 1.00 100.00 0.30
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm M' 12.00 20,442.68 245,312.10 0.02 - - - 12.00 100.00 0.02 12.00 100.00 0.02
4.6.1 Pasangan Horn Speaker Bh 6.00 494,826.75 2,968,960.50 0.30 - - - 6.00 100.00 0.30 6.00 100.00 0.30
4.6.2 Pasangan Volume Kontrol Set 1.00 252,826.75 252,826.75 0.03 - - - 1.00 100.00 0.03 1.00 100.00 0.03
4.6.3 Pasangan Perangkat Sound System Set 1.00 4,565,000.00 4,565,000.00 0.46 - - - 1.00 100.00 0.46 1.00 100.00 0.46
4.6.4 Pasangan TB-Sound System Set 1.00 5,846,326.75 5,846,326.75 0.59 - - - 1.00 100.00 0.59 1.00 100.00 0.59
4.7 Pasangan Instalasi Titik APAR (25Kg) Ttk 2.00 4,600,000.00 9,200,000.00 0.93 - - - 2.00 100.00 0.93 2.00 100.00 0.93
4.8 Pasangan Instalasi Jaringan Kabel Fiber Optic (Akses Point) Ttk 3.00 786,326.75 2,358,980.25 0.24 - - - 3.00 100.00 0.24 3.00 100.00 0.24
4.8.1 Pasangan Server Set 1.00 7,578,826.75 7,578,826.75 0.77 - - - 1.00 100.00 0.77 1.00 100.00 0.77
4.8.2 Pasangan Akses Point Bh 1.00 2,034,826.75 2,034,826.75 0.21 - - - 1.00 100.00 0.21 1.00 100.00 0.21
4.8.3 Pasangan Switch HUB Bh 1.00 2,843,326.75 2,843,326.75 0.29 - - - 1.00 100.00 0.29 1.00 100.00 0.29
4.9 Pasangan Instalasi PLN Power (Inc. Jalur ke Mushollah dan Toilet) Ls 1.00 9,000,000.00 9,000,000.00 0.91 - - - 1.00 100.00 0.91 1.00 100.00 0.91

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 94,450,073.38 9.54 0.00 9.54 9.54

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVC Type AW Diameter 3/4" (Air Bersih Sambungan dari Tandon) M' 33.00 28,300.25 933,908.25 0.09 - - - 33.00 100.00 0.09 33.00 100.00 0.09
5.2 Pipa PVC Type AW Diameter 3" (Air Kotor ke Drainase Lingkungan) M' 25.80 135,531.00 3,496,699.80 0.35 - - - 25.80 100.00 0.35 25.80 100.00 0.35
5.3 Pasangan 1 Bh Wastafel Bh 2.00 3,934,865.00 7,869,730.00 0.79 - - - 2.00 100.00 0.79 2.00 100.00 0.79
5.4 Pasangan 1 Bh Wastafel Cuci Piring (WCP) Bh 1.00 890,945.00 890,945.00 0.09 - - - 1.00 100.00 0.09 1.00 100.00 0.09
5.5 Pasangan 1 Bh Floor Drain Bh 2.00 41,112.50 82,225.00 0.01 - - - 2.00 100.00 0.01 2.00 100.00 0.01
5.6 Pasangan 1 Bh Kran Dia. 1/2" atau 3/4" Bh 10.00 102,217.50 1,022,175.00 0.10 - - - 10.00 100.00 0.10 10.00 100.00 0.10
5.7 Pasangan 1 Bh Kran Wastafel Dia. 1/2" atau 3/4" Bh 3.00 335,417.50 1,006,252.50 0.10 - - - 3.00 100.00 0.10 3.00 100.00 0.10
5.8 Pasangan 1 Bh Stop Kran (Gate Valve) Dia. 3/4" Bh 1.00 141,417.50 141,417.50 0.01 - - - 1.00 100.00 0.01 1.00 100.00 0.01
5.9 Pasangan Mesin Air Bh 1.00 741,000.00 741,000.00 0.07 - - - 1.00 100.00 0.07 1.00 100.00 0.07
5.10 Menara Reservoir 200x150x350 cm - -
5.10.1 Pekerjaan Pondasi Pedestal Pd1 - -
5.10.1.1 Galian Tanah Pondasi Poerplat < 1 m M3 1.62 73,837.50 119,616.75 0.01 - - - 1.62 100.00 0.01 1.62 100.00 0.01
5.10.1.2 Urugan Tanah Kembali Pondasi Poerplat M3 0.43 54,175.00 23,295.25 0.00 - - - 0.43 100.00 0.00 0.43 100.00 0.00
5.10.1.3 Tiang Pondasi Pedestal 50x50 cm - - - -
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.80 1,118,216.00 894,572.80 0.09 - - - 0.80 100.00 0.09 0.80 100.00 0.09
Bekisting 2x Pakai M2 3.20 193,468.00 619,097.60 0.06 - - - 3.20 100.00 0.06 3.20 100.00 0.06
Besi Beton Ø12 SNI, Ø8 SNI Kg 49.44 21,464.85 1,061,130.60 0.11 - - - 49.44 100.00 0.11 49.44 100.00 0.11
5.10.1.4 Pondasi Poerplat 90x90 cm, T.20 cm - -
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.65 1,118,216.00 726,840.40 0.07 - - - 0.65 100.00 0.07 0.65 100.00 0.07
Bekisting 2x Pakai M2 1.44 107,013.50 154,099.44 0.02 - - - 1.44 100.00 0.02 1.44 100.00 0.02
Besi Beton Ø14 SNI Kg 214.35 21,464.85 4,600,940.54 0.46 - - - 214.35 100.00 0.46 214.35 100.00 0.46
5.10.2 Rangka Tengah dan Lantai Menara (Besi Hollow Galvanis 4/4) M2 34.82 244,970.00 8,529,855.40 0.86 - - - 34.82 100.00 0.86 34.82 100.00 0.86
5.10.3 Rangka Utama Menara (Besi Hollow Galvanis 5/10) M' 32.28 179,454.00 5,792,775.12 0.59 - - - 32.28 100.00 0.59 32.28 100.00 0.59
5.10.4 Plat Baja Lantai Menara T.3 mm M2 3.00 740,164.86 2,220,494.57 0.22 - - - 3.00 100.00 0.22 3.00 100.00 0.22
5.10.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) M2 5.00 244,970.00 1,224,850.00 0.12 - - - 5.00 100.00 0.12 5.00 100.00 0.12

TOTAL PEKERJAAN PLAMBING DAN SANITASI 42,151,921.52 4.26 0.00 4.26 4.26

B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Pek. Pembersian Awal m2 81.86 17,600.00 1,440,780.00 0.15 81.86 100.00 0.15 - - - 81.86 100.00 0.15
1.2 Pek. Pengukuran & Pemasangan Bouwplank m1 48.60 106,461.25 5,174,016.75 0.52 48.60 100.00 0.52 - - - 48.60 100.00 0.52

TOTAL PEKERJAAN PERSIAPAN 6,614,796.75 0.67 0.67 0.00 0.67

2. PEKERJAAN STRUKTUR
2.1 Pekerjaan Pondasi
2.1.1 Pekerjaan Pondasi Batu Kali (Badan Bangunan,Ruang Bilas)
2.1.1.1 Galian Pondasi Batu Kali < 1 m m3 22.05 73,892.50 1,629,329.63 0.16 6.62 30.00 0.05 15.44 70.00 0.12 22.05 100.00 0.16
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.1.1.2 Urugan Pasir Dibawah Pondasi Batu Kali T.5 cm m3 1.05 174,757.00 183,494.85 0.02 1.05 100.00 0.02 - - - 1.05 100.00 0.02
2.1.1.3 Pasangan Aanstamping Bawah Pondasi Batu Kali T.10 cm m3 2.10 392,699.70 824,669.37 0.08 2.10 100.00 0.08 - - - 2.10 100.00 0.08
2.1.1.4 Urugan Tanah Kembali Pondasi Batu Kali m3 10.08 54,285.00 547,192.80 0.06 3.02 30.00 0.02 7.06 70.00 0.04 10.08 100.00 0.06
2.1.1.5 Pondasi Batu Kali 1 Sp : 3 Pp m3 8.82 824,945.00 7,276,014.90 0.73 8.82 100.00 0.73 - - - 8.82 100.00 0.73
2.1.2 Perjaan Pondasi Rollage L.15 cm (Selasar) - -
2.1.2.1 Galian Tanah Pondasi Rollage < 1 m m3 1.52 73,892.50 112,501.33 0.01 0.15 10.00 0.00 1.37 90.00 0.01 1.52 100.00 0.01
2.1.2.2 Urugan Pasir Dibawah Pondasi Rollage T.5 cm m3 0.30 174,757.00 53,213.51 0.01 0.03 10.00 0.00 0.27 90.00 0.00 0.30 100.00 0.01
2.1.2.3 Pasangan Lantai Kerja Bawah Pondasi Rollage T.5 cm (Beton K300) m3 0.30 1,118,398.60 340,552.37 0.03 0.30 100.00 0.03 - - - 0.30 100.00 0.03
2.1.2.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp m3 14.21 128,260.00 1,822,574.60 0.18 14.21 100.00 0.18 - - - 14.21 100.00 0.18
2.2 Pekerjaan Sloef, Kolom, Plat dan Ringbalk - - -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Ruang Bilas) - - -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 m3 1.41 1,118,398.60 1,580,297.22 0.16 1.41 100.00 0.16 - - - 1.41 100.00 0.16
2.2.1.2 Bekisting 2x Pakai m2 9.42 114,467.10 1,078,280.08 0.11 9.42 100.00 0.11 - - - 9.42 100.00 0.11
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI kg 243.74 21,465.73 5,232,043.29 0.53 243.74 100.00 0.53 - - - 243.74 100.00 0.53
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan) - - -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slum (12 - 2) cm, w/c = 0,52 m3 0.48 1,118,398.60 533,476.13 0.05 0.48 100.00 0.05 - - - 0.48 100.00 0.05
2.2.2.2 Bekisting 2x Pakai m2 3.18 193,504.30 615,343.67 0.06 3.18 100.00 0.06 - - - 3.18 100.00 0.06
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI kg 98.75 21,465.73 2,119,732.25 0.21 98.75 100.00 0.21 - - - 98.75 100.00 0.21
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Ruang Bilas) - - -
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.25 1,008,343.60 249,111.29 0.03 0.25 100.00 0.03 - - - 0.25 100.00 0.03
2.2.3.2 Bekisting 2x Pakai m2 1.65 193,504.30 318,701.58 0.03 1.65 100.00 0.03 - - - 1.65 100.00 0.03
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI kg 51.14 21,465.73 1,097,861.33 0.11 51.14 100.00 0.11 - - - 51.14 100.00 0.11
2.2.4 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan) - - -
2.2.4.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.04 1,008,343.60 1,043,635.63 0.11 1.04 100.00 0.11 - - - 1.04 100.00 0.11
2.2.4.2 Bekisting 2x Pakai m2 6.90 197,959.30 1,365,919.17 0.14 6.90 100.00 0.14 - - - 6.90 100.00 0.14
2.2.4.3 Besi Beton Ø12 SNI, Ø6 SNI kg 148.86 21,465.73 3,195,302.68 0.32 148.86 100.00 0.32 - - - 148.86 100.00 0.32
2.2.5 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan) - - -
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.09 1,008,343.60 1,103,531.24 0.11 1.09 100.00 0.11 - - - 1.09 100.00 0.11
2.2.5.2 Bekisting 2x Pakai m2 14.59 197,959.30 2,888,622.11 0.29 14.59 100.00 0.29 - - - 14.59 100.00 0.29
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI kg 157.40 21,465.73 3,378,705.12 0.34 157.40 100.00 0.34 - - - 157.40 100.00 0.34
2.2.6 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Pintu Jendela) - -
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.15 1,008,343.60 148,831.52 0.02 0.15 100.00 0.02 - - - 0.15 100.00 0.02
2.2.6.2 Bekisting 2x Pakai m2 0.98 197,959.30 194,791.95 0.02 0.98 100.00 0.02 - - - 0.98 100.00 0.02
2.2.6.3 Besi Beton Ø10 SNI, Ø6 SNI kg 20.35 21,465.73 436,752.39 0.04 20.35 100.00 0.04 - - - 20.35 100.00 0.04
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) m2 59.01 163,856.00 9,669,142.56 0.98 59.01 100.00 0.98 - - - 59.01 100.00 0.98
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4) m2 48.59 102,876.77 4,998,782.09 0.50 48.59 100.00 0.50 - - - 48.59 100.00 0.50
2.5 Pekerjaan Rangka Plafond dan Dinding Dalam PVC Shunda (Besi Hollow Metal Galvalume 4/4) m2 56.16 102,876.77 5,777,559.22 0.58 - - - 56.16 100.00 0.58 56.16 100.00 0.58

TOTAL PEKERJAAN STRUKTUR 59,815,965.86 6.04 5.29 0.75 6.04

3. PEKERJAAN FINISHING ARSITEKTUR


3.1 Pekerjaan Lantai, Dinding, Plafond
3.1.1 Pekerjaan Lantai
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) m3 4.09 174,757.00 715,280.40 0.07 4.09 100.00 0.07 - - - 4.09 100.00 0.07
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) m3 12.28 167,345.00 2,054,804.70 0.21 12.28 100.00 0.21 - - - 12.28 100.00 0.21
3.1.1.3 Rabat Beton T.5 cm (Keseluruhan, Beton K300) m3 4.09 1,118,398.60 4,577,605.47 0.46 4.09 100.00 0.46 - - - 4.09 100.00 0.46
3.1.1.4 Penutup Lantai Keramik Tekstur 60x60 (Badan Bangunan) m2 36.93 413,098.40 15,255,723.91 1.54 29.54 80.00 1.23 7.39 20.00 0.31 36.93 100.00 1.54
3.1.1.5 Penutup Lantai Andesit Polos 30x30 (Selasar, Ruang Bilas) m2 45.89 284,369.80 13,049,730.12 1.32 - - - 45.89 100.00 1.32 45.89 100.00 1.32
3.1.1.6 Penutup Plat Wastafel (Granit 60x60, Toilet Pria dan Wanita) m2 2.20 841,621.73 1,851,567.81 0.19 - - - 2.20 100.00 0.19 2.20 100.00 0.19
3.1.2 Pekerjaan Dinding - - -
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Selasar, 1 Sp : 4 Pp) 90.64 242,533.50 21,983,236.44 2.22 72.51 80.00 1.78 18.13 20.00 0.44 90.64 100.00 2.22
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Wc ) 30.00 65,473.32 1,964,199.60 0.20 24.00 80.00 0.16 6.00 20.00 0.04 30.00 100.00 0.20
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm 121.28 60,304.20 7,313,693.38 0.74 97.02 80.00 0.59 24.26 20.00 0.15 121.28 100.00 0.74
3.1.2.4 Coating Bening 121.28 46,853.13 5,682,347.00 0.57 - - - 121.28 100.00 0.57 121.28 100.00 0.57
3.1.2.5 Dinding Andesit Polos 30x30 cm ( Wc, Ruang Bilas ) 56.52 284,369.80 16,072,581.10 1.62 - - - 56.52 100.00 1.62 56.52 100.00 1.62
3.1.2.6 Dinding Keramik 30x60 cm ( Sisi Dalam ) 69.88 370,557.00 25,894,523.16 2.62 - - - 69.88 100.00 2.62 69.88 100.00 2.62
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) 9.00 995,076.50 8,955,688.50 0.90 - - - 9.00 100.00 0.90 9.00 100.00 0.90
3.1.2.8 Cubicle Panel + Accessories (Pintu Wc dan Partisi Urinoir) 10.86 1,360,000.00 14,769,600.00 1.49 - - - 10.86 100.00 1.49 10.86 100.00 1.49
3.1.2.9 Dinding Bitumen Gelombang 48.59 201,749.24 9,802,995.57 0.99 - - - 48.59 100.00 0.99 48.59 100.00 0.99
3.1.2.10 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Pria) 1.00 1,200,000.00 1,200,000.00 0.12 - - - 1.00 100.00 0.12 1.00 100.00 0.12
3.1.2.11 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Wanita) 1.00 750,000.00 750,000.00 0.08 - - - 1.00 100.00 0.08 1.00 100.00 0.08
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.1.3 Plafond dan Dinding Dalam Shunda ( Badan Bangunan ) 56.16 125,878.50 7,069,336.56 0.71 - - - 56.16 100.00 0.71 56.16 100.00 0.71
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.2 Pekerjaan Pintu dan Jendela ( Badan Bangunan ) - - -
3.2.1 Pintu P1 - - -
3.2.1.1 Pasangan Kusen Almunium Coating P1 (4" x 13/4") cm 10.96 157,199.02 1,722,901.26 0.17 - - - 10.96 100.00 0.17 10.96 100.00 0.17
3.2.1.2 Pasangan Daun Pintu P1 (Panel Almunium Coating - Coating) 4.30 870,323.19 3,742,389.72 0.38 - - - 4.30 100.00 0.38 4.30 100.00 0.38
3.2.1.3 Pasangan Kunci Tanam 2x Slag P1 2.00 416,663.50 833,327.00 0.08 - - - 2.00 100.00 0.08 2.00 100.00 0.08
3.2.1.4 Pasangan ensel P1 6.00 61,225.56 367,353.36 0.04 - - - 6.00 100.00 0.04 6.00 100.00 0.04
3.2.1.5 Pasangan Doorcloser P1 2.00 241,902.10 483,804.20 0.05 - - - 2.00 100.00 0.05 2.00 100.00 0.05
3.2.1.6 Pasangan Handle P1 2.00 229,802.10 459,604.20 0.05 - - - 2.00 100.00 0.05 2.00 100.00 0.05
3.2.2 Jendela J1 - - -
3.2.2.1 Pasangan Kusen Almunium Coating J1 (4" x 13/4") cm 28.80 157,199.02 4,527,331.78 0.46 - - - 28.80 100.00 0.46 28.80 100.00 0.46
3.2.2.2 Pasangan Kaca Mati 5 mm J1 0.60 145,705.56 87,423.34 0.01 - - - 0.60 100.00 0.01 0.60 100.00 0.01
3.2.3 Jendela J2 - -
3.2.3.1 Pasangan Kusen Almunium Coating J2 (4" x 13/4") cm 55.20 157,199.02 8,677,385.90 0.88 - - - 55.20 100.00 0.88 55.20 100.00 0.88
3.2.3.2 Pasangan Kaca Mati 5 mm J2 0.90 145,705.56 131,135.00 0.01 - - - 0.90 100.00 0.01 0.90 100.00 0.01
3.3. Pengecetan Plafond (1 Plamir : 1 Cat Dasar : 2 Cat Penutup), (Interior) 56.16 43,550.65 2,445,804.50 0.25 - - - 56.16 100.00 0.25 56.16 100.00 0.25
3.4 Pekerjaan Atap - - -
3.4.1 Atap Bitumen Gelombang (Badan Bangunan) 59.01 201,749.24 11,905,222.65 1.20 - - - 59.01 100.00 1.20 59.01 100.00 1.20
3.4.2 Nok Bitumen (Badan Bangunan) 35.25 143,629.20 5,062,929.30 0.51 - - - 35.25 100.00 0.51 35.25 100.00 0.51
3.4.3 Listplank (Kasiplank, Badan Bangunan, Enterance) 39.08 70,972.00 2,773,585.76 0.28 - - - 39.08 100.00 0.28 39.08 100.00 0.28

TOTAL PEKERJAAN FINISHING ARSITEKTUR 202,183,111.69 20.42 4.50 15.92 20.42

4. PEKERJAAN MEKANIKAL ELEKTRIKAL


4.1 Pasangan Instalasi Lampu
4.1.1 Pasangan PLP Panel 1.00 1,803,826.75 1,803,826.75 0.18 - - - 1.00 100.00 0.18 1.00 100.00 0.18
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt 10.00 353,938.75 3,539,387.50 0.36 - - - 10.00 100.00 0.36 10.00 100.00 0.36
4.1.3 Pasangan Lampu Down Light 2.5" Outbow LED 5.5 Watt 12.00 305,538.75 3,666,465.00 0.37 - - - 12.00 100.00 0.37 12.00 100.00 0.37
4.1.4 Pasangan Saklar Ganda 5.00 223,478.75 1,117,393.75 0.11 - - - 5.00 100.00 0.11 5.00 100.00 0.11
4.2 Pasangan Instalasi Stop Kontak - - -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA 3.00 216,218.75 648,656.25 0.07 - - - 3.00 100.00 0.07 3.00 100.00 0.07
4.2.2 Pasangan Stop Kontak Wall Exhauser 6.00 216,218.75 1,297,312.50 0.13 - - - 6.00 100.00 0.13 6.00 100.00 0.13
4.3 Pasangan Instalasi Jaringan Wall Exhauser 12.00 108,772.68 1,305,272.10 0.13 - - - 12.00 100.00 0.13 12.00 100.00 0.13
4.3.1 Pasangan Wall Exhauser 12 Inch - FV30RUN 6.00 513,500.00 3,081,000.00 0.31 - - - 6.00 100.00 0.31 6.00 100.00 0.31
4.4 Pasangan Penangkal Petir 1.00 3,500,000.00 3,500,000.00 0.35 - - - 1.00 100.00 0.35 1.00 100.00 0.35
4.5 Pasangan Instlasi Jaringan Kabel Fiber Optic (CCTV) 3.00 786,326.75 2,358,980.25 0.24 - - - 3.00 100.00 0.24 3.00 100.00 0.24
4.5.1 Pasangan CCTV Type Bullet 2 MP (Luar Bangunan, Sambungan Dari Mini Resto) 3.00 656,975.00 1,970,925.00 0.20 - - - 3.00 100.00 0.20 3.00 100.00 0.20
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm 4.00 20,442.68 81,770.70 0.01 - - - 4.00 100.00 0.01 4.00 100.00 0.01
4.6.1 Pasangan Horn Speaker (Sambungan Dari Mini Resto) 2.00 494,826.75 989,653.50 0.10 - - - 2.00 100.00 0.10 2.00 100.00 0.10
4.7 Pasangan Instalasi Titik APAR (25 kg) 2.00 4,600,000.00 9,200,000.00 0.93 - - - 2.00 100.00 0.93 2.00 100.00 0.93
4.8 Pasangan Instalasi PLN Power 1.00 10,000,000.00 10,000,000.00 1.01 - - - 1.00 100.00 1.01 1.00 100.00 1.01

TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 44,560,643.30 4.50 0.00 4.50 4.50

5. PEKERJAAN PLAMBING DAN SANITASI


5.1 Pipa PVc Tipe AW Diameter 3/4" (Air Bersih Dari Sumur Bor / PDAM Reservoir) m1 18.50 28,304.65 523,636.03 0.05 - - - 18.50 100.00 0.05 18.50 100.00 0.05
5.2 Pipa PVC Tipe AW Diameter 3/4" (Distribusi Air Bersih Dari Reservoir) m1 26.50 28,304.65 750,073.23 0.08 - - - 26.50 100.00 0.08 26.50 100.00 0.08
5.3 Pipa PVC Tipe AW Diameter 3" (Air Kotor Ke Drainase Lingkungan) m1 23.00 135,539.80 3,117,415.40 0.31 - - - 23.00 100.00 0.31 23.00 100.00 0.31
5.4 Pipa PVC Tipe AW Diameter 4" (Disposal) m1 18.00 186,689.80 3,360,416.40 0.34 - - - 18.00 100.00 0.34 18.00 100.00 0.34
5.5 Pasangan 1 bh Closet Duduk / Monoblock (TOTO) bh 6.00 3,655,597.00 21,933,582.00 2.22 - - - 6.00 100.00 2.22 6.00 100.00 2.22
5.6 Pasangan 1 bh Wastafel (TOTO) 3.00 3,571,942.00 10,715,826.00 1.08 - - - 3.00 100.00 1.08 3.00 100.00 1.08
5.7 Pasangan 1 bh Uninoir (TOTO) 2.00 6,665,285.00 13,330,570.00 1.35 - - - 2.00 100.00 1.35 2.00 100.00 1.35
5.8 Pasangan 1 bh Floor Drain 9.00 41,123.50 370,111.50 0.04 - - - 9.00 100.00 0.04 9.00 100.00 0.04
5.9 Pasangan 1 bh Kran dia. 1/2' atau 3/4" 8.00 102,228.50 817,828.00 0.08 - - - 8.00 100.00 0.08 8.00 100.00 0.08
5.10 Pasangan 1 bh Kran wastafel dia. 1/2' atau 3/4" 2.00 335,428.50 670,857.00 0.07 - - - 2.00 100.00 0.07 2.00 100.00 0.07
5.11 Pasangan 1 bh shower closet dia. 1/2' atau 3/4" 6.00 142,928.50 857,571.00 0.09 - - - 6.00 100.00 0.09 6.00 100.00 0.09
5.12 Pasangan 1 bh shower Wall dia. 1/2' atau 3/4" (Ruang Bilas) 4.00 1,435,428.50 5,741,714.00 0.58 - - - 4.00 100.00 0.58 4.00 100.00 0.58
5.13 Pasangan 1 bh Stop Kran (Gate Valve) dia. 3/4" 2.00 141,428.50 282,857.00 0.03 - - - 2.00 100.00 0.03 2.00 100.00 0.03
5.14 Pasangan Mesin Air 1.00 741,000.00 741,000.00 0.07 - - - 1.00 100.00 0.07 1.00 100.00 0.07
5.14b Pasangan Mesin Pemanas Air 1.00 5,000,000.00 5,000,000.00 0.51 - - - 1.00 100.00 0.51 1.00 100.00 0.51
5.15 Septictank Biotank Kap. 4m3 1.00 20,380,000.00 20,380,000.00 2.06 - - - 1.00 100.00 2.06 1.00 100.00 2.06
5.16 Pasangan Sumur Bor Jet Pump 30.00 350,000.00 10,500,000.00 1.06 - - - 30.00 100.00 1.06 30.00 100.00 1.06
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.17 Reservoir 1200 Liter 1.00 1,850,000.00 1,850,000.00 0.19 - - - 1.00 100.00 0.19 1.00 100.00 0.19
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.18 Reservoir 200x150x350 cm - - -
5.18.1 Pekerjaan Pondasi Pedestal Pd1 - - -
5.18.1.1 Galian Tanah Pondasi Poerplat < 1m 1.62 74,250.00 120,285.00 0.01 - - - 1.62 100.00 0.01 1.62 100.00 0.01
5.18.1.2 Urugan Tanah Kembali Pondasi Poerplat 0.43 55,000.00 23,760.00 0.00 - - - 0.43 100.00 0.00 0.43 100.00 0.00
5.18.1.3 Tiang Pondasi Pedestal 50x50 cm - -
Beton Mutu fc = 26,6 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.80 1,485,144.21 1,188,115.37 0.12 - - - 0.80 100.00 0.12 0.80 100.00 0.12
Bekisting 2x Pakai 3.20 193,504.30 619,213.76 0.06 - - - 3.20 100.00 0.06 3.20 100.00 0.06
Besi Beton Ø12, Ø8 49.44 21,465.73 1,061,174.10 0.11 - - - 49.44 100.00 0.11 49.44 100.00 0.11
5.18.1.4 Pondasi Poerplat 90x90 cm,T.20 cm - - -
Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.65 1,485,144.21 962,373.45 0.10 - - - 0.65 100.00 0.10 0.65 100.00 0.10
Bekisting 2x Pakai 1.44 124,547.50 179,348.40 0.02 - - - 1.44 100.00 0.02 1.44 100.00 0.02
Besi Beton Ø14 SNI 214.35 21,465.73 4,601,114.73 0.46 - - - 214.35 100.00 0.46 214.35 100.00 0.46
5.18.2 Rangkai Tengah Dan Lantai Menara (Besi Hollow Galvanis 4/4) 34.82 244,970.00 8,529,855.40 0.86 - - - 34.82 100.00 0.86 34.82 100.00 0.86
5.18.3 Rangka Utama menara ( Besi Hollow Galvanis 5/10 32.28 179,454.00 5,792,775.12 0.59 - - - 32.28 100.00 0.59 32.28 100.00 0.59
5.18.4 Tplat Baja Lantai Menara T.3mm 3.00 740,164.86 2,220,494.57 0.22 - - - 3.00 100.00 0.22 3.00 100.00 0.22
5.18.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) 5.00 244,970.00 1,224,850.00 0.12 - - - 5.00 100.00 0.12 5.00 100.00 0.12

TOTAL PEKERJAAN PLAMBING DAN SANITASI 127,466,817.45 12.88 - 12.88 12.88

6. PEKERJAAN AKHIR - - -
6.1 Pembersihan Sisa Pekerjaan Ls 1.00 2,400,000.00 2,400,000.00 0.24 - - - 1.00 100.00 0.24 1.00 100.00 0.24

TOTAL PEKERJAAN AKHIR 2,400,000.00 0.24 0.00 0.24 0.24

C. PENERAPAN SMKK

1. PENYIAPAN RKK
1.1 Pembuatan Dokumen Rencana Keselamatan Konstruksi
1.2 Pembuatan Prosedur dan instruksi kerja Set 1.00 2,000,000.00 2,000,000.00 0.20 1.00 100.00 0.20 - - 1.00 100.00 0.20
1.3 Penyiapan formulir
TOTAL PENYIAPAN RKK 2,000,000.00 0.20 0.20 - 0.20
2. SOSIALISASI, PROMOSI DAN PELATIHAN
2.1 Induksi K3 (Safety Induction) Org 5.00 7,500.00 37,500.00 0.00 0.50 10.00 0.00 4.50 90.00 0.00 5.00 100.00 0.00
2.2 Pengarahan K3 (Safety Briefing) Org 5.00 15,000.00 75,000.00 0.01 5.00 100.00 0.01 - - 5.00 100.00 0.01
2.3 Pelatihan K3 - - -
2.3.1 Bekerja di ketinggian Org 4.00 7,500.00 30,000.00 0.00 4.00 100.00 0.00 - - 4.00 100.00 0.00
2.3.2 Penggunaan Bahan Kimia (MSDS) Org 2.00 7,500.00 15,000.00 0.00 2.00 100.00 0.00 - - 2.00 100.00 0.00
2.4 Simulasi K3 Org 5.00 7,500.00 37,500.00 0.00 5.00 100.00 0.00 - - 5.00 100.00 0.00
2.5 Spanduk (Banner) Lb 1.00 150,000.00 150,000.00 0.02 1.00 100.00 0.02 - - 1.00 100.00 0.02
2.6 Poster 2 2.00 50,000.00 100,000.00 0.01 2.00 100.00 0.01 - - 2.00 100.00 0.01
2.7 Papan Informasi K3 1 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
TOTAL SOSIALISASI, PROMOSI DAN PELATIHAN 945,000.00 0.10 0.09 0.00 0.10
3. ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI
3.1 APK
3.1.1 Tali Keselamatan (Life Line) Ls 1.00 1,700,000.00 1,700,000.00 0.17 1.00 100.00 0.17 - - - 1.00 100.00 0.17
3.1.2 Pembatas Area (Restricted Area) Ls 1.00 2,000,000.00 2,000,000.00 0.20 1.00 100.00 0.20 - - - 1.00 100.00 0.20
3.2 APD - -
3.2.1 Topi Pelindung (Safety Helmet) Bh 10.00 75,000.00 750,000.00 0.08 10.00 100.00 0.08 - - - 10.00 100.00 0.08
3.2.2 Pelindung Mata (Googles, Spectacles) Bh 5.00 25,000.00 125,000.00 0.01 5.00 100.00 0.01 - - - 5.00 100.00 0.01
3.2.3 Pelindung Pernapasan dan Mulut (Masker) Bh 100.00 5,000.00 500,000.00 0.05 100.00 100.00 0.05 - - - 100.00 100.00 0.05
3.2.4 Sarung Tangan (Safety Gloves) Psg 10.00 15,000.00 150,000.00 0.02 10.00 100.00 0.02 - - - 10.00 100.00 0.02
3.2.5 Sepatu Keselamatan (Safety Shoes) Psg 10.00 350,000.00 3,500,000.00 0.35 10.00 100.00 0.35 - - - 10.00 100.00 0.35
3.2.6 Penunjang Seluruh Tubuh (Full Body Harness) Bh 2.00 500,000.00 1,000,000.00 0.10 2.00 100.00 0.10 - - - 2.00 100.00 0.10
3.2.7 Rompi Keselamatan (Safety Vest) Bh 10.00 25,000.00 250,000.00 0.03 10.00 100.00 0.03 - - - 10.00 100.00 0.03
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 9,975,000.00 1.01 1.01 - 1.01
BULAN LALU BULAN INI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4. ASURANSI DAN PERIZINAN
4.1 Asuransi Ls 1.00 3,000,000.00 3,000,000.00 0.30 1.00 100.00 0.30 - - - 1.00 100.00 0.30
TOTAL ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 3,000,000.00 0.30 0.30 - 0.30
5. PERSONEL K3 KONSTRUKSI
5.1 Ahli K3 Konstruksi -
5.2 Petugas K3 Konstruksi Ob 4.00 3,675,000.00 14,700,000.00 1.48 4.00 100.00 1.48 - - - 4.00 100.00 1.48
TOTAL PERSONEL K3 KONSTRUKSI 14,700,000.00 1.48 1.48 - 1.48
6. FASILITAS, SARANA DAN PRASARANA KESEHATAN
6.1 Peralatan P3K (Kotak P3K, Tandu, Obat Luka, Perban, dll) Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
TOTAL FASILITAS, SARANA DAN PRASARANA KESEHATAN 500,000.00 0.05 0.05 - 0.05
7. RAMBU - RAMBU YANG DIPERLUKAN
7.1 Rambu Petunjuk bh 2.00 75,000.00 150,000.00 0.02 2.00 100.00 0.02 - - 2.00 100.00 0.02
7.2 Rambu Larangan bh 2.00 75,000.00 150,000.00 0.02 2.00 100.00 0.02 - - 2.00 100.00 0.02
7.3 Rambu Peringatan bh 2.00 100,000.00 200,000.00 0.02 2.00 100.00 0.02 - - 2.00 100.00 0.02
7.4 Jalur Evakuasi (Escape Route) Ls 1.00 250,000.00 250,000.00 0.03 1.00 100.00 0.03 - - 1.00 100.00 0.03
TOTAL RAMBU - RAMBU YANG DIPERLUKAN 750,000.00 0.08 0.08 - 0.08
8. KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI
8.1 Ahli K3 Konstruksi Oj -
TOTAL KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI - 0.00
9. LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN
KONSTRUKSI
9.1 Alat Pemadam Api Ringan (APAR) bh 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
9.2 Program Inspeksi Ls 1.00 1,500,000.00 1,500,000.00 0.15 1.00 100.00 0.15 - - 1.00 100.00 0.15
9.3 Pelaporan dan Penyeledikan Insiden Ls 1.00 500,000.00 500,000.00 0.05 1.00 100.00 0.05 - - 1.00 100.00 0.05
9.4 Pembuatan Kartu Identitas Pekerja (KIP) Org 10.00 5,000.00 50,000.00 0.01 10.00 100.00 0.01 - - 10.00 100.00 0.01
TOTAL LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN KONSTRUKSI 2,550,000.00 0.26 0.26 - 0.26

A Jumlah Harga Penawaran 989,944,870.91 100.00 34.46 65.54 100.00


B PPN (10%) 98,994,487.09
C Jumlah (A+B) 1,088,939,358.00
PERSENTASE SAMPAI BULAN INI 100.00
D Jumlah Dibulatkan 1,088,939,358.00

Bulukumba, 14 Desember 2020


Disetujui, Diketahui, Diperiksa Oleh, Dibuat Oleh,
Pejabat Pembuat Komitmen Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUTR Prov SulSel Dinas PUTR Prov SulSel CV.MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL

A.KHADAFI HARUN, ST.,MT. L I L I, ST. IRHAM HARAHAP, ST. VIKA APRILIA DWI PUTRI
NIP. 19811126 200901 1 008 NIP. 19821229 201503 2 001 Site Engineer Direktris
LAPORAN KEMAJUAN MINGGUAN

Kegiatan : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba Minggu Ke : 09 ( Sembilan )
Satuan Kerja : Dinas Pekerjaan Umum Dan Tata Ruang Prov. Sulawesi Selatan Bidang Cipta Karya Periode : 11 Desember S/d 14 Desember 2020
Lokasi : Desa Ara, Kecamatan Bonto Bahari, Kabupaten Bulukumba, Provinsi Sulawesi Selatan No. Kontrak : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
Sumber Dana : Dana Bantuan Provinsi Nilai Kontrak : Rp. 1,088,939,358.00
Tahun Anggaran : 2020 Schedule Pelaksanaan : 16 Oktober S/d 14 Desember 2020

MINGGU LALU MINGGU INI S/D MINGGU INI


NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q

A. PEMBANGUNAN RUANG KULINER, SUVENIR, MUSHOLLAH DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN
1.1 Papan Proyek Ls 1.00 500,000.00 500,000.00 0.05 - - 1.00 100.00 0.05 1.00 100.00 0.05 -
1.2 Bedeng/Direksi Keet M2 5.50 1,512,555.00 8,319,052.50 0.84 - - 5.50 100.00 0.84 5.50 100.00 0.84 -
-
TOTAL PEKERJAAN PERSIAPAN 8,819,052.50 0.89 0.00 0.89 0.89 -
-
2. PEKERJAAN STRUKTUR -
2.1 Pekerjaan Pondasi -
2.1.1 Pekerjaan Pondasi Poerplat PP1 (Selasar Samping) -
2.1.1.1 Galian Pondasi Poerplat < 1 m M3 0.32 73,837.50 23,628.00 0.00 - - 0.32 100.00 0.00 0.32 100.00 0.00 0.49
2.1.1.2 Urugan Pasir dibawah Pondasi Poerplat T.5 cm M3 0.04 148,335.00 5,933.40 0.00 - - 0.04 100.00 0.00 0.04 100.00 0.00 0.04
2.1.1.3 Urugan Tanah Kembali Pondasi Poerplat M3 0.31 54,175.00 16,794.25 0.00 - - 0.31 100.00 0.00 0.31 100.00 0.00 0.49
2.1.1.4 Pasangan Lantai Kerja bawah Pondasi Poerplat T.5 cm (Beton K300) M3 0.04 1,118,216.00 44,728.64 0.00 - - 0.04 100.00 0.00 0.04 100.00 0.00 0.04
2.1.1.5 Pondasi Poerplat 35x50 cm, T.20 cm - - -
Beton Mutu F'c = 26,4 mpa (K300), Slump (12-2) cm, w/c = 0,52 M3 0.14 1,118,216.00 156,550.24 0.02 - - 0.14 100.00 0.02 0.14 100.00 0.02 0.29
Bekisting 2x Pakai M2 0.56 107,013.50 59,927.56 0.01 - - 0.56 100.00 0.01 0.56 100.00 0.01 0.99
Besi Beton Ø14 SNI Kg 29.40 21,464.85 631,066.59 0.06 - - 29.40 100.00 0.06 29.40 100.00 0.06 64.25
2.1.2 Pekerjaan Pondasi Batu Kali (Badan Bangunan, Mushollah) - - -
2.1.2.1 Galian Tanah Pondasi Batu Kali < 1 m M3 22.73 73,837.50 1,678,326.38 0.17 - - 22.73 100.00 0.17 22.73 100.00 0.17 26.13
2.1.2.2 Urugan Pasir dibawah Pondasi Batu Kali T.5 cm M3 1.08 148,335.00 160,201.80 0.02 - - 1.08 100.00 0.02 1.08 100.00 0.02 1.28
2.1.2.3 Pasangan Aanstamping bawah Pondasi Batu Kali T.10 M3 2.17 382,674.00 830,402.58 0.08 - - 2.17 100.00 0.08 2.17 100.00 0.08 3.85
2.1.2.4 Urugan Tanah Kembali Pondasi Batu Kali M3 10.39 54,175.00 562,878.25 0.06 - - 10.39 100.00 0.06 10.39 100.00 0.06 12.88
2.1.2.5 Pondasi Batu Kali 1 Sp : 3 Pp M3 9.09 827,447.50 7,521,497.78 0.76 - - 9.09 100.00 0.76 9.09 100.00 0.76 8.12
2.1.3 Pekerjaan Pondasi Rollage L.15 cm (Entrance, Selasar Samping) - - - -
2.1.3.1 Galian Tanah Pondasi Rollage < 1 m M3 2.23 73,837.50 164,657.63 0.02 - - 2.23 100.00 0.02 2.23 100.00 0.02 4.59
2.1.3.2 Urugan Pasir dibawah Pondasi Rollage T.5 cm M3 0.45 148,335.00 66,750.75 0.01 - - 0.45 100.00 0.01 0.45 100.00 0.01 -
2.1.3.3 Pasangan Lantai Kerja bawah Pondasi Rollage T.5 cm (Beton K300) M3 0.45 1,118,216.00 499,003.89 0.05 - - 0.45 100.00 0.05 0.45 100.00 0.05 2.30
2.1.3.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp M2 20.83 128,436.00 2,675,321.88 0.27 - - 20.83 100.00 0.27 20.83 100.00 0.27 22.95
2.2 Pekerjaan Sloef, Kolom dan Ringbalk - - -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Mushollah) - - -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 1.62 1,118,216.00 1,815,703.23 0.18 - - 1.62 100.00 0.18 1.62 100.00 0.18 1.60
2.2.1.2 Bekisting 2x Pakai M2 10.83 114,438.50 1,239,368.96 0.13 - - 10.83 100.00 0.13 10.83 100.00 0.13 10.70
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI Kg 280.09 21,464.85 6,012,089.84 0.61 - - 280.09 100.00 0.61 280.09 100.00 0.61 377.86
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan, Mushollah) - - -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.88 1,118,216.00 981,234.54 0.10 - - 0.88 100.00 0.10 0.88 100.00 0.10 0.82
2.2.2.2 Bekisting 2x Pakai M2 5.85 193,468.00 1,131,787.80 0.11 - - 5.85 100.00 0.11 5.85 100.00 0.11 14.55
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 181.66 21,464.85 3,899,347.58 0.39 - - 181.66 100.00 0.39 181.66 100.00 0.39 193.33
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Selasar, Westafel, Tempat Wudhu) - -
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 - - 0.34 100.00 0.03 0.34 100.00 0.03 0.19
2.2.3.2 Bekisting 2x Pakai M2 2.26 193,468.00 437,237.68 0.04 - - 2.26 100.00 0.04 2.26 100.00 0.04 4.95
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 70.10 21,464.85 1,504,686.30 0.15 - - 70.10 100.00 0.15 70.10 100.00 0.15 41.43
2.2.4 Pekerjaan Kolom K1 15 x 30 (Selasar Samping) - -
2.2.4.1 Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 M3 0.62 1,118,216.00 694,412.14 0.07 - - 0.62 100.00 0.07 0.62 100.00 0.07 0.50
2.2.4.2 Bekisting 2x Pakai M2 6.21 193,468.00 1,201,436.28 0.12 - - 6.21 100.00 0.12 6.21 100.00 0.12 9.90
2.2.4.3 Besi Beton Ø12 SNI, Ø8 SNI Kg 99.69 21,464.85 2,139,830.90 0.22 - - 99.69 100.00 0.22 99.69 100.00 0.22 60.05
2.2.5 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan, Mushollah) - -
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 2.08 1,008,161.00 2,097,478.96 0.21 - - 2.08 100.00 0.21 2.08 100.00 0.21 1.28
2.2.5.2 Bekisting 2x Pakai M2 13.87 197,923.00 2,745,192.01 0.28 - - 13.87 100.00 0.28 13.87 100.00 0.28 10.70
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 299.22 21,464.85 6,422,712.42 0.65 - - 299.22 100.00 0.65 299.22 100.00 0.65 83.60
2.2.6 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan) - -
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.34 1,008,161.00 342,774.74 0.03 - - 0.34 100.00 0.03 0.34 100.00 0.03 0.58
2.2.6.2 Bekisting 2x Pakai M2 2.24 197,923.00 443,347.52 0.04 - - 2.24 100.00 0.04 2.24 100.00 0.04 9.74
2.2.6.3 Besi Beton Ø12 SNI, Ø6 SNI Kg 48.32 21,464.85 1,037,181.55 0.10 - - 48.32 100.00 0.10 48.32 100.00 0.10 179.70
2.2.7 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Mushollah, Pintu Jendela) - -
2.2.7.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.84 1,008,161.00 846,855.24 0.09 - - 0.84 100.00 0.09 0.84 100.00 0.09 -
2.2.7.2 Bekisting 2x Pakai M2 5.59 197,923.00 1,106,389.57 0.11 - - 5.59 100.00 0.11 5.59 100.00 0.11 -
2.2.7.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 115.53 21,464.85 2,479,834.12 0.25 - - 115.53 100.00 0.25 115.53 100.00 0.25 -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.2.8 Pekerjaan Plat Beton (Selasar Samping, Westafel) - -
2.2.8.1 Beton Mutu fc = 14,5 Mpa (K175), Slump (12 - 2) cm, w/c = 0,66 M3 0.22 1,008,161.00 221,795.42 0.02 - - 0.22 100.00 0.02 0.22 100.00 0.02 -
2.2.8.2 Bekisting 2x Pakai M2 2.21 237,468.00 524,804.28 0.05 - - 2.21 100.00 0.05 2.21 100.00 0.05 -
2.2.8.3 Besi Beton Ø10 SNI, Ø6 SNI Kg 54.54 21,464.85 1,170,692.92 0.12 - - 54.54 100.00 0.12 54.54 100.00 0.12 -
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) M2 152.03 163,636.00 24,877,581.08 2.51 - - 152.03 100.00 2.51 152.03 100.00 2.51 152.83
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4, Entrance) M2 42.24 242,170.50 10,229,281.92 1.03 - - 42.24 100.00 1.03 42.24 100.00 1.03 -
2.5 Pekerjaan Tiang Atap Bitumen Gelombang (Besi Hollow Galvanis 5/10, Entrance) M' 20.40 178,365.00 3,638,646.00 0.37 - - 20.40 100.00 0.37 20.40 100.00 0.37 -
2.6 Pekerjaan Rangka Plafond Kalsiboard (Besi Hollow Metal Galvalume 4/4) M2 147.40 102,837.17 15,158,198.37 1.53 - - 147.40 100.00 1.53 147.40 100.00 1.53 -
- -
TOTAL PEKERJAAN STRUKTUR 109,840,345.70 11.10 0.00 - 11.10 11.10 -
- -
3. PEKERJAAN FINISHING ARSITEKTUR - -
3.1 Pekerjaan Lantai, Dinding, Plafond - -
3.1.1 Pekerjaan Lantai - -
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) M3 8.54 148,335.00 1,266,780.90 0.13 - - 8.54 100.00 0.13 8.54 100.00 0.13 11.59
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) M3 25.63 167,227.00 4,285,636.74 0.43 - - 25.63 100.00 0.43 25.63 100.00 0.43 27.59
3.1.1.3 Rabat Beton bawah Lantai T.5 cm (Keseluruhan, Beton K300) M3 8.54 1,118,216.00 9,549,564.64 0.96 - - 8.54 100.00 0.96 8.54 100.00 0.96 5.30
3.1.1.4 Penutup Lantai Keramik Motif 60x60 (Badan Bangunan, Mushollah) M2 62.94 403,309.50 25,384,299.93 2.56 - - 59.79 95.00 2.44 59.79 95.00 2.44 -
3.1.1.5 Penutup Lantai Conwood Deck 6" (Entrance) M2 59.01 866,833.08 51,151,820.09 5.17 - - 56.01 94.92 4.90 56.01 94.92 4.90 -
3.1.1.6 Penutup Lantai Andesit Polos 30x30 (Selasar, Tempat Wudhu, Ram) M2 51.05 232,589.50 11,873,693.98 1.20 - - 51.05 100.00 1.20 51.05 100.00 1.20 -
3.1.1.7 Plint Lantai Keramik 10x60 (Badan Bangunan, Mushollah) M' 38.85 51,605.03 2,004,855.55 0.20 - - - - - - - -
3.1.2 Pekerjaan Dinding - -
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Mushollah, 1 Sp : 4 Pp) M2 74.55 242,979.00 18,114,084.45 1.83 - - 74.55 100.00 1.83 74.55 100.00 1.83 67.31
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Selasar Samping, Tempat Wudhu) M2 5.14 65,550.32 336,928.64 0.03 - - 5.14 100.00 0.03 5.14 100.00 0.03 15.73
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm (Badan Bangunan, Mushollah) M2 91.30 60,403.20 5,514,812.16 0.56 - - 91.30 100.00 0.56 91.30 100.00 0.56 74.37
3.1.2.4 Plesteran Ciprat 1 Sp : 2 Pp Tebal 15 mm (Selasar Samping, Antar Kolom) M2 24.84 49,215.10 1,222,503.08 0.12 - - 24.84 100.00 0.12 24.84 100.00 0.12 -
3.1.2.5 Dinding Keramik Mozaik 30x60 (Selasar Samping, Westafel, Tempat Wudhu) M2 18.44 410,432.00 7,568,366.08 0.76 - - 18.44 100.00 0.76 18.44 100.00 0.76 -
3.1.2.6 Coating Bening (Badan Bangunan, Mushollah, Kolom Luar) M2 127.49 45,973.13 5,861,113.71 0.59 - - - - - - - - -
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) M2 8.64 995,043.50 8,597,175.84 0.87 - - 8.64 100.00 0.87 8.64 100.00 0.87 22.94
3.1.2.8 Dinding Wallpaper Bata L.50 cm (Sisi Dalam) M2 28.13 80,005.50 2,250,554.72 0.23 - - - - - - - - -
3.1.3 Pekerjaan Plafond - -
3.1.3.1 Plafond Kalsiboard (Badan Bangunan, Kemiringan Atap, Mushollah) M2 147.40 44,924.00 6,621,797.60 0.67 - - 147.40 100.00 0.67 147.40 100.00 0.67 -
3.1.3.2 Plafond Kalsiboard (Lapis Bawah Atap, Entrance) M2 42.24 44,924.00 1,897,589.76 0.19 - - 42.24 100.00 0.19 42.24 100.00 0.19 -
3.2 Pekerjaan Pintu dan Jendela (Badan Bangunan) - -
3.2.1 Pintu P1 (Entrance dan Back Entrance, Badan Bangunan) - -
3.2.1.1 Pasangan Kusen Alumunium Coating P1 (4" x 1 3/4") cm M' 22.40 157,194.40 3,521,154.56 0.36 - - 22.40 100.00 0.36 22.40 100.00 0.36 -
3.2.1.2 Pasangan Daun Pintu P1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - - - -
3.2.1.3 Pasangan Kaca Mati 5 mm P1 M2 11.20 145,703.80 1,631,882.56 0.16 - - - - - - - - -
3.2.1.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - - - -
3.2.1.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - - - -
3.2.1.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - - - -
3.2.1.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - - - -
3.2.2 Jendela J1 (Badan Bangunan) - -
3.2.2.1 Pasangan Kusen Alumunium Coating J1 (4" x 1 3/4") cm M' 40.60 157,194.40 6,382,092.64 0.64 - - 40.60 100.00 0.64 40.60 100.00 0.64 -
3.2.2.2 Pasangan Kaca Mati 5 mm J1 M2 8.00 145,703.80 1,165,630.40 0.12 - - - - - - - - -
3.2.3 Pintu PJ1 (Mushollah) - -
3.2.3.1 Pasangan Kusen Alumunium Coating PJ1 (4" x 1 3/4") cm M' 22.20 157,194.40 3,489,715.68 0.35 - - 22.20 100.00 0.35 22.20 100.00 0.35 -
3.2.3.2 Pasangan Daun Pintu PJ1 (Pintu Kaca Rangka Alumunium Coating) M2 7.04 838,794.00 5,905,109.76 0.60 - - - - - - - - -
3.2.3.3 Pasangan Kaca Mati 5 mm P1 M2 8.70 145,703.80 1,267,623.06 0.13 - - - - - - - - -
3.2.3.4 Pasangan Kunci Tanam 2xSlag P1 Bh 2.00 416,652.50 833,305.00 0.08 - - - - - - - - -
3.2.3.5 Pasangan Engsel P1 Bh 12.00 61,223.80 734,685.60 0.07 - - - - - - - - -
3.2.3.6 Pasangan Doorcloser P1 Bh 4.00 241,895.50 967,582.00 0.10 - - - - - - - - -
3.2.3.7 Pasangan Handle P1 Set 4.00 229,795.50 919,182.00 0.09 - - - - - - - - -
3.3 Pekerjaan Pengecatan - -
3.3.1 Pengecatan Plafond (1 Plamir ; 1 Cat Dasar : 2 Cat Penutup), (Interior) M2 189.64 35,536.05 6,739,056.52 0.68 - - 189.64 100.00 0.68 189.64 100.00 0.68 -
3.3.2 Pengecatan Rangka Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 23.76 168,454.00 4,002,467.04 0.40 - - 23.76 100.00 0.40 23.76 100.00 0.40 -
3.3.3 Pengecatan Tiang Atap Entrance (Semprot Sistem 3 Lapis Cat Mutakhir) M2 6.12 168,454.00 1,030,938.48 0.10 - - 6.12 100.00 0.10 6.12 100.00 0.10 -
3.4 Pekerjaan Atap - -
3.4.1 Atap Bitumen Gelombang (Badan Bangunan, Mushollah) M2 152.03 207,297.09 31,515,376.59 3.18 - - 152.03 100.00 3.18 152.03 100.00 3.18 -
3.4.2 Atap Bitumen Gelombang (Entrance) M2 42.24 207,297.09 8,756,229.08 0.88 - - 42.24 100.00 0.88 42.24 100.00 0.88 -
3.4.3 Nok Bitumen (Badan Bangunan, Mushollah) M' 14.55 134,101.00 1,951,169.55 0.20 - - 14.55 100.00 0.20 14.55 100.00 0.20 -
3.4.4 Listplank (Kalsiplank, Badan Bangunan, Mushollah, Entrance) M' 50.00 70,950.00 3,547,500.00 0.36 - - 50.00 100.00 0.36 50.00 100.00 0.36 11.33
- -
TOTAL PEKERJAAN FINISHING ARSITEKTUR 257,222,142.77 25.98 0.00 - 22.27 22.27 -
- -
4. PEKERJAAN MEKANIKAL ELEKTRIKAL - -
4.1 Pasangan Instalasi Lampu - -
4.1.1 Pasangan PLP Panel Bh 1.00 1,572,826.75 1,572,826.75 0.16 - - - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt Bh 16.00 353,938.75 5,663,020.00 0.57 - - 16.00 100.00 0.57 16.00 100.00 0.57 -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
4.1.3 Pasangan Lampu Down Light 2,5" Outbow LED 5,5 Watt Bh 11.00 305,538.75 3,360,926.25 0.34 - - 11.00 100.00 0.34 11.00 100.00 0.34 -
4.1.4 Pasangan Saklar Tunggal Bh 4.00 211,378.75 845,515.00 0.09 - - 4.00 100.00 0.09 4.00 100.00 0.09 -
4.1.5 Pasangan Saklar Ganda Bh 2.00 223,478.75 446,957.50 0.05 - - 2.00 100.00 0.05 2.00 100.00 0.05 -
4.2 Pasangan Instalasi Stop Kontak - - -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA Bh 10.00 216,218.75 2,162,187.50 0.22 - - 10.00 100.00 0.22 10.00 100.00 0.22 -
4.2.2 Pasangan Stop Kontak AC 220 VA/3520 W (AC Split 1 PK) Bh 4.00 253,728.75 1,014,915.00 0.10 - - 4.00 100.00 0.10 4.00 100.00 0.10 -
4.3 Pasangan Instalasi Jaringan AC M' 30.00 108,772.68 3,263,180.25 0.33 - - 30.00 100.00 0.33 30.00 100.00 0.33 -
4.3.1 Pasangan AC Split 1 PK Bh 3.00 3,365,799.34 10,097,398.03 1.02 - - 1.50 50.00 0.51 1.50 50.00 0.51 -
4.4 Pasangan Penangkal Petir Ls 1.00 2,500,000.00 2,500,000.00 0.25 - - 1.00 100.00 0.25 1.00 100.00 0.25 -
4.5 Pasangan Instalasi Jaringan Kabel Fiber Optic (CCTV) Ttk 6.00 786,326.75 4,717,960.50 0.48 - - - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2MP Bh 6.00 656,975.00 3,941,850.00 0.40 - - - - - - - - -
4.5.2 Pasangan NVR Channel Set 1.00 5,023,975.00 5,023,975.00 0.51 - - - - - - - - -
4.5.3 Pasangan Monitor LCD 32" Bh 1.00 2,944,975.00 2,944,975.00 0.30 - - - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm M' 12.00 20,442.68 245,312.10 0.02 - - - - - - - - -
4.6.1 Pasangan Horn Speaker Bh 6.00 494,826.75 2,968,960.50 0.30 - - - - - - - - -
4.6.2 Pasangan Volume Kontrol Set 1.00 252,826.75 252,826.75 0.03 - - - - - - - - -
4.6.3 Pasangan Perangkat Sound System Set 1.00 4,565,000.00 4,565,000.00 0.46 - - - - - - - - -
4.6.4 Pasangan TB-Sound System Set 1.00 5,846,326.75 5,846,326.75 0.59 - - - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25Kg) Ttk 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - - - -
4.8 Pasangan Instalasi Jaringan Kabel Fiber Optic (Akses Point) Ttk 3.00 786,326.75 2,358,980.25 0.24 - - - - - - - - -
4.8.1 Pasangan Server Set 1.00 7,578,826.75 7,578,826.75 0.77 - - - - - - - - -
4.8.2 Pasangan Akses Point Bh 1.00 2,034,826.75 2,034,826.75 0.21 - - - - - - - - -
4.8.3 Pasangan Switch HUB Bh 1.00 2,843,326.75 2,843,326.75 0.29 - - - - - - - - -
4.9 Pasangan Instalasi PLN Power (Inc. Jalur ke Mushollah dan Toilet) Ls 1.00 9,000,000.00 9,000,000.00 0.91 - - - - - - - - -
- -
TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 94,450,073.38 9.54 0.00 - 2.46 2.46 -
- -
5. PEKERJAAN PLAMBING DAN SANITASI - -
5.1 Pipa PVC Type AW Diameter 3/4" (Air Bersih Sambungan dari Tandon) M' 33.00 28,300.25 933,908.25 0.09 - - 16.50 50.00 0.05 16.50 50.00 0.05 -
5.2 Pipa PVC Type AW Diameter 3" (Air Kotor ke Drainase Lingkungan) M' 25.80 135,531.00 3,496,699.80 0.35 - - 25.80 100.00 0.35 25.80 100.00 0.35 -
5.3 Pasangan 1 Bh Wastafel Bh 2.00 3,934,865.00 7,869,730.00 0.79 - - 2.00 100.00 0.79 2.00 100.00 0.79 -
5.4 Pasangan 1 Bh Wastafel Cuci Piring (WCP) Bh 1.00 890,945.00 890,945.00 0.09 - - 1.00 100.00 0.09 1.00 100.00 0.09 -
5.5 Pasangan 1 Bh Floor Drain Bh 2.00 41,112.50 82,225.00 0.01 - - 2.00 100.00 0.01 2.00 100.00 0.01 -
5.6 Pasangan 1 Bh Kran Dia. 1/2" atau 3/4" Bh 10.00 102,217.50 1,022,175.00 0.10 - - 10.00 100.00 0.10 10.00 100.00 0.10 -
5.7 Pasangan 1 Bh Kran Wastafel Dia. 1/2" atau 3/4" Bh 3.00 335,417.50 1,006,252.50 0.10 - - 3.00 100.00 0.10 3.00 100.00 0.10 -
5.8 Pasangan 1 Bh Stop Kran (Gate Valve) Dia. 3/4" Bh 1.00 141,417.50 141,417.50 0.01 - - 1.00 100.00 0.01 1.00 100.00 0.01 -
5.9 Pasangan Mesin Air Bh 1.00 741,000.00 741,000.00 0.07 - - - - - - - - -
5.10 Menara Reservoir 200x150x350 cm - -
5.10.1 Pekerjaan Pondasi Pedestal Pd1 - -
5.10.1.1 Galian Tanah Pondasi Poerplat < 1 m M3 1.62 73,837.50 119,616.75 0.01 - - - - - - - - -
5.10.1.2 Urugan Tanah Kembali Pondasi Poerplat M3 0.43 54,175.00 23,295.25 0.00 - - - - - - - - -
5.10.1.3 Tiang Pondasi Pedestal 50x50 cm - - - -
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.80 1,118,216.00 894,572.80 0.09 - - - - - - - - -
Bekisting 2x Pakai M2 3.20 193,468.00 619,097.60 0.06 - - - - - - - - -
Besi Beton Ø12 SNI, Ø8 SNI Kg 49.44 21,464.85 1,061,130.60 0.11 - - - - - - - - -
5.10.1.4 Pondasi Poerplat 90x90 cm, T.20 cm - -
Beton Mutu F'c = 26,4 Mpa (K300), Slump (12-2) cm, w / c = 0,52 M3 0.65 1,118,216.00 726,840.40 0.07 - - - - - - - -
Bekisting 2x Pakai M2 1.44 107,013.50 154,099.44 0.02 - - - - - - - -
Besi Beton Ø14 SNI Kg 214.35 21,464.85 4,600,940.54 0.46 - - - - - - - -
5.10.2 Rangka Tengah dan Lantai Menara (Besi Hollow Galvanis 4/4) M2 34.82 244,970.00 8,529,855.40 0.86 - - 34.82 100.00 0.86 34.82 100.00 0.86 -
5.10.3 Rangka Utama Menara (Besi Hollow Galvanis 5/10) M' 32.28 179,454.00 5,792,775.12 0.59 - - 32.28 100.00 0.59 32.28 100.00 0.59 -
5.10.4 Plat Baja Lantai Menara T.3 mm M2 3.00 740,164.86 2,220,494.57 0.22 - - - - - - - - -
5.10.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) M2 5.00 244,970.00 1,224,850.00 0.12 - - 4.00 80.00 0.10 4.00 80.00 0.10 -
- -
TOTAL PEKERJAAN PLAMBING DAN SANITASI 42,151,921.52 4.26 0.00 - 3.06 3.06 -
- -
B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR - -
- -
1. PEKERJAAN PERSIAPAN - -
1.1 Pek. Pembersian Awal m2 81.86 17,600.00 1,440,780.00 0.15 - - 81.86 100.00 0.15 81.86 100.00 0.15 81.86
1.2 Pek. Pengukuran & Pemasangan Bouwplank m1 48.60 106,461.25 5,174,016.75 0.52 - - 48.60 100.00 0.52 48.60 100.00 0.52 65.32
- -
TOTAL PEKERJAAN PERSIAPAN 6,614,796.75 0.67 0.00 - 0.67 0.67 -
- -
2. PEKERJAAN STRUKTUR - -
2.1 Pekerjaan Pondasi - -
2.1.1 Pekerjaan Pondasi Batu Kali (Badan Bangunan,Ruang Bilas) - -
2.1.1.1 Galian Pondasi Batu Kali < 1 m m3 22.05 73,892.50 1,629,329.63 0.16 - - 22.05 100.00 0.16 22.05 100.00 0.16 6.94
2.1.1.2 Urugan Pasir Dibawah Pondasi Batu Kali T.5 cm m3 1.05 174,757.00 183,494.85 0.02 - - 1.05 100.00 0.02 1.05 100.00 0.02 1.16
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
2.1.1.3 Pasangan Aanstamping Bawah Pondasi Batu Kali T.10 cm m3 2.10 392,699.70 824,669.37 0.08 - - 2.10 100.00 0.08 2.10 100.00 0.08 2.31
2.1.1.4 Urugan Tanah Kembali Pondasi Batu Kali m3 10.08 54,285.00 547,192.80 0.06 - - 10.08 100.00 0.06 10.08 100.00 0.06 -
2.1.1.5 Pondasi Batu Kali 1 Sp : 3 Pp m3 8.82 824,945.00 7,276,014.90 0.73 - - 8.82 100.00 0.73 8.82 100.00 0.73 9.25
2.1.2 Perjaan Pondasi Rollage L.15 cm (Selasar) - -
2.1.2.1 Galian Tanah Pondasi Rollage < 1 m m3 1.52 73,892.50 112,501.33 0.01 - - 0.15 10.00 0.00 0.15 10.00 0.00 -
2.1.2.2 Urugan Pasir Dibawah Pondasi Rollage T.5 cm m3 0.30 174,757.00 53,213.51 0.01 - - 0.30 100.00 0.01 0.30 100.00 0.01 0.57
2.1.2.3 Pasangan Lantai Kerja Bawah Pondasi Rollage T.5 cm (Beton K300) m3 0.30 1,118,398.60 340,552.37 0.03 - - 0.30 100.00 0.03 0.30 100.00 0.03 0.57
2.1.2.4 Pondasi Rollage L.15 cm 1 Sp : 2 Pp m3 14.21 128,260.00 1,822,574.60 0.18 - - 14.21 100.00 0.18 14.21 100.00 0.18 18.91
2.2 Pekerjaan Sloef, Kolom, Plat dan Ringbalk - - -
2.2.1 Pekerjaan Sloef S1 15/25 (Badan Bangunan, Ruang Bilas) - - -
2.2.1.1 Beton Mutu fc = 26.4 Mpa (K300), Slump (12 - 2) cm, w/c = 0,52 m3 1.41 1,118,398.60 1,580,297.22 0.16 - - 1.41 100.00 0.16 1.41 100.00 0.16
2.2.1.2 Bekisting 2x Pakai m2 9.42 114,467.10 1,078,280.08 0.11 - - 9.42 100.00 0.11 9.42 100.00 0.11 9.42
2.2.1.3 Besi Beton Ø14 SNI, Ø8 SNI kg 243.74 21,465.73 5,232,043.29 0.53 - - 243.74 100.00 0.53 243.74 100.00 0.53 243.74
2.2.2 Pekerjaan Kolom Praktis 15 x 15 (Badan Bangunan) - - -
2.2.2.1 Beton Mutu fc = 26,4 Mpa (K300), Slum (12 - 2) cm, w/c = 0,52 m3 0.48 1,118,398.60 533,476.13 0.05 - - 0.48 100.00 0.05 0.48 100.00 0.05 0.48
2.2.2.2 Bekisting 2x Pakai m2 3.18 193,504.30 615,343.67 0.06 - - 3.18 100.00 0.06 3.18 100.00 0.06 3.18
2.2.2.3 Besi Beton Ø12 SNI, Ø8 SNI kg 98.75 21,465.73 2,119,732.25 0.21 - - 98.75 100.00 0.21 98.75 100.00 0.21 98.75
2.2.3 Pekerjaan Kolom Praktis 15 x 15 (Ruang Bilas) - - -
2.2.3.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.25 1,008,343.60 249,111.29 0.03 - - 0.25 100.00 0.03 0.25 100.00 0.03 0.25
2.2.3.2 Bekisting 2x Pakai m2 1.65 193,504.30 318,701.58 0.03 - - 1.65 100.00 0.03 1.65 100.00 0.03 1.65
2.2.3.3 Besi Beton Ø12 SNI, Ø8 SNI kg 51.14 21,465.73 1,097,861.33 0.11 - - 51.14 100.00 0.11 51.14 100.00 0.11 51.14
2.2.4 Pekerjaan Ringbalk Beton RB 15/20 (Badan Bangunan) - - -
2.2.4.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.04 1,008,343.60 1,043,635.63 0.11 - - 1.04 100.00 0.11 1.04 100.00 0.11 1.04
2.2.4.2 Bekisting 2x Pakai m2 6.90 197,959.30 1,365,919.17 0.14 - - 6.90 100.00 0.14 6.90 100.00 0.14 6.90
2.2.4.3 Besi Beton Ø12 SNI, Ø6 SNI kg 148.86 21,465.73 3,195,302.68 0.32 - - 148.86 100.00 0.32 148.86 100.00 0.32 148.86
2.2.5 Pekerjaan Kuda - Kuda Beton RB 15/20 (Badan Bangunan) - - -
2.2.5.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 1.09 1,008,343.60 1,103,531.24 0.11 - - 1.09 100.00 0.11 1.09 100.00 0.11 0.55
2.2.5.2 Bekisting 2x Pakai m2 14.59 197,959.30 2,888,622.11 0.29 - - 14.59 100.00 0.29 14.59 100.00 0.29 5.47
2.2.5.3 Besi Beton Ø12 SNI, Ø6 SNI kg 157.40 21,465.73 3,378,705.12 0.34 - - 157.40 100.00 0.34 157.40 100.00 0.34 81.28
2.2.6 Pekerjaan Balok Latei BL 15/15 (Badan Bangunan, Pintu Jendela) - -
2.2.6.1 Beton Mutu fc = 14,5 Mpa (K175), Slum (12 - 2) cm, w/c = 0,66 m3 0.15 1,008,343.60 148,831.52 0.02 - - 0.15 100.00 0.02 0.15 100.00 0.02 -
2.2.6.2 Bekisting 2x Pakai m2 0.98 197,959.30 194,791.95 0.02 - - 0.98 100.00 0.02 0.98 100.00 0.02 -
2.2.6.3 Besi Beton Ø10 SNI, Ø6 SNI kg 20.35 21,465.73 436,752.39 0.04 - - 20.35 100.00 0.04 20.35 100.00 0.04 -
2.3 Pekerjaan Rangka Atap Bitumen Gelombang (Kuda - Kuda Baja Ringan) m2 59.01 163,856.00 9,669,142.56 0.98 - - 59.01 100.00 0.98 59.01 100.00 0.98 59.23
2.4 Pekerjaan Rangka Dinding Bitumen Gelombang (Besi Hollow Metal Galvalume 4/4) m2 48.59 102,876.77 4,998,782.09 0.50 - - 48.59 100.00 0.50 48.59 100.00 0.50 -
2.5 Pekerjaan Rangka Plafond dan Dinding Dalam PVC Shunda (Besi Hollow Metal Galvalume 4/4) m2 56.16 102,876.77 5,777,559.22 0.58 - - 56.16 100.00 0.58 56.16 100.00 0.58 -
- -
TOTAL PEKERJAAN STRUKTUR 59,815,965.86 6.04 0.00 - 6.03 6.03 -
- -
3. PEKERJAAN FINISHING ARSITEKTUR - -
3.1 Pekerjaan Lantai, Dinding, Plafond - -
3.1.1 Pekerjaan Lantai - -
3.1.1.1 Urugan Pasir Bawah Lantai T.5 cm (Keseluruhan) m3 4.09 174,757.00 715,280.40 0.07 - - 4.09 100.00 0.07 4.09 100.00 0.07 3.03
3.1.1.2 Urugan Tanah Bawah Lantai T.15 cm (Keseluruhan) m3 12.28 167,345.00 2,054,804.70 0.21 - - 12.28 100.00 0.21 12.28 100.00 0.21 9.10
3.1.1.3 Rabat Beton T.5 cm (Keseluruhan, Beton K300) m3 4.09 1,118,398.60 4,577,605.47 0.46 - - 4.09 100.00 0.46 4.09 100.00 0.46 3.03
3.1.1.4 Penutup Lantai Keramik Tekstur 60x60 (Badan Bangunan) m2 36.93 413,098.40 15,255,723.91 1.54 - - 36.93 100.00 1.54 36.93 100.00 1.54 31.97
3.1.1.5 Penutup Lantai Andesit Polos 30x30 (Selasar, Ruang Bilas) m2 45.89 284,369.80 13,049,730.12 1.32 - - 45.89 100.00 1.32 45.89 100.00 1.32 31.78
3.1.1.6 Penutup Plat Wastafel (Granit 60x60, Toilet Pria dan Wanita) m2 2.20 841,621.73 1,851,567.81 0.19 - - 2.20 100.00 0.19 2.20 100.00 0.19 -
3.1.2 Pekerjaan Dinding - - -
3.1.2.1 Dinding Bata Merah (Badan Bangunan, Selasar, 1 Sp : 4 Pp) 90.64 242,533.50 21,983,236.44 2.22 - - 90.64 100.00 2.22 90.64 100.00 2.22 97.40
3.1.2.2 Plesteran 1 Sp : 2 Pp Tebal 15 mm ( Wc ) 30.00 65,473.32 1,964,199.60 0.20 - - 30.00 100.00 0.20 30.00 100.00 0.20 -
3.1.2.3 Plesteran 1 Sp : 4 Pp Tebal 15 mm 121.28 60,304.20 7,313,693.38 0.74 - - 121.28 100.00 0.74 121.28 100.00 0.74 142.34
3.1.2.4 Coating Bening 121.28 46,853.13 5,682,347.00 0.57 - - - - - - - - -
3.1.2.5 Dinding Andesit Polos 30x30 cm ( Wc, Ruang Bilas ) 56.52 284,369.80 16,072,581.10 1.62 - - 56.52 100.00 1.62 56.52 100.00 1.62 -
3.1.2.6 Dinding Keramik 30x60 cm ( Sisi Dalam ) 69.88 370,557.00 25,894,523.16 2.62 - - 69.88 100.00 2.62 69.88 100.00 2.62 -
3.1.2.7 Dinding Terawang / Roster 20x20 1 Sp : 3 Pp ( Badan Bangunan ) 9.00 995,076.50 8,955,688.50 0.90 - - 9.00 100.00 0.90 9.00 100.00 0.90 -
3.1.2.8 Cubicle Panel + Accessories (Pintu Wc dan Partisi Urinoir) 10.86 1,360,000.00 14,769,600.00 1.49 - - 10.86 100.00 1.49 10.86 100.00 1.49 -
3.1.2.9 Dinding Bitumen Gelombang 48.59 201,749.24 9,802,995.57 0.99 - - 48.59 100.00 0.99 48.59 100.00 0.99 -
3.1.2.10 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Pria) 1.00 1,200,000.00 1,200,000.00 0.12 - - - - - - - - -
3.1.2.11 Pasangan Kaca Cermin Minimalis + Bingkai T.8 mm (Wc Wanita) 1.00 750,000.00 750,000.00 0.08 - - - - - - - - -
3.1.3 Plafond dan Dinding Dalam Shunda ( Badan Bangunan ) 56.16 125,878.50 7,069,336.56 0.71 - - 56.16 100.00 0.71 56.16 100.00 0.71 -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
3.2 Pekerjaan Pintu dan Jendela ( Badan Bangunan ) - - -
3.2.1 Pintu P1 - - -
3.2.1.1 Pasangan Kusen Almunium Coating P1 (4" x 13/4") cm 10.96 157,199.02 1,722,901.26 0.17 - - 10.96 100.00 0.17 10.96 100.00 0.17 -
3.2.1.2 Pasangan Daun Pintu P1 (Panel Almunium Coating - Coating) 4.30 870,323.19 3,742,389.72 0.38 - - - - - - - - -
3.2.1.3 Pasangan Kunci Tanam 2x Slag P1 2.00 416,663.50 833,327.00 0.08 - - - - - - - - -
3.2.1.4 Pasangan ensel P1 6.00 61,225.56 367,353.36 0.04 - - - - - - - - -
3.2.1.5 Pasangan Doorcloser P1 2.00 241,902.10 483,804.20 0.05 - - - - - - - - -
3.2.1.6 Pasangan Handle P1 2.00 229,802.10 459,604.20 0.05 - - - - - - - - -
3.2.2 Jendela J1 - - -
3.2.2.1 Pasangan Kusen Almunium Coating J1 (4" x 13/4") cm 28.80 157,199.02 4,527,331.78 0.46 - - 28.80 100.00 0.46 28.80 100.00 0.46 -
3.2.2.2 Pasangan Kaca Mati 5 mm J1 0.60 145,705.56 87,423.34 0.01 - - - - - - - - -
3.2.3 Jendela J2 - -
3.2.3.1 Pasangan Kusen Almunium Coating J2 (4" x 13/4") cm 55.20 157,199.02 8,677,385.90 0.88 - - - - - - - - -
3.2.3.2 Pasangan Kaca Mati 5 mm J2 0.90 145,705.56 131,135.00 0.01 - - - - - - - - -
3.3. Pengecetan Plafond (1 Plamir : 1 Cat Dasar : 2 Cat Penutup), (Interior) 56.16 43,550.65 2,445,804.50 0.25 - - 56.16 100.00 0.25 56.16 100.00 0.25 -
3.4 Pekerjaan Atap - - -
3.4.1 Atap Bitumen Gelombang (Badan Bangunan) 59.01 201,749.24 11,905,222.65 1.20 - - 59.01 100.00 1.20 59.01 100.00 1.20 -
3.4.2 Nok Bitumen (Badan Bangunan) 35.25 143,629.20 5,062,929.30 0.51 - - 35.25 100.00 0.51 35.25 100.00 0.51 -
3.4.3 Listplank (Kasiplank, Badan Bangunan, Enterance) 39.08 70,972.00 2,773,585.76 0.28 - - 39.08 100.00 0.28 39.08 100.00 0.28 -
- -
TOTAL PEKERJAAN FINISHING ARSITEKTUR 202,183,111.69 20.42 0.00 - 18.16 18.16 -
- -
4. PEKERJAAN MEKANIKAL ELEKTRIKAL - -
4.1 Pasangan Instalasi Lampu - -
4.1.1 Pasangan PLP Panel 1.00 1,803,826.75 1,803,826.75 0.18 - - - - - - - - -
4.1.2 Pasangan Lampu Down Light 4" Outbow LED 7 Watt 10.00 353,938.75 3,539,387.50 0.36 - - 10.00 100.00 0.36 10.00 100.00 0.36 -
4.1.3 Pasangan Lampu Down Light 2.5" Outbow LED 5.5 Watt 12.00 305,538.75 3,666,465.00 0.37 - - 12.00 100.00 0.37 12.00 100.00 0.37 -
4.1.4 Pasangan Saklar Ganda 5.00 223,478.75 1,117,393.75 0.11 - - 5.00 100.00 0.11 5.00 100.00 0.11 -
4.2 Pasangan Instalasi Stop Kontak - - -
4.2.1 Pasangan Stop Kontak 1 Phase 220 VA 3.00 216,218.75 648,656.25 0.07 - - 3.00 100.00 0.07 3.00 100.00 0.07 -
4.2.2 Pasangan Stop Kontak Wall Exhauser 6.00 216,218.75 1,297,312.50 0.13 - - 6.00 100.00 0.13 6.00 100.00 0.13 -
4.3 Pasangan Instalasi Jaringan Wall Exhauser 12.00 108,772.68 1,305,272.10 0.13 - - 12.00 100.00 0.13 12.00 100.00 0.13 -
4.3.1 Pasangan Wall Exhauser 12 Inch - FV30RUN 6.00 513,500.00 3,081,000.00 0.31 - - 6.00 100.00 0.31 6.00 100.00 0.31 -
4.4 Pasangan Penangkal Petir 1.00 3,500,000.00 3,500,000.00 0.35 - - 0.50 50.00 0.18 0.50 50.00 0.18 -
4.5 Pasangan Instlasi Jaringan Kabel Fiber Optic (CCTV) 3.00 786,326.75 2,358,980.25 0.24 - - - - - - - - -
4.5.1 Pasangan CCTV Type Bullet 2 MP (Luar Bangunan, Sambungan Dari Mini Resto) 3.00 656,975.00 1,970,925.00 0.20 - - - - - - - - -
4.6 Pasangan Instalasi Kabel Power NYYH 2 x 2,5 mm 4.00 20,442.68 81,770.70 0.01 - - - - - - - - -
4.6.1 Pasangan Horn Speaker (Sambungan Dari Mini Resto) 2.00 494,826.75 989,653.50 0.10 - - - - - - - - -
4.7 Pasangan Instalasi Titik APAR (25 kg) 2.00 4,600,000.00 9,200,000.00 0.93 - - - - - - - - -
4.8 Pasangan Instalasi PLN Power 1.00 10,000,000.00 10,000,000.00 1.01 - - - - - - - - -
- -
TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL 44,560,643.30 4.50 0.00 - 1.66 1.66 -
- -
5. PEKERJAAN PLAMBING DAN SANITASI - -
5.1 Pipa PVc Tipe AW Diameter 3/4" (Air Bersih Dari Sumur Bor / PDAM Reservoir) m1 18.50 28,304.65 523,636.03 0.05 - - - - - - - - -
5.2 Pipa PVC Tipe AW Diameter 3/4" (Distribusi Air Bersih Dari Reservoir) m1 26.50 28,304.65 750,073.23 0.08 - - 13.25 50.00 0.04 13.25 50.00 0.04 -
5.3 Pipa PVC Tipe AW Diameter 3" (Air Kotor Ke Drainase Lingkungan) m1 23.00 135,539.80 3,117,415.40 0.31 - - 23.00 100.00 0.31 23.00 100.00 0.31 -
5.4 Pipa PVC Tipe AW Diameter 4" (Disposal) m1 18.00 186,689.80 3,360,416.40 0.34 - - 18.00 100.00 0.34 18.00 100.00 0.34 -
5.5 Pasangan 1 bh Closet Duduk / Monoblock (TOTO) bh 6.00 3,655,597.00 21,933,582.00 2.22 - - 3.00 50.00 1.11 3.00 50.00 1.11 -
5.6 Pasangan 1 bh Wastafel (TOTO) 3.00 3,571,942.00 10,715,826.00 1.08 - - 3.00 100.00 1.08 3.00 100.00 1.08 -
5.7 Pasangan 1 bh Uninoir (TOTO) 2.00 6,665,285.00 13,330,570.00 1.35 - - 2.00 100.00 1.35 2.00 100.00 1.35 -
5.8 Pasangan 1 bh Floor Drain 9.00 41,123.50 370,111.50 0.04 - - 9.00 100.00 0.04 9.00 100.00 0.04 -
5.9 Pasangan 1 bh Kran dia. 1/2' atau 3/4" 8.00 102,228.50 817,828.00 0.08 - - 8.00 100.00 0.08 8.00 100.00 0.08 -
5.10 Pasangan 1 bh Kran wastafel dia. 1/2' atau 3/4" 2.00 335,428.50 670,857.00 0.07 - - 2.00 100.00 0.07 2.00 100.00 0.07 -
5.11 Pasangan 1 bh shower closet dia. 1/2' atau 3/4" 6.00 142,928.50 857,571.00 0.09 - - 6.00 100.00 0.09 6.00 100.00 0.09 -
5.12 Pasangan 1 bh shower Wall dia. 1/2' atau 3/4" (Ruang Bilas) 4.00 1,435,428.50 5,741,714.00 0.58 - - 4.00 100.00 0.58 4.00 100.00 0.58 -
5.13 Pasangan 1 bh Stop Kran (Gate Valve) dia. 3/4" 2.00 141,428.50 282,857.00 0.03 - - 2.00 100.00 0.03 2.00 100.00 0.03 -
5.14 Pasangan Mesin Air 1.00 741,000.00 741,000.00 0.07 - - - - - - - - -
5.14b Pasangan Mesin Pemanas Air 1.00 5,000,000.00 5,000,000.00 0.51 - - - - - - - - -
5.15 Septictank Biotank Kap. 4m3 1.00 20,380,000.00 20,380,000.00 2.06 - - 0.50 50.00 1.03 0.50 50.00 1.03 -
5.16 Pasangan Sumur Bor Jet Pump 30.00 350,000.00 10,500,000.00 1.06 - - - - - - - - -
5.17 Reservoir 1200 Liter 1.00 1,850,000.00 1,850,000.00 0.19 - - 1.00 100.00 0.19 1.00 100.00 0.19 -
MINGGU LALU MINGGU INI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
SATUAN (Rp.) (Rp.) % VOLUME VOLUME VOLUME
KOMULATIF (%) (%) KOMULATIF (%) (%) KOMULATIF (%) (%)
a b c d e f g h i k l m o p q
5.18 Reservoir 200x150x350 cm - - -
5.18.1 Pekerjaan Pondasi Pedestal Pd1 - - -
5.18.1.1 Galian Tanah Pondasi Poerplat < 1m 1.62 74,250.00 120,285.00 0.01 - - - - - - - - -
5.18.1.2 Urugan Tanah Kembali Pondasi Poerplat 0.43 55,000.00 23,760.00 0.00 - - - - - - - - -
5.18.1.3 Tiang Pondasi Pedestal 50x50 cm - -
Beton Mutu fc = 26,6 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.80 1,485,144.21 1,188,115.37 0.12 - - - - - - - - -
Bekisting 2x Pakai 3.20 193,504.30 619,213.76 0.06 - - - - - - - - -
Besi Beton Ø12, Ø8 49.44 21,465.73 1,061,174.10 0.11 - - - - - - - - -
5.18.1.4 Pondasi Poerplat 90x90 cm,T.20 cm - - -
Beton Mutu fc = 26,4 Mpa (K300), Slump (12 - 2) cm,w/c = 0,52 0.65 1,485,144.21 962,373.45 0.10 - - - - - - - - -
Bekisting 2x Pakai 1.44 124,547.50 179,348.40 0.02 - - - - - - - - -
Besi Beton Ø14 SNI 214.35 21,465.73 4,601,114.73 0.46 - - - - - - - - -
5.18.2 Rangkai Tengah Dan Lantai Menara (Besi Hollow Galvanis 4/4) 34.82 244,970.00 8,529,855.40 0.86 - - 34.82 100.00 0.86 34.82 100.00 0.86 -
5.18.3 Rangka Utama menara ( Besi Hollow Galvanis 5/10 32.28 179,454.00 5,792,775.12 0.59 - - 32.28 100.00 0.59 32.28 100.00 0.59 -
5.18.4 Tplat Baja Lantai Menara T.3mm 3.00 740,164.86 2,220,494.57 0.22 - - - - - - - - -
5.18.5 Railing Menara T.80 cm (Besi Hollow Galvanis 4/4) 5.00 244,970.00 1,224,850.00 0.12 - - 4.00 80.00 0.10 4.00 80.00 0.10 -
- -
TOTAL PEKERJAAN PLAMBING DAN SANITASI 127,466,817.45 12.88 - - 7.87 7.87 -
- -
6. PEKERJAAN AKHIR - - - - -
6.1 Pembersihan Sisa Pekerjaan Ls 1.00 2,400,000.00 2,400,000.00 0.24 - - - - - - - - -
TIME SCHEDULE

Kegiatan : Pembangunan Stop Area Mini Bira Kabupaten Bulukumba Minggu Ke : 09 ( Sembilan )
Satuan Kerja : Dinas Pekerjaan Umum Dan Tata Ruang Prov. Sulawesi Selatan Bidang Cipta Karya Periode : 11 Desember S/d 14 Desember 2020
Lokasi : Desa Ara, Kecamatan Bonto Bahari, Kabupaten Bulukumba, Provinsi Sulawesi Selatan No. Kontrak : 602.2/DPUTR-BCK/KONTRAK/SAM.BIRA
Sumber Dana : Dana Bantuan Provinsi Nilai Kontrak : Rp. 1,088,939,358.00
Tahun Anggaran : 2020 Schedule Pelaksanaan : 16 Oktober S/d 14 Desember 2020

BULAN OKTOBER - NOVEMBER BULAN NOVEMBER - DESEMBER KETERANGAN


URAIAN BOBOT % MG-01 MG-02 MG-03 MG-04 MG-05 MG-06 MG-07 MG-08 MG-09
16 - 22 23 -29 30 - 05 06 - 12 13 - 19 20 - 26 27 - 03 04 - 10 11 - 14 (%)
A. PEMBANGUNAN RUANG KULINER, SUVENIR, MUSHOLLAH DAN MENARA RESERVOIR 100%

1. PEKERJAAN PERSIAPAN 0.89 0.30 0.59

2. PEKERJAAN STRUKTUR 11.10 1.59 1.59 3.17 3.17 1.59

3. PEKERJAAN FINISHING ARSITEKTUR 25.98 5.20 5.20 10.39 5.20

4. PEKERJAAN MEKANIKAL ELEKTRIKAL 9.54 3.18 6.36

5. PEKERJAAN PLAMBING DAN SANITASI 4.26 1.70 0.85 1.70


` 75%
JUMLAH TOTAL 51.77
B. PEMBANGUNAN TOILET UMUM DAN MENARA RESERVOIR

1. PEKERJAAN PERSIAPAN 0.67 0.22 0.45

2. PEKERJAAN STRUKTUR 6.04 1.51 1.51 1.51 1.51

3. PEKERJAAN FINISHING ARSITEKTUR 20.42 2.55 5.11 5.11 2.55 2.55 2.55

4. PEKERJAAN MEKANIKAL ELEKTRIKAL 4.50 1.50 1.50 1.50

5. PEKERJAAN PLAMBING DAN SANITASI 12.88 3.22 3.22 6.44

6. PEKERJAAN AKHIR 0.24 0.24 50%

JUMLAH TOTAL 44.75


C. PENERAPAN SMKK

1. PENYIAPAN RKK 0.20 0.20

2. SOSIALISASI, PROMOSI DAN PELATIHAN 0.10 0.10

3. ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 1.01 1.01

4. ASURANSI DAN PERIZINAN 0.30 0.30


25%
5. PERSONEL K3 KONSTRUKSI 1.48 1.48

6. FASILITAS, SARANA DAN PRASARANA KESEHATAN 0.05 0.05

7. RAMBU - RAMBU YANG DIPERLUKAN 0.08 0.08

8. KONSULTASI DENGAN AHLI TERKAIT KESELAMATAN KONSTRUKSI 0.00 -

9. LAIN - LAIN TERKAIT PENGENDALIAN RESIKO KESELAMATAN 0.26 0.26

JUMLAH TOTAL 3.48


100.00 0%
PARSIAL 4.00 4.14 4.80 11.30 19.91 21.51 20.81 9.25 4.30
RENCANA
KOMULATIF 0 4.00 8.13 12.93 24.23 44.14 65.65 86.45 95.70 100.00 RENCANA
PARSIAL 0 6.26 8.61 9.86 9.87 9.44 9.53 9.09 8.97 5.37 REALISASI
REALISASI KOMULATIF 0 6.26 14.87 24.74 34.61 44.05 53.58 62.67 71.64 77.01
DEVIASI (%) 2.27 6.74 11.81 10.37 -0.09 -12.07 -23.79 -24.06 -22.99

Bulukumba, 14 Desember 2020


Disetujui, Diketahui, Diperiksa Oleh, Dibuat Oleh,
Pejabat Pembuat Komitmen Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Dinas PUTR Prov SulSel Dinas PUTR Prov SulSel CV.MULTILINE TATARANCANA CV. KARYA WAFIQ GLOBAL
A.KHADAFI HARUN, ST.,MT. L I L I, ST. IRHAM HARAHAP, ST. VIKA APRILIA DWI PUTRI
NIP. 19811126 200901 1 008 NIP. 19821229 201503 2 001 Site Engineer Direktris