GRENPOD
ALAM SUTERA TANGERANG
2. PEKERJAAN PONDASI & STRUKTUR BETON - SHOPPING AVENUE 7.81% 734,632,358.42 0.00% 0.00% 0.00% 0.00%
3. PEKERJAAN STRUKTUR BAJA - SHOPPING AVENUE 8.14% 765,959,967.00 0.00% 0.00% 0.00% 0.00%
5. PEKERJAAN LANTAI - SHOPPING AVENUE 0.84% 78,975,000.00 0.00% 0.00% 0.00% 0.00%
6. PEKERJAAN PENUTUP ATAP - SHOPPING AVENUE 10.69% 1,006,064,850.00 0.00% 0.00% 0.00% 0.00%
7. PEKERJAAN LAIN - LAIN - SHOPPING AVENUE 5.66% 532,217,625.00 0.00% 0.00% 0.00% 0.00% LUAS = 1.215 m2
SUB TOTAL SHOPPING AVENU Rp 3,216,793,095 Rp 2,647,566.33
C. PEKERJAAN FUNCTION HALL
1. PEKERJAAN TANAH & GALIAN - FUNCTION HALL 0.50% 47,037,285.00 0.00% 0.00% 0.00% 0.00%
2. PEKERJAAN PONDASI & STRUKTUR BETON - FUNCTION HALL 2.98% 280,421,905.21 0.00% 0.00% 0.00% 0.00%
3. PEKERJAAN STRUKTUR BAJA - FUNCTION HALL 3.37% 317,180,290.00 0.00% 0.00% 0.00% 0.00%
4. PEKERJAAN DINDING - FUNCTION HALL 3.29% 309,200,000.00 0.00% 0.00% 0.00% 0.00%
5. PEKERJAAN LANTAI - FUNCTION HALL 0.24% 22,620,000.00 0.00% 0.00% 0.00% 0.00%
6. PEKERJAAN PENUTUP ATAP - FUNCTION HALL 2.52% 237,196,085.00 0.00% 0.00% 0.00% 0.00%
7. PEKERJAAN LAIN - LAIN - FUNCTION HALL 2.45% 230,567,500.00 0.00% 0.00% 0.00% 0.00% LUAS 581,52 m2
SUB TOTAL FUNCTION HALL Rp 1,444,223,065 Rp 2,483,531.20
D. PEKERJAAN ART SPACE
1. PEKERJAAN TANAH & GALIAN - ART SPACE 0.57% 53,399,185.00 0.00% 0.00% 0.00% 0.00%
TOTAL Rp 11,668,603,864
Page 1 of 5
RENCANA ANGGARAN BIAYA
GRENPOD
ALAM SUTERA TANGERANG
1 Pengukuran dan pasang bowplang ls 1.00 Rp 20,000,000 Rp 20,000,000 0.21% - 0.00% - 0.00% - 0.00% 0.00%
2 Bedeng pekerja, Gudang, Toilet Pekerja ls 1.00 Rp 60,000,000 Rp 60,000,000 0.64% - 0.00% - 0.00% - 0.00% 0.00%
3 Air kerja ls 1.00 Rp 18,000,000 Rp 18,000,000 0.19% - 0.00% - 0.00% - 0.00% 0.00%
4 Listrik kerja ls 1.00 Rp 60,000,000 Rp 60,000,000 0.64% - 0.00% - 0.00% - 0.00% 0.00%
5 Kebersihan selama proyek berlangsung ls 1.00 Rp 6,000,000 Rp 6,000,000 0.06% - 0.00% - 0.00% - 0.00% 0.00%
6 Site Management bln 6.00 Rp 7,500,000 Rp 45,000,000 0.48% - 0.00% - 0.00% - 0.00% 0.00%
7 Keamanan proyek / koordinasi pengecoran ls 1.00 Rp 80,000,000 Rp 80,000,000 0.85% - 0.00% - 0.00% - 0.00% 0.00%
SUB TOTAL PEKERJAAN PERSIAPAN - SHOPPING AVENUE Rp 289,000,000 3.072% 0.000% 0.000% 0.000% 0.00%
1 Galian tanah pilecap ( 1m x 1m x 0,9m x 28 unit ) m3 25.20 Rp 125,000 Rp 3,150,000 0.03% - 0.00% - 0.00% - 0.00% 0.00%
2 Galian tanah pondasi batu kali ( 192m x 0,9m x 1,72m ) + (105m x 0,7m x 1,02m ) m3 372.19 Rp 125,000 Rp 46,523,750 0.49% - 0.00% - 0.00% - 0.00% 0.00%
3 Galian tanah tie beam ( 297m x 0,45m x 0,3m ) m3 40.10 Rp 125,000 Rp 5,011,875 0.05% - 0.00% - 0.00% - 0.00% 0.00%
4 Urugan tanah bekas galian pile cap m3 18.40 Rp 32,500 Rp 597,870 0.01% - 0.00% - 0.00% - 0.00% 0.00%
4 Urugan tanah bekas galian pondasi batu kali m3 221.84 Rp 32,500 Rp 7,209,800 0.08% - 0.00% - 0.00% - 0.00% 0.00%
5 Urugan pasir bawah pondasi batu kali ( 0,9m x 192m ) + (0,7m x 105m) x 0,05m m3 12.32 Rp - Rp - 0.00% - 0.00% - 0.00% - 0.00% #DIV/0!
6 Urugan pasir bawah lantai ruangan t = 5 cm ( 15m x 81m) x 0,05m m3 60.75 Rp 300,000 Rp 18,225,000 0.19% - 0.00% - 0.00% - 0.00% 0.00%
7 Pemadatan tanah ( 15m x 81m ) m2 1,215.00 Rp 15,000 Rp 18,225,000 0.19% - 0.00% - 0.00% - 0.00% 0.00%
SUB TOTAL PEKERJAAN TANAH & GALIAN - SHOPPING AVENUE Rp 98,943,295 1.052% 0.000% 0.000% 0.000% 0.00%
SUB TOTAL PEKERJAAN PONDASI & STRUKTUR BETON - SHOPPING AVENUE Rp 734,632,358 18.017% 0.000% 0.000% 0.000% 0.00%
SUB TOTAL PEKERJAAN STRUKTUR BAJA - SHOPPING AVENUE Rp 765,959,967 7.485% 0.000% 0.000% 0.000% 0.00%
SUB TOTAL PEKERJAAN DINDING - SHOPPING AVENUE Rp - 0.000% 0.000% 0.000% 0.000% #DIV/0!
SUB TOTAL PEKERJAAN LANTAI - SHOPPING AVENUE Rp 78,975,000 0.839% 0.000% 0.000% 0.000% 0.00%
SUB TOTAL PEKERJAAN PENUTUP ATAP - SHOPPING AVENUE Rp 1,006,064,850 3.301% 0.000% 0.000% 0.000% 0.00%
1 Plafond teakwood m2 1,702.75 Rp 225,000 Rp 383,117,625 4.07% - 0.00% - 0.00% - 0.00% 0.00%
2 Cat duco IWF 200 x 100 x 5,5 x 8 (kolom saja) / ( tidak di finish / cat duco ) m1 168.00 Rp 125,000 Rp 21,000,000 0.22% - 0.00% - 0.00% - 0.00% 0.00%
3 Talang air
Page 2 of 5
RENCANA ANGGARAN BIAYA
GRENPOD
ALAM SUTERA TANGERANG
SUB TOTAL PEKERJAAN LAIN - LAIN - SHOPPING AVENUE Rp 532,217,625 5.657% 0.000% 0.000% 0.000% 0.00%
1 Galian tanah pilecap ( 1m x 1m x 0,9m x 14 unit ) m3 12.60 Rp 125,000 Rp 1,575,000 0.10% - 0.00% - 0.00% - 0.00% 0.00%
2 Galian tanah pondasi batu kali ( 96m x 0,9m x 1,72 ) + ( 36m x 0,7 x 1,02 ) m3 194.44 Rp 125,000 Rp 24,305,000 1.51% - 0.00% - 0.00% - 0.00% 0.00%
3 Galian tanah tie beam ( 132m x 0,45m x 0,3m ) m3 17.82 Rp 125,000 Rp 2,227,500 0.14% - 0.00% - 0.00% - 0.00% 0.00%
4 Urugan tanah bekas galian pile cap m3 9.20 Rp 32,500 Rp 298,935 0.02% - 0.00% - 0.00% - 0.00% 0.00%
4 Urugan tanah bekas galian pondasi batu kali m3 122.98 Rp 32,500 Rp 3,996,850 0.25% - 0.00% - 0.00% - 0.00% 0.00%
5 Urugan pasir bawah pondasi batu kali ( 0,9m x 96m ) + (0,7m x 36m) x 0,05m m3 5.58 Rp 300,000 Rp 1,674,000 0.10% - 0.00% - 0.00% - 0.00% 0.00%
6 Urugan pasir bawah lantai ruangan t = 5 cm ( 12m x 36m) x 0,05m m3 21.60 Rp 300,000 Rp 6,480,000 0.40% - 0.00% - 0.00% - 0.00% 0.00%
7 Pemadatan tanah ( 12m x 36m ) m2 432.00 Rp 15,000 Rp 6,480,000 0.40% - 0.00% - 0.00% - 0.00% 0.00%
SUB TOTAL PEKERJAAN TANAH & GALIAN - FUNCTION HALL Rp 47,037,285 2.917% 0.000% 0.000% 0.000% 0.00%
SUB TOTAL PEKERJAAN PONDASI & STRUKTUR BETON - FUNCTION HALL Rp 280,421,905 17.388% 0.000% 0.000% 0.000% 0.00%
SUB TOTAL PEKERJAAN STRUKTUR BAJA - FUNCTION HALL Rp 317,180,290 19.667% 0.000% 0.000% 0.000% 0.00%
SUB TOTAL PEKERJAAN DINDING - FUNCTION HALL Rp 309,200,000 19.172% 0.000% 0.000% 0.000% 0.00%
SUB TOTAL PEKERJAAN LANTAI - FUNCTION HALL Rp 22,620,000 1.403% 0.000% 0.000% 0.000% 0.00%
SUB TOTAL PEKERJAAN PENUTUP ATAP - FUNCTION HALL Rp 237,196,085 14.708% 0.000% 0.000% 0.000% 0.00%
SUB TOTAL PEKERJAAN LAIN - LAIN - FUNCTION HALL Rp 230,567,500 14.297% 0.000% 0.000% 0.000% 0.00%
1 Galian tanah pilecap m3 46.80 Rp 125,000 Rp 5,850,000 0.36% - 0.00% - 0.00% - 0.00% 0.00%
2 Galian tanah pondasi batu kali m3 122.55 Rp 125,000 Rp 15,318,875 0.95% - 0.00% - 0.00% - 0.00% 0.00%
3 Galian tanah tie beam m3 43.51 Rp 125,000 Rp 5,438,925 0.34% - 0.00% - 0.00% - 0.00% 0.00%
4 Urugan tanah bekas galian pile cap m3 39.89 Rp 32,500 Rp 1,296,360 0.08% - 0.00% - 0.00% - 0.00% 0.00%
4 Urugan tanah bekas galian pondasi batu kali m3 75.42 Rp 32,500 Rp 2,451,020 0.15% - 0.00% - 0.00% - 0.00% 0.00%
Page 3 of 5
RENCANA ANGGARAN BIAYA
GRENPOD
ALAM SUTERA TANGERANG
SUB TOTAL PEKERJAAN TANAH & GALIAN - ART SPACE Rp 53,399,185 3.311% 0.000% 0.000% 0.000% 0.00%
SUB TOTAL PEKERJAAN PONDASI & STRUKTUR BETON - ART SPACE Rp 451,977,183 28.025% 0.000% 0.000% 0.000% 0.00%
SUB TOTAL PEKERJAAN STRUKTUR BAJA - ART SPACE Rp 1,410,329,298 87.449% 0.000% 0.000% 0.000% 0.00%
SUB TOTAL PEKERJAAN DINDING - ART SPACE Rp 391,688,249 24.287% 0.000% 0.000% 0.000% 0.00%
SUB TOTAL PEKERJAAN LANTAI - ART SPACE Rp 75,486,580 0.802% 0.000% 0.000% 0.000% 0.00%
SUB TOTAL PEKERJAAN PENUTUP ATAP - ART SPACE Rp 553,048,100 34.292% 0.000% 0.000% 0.000% 0.00%
SUB TOTAL PEKERJAAN LAIN - LAIN - ART SPACE Rp 292,069,000 18.110% 0.000% 0.000% 0.000% 0.00%
Page 4 of 5
RENCANA ANGGARAN BIAYA
GRENPOD
ALAM SUTERA TANGERANG
SUB TOTAL PEKERJAAN STRUKTURAL R. POMPA & GWT Rp 634,485,699 0.000% 0.000% 0.000% 0.000% #DIV/0!
SUB TOTAL PEKERJAAN STRUKTUR BANGUNAN UTILITAS Rp 595,768,124 35.748% 0.000% 0.000% 0.000% 0.00%
Page 5 of 5