PERHITUNGAN PORTAL PENAHAN

PEMBEBANAN
Dimensi b hTinggi Portal 3 m
Balok 0.1 0.2Lebar Portal m4 m
Kolom 0.1 0.15 m
PEMBEBANAN
Beam
Dead Load Weight/Unit Vol. Distributed area Conversion
Beban Sendiri 2400 kg/m3 48 kg/m 0.48 N/mm
Beban Ceiling 18 kg/m2 54 kg/m 0.54 N/mm
Beban Hebel 480 kg/m3 144 kg/m 1.44 N/mm
Total 246 kg/m 2.46 N/mm
Superdead 198 kg/m 1.98 N/mm
Dead Load Weight/Unit Vol. Distributed area Conversion
Beban Rencana 200 kg/m2 20 kg/m 0.2 N/mm
Total 20 kg/m 0.2 N/mm
Column
Dead Load Weight/Unit Vol. Distributed area Conversion
Sendiri 2400 kg/m3 36 kg/m 0.36 N/mm
Total 36 kg/m 0.36 N/mm
Light Brick
Dead Load Weight/Unit Vol. Distributed area Conversion
Sendiri 480 kg/m3 48 kg/m 0.48 N/mm
CS 7 N/mm2 7 N/mm
ACP 18 kg/m2 18 kg/m 0.18 N/mm
Base Plaster 800 kg/m3 8 kg/m 0.08 N/mm
Total kg/m 7.74 N/mm
SuperDead kg/m 7.26 N/mm
Quake Load
Wt/m = 1.2D + 1.6L
= 3.696 + 0.32
= 4.016 N/mm
Wt = 16064 N
V = (C*1*Wt)/R
= 1436.31059 N
V*0.85 = 1220.864 N
PERHITUNGAN PORTAL PENAHAN

PERHITUNGAN BALOK TUMPUAN

BAHAN STRUKTUR
Kuat tekan beton, f c' = 20 MPa
Tegangan leleh baja (deform) untuk tulangan lentur, fy = 320 MPa
Tegangan leleh baja (polos) untuk tulangan geser, fy = 320 MPa
DIMENSI BALOK
Lebar balok b= 100 mm
Tinggi balok h= 200 mm
Diameter tulangan (deform) yang digunakan, D= 10 mm
Diameter sengkang (polos) yang digunakan, P= 8 mm
Tebal bersih selimut beton, ts = 20 mm

PERHITUNGAN TULANGAN TUMPUAN

Untuk : f c' ≤ 30 MPa, b1 = 0.85


Untuk : f c' > 30 MPa, b1 = 0.85 - 0.05 * ( f c' - 30) / 7 = -
Faktor bentuk distribusi tegangan beton, b1 = 0.85
Rasio tulangan pada kondisi balance ,
rb = b1* 0.85 * f c’/ fy * 600 / ( 600 + f y ) = 0.0294
Faktor tahanan momen maksimum,
Rmax = 0.75 * r b * fy * [1 – ½*0.75* r b * fy / ( 0.85 * f c’ ) ] =
5.5986
Faktor reduksi kekuatan lentur, f = 0.8
Jarak tulangan terhadap sisi luar beton, ds = ts + Æ + D/2 = 0 mm
28.00
Jumlah tulangan dlm satu baris, ns = ((b - (2 * d s)-20) / D =
2.4
Digunakan jumlah tulangan dalam satu baris, ns = 02 bh
Jarak horisontal pusat ke pusat antara tulangan,
x = ( b - ns * D - 2 * d s ) / ( n s - 1 ) = 24.00 mm
Jarak vertikal pusat ke pusat antara tulangan, y = D + 25 = 35.00 mm

1. TULANGAN MOMEN POSITIF


Momen positif nominal rencana, (Aplikasi SAP2000) Mn = Mu +/ f = kNm
0.068
Diperkirakan jarak pusat tulangan lentur ke sisi beton, mm
d' = 38
Tinggi efektif balo . d = h - d' = 162.00 mm
Faktor tahanan momen, Rn = Mn * 10 6/ ( b * d 2 ) = 0.0257
Rn < Rmax >>> OK
Rasio tulangan yang diperlukan :
r = 0.85 * f c’ / f y * [ 1 - Ö * [1 – 2 * R n / ( 0.85 * f c’ ) ] = 0.00008
Rasio tulangan minimum, rmin = Ö f c' / ( 4 * f y ) = 0.00349
Rasio tulangan minimum, rmin = 1.4 / f y = 0.00438
PERHITUNGAN PORTAL PENAHAN
Rasio tulangan yang digunakan, r= 0.00438
2
Luas tulangan yang diperlukan, As = r * b * d = mm
88
Jumlah tulangan yang diperlukan, n = As / ( p / 4 * D 2 ) =
1.114
Digunakan tulangan, 2 D 10 2
Luas tulangan terpakai, As = n * p / 4 * D 2 = mm
157
Jumlah baris tulangan, nb = n / n s =
1.00
nb < 3 >>> (OK)
Baris Jumlah Jarak Juml. Jarak
ke ni yi ni * yi
1 2 38.00 76.00
2 - - -
3 - - -
n= 2 S [ n i * yi ] = 76
Letak titik berat tulangan, d' = S [ n i * yi ] / n = 38.00 mm
38.00 < 38 >>> perkiraan d' (OK)
Tinggi efektif balok, d = h - d' = 162.00 mm
a = As * f y / ( 0.85 * f c' * b ) = 29.568 mm
Momen nominal, Mn = As * f y * ( d - a / 2 ) * 10 -6 = 7.400 kNm
Tahanan momen balok, f * Mn = 5.920 kNm
Syarat : f * Mn ≥ Mu+
5.920 > 0.054 AMAN (OK)

2. TULANGAN MOMEN NEGATIF


Momen positif nominal rencana, Mn = Mu +/ f = kNm
0.154
Diperkirakan jarak pusat tulangan lentur ke sisi beton, mm
d' = 38
Tinggi efektif balok, d = h - d' = 162.00 mm
Faktor tahanan momen, Rn = Mn * 10 6/ ( b * d 2 ) = 0.0257
Rn > Rmax >>> OK
Rasio tulangan yang diperlukan :
r = 0.85 * f c’ / f y * [ 1 - Ö * [1 – 2 * R n / ( 0.85 * f c’ ) ]
= Rasio tulangan minimum, rmin = Ö f c' / ( 4 * f y ) 0.00008
= Rasio tulangan minimum, rmin = 1.4 / f y 0.00349
= Rasio tulangan yang digunakan, r 0.00438
= Luas tulangan yang diperlukan, As = r * b * d 0.00438 mm
2

= 88
Jumlah tulangan yang diperlukan, n = As / ( p / 4 * D 2 ) = 1.114
Digunakan tulangan, 2 D 10
2
Luas tulangan terpakai, As = n * p / 4 * D 2 = 226 mm
Jumlah baris tulangan, nb = n / n s = 0.07
nb < 3 >>> (OK)
PERHITUNGAN PORTAL PENAHAN

Baris Jumlah Jarak Juml. Jarak


ke ni yi ni * yi
1 2 38.00 76.00
2 0 0.00 0.00
3 0 0.00 0.00
n= 2 S [ n i * yi ] = 76
Letak titik berat tulangan, d' = S [ n i * yi ] / n = 38.00 mm
38.00 < 38 >>> perkiraan d' (OK)
Tinggi efektif balok, d = h - d' = 162.00 mm
a = As * f y / ( 0.85 * f c' * b ) = 29.568 mm
-6
Momen nominal, Mn = As * f y * ( d - a / 2 ) * 10 = 10.656 kNm
Tahanan momen balok, f * Mn = 8.525 kNm
Syarat : f * Mn ≥ Mu+
8.525 > 0.123 AMAN (OK)