PROYEK : RUSUN PADAT KARYA

MAPPING : FABRIKASI DAN INSTALL SEPARATOR BEAM


DATE UP TO : 02 Agustus 2021

Ra / JULI AGUSTUS
No ITEM TOTAL Ri 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
1 FABRIKASI
Ra 11 11 11 11 11 11 11 11 11 11 11 11 11
Man Power
Ri 11 11 7 7
Ra 11 11 11 11 11 11 11 11 11 11 11 11 12
FABRIKASI HBEAM 144
Ri 10 5 5 10
Deviasi -1 -6 -6 -1
SISA FABRIKASI HBEAM 134 129 124 114
Ra 6 6 6 6 6 6 6 6 6 6 6 7 7
FABRIKASI UNP 80
Ri 0 6 3 3
Deviasi -6 0 -3 -3
SISA FABRIKASI UNP 80 74 71 68

2 INSTALL
Ra 9 9 9 9 9 9 9 9 9 9 9 9 9 9
Man Power
Ri 5 5
Ra 10 10 10 10 10 10 10 10 10 10 11 11 11 11
INSTALL HBEAM 144
Ri 3 5
Deviasi -7 -5
SISA INSTALL HBEAM 141 136
Ra 5 5 5 5 6 6 6 6 6 6 6 6 6 6
INSTALL UNP 80
Ri 1 2
Deviasi -4 -3
SISA INSTALL UNP 79 77

TOTAL HBEAM Btg 144


TOTAL UNP Btg 80

NO ITEM SAT JUMLAH


FABRIKASI HBEAM Btg 30
INSTALL HBEAM Btg 8
1
SISA FABRIKASI HBEAM Btg 114
SISA INSTALL HBEAM Btg 136
FABRIKASI UNP Btg 12
INSTALL UNP Btg 3
2
SISA FABRIKASI UNP Btg 68
SISA INSTALL UNP Btg 77