NYEPI
No. URAIAN Sat 1-Mar 2-Mar 3-Mar 4-Mar 5-Mar 6-Mar 7-Mar
PLN 1 25 kVA 1 1 1 1 1 1 1
7 Harian K3 14 hari 2 2 2 2 2 2 2
8 Alat Berat 21 bh 3 3 3 3 3 3 3
9 Pile Cap 0 bh
Excavator PC 50 1 bh 1 1 1 1 1 1 1
1 MANPOWER STRUKTUR 34 34 36 36 36 36 36
2 MANPOWER ARSITEKTUR
3 MANPOWER MEP
TOTAL 34 34 36 36 36 36 36
JADWAL PENDATANGAN PERALATAN
No. URAIAN JUMLAH KAPASITAS (Minimum) 1-Mar 2-Mar 3-Mar 4-Mar 5-Mar 6-Mar 7-Mar
A. PERALATAN UTAMA 14
8 Dozer 1
14 Ringlock / Scaffolding 3
15 Pick Up 1 1 m3
16 Concrete Vibrator 2
19 Hand Stamper 1
TOTAL 45
JADWAL PENDATANGAN MATERIAL
1 MATERIAL STRUKTUR
Material Pancang 32 32 32 32 32
Material Beton
Material Baja
2 MATERIAL ARSITEKTUR
Dinding
Lantai
Langit - langit
Sanitary
Fasad
Interior
3 MATERIAL MEP
Material AC
Material Penerangan
Material Grounding
Material Genset
Material Transformator
Material CCTV