RENCANA ANGGARAN BIAYA

RUMAH 1 LANTAI
LUAS 195
JUMLAH RAB 96,455,500
BIAYA PER M2

NO JENIS PEKERJAAN SATUAN VOL HARGA SAT. JUMLAH TOTAL


PEKERJAAN

1 PEK.PERSIAPAN -
1.1 PEK. PENGUKURAN DAN BOWPLANK M' 0 - -
1.2 PEK. PEMBERSIHAN LAPANGAN DAN ALAT M2 195 10,000 1,950,000
-
2 PEL. GALIAN TANAH DAN URUGAN -
2.1 PEK. GALIAN TANAH PONDASI MENERUS M3 0 - -
2.2 PEK. URUG TANAH BEKAS GALIAN M3 0 - -
-
3 PEK. PONDASI -
3.1 PEK. PONDASI BATU KALI M3 0 - -
-
4 PEK. BETON -
4.1 PEK. SLOOF PRAKTIS M3 0 - -
4.2 PEK. KOLOM PRAKTIS M3 0 - -
4.3 PEK. BALOK LATAI M3 0 - -
4.4 PEK. PLAT ATAS KUSEN M3 0 - -
4.5 PEK. RING BALK M3 0 - -
4.6 PEK. BALOK GUNUNG-GUNUNG M3 0 - -
-
5 PEK. DINDING DAN PLESTERAN -
5.1 PEK. DINDING BATA M2 18 100,000 1,800,000
5.2 PEK. GUNUNG-GUNUNG M2 0 - -
5.3 PEK. PLESTERAN DINDING M2 18 50,000 900,000
5.4 PEK. ACIAN DINDING M2 390 20,000 7,800,000
-
6 PEK. KOSEN, DAUN PINTU DAN JENDELA -
6.1 PEK. KOSEN P1 M' 22 250,000 5,500,000
6.2 PEK. KOSEN P2 M' 0 - -
6.3 PEK. KOSEN P3 M' 0 - -
6.4 PEK. KOSEN P4 M' 0 - -
6.5 PEK. KOSEN P5 M' 0 - -
6.6 PEK. KOSEN PJ1 M' 0 - -
6.7 PEK. KOSEN PJ2 M' 0 - -
6.8 PEK. KOSEN J1 M' 25 200,000 5,000,000
6.9 PEK. KOSEN J2 M' 0 - -
6,10 PEK. KOSEN J3 M' 0 - -
6,11 PEK. DAUN PINTU P1 Bh 11 250,000 2,750,000
6,12 PEK. DAUN PINTU P2 Bh -
6,13 PEK. DAUN PINTU P3 Bh -
6,14 PEK. DAUN PINTU P4 Bh -
6,15 PEK. DAUN PINTU P5 Bh -
6,16 PEK. DAUN PINTU PJ1 Bh -
6,17 PEK. DAUN PINTU PJ2 Bh -
6,18 PEK. DAUN JENDELA J1 Bh 10 250,000 2,500,000
6,19 PEK. DAUN JENDELA PJ1 Bh -
-
7 PEK. RANGKA ATAP -
7.1 PEK. RANGKA ATAP m2 30 110,000 3,300,000
7.2 PEK. LISTPLANK M' 20 50,000 1,000,000
-
8 PEK. PENUTUP ATAP -
8.1 PAS. ATAP SENG M2 239.7 65,000 15,580,500
-
9 PEK. PLAFOND -
9.1 PEK. RANGKA PLAFOND DALAM M2 0 60,000 -
9.2 PEK. RANGKA PLAFOND LUAR M2 0 60,000 -
9.3 PEK. PENUTUP PLAFOND DALAM M2 200 50,000 10,000,000
9.4 PEK. PENUTUP PLAFOND LUAR M2 29 50,000 1,450,000
9.5 PEK. LIST PLAFOND DALAM M' 30 25,000 750,000
-
10 PEK. KERAMIK -
10.1 PAS. KERAMIK LANTAI DALAM M2 169 80,000 13,520,000
10.2 PAS. KERAMIK LANTAI KM/ WC M2 4.5 80,000 360,000
10.3 PAS. KERAMIK DINDING KM/ WC M2 10 80,000 800,000
10.4 PAS. PLINT KERAMIK LANTAI M' 0 - -
-
11 PEK. PENGUNCI -
11.1 PEK. KUNCI TANAM BIASA Bh 10 200,000 2,000,000
11.2 PEK. KUNCI TANAM KM/WC Bh 2 150,000 300,000
11.3 PEK. ENGSEL PINTU Psg 10 50,000 500,000
11.4 PEK. ENGSEL JENDELA Psg 17 30,000 510,000
11.5 PEK. SPRING KNIP Bh 0 - -
11.6 PEK. KAIT ANGIN JENDELA Bh 34 20,000 680,000
-
12 PEK. SANITAIR -
12.1 PAS. KLOSET JONGKOK Bh 2 450,000 900,000
12.2 PAS. FLOOR DRAIN Bh 0 - -
12.3 PAS. KRAN AIR Bh 2 50,000 100,000
12.4 PAS. KITCHENZINK Bh 0 - -
12.5 PAS. SHOWER Bh 0 - -
12.6 PAS. JET SPRAY Bh 0 - -
-
13 PEK. PEMIPAAN -
13.1 PEK. PIPA PVC D 3/4" M' 0 - -
13.2 PEK. PIPA PVC D 3" M' 0 - -
13.3 PEK. PIPA PVC D 4" M' 0 - -
-
14 PEK. LISTRIK -
14.1 PEK. TITIK LAMPU BOLAM TTK 19 250,000 4,750,000
14.2 PEK. STOP KONTAK TTK 10 250,000 2,500,000
14.3 PEK. DAYA LISTRIK 1300 WATT Unit 0 - -
-
15 PEK. PENGECATAN -
15.1 PEK. CAT DINDING M2 195 25,000 4,875,000
15.2 PEK. CAT PLAFOND M2 240 17,000 4,080,000
15.3 PEK. CAT LISTPLANK M2 20 15,000 300,000
-
16 PEK. SARANA LAIN -
16.1 PEK. SEPTIC TANK Unit 0 - -
16.2 PEK. SUMUR RESAPAN Unit 0 - -
16.3 PEK. BAK PENAMPUNG AIR Unit 0 - -
16.4 PEK. POMPA BIASA Unit 0 - -
16.5 PEK. SUMUR AIR BERSIH Unit 0 - -
16.6 PEK. PERANCAH Unit 0 - -

JUMLAH TOTAL RENCANA ANGGARAN BIAYA 96,455,500