Anda di halaman 1dari 6

REKAPITULASI RENCANA ANGGARAN BIAYA

NAMA PROJECT : OVERLAY ASPAL & SALURAN AIR


LOKASI : TAPOS, DEPOK (PT PANASONIC COMPONENT INDONESIA)
PEMILIK :
PERIODE : AGUSTUS 2023

HARGA TOTAL
NO. URAIAN PEKERJAAN
RP
1 2 3

A PEKERJAAN PERSIAPAN Rp 25,140,000.00


B PEKERJAAN GALIAN DAN URUGAN Rp 18,575,592.28
C PEKERJAAN SALURAN PIPA TANAM Rp 85,491,589.53
D PEKERJAAN OVERLAY ASPAL Rp 330,660,135.00
E PEKERJAAN PERAPIHAN Rp 10,668,159.00
F PEKERJAAN LAIN - LAIN Rp 20,112,000.00

TOTAL RENCANA ANGGARAN BIAYA Rp 490,647,475.81


DIBULATKAN Rp 490,640,000.00
TERBILANG :

Note :
- Harga diatas belum termasuk PPN 11%

Tangerang, 6 September 2023


RENCANA ANGGARAN BIAYA (RAB)

NAMA PROJECT : OVERLAY ASPAL & SALURAN AIR


LOKASI : TAPOS, DEPOK (PT PANASONIC COMPONENT INDONESIA)
PEMILIK :
PERIODE : AGUSTUS 2023

HARGA SATUAN KOEFISIEN HARGA


NO. Uraian Pekerjaan SATUAN VOLUME TOTAL HARGA (RP) Keterangan
(RP) A
1 2 3 4 5 6

A PEKERJAAN PERSIAPAN
1 Alat Bantu Kerja LS 1 Rp18,855,000 Rp18,855,000
2 Sewa Kontrakan LS 1 Rp6,285,000 Rp6,285,000

TOTAL BIAYA PEKERJAAN PERSIAPAN Rp25,140,000

B PEKERJAAN GALIAN DAN URUGAN

1 Pekerjaan Galian Jalur 1 M3 16.4206 Rp222,489 Rp3,653,403


- Segmen 1
- Segmen 2
- Segmen 3
- Segmen 4
- Segmen 5
- Bak Kontrol Sudah termasuk sampai lantai kerja

2 Pekerjaan Galian Jalur 2 M3 16.4206 Rp222,489 Rp3,653,403


- Segmen 1
- Segmen 2
- Segmen 3
- Segmen 4
- Segmen 5
- Bak Kontrol Sudah termasuk sampai lantai kerja

3 Pekerjaan Galian Jalur 3 M3 16.4206 Rp222,489 Rp3,653,403


- Segmen 1
- Segmen 2
- Segmen 3
- Segmen 4
- Segmen 5
- Bak Kontrol Sudah termasuk sampai lantai kerja

4 Pekerjaan Urugan Tanah Kembali M3 40.935 Rp186,036 Rp7,615,384


- Jalur 1
- Jalur 2
- Jalur 3

TOTAL BIAYA PEKERJAAN GALIAN DAN URUGAN Rp18,575,592


C PEKERJAAN SALURAN PIPA TANAM
C.1 LANTAI KERJA
- Bak Kontrol M3 0.16 Rp4,437,210 Rp718,828
- Pek. Waterproofing Lantai setara aquaproof M2 1.44 Rp370,815 Rp533,974
Rp1,252,802
C.2 BAK KONTROL 60x60x80
- Pek. Pas Dinding Hebel 10 cm M2 13.82 Rp237,573 Rp3,284,209 ###
- Pek. Pas. Plesteran Dinding M2 13.82 Rp186,036 Rp2,571,762
- Pek. Pas Acian Dinding M2 13.82 Rp119,415 Rp1,650,793
- Pek. Waterproofing Dinding setara aquaproof M2 13.82 Rp370,815 Rp5,126,147
- Beton Sitemix (Tutup Bak Kontrol) M3 0.32 Rp4,437,210 Rp1,437,656
- Tulangan P12 (Pegangan Bak Kontrol) KG 6.36 Rp74,163 Rp471,561
- Tulangan P12 (Tutup Bak Kontrol) KG 53.80 Rp74,163 Rp3,990,128
- Pipa PVC 3/4 Inch M' 3.60 Rp148,326 Rp533,974
- Bekisting Kayu M2 5.40 Rp1,479,489 Rp7,989,241
Rp27,055,470
C.3 PIPA BESI 4 INCH
- Pipa Besi 4" T=1,6 mm M' 81.79 Rp628,500 Rp51,407,403
- Sambungan T (Drat) BH 3.00 Rp814,536 Rp2,443,608
- Elbow (Drat) BH 1.00 Rp370,815 Rp370,815
- Floordrain / Floordeck +- 5 inch custom besi BH 4.00 Rp740,373 Rp2,961,492
Rp57,183,318

TOTAL BIAYA PEKERJAAN SALURAN PIPA TANAM Rp85,491,590


###
D PEKERJAAN OVERLAY ASPAL ###
1 Overlay Aspal AW +- 4cm M2 1349.00 Rp245,115 Rp330,660,135

TOTAL BIAYA PEKERJAAN OVERLAY ASPAL Rp330,660,135

E PEKERJAAN PERAPIHAN ###


1 Pek. Perbaikan Kansten TTK 3.00 Rp740,373 Rp2,221,119
2 Pek. Perbaikan Taman dan Curb sekitar Drainase TTK 3.00 Rp1,109,931 Rp3,329,793
3 Pek. Marking Garis Parkir (Putih) M2 34.50 Rp148,326 Rp5,117,247
- Cat setara Nippon Paint

TOTAL BIAYA PEKERJAAN PERAPIHAN Rp10,668,159

F PEKERJAAN LAIN - LAIN


1 Design LS 1 Rp0 Rp0
2 Estimasi LS 1 Rp1,257,000 Rp1,257,000
3 Aspek K3 LS 1 Rp18,855,000 Rp18,855,000

TOTAL BIAYA PEKERJAAN LAIN - LAIN Rp20,112,000


REKAPITULASI RENCANA ANGGARAN BIAYA

NAMA PROJECT : OVERLAY ASPAL & SALURAN AIR


LOKASI : TAPOS, DEPOK (PT PANASONIC COMPONENT INDONESIA)
PEMILIK :
PERIODE : AGUSTUS 2023

HARGA TOTAL
NO. URAIAN PEKERJAAN
RP
1 2 3

A PEKERJAAN PERSIAPAN Rp 16,969,500.00


B PEKERJAAN GALIAN DAN URUGAN Rp 18,575,592.28
C PEKERJAAN SALURAN PIPA TANAM Rp 85,491,589.53
D PEKERJAAN OVERLAY ASPAL Rp 163,001,475.00
E PEKERJAAN PERAPIHAN Rp 7,030,184.80
F PEKERJAAN LAIN - LAIN Rp 20,112,000.00

TOTAL RENCANA ANGGARAN BIAYA Rp 311,180,341.61


DIBULATKAN Rp 311,180,000.00
TERBILANG :

Note :
- Harga diatas belum termasuk PPN 11%

Tangerang, 6 September 2023


RENCANA ANGGARAN BIAYA (RAB)

NAMA PROJECT : OVERLAY ASPAL & SALURAN AIR


LOKASI : TAPOS, DEPOK (PT PANASONIC COMPONENT INDONESIA)
PEMILIK :
PERIODE : AGUSTUS 2023

KOEFISIEN HARGA
NO. Uraian Pekerjaan SATUAN VOLUME HARGA SATUAN (RP) TOTAL HARGA (RP) Keterangan
A
1 2 3 4 5 6

A PEKERJAAN PERSIAPAN
1 Alat Bantu Kerja 1 LS 1 Rp12,570,000 Rp12,570,000
2 Sewa Kontrakan 1 LS 1 Rp4,399,500 Rp4,399,500

TOTAL BIAYA PEKERJAAN PERSIAPAN Rp16,969,500

B PEKERJAAN GALIAN DAN URUGAN

1 Pekerjaan Galian Jalur 1 M3 16.4206 Rp222,489 Rp3,653,403


- Segmen 1 3.07 1 0.3 0.921
- Segmen 2 6 1 0.45 2.7
- Segmen 3 7 1 0.52 3.64
- Segmen 4 6 1 0.62 3.72
- Segmen 5 3.7 1 0.72 2.664
- Bak Kontrol 0.6 0.6 0.81 0.2916 Sudah termasuk sampai lantai kerja

2 Pekerjaan Galian Jalur 2 M3 16.4206 Rp222,489 Rp3,653,403


- Segmen 1 3.07 1 0.3 0.921
- Segmen 2 6 1 0.45 2.7
- Segmen 3 7 1 0.52 3.64
- Segmen 4 6 1 0.62 3.72
- Segmen 5 3.7 1 0.72 2.664
- Bak Kontrol 0.6 0.6 0.81 0.2916 Sudah termasuk sampai lantai kerja

3 Pekerjaan Galian Jalur 3 M3 16.4206 Rp222,489 Rp3,653,403


- Segmen 1 3.07 1 0.3 0.921
- Segmen 2 6 1 0.45 2.7
- Segmen 3 7 1 0.52 3.64
- Segmen 4 6 1 0.62 3.72
- Segmen 5 3.7 1 0.72 2.664
- Bak Kontrol 0.6 0.6 0.81 0.2916 Sudah termasuk sampai lantai kerja

4 Pekerjaan Urugan Tanah Kembali M3 40.935 Rp186,036 Rp7,615,384


- Jalur 1 13.645
- Jalur 2 13.645
- Jalur 3 13.645

TOTAL BIAYA PEKERJAAN GALIAN DAN URUGAN Rp18,575,592


C PEKERJAAN SALURAN PIPA TANAM
C.1 LANTAI KERJA
- Bak Kontrol 9 0.6 0.6 0.05 0.162 M3 0.16 Rp4,437,210 Rp718,828
- Pek. Waterproofing Lantai setara aquaproof 9 0.4 0.4 1.44 M2 1.44 Rp370,815 Rp533,974
Rp1,252,802
C.2 BAK KONTROL 60x60x80
- Pek. Pas Dinding Hebel 10 cm 9 1.6 1.2 0.8 13.824 M2 13.82 Rp237,573 Rp3,284,209 ###
- Pek. Pas. Plesteran Dinding 13.824 M2 13.82 Rp186,036 Rp2,571,762
- Pek. Pas Acian Dinding 13.824 M2 13.82 Rp119,415 Rp1,650,793
- Pek. Waterproofing Dinding setara aquaproof 13.824 M2 13.82 Rp370,815 Rp5,126,147
- Beton Sitemix (Tutup Bak Kontrol) 9 0.1 0.6 0.6 0.324 M3 0.32 Rp4,437,210 Rp1,437,656
- Tulangan P12 (Pegangan Bak Kontrol) 9 0.78 1 0.888 6.3584 KG 6.36 Rp74,163 Rp471,561
- Tulangan P12 (Tutup Bak Kontrol) 9 0.55 12 0.888 53.802 KG 53.80 Rp74,163 Rp3,990,128
- Pipa PVC 3/4 Inch 9 0.1 4 3.6 M' 3.60 Rp148,326 Rp533,974
- Bekisting Kayu 9 0.24 0.36 5.4 M2 5.40 Rp1,479,489 Rp7,989,241
Rp27,055,470
C.3 PIPA BESI 4 INCH
- Pipa Besi 4" T=1,6 mm 26.73 3 81.794 M' 81.79 Rp628,500 Rp51,407,403
- Sambungan T (Drat) 3 3 BH 3.00 Rp814,536 Rp2,443,608
- Elbow (Drat) 1 1 BH 1.00 Rp370,815 Rp370,815
- Floordrain / Floordeck +- 5 inch custom besi 4 4 BH 4.00 Rp740,373 Rp2,961,492
Rp57,183,318

TOTAL BIAYA PEKERJAAN SALURAN PIPA TANAM Rp85,491,590


###
D PEKERJAAN OVERLAY ASPAL ###
1 Overlay Aspal AW +- 4cm 665 M2 665.00 Rp245,115 Rp163,001,475

TOTAL BIAYA PEKERJAAN OVERLAY ASPAL Rp163,001,475

E PEKERJAAN PERAPIHAN ###


1 Pek. Perbaikan Kansten 3 3 TTK 3.00 Rp740,373 Rp2,221,119
2 Pek. Perbaikan Taman dan Curb sekitar Drainase 3 3 TTK 3.00 Rp1,109,931 Rp3,329,793
3 Pek. Marking Garis Parkir (Putih) 5 0.1 33 8.25 M2 8.25 Rp148,326 Rp1,223,690
- Cat setara Nippon Paint
4 Pek. Semen (Area bak kontrol bagian depan)
- Beton sitemix 0.1 0.04 0.6 24 0.0576 M3 0.06 Rp4,437,210 Rp255,583

TOTAL BIAYA PEKERJAAN PERAPIHAN Rp7,030,185

F PEKERJAAN LAIN - LAIN


1 Design 1 LS 1 Rp0 Rp0
2 Estimasi 1 LS 1 Rp1,257,000 Rp1,257,000
3 Aspek K3 1 LS 1 Rp10,056,000 Rp10,056,000

TOTAL BIAYA PEKERJAAN LAIN - LAIN Rp11,313,000