Anda di halaman 1dari 6

REKAPITULASI RENCANA ANGGARAN BIAYA

NAMA PROJECT : OVERLAY ASPAL & SALURAN AIR


LOKASI : TAPOS, DEPOK (PT PANASONIC COMPONENT INDONESIA)
PEMILIK :
PERIODE : SEPTEMBER 2023

HARGA TOTAL
NO. URAIAN PEKERJAAN
RP
1 2 3

A PEKERJAAN PERSIAPAN Rp 30,264,000.00


B PEKERJAAN GALIAN DAN URUGAN Rp 22,361,643.79
C PEKERJAAN SALURAN PIPA TANAM Rp 178,744,932.24
D PEKERJAAN OVERLAY ASPAL Rp 398,054,826.00
E PEKERJAAN PERAPIHAN Rp 12,842,528.40
F PEKERJAAN LAIN - LAIN Rp 24,211,200.00

TOTAL RENCANA ANGGARAN BIAYA Rp 666,479,130.42


DIBULATKAN Rp 666,470,000.00
TERBILANG : ENAM RATUS ENAM PULUH ENAM JUTA EMPAT RATUS TUJUH PULUH RIBU RUPIAH

Note :
- Harga diatas belum termasuk PPN 11%

Tangerang, 27 September 2023

Ruly Fakhri Rusmadi


Civil Engineering
RENCANA ANGGARAN BIAYA (RAB)

NAMA PROJECT : OVERLAY ASPAL & SALURAN AIR


LOKASI : TAPOS, DEPOK (PT PANASONIC COMPONENT INDONESIA)
PEMILIK :
PERIODE : SEPTEMBER 2023

HARGA SATUAN KOEFISIEN HARGA


NO. Uraian Pekerjaan SATUAN VOLUME TOTAL HARGA (RP) Keterangan
(RP) A
1 2 3 4 5 6

A PEKERJAAN PERSIAPAN
1 Alat Bantu Kerja LS 1 Rp22,698,000 Rp22,698,000
2 Sewa Kontrakan LS 1 Rp7,566,000 Rp7,566,000

TOTAL BIAYA PEKERJAAN PERSIAPAN Rp30,264,000

B PEKERJAAN GALIAN DAN URUGAN

1 Pekerjaan Galian Jalur 1 M3 16.4206 Rp267,836 Rp4,398,034


- Segmen 1
- Segmen 2
- Segmen 3
- Segmen 4
- Segmen 5
- Bak Kontrol Sudah termasuk sampai lantai kerja

2 Pekerjaan Galian Jalur 2 M3 16.4206 Rp267,836 Rp4,398,034


- Segmen 1
- Segmen 2
- Segmen 3
- Segmen 4
- Segmen 5
- Bak Kontrol Sudah termasuk sampai lantai kerja

3 Pekerjaan Galian Jalur 3 M3 16.4206 Rp267,836 Rp4,398,034


- Segmen 1
- Segmen 2
- Segmen 3
- Segmen 4
- Segmen 5
- Bak Kontrol Sudah termasuk sampai lantai kerja

4 Pekerjaan Urugan Tanah Kembali M3 40.935 Rp223,954 Rp9,167,541


- Jalur 1
- Jalur 2
- Jalur 3

TOTAL BIAYA PEKERJAAN GALIAN DAN URUGAN Rp22,361,644


C PEKERJAAN SALURAN PIPA TANAM
C.1 LANTAI KERJA
- Bak Kontrol M3 0.22 Rp5,341,596 Rp1,153,785
- Pek. Waterproofing Lantai setara aquaproof M2 1.92 Rp446,394 Rp857,076
Rp2,010,861
C.2 BAK KONTROL 60x60x80
- Pek. Pas Dinding Hebel 10 cm M2 18.43 Rp285,995 Rp5,271,456 ###
- Pek. Pas. Plesteran Dinding M2 18.43 Rp223,954 Rp4,127,913
- Pek. Pas Acian Dinding M2 18.43 Rp143,754 Rp2,649,674
- Pek. Waterproofing Dinding setara aquaproof M2 18.43 Rp446,394 Rp8,227,934
- Beton Sitemix (Tutup Bak Kontrol) M3 0.43 Rp5,341,596 Rp2,307,569
- Tulangan P12 (Pegangan Bak Kontrol) KG 8.48 Rp89,279 Rp756,898
- Tulangan P12 (Tutup Bak Kontrol) KG 71.74 Rp89,279 Rp6,404,521
- Pipa PVC 3/4 Inch M' 4.80 Rp178,558 Rp857,076
- Bekisting Kayu M2 7.20 Rp1,781,036 Rp12,823,462
Rp43,426,504
C.3 PIPA AW 8 INCH
- Pipa AW 8" (Jis) setara Rucika M' 81.79 Rp1,229,475 Rp100,563,432
- Sambungan T BH 3.00 Rp1,475,370 Rp4,426,110
- Elbow BH 1.00 Rp1,080,425 Rp1,080,425
- Floordrain Grating Besi 500x500x40 BH 12.00 Rp2,269,800 Rp27,237,600
Rp133,307,567

TOTAL BIAYA PEKERJAAN SALURAN PIPA TANAM Rp178,744,932


###
D PEKERJAAN OVERLAY ASPAL ###
1 Overlay Aspal AW +- 4cm M2 1349.00 Rp295,074 Rp398,054,826

TOTAL BIAYA PEKERJAAN OVERLAY ASPAL Rp398,054,826

E PEKERJAAN PERAPIHAN ###


1 Pek. Perbaikan Kansten TTK 3.00 Rp891,275 Rp2,673,824
2 Pek. Perbaikan Taman dan Curb sekitar Drainase TTK 3.00 Rp1,336,156 Rp4,008,467
3 Pek. Marking Garis Parkir (Putih) M2 34.50 Rp178,558 Rp6,160,237
- Cat setara Nippon Paint

TOTAL BIAYA PEKERJAAN PERAPIHAN Rp12,842,528

F PEKERJAAN LAIN - LAIN


1 Estimasi LS 1 Rp1,513,200 Rp1,513,200
2 Aspek K3 LS 1 Rp22,698,000 Rp22,698,000

TOTAL BIAYA PEKERJAAN LAIN - LAIN Rp24,211,200


REKAPITULASI RENCANA ANGGARAN BIAYA

NAMA PROJECT : OVERLAY ASPAL & SALURAN AIR


LOKASI : TAPOS, DEPOK (PT PANASONIC COMPONENT INDONESIA)
PEMILIK :
PERIODE : SEPTEMBER 2023

HARGA TOTAL
NO. URAIAN PEKERJAAN
RP
1 2 3

A PEKERJAAN PERSIAPAN Rp 20,428,200.00


B PEKERJAAN GALIAN DAN URUGAN Rp 22,361,643.79
C PEKERJAAN SALURAN PIPA TANAM Rp 178,744,932.24
D PEKERJAAN OVERLAY ASPAL Rp 196,224,210.00
E PEKERJAAN PERAPIHAN Rp 8,451,233.64
F PEKERJAAN LAIN - LAIN Rp 13,618,800.00

TOTAL RENCANA ANGGARAN BIAYA Rp 439,829,019.66


DIBULATKAN Rp 439,820,000.00
TERBILANG : EMPAT RATUS TIGA PULUH SEMBILAN JUTA DELAPAN RATUS DUA PULUH RIBU RUPIAH

Note :
- Harga diatas belum termasuk PPN 11%

Tangerang, 27 September 2023

Ruly Fakhri Rusmadi


Civil Engineering
RENCANA ANGGARAN BIAYA (RAB)

NAMA PROJECT : OVERLAY ASPAL & SALURAN AIR


LOKASI : TAPOS, DEPOK (PT PANASONIC COMPONENT INDONESIA)
PEMILIK :
PERIODE : SEPTEMBER 2023

KOEFISIEN HARGA
NO. Uraian Pekerjaan SATUAN VOLUME HARGA SATUAN (RP) TOTAL HARGA (RP) Keterangan
A
1 2 3 4 5 6

A PEKERJAAN PERSIAPAN
1 Alat Bantu Kerja LS 1 Rp15,132,000 Rp15,132,000
2 Sewa Kontrakan LS 1 Rp5,296,200 Rp5,296,200

TOTAL BIAYA PEKERJAAN PERSIAPAN Rp20,428,200

B PEKERJAAN GALIAN DAN URUGAN

1 Pekerjaan Galian Jalur 1 M3 16.4206 Rp267,836 Rp4,398,034


- Segmen 1
- Segmen 2
- Segmen 3
- Segmen 4
- Segmen 5
- Bak Kontrol Sudah termasuk sampai lantai kerja

2 Pekerjaan Galian Jalur 2 M3 16.4206 Rp267,836 Rp4,398,034


- Segmen 1
- Segmen 2
- Segmen 3
- Segmen 4
- Segmen 5
- Bak Kontrol Sudah termasuk sampai lantai kerja

3 Pekerjaan Galian Jalur 3 M3 16.4206 Rp267,836 Rp4,398,034


- Segmen 1
- Segmen 2
- Segmen 3
- Segmen 4
- Segmen 5
- Bak Kontrol Sudah termasuk sampai lantai kerja

4 Pekerjaan Urugan Tanah Kembali M3 40.935 Rp223,954 Rp9,167,541


- Jalur 1
- Jalur 2
- Jalur 3

TOTAL BIAYA PEKERJAAN GALIAN DAN URUGAN Rp22,361,644


C PEKERJAAN SALURAN PIPA TANAM
C.1 LANTAI KERJA
- Bak Kontrol M3 0.22 Rp5,341,596 Rp1,153,785
- Pek. Waterproofing Lantai setara aquaproof M2 1.92 Rp446,394 Rp857,076
Rp2,010,861
C.2 BAK KONTROL 60x60x80
- Pek. Pas Dinding Hebel 10 cm M2 18.43 Rp285,995 Rp5,271,456 ###
- Pek. Pas. Plesteran Dinding M2 18.43 Rp223,954 Rp4,127,913
- Pek. Pas Acian Dinding M2 18.43 Rp143,754 Rp2,649,674
- Pek. Waterproofing Dinding setara aquaproof M2 18.43 Rp446,394 Rp8,227,934
- Beton Sitemix (Tutup Bak Kontrol) M3 0.43 Rp5,341,596 Rp2,307,569
- Tulangan P12 (Pegangan Bak Kontrol) KG 8.48 Rp89,279 Rp756,898
- Tulangan P12 (Tutup Bak Kontrol) KG 71.74 Rp89,279 Rp6,404,521
- Pipa PVC 3/4 Inch M' 4.80 Rp178,558 Rp857,076
- Bekisting Kayu M2 7.20 Rp1,781,036 Rp12,823,462
Rp43,426,504
C.3 PIPA AW 8 INCH
- Pipa AW 8" (Jis) setara Rucika M' 81.79 Rp1,229,475 Rp100,563,432
- Sambungan T BH 3.00 Rp1,475,370 Rp4,426,110
- Elbow BH 1.00 Rp1,080,425 Rp1,080,425
- Floordrain Grating Besi 500x500x40 BH 12.00 Rp2,269,800 Rp27,237,600
Rp133,307,567

TOTAL BIAYA PEKERJAAN SALURAN PIPA TANAM Rp178,744,932


###
D PEKERJAAN OVERLAY ASPAL ###
1 Overlay Aspal AW +- 4cm M2 665.00 Rp295,074 Rp196,224,210

TOTAL BIAYA PEKERJAAN OVERLAY ASPAL Rp196,224,210

E PEKERJAAN PERAPIHAN ###


1 Pek. Perbaikan Kansten TTK 3.00 Rp891,275 Rp2,673,824
2 Pek. Perbaikan Taman dan Curb sekitar Drainase TTK 3.00 Rp1,336,156 Rp4,008,467
3 Pek. Marking Garis Parkir (Putih) M2 8.25 Rp178,558 Rp1,473,100
- Cat setara Nippon Paint
4 Pek. Semen (Area bak kontrol bagian depan)
- Beton sitemix M3 0.06 Rp5,136,150 Rp295,842

TOTAL BIAYA PEKERJAAN PERAPIHAN Rp8,451,234

F PEKERJAAN LAIN - LAIN


1 Estimasi LS 1 Rp1,513,200 Rp1,513,200
2 Aspek K3 LS 1 Rp12,105,600 Rp12,105,600

TOTAL BIAYA PEKERJAAN LAIN - LAIN Rp13,618,800