JUMLAH
NO. JENIS PEKERJAAN HARGA
( Rp. )
I. PEKERJAAN UTAMA
A. PEKERJAAN PENDAHULUAN Rp 4,092,480.00
B. PEKRJAAN TANAH Rp 3,232,852.00
C. PEKERJAAN PONDASI Rp 13,696,456.40
D. PEKERJAAN BETON Rp 44,195,212.87
E. PEKERJAAN KERAMIK Rp 10,821,264.00
F. PEKERJAAN PASANGAN Rp 21,969,622.88
G. PEK. KUSEN, PINTU, JENDELA DAN PENGGANTUNG Rp 16,392,830.75
H. PEKERJAAN PLAFOND Rp 5,340,842.05
I. PEKERJAAN ATAP Rp 25,680,328.00
J. PEKERJAAN CAT-CATAN Rp 7,887,496.08
K. PEKERJAAN SANITAIR Rp 8,652,116.69
L. PEKERJAAN LISTRIK Rp 4,837,895.00
M. PEKERJAAN MEUBELAIR DAN KELENGKAPANNYA Rp 22,000,000.00
JUMLAH Rp 202,874,396.71
PPN 10% Rp 20,287,439.67
TOTAL JUMLAH 1 UNIT Rp 223,161,836.38
TOTAL JUMLAH 15 UNIT Rp 3,347,427,545.73
DIBULATKAN Rp 3,347,400,000.00
TERBILANG : Tiga Milyar Tiga Ratus Empat Puluh Tujuh Juta Empat Ratus Ribu Rupiah
----------------------------------
Direktur
SATKER : UNIT PENYELENGGARAAN BANDAR UDARA APT PRANOTO
KEGIATAN : PEMBANGUNAN, REHABILITASI DAN PEMELIHARAAN PRASARANA UDARA
PEKERJAAN : PEMBANGUNAN RUMAH DINAS OPERASIONAL TIPE 36 : 15 UNIT BERSERTA MEUBELAIR DAN KELENGKAPANNYA
VOLUME : 15
SATUAN UKUR : UNIT
A PEKERJAAN PENDAHULUAN
1 1 M² MEMBERSIHKAN LAPANGAN DAN PERATAAN A.1 Rp 20,000.00
2 1 M PENGUKURAN DAN PEMASANGAN BOUWPLANK A.2 Rp 73,680.00
B PEKERJAAN TANAH
1 1 M³ GALIAN TANAH BIASA SEDALAM 1 METER B.1 Rp 48,000.00
2 1 M³ URUGAN KEMBALI B.2 Rp 23,000.00
3 1 M³ URUGAN TANAH BAWAH LANTAI DENGAN PEMADATAN B.3 Rp 123,600.00
4 1 M³ URUGAN PASIR B.4 Rp 159,200.00
C PEKERJAAN PONDASI
1 1 TITIK TONGKAT ULIN UK. 10/10 CM - 200CM C.1 Rp 145,460.00
2 1 M³ PASANGAN BATU KOSONG/AANSTAMPING C.2 Rp 415,320.00
3 1 M³ PASANGAN BATU GUNUNG 1PC : 4PS C.3 Rp 748,970.00
4 1 M² PASANGAN ROLLAG BATA CAMP. 1PC : 4PS C.4 Rp 236,300.50
D PEKERJAAN BETON
1 1 M³ MEMBUAT LANTAI KERJA 1 : 3 : 5 D.1 Rp 185,660.00
2 1 M³ MEMBUAT COR RABAT 1 : 3 : 5 D.2 Rp 927,190.00
3 1 M³ BETON CAMPURAN 1 : 2 : 3 D.3 Rp 1,232,431.00
4 10 KG PEMBESIAN DENGAN BESI POLOS D.4 Rp 209,560.00
4.1 1 KG PEMBESIAN DENGAN BESI POLOS 1.4.1
5 1 M² PASANG BEKISTING UNTUK POER PLAT D.5 Rp 155,230.00
6 1 M² PASANG BEKISTING UNTUK SLOOF D.6 Rp 163,832.50
7 1 M² PASANG BEKISTING UNTUK KOLOM D.7 Rp 223,290.00
8 1 M² PASANG BEKISTING UNTUK RINGBALK D.8 Rp 277,190.00
9 1 M² PASANG BEKISTING UNTUK PLATE D.9 Rp 322,390.00
10 1 M³ BETON BERTULANG PEKERJAAN POER PLATE 70X80X20 D.10 Rp 6,042,955.71
11 1 M³ BETON BERTULANG PEKERJAAN SLOOF 15X20 D.11 Rp 7,281,514.16
12 1 M³ BETON BERTULANG PEKERJAAN KOLOM 15X20 D.12 Rp 6,623,446.14
13 1 M³ BETON BERTULANG PEKERJAAN KOLOM 13X13 D.13 Rp 10,786,478.87
14 1 M³ BETON BERTULANG PEKERJAAN RINGBALK 13x20 D.14 Rp 11,235,938.55
15 1 M³ BETON BERTULANG PEKERJAAN BALOK LATAI 13x20 D.15 Rp 11,235,938.55
16 1 M³ BETON BERTULANG PEKERJAAN PLATE DAK TEBAL 12 CM D.16 Rp 9,012,463.96
17 1 M³ BETON BERTULANG PEKERJAAN CANOPY TEBAL 10 CM D.17 Rp 8,167,995.63
E PEKERJAAN KERAMIK
1 1 M² PASANGAN KERAMIK DINDING 20X25 E.1 Rp 261,063.00
2 1 M² PASANGAN KERAMIK LANTAI 20X20 E.2 Rp 191,364.00
3 1 M² PASANGAN KERAMIK LANTAI 40X40 E.3 Rp 155,460.00
F PEKERJAAN PASANGAN
1 1 M² PASANGAN DINDING 1/2 BATA 1PC : 2PS F.1 Rp 124,410.50
2 1 M² PASANGAN DINDING 1/2 BATA 1PC : 4PS F.2 Rp 114,883.00
3 1 M² PLESTERAN DINDING BATA 1PC : 2PS F.3 Rp 79,465.20
4 1 M² PLESTERAN DINDING BATA 1PC : 4PS F.4 Rp 72,824.00
5 1 M² PASANG BATU ALAM F.5 Rp 375,503.00
G PEKERJAAN KUSEN
1 1 M³ MENGERJAKAN KUSEN PINTU DAN JENDELA G.1 Rp 7,700,000.00
2 1 M² PASANG PINTU PANEL KAYU BENGKIRAI G.2 Rp 616,000.00
3 1 M² PASANG DAUN JENDELA KACA G.3 Rp 503,000.00
4 1 M² PASANG KACA BENING TEBAL 5MM G.4 Rp 139,350.00
5 1 BH PASANG ENGSEL PINTU G.5 Rp 68,850.00
6 1 BH PASANG ENGSEL JENDELA G.6 Rp 45,900.00
7 1 BH PASANG HANDEL PINTU (PULL HANDLE) G.7 Rp 188,850.00
8 1 BH PASANG HANDEL PINTU (LEVER HANDLE) G.8 Rp 370,850.00
9 1 BH PASANG HANDEL PINTU KUNCI BULAT (KNOB HANDLE) G.9 Rp 213,800.00
10 1 BH PASANG HANDEL JENDELA G.10 Rp 51,850.00
11 1 BH PASANG KUNCI TANAM G.11 Rp 313,800.00
12 1 BH GRENDEL JENDELA G.12 Rp 48,850.00
13 1 BH PASANG HAK ANGIN G.13 Rp 57,850.00
14 1 UNIT PINTU TYPE 1 (P1) G.14 Rp 2,224,255.00
15 1 UNIT PINTU TYPE 2 (P2) G.15 Rp 1,658,480.00
16 1 UNIT PINTU TYPE 3 (P3) G.16 Rp 1,376,305.00
17 1 UNIT PINTU JENDELA TYPE 1 (PJ1) G.17 Rp 2,910,515.50
18 1 UNIT JENDELA TYPE 1 (J1) G.18 Rp 737,935.00
19 1 UNIT JENDELA TYPE 2 (J2) G.19 Rp 1,687,596.00
20 1 UNIT JENDELA TYPE 3 (J3) G.20 Rp 881,335.50
21 1 UNIT BOUVENLIGHT TYPE 1 (BV1) G.21 Rp 248,333.75
22 1 UNIT BOUVENLIGHT TYPE 2 (BV2) G.22 Rp 92,052.50
23 1 UNIT BOUVENLIGHT TYPE 3 (BV3) G.23 Rp 131,895.00
H PEKERJAAN PLAFOND
1 1 M² PENGGANTUNG DAN RANGKA PLAFOND H.1 Rp 114,220.00
2 1 M² PLAFOND GYPSUM 9 MM H.2 Rp 44,125.00
3 1 M² PLAFOND CALSIBOARD 4.5MM H.3 Rp 51,625.00
4 1 M² LIST PLAFOND GYPSUM H.4 Rp 46,230.00
5 1 M' LIST PLAFOND KAYU PROFIL H.5 Rp 63,540.00
No. URAIAN KODE JUMLAH HARGA
I PEKERJAAN ATAP
1 1 M² PASANG RANGKA ATAP BAJA RINGAN I.1 Rp 202,344.00
2 1 M² PASANG ATAP GENTENG METAL KELAS MENENGAH I.2 Rp 128,480.00
3 1 M PASANG BUBUNGAN GENTENG METAL I.3 Rp 137,100.00
4 1 M PASANG PAPAN LISTPLANK I.4 Rp 64,900.00
J PEKERJAAN PENGECATAN
1 1 M² PENGECATAN TEMBOK BAGIAN LUAR J.1 Rp 37,624.00
2 1 M² PENGECATAN TEMBOK BAGIAN DALAM DAN PLAFOND J.2 Rp 30,864.00
3 1 M² PENGECATAN BIDANG KAYU BARU J.3 Rp 55,780.00
K PEKEERJAAN SANITAIR
1 MEMASANG 1 M' PIPA PVC TYPE AW Ø 4" K.1 Rp 76,795.00
2 MEMASANG 1 M' PIPA PVC TYPE AW Ø 2" K.2 Rp 33,210.00
3 MEMASANG 1 M' PIPA PVC TYPE AW Ø 3/4" K.3 Rp 18,265.00
4 MEMASANG 1 M' PIPA PVC TYPE AW Ø ½" K.4 Rp 17,644.38
5 MEMASANG 1 BUAH CLOSET DUDUK / MONOBLOK K.5 Rp 2,042,198.00
6 MEMASANG 1 BUAH KRAN Ø ½" K.6 Rp 162,550.00
7 MEMASANG 1 BUAH FLOOR DRAIN K.7 Rp 108,800.00
8 MEMASANG 1 BUAH ROOF DRAIN K.8 Rp 106,800.00
9 MEMASANG 1 BUAH BAK MANDI K.9 Rp 381,042.21
10 1 M SALURAN AIR HUJAN K.10 Rp 94,379.98
11 1 BUAH BAK KONTROL K.11 Rp 134,838.88
L PEKERJAAN LISTRIK
1 1 TTK INSTALASI LAMPU L.1 Rp 268,980.00
2 1 TTK INSTALASI STOP KONTAK L.2 Rp 268,980.00
3 1 BH PASANGAN LAMPU SL 18 WATT L.3 Rp 41,655.00
4 1 BH PASANGAN LAMPU SL 8 WATT L.4 Rp 26,655.00
5 1 UNIT SKRING KASH LISTRIK 1 GROUP L.5 Rp 219,320.00
A PEKERJAAN PENDAHULUAN
B PEKERJAAN TANAH
2 1 M³ URUGAN KEMBALI
Upah
0.019 Oh Mandor Rp 200,000.00 Rp - Rp 3,800.00 Rp 3,800.00
0.192 Oh Pekerja Rp 100,000.00 Rp - Rp 19,200.00 Rp 19,200.00
TOTAL Rp - Rp 23,000.00 Rp 23,000.00
4 1 M³ URUGAN PASIR
Bahan
1.200 M³ Pasir urug Rp 106,000.00 Rp 127,200.00 Rp - Rp 127,200.00
Upah
0.010 Oh Mandor Rp 200,000.00 Rp - Rp 2,000.00 Rp 2,000.00
0.300 Oh Pekerja Rp 100,000.00 Rp - Rp 30,000.00 Rp 30,000.00
TOTAL Rp 127,200.00 Rp 32,000.00 Rp 159,200.00
C PEKERJAAN PONDASI
D PEKERJAAN BETON
3 1 M³ BETON CAMPURAN 1 : 2 : 3
Bahan
371.000 Kg Semen Rp 1,350.00 Rp 500,850.00 Rp - Rp 500,850.00
1.047 M³ Koral beton Rp 395,000.00 Rp 413,565.00 Rp - Rp 413,565.00
0.698 M³ Pasir beton (lokal) Rp 137,000.00 Rp 95,626.00 Rp - Rp 95,626.00
Upah
0.028 Oh Kepala tukang Rp 180,000.00 Rp - Rp 5,040.00 Rp 5,040.00
0.083 Oh Mandor Rp 200,000.00 Rp - Rp 16,600.00 Rp 16,600.00
1.650 Oh Pekerja Rp 100,000.00 Rp - Rp 165,000.00 Rp 165,000.00
0.275 Oh Tukang Rp 130,000.00 Rp - Rp 35,750.00 Rp 35,750.00
TOTAL Rp 1,010,041.00 Rp 222,390.00 Rp 1,232,431.00
E PEKERJAAN KERAMIK
F PEKERJAAN PASANGAN
G PEKERJAAN KUSEN
12 1 BH GRENDEL JENDELA
Bahan
1.000 Bh Grendel jendela Rp 25,000.00 Rp 25,000.00 Rp - Rp 25,000.00
Upah
0.015 Oh Kepala tukang Rp 180,000.00 Rp - Rp 2,700.00 Rp 2,700.00
0.001 Oh Mandor Rp 200,000.00 Rp - Rp 150.00 Rp 150.00
0.015 Oh Pekerja Rp 100,000.00 Rp - Rp 1,500.00 Rp 1,500.00
0.150 Oh Tukang Rp 130,000.00 Rp - Rp 19,500.00 Rp 19,500.00
TOTAL Rp 25,000.00 Rp 23,850.00 Rp 48,850.00
H PEKERJAAN PLAFOND
2 1 M² PLAFOND GYPSUM 9 MM
Bahan
0.030 Kg Baut sekrup Rp 30,000.00 Rp 900.00 Rp - Rp 900.00
0.375 Lbr Gypsum 9 mm Rp 55,000.00 Rp 20,625.00 Rp - Rp 20,625.00
Upah
0.010 Oh Kepala tukang Rp 180,000.00 Rp - Rp 1,800.00 Rp 1,800.00
0.004 Oh Mandor Rp 200,000.00 Rp - Rp 800.00 Rp 800.00
0.070 Oh Pekerja Rp 100,000.00 Rp - Rp 7,000.00 Rp 7,000.00
0.100 Oh Tukang Rp 130,000.00 Rp - Rp 13,000.00 Rp 13,000.00
TOTAL Rp 21,525.00 Rp 22,600.00 Rp 44,125.00
I PEKERJAAN ATAP
J PEKERJAAN PENGECATAN
K PEKEERJAAN SANITAIR
L PEKERJAAN LISTRIK
UPAH
1 2 3 4 5
1 Pekerja Oh Rp 100,000
2 Tukang Oh Rp 130,000
3 Kepala tukang Oh Rp 180,000
4 Mandor Oh Rp 200,000
BAHAN
1 2 3 4 5
1 Balok meranti M³ Rp 2,450,000
2 Balok ulin 10x10x400 M³ Rp 4,550,000
3 Batu alam M² Rp 290,000
4 Batu bata Bh Rp 900
5 Batu gunung M³ Rp 200,000
6 Baut sekrup Kg Rp 30,000
7 Besi holo 2x4 M Rp 9,000
8 Besi tulangan (polos) Kg Rp 18,000
9 Bubungan genteng metal Bh Rp 78,000
10 Calsiboard 4.5 mm Lbr Rp 75,000
11 Cat air bagian luar setara mowilex Kg Rp 90,000
12 Cat air bagian dalam setara mowilex Kg Rp 64,000
13 Cat dasar Kg Rp 53,000
14 Cat meni Kg Rp 32,000
15 Cat penutup Kg Rp 64,000
16 Dolken kayu galam Btg Rp 5,000
17 Engsel 3" Bh Rp 30,000
18 Engsel 5" Bh Rp 45,000
19 Fitting lampu Bh Rp 19,000
20 Floor drain Bh Rp 92,000
21 Genteng metal Lbr Rp 54,000
22 Grendel jendela Bh Rp 25,000
23 Gypsum 9 mm Lbr Rp 55,000
24 Hak angin Bh Rp 34,000
25 Handel jendela Bh Rp 28,000
26 Kabel NYM 2 x 2,5 mm² Roll Rp 610,000
27 Kaca bening tebal 5 mm M² Rp 105,000
28 Kawat bendrat Kg Rp 16,000
29 Kayu bengkirai M³ Rp 3,400,000
30 Keramik 20x20 M² Rp 124,000
31 Keramik 20x25 M² Rp 129,000
32 Keramik 40x40 M² Rp 90,000
33 Klam pipa Bh Rp 750
34 Kloset duduk Bh Rp 1,450,000
35 Koral beton M³ Rp 395,000
36 Kran air Bh Rp 145,000
37 Kunci Bulat (Knob Handle) Bh Rp 145,000
38 Kunci tanam 2 slagh Bh Rp 245,000
39 Lampu SL 18 watt Bh Rp 38,000
40 Lampu SL 8 watt Bh Rp 23,000
41 Las dop Bh Rp 5,000
NO URAIAN SATUAN HARGA KETERANGAN
1 2 3 4 5
42 Lem gypsum Kg Rp 17,000
43 Lever Handle Bh Rp 347,000
44 List gypsum M Rp 32,000
45 List kayu profil M Rp 48,000
46 MCB listrik Unit Rp 52,000
47 Minyak bekisting Ltr Rp 6,000
48 Paku biasa Kg Rp 14,000
49 Paku genteng metal Kg Rp 30,000
50 Panel skring listrik Unit Rp 145,000
51 Papan meranti M³ Rp 2,600,000
52 Pasir beton (lokal) M³ Rp 137,000
53 Pasir pasangan (lokal) M³ Rp 106,000
54 Pasir urug M³ Rp 106,000
55 Pipa listrik PVC Btg Rp 12,000
56 Pipa PVC AW Ø 1/2" M Rp 3,100
57 Pipa PVC AW Ø 2" M Rp 9,000
58 Pipa PVC AW Ø 3/4" M Rp 3,500
59 Pipa PVC AW Ø 4" M Rp 30,900
60 Plamir Kg Rp 23,000
61 Plywood 9 mm Lbr Rp 117,000
62 Pull handle Bh Rp 165,000
63 Rangka baja ringan AAA 40x30 Btg Rp 44,000
64 Rangka baja ringan C75 Btg Rp 73,000
65 Roof drain Bh Rp 90,000
66 Saklar Bh Rp 30,000
67 Seal tape Bh Rp 3,000
68 Semen Kg Rp 1,350 Rp 67,500
69 Semen warna Kg Rp 24,000
70 Stop kontak Bh Rp 30,000
71 T dos Bh Rp 8,000
72 Tanah urug M³ Rp 53,000
73 Wood flank M Rp 22,000
NO. URAIAN PEKERJAAN KETERANGAN PANJANG LEBAR
A. PEKERJAAN PENDAHULUAN
1 Pembersihan Lahan 12 6
2 Bouwplank 36 1
B. PEKRJAAN TANAH
1 Galian Tanah Biasa Dinding
x 21.5 0.9
y 24.1 0.9
Pagar
x 0 0.9
y 0 0.9
Poer 0.7 0.8
C. PEKERJAAN PONDASI
1 Pancang Ulin 10x10x200 28 1
2 Aanstamping 45.6 0.9
3 Pas. Batu Gunung 1pc : 4ps 45.6 0.55
4 Pas. Rollag 0 1
D. PEKERJAAN BETON
1 Lantai Kerja 0.7 0.7
F. PEKERJAAN PASANGAN
1 Pas. Dinding 1/2 Bata 1pc : 2ps 45.6 1
Pintu Type 1 (P1) -1 0.9
PintuType 2 (P2) -1 0.8
Pintu Type 3 (P3) -1 0.7
Pintu Jendela Type 1 (PJ1) -1 0.9
Jendela Type 1 (J1) -1 1.15
Jendela Type 2 (J2) -1 1.15
Bouvenligth Type 1 (J1) -1 1.15
H. PEKERJAAN PLAFOND
1 Rangka Plafond Metal Furring R. Tamu 2 3
R. Keluarga 2.5 3
Dapur 2 3
Wc 1.3 3
R. Tidur I 2.5 1
WC II 1.5 1.2
R. Tidur II 2.5 3
Teras Belakang 3 2.2
Teras Depan 1 2.2
I. PEKERJAAN ATAP
1 Kuda-kuda Baja ringan Atap 1 10.6 6
Atap 2 0 9.68
0 9.68
J. PEKERJAAN CAT-CATAN
1 Cat Tembok Luar Dinding 33.44 1
Pagar 0 1
Depan 0 1
0 1
Kanan 0 1
0 1
0 1
Kiri 0 1
0 1
0 1
0 1
Belakang 0 1
0 1
Pintu Type 1 (P1) -1 0.9
PintuType 2 (P2) -1 0.8
Pintu Type 3 (P3) -1 0.7
Pintu Jendela Type 1 (PJ1) -1 0.9
Jendela (PJ) -1 0.55
Jendela Type 1 (J1) -1 1.15
Jendela Type 2 (J2) -1 1.15
Jendela Type 3 (J3) -1 0.6
Bouven Light Type 1 (BV1) -1 1.15
Bouven Light Type 2 (BV2) -1 0.6
Bouven Light Type 3 (BV3) -1 0.3
dak Beton
Depan 4.83 0.4
Kiri 5.4 0.4
Belakang 2.85 0.4
Canopy
Depan 1 0.6 0.6
Depan 2 1.15 0.6
Belakang 4.62 0.6
1.15 0.6
K. PEKERJAAN SANITAIR
1 Pipa PVC dia 4" D dan Accessories 0 1
2 Pipa PVC dia 2" D dan Accessories 0 1
3 Pipa PVC dia 3/4" AW dan Accessories 0 1
4 Pipa PVC dia 1/2" AW dan Accessories 27.81 1
5 Kloset duduk + Jet Shower 1 1
6 Kran Air 1/2" 1 1
7 Floor Drain 1 1
8 Roof Drain 1 1
9 Bak Mandi 1 1
10 Drainase 0 1
11 Bak Kontrol 1 1
12 Kictchen Zink + Kran Air 1 1
13 Septictank Biofil 1 1
L. PEKERJAAN LISTRIK
1 Instalasi Lampu 1 1
2 Instalasi Stop Kontak 1 1
3 Pasang Lampu SL 18 Watt 1 1
4 Pasang Lampu SL 8 Watt 1 1
5 Pasang Skring Kash Listrik 1 Group 1 1
TINGGI JUMLAH VOLUME VOL. TOTAL SATUAN
1 1 72 72.00 M²
1 1 36 36.00 M
41.60 M³
1 1 19.35
1 1 21.69
1 1 #NAME?
1 1
1 1 0.56 #NAME?
3347400000
#NAME?
1 1 10.4 10.40 M³
0.1 0 0 0.00 M³
0.1 0 0
0.1 0 0
1 3 4 4.00 Unit
1 1 2 2.00 Unit
1 0 0 0.00 Unit
1 1 0 0.00 Unit
1 2 4 4.00 Unit
1 0 2 2.00 Unit
1 0 0 0.00 Unit
1 1 2 2.00 Unit
1 1 0 0.00 Unit
1 1 0 0.00 Unit
1 1 32.742
1 -1 -32.742
1 1 52.9496
1 1 52.9496
1 44 44 54.50 M²
1 0 0 0.00 M
1 0 0
1 0 0
1 1 63.6 63.60 M²
1 1
1 1
1 1 6 6.00 M
1 1 14.04 14.04 M
1 1 1.932
1 1 2.16
1 1 1.14
1 1 0.36
1 1 0.69
1 1 2.772
1 1 0.69
1 54.50 54.5
1 1.00 0.7
1 30 30 30.00 M²
1 1 0.00 M
1 1 0.00 M
1 1 0.00 M
1 1 27.81 27.81 M
1 2 2 2.00 Unit
1 6 6 6.00 Bh
1 2 2 2.00 Bh
1 0 0 0.00 Bh
1 1 1 1.00 Bh
1 1 0.00 M
1 1 1 1.00 Bh
1 1 0 0.00 Unit
1 1 1 1.00 Unit
11.00 5
0.03 0.3
Stop Kontak
16.00
Pintu Type 1 (P1) 0.9 2 1
PintuType 2 (P2) 0.8 2 3
Pintu Type 3 (P3) 0.7 2 1
Pintu Jendela Type 1 (PJ1) 0.9 2 1
Jendela (PJ) 0.55 1.4 1
Jendela Type 1 (J1) 1.15 1.85 1
Jendela Type 2 (J2) 1.15 1.4 2
Jendela Type 3 (J3) 0.6 1.4 1
Bouven Light Type 1 (BV1) 1.15 0.6 1
Bouven Light Type 2 (BV2) 0.6 0.25 1
Bouven Light Type 3 (BV3) 0.3 0.6 3
CAT KUSEN
LIST PLANK
= 42.8 M²
= 2.808 M²
= 45.608 M²