HARGA
VOL
NO. URAIAN SATUAN JUMLAH Bank Charges (5%) TOTAL PLOATING
(M2)
(Rp/M2)
I PEKERJAAN KONTRUKSI 5%
1 Basement 10,248 12,000,000 Rp 122,976,000,000 Rp 122,976,000,000
2 Mal/ Comercial Area 10,571 9,000,000 Rp 95,139,000,000 Rp 95,139,000,000
3 Apartemen dan Hotel 34,650 9,000,000 Rp 311,850,000,000 Rp 311,850,000,000
4 Cinema dan Penthouse 1,661 9,000,000 Rp 14,949,000,000 Rp 14,949,000,000
5 Meeting Room 3,566 9,000,000 Rp 32,094,000,000 Rp 32,094,000,000
6 Pekerjaan Infrastruktur #REF! #REF!
Sub Total #REF! #REF!
II PEKERJAAN NONKONTRUKSI
1 #REF! Rp 50,965,420,000 Rp 2,548,271,000 Rp 53,513,691,000
2 #REF! 2.50% #REF! #REF! #REF!
3 #REF! 1% #REF! #REF! #REF!
4 AKUSISI (LAHAN DAN IZIN) Rp 95,000,000,000 Rp 4,750,000,000 Rp 99,750,000,000
5 CADANGAN BIAYA ADMIN/PROVISI BANK 1% #REF! #REF! #REF!
6 BIAYA LAIN-LAIN (FEE MEDIASI/TAK TERDUGA LAINYA) 3% #REF! #REF! #REF!
7 BIAYA OPRASIONAL&AWAL PENGELOLAAN MANAJEMEN (2 TAHUN) 10% #REF! #REF! #REF!
Sub Total #REF! #REF! #REF!
TOTAL #REF! #REF!
PPN 10% #REF!
TOTAL NILAI PLOATING #REF!
TOTAL NILAI PLOATING (Dibulatkan) #REF!
HARGA
VOL
NO. URAIAN SATUAN JUMLAH TOTAL PLOATING
(M2)
(Rp/M2)
I PEKERJAAN KONTRUKSI
1 Basement 10,248 12,000,000 122,976,000,000 122,976,000,000
2 Mal/ Comercial Area 10,571 9,000,000 95,139,000,000 95,139,000,000
3 Apartemen dan Hotel 34,650 9,000,000 311,850,000,000 311,850,000,000
4 Cinema dan Penthouse 1,661 9,000,000 14,949,000,000 14,949,000,000
5 Meeting Room 3,566 9,000,000 32,094,000,000 32,094,000,000
6 Pekerjaan Infrastruktur #REF! #REF!
Sub Total #REF! #REF!
II PEKERJAAN NONKONTRUKSI
1 #REF! 50,965,420,000 53,513,691,000
2 #REF! 2.5% #REF! #REF!
3 #REF! 1% #REF! #REF!
4 AKUSISI (LAHAN DAN IZIN) 95,000,000,000 99,750,000,000
5 CADANGAN BIAYA ADMIN/PROVISI BANK 1% #REF! #REF!
6 BIAYA LAIN-LAIN (FEE MEDIASI/TAK TERDUGA LAINYA) 3% #REF! #REF!
7 BIAYA OPRASIONAL&AWAL PENGELOLAAN MANAJEMEN (2 TAHUN) 10% #REF! #REF!
Sub Total #REF! #REF!
TOTAL #REF! #REF!
PPN 10% #REF!
TOTAL NILAI PLOATING #REF!
TOTAL NILAI PLOATING (Dibulatkan) #REF!
A PEKERJAAN PERSIAPAN
I PEKERJAAN PERSIAPAN
1 Pas. Bowplank dan Pengukuran area Bangunan Gedung 770.15 M' 90,500.00 69,590,462.69
2 Pek. Pengadaan Listrik Kerja 1,100.21 M² 12,500.00 13,070,491.00
3 Administrasi Proyek/Dokumentasi 1.00 Ls 30,000,000.00 18,336,828.00
4 Pek. Pembuatan Papan Nama Proyek 1.00 Ls 500,000.00 392,408.12
SUB TOTAL - A 101,390,189.81
II PEKERJAAN GALIAN DAN URUGAN
I AREA BANGUNAN
1 Pek. Galian Tanah Basement kedalaman 4 m 42,282.66 M³ 100,800.00 4,262,092,377.87
2 Pek. Galian Tanah Pile Cap P1 38.02 M³ 129,000.00 4,904,368.02
3 Pek. Galian Tanah Pile Cap P2 126.62 M³ 129,000.00 16,333,437.86
4 Pek. Galian Tanah Pile Cap P3 1,377.25 M³ 129,000.00 177,665,068.09
5 Pek. Lantai Kerja Bwh Pile Cap 1,2,3 66.43 M³ 1,297,200.00 86,166,716.82
6 Pek. Lantai Kerja Bwh Sloof 41.18 M³ 1,297,200.00 53,420,589.33
7 Pek. Urugan Pasir Bawah Pile Cap P1,P2,P3 66.43 M³ 393,840.00 26,160,884.79
8 Pek. Urugan Pasir Bawah Sloof 41.18 M³ 393,840.00 16,218,906.03
9 Pek. Urugan Tanah Peninggian bangunan 5,102.47 M³ 199,560.00 1,018,248,291.08
SUB TOTAL - B 5,661,210,639.89
III PEKERJAAN STRUKTUR BETON
A PONDASI BETON
1 Pekerjaan Pile cap Type P1 (190 X 190 X 50 )
- Cor Beton K-300 22.25 M³ 1,571,880.00 34,972,262.42
-Tulangan Pembesian dengan Besi Ulir Atau BJTD 40 2,706.41 Kg 16,800.00 45,467,668.65
- Bekisting 41.61 M² 250,200.00 10,410,651.58
2 Pekerjaan Pile cap Type P2 (190 X 190 X 75 )
- Cor Beton K-300 81.83 M³ 1,571,880.00 128,623,945.90
-Tulangan Pembesian dengan Besi Ulir Atau BJTD 40 10,101.67 Kg 16,800.00 169,708,003.28
- Bekisting 172.27 M² 250,200.00 43,103,079.67
3 Pekerjaan Pile cap Type P2 (190 X 290 X 100 )
- Cor Beton K-300 971.41 M³ 1,571,880.00 1,526,937,976.65
-Tulangan Pembesian dengan Besi Ulir Atau BJTD 40 103,426.72 Kg 16,800.00 1,737,568,959.28
- Bekisting 1,692.47 M² 250,200.00 423,456,980.76
SUB JUMLAH C-I 4,120,249,528.19
B STRUKTUR BETON LANTAI Elev -11,55
1 Pekerjaan Sloof (SD) 25/40
- Cor Beton K-300 329.41 M³ 1,571,880.00 517,786,442.92
-Tulangan Pembesian dengan Besi Ulir Atau BJTD 40 43,810.91 Kg 16,800.00 736,023,369.44
-Tulangan Pembesian dengan Besi polos Atau BJTD 24 18,688.27 Kg 16,800.00 313,962,912.33
- Bekisting 2,635.25 M² 265,320.00 699,183,647.78
2 Pekerjaan Kolom Beton KD (75/75) cm
- Cor Beton K-300 442.57 M³ 1,571,880.00 695,674,200.78
-Tulangan Pembesian dengan Besi Ulir Atau BJTD 40 70,467.60 Kg 16,800.00 1,183,855,761.54
-Tulangan Pembesian dengan Besi polos Atau BJTD 24 20,667.29 Kg 16,800.00 347,210,405.37
- Bekisting 3,540.60 M² 412,560.00 1,460,708,696.71
3 Pekerjaan Dinding Beton T 30 Cm K-300
- Cor Beton K-250 903.65 M³ 1,382,400.00 1,249,211,517.17
-Tulangan Pembesian dengan Besi polos Atau BJTD 24 198.44 Kg 16,800.00 3,333,708.68
- Bekisting 14,458.57 M² 265,320.00 3,836,148,747.21
4 Pekerjaan Beton Tangga (1,2,3 ,4 & 5)
- Cor Beton K-300 28.59 M³ 1,571,880.00 44,940,317.98
-Tulangan Pembesian dengan Besi polos Atau BJTD 24 6,216.37 Kg 16,800.00 104,434,983.42
- Bekisting 524.16 M² 412,560.00 216,246,718.72
5 Pekerjaan Beton Wire Mesh (78,79 kg/m3)
- Cor Beton K-300 2.52 M³ 1,571,880.00 3,963,202.81
-Tulangan Pembesian dengan Besi polos Atau BJTD 24 198.45 Kg 16,800.00 3,333,965.39
SUB JUMLAH C-II 11,416,018,598.24
C STRUKTUR BETON LANTAI -7,70
1 Pekerjaan Sloof (SD) 25/40
- Cor Beton K-300 329.41 M³ 1,571,880.00 517,786,442.92
-Tulangan Pembesian dengan Besi Ulir Atau BJTD 40 43,810.91 Kg 16,800.00 736,023,369.44
-Tulangan Pembesian dengan Besi polos Atau BJTD 24 18,688.27 Kg 16,800.00 313,962,912.33
- Bekisting 2,635.25 M² 265,320.00 699,183,647.78
2 Pekerjaan Kolom Beton KD (75/75) cm
- Cor Beton K-300 442.57 M³ 1,571,880.00 695,674,200.78
-Tulangan Pembesian dengan Besi Ulir Atau BJTD 40 70,467.60 Kg 16,800.00 1,183,855,761.54
-Tulangan Pembesian dengan Besi polos Atau BJTD 24 20,667.29 Kg 16,800.00 347,210,405.37
- Bekisting 3,540.60 M² 412,560.00 1,460,708,696.71
C PEKERJAAN ARSITEKTUR
D PEKERJAAN FINISHING
E PEKERJAAN PLAMBING
3 Priming tank kap.100 lt lengkap dgn. Asessories 18.00 unit 2,860,000 51,480,000.00
1 PERALATAN UTAMA
1 Pengadaan dan Instalasi Bak Penampungan (sistem biofill) 20.00 unit 2,340,000 46,800,000.00
2 BASEMENT 2 (B2)
a Instalasi titik lampu dan stop kontak
- Instalasi Penerangan 3,600.00 Ttk 4,633.52 16,680,682.63
b Fixtures & Armatures Lampu -
- Lampu Flourescent TL 2x36W Pasang Outbow 1,800.00 Bh 258,153.42 464,676,159.08
- Lampu Flourescent 2xTL-5 35W Pasang inbow 600.00 Bh 496,448.89 297,869,332.74
- Lampu DownLigth 18w 1,320.00 Bh 231,676.15 305,812,514.95
- Lampu Roset PLE LED 3 W 360.00 Bh 165,482.96 59,573,866.55
c Fixtures Saklar & Stop Kontak -
- Stop Kontak Dinding IPh,10,13-16A 1,140.00 Bh 52,954.55 60,368,184.77
- Soket Telpon 360.00 Bh 86,051.14 30,978,410.61
- Soket Data 240.00 Bh 99,289.78 23,829,546.62
3 BASEMENT 1 (B1)
a Instalasi titik lampu dan stop kontak
- Instalasi Penerangan 3,600.00 Ttk 529.55 1,906,363.73
b Fixtures & Armatures Lampu -
- Lampu Flourescent TL 2x36W Pasang Outbow 1,800.00 Bh 258,153.42 464,676,159.08
- Lampu Flourescent 2xTL-5 35W Pasang inbow 600.00 Bh 496,448.89 297,869,332.74
- Lampu DownLigth 18w 1,320.00 Bh 231,676.15 305,812,514.95
- Lampu Roset PLE LED 3 W 360.00 Bh 165,482.96 59,573,866.55
c Fixtures Saklar & Stop Kontak -
- Stop Kontak Dinding IPh,10,13-16A 1,140.00 Bh 52,954.55 60,368,184.77
- Soket Telpon 360.00 Bh 86,051.14 30,978,410.61
- Soket Data 240.00 Bh 99,289.78 23,829,546.62
4 GROUND FLOOR
a Instalasi titik lampu dan stop kontak
- Instalasi Penerangan 160.00 Ttk 285,954.56 45,752,729.51
b Fixtures & Armatures Lampu -
- Lampu Flourescent TL 2x36W Pasang Outbow Bh 258,153.42 -
- Lampu Flourescent 2xTL-5 35W Pasang inbow 82.00 Bh 496,448.89 40,708,808.81
- Lampu DownLigth 18w 48.00 Bh 231,676.15 11,120,455.09
- Lampu Downlith PLE LED 3 W 22.00 Bh 165,482.96 3,640,625.18
- Lampu Roset PLE LED 3 W 8.00 Bh 165,482.96 1,323,863.70
c Fixtures Saklar & Stop Kontak -
- Stop Kontak Dinding IPh,10,13-16A 78.00 Bh 52,954.55 4,130,454.75
- Soket Telpon 78.00 Bh 86,051.14 6,711,988.96
- Soket Data 68.00 Bh 99,289.78 6,751,704.88
5 UPPER GROUND
a Instalasi titik lampu dan stop kontak
- Instalasi Penerangan 160.00 Ttk 285,954.56 45,752,729.51
b Fixtures & Armatures Lampu
- Lampu Flourescent TL 2x36W Pasang Outbow Bh 258,153.42 -
- Lampu Flourescent 2xTL-5 35W Pasang inbow 82.00 Bh 496,448.89 40,708,808.81
- Lampu DownLigth 18w 48.00 Bh 231,676.15 11,120,455.09
- Lampu Downlith PLE LED 3 W 22.00 Bh 165,482.96 3,640,625.18
- Lampu Roset PLE LED 3 W 8.00 Bh 165,482.96 1,323,863.70
c Fixtures Saklar & Stop Kontak -
- Stop Kontak Dinding IPh,10,13-16A 78.00 Bh 52,954.55 4,130,454.75
- Soket Telpon 78.00 Bh 86,051.14 6,711,988.96
- Soket Data 68.00 Bh 99,289.78 6,751,704.88
6 LANTAI 1
a Instalasi titik lampu dan stop kontak
- Instalasi Penerangan 160.00 Ttk 285,954.56 45,752,729.51
b Fixtures & Armatures Lampu -
- Lampu Flourescent TL 2x36W Pasang Outbow Bh 258,153.42 -
- Lampu Flourescent 2xTL-5 35W Pasang inbow 82.00 Bh 496,448.89 40,708,808.81
- Lampu DownLigth 18w 48.00 Bh 231,676.15 11,120,455.09
- Lampu Downlith PLE LED 3 W 22.00 Bh 165,482.96 3,640,625.18
- Lampu Roset PLE LED 3 W 8.00 Bh 165,482.96 1,323,863.70
c Fixtures Saklar & Stop Kontak - -
- Stop Kontak Dinding IPh,10,13-16A 78.00 Bh 52,954.55 4,130,454.75
- Soket Telpon 78.00 Bh 86,051.14 6,711,988.96
- Soket Data 68.00 Bh 99,289.78 6,751,704.88
- Access Point Wireless/Hot Spot 1.00 Bh 330,965.93 330,965.93
7 LANTAI 2
a Instalasi titik lampu dan stop kontak
- Instalasi Penerangan 160.00 Ttk 285,954.56 45,752,729.51
b Fixtures & Armatures Lampu - -
- Lampu Flourescent TLD 3x14W Pasang inbow Bh 258,153.42 -
- Lampu Flourescent 2xTL-5 35W Pasang inbow 82.00 Bh 496,448.89 40,708,808.81
- Lampu DownLigth 18w 48.00 Bh 231,676.15 11,120,455.09
- Lampu Downlith PLE LED 3 W 22.00 Bh 165,482.96 3,640,625.18
- Lampu Roset PLE LED 3 W 8.00 Bh 165,482.96 1,323,863.70
- Lampu Flourescent TL 1x36W Pasang outbow Bh 165,482.96 -
c Fixtures Saklar & Stop Kontak 78.00 - -
- Stop Kontak Dinding IPh,10,13-16A 78.00 Bh 52,954.55 4,130,454.75
- Stop Kontak Ganda 16A 68.00 Bh 86,051.14 5,851,477.56
- Soket Data GaNda 4.00 Bh 99,289.78 397,159.11
- Access Point Wireless/Hot Spot 2.00 Bh 330,965.93 661,931.85
9 PENANGKAL PETIR
- Air Terminal, System Non Radio Aktif radius 50 m proteksi 1.00 Bh 36,406,251.78 36,406,251.78
- Pemasangan tiang pipa GIP. Dia. 2" kaomplit alat penunjang 1.00 Bh 1,654,829.63 1,654,829.63
- Cosx cable dia. 70 mm2 & Pipa Conduit Ø 3/4" 240.00 M' 112,528.41 27,006,819.50
- Instalasi pembumian lengkap dengan elecrtrode pembumian 1.00 Bh 2,316,761.48 2,316,761.48
terbuat dari copper rod dia.5/8 " panjang minimal 6 m -
- Bak Kontrol (uk. 400 x 400 mm) + Elektroda 1.00 Bh 595,738.67 595,738.67
- Material Bantu 1.00 Lot 6,288,352.58 6,288,352.58
Jumlah C 7,941,580,331.41
D PEKERJAAN KABEL TRAY UNTUK ARUS KUAT
1 BASEMENT 3
- Ukuran 20 x 10 cm 84.00 M 264,772.74 22,240,910.18
2 BASEMENT 2
- Ukuran 30 x 10 cm 132.00 M 297,869.33 39,318,751.92
- Ukuran 20 x 10 cm 52.00 M 264,772.74 13,768,182.49
3 LANTAI 2
- Ukuran 30 x 10 cm 132.00 M 297,869.33 39,318,751.92
- Ukuran 20 x 10 cm 52.00 M 264,772.74 13,768,182.49
4 BASEMENT 1
- Ukuran 30 x 10 cm 132.00 M 297,869.33 39,318,751.92
- Ukuran 20 x 10 cm 52.00 M 264,772.74 13,768,182.49
5 GROUND FLOOR
- Ukuran 30 x 10 cm 132.00 M 297,869.33 39,318,751.92
- Ukuran 20 x 10 cm 52.00 M 264,772.74 13,768,182.49
6 UPPER GROUND
- Ukuran 30 x 10 cm 132.00 M 297,869.33 39,318,751.92
- Ukuran 20 x 10 cm 52.00 M 264,772.74 13,768,182.49
7 LANTAI 1
- Ukuran 30 x 10 cm 132.00 M 297,869.33 39,318,751.92
- Ukuran 20 x 10 cm 52.00 M 264,772.74 13,768,182.49
8 LANTAI 2
- Ukuran 30 x 10 cm 132.00 M 297,869.33 39,318,751.92
- Ukuran 20 x 10 cm 52.00 M 264,772.74 13,768,182.49
9 LANTAI 3 D/D 24
- Ukuran 30 x 10 cm 2,904.00 M 297,869.33 865,012,542.29
- Ukuran 20 x 10 cm 1,144.00 M 264,772.74 302,900,014.81
Jumlah D 1,561,762,008.17
E PEKERJAAN KABEL TRAY UNTUK ARUS LEMAH
1 BASEMENT 3
- Ukuran 20 x 10 cm 84.00 M 264,772.74 22,240,910.18
2 BASEMENT 2
- Ukuran 70 x 10 cm 32.00 M 595,738.67 19,063,637.30
- Ukuran 30 x 10 cm 40.00 M 297,869.33 11,914,773.31
- Ukuran 20 x 10 cm 152.00 M 264,772.74 40,245,456.51
3 LANTAI 1
- Ukuran 30 x 10 cm 40.00 M 297,869.33 11,914,773.31
- Ukuran 20 x 10 cm 152.00 M 264,772.74 40,245,456.51
4 GROUND FLOOR
- Ukuran 30 x 10 cm 40.00 M 297,869.33 11,914,773.31
- Ukuran 20 x 10 cm 152.00 M 264,772.74 40,245,456.51
5 LANTAI 1
- Ukuran 30 x 10 cm 40.00 M 297,869.33 11,914,773.31
- Ukuran 20 x 10 cm 152.00 M 264,772.74 40,245,456.51
6 LANTAI 1
- Ukuran 30 x 10 cm 40.00 M 297,869.33 11,914,773.31
- Ukuran 20 x 10 cm 152.00 M 264,772.74 40,245,456.51
7 LANTAI 1
- Ukuran 30 x 10 cm 40.00 M 297,869.33 11,914,773.31
- Ukuran 20 x 10 cm 152.00 M 264,772.74 40,245,456.51
8 LANTAI 1
- Ukuran 30 x 10 cm 40.00 M 297,869.33 11,914,773.31
- Ukuran 20 x 10 cm 152.00 M 264,772.74 40,245,456.51
Jumlah E 406,426,156.23
II PEKERJAAN TATA UDARA (AC) DAN VENTILASI MEKANIK
A LANTAI BASEMANT 3
I PERALATAN UTAMA
Air Conditioning VRV/VRF Split System c/w remote control, Raf Net &
1
Accessories
Type : FCU
Merk :
Kapasitas : 1 TR /12.000 BTU/H 6.00 Unit 11,252,841.46 67,517,048.76
II DUCTING
1 Ducting Exhaus & Fresh Air tanpa isolasi lengkap hangger dll
500 x 400 858.00 m 536,164.80 460,029,397.49
II DUCTING
1 Ducting Exhaus & Fresh Air tanpa isolasi lengkap hangger dll
500 x 400 858.00 m 536,164.80 460,029,397.49
II DUCTING
1 Ducting Exhaus & Fresh Air tanpa isolasi lengkap hangger dll
500 x 400 858.00 m 536,164.80 460,029,397.49
II DUCTING
1 Ducting Exhaus & Fresh Air tanpa isolasi lengkap hangger dll
500 x 400 290.00 m 536,164.80 155,487,791.69
Ducting Supply & Return Lengkap dengan isolasi luar & dalam glasswool tebal 1" density 24
2
kg/m2,Allumunium foil, penggantung.damper dll
450 x 200 (18x8") 440.00 m 602,357.98 265,037,512.96
III DIFFUSER DAN GRILLE
- Exhaus Air Grille
Bahan : aluminium
400 x 400 220.00 bh 496,448.89 109,218,755.34
- Inteake Grille - -
300 x 300 19.00 bh 364,062.52 6,917,187.84
- Fresh Air Grille - -
Bahan : aluminium - -
30 x 30 220.00 bh 463,352.30 101,937,504.98
F LANTAI 1
I PERALATAN UTAMA
1 Air Conditioning VRV/VRF Split System c/w remote control, Raf Net &
Accessories
Type : Wall Mounted-Inverter
Merk :
Kapasitas : 20500BTU/H 120.00 Unit 11,252,841.46 1,350,340,975.10
-
Type : Cassette 4 way-Inverter -
Kapasitas : 24200 BTU 100.00 Unit 5,163,068.43 516,306,843.42
-
2 Fan dan Exhaus -
- Exhaus -
Type : Axial -
Kapasitas 220.00 Unit 1,985,795.55 436,875,021.36
II DUCTING -
1 Ducting Exhaus & Fresh Air tanpa isolasi lengkap hangger dll -
500 x 400 260.00 m 536,164.80 139,402,847.72
-
Ducting Supply & Return Lengkap dengan isolasi luar & dalam glasswool tebal 1" density 24
2 -
kg/m2,Allumunium foil, penggantung.damper dll
450 x 200 (18x8") 440.00 m 602,357.98 265,037,512.96
450 x 150 (18x6") 270.00 m 559,332.41 151,019,751.70
Ducting Supply & Return Lengkap dengan isolasi luar glasswool tebal 1" density 24
3
kg/m2,Allumunium foil, penggantung.damper dll
4 Flexible duct Ø 20 cm 46.00 m 56,264.21 2,588,153.54
II DUCTING
1 Ducting Exhaus & Fresh Air tanpa isolasi lengkap hangger dll
500 x 400 260.00 m 536,164.80 139,402,847.72
Ducting Supply & Return Lengkap dengan isolasi luar & dalam glasswool tebal 1" density 24
2
kg/m2,Allumunium foil, penggantung.damper dll
450 x 200 (18x8") 480.00 m 602,357.98 289,131,832.32
450 x 150 (18x6") 220.00 m 559,332.41 123,053,131.02
3 Ducting Supply & Return Lengkap dengan isolasi luar glasswool tebal 1" density 24
kg/m2,Allumunium foil, penggantung.damper dll
4 Flexible duct Ø 20 cm 46.00 m 42,500.00 1,955,000.00
H LANTAI 3 S/D 2 4
I PERALATAN UTAMA
1 Air Conditioning VRV/VRF Split System c/w remote control, Raf Net &
Accessories
Type : Cassette 4 way-Inverter
Merk :
Kapasitas : 20500BTU/H 220.00 Unit 11,252,841.46 2,475,625,121.02
II DUCTING
1 Ducting Exhaus & Fresh Air tanpa isolasi lengkap hangger dll
500 x 400 5,720.00 m 536,164.80 3,066,862,649.92
Ducting Supply & Return Lengkap dengan isolasi luar & dalam glasswool tebal 1" density 24
2
kg/m2,Allumunium foil, penggantung.damper dll
450 x 200 (18x8") 10,560.00 m 602,357.98 6,360,900,310.95
450 x 150 (18x6") 4,840.00 m 559,332.41 2,707,168,882.34
Ducting Supply & Return Lengkap dengan isolasi luar glasswool tebal 1" density 24
3
kg/m2,Allumunium foil, penggantung.damper dll
4 Flexible duct Ø 20 cm 1,012.00 m 42,500.00 43,010,000.00
A PERALATAN UTAMA
1 MAIN PATCH PANEL 5.00 unit 52,954,548.04 264,772,740.22
B KABEL PENGHUBUNG
Fiber Optic 2 Core dari Master PATCH Panel ke :
- PATCH Panel 1 280.00 M' 165,482.96 46,335,229.54
- PATCH Panel 2 560.00 M' 165,482.96 92,670,459.08
- PATCH Panel 3 280.00 M' 165,482.96 46,335,229.54
- PATCH Panel 4 560.00 M' 165,482.96 92,670,459.08
- PATCH Panel 5 840.00 M' 165,482.96 139,005,688.61
Jumlah
718,196,057.84
B
C PEKERJAAN INSTALASI DATA
I LANTAI BASEMENT 3
1 Inst.data, kabel UTP category 6+pipa conduit UPVC Ø ¾" 60.00 Ttk 330,965.93 19,857,955.52
2 Outlet wall type RJ 45 (1 Gang) 60.00 Bh 112,528.41 6,751,704.88
3 24-port 10/ 100 Ethernet Switch with PoE 100 w, Managed, SFP 5.00 Unit 11,650,000.57 58,250,002.85
Linksys AC1200, Access Point AC1200, Dual Band, 1 x Gigabit Ethernet, 802.11b/g/n/ac,
4 5.00 Unit 4,368,750.21 21,843,751.07
2.4GHz/5GHz, Up To 1200Mbps, Integrated Power over Ethernet Plus (PoE+)
Linksys AC1200, Access Point AC1200, Dual Band, 1 x Gigabit Ethernet, 802.11b/g/n/ac,
4 5.00 Unit 4,368,750.21 21,843,751.07
2.4GHz/5GHz, Up To 1200Mbps, Integrated Power over Ethernet Plus (PoE+)
Linksys AC1200, Access Point AC1200, Dual Band, 1 x Gigabit Ethernet, 802.11b/g/n/ac,
4 5.00 Unit 4,368,750.21 21,843,751.07
2.4GHz/5GHz, Up To 1200Mbps, Integrated Power over Ethernet Plus (PoE+)
Linksys AC1200, Access Point AC1200, Dual Band, 1 x Gigabit Ethernet, 802.11b/g/n/ac,
4 5.00 Unit 4,368,750.21 21,843,751.07
2.4GHz/5GHz, Up To 1200Mbps, Integrated Power over Ethernet Plus (PoE+)
Linksys AC1200, Access Point AC1200, Dual Band, 1 x Gigabit Ethernet, 802.11b/g/n/ac,
4 5.00 Unit 4,368,750.21 21,843,751.07
2.4GHz/5GHz, Up To 1200Mbps, Integrated Power over Ethernet Plus (PoE+)
Linksys AC1200, Access Point AC1200, Dual Band, 1 x Gigabit Ethernet, 802.11b/g/n/ac,
4 5.00 Unit 4,368,750.21 21,843,751.07
2.4GHz/5GHz, Up To 1200Mbps, Integrated Power over Ethernet Plus (PoE+)
Linksys AC1200, Access Point AC1200, Dual Band, 1 x Gigabit Ethernet, 802.11b/g/n/ac,
4 5.00 Unit 4,368,750.21 21,843,751.07
2.4GHz/5GHz, Up To 1200Mbps, Integrated Power over Ethernet Plus (PoE+)
Linksys AC1200, Access Point AC1200, Dual Band, 1 x Gigabit Ethernet, 802.11b/g/n/ac,
4 110.00 Unit 4,368,750.21 480,562,523.49
2.4GHz/5GHz, Up To 1200Mbps, Integrated Power over Ethernet Plus (PoE+)
A PERALATAN UTAMA
1 Mixer Pre Amplifier, 120W/220V/1Ph 1.00 Unit 4,633,522.95 4,633,522.95
2 Power Amplifier, 3x240W/220V/1Ph/50 Hz 1.00 Unit 7,612,216.28 7,612,216.28
3 Power Amplifier, 3x240W/220V/1Ph/50 Hz (Paging) 1.00 Unit 7,612,216.28 7,612,216.28
4 Voice Alarm Controller 1.00 Unit 19,857,955.52 19,857,955.52
5 Voice Alarm Router 1.00 Unit 13,238,637.01 13,238,637.01
6 MDF-SS, 100 Pairs 1.00 Unit 2,316,761.48 2,316,761.48
7 Speaker Selector 5 Zone 1.00 Unit 3,971,591.10 3,971,591.10
8 Compact Disk MP3/MP4 Player 1.00 Unit 4,302,557.03 4,302,557.03
9 Radio Tuner AM/FM + Antenna 1.00 Unit 5,626,420.73 5,626,420.73
10 Paging Microphone 1.00 Unit 3,971,591.10 3,971,591.10
11 Emergency Microphone 1.00 Unit 6,288,352.58 6,288,352.58
12 Rak kabinet beserta aksesoris 1.00 Unit 11,252,841.46 11,252,841.46
13 Ni-cat Battery 4 jam 1.00 Unit incl
14 Surge Arrester 1.00 Unit 1,323,863.70 1,323,863.70
Jumlah A 92,008,527.23
B PEKERJAAN KABEL FEEDER
Menggunakan kabel NYMHY, termasuk konduit PVC,
klem, soket dan aksesoris.
1 BASEMENT 3
a. Junction Box 2 (JB-SB) 6.00 Bh 992,897.78 5,957,386.65
b. Instalasi -
- Instalasi horn loud Speaker ( Emergency ) 30.00 Ttk 893,608.00 26,808,239.95
c. Fixtures -
- Ceiling Speaker 3 Watt ( Normal) 12.00 Bh 244,914.78 2,938,977.42
- Horn Loud Speaker 6 Watt ( Di dinding) 18.00 Bh 761,221.63 13,701,989.31
Jumlah C-3 49,406,593.32
2 BASEMENT 2
a. Junction Box 2 (JB-SB) 6.00 Bh 992,897.78 5,957,386.65
b. Instalasi -
- Instalasi horn loud Speaker ( Emergency ) 30.00 Ttk 893,608.00 26,808,239.95
c. Fixtures -
- Ceiling Speaker 3 Watt ( Normal) 12.00 Bh 244,914.78 2,938,977.42
- Horn Loud Speaker 6 Watt ( Di dinding) 18.00 Bh 761,221.63 13,701,989.31
Jumlah C-2 49,406,593.32
3 BASEMENT 1
a. Junction Box 2 (JB-SB) 6.00 Bh 992,897.78 5,957,386.65
b. Instalasi -
- Instalasi horn loud Speaker ( Emergency ) 30.00 Ttk 893,608.00 26,808,239.95
c. Fixtures -
- Ceiling Speaker 3 Watt ( Normal) 12.00 Bh 244,914.78 2,938,977.42
- Horn Loud Speaker 6 Watt ( Di dinding) 18.00 Bh 761,221.63 13,701,989.31
Jumlah C-1 49,406,593.32
4 GROUND FLOOR
a. Junction Box 4 (JB-SS.LT1) 6.00 Bh 992,897.78 5,957,386.65
b. Instalasi
- Instalasi Ceiling Speaker ( Normal ) 78.00 Ttk 893,608.00 69,701,423.86
- Instalasi horn loud Speaker ( Emergency ) Ttk 893,608.00 -
- Instalasi Ceiling Speaker ( Normal ) Ttk 269,273.88 -
c. Fixtures
- Ceiling Speaker 3 Watt ( Emergency) 97.00 Bh 244,914.78 23,756,734.12
Jumlah C-2 99,415,544.63
5 UPPER GROUND
a. Junctionl Box 5 (JB-SS.LT2) 6.00 Bh 992,897.78 5,957,386.65
b. Instalasi -
Instalasi Ceiling Speaker ( Normal ) 80.00 Ttk 893,608.00 71,488,639.86
Instalasi horn loud Speaker ( Emergency ) Ttk 893,608.00 -
c. Fixtures -
Ceiling Speaker 3 Watt ( Normal) 80.00 Bh 244,914.78 19,593,182.78
Horn Loud Speaker 15 Watt ( Emergency) Bh -
- Jumlah C- 3 97,039,209.29
6 LANTAI 1
a. Junction Box 5 (JB-SS.LT3) 2.00 Bh 992,897.78 1,985,795.55
b. Instalasi
Instalasi Ceiling Speaker ( Normal ) 50.00 Ttk 893,608.00 44,680,399.91
Instalasi horn loud Speaker ( Emergency ) Ttk 893,608.00 -
c. Fixtures
Ceiling Speaker 3 Watt ( Normal) 50.00 Bh 244,914.78 12,245,739.24
Horn Loud Speaker 15 Watt ( Emergency) Bh - -
Jumlah C-4 58,911,934.70
7 LANTAI 2
a. Junction Box 5 (JB-SS.LT4) 6.00 Bh 992,897.78 5,957,386.65
b. Instalasi -
Ceiling Speaker 3 Watt ( Normal) 80.00 Ttk 893,608.00 71,488,639.86
Instalasi horn loud Speaker ( Emergency ) Ttk 893,608.00 -
c. Fixtures
Ceiling Speaker 3 Watt ( Normal) 80.00 Bh 244,914.78 19,593,182.78
Horn Loud Speaker 15 Watt ( Emergency) Bh -
Jumlah C-5 97,039,209.29
8 LANTAI 3 S/D 24
a. Junction Box 5 (JB-SS.LT4) 132.00 Bh 992,897.78 131,062,506.41
b. Instalasi -
Ceiling Speaker 3 Watt ( Normal) 1,760.00 Ttk 893,608.00 1,572,750,076.88
Instalasi horn loud Speaker ( Emergency ) Ttk 893,608.00 -
c. Fixtures
Ceiling Speaker 3 Watt ( Normal) 1,760.00 Bh 244,914.78 431,050,021.07
Horn Loud Speaker 15 Watt ( Emergency) Bh -
Jumlah C-5 2,134,862,604.36
VI PEKERJAAN INSTALASI FIRE ALRM
Master/ Main Control Fire Alarm (MCFA) Type 1.00 Unit 112,528,414.59 112,528,414.59
Type : Fully Adderssible min 40 zone
Kapasitas :
Lengkap dengan - Nicad battere
- Fuse arrester
- Input module
- LCD
- PC dan Printer
- Lightning Arester
- Sirine
- Lead Acid Rechargeable Dan Power Supply
Sistem ini terkoneksi dengan BAS
Announciator 1.00 Unit 13,238,637.01 13,238,637.01
Mimic Panel 1.00 Unit 9,928,977.76 9,928,977.76
Jumlah A 135,696,029.36
B KABEL DISTRIBUSI & PENTANAHAN
a. Dari MCFA ke :
- Announciator di R.Receptionist,STP AWG 18,1 Pair di Lt.1 20.00 M 19,857.96 397,159.11
b. Kabel Distribusi dari MCFA ke :
- Central Fire Alarm ke Sistem Tata Suara 1.00 Ttk 1,985,795.55 1,985,795.55
- Central Fire Alarm ke Panel Kontrol Pompa 1.00 Ttk 1,985,795.55 1,985,795.55
- Central Fire Alarm ke Panel Kontrol Pressurized Fan 1.00 Ttk 1,985,795.55 1,985,795.55
- Central Fire Alarm ke Panel Kontrol AC 1.00 Ttk 1,985,795.55 1,985,795.55
Central Fire Alarm ke DPK 1.00 Ttk 1,985,795.55 1,985,795.55
c. Kabel dari MCFA ke :
- FA - BSM FRC 2 x 2.5 mm 40.00 M 76,122.16 3,044,886.51
- FA - LT 1 FRC 2 x 2.5 mm 20.00 M 76,122.16 1,522,443.26
- FA - LT 2 FRC 2 x 2.5 mm 40.00 M 76,122.16 3,044,886.51
- FA - LT 3 FRC 2 x 2.5 mm 60.00 M 76,122.16 4,567,329.77
- FA - LT 4 FRC 2 x 2.5 mm 100.00 M 76,122.16 7,612,216.28
d. Pentanahan Menggunakan Tembaga Massif Dengan 1.00 Lot 13,304,830.20 13,304,830.20
Kedalaman Minimum 12 M, Maksimum Tahanan Yang dikehendaki
- Kabel NYA 50 mm² 1,000.00 M 165,482.96 165,482,962.64
- Test Link 1.00 Bh 9,928,977.76 9,928,977.76
Jumlah B 218,834,669.79
C PEKERJAAN INSTALASI & FIXTURES
1 Basement 3
a. Instalasi
- Instalasi Smoke Detector 25.00 Ttk 262,125.01 6,553,125.32
- Instalasi Heat Detector 32.00 Ttk 262,125.01 8,388,000.41
- Instalasi Manual Call Point 8.00 Ttk 262,125.01 2,097,000.10
- Instalasi Indicator Lamp 8.00 Ttk 262,125.01 2,097,000.10
- Instalasi Flow Switch 8.00 Ttk 262,125.01 2,097,000.10
- Instalasi Fireman Telephone 8.00 Ttk 262,125.01 2,097,000.10
b. Fixtures
- Optical Smoke Detector,Addressible c/w Base 25.00 Bh 595,738.67 14,893,466.64
- Optical Heat Detector,Rate Of Rase Type 32.00 Bh 297,869.33 9,531,818.65
- Alarm Bell 8.00 Bh 364,062.52 2,912,500.14
- Indicator Lamp 8.00 Bh 198,579.56 1,588,636.44
- Manual Call Point 8.00 Bh 364,062.52 2,912,500.14
- Jack + Fireman Telephone 8.00 Bh 231,676.15 1,853,409.18
- End of line resistance 1.00 Bh 66,193.19 66,193.19
- Panel Kontrol Fire Alarm 1.00 Bh 3,640,625.18 3,640,625.18
Jumlah C- 60,728,275.70
2 Basement 2
a. Instalasi
- Instalasi Smoke Detector 25.00 Ttk 262,125.01 6,553,125.32
- Instalasi Heat Detector 32.00 Ttk 262,125.01 8,388,000.41
- Instalasi Manual Call Point 8.00 Ttk 262,125.01 2,097,000.10
- Instalasi Indicator Lamp 8.00 Ttk 262,125.01 2,097,000.10
- Instalasi Flow Switch 8.00 Ttk 262,125.01 2,097,000.10
- Instalasi Fireman Telephone 8.00 Ttk 262,125.01 2,097,000.10
b. Fixtures
- Optical Smoke Detector,Addressible c/w Base 25.00 Bh 595,738.67 14,893,466.64
- Optical Heat Detector,Rate Of Rase Type 32.00 Bh 297,869.33 9,531,818.65
- Alarm Bell 8.00 Bh 364,062.52 2,912,500.14
- Indicator Lamp 8.00 Bh 198,579.56 1,588,636.44
- Manual Call Point 8.00 Bh 364,062.52 2,912,500.14
- Jack + Fireman Telephone 8.00 Bh 231,676.15 1,853,409.18
- End of line resistance 1.00 Bh 66,193.19 66,193.19
- Panel Kontrol Fire Alarm 1.00 Bh 3,640,625.18 3,640,625.18
Jumlah C- 60,728,275.70
3 Basement 1
a. Instalasi
- Instalasi Smoke Detector 25.00 Ttk 262,125.01 6,553,125.32
- Instalasi Heat Detector 32.00 Ttk 262,125.01 8,388,000.41
- Instalasi Manual Call Point 8.00 Ttk 262,125.01 2,097,000.10
- Instalasi Indicator Lamp 8.00 Ttk 262,125.01 2,097,000.10
- Instalasi Flow Switch 8.00 Ttk 262,125.01 2,097,000.10
- Instalasi Fireman Telephone 8.00 Ttk 262,125.01 2,097,000.10
b. Fixtures
- Optical Smoke Detector,Addressible c/w Base 25.00 Bh 595,738.67 14,893,466.64
- Optical Heat Detector,Rate Of Rase Type 32.00 Bh 297,869.33 9,531,818.65
- Alarm Bell 8.00 Bh 364,062.52 2,912,500.14
- Indicator Lamp 8.00 Bh 198,579.56 1,588,636.44
- Manual Call Point 8.00 Bh 364,062.52 2,912,500.14
- Jack + Fireman Telephone 8.00 Bh 231,676.15 1,853,409.18
- End of line resistance 1.00 Bh 66,193.19 66,193.19
- Panel Kontrol Fire Alarm 1.00 Bh 3,640,625.18 3,640,625.18
Jumlah C-
60,728,275.70
3
4 GROUND FLOOR
a Instalasi
- Instalasi Smoke Detector 40.00 Ttk 262,125.01 10,485,000.51
- Instalasi Heat Detector - Ttk 0.00 -
- Instalasi Manual Call Point 8.00 Ttk 262,125.01 2,097,000.10
- Instalasi Indicator Lamp 8.00 Ttk 262,125.01 2,097,000.10
- Instalasi Flow Switch 8.00 Ttk 262,125.01 2,097,000.10
- Instalasi Fireman Telephone 8.00 Ttk 262,125.01 2,097,000.10
b Fixtures
- Optical Smoke Detector,Addressible c/w Base 40.00 Bh 595,738.67 23,829,546.62
- Optical Heat Detector,Rate Of Rase Type - Bh 0.00 -
- Alarm Bell 8.00 Bh 364,062.52 2,912,500.14
- Indicator Lamp 8.00 Bh 198,579.56 1,588,636.44
- Manual Call Point 8.00 Bh 364,062.52 2,912,500.14
- Jack + Fireman Telephone 8.00 Bh 231,676.15 1,853,409.18
- End of line resistance 1.00 Bh 66,193.19 66,193.19
- Panel Kontrol Fire Alarm 1.00 Bh 3,640,625.18 3,640,625.18
Jumlah C- 55,676,411.81
5 UPPER GROUND
a Instalasi
- Instalasi Smoke Detector 40.00 Ttk 262,125.01 10,485,000.51
- Instalasi Heat Detector - Ttk 0.00 -
- Instalasi Manual Call Point 8.00 Ttk 262,125.01 2,097,000.10
- Instalasi Indicator Lamp 8.00 Ttk 262,125.01 2,097,000.10
- Instalasi Flow Switch 8.00 Ttk 262,125.01 2,097,000.10
- Instalasi Fireman Telephone 8.00 Ttk 262,125.01 2,097,000.10
b Fixtures
- Optical Smoke Detector,Addressible c/w Base 40.00 Bh 595,738.67 23,829,546.62
- Optical Heat Detector,Rate Of Rase Type - Bh 0.00 -
- Alarm Bell 8.00 Bh 364,062.52 2,912,500.14
- Indicator Lamp 8.00 Bh 198,579.56 1,588,636.44
- Manual Call Point 8.00 Bh 364,062.52 2,912,500.14
- Jack + Fireman Telephone 8.00 Bh 231,676.15 1,853,409.18
- End of line resistance 1.00 Bh 66,193.19 66,193.19
- Panel Kontrol Fire Alarm 1.00 Bh 3,640,625.18 3,640,625.18
Jumlah C- 55,676,411.81
6 Lantai 1
a Instalasi
- Instalasi Smoke Detector 40.00 Ttk 262,125.01 10,485,000.51
- Instalasi Heat Detector - Ttk 0.00 -
- Instalasi Manual Call Point 8.00 Ttk 262,125.01 2,097,000.10
- Instalasi Indicator Lamp 8.00 Ttk 262,125.01 2,097,000.10
- Instalasi Flow Switch 8.00 Ttk 262,125.01 2,097,000.10
- Instalasi Fireman Telephone 8.00 Ttk 262,125.01 2,097,000.10
b Fixtures
- Optical Smoke Detector,Addressible c/w Base 40.00 Bh 595,738.67 23,829,546.62
- Optical Heat Detector,Rate Of Rase Type - Bh 0.00 -
- Alarm Bell 8.00 Bh 364,062.52 2,912,500.14
- Indicator Lamp 8.00 Bh 198,579.56 1,588,636.44
- Manual Call Point 8.00 Bh 364,062.52 2,912,500.14
- Jack + Fireman Telephone 8.00 Bh 231,676.15 1,853,409.18
- End of line resistance 1.00 Bh 66,193.19 66,193.19
- Panel Kontrol Fire Alarm 1.00 Bh 3,640,625.18 3,640,625.18
Jumlah C- 4 55,676,411.81
7 Lantai 2
a Instalasi
- Instalasi Smoke Detector 40.00 Ttk 262,125.01 10,485,000.51
- Instalasi Heat Detector - Ttk 0.00 -
- Instalasi Manual Call Point 8.00 Ttk 262,125.01 2,097,000.10
- Instalasi Indicator Lamp 8.00 Ttk 262,125.01 2,097,000.10
- Instalasi Flow Switch 8.00 Ttk 262,125.01 2,097,000.10
- Instalasi Fireman Telephone 8.00 Ttk 262,125.01 2,097,000.10
b Fixtures
- Optical Smoke Detector,Addressible c/w Base 40.00 Bh 595,738.67 23,829,546.62
- Optical Heat Detector,Rate Of Rase Type - Bh 0.00 -
- Alarm Bell 8.00 Bh 364,062.52 2,912,500.14
- Indicator Lamp 8.00 Bh 198,579.56 1,588,636.44
- Manual Call Point 8.00 Bh 364,062.52 2,912,500.14
- Jack + Fireman Telephone 8.00 Bh 231,676.15 1,853,409.18
- End of line resistance 1.00 Bh 66,193.19 66,193.19
- Panel Kontrol Fire Alarm 1.00 Bh 3,640,625.18 3,640,625.18
Jumlah C- 55,676,411.81
8 Lantai 3 S/D Lantai 23
a Instalasi
- Instalasi Smoke Detector 880.00 Ttk 262,125.01 230,670,011.28
- Instalasi Heat Detector - Ttk 262,125.01 -
- Instalasi Manual Call Point 176.00 Ttk 262,125.01 46,134,002.26
- Instalasi Indicator Lamp 176.00 Ttk 262,125.01 46,134,002.26
- Instalasi Flow Switch 176.00 Ttk 262,125.01 46,134,002.26
- Instalasi Fireman Telephone 176.00 Ttk 262,125.01 46,134,002.26
b Fixtures
- Optical Smoke Detector,Addressible c/w Base 880.00 Bh 595,738.67 524,250,025.63
- Optical Heat Detector,Rate Of Rase Type - Bh 0.00 -
- Alarm Bell 176.00 Bh 364,062.52 64,075,003.13
- Indicator Lamp 176.00 Bh 198,579.56 34,950,001.71
- Manual Call Point 176.00 Bh 364,062.52 64,075,003.13
- Jack + Fireman Telephone 176.00 Bh 231,676.15 40,775,001.99
- End of line resistance 1.00 Bh 1,456,250.07 1,456,250.07
- Panel Kontrol Fire Alarm 1.00 Bh 14,562,500.71 14,562,500.71
3 Automatic Rescue Device (ARD) untuk lift passanger 10.00 unit 36,406,251.78 364,062,517.80
4 Biaya instalasi Unit lift Pasanger ( Penumpang ) 10.00 unit 33,096,592.53 330,965,925.27
4 Pengadaan dan pemasangan sistem netral unit genset 1 & 2 1.00 Lot 52,954,548.04 52,954,548.04
dan pentanahan genset termasuk kabel NYA 240 mm² lengkap
dengan pvc cables, earth bar, test clamp, earthing pits, klem
pipa bak kontrol + tutup beserta perlengkapan lainnya. Tahanan
pentanahan yang diperbolehkan maksimal sebesar 2 Ohm.
7 Pengadaan dan pemasangan pipa gas buang (knalpot) 1.00 Lot 32,434,660.68 32,434,660.68
dari pipa black steel Sch. 40 Æ 150 mm ( disesuaikan dengan
kondisi masing-masing unit genset) lengkap dengan ceramic
wool tebal 2" density 100 kg/M3, alluminium lagging, pipe clamp
vibration hanger, metal expansion plug, flexible connection,
support, pengecatan, rangka penggantung, spring mounting,
dan perlengkapan lain sehingga berfungsi dengan baik.
8 Pengadaan dan pemasangan pipa bahan bakar, black 1.00 Lot 15,224,432.56 15,224,432.56
steel kelas Sch. 40 dari tap point sampai unit genset
termasuk fitting dan material bantu.
11 Pengadaan PP-Pompa Solar, lengkap dengan kabel 1.00 Lot 11,583,807.38 11,583,807.38
power ke pompa dan kontrol fuel tank serta ke PHBUTR
12 Pengadaan Bahan Bakar Minyak jenis Solar pada saat 80.00 Ltr 12,576.71 1,006,136.41
penyerahan pekerjaan.
15 Louvre
- Intake Louvre : 7.000 (L) x 1.800 (W) mm 4.00 Bh 16,548,296.26 66,193,185.05
- Exhaust Louvre : 1.500 (L) x 2.000 (W) mm 4.00 Bh 7,943,182.21 31,772,728.83
- Exhaust Louvre : 1.000 (L) x 1.400 (W) mm 4.00 Bh 5,295,454.80 21,181,819.22
16 Exhaust Mufler Critical type (volume mufler disesuaikan 1.00 Set 33,096,592.53 33,096,592.53
dengan karakteristik unit), counter flange & low noise silencer
dari Weilded sheet steel lengkap rockwool thermal insulation
metal jacketing, clamp penggantung, support, pengecatan dan
perlengkapan lainnya sehingga dapat berfungsi dengan baik.
(Untuk Genset 350 kVA)
18 Drop Kit 1.00 Lot 9,928,977.76 9,928,977.76
17 TESTING & COMMISSIONING 1.00 Lot 20,519,887.37 20,519,887.37
Jumlah 8,895,538,071.00
IX PEKERJAAN TRANSFORMATOR DAYA
F PEKERJAAN INFRASTRUKTUR
HARGA SATUAN
NO URAIAN PEKERJAAN VOL SAT JUMLAH (RP.)
(RP.)
A PEKERJAAN PERSIAPAN
HARGA SATUAN
NO URAIAN PEKERJAAN VOL SAT JUMLAH (RP.)
(RP.)
I PEKERJAAN PERSIAPAN
1 Pas. Bowplank dan Pengukuran area Bangunan Gedung 770.15 M'
2 Pek. Pengadaan Listrik Kerja 1,100.21 M²
3 Administrasi Proyek 1.00 Ls
4 Pek. Pembuatan Papan Nama Proyek 1.00 Ls
SUB TOTAL - A 0.00
II PEKERJAAN GALIAN DAN URUGAN
I AREA BANGUNAN
1 Pek. Galian Tanah Basement kedalaman 4 m 42,282.66 M³
2 Pek. Galian Tanah Pile Cap P1 38.02 M³
3 Pek. Galian Tanah Pile Cap P2 126.62 M³
4 Pek. Galian Tanah Pile Cap P3 1,377.25 M³
5 Pek. Lantai Kerja Bwh Pile Cap 1,2,3 66.43 M³
6 Pek. Lantai Kerja Bwh Sloof 41.18 M³
7 Pek. Urugan Pasir Bawah Pile Cap P1,P2,P3 66.43 M³
8 Pek. Urugan Pasir Bawah Sloof 41.18 M³
9 Pek. Urugan Tanah Peninggian bangunan 5,102.47 M³
SUB TOTAL - B 0.00
III PEKERJAAN STRUKTUR BETON
A PONDASI BETON
1 Pekerjaan Pile cap Type P1 (190 X 190 X 50 )
- Cor Beton K-300 22.25 M³
-Tulangan Pembesian dengan Besi Ulir Atau BJTD 40 2,706.41 Kg
- Bekisting 41.61 M²
2 Pekerjaan Pile cap Type P2 (190 X 190 X 75 )
- Cor Beton K-300 81.83 M³
-Tulangan Pembesian dengan Besi Ulir Atau BJTD 40 10,101.67 Kg
- Bekisting 172.27 M²
3 Pekerjaan Pile cap Type P2 (190 X 290 X 100 )
- Cor Beton K-300 971.41 M³
-Tulangan Pembesian dengan Besi Ulir Atau BJTD 40 103,426.72 Kg
- Bekisting 1,692.47 M²
SUB JUMLAH C-I 0.00
B STRUKTUR BETON LANTAI Elev -11,55
1 Pekerjaan Sloof (SD) 25/40
- Cor Beton K-300 329.41 M³
-Tulangan Pembesian dengan Besi Ulir Atau BJTD 40 43,810.91 Kg
-Tulangan Pembesian dengan Besi polos Atau BJTD 24 18,688.27 Kg
- Bekisting 2,635.25 M²
2 Pekerjaan Kolom Beton KD (75/75) cm
- Cor Beton K-300 442.57 M³
-Tulangan Pembesian dengan Besi Ulir Atau BJTD 40 70,467.60 Kg
-Tulangan Pembesian dengan Besi polos Atau BJTD 24 20,667.29 Kg
- Bekisting 3,540.60 M²
3 Pekerjaan Dinding Beton T 30 Cm K-300
- Cor Beton K-250 903.65 M³
-Tulangan Pembesian dengan Besi polos Atau BJTD 24 198.44 Kg
- Bekisting 14,458.57 M²
4 Pekerjaan Beton Tangga (1,2,3 ,4 & 5)
- Cor Beton K-300 28.59 M³
-Tulangan Pembesian dengan Besi polos Atau BJTD 24 6,216.37 Kg
- Bekisting 524.16 M²
5 Pekerjaan Beton Wire Mesh (78,79 kg/m3)
- Cor Beton K-300 2.52 M³
-Tulangan Pembesian dengan Besi polos Atau BJTD 24 198.45 Kg
SUB JUMLAH C-II 0.00
C STRUKTUR BETON LANTAI -7,70
1 Pekerjaan Sloof (SD) 25/40
- Cor Beton K-300 329.41 M³
-Tulangan Pembesian dengan Besi Ulir Atau BJTD 40 43,810.91 Kg
-Tulangan Pembesian dengan Besi polos Atau BJTD 24 18,688.27 Kg
- Bekisting 2,635.25 M²
2 Pekerjaan Kolom Beton KD (75/75) cm
- Cor Beton K-300 442.57 M³
-Tulangan Pembesian dengan Besi Ulir Atau BJTD 40 70,467.60 Kg
-Tulangan Pembesian dengan Besi polos Atau BJTD 24 20,667.29 Kg
- Bekisting 3,540.60 M²
HARGA SATUAN
NO URAIAN PEKERJAAN VOL SAT JUMLAH (RP.)
(RP.)
C PEKERJAAN ARSITEKTUR
HARGA SATUAN
NO URAIAN PEKERJAAN VOL SAT JUMLAH (RP.)
(RP.)
D PEKERJAAN FINISHING
Jumlah 0.00
Jumlah 0.00
Jumlah 0.00
V FINISHING UPPER GROUND
1 Cat dinding dalam emulsion 7,030.15 M2
2 Cat plafond emulsion 5,621.54 M2
3 Partisi gypsum + rangka hollow galvanized 425.23 m2
4 Partisi cubikle toilet type PK1 + pintu P4 139.88 m2
5 Railing tangga pipa finish cat duco 127.69 M'
6 Sun Shading hollow aluminium 3" 136.92 M'
7 Waterproofing peneseal Pro toilet 76.92 M2
Jumlah 0.00
VI FINISHING LANTAI 1
1 Cat dinding dalam emulsion 2,510.77 M2
2 Cat plafond emulsion 5,581.55 M2
3 Partisi gypsum + rangka hollow galvanized 490.31 m2
4 Railing tangga pipa finish cat duco 127.69 M'
5 Sun Shading hollow aluminium 3" 136.92 M'
Jumlah 0.00
VII FINISHING LANTAI 2
1 Cat dinding dalam emulsion 2,510.77 M2
2 Cat plafond emulsion 2,007.69 M2
3 Partisi gypsum + rangka hollow galvanized 490.31 m2
4 Railing tangga pipa finish cat duco 127.69 M'
5 Sun Shading hollow aluminium 3" 136.92 M'
Jumlah 0.00
HARGA SATUAN
NO URAIAN PEKERJAAN VOL SAT JUMLAH (RP.)
(RP.)
E PEKERJAAN PLAMBING
1 PERALATAN UTAMA
HARGA SATUAN
NO URAIAN PEKERJAAN VOL SAT JUMLAH (RP.)
(RP.)
2 BASEMENT 2 (B2)
a Instalasi titik lampu dan stop kontak
- Instalasi Penerangan 3,600.00 Ttk
b Fixtures & Armatures Lampu
- Lampu Flourescent TL 2x36W Pasang Outbow 1,800.00 Bh
- Lampu Flourescent 2xTL-5 35W Pasang inbow 600.00 Bh
- Lampu DownLigth 18w 1,320.00 Bh
- Lampu Roset PLE LED 3 W 360.00 Bh
c Fixtures Saklar & Stop Kontak
- Stop Kontak Dinding IPh,10,13-16A 1,140.00 Bh
- Soket Telpon 360.00 Bh
- Soket Data 240.00 Bh
3 BASEMENT 1 (B1)
a Instalasi titik lampu dan stop kontak
- Instalasi Penerangan 3,600.00 Ttk
b Fixtures & Armatures Lampu
- Lampu Flourescent TL 2x36W Pasang Outbow 1,800.00 Bh
- Lampu Flourescent 2xTL-5 35W Pasang inbow 600.00 Bh
- Lampu DownLigth 18w 1,320.00 Bh
- Lampu Roset PLE LED 3 W 360.00 Bh
c Fixtures Saklar & Stop Kontak
- Stop Kontak Dinding IPh,10,13-16A 1,140.00 Bh
- Soket Telpon 360.00 Bh
- Soket Data 240.00 Bh
4 GROUND FLOOR
a Instalasi titik lampu dan stop kontak
- Instalasi Penerangan 160.00 Ttk
b Fixtures & Armatures Lampu
- Lampu Flourescent TL 2x36W Pasang Outbow Bh
- Lampu Flourescent 2xTL-5 35W Pasang inbow 82.00 Bh
- Lampu DownLigth 18w 48.00 Bh
- Lampu Downlith PLE LED 3 W 22.00 Bh
- Lampu Roset PLE LED 3 W 8.00 Bh
c Fixtures Saklar & Stop Kontak
- Stop Kontak Dinding IPh,10,13-16A 78.00 Bh
- Soket Telpon 78.00 Bh
- Soket Data 68.00 Bh
5 UPPER GROUND
a Instalasi titik lampu dan stop kontak
- Instalasi Penerangan 160.00 Ttk
b Fixtures & Armatures Lampu
- Lampu Flourescent TL 2x36W Pasang Outbow Bh
- Lampu Flourescent 2xTL-5 35W Pasang inbow 82.00 Bh
- Lampu DownLigth 18w 48.00 Bh
- Lampu Downlith PLE LED 3 W 22.00 Bh
- Lampu Roset PLE LED 3 W 8.00 Bh
c Fixtures Saklar & Stop Kontak
- Stop Kontak Dinding IPh,10,13-16A 78.00 Bh
- Soket Telpon 78.00 Bh
- Soket Data 68.00 Bh
6 LANTAI 1
a Instalasi titik lampu dan stop kontak
- Instalasi Penerangan 160.00 Ttk
b Fixtures & Armatures Lampu
- Lampu Flourescent TL 2x36W Pasang Outbow Bh
- Lampu Flourescent 2xTL-5 35W Pasang inbow 82.00 Bh
- Lampu DownLigth 18w 48.00 Bh
- Lampu Downlith PLE LED 3 W 22.00 Bh
- Lampu Roset PLE LED 3 W 8.00 Bh
c Fixtures Saklar & Stop Kontak
- Stop Kontak Dinding IPh,10,13-16A 78.00 Bh
- Soket Telpon 78.00 Bh
- Soket Data 68.00 Bh
- Access Point Wireless/Hot Spot 1.00 Bh
7 LANTAI 2
a Instalasi titik lampu dan stop kontak
- Instalasi Penerangan 160.00 Ttk
b Fixtures & Armatures Lampu
- Lampu Flourescent TLD 3x14W Pasang inbow Bh
- Lampu Flourescent 2xTL-5 35W Pasang inbow 82.00 Bh
- Lampu DownLigth 18w 48.00 Bh
- Lampu Downlith PLE LED 3 W 22.00 Bh
- Lampu Roset PLE LED 3 W 8.00 Bh
- Lampu Flourescent TL 1x36W Pasang outbow Bh
c Fixtures Saklar & Stop Kontak 78.00
- Stop Kontak Dinding IPh,10,13-16A 78.00 Bh
- Stop Kontak Ganda 16A 68.00 Bh
- Soket Data GaNda 4.00 Bh
- Access Point Wireless/Hot Spot 2.00 Bh
9 PENANGKAL PETIR
- Air Terminal, System Non Radio Aktif radius 50 m proteksi 1.00 Bh
- Pemasangan tiang pipa GIP. Dia. 2" kaomplit alat penunjang 1.00 Bh
- Cosx cable dia. 70 mm2 & Pipa Conduit Ø 3/4" 240.00 M'
- Instalasi pembumian lengkap dengan elecrtrode pembumian 1.00 Bh
terbuat dari copper rod dia.5/8 " panjang minimal 6 m
- Bak Kontrol (uk. 400 x 400 mm) + Elektroda 1.00 Bh
- Material Bantu 1.00 Lot
0.00
D PEKERJAAN KABEL TRAY UNTUK ARUS KUAT
1 BASEMENT 3
- Ukuran 20 x 10 cm 84.00 M
2 BASEMENT 2
- Ukuran 30 x 10 cm 132.00 M
- Ukuran 20 x 10 cm 52.00 M
3 LANTAI 2
- Ukuran 30 x 10 cm 132.00 M
- Ukuran 20 x 10 cm 52.00 M
4 BASEMENT 1
- Ukuran 30 x 10 cm 132.00 M
- Ukuran 20 x 10 cm 52.00 M
5 GROUND FLOOR
- Ukuran 30 x 10 cm 132.00 M
- Ukuran 20 x 10 cm 52.00 M
6 UPPER GROUND
- Ukuran 30 x 10 cm 132.00 M
- Ukuran 20 x 10 cm 52.00 M
7 LANTAI 1
- Ukuran 30 x 10 cm 132.00 M
- Ukuran 20 x 10 cm 52.00 M
8 LANTAI 2
- Ukuran 30 x 10 cm 132.00 M
- Ukuran 20 x 10 cm 52.00 M
9 LANTAI 3 D/D 24
- Ukuran 30 x 10 cm 2,904.00 M
- Ukuran 20 x 10 cm 1,144.00 M
Jumlah D 0.00
E PEKERJAAN KABEL TRAY UNTUK ARUS LEMAH
1 BASEMENT 3
- Ukuran 20 x 10 cm 84.00 M
2 BASEMENT 2
- Ukuran 70 x 10 cm 32.00 M
- Ukuran 30 x 10 cm 40.00 M
- Ukuran 20 x 10 cm 152.00 M
3 LANTAI 1
- Ukuran 30 x 10 cm 40.00 M
- Ukuran 20 x 10 cm 152.00 M
4 GROUND FLOOR
- Ukuran 30 x 10 cm 40.00 M
- Ukuran 20 x 10 cm 152.00 M
5 LANTAI 1
- Ukuran 30 x 10 cm 40.00 M
- Ukuran 20 x 10 cm 152.00 M
6 LANTAI 1
- Ukuran 30 x 10 cm 40.00 M
- Ukuran 20 x 10 cm 152.00 M
7 LANTAI 1
- Ukuran 30 x 10 cm 40.00 M
- Ukuran 20 x 10 cm 152.00 M
8 LANTAI 1
- Ukuran 30 x 10 cm 40.00 M
- Ukuran 20 x 10 cm 152.00 M
Jumlah E 0.00
II PEKERJAAN TATA UDARA (AC) DAN VENTILASI MEKANIK
A LANTAI BASEMANT 3
I PERALATAN UTAMA
Air Conditioning VRV/VRF Split System c/w remote control, Raf Net &
1
Accessories
Type : FCU
Merk :
Kapasitas : 1 TR /12.000 BTU/H 6.00 Unit
II DUCTING
1 Ducting Exhaus & Fresh Air tanpa isolasi lengkap hangger dll
500 x 400 858.00 m
II DUCTING
1 Ducting Exhaus & Fresh Air tanpa isolasi lengkap hangger dll
500 x 400 858.00 m
II DUCTING
1 Ducting Exhaus & Fresh Air tanpa isolasi lengkap hangger dll
500 x 400 858.00 m
II DUCTING
1 Ducting Exhaus & Fresh Air tanpa isolasi lengkap hangger dll
500 x 400 290.00 m
Ducting Supply & Return Lengkap dengan isolasi luar & dalam glasswool tebal 1" density 24
2
kg/m2,Allumunium foil, penggantung.damper dll
450 x 200 (18x8") 440.00 m
III DIFFUSER DAN GRILLE
- Exhaus Air Grille
Bahan : aluminium
400 x 400 220.00 bh
- Inteake Grille -
300 x 300 19.00 bh
- Fresh Air Grille -
Bahan : aluminium -
30 x 30 220.00 bh
F LANTAI 1
I PERALATAN UTAMA
1 Air Conditioning VRV/VRF Split System c/w remote control, Raf Net &
Type : Wall Mounted-Inverter
Merk :
Kapasitas : 20500BTU/H 120.00 Unit
II DUCTING
1 Ducting Exhaus & Fresh Air tanpa isolasi lengkap hangger dll
500 x 400 260.00 m
Ducting Supply & Return Lengkap dengan isolasi luar & dalam glasswool tebal 1" density 24
2
kg/m2,Allumunium foil, penggantung.damper dll
450 x 200 (18x8") 440.00 m
450 x 150 (18x6") 270.00 m
Ducting Supply & Return Lengkap dengan isolasi luar glasswool tebal 1" density 24
3
kg/m2,Allumunium foil, penggantung.damper dll
4 Flexible duct Ø 20 cm 46.00 m
II DUCTING
1 Ducting Exhaus & Fresh Air tanpa isolasi lengkap hangger dll
500 x 400 260.00 m
Ducting Supply & Return Lengkap dengan isolasi luar & dalam glasswool tebal 1" density 24
2
kg/m2,Allumunium foil, penggantung.damper dll
450 x 200 (18x8") 480.00 m
450 x 150 (18x6") 220.00 m
Ducting Supply & Return Lengkap dengan isolasi luar glasswool tebal 1" density 24
3
kg/m2,Allumunium foil, penggantung.damper dll
4 Flexible duct Ø 20 cm 46.00 m
H LANTAI 3 S/D 2 4
I PERALATAN UTAMA
1 Air Conditioning VRV/VRF Split System c/w remote control, Raf Net &
Type : Cassette 4 way-Inverter
Merk :
Kapasitas : 20500BTU/H 220.00 Unit
II DUCTING
1 Ducting Exhaus & Fresh Air tanpa isolasi lengkap hangger dll
500 x 400 5,720.00 m
Ducting Supply & Return Lengkap dengan isolasi luar & dalam glasswool tebal 1" density 24
2
kg/m2,Allumunium foil, penggantung.damper dll
450 x 200 (18x8") 10,560.00 m
450 x 150 (18x6") 4,840.00 m
Ducting Supply & Return Lengkap dengan isolasi luar glasswool tebal 1" density 24
3
kg/m2,Allumunium foil, penggantung.damper dll
4 Flexible duct Ø 20 cm 1,012.00 m
A PERALATAN UTAMA
1 MAIN PATCH PANEL 5.00 unit
B KABEL PENGHUBUNG
Fiber Optic 2 Core dari Master PATCH Panel ke :
- PATCH Panel 1 280.00 M'
- PATCH Panel 2 560.00 M'
- PATCH Panel 3 280.00 M'
- PATCH Panel 4 560.00 M'
- PATCH Panel 5 840.00 M'
Jumlah B 0.00
C PEKERJAAN INSTALASI DATA
I LANTAI BASEMENT 3
1 Inst.data, kabel UTP category 6+pipa conduit UPVC Ø ¾" 60.00 Ttk
2 Outlet wall type RJ 45 (1 Gang) 60.00 Bh
3 24-port 10/ 100 Ethernet Switch with PoE 100 w, Managed, SFP 5.00 Unit
Linksys AC1200, Access Point AC1200, Dual Band, 1 x Gigabit Ethernet, 802.11b/g/n/ac,
4 5.00 Unit
2.4GHz/5GHz, Up To 1200Mbps, Integrated Power over Ethernet Plus (PoE+)
Linksys AC1200, Access Point AC1200, Dual Band, 1 x Gigabit Ethernet, 802.11b/g/n/ac,
4 5.00 Unit
2.4GHz/5GHz, Up To 1200Mbps, Integrated Power over Ethernet Plus (PoE+)
Linksys AC1200, Access Point AC1200, Dual Band, 1 x Gigabit Ethernet, 802.11b/g/n/ac,
4 5.00 Unit
2.4GHz/5GHz, Up To 1200Mbps, Integrated Power over Ethernet Plus (PoE+)
Linksys AC1200, Access Point AC1200, Dual Band, 1 x Gigabit Ethernet, 802.11b/g/n/ac,
4 5.00 Unit
2.4GHz/5GHz, Up To 1200Mbps, Integrated Power over Ethernet Plus (PoE+)
Linksys AC1200, Access Point AC1200, Dual Band, 1 x Gigabit Ethernet, 802.11b/g/n/ac,
4 5.00 Unit
2.4GHz/5GHz, Up To 1200Mbps, Integrated Power over Ethernet Plus (PoE+)
Linksys AC1200, Access Point AC1200, Dual Band, 1 x Gigabit Ethernet, 802.11b/g/n/ac,
4 5.00 Unit
2.4GHz/5GHz, Up To 1200Mbps, Integrated Power over Ethernet Plus (PoE+)
Linksys AC1200, Access Point AC1200, Dual Band, 1 x Gigabit Ethernet, 802.11b/g/n/ac,
4 5.00 Unit
2.4GHz/5GHz, Up To 1200Mbps, Integrated Power over Ethernet Plus (PoE+)
Linksys AC1200, Access Point AC1200, Dual Band, 1 x Gigabit Ethernet, 802.11b/g/n/ac,
4 110.00 Unit
2.4GHz/5GHz, Up To 1200Mbps, Integrated Power over Ethernet Plus (PoE+)
A PERALATAN UTAMA
1 Mixer Pre Amplifier, 120W/220V/1Ph 1.00 Unit
2 Power Amplifier, 3x240W/220V/1Ph/50 Hz 1.00 Unit
3 Power Amplifier, 3x240W/220V/1Ph/50 Hz (Paging) 1.00 Unit
4 Voice Alarm Controller 1.00 Unit
5 Voice Alarm Router 1.00 Unit
6 MDF-SS, 100 Pairs 1.00 Unit
7 Speaker Selector 5 Zone 1.00 Unit
8 Compact Disk MP3/MP4 Player 1.00 Unit
9 Radio Tuner AM/FM + Antenna 1.00 Unit
10 Paging Microphone 1.00 Unit
11 Emergency Microphone 1.00 Unit
12 Rak kabinet beserta aksesoris 1.00 Unit
13 Ni-cat Battery 4 jam 1.00 Unit
14 Surge Arrester 1.00 Unit
Jumlah A 0.00
B PEKERJAAN KABEL FEEDER
Menggunakan kabel NYMHY, termasuk konduit PVC,
klem, soket dan aksesoris.
1 BASEMENT 3
a. Junction Box 2 (JB-SB) 6.00 Bh
b. Instalasi
- Instalasi horn loud Speaker ( Emergency ) 30.00 Ttk
c. Fixtures
- Ceiling Speaker 3 Watt ( Normal) 12.00 Bh
- Horn Loud Speaker 6 Watt ( Di dinding) 18.00 Bh
Jumlah C-3 0.00
2 BASEMENT 2
a. Junction Box 2 (JB-SB) 6.00 Bh
b. Instalasi
- Instalasi horn loud Speaker ( Emergency ) 30.00 Ttk
c. Fixtures
- Ceiling Speaker 3 Watt ( Normal) 12.00 Bh
- Horn Loud Speaker 6 Watt ( Di dinding) 18.00 Bh
Jumlah C-2 0.00
3 BASEMENT 1
a. Junction Box 2 (JB-SB) 6.00 Bh
b. Instalasi
- Instalasi horn loud Speaker ( Emergency ) 30.00 Ttk
c. Fixtures
- Ceiling Speaker 3 Watt ( Normal) 12.00 Bh
- Horn Loud Speaker 6 Watt ( Di dinding) 18.00 Bh
Jumlah C-1 0.00
4 GROUND FLOOR
a. Junction Box 4 (JB-SS.LT1) 6.00 Bh
b. Instalasi
- Instalasi Ceiling Speaker ( Normal ) 78.00 Ttk
- Instalasi horn loud Speaker ( Emergency ) Ttk
- Instalasi Ceiling Speaker ( Normal ) Ttk
c. Fixtures
- Ceiling Speaker 3 Watt ( Emergency) 97.00 Bh
Jumlah C-2 0.00
5 UPPER GROUND
a. Junctionl Box 5 (JB-SS.LT2) 6.00 Bh
b. Instalasi -
Instalasi Ceiling Speaker ( Normal ) 80.00 Ttk
Instalasi horn loud Speaker ( Emergency ) Ttk
c. Fixtures -
Ceiling Speaker 3 Watt ( Normal) 80.00 Bh
Horn Loud Speaker 15 Watt ( Emergency) Bh
- Jumlah C- 3 0.00
6 LANTAI 1
a. Junction Box 5 (JB-SS.LT3) 2.00 Bh
b. Instalasi
Instalasi Ceiling Speaker ( Normal ) 50.00 Ttk
Instalasi horn loud Speaker ( Emergency ) Ttk
c. Fixtures
Ceiling Speaker 3 Watt ( Normal) 50.00 Bh
Horn Loud Speaker 15 Watt ( Emergency) Bh
Jumlah C-4 0.00
7 LANTAI 2
a. Junction Box 5 (JB-SS.LT4) 6.00 Bh
b. Instalasi -
Ceiling Speaker 3 Watt ( Normal) 80.00 Ttk
Instalasi horn loud Speaker ( Emergency ) Ttk
c. Fixtures
Ceiling Speaker 3 Watt ( Normal) 80.00 Bh
Horn Loud Speaker 15 Watt ( Emergency) Bh
Jumlah C-5 0.00
8 LANTAI 3 S/D 24
a. Junction Box 5 (JB-SS.LT4) 132.00 Bh
b. Instalasi -
Ceiling Speaker 3 Watt ( Normal) 1,760.00 Ttk
Instalasi horn loud Speaker ( Emergency ) Ttk
c. Fixtures
Ceiling Speaker 3 Watt ( Normal) 1,760.00 Bh
Horn Loud Speaker 15 Watt ( Emergency) Bh
Jumlah C-5 0.00
a. Dari MCFA ke :
- Announciator di R.Receptionist,STP AWG 18,1 Pair di Lt.1 20.00 M
b. Kabel Distribusi dari MCFA ke :
- Central Fire Alarm ke Sistem Tata Suara 1.00 Ttk
- Central Fire Alarm ke Panel Kontrol Pompa 1.00 Ttk
- Central Fire Alarm ke Panel Kontrol Pressurized Fan 1.00 Ttk
- Central Fire Alarm ke Panel Kontrol AC 1.00 Ttk
Central Fire Alarm ke DPK 1.00 Ttk
c. Kabel dari MCFA ke :
- FA - BSM FRC 2 x 2.5 mm 40.00 M
- FA - LT 1 FRC 2 x 2.5 mm 20.00 M
- FA - LT 2 FRC 2 x 2.5 mm 40.00 M
- FA - LT 3 FRC 2 x 2.5 mm 60.00 M
- FA - LT 4 FRC 2 x 2.5 mm 100.00 M
d. Pentanahan Menggunakan Tembaga Massif Dengan 1.00 Lot
Kedalaman Minimum 12 M, Maksimum Tahanan Yang dikehendaki
- Kabel NYA 50 mm² 1,000.00 M
- Test Link 1.00 Bh
Jumlah B 0.00
C PEKERJAAN INSTALASI & FIXTURES
1 Basement 3
a. Instalasi
- Instalasi Smoke Detector 25.00 Ttk
- Instalasi Heat Detector 32.00 Ttk
- Instalasi Manual Call Point 8.00 Ttk
- Instalasi Indicator Lamp 8.00 Ttk
- Instalasi Flow Switch 8.00 Ttk
- Instalasi Fireman Telephone 8.00 Ttk
b. Fixtures
- Optical Smoke Detector,Addressible c/w Base 25.00 Bh
- Optical Heat Detector,Rate Of Rase Type 32.00 Bh
- Alarm Bell 8.00 Bh
- Indicator Lamp 8.00 Bh
- Manual Call Point 8.00 Bh
- Jack + Fireman Telephone 8.00 Bh
- End of line resistance 1.00 Bh
- Panel Kontrol Fire Alarm 1.00 Bh
Jumlah C- 0.00
2 Basement 2
a. Instalasi
- Instalasi Smoke Detector 25.00 Ttk
- Instalasi Heat Detector 32.00 Ttk
- Instalasi Manual Call Point 8.00 Ttk
- Instalasi Indicator Lamp 8.00 Ttk
- Instalasi Flow Switch 8.00 Ttk
- Instalasi Fireman Telephone 8.00 Ttk
b. Fixtures
- Optical Smoke Detector,Addressible c/w Base 25.00 Bh
- Optical Heat Detector,Rate Of Rase Type 32.00 Bh
- Alarm Bell 8.00 Bh
- Indicator Lamp 8.00 Bh
- Manual Call Point 8.00 Bh
- Jack + Fireman Telephone 8.00 Bh
- End of line resistance 1.00 Bh
- Panel Kontrol Fire Alarm 1.00 Bh
Jumlah C- 0.00
3 Basement 1
a. Instalasi
- Instalasi Smoke Detector 25.00 Ttk
- Instalasi Heat Detector 32.00 Ttk
- Instalasi Manual Call Point 8.00 Ttk
- Instalasi Indicator Lamp 8.00 Ttk
- Instalasi Flow Switch 8.00 Ttk
- Instalasi Fireman Telephone 8.00 Ttk
b. Fixtures
- Optical Smoke Detector,Addressible c/w Base 25.00 Bh
- Optical Heat Detector,Rate Of Rase Type 32.00 Bh
- Alarm Bell 8.00 Bh
- Indicator Lamp 8.00 Bh
- Manual Call Point 8.00 Bh
- Jack + Fireman Telephone 8.00 Bh
- End of line resistance 1.00 Bh
- Panel Kontrol Fire Alarm 1.00 Bh
Jumlah C-
0.00
3
4 GROUND FLOOR
a Instalasi
- Instalasi Smoke Detector 40.00 Ttk
- Instalasi Heat Detector - Ttk
- Instalasi Manual Call Point 8.00 Ttk
- Instalasi Indicator Lamp 8.00 Ttk
- Instalasi Flow Switch 8.00 Ttk
- Instalasi Fireman Telephone 8.00 Ttk
b Fixtures
- Optical Smoke Detector,Addressible c/w Base 40.00 Bh
- Optical Heat Detector,Rate Of Rase Type - Bh
- Alarm Bell 8.00 Bh
- Indicator Lamp 8.00 Bh
- Manual Call Point 8.00 Bh
- Jack + Fireman Telephone 8.00 Bh
- End of line resistance 1.00 Bh
- Panel Kontrol Fire Alarm 1.00 Bh
Jumlah C- 0.00
5 UPPER GROUND
a Instalasi
- Instalasi Smoke Detector 40.00 Ttk
- Instalasi Heat Detector - Ttk
- Instalasi Manual Call Point 8.00 Ttk
- Instalasi Indicator Lamp 8.00 Ttk
- Instalasi Flow Switch 8.00 Ttk
- Instalasi Fireman Telephone 8.00 Ttk
b Fixtures
- Optical Smoke Detector,Addressible c/w Base 40.00 Bh
- Optical Heat Detector,Rate Of Rase Type - Bh
- Alarm Bell 8.00 Bh
- Indicator Lamp 8.00 Bh
- Manual Call Point 8.00 Bh
- Jack + Fireman Telephone 8.00 Bh
- End of line resistance 1.00 Bh
- Panel Kontrol Fire Alarm 1.00 Bh
Jumlah C- 0.00
6 Lantai 1
a Instalasi
- Instalasi Smoke Detector 40.00 Ttk
- Instalasi Heat Detector - Ttk
- Instalasi Manual Call Point 8.00 Ttk
- Instalasi Indicator Lamp 8.00 Ttk
- Instalasi Flow Switch 8.00 Ttk
- Instalasi Fireman Telephone 8.00 Ttk
b Fixtures
- Optical Smoke Detector,Addressible c/w Base 40.00 Bh
- Optical Heat Detector,Rate Of Rase Type - Bh
- Alarm Bell 8.00 Bh
- Indicator Lamp 8.00 Bh
- Manual Call Point 8.00 Bh
- Jack + Fireman Telephone 8.00 Bh
- End of line resistance 1.00 Bh
- Panel Kontrol Fire Alarm 1.00 Bh
Jumlah C- 4 0.00
7 Lantai 2
a Instalasi
- Instalasi Smoke Detector 40.00 Ttk
- Instalasi Heat Detector - Ttk
- Instalasi Manual Call Point 8.00 Ttk
- Instalasi Indicator Lamp 8.00 Ttk
- Instalasi Flow Switch 8.00 Ttk
- Instalasi Fireman Telephone 8.00 Ttk
b Fixtures
- Optical Smoke Detector,Addressible c/w Base 40.00 Bh
- Optical Heat Detector,Rate Of Rase Type - Bh
- Alarm Bell 8.00 Bh
- Indicator Lamp 8.00 Bh
- Manual Call Point 8.00 Bh
- Jack + Fireman Telephone 8.00 Bh
- End of line resistance 1.00 Bh
- Panel Kontrol Fire Alarm 1.00 Bh
Jumlah C- 0.00
8 Lantai 3 S/D Lantai 23
a Instalasi
- Instalasi Smoke Detector 880.00 Ttk
- Instalasi Heat Detector - Ttk
- Instalasi Manual Call Point 176.00 Ttk
- Instalasi Indicator Lamp 176.00 Ttk
- Instalasi Flow Switch 176.00 Ttk
- Instalasi Fireman Telephone 176.00 Ttk
b Fixtures
- Optical Smoke Detector,Addressible c/w Base 880.00 Bh
- Optical Heat Detector,Rate Of Rase Type - Bh
- Alarm Bell 176.00 Bh
- Indicator Lamp 176.00 Bh
- Manual Call Point 176.00 Bh
- Jack + Fireman Telephone 176.00 Bh
- End of line resistance 1.00 Bh
- Panel Kontrol Fire Alarm 1.00 Bh
4 Pengadaan dan pemasangan sistem netral unit genset 1 & 2 1.00 Lot
dan pentanahan genset termasuk kabel NYA 240 mm² lengkap
dengan pvc cables, earth bar, test clamp, earthing pits, klem
pipa bak kontrol + tutup beserta perlengkapan lainnya. Tahanan
pentanahan yang diperbolehkan maksimal sebesar 2 Ohm.
12 Pengadaan Bahan Bakar Minyak jenis Solar pada saat 80.00 Ltr
penyerahan pekerjaan.
15 Louvre
- Intake Louvre : 7.000 (L) x 1.800 (W) mm 4.00 Bh
- Exhaust Louvre : 1.500 (L) x 2.000 (W) mm 4.00 Bh
- Exhaust Louvre : 1.000 (L) x 1.400 (W) mm 4.00 Bh
HARGA SATUAN
NO URAIAN PEKERJAAN VOL SAT JUMLAH (RP.)
(RP.)
F PEKERJAAN INFRASTRUKTUR