Barang
Jasa
III. Manajemen Proyek dan Perekayasaan 358,966,595.52 358,966,595.52 10.00 10.00 10.00
IV. Alat Kerja / Fasilitas Kerja 646,139,871.93 646,139,871.93 18.00 18.00 18.00
DIBULATKAN 3,589,665,000.00
Terbilang tiga milyar lima ratus delapan puluh sembilan juta enam ratus enam puluh lima ribu rupiah
Formulasi Perhitungan
1,938,419,615.80 54% PT. ISTANA PERSAHABATAN TIMUR
3,589,665,955.18
% TKDN Gabungan Barang dan Jasa
+
=
1,651,246,339.38 46%
3,589,665,955.18 MANARSAR PANJAITAN
100% Direktur Utama
BAR CHART
II. PEKERJAAN BANGUNAN 327,078,145.68 9.112 1.519 1.519 1.519 1.519 1.519 1.519
1.PEKERJAAN STRUKTUR LT. 1 1,181,229,473.66 32.906 4.113 4.113 4.113 4.113 4.113 4.113 4.113 4.113
2.PEKERJAAN ARSITEKTUR LT 1 753,766,429.50 20.998 2.100 2.100 2.100 2.100 2.100 2.100 2.100 2.100 2.100 2.100
3.PEKERJAAN MEKANIKAL & ELEKTRIKAL LT. 1 46,176,687.00 1.286 0.257 0.257 0.257 0.257 0.257
1.PEKERJAAN STRUKTUR LT. 2 192,413,199.99 5.360 0.766 0.766 0.766 0.766 0.766 0.766 0.766
2.PEKERJAAN ARSITEKTUR LT 2 720,479,247.85 20.071 2.230 2.230 2.230 2.230 2.230 2.230 2.230 2.230 2.230
3.PEKERJAAN MEKANIKAL & ELEKTRIKAL LT.2 44,502,380.00 1.240 0.207 0.207 0.207 0.207 0.207 0.207
RENCANA BOBOT PER MINGGU 0.233 0.233 1.752 1.752 1.519 1.519 5.632 5.632 4.113 4.113 6.979 6.979 6.979 6.979 2.866 0.766 6.596 5.831 5.831 5.831 6.037 2.694 2.694 2.694 2.989 0.759
KOMULATIF RENCANA 0.233 0.466 2.218 3.970 5.489 7.007 ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
MANARSAR PANJAITAN
Direktur
KURVA S
II. PEKERJAAN BANGUNAN 327,078,145.68 9.112 1.519 1.519 1.519 1.519 1.519 1.519
1.PEKERJAAN STRUKTUR LT. 1 1,181,229,473.66 32.906 4.113 4.113 4.113 4.113 4.113 4.113 4.113 4.113
2.PEKERJAAN ARSITEKTUR LT 1 753,766,429.50 20.998 2.100 2.100 2.100 2.100 2.100 2.100 2.100 2.100 2.100 2.100
3.PEKERJAAN MEKANIKAL & ELEKTRIKAL LT. 1 46,176,687.00 1.286 0.257 0.257 0.257 0.257 0.257
1.PEKERJAAN STRUKTUR LT. 2 192,413,199.99 5.360 0.766 0.766 0.766 0.766 0.766 0.766 0.766
2.PEKERJAAN ARSITEKTUR LT 2 720,479,247.85 20.071 2.230 2.230 2.230 2.230 2.230 2.230 2.230 2.230 2.230
3.PEKERJAAN MEKANIKAL & ELEKTRIKAL LT.2 44,502,380.00 1.240 0.207 0.207 0.207 0.207 0.207 0.207
RENCANA BOBOT PER MINGGU 0.233 0.233 1.752 1.752 1.519 1.519 5.632 5.632 4.113 4.113 6.979 6.979 6.979 6.979 2.866 0.766 6.596 5.831 5.831 5.831 6.037 2.694 2.694 2.694 2.989 0.759
KOMULATIF RENCANA 0.233 0.466 2.218 3.970 5.489 7.007 ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
MANARSAR PANJAITAN
Direktur
REKAPITULASI HARGA PENAWARAN
1 2 3
JUMLAH 3,589,665,955.18
PPN 10% 358,966,595.52
TOTAL 3,948,632,550.70
PEMBULATAN 3,948,632,000.00
Tiga Milyar Sembilan Ratus Empat Puluh Delapan Juta Enam Ratus Tiga
TERBILANG :
Puluh Dua Ribu Rupiah
MANARSAR PANJAITAN
Direktur
RENCANA ANGGARAN BIAYA (RAB)
HARGA SAT.
NO. URAIAN PEKERJAAN VOL. SAT. JUMLAH (Rp)
(Rp)
1 2 3 4 5 6=3X5
I. PEKERJAAN PERSIAPAN
1. Papan Nama Proyek 1.00 buah 303,371.00 303,371.00
2. Penyediaan Direksikeet / Gudang 12.00 m2 369,196.00 4,430,352.00
3. Pembersihan Lahan 680.00 m2 4,600.00 3,128,000.00
4. Administrasi Proyek 1.00 ls 7,500,000.00 7,500,000.00
5. Pengadaan Listrik dan Air Kerja 6.00 bln 1,500,000.00 9,000,000.00
6. Penyambungan daya listrik baru 2,200.00 VA 1,603.00 3,526,600.00
7 Pas. Bouwplank 162.50 m1 34,440.00 5,596,500.00
33,484,823.00
II. PEKERJAAN BANGUNAN
1 Pondasi Batu Kali
- Galian Tanah Biasa Kedalaman 12 m - 23 m 20.22 m3 125,000.00 2,527,500.00
- Urugan Dengan Pasir Urug 1.01 m3 264,850.00 267,498.50
- Pondasi Btu Kali ad. 1 : 5 3.79 m3 802,244.00 3,040,504.76
2 Pondasi Tapak P1
- Galian Tanah Biasa Kedalaman 2 m - 3 m 208.01 m3 80,155.00 16,673,041.55
- Urugan Dengan Pasir Urug 4.84 m3 264,850.00 1,281,874.00
- Lantai Kerja, Mutu fc = 7,4 Mps ( K-100 ) 4.84 m3 890,684.00 4,310,910.56
- Pondasi Tapak/Setempat K.225 4.84 m3 3,715,878.00 17,984,849.52
- Urugan Tanah Kembali 184.21 m3 21,850.00 4,024,988.50
3 Pondasi Tapak P2
- Galian Tanah Biasa Kedalaman 1 m - 2 m 52.27 m3 67,275.00 3,516,464.25
- Urugan Dengan Pasir Urug 4.84 m3 264,850.00 1,281,874.00
- Lantai Kerja, Mutu fc = 7,4 Mps ( K-100 ) 4.84 m3 890,684.00 4,310,910.56
- Pondasi Tapak/Setempat K.225 4.84 m3 3,715,878.00 17,984,849.52
- Urugan Tanah Kembali 35.19 m3 21,850.00 768,901.50
4 Pondasi Tapak P3
- Galian Tanah Biasa Kedalaman 1 m - 2 m 19.80 m3 67,275.00 1,332,045.00
- Urugan Dengan Pasir Urug 4.84 m3 264,850.00 1,281,874.00
- Lantai Kerja, Mutu fc = 7,4 Mps ( K-100 ) 4.84 m3 890,684.00 4,310,910.56
- Pondasi Tapak/Setempat K.225 4.84 m3 3,715,878.00 17,984,849.52
- Urugan Tanah Kembali 3.88 m3 3,715,878.00 14,417,606.64
5 Kolom pedestal K1 30 x 40 K.225 9.29 m3 5,085,574.00 47,244,982.46
6 Kolom pedestal K2 30 x 30 K.225 2.57 m3 5,085,574.00 13,069,925.18
7 Kolom pedestal K3 15 x 30 K.225 1.40 m3 4,617,854.00 6,464,995.60
8 Sloof Beton 25 x 40 - K.225 24.32 m3 4,771,364.00 116,039,572.48
9 Sloof Beton 20 x 25 - K.225 4.97 m3 4,454,354.00 22,138,139.38
10 Sloof Beton 15 x 20 - K.225 1.01 m3 4,771,364.00 4,819,077.64
327,078,145.68
III. PEKERJAAN LANTAI 1
A. PEKERJAAN STRUKTUR
1.Kolom Beton K1 30 x 40 - K.225 19.61 m3 5,085,574.00 99,728,106.14
2.Kolom Beton K2 30 x 30 - K.225 7.52 m3 5,085,574.00 38,243,516.48
3.Kolom Beton K3 15 x 30 - K.225 4.10 m3 4,617,854.00 18,933,201.40
4.Kolom Beton KP 11 x 11 - K.175 2.39 m3 3,896,548.00 9,312,749.72
5. Balok Beton 25 x 60 - K.225 22.05 m3 6,017,223.00 132,679,767.15
6. Balok Beton 25 x 40 - K.225 29.76 m3 5,381,963.00 160,167,218.88
HARGA SAT.
NO. URAIAN PEKERJAAN VOL. SAT. JUMLAH (Rp)
(Rp)
1 2 3 4 5 6=3X5
7. Balok Beton 25 x 35 - K.225 5.60 m3 5,381,963.00 30,138,992.80
8. Canopy Beton (Canopy depan Kelas)- K.225 5.04 m3 3,826,757.00 19,286,855.28
9. Canopy Beton (Canopy Belakang Kelas) - K.225 5.99 m3 3,826,757.00 22,922,274.43
10. Balok Beton Praktis di Atas Kusen Alum. Mutu Beton - K. 1.36 m3 3,545,758.00 4,822,230.88
11. Plat Lantai Beton t = 12 cm - K.225 65.41 m3 8,823,455.00 577,142,191.55
12. Tangga beton - K. 225 7.69 m3 8,823,455.00 67,852,368.95
1,181,229,473.66
B. PEKERJAAN ARSITEKTUR
- Pekerjaan pasangan dinding
1. Pas. Dinding bata ringan (10.20.60) ad. 1:5 787.88 m2 122,163.00 96,249,784.44
2. Plesteran dinding ad. 1:5 1,417.49 m2 49,161.00 69,685,225.89
3. Plesteran dan acian kolom dan balok ad. 1:3 298.30 m2 52,336.00 15,611,828.80
4. Pas. Dinding Roster 13.84 m2 85,000.00 1,176,400.00
5. Rabat beton t = 7 cm 149.49 m2 56,289.00 8,414,642.61
6. Pasangan dinding Batu Candi Teras Depan 29.08 m2 135,000.00 3,925,800.00
7. Pek. Pasangan ACP 46.42 m2 225,000.00 10,444,500.00
8. Pek. Pasangan Huruf Alumunium 20 cm 25.00 huruf 25,000.00 625,000.00
- Pekerjaan kusen pintu dan jendela
1. Kusen P1 kamper samarinda 0.41 m3 12,959,616.00 5,313,442.56
2. Kusen P3 kamper samarinda 0.10 m3 12,959,616.00 1,295,961.60
3. Kusen P4 kamper samarinda 0.20 m3 12,959,616.00 2,591,923.20
4 Pintu Jendela Kaca PJ1 1.00 Unit 2,500,000.00 2,500,000.00
5 Daun pintu panel kayu kamper samarinda 26.46 m2 1,520,398.00 40,229,731.08
6 Kusen jendela aluminium Coated Black ( Pabrikasi )
- J1 48.00 buah 2,164,060.00 103,874,880.00
- BV1 5.00 buah 572,028.00 2,860,140.00
- BV2 4.00 buah 822,290.00 3,289,160.00
6. Pintu KM/WC PVC 5.00 buah 280,900.00 1,404,500.00
- Pekerjaan kunci dan aksesories pintu jendela
1.Engsel Pintu 4" stainless steel 42.00 buah 52,317.00 2,197,314.00
2.Kunci double slaag 14.00 buah 303,300.00 4,246,200.00
- Pekerjaan pasangan plafond
1. Plafond Acoustic Gyptile 9 mm + Rangka Main Tee & Cros 321.61 m2 165,000.00 53,065,650.00
2. Plafond Gypsum Rangka Hollow (Selasar & KM) 234.85 m2 134,382.00 31,559,612.70
3. Plafond GRC t = 6 mm 141.19 m2 139,350.00 19,674,826.50
4. List Plafond Gypsum 7 cm 147.20 m1 29,237.00 4,303,686.40
5. List Plafond Kayu Kamper 5 cm 147.20 m1 71,657.00 10,547,910.40
- Pekerjaan pasangan keramik
1. Lapisan Pasir Urug dibawah Lantai t = 5 cm 29.89 m3 264,850.00 7,916,366.50
2. Lantai Kerja dibawah Lantai t = 3 cm 17.94 m3 890,684.00 15,978,870.96
3. Pas. Keramik Lantai 40 x 40, ad. 1 : 3 321.61 m2 111,588.00 35,887,816.68
4. Pas. Keramik Lantai 40 x 40 ad. 1 : 3 296.74 m2 111,588.00 33,112,623.12
5. Pas. Keramik Lantai 20 x 20 ad. 1 : 3 KM/WC 18.12 m2 112,113.00 2,031,487.56
6. Pas. Keramik Dinding 20 x 25 ad. 1 : 3 158.28 m2 124,781.00 19,750,336.68
7. Pas. Step Noising Tangga 77.70 m1 -
- Pekerjaan finishing
1. Pengecatan Dinding Luar Setara Dulux Weathershield 980.35 m2 64,453.00 63,186,498.55
2.Pengecatan Dinding Dalam Setara Dulux 893.71 m2 57,873.00 51,721,678.83
3.Pengecatan Plafond GRC Setara Jotun 141.19 m2 62,373.00 8,806,443.87
4. Pengecatan Plafond Gypsum 234.85 m2 62,373.00 14,648,299.05
5. Pengecatan List Plafond Kayu 29.44 m2 62,373.00 1,836,261.12
6. Pengecatan Kusen Pintu 60.42 m2 62,920.00 3,801,626.40
753,766,429.50
HARGA SAT.
NO. URAIAN PEKERJAAN VOL. SAT. JUMLAH (Rp)
(Rp)
1 2 3 4 5 6=3X5
C. PEKERJAAN MEKANIKAL & ELEKTRIKAL
- Pekerjaan Sanitair
1. Pompa Air Jet Pump Automatic + Instalasi dan Pengebora 1.00 unit 3,861,292.00 3,861,292.00
2. Pipa PVC AW Ǿ 1/2" ( Dari Pompa ke Rooftank ) 15.00 m1 41,170.00 617,550.00
3. Pipa PVC AW Ǿ 3/4" ( Dari Rooftank ke Kran Air ) 70.00 m1 43,370.00 3,035,900.00
4. Pipa PVC Class D Ǿ 4" ( Dari Kloset ke Septictank ) 30.00 m1 91,009.00 2,730,270.00
5. Pipa PVC Class AW Ǿ 3" ( Dari Floor Drain) 30.00 m1 79,690.00 2,390,700.00
6. Kloset Jongkok KM/WC 4.00 buah 329,570.00 1,318,280.00
7. Kloset Duduk 1.00 buah 2,577,780.00 2,577,780.00
8. Kran Dinding Stainless Ǿ 1/2 " 6.00 buah 36,280.00 217,680.00
9. Washtafel + Kran + Accessories 3.00 buah 1,562,100.00 4,686,300.00
10. Floor Drain Stainless Setara TOTO 7.00 buah 173,045.00 1,211,315.00
11. Urinoir Setara TOTO 2.00 buah 2,246,500.00 4,493,000.00
12. Pembuatan Septictank + Rembesan 1.00 buah 3,739,884.00 3,739,884.00
- Pekerjaan Elektrikal
1.Instalasi Titik Penerangan 48.00 titik 107,502.00 5,160,096.00
2.Instalasi Titik Stop Kontak 10.00 titik 107,502.00 1,075,020.00
3.Pasangan Lampu TKI 2 x 36 watt TKI ( Inbouw ) 30.00 buah 127,340.00 3,820,200.00
4.Lampu bared 40 watt setara philips 20.00 buah 151,971.00 3,039,420.00
5.Pasangan Stop Kontak 10.00 buah 46,975.00 469,750.00
6.Pasangan Saklar Tunggal 8.00 buah 46,175.00 369,400.00
7.Pasangan Saklar Ganda 10.00 buah 51,275.00 512,750.00
8.Box Panel + Isi MCB 32 Ampere 1.00 buah 850,100.00 850,100.00
46,176,687.00
IV. PEKERJAAN LANTAI 2
A. PEKERJAAN STRUKTUR
1. Kolom Beton K1 25/25 - K.225 12.60 m3 4,407,380.00 55,532,988.00
2. Kolom Beton K3 15/30 - K.225 1.70 m3 4,617,854.00 7,850,351.80
3. Kolom Beton KP 15/15 - K.175 3.69 m3 3,896,548.00 14,378,262.12
4. Ring Balok Beton 15 x 25 - K.225 5.64 m3 4,617,854.00 26,044,696.56
5. Ring Balok Beton 15 x 20 - K.225 6.05 m3 4,285,609.00 25,927,934.45
6. Balok Beton Praktis di Atas Kusen Alum. - K.175 4.16 m3 3,896,548.00 16,209,639.68
7. Balok & Canopy Beton 15 x 20 (Canopy Depan) - K.225 6.67 m3 4,285,609.00 28,585,012.03
8. Ring Balk Selasar 15/15 - K.175 1.35 m3 4,424,186.00 5,972,651.10
9. Plat Lantai dan Dak Beton t = 12 cm -K.225 1.35 m3 8,823,455.00 11,911,664.25
192,413,199.99
B. PEKERJAAN ARSITEKTUR
- Pekerjaan pasangan dinding
1. Pas. Dinding bata ringan (10.20.60) ad. 1:5 735.73 m2 122,163.00 89,878,983.99
2. Plesteran dinding ad. 1:5 1,313.19 m2 49,161.00 64,557,733.59
3. Plesteran dan acian kolom dan balok ad. 1:3 358.35 m2 52,336.00 18,754,605.60
4. Pas. Dinding Roster 15.12 m2 85,000.00 1,285,200.00
- Pekerjaan kusen pintu jendela dan kaca
1. Kusen P1 kayu kamper samarinda 0.46 m3 12,959,616.00 5,961,423.36
2. Kusen P3 kayu kamper samarinda 0.10 m3 12,959,616.00 1,295,961.60
3. Kusen P4 kayu kamper samarinda 0.20 m3 12,959,616.00 2,591,923.20
4. Daun pintu panel kayu kamper samarinda 28.35 m2 1,520,398.00 43,103,283.30
5.Kusen jendela aluminium Coated Black ( Pabrikasi )
- J1 53.00 buah 2,164,060.00 114,695,180.00
- BV1 5.00 buah 572,028.00 2,860,140.00
- BV2 4.00 buah 822,290.00 3,289,160.00
6.Pintu KM/WC PVC 5.00 buah 280,900.00 1,404,500.00
- Pekerjaan kunci dan aksesories pintu jendela
HARGA SAT.
NO. URAIAN PEKERJAAN VOL. SAT. JUMLAH (Rp)
(Rp)
1 2 3 4 5 6=3X5
1.Engsel pintu nilon 4" 45.00 buah 52,317.00 2,354,265.00
2.Kunci double slaag 15.00 buah 303,300.00 4,549,500.00
- Pekerjaan pasangan plafond
1. Plafond Acoustic Gyptile 9 mm + Rangka Main Tee & Cros 414.43 m2 165,000.00 68,380,950.00
2. Plafond Gypsum Rangka Hollow (Selasar & KM) 212.87 m2 134,382.00 28,605,896.34
3. List Plafond Kayu Kamper 5 cm 439.43 m1 71,657.00 31,488,235.51
- Pekerjaan pasangan keramik
1. Lantai Kerja dibawah Lantai t = 3 cm 17.98 m3 890,684.00 16,014,498.32
2. Pas. Keramik Lantai 40 x 40, ad. 1 : 3 414.43 m2 111,588.00 46,245,414.84
3. Lantai keramik Selasar & tangga 40x40 cm Kw.1 184.82 m2 111,588.00 20,623,694.16
4. Pas. Keramik Lantai 20 x 20 ad. 1 : 3 KM/WC 18.12 m2 112,113.00 2,031,487.56
5. Pas. Keramik Dinding 20 x 25 ad. 1 : 3 158.28 m2 124,781.00 19,750,336.68
- Pekerjaan finishing
1.Pengecatan Dinding Luar Setara Dulux Weathershield 1,034.23 m2 64,453.00 66,659,226.19
2.Pengecatan Dinding Dalam Setara Dulux 795.58 m2 57,873.00 46,042,601.34
3.Pengecatan Listplank GRC 51.83 m2 62,373.00 3,232,792.59
4.Pengecatan List Plafond Kayu 43.94 m2 62,373.00 2,740,669.62
5.Pengecatan Kusen dan Daun Pintu Melamik 64.74 m2 70,769.00 4,581,585.06
- Pekerjaan Lain-lain
1. Mobilisasi Lantai 2 1.00 ls 7,500,000.00 7,500,000.00
720,479,247.85
C. PEKERJAAN MEKANIKAL & ELEKTRIKAL
- Pekerjaan Sanitair
1.Pipa PVC AW Ǿ 3/4" ( Dari Rooftank ke Kran Air ) 60.00 m1 43,370.00 2,602,200.00
2.Pipa PVC Class D Ǿ 4" ( Dari Kloset ke Septictank ) 30.00 m1 91,009.00 2,730,270.00
3.Pipa PVC Class AW Ǿ 3" ( Dari Floor Drain) 40.00 m1 79,690.00 3,187,600.00
4.Kloset Jongkok KM/WC 4.00 buah 329,570.00 1,318,280.00
5.Kloset Duduk 1.00 buah 2,577,780.00 2,577,780.00
6.Kran Dinding Stainless Ǿ 1/2 " 6.00 buah 36,280.00 217,680.00
7.Washtafel + Kran + Accessories 3.00 buah 1,562,100.00 4,686,300.00
8.Floor Drain Stainless Setara TOTO 7.00 buah 173,045.00 1,211,315.00
9.Urinoir Setara TOTO 2.00 buah 2,246,500.00 4,493,000.00
- Pekerjaan Elektrikal
1.Instalasi Titik Penerangan 52.00 titik 107,502.00 5,590,104.00
2.Instalasi Titik Stop Kontak 10.00 titik 107,502.00 1,075,020.00
3.Pasangan Lampu TKI 2 x 36 watt TKI ( Inbouw ) 31.00 buah 127,340.00 3,947,540.00
4.Lampu bared 40 watt setara philips 21.00 buah 151,971.00 3,191,391.00
5.Pasangan Stop Kontak 10.00 buah 46,975.00 469,750.00
6.Pasangan Saklar Tunggal 6.00 buah 46,175.00 277,050.00
7.Pasangan Saklar Ganda 10.00 buah 51,275.00 512,750.00
8.Box Panel + Isi MCB 32 Ampere 40X60 cm2 1.00 buah 850,100.00 850,100.00
9.Penangkal petir lengkap terpasang 3.00 titik 1,504,750.00 4,514,250.00
10.Bak Kontrol 60x60x40 3.00 titik 350,000.00 1,050,000.00
44,502,380.00
V. PEKERJAAN ATAP
1.Kuda-kuda rangka Baja Ringan Zinc Alume 689.91 m2 165,000.00 113,835,150.00
689.91
2.Genteng Metal Berpasir tebal: 0,35 mm + Alumunium Foil + Roofme m2 216,191.00 149,152,332.81
3.Nok Atap Metal Berpasir 49.82 m1 65,946.00 3,285,429.72
4.Listplank GRC t = 12 mm Profil susun lebar 30 cm 138.75 m1 22,190.00 3,078,862.50
269,351,775.03
VI. PEKERJAAN SARANA LUAR
1. Saluran Buis Beton 1/2 Ǿ 20 cm, Keliling Bangunan 181.23 m1 116,889.00 21,183,793.47
21,183,793.47
HARGA SAT.
NO. URAIAN PEKERJAAN VOL. SAT. JUMLAH (Rp)
(Rp)
1 2 3 4 5 6=3X5
Jakarta, 22 Mei 2015
PENAWAR,
PT. ISTANA PERSAHABATAN TIMUR
MANARSAR PANJAITAN
Direktur
ANALISA TEKNIS
HARGA SATUAN PEKERJAAN
PEKERJAAN PERSIAPAN
PEKERJAAN TANAH
PEKERJAAN PONDASI
PEKERJAAN BETON
DIBULATKAN 11,693.00
BT13 1 m2 - Bekisting dengan papan + bongkaran dan penyiraman
Kayu Papan terentang 2/20-400 cm 0.0240 m3 2,299,000.00 55,176.00
Kayu Kaso terentang 5/7-400 cm 0.0280 m3 3,045,400.00 85,271.20
Paku 0.2500 kg 15,000.00 3,750.00
Pekerja 0.1650 hr 69,000.00 11,385.00
Tukang kayu 0.3940 hr 82,800.00 32,623.20
Mandor 0.0270 hr 115,000.00 3,105.00
JUMLAH 191,310.40
DIBULATKAN 191,310.00
BT14 1 m2 - Bekisting dengan triplex 9 mm + bongkaran dan penyiraman
Kayu Kaso terentang 5/7-400 cm 0.0280 m3 3,045,400.00 85,271.20
Multiplex 9 mm 0.3500 lbr 136,200.00 47,670.00
Paku 0.2500 kg 15,000.00 3,750.00
Pekerja 0.1650 bh 69,000.00 11,385.00
Tukang kayu 0.3940 hr 82,800.00 32,623.20
Mandor 0.0270 hr 115,000.00 3,105.00
JUMLAH 183,804.40
DIBULATKAN 183,804.00
BT14a 1 m3 - Bekisting sloof beton struktur
Kayu Kaso terentang 5/7-400 cm 0.1247 m3 3,045,400.00 379,761.38
Multiplex 9 mm 1.5667 lbr 136,200.00 213,384.54
Paku 1.1120 kg 15,000.00 16,680.00
Pekerja 0.7340 hr 69,000.00 50,646.00
Tukang kayu 1.7507 hr 82,800.00 144,957.96
Mandor 0.1200 hr 115,000.00 13,800.00
JUMLAH 819,229.88
DIBULATKAN 819,229.00
BT15 1 m3 - Bekisting kolom beton struktur
Kayu Kaso terentang 5/7-400 cm 0.2520 m3 3,045,400.00 767,440.80
Multiplex 9 mm 3.1500 lbr 136,200.00 429,030.00
Paku 2.2500 kg 15,000.00 33,750.00
Pekerja 1.4850 hr 69,000.00 102,465.00
Tukang kayu 3.5440 hr 82,800.00 293,443.20
Mandor 0.2430 hr 115,000.00 27,945.00
JUMLAH 1,654,074.00
DIBULATKAN 1,654,074.00
BT16 1 m3 - Bekisting balok beton struktur
Kayu Kaso terentang 5/7-400 cm 0.1870 m3 3,045,400.00 569,489.80
Multiplex 9 mm 2.3500 lbr 136,200.00 320,070.00
Paku 1.6680 kg 15,000.00 25,020.00
Pekerja 1.1010 hr 69,000.00 75,969.00
Tukang kayu 2.6260 hr 82,800.00 217,432.80
Mandor 0.1800 hr 115,000.00 20,700.00
JUMLAH 1,228,681.60
DIBULATKAN 1,228,681.00
BT17 1 m3 - Bekisting lantai beton
Kayu Kaso terentang 5/7-400 cm 0.2320 m3 3,045,400.00 706,532.80
Multiplex 9 mm 2.9050 lbr 136,200.00 395,661.00
Paku 2.0750 kg 15,000.00 31,125.00
Pekerja 1.3700 hr 69,000.00 94,530.00
Tukang kayu 3.2685 hr 82,800.00 270,631.80
Mandor 0.2245 hr 115,000.00 25,817.50
JUMLAH 1,524,298.10
DIBULATKAN 1,524,298.00
BT18 1 m2 - Perancah kayu / stoot werk - tinggi s/d 2 m
Kayu Kaso terentang 5/7-400 cm 0.0608 m3 3,045,400.00 185,160.32
Paku 0.3000 kg 15,000.00 4,500.00
Pekerja 0.6000 hr 69,000.00 41,400.00
Tukang kayu 0.4200 hr 82,800.00 34,776.00
Mandor 0.0300 hr 115,000.00 3,450.00
JUMLAH 269,286.32
DIBULATKAN 269,286.00
BT19 1 m2 - Perancah kayu / stoot werk - tinggi s/d 3 m
NO. URAIAN KOEF. SAT. HARGA SATUAN JUMLAH
DIBULATKAN 4,688,214.00
BT29 1 m3 - Sloof beton 15/20 K.225
Adukan beton K.225 ( konvensional ) 1.0000 m3 1,354,793.00 1,354,793.00
Pembesian besi polos 187.1111 kg 11,693.00 2,187,890.22
Bekisting balok struktur 1.0000 m3 1,228,681.00 1,228,681.00
JUMLAH 4,771,364.22
DIBULATKAN 4,771,364.00
BT30 1 m3 - Kolom beton 30/30 K-225
Adukan beton K-225 (ready-mix) 1.0000 m3 940,891.00 940,891.00
Pembesian 213.0000 kg 11,693.00 2,490,609.00
Bekisting Kolom 1.0000 m3 1,654,074.00 1,654,074.00
JUMLAH 5,085,574.00
DIBULATKAN 5,085,574.00
BT31 1 m3 - Kolom beton 25/35 K.225
Adukan beton K.225 ( ready - mix ) 1.0000 m3 940,891.00 940,891.00
Pembesian besi polos 179.0000 kg 11,693.00 2,093,047.00
Bekisting kolom 1.0000 m3 1,654,074.00 1,654,074.00
JUMLAH 4,688,012.00
DIBULATKAN 4,688,012.00
BT32 1 m3 - Kolom beton 25/25 K.225
Adukan beton K.225 ( ready - mix ) 1.0000 m3 940,891.00 940,891.00
Pembesian besi polos 155.0000 kg 11,693.00 1,812,415.00
Bekisting kolom 1.0000 m3 1,654,074.00 1,654,074.00
JUMLAH 4,407,380.00
DIBULATKAN 4,407,380.00
BT33 1 m3 - Kolom beton 25/25 K.250
Adukan beton K.225 ( ready - mix ) 1.0000 m3 940,891.00 940,891.00
Pembesian besi ulir 260.0000 kg 11,693.00 3,040,180.00
Bekisting kolom 1.0000 m3 1,654,074.00 1,654,074.00
JUMLAH 5,635,145.00
DIBULATKAN 5,635,145.00
BT34 1 m3 - Kolom beton 20/20 K.225 ( K3)
Adukan beton K.225 ( ready - mix ) 1.0000 m3 940,891.00 940,891.00
Pembesian besi ulir 170.0000 kg 11,693.00 1,987,810.00
Bekisting kolom 1.0000 m3 1,654,074.00 1,654,074.00
JUMLAH 4,582,775.00
DIBULATKAN 4,582,775.00
BT35 1 m3 - Kolom beton 15/30 K.225
Adukan beton K.225 ( ready - mix ) 1.0000 m3 940,891.00 940,891.00
Pembesian besi polos 173.0000 kg 11,693.00 2,022,889.00
Bekisting kolom 1.0000 m3 1,654,074.00 1,654,074.00
JUMLAH 4,617,854.00
DIBULATKAN 4,617,854.00
BT36 1 m3 - Kolom beton 15/20 K.225
Adukan beton K.225 ( ready - mix ) 1.0000 m3 940,891.00 940,891.00
Pembesian besi polos 187.1111 kg 11,693.00 2,187,890.09
Bekisting kolom 1.0000 m3 1,654,074.00 1,654,074.00
JUMLAH 4,782,855.09
DIBULATKAN 4,782,855.00
BT37 1 m3 - Kolom beton 15/40 K.225
Adukan beton K.225 ( ready - mix ) 1.0000 m3 940,891.00 940,891.00
Pembesian besi ulir 180.0000 kg 11,693.00 2,104,740.00
Bekisting kolom 1.0000 m3 1,654,074.00 1,654,074.00
JUMLAH 4,699,705.00
DIBULATKAN 4,699,705.00
BT38 1 m3 - Kolom beton 12/30 K.225
Adukan beton K.225 ( ready - mix ) 1.0000 m3 940,891.00 940,891.00
Pembesian besi ulir 170.0000 kg 11,693.00 1,987,810.00
Bekisting kolom 1.0000 m3 1,654,074.00 1,654,074.00
JUMLAH 4,582,775.00
DIBULATKAN 4,582,775.00
BT39 1 m3 - Kolom beton 12/30 K.250
Adukan beton K-225 (ready-mixl) 1.0000 m3 940,891.00 940,891.00
Pembesian besi ulir 170.0000 kg 11,693.00 1,987,810.00
NO. URAIAN KOEF. SAT. HARGA SATUAN JUMLAH
JUMLAH 6,017,223.84
DIBULATKAN 6,017,223.00
BT49 1 m3 - Balok beton 25/60 K.250
Adukan beton K.225 ( ready - mix ) 1.0000 m3 940,891.00 940,891.00
Pembesian besi ulir 150.0000 kg 11,693.00 1,753,950.00
Perancah kayu / stoot werk - tinggi s / d 4 m 1.6675 m2 484,593.00 808,058.83
Bekisting balok 1.0000 m3 1,228,681.00 1,228,681.00
JUMLAH 4,731,580.83
DIBULATKAN 4,731,580.00
BT50 1 m3 - Balok beton 25/65 K.250
Adukan beton K.225 ( ready - mix ) 1.0000 m3 940,891.00 940,891.00
Pembesian besi ulir 230.0000 kg 11,693.00 2,689,390.00
Perancah kayu / stoot werk - tinggi s / d 4 m 1.6675 m2 484,593.00 808,058.83
Bekisting balok 1.0000 m3 1,228,681.00 1,228,681.00
JUMLAH 5,667,020.83
DIBULATKAN 5,667,020.00
BT51 1 m3 - Balok beton 20/50 K-225
Adukan beton K-225 (ready-mix) 1.0000 m3 940,891.00 940,891.00
Pembesian 175.1652 kg 11,693.00 2,048,206.68
Perancah kayu / stoot werk - tinggi s/d 4 m 1.6675 m2 484,593.00 808,058.83
Bekisting balok 1.0000 m3 1,228,681.00 1,228,681.00
JUMLAH 5,025,837.51
DIBULATKAN 5,025,837.00
BT52 1 m3 - Balok beton 20/40 K-225
Adukan beton K-225 (ready-mix) 1.0000 m3 940,891.00 940,891.00
Pembesian 205.6215 kg 11,693.00 2,404,332.20
Perancah kayu / stoot werk - tinggi s/d 4 m 1.6675 m2 484,593.00 808,058.83
Bekisting balok 1.0000 m3 1,228,681.00 1,228,681.00
JUMLAH 5,381,963.03
DIBULATKAN 5,381,963.00
BT53 1 m3 - Balok beton 20/35 K-225
Adukan beton K-225 (ready-mix) 1.0000 m3 940,891.00 940,891.00
Pembesian 180.0000 kg 11,693.00 2,104,740.00
Perancah kayu / stoot werk - tinggi s/d 4 m 1.6675 m2 484,593.00 808,058.83
Bekisting Balok 1.0000 m3 1,228,681.00 1,228,681.00
JUMLAH 5,082,370.83
DIBULATKAN 5,082,370.00
BT54 1 m3 - Balok beton 20/30 K-225
Adukan beton K-225 (ready-mix) 1.0000 m3 940,891.00 940,891.00
Pembesian 180.2920 kg 11,693.00 2,108,154.36
Perancah kayu / stoot werk - tinggi s/d 4 m 1.6675 m2 484,593.00 808,058.83
Bekisting Balok 1.0000 m3 1,228,681.00 1,228,681.00
JUMLAH 5,085,785.18
DIBULATKAN 5,085,785.00
BT55 1 m3 - Balok beton 15/25 K.225
Adukan beton K.225 ( ready - mix ) 1.0000 m3 940,891.00 940,891.00
Pembesian 180.5556 kg 11,693.00 2,111,236.63
Perancah kayu / stoot werk - tinggi s / d 4 m 1.6675 m2 484,593.00 808,058.83
Bekisting balok 1.0000 m3 1,228,681.00 1,228,681.00
JUMLAH 5,088,867.46
DIBULATKAN 5,088,867.00
BT56 1 m3 - Balok beton 15/30 K.225
Adukan beton K.225 ( ready - mix ) 1.0000 m3 940,891.00 940,891.00
Pembesian 196.2427 kg 11,693.00 2,294,665.50
Perancah kayu / stoot werk - tinggi s / d 4 m 1.6675 m2 484,593.00 808,058.83
Bekisting balok 1.0000 m3 1,228,681.00 1,228,681.00
JUMLAH 5,272,296.33
DIBULATKAN 5,272,296.00
BT57 1 m3 - Balok beton 15/60 K.225
Adukan beton K.225 ( ready - mix ) 1.0000 m3 940,891.00 940,891.00
Pembesian 120.0000 kg 11,693.00 1,403,160.00
Perancah kayu / stoot werk - tinggi s / d 4 m 1.6665 m2 484,593.00 807,574.23
Bekisting balok 1.0000 m3 1,228,681.00 1,228,681.00
JUMLAH 4,380,306.23
NO. URAIAN KOEF. SAT. HARGA SATUAN JUMLAH
DIBULATKAN 4,380,306.00
BT58 1 m3 - Balok beton 12/60 K.225
Adukan beton K.225 ( ready - mix ) 1.0000 m3 940,891.00 940,891.00
Pembesian 120.0000 kg 11,693.00 1,403,160.00
Perancah kayu / stoot werk - tinggi s / d 4 m 1.6665 m2 484,593.00 807,574.23
Bekisting balok 1.0000 m3 1,228,681.00 1,228,681.00
JUMLAH 4,380,306.23
DIBULATKAN 4,380,306.00
BT59 1 m3 - Balok beton 12/60 K.250
Adukan beton K.225 ( ready - mix ) 1.0000 m3 940,891.00 940,891.00
Pembesian 120.0000 kg 11,693.00 1,403,160.00
Perancah kayu / stoot werk - tinggi s / d 4 m 1.6665 m2 484,593.00 807,574.23
Bekisting balok 1.0000 m3 1,228,681.00 1,228,681.00
JUMLAH 4,380,306.23
DIBULATKAN 4,380,306.00
BT60 1 m3 - Ring balok beton 13/20 - K. 175 (site mix)
Adukan beton K-225 (site-mix) 1.0000 m3 1,354,793.00 1,354,793.00
Pembesian 157.4200 kg 11,693.00 1,840,712.06
Bekisting Balok 1.0000 m3 1,228,681.00 1,228,681.00
JUMLAH 4,424,186.06
DIBULATKAN 4,424,186.00
BT61 1 m3 - Ring balok beton 13/13 K-175 (site mix)
Adukan beton K-175 (site-mix) 1.0000 m3 1,186,048.00 1,186,048.00
Pembesian besi ulir 155.0000 kg 11,693.00 1,812,415.00
Bekisting Balok 1.0000 m3 1,228,681.00 1,228,681.00
JUMLAH 4,227,144.00
DIBULATKAN 4,227,144.00
BT62 1 m3 - Ring balok beton 15/25 K-175 (site mix)
Adukan beton K-175 (site-mix) 1.0000 m3 1,186,048.00 1,186,048.00
Pembesian besi ulir 160.0000 kg 11,693.00 1,870,880.00
Bekisting Balok 1.0000 m3 1,228,681.00 1,228,681.00
JUMLAH 4,285,609.00
DIBULATKAN 4,285,609.00
BT63 1 m3 - Ring balok beton 25/35 K-225 (ready mix)
Adukan beton K-225 (ready-mix) 1.0000 m3 940,891.00 940,891.00
Pembesian besi ulir 160.0000 kg 11,693.00 1,870,880.00
Perancah kayu / stoot werk - tinggi s / d 4 m 2.8575 m2 484,593.00 1,384,724.50
Bekisting Balok 1.0000 m3 1,228,681.00 1,228,681.00
JUMLAH 5,425,176.50
DIBULATKAN 5,425,176.00
BT64 1 m3 - Plat lantai & tangga beton K.225
Adukan beton K.225 ( ready - mix ) 1.0000 m3 940,891.00 940,891.00
Pembesian 198.4100 kg 11,693.00 2,320,008.13
Perancah kayu / stoot werk - tinggi s / d 4 m 8.3333 m2 484,593.00 4,038,258.85
Bekisting plat lantai 1.0000 m3 1,524,298.00 1,524,298.00
JUMLAH 8,823,455.98
DIBULATKAN 8,823,455.00
BT65 1 m3 - Plat lantai & tangga beton K.250
Adukan beton K.250 ( ready - mix ) 1.0000 m3 956,791.00 956,791.00
Pembesian 198.4100 kg 11,693.00 2,320,008.13
Perancah kayu / stoot werk - tinggi s / d 4 m 8.3333 m2 484,593.00 4,038,258.85
Bekisting plat lantai 1.0000 m3 1,524,298.00 1,524,298.00
JUMLAH 8,839,355.98
DIBULATKAN 8,839,355.00
BT66 1 m3 - Plat listplank beton K.225
Adukan beton K.225 ( ready - mix ) 1.0000 m3 940,891.00 940,891.00
Pembesian 100.0000 kg 11,693.00 1,169,300.00
Perancah kayu / stoot werk - tinggi s / d 4 m 1.0000 m2 484,593.00 484,593.00
Bekisting balok 1.0000 m3 1,228,681.00 1,228,681.00
JUMLAH 3,823,465.00
DIBULATKAN 3,823,465.00
BT67 1 m3 - Plat listplank beton K.250
Adukan beton K.250 ( ready - mix ) 1.0000 m3 956,791.00 956,791.00
Pembesian 100.0000 kg 11,693.00 1,169,300.00
NO. URAIAN KOEF. SAT. HARGA SATUAN JUMLAH
JUMLAH 29,095.40
DIBULATKAN 29,095.00
PA17 1 m2 - Alumunium foil + Roofmesh
Alumunium foil 1.0500 m2 17,900.00 18,795.00
Roofmesh 1.0500 m2 26,600.00 27,930.00
Pekerja 0.0330 hr 69,000.00 2,277.00
Tukang kayu 0.0330 hr 82,800.00 2,732.40
Mandor 0.0050 hr 115,000.00 575.00
JUMLAH 52,309.40
DIBULATKAN 52,309.00
PA18 1 m1 - Talang datar
Papan kayu meranti Oven 0.0096 m3 2,299,000.00 22,070.40
Plat seng 0.5000 m1 49,700.00 24,850.00
Paku 0.0150 kg 15,000.00 225.00
Pekerja 0.0500 hr 69,000.00 3,450.00
Tukang kayu 0.1200 hr 82,800.00 9,936.00
Mandor 0.0120 hr 115,000.00 1,380.00
JUMLAH 61,911.40
DIBULATKAN 61,911.00
PA19 1 m2 - Pasangan Atap Zincalume + Alumunium Foil + Roofmesh
Atap Zincalume 1.0000 m2 75,600.00 75,600.00
Alumunium Foil 1.0500 m2 17,900.00 18,795.00
Roofmesh 1.0500 m2 26,600.00 27,930.00
Paku Pengikat Atap metal/zincalume 0.1750 kg 15,000.00 2,625.00
Sealent 0.0650 tube 15,400.00 1,001.00
Pekerja 0.0695 hr 69,000.00 4,795.50
Tukang kayu 0.1225 hr 82,800.00 10,143.00
Mandor 0.0067 hr 115,000.00 770.50
JUMLAH 141,660.00
DIBULATKAN 141,660.00
PA20 1 m2 - Pasangan Atap Metal berpasir cutting + Alumunium Foil + Roofmesh
Atap Metal berpasir tebal 0,3 mm cutting 1.3000 lbr 113,900.00 148,070.00
Alumunium Foil 1.0500 m2 17,900.00 18,795.00
Roofmesh 1.0500 m2 26,600.00 27,930.00
Paku Pengikat Atap metal/zincalume 0.1200 kg 15,000.00 1,800.00
Pekerja 0.1400 hr 69,000.00 9,660.00
Tukang kayu 0.1000 hr 82,800.00 8,280.00
Kepala Tukang kayu 0.0080 hr 92,000.00 736.00
Mandor 0.0080 hr 115,000.00 920.00
JUMLAH 216,191.00
DIBULATKAN 216,191.00
PA21 1 m2 - Pasangan Atap Metal berpasir cutting
Atap Metal berpasir tebal 0,3 mm cutting 1.3000 lbr 40,500.00 52,650.00
Paku Pengikat Atap metal/zincalume 0.1200 kg 15,000.00 1,800.00
Pekerja 0.1400 hr 69,000.00 9,660.00
Tukang kayu 0.1000 hr 82,800.00 8,280.00
Kepala Tukang kayu 0.0080 hr 92,000.00 736.00
Mandor 0.0080 hr 115,000.00 920.00
JUMLAH 74,046.00
DIBULATKAN 74,046.00
PA23 1 m1 - Pasangan Nok Zincalume
Nok Zincalume 1.1000 lbr 40,500.00 44,550.00
Paku Pengikat Atap metal/zincalume 0.1200 kg 15,000.00 1,800.00
Pekerja 0.1400 hr 69,000.00 9,660.00
Tukang kayu 0.1000 hr 82,800.00 8,280.00
Kepala Tukang kayu 0.0080 hr 92,000.00 736.00
Mandor 0.0080 hr 115,000.00 920.00
JUMLAH 65,946.00
DIBULATKAN 65,946.00
PEKERJAAN KAYU
KY01 1 m3 - Kusen kayu kamper samarinda oven
Kayu balok kamper samarinda Oven 1.1000 m3 9,117,600.00 10,029,360.00
Paku 3.0000 kg 15,000.00 45,000.00
Angkur 10.5600 kg 12,500.00 132,000.00
NO. URAIAN KOEF. SAT. HARGA SATUAN JUMLAH
PEKERJAAN PARTISI
JUMLAH 2,246,500.00
DIBULATKAN 2,246,500.00
ST04 1 bh - Wastafel
Wastafel + Accesoris 1.0000 bh 1,500,000.00 1,500,000.00
Pekerja 0.3000 hr 69,000.00 20,700.00
Tukang batu 0.2500 hr 82,800.00 20,700.00
Mandor 0.1800 hr 115,000.00 20,700.00
JUMLAH 1,562,100.00
DIBULATKAN 1,562,100.00
ST05 1 bh - Kitchen Zink
Kitchen Zink 1.0000 bh 250,000.00 250,000.00
Pekerja 0.3000 hr 69,000.00 20,700.00
Tukang batu 0.2500 hr 82,800.00 20,700.00
Mandor 0.1800 hr 115,000.00 20,700.00
JUMLAH 312,100.00
DIBULATKAN 312,100.00
ST07 1 bh - Floor drain
Floor drain stainless 1.0000 bh 163,500.00 163,500.00
Pekerja 0.0100 hr 69,000.00 690.00
Tukang batu 0.1000 hr 82,800.00 8,280.00
Mandor 0.0050 hr 115,000.00 575.00
JUMLAH 173,045.00
DIBULATKAN 173,045.00
ST08 1 bh - Shower
Shower 1.0000 bh 284,800.00 284,800.00
Pekerja 0.0100 hr 69,000.00 690.00
Tukang batu 0.1000 hr 82,800.00 8,280.00
Mandor 0.0050 hr 115,000.00 575.00
JUMLAH 294,345.00
DIBULATKAN 294,345.00
ST09 1 bh - Kran leher angsa 1/2"
Kran air leher angsa 1/2 1.0000 bh 270,900.00 270,900.00
Seal tape 0.0250 roll 2,400.00 60.00
Lem pipa PVC 0.1250 tube 13,400.00 1,675.00
Pekerja 0.0100 hr 69,000.00 690.00
Tukang batu 0.1000 hr 82,800.00 8,280.00
Mandor 0.0050 hr 115,000.00 575.00
JUMLAH 282,180.00
DIBULATKAN 282,180.00
ST10 1 bh - Kran air 1/2"
Kran air 1/2 1.0000 bh 25,000.00 25,000.00
Seal tape 0.0250 roll 2,400.00 60.00
Lem pipa PVC 0.1250 tube 13,400.00 1,675.00
Pekerja 0.0100 hr 69,000.00 690.00
Tukang batu 0.1000 hr 82,800.00 8,280.00
Mandor 0.0050 hr 115,000.00 575.00
JUMLAH 36,280.00
DIBULATKAN 36,280.00
ST11 1 unit - Pompa air jet pump + Instalasi dan pengeboran
Pompa air jet pump 1.0000 bh 1,871,700.00 1,871,700.00
Pipa PVC 1 " 40.0000 m1 8,700.00 348,000.00
Pipa PVC 4 " 16.0000 m1 10,312.00 164,992.00
Bocht LL-D 1" (lokal) 6.0000 bh 23,500.00 141,000.00
Water moer 2.0000 bh 56,800.00 113,600.00
Ongkos pengeboran 1.0000 ls 1,222,000.00 1,222,000.00
JUMLAH 3,861,292.00
DIBULATKAN 3,861,292.00
ST11 1 unit - Pompa air jet pump tanpa pengeboran
Pompa air jet pump 1.0000 bh 1,871,700.00 1,871,700.00
Ongkos pasang 1.0000 ls 75,000.00 75,000.00
JUMLAH 1,946,700.00
DIBULATKAN 1,946,700.00
ST12 1 unit - Water tower rangka besi siku
Konstruksi besi siku 210.0000 kg 13,400.00 2,814,000.00
NO. URAIAN KOEF. SAT. HARGA SATUAN JUMLAH
JUMLAH 34,845.00
DIBULATKAN 34,845.00
AS03 1 bh - Pasang hak angin
Hak angin 1.0000 bh 13,300.00 13,300.00
Pekerja 0.0100 hr 69,000.00 690.00
Tukang kayu 0.1000 hr 82,800.00 8,280.00
Mandor 0.0050 hr 115,000.00 575.00
JUMLAH 22,845.00
DIBULATKAN 22,845.00
AS04 1 bh - Pasang slot jendela
Slot jendela 1.0000 bh 87,000.00 87,000.00
Pekerja 0.0100 hr 69,000.00 690.00
Tukang kayu 0.1000 hr 82,800.00 8,280.00
Mandor 0.0050 hr 115,000.00 575.00
JUMLAH 96,545.00
DIBULATKAN 96,545.00
AS05 1 bh - Pasang kunci double slaag (SOLID)
Kunci double slaag (SOLID) 1.0000 bh 278,000.00 278,000.00
Pekerja 0.0500 hr 69,000.00 3,450.00
Tukang kayu 0.2500 hr 82,800.00 20,700.00
Mandor 0.0100 hr 115,000.00 1,150.00
JUMLAH 303,300.00
DIBULATKAN 303,300.00
AS06 1 bh - Pasang Grendel pintu
Grendel Pintu 1.0000 bh 38,700.00 38,700.00
Pekerja 0.0100 hr 69,000.00 690.00
Tukang kayu 0.1000 hr 82,800.00 8,280.00
Mandor 0.0050 hr 115,000.00 575.00
JUMLAH 48,245.00
DIBULATKAN 48,245.00
PEKERJAAN SARANA LUAR
SL01 1 m1 - Saluran buis beton 1/2 dia. 20 cm tanpa tulangan
Buis beton 1/2 dia. 20 cm 1.0250 m1 64,600.00 66,215.00
Pasir urug 0.1200 m3 202,500.00 24,300.00
Pasir pasang 0.0540 m3 251,800.00 13,597.20
Semen PC ( 50 kg ) 0.0270 zak 75,000.00 2,025.00
Pekerja 0.0750 hr 69,000.00 5,175.00
Tukang batu 0.0500 hr 82,800.00 4,140.00
Mandor 0.0125 hr 115,000.00 1,437.50
JUMLAH 116,889.70
DIBULATKAN 116,889.00
SL02 1 m1 - Saluran tertutup buis beton dia. 30 cm tanpa tulangan
Buis beton dia. 30 cm 1.0250 m1 124,100.00 127,202.50
Pasir urug 0.1200 m3 202,500.00 24,300.00
Pasir pasang 0.0540 m3 251,800.00 13,597.20
Semen PC ( 50 kg ) 0.0270 zak 75,000.00 2,025.00
Pekerja 0.0750 hr 69,000.00 5,175.00
Tukang batu 0.0500 hr 82,800.00 4,140.00
Mandor 0.0125 hr 115,000.00 1,437.50
JUMLAH 177,877.20
DIBULATKAN 177,877.00
SL03 1 m2 - Paving block t = 6 cm
Paving block t = 6 cm K.250 1.0250 m2 78,100.00 80,052.50
Abu batu 0.0250 m3 251,800.00 6,295.00
Pekerja 0.1500 hr 69,000.00 10,350.00
Tukang batu 0.0500 hr 82,800.00 4,140.00
Mandor 0.0030 hr 115,000.00 345.00
JUMLAH 101,182.50
DIBULATKAN 101,182.00
SL04 1 m2 - Paving block t = 8 cm
Paving block t = 8 cm K.250 1.0250 m2 99,700.00 102,192.50
Abu batu 0.0250 m3 251,800.00 6,295.00
Pekerja 0.1500 hr 69,000.00 10,350.00
Tukang batu 0.0500 hr 82,800.00 4,140.00
NO. URAIAN KOEF. SAT. HARGA SATUAN JUMLAH
PEKERJAAN TANAMAN
PT01 1 pohon - Eucaliptus
Eucaliptus Ø 4 - 7 cm, t = 1 - 3 m 1.0000 phn 97,100.00 97,100.00
Pekerja 0.0200 hr 69,000.00 1,380.00
Mandor 0.0020 hr 115,000.00 230.00
JUMLAH 98,710.00
DIBULATKAN 98,710.00
PT04 1 pohon - Pucuk Merah (tinggi 50 - 60 cm)
Pucuk Merah (tinggi 50 - 60 cm) 1.0000 phn 102,300.00 102,300.00
Pekerja 0.0200 hr 69,000.00 1,380.00
Mandor 0.0020 hr 115,000.00 230.00
JUMLAH 103,910.00
DIBULATKAN 103,910.00
PT04 1 pohon - Kiara Payung
Kiara Payung 1.0000 phn 130,200.00 130,200.00
Pekerja 0.0200 hr 69,000.00 1,380.00
Mandor 0.0020 hr 115,000.00 230.00
JUMLAH 131,810.00
DIBULATKAN 131,810.00
PT04 1 pohon - Pohon Glodogan Tiang T = 1.5m
Pohon Glodogan Tiang T = 1.5m 1.0000 phn 186,000.00 186,000.00
Pekerja 0.0200 hr 69,000.00 1,380.00
Mandor 0.0020 hr 115,000.00 230.00
JUMLAH 187,610.00
DIBULATKAN 187,610.00
NO. URAIAN KOEF. SAT. HARGA SATUAN JUMLAH
ME02 1 m - Instalasi NYY (4X16) mm2 dari panel ke KWH meter PLN
Kabel NYY 4x16 mm 1.0000 m 116,300.00 116,300.00
Klem kabel 0.2500 dus 6,100.00 1,525.00
Pipa PVC AW 1/2" 2.0000 m 4,700.00 9,400.00
Pembantu Instalator 0.3715 hr 73,600.00 27,342.40
Instalator 0.1050 hr 92,000.00 9,660.00
Mandor 0.0050 hr 115,000.00 575.00
JUMLAH 164,802.40
DIBULATKAN 164,802.00
ME02 1 Titik - WLC elektrode + kabel NYM 3X2,5 mm2
Alat dan bahan 1.0000 ls 381,300.00 381,300.00
Pembantu Instalator 0.3715 hr 73,600.00 27,342.40
Instalator 0.1050 hr 92,000.00 9,660.00
Mandor 0.0050 hr 115,000.00 575.00
JUMLAH 418,877.40
DIBULATKAN 418,877.00
ME03 1 bh - Pasang Saklar Tunggal
Saklar tunggal 1.0000 bh 13,400.00 13,400.00
Pembantu Instalator 0.2500 hr 73,600.00 18,400.00
Instalator 0.1500 hr 92,000.00 13,800.00
Mandor 0.0050 hr 115,000.00 575.00
JUMLAH 46,175.00
DIBULATKAN 46,175.00
ME04 1 bh - Pasang Saklar Ganda
Saklar ganda 1.0000 bh 18,500.00 18,500.00
Pembantu Instalator 0.2500 hr 73,600.00 18,400.00
Instalator 0.1500 hr 92,000.00 13,800.00
Mandor 0.0050 hr 115,000.00 575.00
JUMLAH 51,275.00
DIBULATKAN 51,275.00
ME05 1 bh - Pasang Stop Kontak
Stop Kontak 1.0000 bh 14,200.00 14,200.00
Pembantu Instalator 0.2500 hr 73,600.00 18,400.00
Instalator 0.1500 hr 92,000.00 13,800.00
Mandor 0.0050 hr 115,000.00 575.00
JUMLAH 46,975.00
DIBULATKAN 46,975.00
ME06 1 bh - Pasang Stop Kontak
Stop Kontak 1.0000 bh 14,200.00 14,200.00
Pembantu Instalator 0.2500 hr 73,600.00 18,400.00
Instalator 0.1500 hr 92,000.00 13,800.00
Mandor 0.0050 hr 115,000.00 575.00
JUMLAH 46,975.00
DIBULATKAN 46,975.00
ME07 1 set - Panel PP-LP01, 40X60 cm2
Alat dan bahan 1.0000 ls 690,000.00 690,000.00
Pembantu Instalator 3.0000 hr 73,600.00 220,800.00
Instalator 2.0000 hr 92,000.00 184,000.00
Mandor 1.0000 hr 115,000.00 115,000.00
JUMLAH 1,209,800.00
DIBULATKAN 1,209,800.00
ME07 1 set - Pas.Box MCB 10 A
MCB 10 A 3.0000 bh 86,600.00 259,800.00
Box MCB 4 group 1.0000 bh 25,300.00 25,300.00
Pembantu Instalator 3.0000 hr 80,000.00 240,000.00
Instalator 2.0000 hr 100,000.00 200,000.00
Mandor 1.0000 hr 125,000.00 125,000.00
JUMLAH 850,100.00
DIBULATKAN 850,100.00
ME08 1 bh - Lampu TL 2 x 18 watt setara philips (inbouw) termasuk bahan komplit
Lampu TL 2 x 18 watt, armatur, komplit philips 1.0000 bh 94,100.00 94,100.00
Pembantu instalator 0.3132 hr 73,600.00 23,051.52
Instalator 0.1045 hr 92,000.00 9,614.00
Mandor 0.0050 hr 115,000.00 575.00
JUMLAH 127,340.52
NO. URAIAN KOEF. SAT. HARGA SATUAN JUMLAH
DIBULATKAN 127,340.00
ME09 1 bh - Lampu SL 18 watt termasuk bahan komplit
Lampu SL 18 watt, komplit philips 1.0000 bh 29,900.00 29,900.00
Fitting keramik 1.0000 bh 14,800.00 14,800.00
Pembantu instalator 0.3132 hr 73,600.00 23,051.52
Instalator 0.1045 hr 92,000.00 9,614.00
Mandor 0.0050 hr 115,000.00 575.00
JUMLAH 77,940.52
DIBULATKAN 77,940.00
ME10 1 Bh - Lampu Baret Kotak 22 watt
Lampu baret kotat 22 watt, komplit philips 1.0000 bh 125,000.00 125,000.00
Instalator 0.1050 hr 92,000.00 9,660.00
Pembantu instalator 0.2274 hr 73,600.00 16,736.64
Mandor 0.0050 hr 115,000.00 575.00
JUMLAH 151,971.64
DIBULATKAN 151,971.00
ME11 1 Bh - Lampu downlight
Lampudownlight + Accecories 1.0000 bh 90,000.00 90,000.00
Pembantu instalator 0.2294 hr 73,600.00 16,883.84
Instalator 0.1045 hr 92,000.00 9,614.00
Mandor 0.0050 hr 115,000.00 575.00
JUMLAH 117,072.84
DIBULATKAN 117,072.00
ME12 1 Bh - Lampu PLC 13 watt
Lampu PLC 13 watt 1.0000 bh 59,800.00 59,800.00
Pembantu instalator 0.3132 hr 73,600.00 23,051.52
Instalator 0.1045 hr 92,000.00 9,614.00
Mandor 0.0050 hr 115,000.00 575.00
JUMLAH 93,040.52
DIBULATKAN 93,040.00
1 Bh - Lampu Pagar
Lampu pagar 1.0000 bh 171,000.00 171,000.00
Pekerja 0.3132 hr 69,000.00 21,610.80
Tukang listrik 0.1045 hr 92,000.00 9,614.00
Mandor 0.0050 hr 115,000.00 575.00
JUMLAH 202,799.80
DIBULATKAN 202,799.00
1 Bh - Lampu Sorot
Lampu sorot LED 50 watt 1.0000 bh 506,000.00 506,000.00
Pekerja 0.3132 hr 69,000.00 21,610.80
Tukang listrik 0.1045 hr 92,000.00 9,614.00
Mandor 0.0050 hr 115,000.00 575.00
JUMLAH 537,799.80
DIBULATKAN 537,799.00
ME17 1 Kwh - Penyambungan daya
Penyambungan daya 1.0000 ls 1,500.00 1,500.00
Instalator 0.0010 hr 92,000.00 92.00
Mandor 0.0001 hr 115,000.00 11.50
JUMLAH 1,603.50
DIBULATKAN 1,603.00
ME18 1 ttk - Penangkal petir kompensional
Splitzer uk.2 1.0000 bh 44,500.00 44,500.00
Kabel BC 75 mm2 1.0000 m 22,000.00 22,000.00
Klem Kabel 1.0000 bh 2,700.00 2,700.00
Pentanahan 1.0000 ls 826,900.00 826,900.00
Bak kontrol 600 x 600 x 400 1.0000 bh 106,200.00 106,200.00
Pembantu instalator 0.5000 hr 73,600.00 36,800.00
Instalator 0.8000 hr 92,000.00 73,600.00
Mandor 0.0100 hr 115,000.00 1,150.00
Box Test 1.0000 bh 390,900.00 390,900.00
JUMLAH 1,504,750.00
DIBULATKAN 1,504,750.00
PEKERJAAN PINTU DAN JENDELA
PJ01 1 m3 - Kusen kayu kamper samarinda
Kayu balok kamper samarinda Oven 1.1000 m3 9,117,600.00 10,029,360.00
Paku 3.0000 kg 15,000.00 45,000.00
NO. URAIAN KOEF. SAT. HARGA SATUAN JUMLAH
JUMLAH 1,939,350.00
DIBULATKAN 1,939,350.00
1 unit - Pembuatan couter ruang pelayanan
Alat dan bahan 1.0000 ls 1,720,500.00 1,720,500.00
Pekerja 1.0000 hr 69,000.00 69,000.00
Tukang Besi 1.0000 hr 78,200.00 78,200.00
Mandor 0.0500 hr 115,000.00 5,750.00
JUMLAH 1,873,450.00
DIBULATKAN 1,873,450.00
PJ13 1 m2 - Pemasangan Almunium Komposit ( ACP )
Alumunium composite 1.2000 m2 114,900.00 137,880.00
Braket galvanis ACP 2.0000 bh 15,600.00 31,200.00
Rangka alumunium composite (Almn. 4 0 x 40 x 2 mm ) 4.5000 m 18,800.00 84,600.00
Skrup almunium 0.4000 kg 15,500.00 6,200.00
Sealent 1.5000 tube 15,400.00 23,100.00
Pekerja 0.3500 hr 69,000.00 24,150.00
Tukang besi 0.5500 hr 78,200.00 43,010.00
Mandor / pengawas 0.1200 hr 115,000.00 13,800.00
JUMLAH 363,940.00
DIBULATKAN 363,940.00
PEKERJAAN BONGKARAN
BK01 1 m3 - Bongkar struktur bangunan (manual)
Pekerja 2.3520 hr 69,000.00 162,288.00
Mandor 0.0388 hr 115,000.00 4,462.00
JUMLAH 166,750.00
DIBULATKAN 166,750.00
BK02 1 m3 - Bongkar struktur Bangunan ( dengan alat berat )
Pekerja 1.9600 hr 69,000.00 135,240.00
Mandor 0.0323 hr 115,000.00 3,714.50
Kompresor kap.400 - 6500 ltr/menit 0.1000 jam 65,500.00 6,550.00
Jack Hammer 0.1000 set 20,900.00 2,090.00
JUMLAH 147,594.50
DIBULATKAN 147,594.00
BK03 1 m2 - Bongkar dinding bata merah
Pekerja 0.1000 hr 69,000.00 6,900.00
Mandor 0.0250 hr 115,000.00 2,875.00
JUMLAH 9,775.00
DIBULATKAN 9,775.00
BK04 1 m2 - Bongkar lantai keramik
Pekerja 0.0800 hr 69,000.00 5,520.00
Mandor 0.0250 hr 115,000.00 2,875.00
JUMLAH 8,395.00
DIBULATKAN 8,395.00
BK05 1 m2 - Bongkar genteng
Pekerja 0.0400 hr 69,000.00 2,760.00
Mandor 0.0100 hr 115,000.00 1,150.00
JUMLAH 3,910.00
DIBULATKAN 3,910.00
BK06 1 m2 - Bongkar rangka atap
Pekerja 0.2000 hr 69,000.00 13,800.00
Tukang kayu 0.0550 hr 82,800.00 4,554.00
Mandor 0.0102 hr 115,000.00 1,173.00
JUMLAH 19,527.00
DIBULATKAN 19,527.00
BK07 1 m2 - Bongkar plafond
Pekerja 0.1250 hr 69,000.00 8,625.00
Tukang kayu 0.0600 hr 82,800.00 4,968.00
Mandor 0.0500 set 115,000.00 5,750.00
JUMLAH 19,343.00
DIBULATKAN 19,343.00
BK08 1 m2 - Bongkar Kusen
Pekerja 0.3300 hr 69,000.00 22,770.00
Mandor 0.0330 hr 115,000.00 3,795.00
Alat bantu 1.0000 set 1,000.00 1,000.00
NO. URAIAN KOEF. SAT. HARGA SATUAN JUMLAH
JUMLAH 27,565.00
DIBULATKAN 27,565.00
BK09 1 m2 - Pekerjaan kupasan dinding
Pekerja 0.0500 hr 69,000.00 3,450.00
Mandor 0.0250 hr 115,000.00 2,875.00
Alat bantu 1.0000 set 1,000.00 1,000.00
JUMLAH 7,325.00
DIBULATKAN 7,325.00
BK10 1 m2 - Bongkar pintu besi
Pekerja 0.3300 hr 69,000.00 22,770.00
Mandor 0.0330 hr 115,000.00 3,795.00
Alat bantu 2.0000 set 1,000.00 2,000.00
JUMLAH 28,565.00
DIBULATKAN 28,565.00
BK11 1 m1 - Bongkaran karpusan genteng morando glasur
Pekerja 0.0500 hr 69,000.00 3,450.00
Mandor 0.0225 hr 115,000.00 2,587.50
Alat bantu 1.0000 set 1,000.00 1,000.00
JUMLAH 7,037.50
DIBULATKAN 7,037.00
BK12 1 m1 - Bongkaran listplank 3 / 30 + 3 / 15 kayu kamper banjar
Pekerja 0.0840 hr 69,000.00 5,796.00
Tukang kayu 0.1680 hr 82,800.00 13,910.40
Mandor 0.0216 hr 115,000.00 2,484.00
JUMLAH 22,190.40
DIBULATKAN 22,190.00
BK13 1 kg - Bongkar konstruksi gording besi
Pekerja 0.0600 hr 69,000.00 4,140.00
Tukang besi 0.0045 hr 78,200.00 351.90
Mandor 0.0025 hr 115,000.00 287.50
Erection 1.0000 kg 40,000.00 40,000.00
JUMLAH 44,779.40
DIBULATKAN 44,779.00
1 2 3 4
I PASIR DAN BATU
Abu Batu/Screening 5 mm 237,800.00 m3
Batu Belah Pondasi 239,200.00 m3
Batu Pecah/Split ukr. 2 - 3 cm 250,400.00 m3
Batu Pecah/Split ukr. 3 - 4 cm 250,400.00 m3
Macadam/Steel Slag ukr. 5 - 7 cm 217,800.00 m3
Batu Tempel Hitam 133,600.00 m2
Koral Beton 223,100.00 m3
Pasir Beton 270,900.00 m3
Pasir pasang 251,800.00 m3
Pasir urug darat 202,500.00 m3
Sirtu 225,100.00 m3
Tanah Merah 130,500.00 m3
-
II PAVING BLOCK
Kastin Abu-abu ukr. 10.20.40 K 250 29,400.00 m1
Paving Block K 250 Tebal 6 Abu-abu 78,100.00 m2
Paving Block K 250 Tebal 8 Abu-abu 99,700.00 m2
Paving Block K 350 Tebal 6 Abu-abu 91,800.00 m2
Paving Block K 350 Tebal 8 Abu-abu 105,600.00 m2
Grass Blok tebal 6 (spek) 113,200.00 m2
-
III PAGAR PRECAST
pagar panel uk, 5x40x240, mutu beton K225 120,000.00 bh
Tiang pagar uk, 16x18x275, mutu beton K225 259,200.00 bh
Tiang pagar uk, 16x18x340, mutu beton K225 312,900.00 bh
-
IV SEMEN DAN KAPUR
Bata merah 400.00 bh
Bata Ringan / Hebel 8,700.00 bh
Rooster Beton 20 x 20 x 7 cm 7,800.00 bh
Glass block 22,100.00 bh
Semen Tiga Roda 50 kg 75,000.00 zak
Semen Warna 19,800.00 kg
Semen Instan (mortar) 110,500.00 zak
Compound Jaya (20 Kg) 66,600.00 zak
-
V KAYU & PLAFOND
Kaso kayu Meranti Jambi/Palembang - 400 cm 3,045,400.00 m3
Balok Kayu Meranti Jambi/palembang - 400 cm 3,598,500.00 m3
Papan Kayu Terentang - 400 cm 2,299,000.00 m3
Dolken Ø 8 - 10 cm ukr. 350 - 400 cm 26,300.00 btg
List Gypsum 7 cm 18,200.00 m1
List Gypsum 10 cm 22,000.00 m1
List profil kamper 5 Cm 57,400.00 m1
Balok Kayu Kamper Samarinda Oven : 6x15x400 cm 9,117,600.00 m3
Papan Kayu Kamper Samarinda Oven : 3x30x400 cm 10,005,800.00 m3
Daun Pintu Kayu Kamper Samarinda (Bukan Oven) 1,805,000.00 Unit
Daun Pintu Kayu Kamper Samarinda Kualitas Export (Oven) 2,308,500.00 Unit
Bahan plafond hardplex 5 mm 120x240 75,000.00 lbr
Formika ukr. 122 x 244 x 3 mm 115,500.00 lbr
Kusen dan Daun Pintu PVC ukuran standar 225,900.00 Unit
Multiplek ukr. 122 x 244 x 9 mm 136,200.00 lbr
Teakwood ukr. 122 x 244 x 4 mm 97,600.00 lbr
NO. NAMA BAHAN/MATERIAL HARGA SATUAN SATUAN
1 2 3 4
Triplek ukr. 122 x 244 x 4 mm 67,300.00 lbr
Gypsum Jaya 9 mm (122 mm x 244 mm) 71,100.00 lbr
GRC Board t = 4 mm 82,600.00 lbr
Kassa Gypsum / Textille 5,200.00 rol
Plafon Gyptile terpasang 117,000.00 m2
Bambu Ø 8 - 10 Cm Panjang = 5 - 6 M 19,000.00 btg
Galpanis 4x4 tbl = 1,6 mm 152,000.00 btg
Galpanis 5x5 tbl = 1,6 mm 180,500.00 btg
Besi galpanis Ø 2 inch 71,200.00 m1
Besi tempa 16 mm 142,500.00 btg
Zincromate 900.00 m2
-
VI READYMIX
Readymix beton K-225 tanpa pompa 864,000.00 m3
Readymix beton K-250 tanpa pompa 879,900.00 m3
Readymix beton K-300 tanpa pompa 924,000.00 m3
VII BETON
Buis Beton -
Buis Beton Ukuran .Ø 20 cm tanpa tulangan panjang 1,00 m Lokal 113,300.00 m1
Buis Beton Ukuran .Ø 30 cm tanpa tulangan panjang 1,00 m lokal 124,100.00 m1
Buis Beton Ukuran .1/2 Ø 20 cm tanpa tulangan panjang 1,00 m lokal 64,600.00 btg
Buis Beton Ukuran .1/2 Ø 30 cm tanpa tulangan panjang 1,00 m lokal 74,600.00 btg
-
VIII CAT
Amplas Kayu 2,800.00 lbr
Ampelas Besi 4,200.00 lbr
Cat minyak setara F Talit 50,200.00 kg
Cat tembok Dulux/ICI interior 39,000.00 kg
Cat tembok Dulux/ICI exterior 62,500.00 kg
Cat dasar setara Dulux/ICI 43,700.00 kg
Lem Putih 12,800.00 Kg
Dempul plitur 36,500.00 kg
Ijuk 6,400.00 ikat
Kwas 3" 11,600.00 bh
Melamik 50,800.00 kg
Meni setara Nippon 35,500.00 kg
Minyak Cat/Tinner 19,700.00 ltr
Pelamir Tembok 22,600.00 kg
Pelitur 44,900.00 kg
Rool cat tembok 22,000.00 bh
Vernis Bee Brand 66 (kayu/besi) 34,000.00 ltr
Aquaproof 42,100.00 kg
-
IX LANTAI
Ubin Keramik Ukr. 20x20 Standar KW 1 65,800.00 m2
Ubin Keramik Ukr. 20x25 Standar KW1 65,200.00 m2
Ubin Keramik Ukr. 30x30 Standar KW 1 55,300.00 m2
Ubin Keramik Ukr. 40x40 Standar KW 1 65,300.00 m2
Step noising Keramik 10 x 30 21,100.00 bh
-
X ALAT PENGUNCI
Engsel Pintu Nilon ukuran 3" 25,300.00 ps
Engsel Pintu Nilon ukuran 4" 38,000.00 ps
Engsel Jendela Casemen 16 " 95,000.00 set
Dyna Bolt 1,400.00 bh
Kunci KM / WC 33,200.00 bh
Kait Angin 27,700.00 bh
NO. NAMA BAHAN/MATERIAL HARGA SATUAN SATUAN
1 2 3 4
Hak Angin 13,300.00 bh
Grendel tanam pintu 87,000.00 bh
Kunci pintu setara Solid 278,000.00 bh
Kunci Gembok 47,500.00 bh
Grendel Ukuran 4" setara Solid 38,700.00 bh
Handel pintu 128,200.00 set
-
XI SANITASI AIR
Closet Duduk 2,439,900.00 bh
Closet Jongkok setara TOTO 222,200.00 bh
Urinoir 2,186,700.00 bh
Shower 284,800.00 bh
Kitchen zinck 249,400.00 bh
Kran leher angsa 270,900.00 bh
Kran Air TOTO 1/2" 206,000.00 bh
Floor Drain Stainless 163,500.00 bh
Roofdrain 110,600.00 bh
Sealtape 2,400.00 bh
Lem Pipa PVC 13,400.00 tube
Pompa jetpump 1,871,700.00 unit
Bocht LL-D 1" (lokal) 23,500.00 bh
Water moer 56,800.00 bh
Ongkos pengeboran 1,222,000.00 ls
Konstruksi besi siku 13,400.00 kg
Besi siku L.40.40.4 15,100.00 kg
Tangki air kapasitas 1 m3 1,624,000.00 bh
Pipa Galv Medium dia 1/2 inch ; P : 6 m (SNI ) 162,100.00 btg
Pipa Galv Medium dia 1/2 inch (SNI ) 26,900.00 m'
Pipa Galv Medium dia 3/4 inch ; P : 6 m (SNI/SII ) 179,500.00 btg
Pipa Galv Medium dia 3/4 inch (SNI/SII ) 29,800.00 m'
Pipa Galv Medium dia 1 inch P : 6 m (2,95 mm) (SNI) 284,100.00 btg
Pipa Galv Medium dia 1 inch (2,95 mm) (SNI) 47,200.00 m'
Pipa Galv Medium dia 1-1/4 inch P : 6 m (3,65 mm) (SNI) 361,700.00 btg
Pipa Galv Medium dia 1-1/4 inch (3,65 mm) (SNI) 60,200.00 m'
Pipa Galv Medium dia 1-1/2 inch P : 6 m (3 mm) (SNI) 387,500.00 btg
Pipa Galv Medium dia 1-1/2 inch (3 mm) (SNI) 64,500.00 m'
Pipa Galv Medium dia 2 inch P : 6 m (3,2 mm) (SNI) 468,800.00 btg
Pipa Galv Medium dia 2 inch (3,2 mm) (SNI) 78,100.00 m'
-
PIPA PVC Wavin Standard -
Pipa PVC dia. 1/2 inch type AW, tebal 22 mm, panjang 4 m 18,900.00 btg
Pipa PVC dia. 1/2 inch type AW, tebal 22 mm 4,700.00 m'
Pipa PVC dia. 3/4 inch type AW, tebal 26 mm, panjang 4 m 25,700.00 btg
Pipa PVC dia. 3/4 inch type AW, tebal 26 mm 6,400.00 m'
Pipa PVC dia. 1 inch type AW, panjang 4 m 34,800.00 btg
Pipa PVC dia. 1 inch type AW 8,700.00 m'
Pipa PVC dia. 2 inch type AW, panjang 4 m 72,000.00 btg
Pipa PVC dia. 2 inch type AW 18,000.00 m'
Pipa PVC dia. 3 inch type AW, panjang 4 m 139,500.00 btg
Pipa PVC dia. 3 inch type AW 34,800.00 m'
Pipa PVC dia. 4 inch type D, panjang 4 m 131,800.00 btg
Pipa PVC dia. 4 inch type D 32,900.00 m'
Knee 1/2" 2,200.00 Bh
Knee 3/4" 3,000.00 Bh
Knee 1" 6,300.00 Bh
Knee 2" 10,100.00 Bh
Knee 3" 14,200.00 Bh
Knee 4" 20,600.00 Bh
-
NO. NAMA BAHAN/MATERIAL HARGA SATUAN SATUAN
1 2 3 4
XII ATAP
Alumunium Foil 17,900.00 m2
Glasswool 21,400.00 roll
Roofmesh 26,600.00 m2
-
Fiber / Asbes semen gelombang 180x108x0,5 cm 54,800.00 lbr
Zinc Alume (Bahan) Gelombang Besar 75,600.00 m2
-
Genteng Metal Setara rainbow 113,900.00 Lembar
Nok 40,500.00 m1
-
Kusen Alumunium Natural Ukuran 3" x 1 1/2" 91,000.00 m1
Kusen Alumunium Natural Ukuran 4" x 1 3/4" 96,200.00 m1
Jalusi Alumunium Warna 49,500.00 m1
Frame daun Jendela Alumunium 158,400.00 m1
-
Seng gelombang 180 x 90 x 0,20 49,700.00 lbr
Sealent 15,400.00 tube
Karet List 4,900.00 m1
-
Perangkat Penangkal Petir - titik
Splitzer uk.2 44,500.00 bh
Kabel BC 75 mm2 22,000.00 m
Klem Kabel 2,700.00 bh
Pentanahan 826,900.00 ls
Bak kontrol 600 x 600 x 400 106,200.00 bh
Box Test 390,900.00 bh
-
RANGKA ATAP BAJA RINGAN -
Rangka atap baja ringan setara SMART TRUSS (terpasang) 156,500.00 m2
-
PLAFON -
Plafon Gyptile 60 x 60 (Material + Rangka Main Tee + Cross Tee + Terpasang) 110,800.00 m2
Plafon Acoustic Armstrong 60x60 (tebal 15 mm) + Rangka Main Tee + Cross Tee 176,700.00 m2
-
LIST PLANK -
List Plank GRC Uk.15 x 240 cm ; tebal 12 mm 31,500.00 m
List Plank GRC Uk.30 x 240 cm ; tebal 12 mm 33,700.00 m
-
XIII BAJA TULANGAN / PROFIL
Besi beton polos 8,500.00 kg
Besi beton ulir 8,500.00 kg
Baja IWF ex.DN SII 13,300.00 kg
Baja Canal C 28,900.00 kg
Besi Siku/Profil 40 x 40 x 4 15,200.00 kg
Besi Hollow 2 x 4 cm, rangka plafond 19,800.00 Batang
Besi Hollow 4 x 4 cm, rangka plafond 26,700.00 Batang
Besi Hollow 4 x 4 cm, rangka pagar 133,500.00 Batang
Besi Hollow 2 x 4 cm, rangka pagar 65,800.00 Batang
Besi Plat Strip 2 x 30 mm, (6 m) 11,000.00 kg
Besi Plat Strip 5 x 30 mm, (6 m) 13,300.00 kg
Sekrup Gypsum Merk Zolo 2 x 6" (isi 1.000 pieces) 79,900.00 dus
Besi Pipa stainless dia. 2" 78,900.00 m
Besi Pipa stainless dia. 1" 56,800.00 m
Alumunium composite 114,900.00 m2
Braket galvanis ACP 15,600.00 bh
Rangka alumunium composite (Almn. 4 0 x 40 x 2 mm ) 18,800.00 m
Skrup almunium 15,500.00 kg
-
NO. NAMA BAHAN/MATERIAL HARGA SATUAN SATUAN
1 2 3 4
XIV KAWAT
Kawat beton 17,100.00 kg
Paku segala ukuran (rata-rata) 15,000.00 kg
Wiremesh DM 8,dia.8x8,spasi 150x150mm,uk.5,4x2,1 m 598,400.00 lbr
Pagar BRC t = 1,20 m Ø 8 182,600.00 m1
Bondek 118,900.00 m2
-
XV KACA
Kaca bening 5 mm 109,300.00 m2
Kaca Es 5 mm 158,900.00 m2
Kaca Rayben 5 mm 139,300.00 m2
Kaca revlektif 507,100.00 m2
-
XVI LISTRIK
Kabel NYM 3x2.5 mm 11,800.00 m
Kabel NYY 4x35mm2 242,800.00 meter
Kabel NYY 4x16mm2 116,300.00 meter
Kabel NYY 4x10mm2 60,700.00 meter
Klem kabel 6,100.00 dus
Saklar tunggal 13,400.00 bh
Saklar double 18,500.00 bh
Saklar tukar 18,500.00 bh
Stop Kontak 14,200.00 bh
Lampu TL 2 x 18 watt, armatur, komplit philips 94,100.00 bh
Lampu SL 18 watt, komplit philips 29,900.00 bh
Lampu Halogen 50 Watt Merk : Philips/osram 460,000.00 buah
Lampu pagar 171,000.00 bh
Lampu Down Light + Isi SL 25 watt 84,600.00 bh
Fitting Keramik 14,800.00 bh
Panel PP-LP01, 40X60 cm2 690,000.00 bh
Panel PP-LP01, 60X80 cm2 874,000.00 unit
Penyambungan daya Listrik 1,300.00 watt
Lampu PLC 13 watt 59,800.00 bh
Lampu sorot LED 50 watt 506,000.00 bh
MCB 10 A 86,600.00 bh
Box MCB 4 group 25,300.00 bh
1 2 3 4
Huruf Stainles 20 cm 204,600.00 hrf
Huruf Stainles 15 cm 153,400.00 hrf
Tiang pancang 25x25 kelas C K-500 328,300.00 m'
Sambung TP kotak 25x25 kelas C 1,276,700.00 joint
Tiang pancang 25x25 209,700.00 m'
Tiang pancang 20x20 158,500.00 m'
Alat Pancang Hidraulic 79,000.00 m
Pengelasan/Penyambungan/Cutting Beton 74,400.00 ttk
roster beton 25,500.00 m3
Kusen pintu aluminium lengkap 1,278,700.00 unit
Pipa listrik panjang 4 m 9,700.00 btg
Stop kontak telpon 56,200.00 bh
Exhausfan 511,500.00 bh
Kitchen zinc 460,300.00 bh
Frameless tempered 12 mm 971,800.00 m2
Floor hings ex dexon 2,301,700.00 bh
Fitch fitting ex dexon 2,506,300.00 bh
Hendel stainless 460,300.00 bh
Pasang U aluminium 71,600.00 m1
RUMPUT -
Rumput Gajah Mini 20,400.00 m2
Rumput Manila ( Gebalan ) 15,300.00 m2
Eucaliptus Ø 4 - 7 cm, t = 1 - 3 m 97,100.00 phn
Tanaman Pucuk Merah 1 102,300.00 phn
Tanaman Krokol Three Colour 7,600.00 plbg
Tanaman Three Colour 7,600.00 plbg
Tanaman Sansivera 7,600.00 plbg
Tanaman Soka Jepang 25,500.00 plbg
Kiara Payung 130,200.00 phn
Pohon Glodogan Tiang T = 1.5m 186,000.00 phn
Papan kayu 3X10 cm 23,200.00 m1
List profil kayu 2X4 cm 11,100.00 m1
Plint kayu 1,5/10 20,900.00 m1
Besi Hollow 60 x 60 x 1,8 130,700.00 btg
Grendel besi + Kunci 125,500.00 set
Roda Besi 13,900.00 bh
Plat besi 6 mm untuk dudukan roda 10,700.00 kg
Besi Siku 40 x 40 x 4 untuk rel 14,900.00 kg
Pengelasan & Pengecatan hollow pagar 79,000.00 ls
Ongkos pasang Pagar Besi 162,700.00 ls
WLC elektrode 381,300.00 bh
Angkur 11,600.00 bh
Fisher 1,200.00 bh
ramp buncis 27,100.00 bh
Upah potong kaca 51,100.00 m2
Upah pasang + aksesories Jendela 162,700.00 unit
Pengelasan dengan argon 3,300.00 cm
Tangga Besi 1,860,000.00 bh
Meja Counter 1,720,500.00 bh
Angkur bout dia 19mm 127,800.00 bh
Baseplate tebal 10 mm 12,700.00 kg
XVIII UPAH
Pekerja / knek 69,000.00 hari
Tukang gali 78,200.00 hari
Kepala Tukang Batu 92,000.00 hari
Tukang Batu 82,800.00 hari
Kepala Tukang Kayu 92,000.00 hari
Tukang Kayu 82,800.00 hari
Kepala Tukang Besi 87,400.00 hari
NO. NAMA BAHAN/MATERIAL HARGA SATUAN SATUAN
1 2 3 4
Tukang Besi 78,200.00 hari
Kepala Tukang Cat 96,600.00 hari
Tukang Cat 82,800.00 hari
Mandor / pengawas 115,000.00 hari
Instalator / Tukang Listrik 92,000.00 hari
Pembantu Instalator 73,600.00 hari
Operator Alat Berat 96,600.00 hari
Pembantu Operator Alat Berat 73,600.00 hari
MANARSAR PANJAITAN
Direktur