PROGRAM
KEGIATAN
LOKASI
JUMLAH
NO URAIAN PEKERJAAN HARGA
(Rp)
DIBULATKAN Rp 1,335,823,000.00
TERBILANG : ###
"SATU MILYAR TIGA RATUS TIGA PULUH LIMA JUTA DELAPAN RATUS DUA PULUH TIGA RIBU RUPIAH "
###
###
###
###
###
###
###
RENCANA ANGGARAN BIAYA
PROGRAM 0.00
KEGIATAN 0.00
LOKASI 0.00
HARGA
JUMLAH
NO URAIAN PEKERJAAN VOLUME SATUAN KODE SATUAN
Rp Rp
1 2 3 4 5 6
A PEKERJAAN PENDAHULUAN
1 Pembuatan Papan Nama Proyek 1.00 Ls - 500,000.00 500,000.00
2 Direksi Keet & Gudang 1.00 Ls - 4,000,000.00 4,000,000.00
3 Pemasangan Bowplank 79.95 M' A.1 53,500.00 4,277,325.00
Jumlah A 8,777,325.00
B PEKERJAAN TANAH
1 Galian Tanah Biasa 138.29 M3 B.1 41,200.00 5,697,342.00
2 Urugan Tanah Kembali 45.12 M3 B.2 19,750.00 891,120.00
3 Urugan Tanah dan Pemadatan Dalam Bangunan 108.49 M3 B.3 154,400.00 16,751,535.36
4 Urugan pasir bawah pondasi 9.22 M3 B.4 202,300.00 1,865,003.70
5 Urugan pasir bawah Lantai 10.93 M3 B.4 202,300.00 2,210,860.84
Jumlah B 27,415,861.90
C PEKERJAAN PONDASI
1 Tiang Pancang Dalam 2 m + Kalang & Sunduk 100.00 Titik C.1 216,450.00 21,645,000.00
2 Pasangan Batu Kosong (Aanstamping) 18.44 M3 C.3 766,545.00 14,133,556.71
3 Pasangan Batu Gunung 1 : 4 101.52 M3 C.2 1,168,870.00 118,663,682.40
Jumlah C 154,442,239.11
D PEKERJAAN PASANGAN DAN PLESTERAN
1 Pas. Dinding Bata 1/2 camp. 1Pc : 4Ps 484.57 M2 D.1 162,523.00 78,753,363.80
2 Plesteran Camp. 1 PC : 4 PS 994.83 M2 D.2 51,223.00 50,958,228.31
3 Acian 994.83 M2 D.3 46,723.00 46,481,488.81
4 Acian Slof f& Kolom 92.14 M2 D.3 46,723.00 4,305,057.22
5 Pas. Lantai Keramik 40/40 191.14 M2 J.1 245,576.20 46,939,312.08
6 Pas. Lantai Keramik 30/30 15.09 M2 J.2 240,101.20 3,623,247.16
7 Pas. Keramik Dinding KM/WC 20/25 33.90 M2 J.4 197,582.00 6,698,820.13
8 Pas. Lantai Keramik 20/20 19.80 M2 J.3 229,101.20 4,536,203.76
9 Pas. Batu Alam 15.42 M2 J.5 484,375.00 7,469,062.50
10 Pek. Saluran Parit 80.68 M' H.1 133,415.00 10,763,922.20
11 Pek. Pemasangan Grill Saluran 80.68 M' - 300,000.00 24,204,000.00
Jumlah D 284,732,705.97
E PEKERJAAN BETON
1 Cor Rabat Bawah Lantai Keramik 15.30 M3 F.1 1,215,870.00 18,602,902.19
2 Cor Rabat Selasar + Acian 5.56 M3 F.1 1,215,870.00 6,765,482.46
3 Cor Kolom Praktis k1 (13/13) 0.68 M3 F.9 9,932,408.02 6,714,307.82
4 Cor Kolom K2 ( 20x20 ) 5.12 M3 F.11 9,373,653.78 47,993,107.35
5 Cor Kolom K3 ( 30/30) 1.93 M3 F.12 5,603,142.46 10,791,652.37
6 Cor Sloof ( 20x30 ) Kg/M3 9.71 M3 F.13 5,457,474.02 52,981,157.76
7 Cor Sloof ( 30x30 ) 1.01 M3 F.14 4,336,161.99 4,390,364.01
8 Cor Dak Teras (12 Cm) Kg/M3 4.56 M3 F.17 11,934,440.85 54,424,630.59
9 Cor Ring Balok ( 20x30 ) Kg/M3 11.72 M3 F.15 6,581,410.68 77,128,868.09
10 Cor Ring Balok ( 20x20 ) 0.48 M3 F.16 7,588,547.06 3,648,573.43
11 Cor kanopi 1.67 M3 F.18 10,159,669.43 16,942,264.75
12 Cor Balok latei ( 13X13 ) 0.88 M3 F.10 9,932,408.02 8,750,421.67
Jumlah E 309,133,732.50
HARGA
JUMLAH
NO URAIAN PEKERJAAN VOLUME SATUAN KODE SATUAN
Rp Rp
1 2 3 4 5 6
F PEKERJAAN PINTU DAN JENDELA
1 Pek. Kosen Pintu dan Jendela Bengkirai 2.31 M3 E.1 9,257,500.00 21,413,291.81
2 Daun Pintu Panil Bengkirai 22.46 M2 E.2 622,750.00 13,989,456.00
3 Daun Pintu Panil Ulin (WC) 6.53 M2 E.3 642,750.00 4,198,764.38
4 Daun Jendela Kaca Kayu Bengkirai 29.54 M2 E.4 604,522.50 17,859,105.96
5 Pas.Kaca 5 mm 19.79 M2 E.5 217,375.00 4,301,677.35
6 Kunci tanam 16.00 Buah I.1 357,800.00 5,724,800.00
7 Pas. Door Closer 14.00 Buah I.7 316,075.00 4,425,050.00
8 Pas. Door Stoper 14.00 Buah I.8 163,215.00 2,285,010.00
9 Pas. Door Holder 14.00 Buah I.9 416,075.00 5,825,050.00
10 Engsel pintu 63.00 Buah I.2 39,822.50 2,508,817.50
11 Engsel jendela 110.00 Buah I.3 28,215.00 3,103,650.00
12 Grendel jendela 114.00 Buah I.4 34,822.50 3,969,765.00
13 Handle jendela 57.00 Buah I.5 44,822.50 2,554,882.50
14 Kait/hak angin 110.00 Buah I.6 34,822.50 3,830,475.00
Jumlah F 95,989,795.49
G PEKERJAAN KUDA-KUDA DAN ATAP
1 Rangka Kap/Kuda-kuda Baja Ringan 418.69 M2 G.2 193,470.20 81,004,637.80
2 Pek. Penutup Atap (Setara Sakura) 418.69 M2 G.1 126,225.00 52,849,536.55
3 Bubungan Atap (Setara Sakura) 52.67 M' G.4 83,650.00 4,405,845.50
4 Pek. Lisplank 75.78 M' G.3 99,825.00 7,564,738.50
5 Pas. Talang Datar / Jurai 9.40 M' G.9 93,025.00 874,435.00
6 Pekerjaan Gewel 2.00 Bh - 2,000,000.00 4,000,000.00
Jumlah G 150,699,193.34
H PEKERJAAN RANGKA PLAFOND DAN PENUTUP PLAFOND
1 Penutup Plafond Gypsum Board 9 mm (dalam) 231.08 M2 G.6 101,700.00 23,500,988.55
2 Penutup Plafond Calcyboard 3,5 mm (Luar) 55.84 M2 G.7 49,137.50 2,744,073.86
3 Pek. Rangka Plafond 286.93 M2 G.5 140,090.00 40,195,505.37
4 List Plafond 400.88 M' G.8 39,625.00 15,884,870.00
Jumlah H 82,325,437.78
I PEKERJAAN CAT-CATAN
1 Pek. Cat Kilap Kosen, Daun Pintu, Jendela & Boven 96.18 M2 K.1 49,735.00 4,783,512.30
2 Mengecat Dinding (Dalam) 524.09 M2 K.3 41,375.00 21,684,120.31
3 Mengecat Dinding (Luar) 264.15 M2 K.2 43,975.00 11,615,996.25
4 Mengecat Plafond 286.93 M2 K.3 41,375.00 11,871,575.66
Jumlah I 49,955,204.52
J PEKERJAAN INSTALASI LISTRIK
1 Lampu TL 2 x 40 Watt + accesories 17.00 Buah - 700,000.00 11,900,000.00
2 Lampu PL 18 Watt + accesories 6.00 Buah - 200,000.00 1,200,000.00
3 Saklar Doble 5.00 Buah - 150,000.00 750,000.00
4 Saklar Triple 9.00 Buah - 150,000.00 1,350,000.00
5 Stop Kontak 13.00 Buah - 150,000.00 1,950,000.00
6 Instalasi Listrik & Stop Kontak 36.00 Titik L.1 223,410.00 8,042,760.00
7 Box MCB 3 Group Lengkap 1.00 Unit - 400,000.00 400,000.00
Jumlah J 25,592,760.00
K PEKERJAAN SANITASI
1 Kran Air 3.00 Bh H.6 88,925.00 266,775.00
2 Kloset Jongkok 3.00 Bh H.2 609,890.00 1,829,670.00
3 Pasangan Bak Mandi keramik 3.00 Bh H.8 1,791,200.00 5,373,600.00
4 Floor drain 3.00 Bh H.7 73,800.00 221,400.00
5 Pipa PVC 3/4" 45.00 M' H.3 20,746.50 933,592.50
6 Pipa PVC 2" 35.00 M' H.4 51,187.50 1,791,562.50
7 Pipa PVC 4" 45.00 M' H.5 108,981.00 4,904,145.00
8 Septicktank 2.00 Unit - 4,000,000.00 8,000,000.00
9 Pek. Bak Kontrol 10.00 Bh - 200,000.00 2,000,000.00
Jumlah K 25,320,745.00
DAFTAR ANALISA HARGA SATUAN
PROGRAM 0.00
KEGIATAN 0.00
LOKASI 0.00
HARGA BIAYA BIAYA JUMLAH
KODE URAIAN PEKERJAAN SATUAN UPAH BAHAN HARGA
ANALISA (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
A PEKERJAAN PENDAHULUAN
A.1 1 M' Mengukur dan Memasang Bowplank
0.0100 M3 Kayu Meranti 5/7 3,000,000.00 30,000.00
0.0200 Kg Paku 20,000.00 400.00
0.0040 M3 Kayu Papan Meranti 2,800,000.00 11,200.00
0.0500 Oh Tukang 110,000.00 5,500.00
0.0100 Oh Kep. Tukang 125,000.00 1,250.00
0.0500 Oh Pekerja 90,000.00 4,500.00
0.0050 Oh Mandor 130,000.00 650.00
Jumlah 11,900.00 41,600.00 53,500.00
B. PEKERJAAN PASIR DAN TANAH
B.1 1 M3 Galian Tanah Biasa sedalam 1 m
0.4000 Oh Pekerja 90,000.00 36,000.00
0.0400 Oh Mandor 130,000.00 5,200.00
Jumlah 41,200.00 41,200.00
B.2 1 M3 Urugan Tanah Kembali
0.1920 Oh Pekerja 90,000.00 17,280.00
0.0190 Oh Mandor 130,000.00 2,470.00
Jumlah 19,750.00 19,750.00
B.3 1 M3 Urugan Tanah dan Pemadatan Dalam Bangunan
1.2000 M3 Tanah Urug 60,000.00 72,000.00
0.8000 Oh Pekerja 90,000.00 72,000.00
0.0800 Oh Mandor 130,000.00 10,400.00
Jumlah 82,400.00 72,000.00 154,400.00
B.4 1 M3 Urugan Pasir Bawah Lantai
1.2000 M3 Pasir Urug 145,000.00 174,000.00
0.3000 Oh Pekerja 90,000.00 27,000.00
0.0100 Oh Mandor 130,000.00 1,300.00
Jumlah 28,300.00 174,000.00 202,300.00
C PEKERJAAN PONDASI
C.1 1 Titik Tiang Pancang Kedalaman 2 M
0.0200 M3 Kayu Ulin 10/10 5,000,000.00 100,000.00
0.0030 m3 Kayu Ulin 5/10 5,000,000.00 15,000.00
0.0080 m3 Papan Ulin 2/20 6,000,000.00 48,000.00
0.2500 Oh Tukang 110,000.00 27,500.00
0.0250 Oh Kep. Tukang 125,000.00 3,125.00
0.2500 Oh Pekerja 90,000.00 22,500.00
0.0025 Oh Mandor 130,000.00 325.00
Jumlah 53,450.00 163,000.00 216,450.00
C.2 1 M3 Pasangan Batu Gunung 1 : 4
1.1000 M3 Batu Gunung 500,000.00 550,000.00
163.0000 Kg Semen 1,740.00 283,620.00
0.5200 M3 Pasir Pasang 225,000.00 117,000.00
0.6000 Oh Tukang 110,000.00 66,000.00
0.0600 Oh Kep. Tukang 125,000.00 7,500.00
1.5000 Oh Pekerja 90,000.00 135,000.00
0.0750 Oh Mandor 130,000.00 9,750.00
Jumlah 218,250.00 950,620.00 1,168,870.00
F PEKERJAAN BETON
F.1 1 M3 Lantai Cor Rabat (camp 1 : 3 : 5)
0.8700 M3 Kerikil 540,000.00 469,800.00
0.5200 M3 Pasir Pasang 225,000.00 117,000.00
218.0000 Kg Semen 1,740.00 379,320.00
0.2500 Oh Tukang 90,000.00 22,500.00
0.0250 Oh Kep. Tukang 110,000.00 2,750.00
1.6500 Oh Pekerja 130,000.00 214,500.00
0.0800 Oh Mandor 125,000.00 10,000.00
Jumlah 249,750.00 966,120.00 1,215,870.00
F.2 1 M3 Cor Beton K-225
0.6500 M3 Kerikil 540,000.00 351,000.00
0.6500 M3 Pasir Pasang 225,000.00 146,250.00
388.0000 Kg Semen 1,740.00 675,120.00
1.0000 Oh Tukang 90,000.00 90,000.00
0.1000 Oh Kep. Tukang 110,000.00 11,000.00
6.0000 Oh Pekerja 130,000.00 780,000.00
0.3000 Oh Mandor 125,000.00 37,500.00
Jumlah 918,500.00 1,172,370.00 2,090,870.00
F.3 1 M2 Pasang Bekesting Untuk Pondasi
0.0400 M3 Kayu Bekisting 2,500,000.00 100,000.00
0.3000 Kg Paku Biasa 20,000.00 6,000.00
0.1000 Ltr Minyak Bekesting 5,000.00 500.00
0.2600 Oh Tukang 90,000.00 23,400.00
0.0260 Oh Kep. Tukang 110,000.00 2,860.00
0.3000 Oh Pekerja 130,000.00 39,000.00
0.0050 Oh Mandor 125,000.00 625.00
Jumlah 65,885.00 106,500.00 172,385.00
F.4 1 M2 Pasang Bekesting Untuk Sloof
0.0450 M3 Kayu Bekisting 2,500,000.00 112,500.00
0.3000 Kg Paku Biasa 20,000.00 6,000.00
0.1000 Ltr Minyak Bekesting 5,000.00 500.00
0.0260 Oh Tukang 90,000.00 2,340.00
0.0260 Oh Kep. Tukang 110,000.00 2,860.00
0.3000 Oh Pekerja 130,000.00 39,000.00
0.0050 Oh Mandor 125,000.00 625.00
Jumlah 44,825.00 119,000.00 163,825.00
F.5 1 M2 Pasang Bekesting Untuk Kolom
0.0400 M3 Kayu Bekisting 2,500,000.00 100,000.00
0.3000 Kg Paku Biasa 20,000.00 6,000.00
0.1000 Ltr Minyak Bekesting 5,000.00 500.00
0.3500 Lbr Plywood 9 mm 125,000.00 43,750.00
0.2600 Oh Tukang 90,000.00 23,400.00
0.0260 Oh Kep. Tukang 110,000.00 2,860.00
0.5200 Oh Pekerja 130,000.00 67,600.00
0.0260 Oh Mandor 125,000.00 3,250.00
Jumlah 97,110.00 150,250.00 247,360.00
H. PEKERJAAN SANITASI
H.1 1 M' Parit Pas. Batu Bata Camp. 1 : 4
30.0000 Bh Batu Bata 1,300.00 39,000.00
6.0000 Kg Semen 1,740.00 10,440.00
0.1200 M3 Pasir Pasang 225,000.00 27,000.00
0.1500 Oh Tukang 110,000.00 16,500.00
0.0150 Oh Kep. Tukang 125,000.00 1,875.00
0.4000 Oh Pekerja 90,000.00 36,000.00
HARGA BIAYA BIAYA JUMLAH
KODE URAIAN PEKERJAAN SATUAN UPAH BAHAN HARGA
ANALISA (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
0.0200 Oh Mandor 130,000.00 2,600.00
Jumlah 56,975.00 76,440.00 133,415.00
H.2 1 Bh Pasang Kloset Jongkok
1.0000 Bh Kloset Jongkok 280,000.00 280,000.00
8.0000 Bh Batu Bata 1,300.00 10,400.00
6.0000 Kg Semen 1,740.00 10,440.00
0.0100 M3 Pasir Pasang 225,000.00 2,250.00
1.5000 Oh Tukang 110,000.00 165,000.00
0.3000 Oh Kep. Tukang 125,000.00 37,500.00
1.0000 Oh Pekerja 90,000.00 90,000.00
0.1100 Oh Mandor 130,000.00 14,300.00
Jumlah 306,800.00 303,090.00 609,890.00
H.3 1 M' Pasang Pipa PVC Dia 3/4"
1.2000 Bh Pipa PVC 3/4" 6,125.00 7,350.00
35.0% Hrg Pipa Perlengkapan 7,350.00 2,572.50
0.0600 Oh Tukang 110,000.00 6,600.00
0.0060 Oh Kep. Tukang 125,000.00 750.00
0.0360 Oh Pekerja 90,000.00 3,240.00
0.0018 Oh Mandor 130,000.00 234.00
Jumlah 10,824.00 9,922.50 20,746.50
H.4 1 M' Pasang Pipa PVC Dia 2"
1.2000 Bh Pipa PVC 2" 21,575.00 25,890.00
35.0% Hrg Pipa Perlengkapan 25,890.00 9,061.50
0.0900 Oh Tukang 110,000.00 9,900.00
0.0090 Oh Kep. Tukang 125,000.00 1,125.00
0.0540 Oh Pekerja 90,000.00 4,860.00
0.0027 Oh Mandor 130,000.00 351.00
Jumlah 16,236.00 34,951.50 51,187.50
H.5 1 M' Pasang Pipa PVC Dia 4"
1.2000 Bh Pipa PVC 4" 57,250.00 68,700.00
35.0% Hrg Pipa Perlengkapan 68,700.00 24,045.00
0.0900 Oh Tukang 110,000.00 9,900.00
0.0090 Oh Kep. Tukang 125,000.00 1,125.00
0.0540 Oh Pekerja 90,000.00 4,860.00
0.0027 Oh Mandor 130,000.00 351.00
Jumlah 16,236.00 92,745.00 108,981.00
H.6 Memasang 1 Buah Kran Air
1.000 Bh Kran 75,000.00 75,000.00
0.025 Bh Seal Tape 5,000.00 125.00
0.100 Oh Tukang Batu 110,000.00 11,000.00
0.010 Oh Kepala Tukang 125,000.00 1,250.00
0.010 Oh Pekerja 90,000.00 900.00
0.005 Oh Mandor 130,000.00 650.00
Jumlah 13,800.00 75,125.00 88,925.00
PROGRAM 0.00
KEGIATAN 0.00
LOKASI 0.00
HARGA SATUAN
NO JENIS BAHAN SATUAN BAHAN KETERANGAN
( Rp )
A. AGREGAT KASAR, BAHAN PEREKAT DAN BAHAN JADINYA
1 Tanah urug m3 60,000.00 DIPROYEK
2 Pasir urug m3 145,000.00 DIPROYEK
3 Pasir pasang (Tenggarong) m3 225,000.00 DIPROYEK
5 Batu kerikil / koral (Palu) m3 540,000.00 DIPROYEK
6 Batu gunung m3 500,000.00 DIPROYEK
7 Batu bata merah Bh 1,300.00 DIPROYEK
8 Batu alam (Sisir) M2 350,000.00 DIPROYEK
9 Semen Warna Kg 2,500.00 DIPROYEK
10 Semen Kg 1,740.00 DIPROYEK
B. BAHAN FINISHING
1 Meni kayu kg 28,000.00 DIPROYEK
2 Cat tembok Interior (Setara mowilex emulsion) kg 40,000.00 DIPROYEK
3 Cat tembok exterior (setara mowilex weathercoat) kg 50,000.00 DIPROYEK
4 Cat dasar tembok (setara mowilex undercoat) kg 40,000.00 DIPROYEK
5 Cat kayu/minyak (Setara Dulux) kg 40,000.00 DIPROYEK
7 Thiner A spesial (setara avian) kg 28,000.00 DIPROYEK
9 Plamur tembok kg 22,000.00 DIPROYEK
10 Plamur kayu kg 28,000.00 DIPROYEK
11 Minyak Bekesting Ltr 5,000.00 DIPROYEK
13 Dempul kg 28,000.00 DIPROYEK
14 Kuas Bh 9,000.00 DIPROYEK
C. BAHAN KAYU BERIKUT BAHAN JADINYA
1 Papan Meranti m3 2,800,000.00 DIPROYEK
2 Balok Meranti m3 3,000,000.00 DIPROYEK
3 Kayu Bekisting m3 2,500,000.00 DIPROYEK
4 Balok Bengkirai (Kosen) m3 5,500,000.00 DIPROYEK
5 Balok Ulin 10/10 m3 5,000,000.00 DIPROYEK
6 Balok Ulin 5/10 m3 5,000,000.00 DIPROYEK
7 Balok Ulin 5/7 m3 5,000,000.00 DIPROYEK
8 Balok Ulin 8/8 m3 5,000,000.00 DIPROYEK
9 Papan Ulin 2/20 m3 6,000,000.00 DIPROYEK
10 Plywood ukuran 9 mm lembar 125,000.00 DIPROYEK
11 Gypsum Board 9 mm lembar 160,000.00 DIPROYEK
12 Kalsi Board 3,5 mm lembar 75,000.00 DIPROYEK
13 Papan Grc Tebal 4 mm M1 55,000.00 DIPROYEK
14 List Profil Gypsum M' 25,000.00 DIPROYEK
D BAHAN LANTAI DAN PELAPIS DINDING
1 Tegel Keramik 40 x 40 cm M2 100,000.00 DIPROYEK
2 Tegel Keramik 30 x 30 cm M2 95,000.00 DIPROYEK
3 Tegel keramik 20 x 20 cm M2 85,000.00 DIPROYEK
4 Tegel keramik 20 x 25 cm M2 90,000.00 DIPROYEK
E BAHAN LOGAM, PAKU DAN KACA
1 Paku segala ukuran kg 20,000.00 DIPROYEK
2 Paku seng kg 27,500.00 DIPROYEK
3 Paku Skrup Kg 22,000.00 DIPROYEK
4 Paku kecil plywood kg 27,500.00 DIPROYEK
5 Kawat ikat kg 18,000.00 DIPROYEK
6 Besi beton kg 13,500.00 DIPROYEK
7 Kaca Bening 5 mm M2 130,000.00 DIPROYEK
8 Besi Grill M' 200,000.00 DIPROYEK
9 Canal C75.75 Btg 25,000.00 DIPROYEK
10 Reng (Type U) 0,4 TCT Btg 20,000.00 DIPROYEK
11 Screw 12 - 14 x 20 Bh 150.00 DIPROYEK
12 Screw 10 - 16 x 16 Bh 130.00 DIPROYEK
13 L - Braket BH 350.00 DIPROYEK
14 Dynabolt Bh 200.00 DIPROYEK
15 Seng Bjls Lbr 20,500.00 DIPROYEK
16 Hollow 4/4 M1 30,000.00 DIPROYEK
HARGA SATUAN
NO JENIS BAHAN SATUAN BAHAN KETERANGAN
( Rp )
PROGRAM 0.00
KEGIATAN 0.00
LOKASI 0.00
100 %
A PEKERJAAN PENDAHULUAN 8,777,325.00 0.72 0.72 ###
B PEKERJAAN TANAH 27,415,861.90 2.26 0.45 0.45 0.45 0.45 0.45 ###
C PEKERJAAN PONDASI 154,442,239.11 12.72 3.18 3.18 3.18 3.18 75 % ###
D PEKERJAAN PASANGAN DAN PLESTERAN 284,732,705.97 23.45 3.91 3.91 3.91 3.91 3.91 3.91 ###
E PEKERJAAN BETON 309,133,732.50 25.46 6.36 6.36 6.36 6.36 ###
F PEKERJAAN PINTU DAN JENDELA 95,989,795.49 7.90 2.63 2.63 2.63 50 % ###
G PEKERJAAN KUDA-KUDA DAN ATAP 150,699,193.34 12.41 6.20 6.20 ###
H PEKERJAAN RANGKA PLAFOND DAN PENUTUP PLAFOND 82,325,437.78 6.78 4.07 1.36 1.36 ###
I PEKERJAAN CAT-CATAN 49,955,204.52 4.11 1.37 1.37 1.37 25 % ###
0.00
Di buat Oleh :
0.00
0.00
0.00
Direktur
SPESIFIKASI TEKNIS
PENINGKATAN SARANA DAN PRASARANA APARATUR
(PEMBANGUNAN KANTOR DESA SUMBER SARI)
LOKASI : KECAMATAN KOTA BANGUN
4 Kusen + Daun Pintu dan Jendela Kusen Kayu Bengkirai/Ulin mutu A Standard PPKI
Daun Pintu/Jendela Kayu Bengkirai/Ulin mutStandard PPKI
ex San Ei Chroom