Anda di halaman 1dari 3

Analisa Harga ACP Terpasang /m2 Tahun 2019

No Rincian Harga Satuan


1 Seven PE (Polyester) 0.21MM 200,000
2 Rangka Hollow 45,000
3 Sealant / Lem Aluminium 25,000
4 Aksesories, Scrup, Backup 10,000
5 Besi Siku – Bracket 15,000
6 Upah Tenaga Kerja 150,000
7 Pasang Scaffolding 20,000
8 Total Material + Upah 465,000
9 Waste Material 10% 46,500

Total Cost 511,500


Margin 30% 153,450
Total (Harga Jual) 664,950
1 Tenaga Kerja
- Pekerja OH 0.6 150,000.00
- Tukang Besi / Las OH 0.35 150,000.00
- Kepala Tukang Besi / Las OH 0.07 200,000.00
- Mandor OH 0.007 200,000.00
Sub Total

2 Peralatan dan Alat Bantu


- Sewa Stager (2set) set 0.02 55,000.00
- Listrik Kerja ls 1 5,000.00
- Alat bantu lainnya ls 1 10,000.00
Sub Total

3 Material dan Bahan


- Alumunium Composite m2 1.1 340,277.78
- Hollow Besi Galvanis Uk 4 x 4 x 1 mm btg 0.8 115,000.00
- Braket Siku / spigot / stiffener btg 0.267 60,000.00
- Paku Skrup Beton Kg 0.08 21,600.00
- Paku Skrup Kg 0.11 21,600.00
- Sealant tube 0.25 25,000.00
Sub Total
4 Bahan Bakar & Pelumas
Sub Total

5 Lain-Lain
Sub Total

Jumlah Harga A
Over Head and Profit B= A x 10%
Total Harga C=A+B
Harga Satuan Pekerjaan C:P

Untuk Catatan :

Harga Upah perkiraan untuk upah umumnya di wilayah Jabodetabek, sedangkan untuk upah di daerah lainnya bisa menyesua

Untuk harga Composit Panel estimasi nya dari harga Produk Seven PVDF yang berlaku dari distributor dengan harga indeks U
90,000.00
52,500.00
14,000.00
1,400.00
157,900.00

1,100.00
5,000.00
10,000.00
16,100.00

374,305.56 340,277.78
92,000.00
16,020.00
1,728.00
2,376.00
6,250.00
492,679.56

666,679.56

666,679.56
66,667.96
733,347.51
733,347.51

upah di daerah lainnya bisa menyesuaikan dengan harga standar di daerah tersebut.

ari distributor dengan harga indeks US $ 29/m2 = 29 x Rp. 14.500,- = Rp. 420.500,-

Anda mungkin juga menyukai