Anda di halaman 1dari 2

NO URAIAN SATUAN KOEF HARGA SATUAN SUB JUMLAH

(RP) (RP)
PEKERJAAN LISTRIK
1M' Pekerjaan Ducting PU/PIR

Bahan :
-PU duct / Polyisocianurate M2 0.208 765,000 159,426
-Invisible flanged PVC M’ 0.330 55,000 18,150
-Bayonet PVC M' 0.170 36,000 6,120
-Covering angle PVC Bh 0.800 5,500 4,400
-Panel glue Ls 0.130 570,000 74,100
-Sealent Ls 0.108 68,000 7,344
1
-Aluminium tape Ls 0.070 68,000 4,760
-Accessories Ls 0.010 15,675
-Support / Hanger Ls 0.010 15,675
-Material bantu Ls 0.015 23,513

Tenaga Kerja :
-Pembantu instalator org/hr 0.167 150,000 25,050
-Instalator org/hr 0.21 180,000 37,800
-Mandor org/hr 0.09 200,000 18,000
Jumlah Harga :
Keuntungan 10% :
Jumlah Harga :

HARGA SATUAN SUB JUMLAH


NO URAIAN SATUAN KOEF (RP) (RP)
PEKERJAAN LISTRIK
1M' Pekerjaan Ducting BJLS

Bahan :
-BJLS 60 (1.2m x 25m) M2 1.250 221,333 276,667
-Glasswoll density 24 (1.2m x 15m) M2 1.100 40,278 44,306
-Aluminium foil (1.2m x 60m) M2 1.100 11,889 13,078
-Accessories Ls 0.100 27,350
1
-Support / Hanger Ls 0.100 27,350
-Material bantu Ls 0.150 41,025

Tenaga Kerja :
-Pembantu instalator org/hr 0.167 150,000 25,050
-Instalator org/hr 0.21 180,000 37,800
-Mandor org/hr 0.09 200,000 18,000
Jumlah Harga :
Keuntungan 10% :
Jumlah Harga :
JUMLAH (RP)

329,163

80,850
410,013
41,001
451,014

JUMLAH (RP)

429,775

80,850
510,625
51,063
561,688