WORK BREAKDOWN STRUCTURE (WBS)

PROJEK PEMASANGAN KABEL FIBER


OPTIK

PENYEDIAAN PEMASANGAN DAN


SITE VISIT DESIGN PERALATAN DAN PENGUJIAN
BAHAN

SAFETY VEST, PEMASANGAN MENYEDIAKAN SPLICING CORE


SAFETY HELMET DIBUAT DARI BILIK KABEL FIBER OPTIK DENGAN
DAN SAFETY BOOTS FIBER OPTIK (LOOSE TUBE 12 MENGGUNAKAN
CORE) MESIN SPLICING

MEMBUAT SITE MEMBUAT


SURVEY SEBELUM MESIN SPLICING PENGUJIAN
PADESTAL FUSION ARC, VDE
MEMULAKAN MENGGUNAKAN
PROJEK SHEARS CUTTER VISUAL FAULT
LOCATOR

MENGGUNAKAN
MEASURING PENGUJIAN
WHEEL SEMASA MENGGUNAKAN
SITE SURVEY KIMWIPES TISU,
VFL (VISUAL FAULT
DILAKUKAN ALCOHOL, CLEAVER,
PROTECTION SLEEVE LOCATOR) , OTDR,
LIGTH SOURCE
POWER METER

VISUAL FAULT
LOCATOR, POWER
METER, MESIN
OTDR