NO URAIAN PEKERJAAN
VOL. SAT.
1 2 3
I PEKERJAAN PERSIAPAN
III.A Core
IV PEKERJAAN LAIN-LAIN
TOTAL
PROGRES RENCANA MINGGUAN (%)
RENCANA
AKUMULASI PROGRES RENCANA MINGGUAN (%)
RENCANA JADWAL
ONTRAK BULAN KE 1 BULAN KE 2
Bobot
(%) M1 M2 M3 M4 M5 M6 M7 M8
6 7 8 9 10 11 12 13
1.17 0.051
0.73 0.032
17.729
- -
13.516
2.66 0.66 0.66 0.66 0.66
9.303
0.62 0.31 0.31 5.172
4.585
3.468
2.396
1.422
0.225
13.516
9.303
4.585 5.172
3.468
2.396
0.36 0.18 0.18 1.422
0.225
100.00
0.225 1.198 0.973 1.073 1.117 0.587 4.131 4.213
0.225 1.422 2.396 3.468 4.585 5.172 9.303 13.516
CANA JADWAL PELAKSANAAN PEKERJAAN
BULAN KE 3 BULAN KE 4 BULAN KE 5
14 15 16 17 18 19 20 21 22
47.221
0.389 0.389 0.389 0.389 0.389 0.389 0.389 0.389 0.389
43.008
38.795
1.689 1.689 1.689 1.689 1.689 34.581
1.689 1.689 1.689 1.689
13.516
9.303
13.516
9.303
23 24 25 26 27 28 29 30 31
95
91.889
87.720
75.081
70.867
0.044 0.044 0.044 0.044 0.044 0.044 0.044 0.044 0.044
67.062
0.135 0.135 0.135 63.2570.135 0.135 0.135 0.135 0.135 0.135
47.221
0.389 0.389 0.389 0.389 0.389 0.389 0.389 0.389 0.389
32 33 34 35 1019
99.827 100.000
100% 0 -
95.923
87.720 90% 0 -
.507 0.408 0.408 0.408 22 8.98
80% 0 -
0 -
70% 22 0.97
0.135 22 2.97
50% 0 -
40% 0 -
10% 4 2.66
2 0.62
0% 2 0.36
-
-
ADDEN
DUM II
KONTRAK
NO URAIAN PEKERJAAN
VOL. SAT.
1 2 3
I PEKERJAAN PERSIAPAN
III.A Core
IV PEKERJAAN LAIN-LAIN
TOTAL
PROGRES RENCANA MINGGUAN (%)
RENCANA
AKUMULASI PROGRES RENCANA MINGGUAN (%)
RENCANA JADWAL
ONTRAK BULAN KE 1 BULAN KE 2
Bobot
(%) M1 M2 M3 M4 M5 M6 M7 M8
6 7 8 9 10 11 12 13
1.09 0.047
0.74 0.032
18.996
- - 14.838
5.978 6.602
4.440
2.946
0.28 0.14 0.14 1.651
0.178
100.00
0.178 1.473 1.296 1.493 1.538 0.624 4.079 4.158
0.178 1.651 2.946 4.440 5.978 6.602 10.680 14.838
CANA JADWAL PELAKSANAAN PEKERJAAN
BULAN KE 3 BULAN KE 4 BULAN KE 5
14 15 16 17 18 19 20 21 22
48.103
0.395 0.395 0.395 0.395 0.395 0.395 0.395 43.945
0.395 0.395
39.787
14.838
10.680
10.680
23 24 25 26 27 28 29 30 31
96
92.029
87.915
75.441
71.283
0.045 0.045 0.045 0.04567.5670.045 0.045 0.045 0.045 0.045
48.103
0.395 0.395 0.395 0.395 0.395 0.395 0.395 0.395 0.395
32 33 34 35 1019
99.849 100.000
100% 0 -
96.005
87.915 90% 0 -
.757 0.442 0.442 0.442 22 9.72
80% 0 -
0 -
70% 22 0.98
0.137 22 3.01
50% 0 -
40% 0 -
10% 4 4.21
2 0.49
0% 2 0.28
-
-
ADDEN
DUM II
REKAPITULASI
RENCANA ANGGARAN BIAYA
A JUMLAH 39,901,237,424.50
B PPN (11%) 4,389,136,116.70
C JUMLAH (A + B) 44,290,373,541.20
D DIBULATKAN 44,290,373,000.00
A JUMLAH 50,441,206,362.58
B PPN (11%) 5,548,532,699.88
C JUMLAH (A + B) 55,989,739,062.46
D DIBULATKAN 55,989,739,000.00
4.3.3
Alat Pelindung Kerja dan Alat Pelindung Diri
4.3.3.1 Tali keselamatan (Life Line) 1.00 Ls 1,000,000.00 1,000,000.00
4.3.3.2 Pembatas area (Restricted Area) 1.00 Ls 2,500,000.00 2,500,000.00
4.3.3.3 Helm pelindung (Safety Helmet) 25.00 Pcs 125,000.00 3,125,000.00
4.3.3.4 Rompi keselamatan (Safety Vest) 25.00 Pcs 150,000.00 3,750,000.00
4.3.3.5 Sepatu keselamatan (Safety Shoes) 25.00 Pasang 500,000.00 12,500,000.00
4.3.3.6 Sepatu keselamatan (Rubber Safety Shoes and Toe Cap) 25.00 Pasang 145,000.00 3,625,000.00
4.3.3.7 Sarung tangan (Safety Gloves) 50.00 Pasang 25,000.00 1,250,000.00
4.3.3.8 Jaket Pelampung (Life Vest) 25.00 Pcs 100,000.00 2,500,000.00
4.3.4 Asuransi dan Perijinan :
4.3.4.1 BPJS Ketenagakerjaan Dan Keselamatan Kerja 1.00 Ls 33,000,000.00 33,000,000.00
4.3.5 Personel Keselamatan Konstruksi
4.3.5.1 Petugas P3K 8.00 OB 3,500,000.00 28,000,000.00
4.3.6
Fasilitas sarana, prasarana dan alat kesehatan
4.3.6.1 Peralatan P3K (Kotak P3K, obat luka, perban, dll) 1.00 Ls 5,400,000.00 5,400,000.00
4.3.7 Rambu-rambu
4.3.7.1 Rambu petunjuk 5.00 Buah 200,000.00 1,000,000.00
4.3.7.2 Rambu larangan 5.00 Buah 200,000.00 1,000,000.00
4.3.7.3 Rambu peringatan 5.00 Buah 200,000.00 1,000,000.00
4.3.7.4 Rambu kewajiban 5.00 Buah 200,000.00 1,000,000.00
4.3.7.5 Rambu Informasi 5.00 Buah 200,000.00 1,000,000.00
4.3.8 Konsultansi dengan Ahli terkait Keselamatan Konstruksi
4.3.8.1 Ahli K3 Konstruksi 10.00 OJ 1,700,000.00 17,000,000.00
Catatan :
1. Harga Pekerja Sudah Mengikuti Harga Kab. Serang Terbaru
2. Harga Batu sudah dirubah ke 180k tapi masih tanpa dasar
3. Analisa Galian diubah dan menghilangkan DT
RENCANA ANGGARAN BIAYA
Catatan :
1. Harga Pekerja Sudah Mengikuti Harga Kab. Serang Terbaru
2. Harga Batu sudah dirubah ke 180k tapi masih tanpa dasar
3. Analisa Galian diubah dan menghilangkan DT
RENCANA ANGGARAN BIAYA
Catatan :
1. Harga Pekerja Sudah Mengikuti Harga Kab. Serang Terbaru
2. Harga Batu sudah dirubah ke 180k tapi masih tanpa dasar
3. Analisa Galian diubah dan menghilangkan DT
TABEL HARGA BAHAN
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Pekerjaan : Penanganan Muara Sungai Ciujung Kab. Serang
Lokasi : Kab. Serang
Tahun Anggaran : 2022
2 Batu 650 kg - 800 kg m3 225,000.00 Harga Pasar (Batu Banten) 238,500.00 269,500.00 250,000.00 245,000.00 225,000.00
3 Batu Belah m3 231,000.00 Harga Kontrak Terdahulu (PT. NKE) 437,104.00 322,800.00 231,000.00 300,000.00 305,000.00
4 Batu Pecah m3 284,875.00 Harga Kontrak Terdahulu (PT. NKE) 369,353.00 360,800.00 284,875.00 355,300.00 295,000.00 290,000.00
6 Beton Ready mix K-250 m3 1,236,600.00 SSH Banten 2022 1,632,712.00 1,236,600.00 1,650,000.00 1,650,000.00
8 Cerucuk Dolken m' 13,100.00 Harga Kontrak Terdahulu (PT. NKE) 15,000.00 26,000.0 27,400.00 13,100.00
9 Pasir Pasang m3 185,500.00 Harga Kontrak Terdahulu (PT. NKE) 321,400.00 210,000.0 309,900.00 185,500.00 203,500.00
12 Kubus Beton 0,5*0,5*0,5 (pabrikasi) bh 375,000.00 Harga Pasar (PT. Adhimix) 382,000.00 375,000.00
13 Kubus Beton 0,5*0,5*0,5 (pabrikasi) m3 3,000,000.00 Harga Pasar (PT. Adhimix) 3,056,000.00 3,000,000.00
2 Induksi K3 (Safety Induction); khusus untuk pekerja baru Orang 7,500.00 25,000.00
11 Sepatu keselamatan (Rubber Safety Shoes and toe cap); Pasang 145,000.00 150,000.00
19 Peralatan P3K (Kotak P3K, Oksigen, Obat luka, Perban, dll Ls 5,400,000.00 10,000,000.00
Pencegehan COVID-19
L
o
n
t
HARGA UPAH a
r
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II K
Pekerjaan : Penanganan Muara Sungai Ciujung Kab. Serang a
Lokasi : Kab. Serang b
.
Tahun Anggaran : 2022
S
e
r
Harga Satuan SSH
SSH Kab. Serang 2021 BANTEN a
No Uraian Kode Satuan Keterangan
(Rp.) 2022 n
g
)
1 Pekerja L.01 Orang-Hari 155,000.00 SSH Kab. Serang 2021 140,000.00 155,000.00
###
2 Tukang L.02 Orang-Hari 170,500.00 SSH Kab. Serang 2021 148,400.00 170,500.00
###
3 Tukang Batu L.02 Orang-Hari 170,500.00 SSH Kab. Serang 2021 148,400.00 170,500.00
###
4 Mandor L.04 Orang-Hari 193,700.00 SSH Kab. Serang 2021 172,200.00 193,700.00
###
5 Petugas Medis L.16 OB 3,500,000.00 Analisa EE
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : Penanganan Muara Sungai Ciujung Kab. Serang
Jenis Pekerjaan : Mobilisasi dan Demobilisasi Peralatan dan Personil Konstruksi
Satuan Pekerjaan : LS
Harga Satuan : Rp 72,570,000.00
Kode Pekerjaan : L.04
A PERALATAN
Menggunakan Trailer
1 Excavator (Standar) 147 HP E.15.d Unit 4.000 2.000 4,803,000.00 38,424,000.00
B TENAGA KERJA
1 Personil Konstruksi L.15 OK 15.000 2.000 500,000.00 15,000,000.00
C Jumlah A 63,104,400.00
D Biaya Umum dan Keuntungan ( 15% x B) 9,465,660.00
E Jumlah (C+D) 72,570,060.00
F Jumlah Dibulatkan 72,570,000.00
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : Penanganan Muara Sungai Ciujung Kab. Serang
Jenis Pekerjaan : Mobilisasi dan Demobilisasi Peralatan dan Personil Konstruksi
Satuan Pekerjaan : LS
Harga Satuan : Rp 105,796,300.00
Kode Pekerjaan : L.04
A PERALATAN
Menggunakan Trailer
1 Excavator (Standar) 147 HP E.11.b Unit 6.000 2.000 4,803,000.00 57,636,000.00
B TENAGA KERJA
1 Personil Konstruksi L.15 OK 15.000 2.000 500,000.00 15,000,000.00
C Jumlah A 91,996,800.00
D Biaya Umum dan Keuntungan ( 15% x B) 13,799,520.00
E Jumlah (C+D) 105,796,320.00
F Jumlah Dibulatkan 105,796,300.00
Analisa Harga Satuan Pekerjaan
B BAHAN
1
Jumlah-B
C PERALATAN
1 Amphibious Excavator E.16.c Jam 0.0244 1,264,285.71 30,893.36
2 Ponton 2 (angkut 700m) E.50.i Jam 0.0733 96,414.29 7,067.77
3 Excavator 2 (long arm) E.16.c Jam 0.0216 507,400.00 10,967.06
4
Jumlah-C 48,928.19
D Jumlah (A + B + C) 50,297.74
E Biaya Umum dan Keuntungan ( 15% x D) 7,544.66
F Jumlah (D + E) 57,842.40
G Jumlah Dibulatkan 57,800.00
Analisis Produktivitas Penggalian Tanah di Muara Cidurian/Ciujung
Menggunakan Excavator di Ponton 1, Hasil Galian Diangkut dengan Ponton 2
b Ponton 2 E.37.b
Kapasitas V 10.00 m3
Faktor Efisien Alat (Tabel 4) Fa 0.83 pemeliharaan mesin sangat baik
Kecepatan rata-rata bermuatan v.1 5.00 km/jam
Kecepatan rata-rata kosong v.2 7.00 km/jam
Waktu Siklus : Ts.2 menit
Waktu tempuh isi = (L:v.1) x 60 T.1 8.40 menit
Waktu tempuh kosong = (L:v.2) x 60 T.2 6.00 menit
Muat = (v:Q.1) x 60 T.3 13.81 menit
Lain-lain T.4 1.00 menit
Ts.2 29.21 menit
III. Tenaga
a. Di excavator 2 di darat menurunkan Asumsi 1 OH mampu
hasil galian dari ponton 2 ke darat membantu menurunkan 12
m3 (analisa)
(stock pile)
Produksi yang menentukan: 4 buah Q.1 54.57 m3/jam 381.96 / 12 = ± 32 OH
Ponton 2
Produksi /hari = Tk x Q.1 Q.1' 381.96 m3/hari
Kebutuhan tenaga
- pekerja P 3.00 org Bantu menurunkan 12m3/OH
- mandor M 0.30 org P : M = 10 : 1
Koefisien Tenaga/m3
- pekerja : (Tk x P) : Q.1 0.0550 jam manual 10% bantuan
- mandor : (Tk x M) : Q.1 0.0055 jam manual 10% bantuan
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : Penanganan Muara Sungai Ciujung Kab. Serang
Jenis Pekerjaan : Pembuatan Tetrapod berat 0.5 ton ###
Satuan Pekerjaan : buah
Harga Satuan : Rp 775,100.00
Kode Pekerjaan : P.14.d
A TENAGA
1. Pekerja L.01 OH 0.0184 155,000.00 2,852.00
2. Tukang batu/Tembok L.02 OH 0.0092 170,500.00 1,568.60
3. Mandor L.04 OH 0.0018 193,700.00 348.66
Jumlah-A 4,769.26
B BAHAN
1. Beton fc' >= 25 MPa (ready mix) B.02.b.9) m3 0.2125 1,236,600.00 262,777.50
2 Tulangan Praktis 100 kg/m3 B.06.a.1) kg 21.250 17,000.00 361,250.00
624,027.500
C PERALATAN
1 Vibrator Beton E.32.b Hari 0.0304 301,700.00 9,171.68
2 Cetakan Armor 0,5 Ton To.06.g Hari 3.6035 10,000.00 36,035.00
Jumlah-C 45,206.680
D Jumlah (A + B + C) 674,003.44
E Biaya Umum dan Keuntungan ( 15% x D) 101,100.52
F Jumlah (D + E) 775,103.96
G Jumlah Dibulatkan 775,100.00
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : Penanganan Muara Sungai Ciujung Kab. Serang
Jenis Pekerjaan : Pemasangan Tetrapod
Satuan Pekerjaan : m3 atau setara 5 Buah tetrapod
Harga Satuan : Rp 110,000.00
A TENAGA
1. Pekerja L.01 OH 0.0182 155,000.00 2,826.84
2. Mandor L.04 OH 0.0018 193,700.00 353.26
3. - -
Jumlah-A 3,180.10
B BAHAN
1. - -
C PERALATAN
1 Excavator Long Arm 1 E.16.c Jam 0.18238 507,400.00 92,537.87
Jumlah-C 92,537.869
D Jumlah (A + B + C) 95,717.97
E Biaya Umum dan Keuntungan ( 15% x D) 14,357.70
F Jumlah (D + E) 110,075.66
G Jumlah Dibulatkan 110,000.00
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : Penanganan Muara Sungai Ciujung Kab. Serang
Jenis Pekerjaan : Pembuatan Tetrapod berat 0.5 ton
Satuan Pekerjaan : M3
Harga Satuan : Rp 3,647,500.00
Kode Pekerjaan : P.13.h
1 m3 tetrapod 0,5 ton = 4.7059buah
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
1. Pekerja L.01 OH 0.0866 155,000.00 13,421.18
2. Tukang batu/Tembok L.02 OH 0.0433 170,500.00 7,381.65
3. Mandor L.04 OH 0.0085 193,700.00 1,640.75
Jumlah-A 22,443.58
B BAHAN
1. Beton K-250 (ready mix) B.07.c m3 1.0000 1,236,600.00 1,236,600.00
2 Tulangan Praktis 100 kg/m3 M.55.d kg 100.0000 17,000.00 1,700,000.00
2,936,600.000
C PERALATAN
1 Vibrator E.48 sewa-hari 0.1431 301,700.00 43,160.85
2 Cetakan Armor 0,5 Ton M.16.d Hari 16.9576 10,000.00 169,576.47
Jumlah-C 212,737.318
D Jumlah (A + B + C) 3,171,780.89
E Biaya Umum dan Keuntungan ( 15% x D) 475,767.13
F Jumlah (D + E) 3,647,548.03
3,647,500.00
(AHSP) PERMEN 2016
buah
JENIS PEKERJAAN : Biaya Pemasangan Tetrapod
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN
I. ASUMSI
1 Jam kerja efektif per hari Tk 7.00 jam
2. ALAT
2.a. EXCAVATOR LONG ARM 1
Waktu siklus
- Mengangkat, swing, turun+ikat tetrapod/kubus T1 0.80 menit
- Tarik, angkat, swing + lepas depan exca T1 0.53 menit
- Excavator Jalan 1,6 m' T2 0.30 menit
Ts1 1.93 menit
3. TENAGA
Produksi menentukan : Excavator Q2 5.48 M3/Jam
Produksi angkutan / hari = Tk x Q2 Qt 38.38 M3
Kebutuhan tenaga :
- Pekerja P 1.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.0182 Hari 10%
- Mandor = (Tk x M) : Qt (L03) 0.0018 Hari 10%
Rp. / M3
JENIS PEKERJAAN : Biaya Pemasangan Tetrapod
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN
I. ASUMSI
1 Jam kerja efektif per hari Tk 7.00 jam
2. ALAT
2.a. EXCAVATOR LONG ARM 1
Waktu siklus
- Mengangkat, swing, turun+ikat tetrapod/kubus T1 0.80 menit
- Tarik, angkat, swing + lepas depan exca T1 0.53 menit
3. TENAGA
Produksi menentukan : Excavator Q2 4.68 M3/Jam
Produksi angkutan / hari = Tk x Q2 Qt 32.76 M3
Kebutuhan tenaga :
- Pekerja P 1.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.0214 Hari 10%
- Mandor = (Tk x M) : Qt (L03) 0.0021 Hari 10%
Rp. / M3
No Uraian Kode Satuan Biaya Operasi Peralatan
A. Uraian Peralatan Excavator Excavator Excavator Dump Truck Dump Truck
Buldozer Ket.
1 Jenis Peralatan Standar Long Arm Super LongArm 7 Ton 4 Ton
2 Merk/Type - 100-150 HP PC-200 PC-200-6 PC-240LC 4-6 m3 3-4 m3
3 Tenaga Pw HP 150.00 125.00 155.00 170.00 130.00 110.00
4 Kapasitas Cp - 80.00 0.80 0.60 0.50 6.00 3.50
5 Umur Ekonomis A Tahun 5.00 5.00 5.00 10.00 5.00 5.00
6 Jam Operasi Dalam d W Jam 2,000.00 2,000.00 2,000.00 2,000.00 2,000.00 2,000.00
7 Harga Alat B Rp 925,000,000.00 875,000,000.00 1,100,000,000.00 1,600,000,000.00 502,500,000.00 367,500,000.00
Biaya Pasti per Jam: G = (E+F) G Rp/jam 110,730.70 104,745.26 131,679.75 118,776.68 60,153.71 43,993.01
Biaya Operasi (per Jam) P Rp/jam 236,921.57 209,396.57 249,521.57 286,246.57 198,454.07 172,349.07
D Biaya Operasi Alat/Jam = (G+P) S Rp/jam 347,652.27 314,141.83 381,201.32 405,023.25 258,607.78 216,342.08
E Lain-lain
1 Bahan Bakar Premium (non subsidi) Mb Liter 7,650.00 7,650.00 7,650.00 7,650.00 7,650.00 7,650.00
2 Bahan Bakar Solar (non subsidi) Ms Liter 9,400.00 9,400.00 9,400.00 9,400.00 9,400.00 9,400.00
3 Minyak Pelumas Mp Liter 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : Penanganan Muara Sungai Ciujung Kab. Serang
Jenis Pekerjaan : Pemasangan Kubus Beton
Satuan Pekerjaan : m3 atau setara 8 Buah Kubus Beton
Harga Satuan : Rp 128,900.00
Kode Pekerjaan :
A TENAGA
1. Pekerja L.01 OH 0.0214 155,000.00 3,311.65
2. Mandor L.04 OH 0.0021 193,700.00 413.85
3. - -
Jumlah-A 3,725.50
B BAHAN
1. -
C PERALATAN
1 Excavator E.15.d Jam 0.21365 507,400.00 108,408.35
2 ###
3 ###
Jumlah-C 108,408.353
D Jumlah (A + B + C) 112,133.85
E Biaya Umum dan Keuntungan ( 15% x D) 16,820.08
F Jumlah (D + E) 128,953.93
G Jumlah Dibulatkan 128,900.00
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : Penanganan Muara Sungai Ciujung Kab. Serang
Jenis Pekerjaan : Pembuatan 1 buah kubus beton ukuran 50 cm x 50 cm x 50 cm
Satuan Pekerjaan : m3
Harga Satuan : Rp 3,450,000.00
Kode Pekerjaan : P.14.b.x
Analisa Harga Satuan Pekerjaan (Permen PUPR No. 28 Tahun 2016, halaman 226)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
1.
2.
3.
4.
Jumlah-A -
B BAHAN
1. Kubus Beton 50cm * 50cm * 50cm m3 8.000 375,000.00 3,000,000.00
2
3
Jumlah-B 3,000,000.000
C PERALATAN
1.
2
Jumlah-C -
D Jumlah (A + B + C) 3,000,000.00
E Biaya Umum dan Keuntungan (15% x D) 450,000.00
F Jumlah (D + E) 3,450,000.00
G Jumlah Dibulatkan 3,450,000.00
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : Penanganan Muara Sungai Ciujung Kab. Serang
Jenis Pekerjaan : Pembuatan 1 buah kubus beton ukuran 50 cm x 50 cm x 50 cm
Satuan Pekerjaan : m3
Harga Satuan : Rp 632,900.00
Kode Pekerjaan : P.14.b.x
Analisa Harga Satuan Pekerjaan (Permen PUPR No. 28 Tahun 2016, halaman 226)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
1. Pekerja L.01 OH 0.0056 155,000.00 868.00
2. Tukang batu L.02 OH 0.0028 170,500.00 477.40
3. Mandor L.04 OH 0.0006 193,700.00 116.22
4. - -
Jumlah-A 1,461.62
###
B BAHAN
1. Beton fc' >= 25 MPa (ready mix) B.07.c m3 0.1250 1,236,600.00 154,575.00
2 Tulangan Praktis 100 kg/m3 M.55.d kg 12.5000 17,000.00 212,500.00
3
-
Jumlah-B 367,075.000
C PERALATAN
1. Vibrator Beton To.42.b Hari 0.0093 301,700.00 2,805.81
2 Cetakan Armor Kubus 0,5 m' To.06.b Hari 3.5813 50,000.00 179,065.00
Jumlah-C 181,870.810
D Jumlah (A + B + C) 550,407.43
E Biaya Umum dan Keuntungan (15% x D) 82,561.11
F Jumlah (D + E) 632,968.54
G Jumlah Dibulatkan 632,900.00
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : #REF!
Jenis Pekerjaan : Pengadaan dan Pemasangan U-Ditch 0.3x0.3x1.2 m (pabrikasi)
Satuan Pekerjaan : buah
Kode Pekerjaan : F.6.x.1
A TENAGA
1. Pekerja L.01 OH 0.4000 140,000.00 56,000.00
2. Mandor L.04 OH 0.0400 172,200.00 6,888.00
Jumlah-A 62,888.00
B BAHAN
1. U-Ditch 0.3x0.3x1.2 m M.09.x.1 buah 1.0000 293,500.00 293,500.00
2. Portland Cement M.15 sak 0.0800 #REF! #REF!
3. Pasir Beton M.14.a m3 0.0065 #REF! #REF!
Jumlah-B #REF!
C PERALATAN
Jumlah-C -
D Jumlah (A + B + C) #REF!
E Biaya Umum dan Keuntungan ( 15% x D) #REF!
F Jumlah (D + E) #REF!
JENIS PEKERJAAN : Biaya Pemasangan Kubus Beton
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN
I. ASUMSI
1 Jam kerja efektif per hari Tk 7.00 jam
2 Jarak angkut L 3.00 km
2. ALAT
2.a. EXCAVATOR LONG ARM 1
Jumlah kubus beton per M3 8.00 unit
Kapasitas angkut kubus beton V 0.12500 m3
Faktor Efisiensi alat Fa 0.83000 -
Waktu siklus
- Mengangkat, swing, menaruh kubus beton ke atas dump truck T1 0.17 menit
- Swing, kembali dan lain-lain (standar) T1 0.08 menit
Ts1 0.25 menit
Waktu siklus
- Mengangkat, swing, menaruh kubus beton di lokasi T1 0.17 menit
- Swing, kembali dan lain-lain (standar) T1 0.08 menit
Ts1 0.25 menit
3. TENAGA
Produksi menentukan : DUMP TRUCK Q2 4.39 M3/Jam
Produksi angkutan / hari = Tk x Q2 Qt 30.70 M3
Kebutuhan tenaga :
- Pekerja P 8.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.1824 Jam 10%
- Mandor = (Tk x M) : Qt (L03) 0.0228 Jam 10%
Rp. / M3
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : Penanganan Muara Sungai Ciujung Kab. Serang
Jenis Pekerjaan : Pasangan batu 650 kg - 800 kg
Satuan Pekerjaan : m3
Harga Satuan : Rp 551,800.00
Kode Pekerjaan : P.14.w
A TENAGA
1. Pekerja L.01 OH 0.3077 155,000.00 47,693.50
2. Tukang batu L.02 OH 0.2077 170,500.00 35,412.85
3. Mandor L.04 OH 0.0308 193,700.00 5,965.96
Jumlah-A 89,072.31
B BAHAN
1. Batu 650 kg - 800 kg M.27.m m3 1.4500 225,000.00 326,250.00
Jumlah-B 326,250.000
C PERALATAN
1. Excavator PC-200; 0,8 m3; 125 HP E.15.d jam 0.12727 507,400.00 64,576.80
Jumlah-C 64,576.798
D Jumlah (A + B + C) 479,899.11
E Biaya Umum dan Keuntungan (15% x D) 71,984.87
F Jumlah (D + E) 551,883.97
G Jumlah Dibulatkan 551,800.00
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : Penanganan Muara Sungai Ciujung Kab. Serang
Jenis Pekerjaan : Pasangan batu 50 kg - 100 kg
Satuan Pekerjaan : m3
Harga Satuan : Rp 451,890.00
Kode Pekerjaan : P.14.p
A TENAGA
1. Pekerja L.01 OH 0.2522 155,000.00 39,091.00
2. Tukang batu L.02 OH 0.1722 170,500.00 29,360.10
3. Mandor L.04 OH 0.0252 193,700.00 4,881.24
Jumlah-A 73,332.34
B BAHAN
1. Batu 50 kg - 100 kg M.27.f m3 1.3000 225,000.00 292,500.00
Jumlah-B 292,500.000
C PERALATAN
1. Excavator PC-200; 0,8 m3; 125 HP E.15.d jam 0.05345 507,400.00 27,120.53
Jumlah-C 27,120.530
D Jumlah (A + B + C) 392,952.87
E Biaya Umum dan Keuntungan ( 15% x D) 58,942.93
F Jumlah (D + E) 451,895.80
G Jumlah Dibulatkan 451,890.00
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : Penanganan Muara Sungai Ciujung Kab. Serang
Jenis Pekerjaan : Matras Bambu
Satuan Pekerjaan : m2
Harga Satuan : Rp 178,000.00
Kode Pekerjaan : P.13.b
A TENAGA
1. Pekerja L.01 OH 0.1200 155,000.00 18,600.00
2. Tukang Kayu L.02 OH 0.0600 170,500.00 10,230.00
3. Mandor L.04 OH 0.0120 193,700.00 2,324.40
Jumlah-A 31,154.40
B BAHAN
1 Bambu Ø 8-10cm, pjg 4-6m M.40.b batang 11.5000 10,500.00 120,750.00
2 Tali Pengikat M.150.a m' 3.2000 300.00 960.00
Jumlah-B 121,710.000
C PERALATAN
1 Ponton kap <5 Ton (manual) E.48.b Hari 0.0200 96,414.29 1,928.29
Jumlah-C 1,928.286
D Jumlah (A + B + C) 154,792.69
E Biaya Umum dan Keuntungan ( 15% x D) 23,218.90
F Jumlah (D + E) 178,011.59
G Jumlah Dibulatkan 178,000.00
Cek analisa dengan AHSP 2022
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : Penanganan Muara Sungai Ciujung Kab. Serang
Jenis Pekerjaan : Penetrasi Cerucuk Bambu Ø 8-10 cm
Satuan Pekerjaan : m'
Harga Satuan : Rp 45,900.00
Kode Pekerjaan : P.07.bx
A TENAGA
1 Pekerja L.01 OJ 0.0602 22,142.86 1,333.00
2 Tukang L.02 OJ 0.0602 24,357.14 1,466.30
3 Mandor L.04 OJ 0.0060 27,671.43 166.03
Jumlah-A 2,965.33
B BAHAN
1 - -
Jumlah-B -
C PERALATAN
1 Excavator PC-200 (Standar) 20-< E.15.d sewa-jam 0.0612 507,400.00 31,052.88
29ton; 120-130 HP
2 Ponton E.50.i sewa-jam 0.0612 96,414.29 5,900.55
Jumlah-C 36,953.434
D Jumlah (A + B + C) 39,918.76
E Biaya Umum dan Keuntungan ( 15% x D) 5,987.81
F Jumlah (D + E) 45,906.58
G Jumlah Dibulatkan 45,900.00
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : Penanganan Muara Sungai Ciujung Kab. Serang
Jenis Pekerjaan : Cerucuk Dolken
Satuan Pekerjaan : bh
Harga Satuan : Rp 15,000.00
Kode Pekerjaan : P.07.bx
A TENAGA
1 -
2 -
3 -
Jumlah-A -
B BAHAN
1 Cerucuk Dolken Btg 1.0000 13,100.00 13,100.00
Jumlah-B 13,100.000
C PERALATAN
1 -
2 -
Jumlah-C -
D Jumlah (A + B + C) 13,100.00
E Biaya Umum dan Keuntungan ( 15% x D) 1,965.00
F Jumlah (D + E) 15,065.00
G Jumlah Dibulatkan 15,000.00
Analisa Harga Satuan Pekerjaan
A TENAGA
-
B BAHAN
B.1 Penyiapan Rencana Keselamatan Konstruksi (RKK)
1 Pembuatan dokumen Rencana Keselamatan Kerja K.x.b.1 Set 1.00 2,000,000.00 2,000,000.00
B.2 Sosialisasi, promosi dan pelatihan
1 Induksi K3 (Safety Induction); khusus untuk pekerja baru K.x.b.2 Orang 30.00 7,500.00 225,000.00
2 Spanduk (Banner); M.112.a Lembar 5.00 300,000.00 1,500,000.00
3 Poster; M.112.a Lembar 10.00 50,000.00 500,000.00
4 Papan Informasi K3. M.140 Buah 2.00 500,000.00 1,000,000.00
B.3 Alat pelindung kerja dan alat pelindung diri
1 Tali keselamatan (Life Line); - Ls 1.00 1,000,000.00 1,000,000.00
2 Pembatas area (Restricted Area); - Ls 1.00 2,500,000.00 2,500,000.00
3 Helm pelidung (Safety Helmet); T.24 Pcs 25.00 125,000.00 3,125,000.00
4 Rompi keselamatan (Safety Vest); T.25 Pcs 25.00 150,000.00 3,750,000.00
5 Sepatu keselamatan (Safety Shoes); untuk Staf T.26 Pasang 25.00 500,000.00 12,500,000.00
6 Sepatu keselamatan (Rubber Safety Shoes and toe cap); T.26 Pasang 25.00 145,000.00 3,625,000.00
7 Sarung tangan (Safety Gloves); K.x.b.4 Pasang 50.00 25,000.00 1,250,000.00
8 Kacamata K.x.b.5 Pcs 25.00 100,000.00 2,500,000.00
B.4 Rambu-rambu :
1 Rambu petunjuk; K.x.b.6 Buah 5.00 200,000.00 1,000,000.00
2 Rambu larangan; K.x.b.7 Buah 5.00 200,000.00 1,000,000.00
3 Rambu peringatan; K.x.b.8 Buah 5.00 200,000.00 1,000,000.00
4 Rambu kewajiban; K.x.b.9 Buah 5.00 200,000.00 1,000,000.00
5 Rambu Informasi; K.x.b.10 Buah 5.00 200,000.00 1,000,000.00
B.5 Fasilitas sarana kesehatan :
1 Peralatan P3K (Kotak P3K, Oksigen, Obat luka, Perban, dll) K.x.b.11 Ls 1.00 5,400,000.00 5,400,000.00
B.6 Asuransi dan Perijinan :
1 BPJS Ketenagakerjaan Dan Keselamatan Kerja K.x.b.12 Ls 1.00 33,000,000.00 33,000,000.00
B.7 Personel K3
1 Petugas P3K OB 8.00 3,500,000.00 28,000,000.00
B.8 Konsultansi Dengan Ahli Terkait Keselamatan Konstruksi
1 Ahli K3 Konstruksi OJ 10.00 1,700,000.00 17,000,000.00
B.9 Lain-Lain Terkait Pengendalian Resiko K3 :
1 Alat pemadam api ringan (APAR); 10kg K.x.b.13 Buah 3.00 200,000.00 600,000.00
2 Bendera K3; K.x.b.14 Buah 3.00 200,000.00 600,000.00
3 Bendera Proyek dan umbul-umbul K.x.b.15 Buah 3.00 200,000.00 600,000.00
4 Lampu darurat (Emergency Lamp); K.x.b.16 Buah 3.00 200,000.00 600,000.00
B.10 Protokol Kesehatan COVID-19
1 Hazmat Suit T.25.x.1 Unit 2.00 285,000 570,000.00
2 Goggle Chemical Heavy Duty T.25.x.2 Pcs 2.00 170,000 340,000.00
3 Penutup Wajah T.25.x.3 Pcs 2.00 315,000 630,000.00
4 Sarung Tangan Medis (1 Box = 100 Pcs) T.25.x.4 Unit 10.00 70,000 700,000.00
5 Non - Contact Infrared Forehead Thermometer T.25.x.7 Unit 5.00 500,000 2,500,000.00
6 Disinfektan Bakterisidal, Virusidal T.25.x.8 Liter 30.00 500,000 15,000,000.00
7 Masker N95 T.25.x.9 Pcs 30.00 20,000 600,000.00
8 Masker Bedah (1 Box = 50 Pcs) T.25.x.10 Box 50.00 60,000 3,000,000.00
9 Masker Kain T.25.x.11 Pcs 50.00 20,000 1,000,000.00
10 Hand Sanitizer T.25.x.12 Liter 50.00 75,000 3,750,000.00
11 Vitamin C (1 box = 100 tablet) T.25.x.13 Box 50.00 100,000 5,000,000.00
12 Vitamin E (1 box = 100 tablet) T.25.x.14 Box 50.00 100,000 5,000,000.00
13 Cuci Tangan Portable T.25.x.17 Unit 5.00 1,000,000 5,000,000.00
169,365,000.00
C PERALATAN
-
D Jumlah (A + B + C) 169,365,000.00
F Jumlah (D + E) 169,365,000.00
G Jumlah Dibulatkan 169,365,000.00
Page 10
Analisa Harga Satuan Pekerjaan
A TENAGA
Penyiapan -
Rencana
B BAHAN
Keselamatan
B.1 Konstruksi (RKK)
Sosialisasi,
1 Pembuatan
promosi dandokumen Rencana Keselamatan Kerja Set 1.00 2,000,000.00 2,000,000.00
B.2 pelatihan
1 Induksi K3 (Safety Induction) Orang 30.00 7,500.00 225,000.00
2 Spanduk (Banner) Lembar 5.00 300,000.00 1,500,000.00
3 Poster Lembar 10.00 50,000.00 500,000.00
Alat Pelindung
4 Papan Informasi
Kerja dan Alat K3. Buah 2.00 500,000.00 1,000,000.00
B.3 Pelindung Diri
1 Tali keselamatan (Life Line) Ls 1.00 1,000,000.00 1,000,000.00
2 Pembatas area (Restricted Area) Ls 1.00 2,500,000.00 2,500,000.00
3 Helm pelindung (Safety Helmet) Pcs 25.00 125,000.00 3,125,000.00
4 Rompi keselamatan (Safety Vest) Pcs 25.00 150,000.00 3,750,000.00
5 Sepatu keselamatan (Safety Shoes) Pasang 25.00 500,000.00 12,500,000.00
6 Sepatu keselamatan (Rubber Safety Shoes and Toe Cap) Pasang 25.00 145,000.00 3,625,000.00
7 Sarung tangan (Safety Gloves) Pasang 50.00 25,000.00 1,250,000.00
8 Jaket Pelampung
Asuransi dan (Life Vest) Pcs 25.00 100,000.00 2,500,000.00
B.4 Perijinan :
1 BPJS Ketenagakerjaan Dan Keselamatan Kerja Ls 1.00 33,000,000.00 33,000,000.00
B.5 Personel Keselamatan Konstruksi
Fasilitas sarana,
1 Petugas P3K
prasarana dan OB 8.00 3,500,000.00 28,000,000.00
B.6 alat kesehatan
1 Peralatan P3K (Kotak P3K, obat luka, perban, dll) Ls 1.00 5,400,000.00 5,400,000.00
B.7 Rambu-rambu
1 Rambu petunjuk Buah 5.00 200,000.00 1,000,000.00
2 Rambu larangan Buah 5.00 200,000.00 1,000,000.00
3 Rambu peringatan Buah 5.00 200,000.00 1,000,000.00
4 Rambu kewajiban
Kegiatan dan Buah 5.00 200,000.00 1,000,000.00
5 peralatan terkait
Rambu Informasi Buah 5.00 200,000.00 1,000,000.00
B.8 Pengendalian
Konsultansi dengan Ahli terkait Keselamatan Konstruksi
Risiko
1 Ahli K3 Konstruksi
Keselamatan OJ 10.00 1,700,000.00 17,000,000.00
B.9 Konstruksi
1 Alat Pemadam Api Ringan (APAR) Buah 3.00 200,000.00 600,000.00
2 Bendera K3; Buah 3.00 200,000.00 600,000.00
3 Bendera Proyek dan Umbul-Umbul Buah 3.00 200,000.00 600,000.00
Protokol
4 Lampu
KesehatanDarurat (Emergency Lamp)
COVID- Buah 3.00 200,000.00 600,000.00
B.10 19
1 Sarung Tangan Latex (1 Box = 100 Pcs) Unit 10.00 60,000 600,000.00
2 Thermometer Gun Unit 5.00 60,000 300,000.00
3 Disinfektan Liquid (5 Liter) Botol 5.00 120,000 600,000.00
4 Masker Bedah (1 Box = 50 Pcs) Box 50.00 40,000 2,000,000.00
5 Masker Kain Pcs 50.00 10,000 500,000.00
6 Hand Sanitizer Liter 50.00 35,000 1,750,000.00
7 Vitamin C Box 50.00 100,000 5,000,000.00
8 Vitamin E Box 50.00 100,000 5,000,000.00
9 Cuci Tangan Portable Unit 1.00 1,000,000 1,000,000.00
143,025,000.00
C PERALATAN
-
D Jumlah (A + B + C) 143,025,000.00
F Jumlah (D + E) 143,025,000.00
G Jumlah Dibulatkan 143,025,000.00
Page 10
Analisa Harga Satuan Pekerjaan
A TENAGA
Jumlah-A -
B BAHAN
Persiapan
1 Mobilisasi Ls 1.00 5,000,000 5,000,000.00
B.1 Pemasangan Digital Monitoring
1 Pondasi (beton bertulang) Termasuk Galian Tanah (50 cm x 50 cm) K.x.c.1 Titik 4.00 1,500,000 6,000,000.00
2 Tower Triangle Guy Mass 20 x 20 x 20 x 30m (6 Stage) K.x.c.2 Titik 4.00 12,600,000 50,400,000.00
3 Material Bantu (Seling, Span M12, bolt, clamp, anchor, anchor spander) K.x.c.3 Ls 4.00 1,000,000 4,000,000.00
4 Penangkal Petir K.x.c.4 Set 4.00 4,250,000 17,000,000.00
5 Outdoor Camera 8 MP (Fix) K.x.c.5 Unit 10.00 1,500,000 15,000,000.00
6 NVR 16 Channel K.x.c.6 Unit 1.00 3,500,000 3,500,000.00
7 HDD NVR 4TB K.x.c.7 Unit 2.00 2,400,000 4,800,000.00
8 Powerbeam M5 (Transmission) K.x.c.8 Unit 6.00 1,800,000 10,800,000.00
9 STP CAT-6 Outdoor (300 m) K.x.c.9 Rol 5.00 3,680,000 18,400,000.00
10 Konektor RJ-45 CAT 6 + rubber boot (isi 50 pcs) K.x.c.10 Pak 1.00 500,000 500,000.00
11 Kabel NYM 2 x 1,5 mm K.x.c.11 Rol 5.00 310,000 1,550,000.00
12 POE Injector 8 Port K.x.c.12 Unit 5.00 1,250,000 6,250,000.00
13 UPS APC 1500VA K.x.c.13 Unit 1.00 6,380,000 6,380,000.00
14 UPS 600VA K.x.c.14 Unit 3.00 750,000 2,250,000.00
15 Monitor 50" Full HD K.x.c.15 Unit 1.00 5,000,000 5,000,000.00
16 Pipa Conduic 20mm K.x.c.16 Batang 100.00 10,000 1,000,000.00
17 Shock Pipa K.x.c.17 Pcs 100.00 7,500 750,000.00
18 Klem Pipa K.x.c.18 Pcs 100.00 7,500 750,000.00
19 Outdoor Box Panel 30 x 40 x 17 K.x.c.19 Pcs 4.00 350,000 1,400,000.00
20 Aksesories K.x.c.20 Set 1.00 7,445,500 7,445,500.00
21 Installasi CCTV K.x.c.21 Titik 10.00 350,000 3,500,000.00
22 Installasi Radio Transmisi K.x.c.22 Titik 6.00 400,000 2,400,000.00
23 Laptop i7 K.x.c.23 Unit 2.00 20,000,000 40,000,000.00
Jumlah-B 214,075,500.00
C PERALATAN
Jumlah-C -
D Jumlah (A + B + C) 214,075,500.00
E Biaya Umum dan Keuntungan (15% x D) 32,111,325.00
F Jumlah (D + E) 246,186,825.00
G Jumlah Dibulatkan 246,186,800.00
Page 10
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : Penanganan Muara Sungai Ciujung Kab. Serang
Jenis Pekerjaan : Pembuatan 1 m2 jalan sementara
Satuan Pekerjaan : m2
Harga Satuan : Rp 424,300.00
Kode Pekerjaan : EI-511
A TENAGA
1. Pekerja L.01 OH 0.0494 22,142.86 1,093.86
2. Mandor L.03 OH 0.0071 27,671.43 196.47
Jumlah-A 1,290.32
B BAHAN
1 Agregat A M26 m3 1.2608 284,875.00 359,170.40
Jumlah-B 359,170.400
C PERALATAN
1 Wheel Loader E15 jam 0.0071 405,510 2,879.12
4 Vibratory Roller E19 jam 0.0136 417,773 5,681.71
Jumlah-C 8,560.834
D Jumlah (A + B + C) 369,021.56
E Biaya Umum dan Keuntungan ( 15% x D) 55,353.23
F Jumlah (D + E) 424,374.79
G Jumlah Dibulatkan 424,300.00
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : Penanganan Muara Sungai Ciujung Kab. Serang
Jenis Pekerjaan : Mobilisasi dan Demobilisasi
Satuan Pekerjaan : LS
Kode Pekerjaan : L.04
A PEKERJAAN
1 Mobilisasi dan Demobilisasi Personil dan Peralatan L.04 LS 1.00 105,796,320.00 105,796,320.00
2 Pembangunan Direksi Keet, los kerja dan gudang LA.02 m2 300.00 #REF! #REF!
3 Jalan sementara A. 1.2.2.1.12 m2 4,556.60 233,455.46 1,063,762,974.02
4 Penyediaan sarana telekomuninasi LS 1.00 38,709,000.00 38,709,000.00
5 Penyediaan air bersih LS 1.00 #REF! #REF!
6 Papan nama pekerjaan LA.03.a unit 2.00 #REF! #REF!
7 Pengukuran kembali/uitzet T.02.a m' 6,276.90 4,736.25 29,728,980.18
C Jumlah A #REF!
D Biaya Umum dan Keuntungan ( 15% x B) #REF!
E Jumlah (C+D) #REF!
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : #REF!
Jenis Pekerjaan : Pengukuran Kembali/Uitzet Trase Saluran
Satuan Pekerjaan : m'
Kode Pekerjaan : T.02.a
A TENAGA
1. Pekerja L.01 OH 0.0120 140,000.00 1,680.00
2. Pembantu Juru Ukur L.06 OH 0.0040 106,100.00 424.40
3. Juru Ukur L.05 OH 0.0040 283,520.00 1,134.08
Jumlah-A 3,238.48
B BAHAN
Jumlah-B -
C PERALATAN
1. Waterpass E.50 sewa-hari 0.0040 100,000.00 400.00
2. Theodolith E.43a sewa-hari 0.0040 120,000.00 480.00
Jumlah-C 880.000
D Jumlah (A + B + C) 4,118.48
E Biaya Umum dan Keuntungan ( 15% x D) 617.77
F Jumlah (D + E) 4,736.25
4,730.00
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : #REF!
Jenis Pekerjaan : Pembuatan direksi keet, los kerja dan gudang
Satuan Pekerjaan : m2
Kode Pekerjaan : LA.02
A TENAGA
1. Pekerja L.01 OH 1.2000 155,000.00 186,000.00
2. Tukang tembok/batu L.02 OH 0.4000 148,400.00 59,360.00
3. Kepala tukang batu L.03 OH 0.0400 162,400.00 6,496.00
4. Mandor L.04 OH 0.1200 172,200.00 20,664.00
Jumlah-A 272,520.00
B BAHAN
1. Kaso 5/7 M.33.d m3 0.3500 #REF! #REF!
2. Dinding triplek 4 mm M.42.b lembar 1.0000 #REF! #REF!
3. Pondasi pasangan batu P.01d.1) m3 0.1700 #REF! #REF!
4. Plafon asbes 3 mm - lembar 1.2400 #REF! #REF!
5. Paku M.66.c kg 0.7500 #REF! #REF!
6. Asbes gelombang M.110.a lembar 0.3000 134,345.00 40,303.50
7. Paku asbes M.54.f kg 0.1000 #REF! #REF!
8. Floor lantai (Beton lantai kerja) B.01 m3 0.1500 #REF! #REF!
9. Pintu Double teakwood rangka kay M.40.a m2 0.1000 #REF! #REF!
10. Jendela kaca nako - daun 1.0000 #REF! #REF!
11. Cat dinding/plafon M.115.d m2 16.5000 99,412.04 1,640,298.67
Jumlah-B #REF!
C PERALATAN
Jumlah-C -
D Jumlah (A + B + C) #REF!
E Biaya Umum dan Keuntungan ( 15% x D) #REF!
F Jumlah (D + E) #REF!
#REF!
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : #REF!
Jenis Pekerjaan : Mortar tipe O (setara campuran 1 PC : 5 PP) cara manual
Satuan Pekerjaan : m3
Kode Pekerjaan : P.01.d.1)
A TENAGA
1. Pekerja L.01 OH 2.7000 155,000.00 418,500.00
2. Tukang Batu L.02 OH 0.9000 170,500.00
3. Mandor L.04 OH 0.2700 193,700.00 52,299.00
Jumlah-A 470,799.00
B BAHAN
1 Batu Belah M.05 m3 1.2000 231,000.00 277,200.00
2 Pasir Pasang M.14.b m3 0.5440 185,500.00 100,912.00
3 Portland Cement M.15 kg 135.0000 #REF! #REF!
Jumlah-B #REF!
C PERALATAN
Jumlah-C -
D Jumlah (A + B + C) #REF!
E Biaya Umum dan Keuntungan ( 15% x D) #REF!
F Jumlah (D + E) #REF!
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : #REF!
Jenis Pekerjaan : Beton untuk lantai kerja (bedding)
Satuan Pekerjaan : m3
Kode Pekerjaan : B.01.b
A TENAGA
1. Pekerja L.01 OH 1.3200 155,000.00 204,600.00
2. Tukang Batu L.02 OH 0.2200 170,500.00 37,510.00
3. Kepala Tukang batu L.03 OH 0.0220 - -
4. Mandor L.04 OH 0.1320 193,700.00 25,568.40
Jumlah-A 267,678.40
B BAHAN
1 Portland Cement M.15 kg 200.0000 #REF! #REF!
2 Pasir Beton M.14.a m3 0.5220 #REF! #REF!
3 Kerikil M.12 m3 0.8620 #REF! #REF!
Jumlah-B #REF!
C PERALATAN
Jumlah-C -
D Jumlah (A + B + C) #REF!
E Biaya Umum dan Keuntungan ( 15% x D) #REF!
F Jumlah (D + E) #REF!
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : #REF!
Jenis Pekerjaan : Pembuatan Papan Nama Pekerjaan
Satuan Pekerjaan : buah
Kode Pekerjaan : LA.03.a
A TENAGA
1. Pekerja L.01 OH 1.0000 140,000.00 140,000.00
2. Tukang kayu L.02 OH 1.0000 148,400.00 148,400.00
3. Kepala tukang kayu L.03 OH 0.1000 162,400.00 16,240.00
4. Tukang cat dan tulis L.02 OH 1.5000 148,400.00 222,600.00
5. Mandor L.04 OH 0.1000 172,200.00 17,220.00
Jumlah-A 544,460.00
B BAHAN
1. Multiplek tebal 18 mm M.38.d Lembar 0.3500 #REF! #REF!
2. Tiang kayu 8/12 kelas II, tinggi 4 m M.33.a m3 0.0770 2,219,454.30 170,897.98
3. Frame besi L.3030.3 M.54.g kg 5.8000 #REF! #REF!
4. Paku campuran 5 cm dan 7 cm M.65.b kg 1.2500 #REF! #REF!
5. Car Kayu M.115.b kg 2.5000 49,754.80 124,387.00
Jumlah-B #REF!
C PERALATAN
Jumlah-C -
D Jumlah (A + B + C) #REF!
E Biaya Umum dan Keuntungan ( 15% x D) #REF!
F Jumlah (D + E) #REF!
#REF!
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : #REF!
Jenis Pekerjaan : DT angkut material atau hasil galian sejauh 3 km
Satuan Pekerjaan : m3
Kode Pekerjaan : TM.02.b.1
A TENAGA
Jumlah-A -
B BAHAN
Jumlah-B -
C PERALATAN
1. Dump truck E.08.b jam 0.1489 556,140.00 82,803.68
Jumlah-C 82,803.685
D Jumlah (A + B + C) 82,803.68
E Biaya Umum dan Keuntungan ( 15% x D) 12,420.55
F Jumlah (D + E) 95,224.24
95,220.00
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : #REF!
Jenis Pekerjaan : Menggali dengan excavator dan hasil galian dimuat ke DT
Satuan Pekerjaan : m3
Kode Pekerjaan : TM.02.a
A TENAGA
1. Pekerja L.01 OH 0.1630 140,000.00 22,820.00
2. Mandor L.04 OH 0.0163 172,200.00 2,806.86
Jumlah-A 25,626.86
B BAHAN
Jumlah-B -
C PERALATAN
1. Excavator E.11.b jam 0.0372 507,400.00 18,885.43
Jumlah-C 18,885.428
D Jumlah (A + B + C) 44,512.29
E Biaya Umum dan Keuntungan ( 15% x D) 6,676.84
F Jumlah (D + E) 51,189.13
51,180.00
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : #REF!
Jenis Pekerjaan : Pasangan batu 5 kg - 10 kg
Satuan Pekerjaan : m3
Kode Pekerjaan : P.14.m
A TENAGA
1. Pekerja L.01 OH 1.1000 140,000.00 154,000.00
2. Tukang batu L.02 OH 0.2200 148,400.00 32,648.00
3. Mandor L.04 OH 0.1100 172,200.00 18,942.00
Jumlah-A 205,590.00
B BAHAN
1. Batu 5 kg - 10 kg (Berat Jenis 2.6 ton/m3) M.06.a m3 1.2000 225,000.00 270,000.00
Jumlah-B 270,000.000
C PERALATAN
1. Excavator E.11 jam 0.1100 507,400.00 55,814.00
Jumlah-C 55,814.000
D Jumlah (A + B + C) 531,404.00
E Biaya Umum dan Keuntungan ( 15% x D) 79,710.60
F Jumlah (D + E) 611,114.60
611,110.00
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : Pengamanan Pantai Muara Sungai Cidurian Kab. Serang
Jenis Pekerjaan : Pasangan batu 100 kg - 200 kg
Satuan Pekerjaan : m3
Kode Pekerjaan : P.14.q
A TENAGA
1. Pekerja L.01 OH 1.2000 140,000.00 168,000.00
2. Tukang batu L.02 OH 0.2400 148,400.00 35,616.00
3. Mandor L.04 OH 0.1200 172,200.00 20,664.00
Jumlah-A 224,280.00
B BAHAN
1. Batu 100 kg - 200 kg (Berat Jenis 2.6 ton/m3) M.06.a m3 1.3200 215,000.00 283,800.00
Jumlah-B 283,800.000
C PERALATAN
1. Excavator E.11 jam 0.1200 680,374.00 81,644.88
Jumlah-C 81,644.880
D Jumlah (A + B + C) 589,724.88
E Biaya Umum dan Keuntungan (15% x D) 88,458.73
F Jumlah (D + E) 678,183.61
678,180.00
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : Pengamanan Pantai Muara Sungai Cidurian Kab. Serang
Jenis Pekerjaan : Pasangan batu 500 kg - 650 kg
Satuan Pekerjaan : m3
Kode Pekerjaan : P.14.v
A TENAGA
1. Pekerja L.01 OH 1.3500 140,000.00 189,000.00
2. Tukang batu L.02 OH 0.2700 148,400.00 40,068.00
3. Mandor L.04 OH 0.1350 172,200.00 23,247.00
Jumlah-A 252,315.00
B BAHAN
1. Batu 500 kg - 650 kg (Berat Jenis 2.6 ton/m3) M.06.a m3 1.4200 202,627.00 287,730.34
Jumlah-B 287,730.340
C PERALATAN
1. Excavator E.11 jam 0.1300 680,374.00 88,448.62
Jumlah-C 88,448.620
D Jumlah (A + B + C) 628,493.96
E Biaya Umum dan Keuntungan (15% x D) 94,274.09
F Jumlah (D + E) 722,768.05
722,760.00
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : Pengamanan Pantai Muara Sungai Cidurian Kab. Serang
Jenis Pekerjaan : #REF!
Satuan Pekerjaan : buah
Kode Pekerjaan : P.14.w.x
A TENAGA
1. Pekerja L.01 OH 1.3500 140,000.00 189,000.00
2. Tukang L.02 OH 0.2700 148,400.00 40,068.00
3. Mandor L.04 OH 0.1350 172,200.00 23,247.00
Jumlah-A 252,315.00
B BAHAN
1. Tetrapod 0.5 ton P.14.d buah 1.0000 -
Jumlah-B -
C PERALATAN
1. Excavator E.11 jam 0.1300 680,374.00 88,448.62
Jumlah-C 88,448.620
D Jumlah (A + B + C) 340,763.62
E Biaya Umum dan Keuntungan (15% x D) 51,114.54
F Jumlah (D + E) 391,878.16
391,870.00
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : Penanganan Muara Sungai Ciujung Kab. Serang
Jenis Pekerjaan : Pemasangan geotekstil, tebal sedang
Satuan Pekerjaan : m2
Kode Pekerjaan : P.09.b
A TENAGA
1. Pekerja L.01 OH 0.1600 140,000.00 22,400.00
2. Tukang tembok/gali L.02 OH 0.0320 148,400.00 4,748.80
3. Mandor L.04 OH 0.0160 172,200.00 2,755.20
Jumlah-A 29,904.00
B BAHAN
1 Geotekstil M.122.b m2 1.0800 #REF! #REF!
Jumlah-B #REF!
C PERALATAN
Jumlah-C -
D Jumlah (A + B + C) #REF!
E Biaya Umum dan Keuntungan ( 15% x D) #REF!
F Jumlah (D + E) #REF!
#REF!
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan :
Jenis Pekerjaan : Lantai Kerja (Beton K-100)
Satuan Pekerjaan : m3
Kode Pekerjaan : B.01.c
A TENAGA
1. Pekerja L.01 OH 1.3230 140,000.00 185,220.00
2. Tukang batu L.02 OH 0.0220 148,400.00 3,264.80
3. Kepala tukang L.03 OH 0.0220 162,400.00 3,572.80
4. Mandor L.04 OH 0.1320 172,200.00 22,730.40
Jumlah-A 214,788.00
B BAHAN
1. Portland cement M.15 kg 227.0000 #REF! #REF!
2. Pasir beton M.14.a m3 0.6180 #REF! #REF!
3. Kerikil M.12 m3 0.7440 #REF! #REF!
Jumlah-B #REF!
C PERALATAN
Jumlah-C -
D Jumlah (A + B + C) #REF!
E Biaya Umum dan Keuntungan ( 15% x D) #REF!
F Jumlah (D + E) #REF!
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan :
Jenis Pekerjaan : Beton mutu, f'c = 9.8 Mpa (K125) (molen)
Satuan Pekerjaan : m3
Kode Pekerjaan : B.03.b
A TENAGA
1. Pekerja L.01 OH 1.3230 140,000.00 185,220.00
2. Tukang batu L.02 OH 0.1890 148,400.00 28,047.60
3. Kepala tukang L.03 OH 0.0190 162,400.00 3,085.60
4. Mandor L.04 OH 0.1320 172,200.00 22,730.40
Jumlah-A 239,083.60
B BAHAN
1. Portland cement M.15 kg 276.0000 #REF! #REF!
2. Pasir beton M.14.a kg 828.0000 #REF! #REF!
3. Kerikil M.12 kg 1,012.0000 #REF! #REF!
4. Air M.02 liter 215.0000 1.00 215.00
Jumlah-B #REF!
C PERALATAN
1. Molen E.29.b unit-hari 0.2500 528.00 132.00
Jumlah-C 132.000
D Jumlah (A + B + C) #REF!
E Biaya Umum dan Keuntungan ( 15% x D) #REF!
F Jumlah (D + E) #REF!
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan :
Jenis Pekerjaan : Pembesian 100 kg dengan besi polos/ulir (pembesian pelat)
Satuan Pekerjaan : Kg
Kode Pekerjaan : B.17.a
A TENAGA
1. Pekerja L.01 OH 0.7000 140,000.00 98,000.00
2. Tukang besi L.02 OH 0.7000 148,400.00 103,880.00
3. Kepala tukang L.03 OH 0.0700 162,400.00 11,368.00
4. Mandor L.04 OH 0.0700 172,200.00 12,054.00
Jumlah-A 225,302.00
B BAHAN
1. Besi beton (polos/ulir) M.55.d kg 105.0000 12,000.00 1,260,000.00
2. Kawat ikat M.67 kg 1.5000 #REF! #REF!
Jumlah-B #REF!
C PERALATAN
Jumlah-C -
D Jumlah (A + B + C) #REF!
E Biaya Umum dan Keuntungan ( 15% x D) #REF!
F Jumlah (D + E) #REF!
G Harga Satuan Pekerjaan per- kg (F/100) #REF!
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : #REF!
Jenis Pekerjaan : Pemasangan bekisting tangga untuk empat kali pakai
Satuan Pekerjaan : m2
Kode Pekerjaan : A.4.1.1.26
A TENAGA
1. Pekerja L.01 OH 0.6600 140,000.00 92,400.00
2. Tukang kayu L.02 OH 0.3300 148,400.00 48,972.00
3. Kepala tukang L.03 OH 0.0330 162,400.00 5,359.20
4. Mandor L.04 OH 0.0330 172,200.00 5,682.60
Jumlah-A 152,413.80
B BAHAN
1. Kayu kelas II - m3 0.0300 2,219,454.30 66,583.63
2. Paku 5 cm - 12 cm M.71.b kg 0.4000 #REF! #REF!
3. Minyak bekisting M.129 liter 0.1500 #REF! #REF!
4. Balok kayu kelas II - m3 0.0150 2,219,454.30 33,291.81
5. Plywood tebal 9 mm - lembar 0.3500 #REF! #REF!
6. Dolken kayu Dia 8-10 cm, panjang 4 m M.29.d batang 2.0000 13,100.00 26,200.00
Jumlah-B #REF!
C PERALATAN
Jumlah-C -
D Jumlah (A + B + C) #REF!
E Biaya Umum dan Keuntungan ( 15% x D) #REF!
F Jumlah (D + E) #REF!
#REF!
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : #REF!
Jenis Pekerjaan : Beton menggunakan Ready mixed dan pompa beton (K-350)
Satuan Pekerjaan : m3
Kode Pekerjaan : B.13.a
A TENAGA
1. Pekerja L.01 OH 1.0000 140,000.00 140,000.00
2. Tukang batu L.02 OH 0.2500 148,400.00 37,100.00
3. Kepala tukang L.03 OH 0.0250 162,400.00 4,060.00
4. Mandor L.04 OH 0.1000 172,200.00 17,220.00
Jumlah-A 198,380.00
B BAHAN
1. Ready mixed (K350) M.09.x m3 1.0200 1,193,400.00 1,217,268.00
Jumlah-B 1,217,268.000
C PERALATAN
1. Pompa dan conveyor beton E.35 unit-hari 0.1200 3,085,440.00 370,252.80
Jumlah-C 370,252.800
D Jumlah (A + B + C) 1,785,900.80
E Biaya Umum dan Keuntungan ( 15% x D) 267,885.12
F Jumlah (D + E) 2,053,785.92
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : #REF!
Jenis Pekerjaan : Pemasangan paving block natural tebal 8 cm
Satuan Pekerjaan : m2
Kode Pekerjaan : A.4.4.3.65
A TENAGA
1. Pekerja L.01 OH 0.5000 140,000.00 70,000.00
2. Tukang batu L.02 OH 0.5000 148,400.00 74,200.00
3. Kepala tukang L.03 OH 0.0500 162,400.00 8,120.00
4. Mandor L.04 OH 0.0013 172,200.00 223.86
Jumlah-A 152,543.86
B BAHAN
1. Paving block 8 cm natural - m2 1.0100 #REF! #REF!
2. Pasir beton M.14.a m3 2.0700 #REF! #REF!
Jumlah-B #REF!
C PERALATAN
Jumlah-C -
D Jumlah (A + B + C) #REF!
E Biaya Umum dan Keuntungan ( 15% x D) #REF!
F Jumlah (D + E) #REF!
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : #REF!
Jenis Pekerjaan : Penanaman rumput lempengan
Satuan Pekerjaan : m2
Kode Pekerjaan : P.12.a
A TENAGA
1. Pekerja L.01 OH 0.1000 140,000.00 14,000.00
2. Mandor L.04 OH 0.0100 172,200.00 1,722.00
Jumlah-A 15,722.00
B BAHAN
1. Gebalan rumput M.136 m2 1.1000 #REF! #REF!
Jumlah-B #REF!
C PERALATAN
Jumlah-C -
D Jumlah (A + B + C) #REF!
E Biaya Umum dan Keuntungan ( 15% x D) #REF!
F Jumlah (D + E) #REF!
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : #REF!
Jenis Pekerjaan : Penanaman 1 pohon ketapang
Satuan Pekerjaan : batang
Kode Pekerjaan : P.13.a.x
A TENAGA
1. Pekerja L.01 OH 0.0080 140,000.00 1,120.00
2. Mandor L.04 OH 0.0008 172,200.00 137.76
Jumlah-A 1,257.76
B BAHAN
1. Pohon ketapang dia. 8-10 cm, t = 2 m M.136 pohon 1.0000 #REF! #REF!
Jumlah-B #REF!
C PERALATAN
Jumlah-C -
D Jumlah (A + B + C) #REF!
E Biaya Umum dan Keuntungan ( 15% x D) #REF!
F Jumlah (D + E) #REF!
Analisa Harga Satuan Pekerjaan
Satuan Kerja : SNVT Pelaksanaan Jaringan Sumber Air Cidanau-Ciujung-Cidurian
Kegiatan : PPK Sungai dan Pantai II
Paket Pekerjaan : #REF!
Jenis Pekerjaan : Timbunan tanah yang didatangkan termasuk pemadatan
Satuan Pekerjaan : m3
Kode Pekerjaan : T.14.x.1
A TENAGA
1. Pekerja L.01 OH 0.0700 140,000.00 9,800.00
2. Mandor L.04 OH 0.0070 172,200.00 1,205.40
Jumlah-A 11,005.40
B BAHAN
1. Bahan Tanah Timbunan M.17 m3 1.2000 #REF! #REF!
Jumlah-B #REF!
C PERALATAN
1. Bulldozer 20 Ton E.05.b unit-jam 0.0140 893,643.61 12,511.01
2. Water Tanker E.49 unit-jam 0.0070 257,247.00 1,800.73
3. Vibro Roller E.48 unit-jam 0.0160 417,773.00 6,684.37
Jumlah-C 6,684.368
D Jumlah (A + B + C) #REF!
E Biaya Umum dan Keuntungan ( 15% x D) #REF!
F Jumlah (D + E) #REF!