Luas Selimut Jarak Jmh Pjng Berat Bsi Jmh/ Berat Pjng Berat Luas
Dimensi
No Jenis Penampang Beton Sengkang Sengkang Sekng/Bh Tul. Pjng Besi/M' Beton/M3 Besi/M3 Bekisting
B H M2 ./ M' ( Bh ) .+ Hak Kg/M' M Kg M' Kg
TANGGA
PLAT TANGGA 1.00 0.12 0.120
Tul. Pokok Ø 12 - 15 0.020 0.150 7.667 2.130 0.888 16.330 14.497 8.333 204.705 10.333
Tul. Pokok Ø 10 - 15 0.020 0.150 7.667 2.130 0.617 16.330 10.067
Luas Selimut Jarak Jmh Pjng Berat Bsi Jmh/ Berat Pjng Berat Luas
Dimensi
No Jenis Penampang Beton Sengkang Sengkang Sekng/Bh Tul. Pjng Besi/M' Beton/M3 Besi/M3 Bekisting
B H M2 ./ M' ( Bh ) .+ Hak Kg/M' M Kg M' Kg
24.565
KABUPATEN CIAMIS
B BAHAN FINISHING :
LABURAN, PENGISI DAN ALATNYA
1 Plamir Tembok kg 12,000.00
2 Cat Tembok dinding Luar Sek Mowilex kg 78,400.00
3 Cat Tembok Sanlex kg 25,000.00
4 Cat Berkilat/Cat kayu kg 50,000.00
5 Plamir Kayu kg 22,000.00
6 Rool Cat Tembok bh 30,000.00
7 Kape Tembok bh 15,000.00
8 Kape Kayu bh 15,000.00
9 Soligneum 1 blek 5 lt 90,000.00
10 Plincote kg 60,000.00
11 Kwas 3" bh 15,000.00
12 Kwas 2' bh 12,500.00
13 Terpentin lt 9,000.00
14 Tiner A lt 22,000.00
15 Tiner B lt 30,000.00
16 Ampelas lbr 3,500.00
17 Dempul Kayu Cap Kucing kg 27,500.00
18 Meni Kayu / Besi kg 40,000.00
19 Cat Kayu Mowilex kg 60,000.00
20 Cat genting kg 25,000.00
21 Lem Fox bh 15,000.00
1 2 3 4
C BAHAN KAYU BERIKUT BAHAN JADINYA
1 Bambu Biasa bt 10,000.00
2 Bambu Ø 5 s.d 7 bt 12,000.00
3 Bambu Ø 7 s.d 10 bt 12,000.00
4 Kayu Lokal Kelas II m³ 2,500,000.00
5 Kayu Papan Kamper m³ 6,000,000.00
6 Kayu Papan Terentang m³ 1,500,000.00
7 Kayu Balok Albasiah m³ 2,500,000.00
8 Kayu Papan Albasia m³ 2,500,000.00
9 Kayu Balok Jati m³ 14,000,000.00
10 Kayu Papan Jati m³ 14,000,000.00
11 Reng Kayu Kls II m1 2,000.00
12 List profil Kayu 1/4 cm m1 5,000.00
13 List Profil Gypsum 12 cm m1 20,000.00
H BAHAN KACA
1 Kaca Polos 3 mm m² 65,000.00
2 Kaca Polos 5 mm m² 110,000.00
3 Glass Block DN 20 x 20 bh 30,000.00
4 Kaca 6 mm m² 100,000.00
5 Kaca 8 mm m² 130,000.00
6 Kaca 10 mm m² 180,000.00
K BAHAN SANITAIR
1 Closet Jongkok Poslin bh 200,000.00
2 Closet duduk Poslin TOTO unit 3,200,000.00
3 Wastafel Poslin warna unit 750,000.00
4 Selotip bh 5,000.00
5 Sink Washtafel bh 350,000.00
6 Floordrain stainless bh 60,000.00
7 Bath Tub set 2,750,000.00
1 2 3 4
L BAHAN PENUTUP ATAP
1 Atap Genteng Kodok KW 1 bh 2,000.00
2 Atap Genteng morando natural pres Molen Oven KW1 bh 2,700.00
Atap Genteng morando glazur pres Molen Oven KW1 bh 3,600.00
3 Bubung Genteng morando natural pres Bulat bh 2,800.00
Bubung Genteng morando glazur pres Bulat bh 6,000.00
4 Genteng Beton Rengganis Tsm bh 4,000.00
5 Bubungan Genteng Plat Beton Rengganis Tsm bh 10,000.00
2125.956
B1 39.6
1094.4
REKAPITULASI ANGGARAN BIAYA
PEKERJAAN : MAN 1 KABUPATEN TASIKMALAYA
LOKASI : Sukamanah
TAHUN ANGGARAN : 2022
JUMLAH
No URAIAN HARGA
Rp
JUMLAH 22,292,756.61
TERBILANG : Dua Puluh Dua Juta Dua Ratus Sembilan Puluh Dua Ribu Rupiah
HARGA JUMLAH
NO URAIAN PEKERJAAN KODE VOLUME SAT SATUAN HARGA SATUAN
ANALIS Rp Rp
1 2 3 4 5 6 7
A PEKERJAAN ALUMINIUM
1 Lemari Piala dihitung 17.00 m2 200,000.00 3,400,000.00
2 Pintu lemari Piala dihitung 36.00 unit 175,000.00 6,300,000.00
3 Pintu Aluminium + Kaca dihitung 2.00 unit 2,200,000.00 4,400,000.00
Jumlah 14,100,000.00
B PEKERJAAN BACKDROP
1 Pek. Pemasangan Backdrop dihitung 7.87 m2 500,000.00 3,936,250.00
Jumlah 3,936,250.00
C PEKERJAAN PENGECATAN
1 Pek. Pengecatan dihitung 21.3395 m2 35,451.00 Rp 756,506.61
Jumlah Rp 756,506.61
Jumlah Rp 3,500,000.00
REKAPITULASI ANGGARAN BIAYA
KEGIATAN : REHABILITASI GEDUNG
PEKERJAAN : REHABILITASI GEDUNG MTsN SINDANGKASIH
LOKASI : KABUPATEN CIAMIS
SUMBER DANA : APBN
TAHUN ANGGARAN : 2010
JUMLAH
No. URAIAN HARGA
Rp.
TERBILANG : TUJUH RATUS SEMBILAN PULUH ENAM JUTA LIMA RATUS DELAPAN PULUH SATU RIBU RUPIAH
Mengetahui/Menyetujui,
Pejabat Pembuat Komitmen Ciamis Februari 2010
CV. DAYA REKAYASA
Mengetahui/Menyetujui,
Kuasa Pengguna Anggaran
I. PEK. PERSIAPAN
1 Papan Nama Proyek dihitung ls 1.00 100,000.00 100,000.00
2 Biaya Bongkaran dihitung ls 1.00 5,000,000.00 5,000,000.00
3 Pas. Bouwplank A.01.06 m' 16.00 3,584,900.00 57,358,400.00
4 Administrasi, dokumentasi dan perijinan dihitung ls 1.00 7,000,000.00 7,000,000.00
Jumlah 69,458,400.00
II. PEK. TANAH DAN PONDASI
1 Galian tanah pondasi A.02.01 m3 71.36 46,200.00 3,296,832.00
2 Urugan tanah kembali A.02.11 m3 21.41 22,140.00 473,973.12
3 Urugan Pasir alas Pondasi A.02.13 m3 2.20 189,750.00 417,450.00
4 Pas. Lantai kerja beton tumbuk 1 pc : 3 ps : 5 kr A.07.01 m3 2.20 934,890.00 2,056,758.00
5 Pas. Pondasi batu kosong A.03.13 m3 0.84 373,590.00 313,815.60
6 Pas. Pondasi batu belah 1:5 A.03.05 m3 1.12 755,000.00 845,600.00
Jumlah 7,404,428.72
III PEK. DINDING DAN PLESTERAN
1 Pas. Bata dinding baru 1 : 5 A.04.12 m2 39.20 125,750.00 4,929,400.00
2 Pas. Plesteran 1 : 5 + Acian A.05.05 m2 78.40 65,750.00 5,154,800.00
Jumlah 10,084,200.00
IV. PEK. BETON
1 Pek. Pondasi Plat A.07.79A m3 13.40 4,728,200.00 63,357,880.00
2 Pek. Sloof 15/20 A.07.79B m3 4.14 3,690,020.00 15,276,682.80
3 Pek. Kolom 15/20 A.07.79E m3 0.82 7,083,770.00 5,808,691.40
4 Pek. Kolom 12/12 A.07.79D m3 0.05 4,941,070.00 247,053.50
5 Pek. Kolom 25/35 A.07.79F m3 20.79 7,007,340.00 145,682,598.60
6 Pek. Balok 25/55 A.07.79J m3 12.86 5,015,230.00 64,495,857.80
7 Pek. Balok 20/30 A.07.79K m3 8.92 6,572,540.00 58,627,056.80
8 Pek. Balok latai 12/15 A.07.79L m3 0.40 5,634,060.00 2,253,624.00
9 Pek. Pelat tangga dan Lantai 12 Cm A.07.79H m3 72.26 4,663,050.00 336,951,993.00
10 Pek. Pelat topi 8 Cm A.07.79N m3 2.88 4,663,050.00 13,429,584.00
11 Pek. Besi stek kolom dan balok A.07.25 kg 111.00 19,370.00 2,150,070.00
12 Pek. Besi stek pelat A.07.25 kg 39.00 19,370.00 755,430.00
13 Pas. Neut Kusen ls bh 4.00 15,000.00 60,000.00
Jumlah 709,096,521.90
V. PEK. KUSEN,PINTU DAN JENDELA
1 Pek. Kusen Ky.Lokal klas II A.06.03 m3 0.30 5,912,500.00 1,773,750.00
2 Pas. Pintu Panel Kayu lokal kls II A.06.07 m2 4.54 706,750.00 3,208,645.00
3 Pas. Daun Jendela kayu lokal kls II A.06.10 rob m2 0.96 577,500.00 554,400.00
4 Pas. Jalusi Kusen A.06.19 m2 2.02 720,500.00
5 Pek. Kaca 3 mm A.12.16 m2 2.88 100,380.00 289,094.40
Jumlah 5,825,889.40
1 2 3 4 5 6 7
VI PEK. LANTAI
1 Ur. Pasir alas lantai A.02.13 m3 13.71 189,750.00 2,601,472.50
2 Pas.Keramik Lantai 30 x 30 cm putih polos A.13.75 m2 137.10 230,930.00 31,660,503.00
3 Pas. stepnozing tangga 5 x 30 cm warna dihitung m' 20.00 99,000.00 1,980,000.00
Jumlah 36,241,975.50
VII PEK. ALAT PENGGANTUNG
1 Pas. Kunci 2 slaag ukuran besar A.12.02 bh 2.00 190,130.00 380,260.00
2 Pas. Engsel Pintu A.12.05 ps 9.00 32,180.00 289,620.00
3 Pas. Engsel Jendela A.12.06 ps 4.00 28,240.00 112,960.00
4 Pek. Pas. slot Jendela A.12.11A bh 2.00 39,980.00 79,960.00
5 Pek. Pas. Slot Pintu 15 cm A.12.11 ps 2.00 48,230.00 96,460.00
6 Pas. Hak angin kait A.12.09 ps 2.00 54,730.00 109,460.00
Jumlah 1,068,720.00
VIII. PEK. PENGECATAN
1 Cat Dinding sek. Sanlex A.14.28 m2 1,008.00 23,500.00 23,688,000.00
2 Cat Plafond sek. Sanlex A.14.29 m2 575.20 15,666.67 9,011,466.67
3 Cat Kayu sek. Avian A.14.30 m2 304.44 15,666.67 4,769,560.00
Jumlah 37,469,026.67
IX. PEKERJAAN INSTALASI LISTRIK
1 Sambungan kabel listrik dari bangunan terdekat dihitung 1 1.00 200,000.00 200,000.00
2 Pek. Instalasi titik cahaya 2x2.5mm upah bahan ttk 36.00 12,000.00 432,000.00
3 Pek. Instalasi titik stop kontak 3x2.5mm upah bahan ttk 10.00 12,000.00 120,000.00
4 Pas. Lampu PLC 18 watt + plafond fiting upah bahan bh 36.00 40,000.00 1,440,000.00
5 Pek. Stop kontak sek. Broco upah bahan ttk 10.00 22,500.00 225,000.00
6 Pek. Saklar Seri sek. Broco upah bahan ttk 9.00 30,000.00 270,000.00
Jumlah 2,687,000.00
I. PEK. PERSIAPAN
1 Papan Nama Kegiatan Dihitung ls 1.00 100,000.00 100,000.00
2 Pas. Steger bambu Dihitung ls 1.00 1,500,000.00 1,500,000.00
3 Pas. Bouwplank A.01.06 m' 16.00 3,584,900.00 57,358,400.00
4 Administrasi, dokumentasi dan perijinan Dihitung ls 1.00 2,790,000.00 2,790,000.00
Jumlah 61,748,400.00
II PEK. DINDING DAN PLESTERAN
1 Pas. Bata Dinding Baru 1 : 5 A.04.12 m2 193.08 125,750.00 24,279,810.00
2 Pas. Plesteran 1 : 5 + Acian A.05.05 m2 386.16 65,750.00 25,390,020.00
Jumlah 49,669,830.00
III PEK. BETON
1 Pek. Kolom 12/12 A.07.79D m3 0.34 4,941,070.00 1,679,963.80
2 Pek. Kolom 15/20 A.07.79E m3 2.09 7,083,770.00 14,805,079.30
3 Pek. Ring Balk 12/15 A.07.79C m3 1.57 3,690,020.00 5,793,331.40
4 Pek. Balok Lintel 12/15 A.07.79C m3 0.43 3,690,020.00 1,586,708.60
5 Pas. Neut Kusen ls bh 6.00 10,000.00 60,000.00
Jumlah 23,925,083.10
IV PEK. KUSEN,PINTU DAN JENDELA
1 Pek. Kusen Ky.Lokal klas II A.06.03 m3 1.08 5,912,500.00 6,385,500.00
2 Pas. Pintu Panel Kayu Lokal kls II A.06.07 m2 7.56 706,750.00 5,343,030.00
3 Pas. Daun Jendela kayu Lokal kls II A.06.10 rob m2 7.68 577,500.00 4,435,200.00
4 Pas. Papan Jalusi kayu Albasiah A.06.19 m2 20.16 720,500.00
5 Pek. Kaca 3 mm A.12.16 m2 153.60 100,380.00 15,418,368.00
Jumlah 31,582,098.00
V PEK. KUDA-KUDA,ATAP DAN PLAFOND
1 Pas. Kuda-kuda dan Rangka baja ringan m2 317.75 170,000.00 54,017,500.00
2 Pas. Genteng Baru morando natural A.08.03 m2 317.75 69,800.00 22,178,950.00
3 Pas. Bubungan Baru A.08.06 m' 38.00 98,620.00 3,747,560.00
4 Pas. Listplank Kayu kls II 3/20+3/7 cm A.06.50 m' 43.00 108,060.00 4,646,580.00
5 Pas. Rangka Plafond 5/10 & 5/7 kayu Albasiah A.06.44 rob m2 237.00 93,770.00 22,223,490.00
6 Pas. Plafond jabesmen 1 X 1 m A.09.03 m2 237.00 40,620.00 9,626,940.00
7 Pas. List pinggir plafond A.06.60 m' 181.00 10,820.00 1,958,420.00
Jumlah 118,399,440.00
VI PEK. LANTAI
1 Urugan Pasir Alas Lantai A.02.13 m3 6.75 189,750.00 1,280,812.50
2 Pas.Keramik Lantai 30 x 30 cm putih Polos A.13.75 m2 135.00 230,930.00 31,175,550.00
Jumlah 32,456,362.50
VII PEK. ALAT PENGGANTUNG
1 Pas. Kunci 2 Slaag ukuran besar A.12.02 bh 3.00 190,130.00 570,390.00
2 Pas. Engsel Pintu A.12.05 ps 15.00 32,180.00 482,700.00
3 Pas. Engsel Jendela A.12.06 ps 16.00 28,240.00 451,840.00
4 Pek. Pas. slot Jendela A.12.11A bh 8.00 39,980.00 319,840.00
5 Pek. Pas. Slot pintu 15 cm ls ps 4.00 15,000.00 60,000.00
6 Pas. Hak Angin Kait A.12.09 ps 8.00 54,730.00 437,840.00
Jumlah 2,322,610.00
1 2 3 4 5 6 7
VIII. PEK. PENGECATAN
1 Cat Dinding sekualitas Sanlex A.14.28 m2 386.16 23,500.00 9,074,760.00
2 Cat Plafond sekualitas Sanlex A.14.29 m2 237.00 15,666.67 3,713,000.00
3 Cat Kayu sekualitas seiv A.14.08 m2 101.48 16,640.00 1,688,627.20
Jumlah 14,476,387.20
IX. PEKERJAAN INSTALASI LISTRIK
1 Sambungan kabel listrik dari bangunan terdekat ls 1 1.00 100,000.00 100,000.00
2 Pek. Instalasi titik cahaya 2x2.5 mm ls ttk 12.00 12,000.00 144,000.00
3 Pek. Instalasi titik stop kontak 3x2.5mm ls ttk 2.00 12,000.00 24,000.00
4 Pas. Lampu PLC 18 watt + plafond fiting sek broco ls bh 12.00 40,000.00 480,000.00
5 Pek. Stop kontak sek. broco ls ttk 2.00 22,500.00 45,000.00
6 Pek. Saklar Seri sek. Broco ls ttk 3.00 30,000.00 90,000.00
Jumlah 883,000.00
I. PEK. PERSIAPAN
1 Papan Nama Kegiatan Dihitung ls 1.00 100,000.00 100,000.00
2 Pek.. Steger bambu Dihitung ls 1.00 500,000.00 500,000.00
3 Pek. Bouwplank A.01.06 m' 16.00 3,584,900.00 57,358,400.00
4 Administrasi, dokumentasi dan perijinan Dihitung ls 1.00 1,206,000.00 1,206,000.00
Jumlah 59,164,400.00
II PEK. DINDING DAN PLESTERAN
1 Pas. Bata Dinding Baru 1 : 5 A.04.12 m2 119.13 125,750.00 14,980,597.50
2 Pas. Plesteran 1 : 5 + Acian A.05.05 m2 238.26 65,750.00 15,665,595.00
Jumlah 30,646,192.50
III PEK. BETON
1 Pek. Kolom 12/12 A.07.79D m3 0.21 4,941,070.00 1,037,624.70
2 Pek. Kolom 15/20 A.07.79E m3 1.41 7,083,770.00 9,988,115.70
3 Pek. Ring Balk 12/15 A.07.79C m3 0.71 3,690,020.00 2,619,914.20
4 Pek. Balok Lintel 12/15 A.07.79C m3 0.17 3,690,020.00 627,303.40
5 Pek. Pelat meja beton A.07.79N m3 0.58 5,645,730.00 3,274,523.40
6 Pek. Kichen zing satu lubang lengkap aksesoris unit 3.00 450,000.00 1,350,000.00
7 Pek. Pipa pvc 1,5 " A.10.28 m' 24.00 35,350.00 848,400.00
8 Pek. Pipa pvc 1/2 " A.10.25 m' 24.00 22,560.00 541,440.00
9 Pek. Kran 1/2" A.10.35 bh 3.00 61,840.00 185,520.00
10 Pas. Neut Kusen ls bh 10.00 10,000.00 100,000.00
Jumlah 20,572,841.40
IV PEK. KUSEN,PINTU DAN JENDELA
1 Pek. Kusen 5/13 cm Ky.Lokal klas II A.06.03 m3 0.65 5,912,500.00 3,843,125.00
2 Pek. Pintu Panel Kayu Lokal kls II A.06.07 m2 9.07 577,500.00 5,237,925.00
3 Pek. Daun Jendela kayu Lokal kls II A.06.10 rob m2 7.68 720,500.00 5,533,440.00
4 Pek. Papan Jalusi kayu Albasiah A.06.19 m' 10.75 100,380.00
5 Pek. Kaca 3 mm A.12.16 m2 7.68 100,380.00 770,918.40
6 Pek. Lemari asam lengkap unit 1.00 4,000,000.00 4,000,000.00
Jumlah 19,385,408.40
V PEK. KUDA-KUDA,ATAP DAN PLAFOND
1 Pek. Listplank Kayu kls II 3/20+3/7 cm A.06.50 m' 20.00 108,060.00 2,161,200.00
2 Pek. Rangka Plafond 5/10 & 5/7 kayu Albasiah A.06.44 rob m2 103.00 93,770.00 9,658,310.00
3 Pek. Plafond jabesmen 1 X 1 m A.09.03 m2 103.00 40,620.00 4,183,860.00
4 Pek. List pinggir plafond kayu 1/4 cm A.06.60 m' 89.00 10,820.00 962,980.00
Jumlah 16,966,350.00
VI PEK. LANTAI
1 Urugan Pasir Alas Lantai A.02.13 m3 5.49 189,750.00 1,041,727.50
2 Pek. Keramik Lantai 30 x 30 cm putih Polos A.13.75 m2 109.80 230,930.00 25,356,114.00
3 Pek. Keramik meja beton 20 x 20 cm putih Polos A.13.68 m2 17.28 191,600.00 3,310,848.00
Jumlah 29,708,689.50
1 2 3 4 5 6 7
VII PEK. ALAT PENGGANTUNG
1 Pek. Kunci 2 Slaag ukuran besar A.12.02 bh 5.00 190,130.00 950,650.00
2 Pek. Engsel Pintu A.12.05 ps 18.00 32,180.00 579,240.00
3 Pek. Engsel Jendela A.12.06 ps 16.00 28,240.00 451,840.00
4 Pek. slot Jendela A.12.11A bh 8.00 39,980.00 319,840.00
5 Pek. Pas. Slot pintu 15 cm ls ps 2.00 15,000.00 30,000.00
6 Pek. Hak Angin Kait A.12.09 ps 8.00 54,730.00 437,840.00
Jumlah 2,769,410.00
VIII. PEK. PENGECATAN
1 Cat Dinding sekualitas Sanlex A.14.28 m2 238.26 23,500.00 5,599,110.00
2 Cat Plafond sekualitas Sanlex A.14.29 m2 103.00 15,666.67 1,613,666.67
3 Cat Kayu sekualitas seiv A.14.08 m2 50.74 16,640.00 844,313.60
Jumlah 8,057,090.27
IX. PEKERJAAN INSTALASI LISTRIK
1 Sambungan kabel listrik dari bangunan terdekat ls 1 1.00 300,000.00 300,000.00
2 Pek. Instalasi titik cahaya ls ttk 8.00 12,000.00 96,000.00
3 Pek. Instalasi titik stop kontak ls ttk 8.00 12,000.00 96,000.00
4 Pek. Lampu PLC 18 watt + plafond fiting ls bh 8.00 40,000.00 320,000.00
5 Pek. Stop kontak ls ttk 8.00 22,500.00 180,000.00
6 Pek. Saklar tunggal ls ttk 3.00 30,000.00 90,000.00
7 Pek. Saklar Seri ls ttk 2.00 30,000.00 60,000.00
Jumlah 1,142,000.00
191,308,000.00 (177,701,000.00)
73,816,000.00 (133,437,000.00)
801,191,000.00 (742,340,000.00)
801,191,000.00
(742,340,000.00)
(674,854,545.45)
TU RIBU RUPIAH
DAHIT
71.36
2.20
2.20
0.8400
1.1340
39.20
13.40
4.14
0.82
0.05
20.79
12.86
8.92
0.40
70.87 1.39 72.26
2.88
4.54
0.96
2.02
2.88
8.10
137.10 549.00 0.675
20.00
16.6
16.6
1.28
34.48
1.3792
1,008.00
575.20
304.44
36.00
0.38592
2.085
1.566
0.432
1.08
7.56
7.68
20.16
153.6
197.75 120
38
43
237
181
135
101.48
191,308,000.00
(177,701,000.00)
(161,546,363.64)
139.03 19.9 119.13
0.21384
1.413
0.7074
0.1728
0.576
9.072
7.68
10.752
7.68
20
103
89
109.8
17.28
50.743
73,816,000.00
(133,437,000.00)
(121,306,363.64)
REKAPITULASI ANGGARAN BIAYA
KEGIATAN : REHABILITASI GEDUNG
PEKERJAAN : REHABILITASI GEDUNG MAN 2 CIAMIS
LOKASI : KABUPATEN CIAMIS
SUMBER DANA : APBN
TAHUN ANGGARAN : 2009
JUMLAH
No. URAIAN HARGA
Rp.
TUJUH PULUH TUJUH JUTA SERATUS DUA PULUH EMPAT RIBU SEMBILAN RATUS RIBU
TERBILANG :
RUPIAH
I. PEK. PERSIAPAN
1 Papan Nama Proyek A.01.16 m2 0.60 238,900.00 143,340.00
2 Pek. Bongkaran dihitung ls 1.00 1,000,000.00 1,000,000.00
3 Pas. Bouwplank A.01.06 m' 4.00 3,584,900.00 14,339,600.00
4 Administrasi, dokumentasi dan perijinan dihitung ls 1.00 1,676,300.00 1,676,300.00
Jumlah 17,159,240.00
II. PEK. TANAH DAN PONDASI
1 Galian tanah pondasi A.02.01 m3 1.88 46,200.00 86,856.00
2 Urugan tanah kembali A.02.11 m3 0.47 22,140.00 10,405.80
3 Urugan Pasir alas Pondasi A.02.13 m3 0.24 189,750.00 44,591.25
4 Pas. Pondasi batu kosong A.03.13 m3 0.71 373,590.00 263,380.95
5 Pas. Pondasi batu belah 1:5 A.03.05 m3 1.32 755,000.00 993,580.00
Jumlah 1,398,814.00
III PEK. DINDING DAN PLESTERAN
1 Pas. Bata dinding baru 1 : 5 A.04.12 m2 36.74 125,750.00 4,620,055.00
2 Pas. Plesteran 1 : 5 + Acian A.05.05 m2 73.48 65,750.00 4,831,310.00
4 Pas. Keramik meja, ddng Lab. 20 x 20 polos A.13.68 m2 16.73 191,600.00 3,205,468.00
Jumlah 12,656,833.00
IV. PEK. BETON
1 Pek. Kolom praktis 12/12 A.07.79D m3 0.13 4,941,070.00 647,477.81
2 Pek. Kolom 15/20 A.07.79E m3 0.21 7,083,770.00 1,487,591.70
3 Pek. Ring Balok 12/15 A.07.79L m3 1.09 5,634,060.00 6,135,491.34
4 Pek. Plat Meja beton A.07.79N m3 0.54 5,645,730.00 3,048,694.20
Jumlah 11,319,255.05
V. PEK. KUSEN,PINTU DAN JENDELA
1 Pek. Kusen Ky.Lokal klas II A.06.03 m3 0.09 5,912,500.00 532,125.00
2 Pas. Daun Jendela kayu lokal kls II A.06.10 rob m2 1.25 577,500.00 723,492.00
3 Pek. Kaca 5 mm A.12.17 m2 2.39 154,830.00 370,043.70
4 Pas. Pintu Fiber KM/WC lengkap upah bahan unit 2.00 400,000.00 800,000.00
5 Pek. Lemari asam lengkap dihitung Ls 1.00 4,000,000.00 4,000,000.00
Jumlah 6,425,660.70
VI. PEK. KUDA-KUDA,ATAP DAN PLAFOND
1 Pas. Kuda2,Gording dll Ky lokal kla II A.06.35 m3 1.90 4,352,700.00 8,270,130.00
2 Pas. Kuda2,Gording dll Ky lama A.06.35.Rob m3 3.50 1,327,700.00 4,646,950.00
3 Rangka Atap Kaso 5/7 + Reng 2/3 Lokal Kelas II A.06.38 m2 194.80 79,390.00 15,465,172.00
4 Pas. Genteng Baru Palentong A.08.02 m2 203.65 69,800.00 14,214,770.00
5 Pas. Bubungan Baru A.08.05 m' 36.80 119,300.00 4,390,240.00
6 Pas. Listplank baru 3/25 Kayu Albasiah A.06.50 rob m' 59.00 69,560.00 4,104,040.00
7 Pas. Rangka Plafond 5/10 & 5/7 ky. Albasiah A.06.44 rob m2 166.50 93,770.00 15,612,705.00
8 Pas. Eternit 1 X 1 m A.09.02 m2 166.50 23,660.00 3,939,390.00
9 Pas. List pinggir plafond A.06.60 m' 175.00 10,820.00 1,893,500.00
Jumlah 72,536,897.00
VII. PEK. LANTAI
1 Ur. Pasir alas lantai A.02.13 m3 0.09 189,750.00 17,077.50
2 Pas.Keramik Lantai 30 x 30 cm putih polos A.13.75 m2 3.00 230,930.00 692,790.00
3 Pas.Keramik Lantai 20 x 20 cm anti slip A.13.44 m2 4.53 216,270.00 979,703.10
Jumlah 1,689,570.60
VIII PEK. ALAT PENGGANTUNG
1 Pas. Kunci 2 slaag A.12.02 bh 1.00 190,130.00 190,130.00
2 Pas. Engsel Pintu A.12.05 ps 3.00 32,180.00 96,540.00
3 Pas. Engsel Jendela A.12.06 ps 4.00 28,240.00 112,960.00
4 Pek. Pas. slot Jendela A.12.11A bh 2.00 39,980.00 79,960.00
5 Pas. Hak angin kait A.12.09 ps 2.00 54,730.00 109,460.00
6 Pas. moor bout upah bahan kg 43.00 15,000.00 645,000.00
Jumlah 1,234,050.00
IX. PEK. PENGECATAN
1 Cat Dinding baru sek. Sanlex A.14.28 m2 73.48 23,500.00 1,726,780.00
2 Cat Dinding lama sek. Sanlex A.14.15 m2 239.37 17,070.00 4,086,045.90
3 Cat Plafond sek. Sanlex A.14.29 m2 166.50 23,500.00 3,912,750.00
4 Cat Kayu sek. Avian A.14.30 m2 41.00 23,500.00 963,500.00
5 Solignum Rangka Atap A.14.12 m2 194.80 12,810.00 2,495,388.00
Jumlah 13,184,463.90
X. PEKERJAAN INSTALASI LISTRIK
1 Sambungan kabel listrik dari bangunan terdekat dihitung 1 1.00 200,000.00 200,000.00
2 Pek. Instalasi titik cahaya upah bahan ttk 9.00 12,000.00 108,000.00
3 Pek. Instalasi titik stop kontak upah bahan ttk 5.00 75,000.00 375,000.00
4 Pas. Lampu PLC 18 watt + plafond fiting upah bahan bh 9.00 40,000.00 360,000.00
5 Pek. Stop kontak upah bahan ttk 5.00 22,500.00 112,500.00
6 Pek. Saklar Seri upah bahan ttk 2.00 30,000.00 60,000.00
Jumlah 1,215,500.00
XI PEKERJAAN SANITAIR
1 Pas. Pipa PVC Ø 2.5 " instalasi air kotor A.10.30 m' 16.00 41,750.00 668,000.00
2 Pas. Pipa PVC Ø 3/4 " instalasi air bersih A.10.26 m' 12.00 24,700.00 296,400.00
3 Pas. Pipa PVC Ø 1/2 " instalasi air bersih A.10.25 m' 8.00 22,560.00 180,480.00
4 Pas. Closet jongkok A.10.02 bh 2.00 3,660,580.00 7,321,160.00
5 Pas. Bak fiber + pasangan bata A.10.07 bh 2.00 171,520.00 343,040.00
6 Pas. Floor Drain bak cuci A.10.36 bh 4.00 67,200.00 268,800.00
7 Pas. Kran Tembok Ø 1/2 " A.10.35 bh 6.00 61,840.00 371,040.00
Jumlah 9,448,920.00
78,487,500.00
(84,608,600.00)
(76,916,909.09)
###
0.09
13.10
0.864
0.864
0.864
0.6264
0.9
4.1184 (57.93)
6.5088 -
59
162.5
(76,916,909.09)
(4,505.97)
ANALISA SATUAN PEKERJAAN
LOKASI : Kab. Tasikmalaya
TAHUN ANGGARAN : 2021
NO. URAIAN KOEF SAT. HARGA SAT. JUMLAH
1 2 3 4 5 6=(3x5)
A.01.06 PERENCANAAN
I. TENAGA AHLI
Team Leader 0.0750 Org 7,000,000.00 525,000.00
Jumlah 525,000.00
II. TENAGA PENDUKUNG
Surveyor 0.0200 Org 2,700,000.00 54,000.00
Drafter 0.5000 Org 2,700,000.00 1,350,000.00
Administrasi 0.5000 Org 2,200,000.00 1,100,000.00
Jumlah 2,504,000.00
III. LAPORAN
1. Laporan Perencanaan (Gambar, RAB) 1.0000 bh 210,000.00 210,000.00
2. CD Soft Copy Laporan 1.0000 bh 20,000.00 20,000.00
Jumlah 230,000.00
Jumlah I + II + III 3,259,000.00
Keuntungan Max. 10 % 325,900.00
Jumlah Total 3,584,900.00
Dibulatkan 3,584,900.00
A.02.01 1 M3 GALIAN TANAH BIASA KEDALAMAN MAX 1 M
BAHAN :
-
Jumlah Bahan -
UPAH :
Pekerja 0.4000 Oh 90,000.00 36,000.00
Mandor 0.0400 Oh 150,000.00 6,000.00
Jumlah Pekerja 42,000.00
Jumlah Bahan + Pekerja 42,000.00
Keuntungan Max. 10 % 4,200.00
Jumlah Total 46,200.00
Dibulatkan 46,200.00
A.02.11 1 M3 URUGAN TANAH KEMBALI
BAHAN :
-
-
Jumlah Bahan -
UPAH :
Pekerja 0.1920 Oh 90,000.00 17,280.00
Mandor 0.0190 Oh 150,000.00 2,850.00
Jumlah Pekerja 20,130.00
Jumlah Bahan + Pekerja 20,130.00
Keuntungan Max. 10 % 2,013.00
Jumlah Total 22,143.00
Dibulatkan 22,140.00
1 2 3 4 5 6=(3x5)
A.02.13 1 M3 URUGAN PASIR
BAHAN :
Pasir Urug 1.2000 m³ 120,000.00 144,000.00
Jumlah Bahan
UPAH :
Pekerja 0.1500 Oh 90,000.00 13,500.00
Tukang Kayu 0.0750 Oh 110,000.00 8,250.00
Kepala Tukang 0.0080 Oh 120,000.00 960.00
Mandor 0.0050 Oh 150,000.00 750.00
Jumlah Pekerja 23,460.00
Jumlah Bahan + Pekerja 23,460.00
Keuntungan Max. 10 % 2,346.00
Jumlah Total 25,806.00
Dibulatkan 25,800.00
DOKUMEN KONTRAK
MAN 1 KABUPATEN TASIKMALAYA
Sukamanah
ANTARA :
-
Pemilik Pekerjaan,
DENGAN
H. DADANG ROCHANDA
Pelaksana Pekerjaan
2016
II
MAN 1 KABUPATEN TASIKMALAYA
Sukamanah
BILL OF QUANTYTY
DAFTAR HARGA UPAH
ANTARA :
0
Pemilik Pekerjaan,
DENGAN
H. DADANG ROCHANDA
Pelaksana Pekerjaan
2016
I
MAN 1 KABUPATEN TASIKMALAYA
Sukamanah
SPK
REKAPITULASI BIAYA
ANTARA :
0
Pemilik Pekerjaan,
DENGAN
H. DADANG ROCHANDA
Pelaksana Pekerjaan
2016
III
MAN 1 KABUPATEN TASIKMALAYA
Sukamanah
GAMBAR-GAMBAR RENCANA
ANTARA :
0
Pemilik Pekerjaan,
DENGAN
H. DADANG ROCHANDA
Pelaksana Pekerjaan
2016
REKAPITULASI : BILL OFF QUANTITY (BQ)
JUMLAH
No. URAIAN HARGA
Rp.
A. PEK. LANTAI 1
I. PEK. PERSIAPAN -
II. PEK. TANAH DAN PONDASI #REF!
III. PEK. DINDING DAN PLESTERAN #REF!
IV. PEK. BETON #REF!
V. PEK. KUSEN,PINTU DAN JENDELA #REF!
VI. PEK. KUDA-KUDA, ATAP DAN PLAFOND #REF!
VII. PEK. LANTAI #REF!
VIII. PEK. ALAT PENGGANTUNG, RELLING DAN KACA #REF!
IX. PEK. PENGECATAN #REF!
X. PEKERJAAN INSTALASI LISTRIK -
XI. PEKERJAAN INSTALASI AIR -
JUMLAH REAL COST LANTAI 1 #REF!
B. PEK.LANTAI 2
TERBILANG :
HARGA JUMLAH
NO. URAIAN PEKERJAAN KODE SAT. VOLUME SATUAN HARGA SATUAN
ANALIS Rp. Rp.
1 2 3 4 5 6 7
A. PEK. LANTAI 1
I. PEK. PERSIAPAN
1 Pengukuran dan Perencanaan Bangunan 2 lantai dihitung m2 261.44 -
2 Pekerjaan Bouplank and fill A.01.06 m' - -
3 Izin Mendirikan Bangunan (IMB) dihitung m2 261.44 -
Jumlah -
II. PEK. TANAH DAN PONDASI
1 Galian tanah pondasi A.02.01 m3 #REF! #REF!
2 Pas. Aanstamping Batu kosong A.07.01 m3 #REF! #REF!
3 Pondasi Batu Kali A.02.11 m3 #REF! #REF!
4 Urugan Pasir alas Pondasi A.02.13 m3 #REF! #REF!
Jumlah #REF!
III. PEK. DINDING DAN PLESTERAN
1 Pas. Bata dinding bata 1:3 A.04.10 m2 #REF! #REF!
2 Pas. Bata dinding bata 1:5 A.04.12 m2 #REF! #REF!
3 Pas. Plesteran 1:3 + Acian A.05.03 m2 #REF! #REF!
4 Pas. Plesteran 1:5 + Acian A.05.05 m2 #REF! #REF!
5 Pas. Batu Alam Andesit bakar 40x60 cm A.13.77 m2 39.60 -
6 Pas. Dinding Keramik 25/40 cm warna ,KM/WC A.13.68 m2 #REF! #REF!
Jumlah #REF!
IV. PEK. BETON
1 Pek. Sloof Beton 20/30 CM A.07.79B m3 #REF! #REF!
2 Pek. Por Beton A.07.79A m3 #REF! #REF!
3 Pek. Kolom 12/30, 25/25 dan 12/45 A.07.79G m3 #REF! #REF!
4 Pek. Balok Beton 15/20, 15/60 dan 20/40 A.07.79K m3 #REF! #REF!
5 Pek. Ring Balok latai 12/15 A.07.79L m3 #REF! #REF!
6 Pek. Meja Beton Lab A.07.79H m3 #REF! #REF!
7 Pek. Topi Beton dan Dak Beton A.07.79H m3 #REF! #REF!
Jumlah #REF!
V. PEK. KUSEN,PINTU DAN JENDELA
1 Pek. Kusen Aluminium dihitung m' #REF! #REF!
2 Pas. Pintu Panel Multy Rangka Kayu Kamper A.06.07 m2 #REF! #REF!
3 Pas. Pintu Panel Toilet dari Alumunium dihitung m2 #REF! #REF!
4 Pas. Pintu Kaca Rangka Aluminium Ke teras blk dihitung m2 #REF! #REF!
5 Pas. Pintu Kaca Es Rangka Aluminium Ke Ruang
dihitung m2 #REF! #REF!
Dokter disleding+Rell Pintu
6 Pas. Daun Jendela Casmet Aluminium A.06.10 rob m2 #REF! #REF!
Jumlah #REF!
VI. PEK. KUDA-KUDA, ATAP DAN PLAFOND
1 Rangka Atap Baja Ringan dihitung m2 - -
2 Pas. Genteng Plat Beton Cisangkan A.08.03 m2 - -
3 Pas. Bubungan Plat Beton Cisangkan A.08.05 m' - -
4 Pas. Listplank Wood Plank A.06.50 m' - -
5 Pas. Talang Miring Alumunium dihitung m' - -
6 Pas. Rangka Plafond Holo 2/4, 4/4 cm dihitung m2 #REF! #REF!
7 Pas. Plafond Gypsum A.09.03.rob m2 #REF! #REF!
8 Pas. Plafond GRC A.09.03 m2 #REF! #REF!
9 Pas. List Gypsum 12 cm pinggir plafond A.06.60.rob m' #REF! #REF!
10 Pas. List Kayu 4 cm pinggir plafond A.06.60 m' #REF! #REF!
Jumlah #REF!
HARGA JUMLAH
NO. URAIAN PEKERJAAN KODE SAT. VOLUME SATUAN HARGA SATUAN
ANALIS Rp. Rp.
1 2 3 4 5 6 7
VII. PEK. LANTAI
1 Ur. Pasir alas lantai A.02.13 m3 #REF! #REF!
2 Pas. Keramik Lantai 25 x 25 cm Toilet dop A.13.44 m2 #REF! #REF!
3 Pas. Lantai Utama Keramik 40x40 cm A.13.75 m2 92.00 -
4 Pas. Teras Keramik 40x40 cm A.13.75 m2 #REF! #REF!
5 Pas. Selasar 40x40 cm Anti Slip/Corak A.13.75 m2 #REF! #REF!
6 Pas. Floor Beton Dihitung m3 #REF! #REF!
Jumlah #REF!
VIII. PEK. ALAT PENGGANTUNG, RELLING DAN KACA
1 Pas. Handle pintu Utama + Kunci selinder Dihitung Ps 2.00 -
2 Pas. Kunci 2 slaag ukuran besar A.12.02 bh 3.00 -
3 Pas. Engsel Pintu A.12.05 ps 5.00 -
4 Pas. Engsel Jendela A.12.06 ps #REF! #REF!
5 Pek. Pas. slot Jendela A.12.11A bh #REF! #REF!
6 Pek. Pas. Slot Pintu Tanam ls ps 4.00 -
7 Pas. Hak angin kait A.12.09 ps #REF! #REF!
8 Pas. Kunci Slot Grendel Pintu Toilet dihitung bh 3.00 -
9 Rel Pintu Sleding dari R tunggu ke R Dokter dihitung pcs 1.00 -
10 Pas. Kaca 5 mm A.12.17 m2 #REF! #REF!
11 Pas. Kaca Es A.12.17 b m2 #REF! #REF!
12 Pas. Handrelling Pagar dan Balcoun dihitung m2 14.00 -
13 Pas. Pintu Stainllis dihitung m2 1.80 -
Jumlah #REF!
IX. PEK. PENGECATAN
1 Cat Dinding Dalam sek. Catylac A.14.28 m2 #REF! #REF!
2 Cat Dinding Luar sek. Mowilex A.14.28b. m2 #REF! #REF!
3 Cat Plafond sek. Catylac A.14.29 m2 #REF! #REF!
4 Cat Kayu A.14.30 m2 - -
5 Water Proofing dihitung m2 #REF! #REF!
Jumlah #REF!
X. PEKERJAAN INSTALASI LISTRIK
1 Biaya Pasang Listrik (BP) KWH 3200 wtt dihitung 1 1.00 -
2 Pasang Box MCB 3 Pass dihitung Unit 1.00 -
3 Pek. Instalasi titik cahaya 2x1.5 mm upah bahan ttk 18.00 -
4 Pek. Instalasi titik stop kontak 3x1.5mm upah bahan ttk 6.00 -
5 Pas. Lampu Baret upah bahan ttk 2.00 -
6 Pas. Lampu Down Light upah bahan ttk 10.00 -
7 Pas. Lampu PLC 14 watt + plafond fiting upah bahan bh 13.00 -
8 Pas. Lampu TKI 2X14 watt upah bahan bh 5.00 -
9 Pek. Stop kontak sek. Broco upah bahan ttk 6.00 -
10 Pek. Saklar Tunggal sek. Broco upah bahan ttk 3.00 -
11 Pek. Saklar Seri sek. Broco upah bahan ttk 6.00 -
12 Pek. Penangkal Petir dan pentanahan upah bahan ttk - -
Jumlah -
XI. PEKERJAAN INSTALASI AIR
1 Biaya Penyambungan Air (BP PDAM) dihitung Unit 1.00 -
2 Pek. Instalasi air bersih pipa PVC Dia 3/4" A.10.26 m' 24.00 -
3 Pek. Instalasi air bersih pipa PVC Dia 1/2" A.10.25 m' 24.00 -
4 Pek. Instalasi air kotor pipa PVC Dia 4" A.10.30 m' 16.00 -
5 Pek. Instalasi air hujan pipa PVC Dia 2.5" A.10.29 m' 20.00 -
6 Pek. Instalasi air Air Panas dihitung m' - -
7 Pek. Wash Tafle Console Counter dihitung Unit 1.00 -
8 Pek. Kaca Cermin diatas Washtafle dihitung Unit 1.00 -
9 Pas. Closet Duduk Setara TOTO A.10.02 bh 1.00 -
10 Pas. Closet jongkok A.10.02 bh 2.00 -
11 Pas. Kran + Hand Shower 1/2" dihitung bh 2.00 -
12 Pas. Shower Spray 1/2" dihitung bh 1.00 -
13 Pas. Kran air 1/2" A.10.35 bh 3.00 -
14 Pas. Floor drain A.10.36 bh 3.00 -
15 Pas. Sink Washtafel/sfoolhuk dihitung set 1.00 -
16 Pek. Bak Kontrol dihitung set 2.00 -
17 Pek. Septictank + Rembesan A.14.01 set 1.00 -
Jumlah -
HARGA JUMLAH
NO. URAIAN PEKERJAAN KODE SAT. VOLUME SATUAN HARGA SATUAN
ANALIS Rp. Rp.
1 2 3 4 5 6 7
B. PEK.LANTAI 2
Balk
DIA 14 4 #REF! #REF! #REF!
DIA 12 4 #REF! #REF! #REF!
DIA 8 #REF! 0.9 #REF! #REF!
Plat Beton
DIA.8 10.5 0.15 10 700
10 0.15 10.5 700
1,400 2 2,800 253
Lantai 2
Kolom
DIA 12 8 3.5 8 224 11.5 19
DIA 10 4 3.5 17 238 11.5 21
DIA 6 1.5 19 8 222 19
0.5 19 17 157.25 14
33
Ring Balk #REF!
DIA 10 4 #REF! #REF!
DIA 6 #REF! 0.5 #REF! #REF!
KEBUTUHAN BESI
NO URAIAN
LOKASI : Sukamanah
PEMILIK : -
3 PENGADAAN MATERIAL : Pengadaan seluruh material yang dibutuhkan dalam pekerjaan sebagaimana yang
tercantum dalam Bill Off Quantity (BQ)
4 ALAT KERJA : Termasuk pengadaan seluruh alat kerja pekerjaan sipil dan ME.
6 WAKTU PELAKSANAAN : 1. Waktu Pelaksanaan selama 150 ( Seratus Lima Puluh ) hari kerja, Sejak tanggal
ditanda tanganinya Surat Perjanjian Mulai Kerja ini.
2. Waktu Pemeliharaan pekerjaan selama 30 (Tiga puluh) hari kerja, terhitung
sejak dinyatakan selesai pekerjaan tahap ke 1.
10 LAIN-LAIN : 1. Pekerjaan yang dilaksanakan oleh "Penerima Pekerjaan" harus selesai sesuai jadwal
pelaksanaan dan dengan mutu pekerjaan sesuai yang telah ditentukan.
3. Apabila pekerjaan dibatalkan, maka uang muka dan seluruh pembayaran yang telah
diterima oleh Pelaksana wajib dikembalikan ke Pemberi Tugas dalam waktu
selambatnya 7 (tujuh) hari sejak pekerjaan dibatalkan, setelah terlebih dahulu
diperhitungkan dengan nilai pekerjaan yang sudah dilaksanakan.
4. Apabila tenaga kerja tidak cakap atau kurang, maka "Pemberi Pekerjaan" ber-hak
mengajukan untuk diganti oleh tenaga yang lebih cakap kepada pihak "Penerima
pekerjaan" dan biayanya menjadi beban "Penerima pekerjaan".
5. Mutu Pekerjaan :
- Pekerjaan harus baik dan rapih.
- Bertanggung jawab apabila dikemudian hari terdapat pekerjaan yang perlu
diperbaiki sesuai dalam waktu pemeliharaan pekerjaan.
8. Hal-hal yang belum diatur dalam perjanjian ini akan diatur kemudian sesuai dengan
kebutuhan kedua belah pihak secara musyawarah.
9. Demikian Surat Perjanjian ini dibuat rangkap dua, asli masing-masing bermaterai
cukup dan mempunyai kekuatan hukum yang sama.
Berlaku mulai ,
-
BERITA ACARA NEGOSIASI HARGA PEKERJAAN
Pada hari ini Selasa, Tanggal Sembilan Belas Bulan Juli Tahun Dua ribu Enam belas (19/07/2016), telah diadakan
Negosiasi Harga sebagai berikut :
Lokasi : Sukamanah
Luas Bangunan : #REF! M2
Nama :###
Tanggal Lahir : 11 Januari 1970
Alamat : Jl. Harsonosudiro No. 1 Lingkungan Desa, Kelurahan Cigembor Kab./Kec. Ciamis
Sesuai Penawaran Rencana Anggaran biaya (RAB) dan Rekapitulasi Harga dari yang diajuankan oleh pihak kedua
kepada pihak kesatu/Pemilik Pekerjaan untuk pekerjaan tersebut diatas sebesar :
Rp 22,292,000.00 Terbilang : Lima ratus Lima puluh Lima Juta Sembilan ratus Delapan puluh
Enam ribu Rupiah===
Selanjutnya setelah diadakan negosiasi harga pekerjaan oleh kedua belah pihak disepakati harga tersebut sebesar :
Rp 525,000,000.00 Terbilang : Lima ratus Dua puluh Lima juta Rupiah========
Harga yang telah disepakati diatas meliputi seluruh Item pekerjaan sebagaimana yang diuraikan didalam Bill of
Quantity (BQ) terlampir*).
Demikian Negosiasi Harga ini telah disepakati bersama antara Pihak Pertama / pemilik Pekerjaan dan Pihak kedua
/ Pelaksana Pekerjaan yang selanjutnya kesepakatan harga tersebut akan menjadi acuan dan ketetapan terhadap Nilai
Kontrak didalam Surat Perjanjian Kerja (SPK).