RENCANA ANGGARAN BIAYA


PROYEK : RENOVASI RUMAH
Alamat : Kaliberot,Bantul
PEM. : Bp.Rusdy

NO JENIS PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH HARGA


PEKERJAAN LANTAI 2

A. PEKERJAAN BONGKARAN
1 Bongkar Atap 14.0 m2 30,000.00 420,000.00
2 Bongkar Pfafond 14.0 m2 35,000.00 490,000.00
SUB JUMLAH A Rp 910,000.00
B. PEKERJAAN PASANGAN
1 Pasangan Dinding 75 cm 13.90 m2 155,000.00 2,154,500.00
2 Plester dinding 27.80 m2 46,000.00 1,278,800.00
3 Acian 27.80 m2 28,500.00 792,300.00
4 Sponengan 4.00 ml 19,500.00 78,000.00
SUB JUMLAH B Rp 4,303,600.00
C. PEKERJAAN BETON
1 Kolom praktis 0.12 m3 4,850,000.00 572,906.25
2 Ring balok 0.500 m3 4,800,000.00 2,397,600.00
SUB JUMLAH C Rp 2,970,506.25
D. PEKERJAAN FINISHING DAN PLAFOND
1 Cat dinding Jotun dinding baru 27.80 m2 38,500.00 1,070,300.00
2 Rangka + Gypsum 14.00 m2 100,000.00 1,400,000.00
3 Cat Plafond 14.00 m2 35,000.00 490,000.00
SUB JUMLAH D Rp 2,960,300.00
E. PEKERJAAN ATAP DAN RAILLING
1 Pasang Kembali Atap 14.0 m2 45,000.00 630,000.00
2 Ralling pagar atas besi hollo + jaring kawat 9.0 ml 550,000.00 4,950,000.00
SUB JUMLAH G Rp 5,580,000.00
TOTAL PEKERJAAN RENOVASI LANTAI 2 Rp 16,724,406.25
GRAND TOTAL PEKERJAAN RENOVASI LANTAI 2 Rp 16,724,406.25

* Bila ada pekerjaan tambahan masuk adenbum

Yogyakarta, 23 febuari 2024


Di hitung Oleh …........

( Windra Wiwid Widyasmoko,S.Ars)


RENCANA ANGGARAN BIAYA
PROYEK : RENOVASI RUMAH
Alamat : Kaliberot,Bantul
PEM. : Ibu Nindy
NO JENIS PEKERJAAN VOLUME SAT HARGA SATUAN
PEKERJAAN LANTAI 1
A. PEKERJAAN BONGKARAN DAN GALIAN
1 Bongkar Dinding 86.7 m2 40,500.00
2 Bongkar ring balok 18.8 ml 60,000.00
3 Bongkar kolom 14 bh 55,000.00
4 Bongkar topi beton 4.5 m2 65,000.00
5 Bongkar Pintu 5 bh 75,000.00
6 Bongkar Jendela (per daun) 3 bh 60,000.00
7 Bongkar sebagianAtap 25 m2 65,000.00
8 Bongkar plesteran acian dinding lembab 10.8 m2 27,500.00
10 Galian Pondasi 15.616 m3 125,000.00
11 Galian untuk pipa 4.32 m3 105,000.00
SUB JUMLAH A
B. PEKERJAAN PASANGAN
1 Pasangan Pondasi Batu kali 12.90 m3 785,000.00
2 Pasangan Bata merah dinding 100.33 m2 150,000.00
3 Pasangan Bata merah Gunung2 9.20 m2 159,000.00
4 Plester dinding 210.66 m2 39,000.00
5 Plester gunung2 9.20 m2 45,000.00
6 Acian 210.66 m2 28,500.00
7 Acian gunung2 9.20 m2 32,000.00
8 Plester aci lantai 65.00 m2 62,000.00
9 Pas.Roster dan bata expose 12.70 m2 450,000.00
10 Pas.Comwood plank 3.60 m2 475,000.00
11 Sponengan 37.00 ml 19,500.00
SUB JUMLAH B
C. PEKERJAAN BETON
1 Balok Latiu 0.536625 m3 4,250,000.00
2 Plat Lantai beton 1 tebal 8 cm 5.2 m3 4,250,000.00
3 Topi/Talang beton timur 10 cm 0.9 m3 5,250,000.00
4 Kolom praktis 0.76 m3 4,450,000.00
5 Sloof 0.682 m3 4,450,000.00
6 Ring balok 2.232 m3 4,900,000.00
7 Plat dapur 0.25 m3 4,250,000.00
SUB JUMLAH C
D. PEKERJAAN FINISHING DAN PLAFOND
1 Cat dinding Jotun dalam 196.20 m2 38,500.00
2 Cat dinding Jotun luar 79.20 m2 43,500.00
3 Rombak Rangka + Gypsum 75.00 m2 105,000.00
4 Drop ceiling 8.00 ml 60,000.00
5 Cat Plafond 75.00 m2 35,000.00
6 Sika dak 7.00 m2 56,500.00
SUB JUMLAH D
E. PEKERJAAN KERAMIK KAMAR MANDI
1 Pek.Poles lantai acian 60 m2 85,000.00
2 Pas.Keramik Lantai km/wc 25x25 5 m2 225,000.00
3 Pas.Keramik dinding 25x40 33 m2 235,000.00
4 Pas. Keramik meja dapur 60x60 2 m2 295,000.00
5 Pas.Keramik dapur 30x60 5.5 m2 295,000.00
SUB JUMLAH E
F. PEKERJAAN PINTU DAN JENDELA
1 Kusen almunium 18.2 ml 140,000.00
2 Daun Pintu kayu 2 unit 1,750,000.00
3 Pintu Kamar mandi UPVC 2 unit 1,100,000.00
4 Daun pintu almunium untuk belakang 1 unit 1,250,000.00
5 Daun Jendela 1 unit 750,000.00
6 Kunci Hndle set 2 set 210,000.00
7 Kait angin Kunci jendela 1 bh 80,000.00
9 Cat baru dan ulang pintu 5 unit 325,000.00
SUB JUMLAH F
G. PEKERJAAN ATAP DAN RAILLING
1 Penenambahan atap utama baja ringan +galvalum berpasir 29.6 m3 195,000.00
2 Penambahan atap transparan samping 5.4 m2 245,000.00
SUB JUMLAH G
H. PEKERJAAN ELECTRICAL DAN SANITASI
Electrical
1 Instalasi Penerangan 13 unit 190,000.00
2 Instalasi Stopkontak 7 unit 190,000.00
3 Lampu Downlight 11 unit 190,000.00
4 Lampu strep drop ceiling 8 ml 55,000.00
5 Lampu spot roster 2 bh 175,000.00
6 Stopkontak 7 unit 57,000.00
7 Saklar Single 6 unit 57,000.00
8 Saklar Double 3 unit 57,000.00
9 MCB 1 bh 175,000.00

Sanitasi
1 Pipa 3 " 20 ml 110,000.00
2 Pipa 4 " 20 ml 180,000.00
3 Pipa 1 in 19 ml 38,500.00
4 Pipa 3/4 in 6 ml 45,000.00
5 Floordrain 2 bh 135,000.00
6 Shower 2 bh 350,000.00
7 Closet duduk 2 bh 2,150,000.00
8 Kran angsa Onda 1 bh 225,000.00
9 Zink bak cuci rozal 1 bh 850,000.00
10 Kran 1 bh 135,000.00
11 Bak Penghancur 1 bh 1,250,000.00
12 Stop kran 1 bh 155,000.00
SUB JUMLAH H
TOTAL PEKERJAAN RENOVASI LANTAI 1
GRAND TOTAL PEKERJAAN RENOVASI LANTAI 1
NEGOTIABLE

CATATAN :
* Sudah Toren 650 Liter
* Kanopy Depan
Ketentuan :
-
Setelah mencapai kesepakatan harga akan dibuatkan Surat Perjanjian Kontrak bermaterai (lampiran fc ktp)
-
Termin pembayaran :
Bangun Nol (30% + 40% + 25%+5%) sesuai SPK
Renovasi (40% + 30% + 25%+5%) sesuai SPK
Jika Pekerjaan Biaya tambahan sebelum kontrak selesai dibuatkan tagihan adendum
JUMLAH HARGA

3,511,350.00
1,128,000.00
770,000.00
292,500.00
375,000.00
180,000.00
1,625,000.00
297,000.00
1,952,000.00
453,600.00
Rp 10,584,450.00

10,126,500.00
15,049,500.00
1,462,800.00
8,215,740.00
414,000.00
6,003,810.00
294,400.00
4,030,000.00
5,715,000.00
1,710,000.00
721,500.00
Rp 53,743,250.00

2,280,656.25
22,100,000.00
4,725,000.00
3,382,000.00
3,034,900.00
10,936,800.00
1,062,500.00
Rp 47,521,856.25

7,553,700.00
3,445,200.00
7,875,000.00
480,000.00
2,625,000.00
395,500.00
Rp 22,374,400.00

5,100,000.00
1,125,000.00
7,755,000.00
590,000.00
1,622,500.00
Rp 16,192,500.00

2,548,000.00
3,500,000.00
2,200,000.00
1,250,000.00
750,000.00
420,000.00
80,000.00
1,625,000.00
Rp 12,373,000.00

5,772,000.00
1,323,000.00
Rp 7,095,000.00

2,470,000.00
1,330,000.00
2,090,000.00
440,000.00
350,000.00
399,000.00
342,000.00
171,000.00
175,000.00

2,200,000.00
3,600,000.00
731,500.00
270,000.00
270,000.00
700,000.00
4,300,000.00
225,000.00
850,000.00
135,000.00
1,250,000.00
155,000.00
Rp 22,453,500.00
Rp 192,337,956.25
Rp 192,337,956.25
Rp 185,000,000.00

Yogyakarta, 06 Desember 2023


Di hitung Oleh
( Windra Wiwid Widyasmoko,S.Ars)