Satuan A Lokasi Depan PT. Polytech Cilegon 1 Pekerjaan Boring Pipa Æ 12 Inch 48 M 1,140,000.00 54,720,000.00 2 Gali Stand Boring 13 M 350,000.00 4,550,000.00 3 Galian Fit Boring 3 Lb 750,000.00 2,250,000.00 Jumlah 61,520,000.00 B Lokasi Depan PT. Polytech Cilegon 1 Pekerjaan Boring Pipa Æ 12 Inch 24 M 1,140,000.00 27,360,000.00 2 Gali Stand Boring 13 M 350,000.00 4,550,000.00 3 Galian Fit Boring 2 Lb 750,000.00 1,500,000.00 Jumlah 33,410,000.00 C Pekerjaan Gali / Open Cut 1 Pekerjaan Galian tanah Keras 120 M 225,000.00 27,000,000.00 2 Galian Beton 15 M 250,000.00 3,750,000.00 Jumlah 30,750,000.00 TOTAL PEKERJAAN (A+B+C) 125,680,000.00