PEKERJAAN PEMATANGAN LAHAN KAWASAN INDUSTRI TERPADU BATANG KLASTER 1 FASE 2 TAHAP 1
WASKITA KARYA
VOLUME PEKERJAAN
NAMA KAV F02 F03 F01 F03a F05 F06 F08 F07
LUAS (HEKTARE ) 17,96 4,96 18,38 4,62 4,89 3,34 3,76 4,98
CUT (M3 ) 328.757,00 166.731,00 187.601,00 145.502,00 132.268,00 210.528,00 9.859,00 2.957,00
FIL (M3 ) 277.154,00 36.789,00 566.352,00 5.229,00 34.092,00 35.773,00 179.909,00 149.050,00
TOTAL CUT ( M3 ) 1.184.203,00
TOTAL FILL (M3 ) 1.284.348,00
TOTAL LUAS LAHAN (HEKTARE ) 62,89
PROYEKSI KEUNTUNGAN
PROGRESS PER 100.000M3 RAB RAP VOLUME (M3) PROFIT (RAB-RAP)* VOL PROSENTASE PROFIT
CUT AND FILL JARAK 0KM - 1KM 24.000,00 16.000,00 1.200.000,00 9.600.000.000,00 33%
CUT AND FILL JARAK 0KM - 2KM 27.000,00 18.000,00 1.200.000,00 10.800.000.000,00 33%
SKRIPPING 18.000,00 13.000,00 18.000,00 90.000.000,00 28%