SUMMARY PEKERJAAN

PEKERJAAN PEMATANGAN LAHAN KAWASAN INDUSTRI TERPADU BATANG KLASTER 1 FASE 2 TAHAP 1

WASKITA KARYA
VOLUME PEKERJAAN
NAMA KAV F02 F03 F01 F03a F05 F06 F08 F07
LUAS (HEKTARE ) 17,96 4,96 18,38 4,62 4,89 3,34 3,76 4,98
CUT (M3 ) 328.757,00 166.731,00 187.601,00 145.502,00 132.268,00 210.528,00 9.859,00 2.957,00
FIL (M3 ) 277.154,00 36.789,00 566.352,00 5.229,00 34.092,00 35.773,00 179.909,00 149.050,00
TOTAL CUT ( M3 ) 1.184.203,00
TOTAL FILL (M3 ) 1.284.348,00
TOTAL LUAS LAHAN (HEKTARE ) 62,89

JANGKA WAKTU PELAKSANAAN 180 ( SERATUS DELAPAN PULUH HARI) KALENDER.


PROGRES PEMBAYARAN TANGGAL 01 SAMPAI DENGAN TANGGAL 20 PROGRESS LAPANGAN DIBAYAR 1 BULAN KEDEPAN. ( MONTHLY PROGRESS )
PEMBAYARAN REGULER KE BANK MANDIRI ( TIDAK DIKENAKAN DISCONTO ATAU SCF )

HITUNGAN KEBUTUHAN MODAL KERJA.


JANGKA WAKTU 180 HARI ( 6 BULAN )
TARGET PROGRESS PER BULAN 200.000M3
MODAL KERJA DENGAN PEMBAYARAN PROGRESS PEKERJAAN DIBAYAR 1 BULAN KEDEPAN ADALAH 400.000M3 ( PER 2 BULAN )
DENGAN RINCIAN :
KETERANGAN HARGA RAP VOLUME JUMLAH MODAL

CUT AND FILL JARAK 0KM - 1KM 16.000,00 400.000,00 6.400.000.000,00


CUT AND FILL JARAK 0KM - 2KM 18.000,00 400.000,00 7.200.000.000,00
SKRIPPING 13.000,00 9.000,00 117.000.000,00
TOTAL MODAL KERJA 13.717.000.000,00

HARGA RENCANA ANGGARAN BIAYA ( RAB )


HARGA CUT AND FILL DENGAN JARAK 0KM SAMPAI DENGAN 1 KM Rp. 24.000 / M3.
HARGA CUT AND FILL DENGAN JARAK 0KM SAMPAI DENGAN 2 KM Rp. 27.000 / M3.
HARGA SKRIPING DAN BUANG KE LOKASI YANG DI TUNJUK SERTA DI HAMPAR DENGAN JARAK MAKSIMUM 2KM Rp. 18.000 / M3
NOTE :
HARGA SUDAH TERMASUK PPh 2%
CUT AND FIL PADAT VIBRO 10 SAMPAI DENGAN 12 TON

HARGA RENCANA ANGGARAN PELAKSANAAN ( RAP )


HARGA CUT AND FILL DENGAN JARAK 0KM SAMPAI DENGAN 1 KM Rp. 16.000 / M3.
HARGA CUT AND FILL DENGAN JARAK 0KM SAMPAI DENGAN 2 KM Rp. 18.000 / M3.
HARGA SKRIPING DAN BUANG KE LOKASI YANG DI TUNJUK SERTA DI HAMPAR DENGAN JARAK MAKSIMUM 2KM Rp. 10.000 / M3
NOTE :
HARGA SUDAH TERMASUK PPh 2%
CUT AND FIL PADAT VIBRO 10 SAMPAI DENGAN 12 TON

PROYEKSI KEUNTUNGAN

PROGRESS PER 100.000M3 RAB RAP VOLUME (M3) PROFIT (RAB-RAP)* VOL PROSENTASE PROFIT
CUT AND FILL JARAK 0KM - 1KM 24.000,00 16.000,00 1.200.000,00 9.600.000.000,00 33%
CUT AND FILL JARAK 0KM - 2KM 27.000,00 18.000,00 1.200.000,00 10.800.000.000,00 33%
SKRIPPING 18.000,00 13.000,00 18.000,00 90.000.000,00 28%

PROFIT ( KEUNTUNGAN ) BELUM TEERMASUK PPH 2%