Anda di halaman 1dari 2

SURAT PERMINTAAN HARGA

Quo ref No. : QUO-RE-2311017-MT Jakarta, Jan 9th 2024


Your Ref no : Email

To : SUKU DINAS SUMBER DAYA AIR


JAKARTA UTARA
Jl. Swasembada Timur XIV No.49, RT.8/RW.10, Kb. Bawang, Kec.
Tj. Priok, Jkt Utara, Daerah Khusus Ibukota Jakarta 14320

Phone :

Attention :

Project : PEKERJAAN PENGGANTIAN PIPA BUANG PLUIT I

Dear Sir,
Thank you for your enquiries, and we are pleased to quote the scope of supply and specification as below :

No ITEM Qty Total Price


1 UMUM 1 lot Rp 70,000,000.00
2 PENGADAAN MATERIAL 1 lot Rp 2,290,000,000.00
3 PERSIAPAN PEKERJAAN 1 lot Rp 50,000,000.00
4 PENGALIHAN DAN PERLINDUNGAN UTILITAS YANG ADA 1 lot Rp 10,000,000.00
5 PEKERJAAN PEMBONGKARAN 1 lot Rp 70,000,000.00
6 PEKERJAAN PEMASANGAN PIPA BUANG 1 lot Rp 204,000,000.00

Grand Total Rp 2,694,000,000.00

TERMS OF PAYMENT
Currency : Price in IDR Excl VAT 11 %
Delivery Point : Site Project
Delivery time : 10 Weeks
Duration Work : 4 Weeks
Validity : 30 Days, start from the date of this quotation
Payment term :

We trust above is one good prophosed quotation and acceptable, and please kindly do not hesitate to contact us
if you require any further information and clarification.
Thanks for your kind attention and coorporation.

Yours faithfully,
PEKERJAAN PENGGANTIAN PIPA BUANG

HARGA SATUAN JUMLAH HARGA


NO. URAIAN SPESIFIKASI SATUAN VOLUME
(Rp.) (Rp.)
1. 2. 3. 4. 5. 6. 7 = (5. X 6.)
1 UMUM
1.a Mobilisasi & Demobilisasi LS 1 Rp 30,000,000.00 Rp 30,000,000.00
1.b Penanganan Lingkungan Hidup LS 1 Rp 20,000,000.00 Rp 20,000,000.00
1.c Manajemen Mutu LS 1 Rp 10,000,000.00 Rp 10,000,000.00
1.d Pembuatan Prosedur dan Instruksi Kerja LS 1 Rp 10,000,000.00 Rp 10,000,000.00

TOTAL HARGA UMUM Rp 70,000,000.00

2 PENGADAAN MATERIAL
2.a Pengadaan Submersible Pump Dia. 1350mm, 10000 m3 UNIT 1 Rp 1,440,000,000.00 Rp 1,440,000,000.00
2.b Pengadaan Column Pipe Carbon SS400, dia.1632mm, thk : 16mm MTR 5 Rp 160,000,000.00 Rp 800,000,000.00
2.c Pengadaan Material Support Pipa as per drawing LS 1 Rp 50,000,000.00 Rp 50,000,000.00

TOTAL HARGA PENGADAAN MATERIAL Rp 2,290,000,000.00

3 PERSIAPAN PEKERJAAN
3.a Mobilisasi Manpower LS 1 Rp 10,000,000.00 Rp 10,000,000.00
3.b Mobilisasi Alat Berat Truck Mobile Crane 10 TON LS 1 Rp 30,000,000.00 Rp 30,000,000.00
3.c Pembersihan Area Kerja LS 1 Rp 10,000,000.00 Rp 10,000,000.00

TOTAL HARGA PENGADAAN MATERIAL Rp 50,000,000.00

4 PENGALIHAN DAN PERLINDUNGAN UTILITAS YANG ADA


4.a Pengalihan dan Perlindungan Utilitas yang Ada LS 1 Rp 10,000,000.00 Rp 10,000,000.00

TOTAL HARGA PERSIAPAN PEKERJAAN Rp 10,000,000.00

5 PEKERJAAN PEMBONGKARAN
5.a Pekerjaan Pembongkaran Existing Elbow Pump Dia. 1350mm UNIT 1 Rp 50,000,000.00 Rp 50,000,000.00
5.b Pekerjaan Pembongkaran Existing Pipa Kolom Carbon SS400, dia.1632mm, thk : 16mm MTR 4 Rp 5,000,000.00 Rp 20,000,000.00

TOTAL HARGA PERSIAPAN PEKERJAAN Rp 70,000,000.00

6 PEKERJAAN PEMASANGAN PIPA BUANG


6.a Pekerjaan Instalasi Support Pipa LS 1
6.b Pekerjaan Pemasangan Elbow Pump Dia. 1350mm UNIT 1 Rp 100,000,000.00 Rp 100,000,000.00
6.c Pekerjaan Pemasangan Pipa Kolom Carbon SS400, dia.1632mm, thk : 16mm MTR 4 Rp 16,000,000.00 Rp 64,000,000.00
6.d Pekerjaan Pengecatan Pipa Kolom M2 8 Rp 5,000,000.00 Rp 40,000,000.00

TOTAL HARGA PENGGANTIAN PIPA BUANG Rp 204,000,000.00