Anda di halaman 1dari 57

PROGRAM : PROGRAM PENINGKATAN EFISIENSI PERDAGANGAN DALAM NEGERI

KEGIATAN : REVITALISASI PASAR TRADISIONAL ( DAK )


PEKERJAAN : REVITALISASI PASAR TRADISIONAL ( DAK )
LOKASI : PASAR 17 AGUSTUS KABUPATEN PAMEKASAN

NO URAIAN PEKERJAAN JUMLAH HARGA

1 PEMBANGUNAN KIOS ( Type - C1 ) 454,970,000.00

2 PEMBANGUNAN KIOS ( Type - C2 ) 404,185,000.00

3 PEMBANGUNAN KIOS ( Type - C3 ) 404,185,000.00

4 PEMBANGUNAN KIOS ( Type - C4 ) 404,185,000.00

5 PEMBANGUNAN KIOS ( Type - C5 ) 404,185,000.00

6 PEMBANGUNAN KIOS ( Type - C6 ) 402,827,000.00

7 PEMBANGUNAN KIOS ( Type - C7 ) 354,659,000.00

8 PEMBANGUNAN SALURAN KELILING 188,182,000.00

9 PEMBANGUNAN KAMAR MANDI (MCK) 186,628,000.00

JUMLAH TOTAL 3,204,006,000.00

Dana : 3,325,000,000

Sisa : 120,994,000
PROGRAM : PROGRAM PENINGKATAN EFISIENSI PERDAGANGAN DALAM NEGERI
KEGIATAN : REVITALISASI PASAR TRADISIONAL ( BK UEP Prov )
PEKERJAAN : REVITALISASI PASAR TRADISIONAL ( BK UEP Prov )
LOKASI : PASAR 17 AGUSTUS KABUPATEN PAMEKASAN

NO URAIAN PEKERJAAN JUMLAH HARGA

1 PEMBANGUNAN KIOS TYPE-A1 367,458,000.00

2 PEMBANGUNAN KIOS TYPE-A2 + PAGAR 228,046,000.00

3 LANJUTAN LOS DAGING 106,286,000.00

4 LANJUTAN KIOS TYPE B1 & B2 96,404,000.00

JUMLAH TOTAL 798,194,000.00

Dana : 800,000,000

Sisa : 1,806,000
RENCANA ANGGARAN BIAYA
Mata Kuliah : Manajemen Konstruksi
Tugas : Pembuatan Gambar & Rencana Anggaran Biaya (RAB)
Pekerjaan : Pembangunan Rumah Tinggal
Lokasi : Pamekasan

HARGA SATUAN JUMLAH HARGA BOBOT


NO URAIAN PEKERJAAN VOL. SAT.
( Rp. ) ( Rp. ) (%)
I PEKERJAAN TANAH DAN PONDASI
1 Galian tanah 95.45 m3 43,125.00 4,116,065.63 2.0
2 Urugan tanah kembali 29.14 m3 14,375.00 418,889.30 0.2
3 Urugan Sirtu dan Pemadatan 20.75 m3 117,470.00 2,437,355.66 1.2
4 Urugan Pasir 8.13 m3 325,650.00 2,647,168.14 1.3
5 Pas. Aanstampeng 18.18 m3 370,929.00 6,743,489.22 3.3
6 Pas. Pondasi Batu Belah 1 : 6 40.00 m3 647,802.00 25,909,488.79 12.8
Jumlah 42,272,456.74 20.9
II PEKERJAAN BETON
1 Sloof 15/20 2.73 m3 3,936,305.00 10,734,303.74 5.3
2 Kolom 15/30 - m3 3,936,305.00 - 0.0
3 Kolom 15/15 1.97 m3 3,936,305.00 7,740,743.78 3.8
4 Plat beton teras dan kanopi 0.90 m3 3,936,305.00 3,542,674.50 1.7
5 Balok 15/20+Gewel 15/20 3.22 m3 3,936,305.00 12,678,346.37 6.3

Jumlah 34,696,068.38 17.1


III PEKERJAAN PLESTERAN DAN PASANGAN
1 Pas. 1/2 bata 1: 3 13.42 m2 98,660.00 1,323,770.55 0.7
2 Pas. 1/2 bata 1: 6 141.49 m2 91,898.00 13,002,877.77 6.4
3 Plesteran 1 : 3 26.84 m2 53,194.00 1,427,460.99 0.7
4 Plesteran 1 : 6 282.99 m2 56,134.00 15,885,079.99 7.8
5 Acian 327.99 m2 23,825.00 7,814,385.58 3.9
6 Benangan 304.88 m' 7,768.00 2,368,272.88 1.2
7 Pas. Batu Alam 5.20 m2 103,500.00 538,200.00 0.3
Jumlah 42,360,047.75 20.9
IV PEKERJAAN LANTAI
1 Pas. Lantai Keramik 30x30 cm 23.05 m2 167,619.00 3,863,408.43 1.9
1 Pas. Keramik Dinding 20x25 cm 2.05 m2 182,431.00 373,071.40 0.2
Jumlah 4,236,479.82 2.1
V PEKERJAAN LISTRIK
1 Instalasi titik lampu 36.00 Ttk 125,000.00 4,500,000.00 2.2
2 Lampu SL 18 watt ( philips ) 15.00 bh 40,250.00 603,750.00 0.3
3 Skakel Tunggal 7.00 bh 28,750.00 201,250.00 0.1
4 Skakel Ganda 4.00 bh 34,500.00 138,000.00 0.1
5 Stop Kontak 9.00 bh 23,000.00 207,000.00 0.1
6 Stop Kontak AC 3.00 bh 23,000.00 69,000.00 0.0
Jumlah 5,719,000.00 2.8
VI PEKERJAAN ATAP DAN KUDA-KUDA
1 Kuda-kuda, Nok, Gording, Ikatan Angin Kayu Gelam 0.60 m3 1,577,000.00 944,307.60 0.5
2 kaso / usuk + reng genting kodok kayu Gelam 62.40 m3 18,625.00 1,162,200.00 0.6
3 Pas. Atap Genteng Kodok 62.40 m2 83,075.00 5,183,880.00 2.6
4 Pas. Genteng Bubung Kodok 10.00 m2 84,374.00 843,740.00 0.4
5 Listplank Kayu Kempas 3/30 15.69 m2 99,375.00 1,559,193.75 0.8
6 Rangka Plafond + Eternit 43.47 m2 172,875.00 7,514,876.25 3.7
7 List. Gypsum Plafond 57.53 m2 22,350.00 1,285,795.50 0.6
Jumlah 18,493,993.10 9.1
VII PEKERJAAN KUSEN DAN PINTU
1 Pas. Kusen Kayu Bengkirai 1.94 m3 13,185,000.00 25,555,747.14 12.6
2 Pas. Daun Pintu Panil Rangkap Kayu Bengkirai 12.20 m2 717,500.00 8,752,065.00 4.3
3 Pas. Daun Jendela Kayu Bengkirai 1.84 m2 560,250.00 1,030,075.65 0.5
4 Pas. Kaca Paten t = 5 mm 0.76 m2 91,156.25 68,950.59 0.0
5 Pas. Engsel Pintu 7.00 Stel 41,256.25 288,793.75 0.1
6 Pas. Engsel Jendela 10.00 Stel 29,337.50 293,375.00 0.1
7 Pas. Grendel Pintu 14.00 Unit 13,225.00 185,150.00 0.1
8 Pas. Grendel Jendela 28.00 Unit 9,890.00 276,920.00 0.1
9 Hak Angin 8.00 Stel 30,006.25 240,050.00 0.1
10 Kunci 2 x putar 6.00 bh 161,675.00 970,050.00 0.5
11 Pintu Vinil (Kamar Mandi) 1.00 bh 250,000.00 250,000.00 0.1
Jumlah 37,911,177.13 18.7
VIII PEKERJAAN PENGECATAN
1 Cat Tembok 327.99 m2 15,023.50 4,927,572.79 2.4
2 Cat Kayu 39.39 m2 31,227.50 1,229,973.53 0.6
3 Cat Plafond 43.47 m2 22,535.25 979,607.32 0.5
Jumlah 7,137,153.64 3.5
IX PEKERJAAN SANITAIR
1 Floor Drain 2.00 bh 25,625.00 51,250.00 0.0
2 Avour 2.00 bh 20,125.00 40,250.00 0.0
3 kran 3/4" atau 1/2" 3.00 bh 48,162.50 144,487.50 0.1
4 Kran Pembuangan 2.00 bh 26,125.00 52,250.00 0.0
5 Wastafel 3.00 bh 525,820.00 1,577,460.00 0.8
6 Pasang Kaca Wastavel 1.00 Ls 150,000.00 150,000.00 0.1
7 Kloset Jongkok 1.00 bh 431,070.00 431,070.00 0.2
8 Pipa PVC Air bersih 3/4" 20.00 m' 18,835.00 376,700.00 0.2
9 Pipa PVC Air Kotor 3" 20.00 m' 60,982.50 1,219,650.00 0.6
10 Septictank + Resapan 1.00 Unit 5,750,000.00 5,750,000.00 2.8
Jumlah 9,793,117.50 4.8
Jumlah Total 202,619,494.06 100.00
REKAPITULASI RENCANA ANGGARAN BIAYA
Mata Kuliah : Manajemen Konstruksi
Tugas : Pembuatan Gambar & Rencana Anggaran Biaya (RAB)
Pekerjaan : Pembangunan Rumah Tinggal
Lokasi : Pamekasan

BOBOT
NO. JENIS PEKERJAAN JUMLAH HARGA
(%)

I PEKERJAAN TANAH DAN PONDASI Rp 42,272,456.74 20.9


II PEKERJAAN BETON Rp 34,696,068.38 17.1
III PEKERJAAN PLESTERAN DAN PASANGAN Rp 42,360,047.75 20.9
IV PEKERJAAN LANTAI Rp 4,236,479.82 2.1
V PEKERJAAN LISTRIK Rp 5,719,000.00 2.8
VI PEKERJAAN ATAP DAN KUDA-KUDA Rp 18,493,993.10 9.1
VII PEKERJAAN KUSEN DAN PINTU Rp 37,911,177.13 18.7
VIII PEKERJAAN PENGECATAN Rp 7,137,153.64 3.5
IX PEKERJAAN SANITAIR Rp 9,793,117.50 4.8

BIAYA FISIK Rp 202,619,494.06 100.00


PPN (10%) Rp 20,261,949.41
TOTAL BIAYA Rp 222,881,443.47
DIBULATKAN Rp 222,881,000.00
TERBILANG # Seratus Dua Puluh Dua Juta Empat Ratus Delapan Puluh Delapan Ribu Rupiah #

Disetujui Direncanakan
Dosen Pengajar Mahasiswa Teknik Sipil
Manajemen Konstruksi Fakultas Teknik
Universitas Madura

DEDY ASMARONI, ST., MT ACHMAD FAISOL


NIM : 11.22201.225
Pasir pasang : 257,000.00 257,000.00
Batu belah uk. 15 - 2 155,000.00 155,000.00
Mata Kuliah : Manajemen Konstruksi
Tugas : Pembuatan Gambar & Rencana Anggaran Biaya (RAB)
Pekerjaan : Pembangunan Rumah Tinggal
Lokasi : Pamekasan

BOBOT
NO URAIAN KEGIATAN
% BULAN KE-1
1

I PEKERJAAN TANAH DAN PONDASI 20.86 10.43

II PEKERJAAN BETON 17.12

III PEKERJAAN PLESTERAN DAN PASANGAN 20.91

IV PEKERJAAN LANTAI 2.09

V PEKERJAAN LISTRIK 2.82

VI PEKERJAAN ATAP DAN KUDA-KUDA 9.13

VII PEKERJAAN KUSEN DAN PINTU 18.71

VIII PEKERJAAN PENGECATAN 3.52

IX PEKERJAAN SANITAIR 4.83

JUMLAH NILAI PEKERJAAN 100.00


PPN 10%
TOTAL
DIBULATKAN
KEMAJUAN BULANAN DALAM % 0 10.43
KOMULATIF KEMAJUAN DALAM % 0 10.43
KEMAJUAN MINGGU INI 0 5.00
DEVIASI -5.43

Disetujui
Dosen Pengajar
Manajemen Konstruksi
DEDY ASMARONI, ST., MT
JADWAL PELAKSANAAN PEKERJAAN

RENCANA PELAKSANAAN
JANGKA WAKTU PELAKSANAAN = 90 HARI KALENDER
BULAN KE-1 BULAN KE-2
2 3 4 5 6 7 8

10.43

5.71 5.71 5.71

6.97 6.97 6.97

1.41

3.04 3.04

9.36

2.42

10.43 5.71 12.68 17.74 15.09 3.04 3.04


20.86 26.57 39.25 56.98 72.08 75.12 78.16
10.00 20.00 40.00 60.00
-10.86 -6.57 0.75 3.02 -72.08

Direncanakan
Mahasiswa Teknik Sipil
Fakultas Teknik
Universitas Madura

ACHMAD FAISOL
NIM : 11.22201.225
AN

CANA PELAKSANAAN
KALENDER MASA PEMELIHARAAN
BULAN KE-3 FISIK 180 hari kalender
9 10 11 12

100

75

2.09

1.41 50

3.04

9.36 25

1.76 1.76

2.42 0

3.04 15.27 1.76 1.76


81.20 96.48 98.24 100.00
MASA PEMELIHARAAN
180 hari kalender

20.86

17.12

20.91

2.09

2.82

9.13

18.71

3.52

4.83

100.00
Back Up Data / Volume Pekerjaan

Mata Kuliah : Manajemen Konstruksi


Tugas : Pembuatan Gambar & Rencana Anggaran Biaya (RAB)
Pekerjaan : Pembangunan Rumah Tinggal
Lokasi : Pamekasan

No. URAIAN PEKERJAAN PERHITUNGAN VOLUME VOL. SAT.


I PEKERJAAN TANAH DAN PONDASI
1 Galian tanah H V
Panjang 95.45 M3
= 12.50 9.8
12.50 5.5
3.50 3.5
2.00 4
3.00 2
9.00 9.8
4.00 9.8
= 46.50 + 44.4 = 90.90

P L T
= 90.90 x 1 x 1.05 = 95.45

2 Urugan tanah kembali Galian tanah = 95.45 29.14 M3

Urugan Pasir = 8.13


Pas. Aanstampeng = 18.18
Pas. Pondasi Batu Belah 1 : 6 = 40.00 = 66.30
= 29.14

3 Urugan Sirtu dan Pemadatan P L T N 20.75 M3

A = 3.35 x 3.35 x 0.3 x 1.0 = 3.37


B = 2.20 x 1.85 x 0.3 x 1.0 = 1.22
C = 2.65 x 1.85 x 0.3 x 1.0 = 1.47
D = 9.50 x 2.5 x 0.3 x 1.0 = 7.13
E = 2.70 x 2.7 x 0.3 x 1.0 = 2.19
F = 2.85 x 2.85 x 0.3 x 1.0 = 2.44
G = 3.70 x 2.65 x 0.3 x 1.0 = 2.94
20.75

4 Urugan Pasir Bawah Lantai


A = 3.35 x 3.35 x 0.05 x 1.0 = 0.56 8.13 M3
B = 2.20 x 1.85 x 0.05 x 1.0 = 0.20
C = 2.65 x 1.85 x 0.05 x 1.0 = 0.25
D = 9.50 x 2.5 x 0.05 x 1.0 = 1.19
E = 3.70 x 2.65 x 0.05 x 1.0 = 0.49
F = 2.85 x 2.85 x 0.05 x 1.0 = 0.41
G = 3.70 x 2.65 x 0.05 x 1.0 = 0.49
-
Bawah Ponds = 90.90 x 1 x 0.05 = 4.55
8.13

5 Pas. Aanstampeng P L T
= 90.90 x 1 x 0.2 = 18.18 18.18 M3

6 Pas. Pondasi Batu Belah 1 : 6 P ATAS BAWAH T


= 90.9 x 0.3 x 0.8 x 0.8 = 40.00 40.00 M3

II PEKERJAAN BETON
1 Sloof 15/20 P L T
= 90.9 x 0.15 x 0.2 = 2.73 2.73 M3

2 Kolom 15/15 P L T N
= 0.15 x 0.15 x 3.8 X 23 = 1.97 1.97 M3
1.97

3 Plat beton teras dan kanopi P L T N


Teras Depan = 4 x 1.5 x 0.1 X 1 = 0.60 0.90 M3
Jendela Depan = 2 x 0.5 x 0.1 X 1 = 0.10
- Jendela Samping = 2 x 0.5 x 0.1 X 2 = 0.20
0.90

4 Balok 15/20+Gewel 15/20 P L T N


Balok = 82.90 x 0.20 x 0.2 = 2.49 3.22 M3
Ring Gewel = 6.00 x 0.15 x 0.2 x 2 = 0.27
Kolom Gewel = 1.45 x 0.15 x 0.2 x 1 = 0.03
5 Balok 15/25 Balok = 11.50 x 0.25 x 0.2 x 1 = 0.43
3.22
III PEKERJAAN PASANGAN
H V
1 Pas. 1/2 bata 1: 3 3.35 3.35 - 13.42 M2
1.35 3.355
1.50 2.2
2.70 2.65 5
2.85 3
3.60 2.85
2.50 2
1.85 2.85
1.00 2.65

20.70 + 24.905 = 45.61

No. URAIAN PEKERJAAN PERHITUNGAN VOLUME VOL. SAT.

= 45.61 x 0.5 = 17.80

Pintu Jendela 1 = 1.61 x 0.5 x 1 = 0.81


Pintu 1 1.61 x 0.5 x 1 = 0.81
Pintu 2 0.95 x 0.5 x 4 = 1.90
Pintu 3 0.95 x 0.5 x 1 = 0.48
Pintu km 0.80 x 0.5 x 1 = 0.40 = 4.39
13.42

2 Pas. 1/2 bata 1: 6 = P x T 141.49 M2

Dinding = 45.61 x 3.5 = 159.62


Gewel = 0.50 x 4 x 1.45 x 2 = 5.80 = 165.42

Pintu Jendela 1 = 1.70 x 1.61 x 1 = 2.74


Pintu 1 = 1.70 x 1.61 x 1 = 2.74
- Pintu 2 = 1.70 x 0.95 x 4 = 6.46
Pintu 3 = 1.70 x 0.95 x 1 = 1.62
Pintu km = 2.00 x 0.80 x 1 = 1.60
Jendela 1 = 1.88 x 1.60 x 2 = 6.02
Jendela 2 = 0.60 x 0.40 x 5 = 1.20
Jendela 3 = 0.60 x 0.40 x 3 = 0.72
Lobang = 0.20 x 0.20 x 21 = 0.84 = 23.93
141.49

3 Plesteran 1 : 3 Pas. 1/2 bata 1: 3 = 13.42 x 2 = 26.835 26.84 M2

4 Plesteran 1 : 6 Pas. 1/2 bata 1: 6 = 141.49 x 2 = 282.985 282.99 M2

5 Acian Plesteran 1 : 3 = 26.84 327.99 M2


Plesteran 1 : 6 = 282.99
kolom = 0.15 x 0.15 x 3.8 x 2.00 = 0.17
Plat kanopi dan teras
Teras Depan = 4.00 x 1.50 x 1 x 2 = 12.00
Jendela Depan = 2.00 x 0.50 x 1 x 2 = 2.00
Jendela Samping = 2.00 x 0.50 x 2 x 2 = 4.00
327.99

6 Benangan Dinding = 30.0 x 4 x = 120.00


kolom = 3.80 x 4 x 2 = 30.40 304.88 M1
Pintu Jendela 1 = 2.05 x 1.61 x 1 = 3.30
Pintu 1 = 1.70 x 1.61 x 2 x 1 = 10.02
Pintu 2 = 1.70 x 0.95 x 2 x 1 = 8.70
Pintu 3 = 1.70 x 0.95 x 1 x 1 = 1.62
Pintu km = 2.00 x 0.8 x 2 x 1 = 22.40
Jendela 1 = 1.88 x 1.6 x 2 x 2 = 27.84
Jendela 2 = 0.60 x 0.4 x 2 x 5 = 20.00
Jendela 3 = 0.60 x 0.40 x 3 x 3 = 27.00
Lobang = 0.20 x 0.2 x 2 x 21 = 33.60
= 304.88

7 Pas. Batu Alam = 1.20 + 4.00 = 5.20 5.20 M2

IV PEKERJAAN LANTAI A = 3.35 x 3.35 x 0.3 x 1.0 = 3.37 23.05 M2


B = 2.20 x 1.85 x 0.3 x 1.0 = 1.22
Pas. Lantai Keramik 30x30 cm C = 2.65 x 1.85 x 0.3 x 1.0 = 1.47
D = 9.50 x 2.5 x 0.3 x 1.0 = 7.13
E = 2.70 x 2.7 x 0.3 x 1.0 = 2.19
F = 2.85 x 2.85 x 0.3 x 1.0 = 2.44
G = 3.70 x 2.65 x 0.3 x 1.0 = 2.94

Injakan = 4.6 x 0.3 = 1.38


Tanjakan = 4.6 x 0.2 = 0.92
23.05

Pas. Keramik Dinding 20x25 cm Bak Mandi = 1.02 x 2 = 2.05 2.05 M2

VI PEKERJAAN ATAP DAN KUDA-KUDA D P N

1 Kuda-kuda, Nok, Gording, Ikatan Angin 0.60 M3


Gording = 0.08 x 0.12 x 8 x 6 = 0.46
Nok = 0.06 x 0.1 x 8 x 2 = 0.10
ikatan angin = 0.06 x 0.1 x 3.5 x 2 = 0.04
0.60
2 Pas. Atap Genteng = 3.90 X 8 X 2 = 62.40 62.40 M2

3 Pas. Genteng Bubung = 10.00 10.00 M2

4 Listplank Kayu Kempas 3/30 Depan/belakang = 11.80 x 0.3 x 2 = 7.08 15.69 M3


samping = 14.35 x 0.3 x 2 = 8.61
15.69

VII PEKERJAAN KUSEN DAN PINTU H V Dimensi N


1 Pas. Kusen Kayu Bengkirai Pintu 1 = 1.81 + 4.4 = 8.02 x 0.07 x 0.14 x 1 = 0.08 1.94 M3
Pintu 2 = 1.81 + 4.4 = 8.02 x 0.07 x 0.14 x 4 = 0.31
Pintu 3 = 1.13 + 4.4 = 6.66 x 0.07 x 0.14 x 1 = 0.07
Pintu jendela 1 = 2.57 + 6.2 = 11.34 x 0.07 x 0.14 x 1 = 0.11
Jendela 1 = 7.42 + 2.22 = 17.06 x 0.07 x 0.14 x 2 = 0.33
Jendela 2 = 3.68 + 4.44 = 16.24 x 0.07 x 0.14 x 5 = 0.80
Jendela 3 = 1.84 + 2.22 = 8.12 x 0.07 x 0.14 x 3 = 0.24
1.94

No. URAIAN PEKERJAAN PERHITUNGAN VOLUME VOL. SAT.

2 Pas. Daun Pintu Panil Rangkap Kayu Bengkirai - 12.20 M3


Pintu 1 = 1.50 x 2.14 x 1 = 3.21
Pintu 2 = 0.85 x 2.14 x 1 = 1.82
Pintu 3 = 0.85 x 2.14 x 1 = 1.82
Pintu Jendela 1 = 2.50 x 2.14 x 1 = 5.35
12.20

3 Pas. Daun Jendela Jendela 1 = 0.48 x 1.48 x 1 = 0.71 1.84 M3


= 1.22 x 0.31 x 1 = 0.38
Jendela 2 = 0.50 x 0.3 x 5 = 0.75
Jendela 3 = 0.50 x 0.3 x 3 = 0.45
1.84

4 Pas. Kaca Paten t = 5 mm Jendela 1 = 1.22 x 0.31 x 2 = 0.76 0.76 M3

5 Pas. Engsel Pintu 6.00 M3

6 Pas. Engsel Jendela Jendela 1 = 2.00 x 2 = 4.00 4.00 M3


Jendela 2 = 4.00 x 5 = 20.00
Jendela 3 = 4.00 x 3 = 12.00
24.00

7 Kunci 2 x putar - = 2.00 2.00 M3

8 Pintu Vinil (Kamar Mandi) #REF! = 1.00 1.00 M3

IV PEKERJAAN PENGECATAN
1 Cat Tembok Acian = 327.99 327.99 M2

2 Cat Kayu Listplank Kayu Kempas 3/30 = 15.69 39.39 M2

Kusen
Pintu 1 = 8.02 x 0.07 x 0.14 x 1 = 0.08
Pintu 2 = 8.02 x 0.07 x 0.14 x 4 = 0.31
Pintu 3 = 6.66 x 0.07 x 0.14 x 1 = 0.07
Jendela 1 = 17.06 x 0.07 x 0.14 x 2 = 0.33
Jendela 2 = 16.24 x 0.07 x 0.14 x 5 = 0.80
Jendela 3 = 8.12 x 0.07 x 0.14 x 3 = 0.24

Daun Pintu
Pintu 1 = 1.50 x 2.14 x 2 x 1 = 6.42
Pintu 2 = 0.85 x 2.14 x 2 x 1 = 3.64
Pintu 3 = 0.85 x 2.14 x 2 x 1 = 3.64
Pintu Jendela 1 = 2.50 x 2.14 x 1 = 5.35

Daun Jendela
Jendela 1 = 0.48 x 1.48 x 0.08 x 2 x 1 = 0.63
= 1.22 x 0.31 x 0.08 x 2 x 2 = 0.98
Jendela 2 = 0.50 x 0.3 x 0.08 x 2 x 3 = 0.77
Jendela 3 = 0.50 x 0.3 x 3 = 0.45
39.39
ANALISA HARGA SATUAN PEKERJAAN
Mata Kuliah : Manajemen Konstruksi
Tugas : Pembuatan Gambar & Rencana Anggaran Biaya (RAB)
Pekerjaan : Pembangunan Rumah Tinggal
Lokasi : Pamekasan

1. Analisa Biaya Kontruksi Pekerjaan Tanah :

1.1 1 m3 Galian tanah biasa sedalam 1 meter


0.7500 Oh Pekerja Rp. 55,000.00 Rp. 41,250.00
0.0250 Oh Mandor Rp. 75,000.00 Rp. 1,875.00
Rp. 43,125.00
1.3 1 m3 Urugan kembali
0.2500 Oh Pekerja Rp. 55,000.00 Rp. 13,750.00
0.0083 Oh Mandor Rp. 75,000.00 Rp. 625.00
Rp. 14,375.00
1.4 1 m3 Urugan Pasir
1.2000 m3 Pasir urug Rp. 257,000.00 Rp. 308,400.00
0.3000 Oh Pekerja Rp. 55,000.00 Rp. 16,500.00
0.0100 Oh Mandor Rp. 75,000.00 Rp. 750.00
Rp. 325,650.00
1.5 1 m3 Pekerjaan urug Sirtu dengan pemadatan
1.2000 m3 Sirtu Rp. 71,850.00 Rp. 86,220.00
0.0500 Oh Mandor Rp. 75,000.00 Rp. 3,750.00
0.5000 Oh Pekerja Rp. 55,000.00 Rp. 27,500.00
Rp. 117,470.00
2. Analisa Biaya Kontruksi Pekerjaan Pondasi :

2.1 1 m3 Pasangan Pondasi batu kali campuran 1 pc : 6 pasir


1.2000 m3 Batu belah uk. 15 - 20 Rp. 155,000.00 Rp. 186,000.00
0.5610 m3 Pasir pasang Rp. 257,000.00 Rp. 144,177.00
117.0000 Kg Semen PC Rp. 1,500.00 Rp. 175,500.00
1.5000 Oh Pekerja Rp. 55,000.00 Rp. 82,500.00
0.7500 Oh Tukang batu Rp. 65,000.00 Rp. 48,750.00
0.0750 Oh Kepala tukang Rp. 70,000.00 Rp. 5,250.00
0.0750 Oh Mandor Rp. 75,000.00 Rp. 5,625.00
Rp. 647,802.00
2.2 1 m3 Pekerjaan Pasang Batu kosong (aanstamping)
1.2000 m3 Batu belah uk. 15 - 20 Rp. 155,000.00 Rp. 186,000.00
0.4320 m3 Pasir urug Rp. 257,000.00 Rp. 111,024.00
0.7800 Oh Pekerja Rp. 55,000.00 Rp. 42,900.00
0.3900 Oh Tukang batu Rp. 65,000.00 Rp. 25,350.00
0.0390 Oh Kepala tukang Rp. 70,000.00 Rp. 2,730.00
0.0390 Oh Mandor Rp. 75,000.00 Rp. 2,925.00
Rp. 370,929.00
3. Analisa Biaya Kontruksi Pekerjaan Dinding :

3.1 1m2 Pasangan bata tebal 1/2 bata merah campuran 1 Pc : 3 Pasir.
70.0000 Bh Bata merah Rp. 600.00 Rp. 42,000.00
0.0400 m3 Pasir pasang Rp. 257,000.00 Rp. 10,280.00
14.3700 Kg Semen PC Rp. 1,500.00 Rp. 21,555.00
0.3000 Oh Pekerja Rp. 55,000.00 Rp. 16,500.00
0.1000 Oh Tukang batu Rp. 65,000.00 Rp. 6,500.00
0.0100 Oh Kepala Tukang Rp. 70,000.00 Rp. 700.00
0.0150 Oh Mandor Rp. 75,000.00 Rp. 1,125.00
Rp. 98,660.00
3.2 1m2 Pasangan bata tebal 1/2 bata merah campuran 1 Pc : 6 Pasir.
70.0000 Bh Bata merah Rp. 600.00 Rp. 42,000.00
0.0490 m3 Pasir pasang Rp. 257,000.00 Rp. 12,593.00
8.3200 Kg Semen PC Rp. 1,500.00 Rp. 12,480.00
0.3000 Oh Pekerja Rp. 55,000.00 Rp. 16,500.00
0.1000 Oh Tukang batu Rp. 65,000.00 Rp. 6,500.00
0.0100 Oh Kepala Tukang Rp. 70,000.00 Rp. 700.00
0.0150 Oh Mandor Rp. 75,000.00 Rp. 1,125.00
0.4250 Rp. 91,898.00
4. Analisa Biaya Kontruksi Pekerjaan Plesteran :

4.1 1m2 Plesteran tebal 20 mm Campuran 1Pc : 3 Pasir


0.0310 m3 Pasir pasang Rp. 257,000.00 Rp. 7,967.00
10.3680 Kg Semen PC Rp. 1,500.00 Rp. 15,552.00
0.2600 Oh Pekerja Rp. 55,000.00 Rp. 14,300.00
0.2000 Oh Tukang batu Rp. 65,000.00 Rp. 13,000.00
0.0200 Oh Kepala Tukang Rp. 70,000.00 Rp. 1,400.00
0.0130 Oh Mandor Rp. 75,000.00 Rp. 975.00
Rp. 53,194.00
4.2 1m2 Plesteran tebal 20 mm Campuran 1Pc : 6 Pasir
0.0360 m3 Pasir pasang Rp. 257,000.00 Rp. 9,252.00
5.8880 Kg Semen PC Rp. 1,500.00 Rp. 8,832.00
0.4000 Oh Pekerja Rp. 55,000.00 Rp. 22,000.00
0.2000 Oh Tukang batu Rp. 65,000.00 Rp. 13,000.00
0.0200 Oh Kepala Tukang Rp. 70,000.00 Rp. 1,400.00
0.0220 Oh Mandor Rp. 75,000.00 Rp. 1,650.00
Rp. 56,134.00
4.3 1 m' Pekerjaan Benangan
0.1600 Kg Semen PC Rp. 1,500.00 Rp. 240.00
0.0090 m3 Pasir pasang Rp. 257,000.00 Rp. 2,313.00
0.0600 Oh Pekerja Rp. 55,000.00 Rp. 3,300.00
0.0030 Oh Tukang batu Rp. 65,000.00 Rp. 195.00
0.0010 Oh Kepala Tukang batu Rp. 70,000.00 Rp. 70.00
0.0220 Oh Mandor Rp. 75,000.00 Rp. 1,650.00
Rp. 7,768.00
4.4 1 m2 Pekerjaan Acian
3.2500 Kg Semen PC Rp. 1,500.00 Rp. 4,875.00
0.2000 Oh Pekerja Rp. 55,000.00 Rp. 11,000.00
0.1000 Oh Tukang batu Rp. 65,000.00 Rp. 6,500.00
0.0100 Oh Kepala Tukang Rp. 70,000.00 Rp. 700.00
0.0100 Oh Mandor Rp. 75,000.00 Rp. 750.00
Rp. 23,825.00

5. Analisa Biaya Kontruksi Pekerjaan Beton :

5.1 1 m3 Membuat Beton bertulang ( 150 kg besi + bekisting )


0.2000 m3 Papan Begisting Rp. 3,500,000.00 Rp. 700,000.00
1.5000 Kg Paku usuk / reng Rp. 20,000.00 Rp. 30,000.00
0.4000 Lt Minyak bekisting Rp. 3,500.00 Rp. 1,400.00
157.5000 Kg Besi beton polos Rp. 10,900.00 Rp. 1,716,750.00
2.2500 Kg Kawat beton Rp. 19,450.00 Rp. 43,762.50
336.0000 Kg Semen Portland / PC Rp. 1,500.00 Rp. 504,000.00
0.5400 m3 Pasir beton Rp. 378,000.00 Rp. 204,120.00
0.8100 m3 Koral beton Rp. 283,250.00 Rp. 229,432.50
5.3000 Oh Pekerja Rp. 55,000.00 Rp. 291,500.00
0.2750 Oh Tukang batu Rp. 65,000.00 Rp. 17,875.00
1.3000 Oh Tukang kayu Rp. 70,000.00 Rp. 91,000.00
1.0500 Oh Tukang besi Rp. 65,000.00 Rp. 68,250.00
0.2620 Oh Kepala Tukang Rp. 70,000.00 Rp. 18,340.00
0.2650 Oh Mandor Rp. 75,000.00 Rp. 19,875.00
Rp. 3,936,305.00
6. Analisa Biaya Kontruksi Pekerjaan Kayu :

6.1 1 M3 Memasang kusen pintu dan jendela kayu Balau


1.2000 m3 Kayu balau Rp. 9,500,000.00 Rp. 11,400,000.00
1.2500 kg Paku 10 cm Rp. 20,000.00 Rp. 25,000.00
1.0000 kg Lem kayu Rp. 12,500.00 Rp. 12,500.00
6.0000 Oh Pekerja Rp. 55,000.00 Rp. 330,000.00
18.0000 Oh Tukang kayu Rp. 70,000.00 Rp. 1,260,000.00
1.8000 Oh Kepala Tukang Rp. 75,000.00 Rp. 135,000.00
0.3000 Oh Mandor Rp. 75,000.00 Rp. 22,500.00
Rp. 13,185,000.00
6.2 1 M2 Memasang daun pintu panil kayu balau
0.0400 m3 Kayu balau ( papan ) Rp. 10,500,000.00 Rp. 420,000.00
0.5000 kg Lem Kayu Rp. 12,500.00 Rp. 6,250.00
1.0000 Oh Pekerja Rp. 55,000.00 Rp. 55,000.00
3.0000 Oh Tukang kayu Rp. 70,000.00 Rp. 210,000.00
0.3000 Oh Kepala Tukang Rp. 75,000.00 Rp. 22,500.00
0.0500 Oh Mandor Rp. 75,000.00 Rp. 3,750.00
Rp. 717,500.00
6.3 1 M2 Memasang daun pintu dan jendela kaca kayu Balau
0.0240 m3 Kayu Balau ( papan ) Rp. 10,500,000.00 Rp. 252,000.00
0.3000 kg Lem Kayu Rp. 12,500.00 Rp. 3,750.00
1.0000 m2 Kaca bening tebal 5 mm Rp. 71,500.00 Rp. 71,500.00
0.8000 Oh Pekerja Rp. 55,000.00 Rp. 44,000.00
2.4000 Oh Tukang kayu Rp. 70,000.00 Rp. 168,000.00
0.2400 Oh Kepala Tukang Rp. 75,000.00 Rp. 18,000.00
0.0400 Oh Mandor Rp. 75,000.00 Rp. 3,000.00
Rp. 560,250.00
6.4 1 M3 Memasang Konstruksi kuda - kuda Kovensional kayu Gelam
1.1000 m3 Kayu Gelam ( Balok ) Rp. 0.00 Rp. 0.00
15.0000 Kg Besi Strip 5 mm Rp. 20,000.00 Rp. 300,000.00
5.6000 Kg Paku 12 cm Rp. 20,000.00 Rp. 112,000.00
4.0000 Oh Pekerja Rp. 55,000.00 Rp. 220,000.00
12.0000 Oh Tukang kayu Rp. 70,000.00 Rp. 840,000.00
1.2000 Oh Kepala Tukang Rp. 75,000.00 Rp. 90,000.00
0.2000 Oh Mandor Rp. 75,000.00 Rp. 15,000.00
Rp. 1,577,000.00
6.5 1 M2 Memasang kaso / usuk + reng genting kodok kayu Gelam
0.0140 m3 Kayu Usuk Gelam 5 x 7 cm Rp. 0.00 Rp. 0.00
0.0036 m3 Kayu Reng Gelam 3 x 4 cm Rp. 0.00 Rp. 0.00
0.2500 Kg Paku biasa uk. 5 - 10 cm Rp. 20,000.00 Rp. 5,000.00
0.1000 Oh Pekerja Rp. 55,000.00 Rp. 5,500.00
0.1000 Oh Tukang kayu Rp. 70,000.00 Rp. 7,000.00
0.0100 Oh Kepala Tukang Rp. 75,000.00 Rp. 750.00
0.0050 Oh Mandor Rp. 75,000.00 Rp. 375.00
Rp. 18,625.00
6.6 1 M2 Memasang rangka plafon (50 x 100) cm kayu kempas
0.0120 m3 Kayu kempas 5 x 7 cm Rp. 6,250,000.00 Rp. 75,000.00
0.1000 Kg Paku biasa uk. 7 - 10 cm Rp. 20,000.00 Rp. 2,000.00
0.1500 Oh Pekerja Rp. 55,000.00 Rp. 8,250.00
0.2500 Oh Tukang kayu Rp. 70,000.00 Rp. 17,500.00
0.0250 Oh Kepala Tukang Rp. 75,000.00 Rp. 1,875.00
0.0750 Oh Mandor Rp. 75,000.00 Rp. 5,625.00
Rp. 110,250.00
6.7 1 M' Memasang lysplank uk. 3 x 30 cm kayu kempas
0.0110 m3 Kayu kempas ( papan ) Rp. 7,000,000.00 Rp. 77,000.00
0.0500 Kg Paku biasa uk. 5 - 7 cm Rp. 20,000.00 Rp. 1,000.00
0.1000 Oh Pekerja Rp. 55,000.00 Rp. 5,500.00
0.2000 Oh Tukang kayu Rp. 70,000.00 Rp. 14,000.00
0.0200 Oh Kepala Tukang Rp. 75,000.00 Rp. 1,500.00
0.0050 Oh Mandor Rp. 75,000.00 Rp. 375.00
Rp. 99,375.00
7. Analisa Biaya Kontruksi Pekerjaan Penutup Atap :

7.1 1 M2 Memasang atap dengan genting kodok


25.0000 Bh Genting kodok Rp. 2,750.00 Rp. 68,750.00
0.1500 Oh Pekerja Rp. 55,000.00 Rp. 8,250.00
0.0750 Oh Tukang batu Rp. 65,000.00 Rp. 4,875.00
0.0080 Oh Kepala Tukang Rp. 75,000.00 Rp. 600.00
0.0080 Oh Mandor Rp. 75,000.00 Rp. 600.00
Rp. 83,075.00
7.2 1 M' Memasang bubung genting kodok / flam :
5.0000 Bh Genting bubung Rp. 5,500.00 Rp. 27,500.00
8.0000 Kg Semen Portland / PC Rp. 1,500.00 Rp. 12,000.00
0.0320 m3 Pasir pasang Rp. 257,000.00 Rp. 8,224.00
0.4000 Oh Pekerja Rp. 55,000.00 Rp. 22,000.00
0.2000 Oh Tukang batu Rp. 65,000.00 Rp. 13,000.00
0.0200 Oh Kepala Tukang Rp. 75,000.00 Rp. 1,500.00
0.0020 Oh Mandor Rp. 75,000.00 Rp. 150.00
Rp. 84,374.00
8. Analisa Biaya Kontruksi Pekerjaan Langit-langit :

8.1 1 M2 Memasang langit - langit Gypsum


1.1000 lbr Gypsum Rp. 50,000.00 Rp. 55,000.00
0.0100 Kg Paku eternit Rp. 25,000.00 Rp. 250.00
0.0300 Oh Pekerja Rp. 55,000.00 Rp. 1,650.00
0.0700 Oh Tukang kayu Rp. 70,000.00 Rp. 4,900.00
0.0070 Oh Kepala Tukang Rp. 75,000.00 Rp. 525.00
0.0040 Oh Mandor Rp. 75,000.00 Rp. 300.00
Rp. 62,625.00
8.2 1 M' Memasang lyst plafon gypsum profil
1.0500 m' List gypsum profil Rp. 12,500.00 Rp. 13,125.00
0.1500 Kg Semen putih Rp. 7,000.00 Rp. 1,050.00
0.0600 Oh Pekerja Rp. 55,000.00 Rp. 3,300.00
0.0600 Oh Tukang kayu Rp. 70,000.00 Rp. 4,200.00
0.0060 Oh Kepala Tukang Rp. 75,000.00 Rp. 450.00
0.0030 Oh Mandor Rp. 75,000.00 Rp. 225.00
Rp. 22,350.00
9. Analisa Biaya Kontruksi Pekerjaan Kunci dan Kaca :

9.1 1 Buah Memasang Kunci tanam biasa :


1.0000 Bh Kunci tanam Rp. 125,000.00 Rp. 125,000.00
0.0100 Oh Pekerja Rp. 55,000.00 Rp. 550.00
0.5000 Oh Tukang kayu Rp. 70,000.00 Rp. 35,000.00
0.0100 Oh Kepala Tukang Rp. 75,000.00 Rp. 750.00
0.0050 Oh Mandor Rp. 75,000.00 Rp. 375.00
Rp. 161,675.00
9.2 1 Stel Memasang engsel pintu :
1.0000 Stel Engsel pintu Rp. 28,750.00 Rp. 28,750.00
0.0150 Oh Pekerja Rp. 55,000.00 Rp. 825.00
0.1500 Oh Tukang kayu Rp. 70,000.00 Rp. 10,500.00
0.0150 Oh Kepala Tukang Rp. 75,000.00 Rp. 1,125.00
0.0008 Oh Mandor Rp. 75,000.00 Rp. 56.25
Rp. 41,256.25
9.3 1 Stel Memasang engsel jendela :
1.0000 Stel Engsel jendela Rp. 21,000.00 Rp. 21,000.00
0.0100 Oh Pekerja Rp. 55,000.00 Rp. 550.00
0.1000 Oh Tukang kayu Rp. 70,000.00 Rp. 7,000.00
0.0100 Oh Kepala Tukang Rp. 75,000.00 Rp. 750.00
0.0005 Oh Mandor Rp. 75,000.00 Rp. 37.50
Rp. 29,337.50
9.4 1 Stel Memasang hak angin :
1.0000 Stel Hak angin Rp. 17,500.00 Rp. 17,500.00
0.0150 Oh Pekerja Rp. 55,000.00 Rp. 825.00
0.1500 Oh Tukang kayu Rp. 70,000.00 Rp. 10,500.00
0.0150 Oh Kepala Tukang Rp. 75,000.00 Rp. 1,125.00
0.0008 Oh Mandor Rp. 75,000.00 Rp. 56.25
Rp. 30,006.25
9.5 1 M2 Memasang kaca bening tebal 5 mm
1.1000 m2 Kaca tebal bening 5 mm Rp. 71,500.00 Rp. 78,650.00
0.0150 Oh Pekerja Rp. 55,000.00 Rp. 825.00
0.1500 Oh Tukang kayu Rp. 70,000.00 Rp. 10,500.00
0.0150 Oh Kepala Tukang Rp. 75,000.00 Rp. 1,125.00
0.00075 Oh Mandor Rp. 75,000.00 Rp. 56.25
Rp. 91,156.25
10. Analisa Biaya Kontruksi Pekerjaan Penutup Lantai dan Dinding :

10.1 1 M2 Memasang Lantai keramik ukuran 30 x 30 cm


1.0000 m2 Tegel keramik uk. 30 x 30 cm Rp. 65,000.00 Rp. 65,000.00
10.0000 Kg Semen Portland / PC Rp. 1,500.00 Rp. 15,000.00
1.5000 Kg Semen warna Rp. 7,000.00 Rp. 10,500.00
0.0420 m3 Pasir pasang Rp. 257,000.00 Rp. 10,794.00
0.7000 Oh Pekerja Rp. 55,000.00 Rp. 38,500.00
0.3500 Oh Tukang batu Rp. 65,000.00 Rp. 22,750.00
0.0350 Oh Kepala Tukang Rp. 70,000.00 Rp. 2,450.00
0.0350 Oh Mandor Rp. 75,000.00 Rp. 2,625.00
Rp. 167,619.00
10.2 1 M2 Memasang dinding keramik ukuran 20 x 25 cm
1.0000 Bh Tegel keramik uk. 20 x 25 cm Rp. 65,000.00 Rp. 65,000.00
9.3000 Kg Semen Portland / PC Rp. 1,500.00 Rp. 13,950.00
1.9400 Kg Semen warna Rp. 7,000.00 Rp. 13,580.00
0.0180 m3 Pasir pasang Rp. 257,000.00 Rp. 4,626.00
0.9000 Oh Pekerja Rp. 55,000.00 Rp. 49,500.00
0.4500 Oh Tukang batu Rp. 65,000.00 Rp. 29,250.00
0.0450 Oh Kepala Tukang Rp. 70,000.00 Rp. 3,150.00
0.0450 Oh Mandor Rp. 75,000.00 Rp. 3,375.00
Rp. 182,431.00

11. Analisa Biaya Kontruksi Pekerjaan Penutup Lantai dan Dinding :

11.1 1 buah Memasang kloset jongkok porselen


1.0000 bh kloset jongkok porselen Rp. 150,000.00 Rp. 150,000.00
6.0000 kg Semen Protland Rp. 1,500.00 Rp. 9,000.00
0.0100 m3 Pasir Pasang Rp. 257,000.00 Rp. 2,570.00
1.0000 Oh Pekerja Rp. 55,000.00 Rp. 55,000.00
1.5000 Oh Tukang Batu Rp. 65,000.00 Rp. 97,500.00
1.5000 Oh Kepala Tukang Rp. 70,000.00 Rp. 105,000.00
0.1600 Oh Mandor Rp. 75,000.00 Rp. 12,000.00
Rp. 431,070.00
11.2 1 buah Memasang wastafel
1.0000 bh Wastafel Rp. 300,000.00 Rp. 300,000.00
12% Harga wastafel
Perlengkapan Rp. 36,000.00 Rp. 36,000.00
6.0000 kg Semen Protland Rp. 1,500.00 Rp. 9,000.00
0.0100 m3 Pasir Pasang Rp. 257,000.00 Rp. 2,570.00
1.2000 Oh Pekerja Rp. 55,000.00 Rp. 66,000.00
1.4500 Oh Tukang Batu Rp. 65,000.00 Rp. 94,250.00
0.1500 Oh Kepala Tukang Rp. 70,000.00 Rp. 10,500.00
0.1000 Oh Mandor Rp. 75,000.00 Rp. 7,500.00
Rp. 525,820.00
11.3 1 buah Memasang Kran Pembuangan
1.0000 bh Kran Pembuangan Rp. 18,000.00 Rp. 18,000.00
0.0100 Oh Pekerja Rp. 55,000.00 Rp. 550.00
0.1000 Oh Tukang Batu Rp. 65,000.00 Rp. 6,500.00
0.0100 Oh Kepala Tukang Rp. 70,000.00 Rp. 700.00
0.0050 Oh Mandor Rp. 75,000.00 Rp. 375.00
Rp. 26,125.00
11.4 1 buah Memasang kran 3/4" atau 1/2"
1.0000 bh Kran air Rp. 40,000.00 Rp. 40,000.00
0.0250 bh Seal tape Rp. 1,500.00 Rp. 37.50
0.0100 Oh Pekerja Rp. 55,000.00 Rp. 550.00
0.1000 Oh Tukang Batu Rp. 65,000.00 Rp. 6,500.00
0.0100 Oh Kepala Tukang Rp. 70,000.00 Rp. 700.00
0.0050 Oh Mandor Rp. 75,000.00 Rp. 375.00
Rp. 48,162.50
11.5 1 buah Memasang Floor drain
1.0000 bh Floor drain Rp. 17,500.00 Rp. 17,500.00
0.0100 Oh Pekerja Rp. 55,000.00 Rp. 550.00
0.1000 Oh Tukang Batu Rp. 65,000.00 Rp. 6,500.00
0.0100 Oh Kepala Tukang Rp. 70,000.00 Rp. 700.00
0.0050 Oh Mandor Rp. 75,000.00 Rp. 375.00
Rp. 25,625.00
11.6 1 m Memasang pipa PVC diameter 3/4"
1.2000 m' Pipa PVC Rp. 8,000.00 Rp. 9,600.00
35% harga pipa
Perlengkapan Rp. 2,800.00 Rp. 2,800.00
0.0360 Oh Pekerja Rp. 55,000.00 Rp. 1,980.00
0.0600 Oh Tukang Batu Rp. 65,000.00 Rp. 3,900.00
0.0060 Oh Kepala Tukang Rp. 70,000.00 Rp. 420.00
0.0018 Oh Mandor Rp. 75,000.00 Rp. 135.00
Rp. 18,835.00
11.7 1 m Memasang pipa PVC diameter 3"
1.2000 m' Pipa PVC Rp. 30,000.00 Rp. 36,000.00
35% harga pipa
Perlengkapan Rp. 10,500.00 Rp. 10,500.00
0.0810 Oh Pekerja Rp. 55,000.00 Rp. 4,455.00
0.1350 Oh Tukang Batu Rp. 65,000.00 Rp. 8,775.00
0.0135 Oh Kepala Tukang Rp. 70,000.00 Rp. 945.00
0.0041 Oh Mandor Rp. 75,000.00 Rp. 307.50
Rp. 60,982.50
12. Analisa Biaya Kontruksi Pekerjaan Pengecatan :

12.1 1 M2 Pengecatan bidang kayu baru ( 1 lapis plamir, 1 lapis cat dasar & 2 lapis cat penutup )
0.2000 Kg Cat mini Rp. 23,000.00 Rp. 4,600.00
0.1500 Kg Plamir Rp. 22,500.00 Rp. 3,375.00
0.1700 Kg Cat dasar Rp. 23,000.00 Rp. 3,910.00
0.2600 Kg Cat penutup 2 kali Rp. 55,000.00 Rp. 14,300.00
0.0700 Oh Pekerja Rp. 55,000.00 Rp. 3,850.00
0.0090 Oh Tukang cat Rp. 65,000.00 Rp. 585.00
0.0060 Oh Kepala Tukang Rp. 70,000.00 Rp. 420.00
0.0025 Oh Mandor Rp. 75,000.00 Rp. 187.50
Rp. 31,227.50
12.2 1 M2 Pengecatan tembok baru ( 1 lapis plamir, 1 lapis cat dasar & 2 lapis cat penutup )
0.1000 Kg Plamir tembok Rp. 20,000.00 Rp. 2,000.00
0.1000 Kg Cat dasar Rp. 20,000.00 Rp. 2,000.00
0.2600 Kg Cat penutup 2 x Rp. 20,000.00 Rp. 5,200.00
0.0200 Oh Pekerja Rp. 55,000.00 Rp. 1,100.00
0.0630 Oh Tukang cat Rp. 65,000.00 Rp. 4,095.00
0.0063 Oh Kepala Tukang Rp. 70,000.00 Rp. 441.00
0.0025 Oh Mandor Rp. 75,000.00 Rp. 187.50
Rp. 15,023.50
Untuk Pengecatan plafon baru : 1,50 x 15,023.50 = 22,535.25

Pamekasan, 2014

Disetujui Direncanakan
Dosen Pengajar Mahasiswa Teknik Sipil
Manajemen Konstruksi Fakultas Teknik
Universitas Madura

DEDY ASMARONI, ST., MT ACHMAD FAISOL


NIM : 11.22201.225
DAFTAR HARGA SATUAN BAHAN
Mata Kuliah : Manajemen Konstruksi
Tugas : Pembuatan Gambar & Rencana Anggaran Biaya (RAB)
Pekerjaan : Pembangunan Rumah Tinggal
Lokasi : Pamekasan

NO BAHAN / MATERIAL SATUAN HARGA SATUAN KETERANGAN

1 Batu Gunung M³ 155,000.00


2 Krikil 5/7 M³ 165,000.00
3 Krikil 3/5 M³ 189,000.00
4 Krikil 2/3 M³ 283,250.00
5 Krikil 1/2 M³ 309,000.00
6 Krikil 0,5 / 1 ( Split Lokal ) M³ 334,750.00
7 Krikil 1/2 ( Split Jawa ) M³ 513,000.00
8 Krikil 0,5 / 1 ( Split jawa ) M³ 517,500.00
9 Pasir Urug M³ 225,000.00
10 Pasir Pasang Lokal M³ 257,000.00
11 Pasir Pasang Jawa M³ 350,000.00
12 Pasir Beton Jawa M³ 378,000.00
13 Tanah Urug Biasa M³ 71,250.00
14 Sirtu M³ 71,850.00
15 Batu Alam M² 90,000.00
16 Batu Bata Putih Buah 550.00
17 Batu Bata Merah Buah 600.00
18 Roster / terawang Buah 8,000.00
19 Genteng Pres Buah 2,750.00
20 Genting Biasa/Flam Buah 1,700.00
21 Genteng Beton Buah 5,000.00
22 Genteng Bubung Pres / Biasa Buah 5,500.00
23 Genteng Bubung Beton Buah 6,500.00
24 Portland Cement(PC) kg 1,500.00
25 Minyak pelumas ltr 40,000.00
26 Minyak Bekisting/Oli Bekas ltr 3,500.00
27 Filler Kg 1,800.00
28 Cat besi/Kayu kg 55,000.00
29 Cat Tembok kg 20,000.00
30 Cat Meni kg 23,000.00
31 Minyak Cat liter 20,000.00
32 Multiplek tebal 9 mm lbr 110,000.00
33 Multiplek tebal 12 mm lbr 150,000.00
34 Multiplek tebal 15 mm lbr 182,000.00
35 Multiplek tebal 18 mm lbr 195,000.00
36 PlamirTembok kg 20,000.00
37 Plamir Kayu kg 22,500.00
38 Paku Usuk/reng kg 20,000.00
39 Paku Seng kg 26,500.00
40 Paku Eternit kg 25,000.00
41 Paku Ulir kg 5,000.00
42 Paku Sumbat bh 950.00
43 Paku Kait bh 4,800.00
44 Besi Beton Polos U 24 kg 10,900.00
45 Besi Beton Polos U 40 kg 12,500.00
46 Besi Beton Ulir U 32 kg 11,850.00
47 Bidraat kg 19,450.00
48 Besi Profil, Bangel, baut & mur kg 20,000.00
49 Besi profil WF / Besi Strip kg 17,000.00
50 Plat besi penyanggah bh 11,500.00
51 Tegel Galar M² 52,000.00
52 Keramik Kw.1 30 x 30 M² 65,000.00
53 Tegel Abu-Abu M² 32,500.00
NO BAHAN / MATERIAL SATUAN HARGA SATUAN KETERANGAN

54 Tegel Warna M² 42,000.00


55 Plin Tegel Abu-Abu Uk.15x20 M¹ 6,000.00
56 Kayu jati Kangian/Jawa Balok M³ 16,000,000.00
57 Kayu jati Kangian/Jawa Papan M³ 17,500,000.00
58 Kayu Kamper M³ 12,000,000.00
59 Papan Kamper M³ 13,000,000.00
60 Kayu Balau / Bengkirai M³ 9,500,000.00
61 Papan Balau / Bengkirai M³ 10,500,000.00
62 Kayu Kempas M³ 6,250,000.00
63 Papan Kempas M³ 7,000,000.00
64 Kayu Meranti M³ 4,500,000.00
65 Papan Meranti M³ 5,000,000.00
66 Kayu Gelam M³ 4,000,000.00
67 Papan Bekisting M³ 3,500,000.00
68 Kayu lis plafond M¹ 9,000.00
69 Bouwplank M¹ 22,000.00
70 Papan Riuter M¹ 30,000.00
71 Beton Sigar ø 20 Bh/m 35,000.00
72 Beton Sigar ø 30 Bh/m 40,000.00
73 Buis beton ø 20 Bh/m 50,000.00
74 Buis beton ø 40 Bh 77,500.00
75 Pipa PVC ø 1/2" M¹ 7,000.00
76 Pipa PVC ø 3/4" M¹ 8,000.00
77 Pipa PVC ø 1" M¹ 10,500.00
78 Pipa PVC ø 2" M¹ 18,500.00
79 Pipa PVC ø 3" M¹ 30,000.00
80 Pipa PVC ø 4" M¹ 31,000.00
81 Pipa PVC ø 6" M¹ 71,500.00
82 Knei L ø 3" PVC bh 11,000.00
83 Knei L ø 6" PVC bh 25,000.00
84 Pipa GI ø 2" M¹ 90,000.00
85 Pipa GI ø 3" M¹ 132,000.00
86 Pipa GI ø 4" M¹ 181,500.00
87 Pipa GI ø 6" M¹ 242,000.00
88 Seng Plat BJLS 28 M¹ 55,000.00
89 Eternit / Asbes datar M² 24,750.00
90 Calciboard 5mm M² 30,000.00
91 Gypson M² 50,000.00
92 Kaca Bening 5 mm M² 71,500.00
93 Kaca Raiben 5 mm M² 85,000.00
94 Kunci pintu tanam 2 x putar bh 125,000.00
95 Kunci dan pegangan meja stel 17,500.00
96 Engsel pintu stel 28,750.00
97 Engsel Jendela stel 21,000.00
98 Engsel H bh 10,000.00
99 Grendel pintu bh 11,500.00
100 Grendel tanam pintu stel 51,000.00
101 Hak angin stel 17,500.00
102 Grendel jendela bh 8,600.00
103 Kran air bh 40,000.00
104 Avour bh 17,500.00
105 Kran Pembuang bh 18,000.00
106 Lampu TL duble titik 140,000.00
NO BAHAN / MATERIAL SATUAN HARGA SATUAN KETERANGAN

107 Lampu TL Tunggal titik 90,000.00


108 Closed jongkok bh 150,000.00
109 Instalasi Titik Listrik bh 125,000.00
110 Lampu Pijar bh 35,000.00
111 Stop Kontak bh 20,000.00
112 Skakel Engkel bh 25,000.00
113 Skakel Ganda bh 30,000.00
114 Sekring bh 17,500.00
115 Pompa Air bh 1,500,000.00
116 Saptiktank unit 5,000,000.00
117 Glass Box bh 35,000.00
118 Wastavel Kecil bh 275,000.00
119 Wastavel Besar bh 300,000.00
120 - Kran Air 3/4" bh 30,250.00
121 Pintu Vinil (Kamar Mandi) bh 250,000.00
122 Kaca Wastavel bh 150,000.00

Pamekasan,

Disetujui Direncanaka
Dosen Pengajar Mahasiswa Te
Manajemen Konstruksi Fakultas Teknik
Universitas Madura

DEDY ASMARONI, ST., MT ACHMAD FA


NIM : 11.222
DAFTAR HARGA SATUAN UPAH
Mata Kuliah : Manajemen Konstruksi
Tugas : Pembuatan Gambar & Rencana Anggaran Biaya (RAB)
Pekerjaan : Pembangunan Rumah Tinggal
Lokasi : Pamekasan

NO JENIS PEKERJA SATUAN HARGA SATUAN KETERANGAN

1 Mandor lapangan Org/Hr 75,000.00

2 Kepala Tukang Kayu Org/Hr 75,000.00


Kepala Tukang Batu Org/Hr 70,000.00
Kepala Tukang Besi Org/Hr 70,000.00
Kepala Tukang Cat Org/Hr 70,000.00

3 Tukang Kayu Org/Hr 70,000.00


Tukang Batu Org/Hr 65,000.00
Tukang Seng Org/Hr 65,000.00
Tukang Cat Org/Hr 65,000.00
Tukang Besi Org/Hr 65,000.00

4 Buruh Terampil/Pemb. Tukang Org/Hr 57,500.00

5 Buruh Tak Terampil/Pekerja Org/Hr 55,000.00

6 Penjaga Org/Hr 47,500.00

Pamekasan,

Disetujui Direncanaka
Dosen Pengajar Mahasiswa Te
Manajemen Konstruksi Fakultas Teknik
Provinsi Jawa Timur Universitas Madura

DEDY ASMARONI, ST., MT ACHMAD FA


NIM : 11.222
RENCANA ANGGARAN BIAYA (RAB)
PROGRAM : PROGRAM PENINGKATAN EFISIENSI PERDAGANGAN DALAM NEGERI
KEGIATAN : REVITALISASI PASAR TRADISIONAL ( DAK )
PEKERJAAN : PEMBANGUNAN SALURAN KELILING
LOKASI : PASAR 17 AGUSTUS KABUPATEN PAMEKASAN

HARGA SAT. JUML. HARGA


NO URAIAN PEKERJAAN VOLUME
( Rp. ) ( Rp. )

I PEKERJAAN PEMBONGKARAN DAN PEMBERSIHAN


1 Pembongkaran dan Pembersihan 1.00 Ls 1,000,000.00 1,000,000.00
2 Pengukuran Uitset 1.00 Ls 500,000.00 500,000.00
Jumlah I 1,500,000.00
II PEKERJAAN SALURAN
1 Galian Tanah 180.84 m3 43,125.00 7,798,789.69
2 Urugan Pasir 7.75 m3 325,650.00 2,523,901.48
3 Pasangan Batu Kali 1 : 4 90.56 m3 706,265.00 63,961,477.20
4 Plesteran 1 Pc : 5 Ps 479.89 m3 57,413.00 27,551,637.51
5 Plat Beton t = 8 cm 13.81 m3 3,936,305.00 54,347,775.87
6 Plat Beton t = 12 cm 3.40 m3 3,936,305.00 13,391,309.61
Jumlah II 169,574,891.35

Jumlah Total Harga 171,074,891.35


REKAPITULASI RENCANA ANGGARAN BIAYA
PROGRAM : PROGRAM PENINGKATAN EFISIENSI PERDAGANGAN DALAM NEGERI
KEGIATAN : REVITALISASI PASAR TRADISIONAL ( DAK )
PEKERJAAN : PEMBANGUNAN SALURAN KELILING
LOKASI : PASAR 17 AGUSTUS KABUPATEN PAMEKASAN

NO URAIAN PEKERJAAN JUMLAH HARGA

I PEKERJAAN PEMBONGKARAN DAN PEMBERSIHAN 1,500,000.00

II PEKERJAAN SALURAN 169,574,891.35

Total Harga 171,074,891.35


PPN ( 10 % ) 17,107,489.13
JUMLAH + PPN 188,182,380.48
DIBULATKAN 188,182,000.00

TERBILANG : # Seratus Enam Puluh Enam Juta Sembilan Ratus Dua Puluh Dua Ribu Rupiah #

Pamekasan, Mei 2013

Disetujui Direncanakan
Pejabat Pembuat Komitmen CV. KHARISMA CIPTA INDAH
Program Peningkatan Efisiensi Perdagangan
Dalam Negeri

HERMAN HIDAYAT S, ST. MAKSON, ST


NIP. 196807121992021002 Direktur

Mengetahui Disetujui
Kepala Dinas Perindustrian & Perdagangan Kuasa Pengguna Anggaran
Kabupaten Pamekasan Dinas Perindustrian & Perdagangan
Kabupaten Pamekasan

BAMBANG EDY SUPRAPTO, SH. MM. Drs. SLAMET RIADY


NIP. 196209151994011001 NIP. 19590909 198803 1 005

Mengetahui
Kepala Dinas Pekerjaan Umum
Kabupaten Pamekasan

Ir. TOTOK HARTONO


NIP. 196309131990031011
Back Up DATA

PROGRAM : PROGRAM PENINGKATAN EFISIENSI PERDAGANGAN DALAM NEGERI


KEGIATAN : REVITALISASI PASAR TRADISIONAL ( BK UEP Prov )
PEKERJAAN : PEMBANGUNAN LOS DAGING
LOKASI : PASAR 17 AGUSTUS KABUPATEN PAMEKASAN
TAHUN ANGG. : 2012

LOS DAGING

No. URAIAN PEKERJAAN PERHITUNGAN VOLUME VOLUME SAT.

A PEKERJAAN PLAFOND
1 Plafond Rangka Metal Furing + Eternit P L N 399.47 M2
A = 2.85 x 1.85 x 20 = 105.45
B = 9.85 x 29.85 x 1 = 294.023
399.5

2 List Gypsum Plafond P L N 267.40 M1


A = 2.85 + 1.85 x 2 x 20 = 188
B = 9.85 + 29.85 x 2 x 1 = 79.4
267.4

B PEKERJAAN ELEKTRIKAL

1 Instalasi Listrik 50.00 Titik

2 Lampu SL 18 watt ( philips ) 20.00 bh

3 Lampu TL 2x 20 watt 20.00 bh

4 Stop kontak 10.00 bh

5 Saklar Tunggal 4.00 bh

6 Saklar Ganda 2.00 bh

LANJUTAN KIOS B-1

No. URAIAN PEKERJAAN PERHITUNGAN VOLUME VOLUME SAT.

A PEKERJAAN PASANGAN
1 Pas. Rolling Door L T N
= 2.15 X 2.3 X 9 = 44.50 44.50 M2

B PEKERJAAN PLAFOND
1 Pas. Rangka Plafon + Eternit ky. Kempas P L N
= 2.85 x 2.6 x 18 = 133.38 133.38 M2

List Plafond A = 2.85 + 2.6 x 2 x 18 = 196.2 196.20 M1

C PEKERJAAN INSTALASI LISTRIK

4 Lampu TL 2x 20 watt 18.00 BH

VIII PEKERJAAN CAT - CATAN


1 Pengecatan Plafond Pas. Rangka Plafon + Eterni = 133.38 133.38 M2

LANJUTAN KIOS B-2

No. URAIAN PEKERJAAN PERHITUNGAN VOLUME VOLUME SAT.

A PEKERJAAN PASANGAN
1 Pas. Rolling Door L T N
= 2.15 X 2.3 X 9 = 44.50 44.50 M2
2 Urugan Tanah Kembali Galian 399.5 #REF! M3

Urugan Pasir 24.52


Lantai Kerja t= 5 cm 2.20
Foot Plat 100 x 100 cm 4.40
Kolom 20 /30 = 0.3 x 0.2 x 1.3 x 22 = 1.72
Pas . Anstampeng 10.55
Pas . Batu Belah 1 : 4 (Pondasi) 40.60
Saluran #REF! #REF!
#REF!

3 Urugan Sirtu Dengan Pemadatannya P L T N 171.16 M3


A = 2.85 x 1.85 x 0.4 x 34 = 71.71
B = 2.85 x 9.85 x 0.4 x 2 = 22.46
C = 24.15 x 2.85 x 0.4 x 2 = 55.06
D = 2.85 x 4.15 x 0.4 x 1 = 4.73
1 = 0.85 x 8 x 0.4 x 2 = 5.44
2 = 0.7 x 11.85 x 0.4 x 2 = 6.64
3 = 0.85 x 2.85 x 0.4 x 1 = 0.97
4 = 0.7 x 14.85 x 0.4 x 1 = 4.16
171.16

4 Urugan Pasir P L T
Batu kali = 105.45 x 1 x 0.05 = 5.27 24.52 M3
Dalam
A = 2.85 x 1.85 x 0.05 x 34 = 8.96
B = 2.85 x 9.85 x 0.05 x 2 = 2.81
C = 24.15 x 2.85 x 0.05 x 2 = 6.88
D = 2.85 x 4.15 x 0.05 x 1 = 0.59
24.52

5 Pas . Anstampeng P L T
= 105.45 x 1 x 0.1 = 10.55 10.55 M3

6 Pas . Batu Belah 1 : 4 (Pondasi) LA + LB / 2 X T X P

Pondasi = 0.3 x 0.8 / 2 x 0.7 X 105.45 = 40.60 40.60 M3

Saluran Saluran Panjang = #REF! #REF! M3

= #REF! x 1.1 x 0.2 = #REF!

7 Lantai Kerja t= 5 cm P x L x T x N

= 1 x 1 / 0.1 x 22 = 2.20 2.20 M3

III PEKERJAAN BETON


1 Foot Plat 100 x 100 cm P L T N
= 1 x 1 x 0.2 x 22 = 4.40 4.40 M3

2 Sloof 15 /20 P L T
= 105.45 x 0.15 x 0.2 = 3.16 3.16 M3
No. URAIAN PEKERJAAN PERHITUNGAN VOLUME VOLUME SAT.

3 Kolom 15 /15 P L T N
dinding = 0.15 x 0.15 x 4.7 X 30 = 3.17 4.06 M3
= 0.15 x 0.15 x 6 X 4 = 0.54
Tengah = 0.15 x 0.15 x 1.7 X 9 = 0.34
4.06

4 Kolom 15 /20 P L T N
= 0.15 x 0.2 x 2.6 X 18 = 1.40 1.40 M3

5 Kolom 20 /30 P L T N
= 0.2 x 0.3 x 7.1 X 22 = 9.37 9.37 M3

6 Balok Latai 15/20 P L T


Tembok = 88 x 0.2 x 0.15 = 2.64 3.46 M3
Teras = 9.4 x 0.2 x 0.15 = 0.28
atas pintu = 18 x 0.2 x 0.15 = 0.54
3.46

7 Ring Balk 15/20 P L T


Tembok = 148 x 0.2 x 0.15 = 4.44 5.08 M3
Tengah = 21 x 0.2 x 0.15 = 0.64
5.08

8 Ring Balk 15/25 P L T


= 57 x 0.15 x 0.25 = 2.14 2.14 M3

9 Plat Beton t = 10 cm (meja+tutup saluran) P L T N


Saluran = #REF! x 0.8 x 0.1 x 2 = #REF! #REF! M3

Meja Beton = 1 x 0.8 x 0.1 x 64 = 5.12


#REF!

10 Ring Blak Meja 15/15 P L T


= 2.8 x 0.15 x 0.15 x 64 = 4.03 4.03 M3

11 Kanopi P L T N
Ma = 29.8 x 0.5 x 0.08 x 2 = 2.38 3.53 M3
= 2.72 x 0.5 x 0.08 x 2 = 0.22
Mi = 5.8 x 0.5 x 0.08 x 4 = 0.93
3.53

IV PEKERJAAN PASANGAN L T N

1 Pasangan 1/2 Bata 1Pc : 3Ps Meja = 1.80 x 0.65 x 64 = 74.88 174.46 M2

dinding 4.7m = 30.00 x 0.5 x 2 = 30.00


= 2.00 x 0.5 x 4 = 4.00
Penebalan dinding = 1.20 x 0.5 x 8 = 4.80
Teras smpg = 0.85 x 0.5 x 4 = 1.70
= 0.15 x 0.5 x 4 = 0.30
Teras dpn = 0.50 x 0.5 x 4 = 1.00

Dinding Pemisah
Samping = 1.77 x 0.5 x 18 = 15.93
Tengah = 1.80 x 0.5 x 18 = 16.20
= 2.85 x 0.5 x 18 = 25.65
174.46

2 Pasangan 1/2 Bata 1Pc : 5Ps L T N 604.19 M2


dinding 6 m = 30.00 x 2.3 x 2 = 138.00
= 10.00 x 5.5 x 2 = 110.00
dinding 4.7m = 30.00 x 4.2 x 2 = 252.00
= 2.00 x 4.2 x 2 = 16.80
Penebalan dinding = 3.30 x 1.2 x 2 = 7.92
= 3.85 x 1.15 x 1 = 4.43
12.35 x 4 = 49.39
Teras smpg = 0.85 x 2.8 x 4 = 9.52
= 0.15 x 2.8 x 4 = 1.68
Teras dpn = 0.50 x 2.8 x 4 = 5.60

Dinding Pemisah
Samping = 1.77 x 0.75 x 18 = 23.90
Tengah = 1.80 x 0.75 x 18 = 24.30
= 2.85 x 0.75 x 18 = 38.48
atas = 0.40 + 1.15 x 0.45 x 36 = 12.55
= 2.85 x 0.45 x 7 = 8.98 = 691.19
No. URAIAN PEKERJAAN PERHITUNGAN VOLUME VOLUME SAT.

Luas Pintu dan Jendela


L T N
P1 = 1.71 x 2.53 x 6 = 25.96
J1 = 1.4 x 1.5 x 22 = 46.20
J2 = 1.4 x 0.53 x 20 = 14.84 = 87.00
604.19

3 Plesteran 1Pc : 3Ps Pasangan 1/2 Bata 1Pc : 5Ps 174.46 x 2 = 348.92 348.92 M2

4 Plesteran 1Pc : 5Ps Pasangan 1/2 Bata 1Pc : 5Ps 582.66 x 2 = 1165.32 #REF! M2
Plesteran saluran 1.60 x #REF! = #REF!
#REF!

5 Acian Plesteran 1Pc : 3Ps = 348.92 #REF! M2


Plesteran 1Pc : 5Ps = #REF!
#REF!

6 Pasangan Rolag P L N
Meja = 1.80 X 0.15 X 64 = 17.28 28.47 M2
Teras = 10.30 X 0.15 X 2 = 3.09
= 12.00 X 0.15 X 2 = 3.60
= 15.00 X 0.15 X 2 = 4.50
28.47

7 Pasangan Pipa Ø3" L N


Samping = 12.00 X 2 = 24.00 96.00 M1
= 15.00 X 2 = 30.00
Tengah = 9.00 X 2 = 18.00
= 12.00 X 2 = 24.00
96.00

8 Pasangan Kawat Harmonika L T N 135.33 M2


P1 = 0.77 x 0.41 x 2 x 6 = 3.79
J1 = 0.61 x 0.41 x 22 x 22 = 121.05
J2 = 1.28 x 0.41 x 1 x 20 = 10.50
135.33

9 Benangan

10 Pipa Pembuang PVC D 2.5" Tengah = 1.69 X 28 = 47.32 177.28 M'


Samping = 3.61 X 36 = 129.96
177.28

V PEKERJAAN LANTAI P L N 399.43 M3


1 Pas. Lantai Keramik 30 x 30 cm Keramik Lantai
A = 2.85 x 2 x 34 = 193.80
B = 2.85 x 9.85 x 2 = 56.15
C = 24.15 x 2.85 x 2 = 137.66
D = 2.85 x 4.15 x 1 = 11.83
399.43

2 Pas. Keramik dinding 20 x 25 cm Meja Atas = 1 x 0.8 x 1 = 0.80 478.2 M3


Depan = 1 x 0.8 x 1 = 0.88
Samping = 0.8 x 0.8 x 1 = 0.64
2.32 x 64 = 148.48

dinding & pemisah Samping = 2.85 x 1.25 x 20 = 71.25


= 1.77 x 1.25 x 40 = 88.50
= 1.77 x 0.15 x 18 = 4.78
kolom = 0.90 x 1.25 x 20 = 22.50

Tengah = 2.00 x 1.25 x 2 x 18 = 90.00


= 2.85 x 1.25 x 2 x 7 = 49.88
= 2.00 x 0.15 x 18 = 5.40
= 2.85 x 0.15 x 7 = 2.99 = 335.30
483.78

Pintu & Kusen Kusen = 1.4 x 0.05 x 18 = 1.26


Pintu = 1.71 x 1.25 x 2 = 4.28
5.54

TOTAL KERAMIK = 483.78 - 5.54 = 478.2


No. URAIAN PEKERJAAN PERHITUNGAN VOLUME VOLUME SAT.

VI PEKERJAAN DAN ATAP 0.3


1 Kuda-kuda, Nok, Gording, Ikatan Angin Ky. Gelam
Dimensi kayu P N 6.33 M3
KUDA-KUDA A = 0.08 x 0.12 6.60 2 = 0.13
B = 0.08 x 0.12 4.15 1 = 0.04
C = 0.08 x 0.12 3.00 2 = 0.06
D = 0.08 x 0.12 3.30 1 = 0.03
E = 0.08 x 0.12 1.70 2 = 0.03
F = 0.08 x 0.12 10.70 1 = 0.10
0.39 X 7 = 2.74

SETENGAH KUDA-KUDA A = 0.08 x 0.12 8.68 1 = 0.08


B = 0.08 x 0.12 2.78 1 = 0.03
C = 0.08 x 0.12 3.70 1 = 0.04
D = 0.08 x 0.12 3.81 1 = 0.04
E = 0.08 x 0.12 4.30 1 = 0.04
E = 0.08 x 0.12 7.30 1 = 0.07
0.29 X 4 = 1.17

NOK = 0.08 x 0.12 19.50 1 = 0.19

GORDING Ma = 0.08 x 0.12 23.10 2 = 0.44


= 0.08 x 0.12 27.00 2 = 0.52
Mi = 0.08 x 0.12 3.50 2 = 0.07
= 0.08 x 0.12 6.60 2 = 0.13

BALOK TEMBOK = 0.08 x 0.12 30.00 2 = 0.58


= 0.08 x 0.12 10.00 2 = 0.19

IKATAN ANGIN = 0.08 x 0.12 2.67 12 = 0.31


6.33

2 Pas. Atap Asbes Gelombang Besar (Tengah)


A = 19.4 + 32.2 / 2 x 8 X 2 = 412.80 501.20 M2
B = 0.5 x 12.45 x 7.1 x 2 = 88.40
501.2

3 Pas. Nok Asbes Gelombang Besar 19.4 + 8 x 4 51.4 51.40 M1

4 Pas. Atap Asbes Gelombang Besar (Samping) = 1.80 x 30.00 x 2 = 108 108.00 M2

5 Pas. Talang Dalam = 30 x 2 = 60 60.00 M'

6 Lisplank Kayu Kempas 3/30 A = 32.2 x 2 = 64.40 89.30 M'


B = 12.45 x 2 = 24.90
89.30

VII PEKERJAAN KUSEN, PINTU DAN PENGUNCI


1 Pas. Kusen Kayu bengkirai 3.45 M3
H V = Dimensi N
P1 = 3.3 + 4.74 = 15.64 X 0.06 x 0.15 x 6 = 0.84
J1 = 4.02 + 2.76 = 11.10 X 0.06 x 0.15 x 22 = 2.20
J2 = 2.8 + 0.82 = 2.30 X 0.06 x 0.15 x 20 = 0.41
3.45

2 Pas. Daun Pintu Panil Rangkap Kayu Bengkirai P1 = 2 x 1.7 x 6 = 19.88 19.88 m2

3 Pas. Daun Jendela + Kaca kayu Bengkirai J1 = 0.6 x 0.9 x 22 = 12.69 12.69 m2

4 Pas. Kaca Paten t = 5 mm J1 = 0.6 x 0.9 x 22 = 12.69 12.69 m2

5 Pas. Engsel pintu P1 = 1.5 x 2 x 6 = 18.00 18.00 set

6 Pas. Engsel jendela J1 = = 22.00 22.00 bh

7 Kunci 2 x putar P1 = 1 x 1 x 6 = 6.00 6.00 bh

VIII PEKERJAAN CAT - CATAN


1 Pengecatan Tembok Plesteran 1Pc : 3Ps = 348.92 1514.24 M2
Plesteran 1Pc : 5Ps = 1165.32
1514.24

2 Pengecatan Kayu Lisplank Kayu Kempas 3/30 89.30 X 0.3 = 26.79 181.10 M2

P DIMENSI N
KUSEN P1 = 15.64 x 0.06 x 0.15 x 6 = 25.34
KUSEN J1 = 11.10 x 0.06 x 0.15 x 22 = 65.91
KUSEN J2 = 2.30 x 0.06 x 0.15 x 20 = 12.40

PINTU P1 = 2 x 1.7 x 6 x 2 = 39.77


JENDELA J1 = 0.6 x 0.9 x 0.08 x 22 x 2 = 10.90
181.10
MUTUAL CHEK SATU (MC-I)

MINGGU KE- : VIII ( DELAPAN )


TANGGAL : 18 Desember 2012

PROGRAM : PROGRAM PENINGKATAN EFISIENSI PERDAGANGAN DALAM NEGERI


KEGIATAN : REVITALISASI PASAR TRADISIONAL ( BK UEP Prov )
PEKERJAAN : PEMBANGUNAN LOS DAGING
LOKASI : PASAR 17 AGUSTUS KABUPATEN PAMEKASAN

JUMLAH HARGA
NO URAIAN PEKERJAAN
RENCANA REALISASI

1 PEMBANGUNAN LOS DAGING 897,333,000.00 942,491,000.00

2 PEMBANGUNAN LOS PASAR 17 AGUSTUS 486,060,000.00 458,427,000.00

3 REHABILITASI SALURAN 158,857,000.00 141,332,000.00

JUMLAH TOTAL 1,542,250,000.00 1,542,250,000.00

Pamekasan, 18 Desember 2012 -

Dibuat oleh : Diperiksa oleh : Tim direksi

Kontraktor Pelaksana Konsultan Pengawas Program Peningkatan Efisiensi Perdagangan Dalam Negeri

CV. BENTAR ALAM CV. PANUTAN SELARAS CONSULTANT Dinas Perindustrian dan Perdagangan

Kabupaten Pamekasan

MOH. RASYAD FAUZI RAHMAD KURNIAWAN, ST ACHMAD FIRMAN HIDAYAT, SE Ketua 1.......................

Direktur Direktur NIP. 19780206 201101 1 004

Menyetujui Mengetahui

Pejabat Pembuat Komitmen Kuasa Pengguna Aggaran

Dinas Perindustrian dan Perdagangan Dinas Perindustrian dan Perdagangan ACH. FACHRURROZI, SH, MH Anggota 2.......................

Kabupaten Pamekasan Kabupaten Pamekasan NIP. 19711122 199502 1 002

HERMAN HIDAYAT S, ST. Drs. SLAMET RIADY DIDIK ROESWANDI, ST Anggota 3.......................

NIP. 19680712 199202 1 002 NIP. 19590909 198803 1 005 NIP. 19780508 200501 1 009
Back Up DATA

PROGRAM : PROGRAM PENINGKATAN EFISIENSI PERDAGANGAN DALAM NEGERI


KEGIATAN : REVITALISASI PASAR TRADISIONAL ( BK UEP Prov )
PEKERJAAN : PEMBANGUNAN LOS DAGING
LOKASI : PASAR 17 AGUSTUS KABUPATEN PAMEKASAN
TAHUN ANGG. : 2012

No. URAIAN PEKERJAAN PERHITUNGAN VOLUME VOLUME SAT.

I PEKERJAAAN PERSIAPAN
1 Pengukuran dan Pembersihan Pekerjaan

II PEKERJAAN TANAH H V
1 Galian Tanah panjang Galian 30 + 19.5 = 49.5

P L T
Batu kali = 49.5 x 1 x 0.98 = 48.51 49.39 M3
Foot Plat = 0.7 x 0.7 x 0.3 x 6 = 0.88
49.4

2 Urugan Tanah Kembali Galian 49.4 12.83 M3

Urugan Pasir 4.00


Lantai Kerja t= 5 cm 0.15
Foot Plat 70x70x25 cm 0.73
Pas . Anstampeng 9.90
Pas . Batu Belah 1 : 4 (Pondasi) 21.78 = 36.56
12.83

3 Urugan Sirtu Dengan Pemadatannya P L 9.14 M3


A = 30.46 x 0.3 x = 9.14

4 Urugan Pasir P L T
Batu kali = 49.5 x 1 x 0.05 = 2.48 4.00 M3
A = 30.46 x 0.05 = 1.52
4.00

5 Pas . Anstampeng P L T
= 49.5 x 1 x 0.2 = 9.90 9.90 M3

6 Pas . Batu Belah 1 : 4 (Pondasi) LA + LB / 2 X T X P

Pondasi = 0.3 + 0.8 / 2 x 0.8 X 50 = 21.78 21.78 M3

KOLOM PEDESTAL
Foot Plat = 0.20 x 0.2 x 1.05 x 6 = 0.25
21.53

7 Pasangan Rolag Panjang = 2.4 + 6 = 8.4 3.36 M3

= 8.4 x 0.4 = 3.36

8 Lantai Kerja t= 5 cm P x L x T x N

= 0.7 x 0.7 / 0.05 x 6 = 0.15 0.15 M3

III PEKERJAAN BETON

1 Foot Plat 70x70x25 cm P L T N

= 0.7 x 0.7 x 0.25 x 6 = 0.73 0.73 M3

2 Kolom K1 (20/20) P L T N

= 0.20 x 0.2 x 4.6 x 8 = 1.47 1.47 M3

3 Kolom K2 (15/15) P L T N

= 0.15 x 0.15 x 4.6 x 17 = 1.76 1.76 M3

4 Sloof 15/20 P L T

= 1.35 x 0.15 x 0.2 X 26 = 1.05 1.05 M3

5 Balok Latai 15/20 P L T N

= 3.53 x 0.15 x 0.2 X 2 = 0.21 0.21 M3

6 Ring Balok 15/20 P L T N

= 8.4 x 0.15 x 0.2 X 2 = 0.50 0.50 M3


7 Balok Anak 15/30 P L T N

= 7.89 x 0.15 x 0.3 X 2 = 0.71 0.71 M3

6 Balok Induk 20/30 P L T N

= 6.1 x 0.2 x 0.3 x 3 = 1.10 1.10 M3

7 Listplank Beton 10/30 P L T N

= 6.25 x 0.1 x 0.3 x 2 = 0.38 0.83 M3


= 7.6 x 0.1 x 0.3 x 2 = 0.46
0.83

8 Plat Atap Beton t =12 cm P L T N

= 2.85 x 2.1 x 0.12 x 4 = 2.87 4.86 M3


= 2.85 x 0.73 x 0.12 x 4 = 1.00
= 2.1 x 0.73 x 0.12 x 4 = 0.74
= 0.73 x 0.73 x 0.12 x 4 = 0.26
4.86

IV PEKERJAAN PASANGAN H V
14.1 + 19.38 = 33.48
1 Pasangan 1/2 Bata 1Pc : 3Ps 25.84 M2
Dinding = 33.48 x 0.5 = 16.74
Bak Mandi = 1.60 X 1.5 x 5 x = 12.00 = 28.74

Pintu Depan = 0.90 x 0.5 x 2 = 0.90


Pintu Vinil = 0.80 x 0.5 x 5 = 2.00 = 2.90
25.84

2 Pasangan 1/2 Bata 1Pc : 5Ps L T

depan = 33.48 x 3.05 = 102.11 72.79 M2

Pintu Depan = 0.90 x 1.5 x 12 = 16.20


Pintu Vinil = 0.80 x 1.3 x 12 = 12.48
Rosster = 0.20 x 0.2 x 16 = 0.64 = 29.32
72.79

3 Plesteran 1Pc : 3Ps Pasangan 1/2 Bata 1Pc : 5Ps 25.84 x 2 = 51.68 51.68 M2

4 Plesteran 1Pc : 5Ps Pasangan 1/2 Bata 1Pc : 5Ps 72.79 x 2 = 145.588 145.59 M2

5 Acian Plesteran 1Pc : 3Ps = 51.68 197.27 M2


Plesteran 1Pc : 5Ps = 145.59
197.27

6 Benangan H V N
Pintu Depan = 3.50 + 4 X 13 = 97.50 97.50 M2

V PEKERJAAN LANTAI P L N
1 Pas. Lantai Keramik 30 x 30 cm 30.46 M3
= 7.06
= 1.96
= 1.95
= 5.31
= 1.95
= 1.95
= 1.95
= 8.33
30.46

1 Pas. Keramik Dinding 20x25 cm P 97.95 M3


Dilnding = 17.40
= 5.70
= 5.70
= 10.80
= 5.70
= 5.70
= 5.70
56.70 X 1.5 = 85.05
Bak Mandi = 1.60 X 1.5 x 2 x 5 = 24.00 = 109.05

Pintu Depan = 0.90 X 1.5 x 2 = 2.70


Pintu Vinil = 0.80 X 1.5 x 5 = 6.00
Urinoir = 1.20 X 0.5 x 4 = 2.40 = 11.10
97.95

VI PEKERJAAN LANTAI
1 Instalasi Listrik 12.00 M3

2 Sakelar Tunggal 4.00 M3

3 Lampu SL 18 watt ( philips ) 8.00 M3

VII PEKERJAAN PLAFOND DAN ATAP 0.3

3 Rangka plafond Zincalume Metal furing 1200x1200 ex. Boral = 7.22 21.52 M1
= 5.20
= 1.82
= 1.82
= 1.82
= 1.82
= 1.82
21.52

4 List. Gypsum Plafond = 13.40 50.80 M1


= 10.40
= 5.40
= 5.40
= 5.40
= 5.40
= 5.40
50.80

VIII PEKERJAAN KUSEN, PINTU DAN PENGUNCI

1 Pas. Kusen Kayu Bengkirai = 4.9 x 0.08 x 0.15 x 2 = 0.12 0.12 M2

2 Pas. Daun Pintu Panil Rangkap Kayu Bengkirai = 2 + 0.9 x 2 = 11.60 11.60 M1

3 Pas. Engsel Pintu = = 2.00 2.00 M1

4 Pas. Kunci 2x Putar = 2.00 2.00 M1

5 Pintu Vinil (Kamar Mandi) = 5.00 5.00 M1

VIII PEKERJAAN CAT - CATAN


1 Pengecatan Tembok Plesteran 1Pc : 3Ps = 51.68 197.27 M2
Plesteran 1Pc : 5Ps = 145.59
197.27

2 Pengecatan Plafond = 21.5 21.52 M2

3 Pengecatan Kayu = 4.9 x 0.08 x 0.15 x 2 = 4.51 27.71 M2


Pas. Daun Pintu Panil Rangkap Kayu Bengkirai = 23.20
27.71
Back Up DATA

PROGRAM : PROGRAM PENINGKATAN EFISIENSI PERDAGANGAN DALAM NEGERI


KEGIATAN : REVITALISASI PASAR TRADISIONAL ( BK UEP Prov )
PEKERJAAN : PEMBANGUNAN LOS DAGING
LOKASI : PASAR 17 AGUSTUS KABUPATEN PAMEKASAN
TAHUN ANGG. : 2012

No. URAIAN PEKERJAAN PERHITUNGAN VOLUME VOLUME SAT.

I PEKERJAAAN PERSIAPAN
1 Pengukuran dan Pembersihan Pekerjaan

II PEKERJAAN TANAH H V
1 Galian Tanah panjang Galian 177 + 108 = 285

P L T
Batu kali = 285 x 1 x 1 = 285.00 337.93 M3
Foot Plat = 1 x 1 x 0.3 x 22 = 6.60

Saluran = 118.7 + 10 = 128.7

= 0.8 + 0.4 x 0.6 x 128.7 = 46.33

337.9

2 Urugan Tanah Kembali Galian 337.9 129.58 M3

Urugan Pasir 33.49


Lantai Kerja t= 5 cm 2.20
Foot Plat 100 x 100 cm 4.40
Kolom 20 /30 = 0.3 x 0.2 x 1.3 x 22 = 1.72
Pas . Anstampeng 28.50
Pas . Batu Belah 1 : 4 (Pondasi) 109.73
Saluran 28.31 208.35
129.58

3 Urugan Sirtu Dengan Pemadatannya P L T N 171.16 M3


A = 2.85 x 1.85 x 0.4 x 34 = 71.71
B = 2.85 x 9.85 x 0.4 x 2 = 22.46
C = 24.15 x 2.85 x 0.4 x 2 = 55.06
D = 2.85 x 4.15 x 0.4 x 1 = 4.73
1 = 0.85 x 8 x 0.4 x 2 = 5.44
2 = 0.7 x 11.85 x 0.4 x 2 = 6.64
3 = 0.85 x 2.85 x 0.4 x 1 = 0.97
4 = 0.7 x 14.85 x 0.4 x 1 = 4.16
171.16

4 Urugan Pasir P L T
Batu kali = 285 x 1 x 0.05 = 14.25 33.49 M3
Dalam
A = 2.85 x 1.85 x 0.05 x 34 = 8.96
B = 2.85 x 9.85 x 0.05 x 2 = 2.81
C = 24.15 x 2.85 x 0.05 x 2 = 6.88
D = 2.85 x 4.15 x 0.05 x 1 = 0.59
33.49

5 Pas . Anstampeng P L T
= 285 x 1 x 0.1 = 28.50 28.50 M3

6 Pas . Batu Belah 1 : 4 (Pondasi) LA + LB / 2 X T X P

Pondasi = 0.3 x 0.8 / 2 x 0.7 X 285.00 = 109.73 109.73 M3

Saluran Saluran Panjang = 128.7 28.31 M3

= 128.7 x 1.1 x 0.2 = 28.31

7 Lantai Kerja t= 5 cm P x L x T x N

= 1 x 1 / 0.1 x 22 = 2.20 2.20 M3

III PEKERJAAN BETON


1 Foot Plat 100 x 100 cm P L T N
= 1 x 1 x 0.2 x 22 = 4.40 4.40 M3

2 Sloof 15 /20 P L T
= 285.00 x 0.15 x 0.2 = 8.55 8.55 M3
No. URAIAN PEKERJAAN PERHITUNGAN VOLUME VOLUME SAT.

3 Kolom 15 /15 P L T N
dinding = 0.15 x 0.15 x 4.7 X 30 = 3.17 4.06 M3
= 0.15 x 0.15 x 6 X 4 = 0.54
Tengah = 0.15 x 0.15 x 1.7 X 9 = 0.34
4.06

4 Kolom 15 /20 P L T N
= 0.15 x 0.2 x 2.6 X 18 = 1.40 1.40 M3

5 Kolom 20 /30 P L T N
= 0.2 x 0.3 x 7.1 X 22 = 9.37 9.37 M3

6 Balok Latai 15/20 P L T


Tembok = 88 x 0.2 x 0.15 = 2.64 3.46 M3
Teras = 9.4 x 0.2 x 0.15 = 0.28
atas pintu = 18 x 0.2 x 0.15 = 0.54
3.46

7 Ring Balk 15/20 P L T


Tembok = 148 x 0.2 x 0.15 = 4.44 5.08 M3
Tengah = 21 x 0.2 x 0.15 = 0.64
5.08

8 Ring Balk 15/25 P L T


= 57 x 0.15 x 0.25 = 2.14 2.14 M3

9 Plat Beton t = 10 cm (meja+tutup saluran) P L T N


Saluran = 128.7 x 0.8 x 0.1 x 2 = 20.59 25.71 M3

Meja Beton = 1 x 0.8 x 0.1 x 64 = 5.12


25.71

10 Ring Blak Meja 15/15 P L T


= 2.8 x 0.15 x 0.15 x 64 = 4.03 4.03 M3

11 Kanopi P L T N
Ma = 29.8 x 0.5 x 0.08 x 2 = 2.38 3.53 M3
= 2.72 x 0.5 x 0.08 x 2 = 0.22
Mi = 5.8 x 0.5 x 0.08 x 4 = 0.93
3.53

IV PEKERJAAN PASANGAN L T N

1 Pasangan 1/2 Bata 1Pc : 3Ps Meja = 1.80 x 0.65 x 64 = 74.88 174.46 M2

dinding 4.7m = 30.00 x 0.5 x 2 = 30.00


= 2.00 x 0.5 x 4 = 4.00
Penebalan dinding = 1.20 x 0.5 x 8 = 4.80
Teras smpg = 0.85 x 0.5 x 4 = 1.70
= 0.15 x 0.5 x 4 = 0.30
Teras dpn = 0.50 x 0.5 x 4 = 1.00

Dinding Pemisah
Samping = 1.77 x 0.5 x 18 = 15.93
Tengah = 1.80 x 0.5 x 18 = 16.20
= 2.85 x 0.5 x 18 = 25.65
174.46

2 Pasangan 1/2 Bata 1Pc : 5Ps L T N 604.19 M2


dinding 6 m = 30.00 x 2.3 x 2 = 138.00
= 10.00 x 5.5 x 2 = 110.00
dinding 4.7m = 30.00 x 4.2 x 2 = 252.00
= 2.00 x 4.2 x 2 = 16.80
Penebalan dinding = 3.30 x 1.2 x 2 = 7.92
= 3.85 x 1.15 x 1 = 4.43
12.35 x 4 = 49.39
Teras smpg = 0.85 x 2.8 x 4 = 9.52
= 0.15 x 2.8 x 4 = 1.68
Teras dpn = 0.50 x 2.8 x 4 = 5.60

Dinding Pemisah
Samping = 1.77 x 0.75 x 18 = 23.90
Tengah = 1.80 x 0.75 x 18 = 24.30
= 2.85 x 0.75 x 18 = 38.48
atas = 0.40 + 1.15 x 0.45 x 36 = 12.55
= 2.85 x 0.45 x 7 = 8.98 = 691.19
No. URAIAN PEKERJAAN PERHITUNGAN VOLUME VOLUME SAT.

Luas Pintu dan Jendela


L T N
P1 = 1.71 x 2.53 x 6 = 25.96
J1 = 1.4 x 1.5 x 22 = 46.20
J2 = 1.4 x 0.53 x 20 = 14.84 = 87.00
604.19

3 Plesteran 1Pc : 3Ps Pasangan 1/2 Bata 1Pc : 5Ps 174.46 x 2 = 348.92 348.92 M2

4 Plesteran 1Pc : 5Ps Pasangan 1/2 Bata 1Pc : 5Ps 582.66 x 2 = 1165.32 1371.24 M2
Plesteran saluran 1.60 x 128.7 = 205.92
1371.24

5 Acian Plesteran 1Pc : 3Ps = 348.92 1720.16 M2


Plesteran 1Pc : 5Ps = 1371.24
1720.16

6 Pasangan Rolag P L N
Meja = 1.80 X 0.15 X 64 = 17.28 28.47 M2
Teras = 10.30 X 0.15 X 2 = 3.09
= 12.00 X 0.15 X 2 = 3.60
= 15.00 X 0.15 X 2 = 4.50
28.47

7 Pasangan Pipa Ø3" L N


Samping = 12.00 X 2 = 24.00 96.00 M1
= 15.00 X 2 = 30.00
Tengah = 9.00 X 2 = 18.00
= 12.00 X 2 = 24.00
96.00

8 Pasangan Kawat Harmonika L T N 135.33 M2


P1 = 0.77 x 0.41 x 2 x 6 = 3.79
J1 = 0.61 x 0.41 x 22 x 22 = 121.05
J2 = 1.28 x 0.41 x 1 x 20 = 10.50
135.33

9 Benangan

10 Pipa Pembuang PVC D 2.5" Tengah = 1.69 X 28 = 47.32 177.28 M'


Samping = 3.61 X 36 = 129.96
177.28

V PEKERJAAN LANTAI P L N 399.43 M3


1 Pas. Lantai Keramik 30 x 30 cm Keramik Lantai
A = 2.85 x 2 x 34 = 193.80
B = 2.85 x 9.85 x 2 = 56.15
C = 24.15 x 2.85 x 2 = 137.66
D = 2.85 x 4.15 x 1 = 11.83
399.43

2 Pas. Keramik dinding 20 x 25 cm Meja Atas = 1 x 0.8 x 1 = 0.80 478.2 M3


Depan = 1 x 0.8 x 1 = 0.88
Samping = 0.8 x 0.8 x 1 = 0.64
2.32 x 64 = 148.48

dinding & pemisah Samping = 2.85 x 1.25 x 20 = 71.25


= 1.77 x 1.25 x 40 = 88.50
= 1.77 x 0.15 x 18 = 4.78
kolom = 0.90 x 1.25 x 20 = 22.50

Tengah = 2.00 x 1.25 x 2 x 18 = 90.00


= 2.85 x 1.25 x 2 x 7 = 49.88
= 2.00 x 0.15 x 18 = 5.40
= 2.85 x 0.15 x 7 = 2.99 = 335.30
483.78

Pintu & Kusen Kusen = 1.4 x 0.05 x 18 = 1.26


Pintu = 1.71 x 1.25 x 2 = 4.28
5.54

TOTAL KERAMIK = 483.78 - 5.54 = 478.2


No. URAIAN PEKERJAAN PERHITUNGAN VOLUME VOLUME SAT.

VI PEKERJAAN DAN ATAP 0.3


1 Kuda-kuda, Nok, Gording, Ikatan Angin Ky. Gelam
Dimensi kayu P N 6.33 M3
KUDA-KUDA A = 0.08 x 0.12 6.60 2 = 0.13
B = 0.08 x 0.12 4.15 1 = 0.04
C = 0.08 x 0.12 3.00 2 = 0.06
D = 0.08 x 0.12 3.30 1 = 0.03
E = 0.08 x 0.12 1.70 2 = 0.03
F = 0.08 x 0.12 10.70 1 = 0.10
0.39 X 7 = 2.74

SETENGAH KUDA-KUDA A = 0.08 x 0.12 8.68 1 = 0.08


B = 0.08 x 0.12 2.78 1 = 0.03
C = 0.08 x 0.12 3.70 1 = 0.04
D = 0.08 x 0.12 3.81 1 = 0.04
E = 0.08 x 0.12 4.30 1 = 0.04
E = 0.08 x 0.12 7.30 1 = 0.07
0.29 X 4 = 1.17

NOK = 0.08 x 0.12 19.50 1 = 0.19

GORDING Ma = 0.08 x 0.12 23.10 2 = 0.44


= 0.08 x 0.12 27.00 2 = 0.52
Mi = 0.08 x 0.12 3.50 2 = 0.07
= 0.08 x 0.12 6.60 2 = 0.13

BALOK TEMBOK = 0.08 x 0.12 30.00 2 = 0.58


= 0.08 x 0.12 10.00 2 = 0.19

IKATAN ANGIN = 0.08 x 0.12 2.67 12 = 0.31


6.33

2 Pas. Atap Asbes Gelombang Besar (Tengah)


A = 19.4 + 32.2 / 2 x 8 X 2 = 412.80 501.20 M2
B = 0.5 x 12.45 x 7.1 x 2 = 88.40
501.2

3 Pas. Nok Asbes Gelombang Besar 19.4 + 8 x 4 51.4 51.40 M1

4 Pas. Atap Asbes Gelombang Besar (Samping) = 1.80 x 30.00 x 2 = 108 108.00 M2

5 Pas. Talang Dalam = 30 x 2 = 60 60.00 M'

6 Lisplank Kayu Kempas 3/30 A = 32.2 x 2 = 64.40 89.30 M'


B = 12.45 x 2 = 24.90
89.30

VII PEKERJAAN KUSEN, PINTU DAN PENGUNCI


1 Pas. Kusen Kayu bengkirai 3.45 M3
H V = Dimensi N
P1 = 3.3 + 4.74 = 15.64 X 0.06 x 0.15 x 6 = 0.84
J1 = 4.02 + 2.76 = 11.10 X 0.06 x 0.15 x 22 = 2.20
J2 = 2.8 + 0.82 = 2.30 X 0.06 x 0.15 x 20 = 0.41
3.45

2 Pas. Daun Pintu Panil Rangkap Kayu Bengkirai P1 = 2 x 1.7 x 6 = 19.88 19.88 m2

3 Pas. Daun Jendela + Kaca kayu Bengkirai J1 = 0.6 x 0.9 x 22 = 12.69 12.69 m2

4 Pas. Kaca Paten t = 5 mm J1 = 0.6 x 0.9 x 22 = 12.69 12.69 m2

5 Pas. Engsel pintu P1 = 1.5 x 2 x 6 = 18.00 18.00 set

6 Pas. Engsel jendela J1 = = 22.00 22.00 bh

7 Kunci 2 x putar P1 = 1 x 1 x 6 = 6.00 6.00 bh

VIII PEKERJAAN CAT - CATAN


1 Pengecatan Tembok Plesteran 1Pc : 3Ps = 348.92 1514.24 M2
Plesteran 1Pc : 5Ps = 1165.32
1514.24

2 Pengecatan Kayu Lisplank Kayu Kempas 3/30 89.30 X 0.3 = 26.79 181.10 M2

P DIMENSI N
KUSEN P1 = 15.64 x 0.06 x 0.15 x 6 = 25.34
KUSEN J1 = 11.10 x 0.06 x 0.15 x 22 = 65.91
KUSEN J2 = 2.30 x 0.06 x 0.15 x 20 = 12.40

PINTU P1 = 2 x 1.7 x 6 x 2 = 39.77


JENDELA J1 = 0.6 x 0.9 x 0.08 x 22 x 2 = 10.90
181.10
PROGRAM : PROGRAM PENINGKATAN EFISIENSI PERDAGANGAN DALAM NEGERI MUTUAL CHEK SATU ( MC-I )
KEGIATAN : REVITALISASI PASAR TRADISIONAL ( BK UEP Prov )
PEKERJAAN : LOS TYPE-C MINGGU KE- : VIII ( DELAPAN )
LOKASI : PASAR 17 AGUSTUS KABUPATEN PAMEKASAN TANGGAL : 18 Desember 2012

TAMBAH KURANG VOL. PEKERJAAN


RENCANA MC 0
PEK. TAMBAH PEK. KURANG
NO URAIAN PEKERJAAN KETERANGAN
HARGA SAT. JUML. HARGA JUML. HARGA
VOL. SAT. VOL. SAT. VOL. SAT. VOL. SAT.
( Rp. ) ( Rp. ) ( Rp. )

I PEKERJAAAN PERSIAPAN
1 Pembongkaran & Pembersihan 1.00 Ls 1,300,000.00 1,300,000.00 1.00 Ls 1,300,000.00
2 Pengukuran & bouplank 1.00 Ls 2,000,000.00 2,000,000.00 1.00 Ls 2,000,000.00
Jumlah I 3,300,000.00 3,300,000.00
II PEKERJAAN TANAH DAN PONDASI
1 Galian Tanah Pondasi Beton ( 70 x 70 ) 16.46 m3 31,500.00 518,490.00 8.52 m3 7.94 m3 250,047.00 PEKERJAAN KURANG
2 Galian Pondasi Batu Kali 114.44 m3 31,500.00 3,604,860.00 0.94 m3 113.50 m3 3,575,161.80 PEKERJAAN KURANG
3 Pasir Urug Bawah Pondasi 19.07 m3 223,800.00 4,267,866.00 8.88 m3 10.19 m3 2,281,215.78 PEKERJAAN KURANG
4 Lantai Kerja t = 7 cm 1.03 m3 695,895.90 716,772.78 1.03 m3 716,076.88
5 Anstampeng Batu Kali 24.79 m3 275,344.50 6,825,790.15 3.58 m3 28.37 m3 7,812,707.45 PEKERJAAN TAMBAH
6 Pondasi Batu Kali 59.01 m3 568,982.50 33,575,657.32 3.41 m3 62.42 m3 35,517,856.33 PEKERJAAN TAMBAH
7 Pondasi Foot Plat Beton 2.21 m3 3,488,424.30 7,709,417.70 0.36 m3 2.57 m3 8,973,971.51 PEKERJAAN TAMBAH
8 Kolom Beton Pondasi ( 15/25) 1.35 m3 3,488,424.30 4,709,372.81 0.28 m3 1.07 m3 3,728,253.47 PEKERJAAN KURANG
9 Urugan Tanah Kembali 23.43 m3 10,498.00 245,968.14 7.66 m3 15.77 m3 165,596.40 PEKERJAAN KURANG
10 Pasir Urug Bawah Lantai t = 0.2 m 111.61 m3 223,800.00 24,978,318.00 89.98 m3 21.63 m3 4,840,955.14 PEKERJAAN KURANG
11 Urugan sirtu dan pemadatan 101,500.00 165.88 m3 165.88 m3 16,836,989.05 PEKERJAAN TAMBAH
Jumlah II 87,152,512.91 84,698,830.80
III PEKERJAAN BETON
1 Sloof 15/20 9.54 m3 3,488,424.30 33,279,567.82 0.71 m3 8.83 m3 30,786,739.82 PEKERJAAN KURANG
2 Kolom 15/25 6.66 m3 3,488,424.30 23,232,905.84 0.18 m3 6.48 m3 22,604,989.46 PEKERJAAN KURANG
3 Balok Ring 15/15 0.72 m3 3,488,424.30 2,511,665.50 0.72 m3 m3 - PEKERJAAN KURANG
4 Balok Gantung 15/30 14.30 m3 3,488,424.30 49,884,467.49 4.15 m3 10.15 m3 35,423,902.24 PEKERJAAN KURANG
Jumlah III 108,908,606.65 88,815,631.52
IV PEKERJAAN PASANGAN
1 Pas.1/2 bata 1 Pc : 3 Ps 109.79 m2 76,843.00 8,436,592.97 14.74 m2 124.53 m2 9,569,258.79 PEKERJAAN TAMBAH
2 Pas.1/2 bata 1 Pc : 5 Ps 109.79 m2 74,647.00 8,195,494.13 14.74 m2 124.53 m2 9,295,790.91 PEKERJAAN TAMBAH
3 Plesteran 1Pc : 3Ps 219.57 m2 35,746.90 7,848,946.83 29.49 m2 249.06 m2 8,903,122.91 PEKERJAAN TAMBAH
4 Plesteran 1Pc : 5Ps 219.6 m2 32,584.50 7,154,578.67 29.49 m2 249.06 m2 8,115,495.57 PEKERJAAN TAMBAH
5 Pas Rollag 7.53 m3 76,843.00 578,627.79 0.54 m3 8.07 m3 619,800.27 PEKERJAAN TAMBAH
6 Acian 380.54 m2 18,425.00 7,011,449.50 346.08 m2 726.62 m2 13,388,047.20 PEKERJAAN TAMBAH
7 Benangan 2,046.72 m' 5,723.00 11,713,378.56 2,046.72 m' 11,713,378.56
8 stek Tul Ø 12 mm 71.91 kg 9,700.00 697,527.00 71.91 kg kg - PEKERJAAN KURANG
Jumlah IV 51,636,595.45 61,604,894.21
V PEKERJAAN ATAP
1 Kuda-kuda Kayu 8/12 5.32 m3 5,525,500.00 29,395,660.00 5.32 m3 29,387,349.65
2 Gapit 6/12 0.48 m3 5,525,500.00 2,652,240.00 0.48 m3 2,643,620.22
3 Ikatan Angin 6/10 0.18 m3 5,525,500.00 994,590.00 0.18 m3 1,021,112.40
4 Gording 5/7 1.11 m3 5,126,300.00 5,690,193.00 0.09 m3 1.20 m3 6,176,730.13 PEKERJAAN TAMBAH
5 Konsol 5/7 0.80 m3 5,126,300.00 4,101,040.00 0.80 m3 4,096,938.96 PEKERJAAN KURANG
6 List Plank 3 x 30 92.84 m' 72,400.00 6,721,616.00 17.60 m' 110.44 m' 7,995,856.00 PEKERJAAN TAMBAH
7 Atap Asbes Gelombang Besar 651.26 m2 65,402.50 42,594,032.15 61.57 m2 589.69 m2 38,567,514.16 PEKERJAAN KURANG
8 Nok Asbes Gelombang Besar 46.53 m' 106,877.50 4,973,010.08 3.97 m' 42.56 m' 4,548,706.40 PEKERJAAN KURANG
Jumlah V 97,122,381.23 94,437,827.92
VI PEKERJAAN LANTAI
1 Keramik Lantai 30 x 30 459.54 m2 128,704.50 59,144,865.93 19.73 m2 439.81 m2 56,606,092.44 PEKERJAAN KURANG
Jumlah VI 59,144,865.93 56,606,092.44
VII PEKERJAAN SANITAIR
1 Saluran Buis beton U 20 91.20 m' 119,373.80 10,886,890.56 18.80 m' 72.40 m' 8,642,663.12 PEKERJAAN KURANG
2 Bak Kontrol 8.00 bh 817,527.60 6,540,220.80 1.00 bh 7.00 bh 5,722,693.20 PEKERJAAN KURANG
Jumlah VII 17,427,111.36 14,365,356.32
VIII PEKERJAAN CAT-CATAN
1 Cat Tembok 819.68 m2 12,013.25 9,847,020.76 93.06 m2 726.62 m2 8,729,115.77 PEKERJAAN KURANG
2 Cat Kayu 279.64 m2 26,227.50 7,334,258.10 119.70 m2 159.94 m2 4,194,700.46 PEKERJAAN KURANG
Jumlah VIII 17,181,278.86 12,923,816.23
Jumlah Total Harga 441,873,352.37 416,752,449.45
PPN ( 10 % ) 44,187,335.24 41,675,244.94
JUMLAH + PPN 486,060,687.61 458,427,694.39
DIBULATKAN 486,060,000.00 458,427,000.00

PAMEKASAN, 18 Desember 2012

Dibuat oleh : Diperiksa dan Disetujui Oleh :


Kontraktor Pelaksana Konsultan Pengawas Tim direksi
CV. BENTAR ALAM CV. PANUTAN SELARAS CONSULTANT Program Peningkatan Efisiensi Perdagangan Dalam Negeri
Dinas Perindustrian dan Perdagangan
Kabupaten Pamekasan

MOH. RASYAD FAUZI RAHMAD KURNIAWAN, ST


Direktur Utama Direktur ACHMAD FIRMAN HIDAYAT, SE Ketua 1......................
NIP. 19780206 201101 1 004

Menyetujui : Mengetahui :
Pejabat Pembuat Komitmen Kuasa Pengguna Aggaran
Dinas Perindustrian dan Perdagangan Dinas Perindustrian dan Perdagangan
Kabupaten Pamekasan Kabupaten Pamekasan ACH. FACHRURROZI, SH, MH Anggota 2 . . . . . . . . . . . . . . . . . . . . . .
NIP. 19711122 199502 1 002

HERMAN HIDAYAT S, ST. Drs. SLAMET RIADY DIDIK ROESWANDI, ST Anggota 3 . . . . . . . . . . . . . . . . . . . . . .


NIP. 19680712 199202 1 002 NIP. 19590909 198803 1 005 NIP. 19780508 200501 1 009
Back Up DATA

PROGRAM : PROGRAM PENINGKATAN EFISIENSI PERDAGANGAN DALAM NEGERI


KEGIATAN : REVITALISASI PASAR TRADISIONAL ( BK UEP Prov )
PEKERJAAN : LOS TYPE-C
LOKASI : PASAR 17 AGUSTUS KABUPATEN PAMEKASAN
TAHUN ANGG. : 2012

No. URAIAN PEKERJAAN PERHITUNGAN VOLUME VOLUME SAT.

I PEKERJAAAN PERSIAPAN
1 Pembongkaran & Pembersihan
2 Pengukuran & bouplank

II PEKERJAAN TANAH DAN PONDASI V = P X L X T X N


1 Galian Tanah Pondasi Beton ( 70 x 70 ) = 0.7 X 0.7 X 0.54 X 30 = 7.94 7.94 M3

2 Galian Pondasi Batu Kali Panjang galian = H + V


= 214.02 + 101.25 = 315.27

P L T
Batu kali = 315.27 x 0.6 x 0.6 = 113.50 113.50 M3

3 Pasir Urug Bawah Pondasi P L T N


Batu kali = 315.27 x 0.6 x 0.05 = 9.46 10.19 M3
Foot Plat = 0.7 x 0.7 x 0.05 x 30 = 0.73
10.19

4 Lantai Kerja t = 7 cm P L T N
Foot Plat = 0.7 x 0.7 x 0.07 x 30 = 1.03 1.03 M3

5 Anstampeng Batu Kali P L T


Batu kali = 315.27 x 0.6 x 0.15 = 28.37 28.37 M3

6 Pondasi Batu Kali LA + LB / 2 X T X P

Pondasi = 0.35 x 0.53 / 2 x 0.45 X 315.27 = 62.42 62.42 M3

7 Pondasi Foot Plat Beton = P X L X T X N

= 0.7 X 0.7 X 0.175 X 30 = 2.57 2.57 M3

8 Kolom Beton Pondasi ( 15/25) = P X L X T X N

= 0.15 X 0.25 X 0.95 X 30 = 1.07 1.07 M3

9 Urugan Tanah Kembali

Galian Tanah Pondasi Beton ( 70 x 70 ) = 7.94


Galian Pondasi Batu Kali = 113.5 = 121.44

Pasir Urug Bawah Pondasi = 10.19


Lantai Kerja t = 7 cm = 1.03
Anstampeng Batu Kali = 28.37
Pondasi Batu Kali = 62.42
Pondasi Foot Plat Beton = 2.57
Kolom Beton Pondasi ( 15/25) = 1.07 = 105.66 15.77 M3
15.77

10 Pasir Urug Bawah Lantai t = 0.2 m = P X L X T X N

A = 2.78 X 1.76 X 0.05 X 48 = 11.74 21.63 M3


B = 24 X 1.2 X 0.05 X 2 = 2.88
C = 24 X 2 X 0.05 X 2 = 4.80
D = 18.4 X 1.2 X 0.05 X 2 = 2.21
21.63

11 Urugan sirtu dan pemadatan = P X L X T X N

A = 2.78 X 1.76 X 0.4 X 48 = 90.05 165.88 M3


- B = 24 X 1.2 X 0.4 X 2 = 22.09
C = 24 X 2 X 0.4 X 2 = 36.81
D = 18.4 X 1.2 X 0.4 X 2 = 16.93
165.88

III PEKERJAAN BETON


H + V
1 Sloof 15/20 Panjang = 197.52 + 96.66 = 294.18

P L T
= 294.18 x 0.15 x 0.2 = 8.83 8.83 M3
No. URAIAN PEKERJAAN PERHITUNGAN VOLUME VOLUME SAT.

2 Kolom 15/25 = P X L X T X N

= 0.15 X 0.25 X 3.2 X 54 = 6.48 6.48 M3

4 Balok Gantung 15/30 Pajang = H + V


= 125.76 + 99.9 = 225.66

= 225.66 X 0.15 X 0.3 = 10.15 10.15 M3

IV PEKERJAAN PASANGAN
H + V
1 Pas.1/2 bata 1 Pc : 3 Ps Panjang = 149.16 + 99.9 = 249.06

P T
= 249.06 x 0.5 = 124.53 124.53 M3

2 Pas.1/2 bata 1 Pc : 5 Ps H + V
Panjang = 149.16 + 99.9 = 249.06

P T
= 249.06 x 0.5 = 124.53 124.53 M3

3 Plesteran 1Pc : 3Ps Pas.1/2 bata 1 Pc : 3 Ps = 124.53 x 2 = 249.06 249.06 M3

4 Plesteran 1Pc : 5Ps Pas.1/2 bata 1 Pc : 5 Ps = 124.53 x 2 = 249.06 249.06 M3

5 Pas Rollag P L T
= 89.62 x 0.15 x 0.6 = 8.07 8.07 M3

6 Acian Plesteran 1Pc : 3Ps = 249.06 726.62 M2


Plesteran 1Pc : 5Ps = 249.06
Kolom 15/25 = 0.15 X 0.25 X 3.2 X 54 = 138.24
Balok Gantung 15/30 = 0.15 X 0.25 X 225.66 = 90.26
726.62

V PEKERJAAN ATAP
Dimensi P N
1 Kuda-kuda Kayu 8/12 Tengah A = 0.08 X 0.12 X 3.9 X 2 = 0.07 5.32 M3
7.80 B = 0.08 X 0.12 X 1.15 X 2 = 0.02
0.74 C = 0.08 X 0.12 X 8.3 X 2 = 0.16
5.31 D = 0.08 X 0.12 X 5.6 X 1 = 0.05
1.79 E = 0.08 X 0.12 X 2.6 X 2 = 0.05
1.66 F = 0.08 X 0.12 X 2 X 2 = 0.04
1.28 G = 0.08 X 0.12 X 2.5 X 2 = 0.05
1.60 H = 0.08 X 0.12 X 1.25 X 2 = 0.02
0.80 I = 0.08 X 0.12 X 1.6 X 2 = 0.03
1.02 J = 0.08 X 0.12 X 0.65 X 2 = 0.01
0.42 K = 0.08 X 0.12 X 16 X 1 = 0.15
22.42 Sambungan = 0.08 X 0.12 X 1 X 3 = 0.03
Siku = 0.08 X 0.12 X 0.8 X 8 = 0.06
47.35 0.76 X 5 3.79

- Samping A = 0.08 X 0.12 X 11.70 X 1 = 0.11


11.70 1.95 B = 0.08 X 0.12 X 4.88 X 1 = 0.05
4.88 C = 0.08 X 0.12 X 4.68 X 1 = 0.04
4.68 D = 0.08 X 0.12 X 2.44 X 1 = 0.02
2.44 E = 0.08 X 0.12 X 2.93 X 1 = 0.03
2.93 F = 0.08 X 0.12 X 1.56 X 1 = 0.01
1.56 G = 0.08 X 0.12 X 11.70 X 1 = 0.11
28.18 39.88 0.38 X 4 1.53
5.32

2 Gapit 6/12 Dimensi P N

= 0.06 X 0.12 X 13.29 X 5 = 0.48 0.48 M3

3 Ikatan Angin 6/10 Dimensi P N

= 0.06 X 0.1 X 3.85 X 8 = 0.18 0.18 M3

4 Gording 5/7 Dimensi P N

A = 0.05 X 0.07 X 13.6 X 5 = 0.24 1.20 M3

B = 0.05 X 0.07 X 23.38 X 2 = 0.16


= 0.05 X 0.07 X 20.65 X 2 = 0.14
= 0.05 X 0.07 X 17.83 X 2 = 0.12
= 0.05 X 0.07 X 15.01 X 2 = 0.11
= 0.05 X 0.07 X 12.2 X 2 = 0.09
No. URAIAN PEKERJAAN PERHITUNGAN VOLUME VOLUME SAT.

C = 0.05 X 0.07 X 15.38 X 2 = 0.11


= 0.05 X 0.07 X 12.65 X 2 = 0.09
= 0.05 X 0.07 X 9.83 X 2 = 0.07
= 0.05 X 0.07 X 7 X 2 = 0.05
= 0.05 X 0.07 X 4.2 X 2 = 0.03
1.20

5 Konsol 5/7 Dimensi P N

= 0.06 X 0.1 X 4.44 X 30 = 0.80 0.80 M3

6 List Plank 3 x 30 H + V N
Atas = 4.41 + X 4 = 17.64 110.44 M1
Bawah = 27.2 + 19.2 X 2 = 92.80
110.44

7 Atap Asbes Gelombang B A = 13.64 X 4.41 X 2 = 120.30 589.69 M2


B = 13.6 + 27.6 / 2 X 7.3 2 = 300.76
C = 3.5 + 19.6 / 2 X 7.3 2 = 168.63
589.69

8 Nok Asbes Gelombang Besar = 13.64 + 7.23 X 4 = 42.56 42.56 M1

VI PEKERJAAN LANTAI P L N

1 Keramik Lantai 30 x 30 A = 2.78 X 1.76 X 48 = 234.85 439.81 M2


= 1 X 0.15 X 48 = 7.20 = 242.05
B = 24 X 1.2 X 2 = 57.60
C = 24 X 2 X 2 = 96.00
D = 18.4 X 1.2 X 2 = 44.16
439.81

VII PEKERJAAN SANITAIR


H + V
1 Saluran Buis Panjang = 53.6 + 18.8 = 72.4 = 72.40 72.40 M1

2 Bak Kontrol 7.00 Bh

VIII PEKERJAAN CAT-CATAN

1 Cat Tembok Acian = 726.62 726.62 M2

2 Cat Kayu Listplang = 110.44 x 0.3 = 33.13 159.94 M2

kuda-kuda P D N
Tengah = 47.35 x 0.12 x 0.08 x 5 = 75.76
Samping = 39.88 x 0.12 x 0.08 x 4 = 51.04

159.94
Back Up DATA

PROGRAM : PROGRAM PENINGKATAN EFISIENSI PERDAGANGAN DALAM NEGERI


KEGIATAN : REVITALISASI PASAR TRADISIONAL ( BK UEP Prov )
PEKERJAAN : REHABILITASI SALURAN
LOKASI : PASAR 17 AGUSTUS KABUPATEN PAMEKASAN
TAHUN ANGG. : 2012

No. URAIAN PEKERJAAN PERHITUNGAN VOLUME VOLUME SAT.

I PEKERJAAN SALURAN

V type A = P X L X T
1 Galian Tanah = 32.0 X 0.9 X 0.7 = 20.16 20.16 M3

V type B = P X L X T = 92.82 92.82 M3


= 221 X 0.7 X 0.6
TOTAL 112.98 M3

2 Urugan Pasir V type A = P X L X T


= 32 X 0.9 X 0.05 = 1.44 1.44 M3

V type B = P X L X T = 7.73 7.73 M3


= 221.0 X 0.7 X 0.05
TOTAL 9.17 M3

3 Pas.pondasi Batu Kali V Galian A = 20.16


= V.galian -(V.dalam + V.plat beton) = 17.29 17.29 M3
V.dalam = jumlah alas
x t
2
= 0.46+0.3
x 0.48 = 0.18
2
V.plat = P X L X T
32 X 0.7 X 0.12 = 2.688

V.Galian B = 92.82 = 80.24 80.24 M3


= V.galian-(V.dalam+V.plat beton)
V.dalam = B = jumlah alas
x t
2
= 0.47+0.3
x 0.52 = 0.20
2

V.plat = P X L X T
221 X 0.7 X 0.08 = 12.38
TOTAL 97.53 M3

4 Plesteran 1Pc : 5 Ps V.type A = L.penampang x Panjang


= 1.48 x 32 = 47.36 47.36 M3

V.type B = L.penampang x Panjang


= 1.56 x 221 = 344.76 344.76 M3

TOTAL 392.12 M3

5 Plat beton t=8 cm V.plat = P X L X T


221 X 0.7 X 0.08 = 12.38 12.38 M3

12.38 M3

5 Plat beton t=12 cm V.plat = P X L X T


32 X 0.7 X 0.12 = 2.69 2.69 M3

TOTAL 2.69 M3
36 15.84
2.32 8.09
5.16 7.7
2.96 32 panjang type A
17.03
23.6
5.43

48.53
1.44
35.46

221.0 panjang type B

-
Back Up DATA

PROGRAM : PROGRAM PENINGKATAN EFISIENSI PERDAGANGAN DALAM NEGERI


KEGIATAN : REVITALISASI PASAR TRADISIONAL ( BK UEP Prov )
PEKERJAAN : PEMBANGUNAN LOS DAGING
LOKASI : PASAR 17 AGUSTUS KABUPATEN PAMEKASAN
TAHUN ANGG. : 2012

No. URAIAN PEKERJAAN PERHITUNGAN VOLUME VOLUME SAT.

I PEKERJAAAN PERSIAPAN
1 Pengukuran dan Pembersihan Pekerjaan

II PEKERJAAN TANAH H V
1 Galian Tanah panjang Galian 72 + 39 = 111

P L T
Batu kali = 111 x 1 x 0.98 = 108.78 112.60 M3
Foot Plat = 0.7 x 0.7 x 0.3 x 13 = 1.91
Skoor = 0.7 x 0.7 x 0.3 x 13 = 1.91
112.6

2 Urugan Tanah Kembali Galian 112.6 24.08 M3

Urugan Pasir 11.95


Lantai Kerja t= 5 cm 0.64
Foot Plat 70x70x25 cm 3.18
Sloof 15/20 = 0.3 x 0.2 x 1.3 x 22 = 1.72
Pas . Anstampeng 22.20
Pas . Batu Belah 1 : 4 (Pondasi) 48.84 = 88.53
24.08

3 Urugan Sirtu Dengan Pemadatannya P L T N 51.18 M3


A = 2.85 x 2.85 x 0.4 x 12 = 38.99
B = 0.85 x 35.85 x 0.4 x 1 = 12.19
51.18

4 Urugan Pasir P L T
Batu kali = 111 x 1 x 0.05 = 5.55 11.95 M3
Dalam
A = 2.85 x 2.85 x 0.05 x 12 = 4.87
B = 0.85 x 35.85 x 0.05 x 1 = 1.52
11.95

5 Pas . Anstampeng P L T
= 111 x 1 x 0.2 = 22.20 22.20 M3

6 Pas . Batu Belah 1 : 4 (Pondasi) LA + LB / 2 X T X P

Pondasi = 0.3 + 0.8 / 2 x 0.8 X 111 = 48.84 48.84 M3

KOLOM PEDESTAL
Foot Plat = 0.20 x 0.2 x 1.05 x 13 = 0.55
Skoor = 0.15 x 0.2 x 1.05 x 13 = 0.41 = 0.96
47.88

7 Pasangan Rolag Panjang = 1.7 + 36.15 = 37.85 15.14 M3

= 37.85 x 0.4 = 15.14

8 Lantai Kerja t= 5 cm P x L x T x N

= 0.7 x 0.7 / 0.05 x 26 = 0.64 0.64 M3

III PEKERJAAN BETON


1/4 phi D T N
1 Strouss Φ 30 cm ( h = 3 m )
= 0.25 x 3.14 x 0.3 x 3 x 26 = 5.51 5.51 M3

= 26.00 x 3 = 78.00

2 Beton strouss Φ 30 1/4 phi D T N

= 0.25 x 3.14 x 0.3 x 3 x 26 = 5.51 5.51 M3

3 Foot Plat 70x70x25 cm P L T N

= 0.7 x 0.7 x 0.25 x 26 = 3.18 3.18 M3

4 Kolom K1 (20/20) P L T N

= 0.20 x 0.2 x 4.2 x 13 = 2.18 2.18 M3


5 Kolom K2 (15/20) P L T N

= 0.20 x 0.2 x 3.62 x 13 = 1.88 1.88 M3

6 Kolom K3 (15/15) P L T N

= 0.15 x 0.15 x 3.9 X 13 = 1.14 1.14 M3

7 Sloof 15/20 P L T N

= 2.85 x 0.15 x 0.2 X 24 = 2.05 3.07 M3


= 0.8 x 0.15 x 0.2 X 13 = 0.31
= 1.82 x 0.15 x 0.2 X 13 = 0.71
3.07

8 Balok Gantung 15/20 P L T N

= 2.85 x 0.15 x 0.2 x 12 = 1.03 1.03 M3

9 Ring Balok 15/20 P L T N

= 2.85 x 0.15 x 0.2 x 12 = 1.03 1.03 M3

10 Ring Balok 15/15 P L T N

= 2.85 x 0.15 x 0.15 x 12 = 0.77 0.77 M3

IV PEKERJAAN PASANGAN L T N

1 Pasangan 1/2 Bata 1Pc : 3Ps depan = 2.85 x 0.5 x 12 = 17.10 35.70 M2

belakang = 2.85 x 0.5 x 12 = 17.10

samping = 2.85 x 0.5 x 12 = 17.10 = 51.30

Rolling Dor = 2.40 x 0.5 x 12 = 14.40


Skoor = 0.20 x 0.5 x 12 = 1.20 = 15.60
35.70

2 Pasangan 1/2 Bata 1Pc : 5Ps L T N

depan = 2.85 x 1.75 x 12 = 59.85 255.60 M2


= 2.85 x 1.35 x 12 = 46.17
= 1.85 x 0.2 x 12 = 4.44

belakang = 2.85 x 2.26 x 12 = 77.29

samping = 3 + 3.7 / 2 x 2.85 X 2 = 19.10


= 2.5 + 3.54 / 2 x 2.85 X 12 = 103.28 = 310.13

Rolling Dor = 2.40 x 1.75 x 12 = 50.40


Skoor = 0.20 x 1.72 x 12 = 4.13 = 54.53
255.60

3 Plesteran 1Pc : 3Ps Pasangan 1/2 Bata 1Pc : 5Ps 35.70 x 2 = 71.4 71.40 M2

4 Plesteran 1Pc : 5Ps Pasangan 1/2 Bata 1Pc : 5Ps 255.60 x 2 = 511.206 511.21 M2

5 Acian Plesteran 1Pc : 3Ps = 71.40 582.61 M2


Plesteran 1Pc : 5Ps = 511.21
582.61

6 Benangan H V N
Rolling Dor = 2.85 + 4.5 X 12 = 88.20 232.20 M2
Dinding = 3.00 X 4 X 12 = 144.00
232.20

7 Pas. Rolling Door H V N


= 2.40 + 2.25 X 12 = 55.80 55.80 M1
55.80

V PEKERJAAN LANTAI P L N 133.47 M3


1 Pas. Lantai Keramik 30 x 30 cm
Dalam = 2.85 x 2.85 x 12 = 97.47
Teras = 36 x 1 x 1 = 36.00
133.47

VI PEKERJAAN PLAFOND DAN ATAP 0.3


1 Kuda-kuda, Gording, Konsol Ky. Gelam
Dimensi kayu P N 3.10 M3
KUDA-KUDA Blk Tarik = 0.08 x 0.12 35.85 1 = 0.34
Melintang = 0.08 x 0.12 3.60 1 = 0.03
GORDING Ma = 0.06 x 0.10 35.85 5 = 1.08

KONSOL Tiang = 0.08 x 0.12 x 0.85 x 1 = 0.01


Sekor = 0.08 x 0.12 x 0.91 x 1 = 0.01
Gapit = 0.06 x 0.10 x 10.00 x 2 = 0.12
0.14 x 12 = 1.64
3.10

2 Pas. Atap Asbes Gelombang Kecil


A = 3.76 x 35.85 x = 134.80 177.82 M2
B = 1.2 x 35.85 x = 43.02
177.8

3 Rangka plafond Zincalume Metal furing 1200x1200 ex. Boral = 2.85 x 2.85 x 12 = 97.47 97.47 M2

4 List. Gypsum Plafond = 2.85 + 2.85 x 12 = 136.80 136.80 M1

3 Lisplank Kalsiplank 2 x 12/200 37.85 37.85 37.85 M1

VIII PEKERJAAN CAT - CATAN


1 Pengecatan Tembok Plesteran 1Pc : 3Ps = 71.40 582.61 M2
Plesteran 1Pc : 5Ps = 511.21
582.61

2 Pengecatan Plafond = 97.47 = 97.5 97.47 M2

3 Pengecatan Kayu Lisplank Kalsi = 37.85 x 0.25 = 9.5 94.71 M2

KONSOL
Tiang = 0.08 x 0.12 x 0.85 x 1 = 0.34
Sekor = 0.08 x 0.12 x 0.91 x 1 = 0.36
Gapit = 0.06 x 0.10 x 10.00 x 2 = 6.40
7.10 x 12 = 85.25
94.71
Back Up DATA

PROGRAM : PROGRAM PENINGKATAN EFISIENSI PERDAGANGAN DALAM NEGERI


KEGIATAN : REVITALISASI PASAR TRADISIONAL ( BK UEP Prov )
PEKERJAAN : PEMBANGUNAN LOS DAGING
LOKASI : PASAR 17 AGUSTUS KABUPATEN PAMEKASAN
TAHUN ANGG. : 2012

No. URAIAN PEKERJAAN PERHITUNGAN VOLUME VOLUME SAT.

I PEKERJAAAN PERSIAPAN
1 Pengukuran dan Pembersihan Pekerjaan

II PEKERJAAN TANAH H V
1 Galian Tanah panjang Galian 56.36 + 34 = 90.36

P L T
Batu kali = 90.36 x 1 x 0.98 = 88.55 92.23 M3
Foot Plat = 0.7 x 0.7 x 0.3 x 13 = 1.91
Skoor = 0.7 x 0.7 x 0.3 x 12 = 1.76
92.2

2 Urugan Tanah Kembali Galian 92.2 19.67 M3

Urugan Pasir 9.34


Lantai Kerja t= 5 cm 0.61
Foot Plat 70x70x25 cm 3.06
Sloof 15/20 = 0.3 x 0.2 x 1.3 x 22 = 1.72
Pas . Anstampeng 18.07
Pas . Batu Belah 1 : 4 (Pondasi) 39.76 = 72.56
19.67

3 Urugan Sirtu Dengan Pemadatannya P L T N 38.56 M3


A = 2.85 x 2.85 x 0.4 x 9 = 29.24
### B = 0.85 x 27.4 x 0.4 x 1 = 9.32
1,806,000 38.56

4 Urugan Pasir P L T
Batu kali = 90.36 x 1 x 0.05 = 4.52 9.34 M3
Dalam
A = 2.85 x 2.85 x 0.05 x 9 = 3.66
B = 0.85 x 27.4 x 0.05 x 1 = 1.16
9.34

5 Pas . Anstampeng P L T
= 90.36 x 1 x 0.2 = 18.07 18.07 M3

6 Pas . Batu Belah 1 : 4 (Pondasi) LA + LB / 2 X T X P

Pondasi = 0.3 + 0.8 / 2 x 0.8 X 90 = 39.76 39.76 M3

KOLOM PEDESTAL
Foot Plat = 0.20 x 0.2 x 1.05 x 13 = 0.55
Skoor = 0.15 x 0.2 x 1.05 x 12 = 0.38 = 0.92
38.83

7 Pasangan Rolag Panjang = 1.7 + 27.4 = 29.1 11.64 M3

= 29.1 x 0.4 = 11.64

8 Lantai Kerja t= 5 cm P x L x T x N

= 0.7 x 0.7 / 0.05 x 25 = 0.61 0.61 M3

III PEKERJAAN BETON


1/4 phi D T N
1 Strouss Φ 30 cm ( h = 3 m )
= 0.25 x 3.14 x 0.3 x 3 x 25 = 5.30 5.30 M3

= 25.00 x 3 = 75.00

2 Beton strouss Φ 30 1/4 phi D T N

= 0.25 x 3.14 x 0.3 x 3 x 25 = 5.30 5.30 M3

3 Foot Plat 70x70x25 cm P L T N

= 0.7 x 0.7 x 0.25 x 25 = 3.06 3.06 M3

4 Kolom K1 (20/20) P L T N

= 0.20 x 0.2 x 4.2 x 13 = 2.18 2.18 M3


5 Kolom K2 (15/20) P L T N

= 0.20 x 0.2 x 3.62 x 12 = 1.74 1.74 M3

6 Kolom K3 (15/15) P L T N

= 0.15 x 0.15 x 3.9 X 9 = 0.79 0.79 M3

7 Sloof 15/20 H V
Panjang 49 + 24.83 = 73.83

P L T

= 73.83 x 0.15 x 0.2 = 2.21 2.21 M3

8 Balok Gantung 15/20 H V


Panjang 24.64 + 20.97 = 45.61

P L T

= 45.61 x 0.15 x 0.2 = 1.37 1.37 M3

9 Ring Balok 15/20 H V


Panjang 27.74 + = 27.74

P L T

= 27.74 x 0.15 x 0.2 = 0.83 0.83 M3

10 Ring Balok 15/15 H V


Panjang 21.26 + = 21.26

P L T

= 21.26 x 0.15 x 0.15 = 0.48 0.48 M3

IV PEKERJAAN PASANGAN L T N

1 Pasangan 1/2 Bata 1Pc : 3Ps 23.85 M2

belakang = 27.74 x 0.5 x = 13.87

samping = 0.44 + 1.64 / 2 x 0.8 X 12 = 9.98


23.85

2 Pasangan 1/2 Bata 1Pc : 5Ps L T N

depan = 21.26 x 0.68 x 1 = 14.46 89.90 M2

belakang = 27.74 x 2.12 x 1 = 58.81

samping = 0.36 + 0.83 / 2 x 2.33 X 12 = 16.64 = 89.90

3 Plesteran 1Pc : 3Ps Pasangan 1/2 Bata 1Pc : 5Ps 23.85 x 2 = 47.708 47.71 M2

4 Plesteran 1Pc : 5Ps Pasangan 1/2 Bata 1Pc : 5Ps 89.90 x 2 = 179.804 179.80 M2

5 Acian Plesteran 1Pc : 3Ps = 47.71 227.51 M2


Plesteran 1Pc : 5Ps = 179.80
227.51

6 Benangan H V N
Skoor = 2.30 X 2 X 12 = 55.20 127.20 M2
Dinding = 3.00 X 2 X 12 = 72.00
127.20

V PEKERJAAN LANTAI P L N 100.50 M3


1 Pas. Lantai Keramik 30 x 30 cm
Dalam = 2.85 x 2.85 x 9 = 73.10
Teras = 27.4 x 1 x 1 = 27.40
100.50

VI PEKERJAAN PLAFOND DAN ATAP 0.3


1 Kuda-kuda, Gording, Konsol Ky. Gelam
Dimensi kayu P N 3.03 M3
KUDA-KUDA Blk Tarik = 0.08 x 0.12 27.40 1 = 0.26
Melintang = 0.08 x 0.12 3.87 17 = 0.63

GORDING Ma = 0.06 x 0.10 27.40 3 = 0.49

KONSOL Tiang = 0.08 x 0.12 x 0.85 x 1 = 0.01


Sekor = 0.08 x 0.12 x 0.91 x 1 = 0.01
Gapit = 0.06 x 0.10 x 10.00 x 2 = 0.12
0.14 x 12 = 1.64
3.03

2 Pas. Atap Asbes Gelombang Kecil


A = 3.87 x 27.40 x = 106.04 138.92 M2
B = 1.2 x 27.40 x = 32.88
138.9

3 Lisplank Kalsiplank 2 x 12/200 = 27.40 x 2 = 54.8 54.80 M1

VIII PEKERJAAN CAT - CATAN


1 Pengecatan Tembok Plesteran 1Pc : 3Ps = 47.71 227.51 M2
Plesteran 1Pc : 5Ps = 179.80
227.51

3 Pengecatan Kayu Lisplank Kalsi = 54.80 x 0.25 = 13.7 98.95 M2

KONSOL
Tiang = 0.08 x 0.12 x 0.85 x 1 = 0.34
Sekor = 0.08 x 0.12 x 0.91 x 1 = 0.36
Gapit = 0.06 x 0.10 x 10.00 x 2 = 6.40
7.10 x 12 = 85.25
98.95

Anda mungkin juga menyukai