JADWAL WAKTU PELAKSANAAN

PEKERJAAN : PEMBANGUNAN GEDUNG MADARASAH IBTIDAIYAH EL-RAHMAH - SUKODONO


LOKASI : JL. RAYA SAIMBANG SUKODONO - SIDOARJO

WAKTU PELAKSANAAN
BOBOT
NO URAIAN PEKERJAAN M-1 M-3 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M15 M-16 M-17 KETERANGAN
(%)
1-7 8-14 15-21 22-28 29-35 36-42 43-49 50-56 57-63 64-70 71-77 78-84 85-91 92-98 99-105 106-112 113-120
100
A PEK. KESELAMATAN KERJA
I Penyiapan RK3K terdiri atas 0,398 0,023 0,023 0,023 0,023 0,023 0,023 0,023 0,023 0,023 0,023 0,023 0,023 0,023 0,023 0,023 0,023 0,023

B PEKERJAAN GEDUNG 75
I PEKERJAAN PERSIAPAN 1,435 1,435
II PEKERJAAN TANAH 3,146 0,393 0,393 0,393 0,393 0,393 0,393 0,393 0,393
III PEKERJAAN BETON 41,261 3,751 3,751 3,751 3,751 3,751 3,751 3,751 3,751 3,751 3,751 3,751
IV PEKERJAAN PASANGAN 19,146 4,786 4,786 4,786 4,786 50
V PEKERJAAN LANTAI DAN DINDING 8,161 2,720 2,720 2,720
VI PEKERJAAN PINTU DAN JENDELA 5,807 1,452 1,452 1,452 1,452
VII PEKERJAAN PLAFOND 3,277 1,639 1,639
VIII PEKERJAAN PENGECATAN 7,294 2,431 2,431 2,431
IX PEKERJAAN PAGAR DAN RAILING 1,839 0,613 0,613 0,613 25
X PEKERJAAN SANITAIR 3,080 0,440 0,440 0,440 0,440 0,440 0,440 0,440
XII PEKERJAAN INSTALASI LISTRIK 3,074 0,615 0,615 0,615 0,615 0,615
XIII PEKERJAAN HALAMAN 0,699 0,349 0,349
XIII PEKERJAAN SALURAN 1,383 0,461 0,461 0,461 0

100,000
RENCANA PROGRESS MINGGUAN 1,851 4,168 4,168 4,168 4,168 4,168 4,168 4,168 9,001 10,453 13,788 14,401 7,963 6,222 4,320 2,804 0,023 Waktu Pelaksanaan
RENCANA KOMULATIF PROGRESS MINGGUAN 1,851 6,019 10,187 14,355 18,522 22,690 26,858 31,025 40,026 50,479 64,267 78,667 86,630 92,852 97,172 99,977 100,000 120 Hari Kalender
REALISASI PROGRESS MINGGUAN
REALISASI KOMULATIF PROGRESS MINGGUAN