Metode Modifikasi Portal Baja Gewel
Metode Modifikasi Portal Baja Gewel
GG.IX.01A
MODIFIKASI GUDANG
Sheet No. 1 of 6
METODE KERJA
MODIFIKASI DINDING GEWEL AS N/1-7 GUDANG GG.IX.01A
DIBUAT
OLEH
DIPERIKSA
OLEH
NAMA
PAULUS D.
INDRAWAN S.
DIPERIKSA
OLEH
ELFRAN
DISETUJUI
OLEH
TONNY WALUYO
JABATAN
SITE ENGINEER
PT. MURINDA
PROJECT
MANAGER
PT. MURINDA
PROJECT
MANAGER
PT. DUTIKON
PT. GUDANG
GARAM
TANGGAL
PARAF/TTD
GG.IX.01A
MODIFIKASI GUDANG
Sheet No. 2 of 6
DAFTAR ISI
1. LOKASI ------------------------------------------------------------------------------------------3
2. REFERENSI
2.1 Lingkup Pekerjaan -------------------------------------------------------------------------3
2.2 Metode Pelaksanaan -----------------------------------------------------------------------3
3. TENAGA-----------------------------------------------------------------------------------------4
4. PERALATAN------------------------------------------------------------------------------------4
5. K-3-------------------------------------------------------------------------------------------------5
GG.IX.01A
MODIFIKASI GUDANG
Sheet No. 3 of 6
1.
LOKASI
Metode kerja modifikasi dinding gewel as N/1-7 ini di lokasi gudang GG IX 01A PT.
Gudang Garam Kediri.
REFERENSI
2.
GG.IX.01A
MODIFIKASI GUDANG
Sheet No. 4 of 6
11. Menyambung kembali ikatan antara kolom dobel cnp dan cnp cladding.
12. Melakukan pengecekan kelurusan regel diatas pintu.
13. Pintu digeser ke posisi menutup.
TENAGA
3.
Team Site
Team QC
Team Safety
Tukang
: 2 Orang
Welder
: 2 Orang
Team Mekanik
: 2 Orang
Helper
: 6 Orang
PERALATAN
4.
Temporary support
4 Set
Chainblock 5 ton
4 Buah
1 Buah
GG.IX.01A
MODIFIKASI GUDANG
Sheet No. 5 of 6
2 Set
Api potong
2 Set
APAR
4 Buah
Genset 60 KVA
1 Buah
Meteran
Sesuai Kebutuhan
K-3
5.
Sebelum memulai pekerjaan, Supervisor, QC, Site Manager dan Mandor mengadakan
koordinasi untuk kelancaran pekerjaan
GG.IX.01A
MODIFIKASI GUDANG
Sheet No. 6 of 6