REKAPITULASI
Lebar Lebar Rata-Rata Jarak Volume Tiap Unit Progres Pekerjaan
Sta Keterangan
(m) (m) (m) (m2) Sebelumnya Saat ini Kumulatif
28 + 650 47.22
48.535 25 1,213.38
28 + 675 49.85
49.475 25 1,236.88
28 + 700 49.1
47.46 25 1,186.50
28 + 725 45.82
47.43 25 1,185.75
28 + 750 49.04
48.335 25 1,208.38
28 + 775 47.63
45.2 25 1,130.00
28 + 800 42.77
42.005 25 1,050.13
28 + 825 41.24
39.605 25 990.13
28 + 850 37.97
36.065 25 901.63
28 + 875 34.16
33.775 25 844.38
28 + 900 33.39
33.945 25 848.63
28 + 925 34.5
35.495 25 887.38
28 + 950 36.49
36.945 25 923.63
28 + 975 37.4
38.4 25 960.00
29 + 000 39.4
41 25 1,025.00
29 + 025 42.6
42.8 25 1,070.00
29 + 050 43
43.925 25 1,098.13
29 + 075 44.85
46.03 25 1,150.75
29 + 100 47.21
47.82 25 1,195.50
29 + 125 48.43
52.955 25 1,323.88
29 + 150 57.48
59.65 25 1,491.25
29 + 175 61.82
64.43 25 1,610.75
29 + 200 67.04
68.835 25 1,720.88
29 + 225 70.63
70.65 25 1,766.25
29 + 250 70.67
67.795 25 1,694.88
29 + 275 64.92
63.335 25 1,583.38
29 + 300 61.75
59.01 25 1,475.25
29 + 325 56.27
50.91 25 1,272.75
29 + 350 45.55
43.09 25 1,077.25
29 + 375 40.63
Page 1 of 29
Lebar Lebar Rata-Rata Jarak Volume Tiap Unit Progres Pekerjaan
Sta Keterangan
(m) (m) (m) (m2) Sebelumnya Saat ini Kumulatif
39.02 25 975.50
29 + 400 37.41
36.19 25 904.75
29 + 425 34.97
34.105 25 852.63
29 + 450 33.24
32.48 25 812.00
29 + 475 31.72
31.165 25 779.13
29 + 500 30.61
30.325 25 758.13
29 + 525 30.04
30.205 25 755.13
29 + 550 30.37
30.49 25 762.25
29 + 575 30.61
31.405 25 785.13
29 + 600 32.2
33.615 25 840.38
29 + 625 35.03
37.86 25 946.50
29 + 650 40.69
46.95 25 1,173.75
29 + 675 53.21
56.02 25 1,400.50
29 + 700 58.83
59.24 25 1,481.00
29 + 725 59.65
56.325 25 1,408.13
29 + 750 53
51.29 25 1,282.25
29 + 775 49.58
41.77 25 1,044.25
29 + 800 33.96
32.625 25 815.63
29 + 825 31.29
32.565 25 814.13
29 + 850 33.84
35.16 25 879.00
29 + 875 36.48
37.39 25 934.75
29 + 900 38.3
38.7 25 967.50
29 + 925 39.1
39.92 25 998.00
29 + 950 40.74
41.065 25 1,026.63
29 + 975 41.39
41.695 25 1,042.38
30 + 000 42
42.25 25 1,056.25
30 + 025 42.5
42.56 25 1,064.00
30 + 050 42.62
42.08 25 1,052.00
30 + 075 41.54
41.91 25 1,047.75
30 + 100 42.28
42.2 25 1,055.00
30 + 125 42.12
42.1 25 1,052.50
30 + 150 42.08
42.03 25 1,050.75
30 + 175 41.98
42.115 25 1,052.88
30 + 200 42.25
42.15 25 1,053.75
30 + 225 42.05
41.8 25 1,045.00
30 + 250 41.55
42.635 25 1,065.88
30 + 275 43.72
42.82 25 1,070.50
30 + 300 41.92
41.485 25 1,037.13
Page 2 of 29
Lebar Lebar Rata-Rata Jarak Volume Tiap Unit Progres Pekerjaan
Sta Keterangan
(m) (m) (m) (m2) Sebelumnya Saat ini Kumulatif
30 + 325 41.05
40.51 25 1,012.75
30 + 350 39.97
39.5 25 987.50
30 + 375 39.03
38.545 25 963.63
30 + 400 38.06
37.33 25 933.25
30 + 425 36.6
36.19 25 904.75
30 + 450 35.78
37.49 25 937.25
30 + 475 39.2
37.395 25 934.88
30 + 500 35.59
34.12 25 853.00
30 + 525 32.65
33.905 25 847.63
30 + 550 35.16
36.04 25 901.00
30 + 575 36.92
37.585 25 939.63
30 + 600 38.25
38.565 25 964.13
30 + 625 38.88
39.155 25 978.88
30 + 650 39.43
39.51 25 987.75
30 + 675 39.59
39.715 25 992.88
30 + 700 39.84
39.725 25 993.13
30 + 725 39.61
39.705 25 992.63
30 + 750 39.8
39.625 25 990.63
30 + 775 39.45
39.415 25 985.38
30 + 800 39.38
38.865 25 971.63
30 + 825 38.35
37.91 25 947.75
30 + 850 37.47
37.89 25 947.25
30 + 875 38.31
39.285 25 982.13
30 + 900 40.26
40.185 25 1,004.63
30 + 925 40.11
39.875 25 996.88
30 + 950 39.64
39.375 25 984.38
30 + 975 39.11
38.935 25 973.38
31 + 000 38.76
38.49 25 962.25
31 + 025 38.22
38.06 25 951.50
31 + 050 37.9
37.675 25 941.88
31 + 075 37.45
37.165 25 929.13
31 + 100 36.88
36.55 25 913.75
31 + 125 36.22
35.265 25 881.63
31 + 150 34.31
32.93 25 823.25
31 + 175 31.55
33.985 25 849.63
31 + 200 36.42
39.31 25 982.75
31 + 225 42.2
41.33 25 1,033.25
31 + 250 40.46
Page 3 of 29
Lebar Lebar Rata-Rata Jarak Volume Tiap Unit Progres Pekerjaan
Sta Keterangan
(m) (m) (m) (m2) Sebelumnya Saat ini Kumulatif
42.785 25 1,069.63
31 + 275 45.11
42.82 25 1,070.50
31 + 300 40.53
43.965 25 1,099.13
31 + 325 47.4
45.145 25 1,128.63
31 + 350 42.89
46 25 1,150.00
31 + 375 49.11
45.86 25 1,146.50
31 + 400 42.61
41.155 25 1,028.88
31 + 425 39.7
38.98 25 974.50
31 + 450 38.26
38.055 25 951.38
31 + 475 37.85
39.025 25 975.63
31 + 500 40.2
43.065 25 1,076.63
31 + 525 45.93
45.255 25 1,131.38
31 + 550 44.58
39.325 25 983.13
31 + 575 34.07
33.285 25 832.13
31 + 600 32.5
32.09 25 802.25
31 + 625 31.68
31.905 25 797.63
31 + 650 32.13
32.09 25 802.25
31 + 675 32.05
32.145 25 803.63
31 + 700 32.24
31.405 25 785.13
31 + 725 30.57
31.605 25 790.13
31 + 750 32.64
32.55 25 813.75
31 + 775 32.46
32.825 25 820.63
31 + 800 33.19
33.35 25 833.75
31 + 825 33.51
33.75 25 843.75
31 + 850 33.99
34.23 25 855.75
31 + 875 34.47
34.66 25 866.50
31 + 900 34.85
34.915 25 872.88
31 + 925 34.98
35.045 25 876.13
31 + 950 35.11
34.935 25 873.38
31 + 975 34.76
34.575 25 864.38
32 + 000 34.39
34.19 25 854.75
32 + 025 33.99
33.68 25 842.00
32 + 050 33.37
33 25 825.00
32 + 075 32.63
32.255 25 806.38
32 + 100 31.88
32.13 25 803.25
32 + 125 32.38
32.625 25 815.63
32 + 150 32.87
33.025 25 825.63
32 + 175 33.18
32.545 25 813.63
Page 4 of 29
Lebar Lebar Rata-Rata Jarak Volume Tiap Unit Progres Pekerjaan
Sta Keterangan
(m) (m) (m) (m2) Sebelumnya Saat ini Kumulatif
32 + 200 31.91
32.475 25 811.88
32 + 225 33.04
33.45 25 836.25
32 + 250 33.86
35.46 25 886.50
32 + 275 37.06
38.645 25 966.13
32 + 300 40.23
40.155 25 1,003.88
32 + 325 40.08
42.82 25 1,070.50
32 + 350 45.56
51.715 25 1,292.88
32 + 375 57.87
58.65 25 1,466.25
32 + 400 59.43
59.705 25 1,492.63
32 + 425 59.98
54.035 25 1,350.88
32 + 450 48.09
39.95 25 998.75
32 + 475 31.81
33.015 25 825.38
32 + 500 34.22
36.055 25 901.38
32 + 525 37.89
39.21 25 980.25
32 + 550 40.53
41.35 25 1,033.75
32 + 575 42.17
42.845 25 1,071.13
32 + 600 43.52
45.27 25 1,131.75
32 + 625 47.02
48.535 25 1,213.38
32 + 650 50.05
50.29 25 1,257.25
32 + 675 50.53
50.485 25 1,262.13
32 + 700 50.44
50.295 25 1,257.38
32 + 725 50.15
49.975 25 1,249.38
32 + 750 49.8
47.225 25 1,180.63
32 + 775 44.65
44.52 25 1,113.00
32 + 800 44.39
43.965 25 1,099.13
32 + 825 43.54
42.995 25 1,074.88
32 + 850 42.45
41.715 25 1,042.88
32 + 875 40.98
40.26 25 1,006.50
32 + 900 39.54
38.625 25 965.63
32 + 925 37.71
36.11 25 902.75
32 + 950 34.51
33.68 25 842.00
32 + 975 32.85
32.61 25 815.25
33 + 000 32.37
31.535 25 788.38
33 + 025 30.7
33.645 25 841.13
33 + 050 36.59
40.77 25 1,019.25
33 + 075 44.95
47.135 25 1,178.38
33 + 100 49.32
44.595 25 1,114.88
33 + 125 39.87
Page 5 of 29
Lebar Lebar Rata-Rata Jarak Volume Tiap Unit Progres Pekerjaan
Sta Keterangan
(m) (m) (m) (m2) Sebelumnya Saat ini Kumulatif
40.2 25 1,005.00
33 + 150 40.53
41.525 25 1,038.13
33 + 175 42.52
43.99 25 1,099.75
33 + 200 45.46
49.375 25 1,234.38
33 + 225 53.29
52.605 25 1,315.13
33 + 250 51.92
52.54 25 1,313.50
33 + 275 53.16
52.19 25 1,304.75
33 + 300 51.22
53.125 25 1,328.13
33 + 325 55.03
49.05 25 1,226.25
33 + 350 43.07
41.93 25 1,048.25
33 + 375 40.79
40.495 25 1,012.38
33 + 400 40.2
40.295 25 1,007.38
33 + 425 40.39
40.48 25 1,012.00
33 + 450 40.57
41.155 25 1,028.88
33 + 475 41.74
42.035 25 1,050.88
33 + 500 42.33
42.825 25 1,070.63
33 + 525 43.32
44.15 25 1,103.75
33 + 550 44.98
47.13 25 1,178.25
33 + 575 49.28
49.815 25 1,245.38
33 + 600 50.35
51.155 25 1,278.88
33 + 625 51.96
52.675 25 1,316.88
33 + 650 53.39
54.215 25 1,355.38
33 + 675 55.04
59.49 25 1,487.25
33 + 700 63.94
63.61 25 1,590.25
33 + 725 63.28
62.91 25 1,572.75
33 + 750 62.54
64.17 25 1,604.25
33 + 775 65.8
64.85 25 1,621.25
33 + 800 63.9
63.815 25 1,595.38
33 + 825 63.73
63.47 25 1,586.75
33 + 850 63.21
63.78 25 1,594.50
33 + 875 64.35
64.97 25 1,624.25
33 + 900 65.59
68.005 25 1,700.13
33 + 925 70.42
70.22 25 1,755.50
33 + 950 70.02
72.225 25 1,805.63
33 + 975 74.43
72.79 25 1,819.75
34 + 000 71.15
70.325 25 1,758.13
34 + 025 69.5
69.415 25 1,735.38
34 + 050 69.33
68.7 25 1,717.50
Page 6 of 29
Lebar Lebar Rata-Rata Jarak Volume Tiap Unit Progres Pekerjaan
Sta Keterangan
(m) (m) (m) (m2) Sebelumnya Saat ini Kumulatif
34 + 075 68.07
69.16 25 1,729.00
34 + 100 70.25
69.205 25 1,730.13
34 + 125 68.16
65.645 25 1,641.13
34 + 150 63.13
62.145 25 1,553.63
34 + 175 61.16
60.18 25 1,504.50
34 + 200 59.2
56.51 25 1,412.75
34 + 225 53.82
53.005 25 1,325.13
34 + 250 52.19
49.08 25 1,227.00
34 + 275 45.97
45.46 25 1,136.50
34 + 300 44.95
43.54 25 1,088.50
34 + 325 42.13
41.545 25 1,038.63
34 + 350 40.96
37.63 25 940.75
34 + 375 34.3
32.65 25 816.25
34 + 400 31
30.9 25 772.50
34 + 425 30.8
31.495 25 787.38
34 + 450 32.19
32.85 25 821.25
34 + 475 33.51
33.945 25 848.63
34 + 500 34.38
34.665 25 866.63
34 + 525 34.95
35.1 25 877.50
34 + 550 35.25
35.145 25 878.63
34 + 575 35.04
34.915 25 872.88
34 + 600 34.79
34.775 25 869.38
34 + 625 34.76
34.635 25 865.88
34 + 650 34.51
34.41 25 860.25
34 + 675 34.31
34.245 25 856.13
34 + 700 34.18
33.775 25 844.38
34 + 725 33.37
33.56 25 839.00
34 + 750 33.75
33.53 25 838.25
34 + 775 33.31
32.94 25 823.50
34 + 800 32.57
32.075 25 801.88
34 + 825 31.58
32.02 25 800.50
34 + 850 32.46
35.3 25 882.50
34 + 875 38.14
37.1 25 927.50
34 + 900 36.06
37.195 25 929.88
34 + 925 38.33
34.725 25 868.13
34 + 950 31.12
30.595 25 764.88
34 + 975 30.07
30.03 25 750.75
35 + 000 29.99
Page 7 of 29
Lebar Lebar Rata-Rata Jarak Volume Tiap Unit Progres Pekerjaan
Sta Keterangan
(m) (m) (m) (m2) Sebelumnya Saat ini Kumulatif
30.065 25 751.63
35 + 025 30.14
30.225 25 755.63
35 + 050 30.31
30.33 25 758.25
35 + 075 30.35
30.31 25 757.75
35 + 100 30.27
30.105 25 752.63
35 + 125 29.94
30.24 25 756.00
35 + 150 30.54
30.68 25 767.00
35 + 175 30.82
30.95 25 773.75
35 + 200 31.08
31.11 25 777.75
35 + 225 31.14
31.18 25 779.50
35 + 250 31.22
31.455 25 786.38
35 + 275 31.69
31.505 25 787.63
35 + 300 31.32
31.495 25 787.38
35 + 325 31.67
31.405 25 785.13
35 + 350 31.14
31.2 25 780.00
35 + 375 31.26
31.375 25 784.38
35 + 400 31.49
31.27 25 781.75
35 + 425 31.05
31.865 25 796.63
35 + 450 32.68
33.21 25 830.25
35 + 475 33.74
34.21 25 855.25
35 + 500 34.68
35.23 25 880.75
35 + 525 35.78
36.585 25 914.63
35 + 550 37.39
39.72 25 993.00
35 + 575 42.05
42.395 25 1,059.88
35 + 600 42.74
43.87 25 1,096.75
35 + 625 45
45.58 25 1,139.50
35 + 650 46.16
46.76 25 1,169.00
35 + 675 47.36
47.18 25 1,179.50
35 + 700 47
47.47 25 1,186.75
35 + 725 47.94
47.625 25 1,190.63
35 + 750 47.31
46.75 25 1,168.75
35 + 775 46.19
46.655 25 1,166.38
35 + 800 47.12
47.695 25 1,192.38
35 + 825 48.27
50.035 25 1,250.88
35 + 850 51.8
52.075 25 1,301.88
35 + 875 52.35
54.6 25 1,365.00
35 + 900 56.85
57.38 25 1,434.50
35 + 925 57.91
58.445 25 1,461.13
Page 8 of 29
Lebar Lebar Rata-Rata Jarak Volume Tiap Unit Progres Pekerjaan
Sta Keterangan
(m) (m) (m) (m2) Sebelumnya Saat ini Kumulatif
35 + 950 58.98
59.35 25 1,483.75
35 + 975 59.72
59.745 25 1,493.63
36 + 000 59.77
59.67 25 1,491.75
36 + 025 59.57
59.65 25 1,491.25
36 + 050 59.73
59.615 25 1,490.38
36 + 075 59.5
58.9 25 1,472.50
36 + 100 58.3
58.25 25 1,456.25
36 + 125 58.2
57.69 25 1,442.25
36 + 150 57.18
57.45 25 1,436.25
36 + 175 57.72
57.95 25 1,448.75
36 + 200 58.18
57.52 25 1,438.00
36 + 225 56.86
56.02 25 1,400.50
36 + 250 55.18
55.38 25 1,384.50
36 + 275 55.58
57.685 25 1,442.13
36 + 300 59.79
56.315 25 1,407.88
36 + 325 52.84
53.075 25 1,326.88
36 + 350 53.31
53.415 25 1,335.38
36 + 375 53.52
55.055 25 1,376.38
36 + 400 56.59
49.155 25 1,228.88
36 + 425 41.72
37.905 25 947.63
36 + 450 34.09
32.265 25 806.63
36 + 475 30.44
30.8 25 770.00
36 + 500 31.16
31.715 25 792.88
36 + 525 32.27
32.735 25 818.38
36 + 550 33.2
33.485 25 837.13
36 + 575 33.77
33.805 25 845.13
36 + 600 33.84
33.76 25 844.00
36 + 625 33.68
33.115 25 827.88
36 + 650 32.55
31.78 25 794.50
36 + 675 31.01
34.295 25 857.38
36 + 700 37.58
40.97 25 1,024.25
36 + 725 44.36
42.625 25 1,065.63
36 + 750 40.89
38.15 25 953.75
36 + 775 35.41
33.025 25 825.63
36 + 800 30.64
30.45 25 761.25
36 + 825 30.26
30.38 25 759.50
36 + 850 30.5
30.61 25 765.25
36 + 875 30.72
Page 9 of 29
Lebar Lebar Rata-Rata Jarak Volume Tiap Unit Progres Pekerjaan
Sta Keterangan
(m) (m) (m) (m2) Sebelumnya Saat ini Kumulatif
30.765 25 769.13
36 + 900 30.81
30.89 25 772.25
36 + 925 30.97
31.135 25 778.38
36 + 950 31.3
31.355 25 783.88
36 + 975 31.41
31.495 25 787.38
37 + 000 31.58
31.725 25 793.13
37 + 025 31.87
31.79 25 794.75
37 + 050 31.71
31.575 25 789.38
37 + 075 31.44
31.145 25 778.63
37 + 100 30.85
30.54 25 763.50
37 + 125 30.23
30.07 25 751.75
37 + 150 29.91
30.095 25 752.38
37 + 175 30.28
30.35 25 758.75
37 + 200 30.42
30.94 25 773.50
37 + 225 31.46
31.115 25 777.88
37 + 250 30.77
30.92 25 773.00
37 + 275 31.07
30.93 25 773.25
37 + 300 30.79
30.795 25 769.88
37 + 325 30.8
30.43 25 760.75
37 + 350 30.06
29.975 25 749.38
37 + 375 29.89
30.235 25 755.88
37 + 400 30.58
30.79 25 769.75
37 + 425 31
31.345 25 783.63
37 + 450 31.69
31.85 25 796.25
37 + 475 32.01
32.16 25 804.00
37 + 500 32.31
32.465 25 811.63
37 + 525 32.62
32.82 25 820.50
37 + 550 33.02
32.94 25 823.50
37 + 575 32.86
32.49 25 812.25
37 + 600 32.12
31.515 25 787.88
37 + 625 30.91
31.305 25 782.63
37 + 650 31.7
34.26 25 856.50
37 + 675 36.82
38.835 25 970.88
37 + 700 40.85
43.305 25 1,082.63
37 + 725 45.76
41.085 25 1,027.13
37 + 750 36.41
33.51 25 837.75
37 + 775 30.61
31.405 25 785.13
37 + 800 32.2
32.35 25 808.75
Page 10 of 29
Lebar Lebar Rata-Rata Jarak Volume Tiap Unit Progres Pekerjaan
Sta Keterangan
(m) (m) (m) (m2) Sebelumnya Saat ini Kumulatif
37 + 825 32.5
32.325 25 808.13
37 + 850 32.15
31.85 25 796.25
37 + 875 31.55
31.16 25 779.00
37 + 900 30.77
30.465 25 761.63
37 + 925 30.16
31.09 25 777.25
37 + 950 32.02
32.595 25 814.88
37 + 975 33.17
33.865 25 846.63
38 + 000 34.56
34.12 25 853.00
38 + 025 33.68
33.48 25 837.00
38 + 050 33.28
32.46 25 811.50
38 + 075 31.64
32.035 25 800.88
38 + 100 32.43
32.54 25 813.50
38 + 125 32.65
32.555 25 813.88
38 + 150 32.46
32.36 25 809.00
38 + 175 32.26
32.1 25 802.50
38 + 200 31.94
31.965 25 799.13
38 + 225 31.99
31.94 25 798.50
38 + 250 31.89
31.985 25 799.63
38 + 275 32.08
32.225 25 805.63
38 + 300 32.37
32.52 25 813.00
38 + 325 32.67
33.005 25 825.13
38 + 350 33.34
33.615 25 840.38
38 + 375 33.89
34.065 25 851.63
38 + 400 34.24
34.37 25 859.25
38 + 425 34.5
34.755 25 868.88
38 + 450 35.01
35.145 25 878.63
38 + 475 35.28
35.2 25 880.00
38 + 500 35.12
35.04 25 876.00
38 + 525 34.96
35.05 25 876.25
38 + 550 35.14
35.445 25 886.13
38 + 575 35.75
36.005 25 900.13
38 + 600 36.26
36.145 25 903.63
38 + 625 36.03
35.92 25 898.00
38 + 650 35.81
35.615 25 890.38
38 + 675 35.42
35.275 25 881.88
38 + 700 35.13
34.935 25 873.38
38 + 725 34.74
34.82 25 870.50
38 + 750 34.9
Page 11 of 29
Lebar Lebar Rata-Rata Jarak Volume Tiap Unit Progres Pekerjaan
Sta Keterangan
(m) (m) (m) (m2) Sebelumnya Saat ini Kumulatif
35.005 25 875.13
38 + 775 35.11
35.095 25 877.38
38 + 800 35.08
35.22 25 880.50
38 + 825 35.36
35.465 25 886.63
38 + 850 35.57
35.775 25 894.38
38 + 875 35.98
36.15 25 903.75
38 + 900 36.32
36.545 25 913.63
38 + 925 36.77
36.99 25 924.75
38 + 950 37.21
37.505 25 937.63
38 + 975 37.8
38.14 25 953.50
39 + 000 38.48
39.275 25 981.88
39 + 025 40.07
41.215 25 1,030.38
39 + 050 42.36
50.315 25 1,257.88
39 + 075 58.27
61.085 25 1,527.13
39 + 100 63.9
59.255 25 1,481.38
39 + 125 54.61
48.345 25 1,208.63
39 + 150 42.08
40.31 25 1,007.75
39 + 175 38.54
37.315 25 932.88
39 + 200 36.09
35.255 25 881.38
39 + 225 34.42
33.88 25 847.00
39 + 250 33.34
33.025 25 825.63
39 + 275 32.71
32.54 25 813.50
39 + 300 32.37
31.905 25 797.63
39 + 325 31.44
31.395 25 784.88
39 + 350 31.35
31.49 25 787.25
39 + 375 31.63
31.635 25 790.88
39 + 400 31.64
31.65 25 791.25
39 + 425 31.66
31.87 25 796.75
39 + 450 32.08
31.805 25 795.13
39 + 475 31.53
31.55 25 788.75
39 + 500 31.57
31.855 25 796.38
39 + 525 32.14
32.575 25 814.38
39 + 550 33.01
33.11 25 827.75
39 + 575 33.21
33.19 25 829.75
39 + 600 33.17
33.055 25 826.38
39 + 625 32.94
32.77 25 819.25
39 + 650 32.6
32.715 25 817.88
39 + 675 32.83
33.13 25 828.25
Page 12 of 29
Lebar Lebar Rata-Rata Jarak Volume Tiap Unit Progres Pekerjaan
Sta Keterangan
(m) (m) (m) (m2) Sebelumnya Saat ini Kumulatif
39 + 700 33.43
33.845 25 846.13
39 + 725 34.26
34.675 25 866.88
39 + 750 35.09
35.11 25 877.75
39 + 775 35.13
35.15 25 878.75
39 + 800 35.17
35.32 25 883.00
39 + 825 35.47
35.525 25 888.13
39 + 850 35.58
35.605 25 890.13
39 + 875 35.63
35.18 25 879.50
39 + 900 34.73
33.875 25 846.88
39 + 925 33.02
31.9 25 797.50
39 + 950 30.78
37.52 25 938.00
39 + 975 44.26
37.48 25 937.00
40 + 000 30.7
32.455 25 811.38
40 + 025 34.21
35.525 25 888.13
40 + 050 36.84
37.825 25 945.63
40 + 075 38.81
39.425 25 985.63
40 + 100 40.04
40.645 25 1,016.13
40 + 125 41.25
41.735 25 1,043.38
40 + 150 42.22
42.525 25 1,063.13
40 + 175 42.83
43.04 25 1,076.00
40 + 200 43.25
43.53 25 1,088.25
40 + 225 43.81
43.935 25 1,098.38
40 + 250 44.06
43.6 25 1,090.00
40 + 275 43.14
39.16 25 979.00
40 + 300 35.18
34.905 25 872.63
40 + 325 34.63
34.69 25 867.25
40 + 350 34.75
33.365 25 834.13
40 + 375 31.98
31.455 25 786.38
40 + 400 30.93
30.87 25 771.75
40 + 425 30.81
31.79 25 794.75
40 + 450 32.77
36.075 25 901.88
40 + 475 39.38
39.99 25 999.75
40 + 500 40.6
37.08 25 927.00
40 + 525 33.56
34.485 25 862.13
40 + 550 35.41
35.625 25 890.63
40 + 575 35.84
35.86 25 896.50
40 + 600 35.88
35.585 25 889.63
40 + 625 35.29
Page 13 of 29
Lebar Lebar Rata-Rata Jarak Volume Tiap Unit Progres Pekerjaan
Sta Keterangan
(m) (m) (m) (m2) Sebelumnya Saat ini Kumulatif
35.27 25 881.75
40 + 650 35.25
34.755 25 868.88
40 + 675 34.26
33.865 25 846.63
40 + 700 33.47
32.515 25 812.88
40 + 725 31.56
32.34 25 808.50
40 + 750 33.12
38.96 25 974.00
40 + 775 44.8
39.6 25 990.00
40 + 800 34.4
33.75 25 843.75
40 + 825 33.1
34.56 25 864.00
40 + 850 36.02
37.155 25 928.88
40 + 875 38.29
38.805 25 970.13
40 + 900 39.32
39.475 25 986.88
40 + 925 39.63
39.385 25 984.63
40 + 950 39.14
38.06 25 951.50
40 + 975 36.98
35.125 25 878.13
41 + 000 33.27
31.995 25 799.88
41 + 025 30.72
34.775 25 869.38
41 + 050 38.83
41.805 25 1,045.13
41 + 075 44.78
45.86 25 1,146.50
41 + 100 46.94
46.03 25 1,150.75
41 + 125 45.12
44.485 25 1,112.13
41 + 150 43.85
43.985 25 1,099.63
41 + 175 44.12
43.58 25 1,089.50
41 + 200 43.04
43.495 25 1,087.38
41 + 225 43.95
43.57 25 1,089.25
41 + 250 43.19
43.915 25 1,097.88
41 + 275 44.64
43.285 25 1,082.13
41 + 300 41.93
41.81 25 1,045.25
41 + 325 41.69
41.215 25 1,030.38
41 + 350 40.74
40.76 25 1,019.00
41 + 375 40.78
40.835 25 1,020.88
41 + 400 40.89
41 25 1,025.00
41 + 425 41.11
39.68 25 992.00
41 + 450 38.25
38.27 25 956.75
41 + 475 38.29
37.815 25 945.38
41 + 500 37.34
36.91 25 922.75
41 + 525 36.48
36.28 25 907.00
41 + 550 36.08
36.49 25 912.25
Page 14 of 29
Lebar Lebar Rata-Rata Jarak Volume Tiap Unit Progres Pekerjaan
Sta Keterangan
(m) (m) (m) (m2) Sebelumnya Saat ini Kumulatif
41 + 575 36.9
37.775 25 944.38
41 + 600 38.65
37.265 25 931.63
41 + 625 35.88
35.765 25 894.13
41 + 650 35.65
37.28 25 932.00
41 + 675 38.91
38.2 25 955.00
41 + 700 37.49
37.84 25 946.00
41 + 725 38.19
38.315 25 957.88
41 + 750 38.44
38.02 25 950.50
41 + 775 37.6
36.745 25 918.63
41 + 800 35.89
35.92 25 898.00
41 + 825 35.95
35.875 25 896.88
41 + 850 35.8
35.785 25 894.63
41 + 875 35.77
35.88 25 897.00
41 + 900 35.99
35.75 25 893.75
41 + 925 35.51
35.51 25 887.75
41 + 950 35.51
35.715 25 892.88
41 + 975 35.92
35.955 25 898.88
42 + 000 35.99
35.885 25 897.13
42 + 025 35.78
35.425 25 885.63
42 + 050 35.07
35.34 25 883.50
42 + 075 35.61
35.635 25 890.88
42 + 100 35.66
36.005 25 900.13
42 + 125 36.35
36.01 25 900.25
42 + 150 35.67
36.02 25 900.50
42 + 175 36.37
35.355 25 883.88
42 + 200 34.34
33.895 25 847.38
42 + 225 33.45
32.81 25 820.25
42 + 250 32.17
33.88 25 847.00
42 + 275 35.59
34.705 25 867.63
42 + 300 33.82
32.825 25 820.63
42 + 325 31.83
31.89 25 797.25
42 + 350 31.95
32.795 25 819.88
42 + 375 33.64
33.965 25 849.13
42 + 400 34.29
34.34 25 858.50
42 + 425 34.39
34.485 25 862.13
42 + 450 34.58
34.155 25 853.88
42 + 475 33.73
33.235 25 830.88
42 + 500 32.74
Page 15 of 29
Lebar Lebar Rata-Rata Jarak Volume Tiap Unit Progres Pekerjaan
Sta Keterangan
(m) (m) (m) (m2) Sebelumnya Saat ini Kumulatif
32.275 25 806.88
42 + 525 31.81
31.81 25 795.25
42 + 550 31.81
32.08 25 802.00
42 + 575 32.35
34.145 25 853.63
42 + 600 35.94
38.41 25 960.25
42 + 625 40.88
41.7 25 1,042.50
42 + 650 42.52
39.625 25 990.63
42 + 675 36.73
34.02 25 850.50
42 + 700 31.31
32.6 25 815.00
42 + 725 33.89
35.18 25 879.50
42 + 750 36.47
37.37 25 934.25
42 + 775 38.27
39.13 25 978.25
42 + 800 39.99
40.525 25 1,013.13
42 + 825 41.06
41.58 25 1,039.50
42 + 850 42.1
42.095 25 1,052.38
42 + 875 42.09
42.165 25 1,054.13
42 + 900 42.24
42.235 25 1,055.88
42 + 925 42.23
41.18 25 1,029.50
42 + 950 40.13
40.16 25 1,004.00
42 + 975 40.19
39.49 25 987.25
43 + 000 38.79
37.475 25 936.88
43 + 025 36.16
36.195 25 904.88
43 + 050 36.23
35.04 25 876.00
43 + 075 33.85
35.06 25 876.50
43 + 100 36.27
36.065 25 901.63
43 + 125 35.86
35.79 25 894.75
43 + 150 35.72
36.735 25 918.38
43 + 175 37.75
37.9 25 947.50
43 + 200 38.05
37.87 25 946.75
43 + 225 37.69
37.33 25 933.25
43 + 250 36.97
36.655 25 916.38
43 + 275 36.34
36.11 25 902.75
43 + 300 35.88
35.065 25 876.63
43 + 325 34.25
36.375 25 909.38
43 + 350 38.5
39.72 25 993.00
43 + 375 40.94
40.525 25 1,013.13
43 + 400 40.11
39.24 25 981.00
43 + 425 38.37
38.585 25 964.63
Page 16 of 29
Lebar Lebar Rata-Rata Jarak Volume Tiap Unit Progres Pekerjaan
Sta Keterangan
(m) (m) (m) (m2) Sebelumnya Saat ini Kumulatif
43 + 450 38.8
37.98 25 949.50
43 + 475 37.16
37.905 25 947.63
43 + 500 38.65
38.07 25 951.75
43 + 525 37.49
36.765 25 919.13
43 + 550 36.04
35.395 25 884.88
43 + 575 34.75
35.31 25 882.75
43 + 600 35.87
35.32 25 883.00
43 + 625 34.77
34.075 25 851.88
43 + 650 33.38
33.665 25 841.63
43 + 675 33.95
36.455 25 911.38
43 + 700 38.96
39.25 25 981.25
43 + 725 39.54
36.08 25 902.00
43 + 750 32.62
33.935 25 848.38
43 + 775 35.25
33.71 25 842.75
43 + 800 32.17
32.345 25 808.63
43 + 825 32.52
33.355 25 833.88
43 + 850 34.19
34.525 25 863.13
43 + 875 34.86
35.02 25 875.50
43 + 900 35.18
35.695 25 892.38
43 + 925 36.21
36.57 25 914.25
43 + 950 36.93
36.805 25 920.13
43 + 975 36.68
36.395 25 909.88
44 + 000 36.11
35.61 25 890.25
44 + 025 35.11
34.635 25 865.88
44 + 050 34.16
33.305 25 832.63
44 + 075 32.45
31.95 25 798.75
44 + 100 31.45
30.905 25 772.63
44 + 125 30.36
30.7 25 767.50
44 + 150 31.04
32.16 25 804.00
44 + 175 33.28
34.86 25 871.50
44 + 200 36.44
39.475 25 986.88
44 + 225 42.51
51.64 25 1,291.00
44 + 250 60.77
62.035 25 1,550.88
44 + 275 63.3
60.055 25 1,501.38
44 + 300 56.81
51.25 25 1,281.25
44 + 325 45.69
42.825 25 1,070.63
44 + 350 39.96
38.3 25 957.50
44 + 375 36.64
Page 17 of 29
Lebar Lebar Rata-Rata Jarak Volume Tiap Unit Progres Pekerjaan
Sta Keterangan
(m) (m) (m) (m2) Sebelumnya Saat ini Kumulatif
35.96 25 899.00
44 + 400 35.28
34.68 25 867.00
44 + 425 34.08
33.79 25 844.75
44 + 450 33.5
33.035 25 825.88
44 + 475 32.57
32.33 25 808.25
44 + 500 32.09
31.795 25 794.88
44 + 525 31.5
31.36 25 784.00
44 + 550 31.22
31.12 25 778.00
44 + 575 31.02
31 25 775.00
44 + 600 30.98
31.015 25 775.38
Page 18 of 29
Lebar Lebar Rata-Rata Jarak Volume Tiap Unit Progres Pekerjaan
Sta Keterangan
(m) (m) (m) (m2) Sebelumnya Saat ini Kumulatif
44 + 625 31.05
30.675 25 766.88
44 + 650 30.3
TOTAL 630,398.25 - - -
Page 19 of 29
Lebar Lebar Rata-Rata Jarak Volume (m2)
No STA
(m) (m) (m) Tiap Unit Kumulatif
1 28+600 45.760
45.29 25.00 1,132.13 1,132.13
2 28+625 44.810
46.02 25.00 1,150.38 2,282.50
3 28+650 47.220
48.54 25.00 1,213.38 3,495.88
4 28+675 49.850
49.48 25.00 1,236.88 4,732.75
5 28+700 49.100
47.46 25.00 1,186.50 5,919.25
6 28+725 45.820
47.43 25.00 1,185.75 7,105.00
7 28+750 49.040
48.34 25.00 1,208.38 8,313.38
8 28+775 47.630
45.20 25.00 1,130.00 9,443.38
9 28+800 42.770
42.01 25.00 1,050.13 10,493.50
10 28+825 41.240
39.61 25.00 990.13 11,483.63
11 28+850 37.970
36.07 25.00 901.63 12,385.25
12 28+875 34.160
33.78 25.00 844.38 13,229.63
13 28+900 33.390
33.95 25.00 848.63 14,078.25
14 28+925 34.500
35.50 25.00 887.38 14,965.63
15 28+950 36.490
36.95 25.00 923.63 15,889.25
16 28+975 37.400
38.40 25.00 960.00 16,849.25
17 29+000 39.400
41.00 25.00 1,025.00 17,874.25
18 29+025 42.600
42.80 25.00 1,070.00 18,944.25
19 29+050 43.000
43.93 25.00 1,098.13 20,042.38
20 29+075 44.850
46.03 25.00 1,150.75 21,193.13
21 29+100 47.210
47.82 25.00 1,195.50 22,388.63
22 29+125 48.430
52.96 25.00 1,323.88 23,712.50
23 29+150 57.480
59.34 25.00 1,483.50 25,196.00
24 29+175 61.200
64.12 25.00 1,603.00 26,799.00
25 29+200 67.040
68.84 25.00 1,720.88 28,519.88
26 29+225 70.630
70.65 25.00 1,766.25 30,286.13
27 29+250 70.670
Lebar Lebar Rata-Rata Jarak Volume (m2)
No STA
(m) (m) (m) Tiap Unit Kumulatif
67.80 25.00 1,694.88 31,981.00
28 29+275 64.920
63.34 25.00 1,583.38 33,564.38
29 29+300 61.750
59.01 25.00 1,475.25 35,039.63
30 29+325 56.270
50.91 25.00 1,272.75 36,312.38
31 29+350 45.550
43.09 25.00 1,077.25 37,389.63
32 29+375 40.630
39.02 25.00 975.50 38,365.13
33 29+400 37.410
36.19 25.00 904.75 39,269.88
34 29+425 34.970
34.11 25.00 852.63 40,122.50
35 29+450 33.240
32.48 25.00 812.00 40,934.50
36 29+475 31.720
31.17 25.00 779.13 41,713.63
37 29+500 30.610
30.33 25.00 758.13 42,471.75
38 29+525 30.040
30.21 25.00 755.13 43,226.88
39 29+550 30.370
30.49 25.00 762.25 43,989.13
40 29+575 30.610
31.41 25.00 785.13 44,774.25
41 29+600 32.200
33.62 25.00 840.38 45,614.63
42 29+625 35.030
37.86 25.00 946.50 46,561.13
43 29+650 40.690
46.95 25.00 1,173.75 47,734.88
44 29+675 53.210
56.02 25.00 1,400.50 49,135.38
45 29+700 58.830
59.24 25.00 1,481.00 50,616.38
46 29+725 59.650
56.33 25.00 1,408.13 52,024.50
47 29+750 53.000
51.29 25.00 1,282.25 53,306.75
48 29+775 49.580
41.77 25.00 1,044.25 54,351.00
49 29+800 33.960
32.63 25.00 815.63 55,166.63
50 29+825 31.290
32.57 25.00 814.13 55,980.75
51 29+850 33.840
35.16 25.00 879.00 56,859.75
52 29+875 36.480
37.39 25.00 934.75 57,794.50
53 29+900 38.300
38.70 25.00 967.50 58,762.00
54 29+925 39.100
Lebar Lebar Rata-Rata Jarak Volume (m2)
No STA
(m) (m) (m) Tiap Unit Kumulatif
39.92 25.00 998.00 59,760.00
55 29+950 40.740
41.07 25.00 1,026.63 60,786.63
56 29+975 41.390
41.70 25.00 1,042.38 61,829.00
57 30+000 42.000
42.25 25.00 1,056.25 62,885.25
58 30+025 42.500
42.56 25.00 1,064.00 63,949.25
59 30+050 42.620
42.08 25.00 1,052.00 65,001.25
60 30+075 41.540
41.91 25.00 1,047.75 66,049.00
61 30+100 42.280
42.20 25.00 1,055.00 67,104.00
62 30+125 42.120
42.10 25.00 1,052.50 68,156.50
63 30+150 42.080
42.03 25.00 1,050.75 69,207.25
64 30+175 41.980
42.12 25.00 1,052.88 70,260.13
65 30+200 42.250
42.15 25.00 1,053.75 71,313.88
66 30+225 42.050
41.80 25.00 1,045.00 72,358.88
67 30+250 41.550
42.64 25.00 1,065.88 73,424.75
68 30+275 43.720
42.82 25.00 1,070.50 74,495.25
69 30+300 41.920
41.49 25.00 1,037.13 75,532.38
70 30+325 41.050
40.51 25.00 1,012.75 76,545.13
71 30+350 39.970
39.50 25.00 987.50 77,532.63
72 30+375 39.030
38.55 25.00 963.63 78,496.25
73 30+400 38.060
37.33 25.00 933.25 79,429.50
74 30+425 36.600
36.19 25.00 904.75 80,334.25
75 30+450 35.780
37.49 25.00 937.25 81,271.50
76 30+475 39.200
37.40 25.00 934.88 82,206.38
77 30+500 35.590
34.12 25.00 853.00 83,059.38
78 30+525 32.650
33.91 25.00 847.63 83,907.00
79 30+550 35.160
36.04 25.00 901.00 84,808.00
80 30+575 36.920
37.59 25.00 939.63 85,747.63
81 30+600 38.250
Lebar Lebar Rata-Rata Jarak Volume (m2)
No STA
(m) (m) (m) Tiap Unit Kumulatif
38.57 25.00 964.13 86,711.75
82 30+625 38.880
39.16 25.00 978.88 87,690.63
83 30+650 39.430
39.51 25.00 987.75 88,678.38
84 30+675 39.590
39.72 25.00 992.88 89,671.25
85 30+700 39.840
39.73 25.00 993.13 90,664.38
86 30+725 39.610
39.71 25.00 992.63 91,657.00
87 30+750 39.800
39.63 25.00 990.63 92,647.63
88 30+775 39.450
39.42 25.00 985.38 93,633.00
89 30+800 39.380
38.87 25.00 971.63 94,604.63
90 30+825 38.350
37.91 25.00 947.75 95,552.38
91 30+850 37.470
37.89 25.00 947.25 96,499.63
92 30+875 38.31
39.29 25.00 982.13 97,481.75
93 30+900 40.26
40.19 25.00 1,004.63 98,486.38
94 30+925 40.11
39.88 25.00 996.88 99,483.25
95 30+950 39.64
39.38 25.00 984.38 100,467.63
96 30+975 39.11
38.94 25.00 973.38 101,441.00
97 31+000 38.76
PROYEK JALAN TOL TERBANGGI BESAR - PEMATANG PANGANG ZONA KLB I
1 28+850 55.658
39.23 25.00 980.76
2 28+875 22.803
17.08 25.00 426.94
3 28+900 11.353
11.61 25.00 290.31
4 28+925 11.873
16.47 25.00 411.83
5 28+950 21.074
24.96 25.00 623.88
6 28+975 28.836
34.16 25.00 854.08
7 29+000 39.490
45.61 25.00 1,140.19
8 29+025 51.725
63.81 25.00 1,595.33
9 29+050 75.901
85.04 25.00 2,126.01
10 29+075 94.180
101.31 25.00 2,532.81
11 29+100 108.445
118.27 25.00 2,956.84
12 29+125 128.102
154.11 25.00 3,852.68
13 29+150 180.113
237.73 25.00 5,943.27
14 29+175 295.349
286.23 25.00 7,155.82
15 29+200 277.117
326.24 25.00 8,155.98
16 29+225 375.361
376.94 25.00 9,423.48
17 29+250 378.517
377.92 25.00 9,448.05
18 29+275 377.327
309.03 25.00 7,725.85
19 29+300 240.742
215.92 25.00 5,398.06
20 29+325 191.103
160.80 25.00 4,020.12
21 29+350 130.507
111.54 25.00 2,788.55
22 29+375 92.577
79.43 25.00 1,985.82
23 29+400 66.289
58.50 25.00 1,462.40
24 29+425 50.704
44.68 25.00 1,117.02
25 29+450 38.658
34.44 25.00 861.08
PROYEK JALAN TOL TERBANGGI BESAR - PEMATANG PANGANG ZONA KLB I