Anda di halaman 1dari 39

RENCANA ANGGARAN BIAYA K3L

PT. …….
PROYEK : OFFICE TOWER ……..
NO. URAIAN PEKERJAAN BAHAN/UPAH UPAH

A. FASILITAS PENDUKUNG & UMUM Rp 49,728,784.47

B. FASILITAS SAFETY Rp 422,035,100.36

C. Upah Harian Safety ( Analisa Terlampir ) Rp 90,300,000.00

D. Fasilitas House Keeping & Environmental Rp 309,340,809.67

E. Kegiatan Pelatihan dan pendukung sistim manajemen K3 Rp 19,700,000.00

TOTAL SARANA PENDUKUNG, SAFETY & H. KEEPING Rp 891,104,694.50 Rp -


TOTAL Rp 891,104,694.50

* Nilai Kontrak + PPN Rp 158,706,900,000.00


* PPn 10% Rp 14,427,900,000.00
* Nilai Kontrak - PPN Rp 144,279,000,000.00
* RAB K-3 891,104,694.50
Rp 0.618 %

* Jamsostek dari Nilai Kontrak - PPN Rp 145,829,000.00


0.101 %

0.719 %
Jakarta, 13 September 2013
Disetujui : Di buat oleh :
RENCANA ANGGARAN BIAYA K3L
PT. …….
PROYEK : OFFICE TOWER ……..
NO. URAIAN PEKERJAAN BAHAN/UPAH UPAH

TEDI ……… Priyo ………..


PM SHEO
RENCANA ANGGARAN BIAYA K3L
PROYEK: OFFICE TOWER……..
RENCANA ANGGARAN BIAYA K3L
NO. URAIAN PEKERJAAN
Vol Sat. H. Sat Jmlh
A. FASILITAS PENDUKUNG & UMUM
A.1 Accesories Helm
1 Stiker Logo PT…….Kecil (Untuk Helm Karyawan) 200 bh Rp 2,500.00 Rp 500,000.00
2 Stiker Logo K3L & Green Kecil (Untuk Helm Karyawan & MK) 200 bh Rp 2,500.00 Rp 500,000.00
3 Stiker Logo MK Kecil Untuk Helm MK 30 bh Rp 2,500.00 Rp 75,000.00
4 Stiker Safety Induction (untuk pekerja & Karyawan) 300 lbr Rp 2,500.00 Rp 750,000.00
5 Stiker Biru, Merah & Hijau untuk Helm ( ScotLight ) untuk Pejabat Proyek 3 lbr Rp 45,000.00 Rp 135,000.00
A.2 Buku2 dan Blanko
1 Buku Tilang atau hukuman ( rangkap 3 ) 5 bh Rp 28,000.00 Rp 140,000.00
2 Buku Permintaan Barang K3L 1 bh Rp 28,000.00 Rp 28,000.00
A.3 Pembuatan Kartu Identitas Pekerja ( KIP )
1 Mesin Laminating 1 Unit Rp 850,000.00 Rp 850,000.00
2 Mesin Pemotong Kertas 1 Unit Rp 350,000.00 Rp 350,000.00
3 Plastik Laminating Folio ( asumsi 1 lembar untuk 6 Pekerja ) & total pekerja : 1.200 200 Lbr Rp 2,000.00 Rp 400,000.00
4 Kartu Identitas Pekerja (Asumsi 1 Bungkus untuk 50 Pekerja ) total 1000 pekerja 20 Bks Rp 56,000.00 Rp 1,120,000.00
A.4 Alat2 Komunikasi
1 Handy Talky ( Alinco ) untuk Petugas K3L (SHEO+SS) 2 bh Rp 1,500,000.00 Rp 3,000,000.00
2 Megaphone TOASTAR ( untuk Safety Talk ) 1 Unit Rp 925,000.00 Rp 925,000.00
3 Amplifire Rexon Pro-88 1 Unit Rp 1,850,000.00 Rp 1,850,000.00
4 Horn Speaker ZH-5025M+Matching (25 ")/TOA 1 Unit Rp 935,000.00 Rp 935,000.00
5 Microphone meja Rexon Pro 1 Unit Rp 2,650,000.00 Rp 2,650,000.00
6 Kabel Speaker SPK 2x50x40 ( 100 meter ) 2 Roll Rp 475,000.00 Rp 950,000.00
7 Peluit untuk Petugas K3L 15 Bh Rp 5,000.00 Rp 75,000.00
9 SHE Talk Mingguan & Bulanan
- Mike Tanpa Kabel & Miike Head Set Tanpa Kabel 1 Bh Rp 500,000.00 Rp 500,000.00
- Speaker Aktif 1 Set Rp 2,000,000.00 Rp 2,000,000.00
A.5 Seragam K3L Mandor/Sub.Kont & Harian K3L

Page 3 of 39
RENCANA ANGGARAN BIAYA K3L
PROYEK: OFFICE TOWER……..
RENCANA ANGGARAN BIAYA K3L
NO. URAIAN PEKERJAAN
Vol Sat. H. Sat Jmlh

1 Seragam Merah Overall K3L 8 Psng Rp 360,000.00 Rp 2,880,000.00


2 Kaos Pekerja Harian Safety & H. Keeping atau rompi 20 Psng Rp 40,000.00 Rp 800,000.00
A.6 Traffic, tanda dan Rambu serta lampu
1 Senter Traffic Panjang 2 bh Rp 170,000.00 Rp 340,000.00
2 Rubber Cone,Uk. 70 cm 10 bh Rp 197,000.00 Rp 1,970,000.00
3 Senter 4 baterai 1 bh Rp 350,000.00 Rp 350,000.00
4 Rambu " Hati2 Keluar Masuk Kendaraan Proyek " 1 Set Rp 2,200,000.00 Rp 2,200,000.00
5 Rompi Siang Malam, untuk Karyawan Rp 105,000.00 Rp -
6 Lampu Rotary (Lampu Emergency) 1 Pcs Rp 300,000.00 Rp 300,000.00
7 Lampu Selang traffic rol Rp 1,400,000.00 Rp -
8 Rambu "Hati2 ada pekerjaan" (Malam Bisa Menyala) Rp 750,000.00 Rp -
9 Rambu Panah (Kalau Malam Bisa Menyala) Rp 750,000.00 Rp -
10 Rambu "Hati - hati" (Kalau Malam Bisa Menyala) Rp 750,000.00 Rp -

Page 4 of 39
RENCANA ANGGARAN BIAYA K3L
PROYEK: OFFICE TOWER……..
RENCANA ANGGARAN BIAYA K3L
NO. URAIAN PEKERJAAN
Vol Sat. H. Sat Jmlh

11 Rambu "Orang Bekerja" (Kalau Malam Bisa Menyala) Rp 750,000.00 Rp -


A.7 Dokumentasi
1 Camera Digital dan MMC 1 bh Rp 2,000,000.00 Rp 2,000,000.00
A.8 Lain-lain
1 Rompi untuk Riger 4 bh Rp 100,000.00 Rp 400,000.00
2 Bendera ( PT, K3L, MERAH PUTIH ) 6 Bh Rp 100,000.00 Rp 600,000.00
3 Tiang Bendera ( Pipa 2 " ) 2 Set Rp 400,000.00 Rp 800,000.00
4 Jas Hujan ( Harian K3L & Karyawan PT & Petugas K3L ) 30 Bh Rp 85,000.00 Rp 2,550,000.00
5 Tempat meletakkan Helm 34 Bh Rp 16,346.60 Rp 555,784.47
6 Hadiah SHE Talk 11 Bulan+Konsumsi (perincian hadiah s.talk) 1 Ls Rp 13,750,000.00 Rp 13,750,000.00
7 Pilox berwarna 100 Bh Rp 25,000.00 Rp 2,500,000.00
A. FASILITAS PENDUKUNG & UMUM =(A1 sd A8) JUMLAH Rp 49,728,784.47
B. FASILITAS SAFETY
B.1 Alat Pelindung Diri ( APD )
1 Helmet
- Helm, Tali Helm + Accesories Karyawan PT. …. 35 bh Rp 45,000.00 Rp 1,575,000.00
- Helm, Tali Helm + Accesories Karyawan MK 10 bh Rp 45,000.00 Rp 450,000.00
- Helm, Tali Helm + Accesories Untuk Tamu + Direksi PT. PP 50 bh Rp 45,000.00 Rp 2,250,000.00
- Helm, Tali Helm + Accesories Pekerja Harian 20 bh Rp 45,000.00 Rp 900,000.00
2 Sepatu Safety ( Safety Shoes )
- Sepatu Safety Karyawan PT….. ( King 805 C ) 35 Psng Rp 305,000.00 Rp 10,675,000.00
- Sepatu Safety Karyawan MK/Owner ( King 805 C ) 10 Psng Rp 305,000.00 Rp 3,050,000.00
- Sepatu Safety Direksi PT. ... ( King 805 C ) 5 Psng Rp 305,000.00 Rp 1,525,000.00
3 Sepatu Karet ( Rubber Shoes )
- Karyawan (AP) 21 Psng Rp 47,500.00 Rp 997,500.00
- Sepatu Pekerja Harian ( AP ) 20 Psng Rp 47,500.00 Rp 950,000.00
4 Masker Debu
- Masker merk Marsk Karyawan PT. …. 28 Bh Rp 27,500.00 Rp 770,000.00
- Masker Karyawan MK/Owner 10 Bh Rp 27,500.00 Rp 275,000.00
- Masker untuk Direksi PT. 5 Bh Rp 27,500.00 Rp 137,500.00
- Masker Harian K3L 20 Bh Rp 27,500.00 Rp 550,000.00

Page 5 of 39
RENCANA ANGGARAN BIAYA K3L
PROYEK: OFFICE TOWER……..
RENCANA ANGGARAN BIAYA K3L
NO. URAIAN PEKERJAAN
Vol Sat. H. Sat Jmlh

5 Pekerjaan Pengelasan
- Masker Asap
- Peralatan 2 Bh Rp 67,500.00 Rp 135,000.00
- Harian K3L 1 Bh Rp 67,500.00 Rp 67,500.00
- Kedok Las/Kaca Mata Las
- Peralatan 2 Bh Rp 27,500.00 Rp 55,000.00
- Harian K3L 1 Bh Rp 27,500.00 Rp 27,500.00
- Sarung Tangan Tahan Panas
- Peralatan 2 Bh Rp 25,000.00 Rp 50,000.00

Page 6 of 39
RENCANA ANGGARAN BIAYA K3L
PROYEK: OFFICE TOWER……..
RENCANA ANGGARAN BIAYA K3L
NO. URAIAN PEKERJAAN
Vol Sat. H. Sat Jmlh

- Harian K3L 2 Bh Rp 25,000.00 Rp 50,000.00


- Body Protection
- Peralatan 2 Bh Rp 40,500.00 Rp 81,000.00
- Harian K3L 2 Bh Rp 40,500.00 Rp 81,000.00
6 Pekerjaan Pemotongan Besi
- Safety Glasses/Kaca Mata Transparan
- Peralatan 2 Bh Rp 37,500.00 Rp 75,000.00
- Harian K3L 2 Bh Rp 37,500.00 Rp 75,000.00
- Sarung Tangan Kulit
- Peralatan 2 Bh Rp 25,000.00 Rp 50,000.00
- Harian K3L 2 Bh Rp 25,000.00 Rp 50,000.00
7 Safety Belt.
- Safety Belt untuk Karyawan Lapangan 23 Bh Rp 75,000.00 Rp 1,725,000.00
- Safety Belt untuk Petugas K3L 4 Bh Rp 75,000.00 Rp 300,000.00
8 Full Body Harness
- Harian K3L 4 Bh Rp 375,000.00 Rp 1,500,000.00
9 Sarung Tangan Kain
- Karyawan 23 Ps Rp 1,650.00 Rp 37,950.00
- Harian K3L 20 Ps Rp 1,650.00 Rp 33,000.00
- Harian Peralatan 4 Ps Rp 1,650.00 Rp 6,600.00
10 Ear Plug 23 Rp 3,750.00 Rp 86,250.00
B.2 Alat Pengaman Kerja ( APK )
1 Alat Pemadam Api Ringan ( APAR )
- Dry Chemical 3,5 Kg (Fasilitas Apar) 40 Bh Rp 450,000.00 Rp 18,000,000.00
- Pengisian APAR 40 Unit Rp 150,000.00 Rp 6,000,000.00
- Tempat APAR Gantung 4 Bh Rp 16,460.00 Rp 65,840.00
- Tempat APAR Duduk 36 Bh Rp 54,651.00 Rp 1,967,436.00
2 Ralling pinggir Galian Tanah Basement 169 m1 Rp 98,168.82 Rp 16,590,530.00
3,986 m1
3 Ralling pinggir lantai (tambang kuning) Rp 5,660.83 Rp 22,564,477.93
4 Gantungan Besi Ralling (Hunger+ Fisher) 10 Dus Rp 250,000.00 Rp 2,500,000.00

Page 7 of 39
RENCANA ANGGARAN BIAYA K3L
PROYEK: OFFICE TOWER……..
RENCANA ANGGARAN BIAYA K3L
NO. URAIAN PEKERJAAN
Vol Sat. H. Sat Jmlh

5 Ralling Tangga jarak 3 m,tiang besi bekas 576 m1 Rp 6,080.00 Rp 3,502,080.00


6 Ralling Kayu Core Lift 180 unt Rp 62,975.01 Rp 11,335,501.52
7 Safety Net (polynet) keliling Bangunan (Vertical)
- Material+pasang (satu sisi sebelah timur) 3,232 m2 Rp 10,000.00 Rp 32,319,000.00
- Bongkar (satu sisi sebelah timur) 3,232 m2 Rp 1,000.00 Rp 3,231,900.00
- safety net 1 m (Penahan debu) 3,986 m1 Rp 10,000.00 Rp 39,860,700.00
8 Safety Net Horisontal Sisi Bangunan ( 2 x 4 )
- Material 65.6 Unit Rp 1,400,000.00 Rp 91,840,000.00
- Pemasangan & Moving 65.6 Unit Rp 960,000.00 Rp 62,976,000.00

Page 8 of 39
RENCANA ANGGARAN BIAYA K3L
PROYEK: OFFICE TOWER……..
RENCANA ANGGARAN BIAYA K3L
NO. URAIAN PEKERJAAN
Vol Sat. H. Sat Jmlh

9 Safety Net Horisontal Lubang Core (kawat harmonika/pukat harimau) 478.71 m2 Rp 25,000.00 Rp 11,967,750.00
10 Proteksi Penutup Lubang Shaft 72.00 M2 Rp 189,665.70 Rp 13,655,930.74
11 Life Line ( Tambang Manila 1,5 ") 200 m1 Rp 15,500.00 Rp 3,100,000.00
12 Police Line ( Barikade Tape ) 8 cm 5 Roll Rp 75,000.00 Rp 375,000.00
B.3 P3K & Kesiagaan Tanggap Darurat
- Kotak P3K 4 Bh Rp 150,000.00 Rp 600,000.00
- Isi Kotak P3K 4 Set Rp 450,000.00 Rp 1,800,000.00
- Cadangan Isi Kotak P3K ( 24 Bulan ) 11 Bl Rp 450,000.00 Rp 4,950,000.00
- Tandu 1 Bh Rp 1,500,000.00 Rp 1,500,000.00
- Tempat Tidur/ Kasur Lipat 1 Unit Rp 450,000.00 Rp 450,000.00
- Bantal 1 Set Rp 75,000.00 Rp 75,000.00
- Spalk/Bidai 1 Set Rp 250,000.00 Rp 250,000.00
- Mitela atau Kain Penyangga Spalk 3 Roll Rp 250,000.00 Rp 750,000.00
- Papan Assembly Point 1 Unit Rp 750,000.00 Rp 750,000.00
B.4 Rambu & Slogan & Pengumuman
1 SHE Sign Board (Komitmet K3L ),( Analisa fasilitas K3L terlampir) 2 Set Rp 6,450,180.00 Rp 12,900,360.00
2 Papan SHE Information (Pengumuman) 3 Bh Rp 901,935.00 Rp 2,705,805.00
3 Spanduk K3L 12 Bh Rp 350,000.00 Rp 4,200,000.00
4 Rambu2 K3L 280 bh Rp 10,000.00 Rp 2,800,000.00
5 Papan Rambu2 K3L. Uk. 0,45 x 0,35 m. Triplek 6 mm (0,45 X 122) tiang besi 30 Lbr Rp 97,500.00 Rp 2,925,000.00
B.5 Peralatan Kerja ( Analisa Terlampir ) 1 Ls Rp 9,470,500.00 Rp 9,470,500.00
B.6 Tempat Merokok (Analisa Fasilitas K3L) 15 Unit Rp 364,365.95 Rp 5,465,489.18
B. FASILITAS SAFETY =(B1 sd B6) JUMLAH Rp 422,035,100.36

C Upah Harian Safety ( Analisa Terlampir ) 1 Ls Rp 90,300,000.00 Rp 90,300,000.00

Page 9 of 39
RENCANA ANGGARAN BIAYA K3L
PROYEK: OFFICE TOWER……..
RENCANA ANGGARAN BIAYA K3L
NO. URAIAN PEKERJAAN
Vol Sat. H. Sat Jmlh
D. Fasilitas House Keeping & Environmental (lingkungan)
1 Tempat Sampah 3 Tong (terlampir Analisa Fasilitas K3L) 2 Unit Rp 352,555.00 Rp 705,110.00
2 Tempat Sampah 1 Tong (terlampir Analisa Fasilitas K3L) 22 Bh Rp 166,938.24 Rp 3,672,641.39
3 Tempat Sampah Akhir 3 Bagian (terlampir " Analisa Fasilitas K3L) 1 Unit Rp 6,167,644.00 Rp 6,167,644.00
4 Cerobong Sampah 0 Ls Rp -
5 Pengadaan Alat Kebersihan (terlampir Analisa Peralatan Kerja K3L) 11 bln Rp 1,696,800.00 Rp 18,664,800.00
6 Pengadaan Alat Kebersihan ( Jumat Bersih ) 1 ls Rp 1,250,000.00 Rp 1,250,000.00
7 Selang Air 3/4" serat Benang 100 Mtr Rp 11,500.00 Rp 1,150,000.00
8 Tempat Kencing Temporary (terlampir) 15 Unit Rp 491,901.17 Rp 7,378,517.62
9 Jec Cleaner/Engine Cleaner 2 Unit Rp 4,000,000.00 Rp 8,000,000.00
10 Gerobak Dorong 2 Roda 2 Unit Rp 950,000.00 Rp 1,900,000.00
11 Buang Sampah Keluar Lokasi Proyek (Analisa Rit Sampah terlampir) 513.5 rit Rp 130,000.00 Rp 66,752,096.67
12 Sedot Septic Tank 4 3 Bln-1 Rp 650,000.00 Rp 2,600,000.00
13 Semprotan Nyamuk - fooging ( 2 Minggu Sekali, 1 kali semprot Rp.750.000) 11 Bln Rp 1,500,000.00 Rp 16,500,000.00
14 Upah Harian Housekeeping( Analisa Terlampir ) 1 Ls Rp174,600,000.00 Rp 174,600,000.00
Rp 309,340,809.67
E. Kegiatan Pelatihan dan pendukung sistim manajemen K3
14 Inspeksi K3 Kegiatan bersama ( 2 Minggu Sekali, 1 kali konsumsi Rp.100.000) 11 Bln Rp 200,000.00 Rp 2,200,000.00
15 Revisi RK3K diperkirakan ( 4 kali selama Proyek, 1 kali Rp.750.000) 4 6 Bln-1 Rp 750,000.00 Rp 3,000,000.00
16 Pelatihan Siaga Kebakaran diperkirakan ( 2 kali selama Proyek, 1 kali Rp.1.750.000) 2 12 Bln-1 Rp 1,750,000.00 Rp 3,500,000.00
17 Pelatihan Siaga Kecelakaan diperkirakan ( 2 kali selama Proyek, 1 kali Rp.1.750.000) 2 12 Bln-1 Rp 1,750,000.00 Rp 3,500,000.00
18 Pelatihan Siaga Evakuasi diperkirakan ( 2 kali selama Proyek, 1 kali Rp.3.750.000) 2 12 Bln-1 Rp 3,750,000.00 Rp 7,500,000.00
E. Kegiatan Pelatihan dan pendukun SMK3 =(E) JUMLAH Rp 19,700,000.00

TOTAL SARANA PENDUKUNG, SAFETY & H. KEEPING = (A+B+C+D+E) JUMLAH Rp 891,104,694.50


* Nilai Kontrak + PPN 158,706,900,000.00
* PPn 10% 14,427,900,000.00
* Nilai Kontrak - PPN 144,279,000,000.00
* Prosentase RAB K3L 0.618 %

Page 10 of 39
RENCANA ANGGARAN BIAYA K3L
PROYEK: OFFICE TOWER……..
RENCANA ANGGARAN BIAYA K3L
NO. URAIAN PEKERJAAN
Vol Sat. H. Sat Jmlh

ditinjau RAB - PPN

Page 11 of 39
PROYEK : OFFICE TOWER SKY 18
PERHITUNGAN RITASE SAMPAH L
A
1.000 H
A
N
No Jenis Pekerjaan Jenis Sampah Faktor Volume L
P
T
R
Plastik makanan, botol minuman, bungkus O
5
1 Umum dan puntung rokok, puing bobokan 0.3 5 kg Y
###
E
K
Pasir, Sisa adukan, sisa material : Bata,
Finishing yang dikerjakan Keramik, Granit/Marmer, potongan kayu,
2 0.4 15 kg ###
Sendiri Kantong Semen

Sisa potongan plafond, bungkus sisa


3 Pasang Plafond/Partisi compound, sisa potongan rangka 0.15 -10 kg ###

Sisa pipa konduit, Sisa kabel


4 Elektrikal 0.05 -20 kg ###

Sisa potongan seng, Glasswool, Kertas


Aluminium Foil, kardus/kayu, sisa ducting,
7 A/C 0.1 -15 kg ###
pembungkus peralatan utama

Total Berat Sampah Tiap m2 20 kg


Luas Bangunan 46,213 m2
Berat Total Sampah 924 ton
Jumlah Ritase Sampah 513.48 rit

Safety, Health & Environmental Officer


Rencana Fasilitas APD Karyawan
PT. PP ( Persero )
PROYEK : OFFICE TOWER SKY 18

FASILITAS

TALI HELM SEPATU SAFETY MASKER KEDOK S. TANGAN MASKER BODY SAFETY TEMPAT SEPATU
NO NAMA JABATAN
HELM
FLEKSIBEL SAFETY BELT DEBU LAS LAS LAS PROTEC GLASSES HELM BOOT

1 TEDI SURYO SUSENO PM 1 1 1 1 1


2 TEGUH SEM 1 1 1 1 1
3 POP 1 1 1 1
4 TAUFIK SAM 1 1 1 1
5 SUPRIYANTO GSP M/E 1 1 1 1 1 1
6 SOM 1 1 1 1 1 1
7 Akunt + Adm 2 2 2 2
8 Logistik + Penbar 2 2 2 2 2 1
9 GSP 1 1 1 1 1 1
10 SP 1 1 1 1 1 1 1
11 SP 1 1 1 1 1 1 1
12 SP 1 1 1 1 1 1 1
13 SP 1 1 1 1 1 1 1
14 SUNYOTO Uitset 1 1 1 1 1 1 1
15 SUNARDI UItset 1 1 1 1 1 1 1
16 AHMAD Peralatan 2 2 2 2 2 2 2 2 2 2 2 2
17 Peralatan 2 2 2 2 2 2 2 2 2 2 2 2
18 SHEO+ SS 2 2 2 2 2 2 2 2
19 Pekerja Harian K3L 4 4 4 4 1 1 1 1 1 1 4 4
20 Drafter1 DAN 2 2 2 2 2 2 2
21 Office Boy 2 2 2 2 2 2 2
22 SUHANDA Security 1 1 1 1 1 1
23 BUDI S Security 1 1 1 1 1 1
24 Security 1 1 1 1 1 1
25 Security 1 1 1 1 1 1
Jumlah 35 35 35 23 28 5 5 5 5 7 35 21

Priyo Leksono
Safety, Health & Environmental Officer
DATA TEKNIS
PROYEK : OFFICE TOWER SKY 18

No Lantai Luas (m2) Keliling (m1) Elevasi Tinggi


1 Basement Basement 4,074.75 132.20 3.850 3.10
2 Basement Semi basement 4,074.75 286.10 6.950 4.25
3 Lantai Dasar 4,074.75 286.10 11.200 6.00
4 Lantai Mezanine 1,302.19 159.30 17.200 3.70
5 Lantai
6 Lantai 3 1,561.36 187.59 20.200 3.700
7 Lantai 5 1,561.36 187.59 24.600 3.700
8 Lantai 6 1,561.36 187.59 28.300 3.700
9 Lantai 7 1,640.47 175.50 32.000 3.700
10 Lantai 8 1,302.20 160.00 35.700 3.700
11 Lantai 9 1,302.20 160.00 39.400 3.700
12 Lantai 10 1,302.20 160.00 43.100 3.700
13 Lantai 11 1,348.20 153.30 46.800 3.700
14 Lantai 12 1,348.20 153.30 50.500 3.700
15 Lantai 15 1,348.20 153.30 54.200 3.700
16 Lantai 16 1,348.20 153.30 57.900 3.700
17 Lantai 17 1,348.20 153.30 61.600 3.700
18 Lantai 18 1,348.20 153.30 65.300 3.700
19 Lantai 19 1,348.20 153.30 69.000 3.700
20 Lantai 20 1,348.20 153.30 72.700 3.700
21 Lantai 21 1,348.20 153.30 76.400 3.700
22 Lantai 22 1,348.20 153.30 80.100 3.700
23 Lantai 23 1,348.20 153.30 83.800 3.700
24 Lantai
25 Lantai 25 1,348.20 153.30 91.200 3.700
26 Lantai 26 1,348.20 153.30 94.900 3.700
27 Lantai 27 1,232.20 153.90 98.600 3.700
28 Lantai 28 1,232.20 153.90 102.300 3.700
29 Lantai 29 1,232.20 153.90 106.000 3.700
30 Lantai Roof Deck 1,232.20 153.90 113.000 4.900
Total 46,212.99 3,986.07 1,586.80 107.05
SCHEDULLE PEKERJAAN K3L
PT. PP ( Persero )
PROYEK : OFFICE TOWER SKY 18

RENCANA 2013 2014


NO. URAIAN PEKERJAAN
Vol Sat. 0kt Des Jan sept
A. FASILITAS PENDUKUNG & UMUM

1 Pembuatan Kartu Identitas Pekerja ( KIP ) 1 Ls


2 Rambu " Hati2 Keluar Masuk Kendaraan Proyek " 1 Set
1 Bendera ( PP, K3L, MERAH PUTIH ) 2 Set
2 Tiang Bendera ( Pipa 2 " ) 1 Set
3 Tempat Helm 26 Bh
B. FASILITAS SAFETY
1 Alat Pemadam Api Ringan ( APAR )
- Tempat APAR Gantung 17 Bh
- Tempat APAR Duduk Bh
2 Ralling Galian m1

3 Ralling Antar Kolom 4,247.00 m1


4 Ralling Tangga jarak 3 m/tiang 446 m1
5 Ralling Kayu Core Lift 109.2 m1
6 Safety Net Vertikal Tangga Kerja
- Material 2475 m2
- Bongkar 886 m2
7 Safety Net Horisontal Sisi Bangunan ( 2 x 4 )
- Material ( Kebutuhan 43 unt 43 unt
- Pemindahan ( Moving 1 Kali, Dari Lt. 2 Ke 5 ) 43 unt
8 Safety Net Horisontal Lubang Core
- Material. ( Uk. 5,4 x 7,9, Uk. 6,3 x 3,7, Uk. 2,7 x 8,8 ) 89.73 m2

- Pemindahan ( Moving, 1 Kali ) 89.73


Page 15 of 39
SCHEDULLE PEKERJAAN K3L
PT. PP ( Persero )
PROYEK : OFFICE TOWER SKY 18

RENCANA 2013 2014


NO. URAIAN PEKERJAAN
Vol Sat. 0kt Des Jan sept

9 Proteksi Penutup Lubang Shaft 351.5947 M2


10 Pemasangan Life Line ( Tambang Manila 1,5 ") 200 m1
B.4 Rambu & Slogan
1 SHE Sign Board (Slogan K3L ) 2 Unit

2 Papan SHE Information 1 Bh


3 Pemasangan Spanduk K3L 15 Bh

Page 16 of 39
SCHEDULLE PEKERJAAN K3L
PT. PP ( Persero )
PROYEK : OFFICE TOWER SKY 18

RENCANA 2013 2014


NO. URAIAN PEKERJAAN
Vol Sat. 0kt Des Jan sept

4 Rambu2 K3L 165 bh


5 Papan Rambu2 K3L. Uk. 0,45 x 0,35 m. Triplek 6 mm 9.0 Lbr

B.5 Peralatan Kerja ( Analisa Terlampir ) 1 Ls

B.6 Tempat Merokok 2 Unit


C. Fasilitas House Keeping & Environmental
1 Tempat Sampah 3 Tong 3 Unit

2 Tempat Sampah 1 Tong 59 Bh


3 Tempat Sampah Akhir 3 Bagian 1 Unit
4 Cerobong Sampah 1 Ls

5 Pengadaan Alat Kebersihan ( Analisa Terlampir ) 1 Ls

6 Pengadaan Alat Kebersihan ( Jumat Bersih ) 1 Ls

7 Selang Air 3/4" serat Benang 200 Mtr

8 Tempat Kencing Temporary 20 Bh


9 Buang Sampah Keluar Lokasi Proyek ( Analisa Terlampir ) 1 Ls

10 Penyemprotan Nyamuk ( 2 Minggu Sekali ) 11 Bln

1 Buat Fasilitas Housekeeping & Safety Lainnya 5 %


yang tidak terprediksi (Biaya Cadangan)
( 5% dari Total Sarana Pendukung, Safety & H. Keeping )

TOTAL PEKERJAAN

Page 17 of 39
Analisa Peralatan Kerja K3L dan Harga
PROYEK : OFFICE TOWER SKY 18
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SATUAN VOLUME
(Rp.) (Rp.)
A Alat Bantu Pekerjaan
1 Palu/Hammer bh 2 25,000.00 50,000.00
2 Kunci Pas Set 2 195,000.00 390,000.00
3 Kunci Ring Set 2 195,000.00 390,000.00
4 Kunci Inggris bh 2 65,000.00 130,000.00
5 Gergaji Kayu/Wood Saw bh 2 45,500.00 91,000.00
6 Gergaji Besi/Steel Saw bh 2 50,000.00 -
7 Ge'ge'p bh 4 25,000.00 100,000.00
8 Tang Kombinasi bh 2 39,000.00 78,000.00
9 Testpen bh 2 17,500.00 35,000.00
10 Obeng ( + ) bh 2 15,000.00 30,000.00
11 Obeng ( - ) bh 2 15,000.00 30,000.00
12 Isolasi Kabel rol 20 6,500.00 130,000.00
13 Isolasi Kertas rol 20 8,750.00 175,000.00
14 Tas Pinggang bh 2 25,000.00 50,000.00
15 Kuas Cat bh 15 9,000.00 135,000.00
16 Roll Cat bh 6 7,500.00 45,000.00
17 Sendok Semen bh 2 22,500.00 -
18 Sendok Semen Segitiga bh 2 35,000.00 -
19 Mesin Serut Kayu Bh 1 1,500,000.00 -
20 Bor Beton Bh 1 1,560,000.00 1,560,000.00
21 Bor Besi Bh 1 1,560,000.00
22 Mata bor beton D 8 mm Bh 4 25,000.00 100,000.00
23 Mata bor beton D 10 mm Bh 4 35,000.00 140,000.00
24 Mata bor beton D 12 mm Bh 4 45,000.00 180,000.00
25 Mata bor beton D 16 mm Bh 4 65,000.00 260,000.00
26 Mata bor Besi D 5 mm Set 4 125,000.00 500,000.00
27 Gerinda Tanggan Bh 1 1,050,000.00
28 Mata Gerinda Bh 5 162,500.00
29 Mesin Las Bh 1 975,000.00 975,000.00
30 Kawat Las ( Uk.5 Kg/dus ) Dus 6 78,000.00 468,000.00
31 Kedok Las Bh 2 50,000.00 100,000.00
32 Stang Las Bh 2 65,000.00 130,000.00
33 Kabel Las M 12 40,500.00 486,000.00
34 Body Protect Bh 2 35,000.00 70,000.00
35 Meteran Tajima Bh 4 77,500.00 310,000.00
36 Sekop Bh 4 32,500.00 130,000.00
37 Cangkul Bh 2 35,000.00 70,000.00
38 Ember Karet Bh 10 25,000.00 250,000.00
39 Cutter Bh 5 16,500.00 82,500.00
40 Isi Kater Ktk 10 10,000.00 100,000.00
41 Pahat Kayu Bh 1 22,500.00 -
42 Jas Hujan Bh 20 85,000.00 1,700,000.00
Jumlah 9,470,500.00
B Alat - alat Kebersihan
43 Sapu Lidi Ikat 30 16,250.00 487,500.00
44 Sapu Ijuk Bh 4 11,700.00 46,800.00
45 Karung Plastik Bh 500 2,000.00 1,000,000.00
46 Kain Pel Bh 1 7,500.00 -
47 Alat Pel Bh 1 35,000.00 -
48 Garukan Karet Bh 10 16,250.00 162,500.00
Jumlah 1,696,800.00
C Alat - alat Kebersihan Jumat Bersih
49 Sapu Lidi Ikat 30 16,250.00 487,500.00
50 Karung Plastik Bh 300 2,000.00 600,000.00
51 Garukan Karet Bh 10 16,250.00 162,500.00
Jumlah 1,250,000.00
Total 12,417,300.00
Priyo Leksono
Safety, Health & Environmental Officer
Analisa Gaji Harian K3L Proyek Office Tower Sky
JAKARTA -2013 - 2014

Jumlah Jam Kerja 1 2 3 4 OFF 5 6 7 8 9 OFF 10 11 12 OFF 14 15 16 17 18 19 20 21 22

Jam Kerja : 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 1 2 3 4 5 6 7 8

Asumsi Jumlah hari kerja : 31 hari


Harian House Keeping : Dihitung bekerja dalam 1 hari 12 Jam sampai dengan Pkl. 22.00 Wib
Upah Per Jam Rp 6,500.00 Rp 78,000.00 Rp 2,418,000.00
( 1 Hari ) ( 1 Bulan )

- DIJADIKAN Rp 1,800,000.00
- DISEDIAKAN MAKAN
618,000 Rp

Harian Safety : Dihitung bekerja dalam 1 hari 12 Jam sampai dengan Pkl. 22.00 Wib
Upah Per Jam Rp 7,250.00 Rp 87,000.00 Rp 2,697,000.00
( 1 Hari ) ( 1 Bulan )

- DIJADIKAN Rp 2,100,000.00
- DISEDIAKAN MAKAN
597,000 Rp

Jakarta, 13 September 2013

,Menyetujui ,Dbuat Oleh

Priyo Leksono
CM SHE O
RENCANA ANGGARAN BIAYA UPAH HARIAN HOUSE KEEPING
PROYEK : Office Tower Sky
Upah
No Bulan Jumlah Tenaga Rp 1,800,000.00 Jumlah Upah
/ Bulan

1 September 2013 1 orang Rp 1,800,000.00 Rp 1,800,000


2 Oktober 2013 1 orang Rp 1,800,000.00 Rp 1,800,000
3 Nopember 2013 1 orang Rp 1,800,000.00 Rp 1,800,000
4 Desember 2014 2 orang Rp 1,800,000.00 Rp 3,600,000
5 Januari 2014 4 orang Rp 1,800,000.00 Rp 7,200,000
6 Pebruari 2014 4 orang Rp 1,800,000.00 Rp 7,200,000
7 Maret 2014 6 orang Rp 1,800,000.00 Rp 10,800,000
8 April 2014 8 orang Rp 1,800,000.00 Rp 14,400,000
9 Mei 2014 10 orang Rp 1,800,000.00 Rp 18,000,000
10 Juni 2014 12 orang Rp 1,800,000.00 Rp 21,600,000
11 Juli 2014 12 orang Rp 1,800,000.00 Rp 21,600,000
THR bln Agustus 2014 12 orang Rp 1,800,000.00 Rp 21,600,000
12 Agustus 2014 12 orang Rp 1,800,000.00 Rp 21,600,000
13 September 2014 12 orang Rp 1,800,000.00 Rp 21,600,000
Rp 174,600,000

Dibuat :

Priyo Leksono
SHEO
RENCANA ANGGARAN BIAYA UPAH HARIAN SAFETY
PROYEK : Office Tower Sky
Upah
No Bulan/Tahun' Jumlah Tenaga Rp 2,100,000.00 Jumlah Upah
/ Bulan
1 September 2013 1 orang Rp 2,100,000.00 Rp 2,100,000
2 Oktober 2013 1 orang Rp 2,100,000.00 Rp 2,100,000
3 Nopember 2013 1 orang Rp 2,100,000.00 Rp 2,100,000
4 Desember 2014 2 orang Rp 2,100,000.00 Rp 4,200,000
5 Januari 2014 3 orang Rp 2,100,000.00 Rp 6,300,000
6 Pebruari 2014 3 orang Rp 2,100,000.00 Rp 6,300,000
7 Maret 2014 4 orang Rp 2,100,000.00 Rp 8,400,000
8 April 2014 4 orang Rp 2,100,000.00 Rp 8,400,000
9 Mei 2014 4 orang Rp 2,100,000.00 Rp 8,400,000
10 Juni 2014 4 orang Rp 2,100,000.00 Rp 8,400,000
11 Juli 2014 4 orang Rp 2,100,000.00 Rp 8,400,000
THR bln Agustu 2014 4 orang Rp 2,100,000.00 Rp 8,400,000
12 Agustus 2014 4 orang Rp 2,100,000.00 Rp 8,400,000
13 September 2014 2 orang Rp 2,100,000.00 Rp 8,400,000
Total Rp 90,300,000
HADIAH SAFETY TALK BULANAN+KONSUMSI
PT. PP ( Persero )
PROYEK : Office Tower Sky
Tahun 2013 s/d
NO MINGGU BESARNYA KETERANGAN
2014
1 Sep-13 3 Rp 50,000.00 10,000
Hadiah + Konsumsi minggu ke 4 Rp 500,000.00 50
2 Oct-13 1 500,000
2
3 Rp 50,000.00 10,000
Hadiah + Konsumsi minggu ke 4 Rp 400,000.00 40
3 Nov-13 1 Rp -
2 Rp -
3 Rp 50,000.00 10,000
Hadiah + Konsumsi minggu ke 4 Rp 400,000.00 40
4 Dec-13 1 Rp -
2 Rp -
3 Rp 50,000.00 10,000
Hadiah + Konsumsi minggu ke 4 Rp 600,000.00 60
5 Jan-14 1 Rp -
2 Rp -
3 Rp 50,000.00 10,000
Hadiah + Konsumsi minggu ke 4 Rp 600,000.00 60
6 Feb-14 1 Rp -
2 Rp -
3 Rp 50,000.00 10,000
Hadiah + Konsumsi minggu ke 4 Rp 750,000.00 75
7 Mar-14 1 Rp -
2 Rp -
3 Rp 50,000.00 10,000
Hadiah + Konsumsi minggu ke 4 Rp 1,000,000.00 100
8 Apr-14 1 Rp -
2 Rp -
3 Rp 50,000.00 10,000
Hadiah + Konsumsi minggu ke 4 Rp 1,500,000.00 150
9 May-14 1 Rp -
2 Rp -
3 Rp 50,000.00 10,000
Hadiah + Konsumsi minggu ke 4 Rp 1,500,000.00 150
10 Jun-14 1 Rp -
2 Rp -
3 Rp 50,000.00 10,000
Hadiah + Konsumsi minggu ke 4 Rp 1,500,000.00 150
11 Jul-14 1 Rp -
2 Rp -
2 Rp - 10,000
Hadiah + Konsumsi minggu ke 4 Rp 1,500,000.00 150
12 Aug-14 1 Rp -
2 Rp -
2 Rp - 10,000
Hadiah + Konsumsi minggu ke 4 Rp 1,500,000.00 150
13 Sep-14 1 Rp -
2 Rp -
2 Rp - 10,000
Hadiah + Konsumsi minggu ke 4 Rp 1,500,000.00 150
JUMLAH : Rp 13,750,000.00
TAHUN 2013 S/D 2014 Rp 13,750,000.00
TOTAL : Rp 13,750,000.00
Analisa Harga Fasilitas K3L
PROYEK : OFFICE TOWER SKY 18

No Uraian Pekerjaan Volume Satuan Harga Satuan


1 SHE Sign Board (Komitment K3L)
Bahan
- Pipa Black Steel 2,5" x 2 mm x 6 m 8.00 Btng Rp 320,500.00
- Hollow 4 x 4 x 2 mm 10.00 Btng Rp 287,500.00
- Triplek 4 mm 6.00 Lbr Rp 62,500.00
- Plat Baja Uk. 25 x 25 x 12 mm 6.00 Lbr Rp 125,000.00
- Pipa Black Steel 1,5" Tb. 2 mm 0.40 Btng Rp 405,000.00
- Pipa Black Steel 1,25" Tb. 2 mm 1.00 Btng Rp 375,000.00
- Kain Vinil 1 x 2 m 6.00 Lembar Rp 350,000.00
- Angkur D 19 Panjang 50 Cm 24.00 Bh Rp 30,500.00
- Paku Ripet Uk. 4,8 mm x 10 mm 389.00 Bh Rp 150.00
- Cat Minyak 7.00 Kg Rp 48,500.00
- Thinner ND 2.32 Gln Rp 75,000.00
Alat bantu 1.00 Ls Rp 5,000.00
Upah 7.00 Hr Rp 90,000.00
Jumlah
2 Tempat Pemadam Gantung
Bahan
- Multiplek 9 mm 0.07 Lbr Rp 135,000.00
- Fisher Uk. 6 mm Pj. 10 cm 4.00 Bh Rp 150.00
- Cat Minyak ( 2 Lapis ) 0.08 Kg Rp 48,500.00
- Meni Kayu 0.40 m2 Rp 700.00
- Thinner Nd 0.03 Gln Rp 75,000.00
Alat Bantu 1.00 ls Rp 1,000.00
Upah 0.14 Ls Rp 45,000.00
Jumlah
3 Tempat Pemadam Duduk
Bahan
- Multiplek 9 mm 0.07 Lbr Rp 135,000.00
- Kaso 4 x 6 0.63 Btng Rp 45,000.00
- Cat Minyak ( 2 Lapis ) 0.18 Kg Rp 48,500.00
- Meni Kayu 0.93 m2 Rp 700.00
- Thinner ND 0.10 Gln Rp 75,000.00
Alat Bantu 1.00 ls Rp 1,000.00
Upah 0.33 Ls Rp 45,000.00
Jumlah
4 Penutup Shaft. Uk. 1 m x 1 m
Matrial
- Kaso 4/6 1.50 Btng Rp 31,680.00
- Kaso 4/6 1.00 Btng Rp 31,680.00
- Multiplek 9 mm 0.62 Lbr Rp 135,000.00
- Cat Minyak 0.37 kg Rp 48,500.00
- Thinner ND 0.12 Gln Rp 75,000.00
- Alat Bantu 1.00 ls Rp 1,000.00
- Upah 0.25 Ls Rp 45,000.00
Jumlah

Page 24 of 39
Analisa Harga Fasilitas K3L
PROYEK : OFFICE TOWER SKY 18

No Uraian Pekerjaan Volume Satuan Harga Satuan


4 Tempat Kencing Temporary
Bahan
- Triplek 4 mm 0.84 Lbr Rp 62,500.00
- Hollo 4x4x2mm(ganti besi potongan) 2.32 Btng Rp 287,500.00
- Jerigen 2.00 Bh Rp 35,000.00
- Urinoir Bekas 1.00 Bh Rp 150,000.00
- Kran air 1.00 Bh Rp 25,000.00
- Paku Ripet 30.00 Bh Rp 150.00
- Cat Minyak 1.50 Kg Rp 48,500.00
- Thinner ND 0.50 Gln Rp 75,000.00
Alat bantu (paralon 1/5" 1.00 Ls Rp 35,000.00
Upah 0.33 Ls Rp 85,000.00

16 Ralling Tiap Lantai. Antar kolom, menggunakan tali 2 jalur atas bawah
Matrial
- Risher 4.00 Bh Rp 1,000.00
- Tambang Plastik D 8 mm 1.00 m1 Rp 2,080.00
- Jaring Pengaman 9.00 m2 Rp 7,500.00
- Cat Minyak 0.03 Klng Rp 48,500.00
- Thinner ND 0.01 Gln Rp 75,000.00
- Alat Bantu 1.00 ls Rp 1,000.00
- Upah 0.20 Ls Rp 90,000.00
Jumlah
17 Ralling Tiap Lantai. Uk. 6 m1 dengan Jarak Tiang 3 m
Matrial
- Pipa Black Steel 1,5 " Tb. 2 mm 0.33 Btng Rp 265,000.00
- Pipa Black Steel 01,5 " Tb. 1,6 mm 0.01 Btng Rp 106,000.00
- Plat Baja Uk. 15 x 15 x 5 mm 0.05 m2 Rp 609,375.00
- Dynabolt D 10. P. 7 Cm 8.00 Bh Rp 1,000.00
- Tambang Plastik D 8 mm 13.00 m1 Rp 2,080.00
- Jaring Pengaman 7.20 m2
- Cat Minyak 0.05 Klng Rp 48,500.00
- Thinner ND 0.02 Gln Rp 75,000.00
- Alat Bantu 1.00 ls Rp 3,000.00
- Upah 0.10 Hr Rp 90,000.00
Jumlah
- Jadi Ralling Tiap Lantai = Rp 5,660.83
14 SHE Information (Papan Pengumuman)
Matrial
- Hollow 4 x 4 x 2 mm 4.00 Btng Rp 143,750.00
- Triplek 6 mm 2.00 Lbr Rp 97,500.00
- Baut 10 mm P. 2 Cm 4.00 Bh Rp 1,050.00
- Paku Ripet 4,8 x 10 mm 32.00 Bh Rp 300.00
- Cat Minyak 1.61 kg Rp 48,500.00
- Thinner ND 0.53 Gln Rp 75,000.00
- Alat Bantu 1.00 ls Rp 1,000.00
- Upah 1.00 Ls Rp 45,000.00
Jumlah
Page 25 of 39
Analisa Harga Fasilitas K3L
PROYEK : OFFICE TOWER SKY 18

No Uraian Pekerjaan Volume Satuan Harga Satuan


5 Tempat Helm ( 1 Helm )
Bahan
- Triplek 9 mm 0.05 Lbr Rp 135,000.00
- Fisher 5 Cm. 6 mm 4.00 Bh Rp 1,000.00
- Cat Minyak ( 2 Lapis ) 0.07 Kg Rp 48,500.00
- Meni Kayu 0.32 m2 Rp 700.00
- Thinner ND 0.02 Gln Rp 75,000.00
Alat Bantu 1.00 ls Rp 1,000.00
Upah 0.10 Ls Rp 45,000.00
Jumlah
6 Tempat Sampah 3 Tong
- Matrial
- Drum 1/2 3.00 Bh Rp 58,750.00
- Hollow 4 x 4 x 2 mm 2.00 Btng Rp 143,750.00
- Triplek 9 mm 0.60 Lbr Rp 135,000.00
- Pilox 1.00 Klng Rp 23,500.00
- Cat Minyak 2.55 Kg Rp 48,500.00
- Thinner ND 0.73 Gln Rp 75,000.00
- Baut D3 mm 8.00 Bh Rp 1,200.00
- Engsel Tutup 6.00 Bh Rp 10,000.00
- Alat Bantu 1.00 ls Rp 1,500.00
- Upah 1.50 Ls Rp 85,000.00
Jumlah
7 Tempat Sampah 1 Tong
- Matrial
- Drum 1/2 1.00 Bh Rp 58,750.00
- Triplek 9 mm 0.09 Lbr Rp 135,000.00
- Engsel Tutup 2.00 Bh Rp 10,000.00
- Cat Minyak 0.60 Kg Rp 48,500.00
- Pilox 1.00 Klng Rp 23,500.00
- Thinner ND 0.20 Gln Rp 75,000.00
- Besi D 13 0.94 Kg Rp 8,000.00
- Alat Bantu 1.00 ls Rp 1,000.00
- Upah 0.14 Ls Rp 45,000.00
Jumlah
10 Tempat Merokok
Matrial
- Hollow 4 x 4 x 2 mm (ganti besi potong 4.00 Btng Rp 287,500.00
- Triplek 9 mm 0.03 Lbr Rp 135,000.00
- Seng Gelombang, Uk. 0,8 x 1,8 3.00 Lbr Rp 87,500.00
- Besi Beton D 12 2.67 Kg Rp 6,500.00
- Paku Ripet 5 x 10 mm 27.00 m1 Rp 300.00
- Cat Minyak 0.83 Kg Rp 48,500.00
- Thinner ND 0.27 Gln Rp 75,000.00
- Pilox 0.50 Klng Rp 23,500.00
- Alat Bantu 1.00 ls Rp 1,500.00
- Upah 0.67 Ls Rp 85,000.00
Jumlah
Page 26 of 39
Analisa Harga Fasilitas K3L
PROYEK : OFFICE TOWER SKY 18

No Uraian Pekerjaan Volume Satuan Harga Satuan


9 Rambu TC
Matrial
- Triplek 9 mm 1.21 Lbr Rp 135,000.00
- Cat Minyak 1.44 Kg Rp 48,500.00
- Thinner ND 0.48 Gln Rp 75,000.00
- Pilox 1.00 Klng Rp 23,500.00
- Alat Bantu 1.00 ls Rp 1,000.00
- Upah 0.33 Ls Rp 45,000.00
Jumlah
8 Rambu Lalu Lintas
Matrial
- Pipa Black Steel 2" Tb. 2 mm 1.00 Btng Rp 395,000.00
- Rambu Neon Box. 0.9 x 1.2. Tb. 0.25 1.08 m2 Rp 1,000,000.00
- Lampu Rotari 1.00 Bh Rp 175,000.00
- Cat Minyak 0.15 Kg Rp 48,500.00
- Thinner ND 0.06 Gln Rp 75,000.00
- Alat Bantu 1.00 ls Rp 2,000.00
- Upah 0.10 Ls Rp 45,000.00
Jumlah
- Faktor Keamanan 10.00 % Rp 1,668,469.00
Total
12 Tempat Sampah Akhir
Matrial
- Hollow 4 x 4 x 2 mm 15.00 Btng Rp 287,500.00
- Triplek 9 mm 9.00 Lbr Rp 135,000.00
- Engsel Bubut 8 Bh 8.00 Bh Rp 10,500.00
- Paku Ripet 15 cm 376.00 Bh Rp 300.00
- Mur + Baut D10 mm P. 8 cm 32.00 Bh Rp 1,560.00
- Cat Minyak 5.36 kg Rp 48,500.00
- Thinner ND 1.78 Gln Rp 75,000.00
- Alat Bantu 1.00 ls Rp 5,000.00
- Upah 3.00 Hr Rp 85,000.00
Jumlah
13 Ralling Core Lift. Uk. 1' meter
Matrial
- Kaso 4/6 0.63 Btng Rp 31,680.00
- Triplek 6 mm 0.10 Lbr Rp 97,500.00
- Cat Minyak 0.27 kg Rp 48,500.00
- Thinner ND 0.09 Gln Rp 75,000.00
- Alat Bantu 1.00 ls Rp 1,000.00
- Upah 0.14 Ls Rp 45,000.00
Jumlah
- Faktor Keamanan 10.00 % Rp 57,250.01
Total

Page 27 of 39
Analisa Harga Fasilitas K3L
PROYEK : OFFICE TOWER SKY 18

No Uraian Pekerjaan Volume Satuan Harga Satuan


15 Ralling Galian 330 m1
Matrial
- Pipa Black Steel 2" Tb. 1,6 mm 55.00 Btng Rp 290,000.00
- Pipa Black Steel 1,5" Tb. 1,6 mm 19.00 Btng Rp 245,000.00
- Pipa Black Steel 1" Tb. 1,6 mm 55.00 Btng Rp 210,000.00
- Plat Baja Uk. 15 x 15 x 5 mm 1.00 Lbr Rp 1,755,000.00
- Dynabolt D 10. P. 7 Cm 444.00 Bh Rp 1,650.00
- Cat Minyak 19.00 Klng Rp 48,500.00
- Thinner ND 7.00 Gln Rp 75,000.00
- Kawat Las 4.00 Box Rp 350,000.00
- Resibon 7.00 Bh Rp 68,000.00
- Alat Bantu 1.00 ls Rp 150,000.00
- Upah 7.00 Hr Rp 165,000.00
Jumlah
- Faktor Keamanan 10.00 % Rp 39,270,100.00
Total
16 Ralling Galian Basement 169 m1
Matrial
- Pipa Black Steel 2" Tb. 1,6 mm 28.00 Btng Rp 290,000.00
- Pipa Black Steel 1,5" Tb. 1,6 mm 10.00 Btng Rp 245,000.00
- Tambang Plastik kuning D 10 mm 169.00 m1 Rp 3,800.00
- Plat siku 5 X 5 3.00 Btng Rp 250,000.00
- Dynabolt D 10. P. 7 Cm 230.00 Bh Rp 1,650.00
- Cat Minyak 9.00 Klng Rp 63,000.00
- Thinner ND 3.00 Gln Rp 67,500.00
- Kawat Las 2.00 Box Rp 350,000.00
- Resibon 4.00 Bh Rp 68,000.00
- Mur + Baut D10 mm P. 8 cm 122.00 bh Rp 1,550.00
- Alat Bantu 1.00 ls Rp 150,000.00
- Upah 4.00 Hr Rp 165,000.00
Jumlah
- Faktor Keamanan 10.00 % Rp 15,082,300.00
Total
18 Safety Net Horisontal Sisi Bangunan
Matrial
- Pipa Black Steel 1,5 " Tb. 2 mm 3.20 Btng Rp 265,000.00
- Siku 5 x 5 x 5mm 0.10 Btng Rp 335,000.00
- Dynabolt D 12. P. 7 Cm 8.00 Bh Rp 3,500.00
- Seling D 10 mm 15.00 m1 Rp 11,600.00
- Kawat Harmonika 9.24 m2 Rp 25,000.00
- Polinet 9.24 m2 Rp 7,500.00
- Engsel Bubut 32 mm 2.00 Bh Rp 15,000.00
- Klem U bolt D 3/8 8.00 Bh Rp 2,600.00
- Besi D 12 17.41 Kg Rp 8,000.00
- Cat Minyak 0.64 Klng Rp 48,500.00
- Zinchromat 0.64 Klng Rp 2,600.00
- Thinner ND 0.21 Gln Rp 75,000.00
- Alat Bantu 1.00 ls Rp 2,000.00
Page 28 of 39
Analisa Harga Fasilitas K3L
PROYEK : OFFICE TOWER SKY 18

No Uraian Pekerjaan Volume Satuan Harga Satuan


- Upah 0.67 Hr Rp 90,000.00
Jumlah
- Faktor Keamanan 10.00 % Rp 1,684,661.20
Total
- Jadi Safety Net Horisontal = Rp 231,640.92

Page 29 of 39
Analisa Harga Fasilitas K3L
PROYEK : OFFICE TOWER SKY 18

No Uraian Pekerjaan Volume Satuan Harga Satuan


17 Ralling Tiap Lantai. Jarak 3 m dengan 2 Tiang
Matrial
- Pipa Black Steel 1,5 " Tb. 2 mm 0.17 Btng Rp 265,000.00
- Pipa Black Steel 01,5 " Tb. 1,6 mm 0.01 Btng Rp 106,000.00
- Plat Baja Uk. 15 x 15 x 5 mm 0.02 m2 Rp 609,375.00
- Dynabolt D 10. P. 7 Cm 4.00 Bh Rp 2,800.00
- Tambang Plastik D 8 mm 7.00 m1 Rp 2,080.00
- Jaring Pengaman 3.60 m2 Rp 7,500.00
- Cat Minyak 0.02 Klng Rp 48,500.00
- Thinner ND 0.01 Gln Rp 75,000.00
- Alat Bantu 1.00 ls Rp 1,000.00
- Upah 0.50 Hr Rp 90,000.00
Jumlah
- Faktor Keamanan 10.00 % Rp 159,982.94
Total
- Jadi Ralling Tiap Lantai = Rp 58,660.41
17 Ralling Tiap Lantai. Uk. 6 m1 dengan Jarak Tiang 3 m
Matrial
- Pipa Black Steel 1,5 " Tb. 2 mm 25.00 Btng Rp 265,000.00
- Pipa Black Steel 01,5 " Tb. 1,6 mm 1.00 Btng Rp 106,000.00
- Plat Baja Uk. 15 x 15 x 5 mm 3.38 m2 Rp 609,375.00
- Dynabolt D 10. P. 7 Cm 600.00 Bh Rp 2,800.00
- Tambang Plastik D 8 mm 892.00 m1 Rp 2,080.00
- Jaring Pengaman 535.20 m2 Rp 7,500.00
- Cat Minyak 4.50 Klng Rp 48,500.00
- Thinner ND 1.50 Gln Rp 75,000.00
- Alat Bantu 1.00 ls Rp 1,000.00
- Upah 30.00 Hr Rp 90,000.00
Jumlah
- Faktor Keamanan 10.00 % Rp 19,368,750.63
Total
- Jadi Ralling Tiap Lantai = Rp 47,770.46

Page 30 of 39
alisa Harga Fasilitas K3L
EK : OFFICE TOWER SKY 18

Jumlah

Rp -
Rp 2,875,000.00
Rp 375,000.00
Rp -
Rp -
Rp -
Rp 2,100,000.00
Rp -
Rp -
Rp 339,500.00
Rp 174,300.00
Rp -
Rp -
Rp 6,450,180.00

Rp 9,450.00
Rp 600.00
Rp 3,880.00
Rp 280.00
Rp 2,250.00
Rp -
Rp -
Rp 16,460.00

Rp 9,450.00
Rp 28,350.00
Rp 8,730.00
Rp 651.00
Rp 7,470.00
Rp -
Rp -
Rp 54,651.00

Rp 47,520.00
Rp 31,680.00
Rp 83,355.70
Rp 17,945.00
Rp 9,165.00
Rp -
Rp -
Rp 189,665.70

Page 31 of 39
alisa Harga Fasilitas K3L
EK : OFFICE TOWER SKY 18

Jumlah

Rp 52,432.89

Rp 70,000.00
Rp 150,000.00
Rp 25,000.00
Rp 4,500.00
Rp 72,750.00
Rp 37,500.00
Rp 35,000.00
Rp -
Rp 491,901.17

Rp 4,000.00
Rp 2,080.00

Rp 6,080.00

Rp 27,040.00
Rp -
Rp 2,425.00
Rp 1,500.00
Rp 3,000.00
Rp -
Rp 33,965.00
/ m1

Rp 575,000.00
Rp 195,000.00
Rp 4,200.00
Rp 9,600.00
Rp 78,085.00
Rp 40,050.00
Rp -
Rp -
Rp 901,935.00
Page 32 of 39
alisa Harga Fasilitas K3L
EK : OFFICE TOWER SKY 18

Jumlah

Rp 6,795.30
Rp 4,000.00
Rp 3,530.80
Rp 220.50
Rp 1,800.00

Rp 16,346.60

Rp -
Rp -
Rp 81,000.00
Rp 23,500.00
Rp 123,675.00
Rp 54,780.00
Rp 9,600.00
Rp 60,000.00
Rp -
Rp -
Rp 352,555.00

Rp 58,750.00
Rp 12,802.35
Rp 20,000.00
Rp 29,189.24
Rp 23,500.00
Rp 15,189.00
Rp 7,507.66

Rp 166,938.24

Rp 4,050.00
Rp 262,500.00
Rp 17,325.36
Rp 8,100.00
Rp 40,090.59
Rp 20,550.00
Rp 11,750.00

Rp 364,365.95
Page 33 of 39
alisa Harga Fasilitas K3L
EK : OFFICE TOWER SKY 18

Jumlah

Rp 163,087.25
Rp 69,840.00
Rp 35,856.00
Rp 23,500.00

Rp 292,283.25

Rp 395,000.00
Rp 1,080,000.00
Rp 175,000.00
Rp 7,469.00
Rp 4,500.00
Rp 2,000.00
Rp 4,500.00
Rp 1,668,469.00
Rp 166,846.90
Rp 1,835,315.90

Rp 4,312,500.00
Rp 1,215,000.00
Rp 84,000.00
Rp 112,800.00
Rp 49,920.00
Rp 259,960.00
Rp 133,464.00

Rp 6,167,644.00

Rp 20,064.00
Rp 9,815.44
Rp 13,192.00
Rp 6,750.00
Rp 1,000.00
Rp 6,428.57
Rp 57,250.01
Rp 5,725.00
Rp 62,975.01

Page 34 of 39
alisa Harga Fasilitas K3L
EK : OFFICE TOWER SKY 18

Jumlah

Rp 15,950,000.00
Rp 4,655,000.00
Rp 11,550,000.00
Rp 1,755,000.00
Rp 732,600.00
Rp 921,500.00
Rp 525,000.00
Rp 1,400,000.00
Rp 476,000.00
Rp 150,000.00
Rp 1,155,000.00
Rp 39,270,100.00
Rp 3,927,010.00
Rp 43,197,110.00

Rp 8,120,000.00
Rp 2,450,000.00
Rp 642,200.00
Rp 750,000.00
Rp 379,500.00
Rp 567,000.00
Rp 202,500.00
Rp 700,000.00
Rp 272,000.00
Rp 189,100.00
Rp 150,000.00
Rp 660,000.00
Rp 15,082,300.00
Rp 1,508,230.00
Rp 16,590,530.00

Rp 848,000.00
Rp 33,500.00
Rp 28,000.00
Rp 174,000.00
Rp 231,000.00
Rp 69,300.00
Rp 30,000.00
Rp 20,800.00
Rp 139,280.00
Rp 31,137.00
Rp 1,669.20
Rp 15,975.00
Rp 2,000.00
Page 35 of 39
alisa Harga Fasilitas K3L
EK : OFFICE TOWER SKY 18

Jumlah
Rp 60,000.00
Rp 1,684,661.20
Rp 168,466.12
Rp 1,853,127.32
/ m1

Page 36 of 39
alisa Harga Fasilitas K3L
EK : OFFICE TOWER SKY 18

Jumlah

Rp 45,050.00
Rp 742.00
Rp 13,710.94
Rp 11,200.00
Rp 14,560.00
Rp 27,000.00
Rp 970.00
Rp 750.00
Rp 1,000.00
Rp 45,000.00
Rp 159,982.94
Rp 15,998.29
Rp 175,981.23
/ m1

Rp 6,625,000.00
Rp 106,000.00
Rp 2,056,640.63
Rp 1,680,000.00
Rp 1,855,360.00
Rp 4,014,000.00
Rp 218,250.00
Rp 112,500.00
Rp 1,000.00
Rp 2,700,000.00
Rp 19,368,750.63
Rp 1,936,875.06
Rp 21,305,625.69
/ m1

Page 37 of 39
PT.PP(PERSERO) Tbk
PROYEK : OFFICE TOWER SKY 18
RENCANA KEBUTUHAN FASILITAS K3L

FASILITAS
VOLUME
NO LOKASI T. APAR T. APAR T. SAMPAH T. SAMPAH T. SAMPAH TEMPAT TEMPAT SLOGAN SHE KOTAK BENDERA
LUASAN APAR
GANTUNG DUDUK 3 TONG 1 TONG AKHIR KENCING MEROKOK K3L INFORMASI P3K (1 SET )

A Fasilitas Proyek
1 Pos 1 Depan (Pintu Utama 1 1 1 1 1 1 1 1
2 Pos 2 Belakang Pintu Pekerja 1 1 1 1 1
3 R.P3K 1 1 1 1
4 Gudang Logistik 1 1
5 Area lapangan
- Los Kerja Besi 1 1 1 1 1
- Los Kerja Bekisting 1 1 1
- TC 1 1 1
- TC 2 1 1
- ALIMAX 1 1 1
- ALIMAX 2 1 1
- Tempat BBM 1 1 1
- Tower (Basmt s/d atap) bs,smb,grd 26 26 26 13 13
6 Bedeng Pekerja 1 1 2 1 1
7 Toilet Pekerja 1
8 Warung Pekerja 1 1 3
9 Kantor PT. PP 1 1 1 2 1 1 1 1
40 4 36 3 38 1 14 17 2 2 4 2

Priyo Leksono
Safety, Health & Environmental Officer
PT. PP (PERSERO) Tbk
CABANG III

SPP OBAT P3K


PROYEK : OFFICE TOWER SKY 18

NO URAIAN UKURAN JUMLAH


1 Kapas 100 Gram 4 bh
2 Perban Roll 4 roll
3 Plaster no.1226 (1.25cm X 5m) 6 roll
4 Obat Luka Bakar ( Vita Gel ) 10 gram 4 tube
5 Kasa Hidrofil Steril isi 16 lbr :16cm X 16cm 5 kotak
6 Sopra-Tulle bh 4 bh
7 Gelas Pencuci Mata ukuran mata 2 bh
8 Boorwater (Air Pencuci Mata) 120 ml 4 bh
9 Obat Tetes Mata (Insto) 15 ml 4 bh
10 Betadine 60 ml 4 bh
11 Rivanol 300 ml 4 bh
12 Alkohol 300 ml 4 bh
13 Balsem (Caplang) 100 gram 4 bh
14 Peniti isi 10 peniti 2 bh
15 Gunting 20 cm 2 bh
16 Vinset sedang 4 bh
17 Sarung Tangan Karet sedang 4 pasang
18 Minyak Kayu Putih 100 ml 3 bh
19 Obat Gatal (Salep 88) 6 gram 3 bh
20 Obat Luka Robek (Sulfanilamid) 10 gram 3 bh

Note : - Keterangan diatas adalah standar obat P3K

Disetujui, Jakarta, September 2013

Priyo Leksono
CM SHEO