TIME SCHEDULE

KONTRAKTOR : PT. BATARA SAKTI JAYA


BLOK/NO. : RUMAH CONTOH 1 UNIT
PROYEK : GRAHAYANA
LOKASI : PINAYUNGAN - SIRNABAYA, KARAWANG

120.00

MEI JUNI
NO. URAIAN PEKERJAAN BOBOT DURASI
1 2 3 4 5 6 7

100.00

1 PEKERJAAN PERSIAPAN 0.95 15 0.06 0.06 0.06 0.06

2 PEKERJAAN LANTAI SATU ( ± 0.00 ) 26.60 5 5.32 5.32 5.32

LIBUR ID
3 PEKERJAAN LANTAI DUA ( +3.45 )
16.75 5 80.00

4 PEKERJAAN ATAP 6.36 2

5 PEKERJAAN PINTU DAN JENDELA 11.79 6


60.00
R IDUL FITRI
60.00

6 PEKERJAAN PLUMBING DAN SANITASI 6.09 10

7 PEKERJAAN INSTALASI LISTRIK


5.09 10

8 PEKERJAAN PLAFON 4.25 2 40.00

9 PEKERJAAN LANTAI 10.02 2

10 PEKERJAAN TAMPAK 0.36 2


20.00
11 PEKERJAAN PENGECATAN
6.29 6

12 PEKERJAAN CARPORT 3.98 2

13 PEKERJAAN RALLING 1.47 2


0.00
1 2 3 4 5 6 7

TOTAL 100 0.00 0.06 5.38 5.38 5.38 0.00 0.00 0.00
PROGRES RENCANA 0.00 0.06 5.45 10.83 16.22 16.22 16.22 16.22
REALISASI PROGRES PEKERJAAN
DEVIASI

Disetujui, Diperiksa Oleh,


PT. CIPTA GRAHA SEJAHTERA PT. CIPTA GRAHA SEJAHTERA
BUKHORI MUSLIM FEBY A.
SITE KOORDINATOR SUPERVISIOR
0.00

JULI AGUSTUS SEPTEMBER


8 9 10 11 12 13 14 15 16 17 18

0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06

5.32 5.32

3.35 3.35 3.35 3.35 3.35

3.18 3.18

1.97 1.97 1.97 1.97 1.97 1.97


0.61 0.61 0.61 0.61 0.61 0.61 0.61 0.61 0.61 0.61

0.51 0.51 0.51 0.51 0.51 0.51 0.51 0.51 0.51 0.51

2.13 2.13

5.01 5.01

0.18 0.18

1.05 1.05 1.05 1.05 1.05 1.05

1.99 1.99

0.73 0.73
6 7 8 9 10 11 12 13 14 15 16 17 18

5.99 9.85 4.53 4.53 7.89 13.03 13.32 11.93 4.93 4.19 3.59
22.21 32.06 36.59 41.12 49.01 62.04 75.36 87.29 92.22 96.41 100.00
PT. BATARA SAKTI JAYA ( BSJ )

Hal : PROGRESS RUMAH CONTOH


Pekerjaan : Rumah type BHUVANA Standar
Dasar Perhitungan : Gambar Rencana
Lokasi :GRAHAYANA
Luas Bangunan : 85 m²

31 juli 2018
No Uraian Pekerjaan Volume Satuan Bobot Rata2 Bobot Koreksi
A1
I. PEKERJAAN PERSIAPAN
1 Pekerjaan Persiapan Kerja 1 ls 0.95% 100 0.95
0.95% 0.95

II. PEKERJAAN LANTAI SATU ( ± 0.00 )


1 Pekerjaan pasang bowplang 31 m' 0.17% 100 0.17
2 Galian tanah pondasi dan sloof + Pemadatan 29.83 m³ 0.43% 100 0.43
3 Urug pasir bawah pondasi t 10 cm 4.61 m³ 0.41% 100 0.41
4 Lantai kerja pondasi /sloof t 5 cm 2.28 m³ 0.38% 100 0.38
5 Cor beton pondasi P-1 1.305 m³ 0.89% 100 0.89
6 Cor beton pondasi J-1 s/d J-4 3.94 m³ 3.70% 100 3.70
7 Cor beton sloof 3.03 m³ 2.06% 100 2.06
8 Pek. urug tanah kembali sisi pondasi 22.47 m³ 0.14% 100 0.14
9 Cor beton kolom K-0 0.28 m³ 0.39% 100 0.39
10 Cor beton kolom K-1 0.51 m³ 0.72% 100 0.72
11 Cor beton kolom K-1A 0.26 m³ 0.37% 100 0.37
12 Cor beton kolom K-2A 0.20 m³ 0.28% 100 0.28
13 Cor beton kolom K-3A 0.18 m³ 0.25% 100 0.25
14 Cor beton kolom KP 0.42 m³ 0.38% 100 0.38
15 Cor beton kolom KP-1 0.38 m³ 0.34% 100 0.34
16 Cor beton kolom KP-2 0.08 m³ 0.07% 100 0.07
17 Cor beton Canopy 1.81 m³ 1.62% 100 1.62
18 Cor beton ringbalok 0.45 m³ 0.40% 100 0.40
19 Pek. Cor beton tangga 1.41 m³ 1.46% 100 1.46
20 Pek. Cor beton meja dapur 0.12 m³ 0.08% -
21 Pek. Dinding bata kamar mandi trasraam 44.73 m² 1.54% 100 1.54
22 Pek. Dinding bata merah 168.7 m² 5.79% 100 5.79
23 Pek. plesteran dinding 347.6 m² 3.17% 80 2.53
24 Pek. acian dinding 324.3 m² 1.56% -
26.60% 24.33

III. PEKERJAAN LANTAI DUA ( +3.45 )


1 Cor beton balok 11/20 (+3.45) 0.304 m³ 0.24% 95 0.23
2 Cor beton balok 11/25 (+3.45) 0.059 m³ 0.05% 95 0.04
3 Cor beton balok 11/30 (+3.45) 0.736 m³ 0.58% 95 0.56
4 Cor beton balok 15/57 (+3.45) 0.684 m³ 0.54% 95 0.52
5 Cor beton balok 22/20 (+3.45) 0.396 m³ 0.31% 95 0.30
6 Cor beton balok 22/30 (+3.45) 0.099 m³ 0.08% 95 0.07
7 Cor beton plat lantai t 12 cm 3.29 m³ 2.96% 95 2.81
8 Cor beton kolom K-0 0.22 m³ 0.31% 95 0.29
9 Cor beton kolom K-2 0.33 m³ 0.47% 95 0.44
10 Cor beton kolom K-2A 0.24 m³ 0.34% 95 0.32
11 Cor beton kolom KP 0.05 m³ 0.04% 100 0.04
12 Cor beton balok 11/20 (+6,90) 0.18 m³ 0.29% 95 0.28
13 Cor beton balok 11/25 (+6,90) 0.08 m³ 0.13% 95 0.12
14 Cor beton balok 11/30 (+6,90) 0.35 m³ 0.57% 95 0.54
15 Cor beton balok 11/55 (+6,90) 0.36 m³ 0.59% 95 0.56
16 Cor beton balok 15/55 (+6,90) 0.42 m³ 0.68% 95 0.65
17 Cor beton balok 22/25 (+6,90) 0.09 m³ 0.14% 95 0.13
18 Pek. Cor beton plat atap t 12 cm 0.60 m³ 0.54% 95 0.51
19 Pek. Cor beton canopy 0.89 m³ 0.80% 95 0.76
20 Pek. Cor beton ringbalok 0.45 m³ 0.40% 95 0.38
21 Pek. Dinding bata kamar mandi trasraam 6.6 m² 0.23% 100 0.23
22 Pek. Dinding bata 114.4 m² 3.93% 100 3.93
23 Pek. Plester dinding 182 m² 1.66% 70 1.16
24 Pek. acian dinding 182 m² 0.88% 10 0.09
16.75% 14.96
31 juli 2018
No Uraian Pekerjaan Volume Satuan Bobot Rata2 Bobot Koreksi
A1
IV. PEKERJAAN ATAP
1 Rangka atap baja ringan truss C 75 70.24 m² 2.92% 30 0.88
2 Atap genteng beton plate 70.24 m² 1.50% -
3 Genteng nok 21.17 m' 0.65% -
4 Nok Ujung 4 bh 0.05% -
5 Nok Tiga Arah 2 bh 0.03% -
6 Lisplang 37.5 m' 0.78% -
7 Flasing seng/talang upet 27.35 m' 0.39% -
8 Genteng tepi 1.7 m' 0.02% -
6.36% 0.88

V. PEKERJAAN PINTU DAN JENDELA


1 P 1 1 bh 1.04% -
2 P 2 4 bh 2.90% -
3 P 3 2 bh 0.26% -
4 P 4 1 bh 0.88% -
5 P 6 1 bh 0.59% -
6 J2 3 bh 1.59% -
7 J6 1 bh 0.68% -
8 J7 1 bh 0.71% -
9 J8 1 bh 0.30% -
10 J9 1 bh 0.31% -
11 J 10 1 bh 0.92% -
12 V1 1 bh 0.17% -
13 V2 1 bh 0.23% -
14 Opening pintu dan jendela 104 m' 1.20% -
11.79% -

VI. PEKERJAAN PLUMBING DAN SANITASI


Pek. instalasi + Air Bersih
1 Instalasi pipa pvc wavin aw Ø ½ " 28.00 m' 0.09% -
2 Instalasi pipa pvc wavin aw Ø ¾ " 25.00 m' 0.10% -
3 Pek. Hand Shower Set 2.00 set 0.28% -
4 Pek. Shower Jet 2.00 set 0.15% -
5 Pek. Wastafel Set 2.00 set 0.50% -
6 Pek. kitchen sink single ex royal 1.00 bh 0.14% -
7 Pek. Kran Sink ½ " 1.00 set 0.07% -
8 Pek. Kran botol ½" (Carport) 1.00 set 0.05% -
9 Pek. Ground tank vol 1 m³ 1.00 bh 0.63% -
10 Pek. Mesin pompa air jet pump 1.00 bh 0.52% -
Pek. instalasi + Air Kotor
1 Instalasi pipa pvc wavin D Ø 3 " 40.00 m' 0.40% 50 0.20
2 Instalasi pipa pvc wavin D Ø 4 " 32.00 m' 0.37% 70 0.26
3 Instalasi pipa pvc wavin aw Ø 1 " 16 m' 0.16% -
4 Instalasi pipa pvc wavin aw Ø 1¼ " 8.00 m' 0.04% -
5 Instalasi afur AC pipa pvc Ø ¾ " 39.00 m' 0.16% -
6 Pek. Bio septictank vol. 1 m³ 1.00 bh 0.71% -
7 Pek. Closet duduk 2.00 bh 0.88% -
8 Pek. Floor drain Ø 3 " 2.00 bh 0.10% -
9 Pek. Roof drain Ø 3" 2.00 bh 0.06% -
10 Pek. bak kontrol 35x35x35 pas bata 1.00 bh 0.18% -
11 Pek. bak kontrol 50x50x100 pas bata 1.00 bh 0.40% -
12 Pek. Clean Out Ø 2 " 1.00 set 0.04% -
13 Pek. Clean Out Ø 4" 1.00 set 0.06% -
6.09% 0.46

VII. PEKERJAAN INSTALASI LISTRIK


1 Pek. instalasi K W H Meter + Kabel Tufur 1 bh 0.19% 10 0.02
2 Pek. instalasi + Fuse Box 2 bh 0.45% 10 0.04
3 Pek. instalasi + Saklar single 5 titik 0.47% 10 0.05
4 Pek. instalasi + Saklar double 4 titik 0.37% 10 0.04
5 Pek. instalasi + saklar double, tangga (hotel + tunggal) 2 titik 0.19% 10 0.02
6 Pek. instalasi + Stop kontak 8 titik 0.78% 10 0.08
7 Pek. instalasi + Stop kontak AC 5 titik 0.56% 10 0.06
8 Pek. instalasi + stop kontak pompa 1 titik 0.10% 10 0.01
9 Pek. instalasi + Anthenna 1 titik 0.05% -
10 Pek. instalasi + Telefon 1 titik 0.05% -
31 juli 2018
No Uraian Pekerjaan Volume Satuan Bobot Rata2 Bobot Koreksi
A1
11 Pek. instalasi + Down light 11 titik 1.23% -
12 Pek. instalasi + titik lampu 4 titik 0.37% -
13 Pek. instalasi + lampu taman 1 titik 0.09% -
14 Konsoil Sertifikat Laik Operasi ( SLO ) + Gambar 1 unit 0.10% -
15 Pek. instalasi arde 1 titik 0.08% -
5.09% 0.31

VIII. PEKERJAAN PLAFON


1 Gypsum t 9 mm ex Jaya board type GP 1 71.56 m² 2.25% -
Rangka hollow galvanis 40x40, 20x40 t 0,5mm
2 Lis gypsum type bambu L 8 cm 140.35 m' 0.77% -
3 Gypsum t 9 mm ex Jaya board type GP 2 6.1 m² 0.16% -
Rangka hollow galvanis 40x40, 20x40 t 0,5mm
4 Lis gypsum type bambu L 5 cm 14.3 m' 0.08% -
5 Tritis plafon GRC t 6 mm GRC 15.88 m² 0.48% -
Rangka hollow galvanis 40x40, 20x40 t 0,5mm
6 Lis kayu type bambu L 5 cm 64.8 m' 0.35% -
7 Canopy beton finish cat 20.21 m² 0.16% -
4.25% -

IX. PEKERJAAN LANTAI


1 Pek. Urug pasir bawah lantai t 8 cm 4.4 m³ 0.39% -
2 Pek. instalasi + Soft soil 5 bh 0.18% -
3 Pek. Lantai kerja bawah lantai t 4 cm 2.2 m³ 0.37% -
4 Pek. lantai Homogeneous Tile 60x60 HT 1 65.7 m² 3.06% -
5 Plin tinggi : 10cm 69.31 m' 1.58% -
6 Pek. lantai Homogeneous Tile 60x60 HT 2 10.42 m² 0.57% -
7 Plin tinggi : 10cm 13.7 m' 0.31% -
8 Kamar mandi keramik 30x30 cm KR 1 2.87 m² 0.10% -
9 Trap teras keramik 30x30 cm KR 2 3.9 m² 0.13% -
10 Plin tinggi : 10cm 3.2 m' 0.07% -
11 Keramik dinding : KR 3 24.01 m² 1.23% -
12 Keramik dinding : KR 4 4.15 m² 0.21% -
13 Meja dapur Homogeneous Tile uk.60X60 HT 3 4 m² 0.23% -
14 Pek. Fin lantai tangga Homogeneous Tile uk.60X60 HT 1 12.69 m² 0.59% -
15 Plin trap tangga tinggi : 10cm 7.6 m' 0.17% -
16 Pek. Water profing dak atap & Kamar mandi 20 m² 0.42% -
17 Pek. Screed dak atap & Kamar mandi 20 m² 0.42% -
10.02% -

X. PEKERJAAN TAMPAK
1 Penebalan plester type A 2 m² 0.04% -
2 Penebalan plester type B 8.53 m² 0.19% -
3 Penebalan plester type C 5.51 m² 0.12% -
0.36% -

XI. PEKERJAAN PENGECATAN


1 Dinding luar 324.97 m² 2.81% -
2 Dinding dalam 324.97 m² 2.08% -
3 Plafon 113.75 m² 0.73% -
4 Listplank 76.81 m² 0.67% -
6.29% -

XII. PEKERJAAN CARPORT


1 Pek. Urug pasir bawah lantai t 10 cm 0.12 m² 0.01% -
2 Pek. Cor beton t 8 cm k 175 1.152 m² 0.73% -
3 Pek. lantai finis aci dan nat 14.25 m² 0.11% -
4 Pek. Rangka atap uk.5x10cm t=2mm (rangka luar), 15 m² 3.13% -
uk.4x4cm t=2mm (rangka dalam) fin. Polycarbonat
3.98% -

XIII. PEKERJAAN RALLING


1 Ralling Tangga 7 m' 0.84% -
2 Ralling Balkon 5.2 m' 0.63% -
1.47% -

Grand Total ( I - XIII ) 100% 41.89


REKAPITULASI PROGRES PEKERJAAN
PROYEK GRAHAYANA
KONTRAKTOR : PT. BATARA SAKTI JAYA
LOKASI : BLOK A-1/02( R. CONTOH )

31 juli 2018
PROGRESS PROGRESS PROGRESS
NO. URAIAN PEKERJAAN BOBOT MINGGU DEVIASI
RENCANA AKTUAL
LALU
1 PEKERJAAN PERSIAPAN 0.95 0.95 0.51 0.95 0.44
2 PEKERJAAN LANTAI SATU ( ± 0.00 ) 26.60 23.12 26.60 24.33 (2.28)
3 PEKERJAAN LANTAI DUA ( +3.45 ) 16.75 5.59 10.05 14.96 4.91
4 PEKERJAAN ATAP 6.36 - - 0.88 0.88
5 PEKERJAAN PINTU DAN JENDELA 11.79 - - - -
6 PEKERJAAN PLUMBING DAN SANITASI 6.09 0.46 2.44 0.46 (1.98)
7 PEKERJAAN INSTALASI LISTRIK 5.09 - 1.53 0.31 (1.22)
8 PEKERJAAN PLAFON 4.25 - - - -
9 PEKERJAAN LANTAI 10.02 - - - -
10 PEKERJAAN TAMPAK 0.36 - - - -
11 PEKERJAAN PENGECATAN 6.29 - - - -
12 PEKERJAAN CARPORT 3.98 - - - -
13 PEKERJAAN RALLING 1.47 - - - -
TOTAL BOBOT 100.00 100.00%
TOTAL PROGRES MINGGU LALU 30.11%
TOTAL PROGRES RENCANA 41.12%
TOTAL PROGRES AKTUAL 41.89%
KEMAJUAN PROGRESS MINGGU INI 11.78%
TOTAL DEVIASI 0.76%

DI PERIKSA OLEH, DIKETAHUI OLEH,

( FEBY A. ) ( BUKHORI MUSLIM )