REKAPITULASI BILL OF QUANTITY

PEKERJAAN PEMBANGUNAN GEDUNG

JUMLAH
NO. URAIAN PEKERJAAN
(Rp.)
1 2 3
I PEKERJAAN PERSIAPAN 122,825,000
II PEKERJAAN SITE DEVELOPMENT 283,493,868
III PEKERJAAN ARSITEKTUR 2,335,385,727
IV PEKERJAAN FURNITURE 124,714,500
V PEKERJAAN STRUKTUR 1,423,111,716
VI PEKERJAAN MEKANIKAL/ELEKTRIKAL 1,133,412,000

JUMLAH 5,422,942,812
PPN 10% 542,294,281
TOTAL PEKERJAAN 5,965,237,093
PEMBULATAN 5,965,237,000

terbilang : Lima Millyard Sembilan Ratus Enam Puluh Lima Juta Dua Ratus Tiga Puluh Tujuh Ribu Sembilan Puluh
Tiga Rupiah
BILL OF QUANTITY
PEKERJAAN PEMBANGUNAN GEDUNG

PEKERJAAN : PERSIAPAN
HARGA SATUAN JUMLAH
NO. URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6

I PEKERJAAN PERSIAPAN

1 Direksi Keet 16.00 m2 1,250,000 20,000,000


(Untuk barak kerja dan gudang dapat memanfaatkan ruangan eksisting yg ada)
2 Air dan Listrik Kerja 10.00 bln 1,000,000 10,000,000
3 Administrasi Proyek dan Dokumentasi 10.00 bln 5,000,000 50,000,000
4 Pagar depan pengaman proyek t = 180 cm 21.00 m' 350,000 7,350,000
5 Pembersihan lokasi 1,100.00 m2 15,000 16,500,000
6 Papan nama proyek 1.00 ls 3,500,000 3,500,000
7 Pek. papan bowplank & marking 73.00 m' 75,000 5,475,000
8 Pembuatan As Build Drawing 1.00 ls 10,000,000 10,000,000

TOTAL PEKERJAAN PERSIAPAN 122,825,000


BILL OF QUANTITY
PEKERJAAN PEMBANGUNAN GEDUNG

PEKERJAAN : SITE DEVELOPMENT


HARGA SATUAN JUMLAH
NO. URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6

II PEKERJAAN SITE DEVELOPMENT

I PEKERJAAN PAGAR
A PEKERJAAN BONGKARAN
1 Pekerjaan bongkar tembok /pagar bata 11.00 m2 258,000 2,838,000
2,838,000

B PEKERJAAN PASANGAN BATA


1 Pekerjaan Pasangan Bata 1 : 5 10.00 m2 156,400 1,564,000
2 Pekerjaan Pasangan Batu Acak Templek Purwakarta + coating 41.00 m2 375,000 15,375,000
16,939,000
C PEKERJAAN PAGAR BESI
1 Pemasangan pagar besi hollow minimalis finish cat besi t : 1m' 17.80 m' 675,000 12,015,000
2 Pintu pagar besi hollow uk. 200x180 cm fin. Cat (Pintu Mobil) 2.00 set 1,450,000 2,900,000
3 Pintu pagar besi hollow uk. 90x120 cm fin. Cat (Pintu Pejalan Kaki) 1.00 set 750,000 750,000
Sub Total C 15,665,000

TOTAL PEKERJAAN PAGAR 35,442,000

II PEKERJAAN HALAMAN
A PEKERJAAN BONGKARAN
1 Pek. bongkar perkerasan halaman + buang puing 453.57 m2 258,000 117,021,834
Sub Total A 117,021,834

B PEKERJAAN PASANGAN PAVING DAN KANSTEEN


1 Pek. pasang paving blok keseluruhan 453.57 m2 221,700 100,557,134
(termasuk pek. pasir urug t: 10cm, abu beton t: 2cm)
2 Kanstin Beton dan Car stopper 81.00 m' 186,100 15,074,100
Sub Total B 115,631,234
C PEKERJAAN TAMAN
1 Pot taman pas. Bata + Plesteran + Acian 25.00 m2 266,400 6,660,000
2 Urug tanah taman t : 30 cm 7.65 m 3
242,000 1,851,300
3 Rumput Gajah Mini (terpasang) 15.00 m2 75,000 1,125,000
4 Tanaman Perdu (terpasang) 53.50 m' 75,000 4,012,500
Sub Total C 13,648,800

D PEKERJAAN LAIN-LAIN
1 Perbaikan Tempat sampah 1.00 LS 1,750,000 1,750,000
Sub Total D 1,750,000

TOTAL PEKERJAAN HALAMAN 248,051,868


TOTAL PEKERJAAN SITE DEVELOPMENT 283,493,868
REKAPITULASI BILL OF QUANTITY
PEKERJAAN ARSITEKTUR

PROYEK : PROYEK PERENCANAAN GEDUNG


LOKASI :

JUMLAH
NO. URAIAN PEKERJAAN
(Rp.)
A B C
1 PEKERJAAN ARSITEKTUR LANTAI 1 770,820,523
2 PEKERJAAN ARSITEKTUR LANTAI 2 945,769,701
3 PEKERJAAN LANTAI ATAP 304,081,392
4 PEKERJAAN PENUTUP FASADE BANGUNAN 291,558,755
5 PEKERJAAN BANGUNAN PENUNJANG 23,155,356
TOTAL PEKERJAAN ARSITEKTUR 2,335,385,727
BILL OF QUANTITY
PEKERJAAN PEMBANGUNAN GEDUNG

PEKERJAAN : ARSITEKTUR
HARGA SATUAN JUMLAH
NO. URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6

PEKERJAAN ARSITEKTUR

I PEKERJAAN ARSITEKTUR LANTAI 1


A PEKERJAAN BONGKARAN
1 Pek. Bongkaran dinding, partisi, tangga, kolom, balok, dan plafon, dll 600.00 m2 55,000 33,000,000
Sub Total A 33,000,000

B PEKERJAAN DINDING
Pek. Partisi gypsum 12mm 2 muka (ex. Jayaboard-setara) + rangka hollow
1 galvanis 40x40x0,35 141.78 m2 197,500 28,001,550

Pek. Partisi gypsum 12mm 1 muka (ex. Jayaboard-setara) + rangka hollow


2 galvanis 40x40x0,35 (penutup sementara SLP) 52.43 m2 145,500 7,628,565

3 Pasangan 1/2 bata 1:5 239.02 m2 115,000 27,487,300


4 Plesteran Dinding 1:5 + Acian 478.04 m 2
87,500 41,828,500
5 Pasangan 1/2 bata 1:3 - trasram 115.00 m2 125,000 14,374,375
6 Plesteran Dinding 1:3 + Acian 229.99 m2 87,500 20,124,125
Sub Total B 139,444,415

C PEKERJAAN PELAPIS LANTAI DAN DINDING


1 Pek. Pasang lantai HT 60cm x 60cm (Indogress) Polish - Banking Hall 181.00 m2 292,200 52,888,200
2 Pek. Pasang lantai HT 60cm x 60cm Black (Indogress) Polish -Teller 6.00 m2 292,200 1,753,200
3 Pek. Pasang lantai HT 60cm x 60cm (Indogress) Unpolish-Teras 40.86 m2 292,200 11,939,292
4 Pek. Pasang lantai keramik 40cm x 40cm (Roman-setara) 342.00 m2 177,200 60,602,400
Pek. Pasang lantai keramik un polish 40cm x 40cm (Roman-setara) - R.
5 Toilet, Janitor 20.30 m2 177,200 3,597,160

Pek. Pasang Dinding keramik 25cm x 40cm (Roman-setara) - R.Toilet dan


6 Janitor 37.78 m2 162,900 6,154,362

Pek. Pasang lantai homogenius tile 60cm x 60cm (Indogress-setara) Area


7 tangga utama 16.86 m2 292,200 4,926,492

8 Pek. Pasang lantai keramik 40cm x 40cm (Roman-setara) Area tangga 18.32 m2 177,200 3,246,304
service
9 Plint lantai WPC hitam t : 10cm 320.00 m' 50,500 16,160,000
9 Pek. Step nosing tangga 10 cm x 60 cm (Roman-setara) tangga utama 26.87 m' 80,400 2,160,348
10 Pek. Step nosing tangga 10 cm x 40 cm (Roman-setara) tangga service 26.37 m' 62,500 1,648,125
Sub Total C 165,075,883

D PEKERJAAN KUSEN PINTU JENDELA (Include kunci+penggantung)


* Spesifikasi, ukuran dan material lihat pada gambar Denah Kusen dan
Detail Kusen Pintu dan Jendela
1 Type PF1 (Frameless Double Door) - Entrance 1.00 bh 16,500,000 16,500,000
- Door Panel Clear Glass 12 mm tempered ex. Asahi Glass
- Floor Hinge + Aksesoris ex. Dorma
2 Type PF2 (Frameless Single Door) + kusen Jendela- R. ATM 1.00 bh 8,750,000 8,750,000
- Door Panel Clear Glass 12 mm tempered ex. Asahi Glass
- Floor Hinge + Aksesoris ex. Dorma
3 Type PF3 (Frameless Single door ) - pintu penghubung SLP 1.00 bh 8,750,000 8,750,000
- Door Panel Clear Glass 12 mm tempered ex. Asahi Glass
- Floor Hinge + Aksesoris ex. Dorma
4 Type P1 + floorhinge (New Image Door) 2.00 bh 8,750,000 17,500,000
5 Type P3 (Pintu Service) 3.00 bh 3,750,000 11,250,000
5 Type P4 (Pintu Server- Kaca Intip) 1.00 bh 3,750,000 3,750,000
6 Type P5 (Pintu Toilet) 3.00 bh 3,500,000 10,500,000
7 Type P7 (Pintu Diouble Besi Geser) 1.00 set 7,750,000 7,750,000
8 Type P8 (Pintu Jeruji Besi) 2.00 bh 4,750,000 9,500,000

Page 5 of 34 SHEET : Arsitektur


PEKERJAAN : ARSITEKTUR
HARGA SATUAN JUMLAH
NO. URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6
9 Type P9 (Pintu Khasanah) 1.00 bh 2,750,000 by owner
10 J1 (Jendela 3 susun 1 lobang) 5.00 bh 7,275,000 36,375,000
11 J3 (Jendela 1 lobang) 4.00 bh 2,750,000 11,000,000
12 J4 (Jendela 1 lobang - R. ATM) 29.70 m2 975,000 28,957,500
JF (Partisi kaca clear 10mm tempered + stiker sandblast motif standar BRI)
13 full sampai ke ceiling 38.70 m2 1,050,000 40,635,000

Sub Total D 211,217,500

E PEKERJAAN PLAFON
Pek. Plafon Gypsum 9mm ex. Jayaboard + rangka hollow galvanis
1 108.70 m2 107,500 11,685,250
40x40x0,35
Pek. Drop ceiling gypsum 9 mm ex. Jataboard + rangka hollow galvanis
2 15.00 m' 68,750 1,031,250
40x40x0,35
3 Pek. Plafon gyptile ex. Jayaboard + rangka hollow galvanis 40x40x0,35 164.00 m2 137,700 22,582,800

Pek. Plafon PVC ex. Shunda Plafon warna silver + rangka hollow galvanis
4 28.42 m2 197,500 5,612,950
40x40x0,35 (area canopy teras depan)
Pek. Plafon PVC (Shunda Plafon - setara ) warna natural + rangka hollow
5 32.00 m2 197,500 6,320,000
galvanis 40x40x0,35 (area toilet, janitor, teras samping)
6 Pek. List u channel (shadow line) 198.27 m' 27,000 5,353,290
7 Pek. List Plafon PVC ex. Shunda Plafon LS 301 20.25 m' 47,500 961,875
Sub Total E 53,547,415

F PEKERJAAN PENGECATAN
1 Dinding Interior (Dulux pentalite) -CW 44505 - 3 lapis 1,461.00 m2 28,700 41,930,700
2 Dinding Eksterior (Dulux weathershield - Dove 40140M) - 3 lapis 392.89 m 2
38,500 15,126,265
3 Pengecatan plafond (Vinilex - superwhite setara) - 3 lapis 398.60 m2 19,000 7,573,400
4 Pengecatan topi beton (Dulux weathershield - setara) 19.27 m2 38,500 741,895
Sub Total F 65,372,260

G PEKERJAAN SANITAIR
1 Closet ex. Toto CW. 660NJ lengkap accessories 3.00 bh 5,511,100 16,533,300
2 Jet Shower ex. Toto TX 403 SBN 5 3.00 bh 646,800 1,940,400
3 Paper Holder ex. Toto TX 703 AG 3.00 bh 248,800 746,400
4 Floor Drain SS (Toto-setara) 8.00 bh 479,800 3,838,400
5 Double Robe Hook ex. Toto TS118WSB 3.00 bh 217,300 651,900

Wastafel ex. Toto LW 237CJ :


6 - Faucet TX 115LRR 3.00 bh 2,828,000 8,484,000
- Soap Dispenser TS126AR

7 Kitchen Sink SS ex. Modena + kran angsa - ex. Toto tx. 603 1.00 bh 517,400 517,400
8 Kaca cermin+ Box 3.00 bh 2,500,000 7,500,000
Sub Total G 40,211,800

H PEKERJAAN LAIN-LAIN
1 Pekerjaan pasang waterproofing lantai Toilet 20.30 m2 37,500 761,250
2 Pekerjaan dak beton pantry & wastafel 0.13 m 3
1,750,000 227,500
3 Pekerjaan Railling Tangga

a Pekerjaan railling tangga utama stainless steel (Gambar Detail Tangga) 19.90 m' 2,375,000 47,262,500

Pekerjaan railling tangga service besi hollow + plat strip finish cat duco
b (Gambar Detail Tangga) 16.80 m' 875,000 14,700,000

Sub Total H 62,951,250

TOTAL PEKERJAAN ARSITEKTUR LANTAI 1 770,820,523

II PEKERJAAN ARSITEKTUR LANTAI 2

A PEKERJAAN BONGKARAN
1 Pek. Bongkaran dinding, partisi, tangga, kolom, balok, dan plafon, dll 615.00 m2 55,000 33,825,000
Sub Total A 33,825,000

Page 6 of 34 SHEET : Arsitektur


PEKERJAAN : ARSITEKTUR
HARGA SATUAN JUMLAH
NO. URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6
B PEKERJAAN DINDING
Pek. Partisi gypsum 12mm 2 muka (ex. Jayaboard-setara) + rangka hollow
1 208.76 m2 197,500 41,230,100
galvanis 40x40x0,35

Pekerjaan Partisi Standarisasi BRI (Bagian Luar Plywood Fin. Mega Sungkai
Finish Fancy Gray + Bidang Duco Orange 3cm + U Channel Stainless Steel
2 16.52 m2 975,000 16,107,000
dipasang telungkup tebal 2cm, Bagian dalam Gypsum Board 12 mm ex.
Jaya Board/setara. Rangka Double Hollow 40x40x0,35)

3 Pasangan 1/2 bata 1:5 985.68 m2 115,000 113,353,200


4 Plesteran Dinding 1:5 + Acian 1,971.36 m 2
87,500 172,494,000
5 Pasangan 1/2 bata 1:3 - toilet 93.78 m2 125,000 11,722,500
6 Plesteran Dinding 1:3 + Acian 187.56 m2 87,500 16,411,500
Sub Total B 371,318,300

C PEKERJAAN PELAPIS LANTAI DAN DINDING


1 Pek. Pasang lantai keramik 40cm x 40cm (Roman-setara) 491.00 m2 177,200 87,005,200
Pek. Pasang lantai keramik un polish 40cm x 40cm (Roman-setara) - R.
2 20.90 m2 177,200 3,703,480
Toilet + R. Wudhlu
Pek. Pasang Dinding keramik 25cm x 40cm (Roman-setara) - R.Toilet dan
3 49.70 m2 162,900 8,096,130
Wudhlu
4 Plint lantai WPC hitam t : 10cm 421.00 m' 50,500 21,260,500
5 Pek. Pasang karpet 50x50 cm lapis underlayer - R. Pinca dan R. Rapat 95.54 m2 550,000 52,547,000
6 Pek. Pasang karpet roll lapis underlayer - R. Musholla 14.57 m2 575,000 8,377,750
7 Pek. Pasang Wallpaper - R. Pinca dan R. Rapat 166.90 m2 187,500 31,293,750
Sub Total C 212,283,810

D PEKERJAAN KUSEN PINTU JENDELA (Include kunci+penggantung)


*Spesifikasi, ukuran dan material lihat pada gambar Denah Kusen dan
Detail Kusen Pintu dan Jendela
1 Type P1 + floorhinge (New Image) 4.00 bh 6,750,000 27,000,000
2 Type P2 + floorhinge (Double Swing New Image) 1.00 bh 12,825,000 12,825,000
3 Type P3 (Pintu Service) 3.00 bh 3,750,000 11,250,000
4 Type P5 (Pintu Toilet) 3.00 bh 3,250,000 9,750,000
5 Type P6 Pintu Cowboy Musholla 1.00 bh 1,775,000 1,775,000
6 J1 (Jendela 3 susun 1 lobang) 2.00 bh 2,268,000 4,536,000
7 J2 (Jendela 3 susun 2 lobang) 8.00 bh 4,536,000 36,288,000
JF (Partisi kaca clear 10mm tempered + stiker sandblast motif standar BRI)
8 11.20 m2 1,225,000 13,720,000
full sampai ke ceiling
9 FD (Folding Partition) - custom (2,8x2,5m) 2.00 set 15,862,500 31,725,000
Sub Total D 148,869,000

E PEKERJAAN PLAFON

1 Pek. Gypsum 9mm (Jayaboard-setara) + rangka hollow galvanis 40x40x0,35 139.51 m2 107,500 14,997,325

2 Pek. Plafond gyptile + rangka hollow galvanis 40x40x0,35 443.48 m2 137,700 61,067,196

3 Pek. Plafon PVC (Shunda Plafon - setara ) Silver - rangka hollow galvanis 31.76 m 2
197,500 6,272,600
40x40x0,35 (area Toilet, Musholla, R. Wudhlu)
4 Pek. Drop ceiling + rangka hollow galvanis 40x40x0,35 47.50 m' 68,750 3,265,625
5 Pek. List u channel (shadow line) 303.27 m' 21,500 6,520,305
6 Pek. List Shunda plafond 20.25 m' 47,500 961,875
Sub Total E 93,084,926

F PEKERJAAN PENGECATAN
1 Dinding Interior (Dulux pentalite - setara) -Country White 44505 1,070.00 m2 28,700 30,709,000
2 Dinding Eksterior (Dulux weathershield - Dove 40140M) 240.57 m 2
38,500 9,261,945
3 Pengecatan plafond (Vinilex - superwhite setara) 139.51 m2 19,000 2,650,690
4 Pengecatan topi beton (Dulux weathershield - setara) 13.48 m2 38,500 518,980
Sub Total F 43,140,615

G PEKERJAAN SANITAIR

Page 7 of 34 SHEET : Arsitektur


PEKERJAAN : ARSITEKTUR
HARGA SATUAN JUMLAH
NO. URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6
1 Closet ex. Toto CW. 660NJ lengkap accessories 3.00 bh 5,511,100 16,533,300
2 Jet Shower ex. Toto TX 403 SBN 5 3.00 bh 646,800 1,940,400
3 Paper Holder ex. Toto TX 703 AG 3.00 bh 248,800 746,400
4 Floor Drain SS (Toto-setara) 8.00 bh 479,800 3,838,400
5 Double Robe Hook ex. Toto TS118WSB 3.00 bh 217,300 651,900

Wastafel ex. Toto LW 237CJ :


6 - Faucet TX 115LRR 3.00 bh 2,828,000 8,484,000
- Soap Dispenser TS126AR

7 Kitchen Sink SS ex. Modena + kran angsa - ex. Toto tx. 603 1.00 bh 517,400 517,400
8 Kran Wudhlu/Bebek ex. Toto T30ARQ13N 3.00 bh 682,500 2,047,500
9 Kaca cermin+ Box 3.00 bh 2,500,000 7,500,000

Sub Total G 42,259,300

H PEKERJAAN LAIN-LAIN
2 Pekerjaan pasang waterproofing lantai (R. Toilet dan Janitor) 20.30 m2 37,500 761,250
3 Pekerjaan dak beton pantry & wastafel 0.13 m3 1,750,000 227,500
Sub Total H 988,750

TOTAL PEKERJAAN ARSITEKTUR LANTAI 2 945,769,701


III PEKERJAAN ARSITEKTUR LANTAI ATAP

A PEKERJAAN DINDING PARAPET


1 Pasangan 1/2 bata 1:5 287.25 m2 115,000 33,033,750
2 Plesteran + acian dinding 1:5 574.50 m2 87,500 50,268,750
Sub Total A 83,302,500

B PEKERJAAN PENGECATAN
Pengecatan dinding eksterior (Tangga maintenance dan dinding parapet) -
1 (Dulux weathershield - setara) 574.50 m2 38,500 22,118,250

2 Pengecatan list plank grc 24.00 m 2


38,500 924,000
Sub Total C 23,042,250

C PEKERJAAN PENUTUP ATAP DAN PELAPIS DAK BETON


1 Pekerjaan penutup atap spandek BMT 0,35/TCT 0,40 berpasir 492.39 m2 172,800 85,084,992
2 Pekerjaan nok atap BMT 0,35/TCT 0,40 119.64 m' 75,000 8,973,000
3 Pekerjaan pasang thermal shield buble pack 4 mm (indofoil-setara) 492.39 m2 55,000 27,081,450
4 Pekerjaan list plank grc 9mm/300mm 120.00 m' 60,000 7,200,000
5 Pekerjaan screed lantai atap/dak 188.00 m2 76,900 14,457,200
6 Pekerjaan waterproofing membran bakar lantai dak 268.00 m2 205,000 54,940,000
Sub Total D 197,736,642

TOTAL PEKERJAAN ARSITEKTUR LANTAI ATAP 304,081,392


IV PEKERJAAN ARSITEKTUR PENUTUP FASADE BANGUNAN

A PEKERJAAN ACP & CURTAIN WALL


1 Alumunium Composite panel warna silver BRI 42.33 m2 725,500 30,710,415
2 Alumunium Composite panel warna biru BRI 38.33 m2 725,500 27,808,415
Acrilic Orange BRI tebal 8 mm strip 7 buah + ragka besi, lengkap dengan
3 lampu strip backlight 7.00 unit 5,750,000 40,250,000

4 Alumunium Composite panel warna silver BRI crown dan tiang crown 67.98 m 2
725,500 49,319,490
5 Alumunium Composite panel warna silver BRI Kanopi Utama 33.72 m2 725,500 24,463,860
Pekerjaan curtain wall glass reflected 8 mm, ex. Asahi Atlantic Blue/setara
6 warna biru standard BRI 67.12 m2 1,250,000 83,900,000

7 Pekerjaan penutup atap spandek BMT 0,35/TCT 0,40 - canopy entrace 24.00 m2 172,800 4,147,200
8 Pasangan batu alam andesite/susun sirih + coating - sisi luar bawah 55.70 m2 325,000 18,102,500
9 Natt/tali air dinding 202.50 m' 22,750 4,606,875
10 Logo BRI Stainless steel powder coating BIRU BRI uk. 180 x 180 dilengkapi 2.00 unit
4,125,000 8,250,000
lighting + cover acliric biru BRI
11 Wall Sign BRI 1.00 unit by owner

Page 8 of 34 SHEET : Arsitektur


PEKERJAAN : ARSITEKTUR
HARGA SATUAN JUMLAH
NO. URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6
12 ATM Galery/E-Banking Galery BRI Sign 1.00 unit by owner
13 Pylon Sign t : 7 m 1.00 unit by owner

TOTAL PEKERJAAN ARSITEKTUR PENUTUP FASADE BANGUNAN 291,558,755

Page 9 of 34 SHEET : Arsitektur


PEKERJAAN : ARSITEKTUR
HARGA SATUAN JUMLAH
NO. URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6
V PEKERJAAN BANGUNAN PENUNJANG

V.a RENOVASI POS JAGA


A PEKERJAAN ATAP DAN PLAFON
1 Atap spandek BMT 0,35/TCT 0,40 + Rangka baja ringan 8.40 m2 172,800 1,451,520
2 Pekerjaan list plank grc 9mm/300mm 9.20 m' 60,000 552,000
Pek. Plafon PVC (Shunda Plafon - setara ) Silver - rangka hollow galvanis
3 8.40 m2 197,500 1,659,000
40x40x0,35
4 Pek. List Shunda plafond 8.40 m' 47,500 399,000
Sub Total A 4,061,520
B PENGECATAN
1 Cat dinding exterior (dulux weathershield - setara) 9.54 m2 38,500 367,290
2 Cat dinding interior (dulux pentalite - setara) 18.70 m2 28,700 536,690
Sub Total B 903,980

D PEKERJAAN KUSEN DAN JENDELA


1 Sticker Sandblast 7.10 m2 87,500 621,250
Sub Total D 621,250

E PEKERJAAN PELAPIS EKSTERIOR


1 Pek. Pasangan Batu Acak Templek Purwakarta + coating 5.40 m2 325,000 1,755,000
Sub Total E 1,755,000

SUB TOTAL POS JAGA 11,115,702

V.b RUANG GENSET

A PEKERJAAN PASANGAN
1 Pasangan 1/2 bata 1:5 7.71 m2 115,000 886,650
Sub Total A 886,650

B PEKERJAAN LANTAI
1 Pek. Floor hardener lantai 7.08 m2 334,400 2,367,552
Sub Total B 2,367,552

C FINISHING
1 Pek. Pasangan Batu Acak Templek Purwakarta + coating 15.42 m2 325,000 5,011,500
Sub Total C 5,011,500

D PEKERJAAN ATAP
1 Pek. Penutup atap spandek BMT 0,35 /TCT 0,40 21.84 m2 172,800 3,773,952
Sub Total C 3,773,952

SUB TOTAL RUANG GENSET 12,039,654


TOTAL PEKERJAAN POS JAGA DAN RUANG GENSET 23,155,356
TOTAL PEKERJAAN ARSITEKTUR 2,335,385,727

Page 10 of 34 SHEET : Arsitektur


BILL OF QUANTITY
PEKERJAAN PEMBANGUNAN GEDUNG

PEKERJAAN : FURNITURE
HARGA SATUAN JUMLAH
NO. URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6

IV PEKERJAAN STANDARISASI BANK BRI

1 Pekerjaan Meja Counter Teller 4.20 m' 4,750,000 19,950,000


2 Pekerjaan Adjuster counter teller 2.00 unit 2,250,000 4,500,000
3 Pekerjaan backdrop counter teller termasuk portal 3.80 m' 1,250,000 4,750,000
4 Pekerjaan Credenza Counter Teller 1.00 unit 4,725,000 4,725,000
5 Pekerjaan Meja CS 3.00 unit 3,600,000 10,800,000
6 Pekerjaan Backdrop CS 4.90 m' 975,000 4,777,500
7 Credenza CS 3.00 unit 2,700,000 8,100,000
8 Kursi CS 3.00 bh 1,750,000 5,250,000
9 Kursi Hadap 6.00 bh 1,500,000 9,000,000
10 Bench Tunggu Nasabah (3 seater) 6.00 set 5,750,000 34,500,000
11 Pekerjaan locker lantai 2 2.00 unit 5,056,000 10,112,000
12 Writing Desk 2.00 unit 2,375,000 4,750,000
13 Glassboard 2.00 unit 1,750,000 3,500,000
TOTAL PEKERJAAN STANDARISASI BANK BRI 124,714,500
BILL OF QUANTITY
PEKERJAAN PEMBANGUNAN GEDUNG

PEKERJAAN : STRUKTUR
HARGA SATUAN JUMLAH
NO. URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6

PEKERJAAN STRUKTUR

A PEKERJAAN PONDASI
1 Galian pondasi 491.33 m3 60,000 29,479,507
2 Urugan kembali 343.93 m3 27,500 9,458,009
3 Pasir urug 26.90 m3 188,000 5,056,448
4 pas. Batu kosong 1.99 m3 553,100 1,099,120
5 Lantai kerja 8.48 m3 957,300 8,117,904
6 Pondasi batu kali 5.52 m3 907,000 5,006,640
7 Rolag pas. Bata 9.30 m 85,000 790,500
8 Beton Pondasi tapak 140x140x40 85.04 m3 4,921,200 418,514,596
9 Beton Pondasi tapak 100x100x30 2.11 m3 4,921,200 10,381,764

TOTAL A PEKERJAAN PONDASI 487,904,487

B PEKERJAAN PERKAUTAN KOLOM DAN BALOK


1 Beton tie beam 20x30 21.72 m3 4,921,200 106,867,795
2 Beton tie beam 20x25 21.76 m3 4,921,200 107,085,312
3 Beton tie beam 15x20 0.75 m3 4,921,200 3,682,042
4 Beton kolom 30x30 13.50 m3 4,921,200 66,436,200
5 Beton kolom 20x30 9.72 m3 4,921,200 47,834,064
6 Beton kolom 15x15 1.44 m3 4,921,200 7,086,528
7 Beton balok 20x30 lt 02 20.13 m3 4,921,200 99,048,992
8 Beton balok 20x25 7.77 m3 4,921,200 38,213,118
9 Beton balok 20x25 konsul talang 1.41 m3 4,921,200 6,929,050
10 Pedestal 40x40x50 0.80 m3 4,921,200 3,936,960
11 Plat lantai 12 cm lt 02 29.55 m3 4,921,200 145,403,744
12 Plat lantai 12 cm dak 17.43 m3 4,921,200 85,752,894
13 Baja kolom IWF 350 1,240.00 kg 19,600 24,304,000
14 Baja Balok IWF 350 1,240.00 kg 19,600 24,304,000
15 Angkur 16 P=50cm 40.00 bh 160,000 6,400,000
16 Base plate 20mm 116.56 kg 19,600 2,284,556
TOTAL B PEKERJAAN PERKAUTAN KOLOM DAN BALOK 775,569,255

C PEKERJAAN RANGKA ATAP


1 Baja kuda2 portal atap IWF 250 2,061.05 kg 19,600 40,396,541
2 Angkur 16 P=56cm 112.00 bh 160,000 17,920,000
3 Base plate 12mm 187.40 kg 19,600 3,673,118
4 Baja kuda2 portal atap double CNP 150 289.29 kg 19,600 5,669,998
5 Jurai IWF 250 1,830.46 kg 19,600 35,877,094
6 Jurai double CNP 150 160.03 kg 19,600 3,136,674
7 Gording CNP 120 590.67 kg 19,600 11,577,132
8 Trek stang dia 16mm 53.78 kg 19,600 1,053,995

TOTAL C PEKERJAAN RANGKA ATAP 119,304,553

Page 12 of 34 SHEET : Struktur-ok


PEKERJAAN : STRUKTUR
HARGA SATUAN JUMLAH
NO. URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6
D PEKERJAAN RANGKA ATAP CANOPY
1 Kolom /Balok IWF 250 339.51 kg 19,600 6,654,435
2 Besi siku 50 86.03 kg 19,600 1,686,215
3 CNP 75 717.24 kg 19,600 14,057,904
4 CNP 150 321.46 kg 19,600 6,300,518
5 Base plate 12 mm 13.58 kg 19,600 266,168
6 Angkur 16 mm 8.00 bh 160,000 1,280,000
7 Holow 38x38x2mm 196.32 kg 19,600 3,847,831
8 Gutter (talang datar) Metal 12" ex. Lindab - setara 8.60 m 275,000 2,365,000
8 Tutup Gutter 2.00 bh 275,000 550,000
9 Corong talang ex. Lindab 3.00 bh 175,000 525,000
10 Penyambung Talang ex. Lindab 3.00 bh 125,000 375,000
11 Shoe Pipe ex. Lindab 3.00 bh 115,000 345,000
12 Pipa PVC 3" Type AW 12.42 m' 167,500 2,080,350
TOTAL D PEKERJAAN ATAP CANOPY 40,333,421
TOTAL PEKERJAAN STRUKTUR 1,423,111,716

Page 13 of 34 SHEET : Struktur-ok


REKAPITULASI BILL OF QUANTITY
PEKERJAAN ARSITEKTUR

PROYEK : PROYEK PERENCANAAN GEDUNG


LOKASI :

JUMLAH
NO. URAIAN PEKERJAAN
(Rp.)
1 2 3
1 PEKERJAAN ELEKTRIKAL
- Pekerjaan Bongkaran 10,000,000
- Pekerjaan Genset 30,300,000
- Pekerjaan Instalasi Sambungan PLN By Owner
- Pekerjaan Panel Tegangan Rendah 25,347,700
- Pekerjaan Instalasi Kabel Utama 69,287,400
- Pekerjaan Instalasi & Armature 302,234,000
- Pekerjaan Instalasi Penangkal Petir 12,600,000
Sub Total - 1 449,769,100
2 PEKERJAAN ELEKTRONIK
- Pekerjaan Telepon 71,288,540
- Pekerjaan Sistem Data 63,262,500
- Pekerjaan Fire Alarm 61,204,000
- Pekerjaan Tata Suara 11,002,500
- Pekerjaan CCTV 22,927,000
- Pekerjaan MATV 16,117,500
- Pekerjaan Security System 20,404,000
Sub Total - 2 266,206,040
3 PEKERJAAN MEKANIKAL
- Pekerjaan Air Bersih 109,327,300
- Pekerjaan Air Kotor, Bekas & Vent 97,300,500
- Pekerjaan Air Hujan 25,984,000
Sub Total - 3 232,611,800
4 PEKERJAAN VAC & FAN
- Pekerjaan VAC & FAN 184,825,000
Sub Total - 4 184,825,000

TOTAL BIAYA PEKERJAAN MEP 1,133,411,940


PEMBULATAN 1,133,412,000
BILL OF QUANTITY
PERENCANAAN PEMBANGUNAN GEDUNG

PEKERJAAN : BIDANG ELEKTRIKAL


HARGA SATUAN TOTAL HARGA
NO. PERALATAN UTAMA VOLUME SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6

II PEKERJAAN ELEKTRIKAL

1 PEKERJAAN BONGKARAN
a. Bongkaran armarture lampu dan instalasinya 1.00 lot 1,500,000 1,500,000
b. Bongkaran outlet-outlet saklar, stop kontak dan instalasinya 1.00 lot 1,500,000 1,500,000
c. Bongkaran outlet-outlet data, telepon dan instalasinya 1.00 lot 1,500,000 1,500,000
d. Bongkaran armarture fire alarm, security alarm dan instalasinya 1.00 lot 1,500,000 1,500,000
e. Bongkaran panel-panel listrik dan instalasinya 1.00 lot 1,500,000 1,500,000
f. Bongkaran panel-panel alarm, MDP Telp, dan instalasinya 1.00 lot 2,500,000 2,500,000
Jumlah Pekerjaan Bongkaran 10,000,000
TOTAL PEKERJAAN BONGKARAN 10,000,000

2 PEKERJAAN GENSET
a. Relokasi dan pemasangan kembali :
- Unit Genset : SILENT ( EXISTING ) 1.00 unit 15,000,000 15,000,000
- Kapasitas : 100 KVA (Stan By Rating)
- Tegangan Kerja : 380/220.50 HZ
b. Instalasi Grounded & Instalasi Pengkabelan 1.00 lot 11,500,000 11,500,000
c. Pengadaan gerigen dan bahan bakar solar 200 liter 1.00 lot 2,300,000 2,300,000
d. Tescommisioning 1.00 lot 1,500,000 1,500,000

Total Pekerjaan Genset 30,300,000


TOTAL INSTALASI GENSET 30,300,000

3 SAMBUNGAN DAYA DARI PLN


- Biaya pengurusan pengadaan tambah daya dari 3500 VA (daya existing) ke 66.000 VA,
termasuk biaya gambar instalasi listrik dan biaya jaminan instalasi listrik, (biaya resminya PLN 1.00 lot By Owner -
di reimburse ke Bank BRI)

Jumlah Sambungan Daya PLN -


TOTAL SAMBUNGAN DAYA DARI PLN -

4 PANEL TEGANGAN RENDAH


4.1 PANEL DISTRIBUSI Lt.1 Uk. 80 x 100 x 25 CM

a. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk lengkap dengan Bus-Bar,
Ampere/Volt/Frekwensi meter, pilot lamp, sekring. 1.00 bh 2,937,500 2,937,500
b. COS 125 A (4 pole ), 3 phasa Merk Socomec setara 1.00 set 3,915,000 3,915,000
b. Main MCCB 150A, 30 kA (NF125-SW), 3 phasa ex. Schneider setara 1.00 bh 1,131,300 1,131,300
c. Main panel MCCB 80A, 30 kA (NF125-SW), 3 phasa ex. Schneider 1.00 bh 776,250 776,250
d. Main UPS MCCB 50A, 30 kA (NF125-SW), 3 phasa ex. Schneider setara 1.00 bh 540,000 540,000
e. Main MCCB 40A, 30 kA (PD. SLP), 3 phasa ex. Schneider setara 1.00 bh 677,700 677,700
g. MCB 16A, 6kA (BH-D6) 1 6.00 bh 168,750 1,012,500
h. phasa ex.Schneider
MCB 10A, setara 1 phasa ex.Schneider setara
6kA (BH-D6) 18.00 bh 70,200 1,263,600
i. MCB 6A, 6kA (BH-D6) 1 phasa ex.Schneider setara 6.00 bh 56,700 340,200

j. Timer switch + contactor contac berikut instalasinya untuk line power ke Phylonsign 1.00 bh 469,950 469,950

k. Timer switch + contactor contac berikut instalasinya untuk line power wallsign galery e- 1.00 bh 469,950 469,950
banking

Jumlah Panel PD-Lt.1 13,533,950

4.2 PANEL DISTRIBUSI Lt.2 Uk. 60 x 80 x 25 CM


Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk lengkap dengan Bus-Bar,
a. Ampere/Volt/Frekwensi meter, pilot lamp, sekring. 1.00 bh 2,481,300 2,481,300

b. Main panel MCCB 80A, 30 kA (NF125-SW), 3 phasa ex. Schneider 1.00 bh 776,250 776,250
c. MCB 16A, 6kA (BH-D6) 1 phasa ex.Schneider setara 4.00 bh 168,750 675,000
d. MCB 10A, 6kA (BH-D6) 1 phasa ex.Schneider setara 22.00 bh 70,200 1,544,400
e. MCB 6A, 6kA (BH-D6) 1 phasa ex.Schneider setara 7.00 bh 56,700 396,900
PEKERJAAN : BIDANG ELEKTRIKAL
HARGA SATUAN TOTAL HARGA
NO. PERALATAN UTAMA VOLUME SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6
f. Timer switch + contactor contac berikut instalasinya untuk line power Wallsign 1.00 bh 469,950 469,950

g. Timer switch + contactor contac berikut instalasinya untuk line power Lampu Logo & Lampu
Strip Orange 1.00 bh 469,950 469,950

Jumlah Panel PD-Lt.2 6,813,750

4.3 PANEL UPS ( EXISTING )


a. Pemasangan dan regruping panel UPS pindahan dari kantor lama 1.00 bh 2,500,000 2,500,000
b. Pemasangan dan instal unit UPS pindahan dari kantor lama 1.00 unit 2,500,000 2,500,000
Jumlah Panel UPS 5,000,000
TOTAL INSTALASI PANEL TEGANGAN RENDAH 25,347,700

5 KABEL INSTALASI
TR (TEGANGAN RENDAH)

a. Pekerjaan Kabel Tovoor NYY 4 x 50 mm2 + NYA 25 mm2 (Supreme/Kabelindo


/Tranka/Kabelmetal), dari KWH Meter ke Panel Distribusi Lt.1 ( PD Lt.1 ) 47.00 m' 469,800 22,080,600

b. Pekerjaan Kabel Tovoor NYY 4 x 50 mm2 (Supreme/Kabelindo /Tranka/Kabelmetal), dari 58.00 m' 425,250 24,664,500
Panel Genset ke Panel Distribusi Lt.1 ( PD Lt.1 )

c. Pekerjaan Kabel Tovoor NYY 4 x 25 mm2 + BC 16 mm2 (Supreme/Kabelindo


/Tranka/Kabelmetal), dari Panel Distribusi Lt.1 ( PD Lt.1 ) ke Panel Distribusi Lt.2 (PD Lt.2) 46.00 m1 452,250 20,803,500

Pekerjaan Kabel Tovoor NYY 4 x 10 mm2 + BC 6 mm2 (Supreme/Kabelindo


d. /Tranka/Kabelmetal), dari Panel Distribusi Lt.1 ( PD Lt.1 ) ke Panel UPS ( P. UPS ) + Bypass dari 16.00 m1 108,675 1,738,800
mesin UPS ke panel

TOTAL INSTALASI KABEL UTAMA 69,287,400

6 ARMATURE & PEKERJAAN INSTALASI :


INSTALASI PENERANGAN & STOP KONTAK

A LANTAI 1
Pengadaan Material
a. Lampu TL LED 2 x 16W BALK Tipe RM 9.00 bh 476,500 4,288,500
b. Lampu TL LED 2 x 16W BALK Tipe TKO 4.00 bh 438,750 1,755,000
c. Lampu ceiling Mounted SPOT LIGHTING HALOGEN LED 25 W 24.00 bh 775,950 18,622,800
d. Lampu DOWN LIGHT LED 7 W 16.00 bh 168,750 2,700,000
e. Lampu Halogen LED 5, Tipe ADJUSTUBLE 3.00 bh 182,500 547,500
f. Lampu TL 1 x 28W, TIPE T5 8.00 bh 164,700 1,317,600
g. Lampu BARET LED 7 W. Tipe Baret Kotak 3.00 bh 218,700 656,100
h. Lampu DINDING LED 7 W, Tipe INBOW 4.00 bh 375,000 1,500,000
i. Lampu DINDING LED 7 W, Tipe HANGING 4.00 bh 375,000 1,500,000
j. Outlet Stop Kontak Normal 1 phase, 3 pole, 200 W 26.00 bh 275,000 7,150,000
k. Outlet Stop Kontak UPS 1 phase, 3 pole, 250 W 13.00 bh 275,000 3,575,000
l. Outlet Stop Kontak Normal 1 phase, 4 gang, 300 W ( Power extention ) 7.00 bh 325,000 2,275,000
m. Outlet Saklar Tunggal 9.00 bh 30,000 270,000
n. Outlet Saklar Double 6.00 bh 40,000 240,000

Jumlah Armature 46,397,500

INSTALASI :
a. Instalasi titik penerangan NYM 3 x 2,5 mm²+ pipa conduit higt impact 20mm 78.00 Titik 229,000 17,862,000
b. Instalasi titik stop kontak NYM 3 x 2,5 mm²+ pipa conduit higt impact 20mm 46.00 Titik 229,000 10,534,000
c. Instalasi titik Saklar Tunggal 8.00 Titik 157,000 1,256,000
d. Instalasi titik Saklar Double 7.00 Titik 229,000 1,603,000
e. Instalasi kabel tray uk. 400mm x 50mm 18.00 m1 240,000 4,320,000
f. Instalasi kabel tray uk. 200mm x 50mm 76.00 m1 212,500 16,150,000
g. Instalasi Line power ke Pos Jaga NYY 3 x 2,5 mm²+ pipa conduit higt impact 20mm 58.00 m 1 229,000 13,282,000
h. Instalasi Line power ke Wallsign NYY 3 x 2,5 mm²+ pipa conduit higt impact 20mm 43.00 m 1 229,000 9,847,000
i. Instalasi Line power ke Phylonsign NYY 3 x 2,5 mm²+ pipa conduit higt impact 20mm 62.00 m 1 229,000 14,198,000

Jumlah Instalasi 89,052,000


TOTAL LANTAI 1 135,449,500
PEKERJAAN : BIDANG ELEKTRIKAL
HARGA SATUAN TOTAL HARGA
NO. PERALATAN UTAMA VOLUME SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6
B LANTAI 2
Pengadaan Material
a. Lampu TL LED 2 x 16W BALK Tipe RM 49.00 bh 476,500 23,348,500
b. Lampu ceiling Mounted SPOT LIGHTING HALOGEN LED 25 W 15.00 bh 775,950 11,639,250
c. Lampu DOWN LIGHT LED 7 W 16.00 bh 168,750 2,700,000
d. Lampu TL 1 x 28W, TIPE T5 36.00 bh 164,700 5,929,200
e. Lampu BARET LED 7 W. Tipe Baret Kotak 1.00 bh 218,700 218,700
f. Lampu Gantung LED 3 x 7 W, Tipe Klasik 1.00 bh 375,000 375,000
g. Outlet Stop Kontak Normal 1 phase, 3 pole, 200 W 52.00 bh 275,000 14,300,000
h. Outlet Stop Kontak UPS 1 phase, 3 pole, 250 W 27.00 bh 275,000 7,425,000
i. Outlet Stop Kontak Normal 1 phase, 4 gang, 300 W ( Power extention ) 2.00 bh 325,000 650,000
Stop Kontak AH Meyer, Mounted on table (tipe Netbox Turn 4 gang, 2 power, 1 VGA, 1 HDMI,
j. 2 Data), pada meja rapat (Kode A) 2.00 bh 432,500 865,000

k. Outlet Saklar Tunggal 11.00 bh 30,000 330,000


l. Outlet Saklar Double 10.00 bh 40,000 400,000

Jumlah Armature 68,180,650

INSTALASI :
a. Instalasi titik penerangan NYM 3 x 2,5 mm²+ pipa conduit higt impact 20mm 118.00 Titik 229,000 27,022,000
b. Instalasi titik stop kontak NYM 3 x 2,5 mm²+ pipa conduit higt impact 20mm 83.00 Titik 229,000 19,007,000
c. Instalasi titik Saklar Tunggal 11.00 Titik 157,000 1,727,000
d. Instalasi titik Saklar Double 10.00 Titik 229,000 2,290,000
e. Instalasi kabel tray uk. 400mm x 50mm 16.00 m1 240,000 3,840,000
f. Instalasi kabel tray uk. 200mm x 50mm 96.00 m1 212,500 20,400,000

g. Instalasi Line power ke Lampu Logo & Lampu Strip NYY 3 x 2,5 mm²+ pipa conduit higt impact 46.00 m 1
229,000 10,534,000
20mm
h. Instalasi Line power ke Wallsign NYY 3 x 2,5 mm²+ pipa conduit higt impact 20mm 43.00 m1 229,000 9,847,000

Jumlah Instalasi 94,667,000


TOTAL LANTAI 2 162,847,650

C P-POS SECURITY & R. GENSET


Pengadaan Material
a. Lampu TL LED 2 x 16W BALK Tipe TKO 1.00 bh 438,750 438,750
b. Lampu BARET LED 7 W. Tipe Baret Kotak 3.00 bh 218,700 656,100
c. Outlet Stop Kontak Normal 1 phase, 3 pole, 200 W 2.00 bh 275,000 550,000
d. Outlet Saklar Tunggal 2.00 bh 30,000 60,000
e. Outlet Saklar Double 1.00 bh 40,000 40,000
f. Bok MCB 6 gang 1.00 bh 275,000 275,000

Jumlah 2,019,850

INSTALASI :
a. Instalasi titik penerangan NYM 3 x 2,5 mm²+ pipa conduit higt impact 20mm 4.00 Titik 229,000 916,000
b. Instalasi titik stop kontak NYM 3 x 2,5 mm²+ pipa conduit higt impact 20mm 2.00 Titik 229,000 458,000
c. Instalasi titik Saklar Tunggal 2.00 Titik 157,000 314,000
d. Instalasi titik Saklar Double 1.00 Titik 229,000 229,000

Jumlah Instalasi 1,917,000


TOTAL R. POWER HOUSE 3,936,850

TOTAL INSTALASI + ARMATUR 302,234,000

G INSTALASI P PETIR
Pengadaan Material
- Splitzent Tembaga dia-15 + tiang Gips t=1,3 m' 5.00 bh 750,000 3,750,000
- Instalasi kabel BC dia-50 1.00 lot 6,375,000 6,375,000
- Grounding max 3 Ohm 1.00 bh 1,500,000 1,500,000
- Bak kontrol (30x30x40) cm 1.00 bh 475,000 475,000
- Matrial Alat Bantu 1.00 bh 500,000 500,000
PEKERJAAN : BIDANG ELEKTRIKAL
HARGA SATUAN TOTAL HARGA
NO. PERALATAN UTAMA VOLUME SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6
TOTAL INSTALASI PENANGKAL PETIR 12,600,000
TOTAL PEKERJAAN BIDANG ELEKTRIKAL 449,769,100
BILL OF QUANTITY
PERENCANAAN PEMBANGUNAN GEDUNG

PEKERJAAN BIDANG : ELEKTRONIK - TELEPON


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT VOLUME
(Rp.) (Rp.)
1 2 3 4 5 6

1 Peralatan Utama
a Pemasangan PABX ( EXISTING ) unit 1.00 9,062,500 9,062,500
Kapasitas : 6 line, 24 extention
lengkap Nicad Baterry 1 Jam
b Pemasangan Operator Console ( Existing ) unit 1.00 2,500,000 2,500,000
c Pengadaan dan pemasangan MDF - T (Main Distribution Frame Telephone) Kap 48 pai unit 1.00 375,000 375,000
d Surge Arrester unit 1.00 263,500 263,500
e Pengkabelan dan pemrograman peralatan utama telepon ls 1.00 1,500,000 1,500,000

JUMLAH PERALATAN UTAMA 13,701,000

2 Pengkabelan Utama
a Kabel dari Rumah Telkom ke MDF : m 48.00 40,095 1,924,560
b Kabel dari MDF Peralatan Utama telepon :
ITC 20 x 2 x d. 0,6 mm ke TB.TP-1 LT-1 m 16.00 40,095 641,520
ITC 20 x 2 x d. 0,6 mm ke TB.TP-2 LT-2 m 28.00 40,095 1,122,660

JUMLAH PERKABELAN 3,688,740

3 Instalasi Telepon dalam Bangunan

A Lantai 1
1 Terminal Box Telepon Lantai 1 (TB. P-2) kapasitas 20 pairs unit 1.00 375,000 375,000
2 Outlet Telepon Extention bh 6.00 75,000 450,000
3 Outlet Direct Telepon bh 2.00 875,000 1,750,000
4 Pesawat Telepon Analog BY OWNER unit 8.00 -
5 Instalasi titik nyala telepon dengan kabel ITC 2 x 2 x d. 0,6 mm titik 8.00 1,603,800 12,830,400
dalam conduit PVC HI dia. 20 mm

Jumlah Lantai 1 15,405,400

B Lantai 2
1 Terminal Box Telepon Lantai 1 (TB. P-3) kapasitas 20 pairs unit 1.00 375,000 375,000
2 Outlet Telepon Extention bh 15.00 75,000 1,125,000
3 Outlet Direct Telepon bh 3.00 875,000 2,625,000
4 Pesawat Telepon Analog BY OWNER unit 18.00 -
5 Instalasi titik nyala telepon dengan kabel ITC 2 x 2 x d. 0,6 mm titik 18.00 1,603,800 28,868,400
dalam conduit PVC HI dia. 20 mm

Jumlah Lantai 2 32,993,400

TOTAL INSTALASI DALAM BANGUNAN 48,398,800

4 Testing & Commissioning


Testing & Commissioning peralatan dan instalasi telepon lot 1.00 5,500,000 5,500,000

JUMLAH TESTING COMMISSIONING 5,500,000


TOTAL PEKERJAAN TELEPON 71,288,540
BILL OF QUANTITY
PERENCANAAN PEMBANGUNAN GEDUNG

PEKERJAAN BIDANG : ELEKTRONIK DATA


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT VOLUME
(Rp.) (Rp.)
1 2 3 4 5 6

PEKERJAAN SISTEM INTEGRASI DATA


Pengadaan dan pemasangan sistem sesuai dengan
Gambar & Spesifikasi Teknik.

1 Pekerjaan Instalasi

A Lantai 1
1. Jaringan Kabel UTP
a. Instalasi titik data UTP Cable, Cat 6 dalam conduit PVC HI dia 20 mm ttk 23.00 375,000 8,625,000

b. Pemasangan
kantor lama )
Switch hub kaps 24-port D-link, DGS 1024D ( pindahan dari unit 2.00 3,450,000 6,900,000

c. Pemasangan Modular Jack Cat 6 :


- Outlet Data bh 20.00 137,500 2,750,000
- Outlet WIFI bh 3.00 375,000 1,125,000
d. Flush Box + Face Plate bh 20.00 375,000 7,500,000

2 Support Facility
1 Wiring Management unit 1.00 675,000 675,000
2 Wall Mount Rack Management System 20 RU unit 1.00 2,250,000 2,250,000

Sub Total Lantai 1 29,825,000

B Lantai 2
1. Jaringan Kabel UTP
a. Instalasi titik data UTP Cable, Cat 6 dalam conduit PVC HI dia 20 mm ttk 35.00 375,000 13,125,000
b. Pemasangan Modular Jack Cat 6 :
- Outlet Data bh 31.00 137,500 4,262,500
- Outlet WIFI bh 4.00 375,000 1,500,000
c. Flush Box + Face Plate bh 31.00 375,000 11,625,000

2 Support Facility
1 Wiring Management unit 1.00 675,000 675,000
2 Wall Mount Rack Management System 20 RU unit 1.00 2,250,000 2,250,000

Sub Total Lantai 2 33,437,500

TOTAL PEKERJAAN INTEGRASI DATA 63,262,500


BILL OF QUANTITY
PERENCANAAN PEMBANGUNAN GEDUNG

PEKERJAAN BIDANG : ELEKTRONIK - FIRE ALARM


NO. HARGA SATUAN JUMLAH HARGA
ITEM URAIAN PEKERJAAN SAT VOLUME
(Rp.) (Rp.)
1 2 3 4 5 6

IV PEKERJAAN FIRE ALARM


Pengadaan dan pemasangan sistem sesuai dengan Gambar & Spesifikasi Teknis

1 PEKERJAAN PERALATAN UTAMA


1 Pemasangan MCP - FA (Master Control Panel Fire Alarm) termasuk Repeat Panel, Nicad
unit 1.00 1,500,000 1,500,000
Baterry + Charger ( Pindahan dari kantor lama )
Kapasitas : 1 loops
Type : Semi Addressable
2 Pemasangan LCD Announciator ( Pindahan dari kantor lama ) unit 1.00 1,500,000 1,500,000
3 Main Distribution Fire Alarm (MDFA) unit 1.00 1,500,000 1,500,000

TOTAL PEKERJAAN PERALATAN UTAMA 4,500,000

2 PEKERJAAN PENGKABELAN UTAMA


1 Kabel FRC STP AWG 18 4 pair dari MDFA ke Annuciator Pos Jaga dalam conduit PVC HI
mtr 67.00 72,500 4,857,500
dia. 20 mm
2 Kabel dari MCFA ke MDFA dalam conduit PVC HI dia. 20 mm mtr 18.00 72,500 1,305,000

3 Kabel Kontrol dari MCP-FA dengan FRC 2 x 2,5 mm² dalam conduit PVC HI dia. 20 mm

- Sound System mtr 28.00 72,500 2,030,000


- Sentral Access Control mtr 32.00 72,500 2,320,000

TOTAL PEKERJAAN PENGKABELAN UTAMA 10,512,500

3 PEKERJAAN INSTALASI FIRE ALARM DALAM BANGUNAN

A LANTAI 1
a Peralatan Alarm
1 Terminal Box Fire Alarm Lantai 1 bh 1.00 1,750,000 1,750,000
2 Push Button Set (Alarm Bell, Incicator) bh 2.00 781,000 1,562,000
3 Smoke Detector bh 6.00 775,000 4,650,000
4 FIXED Detector bh 4.00 775,000 3,100,000
5 End Of Line bh 1.00 947,500 947,500
b Instalasi
1 Instalasi Push Button dengan kabel FRC 2 x 1,5 mm² + Conduit HI dia 20 mm titik 2.00 375,000 750,000
2 Instalasi Detector dengan kabel NYA 2 x 1,5 mm² + Conduit HI dia 20 mm titik 10.00 375,000 3,750,000
3 Instalasi Fire Intercom Jack dengan kabel FRC 2 x 1,5 mm² + Conduit HI dia 20 mm titik 2.00 375,000 750,000
4 Instalasi End Of Line dengan kabel NYA 2 x 1,5 mm² + Conduit HI dia 20 mm titik 1.00 375,000 375,000

Total Instalasi Lantai 1 17,634,500


B LANTAI 2
a Peralatan Alarm
1 Terminal Box Fire Alarm Lantai 1 bh 1.00 1,750,000 1,750,000
2 Push Button Set (Alarm Bell, Incicator) bh 2.00 781,000 1,562,000
3 Smoke Detector bh 8.00 775,000 6,200,000
4 FIXED Detector bh 6.00 775,000 4,650,000
5 End Of Line bh 2.00 947,500 1,895,000
b Instalasi
1 Instalasi Push Button dengan kabel FRC 2 x 1,5 mm² + Conduit HI dia 20 mm titik 2.00 375,000 750,000
2 Instalasi Detector dengan kabel NYA 2 x 1,5 mm² + Conduit HI dia 20 mm titik 14.00 375,000 5,250,000
3 Instalasi Fire Intercom Jack dengan kabel FRC 2 x 1,5 mm² + Conduit HI dia 20 mm titik 2.00 375,000 750,000
4 Instalasi End Of Line dengan kabel NYA 2 x 1,5 mm² + Conduit HI dia 20 mm titik 2.00 375,000 750,000

Total Instalasi Lantai 2 23,557,000


TOTAL PEKERJAAN INSTALASI FIRE ALARM DALAM BANGUNAN 41,191,500
4 Testing & Commissioning
Testing & Commissioning peralatan dan instalasi fire alarm terpasang lot 1.00 5,000,000 5,000,000
TOTAL TESTING DAN COMMISSIONING 5,000,000
TOTAL PEKERJAAN FIRE ALARM 61,204,000
BILL OF QUANTITY
PERENCANAAN PEMBANGUNAN GEDUNG

PEKERJAAN BIDANG : ELEKTRONIK - TATA SUARA


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT VOLUME
(Rp.) (Rp.)
1 2 3 4 5 6

5 PEKERJAAN TATA SUARA


Pengadaan dan pemasangan sistem sesuai dengan Gambar & Spesifikasi Teknis

A Peralatan Utama Public Address


1 Relokasi peralatan utama dari kantor lama lot 1.00 2,500,000 2,500,000

TOTAL PERALATAN UTAMA PUBLIC ADDRESS 2,500,000

02 Pengkabelan Utama

1 - MDF - TBTS.2 NYMHY 3 (2 x 2,5) MM + Conduit Pvc dia 20 mm m' 36.00 27,500 990,000

TOTAL PENGKABELAN UTAMA 990,000

03 Pekerjaan Instalasi Sound System Pada Bangunan

Lantai 1
1 Ceiling Speaker 3 watt + Maching Transformer bh 4.00 275,000 1,100,000
2 Wall Speaker 3 Watt bh 2.00 275,000 550,000
3 Instalasi Speaker kabel NYA 2 x 1,5 mm² + Conduit Pvc dia 20 mm ttk 4.00 562,500 2,250,000
4 Instalasi Emergency kabel FRC 2 x 1,5 mm² + Conduit Pvc dia 20 mm ttk 2.00 562,500 1,125,000

Sub Jumlah Lantai 1 5,025,000

Lantai 2
1 TBTS. LT-BSM unit 1.00 525,000 525,000
2 Ceiling Speaker 3 watt + Maching Transformer bh 1.00 275,000 275,000
3 Instalasi Speaker kabel NYA 2 x 1,5 mm² + Conduit Pvc dia 20 mm ttk 1.00 562,500 562,500
4 Instalasi Emergency kabel FRC 2 x 1,5 mm² + Conduit Pvc dia 20 mm ttk 2.00 562,500 1,125,000

Sub Jumlah Lantai 2 2,487,500

TOTAL INSTALASI SOUND SYSTEM PADA BANGUNAN 7,512,500


TOTAL PEKERJAAN TATA SUARA 11,002,500
BILL OF QUANTITY
PERENCANAAN PEMBANGUNAN GEDUNG

PEKERJAAN BIDANG : ELEKTRONIK - CCTV


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN UNIT QTY
(Rp.) (Rp.)
1 2 3 4 5 6

CCTV

1 PERALATAN UTAMA
R. Sentral CCTV : ( Perangkat Utama Existing )
- Pemasangan DIGITAL Video Recorder (DVR) ( Pindahan dari kantor lama ) Set 1.00 750,000 750,000
- Pemasangan Switch Set 1.00 75,000 75,000
- Pemasangan TV Monitor LED 22" Set 2.00 1,750,000 3,500,000
- Pemasangan Multi Screen LED 22" Set 1.00 1,952,000 1,952,000

Pengkabelan Utama Lot 1.00 750,000 750,000

TOTAL PERALATAN UTAMA 7,027,000

2 PEKERJAAN PERALATAN CCTV

A LANTAI 1

- Pemasangan Kamera CCTV Type Dome FIXED 3 MP (Existing) Unit 6.00 275,000 1,650,000
- Pemasangan Kamera CCTV Coulor Type Dome FIXED (Existing) Unit 4.00 275,000 1,100,000
- Instalasi titik kamera CCTV + kabel power ttk 10.00 575,000 5,750,000
- Instalasi titik Monitor TV ttk 2.00 575,000 1,150,000

LANTAI 1 9,650,000

B LANTAI 2

- Pemasangan Kamera CCTV Type Dome FIXED 3 MP (Existing) Unit 5.00 275,000 1,375,000
- Pemasangan Kamera CCTV Coulor Type Dome FIXED (Existing) Unit 1.00 275,000 275,000
- Instalasi titik kamera CCTV + kabel power ttk 6.00 575,000 3,450,000
- Instalasi titik Monitor TV ttk 2.00 575,000 1,150,000

LANTAI 2 6,250,000

TOTAL PEKERJAAN PERANGKAT CCTV 15,900,000


TOTAL PEKERJAAN CCTV 22,927,000
BILL OF QUANTITY
PERENCANAAN PEMBANGUNAN GEDUNG

PEKERJAAN BIDANG : ELEKTRONIK - MATV


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT VOLUME
(Rp.) (Rp.)
1 2 3 4 5 6

3 PEKERJAAN MATV
Pengadaan dan pemasangan sistem sesuai dengan Gambar & Spesifikasi Teknis

1 Peralatan Utama dan Pengkabelan


1 Pengadaan dan pemasangan Antena UHF unit 2.00 275,000 550,000
2 Pemasangan CPU + Monitor untuk Character Generator & Video Text Announcement unit 1.00 8,500,000 8,500,000
3 Pengkabelan Peralatan Utama dan Pemograman ls 1.00 750,000 750,000

Sub Jumlah Pekerjaan Utama 9,800,000

2 Pengkabelan Utama
1 Kabel dari Antena ke Peralatan Utama m 45.00 17,500 787,500
Coaxial 7C dalam konduit PVC HI dia. 20 mm

Sub Jumlah Pekerjaan Pengkabelan 787,500


TOTAL PEKERJAAN UTAMA 10,587,500

3 Instalasi TV Dalam Bangunan


Lantai 1
1 Coupler 2 way bh 1.00 375,000 375,000
2 Outlet TV bh 2.00 95,000 190,000
3 Instalasi titik nyala TV dengan kabel coaxial 5C - 75 ohm titik 2.00 475,000 950,000
dalam konduit PVC HI dia. 20 mm

Sub Jumlah Instalasi Lt. 1 1,515,000

Lantai 2
1 Coupler 2 way bh 1.00 375,000 375,000
2 Outlet TV bh 2.00 95,000 190,000
3 Instalasi titik nyala TV dengan kabel coaxial 5C - 75 ohm titik 2.00 475,000 950,000
dalam konduit PVC HI dia. 20 mm

Sub Jumlah Instalasi Lt. 2 1,515,000


TOTAL PEKERJAAN INSTALASI TV DALAM BANGUNAN 3,030,000

4 Testing & Commissioning


Testing & Commissioning peralatan dan instalasi fire alarm terpasang lot 1.00 2,500,000 2,500,000

TOTAL TESTING DAN COMMISSIONING 2,500,000


TOTAL PEKERJAAN MATV 16,117,500
BILL OF QUANTITY
PERENCANAAN PEMBANGUNAN GEDUNG

PEKERJAAN BIDANG : ELEKTRONIK - SECURITY ALARM


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT VOL
(Rp.) (Rp.)
1 2 3 4 5 6

PEKERJAAN SISTEM SECURITY ALARM


Pengadaan dan pemasangan sistem sesuai dengan
Gambar & Spesifikasi Teknik

1 Pekerjaan Instalasi
- Instalasi security alarm UTP Cable Cat 6 dalam conduit PVC HI dia. 20 mm ttk 22.00 375,000 8,250,000
- Pemasangan DCS SECURITY ALARM SISTEM (PC 1616 + PK 1555) (Existing) unit 1.00 475,000 475,000
- Pengadaan dan pemasangan KEYPAD LCD ICON bh 1.00 975,000 975,000
- Pengadaan dan pemasangan HEAVY DUTY DOOR CONTACT bh 3.00 175,000 525,000
- Pengadaan dan pemasangan MAGNETIC CONTACT bh 2.00 75,000 150,000
- Pengadaan dan pemasangan PANIC BUTTON (Inbow hold button) bh 5.00 1,750,000 8,750,000
- Pengadaan dan pemasangan KICK BAR bh 1.00 229,000 229,000
- Pengadaan dan pemasangan POSESIVE INFRA RED ( PIR ) bh 8.00 75,000 600,000
- Pengadaan dan pemasangan MINI SIRENE & STORBE (BLUE) bh 2.00 225,000 450,000

TOTAL PEKERJAAN SECURITY ALARM 20,404,000


BILL OF QUANTITY
PERENCANAAN PEMBANGUNAN GEDUNG

PEKERJAAN BIDANG : MEKANIKAL - AIR BERSIH


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT VOL
(Rp.) (Rp.)
1 2 3 4 5 6

PEKERJAAN AIR BERSIH

1 PERALATAN UTAMA
Peralatan Utama Air Bersih
Pengadaan dan pemasangan peralatan utama air bersih, lengkap dengan
accessories yang diperlukan, sesuai spesifikasi teknis dan gambar perencanaan.

1.1 RUANG POMPA

a Pompa sumur dalam (jet pump) dan pengeboran sumur unit 1.00 17,500,000 17,500,000
- Data Listrik : 220 V/3Ph/50 Hz
- Jumlah : 1 set

b Pompa Transfer Air Bersih Transfer (TP-01 A/B) set 1.00 18,225,000 18,225,000
- Capasitas : 100 L/menit
- Head : 30 mtr
- RPM : 3.000 Rpm
- Daya Listrik : 2,2 kW
- Data Listrik : 380 V/3 Ph/50 Hz
- Jenis Pompa : Centrifugal End Suction
- Operasi : Single Alternate
- Jumlah Pompa : 1 set (2 pomp)

1.2 PEKERJAAN INSTALASI PIPA


Pengadaan dan pemasangan valve Class 10 K lengkap dengan
accessories dan alat bantu, sesuai dengan spesifikasi teknis

a Unit Pompa
- Gate Valve Dia. 25 mm bh 2.00 375,000 750,000
- Floting Valve Dia. 25 mm bh 1.00 575,000 575,000

b Pipa Med Class


- dia. 50 mm Header set 1.00 1,750,000 1,750,000
- Pipa Med Class
- dia. 40 mm m 12.00 115,000 1,380,000
- dia. 25 mm m 24.00 85,200 2,044,800

c Fiting Fiting
- Sock Las, Knee Las lot 1.00 475,000 475,000
- Pressure Gauge 10 kg bh 2.00 1,305,000 2,610,000
- Material bantu (Hanger dll) Lot 1.00 750,000 750,000

TOTAL PEKERJAAN UTAMA 46,059,800

2 PEKERJAAN ROOF TOP


Pengadaan dan pemasangan valve Class 10 K lengkap dengan
accessoris dan alat bantu, sesuai dengan spesifikasi teknis

2.1 RUANG POMPA ROOF TOP

a Sand dan Carbon Filter SF & CF set 1.00 14,500,000 14,500,000


- Capasitas : 100 I/menit
- Tekanan : 3 Bar maks
PEKERJAAN BIDANG : MEKANIKAL - AIR BERSIH
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT VOL
(Rp.) (Rp.)
1 2 3 4 5 6
- Tipe : Vertikal Cylinder Tank
- Jenis : Pressure tipe dengan Automatic Backwash
- Filter : Mildstel dengan epoxy anti karat or FRP
- Kecepatan Aliran di Filt : 10 m³/jam/m²

b Tangki atas/roof tank kap. 1 x 1 m³ unit 1.00 3,750,000 3,750,000


- Capasitas : kap. 1 x 1 m³
- Tipe : FRP

c Pompa Booster Air Bersih Transfer (BP-01 A/B) set 1.00 18,225,000 18,225,000
- Capasitas : 50 L/menit
- Head : 20 mtr
- RPM : 3.000 Rpm
- Daya Listrik : 3 kW
- Data Listrik : 380 V/3 Ph/ 50 Hz
- Jenis Pompa : Centrifugal End Suction
- Operasi : Paralel Alternate
- Jumlah Pompa : 1 set (3 pompo)

2.2 INSTALASI
Pengadaan dan pemasangan valve Class 10 K lengkap dengan
accessoris dan alat bantu, sesuai dengan spesifikasi teknis

a Pipa Med Class


- dia. 40 mm m 6.00 115,000 690,000
- dia. 25 mm m 12.00 85,200 1,022,400

b Fiting Fiting lot 1.00 1,305,000 1,305,000


c Material bantu (Hanger dll) lot 1.00 750,000 750,000

TOTAL PEKERJAAN ROOF TOP 40,242,400

3 PEKERJAAN INSTALASI AIR BERSIH


3.1 PIPA RISER
Pengadaan dan pemasangan Pipa Air Bersih bahan pipa PPR, lengkap dengan
accessories yang diperlukan, sesuai spesifikasi teknis dan gambar perencanaan.

a Dalam Shaf
- Gate Valve Dia. 40 mm bh 1.00 475,000 475,000
- Gate Valve Dia. 25 mm bh 2.00 375,000 750,000

b Pipa Med Class


- dia. 40 mm m 12.00 115,000 1,380,000
- dia. 25 mm m 18.00 85,200 1,533,600

c Fiting Fiting
- Sock Las, Knee Las lot 1.00 475,000 475,000
- Material bantu (Hanger dll) lot 1.00 750,000 750,000

TOTAL PEKERJAAN INSTALASI AIR BERSIH 5,363,600

4 PEKERJAAN INSTALASI STAFF/KARYAWAN

4.1 PEKERJAAN INSTALASI TOILET LANTAI - 1


Pengadaan dan pemasangan Pipa Air Bersih bahan pipa PPR, lengkap dengan
accessories yang diperlukan, sesuai spesifikasi teknis dan gambar perencanaan.
PEKERJAAN BIDANG : MEKANIKAL - AIR BERSIH
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT VOL
(Rp.) (Rp.)
1 2 3 4 5 6
1 Pipa AB Æ 32 m 4.00 85,000 340,000
2 Pipa AB Æ 25 m 46.00 65,000 2,990,000
3 Pipa AB Æ 20 m 23.00 47,000 1,081,000
4 Pipa AB Æ 15 m 32.00 32,500 1,040,000

Pengadaan dan pemasangan Gate Valve, lengkap dengan accessories yang diperlukan,
sesuai spesifikasi teknis dan gambar perencanaan.

1 Gate Valve Æ 25 bh 1.00 375,000 375,000

Sub Total Lantai 1 5,826,000

4.2 PEKERJAAN INSTALASI TOILET LANTAI - 2


Pengadaan dan pemasangan Pipa Air Bersih bahan pipa PPR, lengkap dengan
accessories yang diperlukan, sesuai spesifikasi teknis dan gambar perencanaan.

1 Pipa AB Æ 32 m 3.00 85,000 255,000


2 Pipa AB Æ 25 m 12.00 65,000 780,000
3 Pipa AB Æ 20 m 27.00 47,000 1,269,000
4 Pipa AB Æ 15 m 30.00 32,500 975,000

Pengadaan dan pemasangan Gate Valve, lengkap dengan accessories yang diperlukan,
sesuai spesifikasi teknis dan gambar perencanaan.

1 Gate Valve Æ 25 bh 1.00 375,000 375,000

Sub Total Lantai 2 3,654,000

TOTAL PEKERJAAN INSTALASI STAFF/KARYAWAN 9,480,000

5 PEKERJAAN TOILET KHUSUS


5.1 PEKERJAAN INSTALASI TOILET PINCA LANTAI - 2
Pengadaan dan pemasangan Pipa Air Bersih bahan pipa PPR, lengkap dengan
accessories yang diperlukan, sesuai spesifikasi teknis dan gambar perencanaan.

- Pipa AB Æ 25 m 24.00 65,000 1,560,000


- Pipa AB Æ 20 m 12.00 47,000 564,000
- Pipa AB Æ 15 m 21.00 32,500 682,500

Pengadaan dan pemasangan Gate Valve, lengkap dengan accessories yang diperlukan,
sesuai spesifikasi teknis dan gambar perencanaan.

- Gate Valve Æ 25 bh 1.00 375,000 375,000

Sub Total Toilet Khusus 3,181,500

TOTAL PEKERJAAN TOILET KHUSUS 3,181,500

6 PEKERJAAN TESTING DAN COMMISSIONING


1 Pekerjaan Testing & Commissioning lot 1.00 5,000,000 5,000,000

TOTAL PEKERJAAN TESTING DAN COMMISSIONING 5,000,000


TOTAL PEKERJAAN AIR BERSIH 109,327,300
BILL OF QUANTITY
PERENCANAAN PEMBANGUNAN GEDUNG

PEKERJAAN BIDANG : MEKANIKAL - AIR KOTOR, BEKAS & VENT


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6

PEKERJAAN AIR BEKAS, AIR KOTOR DAN VENT

A PERALATAN UTAMA
1 STP (SISTEM BIOTECHI) 1.00 unit 16,250,000 16,250,000
- Peralatan Utama :
- Bahan frp
- Kapasitas 1,2 M3/day
- Dimensi Pipa (Inlet/Outlet) dia 4"
- Ventilasi Diameter 50(mm)

2 STP (SISTEM BIOTECHI) 1.00 unit 26,750,000 26,750,000


- Peralatan Utama :
- Bahan frp
- Kapasitas 6 M3/day
- Dimensi Pipa (Inlet/Outlet) dia 4"
- Ventilasi Diameter 50(mm)

TOTAL PERALATAN UMUM 43,000,000

B PEKERJAAN INSTALASI TOILET STAFF


1 Toilet Lantai 1
a Pipa PVC AW
- Pipa PVC ∅ 100 (AK) 32.00 m 156,000 4,992,000
- Pipa PVC ∅ 100 (ABK) 56.00 m 156,000 8,736,000
- Pipa PVC ∅ 65 (ABK) 5.00 m 116,000 580,000
- Pipa PVC ∅ 50 (ABK) 36.00 m 97,500 3,510,000
- Pipa PVC ∅ 50 (Vent Class D) 24.00 m 97,500 2,340,000
- Pipa PVC ∅ 32 (Vent Class D) 10.00 m 85,000 850,000
- Pipa PVC ∅ 20 (Vent Class D) 28.00 m 47,500 1,330,000
b Fiting-fitting 1.00 lot 1,250,000 1,250,000
c Vent Cup 2.00 bh 375,000 750,000
d Hanger & Support 1.00 lot 750,000 750,000
e Material Bantu 1.00 lot 750,000 750,000

Sub total toilet lantai 1 25,838,000

2 Toilet Lantai 2
a Pipa PVC AW
- Pipa PVC ∅ 100 (AK) 14.00 m 156,000 2,184,000
- Pipa PVC ∅ 100 (ABK) 8.00 m 156,000 1,248,000
- Pipa PVC ∅ 65 (ABK) 16.00 m 116,000 1,856,000
- Pipa PVC ∅ 50 (ABK) 18.00 m 97,500 1,755,000
- Pipa PVC ∅ 50 (Vent Class D) 10.00 m 97,500 975,000
- Pipa PVC ∅ 32 (Vent Class D) 10.00 m 85,000 850,000
- Pipa PVC ∅ 20 (Vent Class D) 14.00 m 47,500 665,000
b Fiting-fitting 1.00 lot 1,250,000 1,250,000
c Vent Cup 2.00 bh 375,000 750,000
d Hanger & Support 1.00 lot 750,000 750,000
e Material Bantu 1.00 lot 750,000 750,000

Sub total toilet lantai 2 13,033,000

TOTAL PEKERJAAN INSTALASI TOILET STAFF 38,871,000

C PEKERJAAN INSTALASI TOILET KHUSUS


PEKERJAAN BIDANG : MEKANIKAL - AIR KOTOR, BEKAS & VENT
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6
Toilet PINCA - Lantai 3
a Pipa PVC AW
- Pipa PVC ∅ 100 (AK) 2.00 m 156,000 312,000
- Pipa PVC ∅ 100 (ABK) 3.00 m 156,000 468,000
- Pipa PVC ∅ 50 (ABK) 6.00 m 116,000 696,000
- Pipa PVC ∅ 32 (Vent Class D) 3.00 m 97,500 292,500
- Pipa PVC ∅ 25 (Vent Class D) 3.00 m 97,500 292,500
b Fiting-fitting
- CO 100 1.00 bh 175,000 175,000
- CO65 1.00 BJ 157,500 157,500
- CO50 1.00 BH 150,000 150,000
- FD.50 1.00 BH 275,000 275,000
- Vent Cup 1.00 BH 375,000 375,000
- Hanger & Support 1.00 Lot 750,000 750,000
- Material Bantu 1.00 Lot 750,000 750,000

Sub total toilet PINCA - lantai 3 4,693,500


TOTAL PEKERJAAN INSTALASI TOILET KHUSUS 4,693,500

D INSTALASI SITEPLAN
a Pipa PVC AW
- PIPA PVC ∅ 100 (AK) 10.00 m 156,000 1,560,000
- PIPA PVC ∅ 100 (ABK) 46.00 m 156,000 7,176,000
b Fitting - fitting 1.00 lot 1,250,000 1,250,000
c Material Bantu 1.00 lot 750,000 750,000

TOTAL INSTALASI SITEPLAN 10,736,000


TOTAL PEKERJAAN AIR BEKAS, AIR KOTOR DAN VENT 97,300,500
BILL OF QUANTITY
PERENCANAAN PEMBANGUNAN GEDUNG

PEKERJAAN BIDANG : MEKANIKAL - AIR HUJAN


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6

PEKERJAAN AIR HUJAN

Instalasi di Shaft Riser (Vertical & Horizontal)


1 Sumur Resapan Kap 2.00 unit 3,750,000 7,500,000
2 PEMIPAAN
- Pipa PVC AW dia. 100 64.00 m 156,000 9,984,000
- Pipa PVC AW dia. 80 80.00 m 137,500 11,000,000
3 Fitting-fitting 1.00 lot 1,250,000 1,250,000
4 Roof Drain 8.00 bh 375,000 3,000,000
5 Material Bantu 1.00 lot 750,000 750,000

TOTAL PEKERJAAN AIR HUJAN 25,984,000


BILL OF QUANTITY
PERENCANAAN PEMBANGUNAN GEDUNG

PEKERJAAN BIDANG : VAC DAN FAN


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6

PEKERJAAN AC DAN FAN

A PERALATAN UTAMA
Pengadaan dan pemasangan unit AC Indoor (Kabel Kontrol)
termasuk alat bantu sesuai dengan spek Teknis dan gambar, serta tidak terbatas
(Hanger support klem mur dll) terpasang sempurna

1 PEKERJAAN AC LANTAI 1

a ATM CENTER (ACS 1)


- Jenis AC single split type wallmounted 9.000 Btu/h (1 Pk) (EXISTING) 1.00 unit 375,000 375,000
- Instalasi pipa refrigerant lengkap dengan isolasinya 8.00 m' 275,000 2,200,000
- Instalasi stop kontak AC NYY 3x2,5 mm2 + SK-AC 1.00 ttk 337,500 337,500
- Instalasi drainage PVC dia-25 mm + fit 1.00 ttk 97,500 97,500
Sub total 3,010,000
b BANKING HALL (ACS 2, ACS 3, ACS 4)
- Jenis AC single split type wallmounted 18.000 Btu/h (2 Pk)( BARU ) 3.00 unit 14,300,000 42,900,000
- Instalasi pipa refrigerant lengkap dengan isolasinya 26.00 m' 275,000 7,150,000
- Instalasi stop kontak AC NYY 3x2,5 mm2 + SK-AC 1.00 ttk 337,500 337,500
- Instalasi drainage PVC dia-25 mm + fit 1.00 ttk 97,500 97,500
Sub total 50,485,000
c TELLER (ACS 5)
- Jenis AC single split type wallmounted 9.000 Btu/h (1 Pk)( BARU ) 1.00 unit 6,760,000 6,760,000
- Instalasi pipa refrigerant lengkap dengan isolasinya 13.00 m' 275,000 3,575,000
- Instalasi stop kontak AC NYY 3x2,5 mm2 + SK-AC 1.00 ttk 337,500 337,500
- Instalasi drainage PVC dia-25 mm + fit 1.00 ttk 97,500 97,500
Sub total 10,770,000
d R. BACK OFFICE (ACS 6, ACS 7)
- Jenis AC single split type wallmounted 9.000 Btu/h (1 Pk) (EXISTING) 2.00 unit 375,000 750,000
- Instalasi pipa refrigerant lengkap dengan isolasinya 21.00 m' 275,000 5,775,000
- Instalasi stop kontak AC NYY 3x2,5 mm2 + SK-AC 1.00 ttk 337,500 337,500
- Instalasi drainage PVC dia-25 mm + fit 1.00 ttk 97,500 97,500
Sub total 6,960,000
e R. SERVER (ACS 8, ACS 9)
- Jenis AC single split type wallmounted 9.000 Btu/h (1 Pk) (EXISTING) 2.00 unit 375,000 750,000
- Instalasi pipa refrigerant lengkap dengan isolasinya 28.00 m' 275,000 7,700,000
- Instalasi stop kontak AC NYY 3x2,5 mm2 + SK-AC 1.00 ttk 337,500 337,500
- Instalasi drainage PVC dia-25 mm + fit 1.00 ttk 97,500 97,500
Sub total 8,885,000
TOTAL PEKERJAAN AC LANTAI 1 80,110,000

3 PEKERJAAN AC LANTAI 2
a R. TAMU & AKAD (ACS 10)
- Jenis AC single split type wallmounted 9.000 Btu/h (1 Pk) (EXISTING) 1.00 unit 375,000 375,000
- Instalasi pipa refrigerant lengkap dengan isolasinya 14.00 m' 275,000 3,850,000
- Instalasi stop kontak AC NYY 3x2,5 mm2 + SK-AC 1.00 ttk 337,500 337,500
- Instalasi drainage PVC dia-25 mm + fit 1.00 ttk 97,500 97,500
Sub total 4,660,000
b R. PINCA (ACC 11)
- Jenis AC single split type cassete 28.000 Btu/h (3 Pk)(EXISTING) 1.00 unit 775,000 775,000
- Instalasi pipa refrigerant lengkap dengan isolasinya 14.00 m' 575,000 8,050,000
- Instalasi stop kontak AC NYY 3x2,5 mm2 + SK-AC 1.00 ttk 337,500 337,500
- Instalasi drainage PVC dia-25 mm + fit 1.00 ttk 97,500 97,500
PEKERJAAN BIDANG : VAC DAN FAN
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6
Sub total 9,260,000
c R. RAPAT (ACS 12, ACS 14)
- Jenis AC single split type wallmounted 9.000 Btu/h (1 Pk) (BARU) 2.00 unit 6,760,000 13,520,000
- Instalasi pipa refrigerant lengkap dengan isolasinya 28.00 m' 275,000 7,700,000
- Instalasi stop kontak AC NYY 3x2,5 mm2 + SK-AC 1.00 ttk 337,500 337,500
- Instalasi drainage PVC dia-25 mm + fit 1.00 ttk 97,500 97,500
Sub total 21,655,000
d R. RAPAT (ACS 13)
- Jenis AC single split type wallmounted 9.000 Btu/h (1 Pk) (EXISTING) 1.00 unit 375,000 375,000
- Instalasi pipa refrigerant lengkap dengan isolasinya 12.00 m' 275,000 3,300,000
- Instalasi stop kontak AC NYY 3x2,5 mm2 + SK-AC 1.00 ttk 337,500 337,500
- Instalasi drainage PVC dia-25 mm + fit 1.00 ttk 97,500 97,500
Sub total 4,110,000
e RUANG KERJA (ACC 15, ACC 16)
- Jenis AC single split type cassete 28.000 Btu/h (3 Pk)(EXISTING) 2.00 unit 775,000 1,550,000
- Instalasi pipa refrigerant lengkap dengan isolasinya 24.00 m' 575,000 13,800,000
- Instalasi stop kontak AC NYY 3x2,5 mm2 + SK-AC 1.00 ttk 337,500 337,500
- Instalasi drainage PVC dia-25 mm + fit 1.00 ttk 97,500 97,500
Sub total 15,785,000
f MUSHOLA (ACS 17)
- Jenis AC single split type wallmounted 9.000 Btu/h (1 Pk) (EXISTING) 1.00 unit 375,000 375,000
- Instalasi pipa refrigerant lengkap dengan isolasinya 15.00 m' 275,000 4,125,000
- Instalasi stop kontak AC NYY 3x2,5 mm2 + SK-AC 1.00 ttk 337,500 337,500
- Instalasi drainage PVC dia-25 mm + fit 1.00 ttk 97,500 97,500
Sub total 4,935,000
g RUANG KERJA (ACS 18, ACS 19, ACS 20)
- Jenis AC single split type wallmounted 9.000 Btu/h (1 Pk) (BARU) 3.00 unit 6,760,000 20,280,000
- Instalasi pipa refrigerant lengkap dengan isolasinya 38.00 m' 275,000 10,450,000
- Instalasi stop kontak AC NYY 3x2,5 mm2 + SK-AC 1.00 ttk 337,500 337,500
- Instalasi drainage PVC dia-25 mm + fit 1.00 ttk 97,500 97,500
Sub total 31,165,000
TOTAL PEKERJAAN AC LANTAI 2 91,570,000

B PEKERJAAN VENTILASI (VAC)


Pengadaan dan pemasangan exhaust fan
bantu sesuai dengan spek teknis dan gambar, serta tidak terbatas
(Hanger support klem mur dll) terpasang sempurna

Peralatan Utama Ventilasi


LANTAI 1 S/D 2
A. EXHAUST FAN
Fungsi : Exhaust Fan
Ruangan yang dilayani : TOILET (tipikal) 10.00 unit 975,000 9,750,000
Kode : EF-1.TO1 & EF-T02
Jenis Fan : CENTRIFUGAL IN LINE
Jumlah :1
Kapasitas (CFM) : 500
Static Pressure : 0,38
RPM : 2630
Motor Listrik : 0,3 KW/220/1P/50 Hz
Ceilling Fan :6
B. Instalasi stop kontak daya NYM 3x2,5 mm 10.00 ttk 339,500 3,395,000
TOTAL PEKERJAAN VENTILASI (VAC) 13,145,000
TOTAL PEKERJAAN AC DAN FAN 184,825,000