DAFTAR RINCIAN KEBUTUHAN MATERIAL PEMBANGUNAN MASJID

NO MATERIAL SATUAN JUMLAH HARGA SAT TOTAL


1 2 3 4 5 6
A PEKERJAAN TANGGA
1 SEMEN SAK 19.78 43,000 850,540
2 PASIR KUBIK 1.88 90,000 169,200
3 BATU PECAH KUBIK 3.15 850,000
4 BESI BETON 10 BATANG 34 65,000 2,210,000
5 bESI BETON 6 BATANG 3 40,000 120,000
6 TRIPLEKS 6 MM LEMBAR 3 65,000 195,000
7 PAPAN MAL LEMBAR 10 30,000 300,000
8 BALOK 3 X 5 BATANG 5 25,000 125,000

B PEKERJAAN DINDING
1 BATU BATA BIJI 7000 550 3,850,000
2 SEMEN 40 KG SAK 34 43,000 1,462,000
3 PASIR KUBIK 4 90,000 360,000

C PEKERJAAN PLESTERAN
1 SEMEN SAK 30 43,000 1,290,000
2 PASIR KUBIK 4.6 90,000 414,000

D PEKERJAAN ALUMINIUM
1 JENDELA BUAH 16 850,000 13,600,000
2 PINTU UNIT 3 3,500,000 10,500,000

E PEKERJAAN RAILING
1 HOLO 40 X 60 GALVANIL BATANG 38 180,000 6,840,000
2 BESI BETON 14 SNI BATANG 60 135,000 8,100,000
3 TAPAK HOLO BIJI 75 5,000 375,000
4 DINABOL BIJI 150 2,000 300,000

F PEKERJAAN KERAMIK LANTAI


1 KERAMIK 60 X 60 DOS 250 145,000 36,250,000
2 SEMEN SAK 60 43,000 2,580,000
3 PASIR KUBIK 11.25 90,000 1,012,500

JUMLAH 91,753,240
MASJID

KET
7

Belum termasuk
keramik dan
upah

Belum termasuk
plaomor cat dan
upah

belum termasuk
upah

belum termasuk
cat belum
termasuk upah

belum termasuk
upah