RENCANA ANGGARAN BIAYA MATERIAL

STRUKTUR - ARSITEKTUR
RUMAH KOS

NO URAIAN PEKERJAAN SAT VOL HARGA SAT JUMLAH TOTAL JUMLAH TOTAL

I PEKERJAAN SIPIL
1 MATERIAL
- Batu kombong bh 320 Rp 2,000 Rp 640,000
- Bata Ringan M3 72.27 Rp 900,000 Rp 65,042,169 grand elepant
- Semen gresik Zak 381.0 Rp 69,000 Rp 26,289,000
- Semen Perekat Bata Ringan Zak 72.00 Rp 175,000 Rp 12,600,000
- Pasir truck 3.00 Rp 1,900,000 Rp 5,700,000 pasang/lumajang
- Tensla truck 2.00 Rp 1,450,000 Rp 2,900,000
- Besi Ø 8 mm ljr 275.00 Rp 39,000 Rp 10,725,000
- Besi Ø 10 mm ljr 324.00 Rp 58,000 Rp 18,792,000
- Besi Ø 12 mm ljr 34.00 Rp 82,000 Rp 2,788,000
- keramik lantai 40 x 40 Dus 208.00 Rp 114,000 Rp 23,712,000 polished
- keramik kamar mandi 20 x 20 Dus 12.00 Rp 63,000 Rp 756,000
- Plamir kg 30.00 Rp 88,000 Rp 2,640,000
- Genteng bh 1250.00 Rp 5,200 Rp 6,500,000
- Wuwung bh 80.00 Rp 15,000 Rp 1,200,000

JUMLAH Rp 180,284,169