II PEKERJAAN CAT
1 Pekerjaan Cat dinding dalam 10.81 M2 Rp 6,925.00 Rp 3,750.00 Rp 74,859.25 Rp 40,537.50 Rp 115,396.75 3.74177
2 Pekerjaan Cat dinding luar 12.22 M2 Rp 39,200.00 Rp 3,750.00 Rp 479,024.00 Rp 45,825.00 Rp 524,849.00 17.0183
semen : 6,06 m3
smen : 1/6 *6,06= 1,01/0,024= 42 zak
pasir : 2/6*6,06 = 2,02 m3
kerikil : 3/6* 6,06 = 3,03 m3
plasteran :328 m2= 5,07 m3
semen : 1/5*5 = 1/0,024= 42 zak
pasir : 4/5*5= 4 m3
BATA : 177,1 M2
bata : 177,1/0,0164 = 10799bh
semen : 177,1-136 =41,1m2
1/5* 3,288 = 0,6576/0,024= 28 zak
psir : 4/5*3,288 = 2,6m3
plasteran : 12 m2
semen : 1/4 * 0,18 m3 = 0,045/0,024= 1,8 zak
pasir : 3/4*0,18 = 0,135 m3
pengecoran : 0,2 m3
semen : 1,6* 0,2 = 0,033/0,024 = 1,4 zak
pasir : 2/6*0,2 = 0,066 m3
kerikil : 3/6*0,2 = 0,1 m3
semen : 1,67 m3
1/9*1,67= 0,185/0,024=7,7 zak
pasir : 3/9*1,67 = 0,55 m3
kerikil :5/9*1,67 = 0,92 m3
ADDENDUM MATERIAL TYPE PALACIO
RANGKA ATAP M2
LISPLANK M1
TALANG JURAI M1
GENTENG BADAN M2
Genteng beton 14.0000 bh Rp 6,700.00 Rp 93,800.00
Rp 93,800.00
GENTENG NOK M1
GENTENG LISPLANK M1
PLAFOND EXPOSE M2
Triplek 4mm 0.3535 lbr 78,000.00 Rp 27,573.00
Paku triplek 0.1980 kg 15,000.00 Rp 2,970.00
Rp 30,543.00
LIST KAYU AK 21 M1
LIST KAYU AK 21 M1
Accesories 0.2500 bh Rp -
Pipa Pvc 0.2888 btg Rp -
Rp -
CAT PLAFOND M2
BEKISTING PAPAN
ACIAN DINDING
Rp 60,000.00 tukang
Rp 40,000.00 kenek
Rp 0.12
Rp 833,333.33 Rp 4,488,334.33
Rp 60,000.00 tukang
Rp 40,000.00 kenek
Rp 0.25
Rp 400,000.00 Rp 3,793,000.00
Rp 60,000.00 tukang
Rp 40,000.00 kenek
Rp 20.00
Rp 5,000.00 Rp 36,770.00
Rp 60,000.00 tukang
Rp 40,000.00 kenek
Rp 15.00
Rp 6,666.67 Rp 40,766.67
Rp 60,000.00 tukang
Rp 40,000.00 kenek
Rp 20.00
Rp 5,000.00 Rp 53,410.00
Rp 60,000.00 tukang
Rp 40,000.00 kenek
Rp 25.00
Rp 4,000.00 Rp 97,800.00
Rp 60,000.00 tukang
Rp 40,000.00 kenek
Rp 20.00
Rp 5,000.00 Rp 60,292.00
Rp 60,000.00 tukang
Rp 40,000.00 kenek
Rp 20.00
Rp 5,000.00 Rp 5,000.00
Rp 60,000.00 tukang
Rp 40,000.00 kenek
Rp 15.00
Rp 6,666.67 Rp 38,266.67
Rp 60,000.00 tukang
Rp 40,000.00 kenek
Rp 20.00
Rp 5,000.00 Rp 49,916.00
Rp 60,000.00 tukang
Rp 40,000.00 kenek
Rp 15.00
Rp 6,666.67 Rp 53,457.67
Rp 60,000.00 tukang
Rp 40,000.00 kenek
Rp 20.00
Rp 5,000.00 Rp 35,543.00
tukang
Rp 40,000.00 kenek
Rp 50.00
Rp 800.00 Rp 2,222.50
Rp 60,000.00 tukang
Rp - kenek
Rp 30.00
Rp 2,000.00 Rp 6,703.75
Rp 60,000.00 tukang
Rp 40,000.00 kenek
Rp 20.00
Rp 5,000.00 Rp 21,855.00
Rp 60,000.00 tukang
Rp 40,000.00 kenek
Rp 2.00
Rp 50,000.00 Rp 162,910.00
Rp 60,000.00 tukang
Rp 40,000.00 kenek
Rp 5.50
Rp 18,181.82 Rp 148,952.42
Rp 60,000.00 tukang
Rp 40,000.00 kenek
Rp 5.50
Rp 18,181.82 Rp 110,102.42
Rp 60,000.00 tukang
Rp 40,000.00 kenek
Rp 2.00
Rp 50,000.00 Rp 242,020.60
Rp 60,000.00 tukang
Rp 40,000.00 kenek
Rp 8.00
Rp 12,500.00 Rp 90,470.60
Rp 60,000.00 tukang
Rp 40,000.00 kenek
Rp 4.00
Rp 25,000.00 Rp 100,852.00
Rp 60,000.00 tukang
Rp 40,000.00 kenek
Rp 40.00
Rp 2,500.00 Rp 6,409.38
Rp 60,000.00 tukang
Rp 40,000.00 kenek
Rp 25.00
Rp 4,000.00 Rp 17,163.00
Rp 60,000.00 tukang
Rp 40,000.00 kenek
Rp 25.00
Rp 4,000.00 Rp 25,335.31
Rp 60,000.00 tukang
Rp 40,000.00 kenek
Rp 25.00
Rp 4,000.00 Rp 38,675.50
Rp 60,000.00 tukang
Rp 40,000.00 kenek
Rp 30.00
Rp 3,333.33 Rp 3,333.33
Rp 60,000.00 tukang
Rp 40,000.00 kenek
Rp 1.00
Rp 100,000.00 Rp 100,000.00
Rp 60,000.00 tukang
Rp - kenek
Rp 25.00
Rp 2,400.00 Rp 2,400.00
Rp 60,000.00 tukang
Rp - kenek
Rp 20.00
Rp 3,000.00 Rp 3,000.00
Rp 60,000.00 tukang
Rp - kenek
Rp 10.00
Rp 6,000.00 Rp 6,000.00
Rp 60,000.00 tukang
Rp - kenek
Rp 25.00
Rp 2,400.00 Rp 2,400.00
Rp 35,000.00 tukang
Rp 40,000.00 kenek
Rp 30.00
Rp 2,500.00 Rp 28,100.00
Rp 60,000.00 tukang
kenek
Rp 15.00
Rp 4,000.00 Rp 5,232.50
Rp 3,000.00
Rp 3,000.00
Rp 3,000.00
Rp 3,000.00
Rp 4,500.00
Rp 2,000.00
Rp 1,000.00
Rp 7,500.00
Rp 2,000.00
Rp -
Rp -
Rp 2,000.00
Rp 4,500.00
Rp -
Rp -
Rp -
Rp -
Rp -
Rp 4,500.00
Rp 63,000.00 210000
Rp 1,400,000.00
Rp 1,036,000.00
Rp 13,000.00
Rp 9,000.00
Rp 100,000.00
Rp 15,000.00
Rp 2,573,000.00
KEBUTUHAN MATERIAL GRAND SUNAN GIRI TP 37