117
0 A 7 G 26 H 54 C 75
1 2 3 4 5
0 7 7 19 26 28 54 21 75
89 I
7
K B 89 7
7 47 F E
82
6
28 82 7
KET :
LINTASAN KRITIS
LINTASAN TIDAK KRITIS
KETERANGAN :
A : PEKERJAAN PERSIAPAN
B : PEKERJAAN PIPING 7 HARI
C : PEKERJAAN BAK KONTROL 1 ( 60 x 60 cm ) 17 BUAH 28 HARI
D : PEKERJAAN BAK KONTROL 2 ( 80 x 80 cm ) 8 BUAH 21 HARI
E : PEKERJAAN BAK SUMPIT ( 1 unit ) 35 HARI
F : PEKERJAAN BAK EQUALISASI 28 HARI
G : PEKERJAAN DUDUKAN BIOREACTOR ( 1 UNIT ) 14 HARI
H : PEKERJAAN BAK GREASE TRAP 7 HARI
I : PEKERJAAN FISH POND DAN BAK CHLORINASI 7 HARI
J : PEK. TAMAN, PAGAR DAN CANOPY 14 HARI
K : PEKERJAAN RUMAH JAGA 7 HARI
L : MESIN PENGOLAHAN AIR LIMBAH EET: 14 HARI
M : TESTING & COMISSIONING EET: 21 HARI
EET: 1 HARI Jakarta, 18 April 2019
PT. CAHAYA MAS CEMERLANG
100.00% 3.58% 4.51% 5.01% 5.41% 7.63% 8.63% 9.03% 9.29% 7.22% 7.22% 6.27% 5.88% 4.52% 3.49% 4.38% 3.98% 2.48% 1.48%
0 3.58% 8.09% 13.10% 18.51% 26.15% 34.78% 43.81% 53.11% 60.33% 67.54% 73.81% 79.69% 84.21% 87.69% 92.07% 96.04% 98.52% 100.00%
100.00% 0.60% 0.60% 0.94% 0.94% 2.12% 3.97% 5.80% 6.00% 5.23% 6.00% 5.72% 8.62% 11.80% 16.00% 19.86% 5.86%
0 0.60% 1.20% 2.14% 3.08% 5.20% 9.17% 14.97% 20.97% 26.21% 32.21% 37.93% 46.55% 58.35% 74.35% 94.21% 100.00%
NO URAIAN
LURAHAN KOJA
0.51% 0.51%
7.42%
( 60 x 60 cm ) 17 BUAH 0.47%
( 80 x 80 cm ) 8 BUAH 0.55%
0.06%
2.39% 0.48%
ACTOR ( 1 UNIT ) 1.17% 0.59% 0.59%
4.59%
BAK CHLORINASI 0.10%
2.96%
0.78%
27.57% 0.30% 0.30%
0.69%
LURAHAN LAGOA
0.51% 0.51%
8.17%
( 60 x 60 cm ) 0.76%
( 80 x 80 cm ) 0.28%
0.18%
2.39% 0.48%
ACTOR ( 1 UNIT ) 1.17% 0.59% 0.59%
5.03%
BAK CHLORINASI 0.10%
2.96%
0.78%
27.57% 0.30% 0.30%
COMISSIONING 0.79%
0.16% 0.16%
0.50% 0.70% 0.90% 1.10% 1.30% 1.50% 1.70%
0.16% 0.16%
0.50% 0.70% 0.90% 1.10% 1.30% 1.50% 1.70%
0.57%
0.63%
0.59% 0.59% 0.59% 0.59%
0.16% 0.16% 0.16%
1.90% 2.10% 2.30% 2.70% 3.00% 4.00% 2.97%
17.14285714
11
9
BULAN V KET
17 18
100% 0.000%
1.85% 0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.59% 0.000%
0.000%
0.30% 0.000% 27.57%
0.69% 50% 0.000%
0.000%
0.000%
2.04% 0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.59% 0.000%
0.000%
0.30% 0.000%
0.79% 0% 0.000%
5.68% 1.48%
98.52% 100.00%
7,722,727,559.39 100.00% 3.58% 4.51% 5.01% 5.41% 7.63% 8.63% 9.03% 9.30% 7.22% 7.22% 6.27% 5.88% 4.52% 3.49% 4.38% 3.98% 2.48% 1.48%
0 3.58% 8.09% 13.10% 18.51% 26.15% 34.78% 43.81% 53.11% 60.33% 67.54% 73.81% 79.69% 84.21% 87.70% 92.07% 96.05% 98.52% 100.00%
NO URAIAN
JUMLAH
BIAYA BOBOT (%) BULAN I
( Rp ) 1
0.24%
0.28% 0.28%
0.06%
0.80% 0.80% 0.80%
0.59%
1.15% 1.15% 1.15% 1.15%
0.10%
0.74%
0.39% 0.39%
0.60% 0.90% 1.00% 1.10% 1.20% 1.30%
0.38%
0.14% 0.14%
0.18%
0.80% 0.80% 0.80%
0.59%
1.26% 1.26% 1.26% 1.26%
0.10%
0.74%
0.39% 0.39%
0.60% 0.90% 1.00% 1.10% 1.20% 1.30%
KSANAAN 90 H
I BULAN III KET
8 9 10 11 12
100% 0.000%
1.48% 1.48% 1.48% 1.48% 1.48% 0.000%
0.24% 0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.74% 0.74% 0.74% 0.000%
0.000%
1.70% 3.60% 5.90% 8.97% 1.00% 0.000%
0.35% 0.35% 50% 0.000%
0.000%
0.000%
1.63% 1.63% 1.63% 1.63% 1.63% 0.000%
0.38% 0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.74% 0.74% 0.74% 0.000%
0.000%
1.70% 3.60% 5.90% 8.97% 1.00% 0.000%
0.39% 0.39% 0% 0.000%
###
###
27.57%
#################################
#################################
BULAN I
12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4
#####################################################################
#####################################################################
0
0
0
0
WAKTU PELAKSANAAN 90 H
BULAN I
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
#####################################################################
#####################################################################
0
0
0
0
BULAN I
28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
#####################################################################
#####################################################################
0
0
0
0
21 22 23 24 25 26 27 28 29 30
##############################
##############################
TENAGA TOTAL HARGA KEB. OH
JUMLAH
NOURAIAN PEKERJAAN HARGA GAJI OH TOT. OH
( Rp )
A Pembangunan SPALD Kelurahan Koj 134,325.00 0.00
I PEKERJAAN PERSIAPAN 134,325.00 0.00
1 Direksi Keet, 402,975.00 134,325.00 3.00
2 Papan Nama P - 134,325.00 0.00
3 Pembersihan 2,024,949.38 134,325.00 15.08
2,427,924.38 134,325.00 18.075 0.2963
II PEKERJAAN PIPING 134,325.00 0.00
1 Pekerjaan gal 60,929,820.00 134,325.00 453.60
2 Pekerjaan pem - 134,325.00 0.00
3 Pekerjaan pem 3,787,965.00 134,325.00 28.20
4 Pekerjaan pem 11,095,245.00 134,325.00 82.60
5 Pekerjaan pem 2,792,616.75 134,325.00 20.79
6 Pekerjaan pem 8,596,800.00 134,325.00 64.00
7 Pekerjaan uru 8,123,976.00 134,325.00 60.48
8 Restorasi ha - 134,325.00 0.00
95,326,422.75 134,325.00 709.67 11.634
134,325.00 0.00
III PEKERJAAN BAK KONTROL 1 ( 60 x 134,325.00 0.00
1 Galian Tanah 1,534,327.31 134,325.00 11.42
2 Pekerjaan Bob 2,919,475.97 134,325.00 21.73
3 Pek. Dinding 24,205.37 134,325.00 0.18
4 Pek. Rabat Be 2,976,574.84 134,325.00 22.16
5 Acian 94,564.80 134,325.00 0.70
6 Pasir urug 5c 21,760.65 134,325.00 0.16
7 Plat Dak Tutu 183,958.09 134,325.00 1.37
8 Elbow inlet + - 134,325.00 0.00
9 Tutup manhol - 134,325.00 0.00
7,754,867.02 134,325.00 57.73212 0.9464
IV PEKERJAAN BAK KONTROL 2 ( 80 x 134,325.00 0.00
1 Galian Tanah 1,128,330.00 134,325.00 8.40
2 Pekerjaan Bob 2,149,307.46 134,325.00 16.00
3 Pek. Dinding 637,882.56 134,325.00 4.75
4 Pek. Lantai ba 2,092,246.20 134,325.00 15.58
5 Acian 174,085.20 134,325.00 1.30
6 Pasir urug 5c 285,306.30 134,325.00 2.12
7 Plat Dak Tutu 86,438.14 134,325.00 0.64
8 Elbow inlet + - 134,325.00 0.00
9 Tutup manhol - 134,325.00 0.00
6,553,595.86 134,325.00 48.7891 0.7998
V PEKERJAAN BAK SUMPIT ( 1 unit ) 134,325.00 0.00
1 Pek. Bobok Be 322,396.12 134,325.00 2.40
2 Galian Tanah 243,799.88 134,325.00 1.82
3 Pek. Dinding 76,887.63 134,325.00 0.57
4 Pek. Rabat Be 39,894.53 134,325.00 0.30
5 Acian 130,026.60 134,325.00 0.97
6 Lantai kerja, 110,818.13 134,325.00 0.83
7 Plat Penutup 37,709.65 134,325.00 0.28
8 Tutup plat be - 134,325.00 0.00
961,532.52 134,325.00 7.1582544 0.1173
VI PEKERJAAN BAK EQUALISASI 134,325.00 0.00
1 Galian Tanah 9,840,649.50 134,325.00 73.26
2 Urugan sirtu 137,347.31 134,325.00 1.02
3 Pasir urug t 110,012.18 134,325.00 0.82
4 Lantai kerja t 301,425.30 134,325.00 2.24
5 Lantai bak co 2,568,969.79 134,325.00 19.13
6 Dinding beton 12,586,789.80 134,325.00 93.70
7 Balok beton 528,837.53 134,325.00 3.94
8 Acian 26,865.00 134,325.00 0.20
9 Tutup plat ba - 134,325.00 0.00
26,100,896.40 134,325.00 194.311531 3.1854
VII PEKERJAAN DUDUKAN BIOREACTOR 134,325.00 0.00
1 Galian Tanah 6,487,897.50 134,325.00 48.30
2 Pasir Urug 40,700.48 134,325.00 0.30
3 Urugan Kembali 3,746,324.25 134,325.00 27.89
6 Beton Pondasi 4,381,632.01 134,325.00 32.62
7 Baut Angkur M - 134,325.00 0.00
8 Base Plat 10m - 134,325.00 0.00
9 Pengecatan Bas 42,124.32 134,325.00 0.31
10 Plesteran Ponda 1,275,012.90 134,325.00 9.49
11 Acian Pondasi 2,215,825.20 134,325.00 16.50
18,189,516.66 134,325.00 135.4142316 2.2199
VIII PEKERJAAN BAK GREASE TRAP 134,325.00 0.00
1 Pek. Bobok Be 25,137,941.83 134,325.00 187.14
2 Galian Tanah 27,926,167.50 134,325.00 207.90
3 Pek. Dinding 3,088,319.81 134,325.00 22.99
4 Pek. Rabat Be 2,763,804.04 134,325.00 20.58
5 Acian 13,049,136.45 134,325.00 97.15
6 Pasir urug 10 377,184.60 134,325.00 2.81
7 Lantai kerja, 1,037,257.65 134,325.00 7.72
8 Plat Penutup 3,827,529.30 134,325.00 28.49
9 Elbow (L) PVC 556,830.86 134,325.00 4.15
10 Reduser Shock 299,571.62 134,325.00 2.23
11 Elbow ( T ) P 299,571.62 134,325.00 2.23
12 Tutup plat be - 134,325.00 0.00
78,363,315.26 134,325.00 583.3859316 9.5637
IX PEKERJAAN FISH POND DAN BAK C 134,325.00 0.00
1 Galian Tanah 289,134.56 134,325.00 2.15
2 urug pasir ba 9,268.43 134,325.00 0.07
3 Kolom Praktis 12,089.25 134,325.00 0.09
4 Pas. Bata, ca 570,612.60 134,325.00 4.25
5 Plesteran 1,135,583.55 134,325.00 8.45
6 Acian 870,963.30 134,325.00 6.48
7 Lantai Bak co 157,361.74 134,325.00 1.17
3,045,013.43 134,325.00 22.669 0.3716
X PEK. TAMAN, PAGAR DAN CANOPY 134,325.00 0.00
1 PEKERJAAN TAMAN 134,325.00 0.00
Pemupukan - 134,325.00 0.00
Bunga Sab - 134,325.00 0.00
Pucuk mer - 134,325.00 0.00
Begonia co - 134,325.00 0.00
Tanaman c - 134,325.00 0.00
Brokoli hia - 134,325.00 0.00
Lampu ta - 134,325.00 0.00
Name tag - 134,325.00 0.00
2 Pekerjaan paga - 134,325.00 0.00
3 Pekerjaan ata - 134,325.00 0.00
4 Sloof & Ring 4,188,925.13 134,325.00 31.19
5 Kolom Pagar 1,269,371.25 134,325.00 9.45
6 Pekerjaan Bal 4,188,925.13 134,325.00 31.19
7 Pekerjaan Pas 1,269,371.25 134,325.00 9.45
8 Plesteran 4,231,237.50 134,325.00 31.50
9 Acian 2,820,825.00 134,325.00 21.00
10 Pengecatan Pa 987,288.75 134,325.00 7.35
18,955,944.00 134,325.00 141.12 2.3134
XI PEKERJAAN RUMAH JAGA 134,325.00 0.00
1 Pekerjaan Pondasi 134,325.00 0.00
a Galian Tanah 808,972.31 134,325.00 6.02
b Pondasi Batu 566,179.88 134,325.00 4.22
c Urugan Kembal 319,021.88 134,325.00 2.38
2 Pekerjaan Slo 349,110.68 134,325.00 2.60
3 Lantai kerja 82,005.41 134,325.00 0.61
4 Pekerjaan Ko 265,157.55 134,325.00 1.97
5 Pekerjaan Bal 298,537.31 134,325.00 2.22
6 Pekerjaan Din 134,325.00 0.00
a Pasangan 1/2 1,404,367.88 134,325.00 10.46
b Plesteran 2,808,735.75 134,325.00 20.91
c Acian 1,872,490.50 134,325.00 13.94
6 Pekerjaan Ker 1,058,749.65 134,325.00 7.88
7 Pekerjaan Pin - 134,325.00 0.00
8 Pekerjaan Jen - 134,325.00 0.00
9 Pekerjaan Ata 134,325.00 0.00
a Rangka Baja - 134,325.00 0.00
b Atap Zincalum 888,156.90 134,325.00 6.61
c Listplank 78,580.13 134,325.00 0.59
d Profil Etnis Be - 134,325.00 0.00
11 Pengecatan D 187,249.05 134,325.00 1.39
10,987,314.86 134,325.00 81.7965 1.3409
134,325.00 0.00
TOTAL PEKERJAAN SIPIL 268,666,343.13 134,325.00
XII MESIN PENGOLAHAN AIR LIMBAH 134,325.00 0.00
Capacity : 134,325.00 0.00
Biomembrane - 134,325.00 0.00
Submersible i - 134,325.00 0.00
Circulation p - 134,325.00 0.00
Air injection - 134,325.00 0.00
Screen - 134,325.00 0.00
Turbidity pre - 134,325.00 0.00
Chlorinator - 134,325.00 0.00
Water flow me - 134,325.00 0.00
Panel control - 134,325.00 0.00
134,325.00 0.00
134,325.00 0.00
TOTAL PEKERJAAN MESIN - 134,325.00 0.00
XIII TESTING & COMISSIONING 134,325.00 0.00
1 Installation - 134,325.00 0.00
2 Sambung baru - 134,325.00 0.00
3 Sambung baru - 134,325.00 0.00
4 Testing & Com - 134,325.00 0.00
5 Training Oper - 134,325.00 0.00
TOTAL TESTING & COMISSIONING - 134,325.00 0.00
JUMLAH TOTAL PEM 268,666,343.13 134,325.00
B Pembangunan SPALD Kelurahan lag 134,325.00 0.00
I PEKERJAAN PERSIAPAN 134,325.00 0.00
1 Direksi Keet, 402,975.00 134,325.00 3.00
2 Papan Nama P - 134,325.00 0.00
3 Pembersihan 2,024,949.38 134,325.00 15.08
2,427,924.38 134,325.00 18.075
II PEKERJAAN PIPING 134,325.00 0.00
1 Pekerjaan gal 108,126,252.00 134,325.00 804.96
2 Pekerjaan pem - 134,325.00 0.00
3 Pekerjaan pem 11,098,737.45 134,325.00 82.63
4 Pekerjaan pem 7,528,916.25 134,325.00 56.05
5 Pekerjaan pem 3,706,564.05 134,325.00 27.59
6 Pekerjaan pem 4,023,302.40 134,325.00 29.95
7 Pekerjaan uru 44,489,783.25 134,325.00 331.21
8 Restorasi ha - 134,325.00 0.00
178,973,555.40 134,325.00 1332.392
134,325.00 0.00
III PEKERJAAN BAK KONTROL 1 ( 60 x 134,325.00 0.00
1 Galian Tanah 2,347,329.38 134,325.00 17.48
2 Pekerjaan Bob 4,468,768.43 134,325.00 33.27
3 Pek. Dinding 24,205.37 134,325.00 0.18
4 Pek. Rabat Be 4,552,408.58 134,325.00 33.89
5 Acian 94,564.80 134,325.00 0.70
6 Pasir urug 5c 33,446.93 134,325.00 0.25
7 Plat Dak Tutu 281,478.04 134,325.00 2.10
8 Elbow inlet + - 134,325.00 0.00
9 Tutup manhol - 134,325.00 0.00
11,802,201.50 134,325.00 87.86303
IV PEKERJAAN BAK KONTROL 2 ( 80 x 134,325.00 0.00
1 Galian Tanah 564,165.00 134,325.00 4.20
2 Pekerjaan Bob 1,074,653.73 134,325.00 8.00
3 Pek. Dinding 318,941.28 134,325.00 2.37
4 Pek. Lantai ba 1,046,123.10 134,325.00 7.79
5 Acian 87,042.60 134,325.00 0.65
6 Pasir urug 5c 142,653.15 134,325.00 1.06
7 Plat Dak Tutu 44,327.25 134,325.00 0.33
8 Elbow inlet + - 134,325.00 0.00
9 Tutup manhol - 134,325.00 0.00
3,277,906.11 134,325.00 24.4028
V PEKERJAAN BAK SUMPIT ( 3 unit ) 134,325.00 0.00
1 Pek. Bobok Be 976,143.80 134,325.00 7.27
2 Galian Tanah 731,399.63 134,325.00 5.45
3 Pek. Dinding 231,374.81 134,325.00 1.72
4 Pek. Rabat Be 119,683.58 134,325.00 0.89
5 Acian 390,079.80 134,325.00 2.90
6 Lantai kerja, 332,454.38 134,325.00 2.48
7 Plat Penutup 37,709.65 134,325.00 0.28
8 Tutup plat be - 134,325.00 0.00
2,818,845.64 134,325.00 20.9852644
VI PEKERJAAN BAK EQUALISASI 134,325.00 0.00
1 Galian Tanah 9,840,649.50 134,325.00 73.26
2 Urugan sirtu 137,347.31 134,325.00 1.02
3 Pasir urug t 110,012.18 134,325.00 0.82
4 Lantai kerja t 301,425.30 134,325.00 2.24
5 Lantai bak co 2,568,969.79 134,325.00 19.13
6 Dinding beton 12,586,789.80 134,325.00 93.70
7 Balok beton 528,837.53 134,325.00 3.94
8 Acian 26,865.00 134,325.00 0.20
9 Tutup plat ba - 134,325.00 0.00
26,100,896.40 134,325.00 194.311531
VII PEKERJAAN DUDUKAN BIOREACTOR 134,325.00 0.00
1
Galian Tanah 6,487,897.50 134,325.00 48.30
2
Pasir Urug 40,619.88 134,325.00 0.30
3
Urugan Kemba 3,746,324.25 134,325.00 27.89
4
Beton Pondas 4,381,632.01 134,325.00 32.62
5
Baut Angkur - 134,325.00 0.00
6
Base Plat 10 - 134,325.00 0.00
7
Pengecatan Ba 42,124.32 134,325.00 0.31
8
Plesteran Pon 1,275,012.90 134,325.00 9.49
9
Acian Pondasi 2,215,825.20 134,325.00 16.50
18,189,436.06 134,325.00 135.4136316
VIII PEKERJAAN BAK GRASE TRAP 134,325.00 0.00
1 Pek. Bobok Be 27,529,046.38 134,325.00 204.94
2 Galian Tanah 30,585,802.50 134,325.00 227.70
3 Pek. Dinding 3,382,343.80 134,325.00 25.18
4 Pek. Rabat Be 3,027,551.18 134,325.00 22.54
5 Acian 14,291,911.35 134,325.00 106.40
6 Pasir urug 10 413,049.38 134,325.00 3.08
7 Lantai kerja, 1,134,777.60 134,325.00 8.45
8 Plat Penutup 4,190,484.67 134,325.00 31.20
9 Elbow (L) PVC 609,862.37 134,325.00 4.54
10 Reduser Shock 328,102.25 134,325.00 2.44
11 Elbow ( T ) P 328,102.25 134,325.00 2.44
12 Tutup manhole - 134,325.00 0.00
85,821,033.70 134,325.00 638.9058902
IX PEKERJAAN FISH POND DAN BAK C 134,325.00 0.00
1 Galian Tanah 289,134.56 134,325.00 2.15
2 urug pasir ba 9,268.43 134,325.00 0.07
3 Kolom Praktis 12,089.25 134,325.00 0.09
4 Pas. Bata, ca 570,612.60 134,325.00 4.25
5 Plesteran 1,135,583.55 134,325.00 8.45
6 Acian 870,963.30 134,325.00 6.48
7 Lantai Bak co 157,361.74 134,325.00 1.17
3,045,013.43 134,325.00 22.669
X PEK. TAMAN, PAGAR DAN CANOPY 134,325.00 0.00
1 PEKERJAAN TAMAN 134,325.00 0.00
Pemupukan - 134,325.00 0.00
Bunga Sab - 134,325.00 0.00
Pucuk mer - 134,325.00 0.00
Begonia co - 134,325.00 0.00
Tanaman c - 134,325.00 0.00
Brokoli hia - 134,325.00 0.00
Lampu ta - 134,325.00 0.00
Name tag - 134,325.00 0.00
2 Pekerjaan paga - 134,325.00 0.00
3 Pekerjaan ata - 134,325.00 0.00
4 Sloof & Ring 4,188,925.13 134,325.00 31.19
5 Kolom Pagar 1,269,371.25 134,325.00 9.45
6 Pekerjaan Bal 4,188,925.13 134,325.00 31.19
7 Pekerjaan Pas 1,269,371.25 134,325.00 9.45
8 Plesteran 4,231,237.50 134,325.00 31.50
9 Acian 2,820,825.00 134,325.00 21.00
10 Pengecatan Pa 987,288.75 134,325.00 7.35
18,955,944.00 134,325.00 141.12
XI PEKERJAAN RUMAH JAGA 134,325.00 0.00
1 Pekerjaan Pondasi 134,325.00 0.00
a Galian Tanah 808,972.31 134,325.00 6.02
b Pondasi Batu 566,179.88 134,325.00 4.22
c Urugan Kembal 319,021.88 134,325.00 2.38
2 Pekerjaan Slo 349,110.68 134,325.00 2.60
3 Lantai kerja 82,005.41 134,325.00 0.61
4 Pekerjaan Ko 265,157.55 134,325.00 1.97
5 Pekerjaan Bal 298,537.31 134,325.00 2.22
6 Pekerjaan Dinding 134,325.00 0.00
a Pasangan 1/2 1,404,367.88 134,325.00 10.46
b Plesteran 2,808,735.75 134,325.00 20.91
c Acian 1,872,490.50 134,325.00 13.94
6 Pekerjaan Ker 1,058,749.65 134,325.00 7.88
7 Pekerjaan Pin - 134,325.00 0.00
8 Pekerjaan Jen - 134,325.00 0.00
9 Pekerjaan Atap 134,325.00 0.00
a Rangka Baja - 134,325.00 0.00
b Atap Zincalum 888,156.90 134,325.00 6.61
c Listplank 78,580.13 134,325.00 0.59
d Profil Etnis Be - 134,325.00 0.00
11 Pengecatan D 187,249.05 134,325.00 1.39
10,987,314.86 134,325.00 81.7965
TOTAL PEKERJAAN SIPIL 362,400,071.49 134,325.00
XII MESIN PENGOLAHAN AIR LIMBAH 134,325.00 0.00
Capacity : 134,325.00 0.00
Biomembrane - 134,325.00 0.00
Submersible i - 134,325.00 0.00
Circulation p - 134,325.00 0.00
Air injection - 134,325.00 0.00
Screen - 134,325.00 0.00
Turbidity pre - 134,325.00 0.00
Chlorinator - 134,325.00 0.00
Water flow me - 134,325.00 0.00
Panel control - 134,325.00 0.00
134,325.00 0.00
134,325.00 0.00
TOTAL PEKERJAAN MESIN - 134,325.00 0.00
XIII INSTALLATION, TESTING & COMIS 134,325.00 0.00
1 Installation - 134,325.00 0.00
2 Sambung baru - 134,325.00 0.00
3 Sambung baru - 134,325.00 0.00
4 Testing & Com - 134,325.00 0.00
5 Training Oper - 134,325.00 0.00
TOTAL TESTING & COMISSIONING - 134,325.00 0.00
JUMLAH TOTAL PEM 362,400,071.49 134,325.00 4698.06 4698.06
KOREKSI
631,066,414.62
631,066,414.62
RENCANA ANGGARAN BIAYA
Program : 1.03.02 Program Pengembangan dan Pengelolaan Air Limbah
Nama Kegiatan : 1.03.02.001 Pembangunan Sistem Pengelolaan Air Limbah Domestik (SPALD) di Wilayah Jakarta Utara
Kode Rekening : 5.2.3.23.15 Belanja Modal Pengadaan Konstruksi Instalasi Pengelolahan Air Kotor / Limbah (IPAK/IPAL)
Rincian Pekerjaan : Pembangunan Sistem Pengelolaan Air Limbah Domestik (SPALD) di Kecamatan Koja
Lokasi Kegiatan : Jl. Inspeksi Kali Sunter, Kelurahan Koja dan Kelurahan Lagoa
Tahun Anggaran : 2019
Waktu Pelaksanaan : 120 hari Kalender
HPS : Rp8.589.900,00
HARGA JUMLAH
NO URAIAN PEKERJAAN ANALISA VOLUME SAT SATUAN HARGA GAJI OH TOT. OH
( Rp ) ( Rp )
A Pembangunan SPALD Kelurahan Koja 154,722.50 0.00
I PEKERJAAN PERSIAPAN 154,722.50 0.00
1 Direksi Keet, Pondok Kerja dan Gudang Bahan A.2.2.1.6 30.00 m2 77,361.25 2,320,837.50 154,722.50 15.00
2 Papan Nama Proyek Ls 1.00 ls - 154,722.50 0.00
3 Pembersihan Lapangan A.2.2.1.9 150.75 m2 - - 154,722.50 0.00
2,320,837.50 154,722.50 15
II PEKERJAAN PIPING 154,722.50 0.00
1 Pekerjaan galian tanah dalam 50 - 90 cm A.2.3.1.1 604.80 m³ - - 154,722.50 0.00
2 Pekerjaan pemasangan pipa SR PVC 3 inchi P1 2,000.00 m' - - 154,722.50 0.00
3 Pekerjaan pemasangan pipa Sub Line PVC 4 inchi P2 300.00 m' 7,271.96 2,181,587.25 154,722.50 14.10
4 Pekerjaan pemasangan pipa Sub Mainline PVC 6 inchi P3 700.00 m' 9,128.63 6,390,039.25 154,722.50 41.30
5 Pekerjaan pemasangan pipa Mainline PVC 8 inchi P4 110.00 m' 14,698.64 1,616,850.13 154,722.50 10.45
6 Pekerjaan pemasangan pipa Feeder PVC 10 inchi P5 250.00 m' 19,804.48 4,951,120.00 154,722.50 32.00
7 Pekerjaan urugan tanah kembali A.2.3.1.9 120.96 m³ - - 154,722.50 0.00
8 Restorasi halaman rumah warga LS 200.00 kk - 154,722.50 0.00
15,139,596.63 154,722.50 97.85
154,722.50 0.00
III PEKERJAAN BAK KONTROL 1 ( 60 x 60 cm ) 154,722.50 0.00
1 Galian Tanah A.2.3.1.1 15.23 m³ - - 154,722.50 0.00
2 Pekerjaan Bobok Beton Jalan A.2.2.1.13 3.26 m³ - - 154,722.50 0.00
3 Pek. Dinding Bak cor Beton bertulang, tebal : 10cm A.4.1.1.33.ab 0.34 m³ 42,548.69 14,466.55 154,722.50 0.09
4 Pek. Rabat Beton Lantai, tebal : 10cm A.4.1.1.5 13.43 m³ 42,548.69 571,428.87 154,722.50 3.69
5 Acian A.4.4.2.27 3.52 m² 15,472.25 54,462.32 154,722.50 0.35
6 Pasir urug 5cm A.2.3.1.11.b 0.54 m³ - - 154,722.50 0.00
7 Plat Dak Tutup bak cor beton bertulang, t : 10cm, wiremesh 1 layer M8-150 A.4.1.1.1 0.83 m³ 42,548.69 35,315.41 154,722.50 0.23
8 Elbow inlet + outlet( L-45°) PVC 6" LS 2.00 unit - - 154,722.50 0.00
9 Tutup manhole Cor Beton bertulang LS 17.00 bh - 154,722.50 0.00
675,673.16 154,722.50 4.367
IV PEKERJAAN BAK KONTROL 2 ( 80 x 80 cm ) 154,722.50 0.00
1 Galian Tanah A.2.3.1.1 11.20 m³ - - 154,722.50 0.00
2 Pekerjaan Bobok lantai A.2.2.1.13 2.40 m³ - - 154,722.50 0.00
3 Pek. Dinding Bak cor Beton bertulang, tebal : 10cm A.4.1.1.33.ab 8.96 m³ 42,548.69 381,236.24 154,722.50 2.46
4 Pek. Lantai bak, tebal : 10cm A.4.1.1.5 9.44 m³ 42,548.69 401,659.61 154,722.50 2.60
5 Acian A.4.4.2.27 6.48 m² 15,472.25 100,260.18 154,722.50 0.65
6 Pasir urug 5cm A.2.3.1.11.b 7.08 m³ - - 154,722.50 0.00
7 Plat Dak Tutup bak cor beton bertulang, t : 10cm, wiremesh 1 layer M8-150 A.4.1.1.1 0.39 m³ 42,548.69 16,593.99 154,722.50 0.11
8 Elbow inlet + outlet( L-45°) PVC 6" LS 2.00 unit - - 154,722.50 0.00
9 Tutup manhole Cor Beton bertulang LS 8.00 bh - 154,722.50 0.00
899,750.02 154,722.50 5.81525
V PEKERJAAN BAK SUMPIT ( 1 unit ) 154,722.50 0.00
1 Pek. Bobok Beton Lantai Jalan, t : 30cm A.2.2.1.13 0.36 m³ - - 154,722.50 0.00
2 Galian Tanah A.2.3.1.1 2.42 m³ - - 154,722.50 0.00
3 Pek. Dinding Bak cor beton bertulang, t : 10cm, wiremesh 1 layer M8-150 A.4.1.1.33.ab 1.08 m³ 42,548.69 45,952.58 154,722.50 0.30
4 Pek. Rabat Benton Lantai, tebal : 15cm A.4.1.1.5 0.18 m³ 42,548.69 7,658.76 154,722.50 0.05
5 Acian A.4.4.2.27 4.84 m² 15,472.25 74,885.69 154,722.50 0.48
6 Lantai kerja, t : 5cm A.4.1.1.1 0.50 m³ 42,548.69 21,274.34 154,722.50 0.14
7 Plat Penutup Dak Beton Bertulang, t : 10cm A.4.1.1.37 0.08 m³ 266,382.63 21,310.61 154,722.50 0.14
8 Tutup plat besi ( manhole ) LS 1.00 set - 154,722.50 0.00
171,081.99 154,722.50 1.1057344
VI PEKERJAAN BAK EQUALISASI 154,722.50 0.00
1 Galian Tanah A.2.3.1.1 97.68 m³ - - 154,722.50 0.00
2 Urugan sirtu t = 15 cm A.2.3.1.14 4.09 m³ - - 154,722.50 0.00
3 Pasir urug t = 10 cm A.2.3.1.11.b 2.73 m³ - - 154,722.50 0.00
4 Lantai kerja t = 5 cm A.4.1.1.1 1.36 m³ 42,548.69 57,866.22 154,722.50 0.37
5 Lantai bak cor beton bertulang A.4.1.1.37 5.45 m³ 266,382.63 1,451,785.35 154,722.50 9.38
6 Dinding beton bertulang A.4.1.1.33.a 17.68 m³ 406,146.56 7,180,671.23 154,722.50 46.41
7 Balok beton 15/20cm A.4.1.1.31.a 0.62 m³ 514,452.31 318,960.43 154,722.50 2.06
8 Acian A.4.4.2.27 1.00 m² 15,472.25 15,472.25 154,722.50 0.10
9 Tutup plat baja rangka siku L.50.50.5 LS 2.00 set - 154,722.50 0.00
9,024,755.48 154,722.50 58.328656
VII PEKERJAAN DUDUKAN BIOREACTOR ( 1 UNIT ) 154,722.50 0.00
1 Galian Tanah A.2.3.1.1 64.40 m³ - - 154,722.50 0.00
2 Pasir Urug A.2.3.1.11.b 1.01 m³ - - 154,722.50 0.00
3 Urugan Kembali A.2.3.1.9 55.78 m³ - - 154,722.50 0.00
6 Beton Pondasi K350 A.4.1.1.37B 8.62 m³ 264,448.60 2,279,546.95 154,722.50 14.73
7 Baut Angkur M16 c 56.00 bh - - 154,722.50 0.00
8 Base Plat 10mm f 1,758.40 kg - - 154,722.50 0.00
9 Pengecatan Base Plat A.4.4.2.3 4.48 m² 1,392.50 6,238.41 154,722.50 0.04
10 Plesteran Pondasi A.4.4.2.4 31.64 m² 23,208.38 734,312.99 154,722.50 4.75
11 Acian Pondasi A.4.4.2.27 82.48 m² 15,472.25 1,276,151.18 154,722.50 8.25
4,296,249.53 154,722.50 27.7674516
VIII PEKERJAAN BAK GREASE TRAP 154,722.50 0.00
1 Pek. Bobok Beton Lantai Jalan, t :30cm A.2.2.1.13 28.07 m³ - - 154,722.50 0.00
2 Galian Tanah A.2.3.1.1 277.20 m³ - - 154,722.50 0.00
3 Pek. Dinding Bak beton bertulang, t : 10cm, wiremesh 1 layer M8-150 A.4.1.1.33.ab 43.38 m³ 42,548.69 1,845,762.06 154,722.50 11.93
4 Pek. Rabat Benton Lantai, tebal : 15cm A.4.1.1.5 12.47 m³ 42,548.69 530,582.13 154,722.50 3.43
5 Acian A.4.4.2.27 485.73 m³ 15,472.25 7,515,335.99 154,722.50 48.57
6 Pasir urug 10 cm A.2.3.1.11.b 9.36 m³ - - 154,722.50 0.00
7 Lantai kerja, t : 5cm A.4.1.1.1 4.68 m² 42,548.69 199,127.86 154,722.50 1.29
8 Plat Penutup Dak Beton Bertulang, t : 10cm A.4.1.1.37 8.12 m¹ 266,382.63 2,163,026.99 154,722.50 13.98
9 Elbow (L) PVC 4" - 126.00 bh 2,545.19 320,693.33 154,722.50 2.07
10 Reduser Shock PVC 4" - 6" - 63.00 bh 2,738.59 172,531.06 154,722.50 1.12
11 Elbow ( T ) PVC 6" - 63.00 bh 2,738.59 172,531.06 154,722.50 1.12
12 Tutup plat besi ( manhole ) - 126.00 set - 154,722.50 0.00
12,919,590.48 154,722.50 83.5016916
IX PEKERJAAN FISH POND DAN BAK CHLORINASI 154,722.50 0.00
1 Galian Tanah A.2.3.1.1 2.87 m³ - - 154,722.50 0.00
2 urug pasir bawah lantai beton A.2.3.1.11.b 0.23 m² - - 154,722.50 0.00
3 Kolom Praktis A.4.1.1.35 0.50 m³ 9,283.35 4,641.68 154,722.50 0.03
4 Pas. Bata, camp 1 : 4 A.4.4.1.8 14.16 m² 15,472.25 219,087.06 154,722.50 1.42
5 Plesteran A.4.4.2.4 28.18 m² 23,208.38 654,012.01 154,722.50 4.23
6 Acian A.4.4.2.27 32.42 m² 15,472.25 501,610.35 154,722.50 3.24
7 Lantai Bak cor beton camp. K.175 A.4.1.1.5 0.71 m³ 42,548.69 30,209.57 154,722.50 0.20
1,409,560.66 154,722.50 9.11025
X PEK. TAMAN, PAGAR DAN CANOPY 154,722.50 0.00
1 PEKERJAAN TAMAN 154,722.50 0.00
Pemupukan tanah LS 110.25 m² - 154,722.50 0.00
Bunga Sabrina LS 30.00 bh - 154,722.50 0.00
Pucuk merah LS 20.00 bh - 154,722.50 0.00
Begonia cokelat LS 50.00 bh - 154,722.50 0.00
Tanaman calathea ctenanthe LS 10.00 bh - 154,722.50 0.00
Brokoli hias LS 30.00 bh - 154,722.50 0.00
Lampu taman LS 6.00 bh - 154,722.50 0.00
Name tag (Huruf timbul) IPAL LS 1.00 bh - 154,722.50 0.00
2 Pekerjaan pagar besi keliling IPAL LS 105.00 m¹ - 154,722.50 0.00
3 Pekerjaan atap kanopi LS 162.00 m² - 154,722.50 0.00
4 Sloof & Ring Balk uk.15x15 A.4.1.1.36 105.00 m¹ 15,317.53 1,608,340.39 154,722.50 10.40
5 Kolom Pagar uk.30x30 A.4.1.1.35 52.50 m¹ 9,283.35 487,375.88 154,722.50 3.15
6 Pekerjaan Balok Pagar A.4.1.1.36 105.00 m¹ 15,317.53 1,608,340.39 154,722.50 10.40
7 Pekerjaan Pas. Dinding Pagar 1/2 Bata, camp. 1:4 A.4.4.1.8 31.50 m² 15,472.25 487,375.88 154,722.50 3.15
8 Plesteran A.4.4.2.4 105.00 m² 23,208.38 2,436,879.38 154,722.50 15.75
9 Acian A.4.4.2.27 105.00 m² 15,472.25 1,624,586.25 154,722.50 10.50
10 Pengecatan Pagar Besi A.4.4.2.3 105.00 m¹ 1,392.50 146,212.76 154,722.50 0.95
8,399,110.91 154,722.50 54.285
XI PEKERJAAN RUMAH JAGA 154,722.50 0.00
1 Pekerjaan Pondasi 154,722.50 0.00
a Galian Tanah Pondasi A.2.3.1.1 8.03 m³ - - 154,722.50 0.00
b Pondasi Batu Belah 1:4 A.2.2.1.4x 2.81 m³ 116,041.88 326,077.67 154,722.50 2.11
c Urugan Kembali Galian Pondasi A.2.3.1.9 4.75 m³ - - 154,722.50 0.00
2 Pekerjaan Sloof 20x15 A.4.1.1.29.a 0.46 m³ 500,527.29 230,242.55 154,722.50 1.49
3 Lantai kerja K100 A.4.1.1.1 0.37 m³ 42,548.69 15,743.01 154,722.50 0.10
4 Pekerjaan Kolom 15x15 A.4.1.1.35.a 0.28 m³ 622,758.06 174,372.26 154,722.50 1.13
5 Pekerjaan Balok 15x15 A.4.1.1.31.a 0.35 m³ 514,452.31 180,058.31 154,722.50 1.16
6 Pekerjaan Dinding 0.00 - 154,722.50 0.00
a Pasangan 1/2 Bata A.4.4.1.8 34.85 m² 15,472.25 539,207.91 154,722.50 3.49
b Plesteran A.4.4.2.4 69.70 m² 23,208.38 1,617,623.74 154,722.50 10.46
c Acian A.4.4.2.27 69.70 m² 15,472.25 1,078,415.83 154,722.50 6.97
6 Pekerjaan Keramik A.4.4.3.35 11.26 m² 54,152.88 609,761.37 154,722.50 3.94
7 Pekerjaan Pintu Ls 1.00 unit - 154,722.50 0.00
8 Pekerjaan Jendela Ls 4.00 unit - 154,722.50 0.00
9 Pekerjaan Atap 0.00 154,722.50 0.00
a Rangka Baja Ringan Ls 33.06 m² - 154,722.50 0.00
b Atap Zincalume A.4.5.1.7 33.06 m² 15,472.25 511,512.59 154,722.50 3.31
c Listplank A.4.5.2.38b 5.85 m² 30,944.50 181,025.33 154,722.50 1.17
d Profil Etnis Betawi Ls 23.40 m' - - 154,722.50 0.00
11 Pengecatan Dinding A.4.7.1.10 69.70 m² 9,747.52 679,401.97 154,722.50 4.39
6,143,442.53 154,722.50 39.7062
154,722.50 0.00
TOTAL PEKERJAAN SIPIL 61,399,648.88 154,722.50
XII MESIN PENGOLAHAN AIR LIMBAH 154,722.50 0.00
Capacity : 100 m3/day 154,722.50 0.00
Biomembrane Reactor 1.00 set - 154,722.50 0.00
Submersible inlet pump 2.00 unit - 154,722.50 0.00
Circulation pump 1.00 unit - 154,722.50 0.00
Air injection 2.00 unit - 154,722.50 0.00
Screen 1.00 unit - 154,722.50 0.00
Turbidity pretreatment 1.00 unit - 154,722.50 0.00
Chlorinator 1.00 unit - 154,722.50 0.00
Water flow meter 2.00 unit - 154,722.50 0.00
Panel control 1.00 unit - 154,722.50 0.00
154,722.50 0.00
154,722.50 0.00
TOTAL PEKERJAAN MESIN - 154,722.50 0.00
XIII TESTING & COMISSIONING 154,722.50 0.00
1 Installation 1.00 ls - 154,722.50 0.00
2 Sambung baru PLN, Bio-Reaktor IPAL ( 22 KVA, 3 phase ) 1.00 ls - 154,722.50 0.00
3 Sambung baru PLN, Pompa sampit ( 2,200 watt, 1 phase ) 1.00 ttk - 154,722.50 0.00
4 Testing & Comissioning 1.00 ls - 154,722.50 0.00
5 Training Operator 1.00 bln - 154,722.50 0.00
TOTAL TESTING & COMISSIONING - 154,722.50 0.00
JUMLAH TOTAL PEMBANGUNAN SPALD KOJA 61,399,648.88 154,722.50
B Pembangunan SPALD Kelurahan lagoa 154,722.50 0.00
I PEKERJAAN PERSIAPAN 154,722.50 0.00
1 Direksi Keet, Pondok Kerja dan Gudang Bahan A.2.2.1.6 30.00 m2 77,361.25 2,320,837.50 154,722.50 15.00
2 Papan Nama Proyek Ls 1.00 ls - 154,722.50 0.00
3 Pembersihan Lapangan A.2.2.1.9 150.75 m2 - - 154,722.50 0.00
2,320,837.50 154,722.50 15
II PEKERJAAN PIPING 154,722.50 0.00
1 Pekerjaan galian tanah dalam 50 - 90 cm A.2.3.1.1 1,073.28 m³ - - 154,722.50 0.00
2 Pekerjaan pemasangan pipa SR PVC 3 inchi P1 2,000.00 m' - - 154,722.50 0.00
3 Pekerjaan pemasangan pipa Sub Line PVC 4 inchi P2 879.00 m' 7,271.96 6,392,050.64 154,722.50 41.31
4 Pekerjaan pemasangan pipa Sub Mainline PVC 6 inchi P3 475.00 m' 9,128.63 4,336,098.06 154,722.50 28.03
5 Pekerjaan pemasangan pipa Mainline PVC 8 inchi P4 146.00 m' 14,698.64 2,146,001.08 154,722.50 13.87
6 Pekerjaan pemasangan pipa Feeder PVC 10 inchi P5 117.00 m' 19,804.48 2,317,124.16 154,722.50 14.98
7 Pekerjaan urugan tanah kembali A.2.3.1.9 662.42 m³ - - 154,722.50 0.00
8 Restorasi halaman rumah warga LS 200.00 kk - 154,722.50 0.00
15,191,273.94 154,722.50 98.184
154,722.50 0.00
III PEKERJAAN BAK KONTROL 1 ( 60 x 60 cm ) 154,722.50 0.00
1 Galian Tanah A.2.3.1.1 23.30 m³ - - 154,722.50 0.00
2 Pekerjaan Bobok Beton Jalan A.2.2.1.13 4.99 m³ - - 154,722.50 0.00
3 Pek. Dinding Bak cor Beton bertulang, tebal : 10cm A.4.1.1.33.ab 0.34 m³ 42,548.69 14,466.55 154,722.50 0.09
4 Pek. Rabat Beton Lantai, tebal : 10cm A.4.1.1.5 20.54 m³ 42,548.69 873,950.04 154,722.50 5.65
5 Acian A.4.4.2.27 3.52 m² 15,472.25 54,462.32 154,722.50 0.35
6 Pasir urug 5cm A.2.3.1.11.b 0.83 m³ - - 154,722.50 0.00
7 Plat Dak Tutup bak cor beton bertulang, t : 10cm, wiremesh 1 layer M8-150 A.4.1.1.1 1.27 m³ 42,548.69 54,036.83 154,722.50 0.35
8 Elbow inlet + outlet( L-45°) PVC 6" LS 52.00 unit - - 154,722.50 0.00
9 Tutup manhole Cor Beton bertulang LS 26.00 bh - 154,722.50 0.00
996,915.75 154,722.50 6.44325
IV PEKERJAAN BAK KONTROL 2 ( 80 x 80 cm ) 154,722.50 0.00
1 Galian Tanah A.2.3.1.1 5.60 m³ - - 154,722.50 0.00
2 Pekerjaan Bobok lantai A.2.2.1.13 1.20 m³ - - 154,722.50 0.00
3 Pek. Dinding Bak cor Beton bertulang, tebal : 10cm A.4.1.1.33.ab 4.48 m³ 42,548.69 190,618.12 154,722.50 1.23
4 Pek. Lantai bak, tebal : 10cm A.4.1.1.5 4.72 m³ 42,548.69 200,829.81 154,722.50 1.30
5 Acian A.4.4.2.27 3.24 m² 15,472.25 50,130.09 154,722.50 0.32
6 Pasir urug 5cm A.2.3.1.11.b 3.54 m³ - - 154,722.50 0.00
7 Plat Dak Tutup bak cor beton bertulang, t : 10cm, wiremesh 1 layer M8-150 A.4.1.1.1 0.20 m³ 42,548.69 8,509.74 154,722.50 0.06
8 Elbow inlet + outlet( L-45°) PVC 6" LS 8.00 unit - - 154,722.50 0.00
9 Tutup manhole Cor Beton bertulang LS 4.00 bh - 154,722.50 0.00
450,087.75 154,722.50 2.909
V PEKERJAAN BAK SUMPIT ( 3 unit ) 154,722.50 0.00
1 Pek. Bobok Beton Lantai Jalan, t : 30cm A.2.2.1.13 1.09 m³ - - 154,722.50 0.00
2 Galian Tanah A.2.3.1.1 7.26 m³ - - 154,722.50 0.00
3 Pek. Dinding Bak cor beton bertulang, t : 10cm, wiremesh 1 layer M8-150 A.4.1.1.33.ab 3.25 m³ 42,548.69 138,283.23 154,722.50 0.89
4 Pek. Rabat Benton Lantai, tebal : 15cm A.4.1.1.5 0.54 m³ 42,548.69 22,976.29 154,722.50 0.15
5 Acian A.4.4.2.27 14.52 m² 15,472.25 224,657.07 154,722.50 1.45
6 Lantai kerja, t : 5cm A.4.1.1.1 1.50 m³ 42,548.69 63,823.03 154,722.50 0.41
7 Plat Penutup Dak Beton Bertulang, t : 10cm A.4.1.1.37 0.08 m³ 266,382.63 21,310.61 154,722.50 0.14
8 Tutup plat besi ( manhole ) LS 3.00 set - 154,722.50 0.00
471,050.24 154,722.50 3.0444844
VI PEKERJAAN BAK EQUALISASI 154,722.50 0.00
1 Galian Tanah A.2.3.1.1 97.68 m³ - - 154,722.50 0.00
2 Urugan sirtu t = 15 cm A.2.3.1.14 4.09 m³ - - 154,722.50 0.00
3 Pasir urug t = 10 cm A.2.3.1.11.b 2.73 m³ - - 154,722.50 0.00
4 Lantai kerja t = 5 cm A.4.1.1.1 1.36 m³ 42,548.69 57,866.22 154,722.50 0.37
5 Lantai bak cor beton bertulang A.4.1.1.37 5.45 m³ 266,382.63 1,451,785.35 154,722.50 9.38
6 Dinding beton bertulang A.4.1.1.33.a 17.68 m³ 406,146.56 7,180,671.23 154,722.50 46.41
7 Balok beton 15/20cm A.4.1.1.31.a 0.62 m³ 514,452.31 318,960.43 154,722.50 2.06
8 Acian A.4.4.2.27 1.00 m² 15,472.25 15,472.25 154,722.50 0.10
9 Tutup plat baja rangka siku L.50.50.5 LS 2.00 unit - 154,722.50 0.00
9,024,755.48 154,722.50 58.328656
VII PEKERJAAN DUDUKAN BIOREACTOR ( 1 UNIT ) 154,722.50 0.00
1 Galian Tanah A.2.3.1.1 64.40 m³ - - 154,722.50 0.00
2 Pasir Urug A.2.3.1.11.b 1.01 m³ - - 154,722.50 0.00
3 Urugan Kembali A.2.3.1.9 55.78 m³ - - 154,722.50 0.00
4 Beton Pondasi K350 A.4.1.1.37B 8.62 m³ 264,448.60 2,279,546.95 154,722.50 14.73
5 Baut Angkur c 56.00 m³ - - 154,722.50 0.00
6 Base Plat 10mm f 1,758.40 m³ - - 154,722.50 0.00
7 Pengecatan Base Plat A.4.4.2.3 4.48 m² 1,392.50 6,238.41 154,722.50 0.04
8 Plesteran Pondasi A.4.4.2.4 31.64 m² 23,208.38 734,312.99 154,722.50 4.75
9 Acian Pondasi A.4.4.2.27 82.48 m³ 15,472.25 1,276,151.18 154,722.50 8.25
4,296,249.53 154,722.50 27.7674516
VIII PEKERJAAN BAK GRASE TRAP 154,722.50 0.00
1 Pek. Bobok Beton Lantai Jalan, t :30cm A.2.2.1.13 30.74 m3 - - 154,722.50 0.00
2 Galian Tanah A.2.3.1.1 303.60 m3 - - 154,722.50 0.00
3 Pek. Dinding Bak cor beton bertulang, wiremess M8-150, t : 10cm A.4.1.1.33.ab 47.51 m3 42,548.69 2,021,488.14 154,722.50 13.07
4 Pek. Rabat Benton Lantai tanpa tulang, tebal : 15cm A.4.1.1.5 13.66 m2 42,548.69 581,215.07 154,722.50 3.76
5 Acian A.4.4.2.27 531.99 m2 15,472.25 8,231,082.28 154,722.50 53.20
6 Pasir urug 10 cm A.2.3.1.11.b 10.25 m3 - - 154,722.50 0.00
7 Lantai kerja, t : 5cm A.4.1.1.1 5.12 m3 42,548.69 217,849.28 154,722.50 1.41
8 Plat Penutup Dak Beton Bertulang, t : 10cm A.4.1.1.37 8.89 bh 266,382.63 2,368,141.61 154,722.50 15.31
9 Elbow (L) PVC 4" - 138.00 bh 2,545.19 351,235.55 154,722.50 2.27
10 Reduser Shock PVC 4" - 6" - 69.00 bh 2,738.59 188,962.59 154,722.50 1.22
11 Elbow ( T ) PVC 6" - 69.00 bh 2,738.59 188,962.59 154,722.50 1.22
12 Tutup manhole plat beton bertulang - 138.00 pcs - 154,722.50 0.00
14,148,937.11 154,722.50 91.4471852
IX PEKERJAAN FISH POND DAN BAK CHLORINASI 154,722.50 0.00
1 Galian Tanah A.2.3.1.1 2.87 m³ - - 154,722.50 0.00
2 urug pasir bawah lantai beton A.2.3.1.11.b 0.23 m² - - 154,722.50 0.00
3 Kolom Praktis A.4.1.1.35 0.50 m³ 9,283.35 4,641.68 154,722.50 0.03
4 Pas. Bata, camp 1 : 4 A.4.4.1.8 14.16 m² 15,472.25 219,087.06 154,722.50 1.42
5 Plesteran A.4.4.2.4 28.18 m² 23,208.38 654,012.01 154,722.50 4.23
6 Acian A.4.4.2.27 32.42 m² 15,472.25 501,610.35 154,722.50 3.24
7 Lantai Bak cor beton camp. K.175 A.4.1.1.5 0.71 m³ 42,548.69 30,209.57 154,722.50 0.20
1,409,560.66 154,722.50 9.11025
X PEK. TAMAN, PAGAR DAN CANOPY 154,722.50 0.00
1 PEKERJAAN TAMAN 154,722.50 0.00
Pemupukan tanah LS 110.25 m² - 154,722.50 0.00
Bunga Sabrina LS 30.00 bh - 154,722.50 0.00
Pucuk merah LS 20.00 bh - 154,722.50 0.00
Begonia cokelat LS 50.00 bh - 154,722.50 0.00
Tanaman calathea ctenanthe LS 10.00 bh - 154,722.50 0.00
Brokoli hias LS 30.00 bh - 154,722.50 0.00
Lampu taman LS 6.00 bh - 154,722.50 0.00
Name tag (Huruf timbul) IPAL LS 1.00 bh - 154,722.50 0.00
2 Pekerjaan pagar besi keliling IPAL LS 105.00 m¹ - 154,722.50 0.00
3 Pekerjaan atap kanopi LS 162.00 m² - 154,722.50 0.00
4 Sloof & Ring Balk uk.15x15 A.4.1.1.36 105.00 m¹ 15,317.53 1,608,340.39 154,722.50 10.40
5 Kolom Pagar uk.30x30 A.4.1.1.35 52.50 m¹ 9,283.35 487,375.88 154,722.50 3.15
6 Pekerjaan Balok Pagar A.4.1.1.36 105.00 m¹ 15,317.53 1,608,340.39 154,722.50 10.40
7 Pekerjaan Pas. Dinding Pagar 1/2 Bata, camp. 1:4 A.4.4.1.8 31.50 15,472.25 487,375.88 154,722.50 3.15
8 Plesteran A.4.4.2.4 105.00 m² 23,208.38 2,436,879.38 154,722.50 15.75
9 Acian A.4.4.2.27 105.00 m² 15,472.25 1,624,586.25 154,722.50 10.50
10 Pengecatan Pagar Besi A.4.4.2.3 105.00 m¹ 1,392.50 146,212.76 154,722.50 0.95
8,399,110.91 154,722.50 54.285
XI PEKERJAAN RUMAH JAGA 154,722.50 0.00
1 Pekerjaan Pondasi 154,722.50 0.00
a Galian Tanah Pondasi A.2.3.1.1 8.03 m³ - - 154,722.50 0.00
b Pondasi Batu Belah 1:4 A.2.2.1.4x 2.81 m³ 116,041.88 326,077.67 154,722.50 2.11
c Urugan Kembali Galian Pondasi A.2.3.1.9 4.75 m³ - - 154,722.50 0.00
2 Pekerjaan Sloof 20x15 A.4.1.1.29.a 0.46 m³ 500,527.29 230,242.55 154,722.50 1.49
3 Lantai kerja K100 A.4.1.1.1 0.37 m³ 42,548.69 15,743.01 154,722.50 0.10
4 Pekerjaan Kolom 15x15 A.4.1.1.35.a 0.28 m³ 622,758.06 174,372.26 154,722.50 1.13
5 Pekerjaan Balok 15x15 A.4.1.1.31.a 0.35 m³ 514,452.31 180,058.31 154,722.50 1.16
6 Pekerjaan Dinding 154,722.50 0.00
a Pasangan 1/2 Bata A.4.4.1.8 34.85 m² 15,472.25 539,207.91 154,722.50 3.49
b Plesteran A.4.4.2.4 69.70 m² 23,208.38 1,617,623.74 154,722.50 10.46
c Acian A.4.4.2.27 69.70 m² 15,472.25 1,078,415.83 154,722.50 6.97
6 Pekerjaan Keramik A.4.4.3.35 11.26 m² 54,152.88 609,761.37 154,722.50 3.94
7 Pekerjaan Pintu Ls 1.00 unit - 154,722.50 0.00
8 Pekerjaan Jendela Ls 4.00 unit - 154,722.50 0.00
9 Pekerjaan Atap 154,722.50 0.00
a Rangka Baja Ringan Ls 33.06 m² - 154,722.50 0.00
b Atap Zincalume A.4.5.1.7 33.06 m² 15,472.25 511,512.59 154,722.50 3.31
c Listplank A.4.5.2.38b 5.85 m² 30,944.50 181,025.33 154,722.50 1.17
d Profil Etnis Betawi Ls 23.40 m' - 154,722.50 0.00
11 Pengecatan Dinding A.4.7.1.10 69.70 m² 9,747.52 679,401.97 154,722.50 4.39
6,143,442.53 154,722.50 39.7062
TOTAL PEKERJAAN SIPIL 62,852,221.40 154,722.50
XII MESIN PENGOLAHAN AIR LIMBAH 154,722.50 0.00
Capacity : 100 m3/day 154,722.50 0.00
Biomembrane Reactor 1.00 set - 154,722.50 0.00
Submersible inlet pump 2.00 unit - 154,722.50 0.00
Circulation pump 1.00 unit - 154,722.50 0.00
Air injection 2.00 unit - 154,722.50 0.00
Screen 1.00 unit - 154,722.50 0.00
Turbidity pretreatment 1.00 unit - 154,722.50 0.00
Chlorinator 1.00 unit - 154,722.50 0.00
Water flow meter 2.00 unit - 154,722.50 0.00
Panel control 1.00 unit - 154,722.50 0.00
154,722.50 0.00
154,722.50 0.00
TOTAL PEKERJAAN MESIN - 154,722.50 0.00
XIII INSTALLATION, TESTING & COMISSIONING 154,722.50 0.00
1 Installation 1.00 ls - 154,722.50 0.00
2 Sambung baru PLN, Bio-Reaktor IPAL ( 22 KVA, 3 phase ) 1.00 ls - 154,722.50 0.00
3 Sambung baru PLN, Pompa sampit ( 2,200 watt, 1 phase ) 3.00 ttk - 154,722.50 0.00
4 Testing & Comissioning 1.00 ls - 154,722.50 0.00
5 Training Operator 1.00 bln - 154,722.50 0.00
TOTAL TESTING & COMISSIONING - 154,722.50 0.00
JUMLAH TOTAL PEMBANGUNAN SPALD LAGOA 62,852,221.40 803.06 803.06
KOREKSI
124,251,870.27
124,251,870.27
HARGA JUMLAH
NO URAIAN PEKERJAAN ANALISA VOLUME SAT SATUAN HARGA GAJI OH TOT. OH
( Rp ) ( Rp )
A Pembangunan SPALD Kelurahan Koja 169,647.50 0.00
I PEKERJAAN PERSIAPAN 169,647.50 0.00
1 Direksi Keet, Pondok Kerja dan Gudang Bahan A.2.2.1.6 30.00 m2 25,447.13 763,413.75 169,647.50 4.50
2 Papan Nama Proyek Ls 1.00 ls - 169,647.50 0.00
3 Pembersihan Lapangan A.2.2.1.9 150.75 m2 - - 169,647.50 0.00
763,413.75 169,647.50 4.5
II PEKERJAAN PIPING 169,647.50 0.00
1 Pekerjaan galian tanah dalam 50 - 90 cm A.2.3.1.1 604.80 m³ - - 169,647.50 0.00
2 Pekerjaan pemasangan pipa SR PVC 3 inchi P1 2,000.00 m' - - 169,647.50 0.00
3 Pekerjaan pemasangan pipa Sub Line PVC 4 inchi P2 300.00 m' - - 169,647.50 0.00
4 Pekerjaan pemasangan pipa Sub Mainline PVC 6 inchi P3 700.00 m' - - 169,647.50 0.00
5 Pekerjaan pemasangan pipa Mainline PVC 8 inchi P4 110.00 m' - - 169,647.50 0.00
6 Pekerjaan pemasangan pipa Feeder PVC 10 inchi P5 250.00 m' - - 169,647.50 0.00
7 Pekerjaan urugan tanah kembali A.2.3.1.9 120.96 m³ - - 169,647.50 0.00
8 Restorasi halaman rumah warga LS 200.00 kk - 169,647.50 0.00
- 169,647.50 0
169,647.50 0.00
III PEKERJAAN BAK KONTROL 1 ( 60 x 60 cm ) 169,647.50 0.00
1 Galian Tanah A.2.3.1.1 15.23 m³ - - 169,647.50 0.00
2 Pekerjaan Bobok Beton Jalan A.2.2.1.13 3.26 m³ - - 169,647.50 0.00
3 Pek. Dinding Bak cor Beton bertulang, tebal : 10cm A.4.1.1.33.ab 0.34 m³ 44,447.65 15,112.20 169,647.50 0.09
4 Pek. Rabat Beton Lantai, tebal : 10cm A.4.1.1.5 13.43 m³ 4,750.13 63,794.25 169,647.50 0.38
5 Acian A.4.4.2.27 3.52 m² 1,696.48 5,971.59 169,647.50 0.04
6 Pasir urug 5cm A.2.3.1.11.b 0.54 m³ - - 169,647.50 0.00
7 Plat Dak Tutup bak cor beton bertulang, t : 10cm, wiremesh 1 layer M8-150 A.4.1.1.1 0.83 m³ 4,750.13 3,942.61 169,647.50 0.02
8 Elbow inlet + outlet( L-45°) PVC 6" LS 2.00 unit - - 169,647.50 0.00
9 Tutup manhole Cor Beton bertulang LS 17.00 bh - 169,647.50 0.00
88,820.65 169,647.50 0.52356
IV PEKERJAAN BAK KONTROL 2 ( 80 x 80 cm ) 169,647.50 0.00
1 Galian Tanah A.2.3.1.1 11.20 m³ - - 169,647.50 0.00
2 Pekerjaan Bobok lantai A.2.2.1.13 2.40 m³ - - 169,647.50 0.00
3 Pek. Dinding Bak cor Beton bertulang, tebal : 10cm A.4.1.1.33.ab 8.96 m³ 44,447.65 398,250.90 169,647.50 2.35
4 Pek. Lantai bak, tebal : 10cm A.4.1.1.5 9.44 m³ 4,750.13 44,841.23 169,647.50 0.26
5 Acian A.4.4.2.27 6.48 m² 1,696.48 10,993.16 169,647.50 0.06
6 Pasir urug 5cm A.2.3.1.11.b 7.08 m³ - - 169,647.50 0.00
7 Plat Dak Tutup bak cor beton bertulang, t : 10cm, wiremesh 1 layer M8-150 A.4.1.1.1 0.39 m³ 4,750.13 1,852.55 169,647.50 0.01
8 Elbow inlet + outlet( L-45°) PVC 6" LS 2.00 unit - - 169,647.50 0.00
9 Tutup manhole Cor Beton bertulang LS 8.00 bh - 169,647.50 0.00
455,937.84 169,647.50 2.68756
V PEKERJAAN BAK SUMPIT ( 1 unit ) 169,647.50 0.00
1 Pek. Bobok Beton Lantai Jalan, t : 30cm A.2.2.1.13 0.36 m³ - - 169,647.50 0.00
2 Galian Tanah A.2.3.1.1 2.42 m³ - - 169,647.50 0.00
3 Pek. Dinding Bak cor beton bertulang, t : 10cm, wiremesh 1 layer M8-150 A.4.1.1.33.ab 1.08 m³ 44,447.65 48,003.46 169,647.50 0.28
4 Pek. Rabat Benton Lantai, tebal : 15cm A.4.1.1.5 0.18 m³ 4,750.13 855.02 169,647.50 0.01
5 Acian A.4.4.2.27 4.84 m² 1,696.48 8,210.94 169,647.50 0.05
6 Lantai kerja, t : 5cm A.4.1.1.1 0.50 m³ 4,750.13 2,375.07 169,647.50 0.01
7 Plat Penutup Dak Beton Bertulang, t : 10cm A.4.1.1.37 0.08 m³ 29,292.69 2,343.42 169,647.50 0.01
8 Tutup plat besi ( manhole ) LS 1.00 set - 169,647.50 0.00
61,787.90 169,647.50 0.36421344
VI PEKERJAAN BAK EQUALISASI 169,647.50 0.00
1 Galian Tanah A.2.3.1.1 97.68 m³ - - 169,647.50 0.00
2 Urugan sirtu t = 15 cm A.2.3.1.14 4.09 m³ - - 169,647.50 0.00
3 Pasir urug t = 10 cm A.2.3.1.11.b 2.73 m³ - - 169,647.50 0.00
4 Lantai kerja t = 5 cm A.4.1.1.1 1.36 m³ 4,750.13 6,460.18 169,647.50 0.04
5 Lantai bak cor beton bertulang A.4.1.1.37 5.45 m³ 29,292.69 159,645.19 169,647.50 0.94
6 Dinding beton bertulang A.4.1.1.33.a 17.68 m³ 44,447.65 785,834.36 169,647.50 4.63
7 Balok beton 15/20cm A.4.1.1.31.a 0.62 m³ 56,492.62 35,025.42 169,647.50 0.21
8 Acian A.4.4.2.27 1.00 m² 1,696.48 1,696.48 169,647.50 0.01
9 Tutup plat baja rangka siku L.50.50.5 LS 2.00 set - 169,647.50 0.00
988,661.62 169,647.50 5.8277406
VII PEKERJAAN DUDUKAN BIOREACTOR ( 1 UNIT ) 169,647.50 0.00
1 Galian Tanah A.2.3.1.1 64.40 m³ - - 169,647.50 0.00
2 Pasir Urug A.2.3.1.11.b 1.01 m³ - - 169,647.50 0.00
3 Urugan Kembali A.2.3.1.9 55.78 m³ - - 169,647.50 0.00
6 Beton Pondasi K350 A.4.1.1.37B 8.62 m³ 28,995.81 249,943.89 169,647.50 1.47
7 Baut Angkur M16 c 56.00 bh - - 169,647.50 0.00
8 Base Plat 10mm f 1,758.40 kg - - 169,647.50 0.00
9 Pengecatan Base Plat A.4.4.2.3 4.48 m² 1,068.78 4,788.13 169,647.50 0.03
10 Plesteran Pondasi A.4.4.2.4 31.64 m² 2,544.71 80,514.70 169,647.50 0.47
11 Acian Pondasi A.4.4.2.27 82.48 m² 1,696.48 139,925.26 169,647.50 0.82
475,171.99 169,647.50 2.80093716
VIII PEKERJAAN BAK GREASE TRAP 169,647.50 0.00
1 Pek. Bobok Beton Lantai Jalan, t :30cm A.2.2.1.13 28.07 m³ - - 169,647.50 0.00
2 Galian Tanah A.2.3.1.1 277.20 m³ - - 169,647.50 0.00
3 Pek. Dinding Bak beton bertulang, t : 10cm, wiremesh 1 layer M8-150 A.4.1.1.33.ab 43.38 m³ 44,447.65 1,928,138.84 169,647.50 11.37
4 Pek. Rabat Benton Lantai, tebal : 15cm A.4.1.1.5 12.47 m³ 4,750.13 59,234.12 169,647.50 0.35
5 Acian A.4.4.2.27 485.73 m³ 1,696.48 824,028.80 169,647.50 4.86
6 Pasir urug 10 cm A.2.3.1.11.b 9.36 m³ - - 169,647.50 0.00
7 Lantai kerja, t : 5cm A.4.1.1.1 4.68 m² 4,750.13 22,230.61 169,647.50 0.13
8 Plat Penutup Dak Beton Bertulang, t : 10cm A.4.1.1.37 8.12 m¹ 29,292.69 237,856.68 169,647.50 1.40
9 Elbow (L) PVC 4" - 126.00 bh - - 169,647.50 0.00
10 Reduser Shock PVC 4" - 6" - 63.00 bh - - 169,647.50 0.00
11 Elbow ( T ) PVC 6" - 63.00 bh - - 169,647.50 0.00
12 Tutup plat besi ( manhole ) - 126.00 set - 169,647.50 0.00
3,071,489.05 169,647.50 18.10512416
IX PEKERJAAN FISH POND DAN BAK CHLORINASI 169,647.50 0.00
1 Galian Tanah A.2.3.1.1 2.87 m³ - - 169,647.50 0.00
2 urug pasir bawah lantai beton A.2.3.1.11.b 0.23 m² - - 169,647.50 0.00
3 Kolom Praktis A.4.1.1.35 0.50 m³ 1,017.89 508.94 169,647.50 0.00
4 Pas. Bata, camp 1 : 4 A.4.4.1.8 14.16 m² 1,696.48 24,022.09 169,647.50 0.14
5 Plesteran A.4.4.2.4 28.18 m² 2,544.71 71,710.00 169,647.50 0.42
6 Acian A.4.4.2.27 32.42 m² 1,696.48 54,999.72 169,647.50 0.32
7 Lantai Bak cor beton camp. K.175 A.4.1.1.5 0.71 m³ 4,750.13 3,372.59 169,647.50 0.02
154,613.34 169,647.50 0.91138
X PEK. TAMAN, PAGAR DAN CANOPY 169,647.50 0.00
1 PEKERJAAN TAMAN 169,647.50 0.00
Pemupukan tanah LS 110.25 m² - 169,647.50 0.00
Bunga Sabrina LS 30.00 bh - 169,647.50 0.00
Pucuk merah LS 20.00 bh - 169,647.50 0.00
Begonia cokelat LS 50.00 bh - 169,647.50 0.00
Tanaman calathea ctenanthe LS 10.00 bh - 169,647.50 0.00
Brokoli hias LS 30.00 bh - 169,647.50 0.00
Lampu taman LS 6.00 bh - 169,647.50 0.00
Name tag (Huruf timbul) IPAL LS 1.00 bh - 169,647.50 0.00
2 Pekerjaan pagar besi keliling IPAL LS 105.00 m¹ - 169,647.50 0.00
3 Pekerjaan atap kanopi LS 162.00 m² - 169,647.50 0.00
4 Sloof & Ring Balk uk.15x15 A.4.1.1.36 105.00 m¹ 1,696.48 178,129.88 169,647.50 1.05
5 Kolom Pagar uk.30x30 A.4.1.1.35 52.50 m¹ 1,017.89 53,438.96 169,647.50 0.32
6 Pekerjaan Balok Pagar A.4.1.1.36 105.00 m¹ 1,696.48 178,129.88 169,647.50 1.05
7 Pekerjaan Pas. Dinding Pagar 1/2 Bata, camp. 1:4 A.4.4.1.8 31.50 m² 1,696.48 53,438.96 169,647.50 0.32
8 Plesteran A.4.4.2.4 105.00 m² 2,544.71 267,194.81 169,647.50 1.58
9 Acian A.4.4.2.27 105.00 m² 1,696.48 178,129.88 169,647.50 1.05
10 Pengecatan Pagar Besi A.4.4.2.3 105.00 m¹ 1,068.78 112,221.82 169,647.50 0.66
1,020,684.18 169,647.50 6.0165
XI PEKERJAAN RUMAH JAGA 169,647.50 0.00
1 Pekerjaan Pondasi 169,647.50 0.00
a Galian Tanah Pondasi A.2.3.1.1 8.03 m³ - - 169,647.50 0.00
b Pondasi Batu Belah 1:4 A.2.2.1.4x 2.81 m³ 12,723.56 35,753.21 169,647.50 0.21
c Urugan Kembali Galian Pondasi A.2.3.1.9 4.75 m³ - - 169,647.50 0.00
2 Pekerjaan Sloof 20x15 A.4.1.1.29.a 0.46 m³ 54,796.14 25,206.23 169,647.50 0.15
3 Lantai kerja K100 A.4.1.1.1 0.37 m³ 4,750.13 1,757.55 169,647.50 0.01
4 Pekerjaan Kolom 15x15 A.4.1.1.35.a 0.28 m³ 68,367.94 19,143.02 169,647.50 0.11
5 Pekerjaan Balok 15x15 A.4.1.1.31.a 0.35 m³ 56,492.62 19,772.42 169,647.50 0.12
6 Pekerjaan Dinding 0.00 - 169,647.50 0.00
a Pasangan 1/2 Bata A.4.4.1.8 34.85 m² 1,696.48 59,122.15 169,647.50 0.35
b Plesteran A.4.4.2.4 69.70 m² 2,544.71 177,366.46 169,647.50 1.05
c Acian A.4.4.2.27 69.70 m² 1,696.48 118,244.31 169,647.50 0.70
6 Pekerjaan Keramik A.4.4.3.35 11.26 m² 5,937.66 66,858.08 169,647.50 0.39
7 Pekerjaan Pintu Ls 1.00 unit - 169,647.50 0.00
8 Pekerjaan Jendela Ls 4.00 unit - 169,647.50 0.00
9 Pekerjaan Atap 0.00 169,647.50 0.00
a Rangka Baja Ringan Ls 33.06 m² - 169,647.50 0.00
b Atap Zincalume A.4.5.1.7 33.06 m² 1,696.48 56,085.46 169,647.50 0.33
c Listplank A.4.5.2.38b 5.85 m² 3,392.95 19,848.76 169,647.50 0.12
d Profil Etnis Betawi Ls 23.40 m' - - 169,647.50 0.00
11 Pengecatan Dinding A.4.7.1.10 69.70 m² 1,068.78 74,493.91 169,647.50 0.44
673,651.56 169,647.50 3.97089
169,647.50 0.00
TOTAL PEKERJAAN SIPIL 7,754,231.87 169,647.50
XII MESIN PENGOLAHAN AIR LIMBAH 169,647.50 0.00
Capacity : 100 m3/day 169,647.50 0.00
Biomembrane Reactor 1.00 set - 169,647.50 0.00
Submersible inlet pump 2.00 unit - 169,647.50 0.00
Circulation pump 1.00 unit - 169,647.50 0.00
Air injection 2.00 unit - 169,647.50 0.00
Screen 1.00 unit - 169,647.50 0.00
Turbidity pretreatment 1.00 unit - 169,647.50 0.00
Chlorinator 1.00 unit - 169,647.50 0.00
Water flow meter 2.00 unit - 169,647.50 0.00
Panel control 1.00 unit - 169,647.50 0.00
169,647.50 0.00
169,647.50 0.00
TOTAL PEKERJAAN MESIN - 169,647.50 0.00
XIII TESTING & COMISSIONING 169,647.50 0.00
1 Installation 1.00 ls - 169,647.50 0.00
2 Sambung baru PLN, Bio-Reaktor IPAL ( 22 KVA, 3 phase ) 1.00 ls - 169,647.50 0.00
3 Sambung baru PLN, Pompa sampit ( 2,200 watt, 1 phase ) 1.00 ttk - 169,647.50 0.00
4 Testing & Comissioning 1.00 ls - 169,647.50 0.00
5 Training Operator 1.00 bln - 169,647.50 0.00
TOTAL TESTING & COMISSIONING - 169,647.50 0.00
JUMLAH TOTAL PEMBANGUNAN SPALD KOJA 7,754,231.87 169,647.50
B Pembangunan SPALD Kelurahan lagoa 169,647.50 0.00
I PEKERJAAN PERSIAPAN 169,647.50 0.00
1 Direksi Keet, Pondok Kerja dan Gudang Bahan A.2.2.1.6 30.00 m2 25,447.13 763,413.75 169,647.50 4.50
2 Papan Nama Proyek Ls 1.00 ls - 169,647.50 0.00
3 Pembersihan Lapangan A.2.2.1.9 150.75 m2 - - 169,647.50 0.00
763,413.75 169,647.50 4.5
II PEKERJAAN PIPING 169,647.50 0.00
1 Pekerjaan galian tanah dalam 50 - 90 cm A.2.3.1.1 1,073.28 m³ - - 169,647.50 0.00
2 Pekerjaan pemasangan pipa SR PVC 3 inchi P1 2,000.00 m' - - 169,647.50 0.00
3 Pekerjaan pemasangan pipa Sub Line PVC 4 inchi P2 879.00 m' - - 169,647.50 0.00
4 Pekerjaan pemasangan pipa Sub Mainline PVC 6 inchi P3 475.00 m' - - 169,647.50 0.00
5 Pekerjaan pemasangan pipa Mainline PVC 8 inchi P4 146.00 m' - - 169,647.50 0.00
6 Pekerjaan pemasangan pipa Feeder PVC 10 inchi P5 117.00 m' - - 169,647.50 0.00
7 Pekerjaan urugan tanah kembali A.2.3.1.9 662.42 m³ - - 169,647.50 0.00
8 Restorasi halaman rumah warga LS 200.00 kk - 169,647.50 0.00
- 169,647.50 0
169,647.50 0.00
III PEKERJAAN BAK KONTROL 1 ( 60 x 60 cm ) 169,647.50 0.00
1 Galian Tanah A.2.3.1.1 23.30 m³ - - 169,647.50 0.00
2 Pekerjaan Bobok Beton Jalan A.2.2.1.13 4.99 m³ - - 169,647.50 0.00
3 Pek. Dinding Bak cor Beton bertulang, tebal : 10cm A.4.1.1.33.ab 0.34 m³ 44,447.65 15,112.20 169,647.50 0.09
4 Pek. Rabat Beton Lantai, tebal : 10cm A.4.1.1.5 20.54 m³ 4,750.13 97,567.67 169,647.50 0.58
5 Acian A.4.4.2.27 3.52 m² 1,696.48 5,971.59 169,647.50 0.04
6 Pasir urug 5cm A.2.3.1.11.b 0.83 m³ - - 169,647.50 0.00
7 Plat Dak Tutup bak cor beton bertulang, t : 10cm, wiremesh 1 layer M8-150 A.4.1.1.1 1.27 m³ 4,750.13 6,032.67 169,647.50 0.04
8 Elbow inlet + outlet( L-45°) PVC 6" LS 52.00 unit - - 169,647.50 0.00
9 Tutup manhole Cor Beton bertulang LS 26.00 bh - 169,647.50 0.00
124,684.13 169,647.50 0.73496
IV PEKERJAAN BAK KONTROL 2 ( 80 x 80 cm ) 169,647.50 0.00
1 Galian Tanah A.2.3.1.1 5.60 m³ - - 169,647.50 0.00
2 Pekerjaan Bobok lantai A.2.2.1.13 1.20 m³ - - 169,647.50 0.00
3 Pek. Dinding Bak cor Beton bertulang, tebal : 10cm A.4.1.1.33.ab 4.48 m³ 44,447.65 199,125.45 169,647.50 1.17
4 Pek. Lantai bak, tebal : 10cm A.4.1.1.5 4.72 m³ 4,750.13 22,420.61 169,647.50 0.13
5 Acian A.4.4.2.27 3.24 m² 1,696.48 5,496.58 169,647.50 0.03
6 Pasir urug 5cm A.2.3.1.11.b 3.54 m³ - - 169,647.50 0.00
7 Plat Dak Tutup bak cor beton bertulang, t : 10cm, wiremesh 1 layer M8-150 A.4.1.1.1 0.20 m³ 4,750.13 950.03 169,647.50 0.01
8 Elbow inlet + outlet( L-45°) PVC 6" LS 8.00 unit - - 169,647.50 0.00
9 Tutup manhole Cor Beton bertulang LS 4.00 bh - 169,647.50 0.00
227,992.67 169,647.50 1.34392
V PEKERJAAN BAK SUMPIT ( 3 unit ) 169,647.50 0.00
1 Pek. Bobok Beton Lantai Jalan, t : 30cm A.2.2.1.13 1.09 m³ - - 169,647.50 0.00
2 Galian Tanah A.2.3.1.1 7.26 m³ - - 169,647.50 0.00
3 Pek. Dinding Bak cor beton bertulang, t : 10cm, wiremesh 1 layer M8-150 A.4.1.1.33.ab 3.25 m³ 44,447.65 144,454.85 169,647.50 0.85
4 Pek. Rabat Benton Lantai, tebal : 15cm A.4.1.1.5 0.54 m³ 4,750.13 2,565.07 169,647.50 0.02
5 Acian A.4.4.2.27 14.52 m² 1,696.48 24,632.82 169,647.50 0.15
6 Lantai kerja, t : 5cm A.4.1.1.1 1.50 m³ 4,750.13 7,125.20 169,647.50 0.04
7 Plat Penutup Dak Beton Bertulang, t : 10cm A.4.1.1.37 0.08 m³ 29,292.69 2,343.42 169,647.50 0.01
8 Tutup plat besi ( manhole ) LS 3.00 set - 169,647.50 0.00
181,121.34 169,647.50 1.06763344
VI PEKERJAAN BAK EQUALISASI 169,647.50 0.00
1 Galian Tanah A.2.3.1.1 97.68 m³ - - 169,647.50 0.00
2 Urugan sirtu t = 15 cm A.2.3.1.14 4.09 m³ - - 169,647.50 0.00
3 Pasir urug t = 10 cm A.2.3.1.11.b 2.73 m³ - - 169,647.50 0.00
4 Lantai kerja t = 5 cm A.4.1.1.1 1.36 m³ 4,750.13 6,460.18 169,647.50 0.04
5 Lantai bak cor beton bertulang A.4.1.1.37 5.45 m³ 29,292.69 159,645.19 169,647.50 0.94
6 Dinding beton bertulang A.4.1.1.33.a 17.68 m³ 44,447.65 785,834.36 169,647.50 4.63
7 Balok beton 15/20cm A.4.1.1.31.a 0.62 m³ 56,492.62 35,025.42 169,647.50 0.21
8 Acian A.4.4.2.27 1.00 m² 1,696.48 1,696.48 169,647.50 0.01
9 Tutup plat baja rangka siku L.50.50.5 LS 2.00 unit - 169,647.50 0.00
988,661.62 169,647.50 5.8277406
VII PEKERJAAN DUDUKAN BIOREACTOR ( 1 UNIT ) 169,647.50 0.00
1 Galian Tanah A.2.3.1.1 64.40 m³ - - 169,647.50 0.00
2 Pasir Urug A.2.3.1.11.b 1.01 m³ - - 169,647.50 0.00
3 Urugan Kembali A.2.3.1.9 55.78 m³ - - 169,647.50 0.00
4 Beton Pondasi K350 A.4.1.1.37B 8.62 m³ 28,995.81 249,943.89 169,647.50 1.47
5 Baut Angkur c 56.00 m³ - - 169,647.50 0.00
6 Base Plat 10mm f 1,758.40 m³ - - 169,647.50 0.00
7 Pengecatan Base Plat A.4.4.2.3 4.48 m² 1,068.78 4,788.13 169,647.50 0.03
8 Plesteran Pondasi A.4.4.2.4 31.64 m² 2,544.71 80,514.70 169,647.50 0.47
9 Acian Pondasi A.4.4.2.27 82.48 m³ 1,696.48 139,925.26 169,647.50 0.82
475,171.99 169,647.50 2.80093716
VIII PEKERJAAN BAK GRASE TRAP 169,647.50 0.00
1 Pek. Bobok Beton Lantai Jalan, t :30cm A.2.2.1.13 30.74 m3 - - 169,647.50 0.00
2 Galian Tanah A.2.3.1.1 303.60 m3 - - 169,647.50 0.00
3 Pek. Dinding Bak cor beton bertulang, wiremess M8-150, t : 10cm A.4.1.1.33.ab 47.51 m3 44,447.65 2,111,707.61 169,647.50 12.45
4 Pek. Rabat Benton Lantai tanpa tulang, tebal : 15cm A.4.1.1.5 13.66 m2 4,750.13 64,886.78 169,647.50 0.38
5 Acian A.4.4.2.27 531.99 m2 1,696.48 902,507.74 169,647.50 5.32
6 Pasir urug 10 cm A.2.3.1.11.b 10.25 m3 - - 169,647.50 0.00
7 Lantai kerja, t : 5cm A.4.1.1.1 5.12 m3 4,750.13 24,320.67 169,647.50 0.14
8 Plat Penutup Dak Beton Bertulang, t : 10cm A.4.1.1.37 8.89 bh 29,292.69 260,412.05 169,647.50 1.54
9 Elbow (L) PVC 4" - 138.00 bh - - 169,647.50 0.00
10 Reduser Shock PVC 4" - 6" - 69.00 bh - - 169,647.50 0.00
11 Elbow ( T ) PVC 6" - 69.00 bh - - 169,647.50 0.00
12 Tutup manhole plat beton bertulang - 138.00 pcs - 169,647.50 0.00
3,363,834.84 169,647.50 19.82837852
IX PEKERJAAN FISH POND DAN BAK CHLORINASI 169,647.50 0.00
1 Galian Tanah A.2.3.1.1 2.87 m³ - - 169,647.50 0.00
2 urug pasir bawah lantai beton A.2.3.1.11.b 0.23 m² - - 169,647.50 0.00
3 Kolom Praktis A.4.1.1.35 0.50 m³ 1,017.89 508.94 169,647.50 0.00
4 Pas. Bata, camp 1 : 4 A.4.4.1.8 14.16 m² 1,696.48 24,022.09 169,647.50 0.14
5 Plesteran A.4.4.2.4 28.18 m² 2,544.71 71,710.00 169,647.50 0.42
6 Acian A.4.4.2.27 32.42 m² 1,696.48 54,999.72 169,647.50 0.32
7 Lantai Bak cor beton camp. K.175 A.4.1.1.5 0.71 m³ 4,750.13 3,372.59 169,647.50 0.02
154,613.34 169,647.50 0.91138
X PEK. TAMAN, PAGAR DAN CANOPY 169,647.50 0.00
1 PEKERJAAN TAMAN 169,647.50 0.00
Pemupukan tanah LS 110.25 m² - 169,647.50 0.00
Bunga Sabrina LS 30.00 bh - 169,647.50 0.00
Pucuk merah LS 20.00 bh - 169,647.50 0.00
Begonia cokelat LS 50.00 bh - 169,647.50 0.00
Tanaman calathea ctenanthe LS 10.00 bh - 169,647.50 0.00
Brokoli hias LS 30.00 bh - 169,647.50 0.00
Lampu taman LS 6.00 bh - 169,647.50 0.00
Name tag (Huruf timbul) IPAL LS 1.00 bh - 169,647.50 0.00
2 Pekerjaan pagar besi keliling IPAL LS 105.00 m¹ - 169,647.50 0.00
3 Pekerjaan atap kanopi LS 162.00 m² - 169,647.50 0.00
4 Sloof & Ring Balk uk.15x15 A.4.1.1.36 105.00 m¹ 1,696.48 178,129.88 169,647.50 1.05
5 Kolom Pagar uk.30x30 A.4.1.1.35 52.50 m¹ 1,017.89 53,438.96 169,647.50 0.32
6 Pekerjaan Balok Pagar A.4.1.1.36 105.00 m¹ 1,696.48 178,129.88 169,647.50 1.05
7 Pekerjaan Pas. Dinding Pagar 1/2 Bata, camp. 1:4 A.4.4.1.8 31.50 1,696.48 53,438.96 169,647.50 0.32
8 Plesteran A.4.4.2.4 105.00 m² 2,544.71 267,194.81 169,647.50 1.58
9 Acian A.4.4.2.27 105.00 m² 1,696.48 178,129.88 169,647.50 1.05
10 Pengecatan Pagar Besi A.4.4.2.3 105.00 m¹ 1,068.78 112,221.82 169,647.50 0.66
1,020,684.18 169,647.50 6.0165
XI PEKERJAAN RUMAH JAGA 169,647.50 0.00
1 Pekerjaan Pondasi 169,647.50 0.00
a Galian Tanah Pondasi A.2.3.1.1 8.03 m³ - - 169,647.50 0.00
b Pondasi Batu Belah 1:4 A.2.2.1.4x 2.81 m³ 12,723.56 35,753.21 169,647.50 0.21
c Urugan Kembali Galian Pondasi A.2.3.1.9 4.75 m³ - - 169,647.50 0.00
2 Pekerjaan Sloof 20x15 A.4.1.1.29.a 0.46 m³ 54,796.14 25,206.23 169,647.50 0.15
3 Lantai kerja K100 A.4.1.1.1 0.37 m³ 4,750.13 1,757.55 169,647.50 0.01
4 Pekerjaan Kolom 15x15 A.4.1.1.35.a 0.28 m³ 68,367.94 19,143.02 169,647.50 0.11
5 Pekerjaan Balok 15x15 A.4.1.1.31.a 0.35 m³ 56,492.62 19,772.42 169,647.50 0.12
6 Pekerjaan Dinding 169,647.50 0.00
a Pasangan 1/2 Bata A.4.4.1.8 34.85 m² 1,696.48 59,122.15 169,647.50 0.35
b Plesteran A.4.4.2.4 69.70 m² 2,544.71 177,366.46 169,647.50 1.05
c Acian A.4.4.2.27 69.70 m² 1,696.48 118,244.31 169,647.50 0.70
6 Pekerjaan Keramik A.4.4.3.35 11.26 m² 5,937.66 66,858.08 169,647.50 0.39
7 Pekerjaan Pintu Ls 1.00 unit - 169,647.50 0.00
8 Pekerjaan Jendela Ls 4.00 unit - 169,647.50 0.00
9 Pekerjaan Atap 169,647.50 0.00
a Rangka Baja Ringan Ls 33.06 m² - 169,647.50 0.00
b Atap Zincalume A.4.5.1.7 33.06 m² 1,696.48 56,085.46 169,647.50 0.33
c Listplank A.4.5.2.38b 5.85 m² 3,392.95 19,848.76 169,647.50 0.12
d Profil Etnis Betawi Ls 23.40 m' - 169,647.50 0.00
11 Pengecatan Dinding A.4.7.1.10 69.70 m² 1,068.78 74,493.91 169,647.50 0.44
673,651.56 169,647.50 3.97089
TOTAL PEKERJAAN SIPIL 7,973,829.43 169,647.50
XII MESIN PENGOLAHAN AIR LIMBAH 169,647.50 0.00
Capacity : 100 m3/day 169,647.50 0.00
Biomembrane Reactor 1.00 set - 169,647.50 0.00
Submersible inlet pump 2.00 unit - 169,647.50 0.00
Circulation pump 1.00 unit - 169,647.50 0.00
Air injection 2.00 unit - 169,647.50 0.00
Screen 1.00 unit - 169,647.50 0.00
Turbidity pretreatment 1.00 unit - 169,647.50 0.00
Chlorinator 1.00 unit - 169,647.50 0.00
Water flow meter 2.00 unit - 169,647.50 0.00
Panel control 1.00 unit - 169,647.50 0.00
169,647.50 0.00
169,647.50 0.00
TOTAL PEKERJAAN MESIN - 169,647.50 0.00
XIII INSTALLATION, TESTING & COMISSIONING 169,647.50 0.00
1 Installation 1.00 ls - 169,647.50 0.00
2 Sambung baru PLN, Bio-Reaktor IPAL ( 22 KVA, 3 phase ) 1.00 ls - 169,647.50 0.00
3 Sambung baru PLN, Pompa sampit ( 2,200 watt, 1 phase ) 3.00 ttk - 169,647.50 0.00
4 Testing & Comissioning 1.00 ls - 169,647.50 0.00
5 Training Operator 1.00 bln - 169,647.50 0.00
TOTAL TESTING & COMISSIONING - 169,647.50 0.00
JUMLAH TOTAL PEMBANGUNAN SPALD LAGOA 7,973,829.43 92.71 92.71
KOREKSI
15,728,061.30
15,728,061.30
HARGA JUMLAH
NO URAIAN PEKERJAAN ANALISA VOLUME SAT SATUAN HARGA GAJI OH TOT. OH
( Rp ) ( Rp )
A Pembangunan SPALD Kelurahan Koja 182,085.00 0.00
I PEKERJAAN PERSIAPAN 182,085.00 0.00
1 Direksi Keet, Pondok Kerja dan Gudang Bahan A.2.2.1.6 30.00 m2 9,104.25 273,127.50 182,085.00 1.50
2 Papan Nama Proyek Ls 1.00 ls - 182,085.00 0.00
3 Pembersihan Lapangan A.2.2.1.9 150.75 m2 9,104.25 1,372,465.69 182,085.00 7.54
1,645,593.19 182,085.00 9.0375
II PEKERJAAN PIPING 182,085.00 0.00
1 Pekerjaan galian tanah dalam 50 - 90 cm A.2.3.1.1 604.80 m³ 4,552.13 2,753,125.20 182,085.00 15.12
2 Pekerjaan pemasangan pipa SR PVC 3 inchi P1 2,000.00 m' - - 182,085.00 0.00
3 Pekerjaan pemasangan pipa Sub Line PVC 4 inchi P2 300.00 m' 1,638.77 491,629.50 182,085.00 2.70
4 Pekerjaan pemasangan pipa Sub Mainline PVC 6 inchi P3 700.00 m' 2,185.02 1,529,514.00 182,085.00 8.40
5 Pekerjaan pemasangan pipa Mainline PVC 8 inchi P4 110.00 m' 3,459.62 380,557.65 182,085.00 2.09
6 Pekerjaan pemasangan pipa Feeder PVC 10 inchi P5 250.00 m' 4,734.21 1,183,552.50 182,085.00 6.50
7 Pekerjaan urugan tanah kembali A.2.3.1.9 120.96 m³ 9,104.25 1,101,250.08 182,085.00 6.05
8 Restorasi halaman rumah warga LS 200.00 kk - 182,085.00 0.00
7,439,628.93 182,085.00 40.858
182,085.00 0.00
III PEKERJAAN BAK KONTROL 1 ( 60 x 60 cm ) 182,085.00 0.00
1 Galian Tanah A.2.3.1.1 15.23 m³ 4,552.13 69,328.86 182,085.00 0.38
2 Pekerjaan Bobok Beton Jalan A.2.2.1.13 3.26 m³ 121,268.61 395,335.67 182,085.00 2.17
3 Pek. Dinding Bak cor Beton bertulang, tebal : 10cm A.4.1.1.33.ab 0.34 m³ 48,252.53 16,405.86 182,085.00 0.09
4 Pek. Rabat Beton Lantai, tebal : 10cm A.4.1.1.5 13.43 m³ 15,113.06 202,968.33 182,085.00 1.11
5 Acian A.4.4.2.27 3.52 m² 1,820.85 6,409.39 182,085.00 0.04
6 Pasir urug 5cm A.2.3.1.11.b 0.54 m³ 1,820.85 983.26 182,085.00 0.01
7 Plat Dak Tutup bak cor beton bertulang, t : 10cm, wiremesh 1 layer M8-150 A.4.1.1.1 0.83 m³ 15,113.06 12,543.84 182,085.00 0.07
8 Elbow inlet + outlet( L-45°) PVC 6" LS 2.00 unit - - 182,085.00 0.00
9 Tutup manhole Cor Beton bertulang LS 17.00 bh - 182,085.00 0.00
703,975.21 182,085.00 3.86619
IV PEKERJAAN BAK KONTROL 2 ( 80 x 80 cm ) 182,085.00 0.00
1 Galian Tanah A.2.3.1.1 11.20 m³ 4,552.13 50,983.80 182,085.00 0.28
2 Pekerjaan Bobok lantai A.2.2.1.13 2.40 m³ 121,268.61 291,044.66 182,085.00 1.60
3 Pek. Dinding Bak cor Beton bertulang, tebal : 10cm A.4.1.1.33.ab 8.96 m³ 48,252.53 432,342.62 182,085.00 2.37
4 Pek. Lantai bak, tebal : 10cm A.4.1.1.5 9.44 m³ 15,113.06 142,667.24 182,085.00 0.78
5 Acian A.4.4.2.27 6.48 m² 1,820.85 11,799.11 182,085.00 0.06
6 Pasir urug 5cm A.2.3.1.11.b 7.08 m³ 1,820.85 12,891.62 182,085.00 0.07
7 Plat Dak Tutup bak cor beton bertulang, t : 10cm, wiremesh 1 layer M8-150 A.4.1.1.1 0.39 m³ 15,113.06 5,894.09 182,085.00 0.03
8 Elbow inlet + outlet( L-45°) PVC 6" LS 2.00 unit - - 182,085.00 0.00
9 Tutup manhole Cor Beton bertulang LS 8.00 bh - 182,085.00 0.00
947,623.14 182,085.00 5.20429
V PEKERJAAN BAK SUMPIT ( 1 unit ) 182,085.00 0.00
1 Pek. Bobok Beton Lantai Jalan, t : 30cm A.2.2.1.13 0.36 m³ 121,268.61 43,656.70 182,085.00 0.24
2 Galian Tanah A.2.3.1.1 2.42 m³ 4,552.13 11,016.14 182,085.00 0.06
3 Pek. Dinding Bak cor beton bertulang, t : 10cm, wiremesh 1 layer M8-150 A.4.1.1.33.ab 1.08 m³ 48,252.53 52,112.73 182,085.00 0.29
4 Pek. Rabat Benton Lantai, tebal : 15cm A.4.1.1.5 0.18 m³ 15,113.06 2,720.35 182,085.00 0.01
5 Acian A.4.4.2.27 4.84 m² 1,820.85 8,812.91 182,085.00 0.05
6 Lantai kerja, t : 5cm A.4.1.1.1 0.50 m³ 15,113.06 7,556.53 182,085.00 0.04
7 Plat Penutup Dak Beton Bertulang, t : 10cm A.4.1.1.37 0.08 m³ 33,384.56 2,670.76 182,085.00 0.01
8 Tutup plat besi ( manhole ) LS 1.00 set - 182,085.00 0.00
128,546.13 182,085.00 0.70596768
VI PEKERJAAN BAK EQUALISASI 182,085.00 0.00
1 Galian Tanah A.2.3.1.1 97.68 m³ 4,552.13 444,651.57 182,085.00 2.44
2 Urugan sirtu t = 15 cm A.2.3.1.14 4.09 m³ 4,552.13 18,618.19 182,085.00 0.10
3 Pasir urug t = 10 cm A.2.3.1.11.b 2.73 m³ 1,820.85 4,970.92 182,085.00 0.03
4 Lantai kerja t = 5 cm A.4.1.1.1 1.36 m³ 15,113.06 20,553.75 182,085.00 0.11
5 Lantai bak cor beton bertulang A.4.1.1.37 5.45 m³ 33,384.56 181,945.83 182,085.00 1.00
6 Dinding beton bertulang A.4.1.1.33.a 17.68 m³ 48,252.53 853,104.64 182,085.00 4.69
7 Balok beton 15/20cm A.4.1.1.31.a 0.62 m³ 57,903.03 35,899.88 182,085.00 0.20
8 Acian A.4.4.2.27 1.00 m² 1,820.85 1,820.85 182,085.00 0.01
9 Tutup plat baja rangka siku L.50.50.5 LS 2.00 set - 182,085.00 0.00
1,561,565.64 182,085.00 8.5760257
VII PEKERJAAN DUDUKAN BIOREACTOR ( 1 UNIT ) 182,085.00 0.00
1 Galian Tanah A.2.3.1.1 64.40 m³ 4,552.13 293,156.85 182,085.00 1.61
2 Pasir Urug A.2.3.1.11.b 1.01 m³ 1,820.85 1,839.06 182,085.00 0.01
3 Urugan Kembali A.2.3.1.9 55.78 m³ 9,104.25 507,835.07 182,085.00 2.79
6 Beton Pondasi K350 A.4.1.1.37B 8.62 m³ 35,797.18 308,571.71 182,085.00 1.69
7 Baut Angkur M16 c 56.00 bh - - 182,085.00 0.00
8 Base Plat 10mm f 1,758.40 kg - - 182,085.00 0.00
9 Pengecatan Base Plat A.4.4.2.3 4.48 m² 546.26 2,447.22 182,085.00 0.01
10 Plesteran Pondasi A.4.4.2.4 31.64 m² 2,731.28 86,417.54 182,085.00 0.47
11 Acian Pondasi A.4.4.2.27 82.48 m² 1,820.85 150,183.71 182,085.00 0.82
1,350,451.16 182,085.00 7.41659752
VIII PEKERJAAN BAK GREASE TRAP 182,085.00 0.00
1 Pek. Bobok Beton Lantai Jalan, t :30cm A.2.2.1.13 28.07 m³ 121,268.61 3,404,009.88 182,085.00 18.69
2 Galian Tanah A.2.3.1.1 277.20 m³ 4,552.13 1,261,849.05 182,085.00 6.93
3 Pek. Dinding Bak beton bertulang, t : 10cm, wiremesh 1 layer M8-150 A.4.1.1.33.ab 43.38 m³ 48,252.53 2,093,194.53 182,085.00 11.50
4 Pek. Rabat Benton Lantai, tebal : 15cm A.4.1.1.5 12.47 m³ 15,113.06 188,459.80 182,085.00 1.04
5 Acian A.4.4.2.27 485.73 m³ 1,820.85 884,441.47 182,085.00 4.86
6 Pasir urug 10 cm A.2.3.1.11.b 9.36 m³ 1,820.85 17,043.16 182,085.00 0.09
7 Lantai kerja, t : 5cm A.4.1.1.1 4.68 m² 15,113.06 70,729.10 182,085.00 0.39
8 Plat Penutup Dak Beton Bertulang, t : 10cm A.4.1.1.37 8.12 m¹ 33,384.56 271,082.60 182,085.00 1.49
9 Elbow (L) PVC 4" - 126.00 bh 573.57 72,269.54 182,085.00 0.40
10 Reduser Shock PVC 4" - 6" - 63.00 bh 655.51 41,296.88 182,085.00 0.23
11 Elbow ( T ) PVC 6" - 63.00 bh 655.51 41,296.88 182,085.00 0.23
12 Tutup plat besi ( manhole ) - 126.00 set - 182,085.00 0.00
8,345,672.88 182,085.00 45.83393952
IX PEKERJAAN FISH POND DAN BAK CHLORINASI 182,085.00 0.00
1 Galian Tanah A.2.3.1.1 2.87 m³ 4,552.13 13,064.60 182,085.00 0.07
2 urug pasir bawah lantai beton A.2.3.1.11.b 0.23 m² 1,820.85 418.80 182,085.00 0.00
3 Kolom Praktis A.4.1.1.35 0.50 m³ 1,638.77 819.38 182,085.00 0.00
4 Pas. Bata, camp 1 : 4 A.4.4.1.8 14.16 m² 2,731.28 38,674.85 182,085.00 0.21
5 Plesteran A.4.4.2.4 28.18 m² 2,731.28 76,967.33 182,085.00 0.42
6 Acian A.4.4.2.27 32.42 m² 1,820.85 59,031.96 182,085.00 0.32
7 Lantai Bak cor beton camp. K.175 A.4.1.1.5 0.71 m³ 15,113.06 10,730.27 182,085.00 0.06
199,707.19 182,085.00 1.09678
X PEK. TAMAN, PAGAR DAN CANOPY 182,085.00 0.00
1 PEKERJAAN TAMAN 182,085.00 0.00
Pemupukan tanah LS 110.25 m² - 182,085.00 0.00
Bunga Sabrina LS 30.00 bh - 182,085.00 0.00
Pucuk merah LS 20.00 bh - 182,085.00 0.00
Begonia cokelat LS 50.00 bh - 182,085.00 0.00
Tanaman calathea ctenanthe LS 10.00 bh - 182,085.00 0.00
Brokoli hias LS 30.00 bh - 182,085.00 0.00
Lampu taman LS 6.00 bh - 182,085.00 0.00
Name tag (Huruf timbul) IPAL LS 1.00 bh - 182,085.00 0.00
2 Pekerjaan pagar besi keliling IPAL LS 105.00 m¹ - 182,085.00 0.00
3 Pekerjaan atap kanopi LS 162.00 m² - 182,085.00 0.00
4 Sloof & Ring Balk uk.15x15 A.4.1.1.36 105.00 m¹ 2,731.28 286,783.88 182,085.00 1.58
5 Kolom Pagar uk.30x30 A.4.1.1.35 52.50 m¹ 1,638.77 86,035.16 182,085.00 0.47
6 Pekerjaan Balok Pagar A.4.1.1.36 105.00 m¹ 2,731.28 286,783.88 182,085.00 1.58
7 Pekerjaan Pas. Dinding Pagar 1/2 Bata, camp. 1:4 A.4.4.1.8 31.50 m² 2,731.28 86,035.16 182,085.00 0.47
8 Plesteran A.4.4.2.4 105.00 m² 2,731.28 286,783.88 182,085.00 1.58
9 Acian A.4.4.2.27 105.00 m² 1,820.85 191,189.25 182,085.00 1.05
10 Pengecatan Pagar Besi A.4.4.2.3 105.00 m¹ 546.26 57,356.78 182,085.00 0.32
1,280,967.98 182,085.00 7.035
XI PEKERJAAN RUMAH JAGA 182,085.00 0.00
1 Pekerjaan Pondasi 182,085.00 0.00
a Galian Tanah Pondasi A.2.3.1.1 8.03 m³ 4,552.13 36,553.56 182,085.00 0.20
b Pondasi Batu Belah 1:4 A.2.2.1.4x 2.81 m³ 13,656.38 38,374.41 182,085.00 0.21
c Urugan Kembali Galian Pondasi A.2.3.1.9 4.75 m³ 9,104.25 43,245.19 182,085.00 0.24
2 Pekerjaan Sloof 20x15 A.4.1.1.29.a 0.46 m³ 51,530.06 23,703.83 182,085.00 0.13
3 Lantai kerja K100 A.4.1.1.1 0.37 m³ 15,113.06 5,591.83 182,085.00 0.03
4 Pekerjaan Kolom 15x15 A.4.1.1.35.a 0.28 m³ 64,276.01 17,997.28 182,085.00 0.10
5 Pekerjaan Balok 15x15 A.4.1.1.31.a 0.35 m³ 57,903.03 20,266.06 182,085.00 0.11
6 Pekerjaan Dinding 0.00 - 182,085.00 0.00
a Pasangan 1/2 Bata A.4.4.1.8 34.85 m² 2,731.28 95,184.93 182,085.00 0.52
b Plesteran A.4.4.2.4 69.70 m² 2,731.28 190,369.87 182,085.00 1.05
c Acian A.4.4.2.27 69.70 m² 1,820.85 126,913.25 182,085.00 0.70
6 Pekerjaan Keramik A.4.4.3.35 11.26 m² 6,372.98 71,759.70 182,085.00 0.39
7 Pekerjaan Pintu Ls 1.00 unit - 182,085.00 0.00
8 Pekerjaan Jendela Ls 4.00 unit - 182,085.00 0.00
9 Pekerjaan Atap 0.00 182,085.00 0.00
a Rangka Baja Ringan Ls 33.06 m² - 182,085.00 0.00
b Atap Zincalume A.4.5.1.7 33.06 m² 182.09 6,019.73 182,085.00 0.03
c Listplank A.4.5.2.38b 5.85 m² 910.43 5,325.99 182,085.00 0.03
d Profil Etnis Betawi Ls 23.40 m' - - 182,085.00 0.00
11 Pengecatan Dinding A.4.7.1.10 69.70 m² 546.26 38,073.97 182,085.00 0.21
719,379.60 182,085.00 3.95079
182,085.00 0.00
TOTAL PEKERJAAN SIPIL 24,323,111.03 182,085.00
XII MESIN PENGOLAHAN AIR LIMBAH 182,085.00 0.00
Capacity : 100 m3/day 182,085.00 0.00
Biomembrane Reactor 1.00 set - 182,085.00 0.00
Submersible inlet pump 2.00 unit - 182,085.00 0.00
Circulation pump 1.00 unit - 182,085.00 0.00
Air injection 2.00 unit - 182,085.00 0.00
Screen 1.00 unit - 182,085.00 0.00
Turbidity pretreatment 1.00 unit - 182,085.00 0.00
Chlorinator 1.00 unit - 182,085.00 0.00
Water flow meter 2.00 unit - 182,085.00 0.00
Panel control 1.00 unit - 182,085.00 0.00
182,085.00 0.00
182,085.00 0.00
TOTAL PEKERJAAN MESIN - 182,085.00 0.00
XIII TESTING & COMISSIONING 182,085.00 0.00
1 Installation 1.00 ls - 182,085.00 0.00
2 Sambung baru PLN, Bio-Reaktor IPAL ( 22 KVA, 3 phase ) 1.00 ls - 182,085.00 0.00
3 Sambung baru PLN, Pompa sampit ( 2,200 watt, 1 phase ) 1.00 ttk - 182,085.00 0.00
4 Testing & Comissioning 1.00 ls - 182,085.00 0.00
5 Training Operator 1.00 bln - 182,085.00 0.00
TOTAL TESTING & COMISSIONING - 182,085.00 0.00
JUMLAH TOTAL PEMBANGUNAN SPALD KOJA 24,323,111.03 182,085.00
B Pembangunan SPALD Kelurahan lagoa 182,085.00 0.00
I PEKERJAAN PERSIAPAN 182,085.00 0.00
1 Direksi Keet, Pondok Kerja dan Gudang Bahan A.2.2.1.6 30.00 m2 9,104.25 273,127.50 182,085.00 1.50
2 Papan Nama Proyek Ls 1.00 ls - 182,085.00 0.00
3 Pembersihan Lapangan A.2.2.1.9 150.75 m2 9,104.25 1,372,465.69 182,085.00 7.54
1,645,593.19 182,085.00 9.0375
II PEKERJAAN PIPING 182,085.00 0.00
1 Pekerjaan galian tanah dalam 50 - 90 cm A.2.3.1.1 1,073.28 m³ 4,552.13 4,885,704.72 182,085.00 26.83
2 Pekerjaan pemasangan pipa SR PVC 3 inchi P1 2,000.00 m' - - 182,085.00 0.00
3 Pekerjaan pemasangan pipa Sub Line PVC 4 inchi P2 879.00 m' 1,638.77 1,440,474.44 182,085.00 7.91
4 Pekerjaan pemasangan pipa Sub Mainline PVC 6 inchi P3 475.00 m' 2,185.02 1,037,884.50 182,085.00 5.70
5 Pekerjaan pemasangan pipa Mainline PVC 8 inchi P4 146.00 m' 3,459.62 505,103.79 182,085.00 2.77
6 Pekerjaan pemasangan pipa Feeder PVC 10 inchi P5 117.00 m' 4,734.21 553,902.57 182,085.00 3.04
7 Pekerjaan urugan tanah kembali A.2.3.1.9 662.42 m³ 9,104.25 6,030,837.29 182,085.00 33.12
8 Restorasi halaman rumah warga LS 200.00 kk - 182,085.00 0.00
14,453,907.30 182,085.00 79.38
182,085.00 0.00
III PEKERJAAN BAK KONTROL 1 ( 60 x 60 cm ) 182,085.00 0.00
1 Galian Tanah A.2.3.1.1 23.30 m³ 4,552.13 106,064.51 182,085.00 0.58
2 Pekerjaan Bobok Beton Jalan A.2.2.1.13 4.99 m³ 121,268.61 605,130.36 182,085.00 3.32
3 Pek. Dinding Bak cor Beton bertulang, tebal : 10cm A.4.1.1.33.ab 0.34 m³ 48,252.53 16,405.86 182,085.00 0.09
4 Pek. Rabat Beton Lantai, tebal : 10cm A.4.1.1.5 20.54 m³ 15,113.06 310,422.15 182,085.00 1.70
5 Acian A.4.4.2.27 3.52 m² 1,820.85 6,409.39 182,085.00 0.04
6 Pasir urug 5cm A.2.3.1.11.b 0.83 m³ 1,820.85 1,511.31 182,085.00 0.01
7 Plat Dak Tutup bak cor beton bertulang, t : 10cm, wiremesh 1 layer M8-150 A.4.1.1.1 1.27 m³ 15,113.06 19,193.58 182,085.00 0.11
8 Elbow inlet + outlet( L-45°) PVC 6" LS 52.00 unit - - 182,085.00 0.00
9 Tutup manhole Cor Beton bertulang LS 26.00 bh - 182,085.00 0.00
1,065,137.16 182,085.00 5.84967
IV PEKERJAAN BAK KONTROL 2 ( 80 x 80 cm ) 182,085.00 0.00
1 Galian Tanah A.2.3.1.1 5.60 m³ 4,552.13 25,491.90 182,085.00 0.14
2 Pekerjaan Bobok lantai A.2.2.1.13 1.20 m³ 121,268.61 145,522.33 182,085.00 0.80
3 Pek. Dinding Bak cor Beton bertulang, tebal : 10cm A.4.1.1.33.ab 4.48 m³ 48,252.53 216,171.31 182,085.00 1.19
4 Pek. Lantai bak, tebal : 10cm A.4.1.1.5 4.72 m³ 15,113.06 71,333.62 182,085.00 0.39
5 Acian A.4.4.2.27 3.24 m² 1,820.85 5,899.55 182,085.00 0.03
6 Pasir urug 5cm A.2.3.1.11.b 3.54 m³ 1,820.85 6,445.81 182,085.00 0.04
7 Plat Dak Tutup bak cor beton bertulang, t : 10cm, wiremesh 1 layer M8-150 A.4.1.1.1 0.20 m³ 15,113.06 3,022.61 182,085.00 0.02
8 Elbow inlet + outlet( L-45°) PVC 6" LS 8.00 unit - - 182,085.00 0.00
9 Tutup manhole Cor Beton bertulang LS 4.00 bh - 182,085.00 0.00
473,887.14 182,085.00 2.60256
V PEKERJAAN BAK SUMPIT ( 3 unit ) 182,085.00 0.00
1 Pek. Bobok Beton Lantai Jalan, t : 30cm A.2.2.1.13 1.09 m³ 121,268.61 132,182.78 182,085.00 0.73
2 Galian Tanah A.2.3.1.1 7.26 m³ 4,552.13 33,048.43 182,085.00 0.18
3 Pek. Dinding Bak cor beton bertulang, t : 10cm, wiremesh 1 layer M8-150 A.4.1.1.33.ab 3.25 m³ 48,252.53 156,820.71 182,085.00 0.86
4 Pek. Rabat Benton Lantai, tebal : 15cm A.4.1.1.5 0.54 m³ 15,113.06 8,161.05 182,085.00 0.04
5 Acian A.4.4.2.27 14.52 m² 1,820.85 26,438.74 182,085.00 0.15
6 Lantai kerja, t : 5cm A.4.1.1.1 1.50 m³ 15,113.06 22,669.58 182,085.00 0.12
7 Plat Penutup Dak Beton Bertulang, t : 10cm A.4.1.1.37 0.08 m³ 33,384.56 2,670.76 182,085.00 0.01
8 Tutup plat besi ( manhole ) LS 3.00 set - 182,085.00 0.00
381,992.06 182,085.00 2.09787768
VI PEKERJAAN BAK EQUALISASI 182,085.00 0.00
1 Galian Tanah A.2.3.1.1 97.68 m³ 4,552.13 444,651.57 182,085.00 2.44
2 Urugan sirtu t = 15 cm A.2.3.1.14 4.09 m³ 4,552.13 18,618.19 182,085.00 0.10
3 Pasir urug t = 10 cm A.2.3.1.11.b 2.73 m³ 1,820.85 4,970.92 182,085.00 0.03
4 Lantai kerja t = 5 cm A.4.1.1.1 1.36 m³ 15,113.06 20,553.75 182,085.00 0.11
5 Lantai bak cor beton bertulang A.4.1.1.37 5.45 m³ 33,384.56 181,945.83 182,085.00 1.00
6 Dinding beton bertulang A.4.1.1.33.a 17.68 m³ 48,252.53 853,104.64 182,085.00 4.69
7 Balok beton 15/20cm A.4.1.1.31.a 0.62 m³ 57,903.03 35,899.88 182,085.00 0.20
8 Acian A.4.4.2.27 1.00 m² 1,820.85 1,820.85 182,085.00 0.01
9 Tutup plat baja rangka siku L.50.50.5 LS 2.00 unit - 182,085.00 0.00
1,561,565.64 182,085.00 8.5760257
VII PEKERJAAN DUDUKAN BIOREACTOR ( 1 UNIT ) 182,085.00 0.00
1 Galian Tanah A.2.3.1.1 64.40 m³ 4,552.13 293,156.85 182,085.00 1.61
2 Pasir Urug A.2.3.1.11.b 1.01 m³ 1,820.85 1,835.42 182,085.00 0.01
3 Urugan Kembali A.2.3.1.9 55.78 m³ 9,104.25 507,835.07 182,085.00 2.79
4 Beton Pondasi K350 A.4.1.1.37B 8.62 m³ 35,797.18 308,571.71 182,085.00 1.69
5 Baut Angkur c 56.00 m³ - - 182,085.00 0.00
6 Base Plat 10mm f 1,758.40 m³ - - 182,085.00 0.00
7 Pengecatan Base Plat A.4.4.2.3 4.48 m² 546.26 2,447.22 182,085.00 0.01
8 Plesteran Pondasi A.4.4.2.4 31.64 m² 2,731.28 86,417.54 182,085.00 0.47
9 Acian Pondasi A.4.4.2.27 82.48 m³ 1,820.85 150,183.71 182,085.00 0.82
1,350,447.52 182,085.00 7.41657752
VIII PEKERJAAN BAK GRASE TRAP 182,085.00 0.00
1 Pek. Bobok Beton Lantai Jalan, t :30cm A.2.2.1.13 30.74 m3 121,268.61 3,727,797.07 182,085.00 20.47
2 Galian Tanah A.2.3.1.1 303.60 m3 4,552.13 1,382,025.15 182,085.00 7.59
3 Pek. Dinding Bak cor beton bertulang, wiremess M8-150, t : 10cm A.4.1.1.33.ab 47.51 m3 48,252.53 2,292,477.46 182,085.00 12.59
4 Pek. Rabat Benton Lantai tanpa tulang, tebal : 15cm A.4.1.1.5 13.66 m2 15,113.06 206,444.33 182,085.00 1.13
5 Acian A.4.4.2.27 531.99 m2 1,820.85 968,673.99 182,085.00 5.32
6 Pasir urug 10 cm A.2.3.1.11.b 10.25 m3 1,820.85 18,663.71 182,085.00 0.10
7 Lantai kerja, t : 5cm A.4.1.1.1 5.12 m3 15,113.06 77,378.84 182,085.00 0.42
8 Plat Penutup Dak Beton Bertulang, t : 10cm A.4.1.1.37 8.89 bh 33,384.56 296,788.71 182,085.00 1.63
9 Elbow (L) PVC 4" - 138.00 bh 573.57 79,152.35 182,085.00 0.43
10 Reduser Shock PVC 4" - 6" - 69.00 bh 655.51 45,229.91 182,085.00 0.25
11 Elbow ( T ) PVC 6" - 69.00 bh 655.51 45,229.91 182,085.00 0.25
12 Tutup manhole plat beton bertulang - 138.00 pcs - 182,085.00 0.00
9,139,861.45 182,085.00 50.19557594
IX PEKERJAAN FISH POND DAN BAK CHLORINASI 182,085.00 0.00
1 Galian Tanah A.2.3.1.1 2.87 m³ 4,552.13 13,064.60 182,085.00 0.07
2 urug pasir bawah lantai beton A.2.3.1.11.b 0.23 m² 1,820.85 418.80 182,085.00 0.00
3 Kolom Praktis A.4.1.1.35 0.50 m³ 1,638.77 819.38 182,085.00 0.00
4 Pas. Bata, camp 1 : 4 A.4.4.1.8 14.16 m² 2,731.28 38,674.85 182,085.00 0.21
5 Plesteran A.4.4.2.4 28.18 m² 2,731.28 76,967.33 182,085.00 0.42
6 Acian A.4.4.2.27 32.42 m² 1,820.85 59,031.96 182,085.00 0.32
7 Lantai Bak cor beton camp. K.175 A.4.1.1.5 0.71 m³ 15,113.06 10,730.27 182,085.00 0.06
199,707.19 182,085.00 1.09678
X PEK. TAMAN, PAGAR DAN CANOPY 182,085.00 0.00
1 PEKERJAAN TAMAN 182,085.00 0.00
Pemupukan tanah LS 110.25 m² - 182,085.00 0.00
Bunga Sabrina LS 30.00 bh - 182,085.00 0.00
Pucuk merah LS 20.00 bh - 182,085.00 0.00
Begonia cokelat LS 50.00 bh - 182,085.00 0.00
Tanaman calathea ctenanthe LS 10.00 bh - 182,085.00 0.00
Brokoli hias LS 30.00 bh - 182,085.00 0.00
Lampu taman LS 6.00 bh - 182,085.00 0.00
Name tag (Huruf timbul) IPAL LS 1.00 bh - 182,085.00 0.00
2 Pekerjaan pagar besi keliling IPAL LS 105.00 m¹ - 182,085.00 0.00
3 Pekerjaan atap kanopi LS 162.00 m² - 182,085.00 0.00
4 Sloof & Ring Balk uk.15x15 A.4.1.1.36 105.00 m¹ 2,731.28 286,783.88 182,085.00 1.58
5 Kolom Pagar uk.30x30 A.4.1.1.35 52.50 m¹ 1,638.77 86,035.16 182,085.00 0.47
6 Pekerjaan Balok Pagar A.4.1.1.36 105.00 m¹ 2,731.28 286,783.88 182,085.00 1.58
7 Pekerjaan Pas. Dinding Pagar 1/2 Bata, camp. 1:4 A.4.4.1.8 31.50 2,731.28 86,035.16 182,085.00 0.47
8 Plesteran A.4.4.2.4 105.00 m² 2,731.28 286,783.88 182,085.00 1.58
9 Acian A.4.4.2.27 105.00 m² 1,820.85 191,189.25 182,085.00 1.05
10 Pengecatan Pagar Besi A.4.4.2.3 105.00 m¹ 546.26 57,356.78 182,085.00 0.32
1,280,967.98 182,085.00 7.035
XI PEKERJAAN RUMAH JAGA 182,085.00 0.00
1 Pekerjaan Pondasi 182,085.00 0.00
a Galian Tanah Pondasi A.2.3.1.1 8.03 m³ 4,552.13 36,553.56 182,085.00 0.20
b Pondasi Batu Belah 1:4 A.2.2.1.4x 2.81 m³ 13,656.38 38,374.41 182,085.00 0.21
c Urugan Kembali Galian Pondasi A.2.3.1.9 4.75 m³ 9,104.25 43,245.19 182,085.00 0.24
2 Pekerjaan Sloof 20x15 A.4.1.1.29.a 0.46 m³ 51,530.06 23,703.83 182,085.00 0.13
3 Lantai kerja K100 A.4.1.1.1 0.37 m³ 15,113.06 5,591.83 182,085.00 0.03
4 Pekerjaan Kolom 15x15 A.4.1.1.35.a 0.28 m³ 64,276.01 17,997.28 182,085.00 0.10
5 Pekerjaan Balok 15x15 A.4.1.1.31.a 0.35 m³ 57,903.03 20,266.06 182,085.00 0.11
6 Pekerjaan Dinding 182,085.00 0.00
a Pasangan 1/2 Bata A.4.4.1.8 34.85 m² 2,731.28 95,184.93 182,085.00 0.52
b Plesteran A.4.4.2.4 69.70 m² 2,731.28 190,369.87 182,085.00 1.05
c Acian A.4.4.2.27 69.70 m² 1,820.85 126,913.25 182,085.00 0.70
6 Pekerjaan Keramik A.4.4.3.35 11.26 m² 6,372.98 71,759.70 182,085.00 0.39
7 Pekerjaan Pintu Ls 1.00 unit - 182,085.00 0.00
8 Pekerjaan Jendela Ls 4.00 unit - 182,085.00 0.00
9 Pekerjaan Atap 182,085.00 0.00
a Rangka Baja Ringan Ls 33.06 m² - 182,085.00 0.00
b Atap Zincalume A.4.5.1.7 33.06 m² 182.09 6,019.73 182,085.00 0.03
c Listplank A.4.5.2.38b 5.85 m² 910.43 5,325.99 182,085.00 0.03
d Profil Etnis Betawi Ls 23.40 m' - 182,085.00 0.00
11 Pengecatan Dinding A.4.7.1.10 69.70 m² 546.26 38,073.97 182,085.00 0.21
719,379.60 182,085.00 3.95079
TOTAL PEKERJAAN SIPIL 32,272,446.21 182,085.00
XII MESIN PENGOLAHAN AIR LIMBAH 182,085.00 0.00
Capacity : 100 m3/day 182,085.00 0.00
Biomembrane Reactor 1.00 set - 182,085.00 0.00
Submersible inlet pump 2.00 unit - 182,085.00 0.00
Circulation pump 1.00 unit - 182,085.00 0.00
Air injection 2.00 unit - 182,085.00 0.00
Screen 1.00 unit - 182,085.00 0.00
Turbidity pretreatment 1.00 unit - 182,085.00 0.00
Chlorinator 1.00 unit - 182,085.00 0.00
Water flow meter 2.00 unit - 182,085.00 0.00
Panel control 1.00 unit - 182,085.00 0.00
182,085.00 0.00
182,085.00 0.00
TOTAL PEKERJAAN MESIN - 182,085.00 0.00
XIII INSTALLATION, TESTING & COMISSIONING 182,085.00 0.00
1 Installation 1.00 ls - 182,085.00 0.00
2 Sambung baru PLN, Bio-Reaktor IPAL ( 22 KVA, 3 phase ) 1.00 ls - 182,085.00 0.00
3 Sambung baru PLN, Pompa sampit ( 2,200 watt, 1 phase ) 3.00 ttk - 182,085.00 0.00
4 Testing & Comissioning 1.00 ls - 182,085.00 0.00
5 Training Operator 1.00 bln - 182,085.00 0.00
TOTAL TESTING & COMISSIONING - 182,085.00 0.00
JUMLAH TOTAL PEMBANGUNAN SPALD LAGOA 32,272,446.21 310.82 310.82
KOREKSI
56,595,557.23
56,595,557.23
JUMLAH
NO URAIAN BIAYA
( Rp )
I II III
NO URAIAN PEKERJAAN
II PEKERJAAN PIPING
1 Pekerjaan galian tanah dalam 50 - 90 cm
2 Pekerjaan pemasangan pipa SR PVC 3 inchi
3 Pekerjaan pemasangan pipa Sub Line PVC 4 inchi
4 Pekerjaan pemasangan pipa Sub Mainline PVC 6 inchi
5 Pekerjaan pemasangan pipa Mainline PVC 8 inchi
6 Pekerjaan pemasangan pipa Feeder PVC 10 inchi
7 Pekerjaan urugan tanah kembali
8 Restorasi halaman rumah warga
II PEKERJAAN PIPING
1 Pekerjaan galian tanah dalam 50 - 90 cm
2 Pekerjaan pemasangan pipa SR PVC 3 inchi
3 Pekerjaan pemasangan pipa Sub Line PVC 4 inchi
4 Pekerjaan pemasangan pipa Sub Mainline PVC 6 inchi
5 Pekerjaan pemasangan pipa Mainline PVC 8 inchi
6 Pekerjaan pemasangan pipa Feeder PVC 10 inchi
7 Pekerjaan urugan tanah kembali
8 Restorasi halaman rumah warga
HARGA JUMLAH
VOLUME SAT SATUAN HARGA
( Rp ) ( Rp )
30.00 m2 -
1.00 ls 1,500,000.00 1,500,000.00
150.75 m2 -
1,500,000.00
604.80 m³ -
2,000.00 m' -
300.00 m' -
700.00 m' -
110.00 m' -
250.00 m' -
120.96 m³ -
200.00 kk 650,000.00 130,000,000.00
130,000,000.00
15.23 m³ -
3.26 m³ -
0.34 m³ -
13.43 m³ -
3.52 m² -
0.54 m³ -
0.83 m³ -
2.00 unit -
17.00 bh 500,000.00 8,500,000.00
8,500,000.00
11.20 m³ -
2.40 m³ -
8.96 m³ -
9.44 m³ -
6.48 m² -
7.08 m³ -
0.39 m³ -
2.00 unit -
8.00 bh 500,000.00 4,000,000.00
4,000,000.00
0.36 m³ -
2.42 m³ -
1.08 m³ -
0.18 m³ -
4.84 m² -
0.50 m³ -
0.08 m³ -
1.00 set 500,000.00 500,000.00
500,000.00
97.68 m³ -
4.09 m³ -
2.73 m³ -
1.36 m³ -
5.45 m³ -
17.68 m³ -
0.62 m³ -
1.00 m² -
2.00 set 6,500,000.00 13,000,000.00
13,000,000.00
64.40 m³ -
1.01 m³ -
55.78 m³ -
8.62 m³ -
56.00 bh -
1,758.40 kg -
4.48 m² -
31.64 m² -
82.48 m² -
-
28.07 m³ -
277.20 m³ -
43.38 m³ -
12.47 m³ -
485.73 m³ -
9.36 m³ -
4.68 m² -
8.12 m¹ -
126.00 bh -
63.00 bh -
63.00 bh -
126.00 set 850,000.00 107,100,000.00
107,100,000.00
2.87 m³ -
0.23 m² -
0.50 m³ -
14.16 m² -
28.18 m² -
32.42 m² -
0.71 m³ -
-
8.03 m³ -
2.81 m³ -
4.75 m³ -
0.46 m³ -
0.37 m³ -
0.28 m³ -
0.35 m³ -
34.85 m² -
69.70 m² -
69.70 m² -
11.26 m² -
1.00 unit 4,000,000.00 4,000,000.00
4.00 unit 1,500,000.00 6,000,000.00
SIPIL 456,475,250.00
MESIN 2,129,081,000.00
30.00 m2 -
1.00 ls 1,500,000.00 1,500,000.00
150.75 m2 -
1,500,000.00
1,073.28 m³ -
2,000.00 m' -
879.00 m' -
475.00 m' -
146.00 m' -
117.00 m' -
662.42 m³ -
200.00 kk 650,000.00 130,000,000.00
130,000,000.00
23.30 m³ -
4.99 m³ -
0.34 m³ -
20.54 m³ -
3.52 m² -
0.83 m³ -
1.27 m³ -
52.00 unit -
26.00 bh 500,000.00 13,000,000.00
13,000,000.00
5.60 m³ -
1.20 m³ -
4.48 m³ -
4.72 m³ -
3.24 m² -
3.54 m³ -
0.20 m³ -
8.00 unit -
4.00 bh 500,000.00 2,000,000.00
2,000,000.00
1.09 m³ -
7.26 m³ -
3.25 m³ -
0.54 m³ -
14.52 m² -
1.50 m³ -
0.08 m³ -
3.00 set 500,000.00 1,500,000.00
1,500,000.00
97.68 m³ -
4.09 m³ -
2.73 m³ -
1.36 m³ -
5.45 m³ -
17.68 m³ -
0.62 m³ -
1.00 m² -
2.00 unit 6,500,000.00 13,000,000.00
13,000,000.00
64.40 m³ -
1.01 m³ -
55.78 m³ -
8.62 m³ -
56.00 m³ -
1,758.40 m³ -
4.48 m² -
31.64 m² -
82.48 m³ -
-
30.74 m3 -
303.60 m3 -
47.51 m3 -
13.66 m2 -
531.99 m2 -
10.25 m3 -
5.12 m3 -
8.89 bh -
138.00 bh -
69.00 bh -
69.00 bh -
138.00 pcs 850,000.00 117,300,000.00
117,300,000.00
2.87 m³ -
0.23 m² -
0.50 m³ -
14.16 m² -
28.18 m² -
32.42 m² -
0.71 m³ -
-
8.03 m³ -
2.81 m³ -
4.75 m³ -
0.46 m³ -
0.37 m³ -
0.28 m³ -
0.35 m³ -
34.85 m² -
69.70 m² -
69.70 m² -
11.26 m² -
1.00 unit 4,000,000.00 4,000,000.00
4.00 unit 1,500,000.00 6,000,000.00
MESIN 2,129,081,000.00
- 483,195,077.03
1,805,100,000.00 - 52,719,000.00
- 1,271,993,900.73
224,697,600.00
24,449,931.75
106,296,048.25
26,535,649.53
101,215,847.50
2,660,147,710.00
-
5,299,047,660.00
(2,423,679,899.39)
3,910,478,190.27
(1,250,330,480.27) (625,165,240.13)
5,999,000.00
- 224,697,600.00
- 24,449,931.75
- 106,296,048.25
- 26,535,649.53
- 101,215,847.50
483,195,077.03
966,390,154.05
- 224,697,600.00
- 24,449,931.75
- 106,296,048.25
- 26,535,649.53
- 101,215,847.50
RENCANA ANGGARAN BIAYA
I PEKERJAAN PERSIAPAN
1 Direksi Keet, Pondok Kerja dan Gudang Bahan 30.00 m2 1,157,757.12 34,732,713.63
2 Papan Nama Proyek 1.00 bh 1,500,000.00 1,500,000.00
3 Pembersihan Lapangan 150.75 m2 22,536.75 3,397,415.06
39,630,128.69
II PEKERJAAN PIPING
1 Pekerjaan galian tanah dalam 50 - 90 cm 604.80 m3 105,295.88 63,682,945.20
2 Pekerjaan pemasangan pipa SR PVC 3 inchi 2,000.00 m1 55,646.17 111,292,345.00
3 Pekerjaan pemasangan pipa Sub Line PVC 4 inchi 300.00 m1 239,850.00 71,955,000.00
4 Pekerjaan pemasangan pipa Sub Mainline PVC 6 inchi 700.00 m1 151,851.50 106,296,048.25
5 Pekerjaan pemasangan pipa Mainline PVC 8 inchi 110.00 m1 241,233.18 26,535,649.53
6 Pekerjaan pemasangan pipa Feeder PVC 10 inchi 250.00 m1 1,383,750.00 345,937,500.00
7 Pekerjaan urugan tanah kembali 120.96 m3 76,266.75 9,225,226.08
8 Restorasi halaman rumah warga 200.00 m1 650,000.00 130,000,000.00
864,924,714.06
### #REF!
### #REF!
#REF! #REF! #REF! #REF! 1,016,813.39 #REF!
#REF! #REF! #REF! #REF! 910.43 #REF!
#REF! #REF! #REF! #REF! 121,268.61 #REF!
### #REF!
#REF! #REF! #REF! #REF! 80,000.00 #REF!
#REF! #REF! #REF! #REF! #REF! #REF!
#REF!
III PEKERJAAN BAK KONTROL 1
1 Galian Tanah 15.23 m3 105,295.88 1,603,866.77
2 Pekerjaan bobok lantai 3.26 m3 1,016,813.39 3,318,878.89
3 Pek. Dinding Bak cor Beton bertulang, tebal : 10cm 0.34 m2 1,878,922.65 638,833.70
4 Pek. Rabat Beton Lantai, tebal : 10cm 13.43 m2 1,552,320.35 20,847,662.33
5 Acian 3.52 m2 50,915.70 179,223.27
6 Pasir urug 5cm 0.54 m3 365,254.35 198,698.37
7 Plat Dak Tutup bak cor beton bertulang, t : 10cm, wiremesh 1 layer M8-150 0.83 m3 1,444,884.67 1,203,588.93
8 Elbow inlet + outlet( L-45°) PVC 6" 2.00 bh 1,383,750.00 2,767,500.00
9 Tutup manhole Cor Beton bertulang 17.00 pcs 500,000.00 8,500,000.00
39,258,252.25
V PEKERJAAN BAK KONTROL 2
1 Galian Tanah 11.20 m3 105,295.88 1,179,313.80
2 Pekerjaan bobok lantai 2.40 m3 1,016,813.39 2,440,352.12
3 Pek. Dinding Bak cor Beton bertulangan, tebal : 10cm 8.96 m2 1,878,922.65 16,835,146.98
4 Pek. Lantai bak, tebal : 10cm 9.44 m2 1,552,320.35 14,653,904.12
5 Acian 6.48 m2 50,915.70 329,770.82
7 Pasir urug 5cm 7.08 m3 365,254.35 2,585,229.38
8 Plat Dak Tutup bak cor beton bertulang, t : 10cm, wiremesh 1 layer M8-150 0.39 m3 1,444,884.67 566,394.79
9 Elbow inlet + outlet( L-45°) PVC 6" 2.00 bh 1,383,750.00 2,767,500.00
10 Tutup manhole Baja Cor (Costums) 8.00 pcs 500,000.00 4,000,000.00
45,357,612.02
VI PEKERJAAN BAK PENAMPUNG SEMENTARA
1 Galian Tanah 2.40 m3 105,295.88 252,710.10
2 Pek. Dinding Bak cor Beton bertulang, tebal : 10cm 8.96 m2 1,878,922.65 16,835,146.98
3 Pek. Rabat Beton Lantai, tebal : 10cm 9.44 m2 1,552,320.35 14,653,904.12
4 Acian 6.48 m2 50,915.70 329,770.82
5 Pasir urug 5cm 7.08 m3 365,254.35 2,585,229.38
6 Plat Dak Tutup bak cor beton bertulang, t : 10cm, wiremesh 1 layer M8-150 0.39 m3 1,444,884.67 566,394.79
7 Elbow inlet + outlet( L-45°) PVC 6" 2.00 bh 1,383,750.00 2,767,500.00
8 Tutup manhole Baja Cor (Costums) 8.00 pcs 500,000.00 4,000,000.00
41,990,656.20
VII PEKERJAAN BAK SUMPIT ( 1 unit )
1 Pek. Bobok Beton Lantai Jalan, t : 30cm 0.36 m3 1,016,813.39 369,103.26
2 Galian Tanah 2.42 m3 1,016,813.39 2,460,688.39
3 Pek. Dinding Bak cor beton bertulang, t : 10cm, wiremesh 1 layer M8-150 1.08 m2 105,295.88 114,035.43
4 Pek. Rabat Benton Lantai, tebal : 15cm 0.18 m2 1,878,922.65 341,024.46
5 Acian 4.84 m2 1,552,320.35 7,513,230.50
6 Lantai kerja, t : 5cm 0.50 m3 5,529,327.37 2,764,663.69
7 Plat Penutup Dak Beton Bertulang, t : 10cm 0.08 bh 500,000.00 40,000.00
8 Tutup plat besi ( manhole ) 1.00 pcs #REF! #REF!
#REF!
VIII PEKERJAAN BAK GRASE TRAP
1 Pek. Bobok Beton Lantai Jalan, t :30cm 28.07 m3 1,016,813.39 28,538,392.87
2 Galian Tanah 277.20 m3 1,016,813.39 281,860,670.32
3 Pek. Dinding Bak cor beton bertulang, t : 10cm, wiremesh 1 layer M8-150 43.38 m2 105,295.88 4,567,261.23
4 Pek. Rabat Benton Lantai, tebal : 15cm 12.47 m2 1,878,922.65 23,437,681.19
5 Acian 485.73 m2 5,529,327.37 2,685,760,184.11
7 Pasir urug 10 cm 9.36 m3 365,254.35 3,417,137.07
8 Lantai kerja, t : 5cm 4.68 m3 1,444,884.67 6,758,809.26
9 Plat Penutup Dak Beton Bertulang, t : 10cm 8.12 bh 500,000.00 4,059,562.50
10 Elbow (L) PVC 4" 126.00 bh #REF! #REF!
11 Reduser Shock PVC 4" - 6" 63.00 bh #REF! #REF!
12 Elbow ( T ) PVC 6" 63.00 bh #REF! #REF!
13 Tutup plat besi ( manhole ) 126.00 bh #REF! #REF!
#REF!
IX PEKERJAAN BAK EQUALISASI
1 Galian Tanah 97.68 m3 105,295.88 10,285,432.69
2 Urugan sirtu t = 15 cm 4.09 m2 207,066.98 846,696.86
3 Pasir urug t = 10 cm 2.73 m2 365,254.35 995,683.36
4 Lantai kerja t = 5 cm 1.36 m2 1,444,884.67 1,969,377.80
5 Lantai bak cor beton bertulang 5.45 m2 5,529,327.37 30,134,834.17
6 Dinding beton bertulang 17.68 m3 6,956,464.90 122,990,299.48
7 Balok beton 15/20cm 0.62 m3 7,256,082.74 4,498,771.30
8 Acian 1.00 bh 50,915.70 50,915.70
9 Tutup plat baja rangka siku L.50.50.5 2.00 bh 6,500,000.00 13,000,000.00
184,772,011.36
X #REF!
#REF! #REF! 64.40 m³ 105,295.88 6,781,054.35
#REF! #REF! 1.01 m³ 365,254.35 368,906.89
#REF! #REF! 55.78 m³ 76,266.75 4,254,159.32
#REF! #REF! 8.62 m³ 4,297,723.43 37,046,375.99
#REF! #REF! 56.00 bh 67,827.38 3,798,333.00
#REF! #REF! 1,758.40 kg 17,820.00 31,334,688.00
#REF! #REF! 4.48 kg 43,124.77 193,198.96
#REF! #REF! 31.64 m² 84,795.63 2,682,933.65
#REF! #REF! 82.48 m² 50,915.70 4,199,527.14
90,659,177.29
XI #REF!
#REF! #REF! 28.07 m³ 1,016,813.39 28,541,951.72
#REF! #REF! 277.20 m³ 105,295.88 29,188,016.55
#REF! #REF! 43.38 m³ 1,878,922.65 81,507,664.75
#REF! #REF! 12.47 m³ 1,552,320.35 19,357,434.79
#REF! #REF! 485.73 m³ 50,915.70 24,731,284.18
#REF! #REF! 9.36 m³ 365,254.35 3,418,780.72
#REF! #REF! 4.68 m² 1,444,884.67 6,762,060.25
#REF! #REF! 8.12 m¹ 5,529,327.37 44,898,138.26
238,405,331.21
XII PEKERJAAN FISH POND DAN BAK CHLORINASI
1 Galian Tanah 2.87 m³ 105,295.88 302,199.16
2 urug pasir bawah lantai beton 0.23 m² 365,254.35 84,008.50
3 Kolom Praktis 0.50 m³ 103,231.89 51,332.06
5 Plesteran 28.18 m² 84,795.63 2,389,752.77
6 Acian 32.42 m² 50,915.70 1,650,814.36
7 Lantai Bak cor beton camp. K.175 0.71 m³ 1,552,320.35 1,094,385.85
5,572,492.70
XIII PEK. TAMAN, PAGAR DAN CANOPY
1 PEKERJAAN TAMAN
Pemupukan tanah 110.25 m² 25,000.00 2,756,250.00
Bunga Sabrina 30.00 bh 50,000.00 1,500,000.00
Pucuk merah 20.00 bh 200,000.00 4,000,000.00
Begonia cokelat 50.00 bh 25,000.00 1,250,000.00
Tanaman calathea ctenanthe 10.00 bh 300,000.00 3,000,000.00
Brokoli hias 30.00 bh 50,000.00 1,500,000.00
Lampu taman 6.00 bh 300,000.00 1,800,000.00
Name tag (Huruf timbul) IPAL 1.00 bh 25,000,000.00 25,000,000.00
2 Pekerjaan pagar besi keliling IPAL 105.00 m² 500,000.00 52,500,000.00
3 Pekerjaan atap kanopi 162.00 m² 480,000.00 77,760,000.00
hollo 40x40x2,3ml 37.42 kg #REF! #REF!
4 Sloof & Ring Balk uk.15x15 2.36 m³ 133,265.31 314,839.30
5 Kolom Pagar uk.30x20 52.50 m³ 103,231.89 5,419,674.07
6 Pekerjaan Balok Pagar 2.36 m² 133,265.31 314,839.30
7 Pekerjaan Rolak Bata 31.50 m² 172,547.16 5,435,235.38
8 Plesteran 105.00 m² 84,795.63 8,903,540.87
9 Acian 105.00 m² 50,915.70 5,346,148.76
#REF!
XIV PEKERJAAN RUMAH JAGA
1 Pekerjaan Pondasi
a Galian Tanah Pondasi 8.03 m³ 105,295.88 845,525.88
b Pondasi Batu Belah 1:4 2.81 m³ 953,946.32 2,680,589.17
c Urugan Kembali Galian Pondasi 4.75 m³ 76,266.75 362,267.06
2 Pekerjaan Sloof 20x15 4.75 m³ 4,976,251.43 23,612,313.01
3 Lantai kerja K100 0.37 m³ 1,444,884.67 534,607.33
4 Pekerjaan Kolom 15x15 0.37 m³ 9,222,109.53 3,366,069.98
5 Pekerjaan Balok 15x15 0.28 m³ 7,256,082.74 2,057,099.46
6 Pekerjaan Dinding
a Pasangan 1/2 Bata 34.85 m² 176,229.47 6,141,597.03
b Plesteran 69.70 m² 84,795.63 5,910,255.22
c Acian 69.70 m² 50,915.70 3,548,824.46
6 Pekerjaan Keramik 11.26 m² 276,818.49 3,116,976.17
7 Pekerjaan Pintu 1.00 unit 4,000,000.00 4,000,000.00
8 Pekerjaan Jendela 4.00 unit 1,500,000.00 6,000,000.00
9 Pekerjaan Atap
a Rangka Baja Ringan 33.06 m² 150,000.00 4,959,000.00
b Atap Zincalume 33.06 m² 172,058.47 5,688,253.02
c Listplank 5.85 m² 120,702.88 706,111.82
d Profil Etnis Betawi 23.40 m' 250,000.00 5,850,000.00
#REF! #REF! #REF! m² #REF! #REF!
11 Pengecatan Dinding 69.70 m² 34,769.75 2,423,451.70
#REF!
XV #REF!
#REF! #REF! #REF! m³ #REF! #REF!
#REF! #REF! #REF! m³ #REF! #REF!
#REF! #REF! #REF! m³ #REF! #REF!
#REF! #REF! #REF! kg #REF! #REF!
#REF! #REF! #REF! m² #REF! #REF!
#REF! #REF! #REF! m³ #REF! #REF!
#REF! #REF! #REF! bh #REF! #REF!
#REF! #REF! #REF! kg #REF! #REF!
#REF! #REF! #REF! m² #REF! #REF!
#REF! #REF! #REF! m² #REF! #REF!
#REF! #REF! #REF! m² #REF! #REF!
#REF!
TOTAL PEKERJAAN SIPIL #REF!
XVI MESIN PENGOLAHAN AIR LIMBAH
Capacity : 100 m3/day
Biomembrane Reactor 1.00 set 1,752,381,000.00 1,752,381,000.00
Submersible inlet pump 2.00 unit 12,700,000.00 25,400,000.00
Circulation pump 1.00 unit 5,100,000.00 5,100,000.00
Air injection 2.00 unit 33,200,000.00 66,400,000.00
Screen 1.00 unit 4,600,000.00 4,600,000.00
Turbidity pretreatment 1.00 unit 194,600,000.00 194,600,000.00
Chlorinator 1.00 unit 11,600,000.00 11,600,000.00
Water flow meter 2.00 unit 17,200,000.00 34,400,000.00
Panel control 1.00 unit 34,600,000.00 34,600,000.00
2,129,081,000.00
TOTAL PEKERJAAN MESIN
XVII TESTING & COMISSIONING
1 Installation 1.00 ls 15,000,000.00 15,000,000.00
2 Testing & Comissioning 1.00 ls 5,000,000.00 5,000,000.00
3 Training Operator 1.00 bln 5,000,000.00 5,000,000.00
25,000,000.00
TOTAL TESTING & COMISSIONING
TOTAL KESELURUHAN PEKERJAAN #REF!
REKAPITULASI PERKIRAAN HARGA PEKERJAAN
JUMLAH
NO URAIAN BIAYA
( Rp )
I II III
A PEKERJAAN SARANA PENDUKUNG IPAL ( SIPIL )
I PEKERJAAN PERSIAPAN 39,630,128.69
II PEKERJAAN PIPING 1,405,214,845.92
III PEKERJAAN BAK KONTROL 1 ( 60 x 60 cm ) #REF!
IV PEKERJAAN BAK KONTROL 2 ( 80 x 80 cm ) #REF!
V PEKERJAAN BAK SUMPIT ( 1 unit ) 13,670,585.16
VI PEKERJAAN BAK EQUALISASI 186,604,553.37
VII PEKERJAAN DUDUKAN BIOREACTOR ( 1 UNIT ) 101,296,684.98
VIII PEKERJAAN BAK GRASE TRAP 388,617,646.19
IX PEKERJAAN FISH POND DAN BAK CHLORINASI 8,067,549.53
X PEK. TAMAN, PAGAR DAN CANOPY 228,800,657.71
XI PEKERJAAN RUMAH JAGA 60,188,411.71
SUB TOTAL (I - XI) #REF!
B PEKERJAAN (ME) INSTALASI PENGOLAHAN AIR LIMBAH
IPAL
XII MESIN PENGOLAHAN AIR LIMBAH 2,123,100,000.00
XIII INSTALLATION, TESTING & COMISSIONING 25,000,000.00
SUB TOTAL ( I ) 2,148,100,000.00
HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT SATUAN HARGA
( Rp ) ( Rp )
I PEKERJAAN PERSIAPAN
1 Direksi Keet, Pondok Kerja dan Gudang Bahan 30.00 m2 1,157,757.12 34,732,713.63
2 Papan Nama Proyek 1.00 ls 1,500,000.00 1,500,000.00
3 Pembersihan Lapangan 150.75 m2 22,536.75 3,397,415.06
39,630,128.69
II PEKERJAAN PIPING
1 Pekerjaan galian tanah dalam 50 - 90 cm 1,073.28 m³ 105,295.88 113,011,956.72
2 Pekerjaan pemasangan pipa SR PVC 3 inchi 2,000.00 m' 188,300.00 376,600,000.00
3 Pekerjaan pemasangan pipa Sub Line PVC 4 inchi 879.00 m' 239,850.00 210,828,150.00
4 Pekerjaan pemasangan pipa Sub Mainline PVC 6 inchi 475.00 m' 498,750.00 236,906,250.00
5 Pekerjaan pemasangan pipa Mainline PVC 8 inchi 146.00 m' 790,750.00 115,449,500.00
6 Pekerjaan pemasangan pipa Feeder PVC 10 inchi 117.00 m' 1,383,750.00 161,898,750.00
7 Pekerjaan urugan tanah kembali 662.42 m³ 76,266.75 50,520,239.20
8 Restorasi halaman rumah warga 200.00 kk 700,000.00 140,000,000.00
1,405,214,845.92
HARGA SATUAN
NO URAIAN SATUAN KODE ANALISA
(Rp)
1 2 3 4 5
PEKERJAAN BETON
1 Membuat beton tumbuk 1pc:3ps:5kr M3 1,444,884.67 A.4.1.1.1
2 Membuat beton tumbuk 1pc:2ps:3 kr M3 1,464,317.29 A.4.1.1.1b
3 Membuat lantai kerja beton tumbuk 1pc:3ps:5kr M3 1,444,884.67 A.4.1.1.1
4 Pek beton K175 M3 1,552,320.35 A.4.1.1.5
5 Pembesian dgn besi polos atau ulir kg 15,075.02 A.4.1.1.17
6 Pekerjaan sloof 20/30 beton bertulang M3 4,976,251.43 A.4.1.1.29.a
7 Pekerjaan balok beton bertulang M3 7,256,082.74 A.4.1.1.31.a
8 Pekerjaan Ring balok beton bertulang M 133,265.31 A.4.1.1.36
9 Pekerjaan plat lantai beton bertulang M3 5,529,327.37 A.4.1.1.37
10 Pekerjaan pondasi beton bertulang M3 4,297,723.43 A.4.1.1.37B
10 Pek kolom M3 9,222,109.53 A.4.1.1.35.a
11 Pek kolom praktis 11 x 11 cm M 103,231.89 A.4.1.1.35
12 Pek dinding beton tebal 12 cm M3 6,956,464.90 A.4.1.1.33.a
13 Pek dinding beton tebal 10 cm M3 1,878,922.65 A.4.1.1.33.ab
14 Pekerjaan pemasangan keramik ( 30x30 ) cm M2 276,818.49 A.4.4.3.35
15 Pekerjaan pemasangan Batu Tempel / alam M2 196,138.69 A.4.4.3.35a
16 Pekerjaan pemasangan Batu Tempel hitam M2 207,534.69 A.4.4.3.35b
16 Pekerjaan pemasangan conblock M2 80,000.00 TMBHN
17 Pekerjaan pengaspalan jalan M2 80,000.00 TMBHN
PEKERJAAN PENGECATAN
1 Pengecatan bidang dinding baru cat tembok 3 kali cat/M2 M2 34,769.75 A.4.7.1.10
2 Pengecatan bidang kayu baru cat minyak 3 kali cat/M2 M2 43,124.77 A.4.4.2.3
3 Pekerjaan meni kayu M2 43,336.60 A.4.7.1.7
PEKERJAAN SANITASI
2 Pas pipa PVC 3" M' 55,646.17 P1
1 Pas pipa PVC 4" M' 81,499.77 P2
3 Pas pipa PVC 6" M' 151,851.50 P3
4 Pas pipa PVC 8" M' 241,233.18 P4
5 Pas pipa PVC 10" M' 404,863.39 P5
ANALISA HARGA SATUAN PEKERJAAN
PEKERJAAN PIPING
JUMLAH BAHAN
C PERALATAN
JUMLAH BAHAN
C PERALATAN
JUMLAH BAHAN
C PERALATAN
A. A.4.1.1.4 1 m3 beton mutu, f’c = 7.4 MPa (K100), slump (12±2) cm, w/c = 0,87 (Menggunakan Molen)
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
φ
A.4.4.2.3. Pengecatan bidang kayu baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.070 134,325.00 9,402.75
Tukang cat L.02 OH 0.009 154,722.50 1,392.50
Kepala tukang L.03 OH 0.006 169,647.50 1,068.78
Mandor L.04 OH 0.003 182,085.00 546.26
JUMLAH TENAGA KERJA 12,410.29
B BAHAN
Cat Menie Kg 0.200 25,938.00 5,187.60
Dempul Tembok 0.150 15,000.00 2,250.00
Cat dasar Kg 0.170 26,730.00 4,544.10
Cat minyak Kg 0.260 63,954.00 16,628.04
Kuas bh 0.010 13,860.00 138.60
Tinner (Pengencer ) ltr 0.030 25,938.00 778.14
Ampelas Kg 0.200 5,940.00 1,188.00
JUMLAH HARGA BAHAN 30,714.48
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 43,124.77
E Overhead & Profit 10% x D
F Harga Satuan Pekerjaan (D+E) 43,124.77
A BAHAN PENGISI
1 Tanah Urug ( Timbunan Biasa) M3 145,332.00 85.49 145,332.00
2 Pasir Urug M3 229,680.00 135.11 229,680.00
3 Pasir beton M3 269,280.00 192.34 269,280.00
4 Pasir pasang M3 262,350.00 262,350.00
5 Pasir pasang M3 262,350.00 262,350.00
6 Batu Kali / Belah M3 183,150.00 126.31 183,150.00
7 Batu pecah uk. 2 - 3 cm M3 259,875.00 179.22 259,875.00
8 Semen (50 Kg) zak 77,863.50 1,557.27 77,863.50
9 Semen Putih (40 Kg) kg 3,905.55 ###
97.64 3,905.55
10 Sirtu M3 140,778.00 140,778.00
B. BAHAN KAYU
1 Balok kayu Kls II ketam M 3
6,079,986.00 14,591.97 6,079,986.00
2 Papan Kayu Camp. (Klas III) M3 4,729,626.00 4,729,626.00
3 Kayu kelas IV M3 3,356,496.00 3,356,496.00
4 Papan Kayu Camp. (Klas IV) M3 3,356,496.00 3,356,496.00
3 Kayu Bulat O 8 - 12 Cm / 4 M1 (dolken)
Btg 34,650.00 34,650.00
D. BAHAN FINISHING CAT
1 Cat Tembok Kg 25,938.00 25,938.00
2 Cat Dasar Kg 26,730.00 26,730.00
3 Cat Meni Kayu Kg 25,938.00 25,938.00
4 Cat Minyak Kg 63,954.00 63,954.00
5 Pelamur Air Kg 14,196.60 14,196.60
6 Ampelas Bh 5,940.00 5,940.00
7 Kuas Bh 13,860.00 13,860.00
8 Thinner Ltr 25,938.00 25,938.00
E. BAHAN BAKAR
1 Minyak Bekisting Ltr 34,650.00 34,650.00
F. BAHAN PENUTUP LANTAI
1 Keramik 30 x30 ( Polos ) Kpg 6,867.00 6,867.00
2 Bata Merah Bh 1,188.00 1,188.00
Batu Tempel / alam Kpg 7,425.00 7,425.00
Batu Tempel hitam m2 15,840.00 15,840.00
m2 24,750.00 24,750.00
G. BAHAN PENGGANTUNG
1 Paku Biasa Uk. 2" - 4 " Kg 24,750.00 24,750.00
2 Paku Sekrup Kg 21,780.00 21,780.00
H BAHAN LAIN-LAIN
1 Triplek Uk 9 mm Lbr 163,350.00 163,350.00
2 Besi Beton Kg 11,880.00 11,880.00
3 Besi profil Kg 17,820.00 17,820.00
4 Besi siku Kg 17,820.00 17,820.00
5 Angkur Baja M-19 btg 67,827.38 67,827.38
6 Kawat BIndrat Kg 25,740.00 25,740.00
7 Kawat Las Kg 31,407.75 31,407.75
8 Genteng Zincalume Metal Roof Lbr 120,483.00 120,483.00
9 Nok Metal Roof Lbr 64,845.00 64,845.00
10 Listplank GRC Lbr 69,547.50 69,547.50
11 Kabel NYA 2x2,5 m' 44,550.00 44,550.00
12 Isolator bh 31,680.00 31,680.00
13 Lampu Philip bh 66,825.00 66,825.00
14 Stop Kontak bh 26,730.00 26,730.00
NO JENIS BAHAN SAT TOTAL HARGA KETERANGAN TOTAL HARGA
I PEKERJAAN PERSIAPAN
1 Direksi Keet, Pondok Kerja dan Gudang Bahan 30.00 m2 105,295.88 3,158,876.25
2 Papan Nama Proyek 1.00 bh 188,300.00 188,300.00
3 Pembersihan Lapangan 150.75 m2 239,850.00 36,157,387.50
39,504,563.75
II PEKERJAAN PIPING
1 Pekerjaan galian tanah dalam 50 - 90 cm 117.00 m3 1383750 161,898,750.00
2 Pekerjaan pemasangan pipa SR PVC 3 inchi 2,498.00 m1 109,511.47 273,559,650.50
3 Pekerjaan pemasangan pipa Sub Line PVC 4 inchi 879.00 m1 76,266.75 67,038,473.25
4 Pekerjaan pemasangan pipa Sub Mainline PVC 6 inchi 1,209.39 m1 - -
5 Pekerjaan pemasangan pipa Mainline PVC 8 inchi 146.00 m1 241,233.18 35,220,043.92
6 Pekerjaan pemasangan pipa Feeder PVC 10 inchi 117.00 m1 1,383,750.00 161,898,750.00
7 Pekerjaan urugan tanah kembali - m3 - -
8 Restorasi halaman rumah warga 23.30 m1 105,295.88 2,452,972.70
702,068,640.37
### #REF!
### #REF!
### #REF! 0.36 #REF! 1,016,813.39 369,103.26
### #REF! 0.36 #REF! 910.43 330.48
### #REF! #REF! #REF! 121,268.61 #REF!
### #REF!
### #REF! 0.27 #REF! 910.43 246.50
### #REF! #REF! #REF! 80,000.00 #REF!
#REF!
III PEKERJAAN BAK KONTROL 1
1 Galian Tanah 23.30 m3 50,915.70 1,186,132.21
2 Pekerjaan bobok lantai 4.99 m3 1,016,813.39 5,075,932.42
3 Pek. Dinding Bak cor Beton bertulang, tebal : 10cm 0.34 m2 1,878,922.65 638,833.70
4 Pek. Rabat Beton Lantai, tebal : 10cm 0.79 m2 1,552,320.35 1,226,333.08
5 Acian 3.52 m2 #REF! #REF!
6 Pasir urug 5cm 0.04 m3 - -
7 Plat Dak Tutup bak cor beton bertulang, t : 10cm, wiremesh 1 layer M8-150 0.05 m3 1,444,884.67 70,799.35
8 Elbow inlet + outlet( L-45°) PVC 6" 2.00 bh - -
9 Tutup manhole Cor Beton bertulang 1.00 pcs 1,016,813.39 1,016,813.39
#REF!
1 PEKERJAAN BAK KONTROL 2
2 Galian Tanah 23.30 m3 105,295.88 2,452,972.70
3 Pekerjaan bobok lantai 1.20 m3 1,016,813.39 1,220,176.06
4 Pek. Dinding Bak cor Beton bertulangan,tebal : 10cm 0.11 m2 1,878,922.65 202,923.65
5 Pek. Rabat Beton Lantai, tebal :10cm 1.15 m2 1,552,320.35 1,785,168.40
6 Acian 4.84 m2 #REF! #REF!
7 Pasir urug 5cm 0.50 m3 - -
8 Plat Dak Tutup bak cor beton bertulang, t : 10cm, wiremesh 1 layer M8-150 0.08 m3 1,444,884.67 115,590.77
9 Elbow inlet + outlet( L-45°) PVC 6" 2.00 bh 1,383,750.00 2,767,500.00
10 Tutup manhole Baja Cor (Costums) 1.00 pcs 1,016,813.39 1,016,813.39
#REF!
V PEKERJAAN BAK SUMPIT ( 1 unit )
1 Pek. Bobok Beton Lantai Jalan, t : 30cm 0.36 m3 1,016,813.39 369,103.26
2 Galian Tanah 2.42 m3 50,915.70 123,216.00
3 Pek. Dinding Bak cor beton bertulang, t : 10cm, wiremesh 1 layer M8-150 1.08 m2 1,878,922.65 2,034,873.23
4 Pek. Rabat Benton Lantai, tebal : 15cm 0.18 m2 1,016,813.39 184,551.63
5 Acian 7.73 m2 #REF! #REF!
6 Pasir urug 10cm 0.07 m3 - -
7 Lantai kerja, t : 5cm 0.06 m3 - -
8 Plat Penutup Dak Beton Bertulang, t : 10cm 0.04 bh 105,295.88 4,475.07
9 Tutup plat besi ( manhole ) 1.00 pcs 1,552,320.35 1,552,320.35
#REF!
VI PEKERJAAN BAK GRASE TRAP
1 Pek. Bobok Beton Lantai Jalan, t :30cm 0.45 m3 1,016,813.39 452,990.36
2 Galian Tanah 0.36 m3 #REF! #REF!
3 Pek. Dinding Bak cor beton bertulang, t : 10cm, wiremesh 1 layer M8-150 2.23 m2 105,295.88 234,546.56
4 Pek. Rabat Benton Lantai, tebal : 15cm 0.23 m2 1,878,922.65 435,158.49
5 Acian 0.81 m2 133,265.31 107,891.60
7 Pasir urug 10 cm 0.07 m3 - -
8 Lantai kerja, t : 5cm 0.05 m3 - -
9 Plat Penutup Dak Beton Bertulang, t : 10cm 0.11 bh 500,000.00 54,625.00
10 Elbow (L) PVC 4" 2.00 bh #REF! #REF!
11 Reduser Shock PVC 4" - 6" 1.00 bh #REF! #REF!
12 Elbow ( T ) PVC 6" 1.00 bh #REF! #REF!
13 Tutup plat besi ( manhole ) 2.00 pcs 1,552,320.35 3,104,640.70
#REF!
VII PEKERJAAN BAK EQUALISASI
1 Galian Tanah 97.68 m3 5,529,327.37 540,111,609.30
2 Urugan sirtu t = 15 cm 4.09 m2 105,295.88 430,554.83
3 Pasir urug t = 10 cm 2.73 m2 500,000.00 1,363,000.00
4 Lantai kerja t = 5 cm 1.36 m2 - -
5 Lantai bak cor beton bertulang 5.45 m2 105,295.88 573,862.52
6 Dinding beton bertulang 4.09 m3 207,066.98 846,696.86
7 Balok beton 15/20cm 0.62 m3 7,256,082.74 4,498,771.30
8 Acian 1.00 bh 5,529,327.37 5,529,327.37
9 Tutup plat baja rangka siku L.50.50.5 6.00 bh 6,500,000.00 39,000,000.00
592,353,822.18
### #REF!
### #REF! #REF! m³ #REF! #REF!
### #REF! #REF! m³ #REF! #REF!
### #REF! #REF! m³ #REF! #REF!
### #REF! - m³ - -
### #REF! 64.40 bh 105,295.88 6,781,054.35
### #REF! 1.01 kg 365,254.35 368,176.38
### #REF! 55.78 kg 76,266.75 4,253,854.25
### #REF! 8.62 m² 5,529,327.37 47,684,919.25
### #REF! 56.00 m² 67,827.38 3,798,333.00
#REF!
### #REF!
### #REF! #REF! m³ #REF! #REF!
### #REF! #REF! m³ #REF! #REF!
### #REF! #REF! m³ #REF! #REF!
### #REF! - m³ - -
### #REF! 162.00 m³ 172,058.47 27,873,472.14
### #REF! 2.36 m³ 5,529,327.37 13,063,035.91
### #REF! 52.50 m² 768,509.13 40,346,729.19
### #REF! 2.36 m¹ 133,265.31 314,839.30
#REF!