NO JENIS PEKERJAAN VOLUME SAT


( Rp )
1 2 3 4 5

I PEKERJAAN TANAH DAN PONDASI


1 Galian tanah pondasi menerus 57.730 m3 63,250.00
2 Galian tanah pondasi setempat 129.600 m3 92,710.00
3 Urugan pasir dibawah pondasi menerus 9.122 m3 439,300.00
4 Urugan tanah kembali pondasi menerus 0.117 m3 46,500.00
5 Pek. Urugan Tanah Peninggian Lantai 287.722 m3 407,250.00
6 Pek. Urugan pasir di bawah lantai 14.386 m3 439,300.00
TOTAL
JML HARGA
( Rp )
6

3,651,422.50
12,015,216.00
4,007,294.60
5,440.50
117,174,784.50
6,319,769.80
143,173,927.90
PERHITUNGAN VOLUME PEKERJAAN

No. Uraian Pekerjaan Volume Satuan Gambar


1 Pekerjaan Pondasi Footplat
a Pekerjaan Galian 129.6 m3 Volume Galian = (p x l x t) x Jumlah Pondasi Footplat
V = (1.5 x 1.5 x 2.4) x 24 titik
V = (1.5 x 1.5 x 2.4) x 24 titik
Luas Penampang = 129.6 m3

2 Pekerjaan Pondasi Menerus


a Pekerjaan Galian 57.73 m3 Panjang Galian Pondasi Penuh Menerus tipe 1
P = 1500 + 500 + 280 + 427.5 + 200 + 200 + 1650 + 107.5 + 127.5 + 200 + 200 + 300 + 300 + 300
P = 6292.5 cm
Luas Penampang = =pxl
0.8 x 0.35
0.28 m2
Volume Galian Pondasi Menerus = Luas Penampang x Panjang Galian
0.28 x 62.925
Volume = 17.619 m3

Panjang Galian Pondasi Penuh Menerus tipe 2


P = 300 cm
P= 3 m
Luas Penampang = =pxl TYPE 1
0.525 x 0.35
0.183 m2
Volume Galian Pondasi Menerus = Luas Penampang x Panjang Galian
0.183 x 3
Volume = 0.546 M3

Panjang Galian Pondasi Penuh Menerus tipe 3


P = 300 + 427.5
P = 7.275 m
Luas Penampang = =pxl
(0.3+0.3+0.3) x (0.35)
1.25 m2
Volume Galian Pondasi Menerus = Luas Penampang x Panjang Galian
1.25 x 7.275
Volume = 9.093 M3

Panjang Galian Pondasi Penuh Menerus tipe 4


P = 300 + 300 + 300 + 300 + 1500 + 100 + 100
P = 29 m
Luas Penampang = =pxl
0.8 x 0.01
0.008 m2
Volume Galian Pondasi Menerus = Luas Penampang x Panjang Galian
0.008 x 29
Volume = 0.232 M3

Panjang Galian Pondasi Penuh Menerus tipe 5


P = (300 x 4) + (300x2) + (300x2) + (300x4)
P = 36 m
Luas Penampang = =pxl
0.3 x 2.8
0.84 m2
Volume Galian Pondasi Menerus = Luas Penampang x Panjang Galian
0.84 x 36
Volume = 30.24 M3

VOLUME TOTAL = Tipe 1 + Tipe 2 + Tipe 3 + Tipe 4 + Tipe 5


VOLUME TOTAL = 17.619 + 0.546 + 9.093 + 0.232 + 30.24
=57.73 m3

b Urugan Pasir dibawah Pondasi Menerus 9.122 m3 Urugan Pasir dibawah Pondasi Tipe 1
Volume = Luas penampang x panjang
Volume = (0.05 x 0.80) x 62.925
Volume = 2.517 m3

Urugan Pasir dibawah Pondasi Tipe 2


Volume = Luas penampang x panjang
Volume = (0.05 x 0.52) x 3
Volume = 0.078 m3
Urugan Pasir dibawah Pondasi Tipe 3
Volume = Luas penampang x panjang
Volume = (0.05 x 0.90) x 7.275
Volume = 0.3273 m3

Urugan Pasir dibawah Pondasi Tipe 4


Volume = Luas penampang x panjang
Volume = (0.05 x 0.80) x 29
Volume = 1.16 m3

Urugan Pasir dibawah Pondasi Tipe 5


Volume = Luas penampang x panjang
Volume = (0.05 x 2.80) x 36
Volume = 5.04 m3

VOLUME TOTAL = Tipe 1 + Tipe 2 + Tipe 3 + Tipe 4 + Tipe 5


VOLUME TOTAL = 2.517 + 0.078 + 0.3273 + 1.16 + 5.04
=9.122 m3

c Urugan Tanah Kembali 0.117 m3 Urugan Tanah PondasiMenerus tipe 1


V = Luas Penampang x Panjang Pondasi x 2 sisi
V = (a+b)/2 x t x p x 2 sisi
V = (0.0287+0.01) / 2 x 0.0475 x 62.925 x 2
V = 0.115 m3

Urugan Tanah Pondasi Penuh Menerus tipe 2


V = Luas Penampang x Panjang Pondasi
V = (a+b)/2 x t x p x 2 sisi
V = (0.0287+0.01) / 2 x 0.0475 x 3
V = 0.002 m3

VOLUME TOTAL = Volume Tipe 1 + Volume Tipe 2


= 0.115 + 0.002
= 0.117 m3

d Urugan Tanah Peninggi Lantai Urugan Tanah Peninggi Lantai Luas 1


V=pxlxt
V = ((1 x 3)+(20x3)) x 0.85
V = 53.55 m3

Urugan Tanah Peninggi Lantai Luas 2


V=pxlxt
V = (2 x 3) x 0.80
V = 4.8 m3

Urugan Tanah Peninggi Lantai Luas 3


V=pxlxt
V = ((15 x 3)+(15x3)+(1x5)) x 1.3
V = 117 m3

Urugan Tanah Peninggi Lantai Luas 4


V=pxlxt
V = ((15x15)+(3x2.35)-(1x5)+(2x3)+(5x2) x 0.45
V = 109.372 m3

VOLUME TOTAL = 287.722 m3

e Urugan Pasir dibawah Lantai V = Luas Total Tanah Peninggi Lantai x tinggi
V = 287.722 x 0.05
V = 14.386 M3