3,651,422.50
12,015,216.00
4,007,294.60
5,440.50
117,174,784.50
6,319,769.80
143,173,927.90
PERHITUNGAN VOLUME PEKERJAAN
b Urugan Pasir dibawah Pondasi Menerus 9.122 m3 Urugan Pasir dibawah Pondasi Tipe 1
Volume = Luas penampang x panjang
Volume = (0.05 x 0.80) x 62.925
Volume = 2.517 m3
e Urugan Pasir dibawah Lantai V = Luas Total Tanah Peninggi Lantai x tinggi
V = 287.722 x 0.05
V = 14.386 M3