HARGA PERKIRAAN SENDIRI (HPS)

PROGRAM : Program Peningkatan Cakupan Sistem Penyediaan Air Minum


KEGIATAN : Pengembangan Jaringan Pipa di IKK Kurun (DAK)
PEKERJAAN: Pengembangan Jaringan Pipa di IKK Kurun
LOKASI : Kec. Kurun

No. Uraian Kegiatan Analisa Volume Harga Satuan


A. PEKERJAAN PENDAHULUAN
1. Pekerjaan Mobilisasi 1 Keg 500,000.00
TOTAL A.1. (RP.)

B. PENGADAAN DAN PEMASANGAN PIPA DISTRIBUSI

B.I PEKERJAAN PENGADAAN PIPA


1. Pipa HDPE 100 SDR 13,6 , Ø 110 mm Ls - m 265,466.67
2. Pipa HDPE 90 SDR 13,6 , Ø 90 mm Ls 989.00 m 178,200.00
3. Reducer Tee dia 6" x 3 " Ls - Bh 763,670.00
4. Tee 4" x 3 " Ls 3.00 Bh 535,680.00
5. Reducer 6 " x 4 " Ls - Bh 600,170.00
6. Dop Dia. 3 " Ls 3.00 Bh 90,480.00
7. Dop Dia. 4 " Ls - Bh 210,045.00
8. Bend 90 0 Dia 4" Ls - Bh 630,600.00
9. Bend 90 Dia 6"
0
Ls - Bh Err:509
10. Gate Valve 110 mm Ls - Bh 3,163,440.00
11. Stub Flange HDPE 110 mm Ls - Bh Err:509
12. Karet Packing dia. 110 mm Ls - Bh Err:509
13. Besi Plat Penutup Box Valve (Lengkap) Ls - Bh 300,000.00
15. Mur Baut Ls - Bh 150,000.00

TOTAL B.1. (RP.)


B.2 PEKERJAAN PEMASANGAN PIPA
1. Galian Pipa HDPE 100 SDR 13,6 , Ø 110 mm A.2.3.1.4.1 - M3 -
2. Galian Pipa HDPE 90 SDR 13,6 , Ø 90 mm A.2.3.1.4.2 247.25 M 3
-
3. Pengurugkan Kembali Galian Pipa HDPE 100 SDR A.2.3.1.9 - M3 1,852.85
13,6 , Ø 110 mm
4. Pengurugan Kembali Galian Pipa HDPE 90 SDR 13,6 A.2.3.1.9 244.60 M3 1,852.85
, Ø 90 mm
5. Pemasangan Pipa HDPE 100 SDR 13,6 , Ø 110 mm A.8.4.1.18 - M 207,936.00
6. Pemasangan Pipa HDPE 90 SDR 13,6 , Ø 90 mm A.8.4.1.17 989.00 m 125,062.88
7. Pemotongan Pipa HDPE 100 SDR 13,6 , Ø 110 mm A.8.4.2.18 3.00 Bh 16,187.63
8. Pemasangan Reducer Tee 110 mm x 90 mm A.8.4.3.15 - Bh 1,728,162.00
9. Pemasangan Tee 110 mm x 90 mm A.8.4.3.15 3.00 Bh 1,728,162.00
10. Pemasangan Reducer Tee 150 mm x 110 mm A.8.4.3.15 - bh 1,728,162.00
11. Pemasangan Dop Dia. 90 mm Ls 3.00 bh 20,000.00
12. Pemasangan Dop Dia. 110 mm Ls - Bh 20,000.00
13. Pemasangan Bend 90 0 Dia 110 mm Ls - Bh 1,728,162.00
14. Pemasangan Bend 90 0 Dia 160 mm Ls - Bh 20,000.00
15. Pemasangan Gate Valve Ø 110 mm A.8.4.3.1a 0 Bh 248,325.75
16. Cor Box Valve A.4.1.1.2 - m3 1,033,585.29
17. Cor Patok Penanda End Pipa A.4.1.1.2 - m3 1,033,585.29
TOTAL B.2 (Rp.)

B.3 PEKERJAAN PENGETESAN PIPA


1 Pengetesan Pipa HDPE Ø 110 mm A.8.4.5.3 - m 1,993.28
2 Pengetesan Pipa HDPE Ø 90 mm A.8.4.5.3 989.00 m 1,970.78
TOTAL B.3 (RP.)
TOTAL B. (Rp.)

C. PENGADAAN DAN PEMASANGAN SR BERIKUT


ASSESORIESNYA

C.2 PENGADAAN SR DAN ACCESORIESNYA


1 Clamp Sadle PVC Ø 4'' x 1/2'' Ls Bh 140,200.00
2 Pipa HDPE Ø 1/2'' (@ 6 M') Ls M' 6,675.00
3 Pipa PVC Ø 1/2'' AW (sambungan) Ls M' 4,500.00
4 Water Meter Ø 1/2'' Ls Bh 264,000.00
5 Box Meter Ls Bh 65,000.00
6 Stop Kran Ø 1/2'' Ls Bh 46,200.00
7 Atap Kran Ø 1/2'' Ls Bh 23,200.00
8 Famale Elbow PE Ø 1/2'' Ls Bh 7,950.00
9 Elbow PE Ø 1/2'' Ls Bh 4,300.00
10 Knee Ls Bh 5,600.00
11 Fouchet Elbow PVC Ø 1/2'' Ls Bh 4,300.00
12 Double Nepple GI Ø 1/2'' Ls Bh 4,600.00
13 Lem Pipa PVC Ls Bh 15,000.00
14 Seltif Ls Bh 8,000.00
15 Cor Dudukan SR (Sambungan Rumah) A.4.1.1.2 m3 1,033,585.29
Total C.1 (Rp.)
C.2 PEMASANGAN SR BERIKUT ACCESORIESNYA
1. Pemasangan SR Berikut Accesoriesnya Ls 25.00 Unit 65,000.00
Total C.2 (Rp.)
Total C (Rp.)
Total A+ B+ C (Rp.)

REKAPITULASI :

A. PEKERJAAN PENDAHULUAN ............................................


B. PENGADAAN DAN PEMASANGAN PIPA DISTRIBUSI
B.I PEKERJAAN PENGADAAN PIPA ............................................
B.2 PEKERJAAN PEMASANGAN PIPA ............................................
B.3 PEKERJAAN PENGETESAN PIPA ............................................
C. PENGADAAN DAN PEMASANGAN SR BERIKUT
ASSESORIESNYA
C.1 PENGADAAN SR DAN ACCESORIESNYA ............................................
C.2 PEMASANGAN SR BERIKUT ACCESORIESNYA ............................................
D. JUMLAH (RP.)
E. PPN 10 % X D (RP.)
F. TOTAL D + E (Rp.)

Terbilang : # TIGA RATUS SEMBILAN PULUH LIMA JUTA LIMA RATUS RIBU RUPIAH #

Kuala Kurun, April 2018

Kepala Dinas Pekerjaan Umum


Kabupaten Gunung Mas
Selaku PA/PPK

CHAMPILI, ST, MT
Pembina TK. I
NIP. 19660830 199803 1 002
Total Harga

500,000.00
500,000.00

-
176,239,800.00
-
1,607,040.00
-
271,440.00
-
-
Err:509
-
Err:509
Err:509
-
-

Err:509

-
-
-

453,201.45

-
123,687,183.38
48,562.88
-
5,184,486.00
-
60,000.00
-
-
-
-
-
-
129,433,433.70

-
1,949,096.48
260,815,963.88
Err:509

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
1,625,000.00
1,625,000.00
1,625,000.00
Err:509

500,000.00

Err:509
129,433,433.70
260,815,963.88

-
1,625,000.00
Err:509
Err:509
Err:509

A RATUS RIBU RUPIAH #

la Kurun, April 2018

s Pekerjaan Umum
Kepala Dinas Pekerjaan Umum
en Gunung Mas Kabupaten Gunung Mas
ku PA/PPK Selaku PA/PPK

PILI, ST, MT CHAMPILI, ST, MT


mbina TK. I Pembina TK. I
830 199803 1NIP.
002 19660830 199803 1 002
HARGA PERKIRAAN SENDIRI (HPS)
PROGRAM : Program Peningkatan Cakupan Sistem Penyediaan Air Minum
KEGIATAN : Pengembangan Jaringan Pipa di IKK Kurun (DAK)
PEKERJAAN: Pengembangan Jaringan Pipa di IKK Kurun
LOKASI : Kec. Kurun

No. Uraian Kegiatan Analisa Volume Harga Satuan


A. PEKERJAAN PENDAHULUAN
1. Pekerjaan Mobilisasi 1 Keg 200,000.00
TOTAL A.1. (RP.)

B. PENGADAAN DAN PEMASANGAN PIPA DISTRIBUSI

B.I PEKERJAAN PENGADAAN PIPA


1. Pipa HDPE 100 SDR 13,6 , Ø 110 mm Ls 832.00 m 265,466.67
2. Pipa HDPE 90 SDR 13,6 , Ø 90 mm Ls 400.00 m 178,200.00
3. Reducer Tee dia 4" x 3 " Ls 1.00 Bh 763,670.00
4. Reducer Tee Dia 12 " x 4 " Ls 1.00 Bh
4. Tee 6" x 3 " Ls - Bh 535,680.00
5. Reducer 6 " x 4 " Ls - Bh 600,170.00
6. Dop Dia. 3 " Ls 1.00 Bh 90,480.00
7. Dop Dia. 4 " Ls 1.00 Bh 210,045.00
8. Bend 90 0 Dia 4" Ls - Bh 630,600.00
9. Bend 90 Dia 6"
0
Ls - Bh Err:509
10. Gate Valve 110 mm Ls - Bh 3,163,440.00
11. Stub Flange HDPE 110 mm Ls - Bh Err:509
12. Karet Packing dia. 110 mm Ls - Bh Err:509
13. Besi Plat Penutup Box Valve (Lengkap) Ls - Bh 300,000.00
15. Mur Baut Ls - Bh 150,000.00
Air Valve Ls 1.00 Bh
TOTAL B.1. (RP.)
B.2 PEKERJAAN PEMASANGAN PIPA
1. Galian Pipa HDPE 100 SDR 13,6 , Ø 110 mm A.2.3.1.4.1 G 232.96 M3 -
2. Galian Pipa HDPE 90 SDR 13,6 , Ø 90 mm A.2.3.1.4.2 100.00 M3 -
3. Pengurugkan Kembali Galian Pipa HDPE 100 SDR A.2.3.1.9 161.12 M3 1,852.85
13,6 , Ø 110 mm
4. Pengurugan Kembali Galian Pipa HDPE 90 SDR 13,6 A.2.3.1.9 97.35 M3 1,852.85
, Ø 90 mm
5. Pemasangan Pipa HDPE 100 SDR 13,6 , Ø 110 mm A.8.4.1.18 832.00 M 207,936.00
6. Pemasangan Pipa HDPE 90 SDR 13,6 , Ø 90 mm A.8.4.1.17 400.00 m 125,062.88
7. Pemotongan Pipa HDPE 100 SDR 13,6 , Ø 110 mm A.8.4.2.18 1.00 Bh 16,187.63
8. Pemasangan Reducer Tee 160 mm x 90 mm A.8.4.3.15 1.00 Bh 1,728,162.00
9. Pemasangan Tee 110 mm x 100 mm A.8.4.3.15 - Bh 1,728,162.00
10. Pemasangan Reducer Tee 300 mm x 110 mm A.8.4.3.15 1.00 bh 1,728,162.00
11. Pemasangan Dop Dia. 90 mm Ls 1.00 bh 20,000.00
12. Pemasangan Dop Dia. 110 mm Ls 1.00 Bh 20,000.00
13. Pemasangan Bend 90 0 Dia 110 mm Ls - Bh 1,728,162.00
14. Pemasangan Bend 90 0 Dia 160 mm Ls - Bh 20,000.00
15. Pemasangan Gate Valve Ø 110 mm A.8.4.3.1a 0 Bh 248,325.75
16. Cor Box Valve A.4.1.1.2 - m3 1,033,585.29
17. Cor Patok Penanda End Pipa A.4.1.1.2 - m3 1,033,585.29
TOTAL B.2 (Rp.)

B.3 PEKERJAAN PENGETESAN PIPA


1 Pengetesan Pipa HDPE Ø 110 mm A.8.4.5.3 832.00 m 1,993.28
2 Pengetesan Pipa HDPE Ø 90 mm A.8.4.5.3 400.00 m 1,970.78

TOTAL B.3 (RP.)


TOTAL B. (Rp.)

C. PENGADAAN DAN PEMASANGAN SR BERIKUT


ASSESORIESNYA

C.2 PENGADAAN SR DAN ACCESORIESNYA


1 Clamp Sadle PVC Ø 3'' x 1/2'' Ls Bh 140,200.00
2 Pipa HDPE Ø 1/2'' (@ 6 M') Ls M' 6,675.00
3 Pipa PVC Ø 1/2'' AW (sambungan) Ls M' 4,500.00
4 Water Meter Ø 1/2'' Ls Bh 264,000.00
5 Box Meter Ls Bh 65,000.00
6 Stop Kran Ø 1/2'' Ls Bh 46,200.00
7 Atap Kran Ø 1/2'' Ls Bh 23,200.00
8 Famale Elbow PE Ø 1/2'' Ls Bh 7,950.00
9 Elbow PE Ø 1/2'' Ls Bh 4,300.00
10 Knee PVC 1/2" Ls Bh 5,600.00
11 Fouchet Elbow PVC Ø 1/2'' Ls Bh 4,300.00
12 Double Nepple GI Ø 1/2'' Ls Bh 4,600.00
13 Lem Pipa PVC Ls Bh 15,000.00
14 Seltif Ls Bh 8,000.00
15 Cor Dudukan SR (Sambungan Rumah) A.4.1.1.2 m3 1,033,585.29
Total C.1 (Rp.)
C.2 PEMASANGAN SR BERIKUT ACCESORIESNYA
1. Pemasangan SR Berikut Accesoriesnya Ls - Unit 65,000.00
Total C.2 (Rp.)
Total C (Rp.)
Total A+ B+ C (Rp.)

REKAPITULASI :

A. PEKERJAAN PENDAHULUAN ............................................


B. PENGADAAN DAN PEMASANGAN PIPA DISTRIBUSI
B.I PEKERJAAN PENGADAAN PIPA ............................................
B.2 PEKERJAAN PEMASANGAN PIPA ............................................
B.3 PEKERJAAN PENGETESAN PIPA ............................................
C. PENGADAAN DAN PEMASANGAN SR BERIKUT
ASSESORIESNYA
C.1 PENGADAAN SR DAN ACCESORIESNYA ............................................
C.2 PEMASANGAN SR BERIKUT ACCESORIESNYA ............................................
D. JUMLAH (RP.)
E. PPN 10 % X D (RP.)
F. TOTAL D + E (Rp.)

Terbilang : # TIGA RATUS SEMBILAN PULUH LIMA JUTA LIMA RATUS RIBU RUPIAH #

Kuala Kurun, April 2018

Kepala Dinas Pekerjaan Umum


Kabupaten Gunung Mas
Selaku PA/PPK

CHAMPILI, ST, MT
Pembina TK. I
NIP. 19660830 199803 1 002
Total Harga

200,000.00
200,000.00

220,868,266.67
71,280,000.00
763,670.00
-
-
-
90,480.00
210,045.00
-
Err:509
-
Err:509
Err:509
-
-

Err:509

-
-
298,524.94

180,369.59

173,002,752.00
50,025,150.00
16,187.63
1,728,162.00
-
1,728,162.00
20,000.00
20,000.00
-
-
-
-
-
227,019,308.15

1,658,404.80
788,310.00

456,485,331.10
Err:509

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Err:509

200,000.00

Err:509
227,019,308.15
456,485,331.10

-
-
Err:509
Err:509
Err:509

RATUS RIBU RUPIAH #

urun, April 2018

Pekerjaan Umum
Kepala Dinas Pekerjaan Umum
n Gunung Mas Kabupaten Gunung Mas
Selaku PA/PPK

ILI, ST, MT CHAMPILI, ST, MT


Pembina TK. I
30 199803 1 002
NIP. 19660830 199803 1 002
HARGA PERKIRAAN SENDIRI (HPS)
PROGRAM : Program Peningkatan Cakupan Sistem Penyediaan Air Minum
KEGIATAN : Pengembangan Jaringan Pipa di IKK Kurun (DAK)
PEKERJAAN: Pengembangan Jaringan Pipa di IKK Kurun
LOKASI : Kec. Kurun

No. Uraian Kegiatan Analisa Volume Harga Satuan


A. PEKERJAAN PENDAHULUAN
1. Pekerjaan Mobilisasi 1 Keg 200,000.00
TOTAL A.1. (RP.)

B. PENGADAAN DAN PEMASANGAN PIPA DISTRIBUSI

B.I PEKERJAAN PENGADAAN PIPA


1. Pipa HDPE 100 SDR 13,6 , Ø 110 mm Ls 832.00 m 265,466.67
2. Pipa HDPE 90 SDR 13,6 , Ø 90 mm Ls 400.00 m 178,200.00
3. Reducer Tee dia 4" x 3 " Ls 1.00 Bh 763,670.00
4. Reducer Tee Dia 12 " x 4 " Ls 1.00 Bh
4. Tee 6" x 3 " Ls - Bh 535,680.00
5. Reducer 6 " x 4 " Ls - Bh 600,170.00
6. Dop Dia. 3 " Ls 1.00 Bh 90,480.00
7. Dop Dia. 4 " Ls 1.00 Bh 210,045.00
8. Bend 90 0 Dia 4" Ls - Bh 630,600.00
9. Bend 90 Dia 6"
0
Ls - Bh Err:509
10. Gate Valve 110 mm Ls - Bh 3,163,440.00
11. Stub Flange HDPE 110 mm Ls - Bh Err:509
12. Karet Packing dia. 110 mm Ls - Bh Err:509
13. Besi Plat Penutup Box Valve (Lengkap) Ls - Bh 300,000.00
15. Mur Baut Ls - Bh 150,000.00
Air Valve Ls 1.00 Bh
TOTAL B.1. (RP.)
B.2 PEKERJAAN PEMASANGAN PIPA
1. Galian Pipa HDPE 100 SDR 13,6 , Ø 110 mm A.2.3.1.4.1 G 232.96 M3 -
2. Galian Pipa HDPE 90 SDR 13,6 , Ø 90 mm A.2.3.1.4.2 100.00 M3 -
3. Pengurugkan Kembali Galian Pipa HDPE 100 SDR A.2.3.1.9 161.12 M3 1,852.85
13,6 , Ø 110 mm
4. Pengurugan Kembali Galian Pipa HDPE 90 SDR 13,6 A.2.3.1.9 97.35 M3 1,852.85
, Ø 90 mm
5. Pemasangan Pipa HDPE 100 SDR 13,6 , Ø 110 mm A.8.4.1.18 832.00 M 207,936.00
6. Pemasangan Pipa HDPE 90 SDR 13,6 , Ø 90 mm A.8.4.1.17 400.00 m 125,062.88
7. Pemotongan Pipa HDPE 100 SDR 13,6 , Ø 110 mm A.8.4.2.18 1.00 Bh 16,187.63
8. Pemasangan Reducer Tee 160 mm x 90 mm A.8.4.3.15 1.00 Bh 1,728,162.00
9. Pemasangan Tee 110 mm x 100 mm A.8.4.3.15 - Bh 1,728,162.00
10. Pemasangan Reducer Tee 300 mm x 110 mm A.8.4.3.15 1.00 bh 1,728,162.00
11. Pemasangan Dop Dia. 90 mm Ls 1.00 bh 20,000.00
12. Pemasangan Dop Dia. 110 mm Ls 1.00 Bh 20,000.00
13. Pemasangan Bend 90 0 Dia 110 mm Ls - Bh 1,728,162.00
14. Pemasangan Bend 90 0 Dia 160 mm Ls - Bh 20,000.00
15. Pemasangan Gate Valve Ø 110 mm A.8.4.3.1a 0 Bh 248,325.75
16. Cor Box Valve A.4.1.1.2 - m3 1,033,585.29
17. Cor Patok Penanda End Pipa A.4.1.1.2 - m3 1,033,585.29
TOTAL B.2 (Rp.)

B.3 PEKERJAAN PENGETESAN PIPA


1 Pengetesan Pipa HDPE Ø 110 mm A.8.4.5.3 832.00 m 1,993.28
2 Pengetesan Pipa HDPE Ø 90 mm A.8.4.5.3 400.00 m 1,970.78

TOTAL B.3 (RP.)


TOTAL B. (Rp.)

C. PENGADAAN DAN PEMASANGAN SR BERIKUT


ASSESORIESNYA

C.2 PENGADAAN SR DAN ACCESORIESNYA


1 Clamp Sadle PVC Ø 3'' x 1/2'' Ls Bh 140,200.00
2 Pipa HDPE Ø 1/2'' (@ 6 M') Ls M' 6,675.00
3 Pipa PVC Ø 1/2'' AW (sambungan) Ls M' 4,500.00
4 Water Meter Ø 1/2'' Ls Bh 264,000.00
5 Box Meter Ls Bh 65,000.00
6 Stop Kran Ø 1/2'' Ls Bh 46,200.00
7 Atap Kran Ø 1/2'' Ls Bh 23,200.00
8 Famale Elbow PE Ø 1/2'' Ls Bh 7,950.00
9 Elbow PE Ø 1/2'' Ls Bh 4,300.00
10 Knee PVC 1/2" Ls Bh 5,600.00
11 Fouchet Elbow PVC Ø 1/2'' Ls Bh 4,300.00
12 Double Nepple GI Ø 1/2'' Ls Bh 4,600.00
13 Lem Pipa PVC Ls Bh 15,000.00
14 Seltif Ls Bh 8,000.00
15 Cor Dudukan SR (Sambungan Rumah) A.4.1.1.2 m3 1,033,585.29
Total C.1 (Rp.)
C.2 PEMASANGAN SR BERIKUT ACCESORIESNYA
1. Pemasangan SR Berikut Accesoriesnya Ls - Unit 65,000.00
Total C.2 (Rp.)
Total C (Rp.)
Total A+ B+ C (Rp.)

REKAPITULASI :

A. PEKERJAAN PENDAHULUAN ............................................


B. PENGADAAN DAN PEMASANGAN PIPA DISTRIBUSI
B.I PEKERJAAN PENGADAAN PIPA ............................................
B.2 PEKERJAAN PEMASANGAN PIPA ............................................
B.3 PEKERJAAN PENGETESAN PIPA ............................................
C. PENGADAAN DAN PEMASANGAN SR BERIKUT
ASSESORIESNYA
C.1 PENGADAAN SR DAN ACCESORIESNYA ............................................
C.2 PEMASANGAN SR BERIKUT ACCESORIESNYA ............................................
D. JUMLAH (RP.)
E. PPN 10 % X D (RP.)
F. TOTAL D + E (Rp.)

Terbilang : # TIGA RATUS SEMBILAN PULUH LIMA JUTA LIMA RATUS RIBU RUPIAH #

Kuala Kurun, April 2018

Kepala Dinas Pekerjaan Umum


Kabupaten Gunung Mas
Selaku PA/PPK

CHAMPILI, ST, MT
Pembina TK. I
NIP. 19660830 199803 1 002
Total Harga

200,000.00
200,000.00

220,868,266.67
71,280,000.00
763,670.00
-
-
-
90,480.00
210,045.00
-
Err:509
-
Err:509
Err:509
-
-

Err:509

-
-
298,524.94

180,369.59

173,002,752.00
50,025,150.00
16,187.63
1,728,162.00
-
1,728,162.00
20,000.00
20,000.00
-
-
-
-
-
227,019,308.15

1,658,404.80
788,310.00

456,485,331.10
Err:509

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Err:509

200,000.00

Err:509
227,019,308.15
456,485,331.10

-
-
Err:509
Err:509
Err:509

RATUS RIBU RUPIAH #

urun, April 2018

Pekerjaan Umum
Kepala Dinas Pekerjaan Umum
n Gunung Mas Kabupaten Gunung Mas
Selaku PA/PPK

ILI, ST, MT CHAMPILI, ST, MT


Pembina TK. I
30 199803 1 002
NIP. 19660830 199803 1 002
DAFTAR KUANTITAS DAN HARGA
PROGRAM : Program Sistem Penyediaan Air Minum
KEGIATAN : Pemasangan Pipa Distribusi dan SR di 20 Desa Pamsimas 2017-2018*)
PEKERJAAN : Pemasangan Pipa Distribusi dan SR di Desa Tumbang Korik
LOKASI : Desa Tumbang Korik

No. Uraian Kegiatan Analisa Volume


A. PEKERJAAN PENDAHULUAN
1. Pekerjaan Mobilisasi 1 Keg
2. Papan Nama Permanen 1 Bh
TOTAL A.1. (RP.)
B. PEKERJAAN PEMASANGAN DAN PENGETESAN PIPA
B.1 PEKERJAAN PEMASANGAN PIPA
1. Galian Pipa HDPE 63 SDR 13,6 , Diameter 2 Inch A.2.3.1.4.2 35.40 M3
2. Pengurukan Galian Pipa HDPE 63 SDR 13,6 , Diameter 2 Inch A.2.3.1.9 34.85 M3
3. Pemasangan Pipa HDPE 63 SDR 13,6 , Diameter 2 Inch A.8.4.1.17.a 177.00 M'
4. Pemasangan Tee HDPE Dia 2 Inch x 2 Inch A.8.4.3.15.e 1.00 Bh
5. Pemasangan Dop Dia. 2 Inch Ls 1.00 Bh
6. Cor Patok Penanda End Pipa A.4.1.1.2 0.01 m3
TOTAL B.2 (Rp.)
B.2 PEKERJAAN PENGETESAN PIPA
1. Pengetesan Pipa HDPE Diameter 2 Inch A.8.4.5.3 177.00 m

TOTAL B.2 (RP.)


TOTAL B. (Rp.)

C. PENGADAAN DAN PEMASANGAN SR BERIKUT


ASSESORIESNYA

C.1 PENGADAAN SR DAN ACCESORIESNYA


1 Clamp Sadle HDPE Ø 2'' x 1/2'' Ls 65.00 Bh
2 Pipa HDPE 1/2" (6 m) Ls 390.00 m
3 Pipa GIP Ø 1/2'' (sambungan) Ls 78.00 M'
4 Water Meter Ø 1/2'' (SNI) Ls 65.00 Bh
5 Box Meter Ls 65.00 Bh
6 Stop Kran Ø 1/2'' (Kuningan) Ls 65.00 Bh
7 Plug Kran 1/2" Brass Ls 65.00 Bh
8 Katup Searah 1/2" (Kuningan) Ls 65.00 Bh
9 Atap Kran Ø 1/2'' Kuningan Ls 65.00 Bh
10 Tee GI Dia. 1/2" Ls 65.00 Bh
11 Knee 900 GIP 1/2" Ls 325.00 Bh
12 Female Elbow PE 1/2" Ls 65.00 Bh
13 Dop GI 1/2" Ls 65.00 Bh
14 Seal Tape Ls 130.00 Bh
15 Double Nepel GI 1/2 Ls 130.00 Bh
13 Cor Dudukan SR (Sambungan Rumah) A.4.1.1.2 1.64 m3
Total V.1 (Rp.)
C.2 PEMASANGAN SR BERIKUT ACCESORIESNYA
1 Pemasangan SR Berikut Accesoriesnya Ls 65.00 Unit
Total V.2 (Rp.)
Total V (Rp.)
REKAPITULASI :
DAFTAR KUANTITAS DAN HARGA

A. PEKERJAAN PENDAHULUAN ............................................


A. PEKERJAAN MOBILISASI ............................................

B. PEKERJAAN PEMASANGAN DAN PENGETESAN PIPA ............................................


B.1 PEKERJAAN PEMASANGAN DAN PENGETESAN PIPA ............................................

C PENGADAAN DAN PEMASANGAN SR BERIKUT


ASSESORIESNYA
C.1 PENGADAAN SR DAN ACCESORIESNYA ............................................
C.2 PEMASANGAN SR BERIKUT ACCESORIESNYA ............................................
D JUMLAH (RP.)
E PPN 10 % X D (RP.)
F TOTAL D + E (Rp.)

Terbilang : ##Seratus Dua Puluh Sembilan Juta Delapan Ratus Lima Puluh Lima Rib

Kuala Kurun, 14 Agust

CV. KAHAYAN NUR


Pusat Kuala Kuru
AR KUANTITAS DAN HARGA

Harga Satuan Total Harga

3,000,000.00 3,000,000.00
2,000,000.00 2,000,000.00
OTAL A.1. (RP.) 5,000,000.00
A

45,471.38 1,609,686.68
11,580.30 403,556.40
125,062.88 22,136,128.88
200,997.00 200,997.00
202,054.59 202,054.59
1,033,585.29 11,627.83
OTAL B.2 (Rp.) 24,564,051.38

1,959.53 346,835.93

TOTAL B.2 (RP.) 346,835.93


24,910,887.30

140,100.00 9,106,500.00
22,000.00 8,580,000.00
43,700.00 3,408,600.00
420,750.00 27,348,750.00
74,250.00 4,826,250.00
73,000.00 4,745,000.00
51,600.00 3,354,000.00
83,200.00 5,408,000.00
48,300.00 3,139,500.00
12,700.00 825,500.00
11,600.00 3,770,000.00
48,000.00 3,120,000.00
48,000.00 3,120,000.00
5,000.00 650,000.00
9,300.00 1,209,000.00
1,033,585.29 1,693,012.70
Total V.1 (Rp.) 84,304,112.70

59,000.00 3,835,000.00
Total V.2 (Rp.) 3,835,000.00
Total V (Rp.) 88,139,112.70
REKAPITULASI :
DAFTAR KUANTITAS DAN HARGA

............................................ 5,000,000.00
............................................ 5,000,000.00

............................................ 24,910,887.30
............................................ 24,910,887.30

88,139,112.70

............................................ 84,304,112.70
............................................ 3,835,000.00
118,050,000.00
11,805,000.00
129,855,000.00

Dua Puluh Sembilan Juta Delapan Ratus Lima Puluh Lima Ribu Rupiah##

Kuala Kurun, 14 Agustus 2019

Penawar,
CV. KAHAYAN NURPITA Kepala Dinas Pekerjaan Umum
Pusat Kuala Kurun Kabupaten Gunung Mas
Selaku PA/PPK

E. IGINSYAH CHAMPILI, ST, MT


Direktur Pembina TK. I
NIP. 19660830 199803 1 002
HARGA PERKIRAAN SENDIRI (HPS)
PROGRAM : Program Peningkatan Cakupan Sistem Penyediaan Air Minum
KEGIATAN : Pengembangan Jaringan Pipa di IKK Kurun (DAK)
PEKERJAAN: Pengembangan Jaringan Pipa di IKK Kurun
LOKASI : Kec. Kurun

No. Uraian Kegiatan Analisa Volume Harga Satuan


A. PEKERJAAN PENDAHULUAN
1. Pekerjaan Mobilisasi 1 Keg 1,442,148.47
TOTAL A.1. (RP.)

B. PENGADAAN DAN PEMASANGAN PIPA DISTRIBUSI

B.I PEKERJAAN PENGADAAN PIPA


1. Pipa HDPE 100 SDR 13,6 , Ø 110 mm Ls - m 265,466.67
2. Pipa HDPE 90 SDR 13,6 , Ø 90 mm Ls 322.00 m 178,200.00
3. Pipa HDPE 63 SDR 13,6, Ø 50 mm LS 90.00 m 83,930.00
3. Tee dia 3" x 3 " Ls 2.00 Bh 763,670.00
4. Reducer Tee 3" x 2 " Ls 1.00 Bh 535,680.00
5. Reducer 6 " x 4 " Ls - Bh 600,170.00
6. Dop Dia. 3 " Ls 2.00 Bh 90,480.00
7. Dop Dia. 2 " Ls 1.00 Bh 210,045.00
8. Bend 90 0 Dia 4" Ls - Bh 630,600.00
9. Bend 90 Dia 6"
0
Ls - Bh Err:509
10. Gate Valve 110 mm Ls - Bh 3,163,440.00
11. Stub Flange HDPE 110 mm Ls - Bh Err:509
12. Karet Packing dia. 110 mm Ls - Bh Err:509
13. Besi Plat Penutup Box Valve (Lengkap) Ls - Bh 300,000.00
15. Mur Baut Ls - Bh 150,000.00

TOTAL B.1. (RP.)


B.2 PEKERJAAN PEMASANGAN PIPA
1. Galian Pipa HDPE 63 SDR 13,6 , Ø 50 mm A.2.3.1.4.1 G 14.40 M3 -
2. Galian Pipa HDPE 90 SDR 13,6 , Ø 90 mm A.2.3.1.4.2 51.52 M3 -
3. Pengurugkan Kembali Galian Pipa HDPE 63 SDR A.2.3.1.9 4.72 M3 1,852.85
13,6 , Ø 50 mm
4. Pengurugan Kembali Galian Pipa HDPE 90 SDR 13,6 A.2.3.1.9 48.87 M3 1,852.85
, Ø 90 mm
5. Pemasangan Pipa HDPE 63 SDR 13,6 , Ø 50 mm A.8.4.1.18 90.00 M 207,936.00
6. Pemasangan Pipa HDPE 90 SDR 13,6 , Ø 90 mm A.8.4.1.17 322.00 m 125,062.88
7. Pemotongan Pipa HDPE 90 SDR 13,6 , Ø 90 mm A.8.4.2.18 1.00 Bh 16,187.63
8. Pemasangan Reducer Tee 90 mm x 63 mm A.8.4.3.15 1.00 Bh 1,728,162.00
9. Pemasangan Tee 90 mm x 90 mm A.8.4.3.15 1.00 Bh 1,728,162.00
10. Pemasangan Reducer Tee 150 mm x 110 mm A.8.4.3.15 - bh 1,728,162.00
11. Pemasangan Dop Dia. 90 mm Ls 2.00 bh 20,000.00
12. Pemasangan Dop Dia. 63 mm Ls 1.00 Bh 20,000.00
13. Pemasangan Bend 90 0 Dia 110 mm Ls - Bh 1,728,162.00
14. Pemasangan Bend 90 0 Dia 160 mm Ls - 20,000.00
15. Pemasangan Gate Valve Ø 110 mm A.8.4.3.1a 0 Bh 248,325.75
16. Cor Box Valve A.4.1.1.2 - m3 1,033,585.29
17. Cor Patok Penanda End Pipa A.4.1.1.2 - m3 1,033,585.29
TOTAL B.2 (Rp.)

B.3 PEKERJAAN PENGETESAN PIPA


1 Pengetesan Pipa HDPE Ø 63 mm A.8.4.5.3 90.00 m 1,993.28
2 Pengetesan Pipa HDPE Ø 90 mm A.8.4.5.3 322.00 m 1,970.78

TOTAL B.3 (RP.)


TOTAL B. (Rp.)

C. PENGADAAN DAN PEMASANGAN SR BERIKUT


ASSESORIESNYA

C.2 PENGADAAN SR DAN ACCESORIESNYA


1 Clamp Sadle PVC Ø 4'' x 1/2'' Ls Bh 140,200.00
2 Pipa HDPE Ø 1/2'' (@ 6 M') Ls M' 6,675.00
3 Pipa PVC Ø 1/2'' AW (sambungan) Ls M' 4,500.00
4 Water Meter Ø 1/2'' Ls Bh 264,000.00
5 Box Meter Ls Bh 65,000.00
6 Stop Kran Ø 1/2'' Ls Bh 46,200.00
7 Atap Kran Ø 1/2'' Ls Bh 23,200.00
8 Famale Elbow PE Ø 1/2'' Ls Bh 7,950.00
9 Elbow PE Ø 1/2'' Ls Bh 4,300.00
10 Knee Ls Bh 5,600.00
11 Fouchet Elbow PVC Ø 1/2'' Ls Bh 4,300.00
12 Double Nepple GI Ø 1/2'' Ls Bh 4,600.00
13 Lem Pipa PVC Ls Bh 15,000.00
14 Seltif Ls Bh 8,000.00
15 Cor Dudukan SR (Sambungan Rumah) A.4.1.1.2 m3 1,033,585.29
Total C.1 (Rp.)
C.2 PEMASANGAN SR BERIKUT ACCESORIESNYA
1. Pemasangan SR Berikut Accesoriesnya Ls 25.00 Unit 65,000.00
Total C.2 (Rp.)
Total C (Rp.)
Total A+ B+ C (Rp.)

REKAPITULASI :

A. PEKERJAAN PENDAHULUAN ............................................


B. PENGADAAN DAN PEMASANGAN PIPA DISTRIBUSI
B.I PEKERJAAN PENGADAAN PIPA ............................................
B.2 PEKERJAAN PEMASANGAN PIPA ............................................
B.3 PEKERJAAN PENGETESAN PIPA ............................................
C. PENGADAAN DAN PEMASANGAN SR BERIKUT
ASSESORIESNYA
C.1 PENGADAAN SR DAN ACCESORIESNYA ............................................
C.2 PEMASANGAN SR BERIKUT ACCESORIESNYA ............................................
D. JUMLAH (RP.)
E. PPN 10 % X D (RP.)
F. TOTAL D + E (Rp.)

Terbilang : # TIGA RATUS SEMBILAN PULUH LIMA JUTA LIMA RATUS RIBU RUPIAH #

Kuala Kurun, April 2018

Kepala Dinas Pekerjaan Umum


Kabupaten Gunung Mas
Selaku PA/PPK

CHAMPILI, ST, MT
Pembina TK. I
NIP. 19660830 199803 1 002
HPS)

Total Harga

1,442,148.47
1,442,148.47

-
57,380,400.00
7,553,700.00
1,527,340.00
535,680.00
-
180,960.00
210,045.00
-
Err:509
-
Err:509
Err:509
-
-

-
-
8,739.26

90,543.52

18,714,240.00
40,270,245.75
16,187.63
1,728,162.00
1,728,162.00
-
40,000.00
20,000.00
-
-
-
-
-

179,394.75
634,589.55

63,430,264.45

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
1,625,000.00

TUS RIBU RUPIAH #

urun, April 2018

Pekerjaan Umum
Kepala Dinas Pekerjaan Umum
n Gunung Mas Kabupaten Gunung Mas
Selaku PA/PPK

ILI, ST, MT CHAMPILI, ST, MT


Pembina TK. I
30 199803 1 002
NIP. 19660830 199803 1 002
DAFTAR HARGA SATUAN DASAR UPAH

KUALA KURUN - KABUPATEN GUNUNG MAS

HARGA SATUAN
No. URAIAN SATUAN
(Rp.)

1 Mandor org/hr 145,000.00


2 Tukang Gali Tanah org/hr 130,000.00
3 Kepala Tukang Batu org/hr 140,000.00
4 Tukang Batu org/hr 130,000.00
5 Pembantu Tukang Batu org/hr 115,000.00
6 Kepala Tukang Kayu org/hr 140,000.00
7 Tukang Kayu org/hr 130,000.00
8 Pembantu Tukang kayu org/hr 115,000.00
9 Kepala Tukang Besi org/hr 140,000.00
10 Tukang Besi org/hr 130,000.00
11 Pembantu Tukang Besi org/hr 115,000.00
12 Kepala Tukang Pipa org/hr 140,000.00
13 Tukang Pipa org/hr 130,000.00
14 Pembantu Tukang Pipa org/hr 115,000.00
15 Operator org/hr 115,000.00
DAFTAR HARGA SATUAN DASAR BAHAN

KUALA KURUN - KABUPATEN GUNUNG MAS

HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)
BAHAN
1 Pasir Pasang m3 160,000.00
2 Koral /kerikil sungai m3 154,000.00
3 Batu Pecah 2-3 cm m3 850,000.00
4 Batu Belah m3 450,000.00
5 Semen PC 40 kg (Zak) Kg 68,000.00
6 Besi Beton kg 18,000.00
7 Kawat Beton kg 25,000.00
8 Balok Kayu Klas I m3 8,750,000.00
9 Balok Kayu Klas II m3 3,000,000.00
10 Balok Kayu Klas III m3 2,500,000.00
11 Papan Klas III m3 2,600,000.00
12 Kayu galam dia. 10-12 cm btg 9,000.00
13 Paku Kayu kg 25,000.00
14 Air Bersih m3 5,200.00
17 Bahan Bakar (Bensin) liter 10,000.00
18 Oli liter 52,300.00
20 Cat besi kg 55,000.00
21 Kayu Bakar m3 32,500.00

PIPA HDPE, GI DAN AKSESORIES Intilon


1 Pengadaan Pipa HDPE 160 mm m' 562,866.67
2 Pengadaan Pipa HDPE 110 mm m' 265,466.67
3 Pengadaan Pipa HDPE 90 mm m' 178,200.00
4 Pengadaan Pipa HDPE 2'' m' 104,862.00
5 Tee HDPE dia. 160 mm x 160 mm bh 1,094,520.00
6 Reducing Tee 90 mm x 60 mm x 90 mm 600,170.00
7 Reducer Tee HDPE dia. 160 mm x 90 mm x 160 bh 1,515,480.00
8 Tee HDPE dia. 110 mm x 110 mm bh 535,680.00
9 Reducer Tee HDPE dia. 110 mm x 90 mm x 110 bh 763,670.00
10 Tee HDPE dia. 90 mm x 90 mm bh 337,920.00
11 Reduser HDPE Tipe Flange 200 x 160 mm bh 1,427,800.00
12 Reduser HDPE Tipe Flange 160 x 110 mm bh 132,873.33
13 Bend 900 dia 90 mm bh 358,100.00
14 Dof HDPE 110 mm Bh 210,045.00
15 Dop HDPE 90 mm Bh 210,045.00
Dop HDPE Dia 63 mm bh 183,676.00
16 Gate Valve dia. 90 mm bh 2,312,940.00
17 Gate Valve dia. 110 mm bh 3,163,440.00
18 Gate Valve dia. 160 mm bh 6,599,460.00
19 BendHDPE 90o dia. 90 mm bh 277,800.00
20 Bend HDPE 90o dia. 110 mm Bh 630,600.00
22 Stub Flange dia. 110 mm bh 749,040.00
23 Karet Packing dia. 110 mm bh 21,120.00
24 Clamp Sadle 4"x 1/2" bh 60,760.80
25 Clamp Sadle 3"x 1/2" bh 49,766.40
26 Clamp Sadle 2"x 1/2" bh 27,326.40
27 Valve Socket PVC 1/2" bh 152,928.00
28 Knee PVC 1/2" bh 7,000.00
29 Pipa PVC 1/2" m' 7,000.00
30 Foucet Elbow 1/2" bh 7,000.00
31 Double Nepel GI 1/2" bh 7,000.00
32 Stop kran 1/2" bh 50,000.00
33 Water Meter bh 300,000.00
34 Atap Kran 1/2" bh 25,000.00
35 Lem PVC bh 15,000.00
36 Seal Tape bh 5,000.00
DAFTAR HARGA SATUAN DASAR UPAH
KUALA KURUN - KABUPATEN GUNUNG MAS

HARGA SATUAN
No. URAIAN SATUAN
(Rp.)

1 Mandor org/hr 144,000.00


2 Tukang Gali Tanah org/hr 130,000.00
3 Kepala Tukang Batu org/hr 139,000.00
4 Tukang Batu org/hr 130,000.00
5 Pembantu Tukang Batu org/hr 114,000.00
6 Kepala Tukang Kayu org/hr 140,000.00
7 Tukang Kayu org/hr 130,000.00
8 Pembantu Tukang kayu org/hr 115,000.00
9 Kepala Tukang Besi org/hr 140,000.00
10 Tukang Besi org/hr 130,000.00
11 Pembantu Tukang Besi org/hr 115,000.00
12 Kepala Tukang Pipa org/hr 140,000.00
13 Tukang Pipa org/hr 130,000.00
14 Pembantu Tukang Pipa org/hr 115,000.00
15 Operator org/hr 115,000.00

DAFTAR HARGA SATUAN DASAR BAHAN

KUALA KURUN - KABUPATEN GUNUNG MAS

HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)
BAHAN
1 Pasir Pasang m3 159,000.00
2 Koral /kerikil sungai m3 153,000.00
3 Batu Pecah 2-3 cm m3 850,000.00
4 Batu Belah m3 450,000.00
5 Semen PC 40 kg (Zak) Kg 68,000.00
6 Besi Beton kg 18,000.00
7 Kawat Beton kg 25,000.00
8 Balok Kayu Klas I m3 8,750,000.00
9 Balok Kayu Klas II m3 3,000,000.00
10 Balok Kayu Klas III m3 2,500,000.00
11 Papan Klas III m3 2,600,000.00
12 Kayu galam dia. 10-12 cm btg 9,000.00
13 Paku Kayu kg 25,000.00
14 Air Bersih m3 5,000.00
17 Bahan Bakar (Bensin) liter 10,000.00
18 Oli liter 52,300.00
20 Cat besi kg 55,000.00
HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)
21 Kayu Bakar m3 32,500.00

PIPA HDPE, GI DAN AKSESORIES


1 Pengadaan Pipa HDPE 160 mm m' 562,866.67
2 Pengadaan Pipa HDPE 110 mm m' 265,466.67
3 Pengadaan Pipa HDPE 90 mm m' 178,200.00
4 Pengadaan Pipa HDPE 2'' m' 104,500.00
5 Tee HDPE dia. 160 mm x 160 mm bh 1,094,520.00
Tee HDPE Dia 98 mm x 98 mm Bh 158,000.00
6 Reducing Tee 90 mm x 60 mm x 90 mm Bh 600,170.00
7 Reducer Tee HDPE dia. 160 mm x 90 mm x 160 mm bh 1,515,480.00
8 Reducer Tee HDPE Dia. 100 mm x 60 mm x 100 mm Bh 515,200.00
8 Tee HDPE dia. 110 mm x 110 mm bh 535,680.00
9 Reducer Tee HDPE dia. 110 mm x 90 mm x 110 mm bh 763,670.00
10 Tee HDPE dia. 90 mm x 90 mm bh 337,920.00
11 Reduser HDPE Tipe Flange 200 x 160 mm bh 1,427,800.00
12 Reduser HDPE Tipe Flange 160 x 110 mm bh 132,873.33
13 Reducer HDPE 100 x 63 Bh 91,000.00
14 Reducer HDPE 90 mm x 63 mm Bh 67,000.00
14 Bend 900 dia 90 mm bh 358,100.00
15 Dof HDPE 110 mm Bh 210,045.00
16 Dop HDPE 90 mm Bh 210,045.00
17 Dop HDPE Dia 63 mm bh 183,676.00
18 Gate Valve dia. 90 mm bh 2,312,940.00
19 Gate Valve dia. 110 mm bh 3,163,440.00
20 Gate Valve dia. 160 mm bh 6,599,460.00
21 BendHDPE 90o dia. 90 mm bh 277,800.00
22 Bend HDPE 90o dia. 110 mm Bh 630,600.00
23 Stub Flange dia. 160 mm bh 749,040.00
24 Karet Packing dia. 160 mm bh 21,120.00
25 Clamp Sadle 2"x 1/2" bh 140,100.00
26 Valve Socket PVC 1/2" bh 152,928.00
27 Knee PVC 1/2" bh 7,000.00
28 Pipa PVC 1/2" m' 7,000.00
29 Foucet Elbow 1/2" bh 7,000.00
30 Double Nepel GI 1/2" bh 9,300.00
31 Stop kran 1/2" bh 50,000.00
32 Water Meter bh 300,000.00
33 Atap Kran 1/2" bh 25,000.00
34 Lem PVC bh 15,000.00
35 Seal Tape bh 5,000.00
36 Meteran Air Standar SNI Bh 420,750
37 Stop kran 1/2" (Kuningan) Bh 73,125
38 Plug Kran 1/2" Kuningan Bh 51,750
39 Katup Searah 1/2 Kuningan Bh 99,000
40 Knee 90 0 GIP Bh 11,627
41 Atap Kran 1/2" Kuningan Bh 48,375
42 Tee GI Dia 1/2 Bh 12,774
43 Pipa GIP 1/2 " (SNI) m' 43,725
44 Box Meter Warna Kuning Bh 74,250
ANALISA HARGA SATUAN PEKERJAAN

A.2.3.1 HARGA SATUAN PEKERJAAN TANAH

A.2.3.1.4.2 Galian Pipa Dia 2 "

Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
1. Galian Pipa Dia. 2 " Tanah Keras M3 0.2000 132,300.00
2. Galian Pipa Dia 2 " Tanah Biasa M3 0.2000 202,095.00

JUMLAH TENAGA KERJA

B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
1. Tanah Keras
2. Tanah Cadas

E Overhead & Profit (12,5%) 12,5%XD


1. Tanah Keras
2. Tanah Cadas
F Harga Satuan Pekerja (D+E)
1. Tanah Keras
2. Tanah Cadas

A.2.3.1.9 Urugan Kembali Galian Tanah 1 M3

Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0500 114,000.00
Mandor L.04 OH 0.0319 144,000.00

JUMLAH TENAGA KERJA


B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit (12,5%) 12,5%XD
F Harga Satuan Pekerja (D+E)
A.8.4.1 HARGA SATUAN PEKERJAAN PEMASANGAN PIPA DI LUAR GEDUNG

A.8.4.1.17.a (K3) Pemasangan 1 m pipa HDPE Ø 63 mm

Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0350 115,000.00
Tukang Pipa L.02 OH 0.0170 130,000.00
Mandor L..04 OH 0.0030 144,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pipa HDPE Ø 63 mm
mm m 1.000 104,500.00

JUMLAH HARGA BAHAN


C PERALATAN
Sewa Tripot/Tackel
& handle crane 2 T Hari 0.019 -

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit (12,5%) 12,5%XD
F Harga Satuan Pekerja (D+E)

A.8.4.3.15.e (K3) Pemasangan 1 buah TEE Ø 60 mm x 60 mm

No Uraian Kode Satuan Koefisien Harga Satuan


A TENAGA (Rp)
Pekerja L.01 OH 0.1060 115,000.00
Tukang Pipa L.02 OH 0.0530 130,000.00
Mandor L..04 OH 0.0110 144,000.00

JUMLAH TENAGA KERJA


B BAHAN
Tee HDPE Dia. 60 mm x 60 mm Bh 1.000 158,000.00

JUMLAH HARGA BAHAN


C PERALATAN
Hari 0.028 -

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit (12,5%) 12,5%XD
F Harga Satuan Pekerja (D+E)
A.4.1.1.2 Membuat 1 m3 beton mutu f’c = 9,8 Mpa (k.100)

Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.6500 114,000.00
Tukang Batu L.02 OH 0.2750 130,000.00
Kepala Tukang L.04 OH 0.0280 139,000.00
Mandor L.04 0H 0.0830 144,000.00

JUMLAH TENAGA KERJA


B BAHAN
1. Semen PC Kg 276.000 1,700.00
2. Kerikil m3 0.750 153,000.00
3. Pasir Pasang m3 0.591 159,000.00
4. Air m3 0.215 5,200

JUMLAH HARGA BAHAN


C PERALATAN
Hari 0.028 -

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit (12,5%) 12,5%XD
F Harga Satuan Pekerja (D+E)

A.8.4.5 HARGA SATUAN PEKERJAAN PENGETESAN PIPA

A.8.4.5.3 (K3) Pengetesan 1 m pipa Ø 50 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0080 114,000.00
Mandor L.04 0H 0.0008 144,000.00

JUMLAH TENAGA KERJA


B BAHAN
Air Test m3 0.002 5,000.00
Bahan Bakar L 0.060 10,000.00
Olie L 0.002 52,300.00

JUMLAH HARGA BAHAN


C PERALATAN
Hari 0.028 -

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit (12,5%) 12,5%XD
F Harga Satuan Pekerja (D+E)
ANALISA HARGA SATUAN PEKERJAAN

Jumlah Harga
(Rp)

26,460.00
40,419.00

26,460.00
40,419.00

26,460.00
40,419.00

-
3,307.50
5,052.38
-
29,767.50
45,471.38

Jumlah Harga
(Rp)

5,700.00
4,593.60

10,293.60

-
10,293.60
1,286.70
11,580.30
Jumlah Harga
(Rp)

4,025.00
2,210.00
432.00
6,667.00

104,500.00

104,500.00

-
111,167.00
13,895.88
125,062.88

Jumlah Harga
(Rp)
12,190.00
6,890.00
1,584.00

20,664.00

158,000.00

158,000.00

-
178,664.00
22,333.00
200,997.00
Jumlah Harga
(Rp)

188,100.00
35,750.00
3,892.00
11,952.00

239,694.00

469,200.00
114,693.33
94,037.14
1,118.00

679,048.48

-
918,742.48
114,842.81
1,033,585.29

Jumlah Harga
(Rp)

912.00
115.20

1,027.20

10.00
600.00
104.60

714.60

-
1,741.80
217.73
1,959.53
JADUAL PELAKSANAAN PEKERJAAN
(TIME SCHEDULLE)

PROGRAM : Program Sistem Penyediaan Air Minum


KEGIATAN : Pemasangan Pipa Distribusi dan SR di 20 Desa Pamsimas 2017-2018*)
PEKERJAAN : Pemasangan Pipa Distribusi dan SR di Desa Tumbang Korik
LOKASI : Desa Tumbang Korik
WAKTU PELAKSANAAN : 60 ( ENAM PULUH ) HARI KALENDER

2019
NO. URAIAN PEKERJAAN BIAYA BOBOT I II MASA PEMELIHARAAN

(Rp) (%) 1 2 3 4 5 6 7 8 9

I. PEKERJAAN PENDAHULUAN
100
1 Pekerjaan Mobilisasi 3,000,000.00 2.54 2.34 0.20
80
2 Papan Nama Permanen 2,000,000.00 1.69 1.69 90
II. PEKERJAAN PEMASANGAN DAN PENGETESAN PIPA
II.1 PEKERJAAN PEMASANGAN PIPA 80

1 Galian Pipa HDPE 63 SDR 13,6 , Diameter 2 Inch 1,609,686.68 1.36 0.68 0.68
70
2 Pengurukan Galian Pipa HDPE 63 SDR 13,6 , Diameter 2 Inch 403,556.40 0.34 0.34
3 Pemasangan Pipa HDPE 63 SDR 13,6 , Diameter 2 Inch 22,136,128.88 18.75 9.38 9.38 60
4 Pemasangan Tee HDPE Dia 2 Inch x 2 Inch 200,997.00 0.17 0.17
5 Pemasangan Dop Dia. 2 Inch 202,054.59 0.17 0.17 50

6 Cor Patok Penanda End Pipa 11,627.83 0.01 0.01


40
II.2 PEKERJAAN PENGETESAN PIPA
1 Pengetesan Pipa HDPE Diameter 2 Inch 346,835.93 0.29 0.29 30
III. PENGADAAN DAN PEMASANGAN SR BERIKUT ASSESORISNYA
III.1 PENGADAAN SR DAN ACCESORIESNYA 84,304,112.70 71.41 14.28 14.28 14.28 14.28 13.78 0.50 20

III.2 PEMASANGAN SR BERIKUT ACCESORIESNYA


10
1 Pemasangan SR Berikut Accesoriesnya 3,835,000.00 3.25 1.62 1.62
IV. MASA PEMELIHARAAN 0

JUMLAH 118,050,000.00 90.91


PPN 10 % 11,805,000.00 9.09
TOTAL 129,855,000.00 100.00
RENCANA KOMULATIF PRESTASI KERJA (%) 1.69 14.28 14.96 24.34 26.00 14.13 2.32 1.97 0.29
JUMLAH PRESTASI KERJA (%) - 1.69 15.98 30.94 55.28 81.28 95.42 97.74 99.71 100.00

ACTUAL PROGRES PRESTASI KERJA (%)


JUMLAH PRESTASI KERJA (%)
DEVIASI (Plus / Minus)

Catatan : 1 Kolom = 7 Hari Kalender Kuala Kurun, 14 Agustus 2019


Minggu ke 9 = 4 hari
CV. KAHAYAN NURPITA
Pusat Kuala Kurun

E. IGINSYAH
Direktur
DAFTAR HARGA SATUAN DASAR UPAH

KUALA KURUN - KABUPATEN GUNUNG MAS

HARGA SATUAN
No. URAIAN SATUAN
(Rp.)

1 Mandor org/hr 145,000.00


2 Tukang Gali Tanah org/hr 130,000.00
3 Kepala Tukang Batu org/hr 140,000.00
4 Tukang Batu org/hr 130,000.00
5 Pembantu Tukang Batu org/hr 115,000.00
6 Kepala Tukang Kayu org/hr 140,000.00
7 Tukang Kayu org/hr 130,000.00
8 Pembantu Tukang kayu org/hr 115,000.00
9 Kepala Tukang Besi org/hr 140,000.00
10 Tukang Besi org/hr 130,000.00
11 Pembantu Tukang Besi org/hr 115,000.00
12 Kepala Tukang Pipa org/hr 140,000.00
13 Tukang Pipa org/hr 130,000.00
14 Pembantu Tukang Pipa org/hr 115,000.00
15 Operator org/hr 115,000.00
DAFTAR HARGA SATUAN DASAR BAHAN

KUALA KURUN - KABUPATEN GUNUNG MAS

HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)
BAHAN
1 Pasir Pasang m3 160,000.00
2 Koral /kerikil sungai m3 154,000.00
3 Batu Pecah 2-3 cm m3 850,000.00
4 Batu Belah m3 450,000.00
5 Semen PC 40 kg (Zak) Kg 68,000.00
6 Besi Beton kg 18,000.00
7 Kawat Beton kg 25,000.00
8 Balok Kayu Klas I m3 8,750,000.00
9 Balok Kayu Klas II m3 3,000,000.00
10 Balok Kayu Klas III m3 2,500,000.00
11 Papan Klas III m3 2,600,000.00
12 Kayu galam dia. 10-12 cm btg 9,000.00
13 Paku Kayu kg 25,000.00
14 Air Bersih m3 5,200.00
17 Bahan Bakar (Bensin) liter 10,000.00
18 Oli liter 52,300.00
20 Cat besi kg 55,000.00
21 Kayu Bakar m3 32,500.00

PIPA HDPE, GI DAN AKSESORIES


1 Pengadaan Pipa HDPE 160 mm m' 511,500.00
2 Pengadaan Pipa HDPE 110 mm m' 240,900.00
3 Pengadaan Pipa HDPE 90 mm m' 162,000.00
4 Pengadaan Pipa HDPE 2'' m' 79,950.00
5 Tee HDPE dia. 160 mm x 160 mm bh 1,094,520.00
6 Reducing Tee 160 mm x 110 mm x 160 mm 1,515,480.00
7 Reducer Tee HDPE dia. 160 mm x 90 mm bh 1,515,480.00
8 Tee HDPE dia. 110 mm x 110 mm bh 535,680.00
9 Reducer Tee HDPE dia. 110 mm x 90 mm bh 719,640.00
10 Tee HDPE dia. 90 mm x 90 mm bh 337,920.00
11 Reduser HDPE Tipe Flange 200 x 160 mm bh
12 Reduser HDPE Tipe Flange 160 x 110 mm bh 132,873.33
13 Reduser HDPE Tipe Flange 110 x 90 mm bh 90,980.00
14 Dof HDPE 110 mm Bh 126,240.00
15 Dop HDPE 90 mm Bh 90,480.00
16 Gate Valve dia. 90 mm bh 2,312,940.00
17 Gate Valve dia. 110 mm bh 3,163,440.00
18 Gate Valve dia. 160 mm bh 6,599,460.00
19 BendHDPE 90o dia. 90 mm bh 277,800.00
20 Bend HDPE 90o dia. 110 mm Bh 630,600.00
21 Bend HDPE 90o dia. 110 mm Bh 863,520.00
22 Stub Flange dia. 110 mm bh 749,040.00
23 Karet Packing dia. 110 mm bh 21,120.00
24 Clamp Sadle 4"x 1/2" bh 60,760.80
25 Clamp Sadle 3"x 1/2" bh 49,766.40
26 Clamp Sadle 2"x 1/2" bh 27,326.40
27 Valve Socket PVC 1/2" bh 152,928.00
28 Knee PVC 1/2" bh 5,640.00
29 Pipa PVC 1/2" m' 5,640.00
30 Foucet Elbow 1/2" bh 4,320.00
31 Double Nepel GI 1/2" bh 4,560.00
32 Stop kran 1/2" bh 46,200.00
33 Water Meter bh 264,000.00
34 Atap Kran 1/2" bh 23,160.00
35 Lem PVC bh 12,000.00
36 Seal Tape bh 1,920.00