LAMPIRAN SURAT PERINTAH KERJA (SPK)

PROGRAM : PENINGKATAN SARANA DAN PRASARANA APARATUR


KEGIATAN : REHABILITASI SEDANG/BERAT RUMAH JABATAN
PEKERJAAN : REHAB TAMAN RUJAB GUBERNUR
LOKASI : PALANGKARAYA
TAHUN ANGGARAN : 2012

HARGA SATUAN JUMLAH HARGA


NO. URAIAN PEKERJAAN VOLUME
(Rp.) (Rp)

I PEKERJAAN REHAB LANSEKAP (DEPAN PAGAR)


1 Pek. Timbunan Tanah Subur dan Penghamparan 70.50 M3 223,716.69 15,772,026.65
2 Pek. Tanam Angrek Tanah 55.00 Rumpun 29,760.36 1,636,819.80
3 Pek. Tanam Krombusa 85.00 Pohon 34,011.84 2,891,006.40
4 Pek. Tanam Palem Botol 1.00 Pohon 538,920.00 538,920.00
5 Pek. Tanam Simbang Dara 30.00 Pohon 42,514.80 1,275,444.00
6 Pek. Tanam Trikaler Besar 10.00 Pohon 161,676.00 1,616,760.00
7 Pek. Tanam Olena 6.00 Pohon 395,208.00 2,371,248.00
8 Pek. Tanam Daun Dara 4.00 Pohon 12,574.80 50,299.20
9 Pek. Tanam Cemara Papua 8.00 Pohon 297,004.80 2,376,038.40
10 Pek. Tanam Bonsai Dolar 2.00 Pohon 1,856,280.00 3,712,560.00
11 Pek. Tanam Rumput Gajah Mini 78.00 M2 119,167.29 9,295,048.62
SUB TOTAL I 41,536,171.07
II PEKERJAAN REHAB LANSEKAP (BELAKANG SELASAR)
1 Pek. Timbunan Tanah Subur dan Penghamparan 8.00 M3 223,716.69 1,789,733.52
2 Pek. Tanam Angrek Tanah 76.00 Rumpun 29,670.90 2,254,988.40
3 Pek. Tanam Krombusa 120.00 Pohon 33,909.60 4,069,152.00
4 Pek. Tanam Cemara Pentris 4.00 Pohon 254,322.00 1,017,288.00
5 Pek. Pasang Kerikil Taman 20.00 Zak 65,670.00 1,313,400.00
6 Pek. Pasang Pot Lonceng Besar 6.00 Bh 591,030.00 3,546,180.00
7 Pek. Tanam Palm Bismar 4.00 Pohon 593,418.00 2,373,672.00
8 Pek. Tanam Palm Phoniex 4.00 Pohon 254,322.00 1,017,288.00
9 Pek. Tanam Rumput Gajah Mini 50.00 M2 119,167.29 5,958,364.50
SUB TOTAL II 23,340,066.42
III PEKERJAAN REHAB LANSEKAP (KONTUR DEPAN ISTANA)
1 Pek. Timbunan Tanah Subur dan Penghamparan 16.00 M3 223,716.69 3,579,467.04
2 Pek. Tanam Rumput Paitan 135.00 M2 33,367.29 4,504,584.15
3 Pek. Tanam Rumput Gajah Mini 120.00 M2 119,167.29 14,300,074.80
SUB TOTAL III 22,384,125.99
IV PEKERJAAN REHAB LANSEKAP (BELAKANG RUJAB)
1 Pek. Timbunan Tanah Subur dan Penghamparan 14.00 M3 223,716.69 3,132,033.66
2 Pek. Tanam Angrek Tanah 162.00 Rumpun 29,730.54 4,816,347.48
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME
(Rp.) (Rp)

3 Pek. Tanam Krombusa Mini 210.00 Pohon 29,730.54 6,243,413.40


4 Pek. Tanam Pandanus 225.00 Pohon 10,193.33 2,293,498.80
5 Pek. Tanam Rulia 230.00 Pohon 9,224.24 2,121,576.12
6 Pek. Tanam Alur 662.00 Pohon 8,494.44 5,623,319.28
7 Pek. Tanam Bunga Bawang 120.00 Pohon 9,343.88 1,121,266.08
8 Pek. Tanam Jaburan 223.00 Pohon 7,645.00 1,704,834.11
9 Pek. Tanam Bakung 140.00 Pohon 7,645.00 1,070,299.44
10 Pek. Tanam Pandan Bali 3.00 Pohon 424,722.00 1,274,166.00
11 Pek. Tanam Terambulan 100.00 Pohon 9,343.88 934,388.40
12 Pek. Tanam Asoka 45.00 Pohon 10,193.33 458,699.76
13 Pek. Tanam Simbang Dara 50.00 Pohon 42,472.20 2,123,610.00
14 Pek. Tanam Bligo Merah 200.00 Pohon 12,562.20 2,512,440.00
15 Pek. Tanam Olena 16.00 Pohon 394,812.00 6,316,992.00
16 Pek. Tanam Palm Phoniex 2.00 Pohon 254,833.20 509,666.40
17 Pek. Tanam Rumput Gajah Mini 10.00 M2 119,167.29 1,191,672.90
SUB TOTAL IV 43,448,223.83
V PEKERJAAN LAIN-LAIN
1 Pek. Pupuk Kandang 240.00 Zak 27,000.00 6,480,000.00
2 Pek. Perapihan Pekerjaan Akhir 1.00 Sat 1,230,000.00 1,230,000.00
Upah Kerja Jasa Perawatan/Pemeliharaan 4 Orang x 1 Bulan
3 120.00 Hari 94,050.00 11,286,000.00
(Harga Laden/Buruh)
SUB TOTAL V 18,996,000.00

REKAPITULASI
No URAIAN PEKERJAAN JUMLAH

I PEKERJAAN REHAB LANSEKAP (DEPAN PAGAR) 41,536,171.07

II PEKERJAAN REHAB LANSEKAP (BELAKANG SELASAR) 23,340,066.42

III PEKERJAAN REHAB LANSEKAP (KONTUR DEPAN ISTANA) 22,384,125.99

IV PEKERJAAN REHAB LANSEKAP (BELAKANG RUJAB) 43,448,223.83

V PEKERJAAN LAIN-LAIN 18,996,000.00

TOTAL 149,704,587.30

DIBULATKAN 149,700,000.00

TERBILANG : // SERATUS EMPAT PULUH SEMBILAN JUTA TUJUH RATUS RIBU RUPIAH //
LAMPIRAN BERITA ACARA KLARIFIKASI TEKNIS DAN NEGOSIASI HARGA

PROGRAM : PENINGKATAN SARANA DAN PRASARANA APARATUR


KEGIATAN : REHABILITASI SEDANG/BERAT RUMAH JABATAN
PEKERJAAN : REHAB TAMAN RUJAB GUBERNUR
LOKASI : PALANGKARAYA
TAHUN ANGGARAN : 2012

HARGA PENAWARAN TERKOREKSI HARGA NEGOSIASI


NO. URAIAN PEKERJAAN
HARGA SATUAN JUMLAH HARGA HARGA SATUAN JUMLAH HARGA
VOLUME VOLUME
(Rp.) (Rp) (Rp.) (Rp)

I PEKERJAAN REHAB LANSEKAP (DEPAN PAGAR)


1 Pek. Timbunan Tanah Subur dan Penghamparan 70.50 M3 223,716.69 15,772,026.65 70.50 M3 223,716.69 15,772,026.65
2 Pek. Tanam Angrek Tanah 55.00 Rumpun 29,760.36 1,636,819.80 55.00 Rumpun 29,760.36 1,636,819.80
3 Pek. Tanam Krombusa 85.00 Pohon 34,011.84 2,891,006.40 85.00 Pohon 34,011.84 2,891,006.40
4 Pek. Tanam Palem Botol 1.00 Pohon 538,920.00 538,920.00 1.00 Pohon 538,920.00 538,920.00
5 Pek. Tanam Simbang Dara 30.00 Pohon 42,514.80 1,275,444.00 30.00 Pohon 42,514.80 1,275,444.00
6 Pek. Tanam Trikaler Besar 10.00 Pohon 161,676.00 1,616,760.00 10.00 Pohon 161,676.00 1,616,760.00
7 Pek. Tanam Olena 6.00 Pohon 395,208.00 2,371,248.00 6.00 Pohon 395,208.00 2,371,248.00
8 Pek. Tanam Daun Dara 4.00 Pohon 12,574.80 50,299.20 4.00 Pohon 12,574.80 50,299.20
9 Pek. Tanam Cemara Papua 8.00 Pohon 297,004.80 2,376,038.40 8.00 Pohon 297,004.80 2,376,038.40
10 Pek. Tanam Bonsai Dolar 2.00 Pohon 1,856,280.00 3,712,560.00 2.00 Pohon 1,856,280.00 3,712,560.00
11 Pek. Tanam Rumput Gajah Mini 78.00 M2 119,167.29 9,295,048.62 78.00 M2 119,167.29 9,295,048.62
SUB TOTAL I 41,536,171.07 41,536,171.07
II PEKERJAAN REHAB LANSEKAP (BELAKANG SELASAR)
1 Pek. Timbunan Tanah Subur dan Penghamparan 8.00 M3 223,716.69 1,789,733.52 8.00 M3 223,716.69 1,789,733.52
2 Pek. Tanam Angrek Tanah 76.00 Rumpun 29,670.90 2,254,988.40 76.00 Rumpun 29,670.90 2,254,988.40
3 Pek. Tanam Krombusa 120.00 Pohon 33,909.60 4,069,152.00 120.00 Pohon 33,909.60 4,069,152.00
4 Pek. Tanam Cemara Pentris 4.00 Pohon 254,322.00 1,017,288.00 4.00 Pohon 254,322.00 1,017,288.00
5 Pek. Pasang Kerikil Taman 20.00 Zak 65,670.00 1,313,400.00 20.00 Zak 65,670.00 1,313,400.00
6 Pek. Pasang Pot Lonceng Besar 6.00 Bh 591,030.00 3,546,180.00 6.00 Bh 591,030.00 3,546,180.00
7 Pek. Tanam Palm Bismar 4.00 Pohon 593,418.00 2,373,672.00 4.00 Pohon 593,418.00 2,373,672.00
8 Pek. Tanam Palm Phoniex 4.00 Pohon 254,322.00 1,017,288.00 4.00 Pohon 254,322.00 1,017,288.00
9 Pek. Tanam Rumput Gajah Mini 50.00 M2 119,167.29 5,958,364.50 50.00 M2 119,167.29 5,958,364.50
SUB TOTAL II 23,340,066.42 23,340,066.42
III PEKERJAAN REHAB LANSEKAP (KONTUR DEPAN ISTANA)
1 Pek. Timbunan Tanah Subur dan Penghamparan 16.00 M3 223,716.69 3,579,467.04 16.00 M3 223,716.69 3,579,467.04
2 Pek. Tanam Rumput Paitan 135.00 M2 33,367.29 4,504,584.15 135.00 M2 33,367.29 4,504,584.15
3 Pek. Tanam Rumput Gajah Mini 120.00 M2 119,167.29 14,300,074.80 120.00 M2 119,167.29 14,300,074.80
SUB TOTAL III 22,384,125.99 22,384,125.99
IV PEKERJAAN REHAB LANSEKAP (BELAKANG RUJAB)
1 Pek. Timbunan Tanah Subur dan Penghamparan 14.00 M3 223,716.69 3,132,033.66 14.00 M3 223,716.69 3,132,033.66
2 Pek. Tanam Angrek Tanah 162.00 Rumpun 29,730.54 4,816,347.48 162.00 Rumpun 29,730.54 4,816,347.48
3 Pek. Tanam Krombusa Mini 210.00 Pohon 29,730.54 6,243,413.40 210.00 Pohon 29,730.54 6,243,413.40
4 Pek. Tanam Pandanus 225.00 Pohon 10,193.33 2,293,498.80 225.00 Pohon 10,193.33 2,293,498.80
5 Pek. Tanam Rulia 230.00 Pohon 9,224.24 2,121,576.12 230.00 Pohon 9,224.24 2,121,576.12
6 Pek. Tanam Alur 662.00 Pohon 8,494.44 5,623,319.28 662.00 Pohon 8,494.44 5,623,319.28
7 Pek. Tanam Bunga Bawang 120.00 Pohon 9,343.88 1,121,266.08 120.00 Pohon 9,343.88 1,121,266.08
8 Pek. Tanam Jaburan 223.00 Pohon 7,645.00 1,704,834.11 223.00 Pohon 7,645.00 1,704,834.11
9 Pek. Tanam Bakung 140.00 Pohon 7,645.00 1,070,299.44 140.00 Pohon 7,645.00 1,070,299.44
10 Pek. Tanam Pandan Bali 3.00 Pohon 424,722.00 1,274,166.00 3.00 Pohon 424,722.00 1,274,166.00
11 Pek. Tanam Terambulan 100.00 Pohon 9,343.88 934,388.40 100.00 Pohon 9,343.88 934,388.40
12 Pek. Tanam Asoka 45.00 Pohon 10,193.33 458,699.76 45.00 Pohon 10,193.33 458,699.76
13 Pek. Tanam Simbang Dara 50.00 Pohon 42,472.20 2,123,610.00 50.00 Pohon 42,472.20 2,123,610.00
14 Pek. Tanam Bligo Merah 200.00 Pohon 12,562.20 2,512,440.00 200.00 Pohon 12,562.20 2,512,440.00
15 Pek. Tanam Olena 16.00 Pohon 394,812.00 6,316,992.00 16.00 Pohon 394,812.00 6,316,992.00
16 Pek. Tanam Palm Phoniex 2.00 Pohon 254,833.20 509,666.40 2.00 Pohon 254,833.20 509,666.40
17 Pek. Tanam Rumput Gajah Mini 10.00 M2 119,167.29 1,191,672.90 10.00 M2 119,167.29 1,191,672.90
SUB TOTAL IV 43,448,223.83 43,448,223.83
V PEKERJAAN LAIN-LAIN
1 Pek. Pupuk Kandang 240.00 Zak 27,000.00 6,480,000.00 240.00 Zak 27,000.00 6,480,000.00
2 Pek. Perapihan Pekerjaan Akhir 1.00 Sat 1,246,000.00 1,246,000.00 1.00 Sat 1,230,000.00 1,230,000.00
Upah Kerja Jasa Perawatan/Pemeliharaan 4 Orang x 1 Bulan
3 120.00 Hari 94,050.00 11,286,000.00 120.00 Hari 94,050.00 11,286,000.00
(Harga Laden/Buruh)
SUB TOTAL V 19,012,000.00 18,996,000.00
REKAPITULASI
No URAIAN PEKERJAAN JUMLAH JUMLAH

I PEKERJAAN REHAB LANSEKAP (DEPAN PAGAR) 41,536,171.07 41,536,171.07

II PEKERJAAN REHAB LANSEKAP (BELAKANG SELASAR) 23,340,066.42 23,340,066.42

III PEKERJAAN REHAB LANSEKAP (KONTUR DEPAN ISTANA) 22,384,125.99 22,384,125.99

IV PEKERJAAN REHAB LANSEKAP (BELAKANG RUJAB) 43,448,223.83 43,448,223.83

V PEKERJAAN LAIN-LAIN 19,012,000.00 18,996,000.00

TOTAL 149,720,587.30 149,704,587.30

DIBULATKAN 149,720,000.00 149,700,000.00


KOREKSI ARITMATIK

PROGRAM : PENINGKATAN SARANA DAN PRASARANA APARATUR


KEGIATAN : REHABILITASI SEDANG/BERAT RUMAH JABATAN
PEKERJAAN : REHAB TAMAN RUJAB GUBERNUR
LOKASI : PALANGKARAYA
TAHUN ANGGARAN : 2012

HARGA PENAWARAN SAAT PEMBUKAAN HARGA PENAWARAN TERKOREKSI DEVIASI EVALUASI KEWAJARAN HARGA
NO. URAIAN PEKERJAAN Keterangan
HARGA SATUAN JUMLAH HARGA HARGA SATUAN JUMLAH HARGA Harga Satuan % HPS % Thd.
VOLUME VOLUME Rupiah %
(Rp.) (Rp) (Rp.) (Rp) HPS (Rp.) thd. HPS Total HPS

I PEKERJAAN REHAB LANSEKAP (DEPAN PAGAR)


1 Pek. Timbunan Tanah Subur dan Penghamparan 70.50 M3 223,716.69 15,772,026.65 70.50 M3 223,716.69 15,772,026.65 - - 224,991.00 99.43 10.51 Tidak Timpang
2 Pek. Tanam Angrek Tanah 55.00 Rumpun 29,760.36 1,636,819.80 55.00 Rumpun 29,760.36 1,636,819.80 - - 29,820.00 99.80 1.09 Tidak Timpang
3 Pek. Tanam Krombusa 85.00 Pohon 34,011.84 2,891,006.40 85.00 Pohon 34,011.84 2,891,006.40 - - 34,080.00 99.80 1.93 Tidak Timpang
4 Pek. Tanam Palem Botol 1.00 Pohon 538,920.00 538,920.00 1.00 Pohon 538,920.00 538,920.00 - - 540,000.00 99.80 0.36 Tidak Timpang
5 Pek. Tanam Simbang Dara 30.00 Pohon 42,514.80 1,275,444.00 30.00 Pohon 42,514.80 1,275,444.00 - - 42,600.00 99.80 0.85 Tidak Timpang
6 Pek. Tanam Trikaler Besar 10.00 Pohon 161,676.00 1,616,760.00 10.00 Pohon 161,676.00 1,616,760.00 - - 162,000.00 99.80 1.08 Tidak Timpang
7 Pek. Tanam Olena 6.00 Pohon 395,208.00 2,371,248.00 6.00 Pohon 395,208.00 2,371,248.00 - - 396,000.00 99.80 1.58 Tidak Timpang
8 Pek. Tanam Daun Dara 4.00 Pohon 12,574.80 50,299.20 4.00 Pohon 12,574.80 50,299.20 - - 12,600.00 99.80 0.03 Tidak Timpang
9 Pek. Tanam Cemara Papua 8.00 Pohon 297,004.80 2,376,038.40 8.00 Pohon 297,004.80 2,376,038.40 - - 297,600.00 99.80 1.58 Tidak Timpang
10 Pek. Tanam Bonsai Dolar 2.00 Pohon 1,856,280.00 3,712,560.00 2.00 Pohon 1,856,280.00 3,712,560.00 - - 1,860,000.00 99.80 2.48 Tidak Timpang
11 Pek. Tanam Rumput Gajah Mini 78.00 M2 119,167.29 9,295,048.62 78.00 M2 119,167.29 9,295,048.62 - - 119,371.00 99.83 6.20 Tidak Timpang
SUB TOTAL I 41,536,171.07 41,536,171.07 27.69
II PEKERJAAN REHAB LANSEKAP (BELAKANG SELASAR)
1 Pek. Timbunan Tanah Subur dan Penghamparan 8.00 M3 223,716.69 1,789,733.52 8.00 M3 223,716.69 1,789,733.52 - - 224,991.00 99.43 1.19 Tidak Timpang
2 Pek. Tanam Angrek Tanah 76.00 Rumpun 29,670.90 2,254,988.40 76.00 Rumpun 29,670.90 2,254,988.40 - - 29,820.00 99.50 1.50 Tidak Timpang
3 Pek. Tanam Krombusa 120.00 Pohon 33,909.60 4,069,152.00 120.00 Pohon 33,909.60 4,069,152.00 - - 34,080.00 99.50 2.71 Tidak Timpang
4 Pek. Tanam Cemara Pentris 4.00 Pohon 254,322.00 1,017,288.00 4.00 Pohon 254,322.00 1,017,288.00 - - 255,600.00 99.50 0.68 Tidak Timpang
5 Pek. Pasang Kerikil Taman 20.00 Zak 65,670.00 1,313,400.00 20.00 Zak 65,670.00 1,313,400.00 - - 66,000.00 99.50 0.88 Tidak Timpang
6 Pek. Pasang Pot Lonceng Besar 6.00 Bh 591,030.00 3,546,180.00 6.00 Bh 591,030.00 3,546,180.00 - - 594,000.00 99.50 2.36 Tidak Timpang
7 Pek. Tanam Palm Bismar 4.00 Pohon 593,418.00 2,373,672.00 4.00 Pohon 593,418.00 2,373,672.00 - - 596,400.00 99.50 1.58 Tidak Timpang
8 Pek. Tanam Palm Phoniex 4.00 Pohon 254,322.00 1,017,288.00 4.00 Pohon 254,322.00 1,017,288.00 - - 255,600.00 99.50 0.68 Tidak Timpang
9 Pek. Tanam Rumput Gajah Mini 50.00 M2 119,167.29 5,958,364.50 50.00 M2 119,167.29 5,958,364.50 - - 119,371.00 99.83 3.97 Tidak Timpang
SUB TOTAL II 23,340,066.42 23,340,066.42 15.56
III PEKERJAAN REHAB LANSEKAP (KONTUR DEPAN ISTANA)
1 Pek. Timbunan Tanah Subur dan Penghamparan 16.00 M3 223,716.69 3,579,467.04 16.00 M3 223,716.69 3,579,467.04 - - 224,991.00 99.43 2.39 Tidak Timpang
2 Pek. Tanam Rumput Paitan 135.00 M2 33,367.29 4,504,584.15 135.00 M2 33,367.29 4,504,584.15 - - 33,571.00 99.39 3.00 Tidak Timpang
3 Pek. Tanam Rumput Gajah Mini 120.00 M2 119,167.29 14,300,074.80 120.00 M2 119,167.29 14,300,074.80 - - 119,371.00 99.83 9.53 Tidak Timpang
SUB TOTAL III 22,384,125.99 22,384,125.99 14.92
IV PEKERJAAN REHAB LANSEKAP (BELAKANG RUJAB)
1 Pek. Timbunan Tanah Subur dan Penghamparan 14.00 M3 223,716.69 3,132,033.66 14.00 M3 223,716.69 3,132,033.66 - - 224,991.00 99.43 2.09 Tidak Timpang
2 Pek. Tanam Angrek Tanah 162.00 Rumpun 29,730.54 4,816,347.48 162.00 Rumpun 29,730.54 4,816,347.48 - - 29,820.00 99.70 3.21 Tidak Timpang
3 Pek. Tanam Krombusa Mini 210.00 Pohon 29,730.54 6,243,413.40 210.00 Pohon 29,730.54 6,243,413.40 - - 29,820.00 99.70 4.16 Tidak Timpang
4 Pek. Tanam Pandanus 225.00 Pohon 10,193.33 2,293,498.80 225.00 Pohon 10,193.33 2,293,498.80 - - 10,224.00 99.70 1.53 Tidak Timpang
5 Pek. Tanam Rulia 230.00 Pohon 9,224.24 2,121,576.12 230.00 Pohon 9,224.24 2,121,576.12 - - 9,252.00 99.70 1.41 Tidak Timpang
6 Pek. Tanam Alur 662.00 Pohon 8,494.44 5,623,319.28 662.00 Pohon 8,494.44 5,623,319.28 - - 8,520.00 99.70 3.75 Tidak Timpang
7 Pek. Tanam Bunga Bawang 120.00 Pohon 9,343.88 1,121,266.08 120.00 Pohon 9,343.88 1,121,266.08 - - 9,372.00 99.70 0.75 Tidak Timpang
8 Pek. Tanam Jaburan 223.00 Pohon 7,645.00 1,704,834.11 223.00 Pohon 7,645.00 1,704,834.11 - - 7,668.00 99.70 1.14 Tidak Timpang
9 Pek. Tanam Bakung 140.00 Pohon 7,645.00 1,070,299.44 140.00 Pohon 7,645.00 1,070,299.44 - - 7,668.00 99.70 0.71 Tidak Timpang
10 Pek. Tanam Pandan Bali 3.00 Pohon 424,722.00 1,274,166.00 3.00 Pohon 424,722.00 1,274,166.00 - - 426,000.00 99.70 0.85 Tidak Timpang
11 Pek. Tanam Terambulan 100.00 Pohon 9,343.88 934,388.40 100.00 Pohon 9,343.88 934,388.40 - - 9,372.00 99.70 0.62 Tidak Timpang
12 Pek. Tanam Asoka 45.00 Pohon 10,193.33 458,699.76 45.00 Pohon 10,193.33 458,699.76 - - 10,224.00 99.70 0.31 Tidak Timpang
13 Pek. Tanam Simbang Dara 50.00 Pohon 42,472.20 2,123,610.00 50.00 Pohon 42,472.20 2,123,610.00 - - 42,600.00 99.70 1.42 Tidak Timpang
14 Pek. Tanam Bligo Merah 200.00 Pohon 12,562.20 2,512,440.00 200.00 Pohon 12,562.20 2,512,440.00 - - 12,600.00 99.70 1.67 Tidak Timpang
15 Pek. Tanam Olena 16.00 Pohon 394,812.00 6,316,992.00 16.00 Pohon 394,812.00 6,316,992.00 - - 396,000.00 99.70 4.21 Tidak Timpang
16 Pek. Tanam Palm Phoniex 2.00 Pohon 254,833.20 509,666.40 2.00 Pohon 254,833.20 509,666.40 - - 255,600.00 99.70 0.34 Tidak Timpang
17 Pek. Tanam Rumput Gajah Mini 10.00 M2 119,167.29 1,191,672.90 10.00 M2 119,167.29 1,191,672.90 - - 119,371.00 99.83 0.79 Tidak Timpang
SUB TOTAL IV 43,448,223.83 43,448,223.83 28.97
V PEKERJAAN LAIN-LAIN
1 Pek. Pupuk Kandang 240.00 Zak 27,000.00 6,480,000.00 240.00 Zak 27,000.00 6,480,000.00 - - 26,000.00 103.85 4.32 Tidak Timpang
2 Pek. Perapihan Pekerjaan Akhir 1.00 Sat 1,246,000.00 1,246,000.00 1.00 Sat 1,246,000.00 1,246,000.00 - - 1,205,000.00 103.40 0.83 Tidak Timpang
Upah Kerja Jasa Perawatan/Pemeliharaan 4 Orang x 1 Bulan
3 120.00 Hari 94,050.00 11,286,000.00 120.00 Hari 94,050.00 11,286,000.00 - - 95,000.00 99.00 7.52 Tidak Timpang
(Harga Laden/Buruh)
SUB TOTAL V 19,012,000.00 19,012,000.00 12.67

REKAPITULASI
No URAIAN PEKERJAAN JUMLAH JUMLAH

I PEKERJAAN REHAB LANSEKAP (DEPAN PAGAR) 41,536,171.07 41,536,171.07 - - 27.69

II PEKERJAAN REHAB LANSEKAP (BELAKANG SELASAR) 23,340,066.42 23,340,066.42 - - 15.56

III PEKERJAAN REHAB LANSEKAP (KONTUR DEPAN ISTANA) 22,384,125.99 22,384,125.99 - - 14.92

IV PEKERJAAN REHAB LANSEKAP (BELAKANG RUJAB) 43,448,223.83 43,448,223.83 - - 28.97

V PEKERJAAN LAIN-LAIN 19,012,000.00 19,012,000.00 - - 12.67

TOTAL 149,720,587.30 149,720,587.30 99.81 Wajar


DIBULATKAN 149,720,000.00 149,720,000.00
JADWAL WAKTU PELAKSANAAN PEKERJAAN

PROGRAM : PENINGKATAN SARANA DAN PRASARANA APARATUR


KEGIATAN : REHABILITASI SEDANG/BERAT RUMAH JABATAN
PEKERJAAN : REHAB TAMAN RUJAB GUBERNUR
LOKASI : PALANGKARAYA
JUMLAH BOBOT MINGGU KE
NO. URAIAN PEKERJAAN
HARGA (%) I II III IV KET.
1 2 3 4 5
I PEKERJAAN REHAB LANSEKAP (DEPAN PAGAR) 41,536,171.07 27.74 9.25 9.25 9.25 100%

II PEKERJAAN REHAB LANSEKAP (BELAKANG SELASAR) 23,340,066.42 15.59 5.20 5.20 5.20

III PEKERJAAN REHAB LANSEKAP (KONTUR DEPAN ISTANA) 22,384,125.99 14.95 7.48 7.48 50%

IV PEKERJAAN REHAB LANSEKAP (BELAKANG RUJAB) 43,448,223.83 29.02 9.67 9.67 9.67

V PEKERJAAN LAIN-LAIN 19,012,000.00 12.70 6.35 6.35 0%


JUMLAH BIAYA FISIK 149,720,587.30 100.00

DIBULATKAN 149,720,000.00

Jumlah Bobot Komulatife 24.12 31.59 37.94 6.35


JANGKA WAKTU
TINGKAT KEMAJUAN Jumlah Bobot Kuantitatife 24.12 55.71 93.65 100.00 PELAKSANAAN 30
PEKERJAAN Rencana Kemajuan Bobot Pekerjaan (TIGA PULUH) HARI
KALENDER
Bobot Realisasi

Palangka Raya, 01 Nopember 2012


Keterangan :
CV. BERLIAN PERKASA
Kurva "S" Rencana = Pusat Palangka Raya

ATIKA SATRIA
Direktur
DAFTAR KUANTITAS DAN HARGA

PROGRAM : PENINGKATAN SARANA DAN PRASARANA APARATUR


KEGIATAN : REHABILITASI SEDANG/BERAT RUMAH JABATAN
PEKERJAAN : REHAB TAMAN RUJAB GUBERNUR
LOKASI : PALANGKARAYA
TAHUN ANGGARAN : 2012
HARGA SATUAN JUMLAH
NO. URAIAN PEKERJAAN ANALISA VOLUME
PEKERJAAN HARGA

I PEKERJAAN REHAB LANSEKAP (DEPAN PAGAR)


1 Pek. Timbunan Tanah Subur dan Penghamparan SNI 11-2835.A 70.50 M3 223,716.69 15,772,026.65
2 Pek. Tanam Angrek Tanah Ls 55.00 Rumpun 29,760.36 1,636,819.80
3 Pek. Tanam Krombusa Ls 85.00 Pohon 34,011.84 2,891,006.40
4 Pek. Tanam Palem Botol Ls 1.00 Pohon 538,920.00 538,920.00
5 Pek. Tanam Simbang Dara Ls 30.00 Pohon 42,514.80 1,275,444.00
6 Pek. Tanam Trikaler Besar Ls 10.00 Pohon 161,676.00 1,616,760.00
7 Pek. Tanam Olena Ls 6.00 Pohon 395,208.00 2,371,248.00
8 Pek. Tanam Daun Dara Ls 4.00 Pohon 12,574.80 50,299.20
9 Pek. Tanam Cemara Papua Ls 8.00 Pohon 297,004.80 2,376,038.40
10 Pek. Tanam Bonsai Dolar Ls 2.00 Pohon 1,856,280.00 3,712,560.00
11 Pek. Tanam Rumput Gajah Mini SNI.B.02 78.00 M2 119,167.29 9,295,048.62
SUB TOTAL I 41,536,171.07
II PEKERJAAN REHAB LANSEKAP (BELAKANG SELASAR)
1 Pek. Timbunan Tanah Subur dan Penghamparan SNI 11-2835.A 8.00 M3 223,716.69 1,789,733.52
2 Pek. Tanam Angrek Tanah Ls 76.00 Rumpun 29,670.90 2,254,988.40
3 Pek. Tanam Krombusa Ls 120.00 Pohon 33,909.60 4,069,152.00
4 Pek. Tanam Cemara Pentris Ls 4.00 Pohon 254,322.00 1,017,288.00
5 Pek. Pasang Kerikil Taman Ls 20.00 Zak 65,670.00 1,313,400.00
6 Pek. Pasang Pot Lonceng Besar Ls 6.00 Bh 591,030.00 3,546,180.00
7 Pek. Tanam Palm Bismar Ls 4.00 Pohon 593,418.00 2,373,672.00
8 Pek. Tanam Palm Phoniex Ls 4.00 Pohon 254,322.00 1,017,288.00
9 Pek. Tanam Rumput Gajah Mini SNI.B.02 50.00 M2 119,167.29 5,958,364.50
SUB TOTAL II 23,340,066.42
III PEKERJAAN REHAB LANSEKAP (KONTUR DEPAN ISTANA)
1 Pek. Timbunan Tanah Subur dan Penghamparan SNI 11-2835.A 16.00 M3 223,716.69 3,579,467.04
2 Pek. Tanam Rumput Paitan SNI.B.02 135.00 M2 33,367.29 4,504,584.15
3 Pek. Tanam Rumput Gajah Mini SNI.B.02 120.00 M2 119,167.29 14,300,074.80
SUB TOTAL III 22,384,125.99
IV PEKERJAAN REHAB LANSEKAP (BELAKANG RUJAB)
1 Pek. Timbunan Tanah Subur dan Penghamparan SNI 11-2835.A 14.00 M3 223,716.69 3,132,033.66
2 Pek. Tanam Angrek Tanah Ls 162.00 Rumpun 29,730.54 4,816,347.48
3 Pek. Tanam Krombusa Mini Ls 210.00 Pohon 29,730.54 6,243,413.40
4 Pek. Tanam Pandanus Ls 225.00 Pohon 10,193.33 2,293,498.80
5 Pek. Tanam Rulia Ls 230.00 Pohon 9,224.24 2,121,576.12
6 Pek. Tanam Alur Ls 662.00 Pohon 8,494.44 5,623,319.28
7 Pek. Tanam Bunga Bawang Ls 120.00 Pohon 9,343.88 1,121,266.08
8 Pek. Tanam Jaburan Ls 223.00 Pohon 7,645.00 1,704,834.11
9 Pek. Tanam Bakung Ls 140.00 Pohon 7,645.00 1,070,299.44
10 Pek. Tanam Pandan Bali Ls 3.00 Pohon 424,722.00 1,274,166.00
11 Pek. Tanam Terambulan Ls 100.00 Pohon 9,343.88 934,388.40
HARGA SATUAN JUMLAH
NO. URAIAN PEKERJAAN ANALISA VOLUME
PEKERJAAN HARGA
12 Pek. Tanam Asoka Ls 45.00 Pohon 10,193.33 458,699.76
13 Pek. Tanam Simbang Dara Ls 50.00 Pohon 42,472.20 2,123,610.00
14 Pek. Tanam Bligo Merah Ls 200.00 Pohon 12,562.20 2,512,440.00
15 Pek. Tanam Olena Ls 16.00 Pohon 394,812.00 6,316,992.00
16 Pek. Tanam Palm Phoniex Ls 2.00 Pohon 254,833.20 509,666.40
17 Pek. Tanam Rumput Gajah Mini SNI.B.02 10.00 M2 119,167.29 1,191,672.90
SUB TOTAL IV 43,448,223.83
V PEKERJAAN LAIN-LAIN
1 Pek. Pupuk Kandang Ls 240.00 Zak 27,000.00 6,480,000.00
2 Pek. Perapihan Pekerjaan Akhir Ls 1.00 Sat 1,246,000.00 1,246,000.00
Upah Kerja Jasa Perawatan/Pemeliharaan 4 Orang x 1 Bulan (Harga
3 Ls 120.00 Hari 94,050.00 11,286,000.00
Laden/Buruh)
SUB TOTAL V 19,012,000.00

REKAPITULASI
No URAIAN PEKERJAAN JUMLAH

I PEKERJAAN REHAB LANSEKAP (DEPAN PAGAR) 41,536,171.07

II PEKERJAAN REHAB LANSEKAP (BELAKANG SELASAR) 23,340,066.42

III PEKERJAAN REHAB LANSEKAP (KONTUR DEPAN ISTANA) 22,384,125.99

IV PEKERJAAN REHAB LANSEKAP (BELAKANG RUJAB) 43,448,223.83

V PEKERJAAN LAIN-LAIN 19,012,000.00

TOTAL 149,720,587.30

DIBULATKAN 149,720,000.00

TERBILANG : // SERATUS EMPAT PULUH SEMBILAN JUTA TUJUH RATUS DUA PULUH RIBU RUPIAH //

Palangka Raya, 01 Nopember 2012

CV. BERLIAN PERKASA


Pusat Palangka Raya

ATIKA SATRIA
Direktur
URAIAN PERHITUNGAN VOLU
(BACK UP DATA)

PROGRAM : PENINGKATAN SARANA DAN PRASARANA

KEGIATAN : REHABILITASI SEDANG/BERAT RUMAH JABATAN

PEKERJAAN : PENATAAN HALAMAN ISTANA ISEN MULANG

LOKASI : PALANGKARAYA

TAHUN ANGGARAN : 2012

NO. URAIAN PEKERJAAN

1 2

I PEKERJAAN PERSIAPAN

1 Pek. Pembuatan Papan Nama Kegiatan

2 Pek. Bongkaran Pondasi Kolam

3 Pek. Pembuatan Jalan Masuk Sementara (Kayu Dolken)

SUB TOTAL I

II PEKERJAAN TIMBUNAN TANAH

1 Pek. Timbunan/Urugan Tanah Kolam + Termasuk Penghamparan

2 Pek. Timbunan Tanah Subur

SUB TOTAL II

III PEKERJAAN TAMAN

1 Pek. Pupuk Kandang


2 Pek. Penanaman rumput paitan

SUB TOTAL II

IV PEKERJAAN LAIN-LAIN

1 Pek. Bongkaran Plankson dan Pemasangan Kembali (Untuk Jalan Masuk)


TUNGAN VOLUME
UP DATA)

BATAN

BACK UP DATA VOLUME

3 4

1.00 1.00 Bh

(6,8+5,6+22,63+8,9)*((0,4+0,7)/2)*2,5 60.40 M3

1 1.00 Pkt

(931,55*2,5) 2,328.88 M3

(1237,71*0,1) 123.77 m3

335.00 335.00 Zak


1237.71 1,237.71 M2

1 1.00 Pkt
DAFTAR ANALISA PEKERJAAN

SNI 01.6.14 1 M3 Bongkaran dinding tembok bata merah

Harga Satuan
Kebutuhan Satuan Indeks Jumlah (Rp.)
Bahan/Upah (Rp.)

Mandor OH 0.0330 135,729 4,479


Tenaga Kerja
Pembantu tukang OH 6.6670 94,050 627,031

Jumlah Harga Per Satuan Pekerjaan 631,510

SNI 11-2835 Mengurug 1 m3 Pasir/Tanah Urug

Harga Satuan
Kebutuhan Satuan Indeks Jumlah
Bahan/Upah

Bahan Pasir Urug/Tanah Urug M3 1.200 Rp 69,749.50 Rp 83,699.40

Pekerja OH 0.300 Rp 94,050.00 Rp 28,215.00


Tenaga Kerja
Mandor OH 0.010 Rp 135,729.00 Rp 1,357.29

Jumlah Harga Per Satuan Pekerjaan Rp 113,271.69

SNI.B.02 1 M2 Menanam Rumput

Harga Satuan
Kebutuhan Satuan Indeks Jumlah
Bahan/Upah

Bahan Rumput Paitan M2 1.100 Rp 12,000.00 Rp 13,200.00

Rumput Gajah Mini M2 1.100 Rp 90,000.00 Rp 99,000.00

Pekerja OH 0.200 Rp 94,050.00 Rp 18,810.00


Tenaga Kerja
Mandor OH 0.010 Rp 135,729.00 Rp 1,357.29

Jumlah Harga Per Satuan Pekerjaan Rumput Paitan Rp 33,367.29

Jumlah Harga Per Satuan Pekerjaan Rumput Gajah Mini Rp 119,167.29

SNI 11-2835.A Mengurug 1 m3 Tanah Subur

Harga Satuan
Kebutuhan Satuan Indeks Jumlah
Bahan/Upah

Bahan Tanah Subur M3 1.200 Rp 161,787.00 Rp 194,144.40


Pekerja OH 0.300 Rp 94,050.00 Rp 28,215.00
Tenaga Kerja
Mandor OH 0.010 Rp 135,729.00 Rp 1,357.29

Jumlah Harga Per Satuan Pekerjaan Rp 223,716.69


DAFTAR HARGA SATUAN UPAH DAN BAHAN

No Uraian Satuan HARGA SATUAN

A. UPAH TENAGA KERJA

1 Mandor Org/Hari 135,729.00

2 Tukang Gali Tanah Org/Hari 94,050.00

3 Kepala Tukang Batu Org/Hari 125,433.00

4 Tukang Batu Org/Hari 114,840.00

5 Laden Tukang Batu Org/Hari 94,050.00

6 Kepala Tukang Kayu Org/Hari 125,433.00

7 Tukang Kayu Org/Hari 114,840.00

8 Laden Tukang Kayu Org/Hari 94,050.00

9 Kepala Tukang Besi Org/Hari 125,433.00

10 Tukang Besi Org/Hari 114,840.00

11 Laden Tukang Besi Org/Hari 94,050.00

12 Kepala Tukang Cat Org/Hari 125,433.00

13 Tukang Cat Org/Hari 114,840.00

14 Laden Tukang Cat Org/Hari 94,050.00

B. BAHAN BANGUNAN

1 Tanah Urug/Pasir Urug M3 69,749.50

2 Tanah Subur M3 161,787.00

2 Rumput Paitan M2 11,940.00

3 Rumput Gajah Mini M2 69,650.00