JOB/ PROJECT : .............

TAKER OFF : WAHYUHAWARI (18-136)


ELEMENT : PEKERJAAN PENDAHULUAN
DATE :
SHEET NO : 1 s/d ……………

SKETSA GAMBAR ITEM PEKERJAAN VOLUME SAT

1 PEKERJAAN PENDAHULUAN

1 Pembersihan Lapangan 16,947.49 M2


2 Pas. Pagar Proyek seng t = 2 m 525.54 M1
3 Direksi Keet 30.00 M2
4 Papan Nama Proyek 1.00 Ls
5 Pas. Papan Bouplank 364.66 M1
6 Mobilisasi dan Demobilisasi 1.00 Ls

NO PERHITUNGAN VOLUME SAT

1 Pembersihan Lapangan

Pjg Sum X = 149.12 m


Pjg Sum Y = 113.65 m

149.12
113.65
Rumus : V = P x L 16,947.49 M2

2 Pas. Pagar Proyek seng t = 2 m

Pjg Sum X = 149.12 + 2.00 = 151.12 m


Pjg Sum Y = 113.65 + 2.00 = 115.65 m

2
/
149.12
113.65
Rumus : V = 2 x ((P+2) +(L+2)) 525.54 M1

3 Direksi Keet

Pjg Sum X = 6.00


Pjg Sum Y = 5.00

6.00
5.00
Rumus : V = P x L 30.00 M2

4 Papan Nama Proyek

V = 1.00 Ls

1.00
1.00 Ls

5 Pas. Papan Bouplank

Pjg Sum X = 118.83 + 2.00 = 120.83 m


Pjg Sum Y = 59.50 + 2.00 = 61.50 m

2
/
120.83
61.50
Rumus : V = 2 x ((P-2) +( L-2)) 364.66 M1

6 Mobilisasi dan Demobilisasi

V = 1.00 Ls

1.00
1.00 Ls
JOB/ PROJECT :
TAKER OFF : SITI KHOFIFAH RAHMADHANI
ELEMENT : PEKERJAAN PONDASI BORED PILE
DATE :
SHEET NO : 1 s/d ……………
SKET GAMBAR

B PEKERJAAN PONDASI BORED PILE ∅ 𝟏𝟎𝟎 𝒄𝒎

1 pengeboran tanah untuk pondasi


2 pembuangan air tanah (dewatering)
3 pembesian pondasi bored pile D 22
4 pembesian pondasi bored pile D 13
5 beton pondasi bored pile

NO ACTUAL CHECK/ PEKERJAAN VOLUME

1 pengeboran tanah untuk pondasi

kedalaman pondasi = 38 m r=D:2


luas lingkaran = 𝜋𝑟 r=1m:2 = 0.5
^2
= 0.79 m2
jumlah pondasi = 256 titik 256
/
0.79
38.00
Rumus : V = kedalaman pondasi x luas lingkaran x jumlah pondasi

2 pembuangan air tanah ( dewatering )

dalam muka air tanah = kedalaman pondasi - kedalaman muka tanah


= 36 m
luas lingkaran = 𝜋𝑟
^2
= 0.79 m2
256
/
jumlah pondasi = 256 titik 0.79
36.00
Rumus : V = dalam muka air tanah x luas lingkaran x jumlah pondasi

3 pembesian pondasi bored pile D 22

◊ potongan A 14 D 22 ( tulangan utama )


banyak tulangan = 14
diameter tulangan = 0.022
jumlah pondasi = 256 titik
rumus besi = D X D X 0,074 : 12
= 2.98
bengkokan = 2X6XD
= 0.26
panjang = panjang besi + bengkokan
= 1 + 10 + 1 + bengkokan
= 12 + 0.26
= 12.26 m
berat besi tulangan utama = panjang besi x jumlah besi x rumus besi x jumlah pondasi
= 131,188.56 kg

◊ potongan B 10 D 22 ( tulangan utama )


banyak tulangan = 10
diameter tulangan = 0.022
jumlah pondasi = 256 titik
rumus besi = D X D X 0,074 : 12
= 2.98
bengkokan = 2X6XD
= 0.26
panjang = panjang besi + bengkokan
= 11 + 1 + bengkokan
= 12 + 0.26
= 12 m
berat besi tulangan utama = panjang besi x jumlah besi x rumus besi x jumlah pondasi
= 93,706.12 kg

◊ potongan C 5 D 22 ( tulangan utama )


banyak tulangan = 5
diameter tulangan = 0.022
jumlah pondasi = 256 titik
rumus besi = D X D X 0,074 : 12
= 2.98
bengkokan = 2X6XD
= 0.26
panjang = panjang besi + bengkokan
= 11 + 1 + bengkokan
= 12 + 0.26
= 12 m
berat besi tulangan utama = panjang besi x jumlah besi x rumus besi x jumlah pondasi
= 46,853.06 kg

◊ potongan D 5 D 22 ( tulangan utama )


banyak tulangan = 5
diameter tulangan = 0.022
jumlah pondasi = 256 titik
rumus besi = D X D X 0,074 : 12
= 2.98
bengkokan = 2X6XD
= 0.26
panjang = panjang besi + bengkokan
= 6 + bengkokan
= 6.26 m
berat besi tulangan utama = panjang besi x jumlah besi x rumus besi x jumlah pondasi
= 23,930.82 kg

jumlah berat besi = 295,678.56 kg

4 pembesian spiral pondasi bored pile D 13

A. Potongan A Tulangan Sengkang (spiral) d 13 - 100


panjang besi ( C ) = 10 m
jarak besi spiral ( B ) = 0.10 m
selimut beton = 0.05 m
diameter pondasi = 1.00 m
diameter dalam ( A ) = diameter pondasi - 2 x selimut beton
= 0.90
𝜋 = 3.14
diameter tulangan ( d ) = 0.013
jumlah pondasi ( n ) = 256
rumus besi = D X D X 0,074 : 12
= 1.04

L = (C / B X 𝝅 ( A + d )) + (8*D)
= 286.786 m

V = L * Jumlah Pondasi * Rumus Besi yang Digunakan


= 76,512.98 kg

B. Potongan B Tulangan Sengkang (spiral) d 13 - 200


panjang besi ( C ) = 11 m
jarak besi spiral ( B ) = 0.20 m
selimut beton = 0.05 m
diameter pondasi = 1.00 m
diameter dalam ( A ) = diameter pondasi - 2 x selimut beton
= 0.90
𝜋 = 3.14
diameter tulangan ( d ) = 0.013
jumlah pondasi ( n ) = 256
rumus besi = D X D X 0,074 : 12
= 1.04

L = (C / B X 𝝅 ( A + d )) + (8*D)
= 157.779 m

V = L * Jumlah Pondasi * Rumus Besi yang Digunakan


= 42,094.62 kg

C. Potongan C dan D Tulangan Sengkang (spiral) d 13 -300


panjang besi ( C ) = 17 m
jarak besi spiral ( B ) = 0.30 m
selimut beton = 0.05 m
diameter pondasi = 1.00 m
diameter dalam ( A ) = diameter pondasi - 2 x selimut beton
= 0.90
𝜋 = 3.14
diameter tulangan ( d ) = 0.013
jumlah pondasi ( n ) = 256
rumus besi = D X D X 0,074 : 12
= 1.04

L = (C / B X 𝝅 ( A + d )) + (8*D)
= 162.557 m

V = L * Jumlah Pondasi * Rumus Besi yang Digunakan


= 43,369.38 kg

jumlah berat besi = 161,976.97 kg

5 beton pondasi bored pile

kedalaman beton = 38 m

luas lingkaran = 𝜋𝑟
^2
= 0.79 m2

jumlah pondasi = 256 titik 256


/
0.79
38.00
Rumus : V = kedalaman beton x luas lingkaran x jumlah pondasi
7,636.48 M3
7,234.56 M3
Kg
Kg
- -

SATU
AN

7,636.48 M3

7,234.56 M3
7,636.48 M3
JOB/ PROJECT : . . . . . . . . . . . . . diisi
TAKER OFF : WAHYU HAWARI (18-136)
ELEMENT : PEKERJAAN PONDASI BORED PILE
DATE :
SHEET NO : 1 s/d ……………

SKET GAMBAR ITEM PEKERJAAN VOLUME SAT

2 PEKERJAAN PONDASI BORED PILE

- PONDASI BORED PILE


1. PENGEBORAN 2,244.60 M1
2. CASING 2,244.60 M1
3. PEKERJAAN PEMBESIAN
a. Tulangan Utama Kg
b. Tulangan Pengikat Kg
4. PENEGORAN 11,276.87 M3

- Type Selanjutnya
1. PEKERJAAN BETON KOLOM ...... M3
2. PEKERJAAN BEKISTING KOLOM ...... M2
3. PEKERJAAN PENULANGAN KOLOM ...... Kg

ACTUAL CHECK/ PEKERJAAN


N0 VOLUME SATUAN

- PONDASI BORED PILE

1. PENGEBORAN

panjang = 25.80 m 87
/ 25.80
2,244.60 M1

2. CASING

panjang = 25.80 m
87
/
25.80
2,244.60 M1

3. PEKERJAAN PEMBESIAN

Tinggi Bored Pile = 25.80 m'


Jumlah = 87 titik

Pembesian
Tulangan Pokok D 19

Besi menerus sampai kebawah pondasi 5D19


panjang (mm)

25800.00
add
laping ke pile cap
= 900 900

bengkokan
= 2.6.D
= 2 x 6 x 19
= 228 228
26928 87
/
5
/
less s.b 26.83
= 2 x 50 11671.05
= 100 100
26828

Besi dengan bentangan 11,10 m (9D19)


panjang (mm)

11100
add
laping ke pile cap
= 900 900
lapping ke bawah
= 900 900
bengkokan
= 2.6.D
= 2 x 6 x 19
= 228 228
13128

less s.b
= 50 50
13078
87
/
9
/
Berat besi 13.08
= DXDx0,074 10241.64
12
= 19 x 19 x 0.074
12
= 2.22616666666667

Berat Total besi D19


= 30014.13 x 2.226166667
= 66816.4557450047 Kg

Tulangan Pengikat bentangan 22,2 m


D13-75

panjang = √( 3,14 h/h1 x D )2 + h2

4 PENGECORAN

V = luas lingkaran x tinggi 87


/
= 3,14 x ( 400 )2 x 25,80 3.14
1.6
25.8
11,276.87 M3
JOB/ PROJECT
TAKER OFF
ELEMENT
DATE
SHEET NO

SKETSA GAMBAR ITEM PEKERJAA

1 PEKERJAAN PENDAHULUA

1 Pembersihan Lapangan
2 Pas. Pagar Proyek seng t = 2
3 Direksi Keet
4 Papan Nama Proyek
5 Pas. Papan Bouplank
6 Mobilisasi dan Demobilisasi

NO PERHITUNGAN

1 Pembersihan Lapangan

Pjg Sum X
Pjg Sum Y
Rumus : V = P x L

2 Pas. Pagar Proyek seng t = 2 m

Pjg Sum X 108.85 m


Pjg Sum Y 94.03 m

Rumus : V = 2 x ((P+2) +(L+2))

3 Direksi Keet

Pjg Sum X
Pjg Sum Y

Rumus : V = P x L

4 Papan Nama Proyek

V
5 Pas. Papan Bouplank

Pjg Sum X 106.85 m


Pjg Sum Y 92.03 m

Rumus : V = 2 x ((P-2) +( L-2))

6 Mobilisasi dan Demobilisasi

V
ITEM PEKERJAAN VOLUME SAT

JAAN PENDAHULUAN

rsihan Lapangan 9,832.87 M2


agar Proyek seng t = 2 m 405.75 M1
30.00 M2
Nama Proyek 1.00 Ls
apan Bouplank 397.75 M1
sasi dan Demobilisasi 1.00 Ls

VOLUME SAT

106.85
92.03
9,832.87 M2

2
/
108.85
94.03
405.75 M1

6.00
5.00
30.00 M2

1.00
1.00 Ls
2
/
106.85
92.03
397.75 M1

1.00
1.00 Ls