REKAPITULASI TOTAL ANGGARAN BIAYA

PEKERJAAN TALUD

JUMLAH HARGA
No URAIAN PEKERJAAN
(Rp.)

I. PEKERJAAN PERSIAPAN 25,000,000.00

II. PEK. TALUD , L = 254 m' 1,920,219,125.00

JUMLAH BIAYA 1,945,219,125.00


DIBULATKAN 1,945,219,000.00

Terbilang : Satu milyar sembilan ratus empat puluh lima juta dua ratus sembilan belas ribu rupiah.
DAFTAR KUANTITAS DAN HARGA
PEMBANGUNAN TALUD

Volume Harga Satuan Jumlah Harga


No. Uraian Pekerjaan Satuan
( Rp. ) ( Rp. )

I. PEKERJAAN PERSIAPAN
Mobilisasi Dan Dembilisasi Ls 1.000 25,000,000.00 25,000,000.00

Jumlah 25,000,000.00

II. PEK. TALUD , L = 254 m'


1 Pasangan Batu Kali m3 1,219.84 500,000.00 609,917,500.00
2 Pasangan Batu Bolder m3 3,338.76 375,000.00 1,252,033,125.00
3 Plesteran m2 655.35 30,000.00 19,660,500.00
4 Beton Diatas Talud m3 40.64 950,000.00 38,608,000.00
Jumlah 1,920,219,125.00
ANALISIS HARGA SATUAN
PENYELESAIAN PEMBAGUNAN DERMAGA WATUSAMPU

Harga Satuan Jumlah Harga


No Uraian Satuan Koefisien
( Rp ) ( Rp )

Mobilisasi Dan Demobilisasi


Compressor Unit 2.00 400,000.00 800,000.00
Concrete Mixer Unit 5.00 500,000.00 2,500,000.00
Concrete Vibrator Unit 3.00 300,000.00 900,000.00
Dump Truck Unit 3.00 1,000,000.00 3,000,000.00
Ponton Pancang Unit 1.00 65,000,000.00 65,000,000.00
Alat Pancang Unit 1.00 40,000,000.00 40,000,000.00
Water Tank Truk Unit 1.00 1,000,000.00 1,000,000.00
Crane Kap.35 ton Unit 1.00 25,000,000.00 25,000,000.00
Mesin Gilas Unit 1.00 10,000,000.00 10,000,000.00
Diesel Hammer K.35 Unit 1.00 12,000,000.00 12,000,000.00
Generator Set Unit 1.00 300,000.00 300,000.00
Mesin Las Listrik dan Perlengkapannya Unit 2.00 300,000.00 600,000.00
Pompa Air Unit 1.00 300,000.00 300,000.00
Water Pass Unit 2.00 250,000.00 500,000.00
Theodolite Unit 1.00 250,000.00 250,000.00
Jumlah 162,150,000.00

Pengukuran Dan Positioning


Theodolite Hari 30.00 200,000.00 6,000,000.00
Waterpass Hari 30.00 200,000.00 6,000,000.00
Pekerja Hari 30.00 50,000.00 1,500,000.00
Juru Ukur Hari 30.00 70,000.00 2,100,000.00
Jumlah 15,600,000.00

Penerangan Lokasi Pekerjaan/Penyelamatan


Genset Hari 60.00 210,000.00 12,600,000.00
Kabel dan Lampu LS 1.00 750,000.00 750,000.00
Mekanik Hari 60.00 65,000.00 3,900,000.00
Solar Ltr 200.00 9,500.00 1,900,000.00
Olie Ltr 20.00 38,500.00 770,000.00
Peralatan PPPK LS 1.00 1,000,000.00 1,000,000.00
Jumlah 20,920,000.00

Biaya Pengujian dan Laboratorium


Pembuatan Job Mix Formula Ls 1.00 6,500,000.00 6,500,000.00
Pengujian Kubus Beton Ls 1.00 5,000,000.00 5,000,000.00
Pengujian Pemadatan tanah Ls 1.00 3,500,000.00 3,500,000.00
Jumlah 15,000,000.00

Dokumentasi/Administrasi/As Built Drawing


Kertas A3 Rol 2.00 100,000.00 200,000.00
Kertas A4 Rim 5.00 45,000.00 225,000.00
Film & Cetak Rol 10.00 70,000.00 700,000.00
Album Set 10.00 70,000.00 700,000.00
Juru Gambar Hari 90.00 70,000.00 6,300,000.00
Jumlah 8,125,000.00

1 LS -Penyediaan Air Kerja


Biaya Operasional Water Tanker Ls 1.00 8,000,000.00 8,000,000.00
Jumlah 8,000,000.00
Harga Satuan Jumlah Harga
No Uraian Satuan Koefisien
( Rp ) ( Rp )
1 Zak - Semen Pc
Semen P.C Zak 1.00 64,000.00 64,000.00
Transport dan Upah Bongkar di Lokasi Zak 1.00 1,000.00 1,000.00
Jumlah 65,000.00

1 M2 - Keet Pengawas dan Kantor Kontraktor


Bahan / Material Ls 1.00 413,532.00 413,532.00
Pekerja Hr 0.20 50,000.00 10,000.00
Tukang batu Hr 0.50 58,000.00 29,000.00
Tukang kayu Hr 0.50 58,000.00 29,000.00
Mandor Hr 0.04 65,000.00 2,600.00
Jumlah 484,132.00

1 M2 - Barak Kerja, Gudang dan Bengkel


Bahan / Material Ls 1.00 300,000.00 300,000.00
Pekerja Hr 0.20 50,000.00 10,000.00
Tukang Batu Hr 0.50 58,000.00 29,000.00
Tukang Kayu Hr 0.50 58,000.00 29,000.00
Mandor Hr 0.04 65,000.00 2,600.00
Jumlah 370,600.00

1 M' - Profil Baja Siku Untuk Deletasi 100.100.10


Besi Siku L 80.80.8 Kg 9.66 14,500.00 140,070.00
Besi Beton Kg 3.20 12,500.00 39,949.20
Kawat Las Kg 0.25 45,000.00 11,250.00
Pekerja Hari 1.00 50,000.00 50,000.00
Mandor Hari 0.10 65,000.00 6,500.00
Tukang Besi Hari 0.01 58,000.00 580.00
Mesin Las Listrik dan Perlengkapannya Hari 0.57 425,000.00 242,857.14
Jumlah 491,206.34

1 M3 - Pekerjaan Beton K-300


Ready Mix M3 1.00 1,098,500.00 1,098,500.00
Concrete Pump M3 1.00 162,500.00 162,500.00
Upah Kerja M3 1.00 150,000.00 150,000.00
Jumlah 1,411,000.00

Pembesian dengan Besi Polos atau besi Ulir / Kg


Pekerja Hari 0.05 50,000.00 2,500.00
Tukang Besi Hari 0.005 58,000.00 290.00
Kepala Tukang Hari 0.005 65,000.00 325.00
Mandor Hari 0.0025 65,000.00 162.50
Besi Beton Kg 1.050 12,500.00 13,125.00
Kawat Beton Kg 0.015 20,000.00 300.00
Jumlah 16,702.50

1 M2 - Pekerjaan Cetakan Beton/Bekisting


Papan/Kayu Klas II M3 0.08 1,800,000.00 150,876.00
Paku Kg 0.50 19,000.00 9,500.00
Pekerja Hari 0.50 50,000.00 25,000.00
Mandor Hari 0.05 65,000.00 3,250.00
Tukang Kayu Hari 1.00 58,000.00 58,000.00
Kepala Tukang Hari 0.05 65,000.00 3,250.00
Tukang Bongkar Cetakan Beton/Siram Hari 0.50 40,000.00 20,000.00
Jumlah 269,876.00
Harga Satuan Jumlah Harga
No Uraian Satuan Koefisien
( Rp ) ( Rp )
1 M2 - Pekerjaan Perancah Pengecoran
Balok Kayu Klas II M3 0.15 1,800,000.00 270,000.00
Paku Kg 1.00 19,000.00 19,000.00
Pekerja Hari 2.00 50,000.00 100,000.00
Mandor Hari 0.10 65,000.00 6,500.00
Tukang Kayu Hari 1.00 58,000.00 58,000.00
Kepala Tukang Hari 0.05 65,000.00 3,250.00
Tukang Bongkar Cetakan Beton/Siram Hari 0.10 40,000.00 4,000.00
Jumlah 460,750.00

1 - M3 Beton untuk Lantai Kerja K-175


Semen P.C Zak 5.31 65,000.00 345,150.00
Batu Pecah 2/3 M3 1.00 187,500.00 187,500.00
Pasir beton M3 0.500 90,000.00 45,000.00
Pekerja Hr 6.00 50,000.00 300,000.00
Tukang Hr 0.50 58,000.00 29,000.00
Kepala Tukang Hr 0.05 65,000.00 3,250.00
Mandor Hr 0.30 65,000.00 19,500.00
Jumlah 929,400.00

1 M3 - Pekerjaan Beton Bertulang Untuk Dudukan Tiang Listrik


Beton K 300 M3 1.00 1,411,000.00 1,411,000.00
Cetakan Beton M2 5.00 269,876.00 1,349,380.00
Pembesian Kg 250.00 16,702.50 4,175,625.00
Perancah Kerja Pengecoran M2 1.00 460,750.00 460,750.00
Jumlah 7,396,755.00

1 M2 - Pengecatan Kanstain (2 x )
Cat Kg 0.350 41,500.00 14,525.00
Thinner/Minyak Cat Ltr 0.250 30,000.00 7,500.00
Pekerja Hari 0.150 50,000.00 7,500.00
Tukang Cat Hari 0.250 58,000.00 14,500.00
Kepala Tukang Hari 0.025 65,000.00 1,625.00
Mandor Hari 0.008 65,000.00 520.00
Jumlah 46,170.00

1 Ton - Tiang Baja Ø 508 mm & 711,2 mm , t = 12 mm


T.P pipa baja Ø 508 mm & 711,2 mm , t = 12 mm Ton 1.00 13,000,000.00 13,000,000.00
Transport dari pabrik ke Pelabuhan Awal Ton 1.00 300,000.00 300,000.00
Bongkar muat di Pelabuhan Awal Ton 1.00 150,000.00 150,000.00
Transport dari Pel. Awal ke Pel. Tujuan per m3 M3 2.00 950,000.00 1,900,000.00
( 1 ton pipa ekivalent dengan 2 m3 volume )
Bongkar muat di Pelabuhan Tujuan Ton 1.00 150,000.00 150,000.00
Transport dari Pel. Tujuan ke Lokasi per m3 M3 2.00 300,000.00 600,000.00
( 1 ton pipa ekivalent dengan 2 m3 volume )
Bongkar Muat di Lokasi Pekerjaan Ton 1.00 150,000.00 150,000.00
Jumlah 16,250,000.00

1 M' - Pengangkutan Tiang Pancang Ke Titik Pancang


A. Biaya Crawler Crane/Hari
Operator Hari 1.00 70,000.00 70,000.00
Pembantu Operator Hari 2.00 50,000.00 100,000.00
Olie Ltr 5.00 38,500.00 192,500.00
Solar Ltr 250.00 9,500.00 2,375,000.00
Grease Kg 2.00 28,300.00 56,600.00
Crane Hari 1.00 48,000.00 48,000.00
Jumlah 2,842,100.00
Harga Satuan Jumlah Harga
No Uraian Satuan Koefisien
( Rp ) ( Rp )
B. Biaya Ponton Transport/Hari
Operator Hari 1.00 70,000.00 70,000.00
Pembantu Operator Hari 2.00 50,000.00 100,000.00
Pekerja Hari 10.00 50,000.00 500,000.00
Olie Ltr 5.00 38,500.00 192,500.00
Solar Ltr 200.00 9,500.00 1,900,000.00
Grease Kg 2.00 28,300.00 56,600.00
Ponton Transport Hari 1.00 3,150,000.00 3,150,000.00
Jumlah 5,969,100.00

Dalam sehari dapat diangkut tiang pancang sepanjang (L1) :


10 buah x panjang 12 m = 120.00
Biaya transport tiang pancang per meter (A+B)/L1 Rp. 73,426.67

1 Titik - Pemancangan Tiang Pancang


C. Biaya Diesel Hammer
Operator Hari 1.00 70,000.00 70,000.00
Pembantu Operator Hari 2.00 50,000.00 100,000.00
Pekerja Hari 3.00 50,000.00 150,000.00
Olie Ltr 4.00 38,500.00 154,000.00
Solar Ltr 200.00 9,500.00 1,900,000.00
Grease Kg 2.00 28,300.00 56,600.00
Diesel Hammer Hari 1.00 3,150,000.00 3,150,000.00
Jumlah 5,580,600.00

D. Biaya Ponton Pancang


Operator Hari 1.00 70,000.00 70,000.00
Pembantu Operator Hari 2.00 50,000.00 100,000.00
Tukang Pancang Hari 10.00 58,000.00 580,000.00
Olie Ltr 4.00 38,500.00 154,000.00
Solar Ltr 40.00 9,500.00 380,000.00
Grease Kg 2.00 28,300.00 56,600.00
Ponton Pancang Hari 1.00 3,720,000.00 3,720,000.00
Jumlah 5,060,600.00

- Tiang Tegak
Sehari dapat dipancang tiang tegak sepanjang (L2) :
2,5 buah x panjang 12 m = 30.00 m
Harga pemancangan tiang tegak per meter = (C+D)/L2 + (A+B)/L1 = 428,133.33

- Tiang Miring
Sehari dapat dipancang tiang miring sepanjang (L3) :
2 buah x panjang 12 m = 24.00 m
Harga pemancangan tiang miring per meter = (C+D)/L3 + (A+B)/L1 = 516,810.00

1 M2 - Pengecatan Tiang Pancang (12.0 M /Tiang)


AC Marine Use (antiCerosif M.U) Kg 0.200 0.00
AF Marine Use (Anti Fouling M.U) Ltr 0.100 0.00
Mandor Hari 0.008 65,000.00 520.00
Pekerja Hari 0.150 50,000.00 7,500.00
Kepala Tukang Hari 0.025 65,000.00 1,625.00
Tukang Cat Hari 0.250 58,000.00 14,500.00
Jumlah 24,145.00
2 x Cat 48,290.00
Harga Satuan Jumlah Harga
No Uraian Satuan Koefisien
( Rp ) ( Rp )
1 Bh - Penyambungan Tiang Pancang
Kawat Las/Elektroda Kg 3.00 45,000.00 135,000.00
Plat Baja Kg 45.00 15,800.00 711,000.00
Tukang Las Hari 0.75 60,000.00 45,000.00
Mandor Hari 0.10 65,000.00 6,500.00
Pekerja Hari 1.50 50,000.00 75,000.00
Mesin Las Listrik dan Perlengkapannya Hari 0.14 425,000.00 60,714.29
Generator Set Hari 0.14 210,000.00 30,000.00
Alat Bantu Pemotongan Tiang Pancang LS 1.00 2,500.00 2,500.00
Jumlah 1,065,714.29

1 Bh - Pemotongan Tiang Pancang


Oxygen Tabung 0.50 320,000.00 160,000.00
Karbit Kg 1.00 17,500.00 17,500.00
Tukang Las Hari 0.45 60,000.00 27,000.00
Mandor Hari 0.10 65,000.00 6,500.00
Pekerja Hari 0.75 50,000.00 37,500.00
Mesin Las Listrik dan Perlengkapannya Hari 0.57 425,000.00 242,857.14
Alat Bantu LS 0.57 12,000.00 6,857.14
Jumlah 498,214.29

1 Bh - Plat Penutup Tiang


Kawat Las/Elektroda Kg 3.00 45,000.00 135,000.00
Besi Plat Kg 25.00 15,800.00 395,000.00
Tukang Las Hari 0.15 60,000.00 9,000.00
Mandor Hari 0.05 65,000.00 3,380.00
Pekerja Hari 1.00 50,000.00 50,000.00
Mesin Las Listrik dan Perlengkapannya Hari 0.43 425,000.00 182,142.86
Generator Set Hari 0.57 210,000.00 120,000.00
Alat Bantu Penutup Tiang Pancang LS 1.00 10,000.00 10,000.00
Jumlah 904,522.86

1 Bh - Tiang Listrik + Lampu Mercury + Instalasi


Tiang Listrik Galvanis Bh 1.00 7,850,000.00 7,850,000.00
Lampu Mercury Bh 1.00 2,750,000.00 2,750,000.00
Biaya Pemasangan Ls 1.00 950,000.00 950,000.00
Kabel Listrik dan perlengkapannya Ls 1.00 2,850,000.00 2,850,000.00
Alat Bantu Ls 1.00 1,000,000.00 1,000,000.00
Jumlah 15,400,000.00

1 M2 - Plesteran 1 PC : 4 Psr, Tebal 15 mm


Semen Portland Zak 0.170 64,000.00 10,880.00
Pasir Pasang M3 0.017 90,000.00 1,530.00
Tukang Batu Hr 0.150 58,000.00 8,700.00
Pekerja Hr 0.200 50,000.00 10,000.00
Kepala Tukang Hr 0.015 65,000.00 975.00
Mandor Hr 0.010 65,000.00 650.00
Jumlah 32,735.00

Timbunan Pasir
Pasir urug M³ 1.100 90,000.00 99,000.00
Pekerja hari 0.300 50,000.00 15,000.00
Mandor hari 0.030 65,000.00 1,950.00
Jumlah 115,950.00

Timbunan Tanah
Tanah Urug M³ 1.100 87,000.00 95,700.00
Pekerja hari 0.100 50,000.00 5,000.00
Mandor hari 0.010 65,000.00 650.00
Mesin Gilas hari 0.025 1,925,000.00 48,125.00
Harga Satuan Jumlah Harga
No Uraian Satuan Koefisien
( Rp ) ( Rp )
Jumlah 149,475.00
Harga Satuan Jumlah Harga
No Uraian Satuan Koefisien
( Rp ) ( Rp )
1 M3- Galian Tanah Biasa
Pekerja Hari 0.526 50,000.00 26,300.00
Mandor Hari 0.052 65,000.00 3,380.00
Jumlah 29,680.00

1 M3- Urugan kembali


Pekerja Hari 0.192 50,000.00 9,600.00
Mandor Hari 0.019 65,000.00 1,235.00
Jumlah 10,835.00

1 M2 - Filter Cloth / Geotekstil


Geotekstil M2 1.20 50,800.00 60,960.00
tukang Selam Hr 0.10 55,000.00 5,500.00
Pekerja Hr 0.10 50,000.00 5,000.00
Tukang Hr 0.01 58,000.00 580.00
Alat Bantu Ls 1.00 500.00 500.00
Jumlah 72,540.00

1 M3 - Pasangan Batu Kali


batu Gunung / kali M3 1.20 100,000.00 120,000.00
Semen PC zak 3.50 65,000.00 227,500.00
Pasir Pasang M3 0.43 90,000.00 38,475.00
Tukang Hr 1.20 58,000.00 69,600.00
Kepala Tukang Hr 0.12 65,000.00 7,800.00
Pekerja Hr 2.60 50,000.00 130,000.00
Mandor Hr 0.18 65,000.00 11,700.00
Jumlah 605,075.00

1 M3 - Pasangan Batu Bolder


Batu Bolder M3 1.10 150,000.00 165,000.00
Tukang Hr 1.20 70,000.00 84,000.00
Excavator Jam 0.45 500,000.00 225,000.00
Jumlah 474,000.00

1 M2 - Pekerjaan Plester Siar


Semen PC zak 0.150 65,000.00 9,750.00
Pasir Pasang m3 0.010 90,000.00 900.00
Pekerja Hr 0.150 50,000.00 7,500.00
Tukang Hr 0.015 58,000.00 870.00
Kepala Tukang Hr 0.200 65,000.00 13,000.00
Jumlah 32,020.00

1 M3 Urugan Pasir Bawah Pondasi


Mandor Hari 0.01 65,000.00 650.00
Pasir Urug M3 1.20 90,000.00 108,000.00
Pekerja Hari 0.30 50,000.00 15,000.00
Jumlah 123,650.00
DAFTAR HARGA SATUAN
BAHAN, UPAH DAN PERALATAN
PENYELESAIAN PEMBAGUNAN DERMAGA WATUSAMPU

HARGA SATUAN
No URAIAN SATUAN
(Rp)

A. UPAH
1 Pekerja Hari 50,000.00
2 Tukang Besi / Beton / Kayu / Pancang Hari 58,000.00
3 Tukang Las Hari 60,000.00
4 Tukang Bongkar Cetakan / Siram Beton Hari 40,000.00
5 Tukang Selam Hari 55,000.00
6 Kepala Tukang Hari 65,000.00
7 Mandor Hari 65,000.00
8 Operator Hari 70,000.00
9 Pembantu Operator Hari 50,000.00
10 Mekanik Hari 65,000.00
11 Juru Ukur / Surveyor Hari 70,000.00
12 Juru Gambar Hari 70,000.00

B. BAHAN
1 Batu Split 1/2 M3 187,500.00
2 Batu Pecah 2/3 Cm M3 187,500.00
3 Pipa Baja Ø 508 mm, tebal = 12 mm (di Pabrik) Kg 13,000.00
4 Baja Profil Dan Plat Kg 15,800.00
5 Besi Beton (Ulir) Kg 12,500.00
6 Besi Siku L 80.80.80 Kg 14,500.00
7 Cat Besi / Cat Kayu Kg 41,500.00
8 Fender Type V 300 H-2000 L Bh 17,800,000.00
9 Bollard Baja Tuang Bh 29,300,000.00
Batu Bolder M3 150,000.00
10 Cleat Bh 338,500.00
11 Fibre Mesh Kg 161,000.00
12 Grease Kg 28,300.00
13 Geotextile M2 50,800.00
14 Kayu Kelas II ( Nantu ) M3 1,800,000.00
15 Kayu Kelas III ( daerah ) M3 1,500,000.00
16 Kawat Beton /Bindraad Kg 20,000.00
17 Besi Strip Kg 19,800.00
18 Angkur Dudukan Bolard Bh 78,000.00
19 Kawat Las Kg 45,000.00
20 Karbit Kg 22,425.00
21 Oxigen Tbg 320,000.00
HARGA SATUAN
No URAIAN SATUAN
(Rp)
22 Olie Ltr 38,500.00
23 Pasir Pasangan / Pasir Beton M3 90,000.00
24 Batu Gunung/Kali/Belah M3 100,000.00
25 Paku Kg 19,000.00
26 Semen PC Zak 64,000.00
27 Solar ( industri ) Ltr 9,500.00
28 Tanah Timbunan / Urug M3 87,000.00
29 Thinner / Minyak Cat Ltr 30,000.00

C. PERALATAN
1 Alat Survey Hari 200,000.00
2 Compressor Hari 170,500.00
3 Dump Truck Hari 550,000.00
4 Genset Hari 210,000.00
5 Mesin Las Listrik dan Perlengkapannya Hari 425,000.00
6 Pompa Air Hari 275,000.00
7 Vibrator Hari 93,500.00
8 Gurinda Potong Jam 48,000.00
9 Mesin Las dan perlengkapannya Hari 375,000.00
10 Mesin Gilas Hari 1,925,000.00
11 Ponton Transport Hari 3,150,000.00
12 Ponton Pancang Hari 3,720,000.00
Excavator Jam 500,000.00
13 Diesel Hammer Hari 3,150,000.00
BALOK MELINTANG DERMAGA
Lihat Gambar
L Total = 88.00 m
A 0.80 m
B 0.50 m
(juml Tul ats & bwh) tump kiri 12 bh
(Tul Utama) lap 9 bh
tump kanan 12 bh
besi dia 25 mm
(Tul Tengah) jumlah 4 bh
besi dia 16 mm
(Tul Sengkang) besi dia jarak
tump kiri 12 - 150 mm
lap 12 - 200 mm
tump kanan 12 - 150 mm

NO Jenis Balok Tumpuan Kiri Tumpuan Lapangan Tumpuan Kanan Total Berat

1 0 Lihat Gambar L Total = 88.00 m


30-Dec Beton A = 0.80 m Luas Total = 0.40 m2 V. Beton = 35.20 m3 Total berat Besi = Besi skng 12 1,408.19
B = 0.50 m Besi utama 25 3,964.09
Bekisting A bkst = 2.10 m Panjang Total = 2.10 m' L. Bekisting = 184.80 m2 Besi torsi 16 577.55

As Lihat Gambar perancah = 44 m2


Pembesian

a (Tul Utama)
(juml Tul ats & bwh) tump kiri 12
tump kanan 12 a = 0.100 m a total = 0.200 m a = 0.100 m a total = 0.200 m a = 0.100 m a total = 0.200 m
lap 9 b = 11.800 m b total = 11.800 m b = 11.800 m b total = 11.800 m b = 11.800 m b total = 11.800 m
a Besi D 25 W = 3.856 kg W = 3.856 kg W = 3.856 kg
L = 12.000 m L = 12.000 m L = 12.000 m
b c = 1.000 m c = 1.000 m c = 1.000 m
d = 10.800 m d = 10.800 m d = 10.800 m
L2 = 288.000 m L2 = 216.000 m L2 = 288.000 m
= 1110.6 kg = 832.95 kg = 1110.6 kg
Jadi untuk jarak per / m' berat besi = 49.142 kg Jadi untuk jarak per / m' berat besi = 36.856 kg Jadi untuk jarak per / m' berat besi = 49.142 kg 45.046
Bentang = 88.0 3,964.09
b (Tul Tengah) jumlah 4
besi dia 16 a = 0.064 m a total = 0.128 m a = 0.064 m a total = 0.128 m a = 0.064 m a total = 0.128 m
b = 11.872 m b total = 11.872 m b = 11.872 m b total = 11.872 m b = 11.872 m b total = 11.872 m
a W = 1.580 kg W = 1.580 kg W = 1.580 kg
L = 12.000 m L = 12.000 m L = 12.000 m
b c = 0.640 m c = 0.640 m c = 0.640 m
d = 11.232 m d = 11.232 m d = 11.232 m
L2 = 96.000 m L2 = 96.000 m L2 = 96.000 m
= 151.63392 kg = 151.63392 kg = 151.63392 kg
Jadi untuk jarak per / m' berat besi = 6.563 kg Jadi untuk jarak per / m' berat besi = 6.563 kg Jadi untuk jarak per / m' berat besi = 6.563 kg 6.563
Bentang = 88.0 577.55
c (Tul Sengkang) dia tump kiri 12 - 150 a = 0.048 m a total = 0.096 m a = 0.048 m a total = 0.096 m a = 0.048 m a total = 0.096 m
dia tump kanan 12 - 150 b = 0.440 m b total = 0.880 m b = 0.440 m b total = 0.880 m b = 0.440 m b total = 0.880 m
la 12 - 200 c = 0.740 m c total = 1.480 m c = 0.740 m c total = 1.480 m c = 0.740 m c total = 1.480 m
c W = 0.888 kg W = 0.888 kg W = 0.888 kg
800 A L total = 2.456 m L total = 2.456 m L total = 2.456 m
a
b n = 6.267 + 1 = 8 n = 4.700 + 1 = 6 n = 6.267 + 1 = 8
500 Jadi untuk jarak per / m' berat besi = 17.457 kg Jadi untuk jarak per / m' berat besi = 13.093 kg Jadi untuk jarak per / m' berat besi = 17.457 kg 16.002
B Bentang = 88.0 1,408.19
BALOK MEMANJANG DERMAGA
Lihat Gambar
L Total = 109.50 m
A 0.80 m
B 0.50 m
(juml Tul ats & bwh) tump kiri 12 bh
(Tul Utama) lap 12 bh
tump kanan 12 bh
besi dia 25 mm
(Tul Tengah) jumlah 4 bh
besi dia 16 mm
(Tul Sengkang) besi dia jarak
tump kiri 12 - 150 mm
lap 12 - 200 mm
tump kanan 12 - 150 mm

NO Jenis Balok Tumpuan Kiri Tumpuan Lapangan Tumpuan Kanan Total Berat

1 0 Lihat Gambar L Total = 109.50 m


30-Dec Beton A = 0.80 m Luas Total = 0.40 m2 V. Beton = 43.80 m3 Total berat Besi = Besi skng 12 1,752.23
B = 0.50 m Besi utama 25 5,381.00
Bekisting A bkst = 2.10 m Panjang Total = 2.10 m' L. Bekisting = 229.95 m2 Besi torsi 16 718.66

As Lihat Gambar perancah = 54.75 m2


Pembesian

a (Tul Utama)
(juml Tul ats & bwh) tump kiri 12
tump kanan 12 a = 0.100 m a total = 0.200 m a = 0.100 m a total = 0.200 m a = 0.100 m a total = 0.200 m
lap 12 b = 11.800 m b total = 11.800 m b = 11.800 m b total = 11.800 m b = 11.800 m b total = 11.800 m
a Besi D 25 W = 3.856 kg W = 3.856 kg W = 3.856 kg
L = 12.000 m L = 12.000 m L = 12.000 m
b c = 1.000 m c = 1.000 m c = 1.000 m
d = 10.800 m d = 10.800 m d = 10.800 m
L2 = 288.000 m L2 = 288.000 m L2 = 288.000 m
= 1110.6 kg = 1110.6 kg = 1110.6 kg
Jadi untuk jarak per / m' berat besi = 49.142 kg Jadi untuk jarak per / m' berat besi = 49.142 kg Jadi untuk jarak per / m' berat besi = 49.142 kg 49.142
Bentang = 109.5 5,381.00
b (Tul Tengah) jumlah 4
besi dia 16 a = 0.064 m a total = 0.128 m a = 0.064 m a total = 0.128 m a = 0.064 m a total = 0.128 m
b = 11.872 m b total = 11.872 m b = 11.872 m b total = 11.872 m b = 11.872 m b total = 11.872 m
a W = 1.580 kg W = 1.580 kg W = 1.580 kg
L = 12.000 m L = 12.000 m L = 12.000 m
b c = 0.640 m c = 0.640 m c = 0.640 m
d = 11.232 m d = 11.232 m d = 11.232 m
L2 = 96.000 m L2 = 96.000 m L2 = 96.000 m
= 151.63392 kg = 151.63392 kg = 151.63392 kg
Jadi untuk jarak per / m' berat besi = 6.563 kg Jadi untuk jarak per / m' berat besi = 6.563 kg Jadi untuk jarak per / m' berat besi = 6.563 kg 6.563
Bentang = 109.5 718.66
c (Tul Sengkang) dia tump kiri 12 - 150 a = 0.048 m a total = 0.096 m a = 0.048 m a total = 0.096 m a = 0.048 m a total = 0.096 m
dia tump kanan 12 - 150 b = 0.440 m b total = 0.880 m b = 0.440 m b total = 0.880 m b = 0.440 m b total = 0.880 m
la 12 - 200 c = 0.740 m c total = 1.480 m c = 0.740 m c total = 1.480 m c = 0.740 m c total = 1.480 m
c W = 0.888 kg W = 0.888 kg W = 0.888 kg
800 A L total = 2.456 m L total = 2.456 m L total = 2.456 m
a
b n = 6.267 + 1 = 8 n = 4.700 + 1 = 6 n = 6.267 + 1 = 8
500 Jadi untuk jarak per / m' berat besi = 17.457 kg Jadi untuk jarak per / m' berat besi = 13.093 kg Jadi untuk jarak per / m' berat besi = 17.457 kg 16.002
B Bentang = 109.5 1,752.23
DAFTAR KUANTITAS DAN HARGA

### :
### : #NAME?
- : -

Volume Harga Satuan ( Rp. ) Jumlah Harga ( Rp. )


No. Uraian Pekerjaan Satuan
Watusampu Donggala Watusampu Donggala

A. PEKERJAAN PERSIAPAN
Mobilisasi Dan Dembilisasi Ls 1.000 25,000,000.00 526,327,500.00 25,000,000.00 526,327,500.00
-
Jumlah 25,000,000.00 426,327,500.00

B. PEK. CAUSEWAY `
1 Pasangan Batu Kali m3 300.80 500,000.00 713,937.00 150,400,000.00 214,752,249.60
2 Plesteran m2 244.00 30,000.00 27,256.00 7,320,000.00 6,650,464.00
3 Geotextile m2 132.00 Err:509 73,208.00 Err:509 9,663,456.00
4 Timbunan Tanah m3 150.00 Err:509 156,691.00 Err:509 23,503,650.00
Jumlah Err:509 254,569,819.60

C. PEK. PEMBANGUNAN TRESTLE + PELEBARAN


1 Tiang Baja Ø 508 mm , t = 12 mm Ton 35.28 16,250,000.00 20,039,169.00 573,300,000.00 706,981,882.32
2 Pemancangan Tegak M' 240.00 428,133.33 557,494.00 102,751,999.20 133,798,560.00
3 Pengecatan Tiang (12.0 m /tiang) M2 191.41 48,290.00 92,918.00 9,243,188.90 17,785,434.38
4 Penyambungan Tiang Bh 10.00 1,065,714.29 1,345,988.00 10,657,142.86 13,459,880.00
5 Pemotongan Tiang Bh 10.00 498,214.29 514,109.00 4,982,142.86 5,141,090.00
6 Plat penutup Tiang Bh 10.00 904,522.86 1,302,895.00 9,045,228.57 13,028,950.00
7 Beton Lantai Kerja B-0 M3 1.350 929,400.00 1,311,235.00 1,254,690.00 1,770,167.25
8 Beton Bertulang Untuk Abutmen & Plat Injak
Beton K-300 m3 5.650 1,411,000.00 6,184,152.00 7,972,150.00 34,940,458.80
Besi Beton kg 821.036 16,702.50 13,713,353.10
Bekisting Cetakan Beton m2 13.780 269,876.00 3,718,891.28

9 Beton Bertulang Pengisi Tiang


Beton K-300 m3 2.207 1,411,000.00 7,302,902.00 3,113,641.73 16,115,251.91
Besi Beton Ø 10 mm kg 136.883 16,702.50 2,286,287.97
Besi Beton Ø 25 mm kg 298.518 16,702.50 4,986,001.25

10 Beton Bertulang Selimut Tiang


Beton K-300 m3 5.950 1,411,000.00 6,470,887.00 8,396,050.52 38,504,531.66
Besi Beton Ø 10 mm kg 272.250 16,702.50 4,547,250.91
Besi Beton Ø 16 mm kg 374.005 16,702.50 6,246,826.52
Bekisting Cetakan Beton m2 48.790 269,876.00 13,167,323.45

11 Beton Bertulang Untuk Balok Melintang


Beton K-300 m3 5.250 1,411,000.00 7,933,313.00 7,407,750.00 41,649,893.25
Besi Beton Ø 12 mm kg 200.441 16,702.50 3,347,867.27
Besi Beton Ø 16 mm kg 65.631 16,702.50 1,096,202.19
Besi Beton Ø 25 mm kg 395.863 16,702.50 6,611,898.95
Bekisting Cetakan Beton m2 19.000 269,876.00 5,127,644.00
Perancah Beton m2 5.000 460,750.00 2,303,750.00

12 Beton Bertulang Untuk Balok Memanjang


Beton K-300 m3 5.600 1,411,000.00 7,933,313.00 7,901,600.00 44,426,552.80
Besi Beton Ø 12 mm kg 320.706 16,702.50 5,356,587.64
Besi Beton Ø 16 mm kg 105.010 16,702.50 1,753,923.51
Besi Beton Ø 25 mm kg 655.221 16,702.50 10,943,832.74
Bekisting Cetakan Beton m2 30.400 269,876.00 8,204,230.40
Perancah Beton m2 8.000 460,750.00 3,686,000.00

13 Beton Bertulang Untuk Balok Pelebaran


Beton K-300 m3 5.705 1,411,000.00 7,933,313.00 8,049,755.00 45,259,550.67
Besi Beton Ø 12 mm kg 326.719 16,702.50 5,457,023.65
Besi Beton Ø 16 mm kg 106.979 16,702.50 1,786,809.58
Besi Beton Ø 25 mm kg 645.256 16,702.50 10,777,395.29
Bekisting Cetakan Beton m2 30.970 269,876.00 8,358,059.72
Perancah Beton m2 8.150 460,750.00 3,755,112.50
Volume Harga Satuan ( Rp. ) Jumlah Harga ( Rp. )
No. Uraian Pekerjaan Satuan
Watusampu Donggala Watusampu Donggala

14 Stek Besi Untuk Poer


Besi Beton Ø 16 mm kg 98.482 16,702.50 19,279.00 1,644,898.54 1,898,637.87

15 Beton Bertulang Untuk Poer Type I


Beton K-300 m3 8.761 1,411,000.00 7,879,683.00 12,362,272.71 69,036,704.53
Besi Beton Ø 19 mm kg 626.274 16,702.50 10,460,341.33
Bekisting Cetakan Beton m2 35.100 269,876.00 9,472,647.60
Perancah Beton m2 7.800 460,750.00 3,593,850.00

16 Beton Bertulang Untuk Plat Lantai


Beton K-300 m3 24.045 1,411,000.00 6,911,477.00 33,927,664.32 166,187,293.84
Besi Beton Ø 16 mm kg 2,846.173 16,702.50 47,538,200.59
Bekisting Cetakan Beton m2 75.141 269,876.00 20,278,752.52
Perancah Beton m2 75.141 460,750.00 34,621,215.75

17 Beton bertulang untuk Kanstain/Kerb


Beton K-300 m3 0.930 1,411,000.00 5,641,151.00 1,312,230.00 5,246,270.43
Besi Beton kg 149.956 16,702.50 2,504,634.75
Bekisting Cetakan Beton m2 12.400 269,876.00 3,346,462.40

18 Pengecatan Kanstain M2 14.570 46,170.00 60,187.00 672,696.90 876,924.59


19 Profil Baja Siku Untuk Deletasi 100.100.10 M' 26.830 491,206.34 466,540.00 13,179,066.18
20 Beton Bertulang Dudukan Tiang Listrik M3 0.28 7,396,755.00 7,933,313.00 2,034,107.63
Jumlah 1,078,256,652.78 1,356,108,034.30

D. PEK. PEMBANGUNAN DERMAGA (42 x 8 ) M2


1 Tiang Baja Ø 711,2 mm , t = 12 mm Ton 181.410 16,250,000.00 20,039,169.00 2,947,912,500.00 3,635,305,648.29
2 Pengecatan Tiang (12.0 m / Tiang) M2 616.350 48,290.00 92,918.00 29,763,541.50 57,270,009.30
3 Pemancangan Tegak M' 396.000 428,133.33 557,494.00 169,540,798.68 220,767,624.00
4 Pemancangan Miring M' 432.000 516,810.00 640,221.00 223,261,920.00 276,575,472.00
5 Penyambungan Tiang Bh 46.000 1,065,714.29 1,345,988.00 49,022,857.14 61,915,448.00
6 Pemotongan Tiang Bh 23.000 498,214.29 514,109.00 11,458,928.57 11,824,507.00
7 Plat Penutup Tiang Bh 23.000 904,522.86 1,302,895.00 20,804,025.71 29,966,585.00

8 Beton Bertulang Pengisi Tiang


Beton K-300 m3 25.144 1,411,000.00 7,302,902.00 35,478,081.42 183,623,636.98
Besi Beton Ø 10 mm kg 1,056.652 16,702.50 17,648,736.21
Besi Beton Ø 25 mm kg 2,238.887 16,702.50 37,395,009.39

9 Beton Bertulang Selimut Tiang


Beton K-300 m3 29.854 1,411,000.00 6,470,887.00 42,124,014.77 193,181,955.75
Besi Beton Ø 10 mm kg 1,306.080 16,702.50 21,814,798.43
Besi Beton Ø 16 mm kg 1,433.688 16,702.50 23,946,168.33
Bekisting Cetakan Beton m2 187.029 269,876.00 50,474,739.88

10 Stek Besi Untuk Poer


Besi Beton Ø 16 mm kg 681.800 16,702.50 19,279.00 11,387,759.16 13,144,416.03

11 Beton Bertulang Untuk Poer Type I


Beton K-300 m3 23.364 1,411,000.00 7,879,683.00 32,966,060.55 184,097,878.74
Besi Beton Ø 19 mm kg 2,071.022 16,702.50 34,591,241.05
Bekisting Cetakan Beton m2 101.920 269,876.00 27,505,761.92
Perancah Beton m2 27.040 460,750.00 12,458,680.00

12 Beton Bertulang Untuk Poer Type II = III


Beton K-300 m3 18.564 1,411,000.00 7,879,683.00 26,193,732.60 146,278,036.46
Besi Beton Ø 19 mm kg 1,483.989 16,702.50 24,786,325.23
Bekisting Cetakan Beton m2 69.840 269,876.00 18,848,139.84
Perancah Beton m2 23.400 460,750.00 10,781,550.00

13 Beton Bertulang Untuk Poer Type IV+ Fl.Fender


Beton K-300 m3 41.725 1,411,000.00 8,671,292.00 58,873,901.64 361,809,207.88
Besi Beton Ø 19 mm kg 1,436.851 16,702.50 23,999,011.69
kg 3,753.899 16,702.50 62,699,503.48
Bekisting Cetakan Beton m2 153.725 269,876.00 41,486,688.10
Perancah Beton m2 22.880 460,750.00 10,541,960.00

14 Beton bertulang untuk Balok Melintang 50/80


Beton K-300 m3 35.200 1,411,000.00 7,933,313.00 49,667,200.00 279,252,617.60
Besi Beton Ø 12 mm kg 1,408.186 16,702.50 23,520,231.79
Besi Beton Ø 16 mm kg 577.553 16,702.50 9,646,579.31
Besi Beton Ø 25 mm kg 3,964.088 16,702.50 66,210,188.10
Bekisting Cetakan Beton m2 184.800 269,876.00 49,873,084.80
Perancah Beton m2 44.000 460,750.00 20,273,000.00
Volume Harga Satuan ( Rp. ) Jumlah Harga ( Rp. )
No. Uraian Pekerjaan Satuan
Watusampu Donggala Watusampu Donggala
15 Beton bertulang untuk Balok Memanjang 50/80
Beton K-300 m3 43.80 1,411,000.00 7,933,313.00 61,801,800.00 347,479,109.40
Besi Beton Ø 12 mm kg 1,752.23 16,702.50 29,266,652.05
Besi Beton Ø 16 mm kg 718.66 16,702.50 12,003,414.02
Besi Beton Ø 25 mm kg 5,381.00 16,702.50 89,876,226.40
Bekisting Cetakan Beton m2 229.95 269,876.00 62,057,986.20
Perancah Beton m2 54.75 460,750.00 25,226,062.50

16 Beton bertulang untuk Plat Lantai t = 32 cm


Beton K-300 m3 75.920 1,411,000.00 6,911,477.00 107,123,120.00 524,719,333.84
Besi Beton Ø 16 mm kg 8,986.499 16,702.50 150,096,992.20
Bekisting Cetakan Beton m2 237.250 269,876.00 64,028,081.00
Perancah Beton m2 237.250 460,750.00 109,312,937.50

17 Beton bertulang untuk Kanstain/Kerb


Beton K-300 m3 2.555 1,411,000.00 5,641,151.00 3,605,246.10 14,413,704.92
Besi Beton Ø 10 mm kg 411.991 16,702.50 6,881,281.98
Bekisting Cetakan Beton m2 34.068 269,876.00 9,194,135.57

18 Pengecatan Kanstain M2 40.030 46,170.00 60,187.00 1,848,180.48 2,409,279.59


19 Profil Baja Siku Untuk Deletasi 100.100.10 M' 14.830 491,206.34 466,540.00 7,284,590.06 6,918,788.20
20 Cleat Bh 6.000 338,500.00 338,500.00 2,031,000.00 2,031,000.00
21 Fender Type V 300 H-2000 L Bh 11.000 17,800,000.00 22,099,551.00 195,800,000.00 243,095,061.00
22 Bollard 70 ton Bh 2.000 29,300,000.00 38,416,314.00 58,600,000.00 76,832,628.00
23 Beton Bertulang Dudukan Tiang Listrik M3 0.28 7,396,755.00 7,879,683.00 2,034,107.63 2,166,912.83
Jumlah 5,295,028,532.97 6,875,078,860.81

E. PEKERJAAN BOLLARD DI DARAT


1 Galian Tanah m3 30.98 29,680.00 29,680.00 919,367.68 919,367.68
2 Urugan Pasir m3 0.97 123,650.00 123,650.00 119,693.20 119,693.20
3 Urugan Kembali m3 17.04 10,835.00 10,835.00 184,628.40 184,628.40
4 Lantai Kerja K-175, T = 5 cm m3 0.97 929,400.00 1,311,235.00 899,659.20 1,269,275.48

5 Beton Dudukan Bollard


Beton K 300 m3 13.20 1,411,000.00 7,933,313.00 18,625,200.00 104,719,731.60
Besi Beton Ø 16 mm kg 979.52 16,702.50 16,360,413.99
Bekisting Cetakan Beton m2 32.00 269,876.00 8,636,032.00

6 Angkur Dudukan Bollard Bh 32.00 78,000.00 78,000.00 2,496,000.00 2,496,000.00


7 Bollard Kap. 70 T Bh 4.00 30,000,000.00 38,416,314.00 120,000,000.00 153,665,256.00
Jumlah 168,240,994.47 263,373,952.36

Err:509 Rp 9,175,458,167.07

Err:509
PASWORD = rp * * * * * * * * * * * *
. 1,945,219,000.00 * * *
. * * * * * * * * * * * * * * * * *
Satu milyar sembilan ratus empat puluh lima juta dua ratus sembilan b
* * * * * * * * * * * * * * * * * * *
* * satu dua tiga empat lima enam tuj ***
* * ribu juta milyar ***
* * 001945219000 ***
* * * * * * * * * * * * * * * * * * *
* * 000 Rp1.00 ***
* * Rp - ***
* * sepuluh ***
* * Rp - ***
* * Rp - ***
* * ***
* * ***
* * ***
* * ***
* * 219 Rp2.00 ***
* * Rp 2.00 ***
* * dua ratus sembilan belas ***
* * Rp 1.00 sembilan ***
* * Rp 9.00 sembilan ***
* * sembilan belas sembilan belas ***
* * dua ratus sembilan belas ribu ***
* * ***
* * ***
* * 945 Rp3.00 ***
* * Rp 9.00 empat puluh ***
* * sembilan ratus lima belas ***
* * Rp 4.00 lima ***
* * Rp 5.00 empat puluh lima ***
* * empat puluh lima empat puluh lima ***
* * sembilan ratus empat puluh lima juta ***
* * ***
* * ***
* * 001 Rp4.00 ***
* * Rp - ***
* * sebelas ***
* * Rp - satu ***
* * Rp 1.00 satu ***
* * satu satu ***
* * satu milyar ***
* * ***
* * 000 Rp1.00 ***
* * Rp - ***
* * sepuluh ***
* * Rp - ****
* * Rp - ***
* * ***
* * ***
* * ***
* * * * * * * * * * * * * * * * * * *
* * rupiah ### 00
== * * satu milyar sembilan ra satu milyar sembilan ratus empat puluh lima ju
== * * satu milyar sembilan ratus empat puluh lima juta dua ratus sembilan b
== * * Satu milyar sembilan ratus empat puluh lima juta dua ratus sembilan b
* * * * * * * * * * * * * * * * * * *
ta dua ratus sembilan belas ribu rupiah.
tus empat puluh lima juta dua ratus sembilan belas ribu
ta dua ratus sembilan belas ribu rupiah
ta dua ratus sembilan belas ribu rupiah.
DAFTAR KUANTITAS DAN HARGA
PEMBANGUNAN TALUD

Volume upah kerja


No. Uraian Pekerjaan Satuan upah kerja jumlah kerja bt bolder bt. Kali pasir semen

II. PEK. TALUD


1 Pasangan Batu Kali m3 123.65 50,000.00 6,182,500.00 80.37 43.28 166.93
2 Pasangan Batu Bolder m3 307.35 107.57
2 Plesteran m2 205.50 10,000.00 2,055,000.00
TOTAL 107.57 80.37 43.28 166.93
HARGA SATUAN 8,237,500.00 140,000.00 80,000.00 65,000.00 60,000.00
15,060,150.00 6,429,800.00 2,813,037.50 10,015,650.00
34,318,637.50
42,556,137.50