PERHITUNGAN BERAT BESI / PER UNIT PEKERJAAN BETON

1 Sloof S 12/20 K-175


TULANGAN POKOK
A B Uraian Dia. Tul P.Tul. Berat Berat Total
m m m kg/m Kg
0.12 0.20 Tul pokok 2 Ø8 2.26 0.395 0.89
Vol. 1 m3 Tul pokok 2 Ø8 2.26 0.395 0.89
0.02 Berat Tulangan (kg) 1.78224
TULANGAN BEGEL/ SENGKANG
Tekukan tebal Uraian Jml. Tul. P.Tul. P.Tul. Berat Berat Total
Dia. Tul
besi (r) selimut bh m total (m) kg/m Kg
0.05 0.025 tumpuan Ø6 -0.150 3.33 0.54 1.80 0.222 0.40
Lapangan Ø6 -0.200 2.50 0.54 1.35 0.222 0.30

Berat Tulangan (kg) 0.70


Tul. Pokok = 1 m3 74.26
Begel = 1 m3 29.09
Berat total = 1 m3 ###

2 BALOK B2 20/30 K-250


TULANGAN POKOK
A B Uraian P.Tul. Berat Berat Total
Dia. Tul
m m m kg/m Kg
0.20 0.30 Tul pokok 3 D13 3.31 1.040 3.44
Vol. 1 m3 2 D13 2.21 1.040 2.30
0.06 Berat Tulangan (kg) 5.7408
TULANGAN BEGEL/ SENGKANG
Tekukan tebal Uraian Jml. Tul. P.Tul. P.Tul. Berat Berat Total
Dia. Tul
besi (r) selimut bh m total (m) kg/m Kg
0.05 0.025 tumpuan Ø8 -0.150 3.33 0.90 3.00 0.395 1.19
Lapangan Ø8 -0.200 2.50 0.90 2.25 0.395 0.89

Berat Tulangan (kg) 2.07


Tul. Pokok = 1 m3 95.68
Begel = 1 m3 34.56
Berat total = 1 m3 ###
DAFTAR BERAT BESI POLOS
DIA METER BERAT BERAT
MM KG/M1 12 kg/m
Ø6 0.222 2.66
Ø8 0.395 4.74
Ø10 0.617 7.4
Ø12 0.892 10.7
Ø14 1.208 14.5
Ø16 1.583 19
Ø19 2.233 26.8
Ø22 2.983 35.8
Ø25 3.850 46.2
Ø26 0.000 0
Ø28 4.833 58
Ø31 5.925 71.1
Ø32 6.314 75.77

12.00

DAFTAR BERAT BESI ULIR/DEFORM


DIA METER BERAT BERAT
MM KG/M1 12 kg/m
D10 0.617 7.4
D13 1.040 12.48
D16 1.580 18.96
D19 2.230 26.76
D22 2.980 35.76
D25 3.850 46.2
D29 5.190 62.28
D32 6.310 75.72
D35 7.508 90.1
D38 8.917 107
REKAPITULASI R.A.B

NAMA PEMILIK : DJOKO SANTOSO


ALAMAT PEMILIK : RANGKAH II/87 RT 03 RW 05
KELURAHAN : RANGKAH
KECAMATAN : TAMBAKSARI

JUMLAH HARGA
NO. URAIAN PEKERJAAN
(Rp)

I. PEKERJAAN TANAH & URUGAN Rp 970,200.00


II PEKERJAAN STRUKTUR Rp 1,848,000.00
III PEKERJAAN STRUKTUR ATAP Rp 3,170,000.00
IV PEKERJAAN ARSITEKTUR
IV.1 PEKERJAAN PASANGAN DAN PLESTERAN Rp 7,362,750.00
IV.2 PEKERJAAN KUSEN Rp 2,142,000.00
IV.3 PEKERJAAN PENUTUP LANTAI Rp 2,232,000.00

TOTAL Rp 17,724,950.00
PPN 10% Rp 1,772,495.00
Jumlah Nilai Fisik Rp 19,497,445.00
V UPAH TENAGA KERJA Rp 7,019,000.00
Jumlah Nilai Fisik Rp 26,516,445.00
PEMBULATAN Rp 26,510,000.00
Terbilang :
Dua Puluh Enam Juta Lima Ratus Sepuluh Ribu Rupiah

Surabaya, 2017
Mengetahui UPKM "TULUS SEJATI"
Pejabat Pembuat komitmen Kelurahan Rangkah

Agus Rosid, SST Moch. Misbachul Munir


P e n a t a / III - C Ketua UPKM
NIP. 19650813 199302 1 001
3
2
5
RENCANA ANGGARAN BIAYA

NAMA PEMILIK : DJOKO SANTOSO


ALAMAT PEMILIK : RANGKAH II/87 RT 03 RW 05
KELURAHAN : RANGKAH
KECAMATAN : TAMBAKSARI

HARGA SAT JML HARGA


NO. URAIAN PEKERJAAN VOL SAT
(Rp) (Rp)

I. PEKERJAAN TANAH & URUGAN


1. Pengurugan Gragal 6.30 m3 154,000.00 970,200.00
Sub. Total 970,200.00
II PEKERJAAN STRUKTUR
1. Pekerjaan Kolom Praktis (11 x 11 cm) 24.50 m1 36,000.00 882,000.00
2. Pekerjaan Ring Balk (10x15cm) 21.00 m1 46,000.00 966,000.00
Sub. Total 1,848,000.00
III PEKERJAAN STRUKTUR ATAP
1. Pemasang rangka atap Galvalume t=0.8 mm 26.00 m2 50,000.00 1,300,000.00
2. Pemasangan Plafon Triplek Rangka Kayu Meranti 18.00 m2 49,000.00 882,000.00
3. P. Atap Asbes Gelombang kecil 210 cm x 105 cm x 0.4 cm 26.00 m2 38,000.00 988,000.00
Sub. Total 3,170,000.00
IV PEKERJAAN ARSITEKTUR
IV.1 PEKERJAAN PASANGAN DAN PLESTERAN
1. Pasangan dinding bata ringan 10 cm 64.75 m2 81,000.00 5,244,750.00
2. Plesteran 1Pc : 5Ps tebal 1,5cm 68.00 m2 11,000.00 748,000.00
3. Acian 68.00 m2 3,000.00 204,000.00
4. Plamir Tembok 68.00 m2 12,000.00 816,000.00
5. Pengecatan Dinding 70.00 m2 5,000.00 350,000.00
Sub. Total 7,362,750.00
IV.2 PEKERJAAN KUSEN
1. Kusen Pintu/Jendela Kayu Meranti Komplit 1.00 set 1,730,000.00 1,730,000.00
2. Pasangan Jendela Bouvenlist 1.00 set 412,000.00 412,000.00
Sub. Total 2,142,000.00
IV.3 PEKERJAAN PENUTUP LANTAI
1. Pas. Keramik Uk. 40 x 40 cm 24.00 m2 93,000.00 2,232,000.00
Sub. Total 2,232,000.00

V UPAH TENAGA KERJA


1. Upah Pengawas (1 unit x 1 org) 1.00 OH 139,000.00 139,000.00
2. Upah Tukang (1 unit x 2 org x 16 hari) 32.00 OH 120,000.00 3,840,000.00
3. Upah Pembantu Tukang (1 unit x 2 org x 16 hari) 32.00 OH 95,000.00 3,040,000.00
Sub. Total 7,019,000.00

Mengetahui Surabaya, 2017


UPKM "TULUS SEJATI"
Kelurahan Rangkah

Agus Rosid, SST


P e n a t a / III - C Moch. Misbachul Munir
NIP. 19650813 199302 1 001 Ketua UPKM
PEKERJAAN PENDAHULUAN
42.857142857

3.921 6.0 216300.00 1297800.00 NOT OKE


3.921 Sub. Total #VALUE! #VALUE!
0.000 10.0 284804.93 2848049.30 NOT OKE
3.565 10.0 284804.93 2848049.30 NOT OKE
3.904
7.468 Sub. Total #VALUE! #VALUE!
0.000 0.00 OKE
5.254 32.0 57628.50 1844112.00 NOT OKE
3.565 10.0 284804.93 2848049.30 NOT OKE
3.993 10.0 284804.93 2848049.30 NOT OKE
12.811 Sub. Total #VALUE! #VALUE!
0.000 0.00 OKE
0.000 0.00 OKE
21.196 26516445 32.0 67207.50 2150640.00 NOT OKE
3.023 24.0 11989.20 287740.80 NOT OKE
0.824 96.0 16222.50 1557360.00 NOT OKE
3.298
1.414
29.756 Sub. Total #VALUE! #VALUE!
0.000 0.00 OKE
6.992 1.0 1545000.00 1545000.00 NOT OKE
1.665
8.657 Sub. Total #VALUE! #VALUE!
0.000 0.00 OKE
9.020 35.0 88803.95 3108138.25 NOT OKE
9.020 Sub. Total #VALUE! #VALUE!
0.000
0.000
17,719,091.00 0.562
17,724,950.00 15.519
(5,859.000) 12.286
28.367
24,743,950.00 100.000
LAPORAN KEMAJUAN FISIK PEKERJAAN
Minggu Ke - Satu

NAMA KEGIATAN : PEMBANGUNAN RUMAH TIDAK LAYAK HUNI


NAMA UPKM : UPKM "TULUS SEJATI"
LOKASI : KELURAHAN RANGKAH KECAMATAN TAMBAKSARI
NO & TGL SPK :
NILAI KONTRAK : Rp. 26,510,000.00
KODE KEGIATAN : 1.1.1.04.01.0010
NAMA PENERIMA MANF: DJOKO SANTOSO
ALAMAT : RANGKAH II/87 RT 03 RW 05

NILAI FISIK PEKERJAAN YANG TELAH DILAKSANAKAN (VOL. TERPASANG)


DALAM MINGGU INI : s/d 60.053%
MINGGU SEBELUMNYA : s/d -
SAMPAI DG. LAPORAN I: 60.053%

VOLUME TERPASANG
BOBOT HARGA SAT JML HARGA
S/D S/D
NO. URAIAN PEKERJAAN VOL SAT
MINGGU MINGGU MINGGU
(%) (Rp) (Rp)
LALU INI INI
1 2 3 4 5 6 7 8 9

I. PEKERJAAN TANAH & URUGAN


1 Pengurugan Gragal 6.30 m3 - 6.3000 6.3000 100.000 154,000.00 970,200.00
Sub. Total 970,200.00
II PEKERJAAN STRUKTUR
1 Pekerjaan Kolom Praktis (11 x 11 cm) 24.50 m1 - 24.5000 24.5000 100.000 36,000.00 882,000.00
2 Pekerjaan Ring Balk (10x15cm) 21.00 m1 - 21.0000 21.0000 100.000 46,000.00 966,000.00
- Sub. Total 1,848,000.00
III PEKERJAAN STRUKTUR ATAP -
1 Pemasang rangka atap Galvalume t=0.8 mm 26.00 m2 - 26.0000 26.0000 100.000 50,000.00 1,300,000.00
2 Pemasangan Plafon Triplek Rangka Kayu Meranti 18.00 m2 - 18.0000 18.0000 100.000 49,000.00 882,000.00
3 P. Atap Asbes Gelombang kecil 210 cm x 105 cm x 0 26.00 m2 - 26.0000 26.0000 100.000 38,000.00 988,000.00
- Sub. Total 3,170,000.00
IV PEKERJAAN ARSITEKTUIR -
IV.1 PEKERJAAN PASANGAN DAN PLESTERAN -
1 Pasangan dinding bata ringan 10 cm 64.75 m2 - 64.7500 64.7500 100.000 81,000.00 5,244,750.00
2 Plesteran 1Pc : 5Ps tebal 1,5cm 68.00 m2 - 68.0000 68.0000 100.000 11,000.00 748,000.00
3 Acian 68.00 m2 - 34.0000 34.0000 50.000 3,000.00 102,000.00
4 Plamir Tembok 68.00 m2 - - - - 12,000.00 -
5 Pengecatan Dinding 70.00 m2 - - - - 5,000.00 -
- Sub. Total 6,094,750.00
IV.2 PEKERJAAN KUSEN -
1 Kusen Pintu/Jendela Kayu Meranti Komplit 1.00 set - - - - 1,730,000.00 -
2 Daun Pintu Panil (Kayu Kamper) 1.00 set - - - - 412,000.00 -
Sub. Total -
IV.3 PEKERJAAN PENUTUP LANTAI
1 Pas. Keramik Uk. 40 x 40 cm 24.00 m2 - - - - 93,000.00 -
Sub. Total -
V UPAH TENAGA KERJA
1 Upah Pengawas (1 unit x 1 org) 1.00 OH - 0.3750 0.3750 37.500 139,000.00 52,125.00
2 Upah Tukang (1 unit x 2 org x 16 hari) 32.00 OH - 12.0000 12.0000 37.500 120,000.00 1,440,000.00
3 Upah Pembantu Tukang (1 unit x 2 org x 16 hari) 32.00 OH - 12.0000 12.0000 37.500 95,000.00 1,140,000.00
Sub.Total 2,632,125.00

Total Sebelum ditambah PPN 10% 12,082,950.00


PPN 10% 1,208,295.00
Total 15,923,370.00
Dibulatkan 15,920,000.00

Rp 15,920,000.00
PRESTASI FISIK SAMPAI MINGGU SEKARANG = x 100 = 60.053%
Rp 26,510,000.00

Surabaya,
Diketahui, Disetujui, Dibuat Oleh :
PEJABAT PELAKSANA TEKNIS KEGIATAN PENGAWAS LAPANGAN UPKM "TULUS SEJATI"
KELURAHAN RANGKAH KELURAHAN RANGKAH

SUNARKO, S.Ag. Eko Basoeki Moch. Misbachul Munir


Penata Muda Tingkat I Pengawas Ketua
NIP. 19740110 200901 1 002
LAPORAN KEMAJUAN FISIK PEKERJAAN
Minggu Ke - Dua

NAMA KEGIATAN : PEMBANGUNAN RUMAH TIDAK LAYAK HUNI


NAMA UPKM : UPKM "TULUS SEJATI"
LOKASI : KELURAHAN RANGKAH KECAMATAN TAMBAKSARI
NO & TGL SPK :
NILAI KONTRAK : Rp. 26,510,000.00
KODE KEGIATAN : 1.1.1.04.01.0010
NAMA PENERIMA MANF: DJOKO SANTOSO
ALAMAT : RANGKAH II/87 RT 03 RW 05

NILAI FISIK PEKERJAAN YANG TELAH DILAKSANAKAN (VOL. TERPASANG)


DALAM MINGGU INI : s/d 80.385%
MINGGU SEBELUMNYA : s/d 60.053%
SAMPAI DG. LAPORAN I: 80.385%

VOLUME TERPASANG
BOBOT HARGA SAT JML HARGA
S/D S/D
NO. URAIAN PEKERJAAN VOL SAT
MINGGU MINGGU MINGGU
(%) (Rp) (Rp)
LALU INI INI
1 2 3 4 5 6 7 8 9

I. PEKERJAAN TANAH & URUGAN


1 Pengurugan Gragal 6.30 m3 6.3000 - 6.3000 100.000 154,000.00 970,200.00
Sub. Total 970,200.00
II PEKERJAAN STRUKTUR
1 Pekerjaan Kolom Praktis (11 x 11 cm) 24.50 m1 24.5000 - 24.5000 100.000 36,000.00 882,000.00
2 Pekerjaan Ring Balk (10x15cm) 21.00 m1 21.0000 - 21.0000 100.000 46,000.00 966,000.00
Sub. Total 1,848,000.00
III PEKERJAAN STRUKTUR ATAP
1 Pemasang rangka atap Galvalume t=0.8 mm 26.00 m2 26.0000 - 26.0000 100.000 50,000.00 1,300,000.00
2 Pemasangan Plafon Triplek Rangka Kayu Meranti 18.00 m2 18.0000 - 18.0000 100.000 49,000.00 882,000.00
3 P. Atap Asbes Gelombang kecil 210 cm x 105 cm x 0 26.00 m2 26.0000 - 26.0000 100.000 38,000.00 988,000.00
Sub. Total 3,170,000.00
IV PEKERJAAN ARSITEKTUIR
IV.1 PEKERJAAN PASANGAN DAN PLESTERAN
1 Pasangan dinding bata ringan 10 cm 64.75 m2 64.7500 - 64.7500 100.000 81,000.00 5,244,750.00
2 Plesteran 1Pc : 5Ps tebal 1,5cm 68.00 m2 68.0000 - 68.0000 100.000 11,000.00 748,000.00
3 Acian 68.00 m2 34.0000 34.0000 68.0000 100.000 3,000.00 204,000.00
4 Plamir Tembok 68.00 m2 - 34.0000 34.0000 50.000 12,000.00 408,000.00
5 Pengecatan Dinding 70.00 m2 - - - - 5,000.00 -
Sub. Total 6,604,750.00
IV.2 PEKERJAAN KUSEN
1 Kusen Pintu/Jendela Kayu Meranti Komplit 1.00 set - 1.0000 1.0000 100.000 1,730,000.00 1,730,000.00
2 Daun Pintu Panil (Kayu Kamper) 1.00 set - - - - 412,000.00 -
Sub. Total 1,730,000.00
IV.3 PEKERJAAN PENUTUP LANTAI
1 Pas. Keramik Uk. 40 x 40 cm 24.00 m2 - 7.2000 7.2000 30.000 93,000.00 669,600.00
Sub. Total 669,600.00
V UPAH TENAGA KERJA
1 Upah Pengawas (1 unit x 1 org) 1.00 OH 0.3750 0.3125 0.6875 68.750 139,000.00 95,562.50
2 Upah Tukang (1 unit x 2 org x 16 hari) 32.00 OH 12.0000 10.0000 22.0000 68.750 120,000.00 2,640,000.00
3 Upah Pembantu Tukang (1 unit x 2 org x 16 hari) 32.00 OH 12.0000 10.0000 22.0000 68.750 95,000.00 2,090,000.00
Sub.Total 4,825,562.50

Total Sebelum ditambah PPN 10% 14,992,550.00


PPN 10% 1,499,255.00
Total 21,317,367.50
Dibulatkan 21,310,000.00

Rp 21,310,000.00
PRESTASI FISIK SAMPAI MINGGU SEKARANG = x 100 = 80.385%
Rp 26,510,000.00

Surabaya,
Diketahui, Disetujui, Dibuat Oleh :
PEJABAT PELAKSANA TEKNIS KEGIATAN PENGAWAS LAPANGAN UPKM "TULUS SEJATI"
KELURAHAN RANGKAH KELURAHAN RANGKAH

SUNARKO, S.Ag. Eko Basoeki Moch. Misbachul Munir


Penata Muda Tingkat I Pengawas Ketua
NIP. 19740110 200901 1 002
BACKUP VOLUME
NAMA PEMILIK : DJOKO SANTOSO
ALAMAT PEMILIK : RANGKAH II/87 RT 03 RW 05
KELURAHAN : RANGKAH
KECAMATAN : TAMBAKSARI

I. PEKERJAAN TANAH & URUGAN


: Panjang x Lebar x tinggi x Jumlah Volume Sat.
1 Pengurugan Gragal : 6.00 x 3.50 x 0.30 x 1.00 = 6.300 m3 6.30

II. PEKERJAAN STRUKTUR


1 Beton Kolom praktis 11x11 Panjang x Lebar x tinggi x Jumlah Volume Sat.
- Kp 11X11cm : 0.00 x 0.00 x 0.00 x 0.00 = 0.000 m1
24.500 m1 24.50
2 Sloof Praktis 12x20
- S 12X20cm : Panjang x Lebar x tinggi x Jumlah Volume Sat.
: 0.00 x 0.00 x 0.00 x 0.00 = 0.000 m3
: 0.00 x 0.00 x 0.00 x 0.00 = 0.000 m3
: 0.00 x 0.00 x 0.00 x 0.00 = 0.000 m3
: 0.00 x 0.00 x 0.00 x 0.00 = 0.000 m3
0.000 m3 0.00

1 Pekerjaan Ring Balk (10x15cm) Panjang x Lebar x tinggi x Jumlah Volume Sat.
: 0.00 x 0.00 x 0.00 x 0.00 = 0.000 m1
21.000 m1 21.00
III PEKERJAAN STRUKTUR ATAP

Panjang x Lebar x Jumlah


1 Pas. Atap Asbes Gelombang Besar : 0.00 x 0.00 x 0.00 = 0.00 m2 0.00
2 Pemasangan gording meranti : 0.00 x 0.00 x 0.00 = 0.00 m3 0.00
3 Pemasangan plafon kalsiboard : 0.00 x 0.00 x 0.00 = 0.00 m2 0.00
4 Pemasangan Plafon Triplek Rangka Kayu Meranti : 0.00 x 0.00 x 0.00 = 18.00 m2 18.00
5 Pemasang rangka atap Galvalume t=0.8 mm : 0.00 x 0.00 x 0.00 = 26.00 m2 26.00
6 Pas. Atap Asbes Gelombang Kecil : 0.00 x 0.00 x 0.00 = 26.00 m2 26.00
7 Pemasang rangka atap Kayu Meranti : 0.00 x 0.00 x 0.00 = 0.00 m2 0.00
8 Pemasangan Talang : 0.00 x 0.00 x 0.00 = 0.00 m1 0.00

IV PEKERJAAN ARSITEKTUR
IV.1 PEKERJAAN PASANGAN DAN PLESTERAN
1 Pasangan dinding bata ringan 7.5 cm : Panjang x Tinggi x Jumlah = Volume Sat.
: 0.00 x 0.00 x 0.00 = 0.00 m2
: 0.00 x 0.00 x 0.00 = 0.00 m2
: 0.00 x 0.00 x 0.00 = 0.00 m2
: 0.00 x 0.00 x 0.00 = 0.00 m2
: 0.00 x 0.00 x 0.00 = 0.00 m2
0.00 m2 0.00

Pasangan dinding bata ringan 10 cm : 0.00 x 0.00 x 0.00 = 0.00 m2


64.75 m2 64.75

Pasangan dinding bata merah : 0.00 x 0.00 x 0.00 = 0.00 m2


0.00 m2 0.00

2 Plesteran tbl=1,5cm, 1Pc : 5Ps : Panjang x 2 Sisi = Volume Sat.


0.00 x 0.00 = 60.00 m2 60.00

3 Acian Dinding : Panjang x 2 Sisi = Volume Sat.


0.00 x 0.00 = 60.00 m2 60.00
4 Plamir Tembok : 0.00 x 0.00 = 60.00 m2 60.00
IV.2 PEKERJAAN KUSEN
1 Kusen Pintu/Jendela Kayu Meranti Komplit : Panjang x Lebar x tinggi x Jumlah Volume Sat.
: 0.00 x 0.00 x 0.00 x 0.00 = 0.000 m3 0.00
: 0.00 x 0.00 x 0.00 x 0.00 = 0.000 m3 0.00
1.00 set 1.00

Pasangan Jendela Bouvenlist : Panjang x Lebar x tinggi x Jumlah Volume Sat.


: 0.00 x 0.00 x 0.00 x 0.00 = 0.000 bh
1.00 set 1.00

2 Daun Pintu Panil (Kayu Meranti) : Panjang x Lebar x tinggi x Jumlah Volume Sat.
: 0.00 x 0.00 x 0.00 x 0.00 = 0.000 bh
0.00 bh 0.00

Daun Pintu Panil Triplek : Panjang x Lebar x tinggi x Jumlah Volume Sat.
: 0.00 x 0.00 x 0.00 x 0.00 = 0.000 bh
0.00 bh 0.00

Daun Pintu Panil (Kayu Kamper) : Panjang x Lebar x tinggi x Jumlah Volume Sat.
: 0.00 x 0.00 x 0.00 x 0.00 = 0.000 bh
0.00 bh 0.00

Pintu PVC : Panjang x Lebar x tinggi x Jumlah Volume Sat.


: 0.00 x 0.00 x 0.00 x 0.00 = 0.000 bh
0.00 bh 0.00

3 Pas. Engsel H = 0.00 Set 0.00

4 Pas. Kunci Tanam 2x Putar = 0.00 Set 0.00

5 Bak Mandi = 0.00 bh 0.00

IV.3 PEKERJAAN PENUTUP LANTAI


1 Pas. Keramik Lantai, Uk. 40X40cm Panjang x Lebar x Jumlah Volume Sat.
Selasar Dalam : 0.00 x 0.00 x 0.00 = 24.00 m2 24.00
2 Pas. Kramik Km Mandi Uk. 20x20 cm : 0.00 x 0.00 x 0.00 = M2 0.00

3 Pas. Rabatan lantai K-175 : 0.00 x 0.00 x 0.00 = 0.00 m3 0.00

4 Pas. Kramik Km Mandi Uk. 20x25 cm (dinding) : 0.00 x 0.00 x 0.00 = M2 0.00

5 Pas. Kramik Km Mandi Uk. 30x30 cm (lantai) : 0.00 x 0.00 x 0.00 = 0.00 M2 0.00

6 Pas. Kramik Km Mandi Uk. 30x30 cm (dinding) : 0.00 x 0.00 x 0.00 = 0.00 M2 0.00

IV.4 PEKERJAAN PENGECATAN


1 Pengecatan Dinding Dalam Baru : Panjang x 2 Sisi iumlah = Volume Sat.
0.00 x 0.00 0.00 = 72.00 M2 72.00

2 Pengecatan Dinding Dalam Lama Tanpa Plamir : 0.00 x 0.00 0.00 = 0.00 M2 0.00

V. PEKERJAAN MEKANIKAL Jumlah


1 Kloset Jongkok : 0.000 = 0.00 Bh

2 Pembuatan Septicktank : 0.000 = 0.00 m1

3 Pemasangan pipa air bersih diameter 1' : 0.000 = 0.00 m1

4 Pemasangan pipa air kotor diameter 2' : 0.000 = 0.00 m1

5 Pemasangan kran air : 0.000 = 0.00 Bh

6 Pemasangan Pipa Air Kotor diameter 3' : 0.000 = 0.00 m1

7 Pemasangan Pipa Air Kotor diameter 4' : 0.000 = 0.00 m1


ANALISA HARGA SATUAN
DINAS SOSIAL KOTA SURABAYA
NAMA PEMILIK : DJOKO SANTOSO
ALAMAT PEMILIK : RANGKAH II/87 RT 03 RW 05
KELURAHAN : RANGKAH
KECAMATAN : TAMBAKSARI

Harga Satuan Harga Total


No. Uraian Pekerjaan Koefisien Satuan
Rp. Rp.

1 Pengurugan Gragal Campur m3


Bahan :
Gragal Campur 1.2000 m3 128,750.00 154,500.00
Jumlah 154,500.00
Nilai Total : 154,000.00 a
2 Pengurugan Pasir (Padat) m3
Bahan :
Pasir urug 1.2000 m3 236,900.00 284,280.00
Jumlah 284,280.00
Nilai Total : 284,280.00
3 Pekerjaan Beton K - 175 m3
Bahan :
Semen PC (Portland Cement) 50 kg 8.1500 Zak 47,380.00 386,147.00
Pasir Cor 0.4806 m3 267,800.00 128,704.68
Batu Pecah Mesin 1/2 cm 0.5416 m3 286,000.00 154,897.60
Air (biaya air tawar) 215.0000 Liter 30.00 6,450.00
Jumlah 676,199.28
Nilai Total : 676,199.00
4 Acuan Untuk Beton Sloof m2
Bahan :
Kayu meranti begesting 0.0450 m3 3,622,500.00 163,012.50
Paku Usuk 0.3000 kg 16,500.00 4,950.00
Minyak begesting 0.1000 lt 6,600.00 660.00
Jumlah 168,622.50
Nilai Total : 168,622.50
5 Acuan Untuk Beton Kolom m2
Bahan :
Kayu meranti bekisting 0.0400 m3 3,500,000.00 140,000.00
Paku Usuk 0.4000 Kg 13,850.00 5,540.00
Minyak Bekisting 0.2000 ltr 8,500.00 1,700.00
Kayu Meranti balok 3/5 0.0150 m3 3,750,000.00 56,250.00
Tego film tebal 18 mm 0.3500 lembar 308,000.00 107,800.00
Jumlah 311,290.00
Bekisting 3X pakai 0.3333 311,290.00 103,763.33
Nilai Total : 103,763.33
6 Acuan Untuk Beton Balok m2
Bahan :
Kayu meranti bekisting 0.0400 m3 3,500,000.00 140,000.00
Paku Usuk 0.4000 Kg 13,850.00 5,540.00
Minyak Bekisting 0.2000 ltr 8,500.00 1,700.00
Kayu Meranti balok 3/5 0.0180 m3 3,750,000.00 67,500.00
Tego film tebal 18 mm 0.3500 lembar 308,000.00 107,800.00
Jumlah 322,540.00
Bekisting 2X pakai 0.5000 322,540.00 161,270.00
Nilai Total : 161,270.00
7 Acuan Untuk Beton Balok Non Expose m2
Bahan :
Kayu meranti bekisting 0.0400 m3 3,500,000.00 140,000.00
Paku Usuk 0.4000 Kg 13,850.00 5,540.00
Minyak Bekisting 0.2000 ltr 8,500.00 1,700.00
Kayu Meranti balok 3/5 0.0180 m3 3,750,000.00 67,500.00
Plywood tebal 9 mm 0.3500 lembar 82,600.00 28,910.00
Jumlah 243,650.00
Bekisting 2X pakai 0.5000 243,650.00 121,825.00
Nilai Total : 121,825.00
8 Pekerjaan Pembesian dengan besi beton polos / ulir kg
Bahan :
Besi Beton 1.0500 Kg 8,177.06 8,585.91
Kawat ikat Beton 0.0100 Kg 18,025.00 180.25
Jumlah 8,766.16
Nilai Total : 8,766.00
9 Pekerjaan Sloof Praktis (12x20cm) m3
Pekerjaan Beton 1.0000 m3 676,199.00 676,199.00
Pekerjaan Pembesian dengan besi beton 103.3500 kg 8,766.00 905,966.10
Jumlah 1,582,165.10
Nilai Total : 1,582,165.00
10 Pekerjaan Kolom Praktis (11x11cm) m1
Bahan :
Semen PC (Portland Cement) 50 kg 0.1000 zak 47,380.00 4,738.00
Pasir Cor 0.0060 m3 267,800.00 1,606.80
Batu Pecah Mesin 1/2 cm 0.0090 m3 286,000.00 2,574.00
Besi Beton Polos 3.0000 kg 8,766.16 26,298.47
Paku Usuk 0.0100 kg 16,500.00 165.00
Kawat Beton 0.0450 kg 18,025.00 811.13
Jumlah 36,193.40
Nilai Total : 36,000.00 a
11 Pekerjaan Ring Balk (10x15cm) m1
Bahan :
Semen PC (Portland Cement) 40 kg 0.1375 zak 47,380.00 6,514.75
Pasir Cor 0.0090 m3 267,800.00 2,410.20
Batu Pecah Mesin 1/2 cm 0.0150 m3 286,000.00 4,290.00
Besi Beton Polos 3.6000 kg 8,766.16 31,558.17
Paku Usuk 0.0200 kg 16,500.00 330.00
Kawat Beton 0.0500 kg 18,025.00 901.25
Jumlah 46,004.37
Nilai Total : 46,000.00 a
9 Pembongkaran Cetakan m3
Mandor 0.0250 O.H 113,000.00 2,825.00
Pembantu Tukang 0.0500 O.H 108,400.00 5,420.00
Jumlah 8,245.00
Nilai Total : 8,245.00
10 Pasangan 1 batu merah dinding 1Pc : 3Ps Rollag m2
Bahan :
Semen PC (Portland Cement) 40 kg 0.6590 Zak 71,000.00 46,789.00
Pasir Pasang 0.0910 m3 150,000.00 13,650.00
Batu Bata Merah uk 22 x 11 x 4.5 cm 140.0000 Buah 730.00 102,200.00
Jumlah 162,639.00
Nilai Total : 162,639.00
11 Pasangan 1/2 batu merah dinding 1Pc : 2Ps Trasram m2
Bahan :
Semen PC (Portland Cement) 40 kg 0.3790 Zak 71,000.00 26,909.00
Pasir Pasang 0.0380 m3 150,000.00 5,700.00
Batu Bata Merah uk 22 x 11 x 4.5 cm 65.0000 Buah 730.00 47,450.00
Jumlah 80,059.00
Nilai Total : 80,059.00
4 Pasangan dinding bata ringan tebal 7,5 cm m2
Bahan :
Bata Ringan 0.0750 m3 669,500.00 50,212.50
Perekat Bata Ringan 0.0750 zak 108,150.00 8,111.25
Jumlah 58,323.75
Nilai Total : 58,323.00 a
12 Pasangan 1/2 batu merah dinding 1Pc : 4Ps m2
Bahan :
Semen PC (Portland Cement) 50 kg 0.2300 Zak 47,380.00 10,897.40
Pasir Pasang 0.0430 m3 267,800.00 11,515.40
Batu Bata Merah uk 22 x 11 x 4.5 cm 65.0000 Buah 721.00 46,865.00
Jumlah 69,277.80
Nilai Total : 69,277.80
4 Pasangan dinding bata ringan tebal 7,5 cm m2
Bahan :
Bata Ringan 0.0750 m3 850,000.00 63,750.00
Perekat Bata Ringan 0.0790 zak 150,000.00 11,850.00
Jumlah 75,600.00
Nilai Total : 75,600.00 a
5 Pasangan dinding bata ringan tebal 10 cm m2
Bahan :
Bata Ringan 0.1000 m3 721,000.00 72,100.00
Perekat Bata Ringan 0.1050 zak 87,550.00 9,192.75
Jumlah 81,292.75
Nilai Total : 81,000.00
13 Plesteran 1Pc : 2Ps(trasram) tebal 1,5cm m2
Bahan :
Semen PC (Portland Cement) 40 kg 0.2045 Zak 71,000.00 14,518.08
Pasir Pasang 0.0200 m3 150,000.00 3,000.00
Jumlah 17,518.08
Nilai Total : 17,518.08
14 Plesteran 1Pc : 4Ps tebal 1,5cm m2
Bahan :
Semen PC (Portland Cement) 50 kg 0.1248 Zak 47,380.00 5,913.02
Pasir Pasang 0.0240 m3 267,800.00 6,427.20
Jumlah 12,340.22
Nilai Total : 12,340.00
5 Pasangan dinding bata ringan tebal 10 cm m2
Bahan :
Bata Ringan 0.1000 m3 660,000.00 66,000.00
Perekat Bata Ringan 0.1050 zak 85,000.00 8,925.00
Jumlah 74,925.00
Nilai Total : 74,925.00
5 Plesteran 1Pc : 5Ps tebal 1,5cm m2
Bahan :
Semen PC (Portland Cement) 50 kg 0.1037 Zak 47,380.00 4,913.31
Pasir Pasang 0.0260 m3 267,800.00 6,962.80
Jumlah 11,876.11
Nilai Total : 11,000.00 a
6 Acian m2
Bahan :
Semen PC (Portland Cement) 50 kg 0.0650 Zak 47,380.00 3,079.70
Jumlah 3,079.70
Nilai Total : 3,000.00 a
7 Pemasangan Besi Pipa Stainless 2 Inch m1
Bahan :
Besi Pipa Putih (Stainless) SCH Welded uk. 2 inch 0.3500 Bh 107,500.00 37,625.00
Dynabolt Ø10mm 4.0000 Bh 3,750.00 15,000.00
Jumlah 52,625.00
Nilai Total : 52,625.00
8 Pemasangan Baja Profil WF (Termasuk Perakitan dan Pengelasan) KG
Bahan :
Besi Profil (Baja Konstruksi) 1.1000 kg 12,000.00 13,200.00
Elektroda 0.0400 Kg 30,000.00 1,200.00
Cat Meni Besi 0.0300 Kg 32,000.00 960.00
Jumlah 15,360.00
Nilai Total : 15,360.00
9 Pemasangan Gording Meranti m3
Bahan :
Kayu Meranti 6/12 1.0000 m3 4,200,000.00 4,200,000.00
Paku reng 0.2000 kg 15,450.00 3,090.00
Besi plat strip 4.0000 kg 19,800.00 79,200.00
Jumlah 4,282,290.00
Nilai Total : 4,282,290.00
9 Pemasangan Reng Meranti/Usuk Meranti m2
Bahan :
Kayu Meranti 3/5 0.0082 m3 3,862,500.00 31,672.50
Kayu Meranti Usuk (5/7) 1.0000 ljr 61,800.00 61,800.00
Paku Reng 0.2500 kg 17,510.00 4,377.50
Jumlah 97,850.00
Nilai Total : 97,000.00
10 Pemasangan Kalsiplank m2
Bahan :
Paku Klem (No. 4 ) / Beton 0.1000 Doz 190,000.00 19,000.00
Kayu Kalsiplank Balok 5/7 0.0108 m3 6,400,000.00 69,120.00
Jumlah 88,120.00
Nilai Total : 88,120.00

7 Pemasangan rangka Galvalum Uk. 0.8 mm m2


Bahan :
Rangka Galvalume campuran Uk. 0.8 mm 1.1000 m2 46,350.00 50,985.00
Jumlah 50,985.00
Nilai Total : 50,000.00 a
8 Pembongkaran Rangka Atap m2
Upah :
Mandor 0.0030 O.H 113,000.00 339.00
Kepala Tukang Kayu 0.0060 O.H 111,500.00 669.00
Tukang Kayu 0.0600 O.H 110,000.00 6,600.00
Pembantu Tukang 0.0600 O.H 108,400.00 6,504.00
Jumlah 14,112.00
Nilai Total : 14,112.00
9 Pemasangan Genteng Karang Pilang m2
Bahan :
Genteng Karang Pilang 25.0000 bh 4,000.00 100,000.00
Jumlah 100,000.00
Nilai Total : 100,000.00
10 Pemasangan Wuwung Genteng Karang Pilang m1
Bahan :
Semen PC 50 Kg 0.1600 Zak 66,000.00 10,560.00
Pasir Pasang / Plester 0.0323 m3 168,400.00 5,439.32
Genteng Wuwung karang pilang / wisma 5.0000 Buah 13,000.00 65,000.00
Jumlah 80,999.32
Nilai Total : 80,999.32
8 Pemasangan Atap Asbes Gelombang 210 cm x 108 cm m2
Bahan :
Asbes Gelombang Besar 210x108 0.5700 Lembar 97,850.00 55,774.50
Paku Skrup 0.1200 kg 15,450.00 1,854.00
Jumlah 57,628.50
Nilai Total : 57,628.00 a
8 Pemasangan Atap Asbes Gelombang 210 cm x 105 cm m2
Bahan :
Asbes Gelombang Kecil 210x105 0.5700 Lembar 64,375.00 36,693.75
Paku Skrup 0.1200 kg 17,510.00 2,101.20
Jumlah 38,794.95
Nilai Total : 38,000.00 a
8 Pemasangan Atap Asbes Gelombang 210 cm x 108 cm m2
Bahan :
Asbes Gelombang Besar 210x108 0.4900 Lembar 77,000.00 37,730.00
Paku Triplek/Eternit 0.1200 kg 18,700.00 2,244.00
Jumlah 39,974.00
Nilai Total : 39,974.00
8 Pemasangan Atap Asbes Gelombang 180 cm x 105 cm m2
Bahan :
Asbes Gelombang Kecil 180x105 0.5700 Lembar 97,850.00 55,774.50
Paku Skrup 0.1200 kg 30,900.00 3,708.00
Jumlah 59,482.50
Nilai Total : 59,482.00 a
9 Keramik Uk. 40 x 40 cm Motif / Warna m2
Bahan :
Semen PC (Portland Cement) 50 kg 0.1960 Zak 47,380.00 9,286.48
Semen Berwarna Yiyitan 1.3000 Kg 17,510.00 22,763.00
Pasir Pasang 0.0450 m3 267,800.00 12,051.00
Tegel Keramik 40 x 40 Cm 1.0608 m2 46,350.00 49,168.08
Jumlah 93,268.56
Nilai Total : 93,000.00 a
10 Keramik Uk. 30 x 30 cm Motif / Warna m2
Bahan :
Semen PC (Portland Cement) 50 kg 0.1960 Zak 47,380.00 9,286.48
Semen Berwarna Yiyitan 1.3000 Kg 17,510.00 22,763.00
Pasir Pasang 0.0450 m3 267,800.00 12,051.00
Tegel Keramik 30 x 30 Cm 1.0639 m2 46,350.00 49,313.16
Jumlah 93,413.64
Nilai Total : 93,000.00
11 Keramik Uk. 20 x 20 cm KM
Bahan :
Semen PC (Portland Cement) 50 kg 0.2080 Zak 47,380.00 9,855.04
Semen Berwarna Yiyitan 1.6200 Kg 17,510.00 28,366.20
Pasir Pasang 0.0450 m3 267,800.00 12,051.00
Tegel Keramik 20 x 20 Cm 1.0600 m2 48,410.00 51,314.60
Jumlah 51,314.60
1 Pemasangan Tegel Keramik 20x25 cm (Dinding) m2
Bahan :
Semen PC (Portland Cement) 50 kg 0.1860 zak 47,380.00 8,812.68 1
Semen Berwarna Yiyitan 1.9400 Kg 17,510.00 33,969.40
Pasir Pasang 0.0180 m3 267,800.00 4,820.40
Tegel Keramik 20 x 25 Cm 1.0500 Bh 46,350.00 48,667.50
Jumlah 96,269.98
Nilai Total : 96,269.98
2 Pemasangan Tegel Keramik 30x30 cm (Dinding) m2
Bahan :
Semen PC (Portland Cement) 50 kg 0.1860 zak 47,380.00 8,812.68 1
Semen Berwarna Yiyitan 1.5000 Kg 17,510.00 26,265.00
Pasir Pasang 0.0180 m3 267,800.00 4,820.40
Tegel Keramik 20 x 25 Cm 1.0406 m2 46,350.00 48,231.81
Jumlah 88,129.89
Nilai Total : 88,000.00
11 Keramik Dinding Uk. 30 x 60 cm m2
Bahan :
Semen PC (Portland Cement) 40 kg 0.1860 Zak 71,000.00 13,206.00
Semen Berwarna Yiyitan 1.9400 Kg 11,200.00 21,728.00
Pasir Pasang 0.0180 m3 150,000.00 2,700.00
Tegel Keramik 30 x 60 Cm 1.0500 m2 90,000.00 94,500.00
Jumlah 132,134.00
Nilai Total : 132,134.00
12 Keramik Dinding Uk. 10 x 40 cm m1
Bahan :
Semen PC (Portland Cement) 40 kg 0.1860 Kg 1,775.00 330.15 1
Semen Berwarna Yiyitan 0.1000 Kg 11,200.00 1,120.00
Pasir Pasang 0.0030 m3 150,000.00 450.00
Tegel Keramik 10 x 40 Cm 3.0000 Bh 4,166.67 12,500.00
Jumlah 14,400.15
Nilai Total : 14,400.15
1 Pemasangan Plafond Kalsiboard+Rangka Plafon Metalfurring m2
Bahan :
Metalfurring 40/40 0.7500 m1 132,000.00 99,000.00
Metalfurring 20/40 2.0000 m1 66,000.00 132,000.00
Kalsiboard Tebal 4,5 mm uk. 1,22x2,4 m 0.3819 Buah 60,770.00 23,208.06
Skrup 4.0000 Buah 7,354.20 29,416.80
Jumlah 283,624.86
Nilai Total : 283,624.00
1 Pemasangan Plafon Triplek Rangka Kayu Meranti m2
Bahan :
Kayu Meranti (Balok 4/6) 0.0230 ljr 28,840.00 663.32
Triplek tebal 40 mm 1,20 x 2,40 m 0.3900 Lembar 77,250.00 30,127.50
Paku Triplek/Eternit 0.0600 kg 5,150.00 309.00
Paku Usuk 3" & 2.5" 1.0368 Kg 17,510.00 18,154.37
Jumlah 49,254.19
Nilai Total : 49,000.00
13 Pemasangan Plafond Kalsiboard+Rangka Plafon Metalfurring m2
Bahan :
Metalfurring 40/40 1.7000 m1 7,000.00 11,900.00
Metalfurring 20/40 2.0000 m1 6,000.00 12,000.00
Kalsiboard Tebal 4,5 mm uk. 1,22x2,4 m 0.3819 Buah 106,750.00 40,767.83
Skrup 4.0000 Buah 150.00 600.00
Jumlah 65,267.83
Nilai Total : 65,267.82
14 Pembongkaran Plafond m2
Upah :
Mandor 0.0750 O.H 113,000.00 8,475.00
Kepala Tukang Kayu 0.0250 O.H 111,500.00 2,787.50
Pembantu Tukang 0.2500 O.H 110,000.00 27,500.00
Tukang Kayu 0.1500 O.H 108,400.00 16,260.00
Jumlah 55,022.50
Nilai Total : 55,022.50
15 Pemasangan panel pembagi sisi A titik
Bahan :
Boks panel 1.0000 bh 850,000.00 850,000.00
MCCB 20 A 3 phase 1.0000 bh 0.00 0.00
MCB 16 A 1 phase 1.0000 bh 0.00 0.00
MCB 10 A 1 phase 1.0000 bh 94,000.00 94,000.00
MCB 6 A 1 phase 4.0000 bh 56,000.00 224,000.00
Pilot Lamp 3.0000 bh 17,500.00 52,500.00
Fuse 3.0000 bh 4,750.00 14,250.00
Jumlah 1,234,750.00
Nilai Total : 1,234,750.00
16 Pemasangan Titik Lampu Gedung titik
Bahan :
Isolator 4.0000 Buah 5,500.00 22,000.00
Kabel NYM 500 Volt 3 x 2,5 mm2 10.0000 m1 8,340.00 83,400.00
Pipa Pralon 5/8 1.0000 Lonjor 20,000.00 20,000.00
T Doos Pvc 1.0000 Buah 1,750.00 1,750.00
Fiting Plafon 1.0000 Buah 42,500.00 42,500.00
Jumlah 169,650.00
Nilai Total : 169,650.00
17 Pembongkaran Titik Lampu Gedung titik
Upah :
Kepala Tukang Listrik 0.0500 O.H 33,250.00 1,662.50
Tukang Listrik 0.5000 O.H 110,000.00 55,000.00
Pembantu Tukang 0.3000 O.H 108,400.00 32,520.00
Jumlah 89,182.50
Nilai Total : 89,182.50
18 Pemasangan Titik Stop Kontak Gedung titik
Bahan :
Stop Kontak 1.0000 Buah 25,750.00 25,750.00
Kabel NYM 500 Volt 3 x 2,5 mm2 10.0000 m1 8,755.00 87,550.00
Pipa Pralon 5/8 1.0000 Lonjor 20,000.00 20,000.00
T Doos Pvc 1.0000 Buah 1,750.00 1,750.00
Jumlah 135,050.00
Nilai Total : 135,050.00
19 Pemasangan Titik Saklar Ganda titik
Bahan :
Saklar Ganda 1.0000 Buah 35,350.00 35,350.00
Jumlah 35,350.00
Nilai Total : 35,350.00
20 Pemasangan Titik Saklar Tunggal titik
Bahan :
Saklar Tunggal 1.0000 Buah 20,600.00 20,600.00
Jumlah 20,600.00
Nilai Total : 20,600.00
10 Pemasangan Kloset Duduk bh
Bahan :
Closet Duduk 1.0000 bh 750,000.00 750,000.00
Perlengkapan 6 % harga Closet 0.0600 bh 750,000.00 45,000.00
Jumlah 795,000.00
Nilai Total : 795,000.00 a
11 Pemasangan Kloset Jongkok bh
Bahan :
Closet Jongkok 1.0000 bh 154,500.00 154,500.00
Semen portland (50kg) 0.1200 zak 47,380.00 5,685.60
Pasir Pasang 0.0100 m3 267,800.00 2,678.00
Jumlah 162,863.60
Nilai Total : 162,000.00
12 Pemasangan Wastafel bh
Bahan :
Wastafel Besar Warna 1.0000 Buah 327,000.00 327,000.00
Perlengkapan 12 % harga wastafel 0.1200 Buah 327,000.00 39,240.00
Semen PC (Portland Cement) 40 kg 0.1200 zak 71,000.00 8,520.00
Pasir Pasang 0.0100 m3 150,000.00 1,500.00
Jumlah 376,260.00
Nilai Total : 376,260.00
13 Pemasangan Pipa Air Bersih diameter 1'' m1
Bahan :
Pipa PVC 1'' type AW 0.3000 batang 30,600.00 9,180.00
Perlengkapan 35% harga pipa 0.1050 buah 30,600.00 3,213.00
Jumlah 12,393.00
Nilai Total : 12,393.00
14 Pemasangan Pipa Air Bersih diameter 3'' m1
Bahan :
Pipa PVC 3'' type AW 0.3000 batang 133,900.00 40,170.00
Perlengkapan 35% harga pipa 0.1050 buah 133,900.00 14,059.50
Jumlah 54,229.50
Nilai Total : 54,000.00
15 Pemasangan Pipa Air Bersih diameter 4'' m1
Bahan :
Pipa PVC 4'' type AW 0.3000 batang 139,050.00 41,715.00
Perlengkapan 35% harga pipa 0.1050 buah 139,050.00 14,600.25
Jumlah 56,315.25
Nilai Total : 56,000.00
16 Pemasangan Pipa Air Kotor diameter 3'' m1
Bahan :
Pipa PVC 3'' type AW 0.3000 batang 133,900.00 40,170.00
Perlengkapan 35% harga pipa 0.1050 buah 133,900.00 14,059.50
Jumlah 54,229.50
Nilai Total : 54,000.00
17 Pemasangan Pipa Air Kotor diameter 4'' m1
Bahan :
Pipa PVC 4'' type AW 0.3000 batang 139,050.00 41,715.00
Perlengkapan 35% harga pipa 0.1050 buah 139,050.00 14,600.25
Jumlah 56,315.25
Nilai Total : 56,000.00

16 Pemasangan Talang Pembuluh Pipa PVC 3" Type AW m1


Bahan :
Pipa PVC 3" Type AW Pj. 4.00 Mt 0.3000 Lonjor 127,500.00 38,250.00
Perlengkapan 35% harga pipa 0.1050 Buah 127,500.00 13,387.50
Jumlah 51,637.50
Nilai Total : 51,637.50
17 Pemasangan Talang Pembuluh Pipa PVC 4" Type AW m1
Bahan :
Pipa PVC 4" Type AW panjang 4m 0.3000 Lonjor 227,500.00 68,250.00
Perlengkapan 35% harga pipa 0.1050 Buah 227,500.00 23,887.50
Jumlah 92,137.50
Nilai Total : 92,137.50
1 Pemasangan Talang Seng Galvalum tebal 0.3 m1
Bahan :
Seng galvalum lebar 90 tebal 0.03 (galvanis) 1.0000 m1 41,200.00 41,200.00
Jumlah 41,200.00
Nilai Total : 41,000.00
18 Pemasangan Septicktank m1
Bahan :
Buis Beton 2.0000 bh 132,000.00 264,000.00
Jumlah 264,000.00
Nilai Total : 264,000.00
11 Daun Pintu Panil (Kayu Meranti) m2
Bahan :
Kayu Meranti Papan 4/10 1.0000 bh 978,500.00 978,500.00
Plitur lengkap 0.4000 kaleng 463,500.00 185,400.00
Jumlah 1,163,900.00
Nilai Total : 1,163,900.00 a
11 Daun Pintu PVC
Bahan :
Daun Pintu PVC 1.0000 bh 206,000.00 206,000.00
Jumlah 206,000.00
Nilai Total : 206,000.00
12 Kusen Pintu/Jendela Kayu Meranti Komplit m3
Bahan :
kusen komplit 1.0000 bh 1,545,000.00 1,545,000.00
Plitur lengkap 0.4000 kaleng 463,500.00 185,400.00
Jumlah 1,730,400.00
Nilai Total : 1,730,000.00
18 Pemasangan Kusen Alumunium Profil 4" m1
Bahan :
Aluminium Putih Uk. 4 x 10, Profil 4" 1.1000 m1 220,000.00 242,000.00
Skrup/Ripet 2.0000 Buah 150.00 300.00
Sealent 0.0600 Tube 26,800.00 1,608.00
Jumlah 243,908.00
Nilai Total : 243,908.00
19 Pemasangan Slimar Alumunium Profil 3/8" m1
Bahan :
Slimar Alumunium 3/8 1.1000 m1 62,375.00 68,612.50
Sealent 0.0600 Tube 26,800.00 1,608.00
Skrup/Ripet 2.0000 Buah 150.00 300.00
Jumlah 70,520.50
Nilai Total : 70,520.50
20 Pemasangan Kaca Mati tebal 5 mm m2
Bahan :
Kaca Polos Tebal 5 mm 1.1000 m2 90,000.00 99,000.00
Jumlah 99,000.00
Nilai Total : 99,000.00
21 Pemasangan Kawat Nyamuk (Kassa Aluminium) m2
Bahan : 1500000
Plat Besi / Baja 1.7160 m2 25,000.00 42,900.00 1.68
Kawat Nyamuk Kasa Aluminium 1.1000 m2 35,000.00 38,500.00 892857.143
Pekerjaan Pengelasan dengan las listrik 11.1100 m2 2,510.20 27,888.32
Jumlah 109,288.32
Nilai Total : 109,288.32
22 Pemasangan Kisi Kisi Suncreen Aluminium m2
Bahan :
Pas. Sunscreen Alluminium tbl=1mm 1.1000 m1 42,000.00 46,200.00
Jumlah 46,200.00
Nilai Total : 46,200.00
23 Pemasangan Kaca Cermin tebal 5 mm m2
Bahan :
Kaca Cermin Tebal 5 mm 1.1000 m2 182,000.00 200,200.00
Jumlah 200,200.00
Nilai Total : 200,200.00
24 Pemasangan Engsel Kuningan Untuk Pintu stel
Bahan :
Engsel Kuningan (untuk Pintu) 1.0000 stel 34,100.00 34,100.00
Jumlah 34,100.00
Nilai Total : 34,100.00
25 Pemasangan Engsel Besi stel
Bahan :
Engsel Besi 1.0000 stel 165,000.00 165,000.00
Jumlah 165,000.00
Nilai Total : 165,000.00
26 Pemasangan Friction Stay 12" stel
Bahan :
Friction Stay 12" 1.0000 stel 110,000.00 110,000.00
Jumlah 110,000.00
Nilai Total : 110,000.00
27 Pemasangan Kunci Tanam stel
Bahan :
Kunci Tanam 1.0000 buah 62,200.00 62,200.00
Jumlah 62,200.00
Nilai Total : 62,200.00
28 Pemasangan Kunci Tanam Besar 2x Putar kuningan stel
Bahan :
Kunci Tanam Besar 2X Putar (kuningan) 1.0000 buah 108,400.00 108,400.00
Jumlah 108,400.00
Nilai Total : 108,400.00
1 Septictank
Bahan :
Buis Beton Bulat Ukuran 100 x 50 cm 2.0000 bh 180,250.00 360,500.00
Tutup Buis Beton 1.0000 bh 108,150.00 108,150.00
pipa pvc 4" + alat 1.0000 ls 154,500.00 154,500.00
Jumlah 623,150.00
Nilai Total : 623,150.00
29 Plamir Tembok m2
Bahan :
Semen Putih 0.1000 sak 87,550.00 8,755.00
Kertas Gosok no 150 0.5000 lbr 8,240.00 4,120.00
Jumlah 12,875.00
Nilai Total : 12,000.00
30 Plamir Primer Tembok Luar m2
Bahan :
Alkali Resisting Primer 0.1000 kg 25,000.00 2,500.00
Kertas Gosok no 150 0.5000 lbr 8,750.00 4,375.00
Jumlah 6,875.00
Nilai Total : 6,875.00
31 Pengecatan Tembok Lama (1 lapis cat dasar,2 lapis cat penutup) m2
Bahan :
Dempul Tembok (cat Dasar) 0.1200 Kg 15,450.00 1,854.00
Cat Tembok dalam (5 kg) 0.0360 kaleng 87,550.00 3,151.80
Jumlah 5,005.80
Nilai Total : 5,000.00
32 Pengecatan Tembok Weathershield (1 lapis cat dasar,2 lapis cat penutup) m2
Bahan :
Dempul Tembok (cat Dasar) 0.1200 Kg 15,000.00 1,800.00
Cat Tembok Weathershield / Tembok luar 0.0720 kaleng 92,700.00 6,674.40
Jumlah 8,474.40
Nilai Total : 8,474.00
13 Pengecatan Tembok dan plamir m2
Pengecatan Tembok Lama 1.0000 m2 5,000.00 5,000.00
Plamir Tembok 1.0000 m2 12,000.00 12,000.00
Jumlah 17,000.00
Nilai Total : 17,000.00 a
14 Pengecatan Tembok Weathershield dan plamur Primer (1 lapis cat dasar,2 lapis cat p m2
Pengecatan Tembok Weathershield (1 lapis cat dasar,2 lapis cat penutup) 1.0000 m2 8,474.00 8,474.00
Plamur Primer Tembok Luar 1.0000 m2 6,875.00 6,875.00
Jumlah 15,349.00
Nilai Total : 15,349.00
15 Pelapisan Waterprofing Berserat m2
Bahan :
Waterprofing 0.3500 m2 38,750.00 13,562.50
Serat Fiber 1.0000 m1 4,500.00 4,500.00
Jumlah 18,062.50
Nilai Total : 18,062.50
16 Pekerjaan Lapis Melamin Duco (2x Lapis Sampai Rata) m2
Bahan :
Wood Filler 0.2000 Kg 27,500.00 5,500.00
Kertas Gosok no 150 1.0000 Lembar 8,750.00 8,750.00
Kertas Gosok no 280 1.0000 Lembar 10,250.00 10,250.00
Shanding 0.5000 Kg 50,500.00 25,250.00
Clear Doof 0.2000 Kg 46,000.00 9,200.00
Thinner A 0.8370 Liter 24,000.00 20,088.00
Coumpond 0.2000 Kaleng 19,000.00 3,800.00
Jumlah 82,838.00
Alat :
Sewa alat bantu (1 set @ 3 alat) 1.0000 Set 950.00 950.00
Sewa Compresor 0.6250 Jam 33,250.00 20,781.25
Jumlah 21,731.25
Nilai Total : 104,569.25
DAFTAR STANDAR HARGA SATUAN DASAR
(SHSD)
NAMA PEMILIK : DJOKO SANTOSO
ALAMAT PEMILIK : RANGKAH II/87 RT 03 RW 05
KELURAHAN : RANGKAH
KECAMATAN : TAMBAKSARI

No. Uraian Satuan Harga Satuan pph 3% setelah pph 3% Keterangan

A MATERIAL :
1 Kayu Meranti (Papan 2/20) m3 Rp 5,000,000.00 Rp 150,000.00 Rp 5,150,000.00
2 Kayu Balok gording ( 5/7) lonjor Rp 78,000.00 Rp 2,340.00 Rp 80,340.00
3 Kayu Meranti (Usuk 5/7) m3 Rp 4,160,714.29 Rp 124,821.43 Rp 4,285,535.71
4 Kayu Meranti (Usuk 4/6) lonjor Rp 48,000.00 Rp 1,440.00 Rp 49,440.00
5 Kayu Meranti balok 3/5 m3 Rp 3,750,000.00 Rp 112,500.00 Rp 3,862,500.00
6 Kayu meranti bekisting m3 Rp 3,500,000.00 Rp 105,000.00 Rp 3,605,000.00
7 Plywood tebal 9 mm Lembar Rp 82,600.00 Rp 2,478.00 Rp 85,078.00 Parindo
8 Tego film tebal 12 mm Lembar Rp 210,000.00 Rp 6,300.00 Rp 216,300.00
9 Tego film tebal 18 mm Lembar Rp 308,000.00 Rp 9,240.00 Rp 317,240.00
10 Bata Merah biji Rp 600.00 Rp 18.00 Rp 618.00
11 Bata Herbel m3 Rp 660,000.00 Rp 19,800.00 Rp 679,800.00
12 Sirtu m3 Rp 115,000.00 Rp 3,450.00 Rp 118,450.00
13 Pasir urug m3 Rp 175,000.00 Rp 5,250.00 Rp 180,250.00
14 Pasir Cor m3 Rp 187,500.00 Rp 5,625.00 Rp 193,125.00
15 Tiang Pancang m1 Rp 223,000.00 Rp 6,690.00 Rp 229,690.00
16 Penyambungan Tiang Pancang Titik Rp 13,500.00 Rp 405.00 Rp 13,905.00
17 Pasir Pasang colt Rp 250,000.00 Rp 7,500.00 Rp 257,500.00
18 Batu Pecah Mesin 1/2 cm m3 Rp 250,000.00 Rp 7,500.00 Rp 257,500.00 Ex. UD. Hartono
19 Semen Mortar Zak Rp 85,000.00 Rp 2,550.00 Rp 87,550.00
20 Asbes Gel. Kecil 3m bh Rp 50,000.00 Rp 1,500.00 Rp 51,500.00
21 triplek 120, 120x240 lonjor Rp 65,000.00 Rp 1,950.00 Rp 66,950.00
22 Semen PC (Portland Cement) 40 kg Zak Rp 52,000.00 Rp 1,560.00 Rp 53,560.00 Gresik
23 Semen Berwarna Yiyitan Kg Rp 11,200.00 Rp 336.00 Rp 11,536.00 MU
24 Minyak Bekisting ltr Rp 8,500.00 Rp 255.00 Rp 8,755.00 Robinair
25 Air (biaya air tawar) Liter Rp 30.00 Rp 0.90 Rp 30.90
26 Besi beton polos/ulir Kg Rp 8,500.00 Rp 255.00 Rp 8,755.00 Setia Agung Jaya
27 Kawat Bendrat Kg Rp 14,500.00 Rp 435.00 Rp 14,935.00 Hi Steel
28 Talang Beton R.25 (1/2 Lingkaran) Bh Rp 35,000.00 Rp 1,050.00 Rp 36,050.00
29 Paku Usuk Kg Rp 13,850.00 Rp 415.50 Rp 14,265.50 Hi Steel
30 Paku Biasa 2"-5" kg Rp 12,750.00 Rp 382.50 Rp 13,132.50 Hi Steel
31 Hollow Metalfurring 40/40 m' Rp 7,000.00 Rp 210.00 Rp 7,210.00 Hi Steel
32 Hollow Metalfurring 20/40 m' Rp 6,000.00 Rp 180.00 Rp 6,180.00 Hi Steel
33 Skrup bh Rp 150.00 Rp 4.50 Rp 154.50 Hi Steel
34 Aluminium Putih Uk. 4 x 10, Profil 4" m1 Rp 220,000.00 Rp 6,600.00 Rp 226,600.00 YKK
35 Slimar Alumunium 3/8 m1 Rp 62,375.00 Rp 1,871.25 Rp 64,246.25
36 Boks panel bh Rp 850,000.00 Rp 25,500.00 Rp 875,500.00
37 MCB 10 A 1 phase bh Rp 94,000.00 Rp 2,820.00 Rp 96,820.00
38 MCB 6 A 1 phase bh Rp 56,000.00 Rp 1,680.00 Rp 57,680.00
39 Pilot Lamp bh Rp 17,500.00 Rp 525.00 Rp 18,025.00
40 Tegel Keramik 40 x 40 Cm m2 Rp 50,000.00 Rp 1,500.00 Rp 51,500.00
41 Tegel Keramik 30 x 30 Cm m2 Rp 55,000.00 Rp 1,650.00 Rp 56,650.00
42 Tegel Keramik 20 x 20 Cm m2 Rp 55,000.00 Rp 1,650.00 Rp 56,650.00
43 Tegel Keramik 20 x 25 Cm m2 Rp 60,000.00 Rp 1,800.00 Rp 61,800.00
44 Fuse bh Rp 4,750.00 Rp 142.50 Rp 4,892.50
45 Pas. Daun Pintu / pas. daun jendela unit Rp 500,000.00 Rp 15,000.00 Rp 515,000.00
46 Pas. Daun Pintu Wood Solid Panel uk. 70x135 unit Rp 180,000.00 Rp 5,400.00 Rp 185,400.00
47 Isolator bh Rp 5,500.00 Rp 165.00 Rp 5,665.00 Vickers
48 Kabel NYM 3X2,5 m1 Rp 8,340.00 Rp 250.20 Rp 8,590.20 Eterna
49 Pipa Pralon 5/8 m1 Rp 5,000.00 Rp 150.00 Rp 5,150.00 Maspion
50 Fiting Plafon bh Rp 42,500.00 Rp 1,275.00 Rp 43,775.00
51 T doos PVC bh Rp 1,750.00 Rp 52.50 Rp 1,802.50 Shukaku
52 Stop Kontak bh Rp 18,500.00 Rp 555.00 Rp 19,055.00
53 Saklar Ganda bh Rp 35,350.00 Rp 1,060.50 Rp 36,410.50
54 Saklar Tunggal bh Rp 27,300.00 Rp 819.00 Rp 28,119.00
55 lampu LED 4 Watt bh Rp 88,200.00 Rp 2,646.00 Rp 90,846.00 Ex. Philips / Artolite / Saka
56 lampu LED 7 Watt bh Rp 122,050.00 Rp 3,661.50 Rp 125,711.50 Ex. Philips / Artolite / Saka
57 lampu LED 12 Watt bh Rp 149,385.00 Rp 4,481.55 Rp 153,866.55 Ex. Philips / Artolite / Saka
58 Pipa PVC 1'' type AW batang Rp 30,600.00 Rp 918.00 Rp 31,518.00 Wavin
59 Pipa PVC Ø3\ "AW panjang 4 mtr batang Rp 127,500.00 Rp 3,825.00 Rp 131,325.00 Wavin
60 Pipa PVC Ø4\ "AW panjang 4 mtr batang Rp 227,500.00 Rp 6,825.00 Rp 234,325.00 Wavin
61 Kaca Polos Tebal 5 mm m2 Rp 90,000.00 Rp 2,700.00 Rp 92,700.00 Assahimass
62 Kaca Cermin Tebal 5 mm m2 Rp 182,000.00 Rp 5,460.00 Rp 187,460.00 Assahimass
63 Closet Duduk Porselen bh Rp 2,000,000.00 Rp 60,000.00 Rp 2,060,000.00 Toto CW661jt1
64 Closet Jongkok Porselen bh Rp 150,000.00 Rp 4,500.00 Rp 154,500.00
65 Pas Floor Clean Out 3" Ex. San Ei / Onda / American Standart bh Rp 317,400.00 Rp 9,522.00 Rp 326,922.00
66 Pas Floor Clean Out 4" Ex. San Ei / Onda / American Standart bh Rp 423,200.00 Rp 12,696.00 Rp 435,896.00
67 Wastafel Besar Warna bh Rp 327,000.00 Rp 9,810.00 Rp 336,810.00 Toto L38V1
68 Urinoir ex. American standard / Toto bh Rp 2,190,000.00 Rp 65,700.00 Rp 2,255,700.00
69 Keramik 40x 40cm (motif/warna) m2 Rp 80,000.00 Rp 2,400.00 Rp 82,400.00 Platinum / Roman
70 Tegel Keramik 25 x 40 cm(bermotif) m2 Rp 85,000.00 Rp 2,550.00 Rp 87,550.00 Platinum / Roman
71 Tegel Keramik 10 x 40 cm(bermotif) Bh Rp 4,166.67 Rp 125.00 Rp 4,291.67 Platinum / Roman
72 Bio Filter 2 m3 bh Rp 8,000,000.00 Rp 240,000.00 Rp 8,240,000.00 BioSeven
73 Avour bak mandi bh Rp 35,000.00 Rp 1,050.00 Rp 36,050.00
74 Kunci Tanam kecil bh Rp 75,000.00 Rp 2,250.00 Rp 77,250.00 Solid
75 Kunci Tanam Besar 2X Putar (kuningan) bh Rp 97,000.00 Rp 2,910.00 Rp 99,910.00 Solid
76 Engsel Kuningan 4"(untuk Pintu) stel Rp 26,000.00 Rp 780.00 Rp 26,780.00 Solid
77 Cat Tembok luar Kg Rp 21,000.00 Rp 630.00 Rp 21,630.00 jotashiled, dulux weat
78 Plamur Tembok Kg Rp 15,000.00 Rp 450.00 Rp 15,450.00 Big lion
79 Cat Alkali Resisting Primer Kg Rp 25,000.00 Rp 750.00 Rp 25,750.00 Jotun, dulux
80 Dempul Tembok (cat Dasar) Kg Rp 15,000.00 Rp 450.00 Rp 15,450.00 gm2
81 Cat Tembok dalam (5 kg) kaleng Rp 105,000.00 Rp 3,150.00 Rp 108,150.00 jotashiled, dulux weat
82 cat kayu kg Rp 60,000.00 Rp 1,800.00 Rp 61,800.00
83 lem putih dos Rp 150,000.00 Rp 4,500.00 Rp 154,500.00 rajawali
84 kalsium sak Rp 40,000.00 Rp 1,200.00 Rp 41,200.00
85 Kertas Gosok no 150 Lembar Rp 20,000.00 Rp 600.00 Rp 20,600.00 Taiyo
86 Kertas Gosok no 280 Lembar Rp 10,250.00 Rp 307.50 Rp 10,557.50 Taiyo
87 Wood Filler kg Rp 27,500.00 Rp 825.00 Rp 28,325.00
88 Shanding Kg Rp 50,500.00 Rp 1,515.00 Rp 52,015.00 Peacock
89 Clear Doof kg Rp 46,000.00 Rp 1,380.00 Rp 47,380.00 Suzuka
90 Thinner A ltr Rp 15,000.00 Rp 450.00 Rp 15,450.00 Thinner
91 Coumpond Kg Rp 19,000.00 Rp 570.00 Rp 19,570.00 Blinken
92 Waterprofing m2 Rp 38,750.00 Rp 1,162.50 Rp 39,912.50 No drop
93 Serat Fiber m' Rp 4,500.00 Rp 135.00 Rp 4,635.00 serat mat
94 Sealent tube Rp 26,800.00 Rp 804.00 Rp 27,604.00 Shirikon
95 Engsel Sikutan / Friction stay 12" stel Rp 110,000.00 Rp 3,300.00 Rp 113,300.00
96 Engsel Besi stel Rp 165,000.00 Rp 4,950.00 Rp 169,950.00
97 Handle casement bh Rp 17,825.00 Rp 534.75 Rp 18,359.75
98 Handle pintu set Rp 150,000.00 Rp 4,500.00 Rp 154,500.00
99 Kalsiboard Tebal 4,5 mm uk. 1,2x2,4 m Lembar Rp 106,750.00 Rp 3,202.50 Rp 109,952.50 Kalsiboard
100 Besi Pipa Putih (Stainless) SCH Welded uk. 2 inch m1 Rp 107,500.00 Rp 3,225.00 Rp 110,725.00
101 Besi Pipa Putih (Stainless) SCH Welded uk. 1 inch m1 Rp 97,000.00 Rp 2,910.00 Rp 99,910.00
102 Besi Pipa Putih (Stainless) SCH Welded uk. 1/2 inch m1 Rp 89,200.00 Rp 2,676.00 Rp 91,876.00
103 Mesin Pompa groundfos type centrifugal unit Rp 3,500,000.00 Rp 105,000.00 Rp 3,605,000.00
104 Kran air 3/4" ex. Onda / American Standart / San Ei bh Rp 35,000.00 Rp 1,050.00 Rp 36,050.00
105 Profil tank 1100 litter unit Rp 2,383,000.00 Rp 71,490.00 Rp 2,454,490.00 Cipta Proma perkasa
106 Batu Alam Bh Rp 20,800.00 Rp 624.00 Rp 21,424.00
107 Glassblock Uk. 20x20cm Standart Bh Rp 30,800.00 Rp 924.00 Rp 31,724.00 Mulia
108 Roster 20x40cm Bh Rp 18,000.00 Rp 540.00 Rp 18,540.00
109 Besi Profil (Baja Konstruksi) kg Rp 12,000.00 Rp 360.00 Rp 12,360.00
110 Elektroda Kg Rp 30,000.00 Rp 900.00 Rp 30,900.00
111 Cat Meni Besi Kg Rp 32,000.00 Rp 960.00 Rp 32,960.00
112 Baut HTB 16 Bh Rp 12,500.00 Rp 375.00 Rp 12,875.00
113 Angker Bolt Dia 19 mm Bh Rp 16,500.00 Rp 495.00 Rp 16,995.00
114 Rangka Galvalume campuran m2 Rp 264,900.00 Rp 7,947.00 Rp 272,847.00
115 Rangka Galvalume Uk. 0.8 mm m2 Rp 222,000.00 Rp 6,660.00 Rp 228,660.00
116 Genteng Karang Pilang Bh Rp 4,000.00 Rp 120.00 Rp 4,120.00
117 Semen PC 50 Kg Zak Rp 50,000.00 Rp 1,500.00 Rp 51,500.00
118 semen putih zak Rp 100,000.00 Rp 3,000.00 Rp 103,000.00
119 Pasir Pasang / Plester m3 Rp 250,000.00 Rp 7,500.00 Rp 257,500.00
120 Genteng Wuwung karang pilang / wisma Buah Rp 13,000.00 Rp 390.00 Rp 13,390.00
121 Runcingan penangkal petir/ spliter 1" Bh Rp 400,000.00 Rp 12,000.00 Rp 412,000.00
122 Kabel BC dia 50 mm2 m1 Rp 45,000.00 Rp 1,350.00 Rp 46,350.00
123 Pipa Pralon 5/8 lonjor Rp 5,000.00 Rp 150.00 Rp 5,150.00
124 Klem Kabel BC dia 50 mm2 Bh Rp 20,000.00 Rp 600.00 Rp 20,600.00
125 Pentanahan grounding kabel BC 50 mm2 m1 Rp 45,000.00 Rp 1,350.00 Rp 46,350.00
126 Bak kontrol Unit Rp 200,000.00 Rp 6,000.00 Rp 206,000.00
127 Box test line Set Rp 250,000.00 Rp 7,500.00 Rp 257,500.00
128 Kabel schoon Set Rp 5,500.00 Rp 165.00 Rp 5,665.00
129 Connector Set Rp 7,500.00 Rp 225.00 Rp 7,725.00
130 Peralatan bantu jam Rp 950.00 Rp 28.50 Rp 978.50
131 Testing dan commissioning termasuk izin - izin Penangkal petir Ls Rp 500,000.00 Rp 15,000.00 Rp 515,000.00
132 Besi Pipa Putih (Stainless) SCH Welded uk. 2 inch Bh Rp 107,500.00 Rp 3,225.00 Rp 110,725.00
133 Dynabolt Ø10mm Bh Rp 3,750.00 Rp 112.50 Rp 3,862.50
134 Plat Besi / Baja m2 Rp 25,000.00 Rp 750.00 Rp 25,750.00
135 Kawat Nyamuk Kasa Aluminium m2 Rp 35,000.00 Rp 1,050.00 Rp 36,050.00
136 Pekerjaan Pengelasan dengan las listrik m2 Rp 2,510.20 Rp 75.31 Rp 2,585.51
137 Pas. Sunscreen Alluminium tbl=1mm m1 Rp 42,000.00 Rp 1,260.00 Rp 43,260.00
138 kuas cat 4 ∅ bh Rp 50,000.00 Rp 1,500.00 Rp 51,500.00
139 timba cor bh Rp 15,000.00 Rp 450.00 Rp 15,450.00
140 kusen ( 80x200 cm) unit Rp 750,000.00 Rp 22,500.00 Rp 772,500.00
141 bak mandi bh Rp 200,000.00 Rp 6,000.00 Rp 206,000.00
142 pintu PVC bh Rp 200,000.00 Rp 6,000.00 Rp 206,000.00
143
Rp 4,998,471,000.00

Rp 4,998,471,000.00

Rp 4,998,471,000.00

Ex. Philips / Artolite / Saka


Ex. Philips / Artolite / Saka
Ex. Philips / Artolite / Saka

Rp 4,998,471,000.00
Cipta Proma perkasa
TIME SCHEDULE

NAMA PEMILIK : DJOKO SANTOSO


ALAMAT PEMILIK : RANGKAH II/87 RT 03 RW 05
KELURAHAN : RANGKAH
KECAMATAN : TAMBAKSARI

JANGKA WAKTU PELAKSANAAN (HARI)


BOBOT G
NO URAIAN PEKERJAAN R
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 A
(%) F
I
K

I. PEKERJAAN TANAH & URUGAN


1 Pengurugan Gragal 3.921 1.960 1.960 100
3.921

II PEKERJAAN STRUKTUR
1 Pekerjaan Kolom Praktis (11 x 11 cm) 3.565 1.782 1.782
2 Pekerjaan Ring Balk (10x15cm) 3.904 1.952 1.952
7.468

III PEKERJAAN STRUKTUR ATAP


1 Pemasang rangka atap Galvalume t=0.8 mm 5.254 2.627 2.627
2 Pemasangan Plafon Triplek Rangka Kayu Meranti 3.565 1.782 1.782
3 P. Atap Asbes Gelombang kecil 210 cm x 105 cm x 0.4 cm 3.993 1.996 1.996
12.811
IV PEKERJAAN ARSITEKTUR
IV.1 PEKERJAAN PASANGAN DAN PLESTERAN
1 Pasangan dinding bata ringan 10 cm 21.196 4.239 4.239 4.239 4.239 4.239
2 Plesteran 1Pc : 5Ps tebal 1,5cm 3.023 1.511 1.511
3 Acian 0.824 0.824
4 Plamir Tembok 3.298 3.298
5 Pengecatan Dinding 1.414 0.707 0.707
29.756
IV.2 PEKERJAAN KUSEN
1 Kusen Pintu/Jendela Kayu Meranti Komplit 6.992 3.496 3.496
2 Pasangan Jendela Bouvenlist 1.665 1.665
8.657
IV.3 PEKERJAAN PENUTUP LANTAI
1 Pas. Keramik Uk. 40 x 40 cm 9.020 2.255 2.255 2.255 2.255
9.020

V UPAH TENAGA KERJA


1 Upah Pengawas (1 unit x 1 org) 0.562 0.035 0.035 0.035 0.035 0.035 0.035 0.035 0.035 0.035 0.035 0.035 0.035 0.035 0.035 0.035 0.035
2 Upah Tukang (1 unit x 2 org x 16 hari) 15.519 0.970 0.970 0.970 0.970 0.970 0.970 0.970 0.970 0.970 0.970 0.970 0.970 0.970 0.970 0.970 0.970
3 Upah Pembantu Tukang (1 unit x 2 org x 16 hari) 12.286 0.768 0.768 0.768 0.768 0.768 0.768 0.768 0.768 0.768 0.768 0.768 0.768 0.768 0.768 0.768 0.768
28.367
0
JUMLAH 100.000
RENC. KOMULATIF 3.733 3.733 7.794 9.746 7.964 6.012 9.508 7.896 4.400 5.434 5.281 7.322 9.932 4.028 4.735 2.480
RENC.AKUMULATIF - 3.733 7.467 15.261 25.008 32.972 38.984 48.492 56.387 60.787 66.222 71.502 78.824 88.757 92.785 97.520 100.000

Surabaya, 2017
Mengetahui UPKM "TULUS SEJATI"
Pejabat Pembuat komitmen Kelurahan Rangkah

Agus Rosid, SST Moch. Misbachul Munir


P e n a t a / III - C Ketua UPKM
NIP. 19650813 199302 1 001
DAFTAR STANDAR HARGA SATU
(SHSD)
NAMA PEMILIK : DJOKO SANTOSO
ALAMAT PEMILIK : RANGKAH II/87 RT 03 RW 05
KELURAHAN : RANGKAH
KECAMATAN : Sukolilo

No. Uraian Satuan volume

A PERSIAPAN BAHAN ALAT PEKERJA


1 SEKOP bh 1
2 CANGKUL bh 1
3 TIMAH COR bh 4
4 BENANG bh 2
5 KAWAT AYAKAN m1 1
6 KAYU 3X5 MERANTI btg 1
B PEKERJAAN URUGAN
7 URUG colt 8
8
C PEKERJAAN DINDING, PLETERAN & BENANGAN
9 BATA MERAH bh 3000
10 PLESTER & PASANG colt 6
11 SEMEN PASANG & PLESTER sak 16
12 SEMEN ACIAN + BENANG SUDUT sak 5
D PEKERJAAN ATAP
13 KAYU 6X10X4 M btg 4
14 KAYU 5X7X4 M btg 16
15 ASBES GELOMBANG KECIL lmbr 16
16 PAKU kg 4
17 PAKU SKRUP ASBES+ KARET bh 200
E PEKERJAAN PLAFON
18 KAYU 4X6X4 M btg 25
19 TRIPLEK 4MM lmbr 18
20 PAKU USUK 3" & 2.5" kg 4
21 PAKU TRIPLEK kg 1
F BAHAN KUSEN DAN POLITUR
22 KUSEN KOMPLIT & NAKO + KACA set 1
23 DAUN PINTU PANIL set 1
24 POLITUR LENGKAP set 1
G PEKERJAAN KERAMIK
25 KERAMIK LANTAI 40X40 m2 38
26 KERAMIK DINDING 20X25 m2 6
27 KERAMIK LANTAI 20X20 m2 3
28 PASIR PASANG colt 1
29 SEMEN sak 5
30 SEMEN NAT kg 3
31 KLOSET JONGKOK bh 1
32 DAUN PINTU PVC bh 1
H BAHAN CAT TEMBOK
33 PLAMIR TEMBOK JADI kg 20
34 KERTAS GOSOK lmbr 5
35 KUAS/ROL bh 2
36 BAK CAT bh 1
37 CAT CATYLAK kg 20
I INSTALASI LISTRIK
38 KABEL LAMPU m1 60
39 SAKLAR & STOP KONTAK bh 8
40 FITING DAN LAMPU bh 6
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
DAR HARGA SATUAN DASAR
(SHSD)

Harga Satuan 3% Harga Satuan + PPH Jumlah

Rp 55,000.00 Rp 1,650.00 Rp 56,650.00 Rp 56,650.00


Rp 45,000.00 Rp 1,350.00 Rp 46,350.00 Rp 46,350.00
Rp 7,500.00 Rp 225.00 Rp 7,725.00 Rp 30,900.00
Rp 4,500.00 Rp 135.00 Rp 4,635.00 Rp 9,270.00
Rp 25,000.00 Rp 750.00 Rp 25,750.00 Rp 25,750.00
Rp 35,000.00 Rp 1,050.00 Rp 36,050.00 Rp 36,050.00 Rp 204,970.00

Rp 175,000.00 Rp 5,250.00 Rp 180,250.00 Rp 1,442,000.00


Rp 1,442,000.00

Rp 750.00 Rp 22.50 Rp 772.50 Rp 2,317,500.00


Rp 190,000.00 Rp 5,700.00 Rp 195,700.00 Rp 1,174,200.00
Rp 57,000.00 Rp 1,710.00 Rp 58,710.00 Rp 939,360.00
Rp 57,000.00 Rp 1,710.00 Rp 58,710.00 Rp 293,550.00 Rp 4,724,610.00

Rp 145,000.00 Rp 4,350.00 Rp 149,350.00 Rp 597,400.00 Rp 2,266,000.00


Rp 85,000.00 Rp 2,550.00 Rp 87,550.00 Rp 1,400,800.00
Rp 95,000.00 Rp 2,850.00 Rp 97,850.00 Rp 1,565,600.00
Rp 15,000.00 Rp 450.00 Rp 15,450.00 Rp 61,800.00
Rp 1,000.00 Rp 30.00 Rp 1,030.00 Rp 206,000.00

Rp 39,000.00 Rp 1,170.00 Rp 40,170.00 Rp 1,004,250.00


Rp 65,000.00 Rp 1,950.00 Rp 66,950.00 Rp 1,205,100.00
Rp 15,000.00 Rp 450.00 Rp 15,450.00 Rp 61,800.00
Rp 16,000.00 Rp 480.00 Rp 16,480.00 Rp 16,480.00

Rp 2,750,000.00 Rp 82,500.00 Rp 2,832,500.00 Rp 2,832,500.00


Rp 950,000.00 Rp 28,500.00 Rp 978,500.00 Rp 978,500.00
Rp 450,000.00 Rp 13,500.00 Rp 463,500.00 Rp 463,500.00
Rp 55,000.00 Rp 1,650.00 Rp 56,650.00 Rp 2,152,700.00 Rp 2,688,300.00
Rp 45,000.00 Rp 1,350.00 Rp 46,350.00 Rp 278,100.00
Rp 45,000.00 Rp 1,350.00 Rp 46,350.00 Rp 139,050.00
Rp 190,000.00 Rp 5,700.00 Rp 195,700.00 Rp 195,700.00
Rp 57,000.00 Rp 1,710.00 Rp 58,710.00 Rp 293,550.00
Rp 15,000.00 Rp 450.00 Rp 15,450.00 Rp 46,350.00
Rp 150,000.00 Rp 4,500.00 Rp 154,500.00 Rp 154,500.00
Rp 300,000.00 Rp 9,000.00 Rp 309,000.00 Rp 309,000.00

Rp 10,000.00 Rp 300.00 Rp 10,300.00 Rp 206,000.00


Rp 6,500.00 Rp 195.00 Rp 6,695.00 Rp 33,475.00
Rp 22,500.00 Rp 675.00 Rp 23,175.00 Rp 46,350.00 Rp 713,275.00
Rp 15,000.00 Rp 450.00 Rp 15,450.00 Rp 15,450.00
Rp 20,000.00 Rp 600.00 Rp 20,600.00 Rp 412,000.00

Rp 8,500.00 Rp 255.00 Rp 8,755.00 Rp 525,300.00


Rp 15,000.00 Rp 450.00 Rp 15,450.00 Rp 123,600.00
Rp 25,000.00 Rp 750.00 Rp 25,750.00 Rp 154,500.00
TOTAL Rp 21,047,535.00
SEHARUSNYA Rp 17,081,000.00
LEBIHNYA Rp 3,966,535.00
14.285714285714

Rp 7.50

Rp 60,000.00 4,945,050.00 #REF!

660

180,250.00 7,492.50 Rp 6,600.00

749.25
Rp 112,490.71
66

Rp 113,300.00
4,356,000.00

3%
70744.7368421053

Rp (17,081,000.00)
I. PEKERJAAN TANAH & URUGAN
1 Pengurugan Gragal Campur

II PEKERJAAN STRUKTUR ATAP


1 Pemasangan Gording Meranti
2 Pemasangan Reng Meranti/Usuk Meranti
3 Pemasangan Atap Asbes Gelombang 210 cm x 105 cm
4 Pemasangan Plafon Triplek Rangka Kayu Meranti

III PEKERJAAN ARSITEKTUIR


III.1 PEKERJAAN PASANGAN DAN PLESTERAN
1 Pasangan 1/2 batu merah dinding 1Pc : 4Ps
2 Plamir Tembok
3 Pengecatan Dinding

III.2 PEKERJAAN KUSEN


1 Kusen komplit
2 Daun Pintu dan Jendela Panil + kaca naco
3 Pas. Daun Pintu PVC
4 Handle Pintu

III.3 PEKERJAAN PENUTUP LANTAI


1 Pas. Keramik Lantai, Uk. 30X30cm
2 Pas. Kramik Km Mandi Uk. 20x20 cm

IV PEKERJAAN SANITASI
1 Kloset Jongkok
2 Bak mandi