PROYEK PERLUASAN TERMINAL CARGO

BANDARA UDARA JUANDA SURABAYA


2020

TENTANG
PEKERJAAN TAMBAH & KURANG AWAL /
MONTHLY CERTIFIKAT (MC-0 )
SEBAGAI PENGAJUAN ADDENDUM KE - 1

NAMA KEGIATAN
PEKERJAAN PERKERASAN JALAN
TERMINAL CARGO

LOKASI
BANDARA UDARA JUANDA SURABAYA

PENYEDIA BARANG DAN JASA


PT. MULYA ANUGRAH ABADI
REKAPITULASI PERHITUNGAN
PEKERJAAN TAMBAH & KURANG AWAL / MONTHLY CERTIFIKAT (MC-0 )
NAMA KEGIATAN : PEKERJAAN PERKERASAN JALAN TERMINAL CARGO
LOKASI : BANDARA UDARA JUANDA SURABAYA

NO JENIS PEKERJAAN KONTRAK AWAL MUTUAL CHECK (MC-0)

1 Agregat Kelas A tebal 15 cm 78.287.889 101.209.329

2 Prime Coat 17.377.900 22.466.000

3 Lap ATB tbl 7cm 314.752.500 346.434.030

4 Kanstin kerb uk 20x60 14.840.520 22.287.000

JUMLAH SUB TOTAL 425.258.809 492.396.359

DIBULATKAN 425.258.000 492.396.000


EMPAT RATUS SEMBILAN PULUH DUA JUTA TIGA RATUS SEMBILAN PULUH ENAM
TERBILANG :
RIBU RUPIAH

Surabaya, 05 Januari 2021


MENGUSULKAN MENYETUJUI
PT. MULYA ANUGRAH ABADI PT. AMARTA KARYA

HENGKY PURBO PRASETYO, ST


Direktur
REKAPITULASI ANGGARAN BIAYA
PEKERJAAN TAMBAH & KURANG AWAL / MONTHLY CERTIFIKAT (MC-0 )
NAMA KEGIATAN PEKERJAAN PERKERASAN JALAN TERMINAL CARGO
LOKASI BANDARA UDARA JUANDA SURABAYA

KONTRAK AWAL MUTUAL CHECK (MC-0) PEKERJAAN TAMBAH PEKERJAAN KURANG


NO JENIS PEKERJAAN SAT HARGA SATUAN
VOL JUMLAH HARGA VOL JUMLAH HARGA VOL JUMLAH HARGA VOL JUMLAH HARGA
1 Agregat Kelas A tebal 15 cm m3 300.333 260,67 78.287.889 336,99 101.209.329 76,32 22.921.440

2 Prime Coat ltr 10.000 1.737,79 17.377.900 2.246,60 22.466.000 508,81 5.088.100

3 Lap ATB tbl 7cm ton 1.125.000 279,78 314.752.500 307,94 346.434.030 28,16 31.681.530

4 Kanstin kerb uk 20x60 m1 114.000 130,18 14.840.520 195,50 22.287.000 65,32 7.446.480

5 Penghamparan Manual m2 200.000 69,70 13.940.000 69,70 13.940.000

TOTAL 425.258.809 506.336.359 81.077.550 -

Surabaya, 05 Januari 2021


MENGUSULKAN MENYETUJUI
PT. MULYA ANUGRAH ABADI PT. AMARTA KARYA

GENSATYA RAHARDANO, ST
PELAKSANA
ARITMATIK VOLUME PEKERJAAN
NAMA KEGIATAN : PEKERJAAN PERKERASAN JALAN TERMINAL CARGO
LOKASI : BANDARA UDARA JUANDA SURABAYA

NO URAIAN PEKERJAAN PANJANG LEBAR TINGGI JUMLAH VOLUME SAT

1 Agregat Kelas A tebal 15 cm


a Volume Area I
Area A 78,00 18,50 0,15 216,45 m3
Area B 12,00 5,30 0,15 9,54 m3
b Volume Area II 40,00 18,50 0,15 111,00 m3
TOTAL 336,99 m3
2 Prime Coat/Tack coat
a Volume Area I
Area A 78,00 18,50 1,00 1.443,00 ltr
Area B 12,00 5,30 1,00 63,60 ltr
b Volume Area II 40,00 18,50 1,00 740,00 ltr
TOTAL 2.246,60 ltr
3 Lap ATB tbl 7cm
a Volume Area I
Area A 78,00 18,50 0,07 2,28 230,30 ton
Area B 12,00 5,30 0,07 2,28 10,15 ton
b Volume Area II 40,00 18,50 0,04 2,28 67,49 ton
TOTAL 307,94 ton
4 Kanstin kerb uk 20x60
a Volume Area I 113,80 113,80 m1
b Area III 15,70 15,70 m1
c Exit Gate 26,00 26,00 m1
d perpanjangan sisi utara 40,00 40,00 m1
TOTAL 195,50 m1