NAMA : AINUL SAPUTRA

NIM 710017203
KELAS 03
TAMAN WISATA
KULIAH LAPANGAN III “REKLAMASI DAN PASCATAMBANG”
Reklamasi
Luas lahan = 4,99 Ha
Volume ob = 998,291 m3
Tahun Pertama
Biaya pengangkutan material
Luas lahan yang direvegetasi = 20000 m2
Volume material Top Soil = 20000 m2 x 1 m
= 20000 m3
= Volume Top Soil / Swell Factor
= 20000 m3 / 1,25
= 16000 LCM
Kebutuhan Pengangkuat
Volume material = 16000 LCM / 12 bulan
= 1333,3
= 1333,3LCM/ 25 hari
= 53,3 LCM/hari

a. Bulldozer Komatsu D85ESS


Kapasitas blade bulldozer = 2,9 m³
W = 0,8 x 8 = 6,4 jam
S = 12 menit = 0,2 jam
R = 1,4 jam
T = 8 jam
MA = 82%
EA = 90%
Jarak dorong eff bulldozer = 25-40
Tanah yang terisi = Kapasitas blade x Faktor blade
= 2,9 m³ x 1
= 2,9 LCM

Jam efektif kerja Bulldozer = 60 menit/jam x eff


= 60 menit/jam x 1,25
= 75 menit/jam
Kecepatan Bulldozer maju = 3,50 km/jam
= 58,3 m/menit
Kecepatan Bulldozer mundur = 5,5 km/jam
= 91,67 m/menit
jarak dorong
Waktu mendorong maju =
kecepatan maju

40 m
= 58,3 m/menit

= 0,69 menit
jarak dorong
Waktu untuk mundur = kecepatan mundur

40 m
= 91,67 m/menit

= 0,44 menit
Cycle time bulldozer = Waktu maju + waktu ganti gear + waktu
mundur
= (0,69 + 0,6 + 0,44) menit
= 1,72 menit
jam efektif
Jumlah trip/jam =
𝑐𝑦𝑐𝑙𝑒 𝑡𝑖𝑚𝑒

75 menit
= 1,72 menit

= 43,60 = 44 trip/jam
Produksi bulldozer per jam = jumlah trip/jam x kapasitas blade
= 44 trip/jam x 2,9 m3
= 15,17 LCM/jam
Volume tanah penutup/jam
Bulldozer yang bekerja dilapangan =
jumlah trip
53,3 LCM/jam
= 44 𝐿𝐶𝑀/ℎ𝑎𝑟𝑖

= 1,2
= 2 bulldozer
Jumlah bulldozer di lapangan
Bulldozer disediakan = 𝑀𝑒𝑐ℎ𝑎𝑛𝑖𝑐𝑎𝑙 𝐴𝑣𝑎𝑖𝑙𝑎𝑏𝑖𝑙𝑖𝑡𝑦

2
= 0.82

= 2,43
= 3 bulldozer
Bulldozer Cadangan = bulldozer disediakan – bulldozer
dilapangan
=3–2
= 1 bulldozer

b. Backhoe Kobelco SK210

Ukuran bucket = 0,9 m3

Cycle Time = 35 detik/bucket

Fill factor bucket tanah penutup= 0,7

Swell factor tanah = 1,25

Tinggi Jenjang = 8 meter

EA = 90 %

MA = 82 %

Kapasitas Dump Truck = 12,21 m3

Banyak bucket = (kapasitas Dump truck)/(kapasitas bucket)

= (12,21 m3)/(0,9 m3 )

= 13,57 bucket ≈ 14 bucket

Waktu pengisin Dump Truck = banyak bucket x cycle time


= 14 bucket x 35 detik/bucket

= 490 detik

= 8,1 menit

Produksi backhoe untuk pengupasan tanah penutup :

Produksi/jam: 3600/Cycle Time x (bucket capacity x bucket fill factor ) x EA

= (3600/35 detik) x (0,9 m³ x 0,7) x 0,9

= 58,32 LCM/jam

Backhoe di lapangan = (Volume lapisan tanah penutup/jam) /

(Produksi Backhoe/jam)

= (53,3 LCM/jam) / ( 58,32 LCM/jam)


= 0,91 unit backhoe

= 1 unit backhoe

Backhoe disediakan = (Jumlah backhoe di lapangan)/MA

= 1/0,82

= 1,22 ≈ 2 unit Backhoe

Backhoe cadangan = Backhoe disediakan – Backhoe di

lapangan

=2–1

= 1 unit Backhoe

a. Dump Truck Hino Dutro 130 PS


Macam pekerjaan = Mengangkut material hasial penggalian
Jarak angkut untuk tanah penutup = 0,609 km

Power = 128,22 HP
Efisiensi mesin = 85%
Ukuran bak Panjang = 2,9 meter
Lebar = 1,945 meter
Tinggi = 2,165 meter
Waktu ganti gear + menumpahkan = 2 menit
muatan+ maneuver
Berat truck kosong = 2,355 ton
Beban sumbu roda belakang = 60%
Beban sumbu roda belakang = 40%
Rimpul untuk percepatan = 10 kg/ton
Kapasitas DumpTtruck = panjang x lebar x tinggi
= 2,9 m x 1,945 m x 2,165 m
= 12,21 m³
Rute pengupasan ob
Jarak = 0,609 km
Berat truck kosong = 2,355 ton
= 2.355 kg
Berat isi = Kapasitas truck x bobot isi tanah penutup
= 12,21 m³ x 1,2728 ton/m³ x 0,8
= 12,43271 ton
= 12432,71 kg
Beban total = berat truck kosong + berat isi
= 2,355 ton + 12,43271 ton
= 15 ton
= 15.000 kg
Rimpull yang tersedia pada setiap gear Dump Truck Hino D :
Gear Kecepatan (km/h) Eff Mekanis (%) HP Rimpull (lb)
1 8,205 85 128,22 4.981
2 14,04 85 128,22 2.911
Gear Kecepatan (km/h) Eff Mekanis (%) HP Rimpull (lb)
3 26,27 85 128,22 1.556
4 40,87 85 128,22 1.000
5 55,38 85 128,22 0.738

Usable rimpull (yang digunakan) = beban total x distribusi beban x Cycle Time

= 15.000 kg x 60% x 60%

= 5.400 kg

Karena rimpull yang digunakan > rimpul yang tersedia yaitu 5.400 kg > 4.981 kg maka dump truck
tidak mengalami selip.

Waktu tempuh bermuatan pengangkutan lapisan tanah penutup

Jalur A-B

RP untuk RR = 7 %x 15.000 kg = 10.500 kg

RP untuk GR = 0% x 20 kg/ton x 29,8914 ton = 0 kg

RP untuk percepatan = 20 kg/ton x 29,8914 ton = 597,828 kg

RP yang dibutuhkan = 11097,828 kg

Karena rimpull yang dibutuhkan 11097,828 kg, maka digunakan gear 3 dengan kecepatan 26,27
km/jam
Jarak angkut
Waktu yang di butuhkan =
kecepatan

0,609km
= 26,27 km/jam

= 0,02 jam

= 1,2 menit

Waktu kembali kosong

Jalur B-A
RP untuk RR = 7 % x 2.355 kg = 1,6485 kg

RP untuk GR = 0 % x 20 kg/ton x 2,355 ton = 0 kg

RP untuk percepatan = 20 kg/ton x 2,355 ton = 47.1 kg

RP yang dibutuhkan = 48,75 kg

Karena rimpull yang dibutuhkan 48,75 kg, maka digunakan gear 5 dengan kecepatan 55,38
km/jam, karena kecepatan di area penambangan < 50 km/jam, maka di gunakan gearr 4 dengan
kecepatan 40,87 km/jam.
Jarak angkut
Waktu yang di butuhkan =
kecepatan

0,609 km
= 40,87 km/jam

= 0,015 jam

= 0,9 menit

Waktu tetap Pengisian = Cycle Time x banyak bucket

= 35 detik/bucket x 14 bucket

= 4900 detik

= 8,16 menit

Waktu ganti gear + Menumpahkan = 2 menit

muatan + manuver

Waktu variable

Waktu tempuh bermuatan = 1,2 menit

Waktu tempuh kosong = 0,9 menit

Cycle time dump truck = waktu tetap + waktu variable

= 8,16 menit + 2,1 menit

= 10,26 menit
60 menit
Jumlah trip/jam = 10,26 menit

= 5,85 trip ≈ 6 trip

Produksi Dump Truck /jam = kapasitas truk x jumlah trip/jam x EA

= 12,21 LCM/trip x 6 trip/jam truck x 0,90

= 65,934 LCM/jam
material yang di angkut
Dump Truck di lapangan = produksi 𝑑𝑢𝑚𝑝 𝑡𝑟𝑢𝑐𝑘/jam

53,3 LCM/jam
= 65,934 LCM/jam truck

= 0,8 unit Dump Truck  1 unit Dump Truck

Jumlah 𝐷𝑢𝑚𝑝 𝑇𝑟𝑢𝑐𝑘 di lapangan


Dump Truck disediakan = MA

1
= 0,82
= 1,22 unit ≈ 2 unit Dump Truck
Dump Truck cadangan = DT disediakan – DT di lapangan
=2-1
= 1 unit Dump Truck

Biaya Upah Operator :


Jumlah Buldozer : 2 unit
Sewa : Rp 120.000,-/jam
Waktu kerja : 7 jam/hari
Hari kerja : 6 hari
Upah Per Jam : Rp. 15.000,-
Biaya : (Rp. 15.000,- x 7 x 2 x 6) + (7 x 2 x 6 x Rp
120.000,-)
: Rp. 1.260.000,- + Rp 10.080.000,-

: Rp 11.340.000,-

Jumlah Backhoe : 1 unit


Waktu kerja : 7 jam/hari
Sewa : Rp 160.000,/jam
Hari kerja : 6 hari
Upah Per Jam : Rp. 15.000,-
Biaya : (Rp 15.000,- x 7 x 1 x 6) + ( 7 x 1 x 6
Rp 160.000)

: Rp. 630.000,- + Rp 6.720.000,-

: Rp 7.350.000,-

Jumlah Dump Truck : 1 unit


Waktu kerja : 7 jam/hari
Sewa : Rp 400.000,-/jam
Hari kerja : 6 hari
Upah Per Jam : Rp. 15.000,-
Biaya : (Rp 15.000,- x 7 x 1 x 6) + (7 x 1 x 6 x
Rp 400.000,-)
: Rp. 630.000,- + Rp 16.800.000,-

: Rp 17.430.000,-

Total Biaya Upah = Rp 11.340.000 + Rp 7.350.000 + Rp 17.430.000


= Rp 18.690.000,-

Konsumsi bahan bakar :


Jumlah Buldozer : 2 unit
Waktu kerja : 7 jam/hari
Hari kerja : 6 hari
Konsumsi BBM : 29,17 liter/jam
Harga solar : Rp. 6.000,-
Biaya : Rp. 6.000/liter x 29,17 x 7 x 2 x 6
: Rp. 14.968.800,00-,

Jumlah Backhoe : 1 unit


Waktu kerja : 7 jam/hari
Hari kerja : 6 hari
Konsumsi BBM : 6,25 liter/jam
Harga solar : Rp. 6.000,-
Biaya : Rp. 6.000/liter x 6,25 x 7 x 1 x 6 hari
: Rp. 1.575.000,00-

Jumlah DT : 1 unit
Waktu kerja : 7 jam/hari
Hari kerja : 6 hari
Konsumsi BBM : 5,769 liter/jam
Harga solar : Rp. 6.000,-
Biaya : Rp. 6.000/liter x 5,769 x 7 x 1 x 6
: Rp. 1.453.788,00-

Total anggaran = Rp. 14.968.800,00 + 1.575.000 + 1.453.788


= Rp 17.997.588,-
 Pengadaan bibit
Luas lahan yang ditanami rumput = 20000 m2 = 2 Ha
Dimensi penanaman yaitu 0,4m x 0,4m = 0,16 m2
Setiap 10.000 m2 dibutuhkan 10.000/0,16 = 62.500 tanaman rambat/Ha
Jadi rumput gajah yang dibutuhkan keseluruhan :
= 62.500 tanaman rambat x 2 Ha
= 125 tanaman rambat
Harga satu bibit = Rp 5.000,00 /tanaman rambat
Jumlah bibit = 125 bibit
Biaya pembibitan = 125 x Rp.5.000,00
= Rp 625.000,00-

 Pemeliharaan Bibit
Waktu pemeliharaan bibit = 1 tahun
Biaya buruh untuk pemeliharaan bibit = Rp. 12500.000/bulan
Jumlah buruh yang bekerja = 2 orang
Biaya pemeliharaan untuk 2 orang dalam satu bulan :
= Rp.1.250.000 x 2 orang
= Rp. 2.250.000,-
Total biaya pemeliharaan selama 1 tahun (12 bulan) :
= Rp. 2.250.000 x 12 bulan
= Rp 30.000.000,-
 Pembelian pupuk dasar kompos
Luas lahan = 20000 m2 = 2 Ha
Perbandingan tanah dengan pupuk kompos = 1 : 1
= 20000 m2 x 0.02 m
= 400 m2
Dalam 1 bibit diberi pupuk sebanyak 0,5 kg
Jadi, Pupuk kompos yang diperlukan dalam 62 bibit
= 125 bibit x 0,5 kg
= 62,5 kg
Harga pupuk kompos/karung (25 kg) = Rp. 15.000,-
Harga pupuk kompos 1 kg = Rp 7.000,-
Jumlah tanaman rambat = 125 bibit
Biaya pembelian pupuk kompos = Rp 7.000 x 125 kg
= Rp 875.000,00-
 Biaya penanaman tanaman rambat
Luas lahan yang direvegetasi = 20000 m2 = 2 Ha
Biaya penanaman tanaman rambat/Ha = Rp 900.000
Biaya penanaman tanaman rambat keseluruhan = Rp 900.000 x 2 Ha
= Rp 1.800.000,00-
Total = Rp 625.000,00 + Rp. 30.000.000 + Rp 875.000,00 + Rp 1.800.000,00
= Rp 33.300.000,-
Luas lahan yang ditanami pohon sengon = 20000 m2 = 2 Ha
Dimensi penanaman yaitu 4m x 4m = 16 m2
Setiap 10.000 m2 dibutuhkan 10.000/16 = 625 pohon/Ha
Jadi pohon sengon yang dibutuhkan keseluruhan :
= 625 pohon x 2 Ha
= 1250 pohon
Harga satu bibit = Rp 5.000/pohon
Jumlah bibit = 1250 bibit
Biaya pembibitan = 625 x Rp. 5.000 = Rp 6.250.000,-
 Pemeliharaan pohon sengon
Waktu pemeliharaan pohon sengon = 1 tahun
Biaya buruh untuk pemeliharaan sengon = Rp. 1.600.000/bulan
Jumlah buruh yang bekerja = 2 orang
Biaya pemeliharaan untuk 2 orang dalam satu bulan :
= Rp. 1.600.000 x 2 orang
= Rp. 3.200.000,-
Total biaya pemeliharaan selama1 tahun (12 bulan) :
= Rp. 3.200.000 x 12 bulan
= Rp 38.400.000,-
 Pembelian pupuk dasar kompos
Volume pot = 0,30 m x 0,30 m x 0,30 m = 0,027 m3
Perbandingan tanah dengan pupuk kompos =1:1
Volume pupuk kompos yang diperlukan dalam satu pot :
= 0,027 m3 : 2
= 0,0135 m3
Volume pupuk kompos yang diperlukan untuk seluruh pot :
= 0,0135 m3 x 1250 pot
= 16,87 m3
Berat jenis pupuk kompos = 0,5 ton/m3
Berat pupuk kompos total yang diperlukan = 0,5 ton/m3 x 16,87 m3
= 8,435 ton

Harga pupuk kompos/karung (25 kg) = Rp. 15.000,-


Harga pupuk kompos 1 kg = Rp. 7.000,-
Jumlah pot = 1250 pot
Biaya pembelian pupuk kompos = Rp. 7.000 x 8,435 ton
= Rp. 59.010,-
 Biaya penanaman pohon sengon
Luas lahan yang direvegetasi = 20000 m2 = 2 Ha
Biaya penanaman pohon sengon/Ha = Rp 1.500.000
Biaya penanaman sengon keseluruhan = Rp 1.500.000 x 2 Ha
= Rp 3.000.000,-
Total = Rp 6.250.000 + Rp 38.400.000 + Rp. 59.010 + Rp 3.000.000
= Rp 47.650.000,-
Biaya Total : Rp 17.997.588 + Rp 47.650.000 = Rp 65.647.588,-

Tahun kedua
Biaya pengangkutan material
Luas lahan yang direvegetasi = 19000 m2
Volume material Top Soil = 19000 m2 x 1 m
= 19000 m3
= Volume Top Soil / Swell Factor
= 19000 m3 / 1,25
= 15200 LCM
Kebutuhan Pengangkuat
Volume material = 15200 LCM / 12 bulan
= 1266,6
= 1266,6LCM/ 25 hari
= 50,6 LCM/hari

c. Bulldozer Komatsu D85ESS


Kapasitas blade bulldozer = 2,9 m³
W = 0,8 x 8 = 6,4 jam
S = 12 menit = 0,2 jam
R = 1,4 jam
T = 8 jam
MA = 82%
EA = 90%
Jarak dorong eff bulldozer = 25-40
Tanah yang terisi = Kapasitas blade x Faktor blade
= 2,9 m³ x 1
= 2,9 LCM

Jam efektif kerja Bulldozer = 60 menit/jam x eff


= 60 menit/jam x 1,25
= 75 menit/jam
Kecepatan Bulldozer maju = 3,50 km/jam
= 58,3 m/menit
Kecepatan Bulldozer mundur = 5,5 km/jam
= 91,67 m/menit
jarak dorong
Waktu mendorong maju =
kecepatan maju

40 m
= 58,3 m/menit

= 0,69 menit
jarak dorong
Waktu untuk mundur = kecepatan mundur

40 m
= 91,67 m/menit

= 0,44 menit
Cycle time bulldozer = Waktu maju + waktu ganti gear + waktu
mundur
= (0,69 + 0,6 + 0,44) menit
= 1,72 menit
jam efektif
Jumlah trip/jam =
𝑐𝑦𝑐𝑙𝑒 𝑡𝑖𝑚𝑒

75 menit
= 1,72 menit

= 43,60 = 44 trip/jam
Produksi bulldozer per jam = jumlah trip/jam x kapasitas blade
= 44 trip/jam x 2,9 m3
= 15,17 LCM/jam
Volume tanah penutup/jam
Bulldozer yang bekerja dilapangan =
jumlah trip

50,6 LCM/jam
= 44 𝐿𝐶𝑀/ℎ𝑎𝑟𝑖

= 1,15
= 2 bulldozer
Jumlah bulldozer di lapangan
Bulldozer disediakan = 𝑀𝑒𝑐ℎ𝑎𝑛𝑖𝑐𝑎𝑙 𝐴𝑣𝑎𝑖𝑙𝑎𝑏𝑖𝑙𝑖𝑡𝑦

2
= 0.82

= 2,43
= 3 bulldozer
Bulldozer Cadangan = bulldozer disediakan – bulldozer
dilapangan
=3–2
= 1 bulldozer

d. Backhoe Kobelco SK210

Ukuran bucket = 0,9 m3

Cycle Time = 35 detik/bucket

Fill factor bucket tanah penutup= 0,7

Swell factor tanah = 1,25

Tinggi Jenjang = 8 meter

EA = 90 %

MA = 82 %

Kapasitas Dump Truck = 12,21 m3

Banyak bucket = (kapasitas Dump truck)/(kapasitas bucket)

= (12,21 m3)/(0,9 m3 )

= 13,57 bucket ≈ 14 bucket


Waktu pengisin Dump Truck = banyak bucket x cycle time

= 14 bucket x 35 detik/bucket

= 490 detik

= 8,1 menit

Produksi backhoe untuk pengupasan tanah penutup :

Produksi/jam: 3600/Cycle Time x (bucket capacity x bucket fill factor ) x EA

= (3600/35 detik) x (0,9 m³ x 0,7) x 0,9

= 58,32 LCM/jam

Backhoe di lapangan = (Volume lapisan tanah penutup/jam) /

(Produksi Backhoe/jam)

= (50,6 LCM/jam) / ( 58,32 LCM/jam)


= 0,86 unit backhoe

= 1 unit backhoe

Backhoe disediakan = (Jumlah backhoe di lapangan)/MA

= 1/0,82

= 1,22 ≈ 2 unit Backhoe

Backhoe cadangan = Backhoe disediakan – Backhoe di

lapangan

=2–1

= 1 unit Backhoe

b. Dump Truck Hino Dutro 130 PS


Macam pekerjaan = Mengangkut material hasial penggalian
Jarak angkut untuk tanah penutup = 0,609 km

Power = 128,22 HP
Efisiensi mesin = 85%
Ukuran bak Panjang = 2,9 meter
Lebar = 1,945 meter
Tinggi = 2,165 meter
Waktu ganti gear + menumpahkan = 2 menit
muatan+ maneuver
Berat truck kosong = 2,355 ton
Beban sumbu roda belakang = 60%
Beban sumbu roda belakang = 40%
Rimpul untuk percepatan = 10 kg/ton
Kapasitas DumpTtruck = panjang x lebar x tinggi
= 2,9 m x 1,945 m x 2,165 m
= 12,21 m³
Rute pengupasan ob
Jarak = 0,609 km
Berat truck kosong = 2,355 ton
= 2.355 kg
Berat isi = Kapasitas truck x bobot isi tanah penutup
= 12,21 m³ x 1,2728 ton/m³ x 0,8
= 12,43271 ton
= 12432,71 kg
Beban total = berat truck kosong + berat isi
= 2,355 ton + 12,43271 ton
= 15 ton
= 15.000 kg
Rimpull yang tersedia pada setiap gear Dump Truck Hino D :
Gear Kecepatan (km/h) Eff Mekanis (%) HP Rimpull (lb)
1 8,205 85 128,22 4.981
Gear Kecepatan (km/h) Eff Mekanis (%) HP Rimpull (lb)
2 14,04 85 128,22 2.911
3 26,27 85 128,22 1.556
4 40,87 85 128,22 1.000
5 55,38 85 128,22 0.738

Usable rimpull (yang digunakan) = beban total x distribusi beban x Cycle Time

= 15.000 kg x 60% x 60%

= 5.400 kg

Karena rimpull yang digunakan > rimpul yang tersedia yaitu 5.400 kg > 4.981 kg maka dump truck
tidak mengalami selip.

Waktu tempuh bermuatan pengangkutan lapisan tanah penutup

Jalur A-B

RP untuk RR = 7 %x 15.000 kg = 10.500 kg

RP untuk GR = 0% x 20 kg/ton x 29,8914 ton = 0 kg

RP untuk percepatan = 20 kg/ton x 29,8914 ton = 597,828 kg

RP yang dibutuhkan = 11097,828 kg

Karena rimpull yang dibutuhkan 11097,828 kg, maka digunakan gear 3 dengan kecepatan 26,27
km/jam
Jarak angkut
Waktu yang di butuhkan =
kecepatan

0,609km
= 26,27 km/jam

= 0,02 jam

= 1,2 menit

Waktu kembali kosong


Jalur B-A

RP untuk RR = 7 % x 2.355 kg = 1,6485 kg

RP untuk GR = 0 % x 20 kg/ton x 2,355 ton = 0 kg

RP untuk percepatan = 20 kg/ton x 2,355 ton = 47.1 kg

RP yang dibutuhkan = 48,75 kg

Karena rimpull yang dibutuhkan 48,75 kg, maka digunakan gear 5 dengan kecepatan 55,38
km/jam, karena kecepatan di area penambangan < 50 km/jam, maka di gunakan gearr 4 dengan
kecepatan 40,87 km/jam.
Jarak angkut
Waktu yang di butuhkan =
kecepatan

0,609 km
= 40,87 km/jam

= 0,015 jam

= 0,9 menit

Waktu tetap Pengisian = Cycle Time x banyak bucket

= 35 detik/bucket x 14 bucket

= 4900 detik

= 8,16 menit

Waktu ganti gear + Menumpahkan = 2 menit

muatan + manuver

Waktu variable

Waktu tempuh bermuatan = 1,2 menit

Waktu tempuh kosong = 0,9 menit

Cycle time dump truck = waktu tetap + waktu variable

= 8,16 menit + 2,1 menit


= 10,26 menit

60 menit
Jumlah trip/jam = 10,26 menit

= 5,85 trip ≈ 6 trip

Produksi Dump Truck /jam = kapasitas truk x jumlah trip/jam x EA

= 12,21 LCM/trip x 6 trip/jam truck x 0,90

= 65,934 LCM/jam
material yang di angkut
Dump Truck di lapangan = produksi 𝑑𝑢𝑚𝑝 𝑡𝑟𝑢𝑐𝑘/jam

50,6 LCM/jam
= 65,934 LCM/jam truck

= 0,76 unit Dump Truck  1 unit Dump Truck

Jumlah 𝐷𝑢𝑚𝑝 𝑇𝑟𝑢𝑐𝑘 di lapangan


Dump Truck disediakan = MA

1
= 0,82
= 1,22 unit ≈ 2 unit Dump Truck
Dump Truck cadangan = DT disediakan – DT di lapangan
=2-1
= 1 unit Dump Truck

Biaya Upah Operator :


Jumlah Buldozer : 2 unit
Sewa : Rp 120.000,-/jam
Waktu kerja : 7 jam/hari
Hari kerja : 6 hari
Upah Per Jam : Rp. 15.000,-
Biaya : (Rp. 15.000,- x 7 x 2 x 6) + (7 x 2 x 6 x Rp
120.000,-)
: Rp. 1.260.000,- + Rp 10.080.000,-
: Rp 11.340.000,-
Jumlah Backhoe : 1 unit
Waktu kerja : 7 jam/hari
Sewa : Rp 160.000,/jam
Hari kerja : 6 hari
Upah Per Jam : Rp. 15.000,-
Biaya : (Rp 15.000,- x 7 x 1 x 6) + ( 7 x 1 x 6
Rp 160.000)
: Rp. 630.000,- + Rp 6.720.000,-
: Rp 7.350.000,-
Jumlah Dump Truck : 1 unit
Waktu kerja : 7 jam/hari
Sewa : Rp 400.000,-/jam
Hari kerja : 6 hari
Upah Per Jam : Rp. 15.000,-
Biaya : (Rp 15.000,- x 7 x 1 x 6) + (7 x 1 x 6 x
Rp 400.000,-)
: Rp. 630.000,- + Rp 16.800.000,-
: Rp 17.430.000,-
Total Biaya Upah = Rp 11.340.000 + Rp 7.350.000 + Rp 17.430.000
= Rp 18.690.000,-

Konsumsi bahan bakar :


Jumlah Buldozer : 2 unit
Waktu kerja : 7 jam/hari
Hari kerja : 6 hari
Konsumsi BBM : 29,17 liter/jam
Harga solar : Rp. 6.000,-
Biaya : Rp. 6.000/liter x 29,17 x 7 x 2 x 6
: Rp. 14.968.800,00-,
Jumlah Backhoe : 1 unit
Waktu kerja : 7 jam/hari
Hari kerja : 6 hari
Konsumsi BBM : 6,25 liter/jam
Harga solar : Rp. 6.000,-
Biaya : Rp. 6.000/liter x 6,25 x 7 x 1 x 6 hari
: Rp. 1.575.000,00-
Jumlah DT : 1 unit
Waktu kerja : 7 jam/hari
Hari kerja : 6 hari
Konsumsi BBM : 5,769 liter/jam
Harga solar : Rp. 6.000,-
Biaya : Rp. 6.000/liter x 5,769 x 7 x 1 x 6
: Rp. 1.453.788,00-
Total anggaran = Rp. 14.968.800,00 + 1.575.000 + 1.453.788
= Rp 17.997.588,-
 Pengadaan bibit
Luas lahan yang ditanami rumput = 19000 m2 = 1,9 Ha
Dimensi penanaman yaitu 0,4m x 0,4m = 0,16 m2
Setiap 10.000 m2 dibutuhkan 10.000/0,16 = 62.500 tanaman rambat/Ha
Jadi rumput gajah yang dibutuhkan keseluruhan :
= 62.500 tanaman rambat x 1,9 Ha
= 119 tanaman rambat
Harga satu bibit = Rp 5.000,00 /tanaman rambat
Jumlah bibit = 119 bibit
Biaya pembibitan = 119 x Rp.5.000,00
= Rp 595.000,00-

 Pemeliharaan Bibit
Waktu pemeliharaan bibit = 1 tahun
Biaya buruh untuk pemeliharaan bibit = Rp. 12500.000/bulan
Jumlah buruh yang bekerja = 2 orang
Biaya pemeliharaan untuk 2 orang dalam satu bulan :
= Rp.1.250.000 x 2 orang
= Rp. 2.250.000,-
Total biaya pemeliharaan selama 1 tahun (12 bulan) :
= Rp. 2.250.000 x 12 bulan
= Rp 30.000.000,-
 Pembelian pupuk dasar kompos
Luas lahan = 19000 m2 = 1,9
Ha
Perbandingan tanah dengan pupuk kompos = 1 : 1
= 19000 m2 x 0.02 m
= 380 m2
Dalam 1 bibit diberi pupuk sebanyak 0,5 kg
Jadi, Pupuk kompos yang diperlukan dalam 62 bibit
= 119 bibit x 0,5 kg
= 59,5 kg
Harga pupuk kompos/karung (25 kg) = Rp. 15.000,-
Harga pupuk kompos 1 kg = Rp 7.000,-
Jumlah tanaman rambat = 119 bibit
Biaya pembelian pupuk kompos = Rp 7.000 x 59,5 kg
= Rp 416.500,00-
 Biaya penanaman tanaman rambat
Luas lahan yang direvegetasi = 19000 m2 = 1,9 Ha
Biaya penanaman tanaman rambat/Ha = Rp 900.000
Biaya penanaman tanaman rambat keseluruhan = Rp 900.000 x 1,9 Ha
= Rp 1.710.000,00-
Total = Rp 595.000,00 + Rp. 30.000.000 + Rp 416.500,00 + 1.710.000,00
= Rp 57.215.000,-
Luas lahan yang ditanami pohon sengon = 19000 m2 = 1,9 Ha
Dimensi penanaman yaitu 4m x 4m = 16 m2
Setiap 10.000 m2 dibutuhkan 10.000/16 = 625 pohon/Ha
Jadi pohon sengon yang dibutuhkan keseluruhan :
= 625 pohon x 1,9 Ha
= 1189 pohon
Harga satu bibit = Rp 5.000/pohon
Jumlah bibit = 1189 bibit
Biaya pembibitan = 1189 x Rp. 5.000 = Rp 5.945.000,-
 Pemeliharaan pohon sengon
Waktu pemeliharaan pohon sengon = 1 tahun
Biaya buruh untuk pemeliharaan sengon = Rp. 1.600.000/bulan
Jumlah buruh yang bekerja = 2 orang
Biaya pemeliharaan untuk 2 orang dalam satu bulan :
= Rp. 1.600.000 x 2 orang
= Rp. 3.200.000,-
Total biaya pemeliharaan selama1 tahun (12 bulan) :
= Rp. 3.200.000 x 12 bulan
= Rp 38.400.000,-
 Pembelian pupuk dasar kompos
Volume pot = 0,30 m x 0,30 m x 0,30 m = 0,027 m3
Perbandingan tanah dengan pupuk kompos =1:1
Volume pupuk kompos yang diperlukan dalam satu pot :
= 0,027 m3 : 2
= 0,0135 m3
Volume pupuk kompos yang diperlukan untuk seluruh pot :
= 0,0135 m3 x 1189 pot
= 16,05 m3
Berat jenis pupuk kompos = 0,5 ton/m3
Berat pupuk kompos total yang diperlukan = 0,5 ton/m3 x 16,05 m3
= 8,02 ton

Harga pupuk kompos/karung (25 kg) = Rp. 15.000,-


Harga pupuk kompos 1 kg = Rp. 7.000,-
Jumlah pot = 1189 pot
Biaya pembelian pupuk kompos = Rp. 7.000 x 8,02 ton
= Rp. 56.140,-
 Biaya penanaman pohon sengon
Luas lahan yang direvegetasi = 19000 m2 = 1,9 Ha
Biaya penanaman pohon sengon/Ha = Rp 1.500.000
Biaya penanaman sengon keseluruhan = Rp 1.500.000 x 1,9 Ha
= Rp 2.850.000,-
Total = Rp 5.945.000 + Rp 38.400.000 + Rp. 56.140 + Rp 2.850.000
= Rp 47.251.140,-
Biaya Total : Rp 17.997.588 + Rp 47.251.140 = Rp 65.248.728,-

Tahun ketiga
Biaya pengangkutan material
Luas lahan yang direvegetasi = 10000 m2
Volume material Top Soil = 10000 m2 x 1 m
= 10000 m3
= Volume Top Soil / Swell Factor
= 10000 m3 / 1,25
= 8000 LCM
Kebutuhan Pengangkuat
Volume material = 8000 LCM / 12 bulan
= 666,6
= 666,6 LCM/ 25 hari
= 27 LCM/hari

e. Bulldozer Komatsu D85ESS


Kapasitas blade bulldozer = 2,9 m³
W = 0,8 x 8 = 6,4 jam
S = 12 menit = 0,2 jam
R = 1,4 jam
T = 8 jam
MA = 82%
EA = 90%
Jarak dorong eff bulldozer = 25-40
Tanah yang terisi = Kapasitas blade x Faktor blade
= 2,9 m³ x 1
= 2,9 LCM

Jam efektif kerja Bulldozer = 60 menit/jam x eff


= 60 menit/jam x 1,25
= 75 menit/jam
Kecepatan Bulldozer maju = 3,50 km/jam
= 58,3 m/menit
Kecepatan Bulldozer mundur = 5,5 km/jam
= 91,67 m/menit
jarak dorong
Waktu mendorong maju =
kecepatan maju

40 m
= 58,3 m/menit

= 0,69 menit
jarak dorong
Waktu untuk mundur = kecepatan mundur

40 m
= 91,67 m/menit

= 0,44 menit
Cycle time bulldozer = Waktu maju + waktu ganti gear + waktu
mundur
= (0,69 + 0,6 + 0,44) menit
= 1,72 menit
jam efektif
Jumlah trip/jam =
𝑐𝑦𝑐𝑙𝑒 𝑡𝑖𝑚𝑒

75 menit
= 1,72 menit

= 43,60 = 44 trip/jam
Produksi bulldozer per jam = jumlah trip/jam x kapasitas blade
= 44 trip/jam x 2,9 m3
= 15,17 LCM/jam
Volume tanah penutup/jam
Bulldozer yang bekerja dilapangan =
jumlah trip
27 LCM/jam
= 44 𝐿𝐶𝑀/ℎ𝑎𝑟𝑖

= 0,61
= 1 bulldozer
Jumlah bulldozer di lapangan
Bulldozer disediakan = 𝑀𝑒𝑐ℎ𝑎𝑛𝑖𝑐𝑎𝑙 𝐴𝑣𝑎𝑖𝑙𝑎𝑏𝑖𝑙𝑖𝑡𝑦

1
= 0.82

= 1,22
= 2 bulldozer
Bulldozer Cadangan = bulldozer disediakan – bulldozer
dilapangan
=2–1
= 1 bulldozer

f. Backhoe Kobelco SK210

Ukuran bucket = 0,9 m3

Cycle Time = 35 detik/bucket

Fill factor bucket tanah penutup= 0,7

Swell factor tanah = 1,25

Tinggi Jenjang = 8 meter

EA = 90 %

MA = 82 %

Kapasitas Dump Truck = 12,21 m3

Banyak bucket = (kapasitas Dump truck)/(kapasitas bucket)

= (12,21 m3)/(0,9 m3 )

= 13,57 bucket ≈ 14 bucket

Waktu pengisin Dump Truck = banyak bucket x cycle time


= 14 bucket x 35 detik/bucket

= 490 detik

= 8,1 menit

Produksi backhoe untuk pengupasan tanah penutup :

Produksi/jam: 3600/Cycle Time x (bucket capacity x bucket fill factor ) x EA

= (3600/35 detik) x (0,9 m³ x 0,7) x 0,9

= 58,32 LCM/jam

Backhoe di lapangan = (Volume lapisan tanah penutup/jam) /

(Produksi Backhoe/jam)

= (27 LCM/jam) / ( 58,32 LCM/jam)


=0,46 unit backhoe

= 1 unit backhoe

Backhoe disediakan = (Jumlah backhoe di lapangan)/MA

= 1/0,82

= 1,22 ≈ 2 unit Backhoe

Backhoe cadangan = Backhoe disediakan – Backhoe di

lapangan

=2–1

= 1 unit Backhoe

c. Dump Truck Hino Dutro 130 PS


Macam pekerjaan = Mengangkut material hasial penggalian
Jarak angkut untuk tanah penutup = 0,609 km

Power = 128,22 HP
Efisiensi mesin = 85%
Ukuran bak Panjang = 2,9 meter
Lebar = 1,945 meter
Tinggi = 2,165 meter
Waktu ganti gear + menumpahkan = 2 menit
muatan+ maneuver
Berat truck kosong = 2,355 ton
Beban sumbu roda belakang = 60%
Beban sumbu roda belakang = 40%
Rimpul untuk percepatan = 10 kg/ton
Kapasitas DumpTtruck = panjang x lebar x tinggi
= 2,9 m x 1,945 m x 2,165 m
= 12,21 m³
Rute pengupasan ob
Jarak = 0,609 km
Berat truck kosong = 2,355 ton
= 2.355 kg
Berat isi = Kapasitas truck x bobot isi tanah penutup
= 12,21 m³ x 1,2728 ton/m³ x 0,8
= 12,43271 ton
= 12432,71 kg
Beban total = berat truck kosong + berat isi
= 2,355 ton + 12,43271 ton
= 15 ton
= 15.000 kg
Rimpull yang tersedia pada setiap gear Dump Truck Hino D :
Gear Kecepatan (km/h) Eff Mekanis (%) HP Rimpull (lb)
1 8,205 85 128,22 4.981
2 14,04 85 128,22 2.911
Gear Kecepatan (km/h) Eff Mekanis (%) HP Rimpull (lb)
3 26,27 85 128,22 1.556
4 40,87 85 128,22 1.000
5 55,38 85 128,22 0.738

Usable rimpull (yang digunakan) = beban total x distribusi beban x Cycle Time

= 15.000 kg x 60% x 60%

= 5.400 kg

Karena rimpull yang digunakan > rimpul yang tersedia yaitu 5.400 kg > 4.981 kg maka dump truck
tidak mengalami selip.

Waktu tempuh bermuatan pengangkutan lapisan tanah penutup

Jalur A-B

RP untuk RR = 7 %x 15.000 kg = 10.500 kg

RP untuk GR = 0% x 20 kg/ton x 29,8914 ton = 0 kg

RP untuk percepatan = 20 kg/ton x 29,8914 ton = 597,828 kg

RP yang dibutuhkan = 11097,828 kg

Karena rimpull yang dibutuhkan 11097,828 kg, maka digunakan gear 3 dengan kecepatan 26,27
km/jam
Jarak angkut
Waktu yang di butuhkan =
kecepatan

0,609km
= 26,27 km/jam

= 0,02 jam

= 1,2 menit

Waktu kembali kosong

Jalur B-A
RP untuk RR = 7 % x 2.355 kg = 1,6485 kg

RP untuk GR = 0 % x 20 kg/ton x 2,355 ton = 0 kg

RP untuk percepatan = 20 kg/ton x 2,355 ton = 47.1 kg

RP yang dibutuhkan = 48,75 kg

Karena rimpull yang dibutuhkan 48,75 kg, maka digunakan gear 5 dengan kecepatan 55,38
km/jam, karena kecepatan di area penambangan < 50 km/jam, maka di gunakan gearr 4 dengan
kecepatan 40,87 km/jam.
Jarak angkut
Waktu yang di butuhkan =
kecepatan

0,609 km
= 40,87 km/jam

= 0,015 jam

= 0,9 menit

Waktu tetap Pengisian = Cycle Time x banyak bucket

= 35 detik/bucket x 14 bucket

= 4900 detik

= 8,16 menit

Waktu ganti gear + Menumpahkan = 2 menit

muatan + manuver

Waktu variable

Waktu tempuh bermuatan = 1,2 menit

Waktu tempuh kosong = 0,9 menit

Cycle time dump truck = waktu tetap + waktu variable

= 8,16 menit + 2,1 menit

= 10,26 menit
60 menit
Jumlah trip/jam = 10,26 menit

= 5,85 trip ≈ 6 trip

Produksi Dump Truck /jam = kapasitas truk x jumlah trip/jam x EA

= 12,21 LCM/trip x 6 trip/jam truck x 0,90

= 65,934 LCM/jam
material yang di angkut
Dump Truck di lapangan = produksi 𝑑𝑢𝑚𝑝 𝑡𝑟𝑢𝑐𝑘/jam

27 LCM/jam
= 65,934 LCM/jam truck

= 0,40 unit Dump Truck  1 unit Dump Truck

Jumlah 𝐷𝑢𝑚𝑝 𝑇𝑟𝑢𝑐𝑘 di lapangan


Dump Truck disediakan = MA

1
= 0,82
= 1,22 unit ≈ 2 unit Dump Truck
Dump Truck cadangan = DT disediakan – DT di lapangan
=2-1
= 1 unit Dump Truck

Biaya Upah Operator :


Jumlah Buldozer : 1 unit
Sewa : Rp 120.000,-/jam
Waktu kerja : 7 jam/hari
Hari kerja : 6 hari
Upah Per Jam : Rp. 15.000,-
Biaya : (Rp. 15.000,- x 7 x 1 x 6) + (7 x 1 x 6 x Rp
120.000,-)
: Rp. 630.000,- + Rp 5.040.000,-

: Rp 5.670.000,-

Jumlah Backhoe : 1 unit


Waktu kerja : 7 jam/hari
Sewa : Rp 160.000,/jam
Hari kerja : 6 hari
Upah Per Jam : Rp. 15.000,-
Biaya : (Rp 15.000,- x 7 x 1 x 6) + ( 7 x 1 x 6
Rp 160.000)

: Rp. 630.000,- + Rp 6.720.000,-

: Rp 7.350.000,-

Jumlah Dump Truck : 1 unit


Waktu kerja : 7 jam/hari
Sewa : Rp 400.000,-/jam
Hari kerja : 6 hari
Upah Per Jam : Rp. 15.000,-
Biaya : (Rp 15.000,- x 7 x 1 x 6) + (7 x 1 x 6 x
Rp 400.000,-)
: Rp. 630.000,- + Rp 16.800.000,-

: Rp 17.430.000,-

Total Biaya Upah = Rp 5.670.000 + Rp 7.350.000 + Rp 17.430.000


= Rp 30.450.000,-

Konsumsi bahan bakar :


Jumlah Buldozer : 1 unit
Waktu kerja : 7 jam/hari
Hari kerja : 6 hari
Konsumsi BBM : 29,17 liter/jam
Harga solar : Rp. 6.000,-
Biaya : Rp. 6.000/liter x 29,17 x 7 x 1 x 6
: Rp. 7.350.840,00-,

Jumlah Backhoe : 1 unit


Waktu kerja : 7 jam/hari
Hari kerja : 6 hari
Konsumsi BBM : 6,25 liter/jam
Harga solar : Rp. 6.000,-
Biaya : Rp. 6.000/liter x 6,25 x 7 x 1 x 6 hari
: Rp. 1.575.000,00-

Jumlah DT : 1 unit
Waktu kerja : 7 jam/hari
Hari kerja : 6 hari
Konsumsi BBM : 5,769 liter/jam
Harga solar : Rp. 6.000,-
Biaya : Rp. 6.000/liter x 5,769 x 7 x 1 x 6
: Rp. 1.453.788,00-

Total anggaran : Rp. 7.350.840+1.575.000+1.453.788


= Rp 10.379.628,-
 Pengadaan bibit
Luas lahan yang ditanami rumput = 10000 m2 = 1 Ha
Dimensi penanaman yaitu 0,4m x 0,4m = 0,16 m2
Setiap 10.000 m2 dibutuhkan 10.000/0,16 = 62.500 tanaman rambat/Ha
Jadi rumput gajah yang dibutuhkan keseluruhan :
= 62.500 tanaman rambat x 1 Ha
= 62 tanaman rambat
Harga satu bibit = Rp 5.000,00 /tanaman rambat
Jumlah bibit = 62 bibit
Biaya pembibitan = 62 x Rp.5.000,00
= Rp 310.000,00-

 Pemeliharaan Bibit
Waktu pemeliharaan bibit = 1 tahun
Biaya buruh untuk pemeliharaan bibit = Rp. 12500.000/bulan
Jumlah buruh yang bekerja = 2 orang
Biaya pemeliharaan untuk 2 orang dalam satu bulan :
= Rp.1.250.000 x 2 orang
= Rp. 2.250.000,-
Total biaya pemeliharaan selama 1 tahun (12 bulan) :
= Rp. 2.250.000 x 12 bulan
= Rp 30.000.000,-
 Pembelian pupuk dasar kompos
Luas lahan = 10000 m2 = 1 Ha
Perbandingan tanah dengan pupuk kompos = 1 : 1
= 10000 m2 x 0.02 m
= 200 m2
Dalam 1 bibit diberi pupuk sebanyak 0,5 kg
Jadi, Pupuk kompos yang diperlukan dalam 62 bibit
= 62 bibit x 0,5 kg
= 31 kg
Harga pupuk kompos/karung (25 kg) = Rp. 15.000,-
Harga pupuk kompos 1 kg = Rp 7.000,-
Jumlah tanaman rambat = 62 bibit
Biaya pembelian pupuk kompos = Rp 7.000 x 62 kg
= Rp 434.000,00-
 Biaya penanaman tanaman rambat
Luas lahan yang direvegetasi = 10000 m2 = 1 Ha
Biaya penanaman tanaman rambat/Ha = Rp 900.000
Biaya penanaman tanaman rambat keseluruhan = Rp 900.000 x 1 Ha
= Rp 900.000,00-
Total = Rp 310.000,00 + Rp. 30.000.000 + Rp 434.000,00 + Rp 900.000,00
= Rp 1.644.000,-
Luas lahan yang ditanami pohon sengon = 10000 m2 = 1 Ha
Dimensi penanaman yaitu 4m x 4m = 16 m2
Setiap 10.000 m2 dibutuhkan 10.000/16 = 625 pohon/Ha
Jadi pohon sengon yang dibutuhkan keseluruhan :
= 625 pohon x 1 Ha
= 625 pohon
Harga satu bibit = Rp 5.000/pohon
Jumlah bibit = 625 bibit
Biaya pembibitan = 625 x Rp. 5.000 = Rp 3.125.000,-
 Pemeliharaan pohon sengon
Waktu pemeliharaan pohon sengon = 1 tahun
Biaya buruh untuk pemeliharaan sengon = Rp. 1.600.000/bulan
Jumlah buruh yang bekerja = 2 orang
Biaya pemeliharaan untuk 2 orang dalam satu bulan :
= Rp. 1.600.000 x 2 orang
= Rp. 3.200.000,-
Total biaya pemeliharaan selama1 tahun (12 bulan) :
= Rp. 3.200.000 x 12 bulan
= Rp 38.400.000,-
 Pembelian pupuk dasar kompos
Volume pot = 0,30 m x 0,30 m x 0,30 m = 0,027 m3
Perbandingan tanah dengan pupuk kompos =1:1
Volume pupuk kompos yang diperlukan dalam satu pot :
= 0,027 m3 : 2
= 0,0135 m3
Volume pupuk kompos yang diperlukan untuk seluruh pot :
= 0,0135 m3 x 625 pot
= 8,43 m3
Berat jenis pupuk kompos = 0,5 ton/m3
Berat pupuk kompos total yang diperlukan = 0,5 ton/m3 x 8,43 m3
= 4,21 ton

Harga pupuk kompos/karung (25 kg) = Rp. 15.000,-


Harga pupuk kompos 1 kg = Rp. 7.000,-
Jumlah pot = 625 pot
Biaya pembelian pupuk kompos = Rp. 7.000 x 4,21 ton
= Rp. 29.470,-
 Biaya penanaman pohon sengon
Luas lahan yang direvegetasi = 10000 m2 = 1Ha
Biaya penanaman pohon sengon/Ha = Rp 1.500.000
Biaya penanaman sengon keseluruhan = Rp 1.500.000 x 1Ha
= Rp 1.500.000,-
Total = Rp 3.125.000 + Rp 38.400.000 + Rp. 29.470 + Rp 1.500.000
= Rp 43.054.470,-
Biaya Total : Rp 1.644.000+ Rp 43.054.470 = Rp 44.698.470,-
PERHITUNGAN PASCATAMBANG REVEGETASI LAHAN

Tahun Terakhir
Biaya pengangkutan material
Luas lahan yang direvegetasi = 16000 m2
Volume material Top Soil = 16000 m2 x 1 m
= 16000 m3
= Volume Top Soil / Swell Factor
= 16000 m3 / 1,25
= 12800 LCM
Kebutuhan Pengangkuat
Volume material = 12800 LCM / 12 bulan
= 1066,6
= 1066,6 LCM/ 25 hari
= 42,6 LCM/hari

g. Bulldozer Komatsu D85ESS


Kapasitas blade bulldozer = 2,9 m³
W = 0,8 x 8 = 6,4 jam
S = 12 menit = 0,2 jam
R = 1,4 jam
T = 8 jam
MA = 82%
EA = 90%
Jarak dorong eff bulldozer = 25-40
Tanah yang terisi = Kapasitas blade x Faktor blade
= 2,9 m³ x 1
= 2,9 LCM

Jam efektif kerja Bulldozer = 60 menit/jam x eff


= 60 menit/jam x 1,25
= 75 menit/jam
Kecepatan Bulldozer maju = 3,50 km/jam
= 58,3 m/menit
Kecepatan Bulldozer mundur = 5,5 km/jam
= 91,67 m/menit
jarak dorong
Waktu mendorong maju =
kecepatan maju

40 m
= 58,3 m/menit

= 0,69 menit
jarak dorong
Waktu untuk mundur = kecepatan mundur

40 m
= 91,67 m/menit

= 0,44 menit
Cycle time bulldozer = Waktu maju + waktu ganti gear + waktu
mundur
= (0,69 + 0,6 + 0,44) menit
= 1,72 menit
jam efektif
Jumlah trip/jam =
𝑐𝑦𝑐𝑙𝑒 𝑡𝑖𝑚𝑒

75 menit
= 1,72 menit

= 43,60 = 44 trip/jam
Produksi bulldozer per jam = jumlah trip/jam x kapasitas blade
= 44 trip/jam x 2,9 m3
= 15,17 LCM/jam
Volume tanah penutup/jam
Bulldozer yang bekerja dilapangan =
jumlah trip

42,6 LCM/jam
= 44 𝐿𝐶𝑀/ℎ𝑎𝑟𝑖

= 0,96
= 1 bulldozer
Jumlah bulldozer di lapangan
Bulldozer disediakan = 𝑀𝑒𝑐ℎ𝑎𝑛𝑖𝑐𝑎𝑙 𝐴𝑣𝑎𝑖𝑙𝑎𝑏𝑖𝑙𝑖𝑡𝑦

1
= 0.82

= 1,22
= 2 bulldozer
Bulldozer Cadangan = bulldozer disediakan – bulldozer
dilapangan
=2–1
= 1 bulldozer

h. Backhoe Kobelco SK210

Ukuran bucket = 0,9 m3

Cycle Time = 35 detik/bucket

Fill factor bucket tanah penutup= 0,7

Swell factor tanah = 1,25

Tinggi Jenjang = 8 meter

EA = 90 %

MA = 82 %

Kapasitas Dump Truck = 12,21 m3

Banyak bucket = (kapasitas Dump truck)/(kapasitas bucket)

= (12,21 m3)/(0,9 m3 )

= 13,57 bucket ≈ 14 bucket


Waktu pengisin Dump Truck = banyak bucket x cycle time

= 14 bucket x 35 detik/bucket

= 490 detik

= 8,1 menit

Produksi backhoe untuk pengupasan tanah penutup :

Produksi/jam: 3600/Cycle Time x (bucket capacity x bucket fill factor ) x EA

= (3600/35 detik) x (0,9 m³ x 0,7) x 0,9

= 58,32 LCM/jam

Backhoe di lapangan = (Volume lapisan tanah penutup/jam) /

(Produksi Backhoe/jam)

= (42,6 LCM/jam) / ( 58,32 LCM/jam)


=0,73 unit backhoe

= 1 unit backhoe

Backhoe disediakan = (Jumlah backhoe di lapangan)/MA

= 1/0,82

= 1,22 ≈ 2 unit Backhoe

Backhoe cadangan = Backhoe disediakan – Backhoe di

lapangan

=2–1

= 1 unit Backhoe

d. Dump Truck Hino Dutro 130 PS


Macam pekerjaan = Mengangkut material hasial penggalian
Jarak angkut untuk tanah penutup = 0,609 km

Power = 128,22 HP
Efisiensi mesin = 85%
Ukuran bak Panjang = 2,9 meter
Lebar = 1,945 meter
Tinggi = 2,165 meter
Waktu ganti gear + menumpahkan = 2 menit
muatan+ maneuver
Berat truck kosong = 2,355 ton
Beban sumbu roda belakang = 60%
Beban sumbu roda belakang = 40%
Rimpul untuk percepatan = 10 kg/ton
Kapasitas DumpTtruck = panjang x lebar x tinggi
= 2,9 m x 1,945 m x 2,165 m
= 12,21 m³
Rute pengupasan ob
Jarak = 0,609 km
Berat truck kosong = 2,355 ton
= 2.355 kg
Berat isi = Kapasitas truck x bobot isi tanah penutup
= 12,21 m³ x 1,2728 ton/m³ x 0,8
= 12,43271 ton
= 12432,71 kg
Beban total = berat truck kosong + berat isi
= 2,355 ton + 12,43271 ton
= 15 ton
= 15.000 kg
Rimpull yang tersedia pada setiap gear Dump Truck Hino D :
Gear Kecepatan (km/h) Eff Mekanis (%) HP Rimpull (lb)
1 8,205 85 128,22 4.981
Gear Kecepatan (km/h) Eff Mekanis (%) HP Rimpull (lb)
2 14,04 85 128,22 2.911
3 26,27 85 128,22 1.556
4 40,87 85 128,22 1.000
5 55,38 85 128,22 0.738

Usable rimpull (yang digunakan) = beban total x distribusi beban x Cycle Time

= 15.000 kg x 60% x 60%

= 5.400 kg

Karena rimpull yang digunakan > rimpul yang tersedia yaitu 5.400 kg > 4.981 kg maka dump truck
tidak mengalami selip.

Waktu tempuh bermuatan pengangkutan lapisan tanah penutup

Jalur A-B

RP untuk RR = 7 %x 15.000 kg = 10.500 kg

RP untuk GR = 0% x 20 kg/ton x 29,8914 ton = 0 kg

RP untuk percepatan = 20 kg/ton x 29,8914 ton = 597,828 kg

RP yang dibutuhkan = 11097,828 kg

Karena rimpull yang dibutuhkan 11097,828 kg, maka digunakan gear 3 dengan kecepatan 26,27
km/jam
Jarak angkut
Waktu yang di butuhkan =
kecepatan

0,609km
= 26,27 km/jam

= 0,02 jam

= 1,2 menit

Waktu kembali kosong


Jalur B-A

RP untuk RR = 7 % x 2.355 kg = 1,6485 kg

RP untuk GR = 0 % x 20 kg/ton x 2,355 ton = 0 kg

RP untuk percepatan = 20 kg/ton x 2,355 ton = 47.1 kg

RP yang dibutuhkan = 48,75 kg

Karena rimpull yang dibutuhkan 48,75 kg, maka digunakan gear 5 dengan kecepatan 55,38
km/jam, karena kecepatan di area penambangan < 50 km/jam, maka di gunakan gearr 4 dengan
kecepatan 40,87 km/jam.
Jarak angkut
Waktu yang di butuhkan =
kecepatan

0,609 km
= 40,87 km/jam

= 0,015 jam

= 0,9 menit

Waktu tetap Pengisian = Cycle Time x banyak bucket

= 35 detik/bucket x 14 bucket

= 4900 detik

= 8,16 menit

Waktu ganti gear + Menumpahkan = 2 menit

muatan + manuver

Waktu variable

Waktu tempuh bermuatan = 1,2 menit

Waktu tempuh kosong = 0,9 menit

Cycle time dump truck = waktu tetap + waktu variable

= 8,16 menit + 2,1 menit


= 10,26 menit

60 menit
Jumlah trip/jam = 10,26 menit

= 5,85 trip ≈ 6 trip

Produksi Dump Truck /jam = kapasitas truk x jumlah trip/jam x EA

= 12,21 LCM/trip x 6 trip/jam truck x 0,90

= 65,934 LCM/jam
material yang di angkut
Dump Truck di lapangan = produksi 𝑑𝑢𝑚𝑝 𝑡𝑟𝑢𝑐𝑘/jam

42,6 LCM/jam
= 65,934 LCM/jam truck

= 0,64 unit Dump Truck  1 unit Dump Truck

Jumlah 𝐷𝑢𝑚𝑝 𝑇𝑟𝑢𝑐𝑘 di lapangan


Dump Truck disediakan = MA

1
= 0,82
= 1,22 unit ≈ 2 unit Dump Truck
Dump Truck cadangan = DT disediakan – DT di lapangan
=2-1
= 1 unit Dump Truck

Biaya Upah Operator :


Jumlah Buldozer : 1 unit
Sewa : Rp 120.000,-/jam
Waktu kerja : 7 jam/hari
Hari kerja : 6 hari
Upah Per Jam : Rp. 15.000,-
Biaya : (Rp. 15.000,- x 7 x 1 x 6) + (7 x 1 x 6 x Rp
120.000,-)
: Rp. 630.000,- + Rp 5.040.000,-

: Rp 5.670.000,-
Jumlah Backhoe : 1 unit
Waktu kerja : 7 jam/hari
Sewa : Rp 160.000,/jam
Hari kerja : 6 hari
Upah Per Jam : Rp. 15.000,-
Biaya : (Rp 15.000,- x 7 x 1 x 6) + ( 7 x 1 x 6
Rp 160.000)

: Rp. 630.000,- + Rp 6.720.000,-

: Rp 7.350.000,-

Jumlah Dump Truck : 1 unit


Waktu kerja : 7 jam/hari
Sewa : Rp 400.000,-/jam
Hari kerja : 6 hari
Upah Per Jam : Rp. 15.000,-
Biaya : (Rp 15.000,- x 7 x 1 x 6) + (7 x 1 x 6 x
Rp 400.000,-)
: Rp. 630.000,- + Rp 16.800.000,-

: Rp 17.430.000,-

Total Biaya Upah = Rp 5.670.000 + Rp 7.350.000 + Rp 17.430.000


= Rp 30.450.000,-

Konsumsi bahan bakar :


Jumlah Buldozer : 1 unit
Waktu kerja : 7 jam/hari
Hari kerja : 6 hari
Konsumsi BBM : 29,17 liter/jam
Harga solar : Rp. 6.000,-
Biaya : Rp. 6.000/liter x 29,17 x 7 x 1 x 6
: Rp. 7.350.840,00-,
Jumlah Backhoe : 1 unit
Waktu kerja : 7 jam/hari
Hari kerja : 6 hari
Konsumsi BBM : 6,25 liter/jam
Harga solar : Rp. 6.000,-
Biaya : Rp. 6.000/liter x 6,25 x 7 x 1 x 6 hari
: Rp. 1.575.000,00-

Jumlah DT : 1 unit
Waktu kerja : 7 jam/hari
Hari kerja : 6 hari
Konsumsi BBM : 5,769 liter/jam
Harga solar : Rp. 6.000,-
Biaya : Rp. 6.000/liter x 5,769 x 7 x 1 x 6
: Rp. 1.453.788,00-

Total anggaran : Rp. 7.350.840+1.575.000+1.453.788


= Rp 10.379.628,-

Rencana Pembangunan

Luas lahan = 1,6 Ha


Pembuatan Taman Wisata = Rp 300.000.000,-
Fasilitas umum = Rp 150.000.000
Parkiran = Rp 50.000.000
Kantin = Rp.50.000.000
Total = Rp 300.000.000 + Rp 150.000.000 + Rp 50.000.000+ Rp 50.000.000
= Rp550.000.000
Jumlah Keseluruhan = Rp 30.450.000 + Rp 10.379.628 + Rp 550.000.000
= Rp. 590.829.628
PERHITUNGAN RENCANA BIAYA REKLAMASI

Tabel Biaya Langsung


Tahun
No Jenis Biaya Langsung
Tahun 1 Tahun 2 Tahun 3
1 Biaya Penatagunaan Lahan
Penebaran Soil Rp 18.690.000 Rp 17.997.588,00 Rp 10.379.628,00
2 Biaya Revegetasi
Pengadaan bibit
Tanaman Rambat Rp 625.000 Rp 328.125 Rp 940.625
Sengon Rp 6.250.000
Jabon Rp 4.920.000
kakao (cokelat) Rp 28.218.750
Pemupukan
Tanaman Rambat Rp 673.750 Rp 459.375 Rp 1.316.875
Sengon Rp 59.010
Jabon Rp 30.996,00
kakao (cokelat) Rp 88.900,00
Penanaman
a. Penanaman Tanaman Rambat Rp 1.386.000 Rp 945.000 Rp 2.709.000,00
b. Pemeliharaan Tanaman Rp 30.000.000 Rp 30.000.000 Rp 32.000.000,00
c. Penanaman Sengon Rp 3.000.000
d. Pemeliharaan Sengon Rp 38.400.000
e. Penanaman Jabon Rp 1.575.000
f. Pemeliharaan Jabon Rp 40.000.000
g. Penanaman Kakao (cokelat) Rp 1.500.000,00
h. Pemeliharaan kakao (cokelat) Rp 57.600.000,00
3 Biaya Pemantauan
a. Pemantauan Kualitas Tanah Rp 650.000 Rp 650.000 Rp 650.000
b. Pemantauan Kualitas Udara Rp 700.000 Rp 700.000 Rp 700.000
Total Biaya Langsung Rp 100.433.760,00 Rp 97.606.084,00 Rp 134.603.778,00
Tabel Biaya Tidak Langsung
Total Biaya
NO Jenis Biaya Tidak Langsung Tahun 1 Tahun 2 Tahun 3
Biaya mobilisasi dan demobilisasi alat
1 (sebesar 2,5% dari Biaya Langsung atau Rp 2.510.844 Rp 2.440.152 Rp 3.365.094
berdasarkan perhitungan
Biaya perencanaan reklamasi (sebesar
2 Rp 10.043.376 Rp 9.760.608 Rp 13.460.378
10% dari Biaya Langsung
Biaya administrasi (sebesar 14% dari
3 Rp 14.060.726 Rp 13.664.852 Rp 18.844.529
Biaya Langsung
Biaya supervise (sebesar 7% dari
4 Rp 7.030.363 Rp 6.832.426 Rp 9.422.264
Biaya Langsung)
SUB TOTAL BIAYA TIDAK LANGSUNG Rp 33.645.310 Rp 32.698.038 Rp 45.092.266

Tabel Biaya langsung dan tidak langsung

Total
No Jenis
Tahun 1 Tahun 2 Tahun 3
1 Sub Total Biaya Langsung Rp 100.433.760 Rp 97.606.084 Rp 134.603.778
2 Sub Total Biaya Tidak Langsung Rp 33.645.310 Rp 32.698.038 Rp 45.092.266
Total Biaya Rp 134.079.070 Rp 130.304.122 Rp 179.696.044
Tabel Biaya Pasca Tambang
Pasca Tambang
No Jenis Biaya Langsung
Tahun Terakhir
1 Biaya Penatagunaan Lahan
Penebaran Soil Rp 10,379,628
2 Biaya Pembangunan
Fasilitas Umum Rp 150,000,000.00
Kantin Rp 50,000,000.00
Parkiran Rp 50,000,000.00
3 Biaya Pemantauan
a. Pemantauan Kualitas Tanah Rp 600,000.00
b. Pemantauan Kualitas Udara Rp 650,000.00
Biaya Sosial dan Ekonomi Rp 50,000,000.00
Total Biaya Langsung Rp 311,629,628.00
Tabel Biaya Tidak Langsung
Total Biaya
NO Jenis Biaya Tidak Langsung Tahun Terakhir
Biaya mobilisasi dan demobilisasi alat (sebesar 2,5%
1 Rp 7.790.741
dari Biaya Langsung atau berdasarkan perhitungan
Biaya perencanaan reklamasi (sebesar 10% dari Biaya
2 Rp 31.162.963
Langsung
3 Biaya administrasi (sebesar 14% dari Biaya Langsung Rp 43.628.148

4 Biaya supervise (sebesar 7% dari Biaya Langsung) Rp 21.814.074


SUB TOTAL BIAYA TIDAK LANGSUNG Rp 104.395.925

Biaya Total

Total
No Jenis
Tahun Terakhir
Rp
1 Sub Total Biaya Langsung 311.629.628
Rp
2 Sub Total Biaya Tidak Langsung 104.395.925
Rp
Total Biaya 416.025.553