DAFTAR HARGA TENAGA DAN BAHAN

HARGA 2021 PROFIT


Kode Nama Tenaga / Barang Satuan
datar .......%
1 2 3 4 5
TENAGA
1 Tukang batu/cat Org 80,500.00
2 Tukang kayu Org 80,500.00
3 Tukang besi Org 80,500.00
4 Pekerja Org 80,400.00
5 Kepala Tukang Org 80,600.00
6 Mandor Org 80,700.00

2. 2. BAHAN MATERIAL
2. 2. BAHAN BANGUNAN
2. 2. 1. BAHAN ALAM: PASIR, BATU, KERIKIL, BATA, ASPAL, SEMEN
2. 2. 1. 6 Batu andesit bakar M2 125,000.00
2. 2. 1. 14 Batu Bata / Merah Bj 560.00
2. 2. 1. 32 Batu pecah 2-3 cm M3 155,000.00
2. 2. 1. 36 Batu pecah 10-15 cm (15-20) M3 125,000.00
2. 2. 1. 39 Batu putih pecah , 5 - 7 cm M3 105,000.00
2. 2. 1. 43 Grasak M3 70,000.00
2. 2. 1. 44 Ijuk Kg 25,000.00
2. 2. 1. 50 Pasir pasang / beton M3 90,000.00
2. 2. 1. 51 Pasir Urug M3 70,000.00
2. 2. 1. 52 PC / Portland cement Kg 1,000.00
2. 2. 1. 53 Semen Merah M3 145,000.00
2. 2. 1. 54 Semen Putih / warna Kg 2,100.00
2. 2. 1. 56 Sirtu Urug M3 60,000.00
2. 2. 1. 60 Tali ijuk Kg 35,000.00
2. 2. 1. 61 Tanah liat M3 65,000.00
2. 2. 1. 62 Tanah urug M3 55,000.00
2. 2. 1. 63 Urugan Taman M3 85,000.00
64 air 5.00

2. 2. 2. BAHAN KAYU DAN BAMBU :


2. 2. 2. 2 Bambu (Dia 6 - 8 cm x 600cm) Btg 10,000.00
2. 2. 2. 3 Bambu Ori (Dia 10-12 x 600 cm) Btg 25,000.00
2. 2. 2. 4 Bambu Petung (p = 6 m) Ljr 35,000.00
2. 2. 2. 8 Dolken bambu panjang 3 m Btg 15,000.00
2. 2. 2. 9 Dolken Kayu jati lokal dia 10cm -15 cm, pjg = 3 m Btg -
2. 2. 2. 10 HPL Btg -
2. 2. 2. 11 Kayu kaso ( 5/7 ) cm pjg 3 m,kayu bekisting Btg 14,000.00
2. 2. 2. 12 Kayu bakar M3 75,000.00
2. 2. 2. 13 Kayu Balau Balok M3 10,000,000.00
2. 2. 2. 14 Kayu Balau Papan M3 12,000,000.00
2. 2. 2. 15 Kayu bekisting M3 1,100,000.00
2. 2. 2. 16 Kayu Jati Balok eks. Bojonegoro M3 -
2. 2. 2. 17 Kayu Jati Balok lokal M3 -
2. 2. 2. 18 Kayu Jati Papan eks. Bojonegoro M3 -
2. 2. 2. 19 Kayu jati papan lokal M3 -
2. 2. 2. 20 Kayu Kamper Balok M3 -
2. 2. 2. 21 Kayu Kamper papan M3 -
2. 2. 2. 30 Kayu Kruing Balok M3 7,000,000.00
2. 2. 2. 31 Kayu Kruing Papan M3 8,000,000.00
2. 2. 2. 32 Kayu Meranti Balok M3 -
2. 2. 2. 33 Kayu Meranti Papan M3 -
2. 2. 2. 34 Kayu Tahun Balok ( Mauni/ Akasia ) M3 -
2. 2. 2. 35 Kayu Tahun papan ( Mauni/akasia) M3 5,000,000.00

2. 2. 3. BAHAN PLAFOND, KERANGKA ATAP & PENUTUP ATAP:


2. 2. 3. 42 Atap galvalum ( Hollow 4cm ) M2 / psg 300,000.00
2. 2. 3. 43 Atap galvalum tebal 0,25 M2 35,000.00
2. 2. 3. 44 Atap galvalum tebal 0,30 M2 40,000.00
2. 2. 3. 45 Atap galvalum tebal 0,35 M2 45,000.00
2. 2. 3. 46 Atap galvalum tebal 0,40 M2 50,000.00
2. 2. 3. 71 Genteng bubung Mantili ex. Trenggalek / Tulungagung Bh 5,000.00
2. 2. 3. 79 Genteng mantili Bh 2,000.00
2. 2. 3. 85 Gypsum board tebal 9mm ( 1,2 x 2,4 m ) Lbr 65,000.00
2. 2. 3. 90 Kalsiplang motif kayu lebar 20 cm m' 30,000.00
1
2. 2. 3. 91 Kalsiplang polos lebar 30 cm m' 40,000.00
2. 2. 3. 99 Multiplek 9 mm, uk. 1,20 x 2,40 m Lbr 85,000.00
2. 2. 3. 113 Rangka plafond metal furing M' 10,000.00
2. 2. 3. 126 Seng Plat BJLS 30 lebar 0,90 m M' 85,000.00
2. 2. 3. 129 Talang PVC U 4" M' -
2. 2. 3. 141 Tripleks 122 x 244 tbl = 6 mm Lbr -
2. 2. 3. 142 Tripleks 122 x 244 tbl = 9 mm Lbr -
Rangka atap galvalum M2 160,000.00

2. 2. 4. BAHAN BESI / LOGAM :


2. 2. 4. 9 Besi Beton / tulangan beton Kg 9,000.00
2. 2. 4. 9 Besi Beton / tulangan beton ulir Kg 9,500.00
2. 2. 4. 10 Besi Beugel/Baut Kg 17,000.00
2. 2. 4. 11 Besi lis kaca (1 x 1) cm M' -
2. 2. 4. 12 Besi pengaman pipa dia 12 mm Unit -
2. 2. 4. 13 Besi plat Kg -
2. 2. 4. 14 Besi plat strip / Strip plate Kg -
2. 2. 4. 15 Besi siku Kg -
2. 2. 4. 16 Besi Square tube M' -
2. 2. 4. 17 Besi strip + Mur Baut Kg -
2. 2. 4. 20 Daun pintu Kaca pegas lengkap (kunci,engsel dan handle) M' -
2. 2. 4. 21 Grill besi M2 -
2. 2. 4. 23 Huruf logo nama stainlees uk. 30-40 cm M2 -
2. 2. 4. 24 Huruf logo nama stainlees uk. 40-50 cm M2 -
2. 2. 4. 25 Jaring kawat baja dilas (wiremesh) Kg -
2. 2. 4. 30 Kawat Beton / bendraat kg 18,000.00
2. 2. 4. 48 Pagar pipa besi holo (20.20.1)mm,Rangka besi holo (50.50.2)mm dicat M2/Psg -
2. 2. 4. 49 Pagar pipa besi holo (20.20.2)mm,Rangka besi holo (50.50.2)mm dicat M2/Psg -
2. 2. 4. 50 Pintu aluminium coklat / hitam 4" ( 2 sisi ) M2/Psg -
2. 2. 4. 51 Las besi / baja cm / Psg -
2. 2. 4. 52 Pintu besi lipat ( Bukan Harmonika) M2 -
2. 2. 4. 53 Pintu besi lipat ( harmonika) M2 -
2. 2. 4. 56 Pintu Pagar besi holo (20.20.2)mm, Rangka besi holo (50.50.2)mm dicat motif unit -
2. 2. 4. 57 Pintu Pagar Besi Tuang Ø14" (komplit) Bh -
2. 2. 4. 58 Pintu Pagar Besi Tuang Ø16" (komplit) M2/Psg -
Pintu Pagar pipa besi holo (20.20.1)mm, Rangka besi holo (50.50.2)mm dicat
motif -
2. 2. 4. 59 M2/Psg
2. 2. 4. 60 Pintu Plat Harmonika M2 -
2. 2. 4. 61 Pintu PVC Lipat (70x210)cm Unit -
2. 2. 4. 62 Pintu PVC Polos (70x210)cm Unit -
2. 2. 4. 63 Pintu Roling Door aluminium M2 -
2. 2. 4. 64 Pintu Roling Door besi M2 -
2. 2. 4. 65 Pintu Swing Ganda BRC (121x300)cm unit -
2. 2. 4. 66 Pipa Besi  2/4 Tebal= 1.2 mm M' -
2. 2. 4. 67 Pipa Besi  2/4 Tebal= 1.4 mm M' -
2. 2. 4. 68 Pipa Besi  4/4 Tebal= 1.2 mm M' -
2. 2. 4. 69 Pipa Besi  4/4 Tebal= 1.4 mm M' 24,166.67
2. 2. 4. 70 Pipa galvanis spindo SNI 1 - 1/2" x 2,8 - 3 Btg -
2. 2. 4. 71 Pipa galvanis spindo SNI 1 - 1/4" x 2,8 - 3 M' -
2. 2. 4. 72 Pipa galvanis spindo SNI 1" x 2,8 - 3 M' -
2. 2. 4. 73 Pipa galvanis spindo SNI 1/2" x 2,3 - 2,5 M' -
2. 2. 4. 74 Pipa galvanis spindo SNI 2 - 1/2" x 3,2 - 3,5 M' -
2. 2. 4. 75 Pipa galvanis spindo SNI 2" x 3,2 - 3,3 M' -
2. 2. 4. 76 Pipa galvanis spindo SNI 3" x 3,5 - 5 M' -
2. 2. 4. 77 Pipa galvanis spindo SNI 3/4" x 2,3 - 2,5 M' -
2. 2. 4. 78 Pipa galvanis spindo SNI 4" x 4 - 4,4 M' -
2. 2. 4. 79 Pipa galvanis spindo SNI 5" x 4,1 - 4,6 M' -
2. 2. 4. 80 Pipa galvanis spindo SNI 6" x 4,1 - 4,8 M' -
2. 2. 4. 81 Pipa Gas ( selang ) M' -
2. 2. 4. 82 Pipa hitam spindo SNI 1 - 1/2" M' -
2. 2. 4. 83 Pipa hitam spindo SNI 1 - 1/4" M' -
2. 2. 4. 84 Pipa hitam spindo SNI 1" M' -
2. 2. 4. 85 Pipa hitam spindo SNI 1/2" M' -
2. 2. 4. 86 Pipa hitam spindo SNI 2 - 1/2" M' -
2. 2. 4. 87 Pipa hitam spindo SNI 2" M' -
2. 2. 4. 88 Pipa hitam spindo SNI 3" M' -
2. 2. 4. 89 Pipa hitam spindo SNI 3/4" M' -
2. 2. 4. 90 Pipa hitam spindo SNI 4" M' -
2. 2. 4. 91 Pipa hitam spindo SNI 5" M' -
2. 2. 4. 92 Pipa hitam spindo SNI 6" M' -
2. 2. 4. 93 Profil aluminium T (Metal Furring) M' -
2. 2. 4. 94 Profil daun pintu almunium coklat / hitam Bh -
2. 2. 4. 95 Profil kusen almunium coklat / hitam 4" M' -
2
2. 2. 4. 96 Profil kusen aluminium 4" M' -
98 Profil daun aluminium 4" M' 95,000.00
99 Profil daun aluminium 3'' M' 85,000.00
2. 2. 4. 100 Ralling tangga / grill stainlees Dia 2" M2 / Psg -
2. 2. 4. 99 Ralling tangga / pagar besi M2 / Psg -
2. 2. 4. 100 Rel pintu dorong Unit -
2. 2. 4. 105 Teralis Besi M2 -
2. 2. 4. 106 Teralis stainlees btg -
109 Rangka partisi C m' 15,000.00

2. 2. 5. BAHAN PENUTUP LANTAI & DINDING :


2. 2. 5. 7 Calsy bord ( uk. 122 x 244 x 0.3 cm ) Lbr 65,000.00
2. 2. 5. 31 Keramik motif Uk. 30 cm x 30 cm M2 35,000.00
2. 2. 5. 32 Keramik motif Uk. 40 cm x 40 cm M2 36,000.00
2. 2. 5. 34 Keramik putih Uk. 30 cm x 30 cm M2 36,000.00
2. 2. 5. 35 Keramik putih Uk. 40cm x 40 cm M2 38,000.00
2. 2. 5. 43 Keramik tekstur Uk. 30cm x 30 cm M2 35,000.00
2. 2. 5. 51 List Keramik (10x40)cm m' 12,000.00
2. 2. 5. 60 Paving Stone abu - abu t= 6 cm, K225 M2 42,000.00
84 Keramik tekstur Uk. 25 cm x 25 cm M2 42,000.00
85 Keramik dinding 25 x 40 cm M2 39,000.00
86 Keramik tekstur Uk. 40 cm x 40 cm M2 42,000.00
topi uskup/stoper m2 65,000.00

2. 2. 6. BAHAN PENGECATAN & BAHAN CAIR LAINNYA :


2. 2. 6. 2 Aquaproof Kg 65,000.00
2. 2. 6. 3 Cat besi Kg 55,000.00
2. 2. 6. 6 Cat Dasar Kayu Kg 45,000.00
2. 2. 6. 8 Cat Kayu Kg 55,000.00
2. 2. 6. 10 Cat Meny besi Kg 45,000.00
2. 2. 6. 11 Cat Meny kayu Kg 45,000.00
2. 2. 6. 12 Cat Tembok Kg 20,000.00
2. 2. 6. 17 Coatting Ltr 65,000.00
2. 2. 6. 19 HCL / air keras Ltr 15,000.00
2. 2. 6. 21 Kertas gosok ( rempelas ) Lbr 3,500.00
2. 2. 6. 22 Kuas 3 " Bj 9,500.00
2. 2. 6. 23 Kuas 4 " Bj 14,000.00
2. 2. 6. 24 Lem ( Kayu + Tembok ) Bh 15,000.00
2. 2. 6. 25 Lem PVC Tube 7,500.00
2. 2. 6. 26 Meni besi Kg 45,000.00
2. 2. 6. 27 Minyak bekisting Ltr 6,000.00

3
2. 2. 6. 28 Minyak Cat / Thiner A Ltr 30,000.00
2. 2. 6. 29 Minyak Cat / Thiner B Ltr 22,500.00
2. 2. 6. 30 Cat Interior Ltr 23,000.00
2. 2. 6. 31 Cat Eksetrior Ltr 28,000.00
2. 2. 6. 32 Oli Gardan Ltr -
2. 2. 6. 33 Oli rem Ltr -
2. 2. 6. 34 Oli Hidrolis Ltr -
2. 2. 6. 35 Oli Presneleng Ltr -
2. 2. 6. 36 Paint Stone Zak -
2. 2. 6. 37 Plamur kayu Kg 23,000.00
2. 2. 6. 38 Plamur Tembok Kg 15,000.00
2. 2. 6. 39 Politur jadi Ltr -
2. 2. 6. 40 Residu ( Ter ) Ltr -
2. 2. 6. 41 Rol kuas Bh -
2. 2. 6. 42 Sabun Kg -
2. 2. 6. 43 Sending impra ( melamine) Kg -
2. 2. 6. 44 Soda api Kg -
2. 2. 6. 45 Spiritus Ltr -
2. 2. 6. 46 Stempet / Gemuk Kg -
2. 2. 6. 47 Teak oil Ltr -
2. 2. 6. 48 Vernis Ltr 65,000.00

2. 2. 7. BAHAN PENGGANTUNG DAN PENGUNCI :


2. 2. 7. 1 Door Closer ex. Beluci Bh 125,000.00
2. 2. 7. 2 Door Stoper Stainless Bh 35,000.00
2. 2. 7. 3 Engsel pintu kupu - kupu Bh 55,000.00
2. 2. 7. 5 Engsel Jendela (Arch ) Bh 15,000.00
2. 2. 7. 10 Engsel Pintu (Arch ) nylon Bh 25,000.00
2. 2. 7. 11 Engsel pintu ex. Union 4" Bh -
2. 2. 7. 12 Engsel sendok Bh -
2. 2. 7. 25 Grendel jendela merk SES Bh -
2. 2. 7. 26 Grendel Pintu Panjang ( sespen ) Bh -
2. 2. 7. 27 Grendel pintu ganda Dekson 40 cm komplit Bh -
2. 2. 7. 31 Grendel tanam merk SES Set 30,000.00
2. 2. 7. 33 Hak angin (Sikutan) biasa Set -
2. 2. 7. 34 Hak angin 4mm Lurus/plat 4x150mm Bh -
2. 2. 7. 35 Hak angin lurus Bh -
2. 2. 7. 36 Hak angin/sikutan Merk SES Set 35,000.00
2. 2. 7. 37 Handle Bh -
2. 2. 7. 38 Handle pintu ganda Dekson 30 cm komplit Set 450,000.00
2. 2. 7. 39 Handle pintu ganda Dekson 40 cm komplit Set -
40 Handle pintu stanless 30 cm Set 160,000.00
2. 2. 7. 50 Kunci tanam merk SES ( pelor ) Bh -
53 Kunci tanam dekson Bh 95,000.00
2. 2. 7. 56 Selot ( kunci pintu ) merk SES Bh -

2. 2. 8. BAHAN SANITAIR :
2. 2. 8. 2 Avor staninlees steel Bh 45,000.00
2. 2. 8. 4 Bak Cuci Stainlesstel (Royal) Bh 200,000.00
2. 2. 8. 10 Double Kran Dupon Bh -
2. 2. 8. 12 Kloset Duduk Keramik Komplit ex.AMSTAD Bh -
2. 2. 8. 13 Kloset Duduk Keramik Komplit ex.INA Bh -
2. 2. 8. 14 Kloset Duduk Keramik Komplit ex.TOTO Bh 1,250,000.00
2. 2. 8. 15 Kloset Jongkok Keramik ex.AMSTAD Bh -
2. 2. 8. 16 Kloset Jongkok Keramik ex.INA Bh -
2. 2. 8. 29 Kran cucian dia 1/2" Bh 275,000.00
2. 2. 8. 30 Kran Dia 1/2 " stainless steel Bh 40,000.00
2. 2. 8. 31 Kran Dia 3/4 " stainless steel Bh 55,000.00
2. 2. 8. 32 Kran Dupon Bh -
2. 2. 8. 33 Kran Toto 1/2" Bh -
2. 2. 8. 34 Pipa kurasan plastik Bh -
2. 2. 8. 57 PVC AW Dia 0.5 " ( abu - abu ) M' / bhn 2,400.00
2. 2. 8. 61 PVC AW Dia 1,5 " ( abu - abu ) M' / bhn 6,500.00
2. 2. 8. 63 PVC AW Dia 2 ,5" ( abu - abu ) M' / bhn 15,000.00
2. 2. 8. 64 PVC AW Dia 3 " ( abu - abu ) M' / bhn 20,000.00
2. 2. 8. 65 PVC AW Dia 4 " ( abu - abu ) M' / bhn 25,000.00
2. 2. 8. 90 PVC (Class D) Dia 1.5 " ( abu - abu ) M' / bhn -
2. 2. 8. 91 PVC (Class D) Dia 2 " ( abu - abu ) M' / bhn -
2. 2. 8. 92 PVC (Class D) Dia 2.5 " ( abu - abu ) M' / bhn -
2. 2. 8. 93 PVC (Class D) Dia 3 " ( abu - abu ) M' / bhn -
2. 2. 8. 94 PVC (Class D) Dia 4 " ( abu - abu ) M' / bhn -
2. 2. 8. 113 Shower Dupon Set -
2. 2. 8. 114 Shower toilet Bh -
4
2. 2. 8. 115 Seal Tape Bh 4,500.00
2. 2. 8. 116 Stop Kran Dia 1.5 " Bh -
2. 2. 8. 117 Stop Kran Dia 1/2 " Bh -
2. 2. 8. 118 Stop Kran Dia 3/4 " Bh -
2. 2. 8. 119 Stop kran dia 1" kuningan Bh -
2. 2. 8. 120 Stop kran dia 1" plastik Bh -
2. 2. 8. 121 Stop kran dia 1/2" kuningan Bh -
2. 2. 8. 122 Stop kran dia 3/4" kuningan Bh -
2. 2. 8. 123 Stop Kran Ǿ 1/2" Bh -
2. 2. 8. 126 Tandon air stainlees steel kap. 1.000 ltr Bh -
2. 2. 8. 127 Tandon air stainlees steel kap. 550 ltr Bh -
2. 2. 8. 136 Tempat Sabun Keramik ex.INA Bh -
2. 2. 8. 137 Urinoir Bh -
138 Wastafel amstad Bh 500,000.00

2. 2. 9. BAHAN JENIS KACA : -


2. 2. 9. 3 Glass Block Bening (20x20)cm Bh -
2. 2. 9. 4 Glass Block Buram (20x20)cm Bh -
2. 2. 9. 5 Kaca air 5 Cm M2 85,000.00
2. 2. 9. 9 Kaca Bening t= 5 mm M2 75,000.00
2. 2. 9. 30 Sealant Tube 25,000.00
31 Sunblas m2 -

2. 2. 10. BAHAN BETON CETAKAN :


2. 2. 10. 11 Buis Beton 1/2 ø 20 Cm M' -
2. 2. 10. 15 Buis Beton ø 20 Cm M' -

2. 2. 12. BAHAN JENIS PAKU :


2. 2. 12. 1 Paku biasa Kg 15,000.00
2. 2. 12. 2 Paku Eternit / Triplek Kg 15,000.00
2. 2. 12. 3 Paku Gypsum Kg 15,000.00
2. 2. 12. 4 Paku Kalsiboard Kg 15,000.00
2. 2. 12. 5 Paku Kayu Uk.2,5"-5" Kg 15,000.00
2. 2. 12. 6 Paku Reng Kayu 2" Kg 15,000.00
2. 2. 12. 7 Paku Usuk 3" Kg 15,000.00
2. 2. 12. 8 Paku Asbes Kg 15,000.00
2. 2. 12. 9 Paku beton 5cm Bh 750.00
2. 2. 12. 10 Paku Kait ( pancing ) Bh 1,000.00
2. 2. 12. 11 Paku Ramset / dinabolt Bh 1,500.00
2. 2. 12. 12 Paku Sekrup Bh 500.00
2. 2. 12. 15 Skrup Fixer Bh 500.00

2. 2. 13. BAHAN FABRIKASI, ELEKTRIK, POMPA :


2. 2. 13. 16 Exhaust langit-langit 25/25 cm Unit
2. 2. 13. 29 Pompa air listrik 40 lt/menit 125 watt Unit -

3. 6. 1. LAMPU TAMAN DAN PERALATAN LISTRIK -


3. 6. 1. 184 Ongkos pasang titik lampu + instalasi Ttk 70,000.00
3. 6. 1. 200 Saklar Panasonic (ganda) Bh 20,000.00
3. 6. 1. 201 Saklar Panasonic (tunggal) Bh 18,000.00
3. 6. 1. 248 Stop Kontak Panasonic Buah 18,000.00
249 Downlight led 9 w Bh 38,000.00
250 Lampu LED 10 watt Bh 45,000.00
251 Lampu LED 6 watt Bh 28,000.00
252 Lampu spot LED 20 watt Bh 245,000.00
253 Lampu spot LED 30 watt Bh 435,000.00
254 Lampu tempel led Bh 295,000.00
255 saklar hotel Set 50,000.00
256 Ground bh 135,000.00
257 Kabel Penangkal petir m' 45,000.00

Tulungagung, 2021

Dibuat oleh :
CV……………………..

5
…………………………..
Direktur/Direkris

6
ANALISA HARGA SATUAN PEKERJAAN
DILARANG MERUBAH KOEFISIEN
A.2.3.1 HARGA SATUAN PEKERJAAN TANAH
A.2.3.1.1 Pengalian Tanah 1m3 tanah biasa sedalam 1 m
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.750 80,400.00 60,300.00
Mandor L.04 OH 0.025 80,700.00 2,017.50
JUMLAH TENAGA KERJA 62,317.50
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 62,317.50
E Overhead & Profit ...... % x D 1,246.35
F Harga Satuan Pekerja (D + E ) 63,563.85
A.2.3.1.9 Pengurugan Kembali 1m3 galian tanah
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.500 80,400.00 40,200.00
Mandor L.04 OH 0.050 80,700.00 4,035.00
JUMLAH TENAGA KERJA 44,235.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 44,235.00
E Overhead & Profit ...... % x D 884.70
F Harga Satuan Pekerja (D + E ) 45,119.70
A.2.3.1.11 Pengurugan 1m3 dengan Pasir urug
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.300 80,400.00 24,120.00
Mandor L.04 OH 0.010 80,700.00 807.00
JUMLAH TENAGA KERJA 24,927.00
B BAHAN
Pasir urug m3 1.200 70,000.00 84,000.00
JUMLAH HARGA BAHAN 84,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 108,927.00
E Overhead & Profit ...... % x D 2,178.54
F Harga Satuan Pekerja (D + E ) 111,105.54
A.2.3.1.15 Pengurugan 1m3 dengan tanah urug
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.250 80,400.00 20,100.00
Mandor L.04 OH 0.025 80,700.00 2,017.50
JUMLAH TENAGA KERJA 22,117.50
B BAHAN
Tanah urug m3 1.200 55,000.00 66,000.00
JUMLAH HARGA BAHAN 66,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 88,117.50
E Overhead & Profit ...... % x D 1,762.35
F Harga Satuan Pekerja (D + E ) 89,879.85

A.3.2.1.1 HARGA SATUAN PEKERJAAN PONDASI


A.3.2.1.3 Pemasangan 1m3 Pondasi Batu pecah 10-15 cm (15-20) camp. 1SP : 5 PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 1.500 80,400.00 120,600.00
Tukang Batu L.02 OH 0.750 80,500.00 60,375.00
Kepala Tukang L.03 OH 0.075 80,600.00 6,045.00
Mandor L.04 OH 0.075 80,700.00 6,052.50
JUMLAH TENAGA KERJA 193,072.50
B BAHAN
Batu pecah 10-15 cm (15-20) m3 1.200 125,000.00 150,000.00
PC / Portland cement kg 136.000 1,000.00 136,000.00
Pasir pasang / beton m3 0.544 90,000.00 48,960.00
JUMLAH HARGA BAHAN 334,960.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 528,032.50
E Overhead & Profit ...... % x D 10,560.65

7
F Harga Satuan Pekerja (D + E ) 538,593.15

8
A.3.2.1.9 Pemasangan batu kosong ( anstamping )
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.780 80,400.00 62,712.00
Tukang Batu L.02 OH 0.390 80,500.00 31,395.00
Kepala Tukang L.03 OH 0.039 80,600.00 3,143.40
Mandor L.04 OH 0.039 80,700.00 3,147.30
JUMLAH TENAGA KERJA 100,397.70
B BAHAN
Batu pecah 10-15 cm (15-20) m3 1.200 125,000.00 150,000.00
Pasir pasang / beton Kg 0.432 90,000.00 38,880.00
JUMLAH HARGA BAHAN 188,880.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 289,277.70
E Overhead & Profit ...... % x D 5,785.55
F Harga Satuan Pekerja (D + E ) 295,063.25

A.4.1.1 HARGA SATUAN PEKERJAAN BETON


A.4.1.1.1 Membuat 1m3 lantai kerja beton mutu f'c = 7.4 Mpa (K100) slump (3-6)cm w/c = 0.87
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 1.650 80,400.00 132,660.00
Tukang Batu L.02 OH 0.275 80,500.00 22,137.50
Kepala Tukang L.03 OH 0.028 80,600.00 2,256.80
Mandor L.04 OH 0.083 80,700.00 6,698.10
JUMLAH TENAGA KERJA 163,752.40
B BAHAN
PC / Portland cement kg 247.000 1,000.00 247,000.00
Pasir pasang / beton m3 0.6207 90,000.00 55,863.00
Batu pecah 2-3 cm m3 0.7400 155,000.00 114,700.00
Air bersih Liter 215.000 5.00 1,075.00
JUMLAH HARGA BAHAN 418,638.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 582,390.40
E Overhead & Profit ...... % x D 11,647.81
F Harga Satuan Pekerja (D + E ) 594,038.21
A.4.1.1.5 Membuat 1m3 beton mutu f'c = 14.5 Mpa (K175) slump (12 ± 2)cm w/c = 0.66
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 1.650 80,400.00 132,660.00
Tukang Batu L.02 OH 0.275 80,500.00 22,137.50
Kepala Tukang L.03 OH 0.028 80,600.00 2,256.80
Mandor L.04 OH 0.083 80,700.00 6,698.10
JUMLAH TENAGA KERJA 163,752.40
B BAHAN
PC / Portland cement kg 326.000 1,000.00 326,000.00
Pasir pasang / beton m3 0.5429 90,000.00 48,861.00
Batu pecah 2-3 cm m3 0.7622 155,000.00 118,141.00
Air bersih Liter 215.000 5.00 1,075.00
JUMLAH HARGA BAHAN 494,077.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 657,829.40
E Overhead & Profit ...... % x D 13,156.59
F Harga Satuan Pekerja (D + E ) 670,985.99
A.4.1.1.9 Membuat 1m3 beton mutu f'c = 24 Mpa (K275) slump (12 ± 2)cm w/c = 0.53
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 1.650 80,400.00 132,660.00
Tukang Batu L.02 OH 0.275 80,500.00 22,137.50
Kepala Tukang L.03 OH 0.028 80,600.00 2,256.80
Mandor L.04 OH 0.083 80,700.00 6,698.10
JUMLAH TENAGA KERJA 163,752.40
B BAHAN
PC / Portland cement kg 406.000 1,000.00 406,000.00
Pasir pasang / beton m3 0.4886 90,000.00 43,974.00
Batu pecah 2-3 cm m3 0.7600 155,000.00 117,800.00
Air bersih Liter 215.000 5.00 1,075.00
JUMLAH HARGA BAHAN 568,849.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 732,601.40
E Overhead & Profit ...... % x D 14,652.03
F Harga Satuan Pekerja (D + E ) 747,253.43

9
A.4.1.1.17 Pembesian 10 Kg dengan Besi polos atau ulir
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.070 80,400.00 5,628.00
Tukang Besi L.02 OH 0.070 80,500.00 5,635.00
Kepala Tukang L.03 OH 0.007 80,600.00 564.20
Mandor L.04 OH 0.004 80,700.00 322.80
JUMLAH TENAGA KERJA 12,150.00
B BAHAN
Besi Beton / tulangan beton kg 10.500 9,000.00 94,500.00
Kawat Beton / bendraat kg 0.150 18,000.00 2,700.00
JUMLAH HARGA BAHAN 97,200.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 109,350.00
E Overhead & Profit ...... % x D 2,187.00
F Harga Satuan Pekerja (D + E ) 111,537.00
per kg 11,153.70
A.4.1.1.20 Pemasangan 1m2 Bekisting untuk pondasi
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.520 80,400.00 41,808.00
Tukang Kayu L.02 OH 0.260 80,500.00 20,930.00
Kepala Tukang L.03 OH 0.026 80,600.00 2,095.60
Mandor L.04 OH 0.026 80,700.00 2,098.20
JUMLAH TENAGA KERJA 66,931.80
B BAHAN
Kayu bekisting m3 0.040 1,100,000.00 44,000.00
Paku biasa kg 0.300 15,000.00 4,500.00
Minyak bekisting liter 0.100 6,000.00 600.00
JUMLAH HARGA BAHAN 49,100.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 116,031.80
E Overhead & Profit ...... % x D 2,320.64
F Harga Satuan Pekerja (D + E ) 118,352.44
2x pakai 59,176.22
A.4.1.1.21 Pemasangan 1m2 Bekisting untuk sloof
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.520 80,400.00 41,808.00
Tukang Kayu L.02 OH 0.260 80,500.00 20,930.00
Kepala Tukang L.03 OH 0.026 80,600.00 2,095.60
Mandor L.04 OH 0.026 80,700.00 2,098.20
JUMLAH TENAGA KERJA 66,931.80
B BAHAN
Kayu bekisting m3 0.045 1,100,000.00 49,500.00
Paku biasa kg 0.300 15,000.00 4,500.00
Minyak bekisting liter 0.100 6,000.00 600.00
JUMLAH HARGA BAHAN 54,600.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 121,531.80
E Overhead & Profit ...... % x D 2,430.64
F Harga Satuan Pekerja (D + E ) 123,962.44
2 x pakai 61,981.22
A.4.1.1.22 Pemasangan 1m2 Bekisting untuk kolom
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.660 80,400.00 53,064.00
Tukang Kayu L.02 OH 0.330 80,500.00 26,565.00
Kepala Tukang L.03 OH 0.033 80,600.00 2,659.80
Mandor L.04 OH 0.033 80,700.00 2,663.10
JUMLAH TENAGA KERJA 84,951.90
B BAHAN
Kayu bekisting m3 0.040 1,100,000.00 44,000.00
Paku biasa kg 0.400 15,000.00 6,000.00
Minyak bekisting liter 0.200 6,000.00 1,200.00
Kayu bekisting m3 0.015 1,100,000.00 16,500.00
Multiplek 9 mm, uk. 1,20 x 2,40 m lbr 0.350 85,000.00 29,750.00
Bambu (Dia 6 - 8 cm x 600cm) btg 2.000 10,000.00 20,000.00
JUMLAH HARGA BAHAN 117,450.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 202,401.90
E Overhead & Profit ...... % x D 4,048.04
F Harga Satuan Pekerja (D + E ) 206,449.94
2 x pakai 103,224.97

10
A.4.1.1.23 Pemasangan 1m2 Bekisting untuk balok
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.660 80,400.00 53,064.00
Tukang Kayu L.02 OH 0.330 80,500.00 26,565.00
Kepala Tukang L.03 OH 0.033 80,600.00 2,659.80
Mandor L.04 OH 0.033 80,700.00 2,663.10
JUMLAH TENAGA KERJA 84,951.90
B BAHAN
Kayu bekisting m3 0.040 1,100,000.00 44,000.00
Paku biasa kg 0.400 15,000.00 6,000.00
Minyak bekisting liter 0.200 6,000.00 1,200.00
Kayu bekisting m3 0.018 1,100,000.00 19,800.00
Multiplek 9 mm, uk. 1,20 x 2,40 m lbr 0.350 85,000.00 29,750.00
Bambu (Dia 6 - 8 cm x 600cm) btg 2.000 10,000.00 20,000.00
JUMLAH HARGA BAHAN 120,750.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 205,701.90
E Overhead & Profit ...... % x D 4,114.04
F Harga Satuan Pekerja (D + E ) 209,815.94
2x pakai 104,907.97
A.4.1.1.24 Pemasangan 1m2 Bekisting untuk lantai
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.660 80,400.00 53,064.00
Tukang Kayu L.02 OH 0.330 80,500.00 26,565.00
Kepala Tukang L.03 OH 0.033 80,600.00 2,659.80
Mandor L.04 OH 0.033 80,700.00 2,663.10
JUMLAH TENAGA KERJA 84,951.90
B BAHAN
Kayu bekisting m3 0.040 1,100,000.00 44,000.00
Paku biasa kg 0.400 15,000.00 6,000.00
Minyak bekisting liter 0.200 6,000.00 1,200.00
Kayu bekisting m3 0.015 1,100,000.00 16,500.00
Multiplek 9 mm, uk. 1,20 x 2,40 m lbr 0.350 85,000.00 29,750.00
Bambu (Dia 6 - 8 cm x 600cm) btg 6.000 10,000.00 60,000.00
JUMLAH HARGA BAHAN 157,450.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 242,401.90
E Overhead & Profit ...... % x D 4,848.04
F Harga Satuan Pekerja (D + E ) 247,249.94
2x pakai 123,624.97
A.4.1.1.27 1m2 Pemasangan Bekisting ongkos tenaga
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.520 80,400.00 41,808.00
Tukang Kayu L.02 OH 0.260 80,500.00 20,930.00
Kepala Tukang L.03 OH 0.026 80,600.00 2,095.60
Mandor L.04 OH 0.026 80,700.00 2,098.20
JUMLAH TENAGA KERJA 66,931.80
B BAHAN
Paku biasa kg 0.300 15,000.00 4,500.00
Minyak bekisting liter 0.100 6,000.00 600.00
JUMLAH HARGA BAHAN 5,100.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 72,031.80
E Overhead & Profit ...... % x D 1,440.64
F Harga Satuan Pekerja (D + E ) 73,472.44

A.4.2.1 HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM


A.4.2.1.11 Pemasangan 1m' kusen pintu alumunium
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.043 80,400.00 3,457.20
Tukang las L.02 OH 0.043 80,500.00 3,461.50
Kepala Tukang L.03 OH 0.0043 80,600.00 346.58
Mandor L.04 OH 0.0021 80,700.00 169.47
JUMLAH TENAGA KERJA 7,434.75
B BAHAN
Profil kusen almunium coklat / hitam 4" m' 1.100 95,000.00 104,500.00
Skrup Fixer bh 2.000 500.00 1,000.00
Sealant tube 0.060 25,000.00 1,500.00
JUMLAH HARGA BAHAN 107,000.00
C PERALATAN
JUMLAH HARGA ALAT

11
D Jumlah( A + B + C ) 114,434.75
E Overhead & Profit ...... % x D 2,288.70
F Harga Satuan Pekerja (D + E ) 116,723.45

12
A.4.2.1.13a Pemasangan 1m2 pintu kaca rangka alumunium
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.085 80,400.00 6,834.00
Tukang Las L.02 OH 0.085 80,500.00 6,842.50
Kepala Tukang L.03 OH 0.0090 80,600.00 725.40
Mandor L.04 OH 0.0050 80,700.00 403.50
JUMLAH TENAGA KERJA 14,805.40
B BAHAN
Profil daun aluminium 4" m' 4.400 95,000.00 418,000.00
Kaca Bening t= 5 mm m2 1.100 75,000.00 82,500.00
Sealant tube 0.270 25,000.00 6,750.00
JUMLAH HARGA BAHAN 507,250.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 522,055.40
E Overhead & Profit ...... % x D 10,441.11
F Harga Satuan Pekerja (D + E ) 532,496.51
A.4.2.1.13b Pemasangan 1m2 jendela kaca rangka alumunium
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.085 80,400.00 6,834.00
Tukang Las L.02 OH 0.085 80,500.00 6,842.50
Kepala Tukang L.03 OH 0.0090 80,600.00 725.40
Mandor L.04 OH 0.0050 80,700.00 403.50
JUMLAH TENAGA KERJA 14,805.40
B BAHAN
Profil daun aluminium 3'' m' 4.400 85,000.00 374,000.00
Kaca Bening t= 5 mm m2 1.100 75,000.00 82,500.00
Sealant tube 0.270 25,000.00 6,750.00
JUMLAH HARGA BAHAN 463,250.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 478,055.40
E Overhead & Profit ...... % x D 9,561.11
F Harga Satuan Pekerja (D + E ) 487,616.51
A.4.2.1.18 Pemasangan 1m' talang jurai bjls 30 lebar 90 cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.200 80,400.00 16,080.00
Tukang Kayu L.02 OH 0.200 80,500.00 16,100.00
Kepala Tukang L.03 OH 0.020 80,600.00 1,612.00
Mandor L.04 OH 0.001 80,700.00 80.70
JUMLAH TENAGA KERJA 33,872.70
B BAHAN
Seng Plat BJLS 30 lebar 0,90 m m' 1.050 85,000.00 89,250.00
Paku biasa Kg 0.015 15,000.00 225.00
Kayu Tahun papan ( Mauni/akasia) m3 0.019 5,000,000.00 95,000.00
JUMLAH HARGA BAHAN 184,475.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 218,347.70
E Overhead & Profit ...... % x D 4,366.95
F Harga Satuan Pekerja (D + E ) 222,714.65

A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING


A.4.4.1.4 Pemasangan 1m2 dinding Batu Bata / Merah (5x11x22) tebal 1 bata camp 1SP : 5PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.600 80,400.00 48,240.00
Tukang Batu L.02 OH 0.200 80,500.00 16,100.00
Kepala Tukang L.03 OH 0.020 80,600.00 1,612.00
Mandor L.04 OH 0.030 80,700.00 2,421.00
JUMLAH TENAGA KERJA 68,373.00
B BAHAN
Batu Bata / Merah bh 140.000 560.00 78,400.00
PC / Portland cement kg 22.200 1,000.00 22,200.00
Pasir pasang / beton m3 0.102 90,000.00 9,180.00
JUMLAH HARGA BAHAN 109,780.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 178,153.00
E Overhead & Profit ...... % x D 3,563.06
F Harga Satuan Pekerja (D + E ) 181,716.06

13
A.4.4.1.8 Pemasangan 1m2 dinding Batu Bata / Merah (5x11x22) tebal 1/2 bata camp 1SP : 3PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.300 80,400.00 24,120.00
Tukang Batu L.02 OH 0.100 80,500.00 8,050.00
Kepala Tukang L.03 OH 0.010 80,600.00 806.00
Mandor L.04 OH 0.015 80,700.00 1,210.50
JUMLAH TENAGA KERJA 34,186.50
B BAHAN
Batu Bata / Merah bh 70.000 560.00 39,200.00
PC / Portland cement kg 14.370 1,000.00 14,370.00
Pasir pasang / beton m3 0.040 90,000.00 3,600.00
JUMLAH HARGA BAHAN 57,170.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 91,356.50
E Overhead & Profit ...... % x D 1,827.13
F Harga Satuan Pekerja (D + E ) 93,183.63
A.4.4.1.10 Pemasangan 1m2 dinding Batu Bata / Merah (5x11x22) tebal 1/2 bata camp 1SP : 5PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.300 80,400.00 24,120.00
Tukang Batu L.02 OH 0.100 80,500.00 8,050.00
Kepala Tukang L.03 OH 0.010 80,600.00 806.00
Mandor L.04 OH 0.015 80,700.00 1,210.50
JUMLAH TENAGA KERJA 34,186.50
B BAHAN
Batu Bata / Merah bh 70.000 560.00 39,200.00
PC / Portland cement kg 9.680 1,000.00 9,680.00
Pasir pasang / beton m3 0.045 90,000.00 4,050.00
JUMLAH HARGA BAHAN 52,930.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 87,116.50
E Overhead & Profit ...... % x D 1,742.33
F Harga Satuan Pekerja (D + E ) 88,858.83

A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN


A.4.4.2.3 Pemasangan 1m2 Plesteran 1SP : 3PP tebal 15 mm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.300 80,400.00 24,120.00
Tukang Batu L.02 OH 0.150 80,500.00 12,075.00
Kepala Tukang L.03 OH 0.015 80,600.00 1,209.00
Mandor L.04 OH 0.015 80,700.00 1,210.50
JUMLAH TENAGA KERJA 38,614.50
B BAHAN
PC / Portland cement kg 7.776 1,000.00 7,776.00
Pasir pasang / beton m3 0.023 90,000.00 2,070.00
JUMLAH HARGA BAHAN 9,846.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 48,460.50
E Overhead & Profit ...... % x D 969.21
F Harga Satuan Pekerja (D + E ) 49,429.71
A.4.4.2.5 Pemasangan 1m2 Plesteran 1SP : 5PP tebal 15 mm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.300 80,400.00 24,120.00
Tukang Batu L.02 OH 0.150 80,500.00 12,075.00
Kepala Tukang L.03 OH 0.015 80,600.00 1,209.00
Mandor L.04 OH 0.015 80,700.00 1,210.50
JUMLAH TENAGA KERJA 38,614.50
B BAHAN
PC / Portland cement kg 5.184 1,000.00 5,184.00
Pasir pasang / beton m3 0.026 90,000.00 2,340.00
JUMLAH HARGA BAHAN 7,524.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 46,138.50
E Overhead & Profit ...... % x D 922.77
F Harga Satuan Pekerja (D + E ) 47,061.27

14
A.4.4.2.27 Pemasangan 1m2 Acian
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.200 80,400.00 16,080.00
Tukang Batu L.02 OH 0.100 80,500.00 8,050.00
Kepala Tukang L.03 OH 0.010 80,600.00 806.00
Mandor L.04 OH 0.010 80,700.00 807.00
JUMLAH TENAGA KERJA 25,743.00
B BAHAN
PC / Portland cement kg 3.250 1,000.00 3,250.00
JUMLAH HARGA BAHAN 3,250.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah( A + B + C ) 28,993.00
E Overhead & Profit ...... % x D 579.86
F Harga Satuan Pekerja (D + E ) 29,572.86
A.4.4.2.27a 1m' Benangan
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.015 80,400.00 1,206.00
Tukang Batu L.02 OH 0.050 80,500.00 4,025.00
JUMLAH TENAGA KERJA 5,231.00
B BAHAN
PC / Portland cement kg 3.750 1,000.00 3,750.00
Pasir pasang / beton m3 0.030 90,000.00 2,700.00
JUMLAH HARGA BAHAN 6,450.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 11,681.00
E Overhead & Profit ...... % x D 233.62
F Harga Satuan Pekerja (D + E ) 11,914.62

A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING


A.4.4.3.4 Pemasangan 1m2 lantai keramik motif ukuran 40 cm x 40 cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.700 80,400.00 56,280.00
Tukang Batu L.02 OH 0.350 80,500.00 28,175.00
Kepala Tukang L.03 OH 0.035 80,600.00 2,821.00
Mandor L.04 OH 0.035 80,700.00 2,824.50
JUMLAH TENAGA KERJA 90,100.50
B BAHAN
Keramik motif Uk. 40 cm x 40 cm M2 1.0608 36,000.00 38,188.80
PC / Portland cement kg 10.000 1,000.00 10,000.00
Pasir pasang / beton m3 0.045 90,000.00 4,050.00
Semen Putih / warna kg 1.500 2,100.00 3,150.00
JUMLAH HARGA BAHAN 55,388.80
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 145,489.30
E Overhead & Profit ...... % x D 2,909.79
F Harga Satuan Pekerja (D + E ) 148,399.09
A.4.4.3.4b Pemasangan 1m2 lantai keramik ukuran 40 cm x 40 cm tekstur
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.700 80,400.00 56,280.00
Tukang Batu L.02 OH 0.350 80,500.00 28,175.00
Kepala Tukang L.03 OH 0.035 80,600.00 2,821.00
Mandor L.04 OH 0.035 80,700.00 2,824.50
JUMLAH TENAGA KERJA 90,100.50
B BAHAN
Keramik tekstur Uk. 40 cm x 40 cm M2 1.0608 42,000.00 44,553.60
PC / Portland cement kg 10.000 1,000.00 10,000.00
Pasir pasang / beton m3 0.045 90,000.00 4,050.00
Semen Putih / warna kg 1.500 2,100.00 3,150.00
JUMLAH HARGA BAHAN 61,753.60
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 151,854.10
E Overhead & Profit ...... % x D 3,037.08
F Harga Satuan Pekerja (D + E ) 154,891.18

15
A.4.4.3.35b Pemasangan 1m2 lantai keramik ukuran 30 cm x 30 cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.700 80,400.00 56,280.00
Tukang Batu L.02 OH 0.350 80,500.00 28,175.00
Kepala Tukang L.03 OH 0.035 80,600.00 2,821.00
Mandor L.04 OH 0.035 80,700.00 2,824.50
JUMLAH TENAGA KERJA 90,100.50
B BAHAN
Keramik putih Uk. 30 cm x 30 cm m2 1.0683 36,000.00 38,458.80
PC / Portland cement kg 10.0000 1,000.00 10,000.00
Pasir pasang / beton m3 0.0450 90,000.00 4,050.00
Semen Putih / warna kg 1.5000 2,100.00 3,150.00
JUMLAH HARGA BAHAN 55,658.80
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 145,759.30
E Overhead & Profit ...... % x D 2,915.19
F Harga Satuan Pekerja (D + E ) 148,674.49
A.4.4.3.37 Pemasangan 1m2 lantai keramik ukuran 25 cm x 25 cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.700 80,400.00 56,280.00
Tukang Batu L.02 OH 0.350 80,500.00 28,175.00
Kepala Tukang L.03 OH 0.035 80,600.00 2,821.00
Mandor L.04 OH 0.035 80,700.00 2,824.50
JUMLAH TENAGA KERJA 90,100.50
B BAHAN
Keramik tekstur Uk. 25 cm x 25 cm m2 1.060 42,000.00 44,520.00
PC / Portland cement kg 10.400 1,000.00 10,400.00
Pasir pasang / beton m3 0.045 90,000.00 4,050.00
Semen Putih / warna kg 1.620 2,100.00 3,402.00
JUMLAH HARGA BAHAN 62,372.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 152,472.50
E Overhead & Profit ...... % x D 3,049.45
F Harga Satuan Pekerja (D + E ) 155,521.95
A.4.4.3.39 Pemasangan 1m' plint keramik ukuran 10 cm x 40 cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.090 80,400.00 7,236.00
Tukang Batu L.02 OH 0.090 80,500.00 7,245.00
Kepala Tukang L.03 OH 0.035 80,600.00 2,821.00
Mandor L.04 OH 0.005 80,700.00 403.50
JUMLAH TENAGA KERJA 17,705.50
B BAHAN
List Keramik (10x40)cm m' 1.10 12,000.00 13,200.00
PC / Portland cement kg 1.240 1,000.00 1,240.00
Pasir pasang / beton m3 0.003 90,000.00 270.00
JUMLAH HARGA BAHAN 14,710.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 32,415.50
E Overhead & Profit ...... % x D 648.31
F Harga Satuan Pekerja (D + E ) 33,063.81
A.4.4.3.54B Pemasangan 1m2 Dinding keramik ukuran 25 cm x 40 cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.900 80,400.00 72,360.00
Tukang Batu L.02 OH 0.450 80,500.00 36,225.00
Kepala Tukang L.03 OH 0.045 80,600.00 3,627.00
Mandor L.04 OH 0.045 80,700.00 3,631.50
JUMLAH TENAGA KERJA 115,843.50
B BAHAN
Keramik dinding 25 x 40 cm m2 1.060 39,000.00 41,340.00
PC / Portland cement kg 9.300 1,000.00 9,300.00
Pasir pasang / beton m3 0.018 90,000.00 1,620.00
Semen Putih / warna kg 1.940 2,100.00 4,074.00
JUMLAH HARGA BAHAN 56,334.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 172,177.50
E Overhead & Profit ...... % x D 3,443.55
F Harga Satuan Pekerja (D + E ) 175,621.05

16
A.4.4.3.58 Pemasangan 1m2 Dinding batu andesit bakar
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.900 80,400.00 72,360.00
Tukang Batu L.02 OH 0.450 80,500.00 36,225.00
Kepala Tukang L.03 OH 0.045 80,600.00 3,627.00
Mandor L.04 OH 0.045 80,700.00 3,631.50
JUMLAH TENAGA KERJA 115,843.50
B BAHAN
Batu andesit bakar m2 1.060 125,000.00 132,500.00
PC / Portland cement kg 9.300 1,000.00 9,300.00
Pasir pasang / beton m3 0.018 90,000.00 1,620.00
Semen Putih / warna kg 1.940 2,100.00 4,074.00
JUMLAH HARGA BAHAN 147,494.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 263,337.50
E Overhead & Profit ...... % x D 5,266.75
F Harga Satuan Pekerja (D + E ) 268,604.25
A.4.4.3.58d Pemasangan 1m2 Paving tebal 6 cm k225
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.250 80,400.00 20,100.00
Tukang batu L.02 OH 0.500 80,500.00 40,250.00
Kepala Tukang L.03 OH 0.050 80,600.00 4,030.00
Mandor L.04 OH 0.00130 80,700.00 104.91
JUMLAH TENAGA KERJA 64,484.91
B BAHAN
Paving Stone abu - abu t= 6 cm, K225 m2 1.100 42,000.00 46,200.00
Pasir pasang / beton m3 0.035 90,000.00 3,150.00
JUMLAH HARGA BAHAN 49,350.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 113,834.91
E Overhead & Profit ...... % x D 2,276.70
F Harga Satuan Pekerja (D + E ) 116,111.61

A.4.4.3.58e Pemasangan 1m' Topi uskup/ stoper K225 tebal 6 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.200 80,400.00 16,080.00
Tukang batu L.02 OH 0.100 80,500.00 8,050.00
JUMLAH TENAGA KERJA 24,130.00

B BAHAN
Topi uskup/ stoper bh 3.340 65,000.00 217,100.00
Pasir pasang / beton m3 0.001 90,000.00 90.00
JUMLAH HARGA BAHAN 217,190.00

C PERALATAN
JUMLAH HARGA ALAT

D Jumlah( A + B + C ) 241,320.00
E Overhead & Profit ...... % x D 4,826.40
F Harga Satuan Pekerja (D + E ) 246,146.40

A.4.4.3.59 Pemasangan 1m2 rangka besi hollow dinding partisi


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.250 80,400.00 20,100.00
Tukang besi L.02 OH 0.250 80,500.00 20,125.00
Kepala Tukang L.03 OH 0.025 80,600.00 2,015.00
Mandor L.04 OH 0.013 80,700.00 1,049.10
JUMLAH TENAGA KERJA 43,289.10

B BAHAN
Pipa Besi  4/4 Tebal= 1.4 mm m' 3.500 24,166.67 84,583.33
Assesoris (perkuatan,las dll) ls 1.000 5,000.00 5,000.00
JUMLAH HARGA BAHAN 89,583.33

C PERALATAN
JUMLAH HARGA ALAT

D Jumlah( A + B + C ) 132,872.43
E Overhead & Profit ...... % x D 2,657.45
F Harga Satuan Pekerja (D + E ) 135,529.88

17
A.4.5.1 SATUAN PEKERJAAN LANGIT - LANGIT ( PLAFOND)
A.4.5.1.7 Pemasangan 1m2 langit langit gypsum board (120x240x9)mm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.100 80,400.00 8,040.00
Tukang Kayu L.02 OH 0.050 80,500.00 4,025.00
Kepala Tukang L.03 OH 0.005 80,600.00 403.00
Mandor L.04 OH 0.005 80,700.00 403.50
JUMLAH TENAGA KERJA 12,871.50
B BAHAN
Gypsum board tebal 9mm ( 1,2 x 2,4 m ) lbr 0.364 65,000.00 23,660.00
Paku Asbes kg 0.110 15,000.00 1,650.00
JUMLAH HARGA BAHAN 25,310.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 38,181.50
E Overhead & Profit ...... % x D 763.63
F Harga Satuan Pekerja (D + E ) 38,945.13
A.4.5.1.7A Pemasangan 1m2 langit langit Calsy board ( uk. 122 x 244 x 0.3 cm )
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.100 80,400.00 8,040.00
Tukang Kayu L.02 OH 0.050 80,500.00 4,025.00
Kepala Tukang L.03 OH 0.005 80,600.00 403.00
Mandor L.04 OH 0.005 80,700.00 403.50
JUMLAH TENAGA KERJA 12,871.50
B BAHAN
Calsy bord ( uk. 122 x 244 x 0.3 cm ) lbr 0.364 65,000.00 23,660.00
Paku kalsiboard kg 0.110 15,000.00 1,650.00
JUMLAH HARGA BAHAN 25,310.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 38,181.50
E Overhead & Profit ...... % x D 763.63
F Harga Satuan Pekerja (D + E ) 38,945.13

A.4.5.2 HARGA SATUAN PEKERJAAN ATAP


A.4.5.2.1 Pemasangan 1m2 atap genteng mantili
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.150 80,400.00 12,060.00
Tukang kayu L.02 OH 0.075 80,500.00 6,037.50
Kepala Tukang L.03 OH 0.0075 80,600.00 604.50
Mandor L.04 OH 0.008 80,700.00 645.60
JUMLAH TENAGA KERJA 19,347.60
B BAHAN
Genteng mantili bh 25.000 2,000.00 50,000.00
JUMLAH HARGA BAHAN 50,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 69,347.60
E Overhead & Profit ...... % x D 1,386.95
F Harga Satuan Pekerja (D + E ) 70,734.55
A.4.5.2.4 Pemasangan 1m' bubung
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.400 80,400.00 32,160.00
Tukang Batu L.02 OH 0.200 80,500.00 16,100.00
Kepala Tukang L.03 OH 0.0200 80,600.00 1,612.00
Mandor L.04 OH 0.002 80,700.00 161.40
JUMLAH TENAGA KERJA 50,033.40
B BAHAN
Genteng bubung Mantili ex. Trenggalek / Tulungagung bh 4.000 5,000.00 20,000.00
PC / Portland cement kg 8.000 1,000.00 8,000.00
Pasir pasang / beton m3 0.032 90,000.00 2,880.00
JUMLAH HARGA BAHAN 30,880.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 80,913.40
E Overhead & Profit ...... % x D 1,618.27
F Harga Satuan Pekerja (D + E ) 82,531.67

18
A.4.6.1 HARGA SATUAN PEKERJAAN KAYU
A.4.6.1.2 Pembuatan dan Pemasangan 1m3 kusen pintu dan jendela Kayu Balau
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 7.000 80,400.00 562,800.00
Tukang Kayu L.02 OH 21.000 80,500.00 1,690,500.00
Kepala Tukang L.03 OH 2.100 80,600.00 169,260.00
Mandor L.04 OH 0.350 80,700.00 28,245.00
JUMLAH TENAGA KERJA 2,450,805.00
B BAHAN
Kayu Balau Balok m3 1.100 10,000,000.00 11,000,000.00
Paku biasa kg 1.250 15,000.00 18,750.00
Lem ( Kayu + Tembok ) kg 1.000 15,000.00 15,000.00
JUMLAH HARGA BAHAN 11,033,750.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 13,484,555.00
E Overhead & Profit ...... % x D 269,691.10
F Harga Satuan Pekerja (D + E ) 13,754,246.10
A.4.6.1.5b Pembuatan dan Pemasangan 1m2 daun pintu panil Kayu Balau
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 1.000 80,400.00 80,400.00
Tukang Kayu L.02 OH 3.000 80,500.00 241,500.00
Kepala Tukang L.03 OH 0.300 80,600.00 24,180.00
Mandor L.04 OH 0.050 80,700.00 4,035.00
JUMLAH TENAGA KERJA 350,115.00
B BAHAN
Kayu Balau Papan m3 0.040 12,000,000.00 480,000.00
Lem ( Kayu + Tembok ) kg 0.050 15,000.00 750.00
JUMLAH HARGA BAHAN 480,750.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 830,865.00
E Overhead & Profit ...... % x D 16,617.30
F Harga Satuan Pekerja (D + E ) 847,482.30
A.4.6.1.6b Pembuatan dan Pemasangan 1m2 daun pintu dan jendela Kaca Kayu Balau
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.800 80,400.00 64,320.00
Tukang Kayu L.02 OH 2.400 80,500.00 193,200.00
Kepala Tukang L.03 OH 0.240 80,600.00 19,344.00
Mandor L.04 OH 0.040 80,700.00 3,228.00
JUMLAH TENAGA KERJA 280,092.00
B BAHAN
Kayu Balau Papan m3 0.024 12,000,000.00 288,000.00
Lem ( Kayu + Tembok ) kg 0.300 15,000.00 4,500.00
JUMLAH HARGA BAHAN 292,500.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 572,592.00
E Overhead & Profit ...... % x D 11,451.84
F Harga Satuan Pekerja (D + E ) 584,043.84
A.4.6.1.13 Pemasangan 1m3 konstruksi kuda-kuda kayu kruing
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 4.000 80,400.00 321,600.00
Tukang Kayu L.02 OH 12.000 80,500.00 966,000.00
Kepala Tukang L.03 OH 1.200 80,600.00 96,720.00
Mandor L.04 OH 0.200 80,700.00 16,140.00
JUMLAH TENAGA KERJA 1,400,460.00
B BAHAN
Kayu Kruing Balok m3 1.100 7,000,000.00 7,700,000.00
Besi Beugel/Baut kg 15.000 17,000.00 255,000.00
Paku biasa kg 5.600 15,000.00 84,000.00
JUMLAH HARGA BAHAN 8,039,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 9,439,460.00
E Overhead & Profit ...... % x D 188,789.20
F Harga Satuan Pekerja (D + E ) 9,628,249.20

19
A.4.6.1.15 Pemasangan 1m3 konstruksi gording kayu kruing
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 6.700 80,400.00 538,680.00
Tukang Kayu L.02 OH 20.100 80,500.00 1,618,050.00
Kepala Tukang L.03 OH 2.010 80,600.00 162,006.00
Mandor L.04 OH 0.335 80,700.00 27,034.50
JUMLAH TENAGA KERJA 2,345,770.50
B BAHAN
Kayu Kruing Balok m3 1.100 7,000,000.00 7,700,000.00
Besi Beugel/Baut kg 15.000 17,000.00 255,000.00
Paku biasa kg 3.000 15,000.00 45,000.00
JUMLAH HARGA BAHAN 8,000,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 10,345,770.50
E Overhead & Profit ...... % x D 206,915.41
F Harga Satuan Pekerja (D + E ) 10,552,685.91

A.4.6.1.15b Pemasangan 1m3 konstruksi gording kayu kruing


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 6.700 - -
Tukang Kayu L.02 OH 20.100 - -
Kepala Tukang L.03 OH 2.010 - -
Mandor L.04 OH 0.335 - -
JUMLAH TENAGA KERJA -
B BAHAN
Kayu Kruing Balok m3 1.100 -
Besi Beugel/Baut kg 15.000 -
Paku biasa kg 3.000 -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) -
E Overhead & Profit ...... % x D -
F Harga Satuan Pekerja (D + E ) -

A.4.6.1.16 Pemasangan 1m2 usuk + reng Kayu Kruing


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.100 - -
Tukang Kayu L.02 OH 0.100 - -
Kepala Tukang L.03 OH 0.010 - -
Mandor L.04 OH 0.005 - -
JUMLAH TENAGA KERJA -
B BAHAN
Kayu Kruing Balok m3 0.014 - -
Kayu Kruing Balok m3 0.0036 - -
Paku biasa kg 0.250 - -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) -
E Overhead & Profit ...... % x D -
F Harga Satuan Pekerja (D + E ) -

A.4.6.1.19a Pemasangan 1m2 rangka plafond modul 60 x 60 cm plafond metal furing


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.200 80,400.00 16,080.00
Tukang besi L.02 OH 0.300 80,500.00 24,150.00
Kepala Tukang L.03 OH 0.030 80,600.00 2,418.00
Mandor L.04 OH 0.010 80,700.00 807.00
JUMLAH TENAGA KERJA 43,455.00
B BAHAN
Rangka plafond metal furing m1 4.000 10,000.00 40,000.00
assesoris(perkuatan, dll) ls 0.200 16,500.00 3,300.00
JUMLAH HARGA BAHAN 43,300.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 86,755.00
E Overhead & Profit ...... % x D 1,735.10
F Harga Satuan Pekerja (D + E ) 88,490.10

20
A.4.6.1.24 Pemasangan 1m2 rangka dinding pemisah (60x120) besi C
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.650 80,400.00 52,260.00
Tukang Kayu L.02 OH 0.095 80,500.00 7,647.50
Kepala Tukang L.03 OH 0.010 80,600.00 765.70
Mandor L.04 OH 0.006 80,700.00 468.06
JUMLAH TENAGA KERJA 61,141.26
B BAHAN
Rangka partisi C m' 4.400 15,000.00 66,000.00
Besi Beugel/Baut kg 0.150 17,000.00 2,550.00
JUMLAH HARGA BAHAN 68,550.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 129,691.26
E Overhead & Profit ( maks 14 % ) ...... % x D 2,593.83
F Harga Satuan Pekerja (D + E ) 132,285.09

A.4.6.2 HARGA SATUAN PEKERJAAN PENGUNCI


A.4.6.2.2 Pemasangan 1 bh kunci tanam
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.060 80,400.00 4,824.00
Tukang Kayu L.02 OH 0.600 80,500.00 48,300.00
Kepala Tukang L.03 OH 0.060 80,600.00 4,836.00
Mandor L.04 OH 0.003 80,700.00 242.10
JUMLAH TENAGA KERJA 58,202.10
B BAHAN
Kunci tanam dekson bh 1.000 95,000.00 95,000.00
JUMLAH HARGA BAHAN 95,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 153,202.10
E Overhead & Profit ...... % x D 3,064.04
F Harga Satuan Pekerja (D + E ) 156,266.14
A.4.6.2.2b Pemasangan 1 set grendel tanam
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.010 80,400.00 804.00
Tukang Kayu L.02 OH 0.100 80,500.00 8,050.00
Kepala Tukang L.03 OH 0.010 80,600.00 806.00
Mandor L.04 OH 0.0005 80,700.00 40.35
JUMLAH TENAGA KERJA 9,700.35
B BAHAN
Grendel tanam merk SES bh 1.000 30,000.00 30,000.00
JUMLAH HARGA BAHAN 30,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 39,700.35
E Overhead & Profit ...... % x D 794.01
F Harga Satuan Pekerja (D + E ) 40,494.36
A.4.6.2.5 Pemasangan 1 bh engsel pintu 4''
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.015 80,400.00 1,206.00
Tukang Kayu L.02 OH 0.150 80,500.00 12,075.00
Kepala Tukang L.03 OH 0.015 80,600.00 1,209.00
Mandor L.04 OH 0.0008 80,700.00 64.56
JUMLAH TENAGA KERJA 14,554.56
B BAHAN
Engsel Pintu (Arch ) nylon bh 1.000 25,000.00 25,000.00
JUMLAH HARGA BAHAN 25,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 39,554.56
E Overhead & Profit ...... % x D 791.09
F Harga Satuan Pekerja (D + E ) 40,345.65

21
A.4.6.2.6 Pemasangan 1 bh engsel jendela 3''
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.010 80,400.00 804.00
Tukang Kayu L.02 OH 0.100 80,500.00 8,050.00
Kepala Tukang L.03 OH 0.010 80,600.00 806.00
Mandor L.04 OH 0.0005 80,700.00 40.35
JUMLAH TENAGA KERJA 9,700.35
B BAHAN
Engsel Jendela (Arch ) bh 1.000 15,000.00 15,000.00
JUMLAH HARGA BAHAN 15,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 24,700.35
E Overhead & Profit ...... % x D 494.01
F Harga Satuan Pekerja (D + E ) 25,194.36
A.4.6.2.7 Pemasangan 1 set hak angin
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.100 80,400.00 8,040.00
Tukang Kayu L.02 OH 0.200 80,500.00 16,100.00
Kepala Tukang L.03 OH 0.020 80,600.00 1,612.00
Mandor L.04 OH 0.0005 80,700.00 40.35
JUMLAH TENAGA KERJA 25,792.35
B BAHAN
Hak angin/sikutan Merk SES bh 1.000 35,000.00 35,000.00
JUMLAH HARGA BAHAN 35,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 60,792.35
E Overhead & Profit ...... % x D 1,215.85
F Harga Satuan Pekerja (D + E ) 62,008.20
A.4.6.2.8 Pemasangan 1 bh Grendel jendela
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.010 80,400.00 804.00
Tukang Kayu L.02 OH 0.100 80,500.00 8,050.00
Kepala Tukang L.03 OH 0.010 80,600.00 806.00
Mandor L.04 OH 0.0005 80,700.00 40.35
JUMLAH TENAGA KERJA 9,700.35
B BAHAN
Grendel jendela merk SES bh 1.000 30,000.00 30,000.00
JUMLAH HARGA BAHAN 30,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 39,700.35
E Overhead & Profit ...... % x D 794.01
F Harga Satuan Pekerja (D + E ) 40,494.36
A.4.6.2.11 Pemasangan 1 bh kunci selot ex ses
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.020 - -
Tukang Kayu L.02 OH 0.200 - -
Kepala Tukang L.03 OH 0.020 - -
Mandor L.04 OH 0.0010 - -
JUMLAH TENAGA KERJA -
B BAHAN
Selot ( kunci pintu ) merk SES bh 1.000 - -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) -
E Overhead & Profit ...... % x D -
F Harga Satuan Pekerja (D + E ) -

22
A.4.6.2.12d Pemasangan handle pintu stainless steel besar
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.050 80,400.00 4,020.00
Tukang Kayu L.02 OH 0.500 80,500.00 40,250.00
Kepala Tukang L.03 OH 0.050 80,600.00 4,030.00
Mandor L.04 OH 0.0030 80,700.00 242.10
JUMLAH TENAGA KERJA 48,542.10
B BAHAN
Handle pintu stanless 30 cm set 1.000 160,000.00 160,000.00
JUMLAH HARGA BAHAN 160,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 208,542.10
E Overhead & Profit ...... % x D 4,170.84
F Harga Satuan Pekerja (D + E ) 212,712.94
A.4.6.2.13 Pemasangan 1 bh door stop
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.010 - -
Tukang Kayu L.02 OH 0.100 - -
Kepala Tukang L.03 OH 0.010 - -
Mandor L.04 OH 0.0050 - -
JUMLAH TENAGA KERJA -
B BAHAN
Door Stoper Stainless bh 1.000 - -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) -
E Overhead & Profit ...... % x D -
F Harga Satuan Pekerja (D + E ) -

A.4.6.2.17 Pemasangan 1 m2 kaca tebal 5 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.015 80,400.00 1,206.00
Tukang Kayu L.02 OH 0.150 80,500.00 12,075.00
Kepala Tukang L.03 OH 0.015 80,600.00 1,209.00
Mandor L.04 OH 0.0008 80,700.00 64.56
JUMLAH TENAGA KERJA 14,554.56
B BAHAN
Kaca Bening t= 5 mm m2 1.100 75,000.00 82,500.00
Sealant kg 0.05 25,000.00 1,250.00
JUMLAH HARGA BAHAN 83,750.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 98,304.56
E Overhead & Profit ...... % x D 1,966.09
F Harga Satuan Pekerja (D + E ) 100,270.65

A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN


A.4.7.1.4 1m2 pengecatan bidang kayu baru (1lapis plamur, 1lapis cat dasar , 2 lapis cat penutup)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.070 80,400.00 5,628.00
Tukang cat L.02 OH 0.009 80,500.00 724.50
Kepala Tukang L.03 OH 0.006 80,600.00 483.60
Mandor L.04 OH 0.0030 80,700.00 242.10
JUMLAH TENAGA KERJA 7,078.20
B BAHAN
Cat Meny kayu kg 0.200 45,000.00 9,000.00
Plamur kayu kg 0.150 23,000.00 3,450.00
Cat Dasar Kayu kg 0.170 45,000.00 7,650.00
Cat Kayu kg 0.260 55,000.00 14,300.00
Kuas 3 " bh 0.010 9,500.00 95.00
Minyak Cat / Thiner B kg 0.030 22,500.00 675.00
Kertas gosok ( rempelas ) lbr 0.200 3,500.00 700.00
JUMLAH HARGA BAHAN 35,870.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 42,948.20
E Overhead & Profit ...... % x D 858.96
F Harga Satuan Pekerja (D + E ) 43,807.16

23
A.4.7.1.10 1m2 pengecatan tembok baru (1lapis plamur, 1lapis cat dasar , 2 lapis cat penutup)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.020 80,400.00 1,608.00
Tukang cat L.02 OH 0.063 80,500.00 5,071.50
Kepala Tukang L.03 OH 0.0063 80,600.00 507.78
Mandor L.04 OH 0.0030 80,700.00 242.10
JUMLAH TENAGA KERJA 7,429.38
B BAHAN
Plamur Tembok kg 0.100 15,000.00 1,500.00
Cat Tembok kg 0.100 20,000.00 2,000.00
Cat Tembok kg 0.260 20,000.00 5,200.00
JUMLAH HARGA BAHAN 8,700.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 16,129.38
E Overhead & Profit ...... % x D 322.59
F Harga Satuan Pekerja (D + E ) 16,451.97

A.4.7.1.10b 1m2 pengecatan tembok baru (1lapis plamur, 1lapis cat dasar , 2 lapis cat penutup)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.020 80,400.00 1,608.00
Tukang cat L.02 OH 0.063 80,500.00 5,071.50
Kepala Tukang L.03 OH 0.0063 80,600.00 507.78
Mandor L.04 OH 0.0030 80,700.00 242.10
JUMLAH TENAGA KERJA 7,429.38
B BAHAN
Plamur Tembok kg 0.100 15,000.00 1,500.00
Cat Tembok interior premium kg 0.100 23,000.00 2,300.00
Cat Tembok interior premium kg 0.260 23,000.00 5,980.00
JUMLAH HARGA BAHAN 9,780.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 17,209.38
E Overhead & Profit ...... % x D 344.19
F Harga Satuan Pekerja (D + E ) 17,553.57
A.4.7.1.10c 1m2 pengecatan tembok baru (1lapis plamur, 1lapis cat dasar , 2 lapis cat penutup)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.020 80,400.00 1,608.00
Tukang cat L.02 OH 0.063 80,500.00 5,071.50
Kepala Tukang L.03 OH 0.0063 80,600.00 507.78
Mandor L.04 OH 0.0030 80,700.00 242.10
JUMLAH TENAGA KERJA 7,429.38
B BAHAN
Plamur Tembok kg 0.100 15,000.00 1,500.00
Cat Tembok exterior wheathershield kg 0.100 28,000.00 2,800.00
Cat Tembok exterior wheathershield kg 0.260 28,000.00 7,280.00
JUMLAH HARGA BAHAN 11,580.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 19,009.38
E Overhead & Profit ...... % x D 380.19
F Harga Satuan Pekerja (D + E ) 19,389.57
A.4.7.1.11 1m2 pengecatan tembok lama (1lapis cat dasar , 2 lapis cat penutup)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.028 80,400.00 2,251.20
Tukang cat L.02 OH 0.042 80,500.00 3,381.00
Kepala Tukang L.03 OH 0.0042 80,600.00 338.52
Mandor L.04 OH 0.0030 80,700.00 242.10
JUMLAH TENAGA KERJA 6,212.82
B BAHAN
Cat Tembok interior premium kg 0.120 23,000.00 2,760.00
Cat Tembok interior premium kg 0.180 23,000.00 4,140.00
JUMLAH HARGA BAHAN 6,900.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 13,112.82
E Overhead & Profit ...... % x D 262.26
F Harga Satuan Pekerja (D + E ) 13,375.08

24
A.4.7.1.10d 1m2 pengecatan Langit langit ( plafond )
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.020 80,400.00 1,608.00
Tukang cat L.02 OH 0.063 80,500.00 5,071.50
Kepala Tukang L.03 OH 0.0063 80,600.00 507.78
Mandor L.04 OH 0.0030 80,700.00 242.10
JUMLAH TENAGA KERJA 7,429.38
B BAHAN
Cat Tembok kg 0.100 20,000.00 2,000.00
Cat Tembok kg 0.260 20,000.00 5,200.00
JUMLAH HARGA BAHAN 7,200.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 14,629.38
E Overhead & Profit ...... % x D 292.59
F Harga Satuan Pekerja (D + E ) 14,921.97

A.4.7.1.12 10 m2 melabur kayu dengan melamine


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 2.000 - -
Tukang cat L.02 OH 12.000 - -
Kepala Tukang L.03 OH 1.200 - -
Mandor L.04 OH 0.100 - -
JUMLAH TENAGA KERJA -
B BAHAN
Sending impra ( melamine) Ltr 2.400 - -
Wood filler impra ( dempul jati ) Kg 1.500 - -
Kertas gosok ( rempelas ) lbr 6.000 - -
Minyak Cat / Thiner A Liter 2.000 - -
Wood stain impra ( Pewarna melamine) Ltr 1.500 - -
Clear melamin impra dof / gloos Ltr 1.500 - -
JUMLAH HARGA BAHAN -
C PERALATAN
sewa air compresor 0.05 - -
JUMLAH HARGA ALAT -
D Jumlah( A + B + C ) -
E Overhead & Profit ...... % x D -
F Harga Satuan Pekerja (D + E ) -

A.4.7.1.10c 1m2 Pelapisan Aquaproof


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.020 80,400.00 1,608.00
Tukang cat L.02 OH 0.063 80,500.00 5,071.50
Kepala Tukang L.03 OH 0.0063 80,600.00 507.78
Mandor L.04 OH 0.0030 80,700.00 242.10
JUMLAH TENAGA KERJA 7,429.38
B BAHAN
Aquaproof kg 0.260 65,000.00 16,900.00
Kuas 3 " bh 0.100 9,500.00 950.00
JUMLAH HARGA BAHAN 17,850.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 25,279.38
E Overhead & Profit ...... % x D 505.59
F Harga Satuan Pekerja (D + E ) 25,784.97
A.4.7.1.12b 1m2 couting batu hias
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.050 80,400.00 4,020.00
Tukang cat L.02 OH 0.075 80,500.00 6,037.50
Kepala Tukang L.03 OH 0.008 80,600.00 644.80
Mandor L.04 OH 0.003 80,700.00 242.10
JUMLAH TENAGA KERJA 10,944.40
B BAHAN
Coatting kg 0.350 65,000.00 22,750.00
HCL / air keras ltr 0.160 15,000.00 2,400.00
JUMLAH HARGA BAHAN 25,150.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 36,094.40
E Overhead & Profit ...... % x D 721.89
F Harga Satuan Pekerja (D + E ) 36,816.29

25
A.4.7.1.12c 1m2 Pengecatan genteng
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.0280 - -
Tukang cat L.02 OH 0.0420 - -
Kepala Tukang L.03 OH 0.0042 - -
Mandor L.04 OH 0.0025 - -
JUMLAH TENAGA KERJA -
B BAHAN
Cat genteng kg 0.120 - -
Cat genteng ltr 0.180 - -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) -
E Overhead & Profit ...... % x D -
F Harga Satuan Pekerja (D + E ) -

A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG


A.5.1.1.1 Pemasangan 1 bh closet duduk / monoblok
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 3.300 80,400.00 265,320.00
Tukang Batu L.02 OH 1.100 80,500.00 88,550.00
Kepala Tukang L.03 OH 0.0100 80,600.00 806.00
Mandor L.04 OH 0.1600 80,700.00 12,912.00
JUMLAH TENAGA KERJA 367,588.00
B BAHAN
Kloset Duduk Keramik Komplit ex.TOTO bh 1.000 1,250,000.00 1,250,000.00
Perlengkapan Ls 6 % x closed 1,250,000.00 75,000.00
JUMLAH HARGA BAHAN 1,325,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 1,692,588.00
E Overhead & Profit ...... % x D 33,851.76
F Harga Satuan Pekerja (D + E ) 1,726,439.76
A.5.1.1.2 Pemasangan 1 bh closet Jongkok porselin
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 1.000 - -
Tukang Batu L.02 OH 1.500 - -
Kepala Tukang L.03 OH 0.1500 - -
Mandor L.04 OH 0.1600 - -
JUMLAH TENAGA KERJA -
B BAHAN
Kloset Jongkok Keramik ex.INA bh 1.000 - -
PC / Portland cement kg 6.000 - -
Pasir pasang / beton m3 0.100 - -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) -
E Overhead & Profit ...... % x D -
F Harga Satuan Pekerja (D + E ) -
A.5.1.1.4 Pemasangan 1 bh urinoir
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 1.000 - -
Tukang Batu L.02 OH 1.000 - -
Kepala Tukang L.03 OH 0.1000 - -
Mandor L.04 OH 0.0500 - -
JUMLAH TENAGA KERJA -
B BAHAN
Urinoir kg 1.000 - -
PC / Portland cement kg 6.000 - -
Pasir pasang / beton m3 0.010 - -
Perlengkapan % 30.000 - -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) -
E Overhead & Profit ...... % x D -
F Harga Satuan Pekerja (D + E ) -

26
A.5.1.1.5 Pemasangan 1 bh wastafel
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 1.200 80,400.00 96,480.00
Tukang Batu L.02 OH 1.450 80,500.00 116,725.00
Kepala Tukang L.03 OH 0.1500 80,600.00 12,090.00
Mandor L.04 OH 0.0600 80,700.00 4,842.00
JUMLAH TENAGA KERJA 230,137.00
B BAHAN
Wastafel amstad Bh 1.200 500,000.00 600,000.00
PC / Portland cement kg 6.000 1,000.00 6,000.00
Pasir pasang / beton m3 0.010 90,000.00 900.00
Perlengkapan % 20.000 500,000.00 100,000.00
JUMLAH HARGA BAHAN 706,900.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 937,037.00
E Overhead & Profit ...... % x D 18,740.74
F Harga Satuan Pekerja (D + E ) 955,777.74
A.5.1.1.12 Pemasangan 1 bh bak cuci piring stainlesssteel
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.030 80,400.00 2,412.00
Tukang Batu L.02 OH 0.300 80,500.00 24,150.00
Kepala Tukang L.03 OH 0.0300 80,600.00 2,418.00
Mandor L.04 OH 0.0150 80,700.00 1,210.50
JUMLAH TENAGA KERJA 30,190.50
B BAHAN
Bak Cuci Stainlesstel (Royal) unit 1.000 200,000.00 200,000.00
Kran cucian dia 1/2" bh 1.000 275,000.00 275,000.00
JUMLAH HARGA BAHAN 475,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 505,190.50
E Overhead & Profit ...... % x D 10,103.81
F Harga Satuan Pekerja (D + E ) 515,294.31
A.5.1.1.14 Pemasangan 1 bh floor drain stainlees steel
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.010 80,400.00 804.00
Tukang Batu L.02 OH 0.100 80,500.00 8,050.00
Kepala Tukang L.03 OH 0.0100 80,600.00 806.00
Mandor L.04 OH 0.0050 80,700.00 403.50
JUMLAH TENAGA KERJA 10,063.50
B BAHAN
Avor staninlees steel unit 1.000 45,000.00 45,000.00
JUMLAH HARGA BAHAN 45,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 55,063.50
E Overhead & Profit ...... % x D 1,101.27
F Harga Satuan Pekerja (D + E ) 56,164.77
A.5.1.1.14b Pemasangan 1 bh floor drain
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.010 - -
Tukang Batu L.02 OH 0.100 - -
Kepala Tukang L.03 OH 0.0100 - -
Mandor L.04 OH 0.0050 - -
JUMLAH TENAGA KERJA -
B BAHAN
Avor plastik / floor drain unit 1.000 - -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) -
E Overhead & Profit ...... % x D -
F Harga Satuan Pekerja (D + E ) -

27
A.5.1.1.15 Pemasangan 1 bh bak kontrol pasangan bata 30 x30 tinggi 35 cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 2.160 80,400.00 173,664.00
Tukang Batu L.02 OH 0.720 80,500.00 57,960.00
Kepala Tukang L.03 OH 0.0720 80,600.00 5,803.20
Mandor L.04 OH 0.0011 80,700.00 88.77
JUMLAH TENAGA KERJA 237,515.97
B BAHAN
Batu Bata / Merah bh 40.000 560.00 22,400.00
PC / Portland cement kg 44.000 1,000.00 44,000.00
Pasir pasang / beton m3 0.070 90,000.00 6,300.00
Pasir pasang / beton m3 0.060 90,000.00 5,400.00
Batu pecah 2-3 cm m3 0.070 155,000.00 10,850.00
Besi Beton / tulangan beton kg 1.600 9,000.00 14,400.00
JUMLAH HARGA BAHAN 103,350.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 340,865.97
E Overhead & Profit ...... % x D 6,817.32
F Harga Satuan Pekerja (D + E ) 347,683.29
A.5.1.1.16 Pemasangan 1 bh bak kontrol pasangan bata 45 x45 tinggi 50 cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 3.200 - -
Tukang Batu L.02 OH 1.150 - -
Kepala Tukang L.03 OH 0.0110 - -
Mandor L.04 OH 0.0160 - -
JUMLAH TENAGA KERJA -
B BAHAN
Batu Bata / Merah bh 70.000 - -
PC / Portland cement kg 77.000 - -
Pasir pasang / beton m3 0.130 - -
Pasir pasang / beton m3 0.090 - -
Batu pecah 2-3 cm m3 0.020 - -
Besi Beton / tulangan beton kg 2.600 - -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) -
E Overhead & Profit ...... % x D -
F Harga Satuan Pekerja (D + E ) -

A.5.1.1.16 Pemasangan 1 bh kran diameter 1/2 ''


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.010 80,400.00 804.00
Tukang Pipa L.02 OH 0.400 80,500.00 32,200.00
Kepala Tukang L.03 OH 0.0400 80,600.00 3,224.00
Mandor L.04 OH 0.0050 80,700.00 403.50
JUMLAH TENAGA KERJA 36,631.50
B BAHAN
Kran Dia 1/2 " stainless steel bh 1.000 40,000.00 40,000.00
Seal tape kg 0.003 4,500.00 11.25
JUMLAH HARGA BAHAN 40,011.25
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 76,642.75
E Overhead & Profit ...... % x D 1,532.86
F Harga Satuan Pekerja (D + E ) 78,175.61
A.5.1.1.16b Pemasangan 1 bh kran diameter 3/4 ''
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.010 - -
Tukang Pipa L.02 OH 0.400 - -
Kepala Tukang L.03 OH 0.0400 - -
Mandor L.04 OH 0.0050 - -
JUMLAH TENAGA KERJA -
B BAHAN
Kran Dia 3/4 " stainless steel bh 1.000 - -
Seal tape kg 0.003 - -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) -
E Overhead & Profit JUMLAH HARGA BAHAN -
F Harga Satuan Pekerja (D + E ) -

28
A.5.1.1.25 Pemasangan 1 m' pipa pvc type AW diameter 1/2''
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.036 80,400.00 2,894.40
Tukang Pipa L.02 OH 0.060 80,500.00 4,830.00
Kepala Tukang L.03 OH 0.0060 80,600.00 483.60
Mandor L.04 OH 0.0020 80,700.00 161.40
JUMLAH TENAGA KERJA 8,369.40
B BAHAN
PVC AW Dia 0.5 " ( abu - abu ) bh 1.200 2,400.00 2,880.00
perlengkapan % 35.000 2,400.00 840.00
JUMLAH HARGA BAHAN 3,720.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 12,089.40
E Overhead & Profit ...... % x D 241.79
F Harga Satuan Pekerja (D + E ) 12,331.19
A.5.1.1.28 Pemasangan 1 m' pipa pvc type AW diameter 1.5''
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.054 80,400.00 4,341.60
Tukang Pipa L.02 OH 0.090 80,500.00 7,245.00
Kepala Tukang L.03 OH 0.0090 80,600.00 725.40
Mandor L.04 OH 0.0030 80,700.00 242.10
JUMLAH TENAGA KERJA 12,554.10
B BAHAN
PVC AW Dia 1,5 " ( abu - abu ) bh 1.200 6,500.00 7,800.00
perlengkapan % 35.000 6,500.00 2,275.00
JUMLAH HARGA BAHAN 10,075.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 22,629.10
E Overhead & Profit ...... % x D 452.58
F Harga Satuan Pekerja (D + E ) 23,081.68

A.5.1.1.30 Pemasangan 1 m' pipa pvc type AW diameter 2.5''


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.081 80,400.00 6,512.40
Tukang Pipa L.02 OH 0.135 80,500.00 10,867.50
Kepala Tukang L.03 OH 0.0135 80,600.00 1,088.10
Mandor L.04 OH 0.0040 80,700.00 322.80
JUMLAH TENAGA KERJA 18,790.80
B BAHAN
PVC AW Dia 2 ,5" ( abu - abu ) bh 1.200 15,000.00 18,000.00
perlengkapan % 35.000 15,000.00 5,250.00
JUMLAH HARGA BAHAN 23,250.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 42,040.80
E Overhead & Profit ...... % x D 840.82
F Harga Satuan Pekerja (D + E ) 42,881.62
A.5.1.1.31 Pemasangan 1 m' pipa pvc type AW diameter 3''
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.081 80,400.00 6,512.40
Tukang Pipa L.02 OH 0.135 80,500.00 10,867.50
Kepala Tukang L.03 OH 0.0135 80,600.00 1,088.10
Mandor L.04 OH 0.0040 80,700.00 322.80
JUMLAH TENAGA KERJA 18,790.80
B BAHAN
PVC AW Dia 3 " ( abu - abu ) bh 1.200 20,000.00 24,000.00
perlengkapan % 35.000 20,000.00 7,000.00
JUMLAH HARGA BAHAN 31,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 49,790.80
E Overhead & Profit ...... % x D 995.82
F Harga Satuan Pekerja (D + E ) 50,786.62

29
A.5.1.1.32 Pemasangan 1 m' pipa pvc type AW diameter 4''
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.081 80,400.00 6,512.40
Tukang Pipa L.02 OH 0.135 80,500.00 10,867.50
Kepala Tukang L.03 OH 0.0135 80,600.00 1,088.10
Mandor L.04 OH 0.0040 80,700.00 322.80
JUMLAH TENAGA KERJA 18,790.80
B BAHAN
PVC AW Dia 4 " ( abu - abu ) bh 1.200 25,000.00 30,000.00
perlengkapan % 35.000 25,000.00 8,750.00
JUMLAH HARGA BAHAN 38,750.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah( A + B + C ) 57,540.80
E Overhead & Profit ...... % x D 1,150.82
F Harga Satuan Pekerja (D + E ) 58,691.62

A.5.1.1.37 Pemasangan 1 bh shower


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.010 - -
Tukang Kayu L.02 OH 0.400 - -
Kepala Tukang L.03 OH 0.0400 - -
Mandor L.04 OH 0.0050 - -
JUMLAH TENAGA KERJA -

B BAHAN
Shower Dupon bh 1.000 - -
sealtape kg 0.025 - -
JUMLAH HARGA BAHAN -

C PERALATAN
JUMLAH HARGA ALAT

D Jumlah( A + B + C ) -
E Overhead & Profit ...... % x D -
F Harga Satuan Pekerja (D + E ) -

A.5.1.1.38 Pemasangan 1 bh shower dupon


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja / Buruh tak terlatih L.01 OH 0.010 - -
Tukang Kayu L.02 OH 0.400 - -
Kepala Tukang L.03 OH 0.0400 - -
Mandor L.04 OH 0.0050 - -
JUMLAH TENAGA KERJA -

B BAHAN
kran Dupon bh 1.000 - -
sealtape kg 0.025 - -
JUMLAH HARGA BAHAN -

C PERALATAN
JUMLAH HARGA ALAT

D Jumlah( A + B + C ) -
E Overhead & Profit ...... % x D -
F Harga Satuan Pekerja (D + E ) -

30
DAFTAR KUANTITAS HARGA (BOQ)
NAMA PEKERJAAN : PENAMBAHAN RUANG UPTD PUSKESMAS SEMBUNG
LOKASI : KECAMATAN TULUNGAGUNG KABUPATEN TULUNGAGUNG
SUMBER DANA : TAHUN 2021
NAMA PERUSAHAAN : CV………………………

KODE HARGA SATUAN JUMLAH HARGA PPN JUMLAH


No URAIAN PEKERJAAN VOLUME SAT.
ANALISA (Rp) (Rp) 10% ( Rp)
1 2 3 4 5 6 7 8 9
I PEKERJAAN PERSIAPAN
1 Pengukuran / Bouwplank 1.00 Ls 250,000.00 250,000.00 25,000.00 275,000.00
2 Dokumentasi dan Pelaporan 1.00 Ls 250,000.00 250,000.00 25,000.00 275,000.00
3 Pembersihan Lokasi 1.00 Ls 250,000.00 250,000.00 25,000.00 275,000.00
4 Pas. Papan nama 1.00 Ls 250,000.00 250,000.00 25,000.00 275,000.00
5 Bongkaran dan perapian atap lama sebelah barat 1.00 Ls 1,000,000.00 1,000,000.00 100,000.00 1,100,000.00
6 Sewa weerket 1.00 Ls 250,000.00 250,000.00 25,000.00 275,000.00
7 Penyelenggaraan K3 1.00 Ls 4,000,000.00 4,000,000.00 400,000.00 4,400,000.00
8 Pengurusan IMB 1.00 Ls 1,000,000.00 1,000,000.00 100,000.00 1,100,000.00
9 Tes beton 1.00 Ls 1,000,000.00 1,000,000.00 100,000.00 1,100,000.00
10 Pagar pengaman lokasi proyek 1.00 Ls 2,500,000.00 2,500,000.00 250,000.00 2,750,000.00
JUMLAH 10,750,000.00 1,075,000.00 11,825,000.00
II PEKERJAAN TANAH
1 Galian tanah A.2.3.1.1 142.63 m3 63,563.85 9,066,111.93 906,611.19 9,972,723.12
2 Urugan tanah kembali A.2.3.1.9 71.32 m3 45,119.70 3,217,937.00 321,793.70 3,539,730.70
3 Urugan pasir A.2.3.1.11 29.27 m3 111,105.54 3,252,059.16 325,205.92 3,577,265.07
4 Urugan tanah A.2.3.1.15 59.39 m3 89,879.85 5,337,964.29 533,796.43 5,871,760.72
JUMLAH 20,874,072.38 2,087,407.24 22,961,479.61
III PEKERJAAN PASANGAN
1 Pas. Batu kosong/aanstampeng A.3.2.1.9 11.36 m3 295,063.25 3,351,918.57 335,191.86 3,687,110.42
2 Pas. Pondasi batu kali 1 : 5 A.3.2.1.3 24.83 m3 538,593.15 13,373,267.91 1,337,326.79 14,710,594.71
3 Pas. Bata merah 1/2 bata cam 1:3 A.4.4.1.8 43.14 m2 93,183.63 4,019,941.80 401,994.18 4,421,935.98
4 Pas. Bata merah 1/2 bata cam 1:5 A.4.4.1.10 767.27 m2 88,858.83 68,178,714.49 6,817,871.45 74,996,585.94
5 Pas. Bata merah 1 bata cam 1:5 A.4.4.1.4 74.48 m2 181,716.06 13,534,212.15 1,353,421.21 14,887,633.36
6 Plesteran cam 1:3 tebal 15 mm A.4.4.2.3 212.27 m2 49,429.71 10,492,444.54 1,049,244.45 11,541,689.00
7 Plesteran cam 1:5 tebal 15 mm A.4.4.2.5 1,476.03 m2 47,061.27 69,463,846.36 6,946,384.64 76,410,230.99
8 Acian A.4.4.2.27 1,705.31 m2 29,572.86 50,430,893.89 5,043,089.39 55,473,983.28
9 Benangan A.4.4.2.27a 1,889.06 m' 11,914.62 22,507,432.06 2,250,743.21 24,758,175.26
10 Pas. Rangka partisi C A.4.6.1.24 9.90 m2 132,285.09 1,309,622.34 130,962.23 1,440,584.58
11 Pas. Dinding partisi gypsum board A.4.5.1.7 9.90 m2 38,945.13 385,556.79 38,555.68 424,112.47
12 Pas. Tulisan Stainlesseel uk. 30-40 cm "PUSKESMAS SEMBUNG" Hs 16.00 Bh 400,000.00 6,400,000.00 640,000.00 7,040,000.00
13 Pas. Logo puskesmas Hs 1.00 Ls 750,000.00 750,000.00 75,000.00 825,000.00
14 Pas. Railing tangga Hs 6.40 m2 350,000.00 2,240,000.00 224,000.00 2,464,000.00
15 Pas. Pipa stainless steel 2" Hs 56.34 m' 46,666.67 2,629,200.00 262,920.00 2,892,120.00
16 Pas. Besi hollow 4 x 4 cm mainan atas Hs 7.48 m2 300,000.00 2,244,000.00 224,400.00 2,468,400.00
17 Pas. Glasblok Hs 20.00 Bh 35,000.00 700,000.00 70,000.00 770,000.00
18 Pas. Sunblas Hs 74.90 m2 50,000.00 3,745,000.00 374,500.00 4,119,500.00
JUMLAH 275,756,050.90 27,575,605.09 303,331,655.98
IV PEKERJAAN PINTU DAN JENDELA
1 Pas. Kusen pintu dan jendela alumunium 4'' A.4.2.1.11 637.35 m' 116,723.45 74,393,687.67 7,439,368.77 81,833,056.44
2 Pas. Daun pintu kaca bingkai alumunium A.4.2.1.13a 54.53 m2 532,496.51 29,037,034.58 2,903,703.46 31,940,738.04
3 Pas. Daun jendela kaca bingkai alumunium A.4.2.1.13b 37.61 m2 487,616.51 18,339,256.87 1,833,925.69 20,173,182.55
4 Pas. Kunci tanam dekson A.4.6.2.2 24.00 Bh 156,266.14 3,750,387.41 375,038.74 4,125,426.15
5 Pas. Engsel pintu 4'' A.4.6.2.5 48.00 Bh 40,345.65 1,936,591.26 193,659.13 2,130,250.38
6 Pas. Engsel jendela 3'' A.4.6.2.6 110.00 Bh 25,194.36 2,771,379.27 277,137.93 3,048,517.20
7 Pas. Engsel floring Hs 6.00 Set 800,000.00 4,800,000.00 480,000.00 5,280,000.00
8 Pas. Engsel geser Hs 1.00 Bh 450,000.00 450,000.00 45,000.00 495,000.00
9 Pas. Grendel tanam A.4.6.2.2b 24.00 Set 40,494.36 971,864.57 97,186.46 1,069,051.02
10 Pas. Hak angin/sikutan ses A.4.6.2.7 55.00 Set 62,008.20 3,410,450.84 341,045.08 3,751,495.92
11 Pas. Spring kinfe ses A.4.6.2.8 55.00 Bh 40,494.36 2,227,189.64 222,718.96 2,449,908.60
12 Pas. Kaca bening tebal 5 mm A.4.6.2.17 95.11 m2 100,270.65 9,536,741.64 953,674.16 10,490,415.80
13 Pas. Handle pintu stainlessteel A.4.6.2.12d 31.00 Set 212,712.94 6,594,101.20 659,410.12 7,253,511.32
14 Pas. Pintu km alumunium lengkap Hs 15.05 m2 700,000.00 10,535,000.00 1,053,500.00 11,588,500.00
JUMLAH 168,753,684.93 16,875,368.49 185,629,053.42
V PEKERJAAN BETON
A Membuat beton k275
1 Beton
a Plat setempat A.4.1.1.8 12.24 m3 747,253.43 9,146,381.96 914,638.20 10,061,020.15
b Sloof A.4.1.1.8 6.98 m3 747,253.43 5,215,828.93 521,582.89 5,737,411.82
c Kolom A.4.1.1.8 15.03 m3 747,253.43 11,231,219.02 1,123,121.90 12,354,340.93
d Balok A.4.1.1.8 7.54 m3 747,253.43 5,634,290.85 563,429.08 6,197,719.93
e Dak lantai A.4.1.1.8 26.26 m3 747,253.43 19,622,875.02 1,962,287.50 21,585,162.52
f Balok bordes A.4.1.1.8 0.34 m3 747,253.43 254,066.17 25,406.62 279,472.78
g Plat tangga A.4.1.1.8 2.41 m3 747,253.43 1,800,880.76 180,088.08 1,980,968.84
2 Pembesian - - -
a Plat setempat A.4.1.1.17 1,575.40 kg 11,153.70 17,571,538.98 1,757,153.90 19,328,692.88
b Sloof A.4.1.1.17 1,203.83 kg 11,153.70 13,427,158.67 1,342,715.87 14,769,874.54
c Kolom A.4.1.1.17 2,296.00 kg 11,153.70 25,608,895.20 2,560,889.52 28,169,784.72
d Balok A.4.1.1.17 2,842.95 kg 11,153.70 31,709,411.42 3,170,941.14 34,880,352.56
e Dak lantai A.4.1.1.17 1,743.61 kg 11,153.70 19,447,702.86 1,944,770.29 21,392,473.14
f Balok bordes A.4.1.1.17 65.40 kg 11,153.70 729,451.98 72,945.20 802,397.18
g Plat tangga A.4.1.1.17 272.81 kg 11,153.70 3,042,840.90 304,284.09 3,347,124.99
3 Membuat bekisting - - -
a Plat setempat A.4.1.1.20 13.86 m2 59,176.22 820,182.38 82,018.24 902,200.62
b Sloof A.4.1.1.21 25.08 m2 61,981.22 1,554,488.95 155,448.89 1,709,937.84
c Kolom A.4.1.1.21 99.04 m2 61,981.22 6,138,619.83 613,861.98 6,752,481.81
d Balok A.4.1.1.23 90.11 m2 104,907.97 9,453,257.09 945,325.71 10,398,582.80
e Dak lantai A.4.1.1.24 177.41 m2 123,624.97 21,932,305.75 2,193,230.58 24,125,536.33
f Balok bordes A.4.1.1.21 0.77 m2 61,981.22 47,725.54 4,772.55 52,498.09
g Plat tangga A.4.1.1.21 11.56 m2 61,981.22 716,502.88 71,650.29 788,153.17

31
B Membuat beton k175 - - -
1 Beton - - -
a Sloof A.4.1.1.5 2.52 m3 670,985.99 1,690,884.69 169,088.47 1,859,973.16
b Kolom A.4.1.1.5 6.59 m3 670,985.99 4,421,797.66 442,179.77 4,863,977.43
c Balok latai, balok overstek, balok talang A.4.1.1.5 5.42 m3 670,985.99 3,636,744.05 363,674.41 4,000,418.46
d Plat overstek, plat talang, dan meja beton A.4.1.1.5 6.58 m3 670,985.99 4,415,087.80 441,508.78 4,856,596.58
e Ring balok A.4.1.1.5 2.59 m3 670,985.99 1,737,853.71 173,785.37 1,911,639.08
2 Pembesian - - -
a Sloof A.4.1.1.17 289.67 kg 11,153.70 3,230,892.28 323,089.23 3,553,981.51
b Kolom A.4.1.1.17 1,345.63 kg 11,153.70 15,008,753.33 1,500,875.33 16,509,628.66
c Balok latai, balok overstek, balok talang A.4.1.1.17 747.84 kg 11,153.70 8,341,183.01 834,118.30 9,175,301.31
d Plat overstek, plat talang, dan meja beton A.4.1.1.17 415.62 kg 11,153.70 4,635,700.79 463,570.08 5,099,270.87
e Ring balok A.4.1.1.17 445.00 kg 11,153.70 4,963,396.50 496,339.65 5,459,736.15
3 Membuat bekisting - - -
a Sloof A.4.1.1.21 11.09 m2 61,981.22 687,247.75 68,724.77 755,972.52
b Kolom A.4.1.1.21 31.11 m2 61,981.22 1,928,235.69 192,823.57 2,121,059.26
c Balok latai, balok overstek, balok talang A.4.1.1.21 21.14 m2 61,981.22 1,310,282.95 131,028.29 1,441,311.24
d Plat overstek, plat talang, dan meja beton A.4.1.1.21 23.15 m2 61,981.22 1,434,865.20 143,486.52 1,578,351.72
e Ring balok A.4.1.1.21 14.26 m2 61,981.22 883,852.17 88,385.22 972,237.39
C membuat bekisting ( ongkos tenaga ) A.4.1.1.27 344.84 m2 73,472.44 25,336,381.78 2,533,638.18 27,870,019.95
D membongkar bekisting dan menyiram beton Hs 94.50 m3 7,500.00 708,750.00 70,875.00 779,625.00
E Rabat beton A.4.1.1.1 26.92 m3 594,038.21 15,991,508.56 1,599,150.86 17,590,659.42
JUMLAH 305,469,043.03 30,546,904.30 336,015,947.33
VI PEKERJAAN RANGKA ATAP
1 Pas. Rangka atap baja ringan 325.84 m2 160,000.00 52,134,400.00 5,213,440.00 57,347,840.00
JUMLAH 52,134,400.00 5,213,440.00 57,347,840.00
VII PEKERJAAN PENUTUP ATAP
1 Pas. Genteng Mantili A.4.5.2.1 325.84 m2 70,734.55 23,048,146.42 2,304,814.64 25,352,961.07
2 Pas. Bubungan A.4.5.2.4 36.50 m' 82,531.67 3,012,405.88 301,240.59 3,313,646.47
3 Pas. Mainan bubungan tempat ground Hs 2.00 bh 275,000.00 550,000.00 55,000.00 605,000.00
4 Pas. Kalsiplank 20 cm Hs 42.00 m' 30,000.00 1,260,000.00 126,000.00 1,386,000.00
5 Pas. Atap galvalum rangka hollow Hs 23.00 m2 300,000.00 6,900,000.00 690,000.00 7,590,000.00
JUMLAH 34,770,552.31 3,477,055.23 38,247,607.54
VIII PEKERJAAN PLAFOND
1 Pas. Rangka plafond metal furing A.4.6.1.19a 275.09 m2 88,490.10 24,342,741.61 2,434,274.16 26,777,015.77
2 Pas. Gypsumboard A.4.5.1.7 275.09 m2 38,945.13 10,713,415.81 1,071,341.58 11,784,757.39
JUMLAH 35,056,157.42 3,505,615.74 38,561,773.16
IX PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Pas. Keramik lantai 40 x 40 cm motif A.4.4.3.4 442.23 m2 148,399.09 65,626,527.80 6,562,652.78 72,189,180.58
2 Pas. Keramik lantai 40 x 40 cm tekstur A.4.4.3.4b 29.60 m2 154,891.18 4,584,778.99 458,477.90 5,043,256.89
3 Pas. Keramik lantai 30 x 30 cm polos tambal sulam A.4.4.3.35b 16.61 m2 148,674.49 2,469,483.21 246,948.32 2,716,431.53
4 Pas. Keramik lantai kamar mandi 25 x 25 cm tekstur A.4.4.3.37 24.80 m2 155,521.95 3,856,944.36 385,694.44 4,242,638.80
5 Pas. Plint keramik ukuran 10 cm x 40 cm A.4.4.3.39 297.15 m' 33,063.81 9,824,911.14 982,491.11 10,807,402.26
6 Pas. Keramik dinding 25 x 40 cm motif A.4.4.3.54B 123.12 m2 175,621.05 21,622,463.68 2,162,246.37 23,784,710.04
7 Pas. Batu andesit bakar A.4.4.3.58 4.19 m2 268,604.25 1,125,451.81 112,545.18 1,237,996.99
8 Pas. Paving tebal 6 cm k225 A.4.4.3.58d 50.40 m2 116,111.61 5,852,025.05 585,202.51 6,437,227.56
JUMLAH 114,962,586.04 11,496,258.60 126,458,844.64
X PEKERJAAN SANITASI
1 Pas. Pipa air bersih dia 1,5" A.5.1.1.28 53.00 m' 23,081.68 1,223,329.15 122,332.91 1,345,662.06
2 Pas. Pipa air bersih dia 1/2" A.5.1.1.25 30.50 m' 12,331.19 376,101.23 37,610.12 413,711.36
3 Pas. Pipa air hujan 2,5 '' A.5.1.1.30 64.00 m' 42,881.62 2,744,423.42 274,442.34 3,018,865.77
4 Pas. Pipa air kotor dia 3" A.5.1.1.31 132.50 m' 50,786.62 6,729,226.62 672,922.66 7,402,149.28
5 Pas. Biopori Hs 10.00 bh 100,000.00 1,000,000.00 100,000.00 1,100,000.00
6 Pas. Pipa kotoran dia 4" A.5.1.1.32 63.50 m' 58,691.62 3,726,917.62 372,691.76 4,099,609.38
7 Pas. Kloset duduk monoblok toto A.5.1.1.1 10.00 Bh 1,726,439.76 17,264,397.60 1,726,439.76 18,990,837.36
8 Pas. Shower kloset Hs 10.00 Bh 95,000.00 950,000.00 95,000.00 1,045,000.00
9 Tandon air stainlees steel kap. 1.100 ltr ex profil Hs 1.00 Bh 3,000,000.00 3,000,000.00 300,000.00 3,300,000.00
10 Sumur bor Hs 1.00 Ls 5,000,000.00 5,000,000.00 500,000.00 5,500,000.00
11 Pompa air Hs 1.00 Bh 1,500,000.00 1,500,000.00 150,000.00 1,650,000.00
12 Pas. Wastafel besar lengkap ex amstad A.5.1.1.5 7.00 Bh 955,777.74 6,690,444.18 669,044.42 7,359,488.60
13 Pas. Kran dia 1/2" A.5.1.1.16 13.00 Bh 78,175.61 1,016,282.87 101,628.29 1,117,911.15
14 Pas. Avor stainlees steel A.5.1.1.14 10.00 Bh 56,164.77 561,647.70 56,164.77 617,812.47
15 Pas. Bak kontrol 30 x 30 x 35 cm A.5.1.1.15 10.00 Bh 347,683.29 3,476,832.89 347,683.29 3,824,516.18
16 Pas. Bak cuci stainless steel lengkap A.5.1.1.12 3.00 Bh 515,294.31 1,545,882.93 154,588.29 1,700,471.22
17 Pas. Stop kran 1.5 '' Hs 2.00 Bh 95,000.00 190,000.00 19,000.00 209,000.00
18 Septictank Hs 2.00 Ls 2,000,000.00 4,000,000.00 400,000.00 4,400,000.00
JUMLAH 60,995,486.21 6,099,548.62 67,095,034.83
XI PEKERJAAN LISTRIK
1 Pas. Instalasi lampu Hs 61.00 titik 65,000.00 3,965,000.00 396,500.00 4,361,500.00
2 Pas. Instalasi stop kontak Hs 51.00 titik 65,000.00 3,315,000.00 331,500.00 3,646,500.00
3 Pas. Stop kontak panasonic Hs 51.00 Bh 25,000.00 1,275,000.00 127,500.00 1,402,500.00
4 Pas. Saklar ganda panasonic Hs 27.00 Bh 25,000.00 675,000.00 67,500.00 742,500.00
5 Pas. Saklar tunggal panasonic Hs 36.00 Bh 15,000.00 540,000.00 54,000.00 594,000.00
6 Pas. Saklar hotel (tangga) Hs 1.00 Set 50,000.00 50,000.00 5,000.00 55,000.00
7 Pas. Lampu led 10 w Hs 49.00 Bh 45,000.00 2,205,000.00 220,500.00 2,425,500.00
8 Pas. Lampu led 5 w Hs 12.00 Bh 28,000.00 336,000.00 33,600.00 369,600.00
9 Pas. Downlight led 9 w Hs 29.00 Bh 38,000.00 1,102,000.00 110,200.00 1,212,200.00
10 Pas. Ground Hs 3.00 Bh 135,000.00 405,000.00 40,500.00 445,500.00
11 Kabel penangkal petir Hs 30.00 m' 45,000.00 1,350,000.00 135,000.00 1,485,000.00
12 Pas. Operspaning Hs 1.00 Ls 500,000.00 500,000.00 50,000.00 550,000.00
13 Pas. Panel group Hs 2.00 Ls 200,000.00 400,000.00 40,000.00 440,000.00
14 Pas. Pipa wifi Hs 1.00 Ls 300,000.00 300,000.00 30,000.00 330,000.00
15 Pas. Exhausfan 25/25 Hs 1.00 bh 300,000.00 300,000.00 30,000.00 330,000.00
16 Pas. Lampu spot light Hs 1.00 bh 110,000.00 110,000.00 11,000.00 121,000.00
JUMLAH 16,828,000.00 1,682,800.00 18,510,800.00
XII PEKERJAAN CAT CATAN
1 Cat dinding baru interior premium A.4.7.1.10b 1832.01 m2 17,553.57 32,158,311.38 3,215,831.14 35,374,142.52
2 Cat dinding lama interior premium A.4.7.1.11 308.80 m2 13,375.08 4,130,223.59 413,022.36 4,543,245.95
3 Cat plafond A.4.7.1.10d 726.75 m2 14,921.97 10,844,539.95 1,084,454.00 11,928,993.95
4 Cat kayu A.4.7.1.4 29.96 m2 43,807.16 1,312,462.63 131,246.26 1,443,708.90
5 Pelapisan aquaproof A.4.7.1.10c 59.35 m2 25,784.97 1,530,337.83 153,033.78 1,683,371.61
6 Couting batu hias A.4.7.1.12b 4.19 m2 36,816.29 154,260.25 15,426.02 169,686.27
JUMLAH 50,130,135.63 5,013,013.56 55,143,149.19
XIII PEKERJAAN LAIN - LAIN
1 Meja resepsionis dan apotek serta pembatas bahan acrylic 2 mm Hs 6.80 m' 700,000.00 4,760,000.00 476,000.00 5,236,000.00
JUMLAH 4,760,000.00 476,000.00 5,236,000.00

JUMLAH TOTAL 1,266,364,185.72

Terbilang : …………………………………..

32
Tulungagung, 2021

Dibuat oleh :
CV……………………..

33
REKAPITULASI DAFTAR KUANTITAS HARGA (BOQ)
NAMA PEKERJAAN : PENAMBAHAN RUANG UPTD PUSKESMAS SEMBUNG
LOKASI : KECAMATAN TULUNGAGUNG KABUPATEN TULUNGAGUNG
SUMBER DANA : TAHUN 2021
NAMA PERUSAHAAN : CV………………………

No URAIAN PEKERJAAN JUMLAH PPN 10% JUMLAH + PPN

I PEKERJAAN PERSIAPAN 10,750,000.00 1,075,000.00 11,825,000.00


II PEKERJAAN TANAH 20,874,072.38 2,087,407.24 22,961,479.61
III PEKERJAAN PASANGAN 275,756,050.90 27,575,605.09 303,331,655.98
IV PEKERJAAN PINTU DAN JENDELA 168,753,684.93 16,875,368.49 185,629,053.42
V PEKERJAAN BETON 305,469,043.03 30,546,904.30 336,015,947.33
VI PEKERJAAN RANGKA ATAP 52,134,400.00 5,213,440.00 57,347,840.00
VII PEKERJAAN PENUTUP ATAP 34,770,552.31 3,477,055.23 38,247,607.54
VIII PEKERJAAN PLAFOND 35,056,157.42 3,505,615.74 38,561,773.16
IX PEKERJAAN PENUTUP LANTAI DAN DINDING 114,962,586.04 11,496,258.60 126,458,844.64
X PEKERJAAN SANITASI 60,995,486.21 6,099,548.62 67,095,034.83
XI PEKERJAAN LISTRIK 16,828,000.00 1,682,800.00 18,510,800.00
XII PEKERJAAN CAT CATAN 50,130,135.63 5,013,013.56 55,143,149.19
XIII PEKERJAAN LAIN - LAIN 4,760,000.00 476,000.00 5,236,000.00
JUMLAH TOTAL 1,151,240,168.84 115,124,016.88 1,266,364,185.72
Terbilang : …………………………………..

Tulungagung, 2021

Dibuat oleh :
CV……………………..

…………………………..
Direktur/Direkris