KEGIATAN : PEMBANGUNAN WORKSHOP - BLK KOMUNITAS

PEMBERI BANTUAN : KEMNAKER RI


KEJURUAN : MENJAHIT
GROUP : B LOGO
NAMA LEMBAGA : AL MA'UNAH KEPUH LEMBAGA
KOTAMADYA / KABUPATEN : CIREBON
PROVINSI : JAWA BARAT
TAHUN : 2019
TANGGAL MULAI PEKERJAAN : 12 Juni 2019
TANGGAL SELESAI PEKERJAAN : 08 Oktober 2019
MINGGU KE
NO ITEM PEKERJAAN % 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

i KONTRAK / TERMIN I ( 0 % )
A PEKERJAAN PERSIAPAN 1.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
298.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.54 0.54
B PEKERJAAN TANAH DAN PASIR 3.31 0.10 2.50 0.71
C PEKERJAAN PONDASI 8.74 0.60 3.30 4.84
D PEKERJAAN STRUKTUR - 232.32

STRUKTUR BETON 21.35 1.30 4.83 4.83 10.40


PEKERJAAN ATAP 16.13 0.50 5.70 9.92 0.01
E PEKERJAAN PLAFOND 1.40 160.85 0.47 0.47 0.47
F PEKERJAAN PASANGAN 19.10 4.78 4.78 4.78 4.78
G PEKERJAAN KUSEN PINTU & JENDELA 9.69 1.94 1.94 1.94 1.94 1.94
H PEKERJAAN PENGECATAN 2.59 89.75 0.65 0.65 0.65 0.65
I PEKERJAAN PLUMBING & SANITAIR 2.62 56.30 0.33 0.33 0.33 0.33 0.33 0.33 0.33 0.33
J PEKERJAAN LISTRIK 10.24 1.28 1.28 1.28 1.28 1.28 1.28 1.28 1.28
K LAIN - LAIN 3.73 0.00 0.00 19.51
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.86 1.86
0.00 0.00
ii TERMIN II ( 50% )
100.00

Bobot Rencana 0.00 0.70 7.10 9.66 5.33 16.10 11.09 5.26 5.25 8.32 8.32 3.55 3.55 4.20 2.26 4.65 4.65
Akumulasi Rencana 0.00 0.70 7.81 17.47 22.80 38.90 49.99 55.25 60.49 68.82 77.14 80.69 84.24 88.43 90.69 95.34 100.00
Bobot Realisasi 0.00 0.00 19.51 36.79 33.45 71.10 71.47 65.76
Akumulasi Realisasi 0.00 0.00 19.51 56.30 89.75 160.85 232.32 298.07
429.59
KET

298.07

232.32

160.85

89.75

30
KEGIATAN : PEMBANGUNAN WORKSHOP - BLK KOMUNITAS
PEMBERI BANTUAN : KEMNAKER RI
KEJURUAN : MENJAHIT
GROUP : B
NAMA LEMBAGA : AL MA'UNAH KEPUH
KOTAMADYA / KABUPATEN : CIREBON
PROVINSI : JAWA BARAT
TAHUN : 2019
TANGGAL MULAI PEKERJAAN : 12 Juni 2019
TANGGAL SELESAI PEKERJAAN : 08 Oktober 2019

MINGGU 1 MINGGU 2 MINGGU 3 MINGGU 4 MINGGU 5 MINGGU 6 MINGGU 7 MINGGU 8 MINGGU 9 MINGGU 10 MINGGU 11 MINGGU 12 MINGGU 13 MINGGU 14 MINGGU 15 MINGGU 16 MINGGU 17 JUMLAH BOBOT

NO URAIAN PEKERJAAN VOLUME SAT. BOBOT


PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRES S/D MINGGU INI

(%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) S/D MINGGU INI (%)
A PEKERJAAN PERSIAPAN
1 Papan Proyek 1.00 unt 0.12 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 800% 0.9813
2 Pek. Pengukuran dan Bowplank 52.00 m' 0.30 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 800% 2.4058
3 Pek. Listrik & Air Kerja 1.00 ls 0.55 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 600% 3.2706
4 Pek. Laporan & Dokumentasi 1.00 ls 0.11 0% 25% 25% 25% 35% 35% 45% 50% 0% 0% 0% 0% 0% 0% 0% 0% 0% 240% 0.2714
B PEKERJAAN PONDASI & TANAH
1 Pek. Galian Tanah Pondasi 77.38 m3 1.39 0% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 700% 9.7558
2 Pek. Urug Tanah Kembali 25.79 m3 0.10 0% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 700% 0.6775
3 Pek. Urug Tanah Peninggian Peil Lantai (t = 10 cm) 19.55 m3 0.52 0% 0% 25% 50% 100% 100% 30% 45% 0% 0% 0% 0% 0% 0% 0% 0% 0% 350% 1.8177
4 Pek. Pasir Urug 0.00 0% 0% 0% 0% 0% 50% 60% 70% 0% 0% 0% 0% 0% 0% 0% 0% 0% 180% 0.0000
- Bawah Pondasi 11.90 m3 0.59 0% 0% 35% 75% 100% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 510% 2.9937
- Bawah Lantai 19.91 m3 0.98 0% 0% 0% 0% 25% 45% 48% 50% 0% 0% 0% 0% 0% 0% 0% 0% 0% 168% 1.6499
B PEKERJAAN TANAH DAN PASIR
5 Pek. Pondasi Tapak P1 (100x100x20-40) 16.00 bh 2.09 0% 0% 50% 100% 100% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 550% 11.5072
6 Pek. Pondasi Batu Belah P2 69.30 m' 3.10 0% 25% 35% 55% 85% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 500% 15.5198
7 Pek. Sloof Beton (15/30) 51.03 m2 3.30 0% 0% 30% 45% 100% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 475% 15.6545
C PEKERJAAN STRUKTUR
C.1 STRUKTUR BETON
1 Pek. Kolom Beton K1 (30/30) 16.00 bh 6.74 0% 0% 50% 100% 100% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 550% 37.0736
2 Pek. Kolom Praktis KP (15/15) 11.00 bh 1.64 0% 0% 0% 35% 45% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 380% 6.2404
3 Pek. Balok Beton B1 (20/30) 44.40 m2 3.63 0% 0% 40% 70% 100% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 510% 18.4954
4 Pek. Beton Balok Lintel BL (15/15), RB (15/15) 34.66 m2 2.45 0% 0% 25% 30% 100% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 455% 11.1650
5 Pek. Ramp Beton T = 10 cm 0.69 m2 0.16 0% 0% 0% 50% 75% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 425% 0.6692
6 Pek. Kolom Sopi Sopi (30/30) 9.96 m2 0.68 0% 0% 0% 30% 100% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 430% 2.9256
7 Pek. Ring Balok Praktis Sopi Sopi (15/15) 12.81 m2 1.03 0% 0% 0% 30% 68% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 398% 4.0804
8 Pek. Plat Beton Topi Topi (10/60) 12.24 m2 0.99 0% 0% 0% 0% 40% 50% 50% 50% 0% 0% 0% 0% 0% 0% 0% 0% 0% 190% 1.8791
C.2 PEKERJAAN ATAP
1 Rangka Atap Baja Ringan 205.53 m2 6.39 0% 0% 0% 0% 0% 30% 55% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 185% 11.8140
2 Atap Spandek t = 0.35 mm 205.53 m2 3.81 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
3 Listplank GRC 73.80 m' 1.16 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
4 Pasang Aluminium Foil, Glaswool, Roofmesh 140.00 m2 2.90 0% 0% 0% 0% 0% 0% 25% 40% 0% 0% 0% 0% 0% 0% 0% 0% 0% 65% 1.8847
D PEKERJAAN PLAFOND
1 Plafond Gipsum 9 mm + Rangka Hollow 4/4 ; t = 0.35 136.49 m2 2.95 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
2 Plafond Calsiboard 4,5 mm + Rangka 53.31 m2 1.10 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
3 Lis Gipsum 5 cm 94.85 m' 0.37 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
E PEKERJAAN PASANGAN
1 Pasangan Dinding Bata 250.73 m2 5.10 0% 0% 20% 65% 95% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 480% 24.4931
2 Plester + Acian 496.17 m3 7.07 0% 0% 0% 0% 35% 75% 80% 85% 0% 0% 0% 0% 0% 0% 0% 0% 0% 275% 19.4409
3 Pasangan Rolaag Bata 19.80 m' 0.36 0% 0% 30% 85% 100% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 515% 1.8702
4 Pasangan Saluran Terbuka (U pasangan bata) 40.00 m' 1.39 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 1.3892
5 Pekerjaan Rabat Beton t = 5 cm bawah lantai keramik 9.96 m3 1.69 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
6 Pekerjaan Rabat Beton t = 5 cm keliling bang lbr = 60 cm 2.04 m3 0.35 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
7 Pekerjaan Meja Beton Wastafel t = 8 cm 0.10 m3 0.02 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
8 Pasangan Keramik Lantai 40/40 Polished 136.40 m2 2.77 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
9 Pasangan Keramik Lantai 30/30 Polished 52.00 m2 1.03 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
10 Pasangan Keramik Lantai 20/20 Unpolished 3.04 m2 0.06 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
11 Pasangan Plint Keramik Lantai 40/10 polished 97.40 m' 1.01 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
12 Pasangan Keramik Bak & Meja Wastafel 20/20 Polished 1.77 m2 0.03 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
13 Pasangan Keramik Dinding 30/60 Polished 5.29 m2 0.23 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
14 Pasangan Batu Alam Candi Kolom Entrace 7.62 m2 0.32 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
15 Pek. Logo & Tulisan 1.00 ls 0.57 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
16 List Dinding, Kusen 97.36 m1 0.84 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
MINGGU 1 MINGGU 2 MINGGU 3 MINGGU 4 MINGGU 5 MINGGU 6 MINGGU 7 MINGGU 8 MINGGU 9 MINGGU 10 MINGGU 11 MINGGU 12 MINGGU 13 MINGGU 14 MINGGU 15 MINGGU 16 MINGGU 17 JUMLAH BOBOT

NO URAIAN PEKERJAAN VOLUME SAT. BOBOT


PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRESS PROGRES S/D MINGGU INI

(%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) S/D MINGGU INI (%)
F PEKERJAAN KUSEN PINTU & JENDELA
1 Kusen/Pintu type P1 1.00 unt 0.97 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
2 Kusen/Pintu type P2 3.00 unt 1.37 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
3 Kusen/Pintu type P3 (Spandrel) 1.00 unt 0.47 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
4 Kusen/Jendela type J1 2.00 unt 0.89 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
5 Kusen/Jendela type J2 9.00 unt 4.30 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
6 Kusen/Jendela type J3 1.00 unt 0.25 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
7 Kusen/Jendela type BV 1.00 unt 0.05 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
8 Tralis Ventilasi Teras (Besi Hollow) 6.65 m1 0.23 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
G PEKERJAAN PENGECATAN 0.00
1 Pek. Pengecatan Dinding Interior 248.08 m2 1.34 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
2 Pek. Pengecatan Dinding Exterior 248.08 m2 1.14 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
3 Pek. Pengecatan Plafond 189.80 m2 0.66 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
4 Pek. Pengecatan Listplank 22.14 m2 0.13 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
H PEKERJAAN PLUMBING & SANITAIR
1 Instalasi Pipa PVC AW 4" 16.00 m' 0.44 0% 0% 0% 20% 70% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 390% 1.7174
2 Instalasi Pipa PVC AW 2" 12.00 m' 0.11 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
3 Instalasi Pipa PVC AW 3/4" 20.00 m' 0.08 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
4 Instalasi Pipa PVC AW 1/2" 15.00 m' 0.05 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
5 Septic Tank dan Rembesan 1.00 unt 1.17 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
6 Pemasangan Closed Jongkok 1.00 bh 0.12 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
7 Pemasangan Kran Air 2.00 bh 0.04 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
8 Pemasangan Wastafel + Kran 2.00 bh 0.55 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
9 Pemasangan Cermin Wastafel 100x200 1.00 unt 0.05 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
I PEKERJAAN LISTRIK
1 Penyambungan Daya Listrik 5,500.00 VA 1.87 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
2 Perijinan Sertifikat Layak Operasi (SLO) 5,500.00 VA 0.44 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
3 Panel Listrik 1.00 unt 0.30 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0.2962
4 Pek. Instalasi Kabel Feeder NYY 4x10 mm2 2.00 m' 0.04 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
5 Pek. Instalasi Penerangan & Power NYM 3x2,5 mm2 + conduit 66.00 ttk 2.58 0% 0% 0% 0% 0% 40% 50% 75% 0% 0% 0% 0% 0% 0% 0% 0% 0% 165% 4.2495
6 Pek. Instalasi Power AC 2.00 ttk 0.08 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
7 Pemasangan Lampu TKI 2x36W 16.00 bh 1.25 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
8 Pemasangan Lampu Baret Kotak 18/22W 7.00 bh 0.33 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
9 Pemasangan Lampu E27ESS 8 Watt + DL 4'' 3.00 bh 0.12 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
10 Pemasangan Saklar Engkle 5.00 bh 0.05 0% 0% 0% 0% 0% 0% 0% 20% 0% 0% 0% 0% 0% 0% 0% 0% 0% 20% 0.0106
11 Pemasangan Saklar Double 4.00 bh 0.05 0% 0% 0% 0% 0% 0% 0% 20% 0% 0% 0% 0% 0% 0% 0% 0% 0% 20% 0.0093
12 Pemasangan Stop Kontak Single 9.00 bh 0.08 0% 0% 0% 0% 0% 0% 0% 20% 0% 0% 0% 0% 0% 0% 0% 0% 0% 20% 0.0163
13 Pemasangan Stop Kontak Ganda 16.00 bh 0.15 0% 0% 0% 0% 0% 0% 0% 20% 0% 0% 0% 0% 0% 0% 0% 0% 0% 20% 0.0290
14 Pemasangan Stop Kontak AC 2.00 bh 0.03 0% 0% 0% 0% 0% 0% 0% 20% 0% 0% 0% 0% 0% 0% 0% 0% 0% 20% 0.0067
15 Pemasangan AC split wall 2 PK 2.00 unit 2.26 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
16 Grounding (max 2 Ohm) 1.00 lot 0.30 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0000
L LAIN - LAIN
1 IMB 1.00 dok 1.10 0% 0% 0% 20% 30% 40% 50% 50% 0% 0% 0% 0% 0% 0% 0% 0% 0% 190% 2.0912
2 Transportasi 2.00 paket 1.00 0% 0% 25% 25% 50% 50% 50% 50% 0% 0% 0% 0% 0% 0% 0% 0% 0% 250% 2.5014
3 Ketua Unit Pengelola Teknis 4.00 OB 0.32 0% 0% 25% 25% 25% 25% 50% 50% 0% 0% 0% 0% 0% 0% 0% 0% 0% 200% 0.6404
4 Ketua Unit Pengelola Keuangan 4.00 OB 0.32 0% 0% 25% 25% 25% 25% 25% 50% 0% 0% 0% 0% 0% 0% 0% 0% 0% 175% 0.5603
5 Anggota Pengelola Teknis 8.00 OB 0.48 0% 0% 25% 25% 25% 25% 25% 50% 0% 0% 0% 0% 0% 0% 0% 0% 0% 175% 0.8405
6 Anggota Pengelola Keuangan 8.00 OB 0.48 0% 0% 25% 25% 25% 25% 25% 50% 0% 0% 0% 0% 0% 0% 0% 0% 0% 175% 0.8405
TOTAL 100.00 223.7353