13 Maret 2017
PT. Perkasa Citra Unggul
Haporsayaon Purba
Direktur
ANALISA HARGA SATUAN
NO. URAIAN KOEF SAT HARGA SAT matrial HARGA SAT upah JUMLAH matrial JUMLAH upah TOTAL harga
A B C D E F G=(CXE) H = (C X F ) I=(G+H)
ANALISA 001 1 m3 Pek. Galian Tanah Biasa 0.00 34,800.00 34,800.00
Tenaga
Perkerja 0.300 Oh 100,000.00 30,000
Kepala Tukang Oh -
Mandor 0.040 Oh 120,000.00 4,800
ANALISA 010 Membuat Strouspile dia. 30cm ; L=300cm, 639,496.00 461,300.00 1,100,796.00
tul. Utama d12 BJPT24 tul bagi d 8 - 200 BJPT 24
Bahan
Besi Beton Polos/ulir 29.300 Kg 9,100.00 266,630.00
Kawat Beton 0.356 Kg 24,000.00 8,544.00
Semen Portland 70.230 Kg 1,400.00 98,322.00
Pasir Beton 0.320 m3 300,000.00 96,000.00
Koral Beton 0.200 m3 350,000.00 70,000.00
Peralatan
Boring Equipment 0.250 jam 400,000.00 100,000.00
Tenaga
Perkerja 3.200 Oh 100,000.00 320,000
Tukang Batu 0.350 Oh 100,000.00 35,000
Tukang Kayu 0.400 Oh 100,000.00 40,000
Tukang Besi 0.300 Oh 100,000.00 30,000
Kepala Tukang 0.150 Oh 110,000.00 16,500
Mandor 0.165 Oh 120,000.00 19,800
13 Maret 2017
PT. Perkasa Citra Unggul
Haporsayaon Purba
Direktur
O KIJ V
JUMLAH
( Rp )
30 Maret 2017
asa Citra Unggul PT. Perkasa Citra Unggul
MINGGU 1
NO SUB BIDANG PEKERJAAN
1
BOBOT %
7
3.021
I Pekerjaan Persiapan 18.466
Ket :
- Lama Pekerjaan 90 Hari Kalender
ADWAL PELAKSANAAN PEKERJAAN
ning Turap Sutet belakang Kavling PT SOHO KIJ V
TIME SCHEDULE (90 HARI KALENDER)
2 3 4 5 6 7 8 9 10 11
8 15 22 29 36 43 50 57 64 71
14 21 28 35 42 49 56 63 70 77
2.308 2.308 2.052 1.086 1.086 1.086 1.086 0.923 0.923 0.923
5.918 7.412 8.153 10.192 11.648 10.192 8.153 5.824 5.436 4.530
8.23 9.72 10.21 11.28 12.73 11.28 9.24 6.75 6.36 5.45
11.247 20.968 31.173 42.451 55.185 66.463 75.702 82.449 88.808 94.261
02 Mei 2017
PT. Perkasa Citra Unggul
Haporsayaon Purba
Direktur
12 13
KET.
78 85
84 90
0.923 0.739
11.862
4.077
5.00 0.74
99.261 100.000
02 Mei 2017
erkasa Citra Unggul 4.826
porsayaon Purba
PROGRESS PEKERJAAN
Diajukan Oleh :
PT. Perkasa Citra Unggul
Haporsayaon Purba
Direktur
PROGRESS PEKERJAAN
1.430
1.502
0.3332
#REF!
55.185
43.32
JADWAL DAN PROGRESS PELAKSANAAN PEKERJAAN
Perbaikan Lining Turap Sutet Belakang Kavling PT SOHO KIJ V
TIME SCHEDULE (90 HARI KALENDER)
MINGGU 1 2 3 4 5 6 7 8 9 10 11 12 13
NO SUB BIDANG PEKERJAAN KET.
1 8 15 22 29 36 43 50 57 64 71 78 85
BOBOT %
7 14 21 28 35 42 49 56 63 70 77 84 90
100
I Pekerjaan Persiapan 18.466 4.847 1.616 1.616 1.616 1.616 1.616
- Strouspile dia. 30cm ; L=300cm, tul. Utama d12 BJPT24 5.688 0.910 0.910 0.910 0.910 0.910
- Cerucuk Bambu AMPEL dia 7-10 (cm) space 0.5 m ; panjang 2m 5.452 0.872 0.872 0.872 0.872 0.872
- Subdrain pipa (merk bebas) 2" (sulingan)+ ijuk space 1 m zig zag 1.366 0.091 0.273 0.364 0.364