REKAPITULASI

RENCANA ANGGARAN BIAYA ( RAB )


PERUMAHAN AL-GHIFARI

KEGIATAN : PEMBANGUNAN RUMAH SUBSIDI TYPE 36

PEKERJAAN : RENCANA PEMBANGUNAN PERUMAHAN

LOKASI : CENGKONG KARAWANG

NO. PEKERJAAN JUMLAH HARGA ( RP.)

1 2 3
I PEKERJAAN PERSIAPAN 900,000.00

II PEKERJAAN PONDASI 5,881,393.00

III PEKERJAAN BETON BERTULANG 6,881,000.00

IV PEKERJAAN PASANGAN DAN PLASTERAN 15,749,090.00

V PEKERJAAN LANTAI 2,306,500.00

VI PEKERJAAN ATAP DAN PLAFOND 9,090,000.00

VII PEKERJAAN KUSEN PINTU DAN JENDELA 6,900,000.00

VIII PEKERJAAN PENGECATAN 5,274,900.00

IX PEKERJAAN PENGUNCI DAN PENGANTUNG 202,000.00

X PEKERJAAN INSTALASI LISTRIK 2,661,000.00

XI PEKERJAAN SANITASI 10,395,000.00

JUMLAH 66,240,886.00
PEMBULATAN 66,200,000.00
Harga per M2 1,830,000.00
RENCANA ANGGARAN BIAYA ( RAB )
Harga
No. Uraian Pekerjaan Volume
Satuan Jumlah
1 2 3 4 5

I. PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan ls. 300,000.00 300,000.00
2 Pengukuran dan Pemasangan Bowplank ls. 600,000.00 600,000.00
Sub Total 900,000.00

II. PEKERJAAN PONDASI


1 Galian tanah pondasi menerus 11.864 m³ 25,000.00 296,600.00
2 Urugan kembali 1/4 galian 2.966 m³ 15,000.00 44,490.00
3 Urugan tanah bawah lantai 3.780 m³ 80,000.00 302,400.00
4 Urugan pasir bawah lantai 1.890 m³ 82,000.00 154,980.00
5 Urugan pasir bawah pondasi 1.402 m³ 82,000.00 114,923.00
6 Pekerjaan beton pondasi batu kali 11.040 m³ 450,000.00 4,968,000.00
Sub Total 5,881,393.00

III. PEKERJAAN BETON BERTULANG


1 Beton sloof 0.803 m³ 2,000,000.00 1,606,500.00
2 Beton kolom 1.064 m³ 2,000,000.00 2,128,000.00
3 Beton kolom praktis 0.770 m³ 2,000,000.00 1,540,000.00
4 Beton reng balok 0.803 m³ 2,000,000.00 1,606,500.00
Sub Total 6,881,000.00

IV. PEKERJAAN PASANGAN DAN PLASTERAN


1 Pasangan batako 11.249 m³ 400,000.00 4,499,740.00
2 Plasteran dinding + acian 321.410 m² 35,000.00 11,249,350.00
Sub Total 15,749,090.00

V. PEKERJAAN LANTAI
1 Lantai keramik 40 x 40 30.250 m² 70,000.00 2,117,500.00
2 Lantai keramik toilet 25 x 25 2.700 m² 70,000.00 189,000.00
Sub Total 2,306,500.00

VI. PEKERJAANATAP DAN PLAFOND


1 Rangka Baja Ringan 28.000 m² 130,000.00 3,640,000.00
2 Genteng flat beton 28.000 m² 65,000.00 1,820,000.00
5 Plafond gypsum Rangka Hollow 30.250 m² 120,000.00 3,630,000.00
Sub Total 9,090,000.00

VII. PEKERJAAN KOSEN PINTU JENDELA


1 Pintu P1 4 bh 1,000,000.00 4,000,000.00
2 Pintu PVC 1 bh 200,000.00 200,000.00
3 Jendela J1 3 bh 900,000.00 2,700,000.00
Sub Total 6,900,000.00

VIII. PEKERJAAN PENGECATAN


1 Cat dinding tembok 321 m² 15,000.00 4,821,150.00
2 Cat plafond 30.25 m² 15,000.00 453,750.00
Sub Total 5,274,900.00

IX. PEKERJAAN PENGUNCI DAN PENGANTUNG


1 Engsel pintu 5 bh 20,000.00 100,000.00
2 Engsel jendela 5 bh 15,000.00 75,000.00
3 Pacok jendela 5 bh 3,000.00 15,000.00
4 Grendel jendela 4 bh 3,000.00 12,000.00
Sub Total 202,000.00

X. PEKERJAAN INSTALASI LISTRIK


1 Biaya penyambungan baru 4 amper ls 2,000,000.00 2,000,000.00
2 Box zekering 1 bh 85,000.00 85,000.00
3 Saklar ganda setara broco 2 bh 25,500.00 51,000.00
4 Lampu philip 15 watt + Instalasi 6 ttk 87,500.00 525,000.00
Sub Total 2,661,000.00

XI. PEKERJAAN SANITASI


1 Pas instalasi air 6 ttk 150,000.00 900,000.00
2 Pas kran air 3 bh 30,000.00 90,000.00
3 Pemasangan pipa pembuangan air bak 1 bh 15,000.00 15,000.00
4 Pas saringan kamar mandi 1 bh 20,000.00 20,000.00
5 Pas kloset jongkok keramik 1 bh 160,000.00 160,000.00
8 Pas pipa Ø 3 inci + acsesoris 11 M 45,000.00 495,000.00
9 Pas pipa Ø 4 inci + acsesoris 13 M 55,000.00 715,000.00
11 Septictank 1 unit 3,500,000.00 3,500,000.00
Harga
No. Uraian Pekerjaan Volume
Satuan Jumlah
12 Sumur bor + pompa air 1 ls 4,500,000.00 4,500,000.00
Sub Total 10,395,000.00