REKAPITULASI

RENCANA ANGGARAN BIAYA ( R A B )


KEGIATAN : PERENCANAAN
PEKERJAAN : PEMBUATAN ATAP DAN JALAN BETON
LOKASI : PARE-PARE (RS.DR. HASRI AINUN HABIBIE)

NO URAIAN PEKERJAAN JUMLAH HARGA KET


a b c d
I PEKERJAAN MOBILISASI DAN DEMOBILISASI Rp 23,435,000.00
II PEKERJAAN PONDASI Rp 21,041,228.29
III PEKERJAAN LANTAI Rp 82,774,143.82
IV PEKERJAAN ATAP Rp 96,557,025.52

Rp 223,807,397.63
R E A L C O S T ………………………………………………………………………………………………………………………………………………………..
PPN 11% ………………………………………………………………………………………………………………………………………………………..
Rp 24,618,813.74
J U M L A H ………………………………………………………………………………………………………………………………………………………..
Rp 248,426,211.37
DIBULATKAN ………………………………………………………………………………………………………………………………………………………..
Rp 248,400,000.00
Terbilang : Dua Ratus Empat Puluh Delapan Juta Empat Ratus Ribu Rupiah, ......
DAFTAR
RENCANA ANGGARAN BIAYA ( R A B )
KEGIATAN : PERENCANAAN
PEKERJAAN : PEMBUATAN ATAP DAN JALAN BETON
LOKASI : PARE-PARE (RS.DR. HASRI AINUN HABIBIE)

NO URAIAN PEKERJAAN SPESIFIKASI BAHAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA
a b c e f h
I PEKERJAAN PERSIAPAN Rp 23,435,000.00
PEKERJAAN MOBILISASI DAN DEMOBILISASI Rp 23,435,000.00
1 Pembersihan, dan Pematangan Lokasi 1 LS Rp 500,000.00 Rp 500,000.00
2 Pengukuran dan Pemasangan Bowplank 200 M1 Rp 114,675.00 Rp 22,935,000.00

II ITEM PEKERJAAN
1 PEKERJAAN PONDASI Rp 21,041,228.29
1.1 Pekerjaan Pondasi batu kali Camp. 1 : 5 Rp 21,041,228.29
1 Galian Tanah 13.5 M3 Rp 94,545.00 Rp 1,276,357.50
2 Urugan Pasir Bawah Pondasi Pasir Urugan 2.25 M3 Rp 242,110.00 Rp 544,747.50
3 Pasangan Batu Kosong Batu kali 4.5 M3 Rp 523,116.00 Rp 2,354,022.00
4 Pasangan Batu Kali Camp. 1 : 5 Batu Gunung 15.75 M3 Rp 991,237.50 Rp 15,611,990.63
5 Urugan Tanah Kembali Tanah Urug 15.75 M3 Rp 55,550.00 Rp 874,912.50
6 Plasteran Pondasi Camp. 1:5 T.2mm 4 M2 Rp 94,799.54 Rp 379,198.16

2 PEKERJAAN LANTAI Rp 82,774,143.82


2.1
1 Pekerjaan Penimbunan Tanah Bawah Lantai T. 0.5 cm 7.5 M3 Rp 106,975.00 Rp 802,312.50
2 Pekerjaan Penimbunan Pasir Bawah Lantai T. 10 cm 15 M3 Rp 242,110.00 Rp 3,631,650.00
3 Pekerjaan Rabat Beton T. 5 cm 22.5 M3 Rp 1,488,188.30 Rp 33,484,236.67
4 Pekerjaan Pas. Lantai 40x40 150 M3 Rp 299,039.63 Rp 44,855,944.65

3 PEKERJAAN ATAP Rp 96,557,025.52


3.1 Pekerjaan Atap Rp 96,557,025.52
1 Pekerjaan Atap Spandek 144 M2 Rp 213,285.49 Rp 30,713,110.56
2 Pekerjaan Rangka Atap 144 M2 Rp 231,609.84 Rp 33,351,816.96
3 Pekerjaan Nok Atap 100 M1 Rp 222,938.98 Rp 22,293,898.00
4 Pekerjaan LisPlang 60 M2 Rp 169,970.00 Rp 10,198,200.00
RINGKASAN : ANALISA HARGA SATUAN PEKERJAAN BIDANG CIPTA KARYA
KODE HARGA (Rp.) JUMLAH OVERHEAD & JUMLAH TOTAL
NO. URAIAN PEKERJAAN KET.
ANALISA TENAGA BAHAN PERALATAN (Rp.) PROFIT (Rp.) (Rp.)
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
DIV. I A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN 10%

DIV. II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


1 A.2.3.1.1 Penggalian 1 M3 Tanah Biasa Sedalam 1 M 70,250.00 - - 70,250.00 7,025.00 77,275.00
2 A.2.3.1.2 Penggalian 1 M3 Tanah Biasa Sedalam 2 M 85,950.00 - - 85,950.00 8,595.00 94,545.00
3 A.2.3.1.3 Penggalian 1 M3 Tanah Biasa Sedalam 3 M 101,870.00 - - 101,870.00 10,187.00 112,057.00
4 A.2.3.1.9 Pengurugan Kembali 1 M3 Galian Tanah 50,500.00 - - 50,500.00 5,050.00 55,550.00
5 A.2.3.1.11 Pengurugan 1 M3 dengan Pasir Urug 28,100.00 192,000.00 - 220,100.00 22,010.00 242,110.00
6 A.2.3.1.15 Pengurugan 1 M3 dengan Tanah Urug 25,250.00 72,000.00 - 97,250.00 9,725.00 106,975.00

DIV. III A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI


1 A.3.2.1.2 Pemasangan 1 M3 Pondasi Batu Belah Campuran 1 SP : 4 PP 252,000.00 649,125.00 - 901,125.00 90,112.50 991,237.50
2 A.3.2.1.3 Pemasangan 1 M3 Pondasi Batu Belah Campuran 1 SP : 5 PP 252,000.00 612,000.00 - 864,000.00 86,400.00 950,400.00
3 A.3.2.1.9 Pemasangan 1 M3 Batu Kosong (Aanstamping) 131,040.00 344,520.00 - 475,560.00 47,556.00 523,116.00
4 A.3.2.1.10 Pemasangan 1 M3 Pondasi Siklop, 60% beton camp. 1 SP : 2 PB : 3 Kr dan 40% Batu Belah 447,950.00 2,383,494.08 - 2,831,444.08 283,144.41 3,114,588.49
5 A.3.2.1.11 Pemasangan 1 M3 Pondasi Sumuran, diameter dalam 100 cm 345,090.00 689,280.08 - 1,034,370.08 103,437.01 1,137,807.09
6 A.3.2.1.11a Pemasangan 1 M' Gorong2 Pondasi Sumuran, diameter dalam 70 cm 215,750.00 640,000.00 - 855,750.00 85,575.00 941,325.00

DIV. IV A.4.1.1 HARGA SATUAN PEKERJAAN BETON


1 A.4.1.1.1 Membuat 1 M3 Beton Mutu f'c = 7,4 Mpa (K.100), Slump (12 ± 2) cm, w/c = 0,87 197,580.00 925,640.33 - 1,123,220.33 112,322.03 1,235,542.37
2 A.4.1.1.2 Membuat 1 M3 Beton Mutu f'c = 9,8 Mpa (K.125), Slump (12 ± 2) cm, w/c = 0,78 197,580.00 969,052.28 - 1,166,632.28 116,663.23 1,283,295.51
3 A.4.1.1.3 Membuat 1 M3 Beton Mutu f'c = 12,2 Mpa (K.150), Slump (12 ± 2) cm, w/c = 0,72 197,580.00 1,002,280.51 - 1,199,860.51 119,986.05 1,319,846.56
4 A.4.1.1.4 Membuat 1 M3 Lantai Kerja Beton Mutu f'c = 7,4 Mpa (K.100), Slump (3 - 6) cm, w/c = 0,87 143,600.00 907,540.52 - 1,051,140.52 105,114.05 1,156,254.58
5 A.4.1.1.5 Membuat 1 M3 Beton Mutu f'c = 14,5 Mpa (K.175), Slump (12 ± 2) cm, w/c = 0,66 197,580.00 1,042,531.10 - 1,240,111.10 124,011.11 1,364,122.21
6 A.4.1.1.6 Membuat 1 M3 Beton Mutu f'c = 16,9 Mpa (K.200), Slump (12 ± 2) cm, w/c = 0,61 197,580.00 1,079,485.96 - 1,277,065.96 127,706.60 1,404,772.56
7 A.4.1.1.7 Membuat 1 M3 Beton Mutu f'c = 19,3 Mpa (K.225), Slump (12 ± 2) cm, w/c = 0,58 197,580.00 1,109,431.99 - 1,307,011.99 130,701.20 1,437,713.19
8 A.4.1.1.8 Membuat 1 M3 Beton Mutu f'c = 21,7 Mpa (K.250), Slump (12 ± 2) cm, w/c = 0,56 197,580.00 1,126,280.40 - 1,323,860.40 132,386.04 1,456,246.44
9 A.4.1.1.9 Membuat 1 M3 Beton Mutu f'c = 24,0 Mpa (K.275), Slump (12 ± 2) cm, w/c = 0,53 197,580.00 1,155,318.45 - 1,352,898.45 135,289.85 1,488,188.30
10 A.4.1.1.10 Membuat 1 M3 Beton Mutu f'c = 26,4 Mpa (K.300), Slump (12 ± 2) cm, w/c = 0,52 197,580.00 1,164,197.37 - 1,361,777.37 136,177.74 1,497,955.11
11 A.4.1.1.11 Membuat 1 M3 Beton Mutu f'c = 28,8 Mpa (K.325), Slump (12 ± 2) cm, w/c = 0,49 251,300.00 1,198,387.70 - 1,449,687.70 144,968.77 1,594,656.47
12 A.4.1.1.12 Membuat 1 M3 Beton Mutu f'c = 31,2 Mpa (K.350), Slump (12 ± 2) cm, w/c = 0,48 251,300.00 1,210,083.84 - 1,461,383.84 146,138.38 1,607,522.22
13 A.4.1.1.17 Pembesian 1 Kg dengan besi polos (dihitung per 10 kg) 1,689.00 14,061.08 - 15,750.08 1,575.01 17,325.08
14 A.4.1.1.17a Pembesian 1 Kg dengan besi Ulir (dihitung per 10 kg) 1,689.00 14,061.08 - 15,750.08 1,575.01 17,325.08
15 A.4.1.1.18 Pemasangan 10 Kg Kabel Presstressed Polos/Strands 12,080.00 139,240.50 - 151,320.50 15,132.05 166,452.55
16 A.4.1.1.20 Pemasangan 1 M2 Bekisting untuk Pondasi Untuk 3x pakai ..................................................................
87,360.00 31,650.00 - 119,010.00 11,901.00 130,911.00
17 A.4.1.1.21 Pemasangan 1 M2 Bekisting untuk Sloof Untuk 3x pakai ..................................................................
87,360.00 35,325.00 - 122,685.00 12,268.50 134,953.50
18 A.4.1.1.22 Pemasangan 1 M2 Bekisting untuk Kolom Untuk 3x pakai ..................................................................
110,880.00 83,390.17 - 194,270.17 19,427.02 213,697.18
19 A.4.1.1.23 Pemasangan 1 M2 Bekisting untuk Balok Untuk 3x pakai ..................................................................
110,880.00 87,590.17 - 198,470.17 19,847.02 218,317.18
20 A.4.1.1.24 Pemasangan 1 M2 Bekisting untuk Lantai Untuk 3x pakai ..................................................................
110,880.00 95,850.17 - 206,730.17 20,673.02 227,403.18
21 A.4.1.1.25 Pemasangan 1 M2 Bekisting untuk Dinding Untuk 3x pakai ..................................................................
110,880.00 86,155.17 - 197,035.17 19,703.52 216,738.68
22 A.4.1.1.26 Pemasangan 1 M2 Bekisting untuk Tangga 110,880.00 75,915.17 - 186,795.17 18,679.52 205,474.68
23 A.4.1.1.SPL-1 Pemasangan 1 M2 Bondek untuk Plat Lantai Beton 16,800.00 111,404.40 - 128,204.40 12,820.44 141,024.84
24 A.4.1.1.SPL-2 Pembesian 1 M2 dengan Besi Wiremesh M8 16,890.00 100,161.08 - 117,051.08 11,705.11 128,756.18
KODE HARGA (Rp.) JUMLAH OVERHEAD & JUMLAH TOTAL
NO. URAIAN PEKERJAAN KET.
ANALISA TENAGA BAHAN PERALATAN (Rp.) PROFIT (Rp.) (Rp.)
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
DIV. V A.4.2.1 HARGA SATUAN PEKERJAAN BESI DAN ALUMINIUM
1 A.4.2.1.1 Pemasangan 1 Kg Besi Profil 14,430.00 21,562.50 - 35,992.50 3,599.25 39,591.75
2 A.4.2.1.5 Pengerjaan 1 cm Pengelasan dengan Las Listrik (dihitung per 10 cm Pengelasan) 672.00 2,020.00 - 2,692.00 269.20 2,961.20
3 A.4.2.1.18 Pemasangan 1 M' Talang Datar/Jurai Seng BJLS 28 Lebar 90 cm 47,110.00 96,726.93 - 143,836.93 14,383.69 158,220.62
4 A.4.2.1.22 1 M2 Pemasangan Rangka Besi Hollow 1x (20.40.2 + 40.40.2) mm, Modul 60 x 60 cm, Plafond 84,175.00 70,200.00 - 154,375.00 15,437.50 169,812.50
5 A.4.2.1.25 1 M' Pemasangan Pipa Besi diameter 2" (Medium A) 41,560.00 195,750.00 - 237,310.00 23,731.00 261,041.00
6 A.4.2.1.25a 1 M' Pekerjaan Pipa Besi dia. 2", Medium A (Konstruksi Kuda-kuda) 61,500.00 195,750.00 - 257,250.00 25,725.00 282,975.00
7 A.4.2.1.26 1 M' Pemasangan Pipa Besi diameter 3" (Medium A) 45,545.00 304,500.00 - 350,045.00 35,004.50 385,049.50
8 A.4.2.1.26a 1 M' Pemasangan Pipa Besi diameter 3" Medium A (Konstruksi Kuda-kuda) 73,800.00 304,500.00 - 378,300.00 37,830.00 416,130.00
9 A.4.2.1.SPL-2 1 M' Pekerjaan Besi Kotak 4x6 cm, tebal 3 mm (Gording) 36,900.00 74,790.00 - 111,690.00 11,169.00 122,859.00
10 A.4.2.1.SPL-3 1 M' Pekerjaan Besi Kotak 4x4 cm, tebal 2,8 mm (Rangka Atap/Gording) 24,600.00 55,515.00 - 80,115.00 8,011.50 88,126.50
11 A.4.2.1.SPL-4 1 M' Pekerjaan Besi Kotak 5x5 cm, tebal 3 mm (Rangka Atap) 24,600.00 74,925.00 - 99,525.00 9,952.50 109,477.50
12 A.4.2.1.SPL-5 1 M2 Pekerjaan Besi Pagar Besi 6x6 cm + 3x6 cm + Besi Beton Kotak 12.12 369,000.00 717,330.00 - 1,086,330.00 108,633.00 1,194,963.00
13 A.4.2.1.SPL-6 1 M' Pekerjaan Pagar BRC lengkap dengan Tiang, Type HD 53,240.00 535,111.50 - 588,351.50 58,835.15 647,186.65
14 A.4.2.1.SPL-7 1 M' Pekerjaan Kusen Aluminium 4", Silver 33,600.00 142,440.00 - 176,040.00 17,604.00 193,644.00
15 A.4.2.1.SPL-8 1 M2 Pemasangan Alumunium Composite Panel PVDF 37,500.00 817,005.50 2,500.00 857,005.50 85,700.55 942,706.05
DIV. VI A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING
1 A.4.4.1.1 Pemasangan 1 M2 Dinding Bata Merah (5 x 11 x 22) cm, tebal 1 batu Campuran 1 SP : 2 PP 86,300.00 212,512.50 - 298,812.50 29,881.25 328,693.75
2 A.4.4.1.7 Pemasangan 1 M2 Dinding Bata Merah (5 x 11 x 22) cm, tebal 1/2 batu Campuran 1 SP : 2 PP 43,150.00 101,396.25 - 144,546.25 14,454.63 159,000.88
3 A.4.4.1.10 Pemasangan 1 M2 Dinding Bata Merah (5 x 11 x 22) cm, tebal 1/2 batu Campuran 1 SP : 5 PP 43,150.00 88,371.00 - 131,521.00 13,152.10 144,673.10
DIV. VII A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
1 A.4.4.2.2 Pemasangan 1 M2 Plesteran Campuran 1 SP : 2 PP, Tebal 15 mm 50,400.00 20,602.80 - 71,002.80 7,100.28 78,103.08
A.4.4.2.2a Pemasangan 1 M2 Plesteran Screed Campuran 1 SP : 2 PP, Tebal 15 mm 50,400.00 20,602.80 - 71,002.80 7,100.28 78,103.08
2 A.4.4.2.3 Pemasangan 1 M2 Plesteran Campuran 1 SP : 3 PP, Tebal 15 mm 50,400.00 17,422.20 - 67,822.20 6,782.22 74,604.42
3 A.4.4.2.4 Pemasangan 1 M2 Plesteran Campuran 1 SP : 4 PP, Tebal 15 mm 50,400.00 15,228.00 - 65,628.00 6,562.80 72,190.80
4 A.4.4.2.5 Pemasangan 1 M2 Plesteran Campuran 1 SP : 5 PP, Tebal 15 mm 50,400.00 14,014.80 - 64,414.80 6,441.48 70,856.28
5 A.4.4.2.16 Pemasangan 1 M2 Plesteran Campuran 1 SP : 5 PP, Tebal 20 mm 67,420.00 18,761.40 - 86,181.40 8,618.14 94,799.54
6 A.4.4.2.27 Pemasangan 1 M2 Acian 20,160.00 5,118.75 - 25,278.75 2,527.88 27,806.63
DIV. VIII A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
1 A.4.4.3.4 Pemasangan 1 M2 Lantai Ubin Warna Ukuran 40 cm x 40 cm 42,000.00 177,865.40 - 219,865.40 21,986.54 241,851.94
2 A.4.4.3.5 Pemasangan 1 M2 Lantai Ubin Warna Ukuran 30 cm x 30 cm 43,680.00 176,083.50 - 219,763.50 21,976.35 241,739.85
3 A.4.4.3.20 Pemasangan 1 M' Plint Ubin Warna Ukuran 10 cm x 30 cm 21,700.00 16,125.80 - 37,825.80 3,782.58 41,608.38
4 A.4.4.3.21 Pemasangan 1 M' Plint Ubin Warna Ukuran 10 cm x 40 cm 21,700.00 16,931.30 - 38,631.30 3,863.13 42,494.43
5 A.4.4.3.23 Pemasangan 1 M' Plint Keramik Granit Ukuran 10 cm x 60 cm (hitam) 21,700.00 33,881.30 - 55,581.30 5,558.13 61,139.43
6 A.4.4.3.33 Pemasangan 1 M2 Lantai Keramik Granit Ukuran 60 cm x 60 cm (putih) 84,000.00 284,136.21 - 368,136.21 36,813.62 404,949.83
7 A.4.4.3.33a Pemasangan 1 M2 Lantai Keramik Granit Ukuran 60 cm x 60 cm (hitam) 84,000.00 366,648.21 - 450,648.21 45,064.82 495,713.03
8 A.4.4.3.34 Pemasangan 1 M2 Lantai Keramik Ukuran 40 cm x 40 cm 84,000.00 187,854.21 - 271,854.21 27,185.42 299,039.63
9 A.4.4.3.35 Pemasangan 1 M2 Lantai Keramik Ukuran 30 cm x 30 cm 84,000.00 176,083.50 - 260,083.50 26,008.35 286,091.85
10 A.4.4.3.54a Pemasangan 1 M2 Dinding Keramik 30 cm x 60 cm 117,600.00 207,884.02 - 325,484.02 32,548.40 358,032.42
11 A.4.4.3.54b Pemasangan 1 M2 Dinding Granit 60 cm x 60 cm, putih 117,600.00 287,924.02 - 405,524.02 40,552.40 446,076.42
KODE HARGA (Rp.) JUMLAH OVERHEAD & JUMLAH TOTAL
NO. URAIAN PEKERJAAN KET.
ANALISA TENAGA BAHAN PERALATAN (Rp.) PROFIT (Rp.) (Rp.)
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
DIV. IX A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)
1 A.4.4.5.7a Pemasangan 1 m2 Langit-langit Gypsum Board Ukuran (120x240x9) mm, Tebal 9 mm 16,800.00 32,888.45 - 49,688.45 4,968.85 54,657.30
2 A.4.4.5.7b Pemasangan 1 m2 Langit-langit Kalsiboard Ukuran (120x240x6) mm, Tebal 6 mm 16,800.00 30,431.45 - 47,231.45 4,723.15 51,954.60
3 A.4.4.5.9 Pemasangan 1 m' List Langit-langit Kayu Profil 12,080.00 11,225.00 - 23,305.00 2,330.50 25,635.50
4 A.4.4.5.10 Pemasangan 1 m' List Langit-langit, Gypsum Profil 9 x 9 cm 19,240.00 31,695.45 - 50,935.45 5,093.55 56,029.00
5 A.4.4.5.10a Pemasangan 1 m' List Langit-langit, Gypsum Profil 5 x 5 cm 16,835.00 21,949.95 - 38,784.95 3,878.50 42,663.45

DIV. X A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP


1 A.4.5.2.32 Pemasangan 1 M2 Genteng Metal 33,600.00 97,100.04 - 130,700.04 13,070.00 143,770.04
2 A.4.5.2.36 Pemasangan 1 M' Nok Genteng Metal 45,625.00 47,664.75 - 93,289.75 9,328.98 102,618.73
3 A.4.5.2.40 Pemasangan 1 M2 Atap Spandek (Model Standar) 122,910.00 70,985.90 - 193,895.90 19,389.59 213,285.49
4 A.4.5.2.40a Pemasangan 1 M2 Atap Spandek (Model Melengkung) 122,910.00 141,385.90 - 264,295.90 26,429.59 290,725.49
5 A.4.5.2.41 Pemasangan 1 M' Nok Atap Aluminium 159,500.00 43,171.80 - 202,671.80 20,267.18 222,938.98
6 A.4.5.2.Spl-1 Pemasangan 1 M2 Rangka Atap Baja Ringan 15,150.00 190,404.40 5,000.00 210,554.40 21,055.44 231,609.84
7 A.4.5.2.Spl-2 Pemasangan 1 M2 Melapis Atap dengan Aluminium Foil 15,150.00 70,400.00 5,000.00 90,550.00 9,055.00 99,605.00

DIV. XI A.4.6.1 HARGA SATUAN PEKERJAAN KAYU


1 A.4.6.1.1 Pembuatan dan Pemasangan 1 M3 Kusen Pintu dan Jendela, Kayu Kelas I 3,713,500.00 6,959,305.00 - 10,672,805.00 1,067,280.50 11,740,085.50
2 A.4.6.1.5 Pembuatan dan Pemasangan 1 M2 Daun Pintu Panel, Kayu Kelas I (atau kelas II) 530,500.00 264,862.50 - 795,362.50 79,536.25 874,898.75
3 A.4.6.1.6 Pembuatan dan Pemasangan 1 M2 Pintu dan Jendela Kaca, Kayu Kelas I (atau kelas II) 424,400.00 158,917.50 - 583,317.50 58,331.75 641,649.25
4 A.4.6.1.7 Pembuatan dan Pemasangan 1 M2 Pintu dan Jendela Jalusi, Kayu Kelas I (atau kelas II) 530,500.00 415,558.50 - 946,058.50 94,605.85 1,040,664.35
5 A.4.6.1.8 Pembuatan 1 M2 Daun Pintu Multipleks Rangkap, Rangka Kayu Kelas II (Lapis HPL + Almn. plat) 424,400.00 537,637.00 - 962,037.00 96,203.70 1,058,240.70
6 A.4.6.1.8a Pembuatan 1 M2 Daun Pintu Plywood Rangkap, Rangka Kayu Kelas II Tertutup (Lapis HPL) 531,600.00 586,087.00 - 1,117,687.00 111,768.70 1,229,455.70
7 A.4.6.1.21a Pemasangan 1 M' Lijsplank Ukuran (1.8 x 20) cm, Woodplank/Kalsiplank 37,050.00 48,714.75 - 85,764.75 8,576.48 94,341.23
8 A.4.6.1.21b Pemasangan 1 M' Lijsplank Ukuran 2x (1.8 x 20) cm, Woodplank/Kalsiplank 74,100.00 97,429.50 - 171,529.50 17,152.95 188,682.45
DIV. XII A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI DAN KACA
1 A.4.6.2.2 Pemasangan 1 Buah Kunci Tanam Biasa 73,950.00 250,000.00 - 323,950.00 32,395.00 356,345.00
2 A.4.6.2.3 Pemasangan 1 Buah Kunci Kamar Mandi 73,280.00 172,500.00 - 245,780.00 24,578.00 270,358.00
3 A.4.6.2.5 Pemasangan 1 Buah Engsel Pintu 23,188.00 35,000.00 - 58,188.00 5,818.80 64,006.80
4 A.4.6.2.6 Pemasangan 1 Buah Engsel Jendela Kupu-kupu 15,455.00 22,000.00 - 37,455.00 3,745.50 41,200.50
5 A.4.6.2.7 Pemasangan 1 Buah Engsel Angin (Casement, tipe sedang) 38,055.00 45,000.00 - 83,055.00 8,305.50 91,360.50
6 A.4.6.2.9 Pemasangan 1 Buah Kait Angin 23,925.00 23,000.00 - 46,925.00 4,692.50 51,617.50
7 A.4.6.2.17 Pemasangan 1 M2 Kaca Tebal 5 mm (polos) 23,182.50 205,900.00 - 229,082.50 22,908.25 251,990.75
8 A.4.6.2.18 Pemasangan 1 M2 Kaca Tebal 10 mm 26,273.50 1,191,360.00 - 1,217,633.50 121,763.35 1,339,396.85
9 A.4.6.2.19 Pemasangan 1 M2 Kaca Polos Tebal 12 mm, Tempered 38,637.50 1,983,360.00 - 2,021,997.50 202,199.75 2,224,197.25
DIV. XIII A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN
1 A.4.7.1.10 1 M2 Pengecatan Tembok Baru (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup) 11,265.00 12,150.00 - 23,415.00 2,341.50 25,756.50 Dalam
2 A.4.7.1.10a 1 M2 Pengecatan Tembok Baru (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup) 11,265.00 12,150.00 - 23,415.00 2,341.50 25,756.50 Luar
3 A.4.7.1.11 1 M2 Pengecatan Tembok Lama (1 lapis cat dasar, 2 lapis cat penutup) 8,940.00 9,540.00 - 18,480.00 1,848.00 20,328.00
4 A.4.7.1.16 1 M2 Pengecatan Permukaan Besi dengan Cat Epoxy Anti Karat 31,075.00 14,085.00 - 45,160.00 4,516.00 49,676.00
KODE HARGA (Rp.) JUMLAH OVERHEAD & JUMLAH TOTAL
NO. URAIAN PEKERJAAN KET.
ANALISA TENAGA BAHAN PERALATAN (Rp.) PROFIT (Rp.) (Rp.)
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
DIV. XIV A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG
1 A.5.1.1.1 Pemasangan 1 Buah Closet Duduk / Monoblock 459,100.00 3,074,000.00 - 3,533,100.00 353,310.00 3,886,410.00
2 A.5.1.1.2 Pemasangan 1 Buah Closet Jongkok / Monoblock 459,100.00 803,321.00 - 1,262,421.00 126,242.10 1,388,663.10
3 A.5.1.1.5 Pemasangan 1 Buah Wastafel 325,600.00 1,075,700.00 - 1,401,300.00 140,130.00 1,541,430.00
4 A.5.1.1.12 Pemasangan 1 Buah Bak Cuci Piring Stainless Steel 47,850.00 675,000.00 - 722,850.00 72,285.00 795,135.00
5 A.5.1.1.14 Pemasangan 1 Buah Floor Drain 15,950.00 95,000.00 - 110,950.00 11,095.00 122,045.00
6 A.5.1.1.14a Pemasangan 1 Buah Roof Drain dia. 3" 31,900.00 135,000.00 - 166,900.00 16,690.00 183,590.00
7 A.5.1.1.18 Pemasangan 1 Buah Kran Air diameter 1/2" atau 3/4" 59,450.00 100,087.50 - 159,537.50 15,953.75 175,491.25
8 A.5.1.1.26 Pemasangan 1 M' Pipa PVC tipe AW 3/4" 12,160.00 12,400.00 - 24,560.00 2,456.00 27,016.00
9 A.5.1.1.29 Pemasangan 1 M' Pipa PVC tipe AW 2" 18,240.00 43,136.50 - 61,376.50 6,137.65 67,514.15
10 A.5.1.1.31 Pemasangan 1 M' Pipa PVC tipe AW 3" 27,305.00 87,978.00 - 115,283.00 11,528.30 126,811.30
11 A.5.1.1.32 Pemasangan 1 M' Pipa PVC tipe AW 4" 27,305.00 132,146.80 - 159,451.80 15,945.18 175,396.98

DIV. XVIII A.8.5.1 HARGA SATUAN PEKERJAAN ELEKTRIKAL


1 A.8.5.1.1 Pemasangan 1 Unit Panel Penerangan / Stop Kontak 1,476,000.00 6,549,000.00 - 8,025,000.00 802,500.00 8,827,500.00
2 A.8.5.1.2 Pemasangan 1 Unit Panel AC 1,968,000.00 7,722,000.00 - 9,690,000.00 969,000.00 10,659,000.00
3 A.8.5.1.3 Pemasangan 1 Meter Kabel NYFGbY 4 x 50 mm 30,800.00 577,500.00 - 608,300.00 60,830.00 669,130.00
4 A.8.5.1.4 Pemasangan 1 Meter Kabel NYFGbY 4 x 70 mm 33,200.00 675,000.00 - 708,200.00 70,820.00 779,020.00
5 A.8.5.1.5 Pemasangan 1 Titik Instalasi Penerangan 94,200.00 256,250.00 - 350,450.00 35,045.00 385,495.00
6 A.8.5.1.6 Pemasangan 1 Titik Instalasi Stop Kontak 117,750.00 256,250.00 - 374,000.00 37,400.00 411,400.00
7 A.8.5.1.6 Pemasangan 1 Titik Instalasi Saklar 480,150.00
A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN

A.2.2.1.1 Pembuatan 1 M2 Pagar Sementara dari Kayu Tinggi 2 Meter


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.200 90,000.00 18,000.00
Tukang Kayu L.02 OH 0.400 130,000.00 52,000.00
Kepala Tukang L.03 OH 0.020 150,000.00 3,000.00
Mandor L.04 OH 0.020 110,000.00 2,200.00

Jumlah Harga Tenaga .................................................................. 75,200.00


B. BAHAN
Dolken kayu dia. 8 - 10/400 cm Batang 1.250 9,345.00 11,681.25
Semen Portland Kg 2.500 1,575.00 3,937.50
Pasir beton M3 0.005 225,000.00 1,125.00
Koral beton M3 0.009 449,263.00 4,043.37
Kayu 5/7 - Kelas II M3 0.072 4,200,000.00 302,400.00
Paku biasa 2" - 5" Kg 0.060 20,000.00 1,200.00

Jumlah Harga Bahan .................................................................. 324,387.12


C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 399,587.12
E. Overhead & Profit 10% X D 39,958.71
F. Harga Satuan Pekerjaan (D+E) 439,545.83

A.2.2.1.2 Pembuatan 1 M2 Pagar Sementara dari Seng Gelombang Tinggi 2 Meter


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.200 90,000.00 18,000.00
Tukang Kayu L.02 OH 0.400 130,000.00 52,000.00
Kepala Tukang L.03 OH 0.020 150,000.00 3,000.00
Mandor L.04 OH 0.020 110,000.00 2,200.00

Jumlah Harga Tenaga .................................................................. 75,200.00


B. BAHAN
Dolken kayu dia. 8 - 10/400 cm Batang 1.250 9,345.00 11,681.25
Semen Portland Kg 2.500 1,575.00 3,937.50
Seng gelombang Lbr 1.200 40,000.00 48,000.00
Pasir beton M3 0.005 225,000.00 1,125.00
Koral beton M3 0.009 449,263.00 4,043.37
Kayu 5/7 - Kelas III M3 0.072 3,360,000.00 241,920.00
Paku biasa 2" - 5" Kg 0.060 20,000.00 1,200.00
Meni besi Liter 0.450 27,000.00 12,150.00

Jumlah Harga Bahan .................................................................. 324,057.12


C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 399,257.12
E. Overhead & Profit 10% X D 39,925.71
F. Harga Satuan Pekerjaan (D+E) 439,182.83
A.2.2.1.4 Pengukuran dan Pemasangan 1 M' Bouwplank
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.100 90,000.00 9,000.00
Tukang Kayu L.02 OH 0.100 130,000.00 13,000.00
Kepala Tukang L.03 OH 0.010 150,000.00 1,500.00
Mandor L.04 OH 0.005 110,000.00 550.00

Jumlah Harga Tenaga .................................................................. 24,050.00


B. BAHAN
Kayu 5/7 - Kelas II M3 0.012 4,200,000.00 50,400.00
Paku biasa 2" - 3" Kg 0.020 20,000.00 400.00
Kayu papan 3/20 - Kelas II M3 0.007 4,200,000.00 29,400.00

Jumlah Harga Bahan .................................................................. 80,200.00


C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 104,250.00
E. Overhead & Profit 10% X D 10,425.00
F. Harga Satuan Pekerjaan (D+E) 114,675.00
A.2.3.1 HARGA SATUAN PEKERJAAN TANAH

A.2.3.1.1 Penggalian 1 M3 Tanah Biasa Sedalam 1 M


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.750 90,000.00 67,500.00
Mandor L.04 OH 0.025 110,000.00 2,750.00

Jumlah Harga Tenaga ..................................................................


70,250.00
B. BAHAN

Jumlah Harga Bahan .................................................................. -


C. PERALATAN
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 70,250.00
E. Overhead & Profit 10% X D 7,025.00
F. Harga Satuan Pekerjaan (D+E) 77,275.00

A.2.3.1.2 Penggalian 1 M3 Tanah Biasa Sedalam 2 M


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.900 90,000.00 81,000.00
Mandor L.04 OH 0.045 110,000.00 4,950.00

Jumlah Harga Tenaga ..................................................................


85,950.00
B. BAHAN

Jumlah Harga Bahan .................................................................. -


C. PERALATAN
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 85,950.00
E. Overhead & Profit 10% X D 8,595.00
F. Harga Satuan Pekerjaan (D+E) 94,545.00
A.2.3.1.3 Penggalian 1 M3 Tanah Biasa Sedalam 3 M
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 1.050 90,000.00 94,500.00
Mandor L.04 OH 0.067 110,000.00 7,370.00

Jumlah Harga Tenaga ..................................................................


101,870.00
B. BAHAN

Jumlah Harga Bahan .................................................................. -


C. PERALATAN
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 101,870.00
E. Overhead & Profit 10% X D 10,187.00
F. Harga Satuan Pekerjaan (D+E) 112,057.00

A.2.3.1.9 Pengurugan Kembali 1 M3 Galian Tanah


Pengurugan kembali 1 M3 dihitung dari 1/3 kali dari koefisien pekerjaan galian
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.500 90,000.00 45,000.00
Mandor L.04 OH 0.050 110,000.00 5,500.00

Jumlah Harga Tenaga ..................................................................


50,500.00
B. BAHAN

Jumlah Harga Bahan .................................................................. -


C. PERALATAN
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 50,500.00
E. Overhead & Profit 10% X D 5,050.00
F. Harga Satuan Pekerjaan (D+E) 55,550.00
A.2.3.1.11 Pengurugan 1 M3 dengan Pasir Urug
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.300 90,000.00 27,000.00
Mandor L.04 OH 0.010 110,000.00 1,100.00

Jumlah Harga Tenaga ..................................................................


28,100.00
B. BAHAN
Pasir urug M3 1.200 160,000.00 192,000.00

Jumlah Harga Bahan ..................................................................


192,000.00
C. PERALATAN
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 220,100.00
E. Overhead & Profit 10% X D 22,010.00
F. Harga Satuan Pekerjaan (D+E) 242,110.00

A.2.3.1.15 Pengurugan 1 M3 dengan Tanah Urug


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.250 90,000.00 22,500.00
Mandor L.04 OH 0.025 110,000.00 2,750.00

Jumlah Harga Tenaga ..................................................................


25,250.00
B. BAHAN
Tanah urug M3 1.200 60,000.00 72,000.00

Jumlah Harga Bahan ..................................................................


72,000.00
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 97,250.00
E. Overhead & Profit 10% X D 9,725.00
F. Harga Satuan Pekerjaan (D+E) 106,975.00
A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI

A.3.2.1.2 Pemasangan 1 M3 Pondasi Batu Belah Campuran 1 SP : 4 PP


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 1.500 90,000.00 135,000.00
Tukang Batu L.02 OH 0.750 130,000.00 97,500.00
Kepala Tukang L.03 OH 0.075 150,000.00 11,250.00
Mandor L.04 OH 0.075 110,000.00 8,250.00

Jumlah Harga Tenaga ..................................................................


252,000.00
B. BAHAN
Batu belah M3 1.200 229,500.00 275,400.00
Semen Portland Kg 163.000 1,575.00 256,725.00
Pasir pasang M3 0.520 225,000.00 117,000.00

Jumlah Harga Bahan ..................................................................


649,125.00
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 901,125.00
E. Overhead & Profit 10% X D 90,112.50
F. Harga Satuan Pekerjaan (D+E) 991,237.50

A.3.2.1.3 Pemasangan 1 M3 Pondasi Batu Belah Campuran 1 SP : 5 PP


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 1.500 90,000.00 135,000.00
Tukang Batu L.02 OH 0.750 130,000.00 97,500.00
Kepala Tukang L.03 OH 0.075 150,000.00 11,250.00
Mandor L.04 OH 0.075 110,000.00 8,250.00

Jumlah Harga Tenaga ..................................................................


252,000.00
B. BAHAN
Batu belah M3 1.200 229,500.00 275,400.00
Semen Portland Kg 136.000 1,575.00 214,200.00
Pasir pasang M3 0.544 225,000.00 122,400.00

Jumlah Harga Bahan ..................................................................


612,000.00
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 864,000.00
E. Overhead & Profit 10% X D 86,400.00
F. Harga Satuan Pekerjaan (D+E) 950,400.00

A.3.2.1.9 Pemasangan 1 M3 Batu Kosong (Aanstamping)


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.780 90,000.00 70,200.00
Tukang Batu L.02 OH 0.390 130,000.00 50,700.00
Kepala Tukang L.03 OH 0.039 150,000.00 5,850.00
Mandor L.04 OH 0.039 110,000.00 4,290.00

Jumlah Harga Tenaga ..................................................................


131,040.00
B. BAHAN
Batu belah M3 1.200 229,500.00 275,400.00
Pasir urug M3 0.432 160,000.00 69,120.00

Jumlah Harga Bahan ..................................................................


344,520.00
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 475,560.00
E. Overhead & Profit 10% X D 47,556.00
F. Harga Satuan Pekerjaan (D+E) 523,116.00

A.3.2.1.10 Pemasangan 1 M3 Pondasi Siklop, 60% beton camp. 1 SP : 2 PB : 3 Kr dan 40% Batu Belah
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 3.400 90,000.00 306,000.00
Tukang Batu L.02 OH 0.850 130,000.00 110,500.00
Kepala Tukang L.03 OH 0.085 150,000.00 12,750.00
Mandor L.04 OH 0.170 110,000.00 18,700.00

Jumlah Harga Tenaga ..................................................................


447,950.00
B. BAHAN
Batu belah M3 0.480 229,500.00 110,160.00
Semen Portland Kg 194.000 1,575.00 305,550.00
Pasir beton M3 0.312 225,000.00 70,200.00
Kerikil M3 0.468 449,263.00 210,255.08
Besi beton Kg 126.000 13,000.00 1,638,000.00
Kawat beton Kg 1.800 27,405.00 49,329.00

Jumlah Harga Bahan ..................................................................


2,383,494.08
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 2,831,444.08
E. Overhead & Profit 10% X D 283,144.41
F. Harga Satuan Pekerjaan (D+E) 3,114,588.49

A.3.2.1.11 Pemasangan 1 M3 Pondasi Sumuran, diameter dalam 100 cm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 2.400 90,000.00 216,000.00
Tukang Batu L.02 OH 0.800 130,000.00 104,000.00
Kepala Tukang L.03 OH 0.080 150,000.00 12,000.00
Mandor L.04 OH 0.119 110,000.00 13,090.00

Jumlah Harga Tenaga ..................................................................


345,090.00
B. BAHAN
Batu belah M3 0.450 229,500.00 103,275.00
Semen Portland Kg 194.000 1,575.00 305,550.00
Pasir beton M3 0.312 225,000.00 70,200.00
Kerikil M3 0.468 449,263.00 210,255.08

Jumlah Harga Bahan ..................................................................


689,280.08
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 1,034,370.08
E. Overhead & Profit 10% X D 103,437.01
F. Harga Satuan Pekerjaan (D+E) 1,137,807.09

A.3.2.1.11a Pemasangan 1 M' Gorong2 Pondasi Sumuran, diameter dalam 70 cm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 1.500 90,000.00 135,000.00
Tukang Batu L.02 OH 0.500 130,000.00 65,000.00
Kepala Tukang L.03 OH 0.050 150,000.00 7,500.00
Mandor L.04 OH 0.075 110,000.00 8,250.00

Jumlah Harga Tenaga ..................................................................


215,750.00
B. BAHAN
Gorong2 dia. 70 cm (dalam) bh 2.000 320,000.00 640,000.00

Jumlah Harga Bahan ..................................................................


640,000.00
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 855,750.00
E. Overhead & Profit 10% X D 85,575.00
F. Harga Satuan Pekerjaan (D+E) 941,325.00
A.4.1.1 HARGA SATUAN PEKERJAAN BETON

A.4.1.1.1 Membuat 1 M3 Beton Mutu f'c = 7,4 Mpa (K.100), Slump (12 ± 2) cm, w/c = 0,87
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 1.650 90,000.00 148,500.00
Tukang Batu L.02 OH 0.275 130,000.00 35,750.00
Kepala Tukang L.03 OH 0.028 150,000.00 4,200.00
Mandor L.04 OH 0.083 110,000.00 9,130.00

Jumlah Harga Tenaga ..................................................................


197,580.00
B. BAHAN
Semen Portland Kg 247.000 1,575.00 389,025.00
Pasir beton Kg 869.000 160.71 139,660.71
Kerikil (maks 30 mm) Kg 999.000 332.79 332,454.62
Air Liter 215.000 300.00 64,500.00

Jumlah Harga Bahan ..................................................................


925,640.33
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 1,123,220.33
E. Overhead & Profit 10% X D 112,322.03
F. Harga Satuan Pekerjaan (D+E) 1,235,542.37

A.4.1.1.2 Membuat 1 M3 Beton Mutu f'c = 9,8 Mpa (K.125), Slump (12 ± 2) cm, w/c = 0,78
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 1.650 90,000.00 148,500.00
Tukang Batu L.02 OH 0.275 130,000.00 35,750.00
Kepala Tukang L.03 OH 0.028 150,000.00 4,200.00
Mandor L.04 OH 0.083 110,000.00 9,130.00

Jumlah Harga Tenaga ..................................................................


197,580.00
B. BAHAN
Semen Portland Kg 276.000 1,575.00 434,700.00
Pasir beton Kg 828.000 160.71 133,071.43
Kerikil (maks 30 mm) Kg 1,012.000 332.79 336,780.86
Air Liter 215.000 300.00 64,500.00

Jumlah Harga Bahan ..................................................................


969,052.28
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 1,166,632.28
E. Overhead & Profit 10% X D 116,663.23
F. Harga Satuan Pekerjaan (D+E) 1,283,295.51

A.4.1.1.3 Membuat 1 M3 Beton Mutu f'c = 12,2 Mpa (K.150), Slump (12 ± 2) cm, w/c = 0,72
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 1.650 90,000.00 148,500.00
Tukang Batu L.02 OH 0.275 130,000.00 35,750.00
Kepala Tukang L.03 OH 0.028 150,000.00 4,200.00
Mandor L.04 OH 0.083 110,000.00 9,130.00

Jumlah Harga Tenaga ..................................................................


197,580.00
B. BAHAN
Semen Portland Kg 299.000 1,575.00 470,925.00
Pasir beton Kg 799.000 160.71 128,410.71
Kerikil (maks 30 mm) Kg 1,017.000 332.79 338,444.79
Air Liter 215.000 300.00 64,500.00

Jumlah Harga Bahan ..................................................................


1,002,280.51
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 1,199,860.51
E. Overhead & Profit 10% X D 119,986.05
F. Harga Satuan Pekerjaan (D+E) 1,319,846.56
Catatan : Bobot isi pasir = 1.400 kg/m3, bobot isi kerikil = 1.350 kg/m3, Buckling factor pasir = 20 %

A.4.1.1.4 Membuat 1 M3 Lantai Kerja Beton Mutu f'c = 7,4 Mpa (K.100), Slump (3 - 6) cm, w/c = 0,87
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 1.200 90,000.00 108,000.00
Tukang Batu L.02 OH 0.200 130,000.00 26,000.00
Kepala Tukang L.03 OH 0.020 150,000.00 3,000.00
Mandor L.04 OH 0.060 110,000.00 6,600.00

Jumlah Harga Tenaga ..................................................................


143,600.00
B. BAHAN
Semen Portland Kg 230.000 1,575.00 362,250.00
Pasir beton Kg 893.000 160.71 143,517.86
Kerikil (maks 30 mm) Kg 1,027.000 332.79 341,772.67
Air Liter 200.000 300.00 60,000.00

Jumlah Harga Bahan ..................................................................


907,540.52
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 1,051,140.52
E. Overhead & Profit 10% X D 105,114.05
F. Harga Satuan Pekerjaan (D+E) 1,156,254.58

A.4.1.1.5 Membuat 1 M3 Beton Mutu f'c = 14,5 Mpa (K.175), Slump (12 ± 2) cm, w/c = 0,66
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 1.650 90,000.00 148,500.00
Tukang Batu L.02 OH 0.275 130,000.00 35,750.00
Kepala Tukang L.03 OH 0.028 150,000.00 4,200.00
Mandor L.04 OH 0.083 110,000.00 9,130.00

Jumlah Harga Tenaga ..................................................................


197,580.00
B. BAHAN
Semen Portland Kg 326.000 1,575.00 513,450.00
Pasir beton Kg 760.000 160.71 122,142.86
Kerikil (maks 30 mm) Kg 1,029.000 332.79 342,438.24
Air Liter 215.000 300.00 64,500.00

Jumlah Harga Bahan ..................................................................


1,042,531.10
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 1,240,111.10
E. Overhead & Profit 10% X D 124,011.11
F. Harga Satuan Pekerjaan (D+E) 1,364,122.21

A.4.1.1.6 Membuat 1 M3 Beton Mutu f'c = 16,9 Mpa (K.200), Slump (12 ± 2) cm, w/c = 0,61
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 1.650 90,000.00 148,500.00
Tukang Batu L.02 OH 0.275 130,000.00 35,750.00
Kepala Tukang L.03 OH 0.028 150,000.00 4,200.00
Mandor L.04 OH 0.083 110,000.00 9,130.00

Jumlah Harga Tenaga ..................................................................


197,580.00
B. BAHAN
Semen Portland Kg 352.000 1,575.00 554,400.00
Pasir beton Kg 731.000 160.71 117,482.14
Kerikil (maks 30 mm) Kg 1,031.000 332.79 343,103.82
Air Liter 215.000 300.00 64,500.00

Jumlah Harga Bahan ..................................................................


1,079,485.96
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 1,277,065.96
E. Overhead & Profit 10% X D 127,706.60
F. Harga Satuan Pekerjaan (D+E) 1,404,772.56

A.4.1.1.7 Membuat 1 M3 Beton Mutu f'c = 19,3 Mpa (K.225), Slump (12 ± 2) cm, w/c = 0,58
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 1.650 90,000.00 148,500.00
Tukang Batu L.02 OH 0.275 130,000.00 35,750.00
Kepala Tukang L.03 OH 0.028 150,000.00 4,200.00
Mandor L.04 OH 0.083 110,000.00 9,130.00

Jumlah Harga Tenaga ..................................................................


197,580.00
B. BAHAN
Semen Portland Kg 371.000 1,575.00 584,325.00
Pasir beton Kg 698.000 160.71 112,178.57
Kerikil (maks 30 mm) Kg 1,047.000 332.79 348,428.42
Air Liter 215.000 300.00 64,500.00

Jumlah Harga Bahan ..................................................................


1,109,431.99
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 1,307,011.99
E. Overhead & Profit 10% X D 130,701.20
F. Harga Satuan Pekerjaan (D+E) 1,437,713.19

A.4.1.1.8 Membuat 1 M3 Beton Mutu f'c = 21,7 Mpa (K.250), Slump (12 ± 2) cm, w/c = 0,56
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 1.650 90,000.00 148,500.00
Tukang Batu L.02 OH 0.275 130,000.00 35,750.00
Kepala Tukang L.03 OH 0.028 150,000.00 4,200.00
Mandor L.04 OH 0.083 110,000.00 9,130.00

Jumlah Harga Tenaga ..................................................................


197,580.00
B. BAHAN
Semen Portland Kg 384.000 1,575.00 604,800.00
Pasir beton Kg 692.000 160.71 111,214.29
Kerikil (maks 30 mm) Kg 1,039.000 332.79 345,766.12
Air Liter 215.000 300.00 64,500.00

Jumlah Harga Bahan ..................................................................


1,126,280.40
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 1,323,860.40
E. Overhead & Profit 10% X D 132,386.04
F. Harga Satuan Pekerjaan (D+E) 1,456,246.44

A.4.1.1.9 Membuat 1 M3 Beton Mutu f'c = 24,0 Mpa (K.275), Slump (12 ± 2) cm, w/c = 0,53
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 1.650 90,000.00 148,500.00
Tukang Batu L.02 OH 0.275 130,000.00 35,750.00
Kepala Tukang L.03 OH 0.028 150,000.00 4,200.00
Mandor L.04 OH 0.083 110,000.00 9,130.00

Jumlah Harga Tenaga ..................................................................


197,580.00
B. BAHAN
Semen Portland Kg 406.000 1,575.00 639,450.00
Pasir beton Kg 684.000 160.71 109,928.57
Kerikil (maks 30 mm) Kg 1,026.000 332.79 341,439.88
Air Liter 215.000 300.00 64,500.00

Jumlah Harga Bahan ..................................................................


1,155,318.45
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 1,352,898.45
E. Overhead & Profit 10% X D 135,289.85
F. Harga Satuan Pekerjaan (D+E) 1,488,188.30

A.4.1.1.10 Membuat 1 M3 Beton Mutu f'c = 26,4 Mpa (K.300), Slump (12 ± 2) cm, w/c = 0,52
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 1.650 90,000.00 148,500.00
Tukang Batu L.02 OH 0.275 130,000.00 35,750.00
Kepala Tukang L.03 OH 0.028 150,000.00 4,200.00
Mandor L.04 OH 0.083 110,000.00 9,130.00

Jumlah Harga Tenaga ..................................................................


197,580.00
B. BAHAN
Semen Portland Kg 413.000 1,575.00 650,475.00
Pasir beton Kg 681.000 160.71 109,446.43
Kerikil (maks 30 mm) Kg 1,021.000 332.79 339,775.94
Air Liter 215.000 300.00 64,500.00

Jumlah Harga Bahan ..................................................................


1,164,197.37
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 1,361,777.37
E. Overhead & Profit 10% X D 136,177.74
F. Harga Satuan Pekerjaan (D+E) 1,497,955.11

A.4.1.1.11 Membuat 1 M3 Beton Mutu f'c = 28,8 Mpa (K.325), Slump (12 ± 2) cm, w/c = 0,49
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 2.100 90,000.00 189,000.00
Tukang Batu L.02 OH 0.350 130,000.00 45,500.00
Kepala Tukang L.03 OH 0.035 150,000.00 5,250.00
Mandor L.04 OH 0.105 110,000.00 11,550.00
Jumlah Harga Tenaga ..................................................................
251,300.00
B. BAHAN
Semen Portland Kg 439.000 1,575.00 691,425.00
Pasir beton Kg 670.000 160.71 107,678.57
Kerikil (maks 30 mm) Kg 1,006.000 332.79 334,784.13
Air Liter 215.000 300.00 64,500.00

Jumlah Harga Bahan ..................................................................


1,198,387.70
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 1,449,687.70
E. Overhead & Profit 10% X D 144,968.77
F. Harga Satuan Pekerjaan (D+E) 1,594,656.47

A.4.1.1.12 Membuat 1 M3 Beton Mutu f'c = 31,2 Mpa (K.350), Slump (12 ± 2) cm, w/c = 0,48
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 2.100 90,000.00 189,000.00
Tukang Batu L.02 OH 0.350 130,000.00 45,500.00
Kepala Tukang L.03 OH 0.035 150,000.00 5,250.00
Mandor L.04 OH 0.105 110,000.00 11,550.00

Jumlah Harga Tenaga ..................................................................


251,300.00
B. BAHAN
Semen Portland Kg 448.000 1,575.00 705,600.00
Pasir beton Kg 667.000 160.71 107,196.43
Kerikil (maks 30 mm) Kg 1,000.000 332.79 332,787.41
Air Liter 215.000 300.00 64,500.00

Jumlah Harga Bahan ..................................................................


1,210,083.84
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 1,461,383.84
E. Overhead & Profit 10% X D 146,138.38
F. Harga Satuan Pekerjaan (D+E) 1,607,522.22

A.4.1.1.17 Pembesian 1 Kg dengan besi polos (dihitung per 10 kg)


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.070 90,000.00 6,300.00
Tukang Besi L.02 OH 0.070 130,000.00 9,100.00
Kepala Tukang L.03 OH 0.007 150,000.00 1,050.00
Mandor L.04 OH 0.004 110,000.00 440.00

Jumlah Harga Tenaga ..................................................................


16,890.00
B. BAHAN
Besi beton (polos) Kg 10.500 13,000.00 136,500.00
Kawat beton Kg 0.150 27,405.00 4,110.75

Jumlah Harga Bahan ..................................................................


140,610.75
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 157,500.75
E. Overhead & Profit 10% X D 15,750.08
F. Harga Satuan Pekerjaan (D+E) 173,250.83
Untuk 1 Kg pekerjaan besi polos 17,325.08

A.4.1.1.17a Pembesian 1 Kg dengan besi Ulir (dihitung per 10 kg)


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.070 90,000.00 6,300.00
Tukang Besi L.02 OH 0.070 130,000.00 9,100.00
Kepala Tukang L.03 OH 0.007 150,000.00 1,050.00
Mandor L.04 OH 0.004 110,000.00 440.00

Jumlah Harga Tenaga ..................................................................


16,890.00
B. BAHAN
Besi beton (Ulir) Kg 10.500 13,000.00 136,500.00
Kawat beton Kg 0.150 27,405.00 4,110.75

Jumlah Harga Bahan ..................................................................


140,610.75
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 157,500.75
E. Overhead & Profit 10% X D 15,750.08
F. Harga Satuan Pekerjaan (D+E) 173,250.83
Untuk 1 Kg pekerjaan besi polos 17,325.08

A.4.1.1.18 Pemasangan 10 Kg Kabel Presstressed Polos/Strands


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.050 90,000.00 4,500.00
Tukang Besi L.02 OH 0.050 130,000.00 6,500.00
Kepala Tukang L.03 OH 0.005 150,000.00 750.00
Mandor L.04 OH 0.003 110,000.00 330.00

Jumlah Harga Tenaga ..................................................................


12,080.00
B. BAHAN
Besi beton (polos) M3 10.500 13,000.00 136,500.00
Kawat beton Kg 0.100 27,405.00 2,740.50

Jumlah Harga Bahan ..................................................................


139,240.50
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 151,320.50
E. Overhead & Profit 10% X D 15,132.05
F. Harga Satuan Pekerjaan (D+E) 166,452.55
Untuk 1 Kg pekerjaan Kabel Presstressed Polos/Strands 16,645.26

A.4.1.1.20 Pemasangan 1 M2 Bekisting untuk Pondasi


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.520 90,000.00 46,800.00
Tukang Kayu L.02 OH 0.260 130,000.00 33,800.00
Kepala Tukang L.03 OH 0.026 150,000.00 3,900.00
Mandor L.04 OH 0.026 110,000.00 2,860.00

Jumlah Harga Tenaga ..................................................................


87,360.00
B. BAHAN
Kayu kelas III (papan) M3 0.040 2,205,000.00 88,200.00
Paku 5 - 12 cm Kg 0.300 20,000.00 6,000.00
Minyak bekisting Liter 0.100 7,500.00 750.00

Jumlah Harga Bahan ..................................................................


94,950.00
Untuk 3x pakai .................................................................. 31,650.00
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 119,010.00
E. Overhead & Profit 10% X D 11,901.00
F. Harga Satuan Pekerjaan (D+E) 130,911.00

A.4.1.1.21 Pemasangan 1 M2 Bekisting untuk Sloof


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.520 90,000.00 46,800.00
Tukang Kayu L.02 OH 0.260 130,000.00 33,800.00
Kepala Tukang L.03 OH 0.026 150,000.00 3,900.00
Mandor L.04 OH 0.026 110,000.00 2,860.00

Jumlah Harga Tenaga ..................................................................


87,360.00
B. BAHAN
Kayu kelas III (papan) M3 0.045 2,205,000.00 99,225.00
Paku 5 - 12 cm Kg 0.300 20,000.00 6,000.00
Minyak bekisting Liter 0.100 7,500.00 750.00

Jumlah Harga Bahan ..................................................................


105,975.00
Untuk 3x pakai .................................................................. 35,325.00
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 122,685.00
E. Overhead & Profit 10% X D 12,268.50
F. Harga Satuan Pekerjaan (D+E) 134,953.50

A.4.1.1.22 Pemasangan 1 M2 Bekisting untuk Kolom


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.660 90,000.00 59,400.00
Tukang Kayu L.02 OH 0.330 130,000.00 42,900.00
Kepala Tukang L.03 OH 0.033 150,000.00 4,950.00
Mandor L.04 OH 0.033 110,000.00 3,630.00

Jumlah Harga Tenaga ..................................................................


110,880.00
B. BAHAN
Kayu kelas III (papan) M3 0.040 2,205,000.00 88,200.00
Paku 5 - 12 cm Kg 0.400 20,000.00 8,000.00
Minyak bekisting Liter 0.200 7,500.00 1,500.00
Balok kayu kelas II M3 0.015 4,200,000.00 63,000.00
Multipleks tebal 9 mm Lbr 0.350 202,230.00 70,780.50
Dolken kayu dia. 8 - 10/400 cm Batang 2.000 9,345.00 18,690.00

Jumlah Harga Bahan ..................................................................


250,170.50
Untuk 3x pakai .................................................................. 83,390.17
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 194,270.17
E. Overhead & Profit 10% X D 19,427.02
F. Harga Satuan Pekerjaan (D+E) 213,697.18

A.4.1.1.23 Pemasangan 1 M2 Bekisting untuk Balok


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.660 90,000.00 59,400.00
Tukang Kayu L.02 OH 0.330 130,000.00 42,900.00
Kepala Tukang L.03 OH 0.033 150,000.00 4,950.00
Mandor L.04 OH 0.033 110,000.00 3,630.00
Jumlah Harga Tenaga ..................................................................
110,880.00
B. BAHAN
Kayu kelas III (papan) M3 0.040 2,205,000.00 88,200.00
Paku 5 - 12 cm Kg 0.400 20,000.00 8,000.00
Minyak bekisting Liter 0.200 7,500.00 1,500.00
Balok kayu kelas II M3 0.018 4,200,000.00 75,600.00
Multipleks tebal 9 mm Lbr 0.350 202,230.00 70,780.50
Dolken kayu dia. 8 - 10/400 cm Batang 2.000 9,345.00 18,690.00

Jumlah Harga Bahan ..................................................................


262,770.50
Untuk 3x pakai .................................................................. 87,590.17
C. PERALATAN
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 198,470.17
E. Overhead & Profit 10% X D 19,847.02
F. Harga Satuan Pekerjaan (D+E) 218,317.18

A.4.1.1.24 Pemasangan 1 M2 Bekisting untuk Lantai


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.660 90,000.00 59,400.00
Tukang Kayu L.02 OH 0.330 130,000.00 42,900.00
Kepala Tukang L.03 OH 0.033 150,000.00 4,950.00
Mandor L.04 OH 0.033 110,000.00 3,630.00

Jumlah Harga Tenaga ..................................................................


110,880.00
B. BAHAN
Kayu kelas III (papan) M3 0.040 2,205,000.00 88,200.00
Paku 5 - 12 cm Kg 0.400 20,000.00 8,000.00
Minyak bekisting Liter 0.200 7,500.00 1,500.00
Balok kayu kelas II M3 0.015 4,200,000.00 63,000.00
Multipleks tebal 9 mm Lbr 0.350 202,230.00 70,780.50
Dolken kayu dia. 8 - 10/400 cm Batang 6.000 9,345.00 56,070.00

Jumlah Harga Bahan ..................................................................


287,550.50
Untuk 3x pakai .................................................................. 95,850.17
C. PERALATAN
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 206,730.17
E. Overhead & Profit 10% X D 20,673.02
F. Harga Satuan Pekerjaan (D+E) 227,403.18

A.4.1.1.25 Pemasangan 1 M2 Bekisting untuk Dinding


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.660 90,000.00 59,400.00
Tukang Kayu L.02 OH 0.330 130,000.00 42,900.00
Kepala Tukang L.03 OH 0.033 150,000.00 4,950.00
Mandor L.04 OH 0.033 110,000.00 3,630.00

Jumlah Harga Tenaga ..................................................................


110,880.00
B. BAHAN
Kayu kelas III (papan) M3 0.030 2,205,000.00 66,150.00
Paku 5 - 12 cm Kg 0.400 20,000.00 8,000.00
Minyak bekisting Liter 0.200 7,500.00 1,500.00
Balok kayu kelas II M3 0.020 4,200,000.00 84,000.00
Multipleks tebal 9 mm Lbr 0.350 202,230.00 70,780.50
Dolken kayu dia. 8 - 10/400 cm Batang 3.000 9,345.00 28,035.00
Penjaga jarak bekisting/spacer Buah - - -

Jumlah Harga Bahan ..................................................................


258,465.50
Untuk 3x pakai .................................................................. 86,155.17
C. PERALATAN
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 197,035.17
E. Overhead & Profit 10% X D 19,703.52
F. Harga Satuan Pekerjaan (D+E) 216,738.68

A.4.1.1.26 Pemasangan 1 M2 Bekisting untuk Tangga


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.660 90,000.00 59,400.00
Tukang Kayu L.02 OH 0.330 130,000.00 42,900.00
Kepala Tukang L.03 OH 0.033 150,000.00 4,950.00
Mandor L.04 OH 0.033 110,000.00 3,630.00

Jumlah Harga Tenaga ..................................................................


110,880.00
B. BAHAN
Kayu kelas III (papan) M3 0.030 2,205,000.00 66,150.00
Paku 5 - 12 cm Kg 0.400 20,000.00 8,000.00
Minyak bekisting Liter 0.150 7,500.00 1,125.00
Balok kayu kelas II M3 0.015 4,200,000.00 63,000.00
Multipleks tebal 9 mm Lbr 0.350 202,230.00 70,780.50
Dolken kayu dia. 8 - 10/400 cm Batang 2.000 9,345.00 18,690.00

Jumlah Harga Bahan ..................................................................


227,745.50
Untuk 3x pakai .................................................................. 75,915.17
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 186,795.17
E. Overhead & Profit 10% X D 18,679.52
F. Harga Satuan Pekerjaan (D+E) 205,474.68

A.4.1.1.SPL-1 Pemasangan 1 M2 Bondek untuk Plat Lantai Beton


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.100 90,000.00 9,000.00
Tukang Kayu L.02 OH 0.050 130,000.00 6,500.00
Kepala Tukang L.03 OH 0.005 150,000.00 750.00
Mandor L.04 OH 0.005 110,000.00 550.00

Jumlah Harga Tenaga ..................................................................


16,800.00
B. BAHAN
Bondek tebal 0.70 mm M2 1.100 100,000.00 110,000.00
Paku sekrup Kg 0.050 28,088.00 1,404.40
Jumlah Harga Bahan ..................................................................
111,404.40
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 128,204.40
E. Overhead & Profit 10% X D 12,820.44
F. Harga Satuan Pekerjaan (D+E) 141,024.84

A.4.1.1.SPL-2 Pembesian 1 M2 dengan Besi Wiremesh M8


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.070 90,000.00 6,300.00
Tukang Besi L.02 OH 0.070 130,000.00 9,100.00
Kepala Tukang L.03 OH 0.007 150,000.00 1,050.00
Mandor L.04 OH 0.004 110,000.00 440.00

Jumlah Harga Tenaga ..................................................................


16,890.00
B. BAHAN
Besi wiremesh M8 M2 1.050 95,000.00 99,750.00
Kawat beton Kg 0.015 27,405.00 411.08

Jumlah Harga Bahan ..................................................................


100,161.08
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 117,051.08
E. Overhead & Profit 10% X D 11,705.11
F. Harga Satuan Pekerjaan (D+E) 128,756.18
A.4.2.1 HARGA SATUAN PEKERJAAN BESI DAN ALUMINIUM

A.4.2.1.1 Pemasangan 1 Kg Besi Profil


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.060 90,000.00 5,400.00
Tukang Las L.02 OH 0.060 130,000.00 7,800.00
Kepala Tukang L.03 OH 0.006 150,000.00 900.00
Mandor L.04 OH 0.003 110,000.00 330.00

Jumlah Harga Tenaga ..................................................................


14,430.00
B. BAHAN
Besi Profil Kg 1.150 18,750.00 21,562.50

Jumlah Harga Bahan ..................................................................


21,562.50
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 35,992.50
E. Overhead & Profit 10% X D 3,599.25
F. Harga Satuan Pekerjaan (D+E) 39,591.75

A.4.2.1.5 Pengerjaan 1 cm Pengelasan dengan Las Listrik (dihitung per 10 cm Pengelasan)


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.040 90,000.00 3,600.00
Tukang Las Konstruksi L.02 OH 0.020 130,000.00 2,600.00
Kepala Tukang L.03 OH 0.002 150,000.00 300.00
Mandor L.04 OH 0.002 110,000.00 220.00

Jumlah Harga Tenaga ..................................................................


6,720.00
B. BAHAN
Kawat las listrik Kg 0.400 48,000.00 19,200.00
Solar Liter - -
Minyak pelumas Liter 0.040 25,000.00 1,000.00

Jumlah Harga Bahan ..................................................................


20,200.00
C. PERALATAN
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 26,920.00
E. Overhead & Profit 10% X D 2,692.00
F. Harga Satuan Pekerjaan (D+E) 29,612.00
Untuk 1 Cm Pekerjaan Pengelasan 2,961.20

A.4.2.1.18 Pemasangan 1 M' Talang Datar/Jurai Seng BJLS 28 Lebar 90 cm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.200 90,000.00 18,000.00
Tukang Kayu L.02 OH 0.200 130,000.00 26,000.00
Kepala Tukang L.03 OH 0.020 150,000.00 3,000.00
Mandor L.04 OH 0.001 110,000.00 110.00

Jumlah Harga Tenaga ..................................................................


47,110.00
B. BAHAN
Seng plat M' 1.050 40,000.00 42,000.00
Paku sekrup Kg 0.015 29,295.00 439.43
Kalsiboard tebal 6 mm Lbr 0.350 74,750.00 26,162.50
Besi siku L.30.30.30 Kg 1.500 18,750.00 28,125.00

Jumlah Harga Bahan ..................................................................


96,726.93
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 143,836.93
E. Overhead & Profit 10% X D 14,383.69
F. Harga Satuan Pekerjaan (D+E) 158,220.62

A.4.2.1.22 1 M2 Pemasangan Rangka Besi Hollow 1x (20.40.2 + 40.40.2) mm, Modul 60 x 60 cm, Plafond
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.350 90,000.00 31,500.00
Tukang Besi L.02 OH 0.350 130,000.00 45,500.00
Kepala Tukang L.03 OH 0.035 150,000.00 5,250.00
Mandor L.04 OH 0.0175 110,000.00 1,925.00

Jumlah Harga Tenaga ..................................................................


84,175.00
B. BAHAN
Rangka metal hollow 20.40.2 mm M' 2.000 7,950.00 15,900.00
Rangka metal hollow 40.40.2 mm M' 2.000 9,600.00 19,200.00
Assesories (perkuatan, las, dll.) Ls 1.000 35,100.00 35,100.00
(100% X rangka)

Jumlah Harga Bahan ..................................................................


70,200.00
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 154,375.00
E. Overhead & Profit 10% X D 15,437.50
F. Harga Satuan Pekerjaan (D+E) 169,812.50

A.4.2.1.25 1 M' Pemasangan Pipa Besi diameter 2" (Medium A)


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.125 90,000.00 11,250.00
Tukang Batu L.02 OH 0.205 130,000.00 26,650.00
Kepala Tukang L.03 OH 0.020 150,000.00 3,000.00
Mandor L.04 OH 0.006 110,000.00 660.00

Jumlah Harga Tenaga ..................................................................


41,560.00
B. BAHAN
Pipa besi dia. 2" (Medium A) M' 1.100 135,000.00 148,500.00
Perlengkapan Ls 35% 135,000.00 47,250.00

Jumlah Harga Bahan ..................................................................


195,750.00
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 237,310.00
E. Overhead & Profit 10% X D 23,731.00
F. Harga Satuan Pekerjaan (D+E) 261,041.00

A.4.2.1.25a 1 M' Pekerjaan Pipa Besi dia. 2", Medium A (Konstruksi Kuda-kuda)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.250 90,000.00 22,500.00
Tukang Besi L.02 OH 0.250 130,000.00 32,500.00
Kepala Tukang L.03 OH 0.025 150,000.00 3,750.00
Mandor L.04 OH 0.025 110,000.00 2,750.00

Jumlah Harga Tenaga ..................................................................


61,500.00
B. BAHAN
Besi Pipa dia. 2", tebal 3 mm (Med. A) M' 1.100 135,000.00 148,500.00
Perlengkapan Ls 35% 135,000.00 47,250.00

Jumlah Harga Bahan ..................................................................


195,750.00
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 257,250.00
E. Overhead & Profit 10% X D 25,725.00
F. Harga Satuan Pekerjaan (D+E) 282,975.00

A.4.2.1.26 1 M' Pemasangan Pipa Besi diameter 3" (Medium A)


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.135 90,000.00 12,150.00
Tukang Batu L.02 OH 0.225 130,000.00 29,250.00
Kepala Tukang L.03 OH 0.0225 150,000.00 3,375.00
Mandor L.04 OH 0.007 110,000.00 770.00

Jumlah Harga Tenaga ..................................................................


45,545.00
B. BAHAN
Pipa besi dia. 3" (Medium A) M' 1.100 210,000.00 231,000.00
Perlengkapan Ls 35% 210,000.00 73,500.00

Jumlah Harga Bahan ..................................................................


304,500.00
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 350,045.00
E. Overhead & Profit 10% X D 35,004.50
F. Harga Satuan Pekerjaan (D+E) 385,049.50

A.4.2.1.26a 1 M' Pemasangan Pipa Besi diameter 3" Medium A (Konstruksi Kuda-kuda)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.300 90,000.00 27,000.00
Tukang Batu L.02 OH 0.300 130,000.00 39,000.00
Kepala Tukang L.03 OH 0.030 150,000.00 4,500.00
Mandor L.04 OH 0.030 110,000.00 3,300.00

Jumlah Harga Tenaga ..................................................................


73,800.00
B. BAHAN
Pipa besi dia. 3" (Medium A) M' 1.100 210,000.00 231,000.00
Perlengkapan Ls 35% 210,000.00 73,500.00

Jumlah Harga Bahan ..................................................................


304,500.00
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 378,300.00
E. Overhead & Profit 10% X D 37,830.00
F. Harga Satuan Pekerjaan (D+E) 416,130.00

A.4.2.1.SPL-2 1 M' Pekerjaan Besi Kotak 4x6 cm, tebal 3 mm (Gording)


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.150 90,000.00 13,500.00
Tukang Besi L.02 OH 0.150 130,000.00 19,500.00
Kepala Tukang L.03 OH 0.015 150,000.00 2,250.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
Jumlah Harga Tenaga ..................................................................
36,900.00
B. BAHAN
Besi Kotak 4x6 cm, tebal 3 mm M' 1.050 63,000.00 66,150.00
Kawat las Kg 0.180 48,000.00 8,640.00

Jumlah Harga Bahan ..................................................................


74,790.00
C. PERALATAN

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 111,690.00
E. Overhead & Profit 10% X D 11,169.00
F. Harga Satuan Pekerjaan (D+E) 122,859.00

A.4.2.1.SPL-3 1 M' Pekerjaan Besi Kotak 4x4 cm, tebal 2,8 mm (Rangka Atap/Gording)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.100 90,000.00 9,000.00
Tukang Besi L.02 OH 0.100 130,000.00 13,000.00
Kepala Tukang L.03 OH 0.010 150,000.00 1,500.00
Mandor L.04 OH 0.010 110,000.00 1,100.00

Jumlah Harga Tenaga ..................................................................


24,600.00
B. BAHAN
Besi Kotak 4x4 cm, tebal 2,8 mm M' 1.050 48,300.00 50,715.00
Kawat las Kg 0.100 48,000.00 4,800.00

Jumlah Harga Bahan ..................................................................


55,515.00
C. PERALATAN

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 80,115.00
E. Overhead & Profit 10% X D 8,011.50
F. Harga Satuan Pekerjaan (D+E) 88,126.50

A.4.2.1.SPL-4 1 M' Pekerjaan Besi Kotak 5x5 cm, tebal 3 mm (Rangka Atap)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.100 90,000.00 9,000.00
Tukang Besi L.02 OH 0.100 130,000.00 13,000.00
Kepala Tukang L.03 OH 0.010 150,000.00 1,500.00
Mandor L.04 OH 0.010 110,000.00 1,100.00

Jumlah Harga Tenaga ..................................................................


24,600.00
B. BAHAN
Besi Kotak 5x5 cm, tebal 3 mm M' 1.050 64,500.00 67,725.00
Kawat las Kg 0.150 48,000.00 7,200.00

Jumlah Harga Bahan ..................................................................


74,925.00
C. PERALATAN

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 99,525.00
E. Overhead & Profit 10% X D 9,952.50
F. Harga Satuan Pekerjaan (D+E) 109,477.50

A.4.2.1.SPL-5 1 M2 Pekerjaan Besi Pagar Besi 6x6 cm + 3x6 cm + Besi Beton Kotak 12.12
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 1.500 90,000.00 135,000.00
Tukang Besi L.02 OH 1.500 130,000.00 195,000.00
Kepala Tukang L.03 OH 0.150 150,000.00 22,500.00
Mandor L.04 OH 0.150 110,000.00 16,500.00

Jumlah Harga Tenaga ..................................................................


369,000.00
B. BAHAN
Besi Kotak 6x6 cm, tebal 4 mm M' 2.460 88,500.00 217,710.00
Besi Kotak 3x6 cm, tebal 3 mm M' 6.660 57,000.00 379,620.00
Besi beton kotak 12.12 Kg 2.260 - -
Kawat las Kg 2.500 48,000.00 120,000.00

Jumlah Harga Bahan ..................................................................


717,330.00
C. PERALATAN

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 1,086,330.00
E. Overhead & Profit 10% X D 108,633.00
F. Harga Satuan Pekerjaan (D+E) 1,194,963.00

A.4.2.1.SPL-6 1 M' Pekerjaan Pagar BRC lengkap dengan Tiang, Type HD


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.375 90,000.00 33,750.00
Tukang Besi L.02 OH 0.120 130,000.00 15,600.00
Kepala Tukang L.03 OH 0.012 150,000.00 1,800.00
Mandor L.04 OH 0.019 110,000.00 2,090.00

Jumlah Harga Tenaga ..................................................................


53,240.00
B. BAHAN
Pagar BRC, ukuran 240 x 150 cm Lbr 0.417 840,000.00 350,280.00
Tiang galvanis dia. 2", h. 145 cm Bh 0.417 412,500.00 172,012.50
Topi Penutup Tiang Bh 0.417 19,500.00 8,131.50
Cupping / Mur dan baut Bh 1.250 3,750.00 4,687.50

Jumlah Harga Bahan ..................................................................


535,111.50
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 588,351.50
E. Overhead & Profit 10% X D 58,835.15
F. Harga Satuan Pekerjaan (D+E) 647,186.65

A.4.2.1.SPL-7 1 M' Pekerjaan Kusen Aluminium 4", Silver


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.200 90,000.00 18,000.00
Tukang Besi L.02 OH 0.100 130,000.00 13,000.00
Kepala Tukang L.03 OH 0.010 150,000.00 1,500.00
Mandor L.04 OH 0.010 110,000.00 1,100.00

Jumlah Harga Tenaga ..................................................................


33,600.00
B. BAHAN
Aluminium 4" - Silver M' 1.050 95,000.00 99,750.00
Sealant kaca & dinding kg 0.400 48,000.00 19,200.00
Isolasi sealant kg 1.000 7,200.00 7,200.00
Skrup aluminium bh 2.000 540.00 1,080.00
Butyl sealer bh 0.860 11,000.00 9,460.00
Masking tape kg 0.500 11,500.00 5,750.00

Jumlah Harga Bahan ..................................................................


142,440.00
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 176,040.00
E. Overhead & Profit 10% X D 17,604.00
F. Harga Satuan Pekerjaan (D+E) 193,644.00

A.4.2.1.SPL-8 1 M2 Pemasangan Alumunium Composite Panel PVDF


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.150 90,000.00 13,500.00
Tukang Besi L.02 OH 0.150 130,000.00 19,500.00
Kepala Tukang L.03 OH 0.015 150,000.00 2,250.00
Mandor L.04 OH 0.015 150,000.00 2,250.00

Jumlah Harga Tenaga .................................................................. 37,500.00


B. BAHAN

Alucopan PVDF m2 1.100 487,500.00 536,250.00


Besi Kotak 4 x 4 m1 4.025 48,300.00 194,407.50
Bracket besi siku 70.70.7 kg 2.100 21,525.00 45,202.50
Dynabolt M 10 x 120 bh 3.000 2,247.00 6,741.00
Mur + baut M 10 x 70 bh 2.000 2,500.00 5,000.00
Zincromate kg 0.067 135,000.00 9,004.50
Sealant tube 0.250 48,000.00 12,000.00
Ramsel Nails bh 12.000 700.00 8,400.00

Jumlah Harga Bahan .................................................................. 817,005.50


C. PERALATAN
Alat bantu Ls 1.000 2,500.00 2,500.00
-

Jumlah Harga Peralatan .................................................................. 2,500.00


D. Jumlah (A+B+C) 857,005.50
E. Overhead & Profit 10% X D 85,700.55
F. Harga Satuan Pekerjaan (D+E) 942,706.05
A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING

A.4.4.3.4 Pemasangan 1 M2 Lantai Ubin Warna Ukuran 40 cm x 40 cm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.250 90,000.00 22,500.00
Tukang Batu L.02 OH 0.125 130,000.00 16,250.00
Kepala Tukang L.03 OH 0.0125 150,000.00 1,875.00
Mandor L.04 OH 0.0125 110,000.00 1,375.00

Jumlah Harga Tenaga ..................................................................


42,000.00
B. BAHAN
Ubin warna 40 cm x 40 cm Bh 6.630 18,000.00 119,340.00
Semen Portland Kg 9.800 1,575.00 15,435.00
Semen warna Kg 1.300 25,358.00 32,965.40
Pasir pasang M3 0.045 225,000.00 10,125.00

Jumlah Harga Bahan ..................................................................


177,865.40
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 219,865.40
E. Overhead & Profit 10% X D 21,986.54
F. Harga Satuan Pekerjaan (D+E) 241,851.94

A.4.4.3.5 Pemasangan 1 M2 Lantai Ubin Warna Ukuran 30 cm x 30 cm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.260 90,000.00 23,400.00
Tukang Batu L.02 OH 0.130 130,000.00 16,900.00
Kepala Tukang L.03 OH 0.013 150,000.00 1,950.00
Mandor L.04 OH 0.013 110,000.00 1,430.00

Jumlah Harga Tenaga ..................................................................


43,680.00
B. BAHAN
Ubin warna 30 cm x 30 cm Bh 11.870 9,450.00 112,171.50
Semen Portland Kg 10.000 1,575.00 15,750.00
Semen warna Kg 1.500 25,358.00 38,037.00
Pasir pasang M3 0.045 225,000.00 10,125.00

Jumlah Harga Bahan ..................................................................


176,083.50
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 219,763.50
E. Overhead & Profit 10% X D 21,976.35
F. Harga Satuan Pekerjaan (D+E) 241,739.85

A.4.4.3.20 Pemasangan 1 M' Plint Ubin Warna Ukuran 10 cm x 30 cm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.090 90,000.00 8,100.00
Tukang Batu L.02 OH 0.090 130,000.00 11,700.00
Kepala Tukang L.03 OH 0.009 150,000.00 1,350.00
Mandor L.04 OH 0.005 110,000.00 550.00

Jumlah Harga Tenaga ..................................................................


21,700.00
B. BAHAN
Plint ubin warna 10 cm x 30 cm Bh 3.530 3,150.00 11,119.50
Semen Portland Kg 1.140 1,575.00 1,795.50
Semen warna Kg 0.100 25,358.00 2,535.80
Pasir pasang M3 0.003 225,000.00 675.00

Jumlah Harga Bahan ..................................................................


16,125.80
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 37,825.80
E. Overhead & Profit 10% X D 3,782.58
F. Harga Satuan Pekerjaan (D+E) 41,608.38

A.4.4.3.21 Pemasangan 1 M' Plint Ubin Warna Ukuran 10 cm x 40 cm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.090 90,000.00 8,100.00
Tukang Batu L.02 OH 0.090 130,000.00 11,700.00
Kepala Tukang L.03 OH 0.009 150,000.00 1,350.00
Mandor L.04 OH 0.005 110,000.00 550.00

Jumlah Harga Tenaga ..................................................................


21,700.00
B. BAHAN
Plint ubin warna 10 cm x 40 cm Bh 2.650 4,500.00 11,925.00
Semen Portland Kg 1.140 1,575.00 1,795.50
Semen warna Kg 0.100 25,358.00 2,535.80
Pasir pasang M3 0.003 225,000.00 675.00

Jumlah Harga Bahan ..................................................................


16,931.30
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 38,631.30
E. Overhead & Profit 10% X D 3,863.13
F. Harga Satuan Pekerjaan (D+E) 42,494.43

A.4.4.3.23 Pemasangan 1 M' Plint Keramik Granit Ukuran 10 cm x 60 cm (hitam)


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.090 90,000.00 8,100.00
Tukang Batu L.02 OH 0.090 130,000.00 11,700.00
Kepala Tukang L.03 OH 0.009 150,000.00 1,350.00
Mandor L.04 OH 0.005 110,000.00 550.00

Jumlah Harga Tenaga ..................................................................


21,700.00
B. BAHAN
Granit 10 cm x 60 cm (hitam) Bh 1.750 16,500.00 28,875.00
Semen Portland Kg 1.140 1,575.00 1,795.50
Semen warna Kg 0.100 25,358.00 2,535.80
Pasir pasang M3 0.003 225,000.00 675.00

Jumlah Harga Bahan ..................................................................


33,881.30
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 55,581.30
E. Overhead & Profit 10% X D 5,558.13
F. Harga Satuan Pekerjaan (D+E) 61,139.43

A.4.4.3.33 Pemasangan 1 M2 Lantai Keramik Granit Ukuran 60 cm x 60 cm (putih)


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.500 90,000.00 45,000.00
Tukang Batu L.02 OH 0.250 130,000.00 32,500.00
Kepala Tukang L.03 OH 0.025 150,000.00 3,750.00
Mandor L.04 OH 0.025 110,000.00 2,750.00

Jumlah Harga Tenaga ..................................................................


84,000.00
B. BAHAN
Granit 60 cm x 60 cm, putih Bh 3.056 72,000.00 220,032.00
Semen Portland Kg 8.190 1,575.00 12,899.25
Semen warna Kg 1.620 25,358.00 41,079.96
Pasir pasang M3 0.045 225,000.00 10,125.00

Jumlah Harga Bahan ..................................................................


284,136.21
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 368,136.21
E. Overhead & Profit 10% X D 36,813.62
F. Harga Satuan Pekerjaan (D+E) 404,949.83

A.4.4.3.33a Pemasangan 1 M2 Lantai Keramik Granit Ukuran 60 cm x 60 cm (hitam)


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.500 90,000.00 45,000.00
Tukang Batu L.02 OH 0.250 130,000.00 32,500.00
Kepala Tukang L.03 OH 0.025 150,000.00 3,750.00
Mandor L.04 OH 0.025 110,000.00 2,750.00

Jumlah Harga Tenaga ..................................................................


84,000.00
B. BAHAN
Keramik 60 cm x 60 cm, hitam Bh 3.056 99,000.00 302,544.00
Semen Portland Kg 8.190 1,575.00 12,899.25
Semen warna Kg 1.620 25,358.00 41,079.96
Pasir pasang M3 0.045 225,000.00 10,125.00

Jumlah Harga Bahan ..................................................................


366,648.21
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 450,648.21
E. Overhead & Profit 10% X D 45,064.82
F. Harga Satuan Pekerjaan (D+E) 495,713.03

A.4.4.3.34 Pemasangan 1 M2 Lantai Keramik Ukuran 40 cm x 40 cm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.500 90,000.00 45,000.00
Tukang Batu L.02 OH 0.250 130,000.00 32,500.00
Kepala Tukang L.03 OH 0.025 150,000.00 3,750.00
Mandor L.04 OH 0.025 110,000.00 2,750.00

Jumlah Harga Tenaga ..................................................................


84,000.00
B. BAHAN
Keramik 40 cm x 40 cm Bh 6.875 18,000.00 123,750.00
Semen Portland Kg 8.190 1,575.00 12,899.25
Semen warna Kg 1.620 25,358.00 41,079.96
Pasir pasang M3 0.045 225,000.00 10,125.00

Jumlah Harga Bahan ..................................................................


187,854.21
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 271,854.21
E. Overhead & Profit 10% X D 27,185.42
F. Harga Satuan Pekerjaan (D+E) 299,039.63

A.4.4.3.35 Pemasangan 1 M2 Lantai Keramik Ukuran 30 cm x 30 cm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.500 90,000.00 45,000.00
Tukang Batu L.02 OH 0.250 130,000.00 32,500.00
Kepala Tukang L.03 OH 0.025 150,000.00 3,750.00
Mandor L.04 OH 0.025 110,000.00 2,750.00
Jumlah Harga Tenaga ..................................................................
84,000.00
B. BAHAN
Keramik 30 cm x 30 cm Bh 11.870 9,450.00 112,171.50
Semen Portland Kg 10.000 1,575.00 15,750.00
Semen warna Kg 1.500 25,358.00 38,037.00
Pasir pasang M3 0.045 225,000.00 10,125.00

Jumlah Harga Bahan ..................................................................


176,083.50
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 260,083.50
E. Overhead & Profit 10% X D 26,008.35
F. Harga Satuan Pekerjaan (D+E) 286,091.85

A.4.4.3.54a Pemasangan 1 M2 Dinding Keramik 30 cm x 60 cm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.700 90,000.00 63,000.00
Tukang Batu L.02 OH 0.350 130,000.00 45,500.00
Kepala Tukang L.03 OH 0.035 150,000.00 5,250.00
Mandor L.04 OH 0.035 110,000.00 3,850.00

Jumlah Harga Tenaga ..................................................................


117,600.00
B. BAHAN
Keramik 30 cm x 60 cm Bh 5.833 24,000.00 139,992.00
Semen Portland Kg 9.300 1,575.00 14,647.50
Semen warna Kg 1.940 25,358.00 49,194.52
Pasir pasang M3 0.018 225,000.00 4,050.00

Jumlah Harga Bahan ..................................................................


207,884.02
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 325,484.02
E. Overhead & Profit 10% X D 32,548.40
F. Harga Satuan Pekerjaan (D+E) 358,032.42

A.4.4.3.54b Pemasangan 1 M2 Dinding Granit 60 cm x 60 cm, putih


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.700 90,000.00 63,000.00
Tukang Batu L.02 OH 0.350 130,000.00 45,500.00
Kepala Tukang L.03 OH 0.035 150,000.00 5,250.00
Mandor L.04 OH 0.035 110,000.00 3,850.00

Jumlah Harga Tenaga ..................................................................


117,600.00
B. BAHAN
Granit 60 cm x 60 cm, putih Bh 3.056 72,000.00 220,032.00
Semen Portland Kg 9.300 1,575.00 14,647.50
Semen warna Kg 1.940 25,358.00 49,194.52
Pasir pasang M3 0.018 225,000.00 4,050.00

Jumlah Harga Bahan ..................................................................


287,924.02
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 405,524.02
E. Overhead & Profit 10% X D 40,552.40
F. Harga Satuan Pekerjaan (D+E) 446,076.42
A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)

A.4.4.5.7a Pemasangan 1 m2 Langit-langit Gypsum Board Ukuran (120x240x9) mm, Tebal 9 mm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.100 90,000.00 9,000.00
Tukang Kayu L.02 OH 0.050 130,000.00 6,500.00
Kepala Tukang L.03 OH 0.005 150,000.00 750.00
Mandor L.04 OH 0.005 110,000.00 550.00

Jumlah Harga Tenaga ..................................................................


16,800.00
B. BAHAN
Gypsum Board tebal 9 mm Lbr 0.364 81,500.00 29,666.00
Paku Sekrup Kg 0.110 29,295.00 3,222.45

Jumlah Harga Bahan ..................................................................


32,888.45
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 49,688.45
E. Overhead & Profit 10% X D 4,968.85
F. Harga Satuan Pekerjaan (D+E) 54,657.30

A.4.4.5.7b Pemasangan 1 m2 Langit-langit Kalsiboard Ukuran (120x240x6) mm, Tebal 6 mm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.100 90,000.00 9,000.00
Tukang Kayu L.02 OH 0.050 130,000.00 6,500.00
Kepala Tukang L.03 OH 0.005 150,000.00 750.00
Mandor L.04 OH 0.005 110,000.00 550.00

Jumlah Harga Tenaga ..................................................................


16,800.00
B. BAHAN
Kalsiboard tebal 6 mm Lbr 0.364 74,750.00 27,209.00
Paku Sekrup Kg 0.110 29,295.00 3,222.45

Jumlah Harga Bahan ..................................................................


30,431.45
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 47,231.45
E. Overhead & Profit 10% X D 4,723.15
F. Harga Satuan Pekerjaan (D+E) 51,954.60
A.4.4.5.9 Pemasangan 1 m' List Langit-langit Kayu Profil
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.050 90,000.00 4,500.00
Tukang Kayu L.02 OH 0.050 130,000.00 6,500.00
Kepala Tukang L.03 OH 0.005 150,000.00 750.00
Mandor L.04 OH 0.003 110,000.00 330.00

Jumlah Harga Tenaga ..................................................................


12,080.00
B. BAHAN
List kayu profil M 1.050 10,500.00 11,025.00
Paku Kg 0.010 20,000.00 200.00

Jumlah Harga Bahan ..................................................................


11,225.00
C. PERALATAN
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 23,305.00
E. Overhead & Profit 10% X D 2,330.50
F. Harga Satuan Pekerjaan (D+E) 25,635.50

A.4.4.5.10 Pemasangan 1 m' List Langit-langit, Gypsum Profil 9 x 9 cm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.080 90,000.00 7,200.00
Tukang Kayu L.02 OH 0.080 130,000.00 10,400.00
Kepala Tukang L.03 OH 0.008 150,000.00 1,200.00
Mandor L.04 OH 0.004 110,000.00 440.00

Jumlah Harga Tenaga ..................................................................


19,240.00
B. BAHAN
List gypsum profil 9 x 9 cm M 1.050 28,500.00 29,925.00
Lem kayu putih Kg 0.050 29,550.00 1,477.50
Paku sekrup Kg 0.010 29,295.00 292.95

Jumlah Harga Bahan ..................................................................


31,695.45
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 50,935.45
E. Overhead & Profit 10% X D 5,093.55
F. Harga Satuan Pekerjaan (D+E) 56,029.00
A.4.4.5.10a Pemasangan 1 m' List Langit-langit, Gypsum Profil 5 x 5 cm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.070 90,000.00 6,300.00
Tukang Kayu L.02 OH 0.070 130,000.00 9,100.00
Kepala Tukang L.03 OH 0.007 150,000.00 1,050.00
Mandor L.04 OH 0.0035 110,000.00 385.00

Jumlah Harga Tenaga ..................................................................


16,835.00
B. BAHAN
List gypsum profil 5 x 5 cm M 1.050 19,500.00 20,475.00
Lem kayu putih Kg 0.040 29,550.00 1,182.00
Paku sekrup Kg 0.010 29,295.00 292.95

Jumlah Harga Bahan ..................................................................


21,949.95
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 38,784.95
E. Overhead & Profit 10% X D 3,878.50
F. Harga Satuan Pekerjaan (D+E) 42,663.45
A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP

A.4.5.2.32 Pemasangan 1 M2 Genteng Metal


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.200 90,000.00 18,000.00
Tukang Kayu L.03 OH 0.100 130,000.00 13,000.00
Kepala Tukang L.11 OH 0.010 150,000.00 1,500.00
Mandor L.15 OH 0.010 110,000.00 1,100.00

Jumlah Harga Tenaga ..................................................................


33,600.00
B. BAHAN
Genteng metal Bh 1.020 89,452.00 91,241.04
Paku/sekrup genteng Kg 0.200 29,295.00 5,859.00

Jumlah Harga Bahan ..................................................................


97,100.04
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 130,700.04
E. Overhead & Profit 10% X D 13,070.00
F. Harga Satuan Pekerjaan (D+E) 143,770.04

A.4.5.2.36 Pemasangan 1 M' Nok Genteng Metal


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.250 90,000.00 22,500.00
Tukang Kayu L.03 OH 0.150 130,000.00 19,500.00
Kepala Tukang L.11 OH 0.015 150,000.00 2,250.00
Mandor L.15 OH 0.0125 110,000.00 1,375.00

Jumlah Harga Tenaga ..................................................................


45,625.00
B. BAHAN
Nok genteng metal Bh 1.100 42,000.00 46,200.00
Paku/sekrup genteng Kg 0.050 29,295.00 1,464.75

Jumlah Harga Bahan ..................................................................


47,664.75
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 93,289.75
E. Overhead & Profit 10% X D 9,328.98
F. Harga Satuan Pekerjaan (D+E) 102,618.73

A.4.5.2.40 Pemasangan 1 M2 Atap Spandek (Model Standar)


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.150 90,000.00 13,500.00
Tukang Kayu L.03 OH 0.750 130,000.00 97,500.00
Kepala Tukang L.11 OH 0.075 150,000.00 11,250.00
Mandor L.15 OH 0.006 110,000.00 660.00

Jumlah Harga Tenaga ..................................................................


122,910.00
B. BAHAN
Spandek, T. 0.40 M' 1.280 55,000.00 70,400.00
Paku/sekrup genteng/spandek Kg 0.020 29,295.00 585.90

Jumlah Harga Bahan ..................................................................


70,985.90
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 193,895.90
E. Overhead & Profit 10% X D 19,389.59
F. Harga Satuan Pekerjaan (D+E) 213,285.49

A.4.5.2.40a Pemasangan 1 M2 Atap Spandek (Model Melengkung)


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.150 90,000.00 13,500.00
Tukang Kayu L.03 OH 0.750 130,000.00 97,500.00
Kepala Tukang L.11 OH 0.075 150,000.00 11,250.00
Mandor L.15 OH 0.006 110,000.00 660.00

Jumlah Harga Tenaga ..................................................................


122,910.00
B. BAHAN
Spandek lengkung, T. 0.40 M' 1.280 110,000.00 140,800.00
Paku/sekrup genteng/spandek Kg 0.020 29,295.00 585.90

Jumlah Harga Bahan ..................................................................


141,385.90
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 264,295.90
E. Overhead & Profit 10% X D 26,429.59
F. Harga Satuan Pekerjaan (D+E) 290,725.49

A.4.5.2.41 Pemasangan 1 M' Nok Atap Aluminium


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.100 90,000.00 9,000.00
Tukang Kayu L.03 OH 1.000 130,000.00 130,000.00
Kepala Tukang L.11 OH 0.100 150,000.00 15,000.00
Mandor L.15 OH 0.050 110,000.00 5,500.00

Jumlah Harga Tenaga ..................................................................


159,500.00
B. BAHAN
Nok standar Lb. 45 cm m' 1.200 35,000.00 42,000.00
Paku/sekrup genteng/spandek Kg 0.040 29,295.00 1,171.80

Jumlah Harga Bahan ..................................................................


43,171.80
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 202,671.80
E. Overhead & Profit 10% X D 20,267.18
F. Harga Satuan Pekerjaan (D+E) 222,938.98

A.4.5.2.Spl-1 Pemasangan 1 M2 Rangka Atap Baja Ringan


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.150 90,000.00 13,500.00
Tukang Baja Ringan L.03 OH 0.150 - -
Kepala Tukang L.11 OH 0.015 - -
Mandor L.15 OH 0.015 110,000.00 1,650.00

Jumlah Harga Tenaga ..................................................................


15,150.00
B. BAHAN
Rangka atap baja ringan M2 1.050 180,000.00 189,000.00
Sekrup baja ringan Kg 0.050 28,088.00 1,404.40

Jumlah Harga Bahan ..................................................................


190,404.40
C. PERALATAN
Alat bantu Ls 1.000 5,000.00 5,000.00
-

Jumlah Harga Peralatan ..................................................................


5,000.00
D. Jumlah (A+B+C) 210,554.40
E. Overhead & Profit 10% X D 21,055.44
F. Harga Satuan Pekerjaan (D+E) 231,609.84

A.4.5.2.Spl-2 Pemasangan 1 M2 Melapis Atap dengan Aluminium Foil


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.150 90,000.00 13,500.00
Tukang Baja Ringan L.03 OH 0.150 - -
Kepala Tukang L.11 OH 0.015 - -
Mandor L.15 OH 0.015 110,000.00 1,650.00

Jumlah Harga Tenaga ..................................................................


15,150.00
B. BAHAN
Aluminium Foil M2 1.280 55,000.00 70,400.00

Jumlah Harga Bahan ..................................................................


70,400.00
C. PERALATAN
Alat bantu Ls 1.000 5,000.00 5,000.00
-

Jumlah Harga Peralatan ..................................................................


5,000.00
D. Jumlah (A+B+C) 90,550.00
E. Overhead & Profit 10% X D 9,055.00
F. Harga Satuan Pekerjaan (D+E) 99,605.00
A.4.6.1 HARGA SATUAN PEKERJAAN KAYU

A.4.6.1.1 Pembuatan dan Pemasangan 1 M3 Kusen Pintu dan Jendela, Kayu Kelas I
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 7.000 90,000.00 630,000.00
Tukang Kayu L.03 OH 21.000 130,000.00 2,730,000.00
Kepala Tukang L.11 OH 2.100 150,000.00 315,000.00
Mandor L.15 OH 0.350 110,000.00 38,500.00

Jumlah Harga Tenaga ..................................................................


3,713,500.00
B. BAHAN
Balok kayu kelas I M3 1.100 6,279,000.00 6,906,900.00
Paku 10 cm Kg 1.250 20,000.00 25,000.00
Lem kayu Kg 1.000 27,405.00 27,405.00

Jumlah Harga Bahan ..................................................................


6,959,305.00
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 10,672,805.00
E. Overhead & Profit 10% X D 1,067,280.50
F. Harga Satuan Pekerjaan (D+E) 11,740,085.50

A.4.6.1.5 Pembuatan dan Pemasangan 1 M2 Daun Pintu Panel, Kayu Kelas I (atau kelas II)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 1.000 90,000.00 90,000.00
Tukang Kayu L.03 OH 3.000 130,000.00 390,000.00
Kepala Tukang L.11 OH 0.300 150,000.00 45,000.00
Mandor L.15 OH 0.050 110,000.00 5,500.00

Jumlah Harga Tenaga ..................................................................


530,500.00
B. BAHAN
Papan kayu kelas I M3 0.040 6,279,000.00 251,160.00
Lem kayu Kg 0.500 27,405.00 13,702.50

Jumlah Harga Bahan ..................................................................


264,862.50
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 795,362.50
E. Overhead & Profit 10% X D 79,536.25
F. Harga Satuan Pekerjaan (D+E) 874,898.75

A.4.6.1.6 Pembuatan dan Pemasangan 1 M2 Pintu dan Jendela Kaca, Kayu Kelas I (atau kelas II)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.800 90,000.00 72,000.00
Tukang Kayu L.03 OH 2.400 130,000.00 312,000.00
Kepala Tukang L.11 OH 0.240 150,000.00 36,000.00
Mandor L.15 OH 0.040 110,000.00 4,400.00
Jumlah Harga Tenaga ..................................................................
424,400.00
B. BAHAN
Papan kayu kelas I M3 0.024 6,279,000.00 150,696.00
Lem kayu Kg 0.300 27,405.00 8,221.50
Jumlah Harga Bahan ..................................................................
158,917.50
C. PERALATAN

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 583,317.50
E. Overhead & Profit 10% X D 58,331.75
F. Harga Satuan Pekerjaan (D+E) 641,649.25

A.4.6.1.7 Pembuatan dan Pemasangan 1 M2 Pintu dan Jendela Jalusi, Kayu Kelas I (atau kelas II)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 1.000 90,000.00 90,000.00
Tukang Kayu L.03 OH 3.000 130,000.00 390,000.00
Kepala Tukang L.11 OH 0.300 150,000.00 45,000.00
Mandor L.15 OH 0.050 110,000.00 5,500.00
Jumlah Harga Tenaga ..................................................................
530,500.00
B. BAHAN
Papan kayu kelas I M3 0.064 6,279,000.00 401,856.00
Lem kayu Kg 0.500 27,405.00 13,702.50
Jumlah Harga Bahan ..................................................................
415,558.50
C. PERALATAN

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 946,058.50
E. Overhead & Profit 10% X D 94,605.85
F. Harga Satuan Pekerjaan (D+E) 1,040,664.35
A.4.6.1.8 Pembuatan 1 M2 Daun Pintu Multipleks Rangkap, Rangka Kayu Kelas II (Lapis HPL + Almn. plat)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.800 90,000.00 72,000.00
Tukang Kayu L.03 OH 2.400 130,000.00 312,000.00
Kepala Tukang L.11 OH 0.240 150,000.00 36,000.00
Mandor L.15 OH 0.040 110,000.00 4,400.00
Jumlah Harga Tenaga ..................................................................
424,400.00
B. BAHAN
Papan kayu kelas II M3 0.025 4,200,000.00 105,000.00
Paku 1 cm - 2,5 cm Kg 0.030 20,000.00 600.00
Lem kayu fox Kg 0.500 105,000.00 52,500.00
Plywood t. 4 mm uk. (90 x 220) cm Lbr 1.000 112,687.00 112,687.00
HPL Lbr 0.365 360,000.00 131,400.00
Aluminium plat m2 1.050 129,000.00 135,450.00
Jumlah Harga Bahan ..................................................................
537,637.00
C. PERALATAN

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 962,037.00
E. Overhead & Profit 10% X D 96,203.70
F. Harga Satuan Pekerjaan (D+E) 1,058,240.70

A.4.6.1.8a Pembuatan 1 M2 Daun Pintu Plywood Rangkap, Rangka Kayu Kelas II Tertutup (Lapis HPL)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 1.000 90,000.00 90,000.00
Tukang Kayu L.03 OH 3.000 130,000.00 390,000.00
Kepala Tukang L.11 OH 0.300 150,000.00 45,000.00
Mandor L.15 OH 0.060 110,000.00 6,600.00

Jumlah Harga Tenaga ..................................................................


531,600.00
B. BAHAN
Papan kayu kelas II M3 0.025 4,200,000.00 105,000.00
Paku 1 cm - 2,5 cm Kg 0.030 20,000.00 600.00
Lem kayu Kg 1.000 105,000.00 105,000.00
Multipleks. 4 mm uk. (90 x 220) cm Lbr 1.000 112,687.00 112,687.00
HPL Lbr 0.730 360,000.00 262,800.00

Jumlah Harga Bahan ..................................................................


586,087.00
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 1,117,687.00
E. Overhead & Profit 10% X D 111,768.70
F. Harga Satuan Pekerjaan (D+E) 1,229,455.70
A.4.6.1.21a Pemasangan 1 M' Lijsplank Ukuran (1.8 x 20) cm, Woodplank/Kalsiplank
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.100 90,000.00 9,000.00
Tukang Kayu L.03 OH 0.200 130,000.00 26,000.00
Kepala Tukang L.11 OH 0.010 150,000.00 1,500.00
Mandor L.15 OH 0.005 110,000.00 550.00

Jumlah Harga Tenaga ..................................................................


37,050.00
B. BAHAN
Woodplank uk. 1.8 x 20 cm M' 1.0500 45,000.00 47,250.00
Paku genteng Kg 0.050 29,295.00 1,464.75

Jumlah Harga Bahan ..................................................................


48,714.75
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 85,764.75
E. Overhead & Profit 10% X D 8,576.48
F. Harga Satuan Pekerjaan (D+E) 94,341.23

A.4.6.1.21b Pemasangan 1 M' Lijsplank Ukuran 2x (1.8 x 20) cm, Woodplank/Kalsiplank


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.200 90,000.00 18,000.00
Tukang Kayu L.03 OH 0.400 130,000.00 52,000.00
Kepala Tukang L.11 OH 0.020 150,000.00 3,000.00
Mandor L.15 OH 0.010 110,000.00 1,100.00

Jumlah Harga Tenaga ..................................................................


74,100.00
B. BAHAN
Woodplank uk. 1.8 x 20 cm M' 2.1000 45,000.00 94,500.00
Paku genteng Kg 0.100 29,295.00 2,929.50

Jumlah Harga Bahan ..................................................................


97,429.50
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 171,529.50
E. Overhead & Profit 10% X D 17,152.95
F. Harga Satuan Pekerjaan (D+E) 188,682.45
A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI DAN KACA

A.4.6.2.2 Pemasangan 1 Buah Kunci Tanam Biasa


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.010 90,000.00 900.00
Tukang Kayu L.02 OH 0.500 130,000.00 65,000.00
Kepala Tukang L.03 OH 0.050 150,000.00 7,500.00
Mandor L.04 OH 0.005 110,000.00 550.00

Jumlah Harga Tenaga ..................................................................


73,950.00
B. BAHAN
Kunci tanam biasa Bh 1.000 250,000.00 250,000.00

Jumlah Harga Bahan ..................................................................


250,000.00
C. PERALATAN

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 323,950.00
E. Overhead & Profit 10% X D 32,395.00
F. Harga Satuan Pekerjaan (D+E) 356,345.00

A.4.6.2.3 Pemasangan 1 Buah Kunci Kamar Mandi


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.005 90,000.00 450.00
Tukang Kayu L.02 OH 0.500 130,000.00 65,000.00
Kepala Tukang L.03 OH 0.050 150,000.00 7,500.00
Mandor L.04 OH 0.003 110,000.00 330.00

Jumlah Harga Tenaga ..................................................................


73,280.00
B. BAHAN
Kunci tanam KM/WC Bh 1.000 172,500.00 172,500.00

Jumlah Harga Bahan ..................................................................


172,500.00
C. PERALATAN

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 245,780.00
E. Overhead & Profit 10% X D 24,578.00
F. Harga Satuan Pekerjaan (D+E) 270,358.00
A.4.6.2.5 Pemasangan 1 Buah Engsel Pintu
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.015 90,000.00 1,350.00
Tukang Kayu L.02 OH 0.150 130,000.00 19,500.00
Kepala Tukang L.03 OH 0.015 150,000.00 2,250.00
Mandor L.04 OH 0.0008 110,000.00 88.00

Jumlah Harga Tenaga ..................................................................


23,188.00
B. BAHAN
Engsel pintu Bh 1.000 35,000.00 35,000.00

Jumlah Harga Bahan ..................................................................


35,000.00
C. PERALATAN

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 58,188.00
E. Overhead & Profit 10% X D 5,818.80
F. Harga Satuan Pekerjaan (D+E) 64,006.80

A.4.6.2.6 Pemasangan 1 Buah Engsel Jendela Kupu-kupu


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.010 90,000.00 900.00
Tukang Kayu L.02 OH 0.100 130,000.00 13,000.00
Kepala Tukang L.03 OH 0.010 150,000.00 1,500.00
Mandor L.04 OH 0.0005 110,000.00 55.00

Jumlah Harga Tenaga ..................................................................


15,455.00
B. BAHAN
Engsel jendela kupu-kupu Bh 1.000 22,000.00 22,000.00

Jumlah Harga Bahan ..................................................................


22,000.00
C. PERALATAN
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 37,455.00
E. Overhead & Profit 10% X D 3,745.50
F. Harga Satuan Pekerjaan (D+E) 41,200.50
A.4.6.2.7 Pemasangan 1 Buah Engsel Angin (Casement, tipe sedang)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.100 90,000.00 9,000.00
Tukang Kayu L.02 OH 0.200 130,000.00 26,000.00
Kepala Tukang L.03 OH 0.020 150,000.00 3,000.00
Mandor L.04 OH 0.0005 110,000.00 55.00

Jumlah Harga Tenaga ..................................................................


38,055.00
B. BAHAN
Engsel angin / casement Bh 1.000 45,000.00 45,000.00

Jumlah Harga Bahan ..................................................................


45,000.00
C. PERALATAN

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 83,055.00
E. Overhead & Profit 10% X D 8,305.50
F. Harga Satuan Pekerjaan (D+E) 91,360.50

A.4.6.2.9 Pemasangan 1 Buah Kait Angin


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.015 90,000.00 1,350.00
Tukang Kayu L.02 OH 0.150 130,000.00 19,500.00
Kepala Tukang L.03 OH 0.015 150,000.00 2,250.00
Mandor L.04 OH 0.0075 110,000.00 825.00

Jumlah Harga Tenaga ..................................................................


23,925.00
B. BAHAN
Kait angin Bh 1.000 23,000.00 23,000.00

Jumlah Harga Bahan ..................................................................


23,000.00
C. PERALATAN
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 46,925.00
E. Overhead & Profit 10% X D 4,692.50
F. Harga Satuan Pekerjaan (D+E) 51,617.50
A.4.6.2.17 Pemasangan 1 M2 Kaca Tebal 5 mm (polos)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.015 90,000.00 1,350.00
Tukang Kayu L.02 OH 0.150 130,000.00 19,500.00
Kepala Tukang L.03 OH 0.015 150,000.00 2,250.00
Mandor L.04 OH 0.00075 110,000.00 82.50

Jumlah Harga Tenaga ..................................................................


23,182.50
B. BAHAN
Kaca polos t. 5 mm M2 1.100 185,000.00 203,500.00
Sealant Kg 0.050 48,000.00 2,400.00

Jumlah Harga Bahan ..................................................................


205,900.00
C. PERALATAN

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 229,082.50
E. Overhead & Profit 10% X D 22,908.25
F. Harga Satuan Pekerjaan (D+E) 251,990.75

A.4.6.2.18 Pemasangan 1 M2 Kaca Tebal 10 mm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.017 90,000.00 1,530.00
Tukang Kayu L.02 OH 0.170 130,000.00 22,100.00
Kepala Tukang L.03 OH 0.017 150,000.00 2,550.00
Mandor L.04 OH 0.00085 110,000.00 93.50

Jumlah Harga Tenaga ..................................................................


26,273.50
B. BAHAN
Kaca polos t. 10 mm M2 1.100 1,080,000.00 1,188,000.00
Sealant Kg 0.070 48,000.00 3,360.00

Jumlah Harga Bahan ..................................................................


1,191,360.00
C. PERALATAN
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 1,217,633.50
E. Overhead & Profit 10% X D 121,763.35
F. Harga Satuan Pekerjaan (D+E) 1,339,396.85
A.4.6.2.19 Pemasangan 1 M2 Kaca Polos Tebal 12 mm, Tempered
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.025 90,000.00 2,250.00
Tukang Kayu L.02 OH 0.250 130,000.00 32,500.00
Kepala Tukang L.03 OH 0.025 150,000.00 3,750.00
Mandor L.04 OH 0.00125 110,000.00 137.50

Jumlah Harga Tenaga ..................................................................


38,637.50
B. BAHAN
Kaca polos t. 12 mm, tempered M2 1.100 1,800,000.00 1,980,000.00
Sealant Kg 0.070 48,000.00 3,360.00

Jumlah Harga Bahan ..................................................................


1,983,360.00
C. PERALATAN

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 2,021,997.50
E. Overhead & Profit 10% X D 202,199.75
F. Harga Satuan Pekerjaan (D+E) 2,224,197.25
A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING

A.4.4.1.1 Pemasangan 1 M2 Dinding Bata Merah (5 x 11 x 22) cm, tebal 1 batu Campuran 1 SP : 2 PP
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.600 90,000.00 54,000.00
Tukang Batu L.02 OH 0.200 130,000.00 26,000.00
Kepala Tukang L.03 OH 0.020 150,000.00 3,000.00
Mandor L.04 OH 0.030 110,000.00 3,300.00

Jumlah Harga Tenaga ..................................................................


86,300.00
B. BAHAN
Bata merah Bh 140.000 900.00 126,000.00
Semen Portland Kg 43.500 1,575.00 68,512.50
Pasir pasang M3 0.080 225,000.00 18,000.00

Jumlah Harga Bahan ..................................................................


212,512.50
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 298,812.50
E. Overhead & Profit 10% X D 29,881.25
F. Harga Satuan Pekerjaan (D+E) 328,693.75

A.4.4.1.7 Pemasangan 1 M2 Dinding Bata Merah (5 x 11 x 22) cm, tebal 1/2 batu Campuran 1 SP : 2 PP
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.300 90,000.00 27,000.00
Tukang Batu L.02 OH 0.100 130,000.00 13,000.00
Kepala Tukang L.03 OH 0.010 150,000.00 1,500.00
Mandor L.04 OH 0.015 110,000.00 1,650.00

Jumlah Harga Tenaga ..................................................................


43,150.00
B. BAHAN
Bata merah Bh 70.000 900.00 63,000.00
Semen Portland Kg 18.950 1,575.00 29,846.25
Pasir pasang M3 0.038 225,000.00 8,550.00

Jumlah Harga Bahan ..................................................................


101,396.25
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 144,546.25
E. Overhead & Profit 10% X D 14,454.63
F. Harga Satuan Pekerjaan (D+E) 159,000.88

A.4.4.1.10 Pemasangan 1 M2 Dinding Bata Merah (5 x 11 x 22) cm, tebal 1/2 batu Campuran 1 SP : 5 PP
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.300 90,000.00 27,000.00
Tukang Batu L.02 OH 0.100 130,000.00 13,000.00
Kepala Tukang L.03 OH 0.010 150,000.00 1,500.00
Mandor L.04 OH 0.015 110,000.00 1,650.00

Jumlah Harga Tenaga ..................................................................


43,150.00
B. BAHAN
Bata merah Bh 70.000 900.00 63,000.00
Semen Portland Kg 9.680 1,575.00 15,246.00
Pasir pasang M3 0.045 225,000.00 10,125.00

Jumlah Harga Bahan ..................................................................


88,371.00
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 131,521.00
E. Overhead & Profit 10% X D 13,152.10
F. Harga Satuan Pekerjaan (D+E) 144,673.10

A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN


A.4.4.2.2 Pemasangan 1 M2 Plesteran Campuran 1 SP : 2 PP, Tebal 15 mm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.300 90,000.00 27,000.00
Tukang Batu L.02 OH 0.150 130,000.00 19,500.00
Kepala Tukang L.03 OH 0.015 150,000.00 2,250.00
Mandor L.04 OH 0.015 110,000.00 1,650.00

Jumlah Harga Tenaga ..................................................................


50,400.00
B. BAHAN
Semen Portland Kg 10.224 1,575.00 16,102.80
Pasir pasang M3 0.020 225,000.00 4,500.00

Jumlah Harga Bahan ..................................................................


20,602.80
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 71,002.80
E. Overhead & Profit 10% X D 7,100.28
F. Harga Satuan Pekerjaan (D+E) 78,103.08
A.4.4.2.2a Pemasangan 1 M2 Plesteran Screed Campuran 1 SP : 2 PP, Tebal 15 mm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.300 90,000.00 27,000.00
Tukang Batu L.02 OH 0.150 130,000.00 19,500.00
Kepala Tukang L.03 OH 0.015 150,000.00 2,250.00
Mandor L.04 OH 0.015 110,000.00 1,650.00

Jumlah Harga Tenaga ..................................................................


50,400.00
B. BAHAN
Semen Portland Kg 10.224 1,575.00 16,102.80
Pasir pasang M3 0.020 225,000.00 4,500.00
Kawat ram halus m2 1.050 - -

Jumlah Harga Bahan ..................................................................


20,602.80
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 71,002.80
E. Overhead & Profit 10% X D 7,100.28
F. Harga Satuan Pekerjaan (D+E) 78,103.08

A.4.4.2.3 Pemasangan 1 M2 Plesteran Campuran 1 SP : 3 PP, Tebal 15 mm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.300 90,000.00 27,000.00
Tukang Batu L.02 OH 0.150 130,000.00 19,500.00
Kepala Tukang L.03 OH 0.015 150,000.00 2,250.00
Mandor L.04 OH 0.015 110,000.00 1,650.00

Jumlah Harga Tenaga ..................................................................


50,400.00
B. BAHAN
Semen Portland Kg 7.776 1,575.00 12,247.20
Pasir pasang M3 0.023 225,000.00 5,175.00

Jumlah Harga Bahan ..................................................................


17,422.20
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 67,822.20
E. Overhead & Profit 10% X D 6,782.22
F. Harga Satuan Pekerjaan (D+E) 74,604.42
A.4.4.2.4 Pemasangan 1 M2 Plesteran Campuran 1 SP : 4 PP, Tebal 15 mm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.300 90,000.00 27,000.00
Tukang Batu L.02 OH 0.150 130,000.00 19,500.00
Kepala Tukang L.03 OH 0.015 150,000.00 2,250.00
Mandor L.04 OH 0.015 110,000.00 1,650.00

Jumlah Harga Tenaga ..................................................................


50,400.00
B. BAHAN
Semen Portland Kg 6.240 1,575.00 9,828.00
Pasir pasang M3 0.024 225,000.00 5,400.00

Jumlah Harga Bahan ..................................................................


15,228.00
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 65,628.00
E. Overhead & Profit 10% X D 6,562.80
F. Harga Satuan Pekerjaan (D+E) 72,190.80

A.4.4.2.5 Pemasangan 1 M2 Plesteran Campuran 1 SP : 5 PP, Tebal 15 mm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.300 90,000.00 27,000.00
Tukang Batu L.02 OH 0.150 130,000.00 19,500.00
Kepala Tukang L.03 OH 0.015 150,000.00 2,250.00
Mandor L.04 OH 0.015 110,000.00 1,650.00

Jumlah Harga Tenaga ..................................................................


50,400.00
B. BAHAN
Semen Portland Kg 5.184 1,575.00 8,164.80
Pasir pasang M3 0.026 225,000.00 5,850.00

Jumlah Harga Bahan ..................................................................


14,014.80
C. PERALATAN

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 64,414.80
E. Overhead & Profit 10% X D 6,441.48
F. Harga Satuan Pekerjaan (D+E) 70,856.28
A.4.4.2.16 Pemasangan 1 M2 Plesteran Campuran 1 SP : 5 PP, Tebal 20 mm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.400 90,000.00 36,000.00
Tukang Batu L.02 OH 0.200 130,000.00 26,000.00
Kepala Tukang L.03 OH 0.020 150,000.00 3,000.00
Mandor L.04 OH 0.022 110,000.00 2,420.00

Jumlah Harga Tenaga ..................................................................


67,420.00
B. BAHAN
Semen Portland Kg 6.912 1,575.00 10,886.40
Pasir pasang M3 0.035 225,000.00 7,875.00

Jumlah Harga Bahan ..................................................................


18,761.40
C. PERALATAN

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 86,181.40
E. Overhead & Profit 10% X D 8,618.14
F. Harga Satuan Pekerjaan (D+E) 94,799.54

A.4.4.2.27 Pemasangan 1 M2 Acian


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.120 90,000.00 10,800.00
Tukang Batu L.02 OH 0.060 130,000.00 7,800.00
Kepala Tukang L.03 OH 0.006 150,000.00 900.00
Mandor L.04 OH 0.006 110,000.00 660.00

Jumlah Harga Tenaga ..................................................................


20,160.00
B. BAHAN
Semen Portland Kg 3.250 1,575.00 5,118.75

Jumlah Harga Bahan ..................................................................


5,118.75
C. PERALATAN

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 25,278.75
E. Overhead & Profit 10% X D 2,527.88
F. Harga Satuan Pekerjaan (D+E) 27,806.63
A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

A.4.7.1.10 1 M2 Pengecatan Tembok Baru (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.020 90,000.00 1,800.00
Tukang Cat L.02 OH 0.063 130,000.00 8,190.00
Kepala Tukang L.03 OH 0.0063 150,000.00 945.00
Mandor L.04 OH 0.003 110,000.00 330.00

Jumlah Harga Tenaga ..................................................................


11,265.00
B. BAHAN
Plamur (skim coat) Kg 0.100 3,500.00 350.00
Cat dasar Kg 0.100 27,000.00 2,700.00
Cat penutup (warna), dalam Kg 0.260 35,000.00 9,100.00

Jumlah Harga Bahan ..................................................................


12,150.00
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 23,415.00
E. Overhead & Profit 10% X D 2,341.50
F. Harga Satuan Pekerjaan (D+E) 25,756.50

A.4.7.1.10a 1 M2 Pengecatan Tembok Baru (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.020 90,000.00 1,800.00
Tukang Cat L.02 OH 0.063 130,000.00 8,190.00
Kepala Tukang L.03 OH 0.0063 150,000.00 945.00
Mandor L.04 OH 0.003 110,000.00 330.00

Jumlah Harga Tenaga ..................................................................


11,265.00
B. BAHAN
Plamur (skim coat) Kg 0.100 3,500.00 350.00
Cat dasar Kg 0.100 27,000.00 2,700.00
Cat penutup (warna), luar Kg 0.260 35,000.00 9,100.00

Jumlah Harga Bahan ..................................................................


12,150.00
C. PERALATAN
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 23,415.00
E. Overhead & Profit 10% X D 2,341.50
F. Harga Satuan Pekerjaan (D+E) 25,756.50

A.4.7.1.11 1 M2 Pengecatan Tembok Lama (1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.028 90,000.00 2,520.00
Tukang Cat L.02 OH 0.042 130,000.00 5,460.00
Kepala Tukang L.03 OH 0.0042 150,000.00 630.00
Mandor L.04 OH 0.003 110,000.00 330.00

Jumlah Harga Tenaga ..................................................................


8,940.00
B. BAHAN
Cat dasar Kg 0.120 27,000.00 3,240.00
Cat penutup (warna) Kg 0.180 35,000.00 6,300.00

Jumlah Harga Bahan ..................................................................


9,540.00
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 18,480.00
E. Overhead & Profit 10% X D 1,848.00
F. Harga Satuan Pekerjaan (D+E) 20,328.00

A.4.7.1.16 1 M2 Pengecatan Permukaan Besi dengan Cat Epoxy Anti Karat


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.020 90,000.00 1,800.00
Tukang Cat L.02 OH 0.200 130,000.00 26,000.00
Kepala Tukang L.03 OH 0.020 150,000.00 3,000.00
Mandor L.04 OH 0.0025 110,000.00 275.00

Jumlah Harga Tenaga ..................................................................


31,075.00
B. BAHAN
Cat epoxy Kg 0.200 70,000.00 14,000.00
Kuas 3" Bh 0.010 8,500.00 85.00

Jumlah Harga Bahan ..................................................................


14,085.00
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 45,160.00
E. Overhead & Profit 10% X D 4,516.00
F. Harga Satuan Pekerjaan (D+E) 49,676.00
A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG

A.5.1.1.1 Pemasangan 1 Buah Closet Duduk / Monoblock


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 3.300 90,000.00 297,000.00
Tukang Batu L.02 OH 1.100 130,000.00 143,000.00
Kepala Tukang L.03 OH 0.010 150,000.00 1,500.00
Mandor L.04 OH 0.160 110,000.00 17,600.00

Jumlah Harga Tenaga ..................................................................


459,100.00
B. BAHAN
Closet duduk Unit 1.000 2,900,000.00 2,900,000.00
Perlengkapan Ls 6% x closet 174,000.00 174,000.00

Jumlah Harga Bahan ..................................................................


3,074,000.00
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 3,533,100.00
E. Overhead & Profit 10% X D 353,310.00
F. Harga Satuan Pekerjaan (D+E) 3,886,410.00

A.5.1.1.2 Pemasangan 1 Buah Closet Jongkok / Monoblock


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 3.300 90,000.00 297,000.00
Tukang Batu L.02 OH 1.100 130,000.00 143,000.00
Kepala Tukang L.03 OH 0.010 150,000.00 1,500.00
Mandor L.04 OH 0.160 110,000.00 17,600.00

Jumlah Harga Tenaga ..................................................................


459,100.00
B. BAHAN
Closet duduk Unit 1.000 757,850.00 757,850.00
Perlengkapan Ls 6% x closet 45,471.00 45,471.00

Jumlah Harga Bahan ..................................................................


803,321.00
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 1,262,421.00
E. Overhead & Profit 10% X D 126,242.10
F. Harga Satuan Pekerjaan (D+E) 1,388,663.10

A.5.1.1.5 Pemasangan 1 Buah Wastafel


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 1.200 90,000.00 108,000.00
Tukang Batu L.02 OH 1.450 130,000.00 188,500.00
Kepala Tukang L.03 OH 0.150 150,000.00 22,500.00
Mandor L.04 OH 0.060 110,000.00 6,600.00

Jumlah Harga Tenaga ..................................................................


325,600.00
B. BAHAN
Wastafel Unit 1.000 950,000.00 950,000.00
Semen Portland Kg 6.000 1,575.00 9,450.00
Pasir pasang M3 0.010 225,000.00 2,250.00
Perlengkapan Ls 12% 950,000.00 114,000.00

Jumlah Harga Bahan ..................................................................


1,075,700.00
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 1,401,300.00
E. Overhead & Profit 10% X D 140,130.00
F. Harga Satuan Pekerjaan (D+E) 1,541,430.00

A.5.1.1.12 Pemasangan 1 Buah Bak Cuci Piring Stainless Steel


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.030 90,000.00 2,700.00
Tukang Batu L.02 OH 0.300 130,000.00 39,000.00
Kepala Tukang L.03 OH 0.030 150,000.00 4,500.00
Mandor L.04 OH 0.015 110,000.00 1,650.00

Jumlah Harga Tenaga ..................................................................


47,850.00
B. BAHAN
Bak cuci piring Unit 1.000 500,000.00 500,000.00
Waterdrain Bh 1.000 175,000.00 175,000.00

Jumlah Harga Bahan ..................................................................


675,000.00
C. PERALATAN

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 722,850.00
E. Overhead & Profit 10% X D 72,285.00
F. Harga Satuan Pekerjaan (D+E) 795,135.00

A.5.1.1.14 Pemasangan 1 Buah Floor Drain


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.010 90,000.00 900.00
Tukang Batu L.02 OH 0.100 130,000.00 13,000.00
Kepala Tukang L.03 OH 0.010 150,000.00 1,500.00
Mandor L.04 OH 0.005 110,000.00 550.00

Jumlah Harga Tenaga ..................................................................


15,950.00
B. BAHAN
Floor drain Unit 1.000 95,000.00 95,000.00

Jumlah Harga Bahan ..................................................................


95,000.00
C. PERALATAN

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 110,950.00
E. Overhead & Profit 10% X D 11,095.00
F. Harga Satuan Pekerjaan (D+E) 122,045.00

A.5.1.1.14a Pemasangan 1 Buah Roof Drain dia. 3"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.020 90,000.00 1,800.00
Tukang Batu L.02 OH 0.200 130,000.00 26,000.00
Kepala Tukang L.03 OH 0.020 150,000.00 3,000.00
Mandor L.04 OH 0.010 110,000.00 1,100.00

Jumlah Harga Tenaga ..................................................................


31,900.00
B. BAHAN
Roof drain, dia. 3" Unit 1.000 135,000.00 135,000.00

Jumlah Harga Bahan ..................................................................


135,000.00
C. PERALATAN

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 166,900.00
E. Overhead & Profit 10% X D 16,690.00
F. Harga Satuan Pekerjaan (D+E) 183,590.00

A.5.1.1.18 Pemasangan 1 Buah Kran Air diameter 1/2" atau 3/4"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.010 90,000.00 900.00
Tukang Batu L.02 OH 0.400 130,000.00 52,000.00
Kepala Tukang L.03 OH 0.040 150,000.00 6,000.00
Mandor L.04 OH 0.005 110,000.00 550.00

Jumlah Harga Tenaga ..................................................................


59,450.00
B. BAHAN
Kran air Bh 1.000 100,000.00 100,000.00
Seal tape Bh 0.025 3,500.00 87.50

Jumlah Harga Bahan ..................................................................


100,087.50
C. PERALATAN

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 159,537.50
E. Overhead & Profit 10% X D 15,953.75
F. Harga Satuan Pekerjaan (D+E) 175,491.25

A.5.1.1.26 Pemasangan 1 M' Pipa PVC tipe AW 3/4"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.036 90,000.00 3,240.00
Tukang Batu L.02 OH 0.060 130,000.00 7,800.00
Kepala Tukang L.03 OH 0.006 150,000.00 900.00
Mandor L.04 OH 0.002 110,000.00 220.00

Jumlah Harga Tenaga ..................................................................


12,160.00
B. BAHAN
Pipa PVC dia. 3/4" M' 1.200 8,000.00 9,600.00
Perlengkapan Ls 35% 8,000.00 2,800.00

Jumlah Harga Bahan ..................................................................


12,400.00
C. PERALATAN

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 24,560.00
E. Overhead & Profit 10% X D 2,456.00
F. Harga Satuan Pekerjaan (D+E) 27,016.00

A.5.1.1.29 Pemasangan 1 M' Pipa PVC tipe AW 2"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.054 90,000.00 4,860.00
Tukang Batu L.02 OH 0.090 130,000.00 11,700.00
Kepala Tukang L.03 OH 0.009 150,000.00 1,350.00
Mandor L.04 OH 0.003 110,000.00 330.00

Jumlah Harga Tenaga ..................................................................


18,240.00
B. BAHAN
Pipa PVC dia. 2" M' 1.200 27,830.00 33,396.00
Perlengkapan Ls 35% 27,830.00 9,740.50

Jumlah Harga Bahan ..................................................................


43,136.50
C. PERALATAN

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 61,376.50
E. Overhead & Profit 10% X D 6,137.65
F. Harga Satuan Pekerjaan (D+E) 67,514.15

A.5.1.1.31 Pemasangan 1 M' Pipa PVC tipe AW 3"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.081 90,000.00 7,290.00
Tukang Batu L.02 OH 0.135 130,000.00 17,550.00
Kepala Tukang L.03 OH 0.0135 150,000.00 2,025.00
Mandor L.04 OH 0.004 110,000.00 440.00

Jumlah Harga Tenaga ..................................................................


27,305.00
B. BAHAN
Pipa PVC dia. 3" M' 1.200 56,760.00 68,112.00
Perlengkapan Ls 35% 56,760.00 19,866.00

Jumlah Harga Bahan ..................................................................


87,978.00
C. PERALATAN

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 115,283.00
E. Overhead & Profit 10% X D 11,528.30
F. Harga Satuan Pekerjaan (D+E) 126,811.30

A.5.1.1.32 Pemasangan 1 M' Pipa PVC tipe AW 4"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.081 90,000.00 7,290.00
Tukang Batu L.02 OH 0.135 130,000.00 17,550.00
Kepala Tukang L.03 OH 0.0135 150,000.00 2,025.00
Mandor L.04 OH 0.004 110,000.00 440.00

Jumlah Harga Tenaga ..................................................................


27,305.00
B. BAHAN
Pipa PVC dia. 4" M' 1.200 85,256.00 102,307.20
Perlengkapan Ls 35% 85,256.00 29,839.60

Jumlah Harga Bahan ..................................................................


132,146.80
C. PERALATAN
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 159,451.80
E. Overhead & Profit 10% X D 15,945.18
F. Harga Satuan Pekerjaan (D+E) 175,396.98
A.8.5.1 HARGA SATUAN PEKERJAAN ELEKTRIKAL

A.8.5.1.1 Pemasangan 1 Unit Panel Penerangan / Stop Kontak


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 6.000 90,000.00 540,000.00
Tukang Listrik L.02 OH 6.000 130,000.00 780,000.00
Kepala Tukang L.04 OH 0.600 150,000.00 90,000.00
Mandor L.04 OH 0.600 110,000.00 66,000.00

Jumlah Harga Tenaga ..................................................................


1,476,000.00
B. BAHAN
MCCB 30A,3P, 10kA Bh 1.000 1,200,000.00 1,200,000.00
MCB10A,1P Bh 6.000 67,500.00 405,000.00
Pilot lamp Bh 3.000 24,000.00 72,000.00
Fuse 2 A Bh 3.000 24,000.00 72,000.00
Busbar Cu Lot 1.000 1,350,000.00 1,350,000.00
Box Panel Unit 1.000 2,700,000.00 2,700,000.00
Wiring Accessories Lot 1.000 750,000.00 750,000.00

Jumlah Harga Bahan ..................................................................


6,549,000.00
C. PERALATAN
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 8,025,000.00
E. Overhead & Profit 10% X D 802,500.00
F. Harga Satuan Pekerjaan (D+E) 8,827,500.00

A.8.5.1.2 Pemasangan 1 Unit Panel AC


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 8.000 90,000.00 720,000.00
Tukang Listrik L.02 OH 8.000 130,000.00 1,040,000.00
Kepala Tukang L.04 OH 0.800 150,000.00 120,000.00
Mandor L.04 OH 0.800 110,000.00 88,000.00

Jumlah Harga Tenaga ..................................................................


1,968,000.00
B. BAHAN
MCB100A,3P Bh 1.000 1,800,000.00 1,800,000.00
MCB 16A,1P Bh 6.000 135,000.00 810,000.00
Pilot lamp Bh 3.000 24,000.00 72,000.00
Fuse 2 A Bh 10.000 24,000.00 240,000.00
Busbar Cu Lot 1.000 1,350,000.00 1,350,000.00
Box Panel Unit 1.000 2,700,000.00 2,700,000.00
Wiring Accessories Lot 1.000 750,000.00 750,000.00

Jumlah Harga Bahan ..................................................................


7,722,000.00
C. PERALATAN
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 9,690,000.00
E. Overhead & Profit 10% X D 969,000.00
F. Harga Satuan Pekerjaan (D+E) 10,659,000.00

A.8.5.1.3 Pemasangan 1 Meter Kabel NYFGbY 4 x 50 mm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.120 90,000.00 10,800.00
Tukang Listrik L.02 OH 0.040 130,000.00 5,200.00
Kepala Tukang L.04 OH 0.040 150,000.00 6,000.00
Mandor L.04 OH 0.080 110,000.00 8,800.00

Jumlah Harga Tenaga ..................................................................


30,800.00
B. BAHAN
Kabel NYFGbY 4 x 50 mm2 M' 1.000 577,500.00 577,500.00

Jumlah Harga Bahan ..................................................................


577,500.00
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 608,300.00
E. Overhead & Profit 10% X D 60,830.00
F. Harga Satuan Pekerjaan (D+E) 669,130.00

A.8.5.1.4 Pemasangan 1 Meter Kabel NYFGbY 4 x 70 mm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.170 90,000.00 15,300.00
Tukang Listrik L.02 OH 0.060 130,000.00 7,800.00
Kepala Tukang L.04 OH 0.060 150,000.00 9,000.00
Mandor L.04 OH 0.010 110,000.00 1,100.00

Jumlah Harga Tenaga ..................................................................


33,200.00
B. BAHAN
Kabel NYFGbY 4 x 70 mm2 M' 1.000 675,000.00 675,000.00

Jumlah Harga Bahan ..................................................................


675,000.00
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 708,200.00
E. Overhead & Profit 10% X D 70,820.00
F. Harga Satuan Pekerjaan (D+E) 779,020.00

A.8.5.1.5 Pemasangan 1 Titik Instalasi Penerangan


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.400 90,000.00 36,000.00
Tukang Listrik L.02 OH 0.200 130,000.00 26,000.00
Kepala Tukang L.04 OH 0.200 150,000.00 30,000.00
Mandor L.04 OH 0.020 110,000.00 2,200.00

Jumlah Harga Tenaga ..................................................................


94,200.00
B. BAHAN
Kabel Listrik NYM 3x 2,5 mm M' 10.000 22,500.00 225,000.00
PVC Konduit Ø20 mm M' 5.000 5,250.00 26,250.00
Bahan lainnya Ls 1.000 5,000.00 5,000.00

Jumlah Harga Bahan ..................................................................


256,250.00
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 350,450.00
E. Overhead & Profit 10% X D 35,045.00
F. Harga Satuan Pekerjaan (D+E) 385,495.00

A.8.5.1.6 Pemasangan 1 Titik Instalasi Stop Kontak


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.500 90,000.00 45,000.00
Tukang Listrik L.02 OH 0.250 130,000.00 32,500.00
Kepala Tukang L.04 OH 0.250 150,000.00 37,500.00
Mandor L.04 OH 0.025 110,000.00 2,750.00

Jumlah Harga Tenaga ..................................................................


117,750.00
B. BAHAN
Kabel Listrik NYM 3x 2,5 mm M' 10.000 22,500.00 225,000.00
PVC Konduit Ø20 mm M' 5.000 5,250.00 26,250.00
Bahan lainnya Ls 1.000 5,000.00 5,000.00

Jumlah Harga Bahan ..................................................................


256,250.00
C. PERALATAN
-
-

Jumlah Harga Peralatan .................................................................. -


D. Jumlah (A+B+C) 374,000.00
E. Overhead & Profit 10% X D 37,400.00
F. Harga Satuan Pekerjaan (D+E) 411,400.00
DAFTAR HARGA - 2019

1. DAFTAR HARGA BAHAN / MATERIAL

HARGA SATUAN
NO. U R A I A N SATUAN KETERANGAN
(Rp.)
1 2 3 4 5
A. BAHAN DASAR
1 Batu merah bh 900.00
2 Batu belah 15 - 20 m3 229,500.00
3 Batu pecah 2-3 m3 449,263.00
kg 332.79
4 Pasir Pasangan m3 225,000.00
5 Pasir Plester m3 225,000.00
6 Pasir Beton m3 225,000.00
kg 160.71
7 Pasir timbunan/urug m3 160,000.00
8 Tanah Timbunan m3 60,000.00
9 Sirtu m3 191,625.00
10 Semen PC zak 78,750.00
kg 1,575.00
11 Semen Warna (semen nat) kg 25,358.00
12 Gorong2 dia. 70 cm (dalam), p. 50 cm, t. 10 cm bh 320,000.00 Mutu beton K.200
13 Air liter 300.00
B. BAHAN ATAP, BESI & ALUMINIUM
1 Genteng metal lbr (m') 89,452.00 Setara Surya
2 Nok genteng metal (raja) lbr (m') 42,000.00 Setara Surya
3 Spandek / Galvalum t. 0,4 mm (model standar) m' 55,000.00
4 Spandek / Galvalum t. 0,35 mm (model melengkung) m' 110,000.00
5 Nok Baja Ringan (Galvalum) standar Lbr.45 cm m' 35,000.00
6 Seng Gelombang BJLS 0.28 Lbr 40,000.00
Seng plat talang BJLS 0.28
7 Bondek tebal 0.70 mm m2 100,000.00
8 Rangka Atap Baja Ringan m2 180,000.00 Setara Sakura Truss
9 Besi Beton (SIGMA)
- Polos (U.24) kg 13,000.00
- Ulir (U.32) kg 13,000.00
10 Kawat Beton kg 27,405.00
11 Wiremesh M10 M2 95,000.00 Uk. 5.4 m x 2.1 m
12 Kawat ram halus (bahan screed) m2
13 Besi beton kotak 12.12 kg
14 Paku biasa kg 20,000.00
15 Paku biasa 1/2" - 1" (tripleks) kg 20,000.00
16 Paku Biasa 5" - 12" kg 20,000.00
17 Paku sekrup baja ringan (atap) kg 28,088.00
18 Paku sekrup gypsum kg 29,295.00
19 Paku sekrup genteng, woodplank kg 29,295.00
20 Paku seng/payung kg 30,000.00
21 Paku hak panjang 15 cm kg 50,000.00
22 Sekrup spandek bh 700.00
25 Aluminium 4" - Silver m' 95,000.00
26 Bingkai pintu Aluminium 4" - Putih m' 110,000.00
27 Profil aluminium "T" m' 52,000.00
27 ALUMINIUM Foil m2 55,000.00
28 Alumunium Composite Panel (ACP) m2 487,500.00
29 Alumunium Stifner Panel m' 120,000.00
28 Alumunium Siku 30 x 16 m' 72,000.00
29 Bracket besi siku 7 x 7 kg 21,525.00
30 Dynabolt M 10 x 120 bh 2,247.00
29 Mur + baut M 10 x 70 bh 2,500.00
C. BAHAN FINISHING CAT
1 Cat Dasar kg 27,000.00 Setara Metrolite
2 Meni kayu kg 27,000.00
3 Cat Kayu kg 65,000.00 Setara Avian
4 Cat besi Epoxy kg 70,000.00 Setara Altex
DAFTAR HARGA - 2019

HARGA SATUAN
NO. U R A I A N SATUAN KETERANGAN
(Rp.)
1 2 3 4 5
5 Cat Tembok, dalam kg 35,000.00 Setara Mowilex
6 Cat Tembok, luar kg 35,000.00
7 Cat Tembok Wheathershield kg 85,000.00
8 Cat anti bocor / Waterproof kg 82,500.00
9 Skim Coat kg 3,500.00
10 Minyak cat / pengencer kg 25,000.00
11 Minyak bekisting liter 7,500.00
12 Minyak pelumas liter 25,000.00
13 Cornice zak 85,000.00
14 Plaster Gypsum roll 12,000.00
15 Kuas 3" bh 8,500.00
16 Kuas 4" bh 17,000.00
17 Amplas lembar 3,000.00
D. BAHAN PENGGANTUNG & KACA
1 Kunci pintu 2x putar set 250,000.00 Setara Kend
- Handle Type HRE 75.58
- Lockcase Type K 87735-40/60
- Cylinder Type 08610 - 13
2 Kunci pintu KM set 172,500.00 Setara Fino
- Handle Type PP.73.06 FB
- Cylinder Type KC1002-60
3 Engsel Pintu Type SEL FB08 4BB bh 35,000.00
4 Engsel casement sedang Type CMT FB27 16" bh 45,000.00
5 Grendel Jendela, type kodok bh 40,250.00
6 Hak angin/kait angin, 8" bh 23,000.00 Bulat
7 Sealant kaca & dinding kg 48,000.00
8 Isolasi sealant kg 7,200.00
9 Skrup aluminium bh 540.00
10 Butyl sealer bh 11,000.00
11 Terot / track stang bh 25,000.00
12 Masking tape kg 11,500.00
13 Kaca polos tebal 5 mm m2 185,000.00 Setara Asahi
14 Kaca polos tebal 10 mm, tempered m2 1,080,000.00 Setara Asahi
15 Kaca polos tebal 12 mm, tempered m2 1,800,000.00 Setara Asahi
E. BAHAN SANITAIR DAN PIPA
1 Kloset duduk warna, tabung unit 2,900,000.00 Setara American Stdr
2 Kloset jongkok, porselin putih unit 757,850.00 Setara American Stdr
3 Wastafel, porselin unit 950,000.00
4 Urinoir unit 1,450,000.00
5 Bak cuci piring (stainless steel - 1 mata) unit 500,000.00
6 Pipa PVC Ø3/4" - AW m' 8,000.00
7 Pipa PVC Ø2" - AW m' 27,830.00
8 Pipa PVC Ø3" - AW m' 56,760.00
9 Pipa PVC Ø4" - AW m' 85,256.00
10 Floor Drain, Stainless Steel, 3" bh 95,000.00 Setara Onda
11 Roof Drain, Stainless Steel, 3" bh 135,000.00
12 Roof Drain, Stainless Steel, 4" bh 175,000.00
13 Waterdrain untuk bak cuci piring bh 175,000.00
14 Kran air 3/4" bh 100,000.00 Setara Onda
15 Kran wastafel, Angsa bh 150,000.00
16 Kran klosed bh 85,000.00
17 Jet Shower set 135,000.00
18 Bath Shower set 1,425,000.00
19 Seal tape bh 3,500.00
20 Tangki air fiber kapasitas 1 m3 unit 2,700,000.00 Setara Excel, terpasang
21 Pompa air total head 15 m + r. pompa & radar set 2,550,000.00 Setara Sanyo, terpasang
F. BAHAN LANGIT - LANGIT & DINDING PARTISI
1 Multipleks 120 x 240 x 4 mm lbr 112,687.00
2 Multipleks 120 x 240 x 6 mm lbr 159,555.00
3 Multipleks 120 x 240 x 9 mm lbr 202,230.00
DAFTAR HARGA - 2019

HARGA SATUAN
NO. U R A I A N SATUAN KETERANGAN
(Rp.)
1 2 3 4 5
4 Gypsum 120 x 240 x 9 mm lbr 81,500.00
5 Kalsiboard 120 x 240 x 6 mm lbr 74,750.00
6 Rangka plafond hollow 20.40.2 mm m' 7,950.00
7 Rangka plafond hollow 40.40.2 mm m' 9,600.00
G. BAHAN LANTAI & KERAMIK
1 Keramik 30 x 30 cm, motif bh 9,450.00 Setara Asia Tile
2 Keramik 40 x 40 cm, motif bh 18,000.00 Setara Asia Tile
3 Keramik 30 x 60 cm, motif bh 24,000.00 Setara Platinum
4 Keramik 10 x 30 cm, motif bh 3,150.00 Setara Asia Tile
5 Keramik 10 x 40 cm, motif bh 4,500.00 Setara Asia Tile
6 Granit 60 x 60 cm (hitam, motif) bh 99,000.00 Setara Garuda
7 Granit 60 x 60 cm (terang, motif) bh 72,000.00 Setara Garuda
8 Granit 10 x 60 cm (hitam, motif) bh 16,500.00 Setara Garuda
9 Granit 10 x 60 cm (terang, motif) bh 12,000.00 Setara Garuda
10 Granit 30 x 60 cm (terang, motif) bergaris step nosing bh 115,500.00 Setara Garuda, lapis
H. BAHAN KAYU
1 Kayu Klas I - balok m3 6,279,000.00 Setara Bayam
2 Kayu Klas I - papan m3 6,279,000.00 Setara Bayam
3 Kayu Klas II - balok m3 4,200,000.00 Setara Samarinda
4 Kayu Klas II - papan m3 4,200,000.00 Setara Samarinda
5 Kayu Bekisting (papan) m3 2,205,000.00 Setara Garuda
6 Kayu kelas III - balok m3 3,360,000.00
7 Dolken kayu dia. 8 - 10/400 cm btg 9,345.00 dia. 10 - 15 cm
8 Woodplank 1,8/20 cm m' 45,000.00 Motif urat kayu
I. BAHAN LISTRIK
1 Lampu T.8 LED 2 x 18 Watt (RM) bh 825,000.00
2 Lampu T.8 LED 18 Watt bh 195,000.00
3 Down Light 1 X18 Watt, lengkap dengan kap bh 367,500.00
4 Lampu SL. 25 Watt bh 82,500.00 Setara Philips, Tornado
5 Lampu SL. 18 Watt bh 67,500.00 Setara Philips, Tornado
6 Lampu SL. 18 Watt + kap bundar 30 cm (pagar) bh 442,500.00 Setara Philips, Tornado
7 Lampu halogen 8 watt/LED bundar bh 97,500.00 Setara Artolite
8 Lampu Down Light RD 150, 18 Watt bh 525,000.00 Setara Artolite
9 Lampu HPIT 400 Watt bh 2,550,000.00 Setara Artolite
10 Lampu HPIT 250 Watt bh 1,800,000.00 Setara Artolite
11 Fitting Lampu Kapsul (tanam - 4") bh 82,500.00 Setara Helles
12 Fitting Lampu Kapsul (tempel) bh 27,000.00 Setara Helles
13 Stop Kontak Tanam (Putih), 200 W / 16 A bh 52,500.00 Setara Panasonic
14 Stop Kontak AC (Putih), 16 A bh 127,500.00 Setara Panasonic
15 Stop Kontak 3P 32 A bh 525,000.00 Setara Panasonic
16 Saklar Seri Tanam (Putih) bh 67,500.00 Setara Panasonic
17 Saklar Tunggal Tanam (Putih) bh 57,000.00 Setara Panasonic
18 PVC Konduit Ø20 mm m' 5,250.00 Setara Maspion
19 MCB - 1 Group bh 112,500.00
20 MCB - 2 Group bh 180,000.00
21 MCB - 3 Group bh 270,000.00
22 MCCB 30A,3P, 10kA bh 1,200,000.00
23 MCB10A,1P bh 67,500.00
24 MCB100A,3P bh 1,800,000.00
25 MCB 16A,1P bh 135,000.00
26 Pilot lamp bh 24,000.00
27 Fuse 2 A bh 24,000.00
28 Busbar Cu lot 1,350,000.00
29 Box Panel unit 2,700,000.00
30 Wiring Accessories lot 750,000.00
31 Kabel NYFGbY 4 x 50 mm2 m' 577,500.00
32 Kabel NYFGbY 4 x 70 mm2 m' 675,000.00
33 Kabel NYY 4x16 mm2 m' 300,000.00
34 NYY 4 x 25 mm3 m' 330,000.00
35 Kabel Listrik NYM 3x 2,5 mm m' 22,500.00
DAFTAR HARGA - 2019

HARGA SATUAN
NO. U R A I A N SATUAN KETERANGAN
(Rp.)
1 2 3 4 5
36 Kabel Listrik NYM 3x 1,5 mm m' 18,000.00
DAFTAR UPAH - 2018

2. DAFTAR UPAH TENAGA KERJA

HARGA SATUAN
NO. URAIAN TENAGA KERJA SATUAN KETERANGAN
(Rp.)
1 Pekerja oh 90,000.00
2 Tukang Batu oh 130,000.00
3 Tukang Kayu oh 130,000.00
4 Tukang Besi oh 130,000.00
5 Tukang Cat oh 130,000.00
6 Tukang Listrik oh 130,000.00
7 Tukang Las oh 130,000.00
8 Tukang Baja Ringan oh -
9 Kepala Tukang Batu oh 150,000.00
10 Kepala Tukang Kayu oh 150,000.00
11 Kepala Tukang Besi oh 150,000.00
12 Kepala Tukang Cat oh 150,000.00
13 Kepala Tukang Listrik oh 150,000.00
14 Kepala Tukang Las oh 150,000.00
15 Kepala Tukang Baja Ringan oh -
16 Mandor oh 110,000.00

Anda mungkin juga menyukai