Anda di halaman 1dari 3

BILL OF QUANTITY

PROYEK : PEKERJAAN TATA UDARA RS. SARININGSIH - BANDUNG


LOKASI : KOTA BANDUNG

INSTALASI UNIT AC LG VRF SYSTEM 6 Oktober 2022


HARGA (IDR)
NO URAIAN PEKERJAAN VOL SAT MATERIAL JASA
SATUAN TOTAL SATUAN TOTAL
Pemasangan Indoor Unit AC VRF termasuk Bracket,
Hanger, Front Panel dan Aksesoris lainnya sesuai
Gambar dan Spesifikasi

1 Tipe : 4-WAY CASSETTE 112 Unit - - 960,196 107,541,897


Kapasitas : 19.100 BTU/H

2 Tipe : 4-WAY CASSETTE 4 Unit - - 960,196 3,840,782


Kapasitas : 36.200 BTU/H

3 Tipe : 4-WAY CASSETTE 3 Unit - - 960,196 2,880,587


Kapasitas : 48.100 BTU/H

4 Tipe : 4-WAY CASSETTE 1 Unit - - 960,196 960,196


Kapasitas : 54.000 BTU/H

5 Tipe : 1-WAY CASSETTE 6 Unit - - 533,442 3,200,652


Kapasitas : 7.500 BTU/H

6 Tipe : 1-WAY CASSETTE 64 Unit - - 533,442 34,140,285


Kapasitas : 9.550 BTU/H

Pemasangan Outdoor Unit AC VRF termasuk


Pondasi, Canal, Rubber Pad dan Aksesoris lainnya
sesuai Gambar dan Spesifikasi
1 OU-VRF 1 Unit - - 8,961,825 8,961,825
Lokasi : Roof
Kapasitas : 133.800 BTU/H

2 OU-VRF 2 Unit - - 8,961,825 17,923,650


Lokasi : Roof
Kapasitas : 172.000 BTU/H

3 OU-VRF 2 Unit - - 8,961,825 17,923,650


Lokasi : Roof
Kapasitas : 229.300 BTU/H

4 OU-VRF 1 Unit - - 8,961,825 8,961,825


Lokasi : Roof
Kapasitas : 248.400 BTU/H

5 OU-VRF 1 Unit - - 8,961,825 8,961,825


Lokasi : Roof
Kapasitas : 286.600 BTU/H

6 OU-VRF 3 Unit - - 8,961,825 26,885,474


Lokasi : Roof

Page 1 of 3
BILL OF QUANTITY
PROYEK : PEKERJAAN TATA UDARA RS. SARININGSIH - BANDUNG
LOKASI : KOTA BANDUNG

INSTALASI UNIT AC LG VRF SYSTEM 6 Oktober 2022


HARGA (IDR)
NO URAIAN PEKERJAAN VOL SAT MATERIAL JASA
SATUAN TOTAL SATUAN TOTAL
Kapasitas : 305.700 BTU/H

7 OU-VRF 1 Unit - - 13,442,737 13,442,737


Lokasi : Roof
Kapasitas : 477.700 BTU/H

Pemasangan Central Control, Y-Branch dan Outdoor


Pipe Connection termasuk Isolasi Thermal, Support
dan Aksesoris lainnya
1 Branch Pipe ARBLN01621 63 Unit - - 213,377 13,442,737
2 Branch Pipe ARBLN03321 49 Unit - - 213,377 10,455,462
3 Branch Pipe ARBLN07121 52 Unit - - 213,377 11,095,593
4 Branch Pipe ARBLN014521 15 Unit - - 213,377 3,200,652
5 Outdoor Pipe Connection ARCNN21 5 Unit - - 320,065 1,600,326
6 Central Control PACP5A000 1 Unit - - 3,734,094 3,734,094

Pemasangan Exhaust Hood Outdoor Unit


1 Outdoor Unit VRF 16 Modul - - 1,066,884 17,070,142

SUB TOTAL 1 316,224,389

Pengadaan, Pemasangan dan Pengetesan Pipa


Refrigerant AC VRF, Copper Pipe ASTM B280
termasuk Isolasi Thermal, Support, Hanger dan
Aksesoris lainnya
1 Copper pipe c/w closed cell elastomeric 1/4 : 1/2 1,327 M 244,530 324,491,032 64,013 84,945,296
2 Copper pipe c/w closed cell elastomeric 3/8 : 5/8 244 M 343,110 83,718,807 64,013 15,619,180
3 Copper pipe c/w closed cell elastomeric 3/8 : 3/4 38 M 359,753 13,670,624 66,147 2,513,578
4 Copper pipe c/w closed cell elastomeric 3/8 : 7/8 72 M 431,448 31,064,245 66,147 4,762,570
5 Copper pipe c/w closed cell elastomeric 1/2 : 3/4 43 M 382,798 16,460,312 71,481 3,073,693
6 Copper pipe c/w closed cell elastomeric 1/2 : 7/8 56 M 454,493 25,451,582 72,548 4,062,694
7 Copper pipe c/w closed cell elastomeric 1/2 : 1 58 M 509,544 29,553,538 74,682 4,331,549
8 Copper pipe c/w closed cell elastomeric 1/2 : 1 1/8 59 M 532,588 31,422,718 74,682 4,406,231
9 Copper pipe c/w closed cell elastomeric 5/8 : 1 1/8 97 M 599,162 58,118,714 74,682 7,244,142
10 Copper pipe c/w closed cell elastomeric 5/8 : 1 1/4 95 M 659,334 62,636,754 74,682 7,094,778
11 Copper pipe c/w closed cell elastomeric 5/8 : 1 3/8 65 M 759,195 49,347,648 78,949 5,131,712
12 Copper pipe c/w closed cell elastomeric 3/4 : 1 1/4 93 M 675,978 62,865,921 78,949 7,342,295
13 Copper pipe c/w closed cell elastomeric 3/4 : 1 3/8 105 M 775,838 81,462,987 76,816 8,065,642
14 Copper pipe c/w closed cell elastomeric 3/4 : 1 1/2 25 M 796,322 19,908,054 85,351 2,133,768
15 Copper pipe c/w closed cell elastomeric 3/4 : 1 5/8 32 M 910,265 29,128,491 85,351 2,731,223
16 Copper pipe c/w closed cell elastomeric 7/8 : 1 1/2 63 M 868,017 54,685,055 85,351 5,377,095

SUB TOTAL 2 973,986,480 168,835,444

Pengadaan, Pemasangan dan Pengetesan Pipa


Drain, PVC termasuk Isolasi Thermal, Support dan
Aksesoris lainnya

Page 2 of 3
BILL OF QUANTITY
PROYEK : PEKERJAAN TATA UDARA RS. SARININGSIH - BANDUNG
LOKASI : KOTA BANDUNG

INSTALASI UNIT AC LG VRF SYSTEM 6 Oktober 2022


HARGA (IDR)
NO URAIAN PEKERJAAN VOL SAT MATERIAL JASA
SATUAN TOTAL SATUAN TOTAL
1 PVC D Class + Isolasi Diameter 40 mm 55 M 84,497 4,647,346 29,873 1,643,001
2 PVC D Class + Isolasi Diameter 32 mm 110 M 55,051 6,055,633 29,873 3,286,002
3 PVC D Class + Isolasi Diameter 25 mm 110 M 47,370 5,210,661 27,739 3,051,288
4 PVC D Class + Isolasi Diameter 20 mm 792 M 29,873 23,659,217 27,739 21,969,273

SUB TOTAL 3 39,572,858 29,949,565

Pengadaan dan Pemasangan Kabel Kontrol


termasuk Pengisian Refrigerant Tambahan serta
Testing dan Commissioning
1 Kabel Transmisi AC VRF, Shielded Wired 2 x 1,5 mm2 2,472 M 37,341 92,306,795 21,338 52,746,740
2 Kabel Power Indoor Unit VYM 3 x 2,5 mm2 2,472 M 32,007 79,120,110 21,338 52,746,740
3 Penambahan Freon R-410A 23 Can 3,627,405 83,430,321 - -
4 Testing dan Commissioning 1 Lot - - 10,668,839 10,668,839
5 Pengadaan Personal Computer (PC) 1 Unit 19,203,910 19,203,910 - -
6 Pekerjaan Bongkar Pasang Plafon 1 Lot 74,681,873 74,681,873 - -

SUB TOTAL 4 348,743,010 116,162,319


GRAND SUB TOTAL (SUB TOTAL 1 + 2 + 3 + 4) 1,362,302,348 631,171,717
GRAND TOTAL INSTALASI (MATERIAL + JASA) 1,993,474,065
PPN 11% 219,282,147
GRAND TOTAL INSTALASI (MATERIAL + JASA) 2,212,756,212